HomeMy WebLinkAboutHaines-Skagway Region Feasibility Study Volume 1 - Report 1982HAS
014
vol. I
Alaska Power Authority
LIBRARY COpy
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
Volume I -Report
R. W BECK AND AsSOCIATES, INC
ENGINEERS AND CONSULTANTS
June 1982
001
L...-__ ALASIiA .·()\fEll AU'l~HOIl.TY __ .......
WEST CREEK VAllEY
•
•
P.O.80X2400
• SITKA, ALASKA
99835
FILE NO.
•
•
,
..
,
R. W. BECK AND AsSOCIATES, INC
RH-1559-HG3-AA
3110
Mr. Robert A. Mohn
Director of Engineering
Alaska Power Authority
334 West 5th Avenue
Anchorage, Alaska 99501
Dear Mr. Mohn:
Subject:
ENGINEERS AND CONSULTANTS
TOWER BUILDING
711-1 AVENUE AT OLIVE WAY
SEATILE, WASHINGTON 98101
206-622-5000
Haines-Skagway Region
Feasibility Study
HI..:.
OCT 1 1 1982
AlAsKA i v.
P.O. BOX 6818
." In Knt)i;IKAN, ALASKA
99901
June 30, 1982
We herewith submit our report on the Feasiblity Study for the
Haines-Skagway Region.
Our principal findings and conclusions are set forth in the Summary
and Conclusions of the report. Details of the site investigations, engineer-
ing studies, economic evaluations and environmental studies conducted for the
Project are described in the subsequent sections of the report and in Appen-
dices A through C.
Respectfully submitted,
R. W. BECK AND ASSOCIATES, INC.
James V. Williamson
Manager
Hydro-Water Resources Design Office
Registered Professional Engineer
in Alaska
•
•
•
.,
•
"
CERTIFICATE OF ENGINEER
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
The technical material and data contained in this study were
prepared by the following engineers:
! .~ ~.~::Ir:<----
Supervising Engineer
R. W. Beck and Associates, Inc.
Wilson V. Binger, Jr.
Principal Engineer
R. W. Beck and Associates, Inc.
The technical material and data contained in this study were
prepared under the supervision and direction of the undersigned whose seal as
professional engineer is affixed below •
Donald R. Melnick
Executive Engineer
R. W. Beck and Associates, Inc.
•
•
•
•
•
VOLUME I -REPORT
SUMMARY
GENERAL OUTLINE OF REPORT
PART A -SELECTION OF GENERATION PLAN
PART B -FEASIBILITY INVESTIGATIONS OF WEST CREEK HYDROELECTRIC PROJECT
PART C -COMMENTS FROM REVIEWING AGENCIES
PART D -SUMMARY OF GENERATION ALTERNATIVES
VOLUME II -APPENDICES
APPENDIX A -PHASE II -FEASIBILITY STUDY INTERIM REPORT
APPENDIX B -GEOTECHNICAL INVESTIGATION
APPENDIX C -ENVIRONMENTAL INVESTIGATIONS
•
..
..
•
•
Section
Number
I
HAINES-SKAGWAY REGION
PHASE II FEASIBILITY STUDY
VOLUME I -REPORT
TABLE OF CONTENTS
Section and Subsection Title
Letter of Transmittal
Certificate of Engineer
General Outline of Report
Table of Contents
List of Tables
List of Figures
SUMMARY
SUMMARY OF PRINCIPAL STATISTICS OF
RECOMMENDED GENERATION PLAN
PART A: SELECTION OF GENERATION PLAN
INT RODUCT ION
1 •
2.
3.
4.
General
Authorization
Background
Scope of Current Investigations
II SITE DESCRIPTION
1 •
2.
3 •
4.
5.
6.
Geography
Topography
Geology
Climate
Natural Environment
Socioeconomic Setting
Page
Number
1-1
1-1
1-1
1-2
II-1
II-1
II-1
II-2
II-2
II-3
Section
Number
TABLE OF CONTENTS
(continued)
Section and Subsection Title
III REGIONAL POWER MARKET GENERATION REQUIREMENTS
1.
2.
3.
4.
5.
General
Haines Demand and Energy Forecast
a. Residential Load
b. Commercial Load
c. Tourism
d. Sewage Treatment Plant
e. Trans-Alaska Pipeline
f. Barite Mine
g. Industrial Load
h. Tank Farm
i. Public School
j. Schnabel Lumber Company
k. Boat Harbor Customers
1. Streetlight Customers
m. System Losses
n. Peak Demand
o. Monthly Distribution of Energy Use
Skagway Demand and Energy
a. Residential Load
b. Commercial Load
c. Tourism
d. Shopping/Residence Complex
e. Government Load
f. City Requirements
g. National Park Service Historic District
Restoration
h. The White Pass and Yukon Corporation
Limited Railroad
i. Electric Utility Use
j. System Losses
k. Peak Demand
1. Monthly Distribution of Energy Use
Impact of Conversions
a. Haines
b. Skagway
Existing Generating Facilities
a. Haines
b. Skagway
Page
Number
III-1
III-2
III-2
III-2
III-3
III-3
III-4
III-4
III-4
III-4
III-4
III-5
III-6
III-6
III-6
III-6
III-6
III-7
III-7
III-B
III-B
III-B
III-9
III-9
III-9
III-10
III-11
III-11
III-12
III-12
III-12
III-12
III-13
III-14
III-14
III-14
..
•
..
•
•
..
)
•
Section
Number
TABLE OF CONTENTS
( continued)
Section and Subsection Title
IV ALTERNATIVE MEANS OF GENERATION CONSIDERED
V
1 •
2.
3.
4.
5.
6.
General
Hydroelectric Generation
Diesel Generation and Waste Heat
a. Diesel-Electric Plants
b. Waste Heat Recovery
c. Application of Waste Heat Recovery
to Haines and Skagway
Wind Energy Conversion Systems
a. Description of the WECS
b. Application of WECS to Haines and Skagway
c. Costs
d. Environmental Considerations
Conservation
Wood Waste Generation
ALTERNATIVE PLANS IDENTIFIED FOR MEETING AREA
GENERATION REQUIREMENTS
1 •
2.
3.
4.
General
Base Case Plan
West Creek Hydroelectric Plan
Wood Waste Generation Plan
VI EVALUATION OF ALTERNATIVE PLANS
1 •
2.
3.
General
Economic Analysis
a. Method of Analysis
b. Annual Costs
c. Costs of Alternative Plans
d. Cost Comparison
Environmental Evaluation
a. Base Case Plan
b. West Creek Hydroelectric Plan
c. Wood Waste Generation Plan
VII GENERATION PLAN -CONCLUSIONS AND RECOMMENDATIONS
1 •
2.
Conclusions
Recommendations
Page
Number
IV-1
IV-1
IV-2
IV-2
IV-3
IV-3
IV-4
IV-5
IV-6
IV-6
IV-7
IV-7
IV-B
V-1
V-1
V-2
V-2
VI-1
VI-1
VI-1
VI-2
VI-2
VI-2
VI-3
VI-3
VI-3
VI-4
VII-1
VII-2
Section
Number
TABLE OF CONTENTS
(continued)
Section and Subsection Title
PART B: FEASIBILITY INVESTIGATIONS
OF WEST CREEK HYDROELECTRIC PROJECT
VIII EXISTING SITE CONDITIONS
1.
2.
3.
4.
5.
General
Topography
Geology
Environmental Setting
Land Ownership and Use
IX FIELD INVESTIGATIONS
X
1 •
2.
3.
4.
Site Reconnaissance
Land Surveys and Topographic Mapping
Environmental Studies
Geotechnical Investigations
HYDROLOGY
1. General
2. Runoff and Annual Basin Yield
a. Streamflow Records
b. Precipitation and Runoff Correlations
c. Estimated Basin Yield
3. Flood Studies
a. Construction Diversion Flood
b. Probable Maximum Flood
4. Reservoir Sedimentation
XI PROJECT OPERATION STUDIES
1 •
2.
3.
4.
General
Project Sizing
Input Data
a. Reservoir Inflows
b. Reservoir Characteristics
c. Losses
d. System Load Characteristics
Power Operation Studies
a. Method of Project Operation
b. Operation Study Results
Page
Number
VIII-1
VIII-1
VIII-1
VIII-2
VIII-3
IX-1
IX-1
IX-1
IX-2
X-1
X-1
X-1
X-1
X-2
X-2
X-2
X-2
X-4
XI-1
XI-1
XI-1
XI-1
XI-2
XI-2
XI-2
XI-2
XI-2
XI-3
...
•
•
TABLE OF CONTENTS
(continued)
•
Section Page
Number Section and Subsection Title Number
XII ALTERNATIVE PROJECT ARRANGEMENTS
• 1 • General XII-1
2. Dam and Spillway XII-1
a. General XII-1
b. Concrete-Gravity Dam XII-1
c. Concrete-Faced Rockfill Dam XII-2
d. Comparison of Dam Alternatives XII-3
e. Diversion Alternatives XII-3
3. Power Intake Alternatives XII-3
4. Power Conduit and Powerhouse Alternatives XII-4
a. General XII-4
b. Type of Power Conduit XII-4
• c • Location XII-5
d. Alternative Arrangements XII-5
e. Comparison of Alternatives XII-7
f. Refinement of Selected Alternative No. 1 XII-7
g. Powerhouse Superstructure XII-B
5. Transmission Line Alternatives XII-B
a. General XII-B
b. Transmission Line Corridor Alternatives XII-9
c. Alternative Transmission Line Evaluation XII-10
XIII SELECTED PROJECT ARRANGEMENT
1 • General XIII-1
2. Reservoir XIII-1
3. Dam and Spillway XIII-1
4. Power Intake XIII-2
5. Power Conduit XIII-2
6. Powerhouse XIII-3
7. Transmission System XIII-3
B. Access Roads XIII-4
9. Design and Construction Schedule XIII-4
10. Future Expansion XIII-5
Section
Number
TABLE OF CONTENTS
(continued)
Section and Subsection Title
XIV EFFECT ON ENVIRONMENT OF THE SELECTED
PROJECT ARRANGEMENT
1. General
2. Fisheries Resources
3. Water Quality
4. Wildlife
5. Historic and Archaeological Resources
6. Socioeconomic
7. Recreational Resources
8. Aesthetic Resources
9. Air Quality
10. Land Use
XV PROJECT COSTS
1. General
2. Project Capital Costs
a. Direct Construction Cost
b. Contingencies
c. Engineering and Owner Administration
d. Total Construction Cost
e. Interest During Construction
f. Total Investment Cost
g. Escalation Adjustment
3. Annual Costs
XVI REFERENCES
PART C: COMMENTS FROM REVIEWING AGENCIES
Summary of Public Meetings
Division of Parks, Department of Natural Resources
APA Response of May 27, 1982
APA Response of August 2, 1982
Division of Parks Letter of September 7, 1982
Alaska Power Administration
Barbara D. Kalen, Skagway
Haines Light and Power
U.S. Fish and Wildlife Service
APA Response
Skagway Resolution
Page
Number
XIV-1
XIV-1
XIV-4
XIV-5
XIV-7
XIV-8
XIV-10
XIV-11
XIV-12
XIV-13
XV-1
XV-1
XV-1
XV-1
XV-2
XV-2
XV-2
XV-2
XV-2
XV-2
..
•
..
II
•
Section
Number
TABLE OF CONTENTS
(continued)
Section and Subsection Title
Alaska Power & Telephone Co.
APA Response
National Park Service
APA Response
Department of Natural Resources
Department of Fish and Game
APA Response
Skip Elliot
Division of Energy and Power Development
APA Response
Division of Budget and Management
APA Response
PART D: SUMMARY OF GENERATION ALTERNATIVES
Page
Number
•
•
Table
Number
111-1
111-2
111-3
111-4
111-5
111-6
111-7
111-8
111-9
111-10
111-11
111-12
111-13
Vl-1
VI-2
VI-3
VI-4
VI-5
VI-6
VI-7
VI-8
VI-9
VI-10
Vl-11
VI-12
X-1
X-2
X-3
X-4
LIST OF TABLES
Title
Historical Energy Use -Haines Light and Power
Population Projections -Haines
Projection of Community Energy Use for Haines -Scenario A
Projection of Community Energy Use for Haines -Scenario B
Historical Energy Use -Alaska Power & Telephone Company, Skagway
Population Projections -Skagway
Projection of Community Energy Use for Skagway -Scenario A
Projection of Community Energy Use for Skagway -Scenario B
Projection of Community Energy Use for Haines -Scenario C
Projection of Community Energy Use for Skagway -Scenario C
Energy in kWh by Month for Haines and Skagway
Peak Load Forecast
Energy Requirements Forecast
Economic Analysis Scenario B:
Economic Analysis -Scenario B:
Economic Analysis -Scenario B:
Base Case-Diesel Generation
West Creek Project
Wood Waste Generator Case A
Economic Analysis -Scenario B: Wood Waste Generator Case B
Economic Analysis -Scenario A:
Economic Analysis -Scenario A:
Economic Analysis -Scenario A:
Economic Analysis -Scenario C:
Economic Analysis -Scenario C:
Economic Analysis -Scenario C:
Summary of Economic Analysis
Base Case-Diesel Generation
West Creek Project
Wood Waste Generator
Base Case-Diesel Generation
West Creek Project
Wood Waste Generator
Comparison of West Creek Plan On-Line Dates
West Creek Project Average Monthly Discharge in cfs at West Creek
Near Skagway USGS Gaging Station No. 15056200
West Creek Project Average Monthly Discharge in cfs Adjusted
to Dam Site
West Creek Project Peak Flows at West Creek Gage
West Creek Project Probable Maximum Precipitation and Snowmelt
Xl-1 West Creek Project Summary of Basic Input Data
XI-2 West Creek Project Reservoir Inflow (acre-feet)
XI-3 West Creek Project Total Energy Required (MWh)
XI-4 West Creek Project Total Energy Generated (MWh)
XI-5 West Creek Project End-of-Month Reservoir Storage (acre-feet)
XI-6 West Creek Project End of Month Reservoir Elevation (feet)
XI-7 West Creek Project Discharge Through Units (cfs)
XI-8 West Creek Project Spill (cfs)
Table
Number
XII-1 West Creek Project
XII-2 West Creek Project
XIV-1 West Creek Project
XV-1 West Creek Project
XV-2 West Creek Project
LIST OF TABLES
(continued)
Title
Comparison of Power Conduit Alternatives
Transmission Evaluation Summary
Property Ownership in Project Vicinity
Construction Cost Estimate Summary
Construction Cost Estimate
,
•
•
Figure
Number
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Location Map
Load Forecast
LIST OF FIGURES
Title
West Creek Project Flood Hydrographs
West Creek Reservoir Area-Capacity Curves
West Creek Project -Alternative Power Conduit Arrangements
West Creek Project -Alternative Transmission Corridors
West Creek Project -Alternative Transmission Corridor "A" System
One-Line Diagram
West Creek Project -Alternative Transmission Corridor "B" System
One-Line Diagram
West Creek Project -Alternative Transmission Corridor "C" System
One-Line Diagram
West Creek Project -Selected Dam and Power Plant Arrangement
West Creek Project -Dam and Spillway Arrangement
West Creek Project -Power Intake and Conduit Details
West Creek Project -Powerhouse and Tailrace Channel Arrangement
West Creek Project -Powerhouse Details
West Creek Project -Selected Transmission Corridor
West Creek Project -Regional Setting
West Creek Project -Historical and Archaeological Resources
West Creek Project -Land Ownership
West Creek Project -Design and Construction Schedule
SUMMARY
In July 1981 the Alaska Power Authority (APA) authorized a detailed
~ feasibility study to determine the technical, economic, and environmental fea-
sibility of a hydroelectric project on West Creek as a means of meeting the
future electrical requirements of Haines and Skagway. APA' s decision was
based on two previous studies of energy in the Haines-Skagway Region. The
West Creek Project site is about 6 miles northwest of Skagway. West Creek
flows into the Taiya River about 3 miles above its mouth. Part A of this re-
port describes the load and energy forecast prepared for the two communi ties,
the alternative means of meeting these forecasts, and the economic and envi-
ronmental evaluations of the various means. Part B describes the results of
engineering and environmental studies of the West Creek Project conducted dur-
ing the latter part of 1981 and the early part of 1982.
Future energy and peak load requirements for the next 20 years were
evaluated taking into account local historical trends in energy consumption,
population growth, economic trends, and more specific information obtained
from local consumers. Three alternative growth scenarios were developed for
the region analyzing each city individually. The low scenario (Scenario A)
represents a conservative view of growth. The mid-range projection (Sce-
nario B) is a combination of the low scenario and other probable or likely
future loads identified. A third projection (Scenario C) reflects the future
impact of the communities' responses to stable and low relative electric
energy costs. This scenario includes increased trends in conversions of ex-
isting space heating to electric and similar trends for other major energy
users as well as adoption of electric space heating in all new residences and
businesses. The mid-range scenario was considered most reasonable for plan-
ning purposes and was adopted for this study. This scenario forecasts an
average growth in electric load of 4.6% per year in Haines and 3.2% in Skagway.
At present, electric energy needs in Haines are met by diesel gen-
eration. In Skagway the needs are met by a combination of diesel and hydro-
electric generation. Earlier studies had emphasized hydropower as the poten-
tially most viable means of meeting the future requirements. The current
study gave serious consideration to possible alternatives. Those identified
included wind energy conversion systems (WECS) , wood waste generation, waste
heat recovery from diesel generation, and conservation.
Skagway is known to experience prolonged wind, and a 10-kW WECS has
recently been installed in Skagway as a demonstration project. As of the
writing of this report, the results of this demonstration were inconclusive.
However, based on current costs and the most reasonable estimates of potential
output, it was concluded that WECS would have about twice the energy cost of
diesel generation. Thus, it was concluded that WECS were not an economical
alternative at this time.
Page 2
A 4,000-kW wood waste generation plant is currently being installed
at the Schnabel Mill in Haines and will be supplying electricity to Haines
under a five-year contract beginning early in 1983. Based on the terms of the
contract, wood waste generation will provide power at a lower energy cost than
the fuel cost of diesel generation. However, wood waste generation will not
supply the needs of Skagway, nor are the costs assured after the five years
covered in the contract. Despite these uncertainties, wood waste was consid-
ered a strong possibility which was tested economically.
Waste heat recovery and conservation both typically serve to reduce
the overall energy consumption; however, they would do little to reduce elec-
tric requirements in the region since they are primarily aimed at space heat-
ing, and there is little or no electric space heating presently installed in
Haines and Skagway.
Previous studies of the Haines-Skagway Region concluded that the
most economical hydroelectric project in the region would be the West Creek
Project with a storage reservoir and a transmission intertie between Haines
and Skagway. A detailed feasibility study was conducted and is the subject of
Part B of this report. The study included investigations of geology and hy-
drology, environmental studies, power studies, layouts, cost estimates, and
initial optimization of project features.
In order to meet the 1996 loads forecasted under the mid-range
growth Scenario B, a 6,000-kW development on the West Creek site would be
required. The Project would consist of a 117-foot-high concrete-faced rock-
fill dam creating a 635-acre reservoir with a normal maximum level at El 705;
a power intake; a power conduit consisting of 7,460 feet of unlined rock tun-
nel with a surge shaft and 1,520 feet of 3-foot-diameter steel penstock; an
indoor-type powerhouse containing two 3, OOO-kW turbine generators; a
1,200-foot-long tailrace channel from the powerhouse to West Creek; and a com-
bination of overhead, underground and submarine transmission lines construct-
ing with Haines and Skagway. The Project is estimated to have a Total Invest-
ment Cost of $55,908,000 for an assumed on-line date of January 1982 (current
cost level).
Environmental studies showed that the Project would have limited
adverse impacts. West Creek is too steep and fast flowing in the reach above
the Taiya Valley to allow easy migration of fish to its upper reaches. The
Project would flood 635 acres of wildlife habitat, but it is not considered
critical habitat and species living in the area should be able to relocate
wi thout problem. The transmission line would cross the Klondike Gold Rush
National Historical Park and could conceiveably impact some archaeological and
historical sites. Preliminary investigations do not reveal any conflicts with
the proposed route, but further study is necessary. The powerhouse would be
located within the boundary of the park which is prohibited by Federal law.
This will require a legislative change in the boundary or authorization of the
Project within the boundary before a License Application can be considered by
the Federal Energy Regulatory Commission. It seems reasonable to expect that
this would be possible as the Project will have limited aesthetic effect on
Park setting.
•
Page 3
To economically compare the various generation options, three al-
ternative plans were developed which could each meet the region's mid-range
scenario for forecasted loads. The first, or base case plan, is basically a
continuation of the current status quo with the existing diesel and hydro
units meeting loads up to their capacity and new diesel generation being added
when required. The second plan assumes that the West Creek Project would be
built and used up to its capacity. Existing hydro units in Skagway would con-
tinue in operation and the existing diesel generators would initially serve as
reserves and later to meet needs beyond the capacity of the West Creek Proj-
ect. The third plan assumes that the wood waste generation being installed at
the Schnabel Mill would be used to meet part of the Haines load. Under this
plan diesel generators would still be needed to meet part of both the Haines
and Skagway loads.
The three plans were economically compared by calculating the pres-
ent worth life cycle cost of each plan for the mid-range load growth Sce-
nario B over a 55-year analysis period using APA's prescribed procedure. Con-
sistent with this procedure, fuel oil was assumed to escalate at 2.6% per year
for 20 years, but all other costs were assumed free of inflation, and an in-
flation-free discount rate of 3% was used. The resulting costs were:
Base Case Plan
West Creek Plan
Wood Waste Plan
$116,562,000
$ 92,031,000
$101,337,000
Thus, West Creek was determined to be the most economical alternative and the
report recommends that development of this Project proceed immediately. As-
suming a change in the National Park boundary can be made in a timely manner
and that a FERC License is received by spring 1984, construction can be com-
pleted by the middle of 1986.
•
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
SUMMARY OF PRINCIPAL STATISTICS
OF RECOMMENDED GENERATION PLAN:
WEST CREEK HYDROELECTRIC PROJECT
BASIN HYDROLOGY
Drainage area above dam (sq. mi.)
Average annual runoff at dam site
Average annual runoff per sq. mi.
....................................
(ac-ft) ........................ .
(cfsm) ............................ ..
PROJECT POWER DATA
Annual firm energy generated (MWh) •••••••••••••••••••••••
Installed capacity (kW) ••.•••••••••••••••••••••••••••••••
Average annual gross head (ft) •••••••••••••••••••••••••••
RESERVOIR
Normal maximum power pool elevation (ft) ••••••••••••••••.
Minimum power pool elevation (ft) •••••••..•••••••••••••••
Reservoir area at normal maximum pool (ac) •••••••••••••••
Active storage capacity (ac-ft) •••••••••••..••••.••••••••
DIVERSION
Type -Embankment Cofferdam and Concrete Diversion Pipes
Maximum cofferdam height (ft) ••••.•••••••••••••••••••••••
Diversion Pipes(2):
Inside diameter (ft) .................................................... ..
Length (ft) ...................................................................... ..
Maximum discharge (efs) ......................................................... ..
DAM
Type -Concrete-Faced Rockfill
Crest elevation (ft) ..................................................................... ..
Crest length (ft) .............................................................................. ..
Maximum height above foundation (ft) ••••.•••••••••••.••••
Total volume (oy) .............................................................................. ..
37.2
208,500
7.75
23,630
6,000
660
705
660
635
18,130
22
11
765
5,500
729.5
1,000
120
254,000
Page 2
SPILLWAY
Type Ungated Broad Crested Weir Control
With Unlined Chute
Crest length (ft) ••••••••••••••••••••••••••••••••••••••••
Chute side slopes (H:V) •••••.•••••••••••.•.•.....•..••••.
Crest elevation (ft) .................................... .
PMF surcharge elevation (ft) •••••••••••••••••••••••••••••
p~ discharge (ers) ..................................... .
POWER INTAKE
Type -Inclined Intake Structure With Fixed Wheel Gate
and Steel Trashrack
75
0.5: 1
705
729.3
30,600
Intake invert elevation •••••••••••••••••••••••••••••••••• 630
POWER CONDUIT
Type -Tunnel and Steel Penstock
Unlined Tunnel Section
Length (ft) ........................................... .
Inside diameter (ft) .................................. .
Maximum velocity (fps) ................................ .
Manning's "n" (no supports) ••••••••••••••••••••••••••••
Lined Tunnel Section
Length of concrete-lined (ft) ••••••••••••••••••••••••••
Length of steel-lined (ft) •••••••••••••••••••••••••••••
Inside diameter (ft) .•...............•......•........•.
Maximum velocity (fps) ........................ _ ........ .
Single Shaft
Diameter (ft) ......................................... .
Elevation of top (ft)
Penstock
Length (ft) ........................................... .
Maximum inside diameter (ft) •••••••••••••••••••••••••••
Maximum velocity (fps) ........•........................
POWERHOUSE
Type -Indoor With Pre-cast Concrete Superstructure
7,300
9.5
2
0.017
160
70
7.5
3.2
9.5
740
1,520
3
21.2
Width (ft) ............................................... 40
Length (ft) ......... ct • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • 57
Height (ft) .............................................. 20
Unit spacing (ft) ...............•........................ 25
Centerline generator shaft elevation (ft) •••••••••••••••• 45
Generator floor elevation (ft) •••••...••.•..••••••••••••• 42
Normal operating tailwater elevation (ft) ••••..•••••••••• 38
•
..
..,
TAILRACE CHANNEL
Length (ft) ............................................. .
Bot tom width (ft) ....................................... .
Side slopes (H:V) ....................................... .
POWERHOUSE EQUIPMENT
1,200
5
1.5: 1
Page 3
Number of generating units •••••••.•••••••••••••••••.••••• 2
Inlet valve diameter, two (inches) •••••••.••••••••••••••• 24
Turbines, Type -Horizontal Shaft Francis Units:
Net rated head (ft) .................................... .
Rated capacity, best gate (hp) (each) •••••••••••••••••.
Speed (rpm) ••••••••••••••••••.•••••••••••••••••••••••••
Discharge at full-gate and rated head (cfs) ••••••.•••••
Maximum gross head (ft) •••••.•••••••••.••••••••••••••••
Minimum gross head (ft) ............................... .
Generators, Type -Horizontal Shaft Synchronous
With Enclosed Cooling
Generator rating at 0.9 pf, 60 0 C temperature rise (kVA)
SWITCH YARD
No. of transformers (three-phase) ••••••••••••••••••••••••
Transformer voltage (kV) ••••••••••.••••••••••••••••••••••
Transformer bank (kVA) •••..•••••....•••.••••••••.••.•••••
TRANSMISSION LINE
Type -Wood Pole Construction With Single Crossarm
Overhead
Voltage (kV) •••••••••••••••••••••••••••••••••••••••••••
Conduc tor size ........................................ .
Switchyard to Skagway switch (mi) ••••••••••••••••••.••.
Submarine
Type -Oil Impregnated Paper Insulated
Single Conductor, 4 cables (1 spare)
Voltage (kV) •••••....•••.••••..•••...••..•.•••..•.••.••••
Conductor size .......................................... .
Length (mi) .•..••.•.•..•••....•....•.•.•...••......•.....
ACCESS ROAD
635
4,200
1,200
65
667
624
3,450
1
13.8-34.5
7,200
34.5
2/0 ACSR
6.2
34.5
1/0 Copper
16.6
Length (mi) ••••••••..••.•••.•..••...•..•....•....••...... 3 . 2
PART A: SELECTION OF GENERATION PLAN
•
•
SECTION I
INTRODUCTION
1 • GENERAL
Initial reconnaissance studies performed for the Alaska Power
Authority (APA) indicated that the West Creek Hydroelectric Project is prob-
ably the most feasible means of meeting the future electric energy require-
ments of the Haines-Skagway Region. The investigations summarized in this
report were undertaken by R. W. Beck and Associates, Inc. (Beck) under the
direction of APA to determine if West Creek would remain the most feasible
approach when it and the other alternatives available were subjected to more
detailed feasibility level investigations. If confirmed, this would then al-
low APA to proceed with development of the Project pending appropriate legis-
lative approval.
Part A of this report titled "Selection of a Generation Plan" dis-
cusses the detailed investigations of projected energy requirements of the
Haines-Skagway Region; the available alternative plans for meeting these
needs, including West Creek; the relative feasibility of each; and concludes
with recommendations for future action.
Part B titled "Feasibility Investigations of West Creek Hydroelec-
tric Project" describes the detailed investigations conducted to determine the
technical, economic and environmental data required in the Part A feasibility
test. These more detailed studies are required because of the site specific
and capital intensive nature of any hydroelectric project.
Part C includes comments from reviewing agencies and other inter-
ested parties.
2. AUTHORIZATION
The work described in this report was authorized in a contract
dated July 15, 1981 between APA and Beck.
3. BACKGROUND
The energy requirements of Haines and Skagway and the means of
meeting those requirements have been the subject of two recent reports. In
February 1980, CH2M Hill issued a report titled "Reconnaissance Assessment of
Energy Alternatives, Chilkat River Basin Region" (Reconnaissance Report)(1)
which evaluates the various alternatives for supplying electric energy to
Haines and Skagway. That report concludes that the Dayebas Creek Project
should be developed to serve the needs of Haines and that the existing hydro
projects in Skagway be expanded to meet needs in that community.
1-2
Based on that report, together with an in-house evaluation, the APA
retained Beck to perform a more detailed reconnaissance of five sites in the
Haines-Skagway Region to determine the site which appeared most sui table for
meeting the future energy needs of the two communities. The results of this
study are presented in the "Addendum to Reconnaissance Report on Alternatives
for the Haines-Skagway Region" (Addendum). (2) The study concluded that the
West Creek Project with an intertie between Haines and Skagway would be the
most economical means of meeting long-term energy needs in the region.
4. SCOPE OF CURRENT INVESTIGATIONS
The investigations described in this report determine the feasibil-
ity of development of the West Creek Project as a means of meeting the future
energy needs of the Haines and Skagway region. Consistent with the overall
approach to this study, the tasks involved in the current investigations were
generally divided into two parts: those associated with selecting the recom-
mended generation plan for the region (Part A) and those tasks directly asso-
ciated with the detailed investigations of the West Creek site (Part B). The
studies included the following tasks:
PART A: SELECTION OF A GENERATION PLAN
a. Electrical Load Forecast
An electrical load forecast for the 20-year period 1982 through
2001 was prepared. The forecast was based on a time-series analysis of his-
toric population and electrical energy use data tempered with assumptions con-
cerning future economic growth.
b. Alternative Means of Generation
Al ternative means of generation which could meet the forecasted
loads were investigated. Three plans of generation were developed, a base
case plan, the West Creek hydroelectric plan, and a non-hydro alternative plan.
PART B: DETAILED INVESTIGATIONS OF THE WEST CREEK SITE
c. Economic Analysis
The most economical means of meeting the forecasted loads was
determined by comparing the base case plan, the West Creek hydroelectric plan
and the non-hydro plan.
d. Mapping and Surveys
Topographic maps of the West Creek site were prepared from aerial
photographs. Land surveys were made to provide ground control for the topo-
graphic mapping and to locate drill holes, seismic lines and test pits. A
"
(
..
1-3
hydrographic survey of the proposed submarine transmission line route was also
made. This work was performed by Tryck, Nyman & Hayes of Anchorage under sub-
contract to Beck.
e. Geotechnical Investigations
The geotechnical field program consisted of geologic reconnaissance
and mapping, subsurface drilling, seismic refraction surveys, and sampling of
potential borrow areas. Laboratory testing and analysis, evaluation of the
field and laboratory data, initial evaluation of regional seismicity, and
preparation of a report completed the geotechnical investigations. This work
was performed by Converse Consultants, Inc. under subcontract to Beck.
f. Hydrology and Power Studies
Based on the 16-year streamflow record at the West Creek gage,
power studies were performed to determine reservoir size. Flood studies were
made to estimate the Probable Maximum Flood and to size the spillway and
diversion facilities.
g. Project Layouts
The preliminary layout shown in the Addendum was refined based on
the new topographic, geologic, and hydrologic information gathered in this
phase.
h. Cost Estimate and Schedule
Using the refined Project layout, quantities were estimated. A
construction cost estimate was made using these quantities, unit costs from
similar projects, and detailed construction cost estimates for selected major
cost features. The design and construction schedule was refined.
i. Environmental and Socio-Institutional Studies
Environmental investigations of terrestrial and aquatic resources,
historical and archaeological resources, socioeconomics, aesthetics, and land
use were undertaken to determine the potential impacts of the Project develop-
ment. These investigations included field studies, office evaluations, and
discussions with concerned agencies. Portions of this work were performed by
Environaid, Inc. of Juneau under subcontract to Beck.
j. Report
This Feasibility Report was prepared based on the results of the
above described investigations.
•
•
SECTION II
SITE DESCRIPTION
1 • GEOGRAPHY
The City of Haines is located in Southeast Alaska on the Chilkoot
Peninsula near the mouth of Taiya Inlet. (See Fig. 1.) Approximately 16 miles
north of Haines, the City of Skagway is located at the head of Taiya Inlet at
the mouth of the Skagway River. The two cities are about 80 miles north of
Juneau. Roads from both cities connect with the Alaskan Highway in Canada.
The White Pass and Yukon Railroad runs north from Skagway to Whitehorse,
Canada.
The proposed West Creek Project site is located about 6 miles
northwest of Skagway. West Creek is a tributary of the Taiya River which
flows into the north end of Taiya Inlet near the mouth of the Skagway River.
2. TOPOGRAPHY
The Haines-Skagway Region is characterized by steep, rugged ridges
divided by rivers and streams running from high glaciers and snowfields down
to inlets from the ocean. The inlets are generally steep sided with depths to
greater than 1,000 feet. Mountain peaks are generally at the 5000 to
6000 foot elevation. Level ground is limited to the floodplains of the rivers.
The present topography of most of this region is largely the result
of continental and alpine glaciation during the Pleistocene Epoch, approxi-
mately 13,000 years ago. During the last glacial period, an average of 5,000
feet of glacial ice covered most of this region. The weight of the glacier
significantly depressed the land. Upon retreat of the glaciers, many valleys
which had been occupied by ice were inundated by the sea. Ongoing isostatic
rebound has resulted in the slow emergence of several areas of land in this
region above the present sea level including some marine and beach deposits in
coastal areas of Haines and Skagway. Hanging valleys, elongated and deepened
lakes, U-shaped valleys, and deeply scoured embayments, inlets and passages
also reflect the effects of regional glaciation. Locally, a number of alpine
glaciers still occupy the steep-walled valleys and higher mountain sides •
3. GEOLOGY
within the
plex lies
zoic Era.
The Haines-Skagway Region and the West Creek Dam site are located
Coast Range Batholith Complex of the Pacific Coast Range. The Com-
within a region which has been geologically active since the Paleo-
The geologic system of this region is related to interaction of
II-2
plate tectonics, collision and subduction of oceanic and continental plates.
This tectonic belt has been active since at least the late Paleozoic period
and the last major deformation occurred during the late Mesozoic and Tertiary
periods with some minor activity continuing into the Quaternary.
The region has had a complex history of sedimentation, deformation,
igneous intrusion, glaciation and erosion. The bedrock which underlies the
major portion of the region consists primarily of granitic crystalline intru-
sive rocks, ranging in age from Tertiary to Cretaceous period in age, approxi-
mately 40 to 140 million years before the present. Tectonic deformation of
the regional rocks has produced two distinct structural trends, northwest-
southeast and northeast-southwest. These structural trends in the form of
joints and/or shear zones have produced strong lineaments which are evident as
topographic lows on the ground surface and in aerial photographs.
A detailed discussion of the regional geology is presented in the
report titled "Phase II Geotechnical Investigation, West Creek Hydroelectric
Project, Haines-Skagway Regional Studies" prepared by Converse Consultants,
Inc., which is included as Appendix C of this report.
4. CLIMATE
The climate in the Haines-Skagway Region is influenced by interior
and maritime weather patterns and by the surrounding topographical features.
Southeast Alaska is located in the maritime climatic zone which generally ex-
periences considerable precipitation. Climatological records in Haines are
typical of this climate with a mean annual precipitation of 61 inches and a
mean annual snowfall of 133 inches. The mean annual temperature in Haines is
40 0 F with a mean daily maximum in July of about 66 0 F and a mean daily min-
imum in January of 17 0 F. Skagway is located in the rainshadow of the coast-
al mountains and therefore receives significantly less precipitation. Skagway
has an annual precipitation of approximately 26 inches with a mean annual
snowfall of around 39 inches. The mean annual temperature of Skagway is
41 0 F with a mean daily maximum in July of about 67 0 F and a mean daily min-
imum in January of 18°F. Winds in the Skagway area are generally fairly
strong (average speed = 13.0 mph) and are channelled to northerly and south-
erly directions by the mountains surrounding Taiya Inlet.
5. NATURAL ENVIRONMENT
The Haines-Skagway Region is characterized by thick vegetation on
the mountain slopes and in the valleys and by numerous streams. Coniferous
forests dominated by Sitka spruce and western hemlock extend from the timber-
line at approximately El 3000 feet down onto the valley floors. At lower ele-
vations, muskegs or bog plant communities are often interspersed with the for-
est. Riparian shrubs including willow and alder are found along the streams
and black cottonwood stands are common in the major river valleys. In the al-
pine zone above the timberline, heaths and grasses dominate.
•
II-3
Wildlife is abundant in this environment. Common wildlife species
include mountain goat, black bear, river otter, marten, porcupine, red squir-
rel, grouse, golden eagle, bald eagle, and various other species of small mam-
mals and birds. Fisheries resources of the area include coho salmon, chum
salmon, pink salmon, Dolly Varden char, and eulachon. All of these fish spe-
cies are found in the Taiya River but only Dolly Varden char and eulachon are
known in West Creek.
6. SOCIOECONOMIC SETTING
The City of Skagway corporate limits encompass 431 square miles and
include the West Creek Project site. Skagway had a 1980 census population of
768. Most of the employment in Skagway is associated with the White Pass
Railway or summer tourism. The City with its historic Klondike Gold Rush her-
i tage and ready access to White Pass and the Chilkoot Pass Trail is a major
Alaska cruise ship and Alaska ferry tourist destination.
The City of Haines had a 1980 census population of 993. Haines is
located about 20 miles south of the West Creek Project site. The City serves
as a shipping point for the interior via the Haines Highway. Haines has an
economy which is typical of Southeast Alaska with employment primarily in lum-
ber production, fisheries, transportation, trade and services. Tourism was a
significant local industry until its decline in recent years. There are new
efforts underway to reestablish this resource.
..
..
•
•
SECTION III
REGIONAL POWER MARKET GENERATION REQUIREMENTS
1. GENERAL
As part of the current studies, a forecast of energy and peak de-
mand was prepared for both Haines and Skagway to determine the extent of
future growth in electric requirements. The methodology used in preparing the
forecast included an evaluation of historical trends in energy consumption,
population growth of the cities, economic trends and specific information ob-
tained through conversations with local consumers. Saturation of major en-
ergy-using appliances was considered in the consumption-per-customer projec-
tions although specific appliances could not be analyzed individually due to a
lack of available data. Potential conversions to electric space heat and
building construction trends were also considered and the associated impact
was evaluated in the forecast.
An attempt was made to conform to the forecast format established
in the CH2M Hill Reconnaissance Report.(1) The historical data were up-
dated, the assumptions were reevaluated and in some cases adjusted to reflect
more recent trends and developments.
Three growth scenarios were developed for each city which were
premised on differing economic assumptions. The low or base projections (Sce-
nario A) represent the most conservative view of growth. A second set of pro-
jections (Scenario B) includes loads which will probably occur, but are not as
assured as those in Scenario A. Scenario B is the load forecast used for
planning and for the economic analysis of the proposed plans. In each case
the loads are tied to population projections which also have high and low
growth assumptions behind them.
A third growth scenario (Scenario C) was created which evaluates
the potential impact of the communities' responses to a relatively low-cost
and stable power base. This scenario assumes that the State of Alaska would
set the cost of power from a new hydroelectric project at levels enough below
alternative energy costs to encourage conversions to electricity for existing
space heating and other major end uses as well as construction of new all-
electric residences and businesses in both communities.
The following descriptions provide an
and methodologies used in developing Scenarios A
Scenario C is described in a subsequent section.
scenarios in a graphical form •
explanation of assumptions
and B for each community.
Figure 2 shows the three
III-2
2. HAINES DEMAND AND ENERGY FORECAST
a. Residential Load
The City of Haines grew by 45.4%, or by nearly 4% compounded annu-
ally, between 1970 and 1980. However, since 1977, the City has had an 18%
decrease in population. This population fluctuation during the last decade
was caused by steady sawmill activity and a strong tourist industry in the
early 1970's followed by a mill closure, decreasing tourism, and U.S. Army POL
dock and tank farm closure in the later 1970' s. As a result, the number of
residential customers and hence, total residential requirements during that
time have also varied accordingly.
The 1980 U.S. Census shows a population of 993 for the City of
Haines and a total of 1,433 for the greater Haines area, which is the base
population used for the forecast. (See Table 111-2.) Scenario A assumes that
the base population increases at a rate of 1.0% per year and Scenario B at an
average of 2.25% per year. The direct and indirect changes in employment were
then added to this base to produce a total population projection for each
growth scenario. One indirect employee was assumed per direct employee and
1.8 residents were added to the area per new employee. These multipliers were
developed by CH2M Hill based on 1979 employment levels and are discussed in
the Reconnaissance Report. (1) These multipliers appear reasonable for this
level of analysis. This calculation produced a 1.2% average compound annual
population growth rate for Scenario A and a 3.2% annual population growth rate
for Scenario B.
The average electricity usage per residential customer has been
decreasing slightly over the past few years due to conservation in response to
economic conditions and increasing electricity costs. For both scenarios it
was assumed that kilowatt-hour consumption per residential customer will re-
main constant at the 1981 level for the next three years implying continued
conservation efforts. For the following ten years consumption is projected to
increase by 1.5% per year, reflecting a rise in the standard of living, and is
projected to remain constant thereafter. The leveling off assumes that resi-
dences of the area will be approaching a saturation of major electricity-using
appliances similar to consumption levels of other Southeast Alaska cities.
Nei ther Scenario A or B assumes a significant number of conversions to elec-
tric space heating nor significant trends to include electric space heating in
new homes. Table III-1 shows historical loads for each customer class in
Haines and Tables 111-3 and 111-4 give the results of Scenarios A and B, re-
spectively.
In 1981 the ratio of area population to residential customers for
Scenario A was 2.36 and 2.40 for Scenario B. These ratios were kept constant
for the length of the forecast.
b. Commercial Load
For the past few years there has been an average of 3.0 residential
customers for every commercial customer in the Haines area. This relationship
•
III-3
was assumed to prevail for each year of the forecast for both Scenarios A
and B.
The electricity usage per commercial customer increased about 5.7%
annually since 1971 but in more recent years has shown about half that rate of
annual increase, reflecting the use of conservation measures during a time of
increasing fuel and electricity prices. For each year of the forecast, it was
assumed that consumption per commercial customer would increase at the rate of
2% annually. This allows for continued growth by businesses wi thin the area
but also includes a conservation factor.
c. Tourism
Tourism was a larger industry in Haines in the early 1970' s when
cruise ships made regular stops in the City than it is now. The City now
relies on the Alaska State ferries, airlines and the highway to transport vis-
itors. People are attracted to the area primarily for its scenic beauty, its
Indian culture, its access to Glacier Bay and the eagle nesting area of the
Chilkat River Valley, and its sport fishing.
Beginning in 1982, Haines will be a stopping point for an Alaska
Tours and Marketing 124-passenger cruise ship, which will bring additional
tourist activity to the area. In an attempt to round out the tourist season
through the winter months, the City now celebrates a 2-week winter carnival
which includes a variety of snow sports and related activities. Plans are to
expand this carnival to a 10-week celebration which would include a variety of
art and cultural events as well as outdoor sports and other activities. Po-
tential attractions are seminars on art and music, cross-country ski events,
creation of a downhill ski area, and aqua and arena shows. The Smithsonian
Institute has indicated that it intends to conduct Audubon tours during the
winter season, beginning in 1983, to view the bald eagle which is prevalent in
the area.
A new motel, the Captain's Choice, is currently being constructed
in phases. Eight units are now open and 22 more are expected to be finished
by the Fall of 1982. Forty-two units in all with a total of 40,000 square
feet will be constructed by 1984. There is a possibility that some of the
future units may use electricity for space heating.
For Scenario B, it was assumed that the winter carnival activities
would attract 10 additional people in permanent jobs in the years 1983, 1984
and 1985.
d. Sewage Treatment Plant
The Haines sewage treatment plant ceased providing secondary treat-
ment to sewage from the greater Haines area in early 1982. The Environmental
Protection Agency has given the City approval to discharge sewage into tidal
waters after primary treatment. Consequently, the plant's 35,000 kWh per year
electric requirements are expected to decrease by 75%, beginning in 1982. In
III-4
both Scenarios A and B the commercial class requirements were adjusted accord-
ingly, beginning in 1982.
e. Trans-Alaska Pipeline
If the Trans-Alaska natural gas pipeline is constructed, the Port
of Haines is also likely to be used for transportation of materials and equip-
ment. The extent of trucking, labor and related facilities required is still
undetermined but significant impact on the economy can be anticipated. For
Scenario B, an additional 40 new workers were added in the year 1986 and 20
more in 1987 to account for pipeline activity in Haines. After 1989 it was
assumed that 50% of the pipeline workers would remain in the Haines area.
f. Barite Mine
The Alyu Mining Corporation is planning to build a barite mine near
Haines. Following a few years of test drilling, the mine's potential is still
being evaluated and capital is being raised. Employment estimates vary from
30 to 50 people between 5 and 8 years from now. Thus, included in Scenario B
are an additional 30 direct employment workers in 1988 and 10 more in 1989 to
account for the mining, milling and transportation activity. The mining site
is about 35 miles from Haines and will not be served by Haines Light and Power
(HLP) •
g. Industrial Load
Electric requirements of the three industrial customers, the tank
farm, public school and Schnabel Lumber Company, were projected individually,
reflecting knowledge gained from local interviews.
For Scenario B a new industrial customer with beginning annual re-
quirements of 300, 000 kWh was added in 1991. This load was assumed to in-
crease by 1% each year. This load could represent a new fishing-or mining-
related acti vi ty, or it could be an existing small commercial load which has
graduated into the large commercial class because of increasing size.
h. Tank Farm
The U.S. Army POL tank farm load was assumed to remain constant for
the duration of the forecast in both growth scenarios as no expansion is now
foreseen for that facility.
i. Public School
The public school electric requirements were assumed to increase by
2% in 1982 and 1983 to reflect completion and operation of the school's new
swimming pool. Beyond 1983, requirements were assumed to increase by 1% each
year for both scenarios.
III-5
j. Schnabel Lumber Company
The future timber supply of the Schnabel Lumber Company has become
more secure with the signing of a contract with the Alaska Department of
Natural Resources (DNR) in August 1979, although as much as an additional two-
thirds of Schnabel's timber comes from private and U.S. Forest Service lands.
The DNR contract, which allows for 10.2 million feet of saw timber to be cut
per year, is in effect for 15 years, and is renewable for another ten years if
a wood waste treatment plant is constructed and if, in the last 5 of those
10 years, half of the wood products goes to the local market.
The Schnabel sawmill currently employs 41 people, which is a fairly
stable year-round employment level. The associated logging operation employs
between 15 (winter) and 30 (summer) workers. Logs are also provided by North-
ern Timber Corporation which employs 9-10 people.
Because the DNR contract and the good routes now available for log
transportation make the future of the mill seem reasonably secure, the mill is
making plans to add a planer and a dry kiln to expand the types of lumber
products produced at the plant. No significant expansion in staff is antici-
pated in spite of these changes.
The mill experienced a nearly 6-month shutdown between October 1980
and April 1981 due to the wood products market depression. Although overall,
the Northwest and Alaska wood products industry has been experiencing a signi-
ficant slowdown, the mill's management feels that current markets are secure
for the near future and that a drop in the prime interest rate and Asian de-
mand for wood products will improve the outlook.
The Alaska Renewable Resources Corporation is finanCing the build-
. ing of a 4,OOO-kW wood waste-fired generating plant at the mill. The Project,
which is now under construction, is scheduled for operation by summer 1983.
During the year and a half construction time, a crew of 20 people (most from
outside the Haines area) will be needed. When the plant is operating, a nine-
person staff will be hired to run the generator in addition to the existing
mill staff. For both Scenarios A and B, 15 construction workers were assumed
to be added to the local labor force for plant construction beginning in 1982.
A five-year contract has been signed between HLP and Schnabel
which, among other things, requires Schnabel to sell up to 2,000 kW of firm
capacity 24 hours a day, 365 days per year, as required, to HLP. For a more
detailed discussion of wood waste generation, see Section IV. The power sold
to HLP will be generated by the new wood waste generating plant beginning in
early 1983.
Historically, the amount of power purchased by the mill from HLP
has varied widely, depending on the availability of the mill's own diesel gen-
erators to produce power and on fluctuations in the wood products market. It
III-6
is expected that the mill will be able to meet all of its own power needs be-
ginning in 1983 when its wood-waste generator begins operation, and that back-
up power would be provided by its own diesel generators during annual sched-
uled maintenance and occasionally on an unscheduled basis. According to the
report, "1919 Updating of the Feasibility Study and Report on Generation of
Electrical Power From Wood Refuse" prepared by Nor'West Pacific Corpora-
tion, (3) future annual requirements of the generator's boiler and the mill
together would be 1,036,656 kWh assuming a 10-month, one-shift operation with
a peak of 2,123 kW.
The mill, including loads met by its own generation and purchases
from HLP, comprises about 36% of the community's electricity requirements.
Without the mill these requirements plus an estimated decrease of about 20%
within the residential and commercial sectors could also be expected.
k. Boat Harbor Customers
There are currently 10 boat slips in the Haines boat marina which
was built in 1918. About 45% of those are now occupied by boats year-round
which use electricity for lighting and heating. The remainder are seasonal
users only. The forecast projects year-round boat harbor customers to in-
crease at the rate of one new customer every two years and for consumption per
customer to increase by 0.5% every year of the forecast in both growth sce-
narios.
1. Streetlight Customers
Electricity usage for streetlighting in both scenarios was in-
creased at the rate of 1% annually.
m. System Losses
System losses, which have averaged about 10% historically, are pro-
jected to continue to be 10% for each year of the forecast in both scenarios.
n. Peak Demand
Based on historical annual load factors, projections of peak demand
were tied to the energy forecast using a constant load factor of 60% for both
scenarios.
o. Monthly Distribution of Energy Use
The 1919 energy use by month in Haines is shown in Table III-11.
Haines has a winter peak with use during the winter months being about 35%
greater than that during the summer.
•
III-7
3. SKAGWAY DEMAND AND ENERGY
a. Residential Load
The population of the City of Skagway grew by nearly 14% between
1970 and 1980, an average annual rate of 1.3%. The 1980 population according
to the U.S. Census was 768; however, the peak population year during the dec-
ade was 1976 when the population was estimated at 954. Since then some de-
cline has been experienced in two of the City's major employers, the tourist
industry and the operation of the White Pass and Yukon Railroad.
Skagway's 1980 population was used as the population base for the
forecast. (See Table III-6.) Scenario A holds the 1980 population constant
for the next two years, reflecting recovery time from the decreased economic
activity of the last few years. Beyond 1983 the base population is increased
at the rate of 1% annually. For the high growth scenario, the base population
is increased at the rate of 2% annually between 1981 and 1990 and by 3% annu-
ally beyond. The direct and indirect changes in employment were then added to
these bases to produce total population projections.
For Scenario A, no discrete employment changes were added to the
base population growth. For Scenario B, 30 employees were added to the base
in 1986 to account for natural gas pipeline construction and 15 more in 1987.
After 1989 it was assumed that 25% of the pipeline workers would remain in the
Skagway area. A multiplier of .4 was used to estimate the number of indirect
employees for every direct employee and a multiplier of 3 was used to calcu-
late total residents per employee. These multipliers were developed by CH2M
Hill and are discussed in their Reconnaissance Study( 1) and appear reason-
able for this level of analysis. This produced a .9% average annual compound
population growth rate for Scenario A and a 2.5% average annual compound popu-
lation growth rate for Scenario B.
The ratio of area population to 1980 residential customers was
2.52, which was assumed to hold constant for the duration of the forecast.
