HomeMy WebLinkAboutAngoon Hydro Study 1989ANG
012 Alaska Energy Authority
LIBRARY COpy
-
ANGOON HYDRO STUDY
PREPARED FOR
ALASKA ENERGY AUTHORITY
AUGUST 1989
polarconsult alaska, inc.
ENGINEERS. SURVEYORS. ENERGY CONSULTANTS
1503 WEST 33RD AVE.-ANCHORAGE, ALASKA 99503
•
...
...
•
'"
411
""
"',
.,
'"
... ,
,,"
.,
... . ,
.,
111'
.. ,
.,
.,
.. ,
.,
.. ,
.,
polarconsult Angoon Hydro Study
TABLE OF CONTENTS
I. INTRODUCTION ........................................ 1
II. PREVIOUS STUDIES ................................... 1
I I I. COMMUNITY ENERGY PROFILE ........ ' ................... 3
IV. RECONNAISSANCE ..................................... 4
V. PLAN ............................................... 4
A. Assumptions ..................................... 4
B. Diversion ....................................... 5
1. Layout ...................................... 6
2. Construction ................................ 7
3. Intake ...................................... 8
4. Pipeline .................................... 8
5. Powerhouse .................................. 9
6. Transmission ............................... .11
7. Trail ...................................... 11
8. Potential .................................. 12
C. Tunnel ........................................ .13
1. Layout ..................................... 13
2. Intake ..................................... 14
3. Diversion weir .............................. 14
4. Tunnel ..................................... 14
5 . Pipeline .................................. 15
6. Powerhouse ................................. 15
7. Transmission ............................... .16
8. General Discussion .......................... 16
VI. ESTIMATE ......................................... 17
VII. CONCLUSIONS ...................................... 20
VIII. RECOMMENDATIONS ................................. 23
APPENDIX
Location Map
Thayer Lake, Plan (2 Sheets)
Pipeline Route Profile
Photographs, Diversion
Tunnel Site Plan
Typical Pump Turbine
Thayer Creek Flow Duration Curve
,
I (
Olz..
..
..
..
..
...
...
III
III
..
..
.. '
<II,
"',
'.' .. ,
. ,
.,
,""
.a'
polarconsult Angoon Hydro Study
I. INTRODUCTION
Alaska Energy Authority commissioned Polarconsult Alaska, Inc .
to investigate previous reports, review alternatives, make a
field reconnaissance and get community input, develop cost
estimates, and make a report on hydropower potential for the
communi ty of Angoon. The report as follows represents the
culmination of these tasks.
II. PREVIOUS STUDIES
There have been previous studies and reviews of the potential
to provide service to this community. What makes this study
different is that it considers an entirely new project site
and new technology. It also optimizes to the extent possible
local labor and participation .
The previous studies which are listed, analyzed placing a dam
near the mouth of Thayer Creek, constructing a combined power,
water supply, and fish hatchery at Favorite Bay, and a tidal
power generation system adjacent to the community. In addition
to these studies, several economic analyses were made in 1984.
The last conclusion of these analyses was that the previous
hydro projects were not economically feasible. These
conclusions were largely based on the great capital cost of
the al ternati ves and the small size of the resource to make
the pay back. To place the situation in perspective the cost
for the Thayer Creek Project was estimated as $9,400,000 in
1987 dollars. The capital cost for Favorite Bay exceeded
$10,000,000 in 1984 dollars .
The reports and studies reviewed and analyzed are as follows:
1
..
..
.. '. -..
..
..
.. -
...
... '
.' .. ,
'., .,
4111
"'Ii .,
~
•
•
.-
... ..
polarconsult Angoon Hydro Study
Title
1. Thayer Creek Project
2. Angoon Tidal Power &
Comparative Analysis
3. Angoon Hatchery Concept
4. Angoon Water Supply Alts
5. Angoon Hatchery, Final
PNP Permit Application
For
APA*
Div of Energy
Angoon Aquaculture
Association
APA*
Angoon Aquaculture
Association
6. A Comparative Economic APA*
analysis of Electric Energy
Alternatives for Angoon, Alaska
7. Findings & Recommendations
Angoon Hydropower
APA**
* Alaska Power Authority now Alaska Energy Authority
** Internally generated analysis by the Authority .
Date
Oct 1979
Feb 1981
Sep 1980
Aug 1981
Feb 1982
Feb 1984
Dec 1984
2
..
..
... ..
..
•
..
..
-
...
' . .. ..
... ..
..
•
.. ..
-----------,-,--------_._------------_._-, -" ----------------
polarconsult Angoon Hydro Study
III. COMMUNITY ENERGY PROFILE
Angoon is a community of 639 people which is located on
Admiralty Island near Juneau. AngoQn has 134 residential
meters, 22 commercial meters and 7 community meters according
to the "First Annual Statistical Report of Power Cost
Equalization Program" published by the
Authority .
Alaska Energy
Angoon obtains its power from a central diesel electric power
plant. This plant has a installed capacity of about 950 Kw,
and has a typical winter demand of 450 Kw and a summer demand
of 240 Kw. The peak has reached 500 Kw on a 15 minute demand
according to personal communications with Mr. Walter Soboleff.