The 1980 consumption per residential customer was estimated to be
5,600 kilowatt-hours. For both scenarios this usage was assumed to prevail
for the following three years, after which it was increased at an annual rate
of 1.5% for the next ten years, reflecting a rise in the standard of living
with the purchase and use of more electricity-using appliances and is then
projected to level off beyond 1994. Recent conservation efforts in the Skag-
way area are obvious from the change in usage per residential customer which
dropped from 7,160 kWh in 1978 to 5,770 in 1980. However, to assume that con-
sumption would keep decreasing when the economy begins to grow again would be
unrealistic. The assumed growth in consumption-per-customer for years 1984-
1994 would bring consumption levels more in line with other areas of Southeast
Alaska.
Both the high and low scenarios of the forecast assume that there
will be no significant trends toward building homes with electric space heat-
ing nor a significant number of conversions from other fuels to electrici ty
III-8
for space heating. This analysis does not consider any potential impact of
varying fuel prices upon space heating preferences among residential custo-
mers. Table III-5 gives Skagway's historical load data by class of customer
and Tables 111-7 and 111-8 give the Scenario A and B forecasts, respectively.
b. Commercial Load
In 1980 there were 3.7 residential customers for every commercial
customer. This relationship was used for each year of the forecast for both
scenarios. Consumption per customer has decreased slightly in recent years,
primarily as a result of conservation efforts, and the 1981 average usage-per-
customer was estimated to be 20,097 kilowatt-hours which was then increased at
the rate of 2.0% a year to reflect both continued conservation and local eco-
nomic growth.
c. Tourism
The tourist industry in Skagway has increased over the last couple
of years following a stagnant 1978 season. Completion of the Klondike Highway
has contributed to this upswing as has the addition of Westours' passenger
ships between Juneau and Skagway. Ferry traffic, cruise ship traffic, the
Chilkoot Trail, and the Klondike Gold Rush National Historic Park have been
among Skagway's tourist attractions and are expected to continue experiencing
increasing visitor usage.
The White Pass and Yukon Route Railroad transported 43,000 passen-
gers, primarily tourists, in the year 1979; 67,000 in the year 1980; and the
1981 volume was about the same as the 1980 volume. As of mid-June 1982, tour-
ist activity was up somewhat from 1981 levels. With the ongoing renovation of
Skagway's historic district, addition of hotel units and continued levels of
ferry and cruise ship traffic, tourism is expected to be a strong part of the
City's economy in the future.
West ours , a tourist transportation and facilities management busi-
ness for Alaska, operates Skagway's largest hotel, the Klondike Inn, with 150
rooms. Sixty-six additional units are scheduled for completion in 1983, 30 of
which will have extra insulation and will be kept open year-round with oil-
based heating. The remainder will be seasonal units using electric baseboards
for space heating. In 1986, another 50 units are slated for completion, all
of which will be seasonal and will use electricity for space heating.
Westours is also planning to construct a 14,000-square-foot, one-quarter-mil-
lion-dollar historical museum in Skagway. Current plans are to complete the
air-conditioned, controlled-humidity structure within the next few years, but
the timing will depend upon the property acquisition. Westours' long-range
plans anticipate an 8% annual growth rate in their Skagway tourist activity.
d. Shopping/Residence Complex
Currently, there are plans to construct a small shopping complex
(40,000 square feet) in Skagway which includes a 12,000-square-foot grocery, a
..
III-9
covered mall with small shops, and either a motel or 12-unit townhouse living
quarters. Marketing studies have been conducted which show a need for retail
establishments to serve the resident population of Skagway rather than the
tourists. Plans are to begin construction within the next year.
For both the high and low growth scenarios, an additional
35,000 kilowatt-hours was added to the commercial load in 1983 for the new
grocery and 15,000 kilowatt-hours more in 1984 to include the remainder of the
complex. Electricity is not expected to be used for space heating, although
some waste heat from refrigeration will be used for space heat in the grocery
store.
e. Government Load
The base government load was projected to increase by 3.5% annually
for the duration of the forecast, with the number of customers kept constant
at 1 for both scenarios. Although it is expected over the years that more of
the government load will fall within the commercial sector as more buildings
acquired by the National Park Service for restoration are leased back to com-
mercial interests, for the purpose of this forecast these loads were kept in
the government class.
f. City Requirements
The City of Skagway has had studies conducted on the potential for
producing wind power and has recently installed a Jacobs 10-kW wind power gen-
erator at the sewage treatment plant. Estimated energy savings are between
20-50% of the current sewage treatment plant electricity needs. An agreement
was negotiated with the Alaska Power & Telephone Company (AP&T) which stipu-
lates that the City will be compensated for any power generated in excess of
. the treatment plant's needs which would be fed into the electric utility sys-
tem.
The City is also installing power factor controllers on its water
pumps which are expected to reduce average electricity consumption by between
5 and 10%.
Beginning in the year 1983 and for the duration of the forecast,
the sewage treatment plant electric requirements were reduced by 25% annually
to allow for the load offset by wind generation. The water pump electric re-
quirements were reduced by 8% to allow for energy needs offset by the power
factor controllers. For the year 1982, half of those combined savings were
calculated into the forecast.
g. National Park Service Historic District Restoration
The National Park Service has entered into a joint enterprise with
the City of Skagway and several private property owners to develop and manage
the Skagway Historic District. Currently, 15 buildings have been acquired by
the Park Service for restoration as part of this project. Some exterior work,
III-10
rewlrlng, and foundation reinforcement has occurred over the last four years
and the buildings are expected to be completed in stages over the next ten
years. Most of the buildings will be leased back to the private sector for
commercial development, while the others will be preserved as historical
interpretative structures or will be used by the Park Service as its Headquar-
ters and Visitor Center.
The Railroad Depot and Administration Building is expected to be
completely restored in 1983. It will contain Park Service offices and Visitor
Center acti vi ties. As the remaining buildings are restored, their electric
requirements will be included in the commercial class although for the purpose
of this forecast the loads were kept in the government class.
h. The White Pass and Yukon Corporation Limited Railroad
The continued operation of the historical White Pass and Yukon
Railroad has been in question over the past several years due to competition
presented by tour buses and trucks traveling the recently opened Klondike
International Highway between Skagway and White Horse, increasing costs re-
quired to run the railroad and the loss of certain ore cargo to other trans-
portation routes from the Yukon. However, recent statistics on railroad usage
show that the number of passengers has been on the increase indicating contin-
ued inte~est in riding the railroad despite the competition. Also, following
a study completed two years ago by the Canadian Transport Commission, the
Canadian Government has made funds available to assist the railroad in upgrad-
ing its equipment. Recently, the railroad renegotiated its contract with a
Yukon mining company, which, together with the government funding, has re-
sul ted in increased revenues for the railroad. Also, the competition from
trucking companies as an alternate to railroad transportation of ore is sea-
sonal because the highway is closed during the winter months, and the Canadian
Government has no plans to open the highway during the winter. Railroad man-
agement is now optimistic that railroad operations will continue to grow at a
moderate rate in the future. A possible exception to this trend would be if
the Canadian Trans-Alaska gas pipeline is constructed and Skagway is used as a
primary entry point for construction materials in which case more rapid growth
would be expected. The railroad is a likely mode for transporting these mate-
rials and an estimated 30-45 additional people would be required to operate
another shift daily from 11 pm to 7 am.
Scenario A excludes the potential increase in the railroad's elec-
tric load due to the pipeline construction. The railroad's purchases from
AP&T were held constant for the next two years, after which they were in-•
creased at the rate of 1.5% per year. This assumes continued growth in both
Yukon mining and tourist activity. The railroad is billed by the utility as
five separate customers which was kept constant for each year of the forecast
in Scenario A and was increased to seven in 1987 for Scenario B. The rail-
road's own annual generation is estimated at 1,518,270 kWh with a 347-kW peak
which was used for each year of the forecast under each scenario.
"
•
•
111-11
Scenario B includes an increase in the railroad electricity con-
sumption by an additional 20% for the years 1987 through 1989 due to pipeline
construction. After 1989 the annual growth rate is reduced to 3% annually ap-
plied to the pre-pipeline construction railroad requirements. It is still un-
known whether or not the Trans-Alaska gas pipeline will be constructed. If
the United States does not approve the Trans-Alaska pipeline project as it is
now proposed, the Canadian Government may build its own pipeline which would
be smaller in size but would still possibly rely on the White Pass and Yukon
Railroad for transportation during construction.
Although the future of the railroad appears reasonably secure at
this point, there is always the possibility that operation may cease or de-
crease at some point in the future. The overall effect on the community of a
complete shutdown of the railroad would be devastating. The railroad com-
prises about 35% of the community's electric requirements including the por-
tion met by its own generation and its purchases from AP&T. Because such a
large number of local residents are employed by the railroad, an estimated 50%
to 60% decrease in both the residential and commercial class requirements
could eventually be expected as well. The effects of this situation were not
evaluated in either growth scenario as such a closure now appears unlikely.
In the community of Skagway, recent changes have occurred which af-
fect local electric requirements since the time the load forecast for this re-
port was prepared in the Fall of 1981. The Canadian-owned Anvil Mine which
mines lead and zinc has temporarily ceased its ore shipments via the White
Pass and Yukon Railroad due to decreasing world prices of those ores. Other
mines are continuing to operate, but shipments are down sufficiently that
three of the six railroad crews have been temporarily laid off. Those who
have been affected by the layoffs have, thus far, remained in the community
but some will be expected to leave by Fall 1982 if rehiring does not occur by
then. In addition, construction of the Westours museum and the community
shopping complex have both been delayed due to the inability to obtain financ-
ing and because the developers are now waiting to see what happens with the
railroad •
The forecast has not been altered to reflect these latest economic
developments in Skagway, as it is too soon to know whether these are short-
term business fluctuations or longer-term trends.
i. Electric Utility Use
Based on historical figures utility use was assumed to be 4% of
sales for each year of the forecast for both growth scenarios.
j. System Losses
Based on historical system losses, the forecast includes a projec-
tion of losses at 10% of sales annually in both growth scenarios.
III-12
k. Peak Demand
For both Scenarios A and B, projections of peak demand were tied to
the energy forecast at an assumed constant load factor of 50%.
1. Monthly Distribution of Energy Use
The 1978 energy use by month in Skagway is shown in Table III-11.
In contrast to Haines, Skagway has relatively constant usage throughout the
year. This is primarily due to the large summer tourist trade.
4. IMPACT OF CONVERSIONS
This scenario evaluates the impact of residents and businesses
within Haines and Skagway responding to the long-term availability of rela-
tively low cost of electricity, assuming the State would set power costs of a
new hydroelectric facility enough below alternative energy costs to encourage
conversions of space heating and other major end uses to electricity. It is
not expected that Haines and Skagway would necessarily capture a larger share
of the total residential/commercial/industrial market of Southeast Alaska as
other nearby areas also have or will soon have similar hydropower bases. The
stable and relatively low rates would, however, provide the incentive for ex-
isting businesses and residences to gradually convert their heating and other
equipment to electricity. The rate at which conversions occur is never fast
in the absence of other major conservation incentives, even where the price of
electricity is a fraction of that of other fuels due to the high capital costs
of equipment replacement. On the other hand, for new residences and busi-
nesses this trend toward electric space heating and greater use of electricity
for commercial/industrial production occurs more suddenly. The following sce-
nario includes a possible response to the relatively low price of electricity,
and when compared to even the high growth scenario, the difference is dramatic.
The energy uses for Haines and Skagway projected under Scenario C
are shown in Tables 111-9 and 111-10, respectively.
a. Haines
Response to subsidized and stable electric rates among residential
customers was assumed to begin in 1983. A 1.5% annual conversion rate among
existing residences from other fuels to electricity for space heating and
other major uses was assumed for each year of the forecast. It was further
assumed that 50% of all new units built between 1981 and 1985 would be basi-
cally all-electric and that 100% of all residential units built after 1986
(the projected on-line date of a new hydroelectric facility) would be all-
electric. This analysis assumes that an average of 3 kWh per degree day are
required for each all-electric residential customer based on 8,308 degree days
for the Haines area.(4)
'.
'"
•
III-13
The commercial class of customers does not currently rely on elec-
tricity to meet most of its space heating needs. In this scenario the average
use per commercial customer was increased from 18,681 kWh in 1981 to
40,689 kWh in 2000 or by 25% annually between 1983 and 1990 and by 50% annu-
ally thereafter. This increase is based on the assumption that most new com-
mercial customers would utilize electricity for space heating including the
motel now under construction and that some existing commercial customers would
replace their oil or wood furnaces with electric heating.
Haines' three industrial customers used an estimated average of
281,000 kWh in 1981. The potential for conversion to greater use of electric-
ity is limited because of the high capital investment required to replace
equipment for large customers. The Scenario B requirements were increased by
15% annually between 1984 and 1991, after which they were increased by 25% to
reflect the all-electric requirements of the potential new industrial customer
included in the forecast.
The boat harbor and street light customer requirements are the same
as for Scenario B.
b. Skagway
Among residential customers, response to projected competitive and
stable electric rates was assumed to begin in 1983. Again, a 1.5% annual con-
version rate of existing residences from alternative fuels to electricity for
space heating and other major uses was assumed for each year of the forecast.
It was further assumed that 50% of all new units built between 1983 and 1985
would be basically all-electric and that 100% of all residential units built
after 1986 (the projected on-line date of a new hydroelectric facility) would
be all-electric. This analysis assumes that an average of 3 kWh per degree
day are required for each all-electric residential customer based on 8,231 de-
gree days for the Skagway area.(4)
The commercial sector, which currently uses relatively little elec-
tricity for space heating, has considerable potential for conversion to elec-
tricity. In 1981 the estimated average usage per commercial customer was
20,699 kWh which for this scenario was increased to 45,111 kWh by the year
2000 or by an additional 25% annually between 1984 and 1990 and by 50% for
each year beyond over Scenario B. This increase is based on the assumption
that most new commercial customers would rely on electricity for space heating
and that, over the years, some existing commercial customers would replace
their oil or wood furnaces with electric heating.
Within the government sector, where the 1981 consumption per custo-
mer was 93,114 kWh, a conversion rate similar to that assumed for the commer-
cial sector was used. The increases are lower than the commercial sector by
10% in each year beginning 1984 due to the small number of customers and the
major capital investments required by each customer to alter their already
large loads.
III-14
The railroad currently provides a sizeable portion of its power
needs with its own diesel generation and as a result, is probably less likely
to convert to electricity in the short term. A 10% increase in the railroad
load was added to Scenario B in each year beginning in 1984 to account for a
minimal amount of increased electricity usage due solely to availability of •
relatively low-cost power. It is possible that in the long run, the railroad
would consider extensive conversion to electricity including the loads now
served by its own diesel generation. The railroad did prepare a study of the
feasibility of converting its entire system, including the locomotives, to
electric power, but the results of the study are no longer available. The im-
pact of major conversion of railroad loads was not included in this scenario.
5. EXISTING GENERATING FACILITIES
a. Haines
Electric loads in Haines are presently met by diesel generators
owned and opera ted by HLP. HLP has seven uni ts with a total capacity of
4,320 kW. The largest unit is a Fairbanks-Morse 2, 070-kW machine which was
installed in 1973. Two other machines, an 800-kW Caterpiller and a 600-kW
Caterpiller were installed in the late 1960's. The other four machines which
range in size from 150 kW to 300 kW date from the 1940's or early 1950's. The
machines are in generally good operating condition and receive regular mainte-
nance.
As discussed above, starting in 1983, HLP will purchase most of its
electric energy requirements from the Schnabel Lumber Company. Schnabel will
generate the required electricity with a 4, OOO-kW wood waste generator which
is now under construction.
b. Skagway
Electric loads in Skagway are presently met by a combination of
hydroelectric turbine-generators and diesel generators owned and operated by
AP&T. There are three Pelton turbines with capacities of 100 kW, 410 kW and
270 kW installed in the AP&T power plant. The 270-kW unit was installed new
in 1981. The 100-kW and 410-kW units were reconditioned in 1981. In addi-
tion, AP&T has five diesel units which supplement the hydropower. There are ,
two 1,250-kW Fairbanks-Morse units which were installed in the late 1970's.
The other three units are older and smaller ranging in size from 250 kW to
300 kW. The total installed capacity of the system is 4,130 kW.
.,
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
HISTORICAL ENERGY USE -HAINES LIGHT AND POWER
~ ....!ill. 1973 ..J.lli... --.!2l.L ....!ill....
Averaae Number of Customers
Resideottal l .J.4~ •••••••••••.•• 404 407 386 437 4S4 410
Co_erclal (l) ..•.•.•......... 146 148 140 lS9 16S 149
Industrlal .....•............. 4 6 6 6 6 3
Street Ughtlna ••.•........... 1 1 1 1 1 1
Boat Harbor •..................
Total ••.................. -m --s62 533 ~ --rn; -s63
Total Enerll Use ~HWh2
Ileaidentlal ••.•............... 2,214 2,S14 2,193 2,863 3,224 2,912
eo..erclal •••••••••••••••••••• I, S70 l,S66 1,348 2,368 2,702 2,890
IDdUlltrtal •....•...•.......... 2,4S6 2,97S 4,322 S,877 S,297 l,S84
Street Llabt1aa ••••••••••••••• 14 16 94 l1S 110 129
Boat Harbor ..••.•...•.........
Total ...••.............. 6,254 7,071 7,9S7 11,223 11,333 7,SlS
Syatea Loaaea (HWb) ....•.......... ~ ~ S99 844 -2ll -ill
Total IaquireaenU (HWh) . 6,725 7,604 8,S56 12,067 12,186 8,081
Annual Peak Iaand (kW)(2) ........ l,8S0 1,950 1,950 l,9S0 1,950 1,300
0) eo..erclal cuatoaera 1971-1977 satlasted pro rata ratl0 of
1978 actual c~rclal cuatoaera to realdentlal cuatoasra.
(2) !taU_ted.
(3) All flaursa annuallzed baaed on 6 .ontha of data.
1977 1978 2ill....
42S 408 419
154 148 14S
2 2 2
1 1 1
26 29
----s82 --m ---m;
2,S9S 2,S8S 2,S87
2,778 2,96S 2,691
1,038 SS8 812
168 164 166
146 36
6,S79 6,418 6,292
~ --ill -..ill
7,074 6,891 6,732
1,300 1,300 1,296
-illQ...
~3S.
138
3
1
31 ---c;oa
2,4S4
2,S84
1,318
170
20
6,S46
--ill.
7,314
..
1981P2
432
144
3
1
32
"-"6i2
2,3S8
2,691
861
ISS
14
6,079
1-3
~ r-
CD
H
H
H
I ......
1980 1981
..
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
POPULATION PROJECTIONS -HAINES
1982 1983 1984 1985
Low Growth Projection
Base Population (1) 1,433 1,447 1,462 1,476 1,491 1,506 ................
Direct Employment change · .......... 15(5) 15 15 15
Indirect Eaployaent Change (2) ••••• 15 15 15 15
Adjusted Population (3) ----s4 ----s4 ----s4 ----s4
Total Projected Population •••• 1,433 1,447 1,516 1,530 1,545 1,560
Hi~h Growth Projection
Bale Population (4) •............... 1,433 1,469 1,506 1.543 1,582 1.621
Direct Eaployment Change · .......... 15(5) 25(6) 35(6) 45(6)
lDdirect Eaployaent Change ••••••••• 15 25 35 45
Adjusted Population ••••••••••• ---sz; ----go 1"26 -m
Total Projected Population •••• 1,433 1,469 1,560 1,633 1,708 1,783
1993 1994 1995 1996 1997 1998
Low Growth Projection
B.a.le Population •••••••••••••••••••• 1,631 1,664 1,681 1,697 1,714 1,731
Direct Faployaent Quange · .......... 15 15 15 15 15 15
lDdirect Employaent Change ••••••••• 15 15 15 15 15 15
Adjusted Population ••••••••••• ----s4 ---s4 ----s4 ----s4 ---s4 ----s4
Total Projected Population •••• 1,685 1,718 1,735 1,751 1,768 1,785
Hi~h Growth Projection
Rase Population •••••••••••••••••••• 1,975 2,025 2,075 2,127 2,180 2,235
Direct Faplo,.ent Quange · .......... 88 88 88 88 88 88
lDdirect Eaployaent Change ••••••••• 88 88 88 88 88 88
Adjusted Population ••••••••••• ----n6 ---m----m-----n6 ----n6 ---m-
Total Projected Population •••• 2,291 2,341 2,391 "2,"4"4'3 2,496 2,551
CI) Beglnl with 1980 Cenaus figurel and ia increaaed by 1% annuslly.
(2) Ass~ oue indirect employee per direct employee.
(3) ABlume 1.8 relidentl per employee.
(4) Begina witb 1980 Cenaus figurel and 11 increaaed by 2.5% annually.
(5) 15 new conltruction workerl at Schnabel Luaber.
(6) 10 new tourilt industry jobl.
(7) 40 new workerl for Tranl-Alaksa pipeline tranaportation.
(8) 20 new workerl for Trani-Alaska pipeline tranaportation.
(9) 30 new workerl at barite aining operation.
(10) 10 new workerl at barite aining operation.
It
1986 1987 1988 ~ 1990 1991 1992
1,521 1,536 1,552 1,567 1,583 1,599 1,615
15 15 15 15 15 15 15
15 15 15 15 15 15 15
----s4 ----s4 ----s4 ----s4 ---s4 ----s4 ----s4
1.575 1,590 1,606 1,621 1,637 1,653 1,669
1,662 1,703 1,746 1,790 1,834 1,880 1,927
85(7) 105(8) 135(9) 145(10) 88 88 88
85 105 135 145 88 88 88
--r1i6 "378 ~ -su ----n6 ----m ----m
1,968 2,081 2,232 2,312 2.150 2,196 2,243
1999 2000
1,749 1,766
15 15
15 15
---s4 ---s4
1,803 1,820
2,291 2,348
88 88
88 88 ---m----m-
2,607 2,664
H
III
c"
I-'
(l)
H
H
H
I
N
HA INES-SKAGI/AY REGION
FEASIBILITY STUDY
PIlOJECTION or COIMUNITY ENEIGY USE FOIl HAINES -SCENAIlIO A
...illL ~ --'..lli.... ..llli... ...!.lli.... ...illL ...ill!... ~ ~ ...ill.!.... ....!!!L
llaiD" UBht aDd Pover
Cueto_ca
lIe.tdeDUal ............... 453 457 461 466 470 475 479 484 489 493 498
C<.oerc1.1 ............... 151 152 154 155 157 158 160 161 163 164 166
lDduatrial ............... 3 2 2 2 2 2 2 2 2 2 2
Str.et Ullhta ............. 1 1 1 1 1 I 1 I 1 1 1
Io.t llarbor ............... 32 33 33 34 34 35 35 36 36 37 37
Tot.l ............... ---ml ----m-~ ----rn --""664 ---m ---m ----wi ----m ---rn ----ro4
EnUIl u.e \HWhl
•• ddeDtia •••••• e •••••••• 2.472 2.494 2.516 2.582 2.643 2.711 2.775 2,846 2,918 2.987 3.062
C<.ouc1.1 ............... 2.852 2.929 3,028 3.109 3.213 3.299 3.409 3.499 3.615 3,710 3.831
lDduatrial ............... 880 787 791 795 798 802 806 810 814 818 822
Strut Ullht. ............. 157 158 160 161 163 165 166 168 170 171 173
Io.t \\arbor ............... 14 15 15 __ 1_5 15 16 16 16 16 17 17
Total ............... 6.375 6.383 6.510 6.662 6.832 6.993 7.172 7,339 7.533 "'T,"7"O) 7.905
HLP Sy.t_ w .... I,. ••••••••••••••• 638 638 651 666 683 699 717 734 753 770 791
5chD.bel Luaber Coapuy (Con> GaIV (*) 0 ...l.ill. ..2...QE. ..2...QE. ..2...QE. ..2...QE. 7 037 ..2...QE. ..2...QE. ..2...QE. ..2...QE. ..2...QE.
Total C<.o..,1ty IIaqu1r_nt. . ...... 10.676 14,058 14.198 14.365 14.552 14:729 14.926 15,110 15.323 15.510 15,733
HLP Peak Dea.alld (I<W) ............... 1,334 1.336 1.362 1.394 1.430 1.463 1.501 1.535 1.576 1.612 1,654
,..1< Daa&Dd of Sch ... bal (*) 0 000 .. 0 0 0 ...!.a..!.Ql ....hill. ..1.....!!l ....hill. ..1.....!!l ..1.....!!l ....hill. ....hill. ...!.t..!..!! +.ill ~:m Total C<.oun1ty Peak ilia_lid 0 0 0 000000 2.441 3.459 3.485 3,517 3.553 3,586 3,624 3.659 3.699 , 35
...illL ~ ...!m.... ...illL .....!lli... ~ ...!22!... ~
llaiDu Ulht .Dd Powr
Cueto_r,
••• lde"tial ............... 503 513 518 523 528 533 538 543
C<.oerc1.1 ." ............ 168 171 173 174 176 178 179 181
lDd uat rial ............... 2 2 2 2 2 2 2 2
Street Ullht. ........ , .... 1 1 1 1 1 1 1 1
Io.t IIarbor ............... 38 38 39 39 40 40 41 41
Total ••••••••••••• to. --m -rn -----m---rn ---m ~ ----nT ----m
Enerll Uae (HWh)
.uLleDtial .1 ..........••• 3.139 3,249 3.281 3.313 3.344 3.376 3.408 3,439
C<.oerc1.1 ............... 3.956 4.108 4.240 4.350 4.489 4.632 4,752 4,902
lDduatrl.1 ............... 826 830 834 838 842 846 851 855
Street UShti ............. 175 176 178 180 182 184 485 187
Io.t IIarbor ............... 18 18 18 18 19 19 20 20
Total ............... """'8,Ti4 8.381 8.551 8.699 8,876 9,057 9.516 9.403
IILP Sylt_ w .... . ................ 811 838 855 870 888 906 952 940
Schn.bel Luabar CoapaDy (OInl Ga~ (*) 0 ..2...QE. ..2...QE. ..2...QE. ..l.J..Qll. ..2...QE. ~ 7 037 ~ Total ec-.unlt,. laquir.antl •••••••• 15.962 16.256 16.443 16.606 16.801 1 .000 11: 505 1 ,380
H
ID..P Pe.1< Daaand (I<W) ............... 1.698 1.754 1.790 1.821 1,858 1.895 1.992 1.968 III
,..1< Daa&Dd of Sch ... bel (0) 000 .. 0 0 0 0 ...!.t..!..!! ..1.....!!l ...!.t..!..!! -+ffi ...!.t..!..!! +.lli +.ffi --HM CT'
I-' Total C<.ounlty Peak 1lIa.1Id 0 0 0" 0 0 00 3.821 3.877 3.913 3.9 3.981 .018 .115 .091 (tl
(ij -Source, Stud Electrical Po ... r fro. Wood H
H
H
I
LV
• w-
HAINES-SKAGWAY REGION
FEAS IB ILITY STUDY
PROJECTION OF COHHUNITY ENERGY USE FOR HA INES -SCENARIO B
-.illL ---.!.ill.... ~ ~ -.llli.... ~ ~ ...!.2!L ~ ....!!2.!.... ...!22L
Hainee L1iht and power
Cuetomere
Re8idential ............... 459 480 497 524 579 612 656 680 632 646 660
Commercial ............... 153 160 166 175 193 204 219 227 211 215 220
Industrial ............... 3 2 2 2 2 2 2 2 2 3 3
Street Light8 ............. 1 1 1 1 1 1 1 1 1 1 1
Bo8t Harbor ............... 32 33 33 34 34 35 35 36 36 37 37
Tot8l ............... ----p;s ------m------c;99 ----r36 -----so9 --w; -----g[l -----w; ----asz ----"'902 -----ru-
Sale8 (KWh)
Reaidential ............... 2,505 2,620 2,713 2,903 3,256 3,493 3,800 3,998 3,772 3,913 4,058
Coadaercial ............... 2,871 2,968 3,048 3,109 3,213 3,299 3,409 3,499 4,687 4,872 5,086
Industrial ............... 880 787 791 794 798 802 806 810 814 1,118 1,125
Street Light8 ............. 157 158 160 161 163 165 166 168 170 171 173
Boat Harbor ............... 14 15 15 15 15 16 16 16 16 17 17
Total ............... 6,427 6,548 6,727 6,982 7,445 7,775 8,197 8,491 9,459 10,091 10,459
HLP SY8tem Losses .................. 643 655 673 698 745 778 820 849 946 1,009 1,046
Schnabel Lwaber Coapaoy (Ow Getj (*). 3,663 ~ ~ ~ 7,037 7,037 7,037 7,037 ~ ~ 7,037
Total c.-uolty Require •• nta,. •••••• ,. 10,733 14,240 14,437 14,717 15,227 15,590 16,054 16,377 17,442 18,137 18,542
HLP Pealr. Demaad (lr.W) ............... 1,345 1,370 1,408 1,461 1,558 1,627 1,716 1,777 1,980 2,112 2,188
Peak De.and of Schnabel (*) ......... --.!.t.!.Q2 ~ ~ ~ ~ ~ 2,123 2,123 ~ ~ ~
Total Peak _ad ................... 2,452 3,493 3,531 3,584 3,681 3,750 3,839 3,900 4,103 4,235 4,311
--.!lli.... ~ ~ 1996 --.illL ~ ...!!2L 2000
Hainea Ulht and Pover
Customers
Re8idential ............... 674 689 703 719 734 750 767 784
c.-erc1al ............... 225 230 234 240 245 250 256 261
Industrial ............... 3 3 3 3 3 3 3 3
Street Light8 ............. 1 1 1 1 1 I I I
Boat Harbor ............... 38 38 39 39 40 40 41 41
Total .,.,. ... ,. ... ,.,. ... -----m------gc;r ~ 1,002 1,023 1,044 1,068 1,090
Sale8 (MWh)
Reaideot18l ............... 4,206 4,364 4,453 4,554 4,649 4,751 4,858 4,966
Coadaerc1al ............... 5,307 5,534 5,744 6,010 6,260 6,516 6,807 7,080
Industrial ............... 1,132 1,139 1,146 1,153 1,161 1,168 1,176 1,183
Street Lighta ............. 175 176 178 180 182 184 185 187
Boat Harbor ............... 18 18 18 18 19 19 20 20
Total ............... 10,838 11,231 11,539 11,915 12,271 12,638 13,046 13,436
HLP Sy8te. Loa8ea .................. 1,084 1,123 1,154 1,192 1,227 1,264 1,305 1,344
Schnabel Lwaber Coapany (0In> Ge~ (*). ~ ~ ~ ~ ~ ~ 7,037 ~
Total Coadaunity Requirements ........ 18,959 19,391 19,730 20,144 20,535 20,939 21,388 21,817
HLP Peak Demand (lr.W) ............... 2,268 2,350 2,415 2,494 2,568 2,645 2,730 2,812 1-3
III Peak ~and of Schnabel (*) ......... ....h.!Q ~ ~ ~ ~ ~ ~ ~ 0"
Total Coadaunlty Peak ~aad ......... 4,391 4,473 4,538 4,617 4,691 4,768 4,853 4,935 to-' ro (i) _ Source: 1979 DEatinll of the Fea8ibUitl Studl and ReErt on Generation of Electric Power
Frolll Wood bfuae, MJr'Weat Pacific Corporation. H
H
H
I
~
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
HISTORICAL ENERGY USE -
ALASKA POWER AND TELEPHONE COMPANY,
1973 1974 1975 1976
Average Number of Cuatomers ....... 317 347 359 369
Average Use Per Customer (KWh) 11.0 10.0 l2.0 l2.5
Energy Salea (KWh) ................ 3,492 3,454 4,313 4.601
Systea Losses (KWh) ............... 200 ~ ---lli
Total Requirements (KWh) • 3.692 4.034 5,262
Annual Peak Demand (kW) ........... 900 900 1.100
Systea Load Factor (X) ........... 46.8 51.2 54.6
(*) Annualized based on 6 months of data.
SKAGWAY
1977 1978 1979
413 422 378
12.2 l2.5 13.9
5.057 5,254 5.241
---..l!QQ --ill 728
5,857 5,986 5.969
1,300 1,400
51.4 48.8
1980
399
l2.7
5.061
--lli
5.677
...J..2!!.(*)
399
12.3
4.917
---.i!1
5.330
1.296
t-3
~
I-'
CD
H
H
H
I
V1
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
POPULATION PROJECTIONS -SKAGWAY
1981 1982 1983 1984 1985
Low Growth Projection
Base Population (1) , ••••••••••••••• 768(4) 768 768 776 783
Direct Employment Change .......... 0 0
Indirect Employment Change (2) .... 0 0
Adjusted Population (3) ...... --0 --0
Total Projected Population ••• ----m ----m ----m 776 --"Ta3
HiSh Growth Projection
Base Population .•................. 768 783 799 815 831
Direct Employment Change .......... 0 0 0 0 0
Indirect Employment Change ........ 0 0 0 0 0
Adjusted Population .......... --0 --0 --0 --0 --0
Projected Population ......... ----m ----r83 ~ ----ars ----a3T
1994 1995 1996 1997 1998
Low Growth Projection
Base Population ••••••••••••••••••• 857 866 874 883 892
Direct Employment Change .......... 0 0 0 0 0
Indirect Employment Change ........ 0 0 0 0 0
Adjusted Population .......... --0 --0 --0 --0 --0
Total Population •............ ---asr ----a66 ----a74 ----a83 ----a92
HiSh Growth Projection
Base Population ................... 1,023 1,054 1,085 1,118 1,152
Direct Employment Change .......... 11 11 11 11 11
Indirect Employment Change .•...... 4 4 4 4 4
Adjusted Population .•........ ---u --'45 -n --'45 --'45
Total Population ............. 1,068 1,099 1,130 1,163 1,197
(1) Begins with 1980 Census figure which is increased by 1% annuslly after 1983
for low scenario; 2% between 1981 and 1990 and 3% beyond for the high scenario.
(2) Assume .4 indirect employee for every direct employee.
(3) Assume 3.0 residents per employee.
(4) Begins with 1980 Census figure.
(5) Thirty new workers for Trans-Aiaska pipeline transportation.
(6) Fifteen DeW worker. for Trans-Aiaska pipeline transportation.
1986
791
0
0 --0
----m
848
30(5)
12 ---m
~
1999
901
0
0 --0
----gar
1,186
11
4
--'45
1,231
1987 1988 1989
799 807 815
0 0 0
0 0 0 --0 --0 --0
----r99 ----ao7 ---sIS
865 882 900
45(6) 45 45
18 18 18
---rB'9 ---rB'9 ---rB'9
1,054 1,071 1,089
2000
910
0
0 --0
----no
1,222
11
4 -n
1,267
• ~
1990 1991
823 832
0 ·0
0 0 --0 --0
----an -m
918 936
11 11
4 4
--'45 --'45
~ -gar
•
1992
840
0
0 --0
----a4O
964
11
4 ----u
1,009
1993
849
0
0 --0
----a49
993
11
4 ----u
1,038
t-3
III
C"
I--'
!l>
H
H
H
I
0\
.. •
It.UNES-SKAGWAY REGION
FEASIBILITY STUDY
PROJECTION OF CO~UNITY ENERGY USE FOR SKAGWAY -SCEIWlIO A
...llli ..l2!! ---'..2!! ~ ~ ~ ~ ~ ....!!!.2. ...!!!!. ~
Ai •• 1La POwer' Teleehone
euatoaera
iea(deotia1 .............................. 305 307 308 311 314 317 320 323 327 330 333
ec-ercial •••• I ••••••••••••••• 82 83 83 84 85 86 86 87 88 89 90
Gover_ent .................... 7 7 7 7 7 7 7 7 7 7 7
Railroad ...................... 5 5 5 5 5 5 5 5 5 5 5
Total ......................................... ----m ----.02 ~ ---w----m----rr5 ----.ui" ----rn ---m ----m ~
Sal .. (HIIh)
ieaideotia1 ....................................... 1,708 1,714 1,708 1,768 1,811 1,856 1,902 1,949 2,002 2,051 2,101
eo..erc1.1 .................... 1,731 1,823 1,874 1,932 1,992 2,055 2,095 2,190 2,227 2,295 2,367
GoYefount ........................................ 649 663 676 690 704 719 734 749 764 780 796
Railroad ...................... 835 835 848 860 873 886 900 913 927 941 955
Total ...................................... 4,923 5,035 5,106 5,250 5,380 5,516 5,631 5,801 5,920 6,067 6,21.9
APT OW Uae ............................. 197 201 204 210 215 221 225 232 237 243 249
APT 51at .. Lo .. U ....................... 492 504 511 525 538 552 563 580 592 607 622
White Pe .. , Yuk.oo Ii (Ow Geo.) (.) ...... ~ ~ ~ hl.!.! hl.!.! hl.!.! .!2!! hl.!.! .!2!! hl.!.! .!2!!
Total c:o..unity iequ.1r_oU .. , 7,Il1 7,259 7,340 7,504 7,652 7,808 7,938 8,132 8,268 8,436 8,609
APT Pea It Doaand (ltV) ...................... 1,281 1,311 1,329 1,366 1,400 1,436 1,466 1,510 1,541 1,579 1,619
Whiu Pe .. , Yuk.oD Ii Pealt Doaoad (.) .... 347 347 347 347 347 347 347 347 347 347 347
Total Ra t 1Aa t ed eo..UIlit y Peak Dea&Dd ..... 1,628 1,658 1,676 1,713 1,747 1,783 1,813 1,857 1,8811 1,926 1,966
-11.21 ~ ~ ~ ~ ~ ....!2!! ..1..QQQ
Ai .. u powr , Ta102hoDa
eultoMrl
R .. ldeoUol ....................... '" .............. 337 340 344 347 350 354 358 361
ec-.ercl.1 .................... 91 92 93 94 95 96 97 98
Governaeat .................... 7 7 7 7 7 7 7 7
Railroad ............ , ......... 5 5 5 5 5 5 5 5
Total .......... t,··.······ -m --m -m ---m-----m-462 46i ---m
Sol .. ~HIIh)
i .. ldeatiol .................... 2,158 2,210 2,236 2,255 2,275 2,301 2,327 2,346
ec-ercial • I •••••••••• t ....... 2,439 2,514 2,590 2,669 2,750 2,832 2,917 3,006
GovernaeDt •••••••••• t •••••• ••• 812 829 846 863 881 899 917 936
Railroad ........ , ............. 969 984 998 ~ 1,029 1,044 1,060 1,075
Total •••••• t •••••••••••••• 6,378 6,537 6,670 6,800 6,935 7,076 7,221 7,363
APT OW Uoe ................................ 255 261 267 272 277 283 289 295
APT SYST!II Lo .. eo ........................ 638 654 667 680 694 708 722 736
White Pa .. , Yukoo Ii (Ow (loD.) (.) ...... -t.Wo hl.!.! NH t.ffi .!2!! hl.!.! H* Total c:o..UDity "quir.eau ... 8, 90 8,971 9,12 ,271 9,425 9,586 9, 51 9,913
APT Pealt Do.-nd (ltV) ...................... 1,660 1,702 1,736 1,770 1,805 1,842 1,879 1,916
Whi U Pe.. , Yukoa Ii Pealt Do_ad (0) .... 347 147 347 347 347 347 347 347
Total bti.-ted c:o..unity Pealt llIaa"" ..... 2,007 2,049 2,083 2,TT7" 2,152 2,189 2,226 2,263
H
Cil -btl.-ted I\)
0-
I-'
CD
H
H
H
I
""-J
~-• I' ..
HAINES-SKAGWAY IlEGION
FEASlS lLITY STUDY
PiOJECT ION OF COHHUIH TY ENERGY USE FOR SKAGWAY -SCEIWlIO B
....!.ill.... ....!1!L ~ ~ ~ 1987 ~ ~ ~ ....!!!L ~
AI .. ka Po_r , Tel.~hon.
CUlto.erl
i .. 1d.ntial ..................... 310 317 323 330 387 418 425 432 382 389 400
c.-rcial ..................... 84 86 87 89 106 115 117 118 103 105 lOB
GovernaeDt ..................... 7 7 7 7 7 7 7 7 7 7 7
11&11 ro.d ....................... 5 5 5 5 5 7 7 7 7 7 7
Tot.l ...................... --.06 --.-rr -----.-n --m ----m-~ --m ----m --m-----soa --m
Sale. (KWh)
ieddent1al ..................... 1,736 1,775 1,809 1,876 2,233 2,448 2,526 2,606 2,339 2,418 2,524
ec-.erc1al ..................... 1,773 1,887 1,961 2,044 2,472 2,731 2,832 2,912 2,598 2,573 2,830
Goveruent ..................... 659 683 707 733 759 786 815 844 874 905 938
11&11 road ........................ 835 835 848 860 872 ~ ~ ~ 899 925 953
Total ...................... 5,003 5,180 5,325 5,513 6,336 7,013 7,236 7,441 6,710 6,821 7,245
APT Own u. • ............................. 200 207 213 221 253 281 289 298 268 273 290
APT Sy.t .. Lo .... ........................ 500 518 533 551 634 705 724 744 671 682 725
Whit. Pa.. , Yukon RI (Own Cen.) (.) ...... +.ill +.m +.Wo -t.¥oi +.ill ~ +.ill ~ ~ +.ill ~
Total eo..unity .. qu1re .. nt. .... , 2 , 2 ,590 ,80 , 2 9,518 , 68 10,002 9,168 9,2 5 9,779
APT p .. k llIuad (kW) ...................... 1,302 1,348 1,386 1,435 1,649 1,826 1,883 1,937 1,746 1,775 1,886
Wb1 te P... , Yukon RI PI.k llIa&ad (.) .... 347 347 347 347 347 347 347 347 347 347 347
Total IItiut..:l c.-unity Plak _ad ..... 1,649 1,695 1,733 1,782 1,996 2,173 2,230 2,284 2,093 2,122 2,233
....ill!.. ~ ~ ~ ~ ~ ~ 2000
Al •• k.a Power' Teleehone
eulto.erl
i .. idenUoi ..................... 411 424 36 448 462 475 488 503
ec-.erc1.1 ..................... 115 118 121 125 128 132 136 140
GoverlWient ..................... 7 7 7 7 7 7 7 7
11111 rood ....................... 7 7 7 7 7 7 7 7
Tot.l ...................... ----y;o --m ----sIT ----m ----ro4 ~ -rn -----m
Sal •• (1Nh)
ie.id.nt1ol ..................... 2,632 2,756 2,834 2,912 3,003 3,087 3,172 3,269
c.-erciol ..................... 3,069 3,210 3,355 3,533 3,688 3,875 4,070 4,272
GovernaeDt ..................... 971 1,006 1,042 1,079 1,117 1,157 1,197 1,241
11&11 road ....................... 981 +.m +.m ~ f.ffi ~ -HIt ~ Tot.l ...................... ....,-;m ,98 , 2 ,5 , I 9,25 ,611 9,9 9
APT Own u. • ............................. 306 319 331 344 357 370 384 400
Sy.t .. Lo •••• ............................ 765 798 827 860 891 926 961 999
Whit. Pa .. , Yukon RI (Own Cen.) (.) ...... I 519 ~ I 519 I 519 ~ I 519 #.ill ~ Total c.-unity IIaqulr_ent ••••• 10:243 10,619 10: 949 ff.ili 11,680 12: 072 12, 5 12, 7
APT PI.k De •• nd (kW) •••••••••••••••••••••• 1,992 2,078 2,153 2,237 2,320 2,409 2,501 2,600
lIhit. P... , TuIr.on RI Plak Deu.ad (.) .... 347 347 347 347 347 347 347 347
Totll !lt1ut..:l c.-unity Plak _ad ••••• 2,339 "'"'2,""4"25 --r;5OO """'2,'584 ""T,'66f "'T,'156 """'2,84ii "'T,'94'1
1-3
III (il -Ldut.d. 0'
I-'
(l)
H
H
H
I
ex>
it .. • • • , •
IlAINES-SKAGWAY REGION
FEASIB ILllY STUDY
PIlOJECTION OF COHHUNlTY ENERGY USE FOIl IlAlNES -SCENAilO C
...illL ...ill!.. .....ill!... ...ill.L ....!lli.... ...ill!..... ~ ~ ~ ~ ...ill.L
lIaiau U~ht aad Power
CUlto.erl
J.olideatial .............. 459 480 497 524 579 612 656 680 632 646 660
c.-.. cial .............. 153 160 166 175 193 204 219 227 211 215 220
Induotriel .............. 3 2 2 2 2 2 2 2 2 3 3
Street Uahta ............ 1 1 1 1 1 1 1 1 1 1 1
laat Harbor .............. 32 33 33 34 34 35 35 36 36 37 37
Toul .............. -m ----m---m---m -----ao9 --m-----gj'J -w; -m ----g(j2 --m
Salea (HWh)
J.oaldaatial .............. 2,894 3,359 3,764 4,376 5,244 6,833 7,645 8,492 7,150 7,489 7,911
c.-arcial .............. 2,871 3,710 3,810 3,886 4,016 4,124 4,261 4,374 5,859 7,308 7,629
lDd ... trial .............. 880 787 925 928 933 937 942 947 951 1,423 1,431
8tr .. t Uahu ............ 157 158 160 161 163 165 166 168 170 171 173
laat Harbor .............. 14 15 15 15 15 16 16 16 16 17 17
Total .......... , ... 6,816 8,029 ""'8';674 9,366 10,371 12,075 13,030 13,997 14,146 16,408 Tf;"i6i
HLP Syat. Lo •••• . ................ 682 803 867 937 1,037 1,208 1,303 1,400 1,415 1,641 1,716
8cbuhel Luaber !ll.peoy ~ c.u,) (.) ~ 7 037 ~ ~ ~ ~ ~ ~ ~ ~ ~
Total c.-... ity laq"ir_ata .. 11,161 15:869 16,578 17,340 18,445 20,320 21,370 22,434 22,598 25,086 25,914
HLP p.,ak Deaaad (ltW) .............. 1,427 1,680 1,815 1,960 2,170 2,527 2,727 2,929 2,961 3,434 3,592
PoIalt o..ud of Schubel (.) ....... +.ill ..1..t..!l! ..1..t..!l! ..1..t..!l! ....!.J..!Q ~ ....!.J..!Q ..1..t..!l! ..1..t..!l! ~ ..1..t..!l!
Total p.,ak .... ad .................. 2, 52 3,803 3,938 4,083 4,293 ,650 4,850 5,052 5,084 5,55 5,715
...ill.L ...!ill.... ...!ill.... 1996 ...lliL ...ill!... ~ 2000
Baia .. Ulht aad Power
CU:.to.ere
J.oaldeatial .............. 674 689 703 719 734 750 767 784
c.-.. cial .............. 225 230 234 240 245 250 256 261
lDduotriel .............. 3 3 3 3 3 3 3 3
Street Uahta ............ 1 1 1 1 1 1 1 1
laat Harbor .............. 38 38 39 39 40 40 41 41
Total •••••••••••• II ----m ~ --gso 1,002 1,023 1,044 1,068 """'i";09O
!!Dern Oaa ~_)
lIealde.UaI .............. 8,336 8,787 9,161 9,579 9,985 10,408 10,858 11,307
c.-.. cial .............. 7,961 8,301 8,616 9,015 9,390 9,774 10,211 10,620
lDd ... trial .............. 1,440 1,449 1,458 1,466 1,476 1,485 1,495 1,504
Straet Uahta ............ 175 176 178 180 182 184 185 187
laat Harbor .............. 18 18 18 18 19 19 20 20
Total .............. 17,930 18,731 19,431 20,258 21,052 21,870 22,769 23,638
HLP Syat. Lo •••• ................. 1,793 1,873 1,943 2,026 2,105 2,187 2,277 2,364
Sclmabel Luaber Co. ~ c.a)(.) .... ~ ~ ~ ~ ~ ~ ~ ~ Total c.-lIDi ty lIeqllir.aata .. 26,760 27,641 28,411 29,321 30,194 31,094 32,083 33,039
HLP PoIalt Daaud (ltW) .............. 3,752 3,920 4,067 4,240 4,406 4,577 4,765 4,947
PoIalt Daoaad of Schubel (.) ........ ..1..t..!l! --bill ..1..t..!l! ..1..t..!l! ...h.ill -HM ....!.J..!Q -¥o¥a 1-3
III Total Polak Daaaod .................. 5,875 6,0 3 6,190 6,363 6,529 6, 00 6,888 ,a a 0-
(,) -SO"rcel ......
1979 00 Geoeration of Electrical Power CD
Pro.
H
H
H ,
~
• • ,. • ,
lIAINES-SKAGWAY UGIOM
FUSIBILITY STIIDY
PiOJECTIOM ~ COIIIIUlHTY EMEIlGY USE I'Oi. SKAGWAY -SCEIIAIlIO C
--.!2ll.. ~ ~ ~ ...!.ill.... ....!2!L ~ ~ ~ ....ill!.. ...illL
Al .. k.a Po .... r • TeleEhone
CuAto.era
iee1dential ....................... 310 317 323 330 393 425 432 439 382 389 400
eo...rc1e! .............. 84 86 87 89 106 115 117 118 103 105 108
Q)vernaeot .............. 7 7 7 7 7 7 7 7 7 7 7
iellroad ................ 5 5 5 5 5 7 7 7 7 7 7
Tote! .............................. """406 -----m --u2 -rn ---m -----rn--s6J ~ ---:m -soB --m
Sel .. ~HIIh)
iee1denUe! .............. 1,870 2,081 2,267 2,485 3,861 4,767 5,079 5,389 4,291 4,600 5,008
eo...rcial .............. 1,713 1,887 2,451 2,555 3,090 3,414 3,415 3,390 3,248 3,860 4,245
Q)vetlli.-eot .............. 659 683 813 843 873 904 937 971 1,224 1,267 1,313
iellroad ................. 835 835 933 946 959 ~ ~ ....!.t..!!!. 989 1 018 ~
Total .............................. ""'T,T3f 5,486 """"6";4'64 6,829 8,783 10,238 10,600 10,937 9,752 10: 745 11,614
UT llIe ........................... 205 219 259 273 351 410 424 437 390 430 465
APT Syet. Lo .... ................. 513 549 646 683 878 1,024 1,060 1,094 975 1,075 1,161
lihUe P .... Yukon U (Own Oen) (0) .....!.....ill .....!.....ill .....!.....ill .....!.....ill .....!.....ill -..l.t1!! -..l.t1!! -..l.t1!! ~ ~ -..l.t1!!
'lbtal c.-W1it1 iequ.1r.enu .. 7,374 7,773 8,888 9,304 11,531 13,191 13,603 13,987 12,636 13,769 14,7~9
UT .... 1. Dot-.nd (iLW) .............. 1,337 1.428 1.682 1,777 2,286 2,665 2,759 2,847 2,538 2,797 l,023
lIhite PI ... Yukon U Pe.k Doaand (0) 347 347 347 347 347 347 347 347 347 347 347
'lbtal In1ae ted c.-1lAl. t1 Peak o-and ""T;"6M -r;m 2,029 ""T,T24 """'2;'m J;'O'i2 3,TIi6 3,'i94 2,885 -r.m ""T,l7O
~ ...!ill... ~ ~ ....!2!L.. .....!.ill.. ~ ...1.QQQ...
Al •• k.a Power" ,..laehone
Cu.toaera
ielldenU.1 ......................... 424 436 448 462 475 488 503 517
c.-erc1al IO .......................... 115 118 121 125 128 132 136 140
Goveroaent .............. 7 7 7 7 7 7 7 7
iellro.d ................ 7 7 7 7 7 7 7 7
Tote! ............... ----sIT ----m-----m -m ---m----rn--m ----m
Sel .. ~IMI)
iee1denU.1 ........................... 5,414 5,852 6,275 6,736 7,192 7,640 8,125 8.605
eo...rchl ............... , ... 4,604 4,815 5,033 5,300 5,532 5,813 6,105 6,408
GovetoaeDt .............. 1,359 1,408 1,459 1,511 1,564 1,620 1,675 1,737
iellroed ................ ~ 1 112 ~ ~ ....!.t.!!! ~ ~ ~ Total ............... 12, 5 n-:-m 13,912 14,726 15,504 16,325 17,194 18,078
APT Ole •••••••••• , ••••••••••••••••• 498 527 556 589 620 653 688 723
APT SYlt. Lo .... ................. 1,246 1,319 1,391 1,473 1,550 1,633 1,719 1,808
White pe .. , Yukon U (Own Oen) (0) .....!.....ill .....!.....ill ....h1!! -..l.t1!! ~ ~ ~ ~ 'lbtal c.-unit1 iequ.1r.entl .. 15,719 16,552 17,378 18,307 19,193 20,130 21,120 22,128
APT Dnand (kW) ............... , ... 3,242 3,432 3,621 3.833 4,035 4,249 4,475 4,705
White PIli • YukoD U Pe.k Dosand (0) 347 347 347 347 347 347 347 347
ToUI ~ti ... ted c.-unit1 Pe.k DoII&nd ""T.ill" J,779 3.968 4,180 4,382 "'T,1'96 "T,"ffi 5,052
(0) _ ~t1aat.d.