Earlier utility reports gave the demand as 0.3 Mw. For FY 1988
the total Kwh sold are 1.470 million, the fuel consumed was
144,000 gallons, at a cost of $105,000, and the operating
disbursements from the State were $227,349. The Kwh sold per
gallon was 10.2, the operating cost per Kwh was 13.4 cents and
the average PCE was 21.8 cents. This diesel plant is equipped
with a waste heat facility which provides heat to community
buildings.
3
..
'" ..
..
...
..
.. ..
.-
"-
..
..
..
.. ..
...
• .. ..
•
polarconsult Angoon Hydro Study
IV. RECONNAISSANCE
Two members from Polarconsul t went to Angoon in July. During
the visit the diversion scheme was surveyed, the dam and
tunnel site at Thayer Creek was observed, and the electrical
transmission line route was flown. Tpe results of the teams
observations were presented to Richard George, Sterling
Bolima, and Albert Kookesh. Unfortunately, Mr. Soboleff was
called away unexpectedly for a funeral. Discussions were also
conducted as to the communities capability and desires as to a
project of this type .
V. PLAN
Two sites were explored and analyzed. The first one was a
potential diversion site which brings water directly from
Thayer Lake over a divide to a stream which runs into Mitchell
Bay. Alaska Energy Authority, AEA, selected this as the
primary site to be investigated. The other site to be
investigated was a dam site at the mouth of Thayer Creek that
was studied by Harza. (See Ref.i) The task was to determine if
there was a way to make this project less expensive.
A. Assumptions
The basis for this study was to analyze a hydro plant sized to
meet the communities needs, which is about 600 Kw. This sized
plant should have the minimum capital and operational cost. It
was also assumed that maximizing the use of local labor was
desirable. The system should be designed so that it would have
the minimum of environmental impact because some of the
potential project is in a wilderness area and because Alaska
Energy Authority, Polarconsult and the potential client find
this desirable. Further, it is helpful to increase sources of
employment and income for the local people and so it is
desirable to enhance local renewable resources. Therefore,
4
..
..
..
• .. ..
..
..
... ..
..
..
•
,..,
polarconsult Angoon Hydro Study
project criteria also included provision for a hatchery and
the potential for future mariculture.
Flow duration data and a
Reference 1 cited previously.
calculated, Exhibit T-5, of
report's appendix. The flow
geologic report was taken
The flow duration curve that
the Reference is shown in
duration curve shows that
from
was
this
the
minimum flow at 100 percent exceedence is 65 cfs. Polarconsult
selected for the study, an operational flow 50 cfs, which is
conservative, based on the figures. At this flow sufficient
water should remain for the pink' salmon run which stops below
the falls on Thayer Creek. Since the average annual flow of
this creek is estimated at 405 cfs and the minimum monthly
average is estimated as 150 cfs, and Thayer Lake has a
surface area of 2787 acres, one foot of surcharge on the lake
stores about 1393 cfs days. Or for a period of 30 days, a
typical dry period, about 40 cfs could be produced with a draw
down of one foot. During the site visit the lake shore showed
that the water surface was about 1 1/2 feet below its normal
level. This summer had a long very hot dry period and the
water level in the creek was low.
B. Diversion
The diversion system layout is shown in the drawings in the
appendix along with a profile of the ground. The critical area
of the profile which is the first 3000+ feet was measured
utilizing inclinometers and a string transit. Using the lake
elevation as 370 feet, the elevation of the highest point was
417 feet which is 47 feet above the lake elevation. The
balance of the profile was obtained from USGS quad maps and
augmented utilizing photo pairs. The diversion route lies in a
old channel which was cut by a very large stream which
indicates that at one time this location was an outlet of
Thayer Lake or of the glacier which was in its place .
5
..
-.. ..
..
..
..
...
' ..
' .. ..
..
...
OR
•
•
•
•
...
• .. ..
polarconsult Angoon Hydro Study
The diversion system pipeline profile starts from a small lake
which is connected to Thayer Lake but is currently dammed by
beavers. This pond, which is 40 acres in extent, is to become
the intake for the project. The beaver dam will need to be
removed and perhaps the channel between the two lakes
deepened. At the time of the field trip sufficient water would
not have flowed between the two lakes. Excavation between the
lakes can be easily done with a few days of hand labor .
There is a boat lift boom at the beaver dam and a local
family, the Nelsons, use the area during the summer for
wilderness and walking trips. They have a cabin on Thayer
Lake, travel to and through the pond to the head of a trail
which leads to Salt Lake. From this point they say they take
the people to Angoon by boat.
1. Layout
Aerial photos and aircraft observations were used to find a
practical route from the pond to an elevation where the costs
of extending the pipe would exceed its value. The route turned
out to traverse a meadow to the first peak, a boggy area over
the first divide and then follow a incised old stream bottom
until it was possible to leave the stream at station 27+00 or
so. The stream bottom is fairly soft and mucky and is about 50
feet wide over much of its distance which is similar in
geometry to Thayer Creek which drains the lake. The sides and
some of the bottom of the stream are covered with trees up to
six feet in diameter. The banks of the stream are fairly steep
in the order of 20 to 40% at their maximum.
The selected route may not be the optimum as it may be
possible to follow the stream a little further and breakout
wi thout as high of a bank. However, as the stream bed was
meandering away from the powerhouse the current location
seemed best .
6
.,
."" ..
..
..
..
•
..
.. ..
,..
..
...
...
.,
.. ..
.. ..
.. ..