H
~ ......
tTl
H
H
H
I
~
0
., •
Jan. Feb.
Haines (1979) 607 652
Skagway (1978) 409 449
'Potal 1,016 1,101
Source: Reconnaissance Assessment
CI-l2M Hill, February 1980.
• •
HAINES-SKAGvlAY REGION
FEASIBILITY STUDY
ENERGY IN MWH BY MONTE FOR HAINES AND SKP.GHAY
Mar. ~ Hay June July Aug.
530 519 501 456 411 456
425 419 404 429 428 445
955 938 905 885 839 901
of Ener9Y Alternative, Chi1kat River Basin,
Sep. Oct.
492 492
452 514
944 1,006
Nov.
588
430
1,018
Dec.
588
451
1,03g
H
H
H
I
f-'
f-'
•
14,000
12,000
10,000
~ ~ 8,000
a
<t o
...J
~
<t
~ 6,000
4POO
2,000
1975
Historic
peok loads
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
PEAK LOAD FORECAST
TABLE III-12
~.,., ..
~~ ~ .. ~ ..
Growth scenario C \ ~ .. ., .. .," .," .," .,"
~ ~~
~ .. ., .. ~ .... .," .," .," .," .," Growth scenario B '\ ~ ... ~-.. ....:. f
~ .... ~-V ~ ..
~ ~ '/ ~ ~
.... J
~ .... ........ .... ., .. ~ ~ ....... . ..... , ..
CGrowth scenario A t~
~
Projected ...
peak loads
I I
1980 1985 1990
YEAR
1995 2000
•
•
.s:.
~
~
z
0
....J
....J
~
>=" C)
0::
IiJ • Z
IiJ
....J
~
~ z z
~
•
70
60
50
40
30
20
10
o
1975
Historic
energy
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
ENERGY REQUIREMENTS FORECAST
Growth seenorio C y
~.,
~ ... ~.,
TABLE III-13
i ..... ..... .... ~ ... ~
/~
~ -I'
/ ...... Growth scenario B
I -~ ____ V
~ I( ~~ ~ .. , .....
• •••••••
•••••• ~.
~ r.. ..... ~ ....
.t ~ ....
"Growth s"enorio A ~ ... ....
~
~
Projected
energy requ"rements
requ iremerfts
I
1980 1985
I
1990
YEAR
I I I
1995 2000
•
•
•
SECTION IV
ALTERNATIVE MEANS OF GENERATION CONSIDERED
1 • GENERAL
There are a number of generation options available to Haines and
Skagway to meet the loads forecasted above. The most probable are hydropower,
diesel generation, wind power, and wood waste generation. In addition, waste
heat recovery systems attached to the diesel generators could meet some of the
space heating requirements. Conservation generally will have its greatest
impact on space and water heating, but these are not electrical loads in
Haines and Skagway. The various means of generation and conservation are dis-
cussed below.
2. HYDROELECTRIC GENERATION
The climate and topography of Southeast Alaska make it ideally
suited for hydroelectric generation and many of the communities derive a large
part of their energy from this source. As a means of generation, hydropower
has a number of advantages: it uses a renewable resource; it has a high ef-
ficiency (85%); it has a basically nonescalating cost; it is relatively non-
polluting; and it is reliable over a long life. The major problem with hydro-
power is finding a site which can be economically developed. Thus, much of
the early work on any hydroproject focuses on site selection and evaluation.
Hydropower sites are developed in two general patterns, as run-of-
river projects or as storage projects. Run-of-river projects are ones which
operate only when and to the extent that water is naturally available in the
river. During times of high flow, the Project generates at its full capacity,
but during times of low flow, generation is limited by the lack of water. By
developing reservoir storage to regulate streamflows this problem can be rec-
tified. During times of high flow water not required for generation is stored
in a reservoir and then used for generation when flow in the river drops below
the level required for generation. Run-of-river projects have the disadvan-
tage of only being able to generate at full capacity for a part of the year,
but have the advantage of being less expensive to build because they usually
do not require a large dam. Storage projects, on the other hand, have a high
initial cost, but this must be compared with the advantage of having year-
round generating capability •
In the Haines-Skagway Region, this difference is particularly im-
portant because the low flow season occurs during the winter, the time when
energy requirements are generally at their highest level. The potential for
meeting the electric energy requirements of Haines and Skagway using hydro-
electric power has been the subject of two recent reconnaissance studies per-
formed under the direction of the APA. These studies identified 13 potential
IV-2
sites in the region. (2) Most were run-of-river with no potential for stor-
age and of a size which would only meet the needs of one of the communities.
In contrast, the West Creek and Goat Lake sites could be developed as storage
projects with a capacity sufficient to meet the needs of both Haines and Skag-
way.
Based on the work performed in the two studies, the APA concluded
that the most economical hydroelectric project was probably the West Creek
Project with a transmission intertie to Haines and Skagway. A second site at
Goat Lake was also considered a possibility although no site inspection had
been made at that time by either Beck or CH2M Hill. During the summer of 1981
a site reconnaissance of Goat Lake was made by Beck and a letter report to the
APA prepared. The reconnaissance revealed certain potential geological prob-
lems with the Goat Lake site and the study showed that the site would probably
be less feasible than the West Creek site. These results are discussed in de-
tail in the letter report dated October 14, 1982 and included as Appendix A.
In addition, a small run-of-river project on Haska Creek across the
Chilkat River from Haines was investigated at the request of Haines Light and
Power. This site has a hydrology similar to the other run-of-river projects
studied in the Reconnaissance and could generate about 3,400 MWh per year with
an installed capacity of 1,300 kW. The site would be very expensive to devel-
op and was not considered economical.
The West Creek Project, sized to meet the 1996 Scenario B require-
ments of both communities, would have an installed capacity of 6,000 kW and a
firm annual energy production of 23,630 MWh. The Project would consist of a
concrete-faced rockfill dam 120 feet high, a 1.6-mile-long tunnel, a
1,570-foot-long penstock, and a powerhouse with two 3,000-kW units. Power
from the P roj ect would be transmit ted at 34.5 kV overland to Skagway and by
submarine cable to Haines. Details of this Project are discussed in Part B of
this Report.
3. DIESEL GENERATION AND WASTE HEAT
a. Diesel-Electric Plants
At the present time the electrical energy needs of the Haines area
are met by diesel-electric generating units and those of the Skagway area in
part by diesel-electric units and in part by hydroelectric power.
A diesel engine is a device for converting heat energy from the
combustion of fuel into mechanical energy and waste heat. Waste heat is a by-
product of heat engines such as a diesel engine, because not all of the energy
provided from full combustion is converted into mechanical energy. The ratio
of mechanical energy produced to the total energy content of the fuel used is
defined as the efficiency of the engine. Diesels with efficiencies of 35-40%
rank high among thermal engines.
•
..
•
..
IV-3
An electrical generator is directly coupled to the engine and con-
verts the mechanical energy produced by the engine to electricity. Additional
losses associated with the electrical generation reduce the overall efficiency
of the diesel generator to approximately 30%. This implies that around 70% of
the energy content of the fuel is lost due to friction or as waste heat. In
typical engines, approximately 30% of the total heat generated by fuel combus-
tion is absorbed by water in cooling jackets surrounding the combustion zone
and approximately 30% is carried away in hot exhaust gas and radiated from ex-
haust piping. Generally, about half of this waste heat or energy can be re-
covered.
b. Waste Heat Recovery
Attempts to reduce the energy lost in the production of electrical
energy have centered on increasing efficiency of the heat engine and on find-
ing a use for waste heat. Unfortunately, the two are not complementary. Tra-
ditionally, electric utilities have chosen to maximize power plant efficiency
and degrade waste heat. However, because of the relatively low efficiencies
achieved by even the most efficient diesel units, there are still substantial
opportunities to recover heat loss from high efficiency diesel engines so as
to make them even more efficient.
Heat recovery systems generally extract heat from the engine's
cooling system and/or the engine's exhaust system. Heat absorbed by the en-
gine's cooling system is sent to a heat exchanger where the heat is transfer-
red to water or some other fluid that is then piped to another location where
it can then be used for space, water, or process heating. Whether or not such
use is practicable is dependent on the location of the end user with respect
to the diesel plant, the output temperature of the engine's cooling water, and
the ability of the end user to use the heat.
To date, the APA has installed several waste heat recovery systems
in remote Alaskan communities with good results. A recent installation in the
• Town of Unalaska recovers enough waste heat from a 600-kW diesel generator to
heat about 45,000 square feet of public buildings and a 140,000-gallon swim-
ming pool. In most Alaskan installations, the use of waste heat recovery
systems will not reduce electrical energy consumption since very little elec-
tricity is used for space or water heating. The recovered heat, however, can
be used to displace heating oil and thus has a value equal to the value of the
displaced oil. Under these circumstances a waste heat recovery system cannot
be considered an electrical generating resource, but the electric utility can
sell the recovered heat and credit its overall production expenses. To evalu-
ate the economic feasibility of a waste heat recovery system, the cost of in-
stallation must be compared with the estimated credits to be received.
c. Application of Waste Heat Recovery to Haines and Skagway
Initial indications are that for both cities, the existing power
plants are near several potential users of recovered waste heat. Preliminary
evaluations also indicate that the potential for retrofitting the principal
IV-4
generators in Haines to accommodate waste heat recovery is good. Minor modi-
fications to the engines as well as the installation of necessary additional
equipment should provide favorable economic results. The primary generators
for Skagway, however, are two older 300-rpm, 1,250-kW machines which appear to
produce very little waste heat that can be recovered easily. The engine has a
large surface area which allows radiation of heat and thus the jacket water
temperature is only 135 0 F. These temperatures are too low to be used for
space heating applications without the use of a heat pump which is not consid-
ered economical at this time. Output temperatures of the cooling water sys-
tems of these machines are too low to be used as a heat source without the use
of heat pump extraction.
Actual costs of installation and the amounts of heat recovered that
could or would be used are very site specific and would require detailed anal-
yses to determine accurately. To estimate the potential economic effects of
waste heat recovery, however, it has been assumed that the maximum amount of
waste heat easily recoverable through the cooling systems of HLP generators is
recovered and is used to offset the use of heating oil. No waste heat is
assumed to be recovered in Skagway. Based on the load estimates provided in
Scenario B, this would result in approximately $90,000 of heating oil dis-
placed annually at 1982 price levels. The cost of installing such a recovery
system can only be estimated at this time based on a similar installation and
is assumed to be $600,000.
4. WIND ENERGY CONVERSION SYSTEMS
Wind Energy Conversion Systems (WECS) are used to convert wind en-
ergy to electrical energy. This electrical energy source utilizes a renewable
resource, is simple and essentially nonpolluting. Wind energy is intermittent
and cannot be considered a source of firm capacity unless some sort of power
storage, such as batteries, is included. Unfortunately, battery storage tech-
nology is still developing and at the current time is not economical for large
applications. Without storage, WECS are simply fuel savers offsetting the use
of diesel fuel or retaining water in reservoirs behind hydroelectric facil-
ities only when sufficient wind is available.
Small WECS (SWECS) under 10 kW in size have been used to generate
electricity on remote farms and homesteads in Alaska. A 2.2-kW SWECS was in-
stalled at Kotzebue in 1979 and interconnected with the electric utility as a
pilot project to provide data for determining the feasibility of future WECS
installations as well as to supply electricity to the city. Similar study
projects are underway at Nelson Lagoon, Newhalen, Unalakleet, Chevak, Sheldon
Point and Skagway. (5) In the fall of 1981, the City of Skagway installed a
10-kW WECS unit at the sewage treatment plant. Power in excess of the needs
of the treatment plant is fed into the electric system and purchased by AP&T.
The small wind turbine business in the United States has been fair-
ly successful. About 2,000 units were sold in 1981, almost a 50% increase
over 1980. Many of these small machines are designed to be connected to a
•
..
•
IV-5
utility grid, can be erected without a crane and can be dismantled quickly for
maintenance.
a • Description of the WECS
The conventional propeller or horizontal axis WECS is currently the
prototype for utility applications. The rotor diameter and blade characteris-
tics are a function of the wind regime for which the system is designed. A
step-up gearbox and electric generator are used to convert rotor rotation into
electric power and an orientation drive turns the system about the vertical
axis, locating the rotor downwind to provide stability during changes in wind
direction. The cut-in velocity is a design parameter above which usable power
is generated; the blades are feathered to avoid damage during extreme wind
conditions. The control system also provides automatic capability for startup
and shutdown, orientation turning, power regulation and mutual electric pro-
tection of the transmission network and the WECS.
Another design being demonstrated is that of the Darrieus or verti-
cal axis WECS. With this design, each blade is attached to the top and bottom
of the axis giving the machine an "egg beater" appearance. Structurally, this
type of WECS has proven to be more stable than the conventional propeller WECS
since most of its weight, including that of the genera tor, is very near the
ground. Darrieus machines have been demonstrated throughout the U.S. and are
commercially available.
Successful operation for WECS in the 50-200-kW range has been
achieved over the last 3 years by both horizontal and vertical axis machines.
Development of large WECS 1,000 kW and larger, as undertaken by the Federal
Government, has been difficult and has yet to prove the viability of larger
WECS. Demonstration projects have been plagued by failures caused by break-
. down of routine parts and are more subject to failures caused by minor equip-
ment breakdown than the simpler, smaller machines. For example, three
2,500-kW Boeing-built MOD-25 turbines at the United States Department of
Energy's Goldendale, Washington site were shut down soon after startup when
valves of one unit failed because of contaminated hydraulic oil. Two of these
units were restarted in October of 1981 after modification of the hydraulic
and electrical systems. The third unit is expected to be reenergized in early
1982.
The inclusion of individual small and intermediate WECS in utility
systems has proven successful. Control systems within the WECS are capable of
reducing effects on frequency and voltage characteristics of the utility's
electric system. A 200-kW horizontal axis machine has demonstrated the capa-
bility of self regulation in a small 600-kW utility grid in Nova Scotia per-
mitting the WECS to supply the utility's entire load at certain times. How-
ever, the effects of creating wind farms, where several WECS are installed at
the same site, have not been determined. Possible problems could be unwanted
electric resonances interfering with electricity transfer and wind turbulence
created in the wake of one machine affecting other machines near it. (6)
IV-6
Hopefully, the three WECS at Goldendale, Washington will provide data to an-
swer these questions in the next few years because wind farms are considered
to be the most economical way of installing WECS. ~
b. Application of WECS to Haines and Skagway
In order to precisely predict the output of a proposed wind system
certain wind characteristics need to be known. The most important information
is the duration of wind speed or the percent of the total time that the wind
blows at any specific speed.
Other wind statistics that would be useful in determining the via-
bility of WECS at a particular location are:
(1) Seasonal and diurnal variability.
(2) Gust amplitude.
(3) Persistence -percent of time the wind blows from a particu-
lar direction.
(4) Variation of wind with height.
(5) Horizontal variation of the wind in the area under considera-
tion.
Current availability of wind data for Haines and Skagway is primar-
ily limited to information collected at the local airfields. Some of the in-
formation has been analyzed to produce rough wind frequency distributions and
average wind speed but is insufficient to accurately predict the power output
of WECS. Additionally, wind characteristics can vary significantly over small
distances and thus the expected output of WECS at nearby sites might vary
greatly. For the purpose of analysis, the average wind speed is assumed to be
12 mph in Skagway. Based on manufacturer's literature, at this wind speed, a
100-kW WECS will produce approximately 100,000 kWh annually. The same machine
could produce over twice this amount of energy if the average wind speed were
16 mph since available wind power varies as the cube of wind speed.
c. Costs
Many models of WECS are currently available on the market. Most
WECS in the range of 10 to 200 kW, although successfully tested, must still be
considered as demonstration models and the costs estimated for them now do not
reflect the costs anticipated if a large commercial industry develops and the
machines are mass produced. Typical capital costs of 100-200-kW WECS on the
market today are around $3,000 per kW including machinery, installa tion and
shipping. Transmission facilities are site specific depending primarily on
the distance of the WECS from existing transmission lines. The cost per kW
assoc ia ted with transmission would decline if several WECS were si tua ted to-
gether.
•
•
..
IV-1
Assuming a WECS located at a convenient tie-in point with existing
transmission facilities, a 20-year economic life, 3% financing, and minimal
operation and maintenance expenses, the annual cost of power from a WECS in
the Skagway area with 12 mph average wind speed would be about 22¢/kWh at 1982
price levels. Locating the WECS away from existing transmission facilities
would entail the construction of a transmission line thus increasing costs
further. At $1.16 per gallon and at current consumption rates, the cost of
diesel fuel replaced is 10¢/kWh. Thus, based on these assumptions, the cost
of power produced by the WECS is over twice the benefit received from the fuel
replacement. It cannot be overemphasized, however, that power costs estimated
for WECS are very site specific and detailed data collection is necessary to
estimate these costs completely. Additionally, the type of wind generation
industry that develops over the next few years will figure greatly into eco-
nomic evaluations as will escalation of fuel costs.
d. Environmental Considerations
There are possible safety hazards resulting from improper installa-
tion, malfunctioning equipment or severe environmental conditions which could
cause the windmill to collapse, throw blades or throw ice. WECS have been
known to cause communication interference as a result of rotating metal blades
and metal parts in the generators. This can be mitigated by using nonmetallic
blades and encasing the generators in properly grounded metallic shields.
Noise created by rotating blades can be mitigated by proper design to reduce
vibration. To some the appearance of windmills is objectionable. Color and
location could lessen this visual impact.
5. CONSERVATION
There are currently two State-sponsored conservation programs
available to residents of Alaska. One program, conducted by the Alaska State
Department of Commerce and Economic Development Conservation Division, in-
cludes up to a $300 refund for home weatherization efforts taken following an
energy audit conducted by the State. The Department of Commerce's Division of
Business is offering $5,000 and $10,000 low-interest home weatherization loans
to residents following an energy audit (the amount is determined by State-
determined payback time periods).
The U.S. Department of Energy is sponsoring a program for low in-
come people and other Federal aid-dependent residents who can qualify to re-
ceive up to $810 of weatherization materials following a home energy inspec-
tion. All of these programs are now being implemented in the Haines-Skagway
area. Building code standards in the area require total insulation levels of
R-20 in walls and floors and R-40 in the ceilings for new homes. Many of the
older homes in these communities have far less insulation, indicating a signi-
ficant potential for additional conservation. Space and water heating are the
two largest end uses of energy in the residential and commercial areas; how-
ever, only a small portion of such heating is now provided by electricity, so
that the overall potential for conserving electricity is limited. As a re-
sult, the projected load requirements under forecast Scenarios A and B would
Iv-8
not be significantly reduced by home weatherization and such potential has
already been included in Scenario C.
Other forms of conservation include Skagway's recently installed
power factor control devices on three water pumps which may reduce power re-
quirements for that equipment by between 5-10%. This reduction has been in-
cluded in all forecast scenarios. The use of heat pumps to reduce use of
fuels in existing forced air space heating systems has also been considered as
a method of reducing energy usage in Southeast Alaskan communities; however,
without some form of subsidy, extensive use of heat pumps seems unlikely be-
cause of the high capital costs required. Using wood as a supplement to or as
a substitute for other fuels is another al terna ti ve in Haines and Skagway.
About 20% of the local residents rely on wood for their primary fuel source
and many homes use either fireplaces or wood stoves to supplement the use of
other fuels. At a cost of about $85-$100 per cord (less if gathered by resi-
dents), wood is a very viable alternative in spite of its contribution to air
pollution.
Passive solar design in homes and buildings is another method of
offsetting water and space heating. Passive solar heating involves the col-
lection and storage of heat produced by the sun, which is used to heat water
or is circulated throughout the structure during times of low temperature.
For load growth Scenarios A and B, it is assumed there would be no impact from
the use of solar heating. Some of the Scenario C growth in electric require-
ments, which includes electric space and water heating, could be offset with
the increasing use of solar heat. A passive solar house has been constructed
in Skagway and is reported to have good results. However, due to the high
capital costs and special sun orientation requirements of solar-designed
buildings, it is doubtful that a large number of solar units will be built in
these communities.
Other conservation measures such as limiting use of energy-using
appliances, use of energy-efficient appliances and equipment and building
weatherization are expected to continue to be implemented in Haines and Skag-
way. The impact of these measures as well as likely conservation response to
increasing electricity prices, has been included in all of the load forecast
scenarios.
6. WOOD WASTE GENERATION
The Schnabel Lumber Company near Haines is the only sawmill in the
Haines-Skagway study area which is presently producing wood waste. The feasi-
bility for use of this wood waste in the generation of electricity has been
studied by Nor'West-Pacific Corporation (NWPC), and is the subject of a report
dated January 1974 and updated in 1979. This report recommends proceeding
with the installation of a 4, OOO-kW wood waste-fired generating plant at the
mill. The project is now under construction and is scheduled to commence
operation by January 1, 1983.
•
•
,
IV-9
Electrical energy for the mill is currently produced by a 2,100-kW
power plant containing three diesel-generating units. Energy is purchased
from HLP when the diesel plant cannot supply the entire mill load. The new
4,000-kW wood waste-fired plant will be capable of supplying the power re-
quirements of the new power plant and the mill and still have capability to
sell energy to HLP. The NWPC updated feasibility study indicates that the new
power plant can produce 20,000,000 kWh per year based on the mill cutting
28 million board feet (mmbf) per year. Of the 20,000,000 kWh per year, ap-
proximately 35% would be required at the mill and 65% would be available for
sale based on the NWPC study.
Schnabel and HLP have recently executed a contract whereby the mill
will sell up to 2,000 kW of firm capacity 24 hours a day, 50 weeks per year,
as required by HLP. The contract becomes effective on the date of commence-
ment of delivery of electric power to HLP and runs for five years or until
August 1, 1988, whichever occurs first. Schnabel has the right to remove its
generating plant from operation for maintenance and repairs for a thirty-day
period each year during the months of May through September. Under terms of
the contract, Schnabel will sell power to HLP at a rate of 8 cents per kWh
during the first year of production increasing 1/2 cent per kWh each year
thereafter during the contract period ("Contract for Electric Service" between
Schnabel and HLP).
Use of the wood waste-fired generator as an alternative for meeting
the energy needs of the region is possible if there is continued supply of
wood waste. This depends on the availability of wood to the mill, the market
for wood from the mill, and the market for wood waste. As long as the mill is
processing on the order of 28 mmbf and does not have abetter market for the
wood waste, the wood waste-fired generator is a viable alternative. If, how-
ever, wood waste must be purchased from other mills, or if a market for wood
waste develops, the cost of the fuel will increase and hence the cost of en-
ergy electricity. Another added cost would occur if it were necessary to use
oil to help fire the wood waste. This would be the case if the moisture con-
tent of the wood waste is greater than 55%, in which case the wood should be
fired with sufficient oil to dry the wood to 55% moisture content. Approxi-
mately 1,000 Btu's would be required per pound of water. Based on the NWPC
study, wood waste from wood processed at the mill should have a moisture con-
tent of 55%. However, if the wood waste is stockpiled during a wet period or
is barged in from another mill, it may have a higher moisture content and thus
need oil firing.
The 20,000,000 kWh annual output of the wood waste-fired power
plant is adequate to meet the energy requirements of the power plant itself,
the mill, and the Haines load area through 1995 based on the Scenario B load
forecast. The peak load would exceed the capacity of the plant in 1990. In
earlier years when the annual energy load is less than 20,000,000 kWh it would
be necessary to operate the power plant at reduced efficiency in order to dis-
pose of all of the wood waste produced at the mill.
IV-10
Based on experience with general operation of fossil-fuel thermal
uni ts, it is reasonable to expect that the wood waste-fired plant would be
available a maximum of 85% of the year. Diesel generation would be required
to meet the remaining 15% of the energy requirements.
Although the wood waste-fired power plant can be considered an eco-
nomic and feasible means of meeting Haines' requirements for the five-year
term of the agreement between Schnabel and HLP, it cannot be considered a firm
resource beyond that period. In addition to the questions pertaining to the
supply of wood waste which are discussed above, there are questions as to the
cost to the community. Under the present contract, HLP is purchasing its
total energy requirements for 50 weeks each year at a price below the cost of
diesel fuel. Conditions at the end of the five-year contract may be such that
the energy costs will be higher than diesel fuel or that there will be much
less energy available either because of increased energy usage at the mill or
because of a reduced availability of wood waste.
•
,.
•
..
..
SECTION V
ALTERNATIVE PLANS IDENTIFIED
FOR MEETING AREA GENERATION REQUIREMENTS
1. GENERAL
From the various means of generation discussed in Section IV, three
al ternati ve plans were identified for meeting the area's future generation
requirements: ( 1) a base case of continued use of diesel genera tors; (2) a
West Creek hydroelectric plan; and (3) a wood waste generation plan. The
three plans are discussed in the following.
2. BASE CASE PLAN
The base case plan is basically a continuation of the status quo.
Electric loads in Haines are met entirely by diesel; in Skagway the loads are
met by a combination of diesel and hydroelectric power. The base case plan
assumes that the present generating facilities will continue to operate
through their economic lives and then be replaced with similar units. New
generation requirements will be met by the installation of new diesel genera-
tion. In the base case plan 10% of the requirements of the Schnabel mill are
included in the plan's loads. The remaining 90% will be met by the mill's own
resources. This is consistent with the assumptions used in the West Creek
Hydroelectric Plan.
The plan includes a net credit for the value of a waste heat recov-
ery retrofitting of the Haines diesel generators. This credit is the differ-
ence between the value of the heating which can be achieved with waste heat
and the amortized cost of the waste heat recovery system. For 1982, this is
estimated to be an annual amount of $50,000. The credit increases from year-
to-year as generation increases and as the cost of oil escalates. No credit
is given for retrofitting the Skagway plant since it is considered uneconomi-
cal as discussed in Section IV. No credit is applied in either of the other
plans since the diesel generator in Haines would not operate on a continuous
basis and hence the economic value of retrofitting for waste heat recovery
would be limited.
For the Scenario B loads, new diesel generators are required in
1993 and 1998. In 1993 2,070 kW are needed to replace the Haines unit of the
same capacity. In 1998 the two 1,250-kW units in Skagway would have to be
replaced. Reserve requirements for the two systems indicate that an addi-
tional 600 kW of capacity will be required in 1998. New diesel plants are
estimated to have a Total Investment Cost of $800 per kW in 1982 dollars based
on actual installation of a similar unit in Alaska. The cost is based on a
current cost level, that is for plants coming on-line in January 1982. The
V-2
annual operating cost of the diesel alternative is estimated to be $852,000,
also in 1982 dollars. Operating costs are based on operating experience in-
formation which includes Alaskan experience.
The existing hydro units in Skagway are assumed to have an economic
life equal to the period of analysis and thus will not need to be replaced.
3. WEST CREEK HYDROELECTRIC PLAN
The West Creek hydroelectric plan assumes that a 6, OOO-kW hydro--
electric project on West Creek will come on-line in late 1986. The Project is
sized to meet the 1996 energy requirements during the worst hydrologic condi-
tions recorded on West Creek. However, after 1996 the Project can meet all
the region's additional energy needs during the high streamflow months until
such time as the loads grow beyond the capacity of the plant, about the year
2001. This is a conservative analysis in that during most years, there will
be sufficient inflow even during the dry season to meet more than just the
1996 loads. The Project has a Total Investment Cost of $48,803,000 in January
1982 dollars, that is, for a project coming on-line in January 1982. The an-
nual operating costs are $634,000, also in January 1982 dollars.
The plan assumes that the existing hydro units in Skagway continue
to operate. Based on the 1981 generation records, the upgraded hydro units in
Skagway were assumed to generate 2,900 MWh per year. It also assumes that 10%
of the Schnabel Mill requirements would be met by the Project with the remain-
ing 90% being provided by the mill's own resources.
The existing diesel units are assumed to be maintained and operated
as reserve for the Project until 1996. After 1996 it is assumed that the die-
sel units would meet the requirements in excess of those met by the Project.
4. WOOD WASTE GENERATION PLAN
The wood waste generation plan assumes that the Haines energy re-
quirements will be met by the wood waste generation plant being installed at
the Schnabel Mill. Energy requirements in Skagway will continue to be met by
the present combination of diesel and hydroelectric generation; the feasibil-
ity of installing the submarine cable between Haines and Skagway and using
some of the surplus power from the wood waste generator was considered but is
not economical for the wood waste generation plan.
Under this plan it is assumed that the wood waste generator could
operate 85% of the time and meet all Haines requirements in addition to those
of the mill up to 20,000 MWh per year. The remaining 15% will be met by die-
sel generation, either at the Schnabel diesel plant or at the HLP plant. Be-
cause there was some question as to the availability and cost of wood waste
•
..
•
,
..
V-3
for fuel over the entire period of analysis, a second case with an annual gen-
eration of only 12,000 MWh was also studied. This level of generation corres-
ponds to a production of 17 mmbf per year. Other than this sensitivity analy-
sis, no analysis was made of the effect of the cost of wood waste or of the
need for adding oil for firing the wood waste.
The economic life of the wood waste generator is assumed to be
20 years. At that point a new wood waste generator will replace the one being
presently installed. The eXisting diesel generators are assumed to continue
operating for their economic life of 20 years and will then be replaced as in
the base case plan.
Based on information supplied by NWPC, the Total Investment Cost of
the wood waste generator now being installed is $4,300,000 in January 1982
dollars. This is the actual cost for a new plant using a renovated boiler and
generator. The annual operating costs are $508,800, also in January 1982 dol-
lars. When the plant would have to be replaced, it was assumed that the new
plant would have a Total Investment Cost of $12,500,000, since it is unlikely
that another used plant would be available •
"
•
to
•
SECTION VI
EVALUATION OF ALTERNATIVE PLANS
1 • GENERAL
Evaluation of the three alternative plans for meeting the energy
requirements of Haines and Skagway was made based on both economic and envi-
ronmental criteria. The economic evaluation was made using criteria estab-
lished by the APA in its Feasibility Study Regulations which allow for a com-
parison of the total cost of each plan over an evaluation period from the
present through the economic life of the West Creek Project. The environ-
mental evaluation included a comparison of the major impacts of each plan.
2. ECONOMIC ANALYSIS
a. Method of Analysis
The method of analysis used for this study computed the total pres-
ent worth cost of each plan over a period from the present through the 50-year
economic life of the West Creek Project (1982-2036). The method assumed no
inflation except that real escalation of oil fuel costs was assumed to be 2.6%
per year for 20 years and then was held constant. A discount rate of 3% was
assumed.
Cri teria used for conducting Project economic analysis as estab-
lished by the APA, were as follows:
(1) Constant dollars assumed (zero inflation).
(2 ) Inflation-free present worth discount rate of 3%.
(3) Petroleum fuel cost escalated at 2.6% per year for 20 years
and then held constant.
(4) Electrical energy demand is forecasted according to Load
Growth Scenarios described above and then held constant.
(5) Interest During Construction is calculated using a 3% inter-
est rate.
(6) No financing expenses are included.
(7) No debt service on existing diesel or hydroelectric genera-
tion is included •
VI-2
(8) Period of economic analysis is 55 years (1982 through 2036).
(9) Economic life of hydroelectric plant is 50 years.
(10) Economic life of diesel generation facility is 20 years.
(11) Economic life of wood waste generation facility is 20 years.
b. Annual Costs
The annual cost for each plan is the sum of the Total Investment
Cost of each part of the plan amortized at a 3% interest rate over the eco-
nomic li fe of the generating unit, the operation and maintenance costs, and
the fuel costs. For the base case plan a credit is also given for the value
of waste heat recovered from the diesel generator. For the Scenario B loads,
the annual costs are listed for each year from 1982 through 2001 in
Tables VI-1, VI-2, and VI-3 for the base case plan, the West Creek hydroelec-
tric plan and the wood waste generation plan respectively. Table VI-4 gives
the annual costs for a wood waste generation plan with only 12,000 MWh of gen-
eration available. From 2001 to 2036, the annual costs remain the same, ex-
cept for the wood waste plan where a new plant must be added in 2003, and the
capital costs of the alternative increase accordingly.
c. Costs of Alternative Plans
The total cost of each plan is the sum of the present worth of each
year's cost discounted at 3% to 1982. The results for the Scenario B loads
are included in Tables VI-1, VI-2, VI-3 and VI-4 for the base case plan, the
West Creek plan, the 20, OOO-MWh wood waste plan (Case A) and the 12,000 MWh
wood waste plan (Case B), respectively. The results for the Scenario A loads
are included in Tables VI-5, VI-6 and VI-7 for the base case plan, the West
Creek plan, and the 20,000 MWh wood waste plan respectively. Tables VI-B,
VI-9 and VI-10 present the results for the three plans with the Scenario C
loads. Table VI-11 is a summary of the total present worth costs for the
three plans for each of the three scenarios.
Table VI-12 presents the total present worth costs for the West
Creek plan assuming the on-line date is delayed between one and eight years.
d. Cost Comparison
The comparison of total present worth costs of the alternative
plans shows that the least expensive plan is the West Creek Project. This
plan has a total cost of $92,031,000 and a 1.27 base case to alternate plan
ratio. The wood waste generation plan is also less expensive than the base
case plan assuming there is a free supply of wood waste which can produce
20,000 MWh of electrical energy annually. When the annual generation from
wood waste decreases to 12,000 MWh, the al terna ti ve becomes more expensive
than the base case.
..
..
..
&
•
VI-3
3. ENVIRONMENTAL EVALUATION
a. Base Case Plan
4 The base case plan assumes that Skagway would continue with current
use of diesel and hydro generation and Haines would continue with diesel gen-
eration. Increased demand for both cities would be met with additional diesel
units.
Utilizing diesel generation in the base case plan could result in
negative environmental impacts of noise and air pollution. The noise of die-
sel combustion may be mitigated, at least in part, by facilities design and
location. Emissions from diesel combustion include particulates, S02, CO,
NO and hydrocarbons. Whether these emissions would cause an air quality prob-
lem depends on the magnitude of the emissions, the particular air shed, and
the existing air quality. The current diesel operations do not significantly
affect air quality of the region. The Haines Power Plant formerly required an
Air Quality Permit to Operate from the Alaska Department of Environmental Con-
servation but a recent revision in regulations has made this unnecessary.
Potential effects on air quality of additional diesel units would need to be
addressed.
Under the base case plan, the wood waste generator would probably
be used to meet 90% of the requirements of the Schnabel mill. Environmental
impacts of this energy source are addressed below in the discussion of the
wood waste generation plan.
b. West Creek Hydroelectric Plan
This plan assumes that the West Creek Project would meet the major-
ity of power requirements in the region. The existing hydro units in Skagway
would continue to operate and the existing diesel units in Skagway and Haines
would function in a reserve capacity until 1996 and then would be used to meet
requirements in excess of those provided by hydroelectric generation. The
wood waste generator would provide 90% of the Schnabel mill requirements.
The West Creek Project would cause 635 acres of the upper West
Creek Valley to be inundated with subsequent loss of terrestrial and aquatic
habitat and formation of new shoreline. Losses of wildlife would be small and
over the Project lifetime, wildlife populations would readjust. No signifi-
cant effects on anadromous or resident fishes are expected from the Project.
Potential visual impacts of the penstock, powerhouse and transmission line
would be minimized by design of facilities and vegetative management to camou-
flage the facilities. (See Section XIV, Effect on Environment of the Selected
Project Arrangement, for a comprehensive evaluation of West Creek Project en-
• vironmental impacts.)
Environmental impacts of the diesels when operating would be noise
and air pollution as discussed previously. However, the magnitude of poten-
tial impacts would be less than with the base case plan because operation
VI-4
would be reduced in the reserve capacity and no new units would be necessary
to meet future demand. Similarly, generation requirements of the wood waste
generator and, therefore, its negative impacts would be less than with the 1
wood waste generation plan.
c. Wood Waste Generation Plan
In this plan Schnabel Lumber Company's wood waste plant is assumed
to meet all the mill's requirements plus the requirements of Haines. However,
the wood waste plant was assumed to operate only 85% of the time, and thus
diesel generation would have to meet the load 15% of the time. Skagway would
continue with existing diesel and hydroelectric generation.
The wood waste-fired plant would produce emissions expected to con-
tain particulates, hydrocarbons, carbon monoxide, sulphur dioxide and nitrogen
dioxide. The indication, however, is that the pollutants would be reduced to
acceptable levels by use of a scrubbing unit. The State Department of Envi-
ronmental Conservation has issued a Permit to Operate pending review of
Schnabel's plans.
Residual ash from the wood waste plant would be disposed of in a
landfill. Leachates from the disposal are not expected to be a significant
problem at the planned landfill location. The plant will burn material which
otherwise would become landfill.
Noise and air pollution from the diesel plants would be as ad-
dressed previously.
. .
..
• • •
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO B BASE CASE DIESEL GENERATION
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel Annual Annual
Required Required Required Cost O&M Cost Cost O&M Cost Cost Cost Cost
Year (MWh) (1) (KW) (2) (MWh) (3) ($000)(4) ($000) (5) ($000) (6) ($000)(7) ($000) (8) ($000) (9) ($000) (10)
----------------------------------------------------------------------------------------------------
1982 11,758 0 11,758 0 0 0 901 1,137 2,038 2,008
1983 12,431 0 12,431 0 0 0 845 1,233 2,078 1,988
1984 12,794 0 12,794 0 0 0 842 1,302 2,144 1,991
1985 13 ,288 0 13,288 0 0 0 839 1,387 2,226 2,007
1986 14,736 0 14,736 0 0 0 828 1,579 2,407 2,107
1987 15,875 0 15,875 0 0 0 821 1,745 2,566 2,181
1988 16,589 0 16,589 0 0 0 816 1,871 2,687 2,217
1989 17,146 0 17,146 0 0 0 812 1,984 2,796 2,240
1990 17,376 0 17,376 0 0 0 810 2,063 2,873 2,235
1991 18,199 0 18,199 0 0 0 804 2,216 3,020 2,281
1992 19,088 0 19,088 0 0 0 798 2,385 3,183 2,334
1993 19,969 0 19,969 0 0 111 792 2,560 3,463 2,465
1994 20,777 0 20,777 0 0 111 786 2,733 3,630 2,509
1995 21,446 0 21,446 0 0 111 782 2,894 3,787 2,541
1996 22,230 0 22,230 0 0 111 776 3,078 3,965 2,583
1997 22,982 0 22,982 0 0 111 771 3,265 4,147 2,623
1998 23,778 600 23,778 0 0 286 837 3,466 4,589 2,818
1999 24,636 0 24,636 0 0 286 831 3,684 4,801 2,862
2000 25,491 0 25,491 0 0 286 825 3,911 5,022 2,907
2001 26,381 0 26,381 0 0 286 819 4,153 5,258 2,955
2002-2036 ( Assuming no additional growth or escalation 35 Years Cumulative 63,485
Cumulative Present Worth
of Project Annual Costs 111,337
----------
(1)-Scenario B loads less 2900 MWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
(2)-Based on existing capacity of 7510 KW for both systems.
(3)-
(4)-
(5)-
(6)-Replacement of existing and addition of new base load diesel generators. Assumes capital cost of $800/KW.
(7)-Assumes $120 per KW-YR less net credit for waste heat recovery.
(8)-Assumes diesel fuel cost of $1.16/gallon in 1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(9)-
(10)-Discounted to January 1982 at 3% per year.
<
..
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO B WEST CREEK PROJECT
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel .1 Annual Annual
Required Required Required Cost O&K Cost Cost O&K Cost Cost :' Cost Cost
Year (KWh) (1) (KW) (2) (KWh) (3) ($ 00 0) (4) ($000) (5) ($000) (6) ($000) (7) ($000)(8) ($000) (9) ($000) (10)
----------------------------------------------------------------------------------------------------
1982 11,758 0 11 ,758 0 0 0 901 1,137 2,038 2,008
1983 12,431 0 12,431 0 0 0 901 1,233 2,134 2,041
1984 12,794 0 12,794 0 0 0 901 1,302 2,203 2,046
1985 13 ,288 0 13,288 0 0 0 901 1,387 2,288 2,063
1986 14,736 0 14,736 0 0 0 901 1,579 2,480 2,171
1987 15,875 0 0 2,173 727 0 459 0 3,359 2,855
1988 16,589 0 0 2,173 727 0 459 0 3,359 2,772
1989 17,146 0 0 2,173 727 0 459 0 3,359 2,691
1990 17,376 0 0 2,173 727 0 459 0 3,359 2,613
1991 18,199 0 0 2,173 727 0 459 0 3,359 2,537
1992 19,088 0 0 2,173 727 0 459 0 3,359 2,463
1993 19,969 0 0 2,173 727 0 459 0 3,359 2,391
1994 20,777 0 0 2,173 727 0 459 0 3,359 2,321
1995 21,446 0 0 2,173 727 0 459 0 3,359 2,254
1996 22,230 0 0 2,173 727 0 459 0 3,359 2,188
1997 22,982 0 0 2,173 727 0 459 0 3,359 2,124
1998 23,778 0 0 2,173 727 0 459 0 3,359 2,062
1999 24,636 0 46 2,173 727 0 459 7 3,366 2,007
2000 25,491 0 557 2,173 727 0 459 85 3,444 1,993
2001 26,381 0 1,091 2,173 727 0 459 172 3,531 1,984
2002-2036 ( Assuming no additional growth or escalation 35 Years Cumulative 42,633
Cumulative Present Worth
of Project Annual Costs 88,217
----------
(1)-Scenario B loads less 2900 KWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
(2)-Based on existing capacity of 7510 KW for both systems.
(3)-Assumes 23,630 KWh annually of West Creek generation to begin in 1987 plus 40% of load requirements above 23,630 KWh.
(4)-Assumed level debt service at 3% over 50 years. Total investment cost assumed to be $55,908,000 including IDC at 3%.
(5)-Based on 1.3% of total investment cost.
(6) -
(7
8
): Assumes $120 per KW annual expense. Approximately 50% of existing capacity is mothballed at 2% base cost in 1987.
() Assumes diesel fuel cost of $1.16/ga11on in 1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(9)-
(10)-Discounted to January 1982 at 3% per year.
H
5;
t-'
M
<:
H
I
N
• .. • • ..
HAINES-SKAGWAY REGION .....
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO B WOOD WASTE GENERATOR CASE A
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel Annual Annual
Required Required Required Cost O&M Cost Cost O&M Cost Cost Cost Cost
Year (MWh) (1) (KW) (2) (MWh) (3) ($000)(4) ($000) (5) ($000) (6) ($000) (7) ($000) (8) ($000)(9) ($000) (10)
---------------------------------------- ------------------------------------------------------------
1982 11 ,758 0 11,758 0 0 0 901 1,137 2,038 2,008
1983 12,431 0 5,710 289 509 0 901 566 2,265 2,167
1984 12,794 0 5,906 289 509 0 901 601 2,300 2,136
1985 13,288 0 6,162 289 509 0 901 643 2,342 2,112
1986 14,736 0 7,176 289 509 0 901 769 2,468 2,161
1987 15,875 0 8,007 289 509 0 901 880 2,579 2,192
1988 16,589 0 8,326 289 509 0 901 939 2,638 2,177
1989 17,146 0 8,609 289 509 0 901 996 2,695 2,159
1990 17 ,376 0 7,934 289 509 0 901 942 2,641 2,054
1991 18,199 0 8,166 289 509 0 901 995 2,694 2,034
1992 19,088 0 8,711 289 509 0 901 1,088 2,787 2,043
1993 19,969 0 9,237 289 509 111 901 1,184 2,994 2,131
1994 20,777 0 9,678 289 509 111 901 1,273 3,083 2,131
1995 21,446 0 10,059 289 509 111 901 1,358 3,168 2,126
1996 22,230 0 10,491 289 509 111 901 1,453 3,263 2,126
1997 22,982 0 10,911 289 509 111 901 1,550 3,360 2,125
1998 23,778 300 11 ,363 289 509 147 937 1,656 3,538 2,172
1999 24,636 0 11,839 289 509 147 937 1,771 3,653 2,178
2000 25,491 0 12,330 289 509 147 937 1,892 3,774 2,184
2001 26,381 0 12,848 289 509 147 937 2,023 3,905 2,194
2002 26,381 0 12,848 289 509 147 937 2,023 3,905 2,130
2003 26,381 0 12,848 840 509 147 937 2,023 4,456 2,360
2004-2036 ( Assuming no additional growth or escalation 33 Years Cumulative 49,010
(1) -
(2)-
(3) -
(4)-
(5)-
(6)-
(7)-
(8) -
(9)-
Cumulative Present Worth
of Project Annual Costs 96,110
----------
Scenario B loads less 2900 MWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
Based on existing capacity of 7510 KW for both systems.
Assumes Wood Waste Generator will supply 85% of Haines total load less mill load up to 20,000 MWh annually.
Assumed level debt service at 3% over 20 years. Total capital cost assumed to be $4.3M. Plant replaced for $12.5M in 200
Preliminary estimate. No escalation.
Addition of new and replacement of existing
Assumes $120 per KW annual expense. Assumes
Assumes diesel fuel cost of $1.16/ga11on in
base load diesel in Skagway at $800 per KW.
100% of existing capacity to be available for service.
1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(10)-Discounted to January 1982 at 3% per year.
• .. • • • • • ~
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO B WOOD WASTE GENERATOR CASE B
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel Annual Annual
Required Required Required Cost O&M Cost Cost O&M Cost Cost Cost Cost
Year (MWh) (1) (KW) (2) (MWh) (3) ($000) (4) ($000)(5) ($000) (6) ($000) (7) ($000) (8) ($000)(9) ($000) (10)
------------------------------------------------------------ ----------------------------------------
1982 11 ,758 0 11 ,758 0 0 0 901 1,137 2,038 2,008
1983 12,431 0 6,413 289 509 0 901 636 2,335 2,234
1984 12,794 0 6,776 289 509 0 901 690 2,389 2,219
1985 13,288 0 7,270 289 509 0 901 759 2,458 2,216
1986 14,736 0 8,718 289 509 0 901 934 2,633 2,305
1987 15,875 0 9,857 289 509 0 901 1,083 2,782 2,365
1988 16,589 0 10,571 289 509 0 901 1,192 2,891 2,386
1989 17,146 0 11 ,128 289 509 0 901 1,287 2,986 2,392
1990 17,376 0 11 ,358 289 509 0 901 1,348 3,047 2,370
1991 18,199 0 12,181 289 509 0 901 1,483 3,182 2,403
1992 19,088 0 13,070 289 509 0 901 1,633 3,332 2,443
1993 19,969 0 13 ,951 289 509 III 901 1,789 3,599 2,562
1994 20,777 0 14,759 289 509 III 901 1,941 3,751 2,592
1995 21,446 0 15,428 289 509 111 901 2,082 3,892 2,611
1996 22,230 0 16,212 289 509 111 901 2,245 4,055 2,641
1997 22,982 0 16,964 289 509 III 901 2,410 4,220 2,669
1998 23,778 600 17,760 289 509 286 973 2,589 4,646 2,853
1999 24,636 0 18,618 289 509 286 973 2,784 4,841 2,886
2000 25,491 0 19,473 289 509 286 973 2,988 5,045 2,920
2001 26,381 0 20,363 289 509 286 973 3,206 5,263 2,957
2002 26,381 0 20,363 289 509 286 973 3,206 5,263 2,871
2003 26,381 0 20,363 840 509 286 973 3,206 5,814 3,079
2004-2036 ( Assuming no additional growth or escalation 33 Years Cumulative 63,947
(1)-
(2)-
(3)-
(4)-
(5)-
(6)-
(7)-
(8)-
(9)-
Cumulative Present Worth
of Project Annual Costs 119,929
----------
Scenario B loads less 2900 MWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
Based on existing capacity of 7510 KW for both systems.
Assumes Wood Waste Generator will supply 85% of Haines total load less mill load up to 12,000 MWh annually.
Assumed level debt service at 3% over 20 years. Total capital cost assumed to be $4.3M. Plant replaced for $12.5M in 200
preliminary estimate. No escalation.
Addition of new and replacement of existing
Assumes $120 per KW annual expense. Assumes
Assumes diesel fuel cost of $1.16/gallon in
base load diesel generators at $800 per KW.
100% of existing capacity to be available for service.
1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(10)-Discounted to January 1982 at 3% per year.
• • • ..
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO A BASE CASE -DIESEL GENERATION
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel Annual Annual
Required Required Required Cost O&M Cost Cost O&M Cost Cost! Cost Cost
Year (MWh) (1) (KW) (2) (MWh) (3) (SOOO) (4) (SOOO)(5) (SOOO)(6) (SOOO) (7) (SOOO)(8) (SOOO) (9) (SOOO) (10)
------------------------------ ----------------------------------------------------------------------
1982 11 ,610 0 11 ,610 0 0 0 901 1,122 2,023 1,993
1983 12,084 0 12,084 0 0 0 845 1,198 2,043 1,954
1984 12,305 0 12,305 0 0 0 842 1,252 2,094 1,945
1985 12,636 0 12,636 0 0 0 839 1,319 2,158 1,946
1986 12,971 0 12,971 0 0 0 828 1,389 2,217 1,941
1987 13,304 0 13 ,304 0 0 0 821 1,462 2,283 1,940
1988 13,631 0 13 ,631 0 0 0 816 1,537 2,353 1,942
1989 14 ,009 0 14,009 0 0 0 812 1,621 2,433 1,949
1990 14,358 0 14,358 0 0 0 810 1,704 2,514 1,955
1991 14,713 0 14,713 0 0 0 804 1,792 2,596 1,960
1992 15,109 0 15,109 0 0 0 798 1,888 2,686 1,969
1993 15,519 0 15,519 0 0 III 792 1,990 2,893 2,059
1994 15,994 0 15,994 0 0 111 786 2,104 3,001 2,074
1995 16,337 0 16,337 0 0 111 782 2,205 3,098 2,079
1996 16,644 0 16,644 0 0 111 776 2,305 3,192 2,079
1997 16,993 0 16,993 0 0 111 771 2,414 3,296 2,085
1998 17 ,353 0 17,353 0 0 245 766 2,529 3,540 2,174
1999 17,723 0 17,723 0 0 245 761 2,650 3,656 2,179
2000 18,060 0 18,060 0 0 245 756 2,771 3,772 2,183
2001 18,435 0 18,435 0 0 245 751 2,902 3,898 2,190
2002-2036 ( Assuming no additional growth or escalation 35 Years Cumulative 47,064
Cumulative Present Worth
of Project Annual Costs 87,660
----------
(1)-Scenario A loads less 2900 MWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
(2)-Based on existing capacity of 7510 KW for both systems.
(3)-
(4)-
(5)-
(6)-Replacement of existing base load diesel generators. Assumes capital cost of S800/KW.
(7)-Assumes $120 per KW-YR less net credit for waste heat recovery.
~~l: Assumes diesel fuel cost of Sl.16/ga11on in 1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(10)-Discounted to January 1982 at 3% per year.
•
• • ..
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO A WEST CREEK PROJECT
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel Annual Annual
Required Required Required Cost O&M Cost Cost O&M Cost Cost Cost Cost
Year (MWh) (1) (KW) (2) (MWh) (3) ($000) (4) ($000)(5) ($000)(6) ($000) (7) ($000) (8) ($000)(9) ($000) (10)
----------------------------------------------------------------------------------------------------
1982 11 ,610 0 11 ,610 0 0 0 901 1,122 2,023 1,993
1983 12,084 0 12,084 0 0 0 901 1,198 2,099 2,008
1984 12,305 0 12,305 0 0 0 901 1,252 2,153 2,000
1985 12,636 0 12,636 0 0 0 901 1,319 2,220 2,002
1986 12,971 0 12,971 0 0 0 901 1,389 2,290 2,005
1987 13 ,304 0 0 2,173 727 0 459 0 3,359 2,855
1988 13 ,631 0 0 2,173 727 0 459 0 3,359 2,772
1989 14,009 0 0 2,173 727 0 459 0 3,359 2,691
1990 14,358 0 0 2,173 727 0 459 0 3,359 2,613
1991 14,713 0 0 2,173 727 0 459 0 3,359 2,537
1992 15,109 0 0 2,173 727 0 459 0 3,359 2,463
1993 15,519 0 0 2,173 727 0 459 0 3,359 2,391
1994 15,994 0 0 2,173 727 0 459 0 3,359 2,321
1995 16,337 0 0 2,173 727 0 459 0 3,359 2,254
1996 16,644 0 0 2,173 727 0 459 0 3,359 2,188
1997 16,993 0 0 2,173 727 0 459 0 3,359 2,124
1998 17,353 0 0 2,173 727 0 459 0 3,359 2,062
1999 17,723 0 0 2,173 727 0 459 0 3,359 2,002
2000 18,060 0 0 2,173 727 0 459 0 3,359 1,944
2001 18,435 0 0 2,173 727 0 459 0 3,359 1,887
2002-2036 ( Assuming no additional growth or escalation 35 Years Cumulative 40,556
Cumulative Present Worth
of Project Annual Costs 85,668
----------
(1)-Scenario A loads less 2900 MWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
(2)-Based on existing capacity of 7510 KW for both systems.
(3)-Assumes 23,630 MWh annually of West Creek generation to begin in 1987 plus 40% of load requirements above 23,630 MWh.
(4)-Assumed level debt service at 3% over 50 years. Total investment cost assumed to be $55,908,000 including IDC at 3%.
(5)-Based on 1.3% of total investment cost.
(6)-
(7
8
l-_ Assumes $120 per KW annual expense. Approximately 50% of existing capacity is mothballed at 2% base cost in 1987.
( Assumes diesel fuel cost of $1.16/ga11on in 1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(9)-
(10)-Discounted to January 1982 at 3% per year.
<::
H
I
0\
.. .. • .. ~ HAINES-SKAGWAY RtGION • ~
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO A : WOOD WASTE GENERATOR
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel Annual Annual
Required Required Required Cost O&M Cost Cost O&M Cost Cost Cost Cost
Year (MWh) (1) (KW) (2) (MWh) (3) ($000) (4) ($000) (5) ($000) (6) ($000)(7) ($000) (8) ($000) (9) ($000) (10)
----------------------------------------------------------------------------------------------------
1982 11 ,610 0 11 ,610 0 0 0 901 1,122 2,023 1,993
1983 12,084 0 5,518 289 509 0 901 547 2,246 2,149
1984 12,305 0 5,620 289 509 0 901 572 2,271 2,109
1985 12,636 0 5,809 289 509 0 901 606 2,305 2,078
1986 12,971 0 5,985 289 509 0 901 641 2,340 2,049
1987 13,304 0 6,168 289 509 0 901 678 2,377 2,020
1988 13 ,631 0 6,327 289 509 0 901 713 2,412 1,990
1989 14,009 0 6,549 289 509 0 901 758 2,457 1,968
1990 14 ,358 0 6,717 289 509 0 901 797 2,496 1,941
1991 14,713 0 6,913 289 509 0 901 842 2,541 1,919
1992 15,109 0 7,119 289 509 0 901 890 2,589 1,898
1993 15,519 0 7,335 289 509 0 901 940 2,639 1,878
1994 15,994 0 7,560 289 509 0 901 994 2,693 1,861
1995 16,337 0 7,744 289 509 0 901 1,045 2,744 1,841
1996 16,644 0 7,912 289 509 0 901 1,096 2,795 1,821
1997 16,993 0 8,095 289 509 0 901 1,150 2,849 1,802
1998 17,353 0 8,286 289 509 134 901 1,208 3,041 1,867
1999 17,723 0 8,482 289 509 134 901 1,268 3,101 1,849
2000 18,060 0 8,670 289 509 134 901 1,330 3,163 1,831
2001 18,435 0 8,867 289 509 134 901 1,396 3,229 1,814
2002 18,435 0 8,867 289 509 134 901 1,396 3,229 1,762
2003 18,435 0 8,867 840 509 134 901 1,396 3,780 2,002
2004-2036 ( Assuming no additional growth or escalation 33 Years Cumulative 41 ,575
(1)-
(2)-
(3)-
(4)-
(5)-
(6)-
(7)-
(8)-
(9)-
Cumulative Present Worth
of Project Annual Costs 84,017
----------
Scenario A loads less 2900 MWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
Based on existing capacity of 7510 KW for both systems.
Assumes Wood Waste Generator will supply 85% of Haines total load up to 20,000 MWh annually less mill load.
Assumed level debt service at 3% over 20 years. Total capital cost assumed to be $4.3M. Plant replaced for $12.5M in 200
Preliminary estimate. No escalation.
Replacement of existing base load diesel generators in Skagway at $800 per KW.
Assumes $120 per KW annual expense. Assumes 100% of existing capacity to be available for service.
Assumes diesel fuel cost of $1.16/gal10n in 1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(10)-Discounted to January 1982 at 3% per year.
• .. ...
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO C BASE CASE -DIESEL GENERATION
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel Annual Annual
Required Required Required Cost O&M Cost Cost O&M Cost Cost Cost Cost
Year (MWh) (1) (KW) (2) (MWh) (3) ($000)(4) (SOOO) (5) (SOOO) (6) (SOOO) (7) (SOOO) (8) (SOOO) (9) (SOOO) (10)
---------------------------------------- ------------------------------------------------------------
1982 12,338 0 12,338 0 0 0 901 1,193 2,094 2,063
1983 14,409 0 14,409 0 0 0 790 1,429 2,219 2,123
1984 16,233 0 16,233 0 0 0 778 1,652 2,430 2,257
1985 17,410 0 17,410 0 0 0 770 1,818 2,588 2,334
1986 20,743 0 20,743 0 0 0 746 2,222 2,968 2,598
1987 24,277 1,250 24,277 0 0 67 872 2,668 3,607 3,066
1988 25,740 0 25,740 0 0 67 861 2,902 3,830 3,161
1989 27,187 0 27,187 0 0 67 851 3,145 4,063 3,255
1990 26,000 0 26,000 0 0 67 860 3,086 4,013 3,121
1991 29,800 0 29,800 0 0 67 833 3,629 4,529 3,420
1992 31,440 1,250 31,440 0 0 134 971 3,929 5,034 3,691
1993 33,246 0 33,246 0 0 245 958 4,262 5,465 3,890
1994 34,960 0 34,960 0 0 245 947 4,599 5,791 4,002
1995 36,556 1,250 36,556 0 0 312 1,085 4,933 6,330 4,247
1996 38,395 0 38,395 0 0 312 1,073 5,316 6,701 4,365
1997 40,154 0 40,154 0 0 312 1,060 5,704 7,076 4,475
1998 41 ,991 1,250 41,991 0 0 512 1,147 6,121 7,780 4,777
1999 43,970 0 43,970 0 0 512 1,184 6,576 8,272 4,931
2000 45,934 0 45,934 0 0 512 1,170 7,048 8,730 5,053
2001 47,938 0 47,938 0 0 512 1,156 7,547 9,215 5,178
2002-2036 ( Assuming no additional growth or escalation 35 Years Cumulative 111,261
Cumulative Present Worth
of Project Annual Costs 183,268
----------
(1)-Scenario C loads less 2900 MWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
(2)-Based on existing capacity of 7510 KW for both systems.
(3)-
(4)-
(5) -
(6)-Replacement of existing and addition of new base load diesel generators. Assumes capital cost of S800/KW.
(7)-Assumes S120 per KW-YR less net credit for waste heat recovery.
(8)-Assumes diesel fuel cost of Sl.16/gallon in 1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(9)-
(10)-Discounted to January 1982 at 3% per year.
• • •
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO C : WEST CREEK PROJECT
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel Annual Annual
Required Required Required Cost O&M Cost Cost O&M Cost Cost Cost Cost
Year (MWh) (l) (KW) (2) (MWh){3) ($OOO) (4) ($000){5) ($OOO) (6) ($OOO) (7) ($OOO) (8) ($OOO) (9) ($OOO) (10)
------------------------------ -------------------- --------------------------------------------------
1982 12,338 0 12,338 0 0 0 901 1,193 2,094 2,063
1983 14 ,409 0 14,409 0 0 0 901 1,429 2,330 2,229
1984 16,233 0 16,233 0 0 0 901 1,652 2,553 2,371
1985 17,410 0 17,410 0 0 0 901 1,818 2,719 2,452
1986 20,743 0 20,743 0 0 0 901 2,222 3,123 2,734
1987 24,277 0 0 2,481 829 0 459 0 3,769 3,203
1988 25,740 0 0 2,481 829 0 459 0 3,769 3,110
1989 27,187 0 0 2,481 829 0 459 0 3,769 3,020
1990 26,000 0 0 2,481 829 0 459 0 3,769 2,932
1991 29,800 0 0 2,481 829 0 459 0 3,769 2,846
1992 31,440 0 0 2,481 829 0 459 0 3,769 2,763
1993 33,246 0 0 2,481 829 0 459 0 3,769 2,683
1994 34,960 0 0 2,481 829 0 459 0 3,769 2,605
1995 36,556 0 0 2,481 829 0 459 0 3,769 2,529
1996 38,395 0 0 2,481 829 0 459 0 3,769 2,455
1997 40,154 0 0 2,481 829 0 459 0 3,769 2,384
1998 41,991 0 1,293 2,481 829 0 459 188 3,957 2,430
1999 43,970 0 2,777 2,481 829 0 459 415 4,184 2,494
2000 45,934 0 4,250 2,481 829 0 459 652 4,421 2,559
2001 47,938 0 5,753 2,481 829 0 459 906 4,675 2,627
2002-2036 ( Assuming no additional growth or escalation 35 Years Cumulative 56,446
Cumulative Present Worth
of Project Annual Costs 108,935
----------
(1)-Scenario C loads less 2900 MWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
(2)-Based on existing capacity of 7510 KW for both systems.
(3)-Assumes 39,800 MWh annually of West Creek generation to begin in 1987 plus 25% of load requirements above 39,800 MWh.
(4)-Assumed level debt service at 3% over 50 years. Total investment cost assumed to be $63,781,000 including IDC at 3%.
(5)-Based on 1.3% of total investment cost.
(6)-
(7)-Assumes $120 per KW annual expense. Approximately 50% of existing capacity is mothballed at 2% base cost in 1987.
(8)-Assumes diesel fuel cost of $1.16/ga110n in 1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(9)-
(10)-Discounted to January 1982 at 3% per year.
• • • • • ....
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
ECONOMIC ANALYSIS
SCENARIO C : WOOD WASTE GENERATOR
Total Present
Annual New Diesel Diesel Altern. New Diesel Diesel Total Worth of
Generation Capacity Generation Capital Altern. Capital Diesel Fuel Annual Annual
Required Required Required Cost O&M Cost Cost O&M Cost Cost Cost Cost
Year (MWh) (1) (KW) (2) (MWh) (3) ($000)(4) ($000) (5) ($000)(6) ($000) (7) ($000) (8) ($000) (9) ($000) (10)
----------------------------------------------------------------------------------------------------
1982 12,338 0 12,338 0 0 0 901 1,193 2,094 2,063
1983 14,409 0 6,304 289 509 0 901 625 2,324 2,223
1984 16,233 0 7,525 289 509 0 901 766 2,465 2,289
1985 17,410 0 8,054 289 509 0 901 841 2,540 2,290
1986 20,743 0 10,448 289 509 0 901 1,119 2,818 2,467
1987 24,277 600 12,388 289 509 32 973 1,361 3,164 2,689
1988 25,740 0 12,959 289 509 32 973 1,461 3,264 2,693
1989 27,187 0 13,654 289 509 32 973 1,580 3,383 2,710
1990 26,000 0 12,467 289 509 32 973 1,480 3,283 2,554
1991 29,800 0 16,267 289 509 32 973 1,981 3,784 2,858
1992 31,440 600 17,907 289 509 64 1,045 2,238 4,145 3,039
1993 33,246 0 19,713 289 509 175 1,045 2,527 4,545 3,235
1994 34,960 0 21,427 289 509 175 1,045 2,818 4,836 3,342
1995 36,556 1,250 23,023 289 509 242 1,195 3,107 5,342 3,584
1996 38,395 0 24,862 289 509 242 1,195 3,443 5,678 3,699
1997 40,154 0 26,621 289 509 242 1,195 3,782 6,017 3,805
1998 41 ,991 1,250 28,458 289 509 444 1,345 4,148 6,735 4,135
1999 43,970 0 30,437 289 509 444 1,345 4,552 7,139 4,256
2000 45,934 0 32,401 289 509 444 1,345 4,972 7,559 4,375
2001 47,938 0 34,405 289 509 444 1,345 5,416 8,003 4,497
2002 47,938 0 34,405 289 509 444 1,345 5,416 8,003 4,366
2003 47,938 0 34,405 840 509 444 1,345 5,416 8,554 4,531
2004-2036 ( Assuming no additional growth or escalation 33 Years Cumulative 94,083
(1)-
(2)-
(3)-
(4)-
(5)-
(6) -
(7)-
(8)-
(9)-
Cumulative Present Worth
of Project Annual Costs 165,783
----------
Scenario C loads less 2900 MWh annually of existing hydro generation. Includes 10% of Schnabel load. Includes WP&Y RR.
Based on existing capacity of 7510 KW for both systems.
Assumes Wood Waste Generator will supply 85% of Haines total load up to 20,000 MWh annually less mill load.
Assumed level debt service at 3% over 20 years. Total capital cost assumed to be $4.3M. Plant replaced for $12.5M in 200
Preliminary estimate. No escalation.
Addition of new and replacement of existing
Assumes $120 per KW annual expense. Assumes
Assumes diesel fuel cost of $1.16/gallon in
base load diesel at $800 per KW.
100% of existing capacity to be available for service.
1982 escalated at 2.6% per year. Fuel usage assumed to be 12 gallons/KWh.
(10)-Discounted to January 1982 at 3% per year.
•
[
..
•
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
SUMMARY OF ECONOMIC ANALYSIS
TABLE VI-11
Total Present Worth Cost
Plan
Base Case ••••••••••••
West Creek
Wood Waste -Case A(1)
Wood Waste -Case B(2)
Scenario A
($1,000)
87,660
85,668
84,017
Scenario B
($1,000)
111,337
88,217
96,110
119,929
Scenario C
($1,000)
183,268
108,935
165,783
,
1987
1989
1991
1993
1995
..
"
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
COMPARISON OF WEST CREEK PLAN
ON-LINE DATES
TABLE VI-12
Total Present Worth Cost
On-Line Date Scenario A Scenario B Scenario C
($1,000) ($1,000) ($1,000)
· ................ 85,668 88,217 108,935 · ................ 84,061 87,126 109,633 · ................ 82,804 86,438 110,138 · ................ 81,883 86,201 113,112 · ................ 81,306 86,464 116,285
r
•
"
1. CONCLUSIONS
SECTION VII
GENERATION PLAN
CONCLUSIONS AND RECOMMENDATIONS
Based on the results of these feasibility studies, the following
conclusions have been reached:
a. The most economical means of meeting future load and energy re-
quirements in the Haines-Skagway Region is the West Creek Hydroelectric Proj-
ect with a transmission intertie between Haines and Skagway.
b. The wood waste generator being installed at the Schnabel Lumber
Company Mill in Haines will provide economical power to Haines for the next
five years, but the cost of power after that period depends on the availabil-
ity and cost of wood waste.
c. The West Creek Project sized to fit the forecasted 1996 loads will
include a 117-foot-high concrete-faced rockfill dam, a tunnel and penstock, a
powerhouse with an installed capacity of 6,000 kW, and a transmission line to
Haines and Skagway. Roller compacted concrete could provide a more economical
dam if current bids are born out.
d. The Project has minimal adverse environmental impacts. However,
the powerhouse is located within the boundary of the Klondike Gold Rush
National Historical Park. A change in the boundary or in the authorizing leg-
islation will be required before the Project can be licensed.
e. The load forecasts included in this report be reviewed regularly
with respect to changing economic conditions. Where developments and trends
have diverged from those included in these forecasts, we suggest that they be
updated and the forecasts changed accordingly. Care should always be taken to
avoid overresponding in making forecast judgments to what could be short-term
business cycle fluctuations and resulting temporary increases or decreases in
growth.
f. The Project could be sized to meet larger load and energy require-
ments if growth in the two communities is greater than that forecasted for
planning.
VII-2
2. RECOMMENDATIONS
Therefore, it is recommended that:
a. The Alaska Power Authority proceed with development of the West
Creek Project.
b. Steps be taken to change the boundary of the Klondike Gold Rush 4
National Historical Park so that the powerhouse is outside the park.
c. A license application be prepared and filed with the Federal Energy
Regulatory Commission.
d. Field investigations for design be started in the summer of 1982.
f
PART B: FEASIBILITY INVESTIGATIONS
OF WEST CREEK HYDROELECTRIC PROJECT
•
,.
..
SECTION VIII
EXISTING SITE CONDITIONS
1. GENERAL
The proposed West Creek Project site is located about 6 miles
northwest of Skagway. An all-weather dirt road about 10 miles long provides
access from Skagway to the lower reaches of West Creek. From there a logging
road extends 2.2 miles into the middle section of the West Creek basin.
2. TOPOGRAPHY
West Creek, a 9.0-mile-long stream, originates in an arm of the
Chilkoot Glacier at about the 1600-foot elevation. For a little more than a
mile it passes down a steep valley surrounded by rock and upland shrub. The
stream then skirts another arm of the glacier and enters a broad valley
approximately 0.5 mile wide with a moderate gradient through which it flows
for about 5 miles. The proposed dam site is located at the lower end of the
valley at approximately River Mile (R.M.) 2.8 (measured from the confluence of
West Creek with the Taiya River). The stream gradient sharply increases below
the dam site as the creek passes through an upper gorge approximately 0.3 mile
long. For the next mile the gradient moderates before the stream enters a
steep lower gorge that extends for 0.6 mile. The remaining mile of the
stream, to its confluence with the Taiya River, is a low-gradient braided
channel. The Taiya River flows south through an alluvial floodplain 3/4 mile
wide for about 2.5 miles to the head of the Taiya Inlet. The proposed power-
house site lies at the west edge of this floodplain about 1,200 feet south of
West Creek.
3. GEOLOGY
The Project area is underlain by granitic crystalline rocks, pri-
marily granodiorite. The rocks are part of a large multi-stage batholith
known as the Coast Range Plutonic Complex. Bedrock is exposed intermittently
throughout the Project area. The bedrock is generally a slightly weathered to
unweathered, hard granodiorite with widely spaced fractures. Tectonic defor-
mation has produced two distinct structural trends, northwest-southeast and
northeast-southwest in the form of joints and/or shear zones. One of the
trends appears to be related to surface lineaments identified in the field and
aerial photographs. During the Pleistocene Epoch, the area was subjected to
continental glaciation and since that period to alpine glaciation. The gla-
ciers created U-shaped valleys and removed pre-glacial soils and incompetent
rock by scouring and plucking action. In the Project area, the most signifi-
cant evidence of glaciation is the overdeepening of the upper West Creek
drainage, the area upstream of the proposed dam site.
VIII-2
In the dam site area, rock is at or near the ground surface. A
thin mantle of overburden ranging up to approximately 10 feet in thickness
covers the abutment areas. Recent alluvium underlies the active stream chan-1
nel and is estimated to be about 20 feet thick.
At the powerhouse site the bedrock surface slopes downward beneath
the Taiya River floodplain at approximately the same slope as the valley
wall. The floodplain consists of sand, gravel, and interbedded sand and
sil t. Immediately to the south of West Creek is an area of overburden con-
sisting of cobbles and boulders with a sand and silt matrix. The deposit ex-•
tends up to about EI 300 feet and south about 600 feet.
The Project site geology is discussed in detail in the report pre-
pared by Converse titled "Phase II Geotechnical Investigations, West Creek
Hydroelectric Project, Haines-Skagway Region Studies," which is included as
Appendix B.
4. ENVIRONMENTAL SETTING
The Project area is generally coniferous forest with riparian shrub
and marsh and an area of deciduous woodland near the powerhouse. The West
Creek Valley is populated by black bear, mountain goat, various furbearers and
several types of voles and mice. There have been occasional sightings of wol-
verine and coyote. Bird species common to the valley include grouse, bald
eagle and other raptors, shore birds, waterfowl, and passerines. No Feder-
ally-listed endangered or threatened species reside in the Project area.
West Creek has few fisheries resources. The steep gradient and
high velocities in the lower and upper gorges make upstream fish passage ex-
tremely difficult if not impossible. The Creek is not used for fishing by
residents in Dyea or Skagway and fish sampling attempts yielded only a low
density, slow growing population of Dolly Varden char in two small tributaries
of the middle basin. Dolly Varden were also observed in a tributary near the
mouth of the Creek. There is also the possibility that some fall chum or coho
use the tributary or the lower reach of West Creek. Eulachon are known to
spawn in the lower Taiya River and the lower sandy reaches of West Creek.
The historic townsite of Dyea lies to the south of West Creek near
the mouth of the Taiya River (Fig. 16). The Chilkoot Unit of the Klondike
Gold Rush National Historical Park is a corridor approximately one mile wide
extends from the head of Taiya Inlet about 17 miles up the Taiya River to
Chilkoot Pass, and encompasses approximately the lower mile of West Creek.
Dyea Road which begins at the City of Skagway approximately six miles
(10 miles by road) southeast of West Creek, progresses up the Taiya Valley,
crosses the Taiya River, and terminates just north of West Creek. The his-
toric Chilkoot Trail extended north from Dyea along the west side of the Taiya
River, crossed the river below West Creek, and continued up the river to Chil-
koot Pass. A modern extension of the trail connects with Dyea Road on the
east side of the river.
•
•
..
•
..
VIII-3
5. LAND OWNERSHIP AND USE
Most of the land at or near the Project site is government-owned.
In the West Creek Valley where the reservoir is to be located, all of the land
is State selected land which is in the process of transfer from Federal con-
trol. Some of the State land at the reservoir site has been selected by Skag-
way as part of its allotment lands. (See Fig. 18.)
In the Taiya River Valley almost all of the valley floor lies with-
in the boundary of Klondike Gold Rush National Historical Park. Land within
the boundary is owned by the National Park Service, the State of Alaska, and
private individuals. There are several year-round residents of Dyea.
The entire Taiya Valley and West Creek Valley lie within the corpo-
rate limits of the City of Skagway. Management responsibilities for govern-
ment-owned lands are as follows: the Alaska Department of Natural Resources
for State select lands, the National Park Service for parklands, and the City
of Skagway for allotment lands. The Park Service and the Department of
Natural Resources have signed a cooperative agreement concerning management
policies of State select lands within the Park boundary.
Most of the land remains in a natural or currently undeveloped
state consisting of brush, second growth forest or higher elevation meadow
land. The private land area located at the confluence of West Creek and the
Taiya River has a mixture of brush and cleared pastureland. Residential
buildings, barns and sheds have been constructed by the dozen or so families
owning land in this area •
,
•
a
•
..
SECTION IX
FIELD INVESTIGATIONS
1 • SITE RECONNAISSANCE
Personnel from Beck and Converse made a site reconnaissance of the
West Creek Project area in July 1981. During this reconnaissance, the major
Project features were located based on the initial map studies and observed
field conditions. Subsequent investigations changed some of the locations and
these were reviewed in a second reconnaissance in August 1981.
Personnel from Beck made
mission corridors in August 1981.
the costs of lines in each corridor
potential construction difficulties
route.
a reconnaissance of the alternative trans-
This allowed for comparative estimates of
to take into account field observations of
and environmental impacts of each proposed
2. LAND SURVEYS AND TOPOGRAPHIC MAPPING
Land surveys, aerial photography, topographic mapping and fa tho-
metric surveys were performed by Tryck, Nyman & Hayes and Air Photo Tech,
Inc., in the summer and fall of 1981. Horizontal control was established from
existing U.S. Coast and Geodetic Survey (USC&GS) monuments in the region.
Vertical control was established from the USGS datum. Permanent monuments
were set in the vicinity of the proposed dam axis. Aerial photographs of the
entire West Creek drainage basin were taken and 1 "=400' scale topographic maps
were made of the area. Topographic maps at a scale of 1 "=200' were also made
of the dam site and powerhouse site. Fathometric profiling was performed at
five cross-sections along the proposed submarine cable route in the Taiya In-
let and at two cross-sections at the head of the Chilkoot Inlet. A total of
about ten miles of fathometric survey was performed.
3. ENVIRONMENTAL STUDIES
Beck performed field investigations addressing recreation re-
sources, aesthetics, socioeconomic conditions, and land use. Under subcon-
tract to Beck, Environaid, Inc. of Juneau conducted field studies of fisher-
ies, wildlife, historical and archaeological resources. All investigations
included field reconnaissance and interviews with knowledgeable agencies and
local personnel. The studies were completed between July and early November
1981, except that water temperature monitoring by Environaid will continue for
one full year until the summer of 1982. Appendix C contains a detailed report
of the Environaid studies. The results of all studies are described in Sec-
tion XIV, Effect on Environment of the Selected Project Arrangement.
IX-2
4. GEOTECHNICAL INVESTIGATIONS
Geotechnical investigations performed by Converse involved geologic
mapping, diamond core drilling, water pressure testing, seismic refraction
surveys, and materials testing. The initial site reconnaissance was conducted
with Beck personnel in July 1981. Mapping and seismic refraction surveys were
conducted in August, September, October and December 1981.
Converse contracted with Wyman Construction Company of Ketchikan to
take NX core borings at the dam site, spillway site, surge tank site and the
original powerhouse site to determine the depth of overburden in these areas
and to give a general indication of the quality of bedrock for structure foun-
dations. This work was completed between September 23 and October 22, 1981.
Converse contracted with Alaskan Enterprises of Juneau to take core borings at
the alternative powerhouse site 1,200 feet south of West Creek. This work was
completed December 2 through 12, 1981. A total of 12 holes with an aggregate
of 1,647.3 lineal feet were drilled. Six borings, three on each abutment,
were made at the dam site ranging in depth from 75.2 to 201.5 feet. One bor-
ing of 100.5 feet in depth was made at the left abutment spillway site. At
the surge shaft site, one boring 502.2 feet deep was made. Four borings, two
at each of the alternative powerhouse sites, were made with depths ranging
from 50.5 to 141.4 feet. The six drill holes in the dam abutments, the drill
hole in the spillway area and the drill hole at the surge shaft were water
pressure tested.
Preliminary geologic mapping was performed at the dam, spillway,
powerhouse and along the power conduit alignment.
The geophysical surveys consisted of seismic refraction profiling
to determine the depth of subsurface layers above bedrock. Of the 5,750 lin-
eal feet of seismic refraction profiling, 2,450 feet was completed in the left
and right abutment areas, 275 feet in the spillway area and 3,025 feet at the
two alternative powerhouse sites.
Potential sand and gravel borrow areas were sampled and materials
tested for their suitability as fill and concrete aggregate.
Detailed results of the geotechnical investigations conducted for
the Project are included in the report prepared by Converse attached as Appen-
dix B.
1
..
..
,
..
•
...
..
SECTION X
HYDROLOGY
1 • GENERAL
Hydrologic investigations of the West Creek Project are based on
the 15 years of streamflows recorded at the West Creek gage near the mouth of
the Creek. Analysis of these together with climatological records at Haines
and Skagway resulted in the development of basin yield estimates, flood fre-
quency and the Probable Maximum Flood (PMF).
2. RUNOFF AND ANNUAL BASIN YIELD
a. Streamflow Records
The USGS has streamflow records for the West Creek near Skagway
gaging station from May 1962 to September 1977. (7) The gage has since been
discontinued. Its location was latitude 59 0 31'35", longitude 135 0 21'10"
on the right bank of West Creek about 700 feet upstream from a highway bridge,
0.2 mile upstream from the mouth, and 5 miles northwest of Skagway. The
drainage area at the gage was 43.2 sq. mi. Monthly flows at the gaging sta-
tion are shown, as well as average monthly and annual flows in Table VIII-1 •
Flows for 1962 were omitted since only partial data were recorded. The flow
data indicate an average annual flow for West Creek at the gaging station of
334.9 cfs or 242,000 acre-feet. This is an average runoff of 7.75 cfs per
sq. mi. or 105 inches per sq. mi.
b. Precipitation and Runoff Correlations
In order to derive long-term streamflow data that could be used to
conduct power studies, and to estimate flood flows for spillway and diversion
facility sizing, an effort was made to extend the available flow data by sta-
tistical means. This involved correlating recorded West Creek flow data with
other recorded flow data from nearby drainage basins as well as with long-term
precipitation data in the region.(8)
The resulting correlations for monthly and annual streamflow data
were found to be poor. Thus, since 15 years is a reasonable length for the
sizing of a project, it was decided to use the West Creek record as the best
representation of the long-term average flows to be expected. The flow data
indicate an average annual flow for West Creek at the dam site of 288 cfs or
208,500 acre-feet.
X-2
c. Estimated Basin Yield
The average monthly infloli into the West Creek storage dam reser-
voir has been taken as 86% of the gaged flows at the former gage based on a
ratio of the corresponding drainage areas. The drainage area at the dam site
is 37.2 sq. mi. Reservoir inflow data for the years 1963 through 1977 are
shown in Table X-2.
3. FLOOD STUDIES
a. Construction Diversion Flood
Flood frequency studies on West Creek have been conducted using the
Gumbel Extreme-value Type I Distribution as well as the Log Pearson Type III
method applied to the recorded momentary maximum discharges. (9) Peak flows
for each year of record at the West Creek gage are shown in Table X-3. For
the purpose of sizing construction diversion facilities, a peak discharge with
a 10-year recurrence interval was considered to be reasonable for the
2-1/2-year construction period and for the type of construction contemplated.
This resulted in a peak discharge of 5,500 cfs to be used to size construction
diversion facilities. It is possible that a larger flood might occur during
the construction period which could overtop the upstream cofferdam and cause
temporary flooding of the work area. Should this occur, the damage to the
work area and/or delay in construction is a risk that must be taken in Project
development.
b. Probable Maximum Flood
(1) Unitgraph Development(10)
Available precipitation and streamflow records were reviewed and a
unitgraph was developed from USGS bi-hourly flood hydrograph data for a repre-
sentative high peak at the West Creek gage. The recorded floods persisted for
several days and were clearly the result of storms lasting several hours or
days. The lack of concurrent hourly precipitation records at stations in the
vicinity of the Project made it impossible to determine the effective duration
of the precipitation necessary to specify the unit hydrograph. A synthetic
unit hydrograph derived using U.S. Bureau of Reclamation methodology was found
to have a significantly shorter time to peak then the unit hydrograph derived
from USGS records. Given the uncertainty in the unitgraph derived from USGS
records caused by the lack of concurrent precipitation records, the more con-
servative synthetic unitgraph was used to derive the PMF. First, a probable
value for time of concentration (Tc) was arrived at considering the high per-
centage of glaciers in the West Creek drainage area. Then a simple triangular
unit hydrograph was made based on time to peak (Tp), peak flow (Qp), and time
base (Tb) values. A time of concentration (Tc) of 1.8 hours was used to cal-
culate the values of Tp, Qp, and Tb. (10) From this a curvilinear graph was
constructed from values of Qp and Tp by using ratios from a table developed by
the U. S. Soil Conservation Service reflecting analyses of many uni tgraphs.
•
,
•
..
X-3
The reservoir, with normal maximum El 705, will have a surface area of about
one square mile which is 2.6% of the total drainage basin area. To properly
evaluate inflow from storm runoff, rain falling directly on the reservoir area
was considered to have a zero time of concentration.
The unitgraph developed has a precipitation duration of 30 minutes
and a peak of 13,835 cfs. The unitgraph is shown in Fig. 3.
(2) Probable Maximum Precipitation
Review was made of available precipitation data for Haines and
Skagway. It appeared reasonable that the spillway design storm would occur in
the late summer or early fall. This would produce a flood with a higher peak
inflow than a flood which might occur during the spring snowmelt season, al-
though a spring flood would have a much longer duration and volume. On this
basis the PMP design storm was assumed to occur in the fall (October) and a
24-hour duration was selected.
Generalized storm isohyets have been developed by the National
Weather Service which facilitates determination of the characteristics of
large storms for an area. For the Project the basis used for determining the
Probable Maximum Precipitation (PMP) was the U.S. Weather Bureau (now the
National Weather Service) Technical Paper No. 47 (TP-47). (11) For the Proj-
ect area, TP-47 shows the probable maximum 24-hour point precipitation to be
22.5 inches for the month of October. Since this 22.5-inch rainfall value
applies to a small drainage area (less than 10 square miles) an adjustment
factor of 0.96 could be applied to reflect the larger drainage basin of the
West Creek Reservoir. It was decided, however, that a small change in PMP
values would be relatively insignificant considering the assumptions made to
arrive at values for excess precipitation. Therefore, the value of
22.5 inches for PMP was maintained and was considered a conservative value.
A depth duration curve was developed based on estimates of maximum
1-hour, 2-hour, 3-hour, 6-hour, 9-hour, 12-hour, 18-hour, and 24-hour area
precipitation amounts and this curve was then used to obtain 3D-minute incre-
ments of precipitation. These increments were rearranged in a bell-shaped
distribution to produce the 24-hour PMP •
(3) Snowmelt
Considering the range of temperatures that can be expected for the
month of October, it was considered possible to have a snowpack condition
antecedent to the PMP, at least in the higher elevations of the basin which
would contribute to the runoff. The combination of an October PMP together
with some snowmelt runoff was considered appropriate and reasonable in formu-
lating the spillway design flood.
For calculating snowmelt a normal maximum October sea level temper-
ature of 68 0 F was assumed to accompany the PMP storm and this temperature
was then adjusted for elevation by assuming a -3 0 F change in temperature per
X-4
1000 feet of elevation change above sea level. It is generally accepted that
fresh fallen snow has about a 10% density factor. Based on the resulting sat-
urated air temperatures, and a conservative value of 19 inches of fallen snow
during the month of October, it was estimated that about 2.0 inches of snow-
mel t runoff could be expected during the PMP storm. The snowmelt runoff was
assumed to correspond to the distribution of the PMP with the major amount of
snowmelt occurring in the first half of the storm.
For calculating the net excess precipitation, 2.76 inches was
assumed to be lost by infiltration during the first 5 hours of the storm and
0.1 inch per hour thereafter for a total of 4.66 inches of losses. The net
excess runoff considering precipitation, snowmelt and infiltration totalled
19.84 inches in 24 hours. The PMP, snowmelt and excess runoff values are
shown in Table X-4.
(4) Probable Maximum Flood
The Probable Maximum Flood is the flood resulting from the occur-
rence of the PMP in combination with snowmelt as described above. The PMF,
based on 22.5 inches of rain and 2.0 inches of snowmelt, has a peak inflow of
59,700 cfs and a volume of 118,400 acre-feet.
4. RESERVOIR SEDIMENTATION
Sediment yield from West Creek was based upon suspended sediment
measurements made by the USGS between the years 1963 through 1977. Using
these measurements a suspended sediment rating curve was developed and used
with the flow duration curve to estimate average annual suspended sediment
quantities. (12) For an assumed sediment density of 70 lbs/ft3 and a bed
load factor of 1.25, the annual sediment yield was estimated to be 10 acre-
feet. On this basis, the sediment yield to the reservoir for a 1 DO-year
period would be 1,000 acre-feet.
The 100-year sediment accumulation was distributed in the reservoir
based upon the Empirical Area-Reduction Method for a Type II (floodplain-foot-
hill) reservoir. (10) At the dam, the 100-year sediment level was calculated
to be El 640 which corresponds to a sediment depth of 7.5 feet.
..
..
..
1/ • .. • .. • .. "
TABLE X-I
HAINES-SKAGWAY REGION
FEAS IBlI,ITY STUDY
WEST CREEK PROJECT
MONTHLY AVERAGE DISCHARGE IN CFS
AT WEST CREEK NEAR SKAGWAY
USGS GAGING STATION NO. 15056200
Year Oct. Nov. Dec. Jan. Feb. Har. ~ ~ June ~ ~ ~ Annual
1963 290 197 34.4 8.03 13.6 58.4 86.1 309 473 1171 1316 920 410
1964 281 64.5 65.7 44.4 34.9 26.0 40.9 171 1004 1089 777 358 331
1965 265 92.1 16.0 17.6 17.7 14.8 53.7 207 490 983 937 654 315
1966 360 105 30.2 11.5 13.4 23.6 70.5 164 685 959 844 616 326
1967 271 62.4 1<1.5 8.73 14.8 12.7 18.6 166 878 854 1203 1286 400
1968 191 97.8 42.3 27.0 46.0 72.9 47.1 3B2 641 1041 749 582 328
1969 144 68.3 37.2 20.2 21.0 32.9 63.1 238 798 831 641 444 277
1970 307 221 103 39.0 42.7 39.7 51. 7 223 593 732 801 574 312
1971 317 192 45.6 29.4 22.1 20.6 43.9 143 664 1076 9'12 395 331
1972 115 32.2 31. 7 20.7 13.4 19.3 20.1 189 527 1179 1196 487 322
1973 194 93.8 35.7 9.03 16.9 17.4 59.0 209 462 797 961) 374 272
1974 173 39.9 18.9 9.65 14.1 8.65 20.6 183 481 840 980 862 304
1975 390 264 74.5 40.3 27.0 23.3 54.1 199 549 1163 761 930 375
1976 188 33.0 22.6 24.7 17.6 15.5 58.1 159 528 899 817 843 301
l'l77 327 237 118 78.2 95.9 58.3 107 240 669 ~ .!l!L ~ 419
Avg. 254.2 120 46.0 75.9 27.4 29.6 53.0 212.1 629.5 983.9 953.1 661. 9 334.9
"" • .. ( , "
'I'ABLE )(-2
HAINES-SKAmIAY REGION
FEASIBILI'l'Y STUDY
WEST CREEK PROJECT
AVERAGE MONTHLY DISCHARGE IN CFS
ADJUSTED TO DAM SITE
Year Oct. Nov. Dec. Jar,. Feb. Mar. ~ ~ June ~ ~ Sept. Annual
1963 249 169 30 7 12 50 74 266 407 1,007 1,132 791 352
1964 242 55 57 3B 30 22 35 147 B63 937 66B 30B 2B5
1965 22B 79 14 15 15 13 46 17B 421 B45 B06 562 271
1966 310 90 26 10 12 20 61 141 5B9 B25 726 530 2BO
1967 233 54 12 7 13 11 16 143 755 734 1,035 1,106 344
196B 164 B4 36 23 40 63 41 32'01 551 B95 644 501 2B2
1969 124 59 32 17 IB 2B 54 205 6B6 715 52B 3B2 239
1970 264 190 B9 34 37 34 44 192 S10 630 6B9 494 269
1971 273 165 39 25 19 IB 3B 123 571 925 B53 340 2B5
1972 99 2B 27 IB 12 17 17 163 453 1,014 1,029 419 276
IY73 167 Bl 31 B 15 15 51 IBO 397 6B5 B31 322 234
1974 149 34 16 B 12 7 IB 157 414 722 B43 741 262
1975 335 227 64 35 23 20 47 171 472 1,000 6S4 BOO 322
1976 162 2B 19 21 15 13 50 137 454 773 703 725 259
1977 2Bl 204 101 67 B2 50 92 206 575 9B5 1,130 519 360
Avg. 219 103 40 7.2 24 25 ~6 IB2 541 B46 BIB 569 2BB
TABLE X-3
HAINES-SKAGWAY REGION ,. FEASIBILITY STUDY
WEST CREEK PROJECT ..
PEAK FLOWS AT WEST CREEK GAGE
Year Peak Flow Date
• (crs)
1962 3,760 September 25
2,490 August 23
1963 2,850 August 8
2,500 July 18
1964 1,680 June 9
1965 1,630 August 11
1966 2,760 October 4
1,900 September 26
1967 9,800 September 15
3,200 August 9
1968 2,350 September 28
2,090 September 5
1969 3,190 August 8 .. 2,280 November 1
1970 1,660 September 27
1971 2,130 August 2
1,840 July 16
1972 2,910 August 6
2,290 August 26
1973 2,670 August 12
1974 2,480 September 13
2,430 September 25
1975 3,310 September 13 • 2,440 July 10
1976 3,000 September 27
2,390 October 1
1977 2,760 September 12 .,. 2,400 August 20
TABLE X-4
HAINES-SKAGWAY REGION ,
FEASIBILITY STUDY
WEST CREEK PROJECT
PROBABLE MAX IlJiUH PRECIPITATION AND SNOWMELT
(Inches)
Total
Hours PMP Snowmelt PreciEitation Loss Excess •
0:30 0.10 0.02 0.12 0.12 0.00
1:00 0.20 0.04 0.24 0.24 0.00
1:30 0.20 0.04 0.24 0.24 0.00
2:00 0.20 0.05 0.25 0.25 0.00
2:30 0.20 0.05 0.25 0.25 0.00
3:00 0.30 0.06 0.36 0.36 0.00
3:30 0.30 0.06 0.36 0.36 0.00
4:00 0.30 0.06 0.36 0.32 0.04
4:30 0.30 0.06 0.36 0.32 0.04
5:00 0.35 0.06 0.41 0.30 0.11
5:30 0.35 0.07 0.42 0.05 0.37
6:00 0.40 0.07 0.47 0.05 0.42
6:30 0.40 0.08 0.48 0.05 0.43
7:00 0.40 0.08 0.48 0.05 0.43
7:30 0.45 0.08 0.53 0.05 0.48
8:00 0.45 0.08 0.53 0.05 0.48
8:30 0.45 0.09 0.54 o. as 0.49
9:00 0.45 0.09 0.54 0.05 0.49 .. 9:30 0.50 0.10 0.60 0.05 0.55
10:00 0.60 0.11 0.71 0.05 O.H
10:30 0.65 0.12 0.77 0.05 0.72
11:00 0.70 0.14 0.84 0.05 0.79
11:30 0.80 0.16 0.96 0.05 0.91
12:00 1.15 0.23 1.38 0.05 1.33
12:30 1. 80 0.00 1.80 0.05 1. 75
13:00 1.10 0.00 1.10 0.05 1. 05
13 :30 0.95 0.00 0.95 0.05 0.90
14: 00 0.80 0.00 0.80 0.05 0.75
14:30 0.75 0.00 0.75 O. as 0.70
15:00 0.65 0.00 0.65 0.05 0.60
15:30 0.50 0.00 0.50 0.05 0.45
" 16:00 0.50 0.00 0.50 0.05 0.45
16:30 0.50 0.00 0.50 0.05 0.45
17:00 0.50 0.00 0.50 0.05 0.45
17:30 0.45 0.00 0.45 o. as 0.40
18:00 0.40 0.00 0.40 0.05 0.35
18:30 0.40 0.00 0.40 0.05 0.35 • 19:00 0.40 0.00 0.40 0.05 0.35
19:30 0.30 0.00 0.30 0.05 0.25
20:00 0.30 0.00 0.30 0.05 0.25
20:30 0.30 0.00 0.30 0.05 0.25
21:00 0.30 0.00 0.30 0.05 0.25
21: 30 0.30 0.00 0.30 0.05 0.25
22:00 0.30 0.00 0.30 0.05 0.25
22:30 0.20 0.00 0.20 0.05 0.15
23:00 0.20 0.00 0.20 0.05 0.15
23:30 0.20 0.00 0.20 0.05 0.15
24:00 0.20 0.00 0.20 0.05 0.15
Tot .. 1 22.5 2.00 24.50 4.66 19.84
•
•
SECTION XI
PROJECT OPERATION STUDIES
1 • GENERAL
Studies were performed to determine the reservoir size required to
meet given loads and energy output utilizing a computer model to simulate
monthly reservoir operation. Input data to this study include monthly reser-
voir inflows, system load characteristics, reservoir data, and approximate
turbine, generator, transformer and hydraulic losses. Results of the analysis
are shown in Tables XI-1 through XI-B. These tables contain a summary of
input data as well as output.
2. PROJECT SIZING
For most hydroelectric projects, the sizes of the various features
are optimized to produce a project which makes the best use of the hydrologic,
topographic and geologic conditions of the site. This presupposes that there
is a market for any and all power produced by the project. However, in the
case of the West Creek Project, the output from the Project can be used only
in Haines and Skagway. Thus, the size of the project is limited by the fore-
casted loads and energy requirements rather than site conditions. The fore-
cast of energy and peak load described in Section III developed three Sce-
narios, A, B, and C. Scenario A was a low, base case condition. Scenario B
was a mid-range forecast including the base case plus some more speculative
loads. Scenario C considered the loads and energy requirements which would
resul t if conversion to electricity for heating as well as other loads now
served by other energy sources became common.
For planning purposes, the West Creek Project was sized to meet the
1996 peak load and energy requirements forecasted in Scenario B less the por-
tion of the load which would be met by the existing hydroelectric units in
Skagway and 90% of the Schnabel Mill load which it was assumed would continue
to be met by the mill. The resulting 1996 requirements are 23,630 MWh with a
peak of 5,400 kW for a system load factor of 50%. The installed capacity was
set at 6,000 kW which allows some margin should the system load factor
change. As described herein, the reservoir was sized to meet the 1996 energy
requirements during the driest year of record.
3. INPUT DATA
a. Reservoir Inflows
A summary of the streamflow data adjusted to the dam site is pre-
sented in Table X-2. The streamflows developed were assumed to represent res-
ervoir inflows for the purpose of this study. The reservoir inflows in acre-
feet as input to the operation program are presented in Table XI-2.
XI-2
b. Reservoir Characteristics
Reservoir area-capacity curves as a function of elevation are pre-
sented in Fig. 4. These curves were derived from photogrammetric mapping of
the reservoir compiled in August 1981.
c. Losses
Losses in the system are of two major types, hydraulic losses in
the power conduit and losses in the conversion to mechanical and electrical 'i
energy. The hydraulic losses are included as a head loss and reduce the total
head available for generation. The hydraulic losses are a function of the
flow in the conduit. The conversion losses are included in the efficiency of
the plant. The overall plant efficiency is the combination of the efficien-
cies of the turbines, generators and transformers. For this study, an average
plant efficiency was estimated to be 85%, based on net power head for genera-
tion. Operation study results show net generation at the power plant and do
not include transmission losses.
d. System Load Characteristics
The historical monthly load distribution for the Haines-Skagway
Region is presented in Table III-11. Reservoir operation and power studies
for the Project were performed based on the assumption that future system gen-
erating requirements would follow this monthly load pattern. Firm generation
from the Project was shaped to fit this monthly distribution so that total
Project output would match system requirements. It should be recognized, how-
ever, that a different mode of reservoir operation may be desired in the
future, depending upon future system load requirements.
4. POWER OPERATION STUDIES
a. Method of Project Operation
The reservoir operation was modeled on a monthly basis using the
Corps of Engineers' HEC-5 program. (13) Power plant output was calculated
based on the following formula:
Where: kW =
Q =
h =
e =
kW = Qhe
11.82
power plant output, kilowatts
discharge through generating units, cfs
net head, feet
overall plant efficiency
Using this equation, the model simulated a month-by-month operation
following a rule curve of operation whereby water is withdrawn from storage to
generate required energy each month. When the reservoir is full and there is
•
..
•
XI-3
excess inflow available, water is spilled. This is based on the fact that
there would be no load which could use excess (secondary) energy beyond what
is required. If a market for the secondary energy were found, the spill could
be used to generate up to the capacity of the Project.
For this Project, firm energy is defined to be the 1996 required
energy. The operation studies were used to size the reservoir in order to
meet the required loads during all months of the driest year of record. Sec-
ondary energy is defined to be energy generated in excess of the firm energy.
b. Operation Study Results
For the Scenario B load and energy requirements, the operation
studies showed that a reservoir with a usable storage of 18,130 acre-feet
would be required. This would require a reservoir with a normal maximum level
of EI 705 and a minimum operating level of EI 662. The operation studies also
showed that the reservoir will be drafted an average of only about 7.4 feet,
or to an average reservoir elevation of 697.6. Average gross power head,
based on an average reservoir elevation of 697.6 for the period of study and
tailwater at El 38, is 659.6 feet. Maximum gross head is 667 feet and minimum
gross head is 624 feet.
These results indicate that secondary energy could be generated
during the dry months when the inflows are higher than those occurring in the
driest year of record. This secondary energy would only have an economic val-
ue after 1996 when the load is there. In order to provide a conserva ti ve
analysis, no credit has been taken for secondary energy during the dry months.
The operation studies also show that during months of high flow,
June-October, there is sufficient excess water to generate up to the installed
capacity of the plant. This would be a total energy of 22,000 MWh as compared
with the 9,381 MWh required during those months in the 1996 Scenario B fore-
cast. The only limitation on use of this energy is the availability of a load
which can make use of the energy. Thus, as the load grows after 1996 the
energy from the Project will increase during the high flow months. Since this
energy is available in all years, credit is taken as discussed in Section V.
The Project as sized does not make full use of the West Creek
site. Hence, two larger projects were investigated: first, a project which
could meet the Scenario C load and energy requirements, and second, the larg-
est project which could be developed without increasing the tunnel diameter.
(See Section XII.) Sizing the Project to meet the loads and energy require-
ments forecasted in Scenario C would mean a Project with an installed capacity
of 9,000 kW and a reservoir with a normal maximum level of El 725 feet. The
Project would have a firm energy output of 39,800 MWh.
The Project will have an unlined tunnel with a 9.5 foot diameter.
Assuming a maximum allowable velocity in the unlined portion of 5 fps, the
Project could have an installed capacity of 17,000 kW. Using a plant factor
XI-4
of 0 • 5 , the Pro j ec t could generate 74,500 MWh per year and would req ui re a
reservoir with a normal maximum level of El 755.
Future expansion of the Project is further discussed in Sec-
tion XIII.
,
•
•
.'
Month
Oct (31)
Nov (30 )
Dec (31)
Jan (31)
Feb (28)
Mar (31)
Apr (30)
May (31)
Jun (30)
Jul (31)
Aug (31)
Sep (30 )
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
SUMMARY OF BASIC INPUT DATA
Rule Curve
Elev. (ft) Stor. (ac-ft)
705.00
705.00
705.00
705.00
705.00
705.00
705.00
705.00
705.00
705.00
705.00
705.00
21,680
21,680
21,680
21,680
21,680
21,680
21,680
21,680
21,680
21,680
21,680
21,680
Annual Required Energy (GWh) = 23.6
Starting Month and Year of Data = 10/1963
Overall Efficiency = 85%
Rated Head
Required
Generation
(PCT of Annual)
8.7
8.8
9.0
8.8
9.5
8.3
8.1
7.8
7.7
7.3
7.8
8.2
Hydraulic Capacity at Maximum Head = 75 cfs
Beginning Storage in Reservoir = 21,680 acre-feet
Maximum Reservoir Capacity = 21,680 acre-feet
Tailwater Elevation = 38.0 feet
Flow Adjustment Factor (Multiplier) = 0.86
TABLE XI-1
• ..
Year Oct. Nov. Dec. Jan.
1963-64 15,310 10,056 1,845 430
1964-65 14,080 3,273 3,505 2,337
1965-66 14,019 4,701 861 922
1961;-67 19,061 5,355 1,599 615
1967-68 14,327 3,213 738 492
1968-69 10,084 4,998 2,214 1,414
1969-70 7,624 3,511 1,968 1,045
1970-71 16,233 11,306 5,472 2,091
1971-72 16,786 9,818 2,398 1,537
1972-73 6,087 1,666 1,660 1,107
1973-74 10,268 4,820 1,906 492
1974-75 9,162 2,023 984 492
1975-76 20,598 13,507 3,935 2,152
1976-77 9,961 1,666 1,168 1,291
1977-78 17,278 12,139 6,210 4,120
Average 13,445 6,137 2,431 1,369
,
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WES'l' CREEK PROJECT
RESERVOIR INFLOW (ACRE-FEET)
Feb. Mar. ~ ~
666 3,074 4,403 16,356
1,666 1,353 2,083 9,039
833 799 2,737 10,945
666 1,230 3,630 8,670
722 676 952 8,793
2,221 3,874 2,440 20,229
1,000 1,722 3,213 12,605
2,055 2,091 2,618 11,806
1,055 1,107 2,261 7,563
666 1,045 1,012 10,022
033 922 3,035 11,068
666 430 1,071 9,654
1,277 1,230 2,797 10,514
833 799 2,975 8,424
4,554 3,074 5,474 12,666
1,314 1,51;2 2,713 11,224
• •
.June ~ ~
I
24,218 61,I1l8 69,604
51,352 57,614 41,074
25,051 51,957 49,559
35,048 50,727 44,640
44,926 45,132 63,640
32,787 55,031 39,598
40,820 43,964 32,465
30,347 38,737 42,365
33,977 56,876 52,449
26,955 62,348 1;3,271
23,623 42,119 51,096
24,635 44,394 51,834
28,086 61,488 40,213
27,015 47,530 43,226
34,215 60,565 69,481
32,204 52,027 50,301
.. ""f
~
47,01;8
18,327
33,441
31,537
65,812
29,812
22,731
2'l,395
20,231
24,932
19,160
44,093
47,603
43,140
30,883
33,878
TABLE )(1-2
Averagf'
21,246
17,209
11;,319
16,898
20,785
17,059
14,38'l
16,210
17,172
16,731
14,112
l'i,787
19,450
15,669
21,722
17,384
r-3
6;
r
trl
~
H
I
N
•
HAINES-SKAGwAY REGION
FEASIBILITY STUDY
WEST CREEK pnOJECT
'l'OTAL ENERGY REQUIRED (MWh)
Year Oct. Nov. Dec. Jan. Feb. lIiar. ~
1963-64 2,056 2,080 2,127 2,080 2,244 1,961 1,914
1961\-65 2,056 2,080 2,127 2,080 2,244 1,961 1,914
1965-66 2,056 2,080 2,127 2,080 2,244 1,961 1,914
19 &6-6 7 2,056 2,080 2,127 2,080 2,244 1,961 1,914
1967-68 2,056 2,080 2,127 2,080 2,244 1,961 1,914
196B-69 2,056 2,080 2,127 2,OBO 2,244 1,961 1,914
1969-70 2,056 2,080 2,127 2,080 2,244 1,961 1,914
1970-71 2,056 2,080 2,127 2,OBO 2,2-14 1,961 1,914
1971-72 2,056 2,080 2,127 2,080 2,244 1,961 1.,914
1972-73 2,056 2,080 2,127 2,080 2,244 1,961 1,914
1973-74 2,056 2,080 2,127 2,080 2,244 1,961 1,914
1974-75 2,056 2,080 2,127 2,OBO 2,244 1,961 1,914
1975-76 2,056 2,OBO 2,127 2,080 2,24-1 1,961 1,914
1976-77 2,056 2,080 2,127 2,OBO 2,244 1,961 1,914
1977-78 2,056 2,080 2,127 2,080 2,244 1,961 1,914
Average 2,056 2,OBO 2,127 2,OBO 2,244 1,961 1,914
NOTE: The above are the energy requirements for Haines and Skagway
in 1996 under the Scenario B forecast.