""" -"~~.~--"-----~---------------,------------
polarconsult Angoon Hydro Study
With a relief of 47 feet in elevation and the hydraulic losses
of the pipe it is impossible to syphon the water from the
pond. A deep ditch would have to be excavated for a syphon.
This ditch would be a minimum of 25 feet deep and 3000 feet
long, providing it were possible to reduce the profile
elevation below the hydraulic grade line from station 35+00
on. The only other alternative would be to drive a tunnel in
the order of 3000 feet or so .
The alternative selected is to pump the water over the divide
and use the greater fallon the other side to generate
sufficient power to run the pumps and provide the community
with energy. This alternative is not the usual one used for a
hydro plant as it involves more equipment, wastes some
additional energy in pumping losses, requires larger, turbines
and generators which have higher losses. However, in a
situation such as Angoon's where there
needed, where the ratio of pumping head
and alternatives are expensive, then
provide excellent economics.
2. Construction
is
to
a
more water than
output head is
pumping scheme
is
low
may
The construction of the diversion scheme is designed in a
manner to use hand labor for the entire project with the
exception of boats, and helicopters for basic transportation
and a winch for pulling pipe and trees. Provided a good trail
can be developed, 4 wheelers can be used for the smaller
items.All of the parts and equipment items are sized to weigh
less than 3,500 pounds which allows them to be lifted by a
Bell 212 .
Using hand labor will provide added employment to the
community and will result in a project with very reduced
environmental disturbance. From the ground it will be very
difficult to see this project with the exception of the intake
and a short section of the pipeline near it which will be
7
..
.. ..
'" ..
..
..
...
..
..
..
..
WI
..
..
..
-
,,-------~--------------~------------
polarconsult Angoon Hydro Study
visible from the pond. From the air only short sections of the
pipe and trail will be visible and one will have to know they
are there and be lined up with them to see them. The equipment
will be quiet with the pumps under water and the turbines in a
building .
3. Intake
The intake for this plant will consist of four screened pipes
with a floating fine mesh net on the outside to prevent
ingesting some of the native cutthroat trout. Each intake will
be equipped with a submersible pump. The water will be pumped
through check valves into the pipeline which will cross the
meadow up the hill. The intake will be constructed of
prefabricated metal or treated wood which will be modularized
in sizes easily handled by helicopter. Power to the intake
will be transported by tree suspended cable hence underground
in the meadow. There will be two transformers and four
contactors located near the pumps which will be enclosed in a
weather proof metal enclosure which will be painted green .
Hemlock and spruce trees will be planted around the enclosure
to screen it from the pond .
4. Pipeline
From the intake the pipeline route for several hundred feet
passes through grassy meadow hence through a soft surface
boggy cut through the divide between drainage to the lake and
to the inlet. From this point it travels along an ephemeral
stream which has soft black organic material in its bottom.
Once leaving the stream area it crosses out of the immediate
stream drainage and continues on gently sloping ground which
is forest floor with a bog along the way. The route is covered
with a number of trees as shown in the photograph .
The pipeline was planned to be constructed of 32 inch
polyethylene pipe in the upper section with the use of 3/16 th
inch steel from the 210 foot elevation to the 100 foot
elevation where the power house is to be sited. Polyethylene
8
..
..
•
... ..
..
..
•
..
.. ..
..
•
polarconsult Angoon Hydro Study
pipe was selected because it can be bent, can accommodate to
the ground, has a low coefficient of friction, can be pulled
in long lengths and if a tree drops on it will spring back to
its original shape. Polyethylene was selected as it can easily
accommodate temperature changes.
The plan used for this project is to hand clear a narrow trail
along the pipeline route. Then with shovels and perhaps a very
small backhoe, construct a bench on the side slopes where
needed for the pipe. In addition to the pipe bench which will
only be 3 feet or so wide, a bench would be constructed for
the foot and 4 wheeler access trail. Although the pipeline
bench may require tree removal at intervals, the access trail
construction can generally avoid removing many trees. The
pipeline will be anchored with cable connected to the flanges,
ground anchors or trees.
Staging locations will be developed and the pipe brought in
and stacked on skids by helicopters. A fusion machine will set
up at one of these stacks and the pipe will be fused and
pulled along the pipeline with a winch line. In the lower
section of the pipeline the material will be steel. In this
location it will be spotted with a helicopter, pulled into
place a joint at a time and fillet welded. The steel pipe will
be supported on timber fabricated from local felled trees.
5. Powerhouse
The powerhouse which will be about 20 X 30 feet in dimension,
will be constructed of wood or metal on a reinforced concrete
slab. There will be five pumps operating as turbines in the
powerhouse. These pumps will drive synchronous generators
which will connect through two transformers which will raise
the 480 volts to 7.2/12.4 Kv .
The powerhouse will be equipped with alarms and a SCADA system
and will have a programmable controller which will sequence
9
'. ..
..
..
..
•
..
• ..
•
III
..
•
... ..
..
...
polarconsult Angoon Hydro Study
the system as to operation. To operate the system one of the
pumps will start at reduced voltage, when the pressure reaches
a certain point the pump will be advanced to a higher voltage
and the turbine valve will open and the turbine synchronize to
the line. At that time a second pump will turn on and a second
turbine and so forth until all five turbines are operating. At
that point the system will be producing about 625 Kw net .
Assuming that there are 5% line losses the net at Angoon would
be 594 Kw which at 95% availability will produce 4.94 million
Kwh per year.