~
1,843
1,843
1,843
1,843
1,843
l,B43
l,B43
1, B43
1,843
1,843
1,843
1,843
1,843
1,843
1,843
1,843
• ~
TABLE XI-3
June ~ ~ ~ Total
1,820 1,725 1,843 1,937 23,630
1,820 1,725 1,843 1,937 23,630
1,820 1,725 1,843 1,937 23,630
1,820 1,725 1,843 1,937 23,630
l,B20 1,725 1,843 1,937 23,630
1, B20 1,725 1,843 1,937 23,630
1,820 1,725 1,843 1,937 23,630
1,820 1,725 1,843 1,937 23,630
l,B20 1,725 1,843 1,937 23,630
1,820 1,725 1,843 1,937 23,630
1,820 1,725 1,843 1,937 23,630
1,820 1,725 1,843 1,937 23,630
l,B20 1,725 1,843 1,937 23,630
1, B20 1,725 1,843 1,937 /.3,630
1,820 1,725 1,843 1,937 21,630
1,820 1,725 1,843 1,937 23,630
.. • • ~
TABLE XI-4
HAINES-SKAGWAY REGIOr.
FEASIBILITY S'I'UDY
WI::S'l' CREEK l'ROJEC'l'
'fOTAL BNERGY GENBRA'l'BD (rvil"/h)
Year Oct. Nov. Dec. Jan. Feb. lV~Qr • ~ ~ June ~ ~ ~ 'i'otal
1963-64 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,7;:5 1,843 1,937 23,030
1964-65 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,B43 1,820 1,725 1,843 1,937 23,630
1965-66 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,725 1,843 1,937 23,630
1966-67 2,056 2,080 2,1~7 2,080 2,244 1,~61 1,914 1,843 1, B20 i.,7~5 1,843 1,937 23,630
1967-68 2,056 2,000 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,725 1,843 1,937 23,630
196B-69 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,725 1,843 1,937 23,630
1969-70 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,725 1,843 1,937 23,630
1970-71 2,056 2,080 2,127 2,080 2,244 1,%1 1,914 1,8<U 1,820 1,725 1,843 1,937 23,630
1971-72 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,725 1,843 1,937 23,630
1972-73 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,725 1,843 1,937 23,630
1973-74 2,056 2,OBO 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,725 1,043 1,937 23,630
1974-75 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,843 1,B20 1,725 1,843 1,937 23,630
1975-76 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,725 1,843 1,937 23,630
1976-77 2,056 2,080 2,127 2,080 2,244 1,961 1,914 I,B43 1,820 1,725 1,843 1,937 23,630
1977-78 2,056 2,080 2,127 2,080 2,244 1,961 1,914 1,843 1,820 1,725 1,843 1,937 23,630
Average 2,056 2,000 2,127 2,080 2,244 1,961 1,914 I,B43 1,820 1,725 1,843 1,937 23,630
• • •
• ""
TABLE XI-5
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
wES~.· CREEK PROJECT
END-OF-MONTH RESERVOIR STORAGE (ACRE-FEET)
Year Oct. Nov. Dec. .1an. ~ l'-iar. ~ ~ June ~ ~ ~ Average
J
1963-64 21,680 21,68U 19,247 15,471 11,653 10,681 11,127 21,680 21,680 21,~80 21,680 21,680 18,328
1964-65 21,680 20,835 20,056 18,222 15,457 12,804 10,946 16,161 21,680 21,680 21,680 21,680 18,573
1965-66 21,680 21,680 10,270 14,992 11,361 8,068 6,810 13,895 21,680 21,680 21,680 21,680 16,956
1966-67 21,680 21,680 19,024 15,430 11,598 8,775 8,398 13,214 21,680 21,680 21,680 21,680 17,210
1967-68 21,680 20,727 17,229 13,468 9,685 6,257 3,150 7,<194 21,680 21,680 21,680 n,680 15,576
1968-69 21,680 21,680 19,666 16,904 14,657 14,488 12,968 21,680 21,680 21,680 21,680 21,680 1Q ,204
1969-70 21,680 21,030 18,740 15,606 12,141 9,819 9,072 17,828 21,680 21,680 21,680 21,680 17,720
1970-71 21,680 21,680 21,680 19,572 17,198 15,291 14,016 21,680 21,680 21,680 21,680 21,680 19,960
1971-72 21,680 21,680 19,841 17,209 13,835 10,877 9,153 12,862 21,680 21,680 21,680 21,680 17,821
1972-73 21,680 19,175 16,576 13,445 9,588 6,510 3,485 9,564 21,680 21,680 21,680 21,680 15,562
1973-74 21,680 21,680 19,316 15,594 11,<132 8,784 7,813 15,015 21,680 21,680 21,680 21,680 17,378
1974-75 21,680 19,571 16,296 12,573 8,739 5,076 2,049 7,780 21,680 21,680 21,680 21,680 15,040
1975-76 21,680 21,680 21,376 19,334 16,230 13,442 12,270 18,986 21,680 21,680 21,680 21,680 19,310
1976-77 21,680 19,216 16,134 13,210 9,552 6,271 5,205 9,714 21,680 21,680 21,680 21,680 15,642
1977-78 21,680 21,680 21,680 21,653 21,680 20,801 21,680 21,680 21,680 21,680 21,680 21,680 21,605
Average 21,680 21,045 19,009 16,179 13,0~0 10,530 9,209 15,316 21,680 21,680 21,680 21,680 17,726
Average 705.00 704.52 702.46 698.16 692.27 686.22 680.37 686.56 699.69 705.00 705.00 705.00 697.58
TABJ.E XI-7
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
DISCHARGE THROUGH UNI'rS (CFS)
Year Oct. Nov. Dec. Jan. Feb. Mar. ~ ~ June .Tuly Aug. Sep. Average
1963-64 57 60 59 58 68 56 57 52 52 48 51 56 56.17
1964-65 57 60 59 58 70 56 56 52 52 48 51 56 56.25
1965-66 57 60 59 58 71 56 57 53 53 48 51 56 56.58
1966-67 57 60 59 58 71 56 57 53 53 48 51 56 56.58
1967-68 57 60 59 59 69 57 58 54 53 48 51 56 56.75
1968-69 57 60 59 58 70 55 56 52 52 48 51 56 56.17
1969-70 57 60 59 58 70 56 57 52 52 48 51 56 56.33
1970-71 57 60 59 58 69 55 56 52 52 48 51 56 56.08
1971-72 57 60 59 58 68 56 57 53 53 48 51 56 56.33
1972-73 57 60 60 59 71 57 58 54 53 48 51 56 57.00
1973-74 57 60 59 58 70 56 57 53 53 48 51 56 56.50
1974-75 57 60 60 59 71 57 59 54 53 48 51 56 57.08
1975-76 57 60 59 58 67 55 56 52 52 48 51 56 55.92
1976-77 57 60 60 59 71 57 58 53 53 48 51 56 56.92
1977-78 57 60 59 58 69 54 55 51 52 48 51 56 55.83
Average 57 60 59.20 58.27 69.67 55.93 56.93 52.67 52.53 48 51 56 56.43
• • • .. .. " • .. '\
TABLE XI-8
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PRO.JECT
SPILL (CFS)
Year Oct. Nov. Dec. Jan. Feb. Mar. ~ ~ June ~ Aug. SeE' Average
1963-64 182 100 0 0 0 0 0 32 345 949 1.071 726 283.75
1964-65 175 0 0 0 0 0 0 0 708 879 607 242 217.58
1965-66 161 10 0 0 0 0 0 0 228 788 745 497 202.42
1966-67 243 21 0 0 0 0 0 0 384 767 665 464 212.00
1967-68 166 0 0 0 0 0 0 0 462 677 973 1,040 276.50
1968-69 97 14 0 0 0 0 0 125 489 837 583 435 215.00
1969-70 57 0 0 0 0 0 0 0 559 657 467 316 171. 33
1970-71 197 120 20 0 0 0 0 6 448 562 628 428 201. 58
1971-72 206 96 0 0 0 0 0 0 360 868 792 274 216.33
1972-73 32 0 0 0 0 0 0 0 187 956 967 353 207.92
1973-74 100 11 0 0 0 0 0 0 223 628 770 256 165.67
1974-75 82 0 0 0 0 0 0 0 117 665 782 676 193.50
1975-76 268 157 0 0 0 0 0 0 365 942 593 734 254.92
1976-77 95 0 0 0 0 0 0 0 190 715 642 659 191. 75
1977-78 214 134 32 0 3 0 12 145 513 927 1,069 453 291.83
Average 151.67 44.20 3.47 o 0.2 o 0.00 20.53 371.87 788.47 756.93 503.53 220.14
•
•
•
•
•
SECTION XII
ALTERNATIVE PROJECT ARRANGEMENTS
1. GENERAL
To arrive at the optimum Project arrangement, alternatives for the
configuration and layout of the major features were identified, evaluated, and
refined to arrive at a layout which is referred to herein as the "Selected
Project Arrangement." During the final design phase, further optimization and
refinement of this arrangement can be expected to occur.
The Project and its major features were sized to meet the Sce-
nario B load forecast in 1996. This resulted in an installed capacity of
6,000 kW and a reservoir capable of storing sufficient water to produce
23,630 MWh during the driest year of record. In addition future expansion to
a project with a capacity to meet the larger energy requirements forecasted in
Scenario C was also studied •
The comparative costs used in this section are estimated on a Janu-
ary 1982 bid basis and include only Direct Construction Costs.
2. DAM AND SPILLWAY
a. General
Two alternative types of dams were considered for the Project: a
concrete-gravity and a concrete-faced rockfill, both of which could be devel-
oped for the highest dams considered. The geotechnical investigations indi-
cate that the dam site is suitable for construction of either of these types
of structures. Impervious core embankment dams were not considered because
the geotechnical investigations did not find any source of core material with-
in easy haul distance of the dam site. Cost comparisons were made of the two
types of dam including spillway costs but not including power conduit and
powerhouse costs which are common for either type of dam and depend only on
the size project selected.
Initial comparisons were made for a normal maximum reservoir level
of 705 feet and spillway widths of 100 feet, 150 feet, and 200 feet. The dif-
ferent spillway widths affect the height of dam since the maximum water sur-
face level during the PMF will be a function of the spillway width.
b. Concrete-Gravity Dam
The concrete-gravity dam alternative would have a vertical upstream
face, a 1,000-foot-wide crest, and a downstream slope of 0.6:1. An ungated
XII-2
ogee-shaped spillway would be located within the central portion of the dam
crest with a chute extending to a flip bucket structure near the downstream
toe of the dam. A bridge would be required over the spillway to allow access
to the intake on the right abutment. The crest elevation of the dam would
depend on the spillway width. For a 100-foot-wide spillway, it would be
E1720; for a 150-foot-wide spillway, El 718 feet; and for a 200-foot-wide
spillway, E1716 feet. The gravels deposited in the alluvial deltas upstream
of the dam site would provide a ready source of high quality concrete aggre-
gate.
The cost estimates for the concrete gravity dam were made assuming
the dam were constructed of roller compacted concrete (RCC). This is a rela-
tively new method for construction of concrete dams which utilizes more effi-
cient placement techniques similar to earth dams to construct concrete struc-
tures. The improved efficiency promises significant construction cost econo-
mies for concrete-gravity structures. Although the RCC technology is based on
well established construction techniques, its use for concrete dams is quite
new with only two projects having been bid to date in the United States and
only a small one having been completed. The second will be constructed this
summer. A third project will be bid this year. Bid costs for these jobs con-
firm that RCC has great potential showing in-place unit prices well below
those of conventionally-placed concrete. Another six RCC dams are under study
by various organizations in the United States. Although in-house cost esti-
mates for RCC were used for this cost comparison, the recent bid has a unit
price which is about 70% of that used herein. Thus, if future bid prices and
actual construction experience confirm the lower prices, a RCC dam would be
competitive with, or less expensive than, the concrete-faced rockfill dam for
the West Creek Project.
Because of the clear indication of great potential cost savings,
RCC should be given serious consideration during the Project design phase.
c. Concrete-Faced Rockfill Dam
The concrete-faced rockfill dam alternative would consist of a com-
pacted rockfill or rock and gravelfill embankment with an upstream slope of
1.6:1 and a downstream slope of 1.5:1. The upstream slope would be faced with
a slip-formed reinforced concrete slab with a thickness of 12 inches at the
crest expanding to 18 inches at the base. The facing slab would be placed on
a 10-foot-thick select gravel bedding. Unlined, open channel spillways exca-
vated in rock were considered on both abutments. Material from the spillway
excavation would be used to construct the embankment. After initial cost
estimates, it was obvious that a spillway through the left abutment would
require the excavation of considerably more rock than could be used in the dam
and hence was a more expensive option. The left abutment spillway was dropped
at this point and only the right abutment spillway options were considered.
A preliminary spillway channel alignment through a saddle in the
right abutment was developed and three dam options for spillway widths of
100 feet, 150 feet and 200 feet were priced out.
•
•
•
..
..
•
•
•
XII-3
d. Comparison of Dam Alternatives
Preliminary cost estimates of the dam alternatives described above
resul ted in the following costs for the least expensive concrete-gravity and
concrete-faced rockfill dams:
Dam Type
Concrete-Gravity •••••••.••.
Concrete-Faced Rockfill
e. Diversion Alternatives
Comparative
Direct Construction Cost
$10,750,000
$ 7,700,000
Three alternative diversion schemes were studied. In the first
scheme a 22-foot-high cofferdam diverts flow through a 20-foot-diameter tunnel
in the right abutment. The tunnel would extend 590 feet downstream past a
15-foot-high downstream cofferdam. The tunnel was sized to handle 5,500 cfs,
the 10-year flood. After construction, the tunnel would be plugged with con-
crete. The second scheme was similar to the first, but with an 890-foot-long,
20-foot-diameter tunnel in the left abutment. In the third scheme flow would
be passed through two 11-foot-diameter concrete pipes placed along the stream-
bed from the upstream cofferdam 765 feet downstream past the downstream cof-
ferdam.
Each scheme was priced and the costs compared as follows:
Diversion Scheme
Right Abutment Tunnel
Left Abutment Tunnel
Concrete Pipe Conduit
Comparati ve
Direct Construction
Cost
$3,800,000
ll,900,OOO
2,500,000
The diversion tunnels for the concrete dam could be somewhat
shorter, but the general cost comparison remains valid.
Further, it should be noted that no cost for diversion is included
and that the concrete-gravity estimates are based on a new construction meth-
od. Thus, on the basis of cost, the concrete-faced rock fill dam type was cho-
sen for the Project. The dam is further described in Section XIII.
3. POWER INTAKE ALTERNATIVES
Four alternative power intakes were studied as follows:
a. A vertical intake tower with an access bridge.
XII-4
b. Similar to a. with a vertical intake structure constructed at the
end of a long approach channel but with no bridge.
c. A low-level intake with a downstream gate shaft.
d. An intake structure inclined at a 0.25:1 slope constructed at the
end of a shorter approach channel.
Each alternative is technically feasible for the West Creek site. Comparative
..
cost estimates were made to determine the most economical option. These esti-•
mates show that the first three alternatives all have about the same cost and
that the fourth alternative was about $300,000 less expensive. Hence, alter-
native d. was selected.
4. POWER CONDUIT AND POWERHOUSE ALTERNATIVES
a. General
Selection of the power conduit type and alignment including the
location of the powerhouse was made in three steps. First, the type of power
conduit, either tunnel or surface penstock, was selected. Next, the alignment
of the power conduit was determined. Third, the selected alignment was re-
fined to develop the least expensive power conduit for that alignment. These
steps are described in the following. The alternative alignments are shown in
Fig. 5.
b. Type of Power Conduit
A comparison of the tunnel proposed in the Addendum and a surface
penstock was made to determine which should be considered in developing the
Project. A penstock could be most easily installed on the north side of West
Creek running from an intake on the left abutment, paralleling the existing
logging road through the middle basin and then down to a powerhouse on the
north side of the creek. The penstock would have a total length of about
11,000 feet. A surge tank would be required at the top of the slope above the
powerhouse. In order to reduce hydraulic losses a five-foot-diameter penstock
was used for comparison. Based on detailed estimates for other projects, the
five-foot-diameter surface penstock would cost about $1,000/foot. Thus, the
direct construction cost would be $11,000,000, not including the surge tank.
This cost is somewhat higher than that estimated for the tunnel.
In addition, the tunnel has several advantages. The tunnel has the capability
of expansion since it must be constructed at a diameter larger than that re-
quired initially. In order to expand, the capacity of the penstock would re-
quire installation of another penstock. Also, the tunnel will be more reli-
able in that it is less vulnerable to weather and vandalism, and thus will
require less maintenance. Together with the cost comparison, these factors
were the basis for choosing the tunnel. The following discusses the selection
of the alternative alignment for the tunnel.
•
..
•
• XII-5
c. Location
.. In the Addendum Report, the powerhouse was proposed to be located
on the south slope of the mouth of West Creek about two miles downstream of
• the dam, adjacent to where West Creek enters the Taiya River Valley. Initial
geotechnical investigations conducted in Phase II showed that this slope is
overburden about 80 feet thick, whereas near-surface bedrock had been origi-
• nally assumed. Because this creates potentially difficult and expensive tun-
neling and foundation problems, alternative locations for the powerhouse were
• investigated. Two sites, one on the north side of West Creek and one about
1,200 feet south of the creek, were located where the powerhouse could be
founded on rock. All three powerhouse locations would return flow to approxi-
mately the same point on West Creek and thus would develop essentially the
same head. Also, two possible developments at the original site were consid-
ered in an effort to compensate for the thick overburden. The various alter-
natives were compared judgmentally based on length of tunnel and quantity of
excavation.
d. Alternative Arrangements
..
(1)
•
General
Each alternative involved a tunnel excavated in rock generally par-
alleling existing topography. The first three alternatives involve a
7 ,500-foot-Iong horizontal tunnel extending from the intake through the south
ridge of the West Creek Valley to a surge shaft above the Taiya Valley. From
there the power conduit would be a vertical shaft extending down to a lower
horizontal tunnel leading to the appropriate powerhouse location. The fourth
alternative is a similar tunnel-shaft combination on the north side of West
Creek. Preliminary hydraulic transient analysis determined that there would
be a need for a surge shaft in each case. In all cases the tunnel diameter
was the minimum which was considered practical to construct. Thus, for ini-
tial comparisons the tunnel costs can be considered proportional to length.
Once the power conduit alternative was selected, the arrangement was further
refined to determine the least cost conduit arrangement.
(2) Alternative Alignment No.1
As described above, the power conduit for this alternative would
consist of a tunnel extending approximately 7,500 feet to a surge shaft and
vertical shaft. The lower tunnel would then extend another 2,700 feet to the
powerhouse situated as shown in Fig. 5. At the powerhouse the tunnel would
have a short steel-lined concrete-encased penstock section which, at the por-
tal, would branch into two smaller diameter penstocks before entering the
powerhouse •
The powerhouse would be an indoor-type structure partially exca-
vated into the hillside. This alternative would require a small amount of ex-
cavation mainly in rock. A tailrace channel, approximately 1,200 feet in
XII-6
length, would be constructed to conduct the plant discharges back into the ex-
isting West Creek channel. The tailwater level would be maintained by a weir
at a level sufficient to protect the turbines from cavitation. ~
Alternative Alignment No.2
Alternative Alignment No. 2 would be the same as Alternative Align-
ment No. 1 for the tunnel distance between the power intake up to and includ-
ing the surge shaft. From there the alignment of the lower tunnel would fol-
low a more northwesterly course to a powerhouse site located close to West
Creek on the south side, as shown in Fig. 5. Three powerhouse options were
considered for the site.
Powerhouse Option No. 1 would include a powerhouse built on a pile
foundation near the south bank of West Creek. Piles would bear on solid rock
and average 40 to 50 feet in length. A tailrace channel would be constructed
to conduct the plant discharges to West Creek. The channel would be approxi-
mately 250 feet long and the tailwater elevation would be set slightly above
the level of West Creek.
This option would require a 2, 600-foot rock tunnel from the verti-
cal shaft with a 180-foot-long soft ground tunnel through the overburden. A
4-foot-diameter steel penstock would be used from the end of the rock tunnel
to the powerhouse. The penstock would branch into two smaller diameter pen-
stocks just prior to entering the powerhouse.
Powerhouse Option No. 2 involved an indoor powerhouse excavated
into the overburden immediately south of West Creek. This option would re-
quire sufficient excavation of the overburden to provide a solid rock founda-
tion. A tailrace channel, approximately 250 feet long, would be required to
conduct the plant discharges into the existing West Creek channel. The tail-
water level would be El 38.0. This option eliminated the need for the soft
ground tunnel, but otherwise the tunnel was similar to Option No.1.
Option No. 3 would require excavation in both common overburden and
solid rock to construct an underground powerhouse. The location would have to
be deep enough into the hillside on the south side near West Creek to allow
adequate rock cover for the structure. A tailrace tunnel, approximately
250 feet long, would be excavated through rock to conduct the plant discharges
into the existing West Creek channel slightly above where the creek enters the
Taiya Valley. The tailwater level would be maintained at or above El 40.0.
The rock tunnel to the powerhouse would be shorter than for the other options,
but the tailrace tunnel would make the total tunnel length about the same.
This option would also require an additional access tunnel.
(4 ) Alternative Alignment No.3
This alternative started along the same alignment as Alternative
Alignments 1 and 2 from the power intake up to and including the vertical
shaft. From there, the tunnel would continue for about 4,000 feet passing
•
..
..
•
•
•
,
•
•
XII-7
north underneath West Creek and curving eastward to a powerhouse location on
the north side of the stream. The tunnel would include a steel-lined section
, under West Creek. At the powerhouse the tunnel would have a short steel-lined
concrete-encased penstock section before branching at the portal and entering
• the powerhouse. The powerhouse would be similar to that required for Alterna-
ti ve 1. Power plant discharges would be conveyed directly back into West
Creek via a 350-foot-long tailrace channel.
..
(5) Alternative Alignment No.4
Al ternati ve Alignment No.4, the most northerly alignment, would
consist of a tunnel extending approximately 10,800 feet along the north wall
of the canyon from a power intake on the left abutment to a surge shaft. The
surge shaft would connect with a lower tunnel approximately 2,500 feet long to
a powerhouse at the same location as the one described for Alternative Align-
ment No.3.
e. Comparison of Alternatives
Table XII-1 summarizes the principal statistics for the various
al ternatives and options. The cost of each alternative is a function of the
length of the tunnel and the quantity of excavation for the powerhouse.
Hence, a comparison of the al terna ti ves on the basis of these two items de-
fines the relative costs •
Comparing the alternatives shows that Alternative No. 1 has the
shortest tunnel as well as the smallest quantity of excavation. However, the
alternative would require a long tailrace channel. Alternative No. 2 has a
tunnel length only 180 feet longer than in Alternative No.1, but requires
either a large quantity of excavation or a 180-foot-long soft ground tunnel.
It is estimated that the cost of the tailrace would be less than the added
costs of excavation or of the soft ground tunnel in Alternative No.2. Thus,
Alternative No. 1 was selected as the power conduit alignment.
f. Refinement of Selected Alternative No.1
The selected Power Conduit Alternative was further studied to
determine the least expensive means of excavating the tunnel. Both conven-
tional drill and blast excavation and machine boring were studied. The drill
and blast approach would require excavating the lower tunnel in from the por-
tal at the powerhouse, the vertical shaft up from the end of that tunnel, and
the upper tunnel from the power intake down to the vertical shaft. Construc-
tion by drill and blast would cost about $17,400,000 and take about 490 work-
ing days. A second approach would be to excavate the upper tunnel using a
tunnel boring machine. The shaft and lower tunnel would still be excavated
using drill and blast techniques. This approach would cost about
$12,000,000. Of this total, the shaft and lower tunnel would cost $3,000,000.
A third approach would be to excavate the upper tunnel from the
power intake past the surge shaft and straight through to daylight in the
XII-B
hillside above the powerhouse site with a tunnel boring machine and place a
3-foot-diameter surface penstock down the slope to the powerhouse. This
approach would cost $10,600,000 and take about 240 working days to construct.
Thus, based on a comparison of costs, the machine bored tunnel with
the surface penstock was selected. The selected power conduit alternative is
described in detail in Section XIII.
g. Powerhouse Superstructure
The powerhouse for the selected alternative will be an above-
ground, indoor-type founded on rock. Three types of superstructures, cast-in-
place concrete, prefabricated steel, and precast concrete, were compared. It
was determined that the prefabricated steel and the precast concrete buildings
have about the same cost and are less expensive than the cast-in-place con-
crete option. The precast concrete superstructure was selected because it was
considered less vulnerable to vandalism and adverse weather, and should have a
longer useful life.
5. TRANSMISSION LINE ALTERNATIVES
a. General
The preferred transmission line alternative for the Project was
selected in a multi-stepped evaluation with the following basic evaluation
criteria: minimizing adverse environmental impacts, maximizing system relia-
bility and minimizing cost. The evaluation was based on a literature search,
detailed map study, field reconnaissance, fathometric survey, engineering
studies, and comparative environmental analyses of potential impacts on aes-
thetics, raptors, and archaeological and historical sites.
The transmission system must provide power from the West Creek
Project to both the Haines and Skagway areas. The rated capacity of the West
Creek Project is 6,900 kVA. Based on forecasted loads, the Haines loads would
require approximately 4,500 kVA and the Skagway loads would require approxi-
mately 2,400 kVA.
The existing distribution system in Haines contains four feeders
out of a central diesel generating plant. The distribution system generally
is at 2.4 kV except for the line to the Schnabel Mill which is presently at
7.2 kV. As discussed in Part A, the Schnabel Mill is presently constructing a
wood waste generating plant. Haines will upgrade the tie line to the mill to
34.5 kV to handle the new power requirements. The West Creek Project can
interconnect with the Schnabel Mill to Haines tie line.
The Skagway system includes hydroelectric and diesel generation,
both located in Skagway at the same plant. The distribution system is at
2.4 kV. After a review of the Skagway system, it was determined to intercon-
nect the West Creek Project with the generating plant switchyard.
•
..
•
•
•
••
..
)
•
XII-9
b. Transmission Line Corridor Alternatives
Three alternative transmission corridors were identified as shown
on Fig. 6 and discussed below. The corridors were assumed to be approximately
one-half mile wide to allow for subsequent adjustment of the rights-of-way
depending on the type of transmission system, specific environmental consider-
ations, and the final design. The alternative corridors were selected to:
• Minimize transmission line length in order to reduce environ-
mental impacts, construction costs, and reliability problems.
• Avoid areas with high environmental and engineering sensitiv-
ity including glaciers, and construction above El 4000 feet.
Due to the special requirements dictated by the terrain, weather
and recreation in the Haines-Skagway area, alternative types of transmission
systems were evaluated in some detail. One of the major concerns was the
potential adverse aesthetic impact relating to the extensive recreational uses
of the area. Also of major concern were the potential engineering and relia-
bility problems caused by the rugged nature of the terrain and the adverse
weather conditions. The following systems were considered: overhead bare
conductor, underground cable, and submarine cable. The voltage was determined
by limiting the voltage drop for any total line to less than 5%. Where sub-
marine cable was used, it was based on three single conductors and one spare
conductor.
Alternative transmission corridors and systems were selected as
follows. The Alternative A transmission line would exit the West Creek Power
Plant as a 34.5-kV overhead or underground transmission line easterly then
southerly following existing roads approximately 1.2 miles through the Klon-
dike Gold Rush National Historical Park. It would continue southerly as a
34.5-kV overhead transmission line along the east side of Taiya River flood-
plain following the road from West Creek to Skagway. At a point east of the
original Dyea downtown site, the corridor would leave the road and turn south-
easterly across a ridge to Long Bay (Nahku Bay) where it again would intersect
with the road. It would follow the road southerly along the eastern side of
Long Bay to a point northwest of Skagway, approximately 2.8 miles from the
park, where a switching station would be constructed to tap off a transmission
line to Skagway and another transmission line to Haines. The 34.5-kV overhead
transmission line to Skagway would cross a ridge in a southeasterly direction,
then cross the Skagway River, and follow existing streets approximately
2.2 miles to the Skagway Power Plant Switchyard. The 34.5-kV transmission
line to Haines would run southwesterly to the Taiya Inlet where it would enter
the water and continue southerly as a 34.5-kV submarine transmission line.
The submarine transmission line would run south along the west side of Taiya
Inlet. At a point near Taiya Point, the line would turn southwesterly through
Chilkoot Inlet and intersect land north of Haines just south of Tanani Point
approximately 16.6 miles from the switching station. At Tanani Point the
transmission line would exit the inlet and intersect with the existing Haines
XII-10
to Schnabel Mill 34.5-kV overhead transmission line at a proposed Haines ter-
minal switching station. See Fig. 7 for the Alternative A system one-line
diagram.
Alternative B transmission line from the powerhouse to the Skagway
Power Swi tchyard also would cross the Klondike Gold Rush National Historical
Park but as 12. 5-kV overhead or underground transmission line following the
same corridor as Al ternati ve A for approximately 1.2 miles. The line would
continue along the same corridor as Alternative A as a 12.5-kV overhead trans-
mission line approximately 5.0 miles to the Skagway Power Plant Switchyard.
At the Skagway Power Plant Switchyard, the voltage would be reduced to the
distribution system voltage. The Alternative B 34.5-kV overhead transmission
line from the Project powerhouse to Haines would exit the power plant south-
erly and follows the west side of the Taiya River floodplain to the Taiya In-
let. It would continue southerly on land following the western bank of the
Taiya Inlet approximately 18.7 miles from the plant to the Taiya Point. At
the Taiya Point the line would enter the inlet and become a 34.5-kV submarine
transmission line crossing approximately 2.1 miles southwesterly through Chil-
koot Inlet, intersecting land north of Haines and just south of Tanani Point.
At Tanani Point the transmission line would exit the inlet and intersect with
the eXisting Haines to Schnabel Mill 34. 5-kV overhead transmission line at a
proposed Haines Terminal Switching Station. See Fig. 8 for the Alternative B
system one-line diagram.
Alternative C would use the same corridor and 12.5-kV transmission
system as Alternative B from the West Creek Project to the Skagway Power Plant
Swi tchyard. The Al ternati ve C 34. 5-kV overhead transmission line to Haines
would exit the power plant westerly and follow the south side of the West
Creek Valley. A t a point approximately three miles west of the proposed
powerhouse the transmission line would turn southwesterly crossing Halutu
Ridge to the Ferebee River Valley. Several miles south of Ferebee Glacier,
the line would turn southeasterly and follow the Ferebee River along the west
side. It would then turn southwesterly and cross the ridge south of the gla-
ciers running to the southern end of Chilkoot Lake. At the outlet of Chilkoot
Lake, the overhead line would avoid the Chilkoot Lake Wayside Park, turn
south, and follow the existing road along the southwestern side of Lutak Inlet
to the Schnabel Mill, where it would intersect with the existing Haines to
Schnabel Mill 34.5-kV overhead transmission line at a proposed Haines Terminal
Switching Station.
c. Alternative Transmission Line Evaluation
The transmission alternatives were evaluated based on the following
objectives:
(1) Minimize engineering construction costs.
(2) Maximize transmission system reliability.
(3) Minimize adverse aesthetic impacts.
•
..
I
•
•
..
•
"
..
,.
•
..
XII-11
(4) Minimize possible impact to raptors. This is only an evalua-
tion consideration because the overhead lines can be designed to avoid being a
hazard to raptors.
(5) Minimize adverse impact to known and expected archaeological
and historical sites.
(6) Minimize transmission right-of-way clearing.
The transmission alternatives were compared both qualitatively and
quantitatively, and the preferred transmission alternative was selected as
discussed below. (See Table XII-2 for a summary.)
Alternative A has the least relative transmission line and system
cost. Based on an evaluation of reliability factors, it also has the least
chance for outages due to the reliability factors. Since Alternative A would
be mostly underwater, it also has the least aesthetic impact of all the alter-
natives and the least possible impact on raptors. Alternatives A and C were
both seen as having no impact on archaeological and historical sites, but all
three alternatives might impact sites from the historical town site of Dyea
between the plant and Skagway. Again since Alternative A would be mostly sub-
marine cable, it has the least number of acres required to be cleared.
Alternative B has the next to highest relative cost. The reliabil-
ity exposure of this alternative would be high due to the overhead line along
Taiya Inlet being subject to falling trees and landslides. Alternative B has
the greatest impact on aesthetics since it runs overhead the full length of
the Taiya Inlet. This area receives a great deal of tourist use and is con-
sidered highly desirable aesthetically. Alternative B also has greater poten-
tial impact on archaeological and historical sites in the park, since it would
have a greater length of line within the park. Finally, Alternative B has
more right-of-way to be cleared than Alternative A, but less than Alterna-
tive C.
Alternative C has the highest construction costs, and has possibly
the greatest maintenance costs since it runs cross-country through very rugged
mountains where it would be exposed to severe weather conditions and hence
would experience more reliability problems. Alternative C would not have as
great an impact on aesthetics as Alternative B, but would be visible from
Chilkoot Lake State Wayside, and from Lutak Inlet. It would also be exposed
to raptors over its longer length. Alternative C has the same impact on
archaeological and historical sites as Alternative A. This alternative has
the largest number of acres required for clearing.
Since Alternative A has the lowest construction costs, the fewest
reliability problems, the least impact on aesthetics, raptors, and the small-
est right-of-way area to be cleared, it was selected as the preferred alterna-
tive. Table XII-2 summarizes the transmission line alternative comparison.
See Fig. 15 for the selected transmission corridor.
•
Al ten ... ;:;;tive
N<}. 1 (OJ.:;;)
T,lO. 1. (H.evis0c')
i·!n. ? (P. V. O?t.. 1)
(P.T;. Opt. 3)
Hl\INES-SKAGVJAY RI!GION
FEASIBJT.ITY STUDY
bES'l' CREEK PRo.:mCT
CO~fi,f'ARISOilJ OF Po\iER CONDUI'I' ATJTERNA'J'IVES
Length of 'l'unn81
10,150'
8,1;.70' T\1nnel: 1,570 Penstock
PO~J8rhouse
Foundation
Roc!,
:lO,330' H.ock Tunnel; piles
180' Soft Ground 'runnel
(/.30' T'21~Stock-Rocl; ~nuni1e1 to po~\!erhouse)
10,300' Rock
10,250' Undergr:ouJ1d
11,450' Rocl~
13,100' Rock
.. • ,
Exc~vation for Powerhnusp
·B5 cy rock
2,300 cy cornman
2,500 cv rock
173,100 cy common
5,000 C" rocl~
AOr) cy rocl~
2,000 cy commor)
/,000 cy C:JTT11'10n
•
.1
~.
..
..
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
TRANSMISSION EVALUATION SUMMARY
Alt. A.
I. ENGINEERING:
A. Line Length (miles) . ............ 22.8
B. Transmission Line Costs ($1 ,000) • 12, 196.1
C. Total Transmission Costs ($1,000) 12,872.0
D. Total Adverse Exposure (miles) . . 34.2
E. Right-of-Way (acres) . ........... 14.9
II. ENVIRONMENTAL:
A. Aesthetics (miles) .............. 2.1
B. Raptor Exposure ( miles) . ........ 1.9
C. Archaeological and Historical
Exposure (miles) .............. 1.2
D. Clearing (acres) . ............... 7.5
TABLE XII-2
Alt. B Alt. C
27.0 32.9
13,057.3 15,371.9
13,408.0 15,723.0
71.9 86.3
47.5 91.6
16.6 10.0
18.0 8.9
4.7 1.2
47.5 91.6
,.
. ,
. '
••
•
SECTION XIII
SELECTED PROJECT ARRANGEMENT
1. GENERAL
Following selection of the basic Project arrangement, final refine-
ments were performed consistent with the feasibility level investigations .
This included detailed layouts of the features, quantity take-offs, and cost
estimates. This section contains a description of the major features of the
selected Project arrangement. Project data for the selected arrangement are
listed in the Summary of Principal Project Statistics in the Summary portion
of this report.
The major features of the Project are the reservoir, dam, power in-
take, power condul t and surge shaft, powerhouse, si te access facili ties, and
transmission system. The selected Project arrangement and related details are
shown in Figs. 10 through 15 •
2. RESERVOIR
The reservoir formed by the dam will provide 18,130 acre-feet of
active storage above the minimum pool at El 662. At normal maximum reservoir
El 705 feet, the surface area will be 635 acres. Some of the areas on both
sides of West Creek are densely forested so that it will be necessary to clear
about 330 acres within the area of the reservoir. The remaining area is cov-
ered with low brush with a good root structure which should hold the brush in
place after filling. A survey of the reservoir rim area revealed no potenti-
ally unstable slopes which could result in a future hazard to Project opera-
tion from landslide action •
3. DAM AND SPILLWAY
The selected dam type is a concrete-faced rockfill embankment. (See
Fig. 11.) The downstream face will have a slope of 1.5:1. The upstream face
will have a slope of 1.6: 1. The embankment will be constructed entirely of
compacted rock excavated from the spillway and intake except for a ten-foot-
thick layer of processed gravel on the upstream face which will serve as a
bedding for the reinforced concrete face. The concrete face will be 12 inches
thick at the crest thickening to 18 inches at the toe. Foundation water bar-
rier and cutoff will be achieved by a cutoff slab 2 feet thick and 12 feet
wide and a grout curtain.
The dam will have a crest at El 729.5, including a 3. 5-foot-high
parapet wall, and an overall height of 117 feet. During the PMF, the maximum
XIII-2
water level would be El 729.5. The dam will have a volume of 254,000 cy of
rock and 30,500 cy of processed gravel.
A 75-foot-wide unlined, open channel spillway will be excavated in
the right abutment. The spillway approach channel will extend 100 feet to a
low concrete weir with a crest at El 705. From the concrete weir the chute
will extend 720 feet at a slope of 0.013. From that point it will extend
610 feet at steeper slopes of 0.29 and 0.36, to where it will discharge into
West Creek at a point 450 feet downstream of the toe of the dam.
4. POWER INTAKE
A power intake will be located on the right abutment, adjacent to
the dam. (See Fig. 12.) The intake will be a 96-foot-high inclined reinforced
concrete structure placed against the end of a 110-foot-long approach channel
excavated in rock 10 feet wide at the base. The intake tower will extend
above the maximum reservoir level so that access is possible at all times.
The intake invert will be at El 630. Steel trashracks will be provided. A
12.5-foot-high by 6. 5-foot-wide fixed wheel gate will be provided for emer-
\
gency closure and for inspection and maintenance of the tunnel. A single lane •
roadway, extending across the dam crest from the left abutment, will provide
vehicle access to the power intake for operation and maintenance of these
facilities.
5. POWER CONDUIT
The tunnel will be excavated using a 9.5-foot-diameter tunnel bor-
ing machine. The tunnel will be left unlined except for a 50-foot length at
the upstream end and a lBO-foot length at the downstream end. The upstream
end will be concrete lined to a diameter of 7.5 feet. The downstream end will
be concrete lined for 110 feet and concrete and steel lined for 70 feet, all
to a 7.5 foot diameter. Rock bolts and steel sets will be installed at areas
where the quality of the rock requires the support. The steel sets will be
covered with shotcrete. At the downstream end of the tunnel, a rock trap will
be constructed immediately upstream of the lined section. A 9.5-foot-diameter
surge shaft extending up to El 740 will be excavated adjacent to the tunnel
and connected by a short lateral section. A 1.5-foot-diameter air vent will
extend from the top of the surge shaft to the ground surface.
From the downstream portal a 7. 5-foot-diameter steel penstock will
extend out of the tunnel about 50 feet to a 15-foot-long transition section
reducing the diameter to 3 feet. A 20-foot-long roll-out section in the
7.5-foot-diameter penstock at the portal will allow access into the tunnel for
maintenance when necessary. A 1,520-foot-long, 3-foot-diameter penstock will
extend down the hill to the powerhouse. The penstock will be connected by
couplings and supported on concrete piers on 40-foot centers. Anchor blocks
will be provided where necessary. Before entering the powerhouse, the pen-
stock bifurcates into two 24-inch-diameter branches. A profile of the power
•
•
..
.'
...
..
XIII-3
conduit is shown in Fig. 10. Details of the tunnel and penstock are shown in
Fig. 12.
6. POWERHOUSE
The powerhouse will be an indoor-type structure founded on rock
located about 1,200 feet south of West Creek. (See Figs. 13 and 14.) The
structure will have a cast-in-place reinforced concrete substructure and a
superstructure of precast concrete panels. The roof panels will be removable
to allow access by mobile crane for maintenance of equipment. This will elim-
inate the need for a powerhouse crane. The powerhouse will be 40 feet wide by
57 feet long and 20 feet high. Rock under a parking area adjacent to the
south wall will be drilled and blasted to subgrade but left in place in order
to facilitate future expansion of the powerhouse.
The powerhouse will contain two horizontal shaft 1,200-rpm Francis
turbine-generator units. Each turbine will deliver 4,200 hp at a rated net
head of 635 feet at best gate. The corresponding discharge through each tur-
bine will be 65 cfs. Each turbine will drive a synchronous, three-phase
alternating current generator rated at 3,450 kVA, at 0.9 pf, 12.47 kV and
1,200 rpm with a 60 0 C temperature rise. The plant installed capacity will
be 6,000 kW. Each generator will be enclosed and will include a solid state
exciter, voltage regulator, surface air collers, a C02 fire protection sys-
tem and all necessary auxiliary features.
A 24-inch butterfly valve will be provided upstream of each turbine
to serve as a guard gate for the unit. In addition, a bypass line and valve
to drain the power conduit would be provided. A tailrace channel will be con-
structed to divert plant discharges back into the existing West Creek chan-
nel. The channel will be a combination embankment and fill. It will have a
bot tom width of 5 feet with 1.5: 1 side slopes to a height of 12 feet. The
channel will be lined with a PVC membrane covered with gravel. The tailwater
level will be maintained by a fixed weir to protect the turbines against cavi-
tation.
The plant control system will be designed for fully automatic oper-
ation from a remote location to be determined later. The plant will also be
controllable locally from control panels in the powerhouse. The main control
panel will consist of unit, station and switchyard controls, indication and
alarms. The protective relay board will consist of metering, recording meters
and unit and line protective relays. Miscellaneous controls will be included
as required for all accessory mechanical and electrical equipment •
7. TRANSMISSION SYSTEM
The generator step-up transformer will be located in the switchyard
just south of the powerhouse. The transformer will be rated 7,200 kVA,
13.8-34.5 kV, 3-phase, forced-air cooled, 60 Hz, two-winding with a 55 0 C
XIII-4
temperature rise over an ambient of 40 oc. The switchyard will also include
a 34. 5-kV, three-phase circuit breaker, two 34. 5-kV, three-phase, gang-oper-
ated disconnect switches, current and potential transformers for metering and ~
protection, buswork, and miscellaneous structures.
From the switchyard, a 34.5-kV transmission line will run approxi-
mately 1.2 miles with overhead or underground construction through the park.
The line will then run overhead on wood pole structures approximately
2.8 miles along the existing road to the Skagway Tap Switching Station.
From the tap station a 34.5-kV transmission line will continue
2.2 miles to the Skagway Power Plant. The line will be wood pole structures
typical of the existing distribution lines.
The 34.5-kV transmission line to Haines will leave the tap station
and enter the water north of the mouth of the Skagway River. The line will
consist of four single conductor 35-kV submarine cables. Three cables are
necessary for the three-phase system and the fourth will be a spare in case
there are any problems with one of the other conductors. The cable will be
copper with liquid dielectric impregnated paper insulation, lead sheathing,
and a layer of galvanized steel armor wires. The line will run approximately
16.6 miles to just south of Tanani Point at Haines where it will leave the
water and tap into the Haines-Schnabel Mill tie line at a new Haines Terminal
Switching Station.
8. ACCESS ROADS
Construction materials and equipment will most likely be trans-
ported by sea to Skagway and off-loaded at existing facilities there. From
Skagway a good all-season road runs to West Creek in the area of the power-
house. Some improvement of the existing roads in Dyea may be required to pro-
vide access to the actual powerhouse site. From Dyea a log bridge crosses
West Creek and an old logging road extends 2.2 miles up the West Creek Val-
ley. It is planned that the bridge will be reinforced or replaced and the
existing road improved. From the end of the road a new access road will be
constructed to the dam site. The access road will be single lane, about
16 feet in width and will be constructed to a minimum standard necessary to
support transportation of the construction materials and equipment.
9. DESIGN AND CONSTRUCTION SCHEDULE
A design and construction schedule developed for the Project is
shown on Fig. 19. This schedule contemplates commercial operation of both
uni ts by September 1986, which is considered to be the earliest reasonable
date considering the time required for additional final design investigations,
preparation and processing of the FERC License Application, design, and con-
struction.
..
,
t
•
,j
tr·
•
XIII-5
The schedule assumes that a License Application would be filed with
the FERC in September 1982 and accepted for processing by January 1983. Based
on meeting with regulatory agencies, the only problem currently anticipated
with FERC Licensing is that of the location of the powerhouse within the boun-
dary of the Klondike Gold Rush National Historical Park. Assuming that the
boundary can be changed in a timely manner, the FERC should be able to issue a
License by April 1984. That would allow construction to start in the summer
of 1984. In the meantime, design investigations, design, and preparation of
bid documents would be underway.
Construction would start with mobilization and construction of the
access road to the dam in the summer of 1984. Clearing and grubbing of the
dam abutments and the intake area would also start. During the first winter,
the streambed would be stripped and prepared and the diversion conduits
placed. Once these are in place, the upstream and downstream cofferdams would
be built.
During the second summer, 1985, the spillway would be excavated and
the dam constructed. During the same period the contractor would excavate the
intake channel, prepare the tunnel portal, and start excavating the tunnel
from the upstream end. Rock excavated from the intake and spillway would be
used in the dam. Rock excavated from the tunnel would be spoiled in the res-
ervoir area. Upon completion of the embankment, the concrete facing would be
slip formed. Also during the second summer, the penstock would be con-
structed, the powerhouse civil works and tailrace channel would be completed,
and the transmission line started.
Closure of the diversion conduits would be done during the
1985-1986 winter and the pipes plugged with concrete. Also, the electrical!
mechanical equipment would be received and installed. Filling of the reser-
voir would take an estimated 40 days during the spring runoff. Startup and
testing can take place as soon as the reservoir has enough water to allow safe
operation.
10. FUTURE EXPANSION
As discussed previously, the West Creek site is suitable hydrologi-
cally and topographically for a larger project than that required for Sce-
nario B loads. Thus, it was recognized that a future expansion of the Project
may be desired. For this reason, consideration was given to the possibility
of increasing the capacity of the Project and raising the dam.
The Scenario C loads require an installed capacity of 9,000 kW and
an annual generation in 1996 of 39,000 MWh which means a reservoir with a
normal maximum level at El 725. This would mean raising the dam 20 feet. The
crest of the spillway could be raised using a higher concrete weir in the same
channel. In addition, the intake gate shaft would have to be raised, the
surge shaft enlarged, and another penstock added. Another unit could be added
to the powerhouse by extending the building.
XIII-6
Raising the dam would require quarrying additional rock and placing
it against the downstream face. Once the fill has been raised to the desired
crest elevation, the parapet wall at the top of the original dam would be
removed and concrete facing continued up to the new crest.
The unlined tunnel can safely handle velocities up to 5 or 6 fps.
Assuming a maximum velocity of 5 fps, the maximum discharge would be 350 cfs.
This would permit an installed capacity of 16,000 kW. With this capacity and
a plant factor of 50%, a reservoir with a maximum normal level of EL 755 would
be required. Expansion of the Project to this size would require similar, but
more extensive work than described above. In order to raise the reservoir
normal maximum level to El 755, a new spillway would probably be required.
This spillway could be built in the left abutment. Again, material excavated
from the spillway would be used in the dam embankment.
•
..
•
•
..
•
•
SECTION XIV
EFFECT ON ENVIRONMENT
OF THE SELECTED PROJECT ARRANGEMENT
1. GENERAL
The following discussion addresses potential impacts and mitigation
with respect to fisheries resources, wildlife resources, water quality, his-
torical and archaeological resources, socioeconomics, recreational resources,
aesthetic resources, air quality, and land use. Environmental studies found
that the environmental impacts of the West Creek Project are limited in scope
and not expected to significantly affect Project development. A report by the
consul tant, Environaid, describing on-site environmental investigations pro-
vides the basis for discussion of the fisheries, wildlife, and historical and
archaeological resources and is included in Appendix C.
2. FISHERIES RESOURCES
Few fisheries resources are known to occur in West Creek based on
field observations, fish sampling and inteviews with local residents. Conse-
quently, impacts on the fisheries resources are expected to be minimal. The
following presentation describes the habitat and fisheries resources of West
Creek, and discusses potential Project impacts.
Above the dam site, the creek is a stream of moderate gradient,
turbid waters, and predominantly boulder, cobble, and gravel substrate. There
are a number of small tributaries of relatively clear water with suitable sal-
monid spawning substrate. These tributaries were in the general area of the
proposed reservoir and would be the most probable location of residential
fish. Attempts were made to sample fish with minnow traps in three of the
tributaries. However, no fish were encountered. Reports by residents at
Skagway and Dyea indicate that few if any fish reside or spawn in waters near
the proposed dam site.
Below the dam site, the upper gorge has a steep gradient and con-
tains a series of cataracts and chutes. Upstream fish passage is extremely
difficult if not impossible, at least during the periods of high flow from May
to November.
Further downstream within the middle basin, high velocity flows
persist and the substrate is predominantly boulder and cobble. Little rearing
or spawning habitat occurs in the stream channel in this area. However, two
small tributaries enter this section that contain good quality spawning gravel
in their lower reaches. Sampling of these tributaries with minnow traps re-
vealed a low density, slow growing population of Dolly Varden char that is be-
lieved to be resident rather than anadromous •
XIV-2
The lower gorge just below the middle basin is an extended section
of rapids and falls. The sustained high velocity of this reach appears to
prevent upstream passage by fish and, therefore, would block use of the creek
above this point by anadromous fish.
Between the lower gorge and its mouth, West Creek widens and the
velocity is reduced. As the creek approaches its confluence with the Taiya
River, the gradient declines and the substrate changes from boulder to cobble,
gravel, and finally sand at the confluence. There is a single tributary on
the north side of West Creek below the bridge that connects to a cutoff mean-
der channel. Large Dolly Varden have been observed in the tributary but no
other fish have been seen in this small stream or in West Creek. The possi-
bility exists that a few fall chum or coho may utilize the tributary or lower
West Creek. Eulachon (candlefish) are known to spawn in the lower Taiya River
and are reported to spawn in the lower sandy reaches of West Creek.
Sources of potential impacts on fisheries resources include inunda-
tion of stream habitat by the reservoir, alterations of the West Creek flow
regime due to Project operation, increased turbidity and sediments from con-
struction activity, changes in stream temperature due to the reservoir, and
nitrogen supersaturation from water plunging over the spillway.
The reservoir would inundate approximately 2.5 miles of stream
habitat in West Creek and small amounts of stream habitat in the lower reaches
of three minor tributaries (Fig. 16). Because there is no evidence of fish
populations in this general area, it appears that no fishery impacts would
result from inundating the upper valley. The indicated lack of fish resources
also eliminates any concern for turbine-related injuries or mortalities of
fishes entering the power intake from the reservoir.
The proposed Project would cause changes in the flow between the
dam and the powerhouse. During the low flow months, December through April,
there would be no flow below the dam. The lack of flows could extend into
early summer as the reservoir fills. In summer and early fall, the flows
would be much greater as melt-water flows fill the reservoir exceeding genera-
tion requirements and result in excess water being spilled. In general, how-
ever, flows would still be less than under natural conditions. (See Sec-
tion XI, Power Operation Studies.) However, little impact on fisheries is
expected in West Creek between the dam and the powerhouse because no fish are
known to reside in or migrate through the creek above the lower gorge. The
small population of resident Dolly Varden char, known to exist in the lower
sections of the two tributaries of this part of West Creek, should not be sig-
nificantly affected by the reduced flows.
Below the powerhouse site, the major changes in the flow regime
would occur during the winter and spring months. The principal demand for
power is from December to April which are generally low flow months in the
watershed. During this period, generation would come from reservoir storage.
Thus, average daily flows below the powerhouse would increase during the
winter and spring. Substantial daily variation in flow would occur because
.. .,
•
•
•
•
..
XIV-3
power generation would be keyed to the daily cycle of electrical load demand.
This may cause flows to be less than what would occur under natural conditions
for a part of the day and greater for the remainder. These effects could con-
tinue into early summer while the reservoir is filled. During the naturally
high flow months of summer and early fall, the average daily flows would not
change and the daily variations associated with electrical load demand would
be small relative to the magnitude of the total flows resulting from spill.
The changes in the flow regime of lower West Creek are not expected
to impact fish access to or use of the single tributary where Dolly Varden are
known to occur. Flow variations in the winter and spring could affect fish
spawning or rearing activities in lower West Creek; however, indications are
that little if any of these activities exist with the exception of spring
spawning of eulachon.
Turbidity and sediments may increase in West Creek because of
blasting and other construction activities. This would result in transient
impacts on the stream habitat, fishes, and other aquatic organisms. Currently
accepted, prudent construction practices would be implemented to minimize
these effects, including proper application of bank stabilization, control of
surface runoff, reclamation, and revegetation measures.
No significant alterations in the water temperature regime are
anticipated to result from the effects of the proposed reservoir or operation
of the Project; therefore, no fisheries-related impacts would be expected.
Stream temperatures are currently being monitored, and potential water temper-
ature changes will be evaluated after one year's temperature record is com-
pleted in the summer of 1982.
Supersaturation of nitrogen in the stream waters below a dam could
impact fisheries resources. This phenomenon can develop from waters plunging
over a spillway into a stilling basin below a dam. Nitrogen supersaturation
causes gas bubble disease in fishes and is destructive to both juvenile and
adult fishes. The chute spillway planned for the Project would not cause
supersaturation of nitrogen.
Sport or subsistence fishing opportunities in West Creek are lim-
ited by the available fish resources. No fishermen were encountered during
Project studies on West Creek. Fishing for Dolly Varden in the tributary near
the creek mouth and dip netting for eulachon in lower West Creek appear to
present the best opportunities. No impact on sport or subsistence fishing is
expected.
The Taiya River supports runs of coho, chum, pink, Dolly Varden,
and eulachon. Impacts of West Creek flow variations, possible turbidity
increases, and possible temperature alterations on these fish resources are
expected to be minimal because West Creek contributes only 30% of the total
flows of the Taiya River.
XIV-4
The submarine routing of the transmission cable from Skagway to
Haines would have little impact on marine organisms. Minor physical disrup-
tion of marine benthic and intertidal communi ties would occur when the cable
is laid. Electrical and magnetic-field effects of the 34.5-kV insulated cable
would be minimal and localized with little-to-no physical or behavioral ef-
fects on fishes and other organisms. There may be some risk of fishing gear
or anchors fouling on the transmission cable.
The major mitigation concerns for fisheries are to assure no impact
from nitrogen supersaturation through proper design of the spillway and to
maintain the alluvial channel in West Creek below the powerhouse and gorge.
The latter provision would allow fish access to the tributary on the north
side of the creek below the bridge. It is unlikely, however, that the Project
would adversely affect access to the tributary. A more complete assessment
will be made after topographic mapping of the lower creek section is completed
and Project layout has been determined. No mitigation activity would be re-
quired for the Dolly Varden in the tributaries of the middle basin because the
populations are not expected to be significantly affected by any changes in
habitat due to alterations of West Creek flows.
Two fisheries enhancement possibilities have been suggested: ( 1 )
providing a water supply source for a hatchery at the tailrace; and (2) modi-
fying the tailrace to serve as a spawning channel. It is expected that imple-
mentation of either enhancement measure would entail development of required
fish facilities by the Alaska Department of Fish and Game (ADF&G) or the
Northern Southeast Regional Aquaculture Association (NSRAA). Factors to con-
sider in evaluating the potential of the hatchery or spawning channel include
quality of water from the reservoir, the capacity of the Taiya River and Taiya
Inlet to support an increase of outmigrants, the availability of fish stocks
to be used in the facilities, and specific effects of a propagated run on ex-
isting fisheries and management of the fisheries. Discussions have been ini-
tiated with ADF&G and NSRAA regarding the possibility of developing a spawning
channel in the tailrace. Further consultation with these agencies is expected
to better assess these fisheries enhancement opportunities.
3. WATER QUALITY
West Creek is a glacially-fed stream with highly turbid waters,
particularly during the high flow months of summer. Water temperatures range
from less than 10 0 C in the summer down to OOC in the winter. Dissolved
oxygen is high because of the low temperatures and cascading passages. The
clearcut area on the north side of the middle basin (Fig. 16) has been revege-
tated and does not affect stream water quality. Currently, there is no known
human activity or development in the watershed that has any significant impact.
No significant effects on water quality would be expected from the
Project. Temporary increases in suspended sediments and turbidity would occur
in West Creek during construction due to erosion associated with clearing and
grading of lands, spoil disposal, road use, and blasting at the dam site.
..
•
..
..
•
XIV-5
Standard prudent construction industry practices including proper bank stabil-
ization, runoff control, and revegetation of exposed soils would minimize im-
pacts on water quality.
~ Subsequent to construction, the reservoir would act as a sediment
trap removing larger sediments from the downstream flow. Generally, only col-
loidal-sized particles would remain in suspension by the time waters passed
out of the reservoir. There is, however, the potential for erosion of the ex-
posed banks of the reservoir during periods of drawdown. This could have the
• effect of increasing turbidity in the reservoir and downstream.
..
•
No major alterations of the water temperature regime would be ex-
pected. The proposed reservoir could cause a slight delay in warming of the
stream in the spring and cooling in the fall. An evaluation of potential
Project effects on water temperature will be made at the completion of ongoing
stream temperature monitoring studies during the summer of 1982.
4. WILDLIFE
The major wildlife species in West Creek Valley are mammals and
birds. Common mammalian species include black bear, mountain goat, various
furbearers, and several species of voles and mice. The Sitka black-tailed
deer, moose, and wolf are not found in the valley. A few brown bears may
include portions of West Creek within their home range, and there have been
occasional sitings of wolverine and coyote. Bird species include various
waterfowl, grouse, and the bald eagle. Many other birds, such as other rap-
tors, shore birds, and passerines, also occur in the valley. No Federally-
listed endangered or threatened species reside in the Project area.
The principal impacts on wildlife would result from inundation of
habitat by the storage reservoir, loss of habitat on lands required for Proj-
ect structures, disturbance of wildlife by construction activities, and wild-
life disturbance associated with improved public access.
The storage reservoir would inundate approximately 600 acres of
conifer forest, riparian shrub, and sedge marsh. Most of the resident wild-
life would be immediately lost. Birds and larger mammals would be dislocated
to other areas. These animals could only become established on adjacent habi-
tat if those areas were capable of supporting them.
Indications are that black bear occupy virtually all of the valley
floor and forested slopes and, therefore, have fully partitioned the habitat
of the watershed among the population. Loss of habitat to the reservoir would
require a readjustment of individual bear home ranges and if the remalnlng
habi ta t is fully occupied, the loss of one or more bears from the watershed
could occur.
The side slopes of the valley support a stable mountain-goat popu-
lation. The reservoir and other Project features would not be expected to
affect any of their habitat and would have no direct impact on the population.
XIv-6
The elimination of habitat would impact small mammals that are
abundantly distributed in the area of the proposed reservoir, including deer
mice, least shrews, porcupines, and red squirrels. Furbearers such as river
otter, marten, least weasels, and mink may also be impacted. Some benefits to
furbearers would be derived from the reservoir's new riparian habitat although
these benefits would be tempered by the annual fluctuations of the reservoir
surface.
Birds would be only slightly impacted by reservoir inundation. The
proposed reservoir area contains less than 3 acres of waterfowl habitat or
approximately half of the open stillwater habitat in the valley. In addition,
the reservoir would inundate only one square mile of poor quality grouse habi-
tat or about one-eighth of the total grouse habitat in the watershed. Virtu-
ally all of the bottomland to be inundated has some habitat value for the gen-
eral avifauna. The impacts due to the inundation of bird habitats are ex-
pected to be small.
At maximum pool elevation, the reservoir would create 600 acres of
standing water with approximately 5 miles of shoreline and associated shal-
lows. It is probable that more waterfowl habitat would be created than de-
stroyed, although the habitat quality would be influenced by the extent and
timing of reservoir drawdowns. The reservoir would displace a small number of
grouse, but the effect on the overall grouse population would be minor. Num-
bers of some species of the general avifauna would be reduced and others in-
creased, but no species would be eliminated. In fact, habitat may be created
for new species resulting in a more diverse avifauna overall.
Additional habitat losses, with fewer though similar impacts on
wildlife, would develop from emplacement of Project structures. The impacts
would be smaller in scale and would result from building the dam, surface pen-
stock, powerhouse, access roads, and transmission line. Minimal effects would
resul t from construction of the power tunnel because the overlying land sur-
face would remain undisturbed.
Localized disturbance to wildlife would be caused by construction
activities such as blasting, road use, heavy equipment operation, and tunnel
boring. Changes in wildlife distribution and behavior, such as relocation of
black bear home ranges, would be expected. These changes would be temporary
and subject to readjustments on completion of construction.
Presently, the West Creek valley supports little recreational hunt-
ing or wildlife observation activities, probably because access is limited by
the steep valley walls and dense bottomland vegetation. The possibility ex-
ists that road improvements associated with Project development would, by im-
proving access, encourage an increase in wildlife use. The Alaska Department
of Fish and Game is interested in any associated increase in hunting pressure
on mountain goats in the valley. The West Creek goat population appears capa-
ble of sustaining a larger harvest than it has experienced in recent years.
• ..
•
,
..
•
•
•
XIV-7
No major wildlife mitigation measures are planned because no signi-
ficant detrimental effects on the populations of any wildlife species are
anticipated. Planned mitigation measures include minimizing the clearing of
vegetation to curtail destruction of habitat during construction; locating the
access road and other Project features to minimize disruption of the travel
routes of wide-ranging mammals within the narrow valley-bottom corridor near
the dam site; revegetating areas denuded during the construction process; and
designing the above-ground sections of the transmission line to minimize
potential impact on rap tors such as the bald eagle •
5. HISTORIC AND ARCHAEOLOGICAL RESOURCES
Potential impacts on historic and archaeological resources were
evaluated based on field reconnaissance, review of ethnographic literature,
and interviews with local residents. The evaluation focused on locations of
potential ground disturbance associated with construction of the dam and res-
ervoir, power tunnel, powerhouse, and transmission line. Archaeological and
historical field investigations were limited to surface inspection of study
areas. No excavations or test pits were dug in compliance with agreements
with the National Park Service and the Alaska State Historic Preservation Of-
ficer.
No cultural resources were found at the proposed dam site, within
the proposed reservoir, or in the areas of expected construction activity
associated with the power tunnel or powerhouse. Consequently, no impacts on
historic and archaeological resources are expected relative to the development
of these Project features.
The transmission line could be buried throughout its route within
the National Park to avoid negative aesthetic impacts. Within the National
Park and along the west side of the Taiya River, the transmission line corri-
dor would cross the historic Chilkoot Trail, northern portions of the Dyea
community, and other areas of gold rush activity (Fig. 17). In this same gen-
eral area, parts of the native Village of Dyea may have existed, though its
presence was not identified during current field investigations. Evidence of
the pre-gold rush native village may have been overlain by or incorporated
into subsequent site developments •
Although the potential exists for cultural impacts west of the
Taiya River, the area has been disturbed by relatively recent activities. The
short section of the corridor between the powerhouse and Dyea Road is criss-
crossed with roads and tracks. It contains houses, sheds, and barbed wire
fencing along with abandoned wood stoves, large kitchen appliances, motor
vehicle parts, and other contemporary discarded materials. Parts of the area
have been selectively logged. The State Department of Transportation and Pub-
lic Facilities has cleared the roadside within the right-of-way. The trans-
mission line would likely be located within this roadside clearing. The road,
built in the 1940's, was cleared by pushing the vegetation and topsoil to each
side. There is some disturbance beyond the roadside where excess construction
XIv-8
material was deposited. Most cultural resources of the gold rush period are
located away from Dyea Road, although the Chilkoot Trail crosses the road
approximately 0.1 mile northwest of the Taiya River bridge.
After determining the exact transmission route within the corridor
on the west side of the Taiya River, additional archaeological/historical
investigation would be required. Final location of this section of the trans-
mission line would necessitate consulting with and obtaining approval of the
Alaska State Historical Preservation Officer and the National Park Service.
Four potential areas of concern were found within the transmission
corridor on the east side of the Taiya River Valley: the modern Chilkoot
Trail and trailhead; the wooden structures and out-buildings east of Dyea Road
at Mile 8.4; the National Park Service ranger station at Mile 8.3; and the
marine shell deposit at Mile 8.0 (Fig. 17). By avoiding these areas in final
routing, the need for investigating these sites further may be eliminated.
Similarly, in the corridor section between the Taiya River and
Skagway, potential impacts would be eliminated by avoiding specific areas con-
taining cultural materials. These materials include a single steel wire tele-
graph/telephone line that runs over the east ridge at about Mile 6.6 and, of
less significance, the shed and possible other materials at the trailhead of
the Skyline Trail, the pet cemetery, and the suspension bridge remains near
the Skagway River (Fig. 17).
Mitigation for historical and archaeological resources usually
takes two forms: avoidance of impacts by relocating Project facilities and
scientific data recovery. Pending results of additional surveys in the sensi-
tive areas noted above, no specific mitigation requirements are indicated at
this time. The potential does exist for cultural remains to be encountered
unexpectedly during construction. In that event, investigation of the find
would be necessary to determine its value and whether mitigation would be nec-
essary.
6. SOCIOECONOMIC
The principal socioeconomic impacts would be the housing needs and
payroll spending of temporary construction workers on the Ci ty of Skagway.
The Project site is located within Skagway's corporate limits approximately
10 miles by road from the center of Town.
It is common practice in Alaska for dam construction workers to
live in "bachelor quarters" near a project site. The remote location of many
construction sites, the need to import workers with special skills, transpor-
tation difficulties, and union requirements to provide worker transportation
between the job site and the place of worker residence all contribute to this
practice. Except for workers already living in the local area, Alaska dam
construction projects usually have few workers accompanied by dependents. Be-
cause housing would be provided by the construction contractor at the Project
•
..
•
..
•
XIV-9
site, the average work force of 100 men would have little impact on the City
of Skagway's summer housing shortage, schools, and other facilities. However,
if the City of Skagway adopts land use policies that would restrict the loca-
tion of temporary housing at the Project site, the impacts of temporary con-
struction workers on the City's housing stock and public facilities would re-
quire further investigation.
The construction contractor would provide meals for workers living
at the construction site. Some supplies would likely be purchased locally.
Most construction equipment and materials are not available locally and would
be purchased from available sources located outside Alaska and transported to
the site either by sea, road, or rail. A portion of the construction workers'
payroll would be spent for entertainment and personal supplies in Skagway.
Another possible socioeconomic impact would be a tax loss to the
City of Skagway due to the purchase of private lands for the Project. Project
lands and properties would not be taxable as public assets. However, the
amount of private land to be used for the Project is very small. The Project
reservoir and dam site are located almost entirely on State land. A portion
of the reservoir would include State lands which have been allocated to the
City of Skagway for future private sale. (See Fig. 18.) Ten acres of National
Park land would probably be used for the powerhouse site. Approximately
2 acres of private land would be used for the tailrace as well as approxi-
mately 2 acres of State lands and 4 acres of National Park lands. The as-
sessed value of the private land and Skagway allotment lands currently is
estimated to equal about $75,000 (Charles Horan, December 1, 1981).(14) The
value of the remainder of State lands is estimated to equal about $250, 000.
In the area of the Project, the City of Skagway levies a property tax on the
assessed value of private land of 19% of $4. 00 per $1, 000 assessed value or
$0.76 per $1,000. Possible tax revenue losses from private lands and State
allotment lands (if sold for private use) currently would equal about $60 a
year. In 1981 the City did not assess personal property, indicating no off-
setting tax revenue would accrue from a tax on the value of construction
equipment to be located at the Project site. If the tax were collected, it
would be assessed at the same rate as for property tax.
The State-maintained Dyea Road will provide public access to the
Project site. The road may have short periods of restricted travel when con-
• struction equipment is being mobilized. Equipment could be moved during peri-
ods of light traffic and would avoid periods of peak summer use of the Klon-
dike Gold Rush National Historical Park. No permanent road closures or modi-
fications of the State road would be required during or after Project con-
struction.
The Project area is not served by electric or telephone service.
The site is not within the franchise service area of the local private elec-
tric and telephone company. Construction would require providing electric and
telephone service at the Project site. Electrical service could be provided
by the construction contractor or purchased from the electric utility.
XIV-10
Providing electric and telephone services to the Project offers the
possibility of providing one or both of these services to local residents liv-
ing in the Taiya River Valley near the Dyea Road. Since this opportunity for
service occurs outside the franchise area of the electric and phone company, a
mechanism for financing these improvements would need to be developed. The
small population of the area may make the cost of improvements difficult to
finance. The impact on future residential development in the area would also
need to be considered. The National Park Service would be a major participant
in any discussions on extending electrical or telephone service wi thin the
park boundary.
7. RECREATIONAL RESOURCES
The Chilkoot Trail Unit of the Klondike Gold Rush National Histori-
cal Park is the only established recreation facility in the vicinity of the
Project. This Unit totals approximately 9,100 acres and consists of a corri-
dor of parkland approximately one mile wide and 17 miles long, paralleling the
entire length of the Chilkoot Trail within the United States. The Unit lies
principally in a north-south direction, with the south boundary extending to
saltwater at Taiya Inlet and the north boundary located at Chilkoot Pass on
the United States-Canadian border. Included in the Unit are the historic
townsite of Dyea, the 36-campsite Dyea Campground, the Chilkoot Trail, and all
related historic sites and artifacts along the trail and in the vicinity of
Dyea. The modern Chilkoot Trail begins where the Dyea Road crosses the Taiya
River. The trail is located on the east side of the river and traverses Chil-
koot Pass to Lake Bennett, Canada. (15,16) More than 2,500 hikers traveled
the trail in 1981 with almost 80% of the use occurring in the months of July
and August. (17)
There are several trails in the vicinity of the Project in addition
to the famous Chilkoot Trail. The little-used Lost Lake Trail begins on the
west side of the Taiya River Valley about .75 mile south of West Creek near
Dyea. (See Fig. 16.) The trail climbs steeply for about 2 miles to Lost Lake
which is nestled on the slope above the Taiya Valley. The only other trail is
the Skyline and AB Mountain Trail which begins from the Dyea Road near Yaku-
tania Point and extends 6 miles north to AB Mountain. Most hikers only travel
the first 3 miles to a viewpoint of Skagway and Taiya Inlet.
There are no recreational facilities located in the West Creek Val-
ley. A logging road extends for approximately 2 miles from the Taiya Valley
into the lower West Creek Valley, but not as far as the proposed dam site. An
informal trail beginning at the road's end provides access to the upper val-
ley. Some residents of Skagway hunt, hike, and pick berries within the middle
section of West Creek Valley. Some firewood is gathered in the lower valley.
The Haines-Skagway Area Land-Use Plan classifies the West Creek
Valley as public recreation land. Alaska Department of Natural Resources'
management policy recommends that this area be managed in a manner that per-
mi ts existing recreational uses to continue and is compatible with Klondike
Gold Rush National Historical Park objectives. (18)
.. .,
..
•
•
..
XIV-11
During construction, access to the West Creek Valley for recreation
would be limited. However, there is the possibility of providing a dam over-
look to accommodate public interest in construction activities. Construction
activity, traffic, and noise may affect the recreationists at Klondike Gold
Rush National Historical Park, particularly at the Dyea Campground, and hikers
along the first 2 miles of the modern Chilkoot Trail. This impact would pri-
marily occur in July and August when the majority of people visit the Park.
There should be no impact to tourists visiting Skagway and the Skagway River
Valley nor to the cruise ship, ferry, and airplane travelers in the region.
Maintenance of the road to the dam would improve access to the val-
ley. The reservoir and improved access could stimulate recreation use in the
Project area. In addition to the possibility of a dam overlook, other possi-
ble recreation facilities include a hiking trail to Upper West Creek Valley
and a boat launch ramp. Recreationists would probably be primarily Skagway
residents. Visitors to the Project area would have to travel through the
National Park but there should be minimal impact to existing Park uses and
management objectives. (18)
8. AESTHETIC RESOURCES
Most of the Taiya River Valley floodplain is included in the Klon-
dike Gold Rush National Historical Park. The Dyea Road, running from Skagway
through the valley, is frequently traveled by tourists and residents. The
vegetation of the valley is mixed coniferous-deciduous forests (western hem-
lock, mountain hemlock, Sitka spruce, alpine fir, lodgepole pine, black cot-
tonwood, alder, willow, and poplar) and provides dense cover during the summer
except along areas that have been cleared, such as roadways. Visitors and
residents alike have a high appreCiation for scenic values.
Project impacts that would affect residents and visitors to the
Klondike Gold Rush National Historical Park would occur in the Taiya River
Valley. During construction, traffic would increase, the noise of clearing,
grading, blasting, and other activities would be evident, and scenic values
would be diminished by construction of Project features such as the penstock,
powerhouse, tailrace, and transmission line. Construction activity, though
temporary, would be greatest during the months of July and August when most
National Park visitation occurs •
Subsequent to construction, impacts would be minimal because of
mitigative measures incorporated into Project design, particularly as they
apply to the penstock, powerhouse, tailrace, and transmission line. The
3-foot-diameter, 1,520-foot-long penstock is located on the west sideslope of
the Taiya River Valley on State of Alaska land and in part within the National
Park boundary. The 25-foot-high concrete powerhouse and 1,150-foot-long tail-
race are located within the National Park. The penstock, powerhouse, and
tailrace might be visible from the Lost Lake Trail, several points along the
XIV-12
Chilkoot Trail, the Dyea Road, and several residences in the Taiya River Val-
ley. The National Park Service and State of Alaska have a cooperative manage-
ment a,reement to protect the scenic qualities of the Taiya River Val-
ley. (19 Mitigation measures to protect the scenic resources will include
painting the penstock and revegetating the right-of-way to blend in with the
existing landscape.
The transmission line could be located underground where it passes
through the National Park. Most of its route between the powerhouse and Skag-
way would probably parallel the Dyea Road, resulting in reduced clearing re-
quirements for the right-of-way. Between the National Park and Skagway, the
line would be single-pole construction supporting stand-off insulators and
would be designed to minimize any adverse impacts to scenic value. Submarine
routing of the transmission line between Skagway and Haines would eliminate
potential aesthetic impacts along Taiya Inlet.
The dam and spillway would impact the scenery in upper West Creek.
However, there is currently little public use of this area and these facili-
ties would not be visible from the National Park or the Taiya Valley.
9. AIR QUALITY
The air quality within the Skagway City limits is excellent.
Winds, often in excess of 20 mph in Skagway and the nearby river valleys, and
the lack of air pollution sources prevent concentration of air contaminants.
No polluting industries are located within the City of Skagway, and no sources
of air pollutants exist which require a Federal or State operating permit.
The nearest permitted sources of air contaminants are located in Haines.
These sources are some 20 miles distant from the Project and do not affect air
quality in the Skagway area.
The Project is located within the Southeastern Alaska Intrastate
Air Quality Control Region (SAIAQCR). The entire air quality control region
is under the jurisdiction of the Alaska Department of Environmental Conserva-
tion. For this air quality control region, the State of Alaska has determined
that for all regulated air pollutants (total suspended particulates, nitrogen
oxides, sulfur oxides, photochemical oxidants, carbon monoxide, and lead) the
ambient concentrations fall within all Federal and State air quality standards
(Alaska Department of Environmental Conservation, 1980). The Project study
area (and the entire SAIAQCR) is designated an attainment area for all regu-
lated air pollutants. (20)
During the construction phase of the West Creek Hydroelectric Proj-
ect, pollutants emitted to the atmosphere would be of two types: fugitive
dust generated by transportation and construction activities, and gaseous
emissions from internal combustion engines. The fugitive dusts would result
from land clearing, road construction and maintenance, blasting, site prepara-
tion, rock crushing, concrete batching, and vehicular traffic. Gaseous emis-
sions would be produced from internal combustion engines and would consist of
•
..
XIV-13
oxides of nitrogen, carbon monoxide, sulfur dioxide, and hydrocarbons. In
general, these emissions would be temporary, lasting only during the construc-
tion phase and would not significantly impact air quality.
Additional pollutants would be emitted from the reservoir clearing
operations and during periods of forest residue burning. These emissions
would consist of particulates, carbon monoxide, hydrocarbons, and oxides of
nitrogen. These emissions would be localized and temporary, and would have no
long-term air quality impacts in the study area.
There may be a minor increase in local fog in the vicinity of the
reservoir. However, operation of the West Creek Project would not cause or
contribute to any air quality impacts in the study area.
10. LAND USE
As shown in Fig. 18 and Table XIV-1, most land in the Project
vicini ty is State selection land which is being transferred from the Federal
Government. Some of this land has been alloted to Skagway for eventual pri-
vate sale. The Federal Government also owns about 600 acres included in Klon-
dike Gold Rush National Historical Park. Only about 55 acres, or 0.3%, of
lands in the vicinity of the Project, are privately owned.
The Department of Natural Resources, in its Haines-Skagway Area
Land Use Plan, has classified State selection lands in the West Creek Valley
for recreation use.(18) The intent of the classification is to keep the
valley in an undeveloped state. However, the plan classification can be
changed to meet new land use requirements. Modification of the plan will
require a public hearing with legal notices. The process would probably take
6 months to 1 year.
Construction of the Project would require about 10 acres of
National Park land for the powerhouse site. The tailrace right-of-way from
the powerhouse to West Creek would use about 8 acres of private, National Park
and State land. A penstock would cross State and National Park land for a
distance of about 1,400 feet on the hillside located above the powerhouse.
The dam and reservoir would use about 600 acres of State land of which about
~ 100 acres is Skagway allotment land. (See Fig. 18.) Additionally, an easement
or right-of-way across private land and an easement along the State highway
right-of-way would be required for the transmission line.
The proposed powerhouse site, tailrace, and portions of the pen-
stock and transmission line would be within the boundary of the National
Park. An Act of Congress would be required to allow construction of a power
plant on any land which is within a National Park boundary or to relocate the
park boundary. However, it is possible that permission to build the transmis-
sion line within the National Park boundary can be secured administratively.
XIV-14
The principal land use change associated with the Project would be
the flooding of the partially-wooded upper West Creek Valley. The lower ele-
vation, eastern part of the valley, has some commercial forests of spruce and
hemlock. The area to be inundated by the reservoir is in the upper part of
the valley where soil conditions and drainage are generally not conducive to
commercial forest production.
The land to be used for the powerhouse and tailrace is covered pri-
marily with brush and cottonwood trees. Adjacent privately-owned bottomlands
of brush and pasture would be crossed by the transmission line from the power-
house to the State highway. The transmission line would then follow the State
road except at a point where a hillside is crossed at the head of Nahku Bay.
The State highway right-of-way crosses through lands owned by the National
Park Service and Skagway State allotment funds.
Except for two unoccupied cabins, no structures would be lost due
to Project construction or operation. No valuable agricultural lands in the
area would be impacted by the Project. No permanent garden plots or improved
pasture lands in private ownership would be used for the powerhouse site or
transmission line route. A local access dirt road adjacent to the proposed
route for the powerhouse tailrace may lie within the Project boundaries. Road
access would still be maintained.
..
..
..
•
..
..
..
•
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
PROPERTY OWNERSHIP IN PROJECT VICINITY·
Category
Federal:
Bureau of Land Management •••••••
Park Service ................... .
State Selection Lands (excluding
Skagway allocation lands and
private claim lands):
Skagway Allocation ••••••••••••••
Private Ownership •••••.•••••••••
Private Claim for State Land ••••
Taiya Inlet ••••••••••••••.••••••
Total ........................ .
Area Within Klondike National Park
Boundary ....................... .
Approximate Number
of Acres
640
590
18,520
230
55
330
120
20,480
2,230
• See Fig. 18 for boundaries of area used in Table •
Source: Planimeter estimates made from maps
contained in following publications:
TABLE XIV-1
Percentage of
Total Area
3.1
2.9
90.4
1 • 1
0.3
1.6
0.6 --
100.0
10.9
Alaska Department of Natural Resources, Haines-Skagway Area
Land Use Plan, June 1979.(18)
U.S. Department of Interior, National Park Service, Klondike
Gold Rush National Historic Park Land Acquisition Plan (Draft),
April 11, 1980. (21 )
..
•
•
SECTION XV
PROJECT COSTS
1 • GENERAL
Project capital and annual costs were estimated for input to the
economic analysis discussed in Section VI. Direct Construction Cost estimates
for the Project were prepared for the selected arrangement based on the pre-
liminary design layouts and details discussed in the previous section. The
Total Investment Cost was arrived at by summing the Direct Construction Costs
of each major Project component and adding Indirect Costs and Interest During
Construction. The effect of escalation was considered and the Total Invest-
ment Cost adjusted to reflect a project on-line date in January 1982.
Annual operating costs such as operation and maintenance, owner
administration, insurance, and interim replacements were estimated.
2. PROJECT CAPITAL COSTS
a. Direct Construction Cost
This cost includes the total of all costs directly chargeable to
the actual construction of the Project, which can be considered equivalent to
a contractor's bid based on a January 1982 bid price level, and reflects esti-
mated inflation of costs which would occur during the 2-1/2-year construction
period. This corresponds to the Project entering into service in July 1983.
The Direct Construction Cost was developed based on unit prices
from actual contractor's bids on similar projects, adjusted to reflect loca-
tion, project size and bid price level and applied to quantities estimated for
the major construction features. A contractor's estimate of the tunnel was
independently made by Diversified Constructors, Inc. Mechanical and electri-
cal item costs were based on preliminary quotations from equipment suppliers,
catalog values and experience costing data. Detailed Direct Construction Cost
estimates for the Project are shown in Table XII-2.
b • Contingencies
To allow for unforeseen conditions during construction and miscel-
laneous items not included in the estimate, an allowance of 20% for Contingen-
cies was applied to the Direct Construction Cost of major civil items and 15%
to the Direct Construction Cost of the powerhouse electrical and mechanical
equipment, and the transmission line. The costs of recreation facilities and
mitigation were assumed to be very small and are included in the contingency
allowance.
XV-2
c. Engineering and Owner Administration
Engineering and Owner Administr~tion costs are based on actual
experience with costs for similar work. This item includes all preliminary
engineering work; Project feasibility and environmental studies; field inves-
tigations; applications for and processing of required permits and licenses;
final design and preparation of construction contract documents; inspection of
construction; and Owner Administration. An allowance of 15% of the sum of the
Direct Construction Cost plus Contingencies is considered a reasonable esti-
mate for this item.
d. Total Construction Cost
The Total Construction Cost includes the Direct Construction Cost
plus Contingencies and Engineering and Owner Administration. A summary of
Project costs showing all cost factors leading to the Total Construction Cost
is shown in Table XII-1. The Total Construction Cost for the Project with a
bid date of January 1982 is estimated to be $61,324,000.
e. Interest During Construction
Interest During Construction (IDC) is dependent on the interest
rate at which money is available for the Project and the cash flow during con-
struction. Using the inflation-free interest rate of 3% (as discussed in Sec-
tion VI) and typical cash flow patterns for projects similar to the West Creek
Project, IDC was calculated to be 3.6% of the Total Construction Cost.
f. Total Investment Cost
The Total Investment Cost (TIC) is the sum of the Total Construc-
tion Cost and Interest During Construction. The TIC for the West Creek Proj-
ect is $63,532,000. This TIC is for a Project bid in January 1982 and coming
on-line in June 1984.
g. Escalation Adjustment
The cost estimates discussed above include estimates of escalation
over the 2-1/2-year construction period. Thus, they represent a project com-
ing on-line in June 1984. In order to compare project feasibility in the man-•
ner prescribed by the APA, it was necessary to take escalation out of the
estimate. This would give an "inflation-free" estimate for a project which
would theoretically be built at January 1982 costs of material and labor.
Escalation was estimated to be 12% of the TIC. Thus, the TIC for an "infla-
tion-free" project would be $55,908,000.
3. ANNUAL COSTS
The principal annual cost of any hydro project is the debt service
on the capital cost. Since the financial terms for the Project are still un-
certain, these costs were not computed except as part of the economic analysis
discussed in Part A. (See Section VI.)
•
•
•
•
•
"
•
..
•
XV-3
Annual costs for operation and maintenance, administration, insur-
ance, and interim replacement of Project components were estimated based on
experience on similar projects as well as FERC guidelines. The variable
annual costs are estimated to be $634,000 at the January 1982 cost level •
..
•
•
•
1 •
2.
3.
4.
5.
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
CONSTRUCTION COST ESTIMATE SUMMARY
Item
Preparatory Work . .......................... .
Dam and Reservoir ..........•................
Power Conduit ....•..........................
Powerhouse ................................. .
Switchyard and Transmission Line ••••••••••••
DIRECT CONSTRUCTION COST
(Bid 1/82, On-Line 6/84)
..................
Contingencies .................................. .
Subtotal ................................. .
Engineering and Owner Administration ••••••••••••
TOTAL CONSTRUCTION COSTS
(Bid 1/82, On-Line 6/84)
..................
Interest During Construction ••••••••••••••••••.•
TOTAL INVESTMENT COST •••••••••••••••••••••
(Bid 1/82, On-Line 6/84)
Escalation During Construction ••••••••••••••••••
TOTAL INVESTMENT COST ••••••••••••.•••.••••
(Inflation-free on 1/82)
TABLE XV-1
Estimated Cost
$ 2,786,000
11,571,000
12,348,000
5,382,000
13,273,000
$45,360,000
8,139,000
$53,499,000
7,825,000
$61 ,324,000
2,208,000
$63,532,000
7,624,000
$55,908,000
RWB
50-41
1
1.1
1.2
1.3
1.4
.. .. • .,
R. W. Beck and Associate.
CONSTRUCTION COST ESTIMATE
PROJ ECT _W_e_s_t __ C_r_e_e_k_H..:.y_d_r_o_e_1_e_c_t_r_l_· c_P_r_o....;J=-· e_c_t __ FEATURE Prep ar a tory Wo r k LOCATION __ A_1_a_s_k_a ______ w. O. H_H_-_1_5_5_9_-_H_G_3_-_AA __
TYPE EST TAKE OFF ARN PRICED JAS "ALC CHKD WB APPROVED GGG DATE February 1982 .-----v
Bid Price Level -Januarv 1982
ITEM AND DESCRIPTION QUANTITY UNIT MAT'L LABOR UNIT COST Subtotal TOTAL
Preparatory Work $2,786,000
Improving Existing Road 2.2 MI 150 000 330 000
West Creek Bridge LS 250 000
New Access Road 1.0 MI 875 000 87'1 nnn
Mobilization LS 1,331 000
---
$2,786,000
Sheet~of~
RWB
5D~41
2
2.1
2.2
2.3
..
• R. W. Beck and Associates
CONSTRUCTION COST ESTIMATE
PROJECT_W_e_s_t_C_r_e_e_k_H.::.,.y_d_r_o_el_e_c_t_r_l_· c_P_r_o~j_e_c_t __ F£ATURE __ D_a_rn_a_n_d_R_e_s_e_r_v_o_i_r __ LOCATION _Al~a::....s:....:k~a~ ____ w.o. HH-1559-HG3-AA
TYPE EST:_P ANNIN ~ ---L TAKE OFF ARN PRICED JAS CALC CHKD WVB APPROVED GGG DATE February 1982
Bi CI prirp T,p'pl -.T;:,n11"''-'' lOR?
ITEM AND DESCRIPTION QUANTITY UNIT MAT'L LABOR UNIT COST Subtotal TOTAL
Darn and Reservoir $11 571.000
Reservoir Clearing 330 AC 4,000.00 81,320.000 1. 320 000
Diversion is 2 569 000
2.2.1 Diversion Conduits
a. Select Gravel Backfill 8,000 CY 10.00 80,000
b. 11'{;1 r.oncrete "Pine 1,530 1F 1 360.00 2,081,000
2.2.2 Cofferdams
a Fill 6,320 CY 5.00 32 000
b. P1Rl'>tir T,iner 6,620 SF 1. 60 11 000
? ? "\ r.onrrptp r.,tnff r.nll::l,-
;:, C:tr11rt11'-"" 1 r.onr,-prp 100 CY 500.00 50 000
h rpmPllt 580 CWT 12.20 7 000
(' Rpinfnrrino C:rppl 10,300 1BS 1. 25 13 000
I? ? !J. ni1Tpr<::i on r.onrt,; r Pl IOC:
!O M!OQQ r,....nl",-"r", 140 CY 250 00 35 000
h r.pmpnt 800 CWT 12.20 10 000
c Gravel Fill 2,710 CY 11.00 30 000
I? ? <; T",mn",-",,-,, n;H".,..,,;r.n 1S 20.000
2.2.6 Dewaterin£ and Care of Water 1S 200 000
Dam ~ 4 200 000
2.3.1 Excavation
a. Common 35 780 CY 9 nn 122.000
b. Dental 200 CY 7000 14 000
~L,905,OOO
SheetLof9~
RWB
50-41
2
? 4
.. .. •
R. W. Beck and Associate.
CONSTRUCTION COST ESTIMATE
PROJECT West Creek Hydroelectric Proj ect FEATURE Dam and Reservoir LOCATION __ A_1_a_s_k_a _____ w. o. _H_H_-_1_5_5_9_-H_G_3_-AA __
TYPE EST" PLANNING-::RJmD£XIIII{~K TAKE OFF ARN PRICED JAS CALC CHKD WVB APPROVED GGG DATE Februar~ 1982 .----
Rii! Pri~e T.f>" ·f>l .T::ln::l IT, 1 q,q?
ITEt.I AND DESCRIPTION QUANTITY ~IT t.lAT'L LABOR UNIT COST Subtotal TOTAL
Dam and Reservoir lCont. )
2.3.2 Embankment
a. Rock Placement 254,000 CY 3.75 953,000
b Pro~eSSf>i! (;r::tve1 30,500 CY 15.00 458,000
2.3.3 Concrete Face & Grouting
a Grout Curtain 5,060 LF 110.00 557,000
b. Facinp-ani! P::tr::tnet Wall 3,790 CY 200.00 758,000
c Cutoff Slab 660 CY 250.00 165,000
i! Cemf'nt 25,100 CWT 12.20 306,000
e RpinfnTC'inp-Stppl 533,400 LBS 1. 25 667,000
ISnillw::lv 1$3.482.000
,.., 4 1 FYC'::l"::lt-;nn
R r.nmmnn 87 900 CY 7.50 659,000
b. Rock 245 000 CY 11.25 2,756,000
2.4.2 Soi11wav Weir
a. Concrete 180 CY 200.00 36,000
b. Cement 1 010 CWT 12.20 13 .000
c. Reinforcing Steel 14 570 LBS 1. 25 18,000
1$7 346 000
SheetlofL
RWB
50-41
3
3.1
• ,
R. W. Beck and~Associate. •
CONSTRUCTION COST ESTIMATE
PROJECT West Creek Hydroelectric Proj eet .FEATURE power Condll; t LOCATION _-<A:ulu::8...::S'-"k""8 _____ W.O. HH 1559 HG3-AA
TYPE EST:_PLANNING-JHIl[~IX&6mII __ TAKE-OFF ABN PRICED JAS CALC. CHKD.--"WV,-,-"",B ___ APPROVED ---,OG"-"'G!.>.G'---___ DATE February 19~
R;rl Pr;('p T upl T"nl1"r 1qR?
ITEM AND DESCRIPTION QUANTITY LNIT IoIAT'L LABOR UNIT COST Slht"ot"::ll TOTAL
Power Cononit" 512 14R 000
Intake ~ 1.757.000
3.1.1 Excavation
a. Conunon 5.920 CY 9.00 47 000
b. Rock 9.820 CY 11.25 110 000
c. Trim 1. 090 CY 45.00 49,000
3.1. 2 Backfill 160 CY 10.00 2,000
3.1. 3 Rockbolts 2.680 1F 50.00 134 000
3.1.4 Structural Concrete
a. Concrete 880 CY 650.00 572 000
b. Cement 4 970 CWT 12.20 61 000
c. Reinforcin2 Steel 88 210 1BS 1. 25 110 000
3.1. 5 Gate and Hoist 1S 200 000
316 Tr::u::;hrac.ks 1S 90 000
3.1. 7 Ice Prevention & Reservoir 1S 15 000
Monitorin2:
J 1 8 Ac.cess to Int"::lke
a Bac.kfill 540 CY 8.00 4 000
b Concrete 260 CY 240.00 62.000
(' Cpmput 1 400 CWT 12 20 17 000
d Rp;nfor(';no ~t"pel ,}'i 'i00 T.RS 1 25 32 000
e Ro"rl 3?O T.li' 130 00 42 000
3 1 q Powprl iup ~ Intake 1S 210.000
~t.rll('tl"''''
;>1,751,000
• .. • ~ • • " •
RWB R. W. Beck and Associates SO-41
CONSTRUCTION COST ESTIMATE
PROJECT West Cr:eek II¥dr:oe] ectd c Er:oject FEATURE Power Conduit LOCATION Alaska ~===-_____ W.O. HH-1559-HG3-AA
TYPE EST' PLANNI NG ~1I&SlIHI TAKE OFF ARN PRICED .J .. A .. S_ CALC CHKD WB APPROVED GGG DATEFebruary 1982 .-----
Bid Price Level -Januar 1982
ITEM AND DESCRIPTION QUANTITY LtlIT MAT'L LABOR UNIT COST subtotal TOTAL
~ Power Conduit (Cont.)
3.2 Tunnel and Surl!e Shaft $ 9,864,000
3.1.1 Excavation in DiS Portal
a. Rock 3 920 CY 20.00 66 000
b. Trim 370 CY 45.00 17 000
3.2.2 Excavation -All Classes 22 240 CY 410.00 9.118 000
Tunnel
,., 2 3 Excavflr; on -Rock Tr;:m 180 CY 400.00 72 000
3.2.4 Excavation -All Classes 350 CY 400.00 140 000
Shaft
3 2 'i Srppl Sprq (mRrpr;;:tl q onlv) 1q 1RO T.RS 1 35 53 000
326 Rork Rolrq (mRrpriRlq nnlv) 21 ')40 LF 7.45 160 000
i ') 7 T,in;no
a r.nnrrptf> ')10 r.v 'i')O 00 120 000
b Cpmpnt 1 300 r.WT 12 20 16 000
c Rein£nrr;no Srppl lR RnO T.RS 1 25 24 000
d Steel 7 5'~ ~l OL,O T,RS ? ')0 78 000
3 3 Penstock $ 727,000
11 1 F.xcavation
R r.ommon ')00 r.v 7 50 2 000
~ (Sock ?OO r.v ')f, 00 5 000
-
i ~ ? "rppl Ppnc::r()('k "1Il lRR oon T,RS ') 50 471 000
111 nrpqqpr r.ol1nl;noq - 7 ')' V1 2 EA 10 000.00 20,000
S10 362 000
Sheel...2of...2....
RWB
50-41
3 1
..
(.
..
R. W. Beck and·Associatel
CONSTRUCTION COST ESTIMATE
• ,
~
PROJECT West Creek Hydroelectric Proj ect Power Conduit FEATURE ___________ LOCATION __ Atl.oL1 Ai::I.liskllo.AtI.....-____ W.o. HH-J 559 HG3-AA
TYPE EST:_PLANNING-HI;(~~ __ TAKE-OFF ARN PRICED JAS CALC. CHKD._...;..WV~B __ APPROVED GGG DATE February 1982 ~~-~--82 Bid Price Level Januar 19
ITEM AND DESCRIPTION QUANTITY UNIT MAT'L LABOR UNIT COST Subtotal TOTAL
Pensrork (r.onr )
334 r.onrrprp 250 CY 700.00 175 000
335 r.pmpnr 1 410 CWT 12.20 17 000
3.3.6 Reinforcin~ Steel 20 000 LBS 1. 25 ~5--,-000
337 Cl earim! 2 AC 6.000.00 12.000
i
Is ?'1q noo
Sheet .2...of~
RWB
50-41
4
4.1
_4·2
4.3
--
4.4
4 "i
4 n
• •
" .',
R. W. Beck and Associates
CONSTRUCTION COST ESTI MATE
PROJ ECT _W=eliSLt ---.l.....CrL.t:.e et::..k~HD-:y)'-ld.J.JrL.J.o..u;e,,-,Ju;e ..... c .... t .... r...Lj.J..;c.....J...P.L..r~QJd-· e!iO.c ... tl.....-_ FE ATURE __ --'P!:..:o:::cw~e=-:r=_.!hc!.!o~u~s~e=___ ___ LOCAT ION ----=A:.:::l=-=a=-=s::.::.ka:=...-_____ w. o. HH-1559-HG3-AA
TYPE EST: _PLANNI NG~IXElIlmIIXDlfl8lGII __ TAKE-OFF Ml,S (ROE I PRICED JAS /PTcl CALC. CHKD. WB APPROVED GGG/PTC/PC DATE February 1982 -JLS WLS ----'-'--'-=---B' d P' L 1 J 1982 1 l rlce eve -anuar
ITEM AND DESCRIPTION QUANTITY UNIT MAT'L LABOR UNIT COST Subtotal TOTAL
Powerhouse $ 5.382 000
r.ivil T.1r.,.,-lrc S 7g"j 000
L~ 1 1 Powerhouse Excavation
a. Common 2 520 CY 7.50 19.000
b. Rock 3 940 CY 35.00 138,000
4.1 2 Fill 3 980 CY 5.00 20 000
4.1. 3 Substructure
a. Concrete 520 CY 740.00 385,000
b. Cement 2.930 CWT' 12.20 36,000
c. Reinforcing Steel 62.400 LBS 1.25 78,000
4 , 4 Sup~structure
a Precast-Roof Panels 2.240 SF 21.00 47,000
b Prer::l~r W,qll 'P,qnels 4 040 SF 15.00 61. 000
C 'Precast 'Re::lm~ 40 LF 270.00 11,000
Mechanical Equipment $1,713,000
4 :> , Tl1rhine~ .Valves & GovernorE 2 EA 729 000.00 1,458,000
422 Mi~r Merhrmic,ql Eauinmenr LS 255 000
Electrical Eauipment $2,061,000
4.3.1 Generators 2 EA 581 000.00 1.162.000
4.3.2 Accessorv Electrical Eauin. LS 899 000
20 Ton Mobile r.r,qne LS $ 150 000 150,000
1
Mi~rell::lne() 10::: l,S $ 100 000 100 000
A rchi t:<=>f' 1""1,1'"" 1 LS S 60 000 60 000
-
Is /f 879 000
Sheet~of!L
RWB
50-41
4
4 7
• .. • ..
R. W. Beck ana Associate.
CONSTRUCTION COST ESTIMATE
PR~Ecr West Creek Hydroelectric Project . FEATURE Powerhouse LOCATION Alaska W.O. HlI-1559-HG3-AA
TYPE EST:_PLANNI NG-W~~ TAKE-OFF MI,S IROE PRICEo.TAS IPTC CALC. CHKO.--,WV",-,,-,B.L...-__ APPROVED GGGIPTC IPC DATE Febrllary 1982
WLS WLS B·d 1 1982 1 Prlce Leve -January
ITEM AND DESCRIPTION QUANTITY lJIIlT MAT'L LABOR UNIT COST Subtotal TOTAL
Powerhouse (Cont )
Tailrace _S "icn nnn
471 Common Exr::lv::lrion 5 290 CY 9 00 48.000
4. 7 2 EmbRnkmenr 2 7<10 r.v 9 00 25 000
473 Channel Lining
a. Plastic Liner 42 000 SF 1.60 67,000
b GrAvel 2 100 CY 50.00 105,000
474 r.nnrrere r.nlvprt Wing/
Ret::lining W::llls
::l rnnrrete 230 CY 9QQ,00 207 000
h r",m",nr 1 2CJ7 r.WT 12 20 In 000
r R",;nfnrr;nICT Stepl 27 fiOO T.BS 1 2 "i 35 000
S 503 000
Sheet~oL.2 ...
RWB
50-41
5
') 1
'i 2
5.3
5.4
5.5
• • • • • .' R. W. Beck and Associates
CONSTRUCTION COST ESTIMATE
PROJ ECT __ W~e~s~t_C~r=--e~e~k~H~Yr....::d~r:...:::o:...:e:.::l:..::e~c:..::t~r-=i..:::c--.:P=-r=-o=.,J./....· e::.:c::.:t~_ FEATURE _S_W_l_' t_c_h--.:y~a_r_d_a_n_d ___ LOCATION Alaska W.O. HH-1559-HG3-AA
Transmission
TYPE EST:_PLANNING~lQlII~lGlII __ TAKE-OFF WI,S PRICED WI,S CALC. CHKD. WLS APPROVED _----"'-P-"'C'--:: __ DATEFebruary 1982
B'd P . I 1982 1 rlce Leve -January
ITEM AND DESCRIPTION QUANTrTY UNIT MAT'L LABOR UNIT COST Sl1hrnr::l1 TOTAL
Shlirrhv::lrn ;;, Tr::ln~mi~~inn Line LS IS11 271 oon -
5hlitc:hvarrl Is 401 nnn
5 1 1 Tr::ln~fnrmpr 1,S l':l.A nnn
'i ~ .2 Af'f'p<><>,.,rv C::T.ri rrhi ncr 1,S, 21)1 nnn
Rurierl Tran~mi~~ion Line 16. " 1..." 1 ? MT /,n7 nnn nn Is 4RR onn 4R8 000
Overhead Transmission Cable 5.0 MI 203.000.00 $ 1,016,000 1,016,000
Submarine Transmission Cable 16.7 MI 648.070.00 $10,759,000 10,759,000
Substations 1$ 609.000
5.5.1 Haines Terminal LS 231,000
5.5.2 Switchine Stations LS 231,000
5.5.3 Skaewav Substation LS 147.000
I
S 13 273 000
Sheet2....oL.2_
..
•
,
•
•
SECTION XVI
CITED REFERENCES
(1) CH2M Hill, Reconnaissance Assessment of Energy Alternatives, Chilkat
Basin Region, prepared for the State of Alaska, Alaska Power Authority,
February 1980 •
(2) R. W. Beck and Associates, Addendum to Reconnaissance Report on Alterna-
tives for the Haines-Skagway Region, prepared for the State of Alaska,
Alaska Power Authority, April 1981.
(3) Nor'West Pacific Corporation, 1979 Updating of the Feasibility Study and
Report on Generation of Electrical Power From Wood Refuse, prepared for
the Schnabel Lumber Company, 1979.
(4) United States Department of Commerce, National Oceanic and Atmospheric
Administration, Climatological Data, Alaska, 1976-1980.
(5) State of Alaska, Long-Term Energy Plan, August 1981 •
(6) Bonneville Power Administration, Mod-2, New Source of Windpower for the
Pacific Northwest, September 1980.
(7) United States Department of the Interior, Geological Survey Division,
Water Resources Data for Alaska (formerly "Surface Water Records of
Alaska"), from May 1962 through September 1977.
(8) United States Department of the Army, Corps of Engineers, The Hydrologic
Engineering Center, HEC-4 Computer Program, Monthly Streamflow Simula-
tion, February 1971.
(9) Linsley, Kohler, Paulhus, Hydrology for Engineers, 2nd Edition, 1975.
(10) United States Department of the Interior, Bureau of Reclamation, Design
of Small Dams, 1974.