With the pump pump-turbine scheme the power can only be
controlled in blocks of 120 Kw net each. To control the
frequency it is proposed to use a load governor. A primary
governor with resistance heaters will be located at the
powerplant. The amount of heating will likely be near 250 Kw.
In Angoon control units will be located in strategic areas
which will be capable of extracting the extra 3.5 million or
so Kwh that is excess to current community needs. This amount
of excess electricity can produce the equivalent of 125,000
gallons of fuel oil worth of heat per year assuming oil at
120,000 Btu per gallon and burnt at 80% efficiency.
A variable flow
francis turbines
their generators
$100,000 higher
system can be built which would utilize two
turning at 1200 RPM each. These turbines with
will cost about $250,000 which is about
than the pumps used as turbines. Their
efficiency is about 4% higher .
Using the scheme that was outlined, the system will operate
continuously, only being turned off for maintenance or when
water levels at the lake are low and extra discharge is needed
for the pinks at the mouth of Thayer Creek. This constant
operation at about 10 cfs per unit makes a constant flow of
water available which can be used near the shore line or at
10
..
..
',"
..
.,
..
..
...
..
..
.. ..
..
..
..
polarconsult Angoon Hydro Study
Fresh Water Lake, or Salt Water Lake for hatchery or
mariculture operations.
6. Transmission
The transmission line which is about 6.5 miles in length is
planned to be constructed as insulated cables suspended by a
messenger from trees or on the ground in plastic, PE, duct .
The tree cable has been used very successfully by Horner
Electric Association who have 25 miles of 14.4/24.9 Kv tree
suspended cable in service. The reason they use this cable is
for environmental and costs reasons as part of the route is in
a park. They have had only three squirrel outages, all in the
same area, during the 15 years the system has been in
operation. When a tree falls over the line the system is
designed so it pulls the cable off of the supports without
breaking it. Therefore it continues in operation unlike
conventional overhead systems. With 25 miles of this cable
inservice HEA reports only one tree incident per year and has
to inspect the line once each two years .
Crossing the channel to Angoon will be done with half inch or
heavier thickness walled pipe with pulled in cable. The pipe
wall will be so heavy that no 'supplemental weights will be
required. The pipe will be protected with a coating, impressed
current system and anodes at each end. A similar system such
as this used for the water line failed. However, it is
intended to search out a wider deeper location where water
velocities are appreciably under the 16 mph reported to be
found at the site of the current crossing .
A small switching station will be constructed to tie in the
transmission line to the Angoon utility system. This
substation will be the metering point for the system .
7. Trail
After engineering, the first construction item will be the
trail. The trail which will be about 2.3 miles long will start
11
III
..
..
•
-II
• ..
..
... ..
oil
..
..
..
..
..
..
polarconsult Angoon Hydro Study
at one of the inlets off of Mitchell Bay. The starting
location will likely be integrated with future fish hatchery
plans. The trail will be designed and constructed so it can be
used by small low tire pressure all terrain vehicles. It will
be constructed with hand labor and will use planks, logs,
corduroy, and geofabrics to cross the boggy or soft areas. The
heaviest single item which will travel over the trail is a
cart with a replacement generator. The cost estimate for the
project assumes that 1/3 of the trail will require plank
construction of treated materials. If cedar is readily
available in the area, local trees can be used which could
include the manufacture of planking on site with a bandsaw
mill.
8. Potential
The potential of the diversion site is substantial. It could
be enlarged several times and with the addition of a small
weir and controls at the lake mouth the capacity could be
increased to perhaps almost 2 Mw. The water from this site
will flow to inlets in Mitchell Bay where a hatchery and
mariculture can be sited which will provide employment and
income for the local people from a renewable resource. The
water can readily be diverted to Fresh Water Lake and to Salt
Lake and there is a potential
which if environmentally and
for a red salmon rearing area
biologically favorable could
result in substantial income to the community. Access to the
site is from protected waters versus the alternative which is
out in Chatham Straits. Additionally this location can be
easily hidden from most normal traffic by boats and aircraft.
Because the power line passes through an area which is the
most likely source of water for the community, power and
communications can be made available to those facilities along
the route, which should save money .
The negative part of this scheme is that it is in a wilderness
area and secondly has more equipment to maintain. However, as
12
•
•
..
.. .. -
•
..
.-..
..
...
....
.-
-...
• ..
..
•
...
..
polarconsult Angoon Hydro Study
pumps and contractors are highly reliable it is not believed
that the maintenance costs will be much more expensive than
those for more conventual facilities .
Draining the beaver pond will result in a muddy shore line
which will take several years before the grass reestablishes
itself. It should result in a beautiful grassy meadow until
the trees reinvade the area.
Additional water in the creek from the plant discharge will
result in some increases in erosion for a short while until
the banks and bed restabilze themselves. Since most erosion
occurs during flood stage and the amount of water may not be
significantly greater it is likely this will not create a real
problem .
c. Tunnel
The Thayer Creek or Tunnel Scheme is a modification of the one
proposed by Harza Company. The Harza proposal was a concrete
dam with a net head of 45 feet, two propeller turbines, with a
firm capacity of 210 Kw, a installed capacity of 400 Kw, a
flow of 128 cfs and generation of 1.575 Mwh.The essential
differences between that system and the new scheme are that a
tunnel is proposed rather than a dam, that the water will not
be returned to the creek, that the turbines will have near 4
times the head hence producing more power using less water,
that a load governor is to be used and finally the cost of the
system is much reduced, and the power output much increased .
1. Layout
The system layout is as shown on the sketches in the appendix .
It is comprised of a tunnel whose mouth is about one half mile
north of the mouth of Thayer Creek and whose entrance is above
the rapids at the 200 foot contour level. From the tunnel a
penstock follows the fall line directly downhill to the
13
• ..
....
..
• ..
..
.. ..
..
.. ..
• -..
•
..
• ..
• ..
,II
..
T1
polarconsult Angoon Hydro Study
powerhouse on the banks of Chatham Straits. The tailrace
drains directly into the strait .
2. Intake
The intake will be a modification of the tunnel entrance to
the stream. The rock will be presplit to a vertical face and
steel H beams will be set to support °a 20 foot or more long
trash rack, stop log system for screening debris and shutting
off the tunnel when necessary. Concrete quantities will be
reduced to the minimum required to seal or level critical
locations in the structure .
3. Diversion weir
A diversion weir about 4 to 5 foot high will be used to get
the water into the tunnel entrance. The weir will consist of
steel H beams about 10 feet on center which will be cemented
into the rock. The holes will be excavated with shaped charges
or conventional drilling and blasting. Each of the H beams
will be equipped with a support for planking to walk out and
remove or add the wooden stop logs. A small hoist system will
be devised so the stop logs can easily be removed to flush out
the gravel and rock as it accumulates behind the planking.
4. Tunnel
A geologic report states that the material where the tunnel is
to be excavated is marble with bands of shist. The foliation
strikes NW, parallel to the coast, and dips 40 0 NE. There are a
strong set of right angle vertical joints and another set of
N-S vertical joints. The rock appears from this report to be
of a type that would not need extensive supports and should be
easy to tunnel .
The tunnel is to start from below the 200 foot level on the
seaward side of the hill and extend about 4000 feet to the
right bank of the creek. The tunnel will be a size selected by
the tunneler which will be a 5 x 7 foot or larger. The tunnel
14
..
... ..
..
...
..
..
...
.. ..
.,..
...
,.
..
-..
..
..
..
..
... ..
... ,. i. ttll_at II -f ..
polarconsult Angoon Hydro Study
grade will be less than one percent and all of the tailing
rock will be dumped under the trees at the entrance .
To keep tunneling costs down the contract will be written on
a performance basis with a time and material clause for
special conditions like unstable ground that calls for sets,
grouting, shotcrete other remedies. The risks will be carried
by the community rather than the contractor. Tunneling can
also be done with force account labor and if this is the case
it is projected that the costs could drop from $375 per foot
to $200 per foot .
For a small project of this type, a team of miners equipped
with a mucker, track, locomotive, 20 cars, air legs and a
compressor could earn considerable amounts of money and still
construct a very economical tunnel. When the 10,000 AJ adit
was driven at Juneau a crew of 3 mem drove 10.5 feet a shift
with a mucker, hand tram and air legs. Small tunnels generally
do not require the support system larger ones do and this
tunnel because it is near the top of the hill is less likely
to have excessive high pressure water that can be found in
other tunnels .
5. Pipeline
The pipeline will be made of 32 inch polyethylene pipe, which
lS flanged and will be winched up the hill and bolted into
place. The 1000 foot pipeline will have flanges which will
provide the locations for cable connections to rock and ground
anchors to restrain the pipe .
6. Powerhouse
The powerhouse will be a reinforced concrete slab with either
wood or metal building construction. The powerhouse size is
estimated to be 20 x 30 feet and will house four 10 inch pumps
run as turbines. The installed capacity of the system will be
near 600 Kw and the output of the pumps at 170 feet of net
15
..
..
•
..
• -
...
• -
•
...
•
...
•
"" -
..
•
...
• ..
...
polarconsult Angoon Hydro Study
head will be 595 Kw. The system will generate about 4.71 Mwh
per year using 95% plant availability and 5% line losses .
7. Transmission
The transmission line route is "slightly shorter, 6.2 miles,
than the diversion route but crosses steeper country and areas
which have cliffs. Therefore, it "likely will be more
expensive. Because it is less expensive and easier to repair
tree cable was selected. Submarine cable was investigated but
areas with good bottom conditions are probably over 600 feet
in depth which requires special cable, splices and laying
equipment. This transmission route also will require a
crossing to the peninsula that Angoon is on. The crossing will
be done further north than the narrows where velocities are
low enough to utilize standard cable .
A small switching and metering station will be needed to
connect to the community distribution system .
8. General Discussion
The tunnel scheme has the advantage of being on land already
selected by the Angoon Native Corporation, Kootznoowoo, Inc.,
which will make it easier to initiate the construction of a
power plant. The tunnel scheme is simpler in operation then
the diversion scheme and can be readily added to with
additional penstocks, as the minimum sized tunnel is more than
sufficient. Although the tunnel scheme is more expensive it
should be somewhat less expensive to maintain. Because of the
exposed location, lack of space, the tunnel scheme will not
likely support a large mariculture operation. It could support
a hatchery however. Access to the tunnel scheme is not in
protected waters and during winter storms it may not be
possible to reach the site. Therefore, this scheme may call
for a permanent operator/caretaker during winter periods .