(11) United States Department of Commerce, Weather Bureau (now National
Weather Service), Technical Paper No. 47, PMP and Rainfall-Frequency Data
for Alaska, 1963 •
(12) Davis and Sorensen, Handbook of Applied Hydraulics, 3rd Edition, McGraw-
Hill Book Company, 1969.
(13) United States Department of the Army, Corps of Engineers, The Hydrologic
Engineering Center, HEC-5 Computer Program, Simulation of Flood and Con-
servation Systems, June 1979.
XVI-2
(14) Horan, Charles, City of Skagway Assessor, Letter to Skip Elliott (Skagway
City Manager) on estimates of assessed property values in the West Creek
Area, December 1, 1981.
(15) United States Department of the Interior, National Park Service. Final
Environmental Statement -Proposed Klondike Gold Rush National Historical
Park, Alaska and Washington, Pacific Northwest Region, National Park Ser-
vice, Seattle, Washington 1974.
(16) Ibid. Master Plan Klondike Gold Rush National Historical Park, Alaska-
Washington, Pacific Northwest Region, National Park Service, Seattle,
Washington, October 1976.
(17) Ibid. Klondike Gold Rush National Historical Park Visitation Records,
Skagway, Alaska, 1981.
(18) State of Alaska, Department of Natural Resources, Haines-Skagway Land Use
Plan, Juneau, Alaska, June 1979.
(19) United States Department of the Interior, National Park Service, Interim
Cooperative Agreement Between the Klondike Gold Rush National Historical
Park, National Park Service, Department of the Interior and the Depart-
ment of Natural Resources, State of Alaska, Anchorage, Alaska, April 22,
1981.
(20) Alaska Department of Environmental Conservation, State Air Quality Con-
trol Plan, Volume II: Analysis of Problems, Control Actions, Juneau,
Alaska.
(21) United States Department of the Interior, National Park Service, Klondike
Gold Rush National Park Land Acquisition Plan (Draft), Anchorage, Alaska,
April 11, 1980.
..
•
•
..
•
•
•
•
•
•
•
XVI-3
GENERAL REFERENCES
City of Skagway City Clerk's Office, Ordinance 79-10 (Solid Waste Ser-
vices), Ordinance 80-8 (Rates and Water Service Fees), Ordinance 81-1
(Water Quality Protection System), Ordinance 81-1 (1982 Fiscal Budget),
Skagway, Alaska •
Clark, Roger N., Robert C. Lucas, The Forest Ecosystem of Southeast
Alaska: Outdoor Recreation and Scenic Resources, USDA, Forest General
Technical Report PNw-66. Pacific Northwest Forest and Range Experiment
Station, Portland, Oregon, 1978.
Elliot t, Skip, Skagway City Manager, Nota ted Map Showing Land Uses of
Parcels Near Proposed Project Powerhouse Site, November 1981.
Engineering Manpower Services, Skagway Campground Study for the Alaska
Legislative Council, Juneau, Alaska, January 1978 •
Environmental Services L imi ted, Ska~Way Coastal Management and Energy
Impact Program, Anchorage, Alaska, 19 o.
Environmental Services Limited, City of Haines Coastal Management Plan,
Anchorage, Alaska, January 1980.
Joint Federal-State Land Use Planning Commission, Alaska Resources Inven-
tory, Southeast Region: Recreation and Preservation Opportunities,
Anchorage, Alaska, May 1974.
Kramer, Chin and Mayo, Inc., City of Skagway, Alaska, Coastal Land Man-
agement Study, Revisions, Juneau, Alaska, June 1981.
Sims, Richard, Superintendent,
Park. Personal communication
August 26, 1981.
Klondike Gold Rush National Historical
with Thomas Peterson, Skagway, Alaska.
State of Alaska, Department of Commerce and Economic Development. Visi-
tor Census and Expenditure Survey -Winter, 1976-1977, Juneau, Alaska,
December 1977.
State of Alaska, Department of Commerce and Economic Development, Impact
of Visitor Expenditures Upon Alaska's Economy for the Year 1975, Juneau,
Alaska, February 1978 •
State of Alaska, Department of Commerce and Economic Development, Visitor
Census and Expenditure Survey -Summer 1977, Juneau, Alaska, March 1978.
XVI-4
State of Alaska, Department of Environmental Conservation, Air Quality
Data for the Southeastern Alaska Intrastate Air Quality Control Region,
1975 to 1980, Juneau, Alaska, April 1981.
State of Alaska, Department of Environmental Conservation, Proposed Revi-
sions to Air Quality Control Plan, Volume I, Juneau, Alaska, December
1977.
State of Alaska, Department of Environmental Conservation (DEC), personal
communication between Tom Chappel (DEC) and Mark Sadler (R. W. Beck and
Associates), December 1981.
State of Alaska, Department of Economic Development, Division of Economic
Enterprise, Community Profile -Skagway, Alaska, Juneau, Alaska, July
1974.
State of Alaska, Department of Economic Development, Division of Economic
Enterprise, Community Profile -Haines, Alaska, Juneau, Alaska, July 1973.
State of Alaska, Department of Labor -Research and Analysis Section,
1950 U.S. Census Enumeration Data for Ska wa and Haines Census Areas,
Juneau, Alaska, 19 o.
State of Alaska, Department of Natural Resources, Division of Parks,
Alaska Outdoor Recreation Plan, 1981, Juneau, Alaska, 1981.
State of Alaska, Department of Natural Resources, Division of Parks,
Alaska Trail Plan, Juneau, Alaska, 1973.
State of Alaska, Department of Natural Resources, Andrew Pekovich, Dis-
trict Lands Officer, Notated Map Showing Land OwnerShips in the Taiya
River and West Creek Valleys, Juneau, Alaska, February 1982.
United States Department of Agriculture, Forest Service Recreation and
Scenic Resources in Alaska: An Annotated Bibliography, Forest Service
General Technical Report PNW-50, Pacific Northwest Forest and Range Ex-
periment Station, Portland, Oregon, 1976.
United States Department of Agriculture, Forest Service, Selected Find-
ings From the Alaska Public Survey: A Summary of Responses From South-
east and South-Central Alaska, U.S. Forest Service Wildland Recreation
Research Station, Seattle, Washington, August 1981.
United States Department of Commerce, Bureau of the Census, 1980 Census
Advance Reports -Alaska, Washington, D.C., March 1981.
United States Department of the Interior, Bureau of Land Management,
Decision dated June 25, 1974 (Modified) regarding tentative approval to
the State of Alaska for certain lands in the Skagway-Taiya Area, Juneau,
Alaska, June 25, 1974.
•
•
..
•
•
"
..
XVI-5
United States Department of the Interior, Bureau of Land Management, Pub-
lic Room Files -Anchorage, Alasksa, Master Title Plat for Township 27
South, Range 59 East, Copper River Meridian, July 21, 1981 •
White, G. K. and W. C. Thomas, "A Method for Establishing Outdoor Recrea-
tion Project Priorities in Alaska," Research Bulletin No. 40, Agricul-
tural Sciences, University of Alaska, Fairbanks, Alaska, August 1973.
Wilson Condon, Alaska Attorney General, Memorandum to Jon Halliwell and
James Souby, Coastal Policy Commission, on Comparison of Local Government
Planning Powers Under Titles 29 and 46 of the Alaska Statutes, Juneau,
Alaska, August 24, 1981 •
\-. .
~'~
• " -IV'?
•
•
0°
•
•
..
..
,
\ ,
\
ALASKA CANADA \ Fairbanks •
KEY MAP
LEGEND
o
NOTE:
Gaging station location
Topography from U.S.G.S. I: 250,000
Skagway, Alaska -Canada, 1961 .
DATE:
4 Miles
I
o
I
Scale
R. W. BECK and ASSOCIATES
ENGINEERS AND CONSULTANTS
4 Miles
s..tlle. Wlllhington Denver. Colorado
Gonetal _ T_ Buildlnl, SeaIIIe, Wash""" 98101
ALASKA POWER AUTHORITY
HAINES -SKAGWAY REG:ON
FEASIBILITY STUDY
LOCATION MAP
RS:
/'PRIL i982
14,000
•
12,000
..
.. 10,000
..
~ ~ 8,000
..
4,000
•
2,000
... 1975
~ ......
...... ' .... .. ..
Growth scenorio C \ .... .... .... .... .... .... .. ~ ~~
,," .. "~ ,," ,," .. " ,," .... ... .: Growth scenario B", .....
~ .. ,,(;###. ...
~
.. ""-.... V ~ .. .: .: / .: .:
~ ~ .. ,,~ ~ ........ ....
,,""'-~ ....... ' ...... . ,"
'CGrowth scenario A r~ .'
~
Historic Projected
peak loads peak loads
I I
1980 1985 1990 1995 2000
YEAR
PEAK LOADS AT LOAD CENTERS
s:.
~
~
Z
0
-J
-J
~
>"
C)
0:::
W z w
-J « => z z «
70
60
50
40
30
20
10
o
1975
Historic
energy
requirements
I
1980
~ ,:t ,:t ,:t ~~ A~~~ .." .. ~
Growth scenario c~ .... ....
~ ~ .. .... ....
.. ~.,#;#J
,,"" 'Jt; .. ",," ....
~ .: -~
.: ~
~ ~~~~ .~ .... .. ~ ..... ~ ~ , ....
~ ... ....
.: '
... q
Projected
energy requ'rements
, I .
1985 1990
YEAR
.... .... .... .. .. ~ .... ~ . .. .. ~
Growth scenario B
~ /
-~ , ..... ........ . ..... . . . ...
"'Growth scenario A
1995 .'. 2000
ENERGY REQUIREMENTS AT LOAD CENTERS
DATE:
R. W. BECK and ASSOCIATES
ENGINEERS AND CONSULTANTS
S.attle, Washington Denver, Colorado
General otrteeS: Tower Building. Seattle, Washington 98101
ALASK A PO WE R AUTHOR I TY
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
LOAD FORECAST
APRIL 1982
FIG: 2
•
( •
~
•
..
..
•
..
,
(I)
W
rO
J ,-Z (I) _ I
z~~ -u' «zO 2 Il::_rc"l
14
12
(I) 10 u.. u
0 8 0
0
~ 6
0
..J 4 u..
J 2 V o o
740
~ 735
W
W
u.. 730
"> w 725
-.J w
Il:: 720
0 > 715
Il::
W
Peak . fl 13 840 10 ow
~
\
\.~-30-rninute unit
\ hydrograph
\
\
r\..
"'-~
2 3 4 5 6 7
TIME, HOURS
ONE-HALF HOUR
UNIT HYDROGRAPH
, V-Top of dam parapet wall
EI. 729.5
.".,
V ~
~ V
~ V
V
(1)710 w /' Il::
705 o
Spillway Cre:;t EI. 705.0
5 10 15 20 25 30
DISCHARGE, 1000 CFS
SPILLWAY RATING CURVE
35
o (1)0
W ~" ~
z=> oz
~~I
~,
-0 ~rc"l u,2
W 0:::(1)
a..W ::c
~3
70
60
50
(I)
lL.
U 40
0
•
2 4 6
~~ ~~~ ~'T
"-Runoff losses
TIME, HOURS
8 10 12 14 16 18 20 22 24
Runoff excess
IZO ~ .J
r
~L
'J
Snowmelt/
Peak linflow
l
59> 70
1
0 cfs
I \/ .I ,
vlnflow hydrograph
I \
If \
NOTE:
I. Elevations based on U.S.G.S.
datum (mean sea level) and tied
into Bench Mark "Sharp" at
Yakutania Point.
0
0 30 I ~ Peak outflow 30 560 cfs
?;-V /' '" --......... ~ -Spillway ou ./ /
tflow hydrograph
0
-.J u..
20
10
o o 2 4
/ / V
./ ~
,,/ --6 8 10 12 14
TIME, HOURS
~ w 7 30 ==-,-----.-----,---,--------. w
........ .............
............ I'-.. -.........
16 18 20 22 24
u.. 725r-~r---r---+---+---+---~~~--~--~--~~~~~
~ 720 r---r---+---+---+_--+-----bI'~+_--+_--_+_--_+--__+--__1
-.J w 715r-~~--+-~~~~~~~~--~--~--~--~--~--~
tf 7 I 0 r-t---1---t---+-~"""f7~+---+---+_--_+__--_+_--_+--_+--__1 o
~ 705~--L---L-~~--~--~--~--~--~ __ _L--_L __ _L __ ~
W 0
(I)
W
0:::
2 4 6 8
PROBABLE
10 12 14 16 18 20 22 24
TIME, HOURS
MAXIMUM FLOOD
R. W. BECK and ASSOCIA rES
ENGINEERS AND CONSULTANTS
Selttle. Washington Denver, Colorado
Goneno. oIIices: Tower Bulldl ... Seattle, WuhinalDn 98101
ALASKA POWER AUTHORITY
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
FLOOD HYDROGRAPHS
DATE: RS: 3 APRIL 1982
,
..
...
~ w w
LL .. ..
Z
0
~
~
W
...J
W
..
..
•
..
SURFACE AREA, ACRES
1300 1200 1100 1000 900 800 700 600 500 400 300 200 100 0
8oor-----.------.~r---.------.------r-----.-----~------.------.------r---~.------.------.-----~800
", I ~~ ,~ ~
780~----+-----~-----r,~--~------~----+-----~-----+--~~~------~----+------r-----+----~780
"',(,r------Area /~capacltY
·'r'_. ./
7601---------r------r-----~------~----~------r-~~-r------~-----+------~-----r------r------r-----4 160
] ',,~~
740 1-------/-----~ ---+_--___f--~/fL-+_''-.~-___f---__+---_+_---+_--_____+---_1__---+_---+__--____t 740 ~ / "", ~
g ~ ~" ;1--~-------+------_1__------_+_------4_------+_----~ 720 r_----l------,., 120 NV Normal maximum reservoir EI. 705 ' ""':
6 B 0 i( ........................... ~ ~:-t-----t-------t 680
Minimum reservoir EI. 662 ~
660 I "
'~~.
"
660
640~-----r------r------r------r-----~------r------r------~-----+------r------r------r------+--~~ 640 ~\
\ 620L-----~--~----~-----L--~~--~---~----~--~------~----~----~------~----~ 620
10 20 30 40 50 60 70 80 90 100 110 120 130
CAPACITY, 1000 ACRE -FEET
NOTES
I. Area -capacity curves based on
mapping of aerial photographs
conducted by Tryck, Nyman and
Hayes, June 1981.
2. Elevations shown are based on
U.S.G.S. datum (mean sea level)
and tied into Bench Mark "Sharp"
at Yakutania Point.
R. W. BECK and ASSOCIATES
ENGINEERS AND CONSULTANTS
5.0111e, Washington Denver, Colorado
General otIice.: T""", Buildlnll. Seattle, washina\<XI 98101
ALASKA POWER AUTHORITY
HAINES -SKAGWAY REGION
FEASI BILITY STUDY
WEST CREEK RESERVOIR
AREA-CAPACITY CURVES
•
•
•
•
•
,
..
//'
/
'/
/
Intake
o
/.?
illwayweir
Existing logging road
~,:~~~~
(To be improved) :,",
~d
140 0
/800
700
600
700
BOO
900
10 00
PLAN
400' 0 400'
~"I I
Scale
Surge shaft
-----~------------------\-----
Upper tunnel
\,~,'\ .. "~
\
(LOWer tunnel
TYPICAL POWER CONDUIT PROFILE
Not to scale
1000
Surge shaft
700
1
-J--\
Powerhouse
Access road,
(New construction) '. t ~,
Powerhouse
NOTES:
,ACCS!;!I road
(New construction)
. I
" dccess road ----.., I <' "(Existing road) ~ '-........ --.,. I ...... , I
""-1
I
To Skagway 1
9.3 miles ,
I. Topography is based on mapping of aerial
photographs conducted by Tryck, Nyman a
Hayes, June 1981.
2.Vertical control based on U.S.G.S. datum
{mean sea level) and tied into Bench mark
'Sharp" at Yakutania Point.
3. Horizontal control grid based on the
Alaska State Grid Coordinate System,Zone I.
DATE:
R. W. BECK and ASSOCIATES
ENGINEERS AND CONSULTANTS
Seattle, Washington Denver. Colorado
General omces, TowerBuildinll, Seallle, Washlna\l>n 98101
ALASKA POWER AUTHORITY
HAINES -SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
ALTERNATIVE
POWER CONDUIT ARRANGEMENTS
APRIL 1982
AS: 5
I
•
•
a.
"
•
NOTES:
I. Topography is based on U.S.G.S.
15 minute quadrangles at a scale of
I : 63,360. Skagway A-I, A-2, B-1, B-2,
C-I and C-2.
2. Vertical and horizontal control based
on U5.G.5., U.S.C. a G.S.and LB.c.
datum (mean sea level).
• o
D.
LEGEND
Power conduit alignment
Over land transmission corridor
Submarine transmission corridor
Existing tie line
Existing power plant
Proposed power plant
Proposed switching station
I 0 Imlle
I , I I I , I , I " I
Scale
R. W. BECK and ASSOCIATES
ENGINEERS AND CONSULTANTS
Seattle. Washington Denver, Colorado
General offices: Tower Bunding, Seattle, Washington 98101
ALASKA POWER AUTHORITY
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
ALTERNATIVE TRANSMISSION CORRIDORS
6 DATE:
APRIL 1982
APPRO~ FIG:
0 l>~ -cIT'
::0
r
<D co
N
0
;u~ f'Tlz 0--
> "" "" '" 0 ~
-
:!!
!!l
-...!
LEGEND
U G -Underg round
OH -Overhead
SUB -Submarine
»
Ci
ITI CJ) ;:0 :: (f)Z
~ ~ -<l> ?O ~ (f):"; ~ :r l> [ ~ r --I < m ,,~ l> 0 :r
1TI1TI(f) en 31 5· "' rrtZ ~ cc z 0::1 3: --I l>rrt ;:0; 0 '" l> -I " Z IT! --I en en ~ "' (') 0;:00 , "' !!!en -c '" "" Z»;:O ~ '" ITIZITI r ;:0; 0 > Q -l> :if 0-Z :: 1(f)1TI -IGl rrt ~. 0 Q,. !:~;1i: -<:if ::0 0 en
enl> m 0 > ZU;""tJ z
-1-< l> ~ '" V) c V) m(f);:O C r-
06° C::o -I ~ > 0 Orrt :r z (') );Z~ -<Gl 0 5· 0 VI 0 ::0 ~ " 5: " G'>00 Z < -i -I <D <l>
:0 0 --I e '" ~ -< 0 »:0 e 0
3::0 ~ 0 c-o
0
:0
~
.. .. . ..
2.2 miles
1----1-l OH
1 r< 134.5 kV 'I J\ t --2225/2780-;;VA
I ~ I
1.2 miles 2.Smiles I . s-L. 1 1
UG OH I ~-, I r---l 34.5kV
I WEST CREEK I I
I L ---, SKAGWAY
I TAP 6360/7950 kVA SWITCHING L_ 13.8 -34.55 STATION
G STATION G
SERVICE
3450kVA 3450kVA
, vl~ \ 34.5 -2.4kV I
I I) I
I--+-I L ____ ~
SKAGWAY POWER
PLANT SWITCHYAR"D
16.6miles
J-tAINES TERMINAL
SWITCH ING STATION
WEST CREEK PROJECT EXISTING OVERHEAD
TRANSMISSION LINE 34.5kV
X>~ -ui'il :0"
r
(D
(»
'"
AJ~ ~~
> ... ...
~
-
."
iP
CD
LEGEND
UG -Underground
o H -Overhead
SUB -Submarine
» r -I ITl
:::0 en
'" cnz .. :::
-<» Ii? 1ii"
cn-l:E X> ~ ~ ~<1Tl :J: r
"X> X> 0 or
~lTlcn fTI-(J) ~ ;;' '" x>Z ::0; (Q z
-1-1 ~~ X> ;; C'>
-i " Z
0:::0(") ~ '" III I '" Z»:::O -(J) -0 ..
[:::0; 0 ~
.,.
ITlZITl ~ >-
'cnlTl -Ix> c: z
-<G1 fTI ~. <:>
!:~" ~ :0 ...,
(J)X> g' 0
zc;;;." X> z -1-< ~ .,.
ITlcn:::O c c ~
06 0 0:0 -I i := -<fTI :J:
);zl=r; 0 z G1 f <:> ....
0 :0 '" .,.
G')(")(") " z ::::j <
::00-1 '" '" -< ~ .~
»:::0 n g 0
~~ 0'
Ol
0 a.
0
0 :::0 ro:
?:J
~
~
IT!
(")
~
Q :::
Q,.
» V')
V')
0
~
-I ~
)
1.2 miles 5.0 miles
UG
WEST CREEK
SWITCHYARD r ---,
I ~ I
14140/5170kVA\ I
I 13.a-34.5kVi' I
L _____ ~
OH
12.5kV
'~~ 18.7 miles
0) ~480V~ 0)
STATION
SERVICE G
3450kVA 3450kVA
WEST CREEK PROJECT
OH
34.5kV
..
to ..
r-------,
I A 1 A 2225/2780 k VA I ' vl~ \ 12.5 -2.4kV I
I ---L I L _____ J
SKAGWAY POWER
PLANT SWITCHYARD
EXISTING OVERHEAD
TRANSMISSION LINE
HAINES TERMINAL
SWITCHING STATION
'" l>~
-O~
~
r
to
CD
I\)
'" AJ~ ~~
> ... ...
'" 0 ~
."
1!i
to
LEGEND
UG -Underground
OH -Overhead
SUB -Submarine
l>
~
ITI CI> :::0 ll: enz ::
-<l> W !' ~ en ':E l> i ~ .,~ :r r ~ ITI<ITI "TI~ l> 0 !}
(f) f ;:j" "' ~lTIen fTlZ ;>; "' z ~ .,., l>fTI S '" l> :0 Z m
0:::0(')
(f)(f) i ... () , "' z»:::o !:!!(f) -u ~ ~
ITIZITI r;>; ~ ~ > Q -l> c: :z :: lenlTl -tG) fTI :r 0 Q., !!" ~~A -<::e ::0 go n
0 ):-Zen"'tJ ~=< J z l> '" V) lTIen:::o c := ~ 00 0 C::O -i ~ ~ OfTI :r ~ :z ~ l>z~ -<G) 0 f '" ;;!
6 ::0 CD
(j)(')(,) :0
:::j <
:::00., Z '" CD -I -< ~ .~ ~ l>:::O 0 S 0 "~~ 0
il 0 Q.
0 0
:::0
<i
•
ro
c3
G')= CD en
)
WEST
CREEK
SWITCH-
YARD
5.0miles
OH
12.5kV
.. .
1-2225/2780 kVA I + 12.5 -2.4 kV I
I ~ I L _____ ~
SKAGWAY POWER
PLANT SWITCHYARD
26.7 miles
1-----, OH
~ I 34SkV
I I
I 4140/5170 kVA
I ''t13 .8-340 5kV i L _____ -.J
EXISTING
OVERHEAD
TRANSMISSION
LlNE.--
~¢
I 0) ~480V; 0)
STATION
G SERVICE G ~ I ~ __ 34_o5k~j+-++--l 3450kVA 3450kVA
WEST CREEK PROJECT HAINES TERMINAL
SWITCHING STATION
•
I
-G
G -C
0 -400 CI >
II)
iii 0
maximum
EI.705
Spillway weir
~ EI.705
''\
'~,
\
EI.695
/""\.J'j . i
;!
Original ground
1200
1300
POWER CONDUIT PLAN
400 400
I , ,
\.5' Dia. air vent
r-tt-t----=+-r---+===~-+-------7;-,-;--___._;___-·_;__.+--__;__;-·~--__;~--------_+9,5' Dia. surge
section
0+00 10+00
Cnnr:r'Ahl lined section
(parti steel lining)
____ ~~~-.------~~~~.-------~~L~------~~~~----------~~~.----------~~
40+00 50+00 60+00 70+00 80+00
STATIONS
POWER CONDUIT PROFILE
Power conduit
90+00
..' \
L6g bridge,}
(Replace exist "'0. ........ ;/'
)
, :, " \
! I " , ,
i A~cess rQad
(New construct'>~/! ~\~\
units
'(\ .'. . / \\~~ \) \ l: ~'. To Skagway . \.ri,
1.:\ "'~1! 9.3miles \.
NOTES: .1/ ", \.
I. Topography is based on rkcf~ping of aerial
photographs conducted by Tryck, Nyman a
Hayes, June 1981
2. Vertical control based on U.S,G.S. datum
(mean seo level) and tied into 8ench Mark
.. Sharp" at Yakutania Point.
3. Horizontal control grid based on the Alaska
State Grid Coordinate System, Zone I.
DATE:
R. W. BECK and ASSOCIA rES
ENGINEERS AND CONSULTANTS
Seattle. WaShington Denver, Colorado
General offices: Tower Building, Seattle, Washington 98101
ALASKA POWER AUTHORITY
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
W EST CREEK PROJECT
SELECTED DAM AND POWER PLANT
. ARRANGEMENT
APRIL 1982 RS: 10
•
•
..
-CD
Power
Normal maximum
reservoir EI. 705
Approach channel
Spillway weir EI. 705
... 900
I .~ I 0
10
.!800 +
~A
PLAN
200' 0'
I I, I
Scale
Access road
(New construction)
g .,
Dam crest
EI. 729.5
'"~I Power tunnel
,
""'-~ Spillway chute _ ~
"--..
200'
I
o
/2
Parapet wall
Crest EI. 729.5 Normal maximum
reservoir EI. 705~
~~~~~-------
Normal minimum
reservoir EI. 662)
10'-Process-e-d'---g-r-a--'-ve-I,=~e------------:/
bedding ----------_______
Grout cap-
'---=-"""",
Grout curtain~
~OCkfill from
SPillWay:)
EI.726
1.5 "JI
Estimated rock surface
Original ground
TYPICAL TRANSVERSE DAM SECTION
50' 0 50'
I , ! I I I I
Scale
Dam crest EI. 726
Diversion conduits
Original ground Estimated
rock surface
Upstream cofferdam
Diversion flood W.S. EI.635 \
EI.618
SECTION A-A
(Dam axis profile)
100' 0 100'
I II I I I I! II I I
Scale
Plug pipes following
di version closure
NOTES:
I. Topography is based on mapping of aerial
photographs conducted by Tryck. Nyman a
Hayes. June 1981
2. Vertical control based on U.S.G.S. datum
(mean sea level) and tied into Bench Mark
It Sharp" at Yakutania Point.
3. Horizontal control grid based on the Alaska
State Grid Coordinate System. Zone I. 10 -yr return period -\L 1 Downstream
Invert cofferdam \
Original ~ound~_~_=_=_~_~_~;~;_~\~_~_~_~ __ ~_~_~_~_d_~_~_~_~_=_~ __ =_=_=_=_=_=_=_~_=_=_; __ ~_~_~_~_~_~_~_~_~_~~~~.!6~~L_~WSEI.605£
Estimated 2 -II' Dia. reinforced concrete pipes
rock surface 0" I I 0 I I nglna (D Estimated L
-----1-------DIVERSION SCHEME ground .» _ r rock surface ~i ~'~~I !I c
--ffi :1 11 r fff:1:.013~
-!---r c~t-
100' 0 R. W. BECK and ASSOCIA rES 100'
Scale ENGINEERS AND CONSULTANTS
;03)
"1'1''' ./1'13 I/V, ~V(ll' 0\ ~ u; EI. Ft:t:e ct~35b'
I
-----,-----1----
I
600
0+00 2+00 4+00 6+00 8+00 10+00 12+00
STATIONS
SPILLWAY PROFILE
r:I:J'\
14+00 16+00
So.Iife. w .... ;n¢o"
Columbus. Nebr.ska Denver. CoIor.do O~."do, Ro.id •
Indianapolis, Indiana Phoenix, Arizona Welesley. MalHchusettt
ALASKA POWER AUTHORITY
HAINES -SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
DAM AND SPILLWAY ARRANGEMENT
II DATE:
APRIL 1982
FIG:
t
•
•
,
720
-: 680
u.
c o
:; 640
~
iii
600
o o r-
POWER INTAKE-PLAN
40' 0 40'
I !! I I
Scale
Normal maximum
Original ground
Minimum W.S. EI. 662.0
Gate house
Deck EI. 726.0
Trashrack
Gate house
Gate hoist
Top of parapet wall
EI. 729.5
rock bolts
a~~::::::;(~t1u~~~Jl,",~jl~~~!~~;t~ Fixed wheel gate =-7ocW,,-~'" EI. 630.0 ____ ~ Power tunnel
POWER INTAKE-PROFILE
40' 0 40'
I I I I I I
Scale
Steel sets and
additional
0-excavation
"\\ as req'd.
-0 CD It) c+ SC\I
1-0 -(/)
Steel lining
9.5' I. D. machine
bored tunnel
Steel penstock
with couplings
Concrete pier
UNLINED TUNNEL LINED TUNNEL PENSTOCK
TYPICAL POWER CONDUIT SECTIONS
4' 0
I I I I I
Scale
4'
I
o ~
3' dia. steel
penstock
" II
POWER TUNNEL PORTAL-PLAN
20' 0
LI !! r
Scale
Rollout section
20'
I
Original ground
Estimated rock
Anchor block
Pier
POWER TUNNEL PORTAL-PROFILE
29', 0
, Scale
20' ,
Anchor block
Steel penstock
Pier s ----''-----------''''-J::::::-.-.
TYPICAL PROFILE OF PENSTOCK SECTION
Not to scale
o o
\D
\
NOTES:
I. Topography is based on mapping of aerial
photographs conducted by Tryck, Nyman a
Hayes, June 1981.
2. Vertical control based on U.S.G.s. datum
(mean sea lev ell and tied into Bench Mark
.. Sharp" at Yakutania Point.
DATE:
R. W. BECK and ASSOCIA rES
ENGINEERS AND CONSULTANTS
Seattle, Washington Denver, Colorado
General offices: Tower Building, Seattle, Washington 98101
ALASKA POWER AUTHORITY
HAINES -SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
POWER CONDUIT DETAILS
APRIL 1982
APPRO~ FIG: 12
I
"
..
.......---'2.00
Switrhvnrl'll--"""""
Access road------t' ----
(new construction) t-----~::-~~~7-=-=::~~~~-:;-;~./-------
1-------()y / -~//
Access roadf ~
(existing road) C?
~
--------
/ /
/ /
./ / ------.-/ -------
POWERHOUSE AND TAILRACE CHANNEL-PLAN
260
60' 0 60'
I , , , , , I I
~ Scale
200 Penstock <5
d -en
Original ground
Top of embankment 100
Powerhouse
NOTES:
I. Topography is based on mapping of aerial
photographs conducted by Tryck, Nyman a
Hayes, June 1981.
2. Vertical control based on U.S.G.S. datum
(mean sea level) and tied into Bench Mark
"Sharp" at Yakutania Point.
3. Horizontal control grid based on the Alaska
State Grid Coordinate System, Zone I.
We.t creek
Original ground Tailrace channel invert, • -0.0008 channel invert '="==-~~01.~~1~~N~or;m:;;a~l:=-t=a_I;·I_w~a~_t~e~r ~E~I_.~3=-8=.:::O--=-:::-=~~=-=---=--=:=~ _=_ ::::-::-::=-~~::-==========-::-~=-::E-,;:",;::~~~--=-:::=-=--===--=-===-=-===--=~=-=-===--=--==:=-=-:::::::~~=====:::::..... LroXimate EJ. 22.0
o L-~ ______ ~ ____ ~~~~~~--____ -=~~ ____ ~ ______ ~~~ ____ ~ ____ ~~~ ____ ~ ______ ~~~ ____ ~ ____ ~~~~--~------~
100+00 104+00 106+00 108+00 110+00 112+00 114+00
Coarse gravel
I~
Typ.1.5
STATIONS
POWERHOUSE AND TAILRACE CHANNEL-PROFILE
60' 0 60'
~LJ" __ -J
Scale El. varies --"""""'"""'-
Coarse gravel
5'
R.· W. BECK and ASSaCIA rES
ENGINEERS AND CONSULTANTS
Seattle, Washington Denver, Colorado
General offices: Tower Building, Seattle, Washington 98101
Impervious membrane
--------\-----
Original ground
Impervious membrane
ALASKA POWER AUTHORITY
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
TAILRACE EMBANKMENT SECTION
10' 0 10'
I ! ! II I ! " ! I
Scale
TAILRACE SECTION IN CUT
10' 0 10'
~~~" ',-:--_~I
Scale DATE:
WEST CREEK PROJECT
POWERHOUSE AND TAILRACE CHANNEL
ARRANGEMENT
APRIL 1982
FIG: 13
50
45
(
40
Pier
Penstock
Fuse box(typJ
Exciter (typ') ___ ---J-~
Service door
Switchgear
/ ~ Gover,r "P.
Parking area)
//
//
/ /
/ / Man door
/f/
/ //(3' cable duct (Generator
~/ LEI. 44.5 Tall,ace headw«ks
/
/ / Access road
Concrete
encasement-
Original ground
Estimated rock surface
PLAN
(EL. 45)
TRANSVERSE SECTION
I I t~,-: ::
~~=8": ji -+if"''1:11---I "
---I II
I I I o I I I I
I I I ~t', : I~,'
I I
I I
Tailrace channel
+ ~
(\J " 0:5
-0 of -U)
Precast concrete
wall panels
Handrail
EL445
=~m'<m h,,=,
-111.""2
---
~Berm~
Removable precast
roof panels
Francis Turbine
4200H.P.--
Precast concrete
wall panels
75 <l Unit E1.45.0
-R'Il-------lllt--J:et--+ '>,--+-15------JfJt19t"T"-"T--t-t-------Generator floor
EI. 42.0/ •• ' Normal T.W. EI. 38
50
45
40
Stop log slot
Top of embankment
EI. 35.0
:.-'". ,~."' .'"
Tailrace channel
E1.23.0
70 EI.30.0
LONGITUDINAL SECTION
NOTES:
I. Topography is based on mapping of aerial
photographs conducted by Tryck. Nyman a
Hayes, June 1981.
2. Vertical control based on U.S. G. S. datum
(mean sea level) and tied into Bench Mark
Sharp" at Yakutania Point".
DATE:
10' 0
\,''"', ,t
Scale
10'
I
R .. W. BECK and ASSOCIA rES
ENGINEERS AND CONSULTANTS
Seattle, Washington Denver, Colorado
General offices: Tower Building, Seattle, Washington 98101
ALASKA POWER AUTHORITY
HAINES -SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
POWERHOUSE DETAILS
APRIL 1982 FIG: 14
•
..
•
..
..
R.o.W.
TYPICAL OVERHEAD TRANSMISSION
STRUCTURE
NOTES:
I. Topography Is based on US.G.S.
15 minute quadrangles at a scale of
I' 63,360. Skagway A-I, A-2, 8-1,8-2,
C-I and C-2.
2. Vertical and horizontal control based
on us.GS., us.c. and G.S. and I.B.C.
datum (mean sea level).
----
6,
D •
LEGEND
Power conduit alignment
Existing transmission tie line
Proposed overland transmission line
Proposed submarine tronsmlsslon line
Proposed switching station
Proposed power plant
Existing power plant
I 0 Imlle
I, ,,, " I ," I
Scale
R. W. BECK and ASSOCIATES
ENGINEERS AND CONSULTANTS
Seattle, Washington Denver, Colorado
General offices, Tower Bulldl"" _eo W.shlns\On 98101
ALASKA POWER AUTHORITY
HAINES-SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
SELECTED TRANSMISSION CORRIDOR
15 DATE:
APRIL 1982
AS:
T. 26S.
T. 27 S. ,
T. 27 S.
T.28 S.
..
"
-'---'
Head of
WesfCreek
W
CD
LO a::
RESERVOIR
(Normal maximum W.S.
W
(1)
LO
0:::
EI. 705)
-,
(
Existing
road
I
+ /
~
Modern
----'-Chilkoot Trail
,-
I
I •
I
j r'-'-'
T. 26 S.
T,27 S.
-----'-
AS Mtn
6~
"-'\
/ i Klondike Gold Rush
I i--National Historical Park
\
\
Skyline/
AS Mtn Trail
I ' Ir' -'
I' II
II
Ii
I
I
TRANSMISSION LlNE/
I
/
/
/
I
I
/
ww
(1)0
LOW
a::ci
T. 27 S.
T. 28 S.
-----National Park boundary
------Trail
Proposed transmission line
~ Overland .... --"IV-_ Underground
.--"N'--" Submarine
Clearcut area
Glacier
N~r~t.J730: Magnetic
North
Approximate Mean
De~~"5'~on ~
o
Scale
R. W. BECK and ASSOCIATES
fN&INffltS AND CONSULTANTS
ALASKA POWER AUTHORITY
HAINES -SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
REGIONAL SETTING
I Mile
DATE:
APRIL 1982 A6: 16
T. 26 S.
T. 27 S.
,
..
T. 27 S.
T. 28 S.
..
..
..
u.iw
co(j)
LOLO
Ii Ii
RESERVOIR
(Normal maximumW.S.
WW
co(j)
LOLO
Ii Ii
EI. 705)
............. _ ..... ~ENSTOC~:-· ~
l3~~~i·········-···/f
POWERHOUSE o !
I
North Dyea
Native village
/
Modern
l--~Chilkoot Trail
,-
I
I
Historic
Chilkoot Trail
/Wooden structures
i\'{·--t--Ranger station
"-Marine shell deposit
-TRANSMISSION L1NE/
Steel wire telegraph/ /
telephone line /
/
/
/
/
/
/
/
/
/
ww
(j)O
LO<.D
0:::0:::
AS Mtn
6
T26S.
T. 27 S.
Skyline/
AS Mtn Trail
/
/
/
/
Suspension
bridge
remains
WW
(j)o
LO<.D " . . 0:::0:::
T. 27 S.
T. 28 S.
-~---National Park boundary
------Trail
Proposed transmission line
~ Overland
"'--"111--_ Underground
.--"1\1'--.... Submarine
Glacier
J~~?h 1~/300, Magnetic 1 North
APPb~~[~l~o~~
DATE:
o I Mile
Scale
R. W. BECK and ASSOCIATES
£N6IN££1IS AND CONSULTANTS
s..ttIe, W .... lngton
ALASKA POWER AUTHORITY
HAINES -SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
HISTORICAL AND
ARCHAEOLOGICAL RESOURCES
APRIL 1982
APl'ltO~ FI6: 17
T. 26 S.
T.27 S.
•
•
T. 27 S.
T. 28S.
I / . /
, 0 I
;' V& I
TAilRACE' I
I
Modern
,----'-Chilkoot Trail
,_.
I ~!'!
?~:::"::~':::m. ;' / [._._i
•••••••
•••••••
RESERVOIR
(Normal maximumW.S.
.... ;.. . / I Klondike Gold Rush
...... ~.E.NSTOC'S~ I i---National Historical Park POWER./ ••••.•••• 1 I • ::::::: I Ir"-' '.' CONDUIT . . .... ;, ;:;:;:;
POWERHOUSEI I' iIi! :' ;~;> EI. 705)
SOURCES:
I. Alaska Dept. of Natural Re.sources,
Haines-Skagway Area land Use Plan (June 1979).
2. u. S. Dept. of the Interior, National Park Service, Klondike Gold Rush
National Historical Park land Acquisition Plan (Draft) (April II, 1980).
3. Kramer, Chin, and Mayo, City of Skaqway!
Coastal land Management Study (June 1981).
W LU
00 en
LC') LC')
0:: a:::
o I I /1 '::::::.
i /i )(
I ,
J
I ,
;
I
~
I •
, 'I
li!llll:
}!!![
-TRANSMISSION LINE
••••••••
LULU
enO
LC')(,!)
a::: a:::
T. 26 S.
"T. 27 S.
~ ----.,
T. 27 S.
T. 28 S.
Private land ownership
:;>:U:>~V: Private land claim
State lands allotment
to Skagway
D State lands (to be transferred
from Federal government)
//////
////// BlM lands //////
1111111111111111
National Park ownership
-----National Park boundary
------Trail
Proposed transmission line
~ Overland
e---'V\I'-_ Underground
.--'N'---e Submarine
Study area boundary
Glacier
N~r~~11---.:::..30: Magnetic
North
Approximate Mean
De~~5o':ion IJ
o I Mile
Scale
It W. BECK and ASSOCIATES
ENeINEEIS AND CONSULTANTS
5M1t1e. Wahlngton Oen_. Colorado
DATE:
ALASKA POWER AUTHORITY
HAINES" SKAGWAY REGION
FEASIBILITY STUDY
WEST CREEK PROJECT
lAND OWNERSHIP
APRIL 1982 18
FEASIBILITY (CONTINUED)
LICENSING AND PERMITTING r" \.:.,,; 72" \.!~
FERC APPLICATION PREPARATION • • :::;"0 I
f--f--
FERC PROCESSING • • • • • • • • • II • • • • • •
OTHER PERMITS I ' ~~ ~III 1111 1111 .I~"I
DESIGN AND CONTRACT DOCUMENTS
FIELD INVESTIGATIONS •• ~I I~I ~4) I(~
DAM AND POWER PLANT I I .,~ Ir5"
4t 1\
MAJOR EQUIPMENT • .1 •• I~ f-'~
TRANSMISSION LINE I • ~
CONSTRUCTION
MOBILIZATION ~.
ACCESS ROADS • DIVERSION
DAM AND SPILLWAY .~~
• POWER INTAKE ~ .
POWER CONDUIT -TUNNEL
-PENSTOCK .. ~ •• •
POWERHOUSE -CIVIL • • • • .~I
-MECHANICAL • • .1. • • • • • • ~I I • • • • • •
-ELECTRICAL • • .~. • • • I • • .~I .1 • I I • I
TRANSMISSION LINE ~II • • • • • • •• ~I ••
RESERVOIR FILLING
START -UP .AND TESTING .~ ••
~ --'" --. CD"-..... >,~>,Il£IO"~>v ~~~O'~~-3~guo~ c..c ..... "'->,~>,Il£IO"_>u ~~~~i~i1,~2~~ C..D"-..... >,c~tlDa._>u ~~~~~~~~~o~~ ~~~~~~~.ij)C5~~ .....,u...~o:t:~-,.....,<:«(/)OZO ~~~~~~~.i~o~~
1982 1983 1984 1985 1986 •
LEGEND R. W. BECK and ASSOCIATES
fWlNfflS AND CONSULTANTS
SuftIe, weehlngton 0.-, Colorado
CD Submit application Primary effort __ aIIIooo: T_ Build ..... _. -..... 91101
® Application accepted ......... Continuing effort ALASKA POWER AUTHORITY
HAl NES -SKAGWAY REGION
@ license issued FEASIBILITY STUDY
@ Issue bid documents WEST CREEK PROJECT
DESIGN AND CONSTRUCTION SCHEDULE
® Receive bids
GAllo r DlAWN! l~ I~ APRIL 1982 fjG 19
PART C: COMMENTS FROM REVIEWING AGENCIES
•
•
•
..
•
..
ALASKA POWER AUTHORITY
Haines, Alaska
ALASKA POWER AUTHORITY
SUMMARY OF PUBLIC MEETINGS
ON HAINES-SKAGWAY
ENERGY ALTERNATIVES
7:00 p.m., Tuesday, April 20, 1982
The Haines public meeting on energy alternatives convened at 7:00
p.m. at the Haines City Hall. A total of nine (9) people were in
attendance, including utility and city officials, Power Authority staff
and consulting engineers.
Mr. Melnick and Mr. Binger of R. W. Beck and Associates reviewed
the history of the project studies and reported on the details contained
in the feasibility report which resulted form investigations during the
1981 field season and subsequent analysis. During 1981, detailed
interviews were conducted in the communities with residents, utility
officials, and business interests to ascertain existing or planned
activities that would affect energy demand. This information was
correlated with other information obtained from agencies in Juneau and
Canadian business interests that could affect energy demands in Haines
and Skagway.
t'ir. t',elnick and ~1r. Binger reported on the detailed evaluation of
energy alternatives 'vhich included continued diesel and existing Skaglvay
hydro genel'ation, diesel with 'vaste heat recovery, vJOod waste generation
from the Schnabel i'lill in Haines, wind energy generation, and
hydroelectric generation from West Creek near Skagway. Only woodwaste
and hydro provided more economic savings than continued diesel
generation. Woodwaste generation was subject to market risks and
potential shutdowns. The hydroelectric alternative was not subject to
such market risks but the economics were sensitive to load growth in the
tvJO communities. Although the West Creek site has a 13-15 ~iW potential,
the consul tants I'ecommended a 6 HW installation as being sufficient to
meet the 1996 needs of Haines and Skagway. If a need developed, the
project could be expanded at a later date. No significant environmental
concerns were discovered that vvould preclude development of \~est Creek.
West Creek itself is impassible to salmon but has a few resident Dolly
Varden in the lower reaches.
General discussion went over issues of land status, schedule and
costs.
•
•
•
•
Marty Tengs asked when the crossover point between diesel and hydro
costs occurred. From the information to date, the costs are expected to
crossover in 1989-1991. The earliest online date of the project would
be 1987.
The meeting concluded about 9:30 p.m .
..
Name
Archie Hinman
Marty A. Tengs
Sharon Resnick
Da rre 11 ~1ap 1 e
Thomas R. Quinlan
Thomas E. Jackson
Brent Petrie
Wilson Binger
Don Melnick
HAINES PUBLIC MEETING
ATTENDANCE
Apri 1 20, 1982
Ma il i ng Address
P. O. Box 1, Haines, Alaska
P. O. Box 148, Haines, Alaska
P. O. Box 631, Haines, Alaska
City Hall, Haines, Alaska
P. O. Box 130, Haines, Alaska
P. O. Box 402, Haines, Alaska
Alaska Power Authority, Anchorage, Alaska
R. W. Beck, Seattle, Washington
R. W. Beck, Seattle, Washington
....
ALASKA POUTElt AUTHORITY
S~AGWAY PUBLIC MEETING
7:00 p.m., Wednesday, April 21, 1982
The Skagway public meeting on Haines-Skagway energy alternatives
convened at 7:00 p.m., Wednesday, April 21, 1982 at the Skagway City
Hall. Mayor Robert Messegee introduced the study team and members of
the audience. Nineteen people attended on a night when a local softball
game was underway .
~lessrs. t~elnick, Binger, and Petrie gave a summary presentation as
provided in Haines the night before.
General discussion included the merits of an underground vs. an
overhead transmission line in the Klondike Historic Park near Dyea. The
consultants said cost estimates were based on an underground line from
the powerhouse to the Taiya River bridge. However, several Dyea resi-
dents said they would like retail electrical service at their Dyea
homes. This suggests a pole line may be required for distribution and
will need to be considered in discussions with the National Park Ser-
vice.
Land status was discussed and it was reported that the Alaska
Department of Natural Resources and National Park Service were pursuing
a land exchange that would make property available for the West Creek
powerhouse and switchyard.
A woman asked if people would be allowed to harvest firewood from
the area to be cleared. Mr. Petrie replied that arrangements may be
needed with the Department of Natural Resources which owned the
firewood. Mr. Melnick pointed out that a contractor may be concerned
with liability anci accidents if the general public \-Jere in an area vlhere
tree falling \,/as unden;ay and heavy equipment was operating. At G\'een
Lake near Sitka the contractor moved the wood out of the restricted area
and piled it so residents could cut it up. All participants desired
that any wood cleared be made available for local fuel and not be burned
on-site.
There was considerable discussion of wood waste and wind gen-
eration. One reason the woodwaste costs are higher than hydro is due to
the operations costs which are higher. At the present time, the City of
Skagway is using a 10 KW wind generator to supply part of the sewage
treatment plant energy needs. The system has broken down on occasion
but the feasibility report assumes that 20% of the plant needs will
continue to be met by wind generation.
Conservation was discussed. Electrical energy conservation is most
effective where electric heating is involved which is not the situation
in Haines or Skag~ay. Some conservation can be achieved through load
managenient but it \-,i 11 not be enough to offset the need for new gen-
eration.
Mr. Neitzer of Alaska Power and Telephone Company pointed out that
the reports estimated 1981 hydro generation in Skagway to be lower than
actual. Mr. Binger said they would factor the actual AP &T generation
into the final report. A local resident cautioned that 1981 was
actually a wet year in Skagway. Mr. Neitzer pointed out that the new
hydro unit came on-line in July, 1981.
A resident asked if we intended to look at other dam designs. Mr.
Melnick recommended looking at roller compacted concrete if the Power
Authority agreed examination of that option was worthwhile. The
economic analysis period for the project is 50 years but hydro projects
often last longer.
Mr. Petrie asked Mr. Corbus how long the Salmon Creek Project in
Juneau had been in operation. Mr. Corbus replied that Salmon Creek and
Annex Creek (also located in Juneau) were constructed in 1914 and were
on the books for $2 million and still producing electricity.
The meeting adjourned about 10:45 p.m.
,
Name
A. Gordon
Ken Nalan
B. Kalen
Richard Sims
M. Colyer
Jeff Brady
Ken Russo
John McDermott
Pat E1uwe
Bob Messegee
Patrick Mahoney
Bob Zy1man
Remy Wi 11 i ams
Archie Hinman
Bill Corbus
(Haines Lt. & Pwr Co.)
G. Glen Gage
Don Corwin
Mindy Bell
Gary Holmes
Clarisse 1·lahoney
Vernon Neitzer
Stan Seago
SKAGvJAY PUBLIC r~EETING
April 21, 1982
ATTENDANCE LIST*
Mailing Address
Box 375, Skagway, Alaska
Box 138, Skagway, Alaska
Box 317, Skagway, Alaska
Box 517, Skagway, Alaska
Box 245, Skagway, Alaska
Box 1894, Skagway, Alaska
Box 125, Skagway, Alaska
Box 501, Skagway, Alaska
Box 213, Skagway, Alaska
Box 351, Skagway, Alaska
Box 127, Skagway, Alaska
400-112th Avenue, N.E., Redmond, Washington
98004
334 W. 5th Avenue, Anchorage, Alaska
Box 1, Haines, Alaska
134 Franklin Street, Juneau, Alaska
R. W. Beck, Seattle, Washington
Box 88, Skagway, Alaska
Box 222, Skagway, Alaska
Box 124, Sk2gway, Alaska
Box 127, S~a~way, Alaska
Box 207, Skagway, AP&T
Box 1, SkagvJay, Alaska
* Note: All people did not sign in.
JAY S. HAMMOND, GOVERNOR
DEPARTMElft' OF 5&nJRAL RESOtJRCES
DIVISION M MIIICS
619 WAREHOUSE DR., SUITE 210
ANCHORAGE, ALASKA 99501
PHONE: 274-4676
10.J11LH
April 13, 1982
Re: 1130-13
Mr. Brent Petrie, Project Manager
Alaska Power Authority
334 W. 5th Avenue, 2nd Floor
Anchorage, Alaska 99501
Dear Brent:
BECEIVEQ
APR 1 5 1982
ruASKA POWER AUTHORITY
Reference our conversation of this morning with regard to the archaeological
investigation of the West Creek Hydroelectric project area. This letter is to
serve as back-up to indicate the concerns that I mentioned with regard to that
particular survey. Basically speaking, we are concerned that the individuals
involved do not meet the minimum federal requirements, as per 36 CFR 66, to do
archaeological survey. Of course, the federal requirements come into play
since this is a Federal Energy Regulatory Commission project. We are also
concerned that no archaeological permit was granted by either this office or
by any federal agency, as far as we can ascertain, to do the survey work
itself. In addition, the survey methodology is not adequate since no sub-
surface testing was accomplished. The report itself concerns us as well. For
example, on page 63, no mention is made of the importance of coordinating with
the State Historic Preservation Officer (this under the West Creek Drainage
subsection). In addition, on the same page (again concerning the West Creek
Drainage SUbsection) it is apparent that an area of the power corridor was not
surveyed by the team doing the fieldwork. This, then, makes even the
methodology employed suspect. Moreover, to the best of our knowledge, no
consultation was made with this office with regard to the Alaska Heritage
Resources Survey and the information it contains. This is the statewide
survey of historic and prehistoric sites, and it is essential for any archae-
ologist contemplating fieldwork to, among other things, check this inventory
to see what sites are currently known for his/her area of interest.
Because of the reasons stated above, we are not able to accept the archae-
ological survey report for the West Creek proposal. In order to bring the
fieldwork up to acceptable standards, it will be necessary for your agency to
obtain the services of a qualified archaeologist to do an adequate subsurface
survey of the proposed areas of impact. Once the archaeologist is hired to do
this work, we will look forward to consulting with that person to discuss
adequate survey/subsurface testing methodology.
..
Mr. Brent Petrie, Project Manager
April D, 1982
Page 2 -
We look forward to hearing from you concerning this situation, and the steps
to be taken to correct it, at your earliest convenience.