16
..
.. ..
.. ..
... ..
.. ..
..
..
-
...
..
..
• ..
..
..
It
polarconsult Angoon Hydro Study
VI. ESTIMATE
Two estimates where made. One for the Diversion system and one
for the Tunnel system. Both estimates qssumed the use of local
labor at 15$ per hour with 35% fringes, insurance and social
securi ty. The assumption because of travel time that only 6
working hours per day is available and that travel is by boat .
All hand labor is to be used at each site with the exception
of helicopters to bring in pipe, lumber and powerhouse
materials from the beach. There is to be expert help during
construction of various features such as installing the
equipment, and fusing the pipeline .
For the tunnel scheme is estimated on the basis of being done
with a performance contract with little control from the
communi ty. The tunnel drilling is to be arranged so a small
group of miners can bid and do the work without the heavy
burdens and guarantees which are typical of institutional
organizations .
The turbines for the system were estimated on the basis of
using pumps. Francis Turbines will add $100,000 to $150,000 to
the costs. Pumps are inexpensive, light, easy to install and
easy to maintain. They are highly reliable as they have only
two moving parts .
Contingencies are allocated based on the degree of uncertainty
in the estimate. Material contingencies are considerably lower
as their probable costs were lower.
All costs are based on a 1990 construction start and based on
a single barge lift to the site .
17
_ .. _. __ .------------------_. ------
poiarconsult Angoon Hydro Study
.. ..
..
.. .. ESTIMATE, DIVERSION SYSTEM
-.. ITEM COST CONTINGENCY TOTAL MD
Trail 79 12 81 150 .. Pipe Mat. 334 33 367 .. Pipeline 254 51 305 800
Intake, Mat 100 10 110 .. Intake 102 21 123 100
Turbines 150 15 165 .. Powerhouse 138 21 159 .. Powerhouse, lab 79 16 95 35
Substation 10 2 12 15 ... Transmission 277 42 319 300 .. Crossing 40 8 48 40
Switching station 10 2 12 10 ..
Direct Csts 1573 233 1796 1450 .. Total Csts 1796
Engr + Admin, 15% 269 .. TOTAL $2065
• * All values in $1000's
..
, ..
..
..
•
...
18
-..
•
• ..
..
..
..
-
...
•
..
' .
...
..
•
polarconsult Angoon Hydro Study
ESTIMATE, TUNNEL SYSTEM
ITEM COST CONTINGENCY
Tunnel 1500 300
Plug 21 4
Pipeline 107 22
Diversion 22 7
Intake 36 8
Turbines 160 16
Powerhouse 138 21
Powerhouse, lab 79 16
Substation 10 2
Transmission 250 38
Crossing 40 8
Switching station 10 2
Direct Csts 2373 444
Total Csts
Engr + Admin, 15%
TOTAL
* All values in 1000's
Whether the contractor will hire local
work is not known. Therefore, the
represents 3 men working about a year
TOTAL MD
1800 600
25 31
129 140
39 56
44 78
176
159
95 35
12 15
288 280
48 40
12 10
2827 1285
2827
424
$3,251
labor for tunneling
600 man days which
is a estimate only.
Should the community decide to do their own tunneling, then
these hours would be guaranteed. It is estimated that by using
non contract work the tunnel costs could approximate as little
as $800,000 or the Tunneling System costs would total
$2,411,000 .
19
.. ..
..
• ..
..
..
..
III
..
III
..
.. ..
..
..
" ..
polarconsult Angoon Hydro Study
VII. CONCLUSIONS
There are two hydro systems that can be built that use the
Thayer Lake resource. Either of them will provide large
amounts of energy to the community. The community can use the
extra energy for space heating, gr~enhouses, operating a
hatchery, freezer plant for fish and sea food, and for a
mariculture operation. The cost of both plants is near a 10
times multiple of the money now 'being given to the community
for power cost equalization and 20 times the value of the
fuel. Each of these hydro plants will be less expensive to
operate than the alternative diesel plant. But the diesel
plant will have to be retained for standby as these plants may
need to be shut down for maintenance and if there is a failure
of the transmission line.
Each of the systems will require considerable local labor
during its construction and if the plants were built by
contractors their costs would increase considerably. The
diversion scheme uses about 1450 man days of labor versus the
tunnel scheme which uses 1285. Adding another 1,000 man days
of labor would represent a cost increase of $170,000 which
shows that if the labor hours increase the cost increases will
not be great .
The diversion scheme with its continuous supply of water to a
protected area can provide the basis for a hatchery and future
mariculture which can provide income and employment for
members of the community for countless years in the future.
Freshwater Lake could receive some of the water and become a
rearing ground for highly valuable red salmon.
The diversion schemes power line will pass close to a viable
source of water for the community. In addition during the
construction of the power line it would make sense to do the
expansion for the water lines as workers, helicopters and
other logistic support will be available. Further,
20
...
.. ..
..
-/If
.. ..
..
..
..
.. ..
•
..
..
-
..
..
...
....
..
..
polarconsult Angoon Hydro Study
electricity, telemetry and control functions can be done over
the same circuit .
The major problem with the diversion scheme is the fact that
it is in a wilderness area. But when consideration is given to
the clean nature of the project, the obligation of Congress to
the community, and the arbitrary nature of the current
boundaries, the resolution of this matter may not prove
difficult .
Technically, neither the diversion scheme nor the tunnel
scheme is difficult. Operationally, the diversion scheme to
start up will require sufficient diesel generators on line at
Angoon to start one of the pumps. Since the system will seldom
be shut down it is not likely that start ups will be required
more frequently than once per year or so. Both systems can be
expanded to about 3 times their initial output. The tunnel
scheme will be the least expensive to expand. Both systems
will have to deal with the pink run at the mouth of Thayer
Creek and if provided with a very modest amount of storage,
perhaps two feet, can guarantee sufficient water flows so as
to have little effect on the resource .
All of the calculations are based on a synthesized water
record. The schemes are not sensitive to large variations in
the values of these records .
Both schemes if economically viable will need more data to
progress to a greater level of accuracy in the cost
estimating. A stream gage should be installed on the creek and
perhaps several rain gages for basic data. For the diversion
scheme some surveying, of the pond, and the pipeline route
would allow more accurate determination of the pipeline costs.
For the tunnel scheme geological work which would include some
seismic surveys and better delineation of the intake areas
21
..
..
.. ..
...
..
•
, ..
..
..
..
•
..
•
•
•
polarconsult Angoon Hydro Study
would be appropriate. Investigation into velocities for the
cable crossing area would be very useful to determine where a
safe crossing can be made .
The community of Angoon can build one of these hydro plants
which will provide income during the construction and displace
the cost of diesel fuel during its life which should be
substantial. A hydro plant equipped with load governors can be
used to provide supplemental heat in the town up to the
capacity of the machines. A hydro facility will isolate the
community from rate
and reductions in
shock caused by increases in fuel costs
power cost equalization funding. With
decreased
hydro can
community needs
make favorable
for power during the summer the
the addition of a modest freezer
facility. The Diversion system can make it possible for the
community to increase the harvest of fish which can result in
employment and income for generations of future residents .
22
..
.,.
..
...
..
•
..
•
...
...
..
till
...
polarconsult Angoon Hydro Study
VIII. RECOMMENDATIONS
Looking at the long term future for the community assuming
that low cost money is available, the economic projections
will likely show the project is feasible. With additional
engineering and the conservative nature of the estimate it is
likely that some of the costs can be reduced. But before
reducing costs additional basic data is needed. Therefore,
assuming that economics show the project feasible at the
current figures, and assuming that a project can be selected,
the field work discussed in conclusions should be done. In
addition to this field work, a more accurate cost estimate
should be provided which will include further details on the
project's technical features. To further understand project
benefits a analysis should be made on the added uses of low
cost power in the community and what the value of this energy
will have for the community .
23
APPENDIX
•
..
..
II
..
II
..
II
II
•
.AI
..
•
•
• ..
II
..
INTERVAL 100 FEET
GEOOETIC VERTICAl OATUM OF 1929
IN rEET -DATUM IS M(AN LOWER LOW waTER
TH( AfIiIIWOllMATl UN[ OF' MEAN HIGH "1'IJI
"lOG( IJf nil( IS _IMATtL, Il F'£[T
E BY U. S. GEOLOGICAL SURVEY
NVER. COLORADO 80225. DR RESTON. VIRGINIA 22092
MAPS ANO SYMBOLS IS AVAILABLE ON REQUEST
LOCATION .M·AP
"~ , .
"'''-0 .. ~--QI.WlIWIGlE LOCATlON
ROAD CLASSIFICATION
Unimproved dirt •••••••••
SITKA (C-2), ALASKA
57134-E3-Tf-063
1951
LIMITED REVISIONS 1983
THAYER LAKE PIPELINE
o 250 500 750 1000
FEET
• SURVEY POINTS
/---, /
/" ~-----z"
/ ...... , C / -, /
1\/
/ \ /
I \ ~ , fJ.J \. .". 5 -~, /
10 ......../ ,.,. "'". I.>-~ / ,~ -.",
l!!i
-.J 1&
I
~--.." -
~
/
/
I
I
I
I ,
f
I ,
I
I
I
/
polarconsult alaska, inc.
ENGINEERS -SURVEYORS -ENERGY CONSULTANTS
1503 WEST 33RD AVE.-ANCHORAGE, ALASKA 99503
JULY 17, t-989
\
s:::
~ o :::c
r
Z m
SHEET 1
r
Z m
c Z
OU1e. ., --- - - - - - -GUL;;.e..:!. ~ -., "
~-~~-~~--; \
\ \
I ,
\
\
\ ;I'"
,--fill!"
..... ...... .....
"-
POWER HOUSE "
ELEV.100;
THAYER LAKE PIPELINE
~ ......
" " \
\
" ,
--o --250 500
FEET
750 100Cf
polarconsult alaska, inc.
ENGINEERS. SURVEYORS. ENERGY CONSULTANTS
1503 WEST 33RD AVE.-ANCHORAGE, ALASKA 99503
JULY 17, 1989
"
SHEET 2
GULL Y PROFILE r --PHOTOGF AMMETRIC
/ PROFILE ,
3001-----+-----I---+----+---+------J---+---'\·-+-,~-+__-___I_--+__-_+_-____I,__-__+_-__+___t ~ '" /~ "---~ \\
200r-------~------_+--------~------~------_+--------+_------~------~--------+_------~------~~------+---~--~------~r-------+_--~ "'~
'~
100~----~~------~----~~------~----~~------~------~-------~------+_------+_------+_------r_------+_------+_------~~--_.
~ w w
U-
500 I 1000 1500 2000
FEET '<to roO)
zro O~ -> .-w <.....J '-w C/)
2500 I. !3000 I 3500 4000
00 < Z)( z'" z Q< 0'" 0 -. i= ~~ ~> cw <
~ .... .-We")
(l)W C/) .....J'<t
W
4500
PIPELINE ROUTE PROFILE
5000 5500 6000 6500 7000
polarconsult alaska, inc.
ENGINEERS e SURVEYORS e ENERGY CONSULTANTS
1503 WEST 33RD AVE.eANCHORAGE,ALASKA99503
JULY 17,1989
7500 (
W
C/)
::J.
0° :r:~ a:::. w> ~~ OW a..
SHEET 3
Figure 1. Looking at the S.W. arm of Thayer Lake. The
intake is located at the upper left of the photograph.
Figure 3. Looking S.W. alon~ the still water anchorage
towards Angoon. TransmissIon line route on right.
Figure 2. The intake is on the left in the small pond, Thayer
Lake is on the right. __ _
Figure 4. Transmission line continuing to a turn point and
then crossinQ the water to the villaQe of AnQoon.
Figure 5. Aerial view of the small inlet on the end of Thayer
Lake. Note the channel and beaver dam.
Figure 7. View of channel and beaver dam, looking towards
the pond.
Figure 6. Mouth of the channel between Thayer lake and the
pond looking out onto Thayer Lake.
. Figure 8. Intake location on the pond.
Figure 9. Pipeline route over first ridge. Figure 10. Typical forest; trees reaching six feet in diameter
Figure 11. 190 kW pump turbine similar to that for Angoon.
INTAKE
TUNNEL ROUTE
PENSTOCK
POWER HOUSE
TRANSMISSION LINE
TUNNEL ALTERNATIVE
35'
2080000
FEET
, ,
\ ',-
,
\
\
\
\
\
Danger PI
31
" ! (
of ./
,0
18
558
57°30 '---t-:;-:;-;::,,,,,,,,~~---~----'----+-'---·'\'-------L=~~-------cCJ"L.:.:.-":--I
134040 2490000 FEET
Mapped, edited, and published by the Geological Survey
Control by USGS and NOS/NOAA
Topography by photogrammetric methods from aerial photographs
taken 1948, field annotated 1951. Map not field checked
Selected hydrographic data compiled from NOS charts
17320 and 17339
This information is not intended for navigational purposes
Projection and 1000-meter grid ticks shown in blue,
Universal Transverse Mercator, zone 8
10,OOO-foot grid ticks based on Alasl<a coordinate
system, zone 1. 1927 North American Datum
To place on the predicted North American Datum 1983 move
the projection lines 38 meters north and 106 meters east
35'
~ ~ ~ f
~ ~
:= J
~
APPROXIMATE MEAN
DECLINATlON,1951
3000
IOTR I TURBINE INDUCTION GENERATOR ASSEMBLY
FOR
GENERATION UNLIMITED NEWPORT BEACH , CA.
• • i"~
.800
:.7to ..
-j
J , ,
~ __ .. _ ._.~..2t1()_
i~
'.\oJ ... _~_4iJQ.
!
! . ---"--1--... -.~ ,
!
, '
-+
--1--", .-.. --.-. ., .-.
, .,.
.-.---... ~.-•• .!...--. t--~·'-·······~ t·
i '
J
I T
'\.
-----.~-.-.+-.-
!\
.. 1..
,
~-.-.~~ ... -~ -. .. -.-.--'-;----.-.~.---
L· .... sllO·K,w .. ·-----
! < _. ! ,
.' ----~--J-.----i.------~ .... --.~ ~OO k:W:! ' ,
,
.~
, ' L. __ -:_,. __ .:. __ ,_'-;"~ .• _ .•. --.:. ___ + ... _ .. :.. ___ ._,1 -_.--..•• t-. -. ___ +-_. ""'j_ ._ .• _. _____ ••..• ..:. _____ ....,;
r j" !
i ,-: .,-i'i t· I·t 4tJO KjI,/ .,'
:._. _____ ~JOO "--"--i~-.:~-t'~--:i' .-----.. ------.. ----.,: .. --. -..... --.. _ .. ,-... --.---~
1-.,. , '
! --.----l--.-~--i--: _L'-" i._~:-. .. _____ :;~ .. _ ... ___ ~_. ___ ._~~~q~.r· ;-'-~-'-T--;"';" , I j . ;·-T----·--T----! i i
r·. i~··~( .. ~-;l. ;. 1 ;'! l' "1-.. T .,. . .... ~
r--I.· •. 1
1
e# c1t:.~ ~$~;!,t-,;~~~~~u~~~E:~~~()·--f~;ckr:i
, .' ., I· .. I .. -., CIII, =c;;, a.., . ,',.."....£1 ~ ~.I,.., '" [ii-;---~·---~-·J.:·-;~-~·:--~:-·"~--:1·-.. t""~-·-I-; '--(--'-:1-T ''!'''':FLc) ':Cij/flAit'O/J'¢lJRVc 'tflr.ed-Ul9 . ...1ia __ ~_7~ ______ ~_. _~_-L.....;.. ... L ~ ___ .__ _ ____ ~ _ _L___ .. ____ ._ ,_", __