Sincerely,
Chip Dennerlein
Director
iplane
oric Preservation Officer
cc: Dr. Edwin D. Slatter
Staff Archaeologist
Office of Electric Power Regulation
Federal Energy Regulatory Commission
Washington, D.C. 20426
TLD:clk
"
ALASKA POWER AUTHORITY
r--------~.,.,.,._"""" ~~ 277-7641
WORK ORDER$-ISS-'-#?3-cAAP 7) 276-0001
~ 334 WEST 5th AVENUE -ANCHORAGE, ALASKA 99501
•
J U' pooJ' Ul 0 'IClu' '-I ,_-, "u~
Mr. Ty Dilliplane
State Historic Preservation Officer
Division of Parks
Department of Natural Resources
619 Warehouse Drive, Suite 210
Anchorage, Alaska 99501
SUBJECT: Haines-Skagway Region Project
Archaeology Study
Dear Mr. Dilliplane:
FILE CODE 3107'-3 '
EDIN_
We have carefully reviewed your letter of April 12, 1982 in which
you outline your concerns regarding the archaeological reconnaissance
portion of the Haines-Skagway Region Feasibility Study. We believe many
of your objections may stem from a basic misunderstanding of our
intended purpose for this study. As the title of the report implies,
this work examines the feasibility of several electric power generation
alternatives, including the West Creek Hydroelectric Project, to
deternline which is the most economical means for meeting future
electrical energy needs. The study showed that the West Creek Project
was the most economical source of energy for the Region. As part of the
study we also wanted to make certain that no major impediments to
project development existed from an engineering or environmental
perspective before we proceeded with the preparation of a license
application for submittal to the Federal Energy Regulatory Commission.
The preparation of a license application for this project is something
separate from and subsequent to the feasibility study.
In this regard, we often find it helpful in our planning activities
to conduct reconnaissance surveys to obtain prel"iminary predictive data.
This archaeology survey was designed to provide a general impression of
the area's historic properties and their values, and involved
small-scale field work relative to the overall size of the area under
study. We recognized that this survey might not provide sufficient data
to ensure identification of all historic properties in the area. We
believe, however, it has identified areas with obvious or well-known
historic or archaeological value as well as areas where historic
properties are obviously lacking and thus makes possible a more informed
and efficient intensive survey at a later time as part of the FERC
license application process. We believe our consultant's study of the
area was adequate for reconnaissance purposes and that their report
provides a generally informed opinion about the kinds of properties that
might be encountered should a decision to proceed make necessary a more
intensive survey.
".
Mr. Ty Dilliplane
May 27, 1982
Page 2
You mention concern that the archaeology reconnaissance team used
by our consultant does not meet "minimum federal requirements". After
careful review of 36 CFR Part 66 and several discussions with Dr. Edwin
Slatter of the FERC, we do not understand this concern. Your conclusion
comes as a further surprise since Dr. Slatter reviewed the pertinent
resumes and advised our consultants on September 9, 1981 that he felt
the team's experience was entirely adequate for the level of work being
done. In addition, Dr. Slatter advised our consultant on September 16,
1981 that he had informed you of his opinion by phone on September 11,
1981.
The above concern with respect to the qualifications of the study
team had been raised in response to our consultant's application for a
Field Archaeology Permit. No written rejection of the permit was ever
received, although you indicated orally that in your opinion the team
did not meet federal requirements. This precipitated Dr. Slatter's call
of September 11, 1981 in which he informed you that he found the team
acceptable. Although Dr. Slatter's call was not followed by a letter,
at that point we thought the matter was settled, even though the
consultant never received the permit or a letter explaining why it was
not granted.
With regard to subsurface testing, we do not agree that the lack of
such testing renders the survey methodology inadequate. As we explain
above, the purpose of this study is the preliminarf identification of
areas which could have historical or archaeolog;ca significance, not an
exhaustive study of those areas. Furthermore, the consultant
specifically stated in their letter to you dated July 30, 1981, "We do
not intend to do any archaeological digging or recovering as part of
this work."
The point is made in your letter that the report includes no
mention of the "importance of coordinating with the State Historical
Preservation Officer". We are not certain why such coordination needs
to be referenced in a feasibility study. We did notify you of our
interest in the area through the permitting process and our consultant
provided you with a copy of the draft archaeological-historical
resources report in December 1981. They received no response to this
draft. Further we provided your office with a draft of the full
feasibility report for review and comment in April 1982.
We are aware that coordination with the SHPO is required during
preparation of the FERC license application and intend to consult with
you during that phase of our work.
We also see no cause for alarm that portions of the power corridor
were not included in the archaeological reconnaissance since the length
of corridor not surveyed coincides with the power tunnel which would be
excavated through bedrock several hundred feet below the earth's
surface. We can see no way in which surface or near surface sites will
be disturbed as a result of constructing this portion of the project.
•
Mr. Ty Dilliplane
May 27, 1982
Page 3
Now that our feasibility study has been completed, the decision has
been made to prepare a draft license application for the West Creek
Hydroelectric Project. You will be pleased to know that we fully intend
to coordinate the preparation of pertinent portions of this application
with you and your staff in your role as State Historic Preservation
Officer. We anticipate that some additional field work may be required
during the preparation of the application. Any work performed as part
of the licensing process will, of course, be coordinated through the
SHPO.
Since your letter of April 13, 1982 addresses processes more than
substance, we would appreciate a more substantive review of the subject
report to aid us in determining those areas where detailed field surveys
may be warranted. Such feedback will aid us in defining the scope of
work of additional cultural and historical survey services. We look
forward to receiving your reply to our requests for clarification
included above so that future misunderstandings can be averted and
mutual goals met in a spirit of professionalism and cooperation.
FOR THE EXECUTIVE DIRECTOR
BNP:mw
cc: Dr. Edwin D. Slatter
Division of Environmental Analysis
Federal Energy Regulatory Corrmission
Washington, D.C. 20426
Wilson Binger
R.W. Beck & Associates
200 Tower Building
Seattle, Washington 98101
Dan Bishop
Environaid
12175 Mendenahll Loop Road
Juneau, Alaska 99801
John Cook
Director
National Park Service
540 West 5th Avenue
Anchorage, Alaska 99501
Dan Robinson
Acting Director
Alaska Division of Parks
619 Warehouse Drive, Suite 210
Anchorage, Alaska 99501
Brent N. Petrie
Project Manager
ALASKA POWER AUTHORITY
~ 334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501 Phone: (907) 277·7641
(907) 276·0001
•
..
..
,
Mr. Ty Dilliplane
State Historic Preservation Officer
Alaska Division of Parks
619 Warehouse Drive, Suite 210
Anchorage, AK 99501
August 2, 1982
RE: Haines -Skagway Feasibility Studies
West Creek Project Site
Dear Mr. Dilliplane:
Thank you for your letter of July 1, 1982 regarding archeological
surveys for the West Creek hydroelectric project. After considering the
geotechnical, environmental, economic, and cultural resource issues
addressed in the project, we have instructed our prime consultant, R. W.
Beck and Associates, to proceed with the next phase of the project and
to prepare a draft license application. To address the cultural and
archaelogical resources in proper detail for this phase, R. W. Beck has
proposed to engage the services of Ertech, with Gail Thompson of Ertech
in charge of the research methodology. Ms. Thompson has done previous
similar work in Alaska and her credentials are known to your office.
R. W. Beck has instructed Ms. Thompson to coordinate directly with your
office to develop an acceptable research program building upon available
documentation and field visits as required. We understand that such
consultation is presently underway.
Please do not hesitate to contact U$ if you have any further
comments or concerns on this matter.
cc: W. Binger, R. W. Beck
Dr. E. Slatter, FERC
John Cook, NPS
hr Brent N. Petrie
Project Manager
•
•
DEPlUlTMENl' OF lWBIJRAL RESOIJR~ES
DIVISION OF PAllleS
September 7, 1982
Re: 1130-13 (West Creek Hydro)
Brent Petrie
Alaska Power Authority
334 W. 5th Avenue
Anchorage, Alaska 99501
Dear Mr. Petrie:
JAY S. HAMMOND, GOVERNOR
619 WAREHOUSE DR., SUITE 210
ANCHORAGE, ALASKA 99501
PHONE: 274-4876
RECElVEO
SEP 1 31982
A\.}.S'AA PO'l'JER AUTHORITY
Thank you for your letter of August 2 regarding archaeological survey for the
West Creek Hydro Project.
Ertec has been on our list of qualified archaeological contractors for some
time. We have been in contact on several occasions with Dr. Gail Thompson and
have received a proposed research design for supplementary survey on the West
Creek Project. We find the research design completely acceptable and have
informed Dr. Thompson of this by phone and letter (copy enclosed).
We look forward to continuing consultation with Ertec and good working rela-
tionships with all parties involved.
Sincerely,
Judith E. Marquez
By: Ty L.
('~
iplane -----toric Preservation
enclosure
TAS: elk
..
"
..
Department Of Energy
Alaska Power Administration
P.O. Box 50
Juneau, Alaska 99802
iVlr. Eric Yould
Executive Director
Alaska Power Authority
334 West 5th Street, 2nd Floor
Anchorage, AK 99501
Dear Hr. Yould:
April 21, 1982
We have reviewed the draft Ha';nes-Skagway Region Feasibil ity Study and
found it very well done and complete. We agree with the conclusions that
West Creek is probably the best energy alternative to meet projected
loads for the area. The wood waste steamplant at Haines looks like a
reasonable short-term energy supply, but the dependence on a sizable
local timber harvest reduces the long-term energy reliability.
We have a few specific comments to offer.
o The degree-days and annual space heating kWh seem to be interchanged
on pages III 17 and 18.
o The operation, maintenance and replucement costs on page XV-4 are
not presented in enough aetail to fully review, however, the annual
provision for replacement of the underwater cable could well amount
to 50 percent of the total estimated $634,000 annual cost .
o A table or graph showing future loads and resources would help
illustrate how the existing and planned hydro resources would be
ut il i zed.
We appreciate the opportunity to comment.
Sincerely,
r') U" ,f~ \_ .. \ / /,,' _, "''',
• \ .J f't (' , ./.--~ i _., -~ .-,-----
Robert J. Cross
Adm'; ni strator
DEDMAN'S PHOTO SHOP
BOX 417
SKAGWAY, ALASKA 99840
April 23, 1982
Hr. Brent Petrie, Project i'lgr.
Alaska Fower uthority
334 West 5th Ave, Second ~oor
Anchorage, Alaska
Dear :.1r. Petrie:
RECEIVED
P.?R 2 71982
~ POWER AUTHORITY
I would like my com~ents on the written record, in favor
of continuing with the West Creek Hydro project. From the figures you showed at
the hearing this week, it is definitely the cheapest way to go for ..:Jkagway-Haines
power over a :?eriod of years. I think that in any case, ' .... herever possible, Hydro
projects shaa~dbe developed to protect communities from the uncertainties of
petroleum .supply. In addition tltl price increases, over the next 2D-30 years,
who knows what the situation ~i6ht be? Thi.s particular little project seems
like a very good one, as there is so little in the way of fisheries or ~ame to
be displaced. I do hope, however, that .some timber can be salvaged from the
area to be flooded.
3incerely yours, ~
B~/
Barbara D. Kalen
,
'f
•
P. o. BOX -·303 ,,'
HAINES, ALASKA 99827
April 26, 1982
HECEIVED
:' ~~ 3 a 1982
Mr. Brent Petrie l,~,ASKA POWER AUTHORITY
Project Manager
Alaska Power Authority
334 West 5th Avenue, Second Floor
Anchorage, Alaska 99501
Dear Mr. Petrie:
The Haines Light and Power Co., Inc. (HLP) has carefully
reviewed the draft Feasibility Study of Energy Alternatives
for the Haines-Skagway Region. HLP is pleased with the
Study and has no further suggestions to make in regard to
its accuracy or comprehensiveness. HLP is of the opinion
that the wood waste steam generator to be operated by the
Schnabel Lumber Company will not provide a reliable source
of energy for the Haines area over the long run. Therefore,
HLP recommends that the Alaska Power Authority proceed with
the development of the West Creek Hydroelectric Project.
HLP urges the Alaska Power Authority to press forward with
the resolution of the land status and water rights problems
in order that the license application can be prepared and
submitted to the Federal Energy Regulatory Commission .
Please contact me if you have any questions.
Copy to: City of Haines
AH/ak
Very truly yours,
a~~
Archie Hinman
Manager
•
United States Department of the Interior
IN REPLY REFER TO:
Mr. Eric Yould
Executive Director
Alaska Power Authori ty
334 West 5th Avenue
Anchorage, Alaska 99501
Dear Mr. Yould:
FISH AND WILDLIFE SERVICE
P. O. Box 1287
Juneau, Alaska 99802
RECEIVED.
PIPR 2 81982
'AfN,KA POWER AUTHORITY
April 26, 1982
Re: Energy Alternatives for the
Haines-Skagway Region (West Creek)
Draft Feasibility Report
We have reviewed the subject draft feasibility report and offer the following
comments.
General Comments
We are pleased that alternatives previously considered at Kelsall River and
Nataga Creek have been removed from further consideration. Transmission lines
would have been routed through important eagle habitat and created
unacceptable impacts. In contrast, fish and wildlife values are relatively
low at the \vest Creek. However, there is existing fish and wildlife habitat.
Therefore, the subject report should include more specific information to show
that all reasonable measures will be taken to minimize potential impacts.
Specific Comments
Page IV-2, third paragraph. Hydroelectric Generation. The narrative states
that a letter report on Goat Lake is incluned in Appendix B; it was not
included in the subject feasibility report. Since Goat Lake was the most
likely hydroelectric alternative to the West Creek project, we suggest that
the analysis of this alternative be included in the main text of the final
report.
Page XIV-3, third paragraph, Fisheries Resources. He suggest that the last
sentence of this paragraph be expanded to more accurately describe the
potential impacts on Dolly Varden when West Creek is dewatered. Furthermore,
during initial dewatering, this stream reach should be monitored for fish
entrapment problems and if they exist, mitigative measures should be developed.
Page XIV-4, second paragraph. Fisheries Resources. The first sentence should
be expanded to describe anticipated flow rates with the project. We also
suggest that data on the relative abundance of eulachon be collected for
inclusion jn the future environmental impact statement. Runs of these species
often provide food for eagles.
•
Page XIV-4, third paragraph. Fisheries Resources. We suggest that the
accepted construction practices be described in more detail.
Page XIV-4, fourth paragraph. Fisheries Resources. We suggest that this
paragraph be modified to describe the anticipated changes in temperature
whether significant or not.
Thank you for the opportunity to comment.
Sincerely yours,
-; t,
Field Supervisor
a"
./ ,
>c:L ""-.
2
.•
,.
•
Mr. Waine E. 01en
Field Supervisor
Division of Ecological Services
Fish and Wildlife Service
P.O. Box 1287
Juneau. Alaska 99802
Dear Mr. 0ien:
May 24, 1892
Subject: Energy Alternatives for the
Haines-Skagway Region (West Creek):
Draft Feasibility Report Comments
We appreciate reeeivingyour comMents of April 2&, 1982, regarding
the subject feasibl1ity report. Following 11 further information
regarding your specific COlllnentS:
Page IV-2 third paragraph;
The Goat Lake alternative was found to be less feasible than the
West Creek alternative as discussed in the feasibl1ity report. A copy
of the letter report describing the results of our reconnaissance of
Goat Lake is enclosed for your information and will be included in the
final version of the subject report as Appendix A.
Page XIV-3, third paragraph;
Two smell tributaries (les5 than 1 cfs each) join together to flow
into West Creek between the dam site and the proposed tailrace location.
These two streallS Ire located in the middle blsin of West Creek and
support a very low dt!nsity population of resident 00l1y Varden char
according to a survey made on August 27, 1981 by AOF&G biologists
Steven T. Elliott and Mark Schwan. Th@y concluded that the stream makes
an insignificant contribution to the annual production of char from West
Creek (Memorandum from S. Elliott to ~. Schwan dated
September 30. 1981). In view of this conclusfon, we also beHeve the
impact to the West Creek char population from dewatering this portion of
West Creek will be insignificant. We agree, however, that this reach of
stream bears inspection during the initial dewltering to t~ to
detennine if any strand1ng occurs.
Page XIV-4, second paragraph;
Data on proposed changes in flow regime were not included in the
fisheries section IS noted in your letter. Please refer to Section XI
••
Mr. Walne E. Ulen
May 24, l.982
Page 2
of the same report where the information you seek will be found in
Tables XI-7 and XI-8.
Page XIV-4, third paragraph;
Investigations of the timing and distribution of eulachon runs in
the Tl1ya River and at the mouth of Vest Creek are still in progress.
As indicated in our feasibil1ty report, water temperature data are still
being collected from the ma1nstem Ta1ya River and West Creek. Upon
conclusion of this wort, Env1ronafd will prepare I supplementary report
covering eulachon runs and water temperature impacts. Information from
this report will be incorporated into appropriate sections of Exhibit E
of the FERe license application for the West Cruk Project. In this
manner, study results will become Iva11able to 811 concerned agencies
for their review and connent •.
Page XIV-4 t fourth paragraph;
At the feasibility stage. it il often premature to identify
specific construction .alures that contracto" will employ to meet
constMlction standards and contract stipulations. license articl" do
specify that contract doculll!nts include eroSion control plans. soils
waste disposal plans. hazardous substance control pl.ns. water quality
control plans, and required site restoration programs. All such plans
will be developed in coordination ~th the concerned federal and state
agencies involved before the p.lans are sent to the FERC for final
approval. This opportunity for agency input COIIeS after the contractor
has had an opportunity to develop a let of draft plans for the
particular site conditions associated with the project.
We hope thi s response has answered your concerns and we look
forward to continuing our coordination with your staff as the West Creek
Project progresses. If you have any further questions regarding West
Creek, please get in touch wfth us.
FOR THE EXECUTIVE DIRECTOR
Very truly your! •
(5 1/M~J ?,be JoY'') ~ )
Brant N. Petrie
PnJject Manager
RECEIVEC
"t 0 . " . ~i 1992
~Y.A PC'I:EH ACTNORITY
CITY OF SKAGWAY, ALASKA
RESOLUTION 82-9R
A RESOLUTION SUPPORTING DEVELOPMENT BY THE
ALASKA POWER AUTHORITY OF A HYDROELECTRIC
FACILITY ON WEST CREEK
WHEREAS: The cost of diesel-generated electricity is
burdensome to the consumers of the Haines-
Skagway area, and
j
WHEREAS: A recent feasibility study of the hydroelectric
potential of the Haines-Skagway Region conducted
by R. W. Beck and Associates, Inc. has identified
West Creek as the most desirable economic
engery alternative for the region, and
WHEREAS: The National Park Service has shown a willingness
to cooperate with development of this project, and
WHEREAS: The hydroelectric development of West Creek could
adequately handle all projected load growths for
the region through the year 2000.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY
OF SKAGWAY, ALASKA:
That the Skagway City Council supports development of a
hydroelectric facility at West Creek and urges the Alaska
Power Authority to actively continue geotechnical investi-
gations, design, and FERC licensing procedures relevant to
completion of this project.
PASSED AND APPROVED April 29 , 1982. ------------~--------------------
ATTEST:
~_8 . .J~c!~) ene: Gordon; 1. ty erlC
. -----I
702 WATER STREET, PORT TOWNSEND, WASHINGTON 98368
TElEPHONE (206)385·1733
AL~KA SOUTHERN POWER COMPANY
SKAGWA Y POWER & LIGHT SYSTEM
TOK .,OWER & LIGHT SYSTEM
NATIONAL UTILITIES, INC.
ALASKA CENTRAL TElEPHONE SYSTEM
SKAGWAY TElEPHONE SYSTEM
SOUTHERN ALASKA TElEPHONE SYSTEM
AL~SKA POWER & TElEPHONE CORPORATION
Mr. Eric P. Yould, Executive Director
Alaska Power Authority
334 West 5th A venue
Anchorage, Alaska 99501
Dea r Mr. Yould:
ftECIPiiD
.. ,~,'( 0 5 1SS'2 ARTHUR GARRETT
Chairman
\lIl::ft A I !T!i!lRlT'l NANCY GARRETT BROWN 'a,·ac:.v.A PCl";!;n ~ . Vice Chairman
~' MARGUERITE GARRETT
May 5, 1982
Secretory
MARILOU K. RAYMOND
Senior As't. Secretory
RALPH J. WILSON
President
VERNON J. NEITZER
Vice President & Chief Engineer
ROBERT S. GRIMM
Vice President & Treasurer
GAIL BROWN HOBBS
As't. Secretory & As't. Treasvrer
In response to your letter of March 3, 1982, I have reviewed your draft feasibility
study of Energy Alternatives for the Haines -Skagway Region and I am struck again by your
proposal to ha ve the people of Skagway pay and pay dearly for the $10 million interconnection
transmission line to Ha ines which could, at the very most, be a rna rginal benefit to Haines
alone. Twenty-five years ago, a very prominent engineering finn looked at the possibility
of a transmission line interconnection between Skagway and Ha ines and decided that it wa s
not feasible. If there had been any potential outside of a limitless government financing
situation, they would have told us.
The Dewey Lakes System actually generated 2,915 MWh of energy in 1981, not the 1,500
MWh that you show in your report. This 2,915 MWh of hydro generation is 50% of the total
of 5,824 MWh generated at Skagway in 1981 and shows that the current Skagway system has
" a 5096 hydro mix and not the 1096 hydro mix that you use as a base case alternative. The
large unused head in the Dewey Lakes System which can be utilized as the load grown insures
a high percentage of hydro at Skagway for the foreseeable future.
It would apparently be against all public policy for the people of Skagway to have to sub-
sidize the power costs at Haines. The Haines load is not dependable because of the problems
of a submarine transmission cable which lea ves the proposed $56 million project with no
dependable load. The people of Skagway cannot be expected to foot the bill for such a project
when the small scale development of the existing system will meet all foreseeable energy
needs at a far less cost. The $56 million project you are proposing to serve less than
3,000 people at an investment of around $20,000 per person is apparently the result of
taking the commendable concept of renewable resource development and expanding it all out
of proportion on the basis of using as much of the State of Alaska's oil wealth as possible.
,
Mr. Eric P. Yould, Executive Director
Alaska Power Authority
Page Two
The annual interest of $6.7 million on $56 million at 12% is over three times the total present
annual amount that the people in Skagway and Haines pay for their energy needs. We can
only look at these projects from the standpoint of hard economics and the people paying
the cost of the power they use and we can therefore see no justification in this project that
you are proposing.
Sincerely,
Presi
RJW/ry
ALASKA POWER AUTHORITY
• 334 WEST 5th AVENUE -ANCHORAGE, ALASKA 99501 Phone: (907) 277-7641
(907) 276-0001
..
Mr. Ralph Wil son
President
Alaska Power and Telephone Company
P.O. Box 222
Port Townsend, Washington 98368
July 30, 1982
Subject: Haines-Skagway Feasibility Study
Oea r Mr. Wi 1 son:
Thank you for taking the time to review the Haines-Skagway fea-
sibility report and provide some thoughts on the study in your May 5,
1982 letter. We would l"ike to provide some comments in response to the
issues you raise.
In paragraph one you state IITwenty-five years ago, a very prominent
engineering firm. looked at the possibility of a transmission intercon-
nection between Skagway and Haines and decided that it was not feasi-
ble.1I In earlier correspondence, you advised us that the Ilprominent
engineering firmll is the same firm that has conducted the present
feasibility study. Since 1957 the loads, costs of diesel fuel to
generate electricity, and cable manufacture and installation have all
undergone changes. In 1957 the cost of diesel fuel was less than 20¢
per gallon and in 1981 the price in the Haines-Skagway area was about
$1.12 per gallon. Furthermore, the past twenty-five years have resulted
in improvements in submarine cable manufacture and installation. These
factors combined with the possible utilization of renewable generation
source and the combined loads of Skagway and Haines make the submarine
cable interconnection look much better today than it may have in 1957.
In response to paragraph two, we were first given the new hydro
generation data by Mr. Vernon Neitzer of AP&T at the April 21, 1982
public meeting on the draft report in Skagway. We are now incorporating
that into the feasibility study. However, we do not believe that the
new data will be a significant factor in the final conclusions of the
study. While the 2915 MWh represents 50% of the 1981 AP&T generation in
Skagway, it is less than 20% of the combined Haines and Skagway 1981
energy usage. Further under Scenario B this drops to 9% of the combined
energy requirements by 1996. Thus, even with the new data, the hydro
mix may decrease to below 10% as the load grows. In addition, the
expanded Skagway hydro plant has been in operation only one year. We
intend to increase the hydro generation figure for Skagway, although we
would like to point out that the long term average will, in fact, be
subject to the natural variation in runoff. 1981 was a wet year in
Skagway and thus there is reason to think that the long term average
will be less than the 2915 MWh generated in 1981.
•
..
Mr. Ralph Wilson
July 19, 1982
Page 2
The final statement that the large unused head in the Dewey Lakes
system can be used to maintain a high percentage of hydro even as the
load grows is only partially correct. The Dewey Lakes system is ba-
sically a run-of-river system with little storage; flow is available
mainly in the summer and the energy generated can be used only to the
extent that there is a demand for energy concurrently with the flow .
Developing the Upper Dewey Lake project will not change this. Thus,
while development of the complete Dewey Lake system would increase the
hydro capacity of the Skagway system, the increase in energy production
will be limited by the demand for electricity during the summer months.
This restriction would probably mean that the Dewey Lake hydro system
without some sort of storage for carryover into the low flow months
would not meet more than 50% of the energy requirements of Skagway and a
significantly smaller percentage of the combined Haines and Skagway
loads.
We are making adjustments in the economic analysis to include the
additional hydro generation by AP&T and will also consider the gener-
ation in preparing a plan of finance for the project.
As far as costs go we are actively investigating two alternatives
that may lower the cost of the dam. One possibility is the use of
roller compacted concrete and the other is the use of waste rock from a
highway project. A dam in Oregon is presently under construction using
roller compacted concrete, and the highway work is still being engi-
neered. The cost estimate for the rockfill dam with rock quarried at
the site may be higher than with the other alternatives but does provide
a greater degree of confidence for use in the economic analysis at this
time .
There are a variety of methods of finance available through
Power Authority and these will be developed in a plan of finance
will accompany our findings and recommendations on this project.
of an on-line date for the project will also be discussed in the
mendations. These will not be available until about three weeks
release of the final feasibility report.
the
that
Timing
recom-
after
Based on the technical data, economic analysis and comments on the
draft report, we will be recommending that state and federal govern-
ments proceed to amend any land ownership patterns or land classifica-
tions that my adversely affect development of any West Creek project.
The land situation is quite important as it affects all of the West
Creek project configurations that have been suggested.
s;nCe~elY~. ~ ~Uld~
Executive Director
United States Department of the Interior
NATIONAL PARK SERVICE
IN REPLY REFER TO:
L7619(ARO-P)
Mr. Brent Petrie
Project Manager
Alaska Power Authority
333 West 4th Avenue, Suite #31
Anchorage, Alaska 99501
Dear Mr. Petrie:
SRCErVED.
MAY 1 1 1982
A11SKA POWER AUTHORITY
We have reviewed the Environmental Investigation of the West Creek Hydroelectric
Project by Daniel M. Bishop and Associates, and the Haines-Skagway Feasibility
Study, Volume 1, Report by R. W. Beck and Associates, Inc. Our main concerns
have to do with the cultural resources section and the section on fisheries.
We appreciate the opportunity to review these documents and our comments
foll ow.
Fisheries
On page XIV-4 of the feasibility study, it is unclear how or why no significant
alterations in water temperature regime are anticipated. The text indicates
an evaluation of natural preproject water temperature regime is planned but no
mention is made of the possible mitigation of unnatural stream water tempera-
tures through dam intake design or other methods. Perhaps you are considering
this; however, it is not stated in the report.
Page XIV-4 mentions the spring spawning of eulachon in lower West Creek and
that the annual flow variation could affect fish spawning or rearing in lower
West Creek. The report continues on to say that no impact on sports or subsis-
tence fishing is expected. Presently, dip netting for eulachon in lower West
Creek is a recognized sports fishing activity. Perhaps an in-stream flow
study, a study of the ecological requirements of eulachon spawning, and a
development of mitigating measures is needed. We do feel there should be some
discussion of these concerns.
Page XIV-6 suggests either a hatchery or artificial spawning channels at the
tailrace, presumably for salmon. We are more concerned with the possible loss
of eulachon since significant runs could be affected while salmon losses might
be minimal.
We are also concerned with salmon production. However, hatcheries or spawning
channels might produce far more salmon than project losses. We feel discussions
and concerns for the perpetuation of the euchalon runs in West Creek should be
given more consideration than is presently in the report.
Cultural Resources
The cultural resources investigations appear to be superficial, amounting to
an incomplete, limited reconnaissance, and at the most a basic evaluation of
both resources values and potential impacts of the proposed project upon these
values. Given the objectives and intent of the survey, the cultural resources
report was found to be seriously deficient and of limited utlility for deter-
mining potential project impacts on archeological and historical values in
2
areas proposed for development and in areas adjacent to the planned development.
In particular, we are concerned because the National Register status of the
area was virtually ignored and is an oversight that should be corrected, e.g.,
Klondike Gold Rush National Historical Park was listed on the National Register
of Historic Places on June 30, 1976; the Skagway and White Pass District
(Alaska Heritage Resources Survey Site No. SKG-013) was entered on June 13,
1962 as a National Historic Landmark; and the Dyea and the Chilkoot Trail
(SKG-067) was listed on the National Register on April 14, 1975 and designated
a National Historic Landmark on June 2, 1978. The resource document is also
inadequate for determining the effect of the proposed project on these National
Register properties; a requirement of federal law and regulation.
We also have reservations about the survey design and sampling strategy, and
criteria for determining site significance, the nature of survey permissions
and permits reportedly obtained, and whether the survey archeologists were
qualified under Department of the Interior regulations to conduct archeological
investigations on federal lands.
We do support one conclusion reiterated throughout the cultural resource
section of the environmental investigation: additional archeological-
historical surveys and evaluations are needed. Because of this fact and the
nature of the reconnaissance described in the report, many areas w"ill need to
be not only surveyed but reexamined as well.
In summary, the cultural resources survey and report document for the West
Creek Hydroelectric Project serves as a basic resource evaluation of limited
utility for determining potential impacts of the proposed development upon
archeological and historical resources. In light of the report deficiencies,
we regard it as an unacceptable product. We therefore do not support the
conclusions concerning potential project impacts upon cultural resources
discussed on page XIV-10 to XIV-12 of the feasibility study. Instead, we see
a likelihood that impacts (direct, indirect and secondary) could occur to
cultural resources in the project areas as a result of any of the proposed
developmental alternatives.
We hope this critique will assist project planners in rectifying the inadequacies
of the evaluation documents and the mitigation strategies proposed in the
feasibility study and bring them more into line with accepted procedures and
objectives for such undertakings.
Our third and last concern is that serious consideration be given to placing
all power lines underground where they pass through the park.
1
We look forward to working with you as the project moves forward.
Sincerely,
~~0~
Regional Director
Alaska Region
3
,
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Mr. Douglas G. Warnock
Acting Director, Alaska Region
National Park Service
U. S. Department of Interior
540 West Fi fth
Anchorage, Alaska 99501
July 16, 1982
Subject: Haines Skagway Region Project
Feasibility Study
Dear Mr. Warnock:
We have reviewed your letter of May 6, 1982 (L 7619
(ARO-P) in which you outline your concerns regarding the
cultural resources and fisheries sections of the
Haines-Skagway Region Feasibility Study.
Phone: (907) 277-7641
(907) 276-0001
Your comments on the fisheries section are primarily
concerned with the potential impact of the Project on the
eulachon run in the Taiya River. Our environmental
consultant, Environaid, has recently completed some additional
field work which should answer some of your concerns. They
wi 11 prepare a report di scussi ng these studi es and any
concl us ions whi ch can be drawn as to the impact of the Project
on eulachon spawning. This information will be included in
the draft FERC license application when it is prepared.
Your comments on cultural resources deal mainly with the
perceived deficiencies in the archaeological studies which
have been conducted to date. We think many of your objections
may stem from a basic misunderstanding as to the purpose of
the study. Our response to the comments from the State
Historic Preservation Officer discusses this point in detail
and we refer you to the attached copy of that letter. For
preparation of the draft FERC application, the consultant in
supplementing the project team and field work with individuals
and activities that should be acceptable to the SHPO and NPS
for the more detailed level of analysis.
Finally, as stated in the report and in discussions with
Park Service personnel, we are prepared to place'the
transmission line underground where it passes through the
Park, if that is considered desirable at the time of
Mr. Douglas G. Warnock
July 16,1982
Page 2
construction. However, during-public hearings on the project
in Skagway, there was substantial interest expressed in
electrical service in the Dyea area. If poles are utilized
for retail distribution of electricity, then we would suggest
consideration of placing the distribution and transmission
lines on the same poles where possible.
Sincerely,
'ic 'Po ~;>-\ ~
Executive Director
Attachment: as stated
,
•
MEMORANDUM State of Alaska
TO:
FROM:
DEPA.RTMENT OF NATURAL RESOURCES
IJ[VISION OF RESEARCH AND DEVELOPMENT
BRENT PETRIE
Alaska Power Authority
REQEIVell,
DATE:
FILE NO:
~ .:AY 71982
TELEPHONE NO:
LEILA~:SE POWER AUTHDBJD'
DNR Clearinghous~ainator
SUBJECT:
May 6, 1982
276-2653
DNR Comments: Draft
Feasibility Study
Haines/Skagway
The Department of Natural Resources appreciates the opportunity to
comment on the draft feasibility study of Energy Alternatives for
the Haines/Skagway region. Following are comments from the Division
of Land and Water Management, Water Management Section. Comments
from the Division of Parks were sent directly to your office.
The DLWM, Water Management Section, reports that this appears to
be a thorough feasibility study and agrees that this appears to be
a viable project. APA is reminded that the Division of Land and
Water Management is responsible for issuing both a permit to
construct or modify a dam and a water rights permit.
a. Permit to Construct or Modify a Dam:
Prior to issuing the permit, DLWM must be assured that the
dam will not create a public safety hazard. After state of
the art analysis of the design and construction and the
proposed operation and maintenance schedules, certification
to this effect will be acceptable. If the Federal Energy
Regulatory Commission (FERC) is involved in licensing the
project, their dam safety certifications will be accepted.
For dams not reviewed by FERC, DLWM will review work done by
the applicant so that DLWM may certify the dam's safety. As
the project develops, please send DLWM dam safety certifications
or other appropriate documents.
b. Water Rights Permits:
According to AS 46.15.080, a water rights permit shall be
issued if it is found that:
1. The proposed appropriation will not unduly affect the
rights of a prior appropriator.
2. The proposed means of diversion or construction are
adertuate.
3. The proposed appropriation is in the public interest.
To ,~valuate this, among the items to be considered are
changes in the following as a result of the proposed
water appropriation:
(a) economic activity
(b) fish and game resources,
(c) public recreational opportunities,
02-001 AI Rev,1 0179)
.-
Brent Petrie 2 May 6, 1982
(d) public health,
(e) loss of alternate uses of water that might be made
within a reasonable time,
(f) harm to persons, or
(g) access to navigable or public waters.
APA has filed a water right application for this project; the
application has a priority date of June 4, 1981. The Alaska Power
and Telephone Company has also proposed a hydroelectric project on
West Creek and has filed a water right application for their
project. The AP&T project has a priority date of October 10, 1980,
some 7 months earlier than that by APA. DLWM is currently evaluating
the merits of both projects. A final decision on award of permit
will forthcoming. Depending on the decision, processing of APA's
water right application may continue at that time. To do this,
the items mentioned above must be addressed for each project
stage, including construction, reservoir filling, and operation.
If negative impacts are noted, mitigation strategies and associated
costs should also be discussed. DLWM considers the report being
reviewed partially adequate for water rights adjudication. Some
items mentioned earlier are not discussed in enough detail and
others are not discussed at all.
DLWM understands that it is not the intent of this study to present
detailed information as described above. However, please be
advised that this information is necessary to adjudicate the
application to construct or modify a dam and the application for
water rights according to DLWM legal responsibilities.
...
•
DEPAR'DIE5T OF lW&rIJRAL RESOIJRCES
DIVISION M PAIIKS
May 6, 1982
Mr. Brent Petrie, Project Manager
Alaska Power Authority
334 West 5th Avenue
Anchorage, Alaska 99501
Dear Mr. Petrie:
JAY S. HAMMOND, Conrnor
230 South Franklin
Suite #307
Juneau, Alaska 99801
PHONE: 465-4290
REOEIVED.
MAY 1 01982
AL'SKA POWER AUTHORITY
The Department of Fish and Game has reviewed the final draft of the
Haines-Skagway Region Feasibility Study. This Department has no serious
objections to the proposed hydroelectric project on West Creek. We feel
the impacts to fish and wildlife resources can be kept to a minimum with
proper project planning.
In discussions with R. W. Beck and Associates, we were assured that the
minimum flow of 10 CFS we requested in West Creek could be maintained in
the channel below the powerhouse with no trouble.
We strongly recommend that the off-site housing option be employed
during construction to reduced bear/people conflicts. If the on-site
option is selected, careful garbage disposal and camp maintenance will
be necessary to prevent attraction of bears.
We do feel two additional items regarding wildlife impacts need to be
addressed prior to filing the license application:
1. What long term impacts, if any, of moose habitat might occur down-
stream of the project area due to flow regime changes?
2. A more detailed survey to determine if bear dens are present in the
project area.
We also assume that more detailed construction information would be in-
cluded in the license application if it ;s eventually filed.
Thank you for the opportunity to comment and we look forward to working
with you as the project develops.
Sincerely,
Richard D. Reed
Regional Supervisor
..
..
Mr. Brent Petrie
cc: R. W. Beck and Associates
R. Ball, ADF&G, Yakutat
R. Staska, ADF&G, Haines
D. Marriott, ADF&G, Juneau
RDR:kk
- 2 -May 6, 1982
•
•
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE -ANCHORAGE, ALASKA 99501
Mr. Richard D. Reed
Regional Supervisor
Habitat Division
Department of Fish and Game
230 South Franklin
Juneau, Alaska 99801
SUBJECT: Haines-Skagway Region Project
Feasibility Study Report
Dea r r~r. Reed:
July 12, 1982
Phone: (907) 277-7641
(907) 276-0001
Thank you for your 1 etter of ~1ay 6 1982 commenting on the subject
report. In the letter you mentioned two items which you feel should be
addressed prior to filing the license application of the project.
Copies of your letter went to both Haines and Skagway. As a result we
received the attached response from Skip Elliott, the City Manager of
Skagway and a resident of Dyea. Based upon further discussions with our
environmental consultants and Mr. Eliott's letter, we do not believe
that either area of concern warrants further field study. We will be
prepared to elaborate on those items during preparation of a draft FERC
license application.
If you have any further comments, please contact us.
FOR THE EXECUTIVE DIRECTOR
Very truly yours, &~~fl(?e~
Brent N. Petrie
Project Manager
'I
•
CITY OF SKAG WAY
May 20, 1982
Mr. Brent Petrie
Alaska Power Authority
334 West 5th Avenue
Anchorage, Alaska
99501
Dear Mr. Petrie:
GATEWAY TO THE GOLD RUSH OF "98"
P. O. BOX 415 SKAGWAY. ALASKA 99840
Kevt::l'1It:tJ
I~ ~J\V ~ S 1('10')
"./"'\ --. ~ .... -.', ..
I have reviewed the Environmental Investigation of the West Creek
Hydroelectric Project by Dan Bishop and the Haines-Skagway Region
Feasibility Study by R.W. Beck and I found them to be quite thorough.
In addition, I have reviewed the comments submitted by the National
Park Service, the Alaska Department of Fish & Game, and the Division
of Parks regarding these studies and I would like to respond to them.
As you know, I have lived in Dyea near the proposed hydroelectric
project for nearly eight years. In addition, I believe that I have
spent more time within the proposed reservoir area than anyone else.
First, I feel that Mr. Warnock's statement that "Presently, dip
netting for eulachon in lower West Creek is a recognized sports
fishing activity" is completely unfounded. I have always taken a
deep interest in these fish and their habits and I feel that Mr.
Bishop was quite generous in presuming that they spawn in West Creek
at all. At any rate. I have never known anyone to catch them there.
Second, I am surprised that Mr. Reed is concerned about moose habitat
in the West Creek and Taiya River drainages. Not only have I never
seen any evidence of moose downstream of the project area, but I
have also never heard of anyone else who has seen any evidence of
moose within this area. Surely, Fish & Game is aware of this. Third,
I have walked the cliffside several times in the project and reservoir
areas and have found no evidence of bear dens. I sincerely doubt that
any exist at the lower elevations. Fourth. regarding an archaeological
survey, I can say that on the surface at least, there is little or
nothing of historical significance. I have walked over virtually all
of the dam and reservoir areas and have found nothing more than two
huntipg campsites of relatively recent vintage. In fact, I have made
two special trips in search of artifacts dating from the three mining
claims staked on the c1iffsides in 1898 and have been unable to find
anything. At any rate, none of these claims would be affected by the
proposed hydro project. Of course, subsurface artifacts may exist,
but given the poor mineralization and the lack of game within t~e
West Creek valley, I sincerely doubt that anything could be found.
,
"
•
~~ay 20,1982
Mr. Brent Petrie
Page 2
I hope these comments prove helpful in your analysis of this project.
I sincerely hope that the project is developed rationally and with
minimal impacts and maximum regard to safety. However, I feel that
spending too much time studying wildlife and archaeological impacts
would be a costly, unfruitful endeavor.
Si~'UJIAf-
Skip Elliott
City ~~anager
cc: NPS
F&G
DNR
,-
MEMORANDUM
TO Eric Yould
Executive Director
Alaska Power Authority
Department of Commerce and
Economic Development
FROM: Bill Beardsley, Director
Division of Energy and ~!dd
Power Development uI!L/
Department of Commerce and
Economic Development
State of Alaska
DATE: May
FILE NO:
TELEPHONE NO:
SUBJECT: Comments on Haines-
Skagway Feasibility
Study Draft
Probably there are good answers for the following concerns
which I missed in my cursory review.
1. I am not convinced that a four square mile reservoir is
adequate to make up for inflow deficiency, during the five
months each year when discharge to penstocks (75 CFS)
exceeds enflow to reservoir.
2. Given wind assumption on page IV-9 of 22¢/kwh for wind
in 1982 vs. diesel at 10¢/kwh I would say wind beats the
pants off diesel in any present working analysis. Either
the report should not discount wind in so cavalier a fashion
or the assumptions had best be changed (would that I could
find a windmill that produced firm capacity and energy at
22¢/kwh in 1982).
3. In the wood scenario, forest residue is completely
ignored. Assuming ~ of all local vegetation (by weight) is
non commercial for species, mortality or other reasons, and
that only ~ of the biomass of commercial trees is removed,
the volume of forest residue to mill residue works out to a
ratio of perhaps 10 to 1. Other benefits not considered
were the jobs created by using a local fuel.
4. ~he report assumes that 90% of the Schnabel Mill
requirements will be met by the project (page V-3) while the
mills new 4000kw waste-fueled power plant will have excess
capacity of 65% in a capitalized plant with no significant
fuel costs (page IV-12). Something doesn't add up.
02-0011\1 Re •. ; 01791
,
..
,
Eric Yould
Page two
May 13, 1982
5. The diesel fuel cost escalator used -2.6% over inflation
seems high (VI-2).
6. It is unclear if load
communities have been taken
demand may be overstated.
diversity between
into account. If
the two
not peak
7. I am unclear why there is such a load jump
as set forth in Table III 12 and how is
generation treated (externalized or included?)
in 1982-1983
non utility
8. It is proposed that the facility will be on line in late
1986. Assuming FERC licensing, right-of-way acquisition,
tunnel and dam, this seem like a very optimistic time frame.
9. Since population has been declining up to 1980 I am
concerned about the assumption of compound annual growth
rates in the early 1980's. It shouldn't be to hard to find
out whether 1982 population is up from 6 to 9% over 1980 as
suggested in Table 111-2.
10. Given six months of spilling it should be mentioned
that additional low cost energy and some capacity would be
possible in the future at relatively low increment costs.
Comment: I intuitively believe hydro is feasible for
Haines-Skagway and I believe this report can confirm it. I
am, however, worried that unless the analysis is tightened
up and assumptions made a bit more conservative, the report
(as is) may do more harm than good .
1>
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
July 19, 1982
Mr. William Beardsley, Director
Division of Energy and Power Development
Department of Commerce and Economic Development
MacKay Building, 7th Floor
338 Denali Street
Anchorage, Alaska 99501
Dear Bi 11 :
Phone: (907) 277·7641
(907) 276·0001
Thank you for your May 13, 1982 comments on the Haines-Skagway
feas i bi 1 i ty study. We di d not recei ve any addi tiona 1 comment s from
your office and, therefore, we offer the following responses:
1. Reservoir size was carefully analyzed during feasibility
study. The reservoir contains an active storage of 18,130
acre-feet and a maximum surface area of 635 area
(approximately one square mile) which is sufficient to provide
four months of average discharge to the power plan with no
inflow. A four square mile reservoir, as you mentioned..,-n
your comments, would have 2,560 surface acres which means that
if the reservoir had vertical sides it would need be only 7
ft. deep to provide all the active storage needed for annual
regulation of the stream flow.
2. The 22~/kWh for wind power is not for firm capacity and
energy. It is for energy available when the wind blows and
back up would be needed. The system would still require
diesel generators which would need to operate at least 50% of
the time. Thus, the 22~/kWh would be replacing the fuel cost
of generating with diesel (10~/kWh). This is hardly
economi ca 1 and wou 1 d not become economi ca 1 unt il di ese 1 fuel
costs are greater than 22~/kWh. Based on our fuel escalation
assumption of 2.6% per year and real discount rate of 3% per
year, the crossover between the wind system and diesel does
not occur until about 14 years into the future.
3. For purposes of the economic analysis, the assumptions used in
the report are conservative; there is no cost associated with
fuel for wood waste. In order to use the forest residue, a
cost would have to be added for fuel to the wood waste
generator. Although, some of the logs processed at the mill
are hauled from state timber sales near Haines, other logs are
rafted from timber sales elsewhere in Southeast Alaska.
Mr. William Beardsley
July 19, 1982
Page 2
4. The report assumes that the wood waste generator at Schnabel
Mi 11 wi 11 meet 90% of the mi 111 s energy requi rements under all
generation plans. The hydro project would meet 10% of the
mill IS requirements. The 10% is to account for maintenance
time, unscheduled outages, or temporary fuel shortages.
5. We have recently gone through an extensive survey to develop
this yearls fuel escalation rate. Subsequent studies to be
completed in 1983 will use a 2.5% escalation rate which was
approved by the Alaska Power Authority Board.
6. Load diversity between the communities has been considered.
7a. The assumptions and methodology for developing the load
forecast are discussed in detail in Section III. The load
jump is a function of many factors which are explained in the
report.
7b. Non utility generation is included in the analysis.
8. The late 1986 on-line date was optimistic, but possible. The
project is now being postponed at least one year. Project
timing will be discussed in our findings and recommendations
which will be submitted after completion of the final report.
9. Annual estimates of population are prepared for individual
communities in cooperation with the Alaska Department of
Community and Regional Affairs. These estimates are used for
federal revenue shari ng purposes and are based on a Ju1 y 1
date. The communities have until the end of December to submit
their population estimates and the final figures are published
in January of the following year. Thus. 1982 figures will not
be available until next year. The July 1. 1981 estimated
populations are 1.712 for the Haines Borough and 819 for the
City of Skagway.
10. Credit for some additi ona1 energy was taken into account for
the years after 1995. Before 1995. all the projected load
would be met by the project and thus the surplus would have no
value. However, as noted in the comment. there would be
surplus power available.
Mr. William Beardsley
Jul y 19; 1982
Page 3
Thank you for your comments.
Si ncere ly,
s:--------
E ri c. P. You 1 d
Executive Director
02·0018IRev. 10/761
STATE I£M"1II1"l/ll of ALASKA
TO: r
FROM:
Brent Petrie
Project Manager
Alaska Power Authority
G~tf'
George Matz, Program Budget Analyst
Division of Budget and Management
Office of the Governor
DATE: May 13, 1982 BECEI.veQ
JUN 0 11982
AlASKA POWER AUTHORITY
Draft Feasibility Study
FilE NO:
TELEPHONE NO:
SUBJECT,
The purpose of this memo is to provide prel iminary comments on the draft
vers i on of the Haines -Skagway Regi on Feas i bi 1 i ty Study. Hopefully, these
comments will help assure that the final copy is in close compliance with
statutory and regulatory requirements. However, these comments do not substi-
tute for the review done by Budget and Management once it receives a final
copy with a letter of findings and recommendations.
The study accepts the Scena ri 0 B load forecast as bei ng the most 1 ike ly.
However, this scenario assumes some conditions which are not consistent with
recent trends. For instance, consumption per residential customer is assumed
to increase at 1.5% per year, after no increases for the next three years,
even though lithe average electricity usage per residential customer has been
decreasing over the past few years".
Also events which could noticeably increase energy demand are not treated in a
probabilistic manner even though their occurrence i~ far from certain. For
instance, Scenario B assumes that, by 1987, there will be 105 new jobs in
Haines and Skagway for construction of the ANGTS project and that a portion of
these new employees will continue to live in the area. By 1989, 40 new
employees are assumed for a barite mine near Haines. Accounting for indirect
employment and families, these two activities result in 570 new residents by
1989 which is a 26% increase over the 1980 population. It should be noted
that this 26% increase is nearly identical (but not directly comparable) to
the differential between the life cycle costs for the West Creek Plan ($92
million) and the Base Case Plan ($116.6 million). It appears as if the
economic feasibility of the West Creek Plan is very sensitive to population
projection assumptions and should be treated accordingly.
It is to the study's credit that electric space heating is addressed and
handled as a separate scenario. However, further explanation is needed
regarding the statement (p. III-l7) "This analysis assumes that an average of
3 kwh per degree day are required for each all-electric residential customer
based on 24,924 degree days for the Haines area" and a similar statement for
Skagway. Does 3 kwh per degree day represent some kind of predetermi ned
average? If so, how well does the condition of the Haines and Skagway housing
stock correlate with this data? What is the significance of 24,924 degree
days? If that refers to degree days, it is not correct.
..
Srent Petrie, Project Manager ,)
'-i'1ay 13, 1982
If substantial conversion to electric space heating is to be seriously consid-
ered, the study needs to include a more detailed account of price elasticity
and the benefit/costs of meeting thermal end-use by non-util ity sources of
energy as well as conservation strategies .
The feasibility study seems to underrate the viability of the existing elec-
trical generation system. It appears that the Dewey Lakes hydro project,
operated ~y Alaska Power and Telephone Co., actually generates more energy
than it is given credit for. Also, if there are serious questions about the
long term viability of the Schnabel Lumber Co. wood-waste generation system,
these question should also apply to the population and load forecasts.
Some alternatives, such as wind generation, were not considered because of
lack of data. It should be pointed out that the purpose of the feasibility
study is to proviae such aata. Although wind gen2ration is a questionable
source of electric generation at this time, it may, within several years, be
considered feasible from a utilities perspective. Since the justification of
the West Creek Project seems dependent on the development of future demand, it
is appropriate to compare t~est Creek to alternatives which are not yet
feasible but may be within several years.
The tables used for the economic analysis data are very gooa. Data is
presented in logical progressions and assumptions are clearly stated. The
only comments are 1) it is not clear why diesel operating and maintenance
costs decline for Table VI-l and 2) Table VI-3, assumption 4, states that the
plant is replaced in 200 (year presumably) which is apparently incomplete.
Considering the importance of the wood waste alternative and the substantial
cost -For plant replacement, a life cycle cost analysis at the time of
retirement of the present wood waste generation plant would be very useful.
In order to accurately represent costs, this analysis should discount costs
from the year in which the casts are incurred r~ther than discount amortized
costs. The advantage of the former methoa is appare:1t when a truncated
situation exists such as the wood waste alternative.
The timing exercise (Table VI-12). provides essential information for optimiz-
ing state investments. It would be useful to include some explanation as to
how this calculation was made and what assumptions were used. These costs
should include a real escalation for capital costs, although it is not clear
what the escalation factor should be.
In summary, the economic f2asibility of the West Creek Project and its timing
appear to be very sensitive to the assumptions used for the demand proJec-
tions. Although the basis for the oemand projections is very explicit and
detailed, additiunal emohasis should be given to sensitivity.
One again, these comments should be considered prelimin~ry. A formal review
of the feasioility study will be undertaken by Budget and Management when the
feasibility study is finalized and submitted with a letter of findings and
r2cornmendations.
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE -ANCHORAGE, ALASKA 99501
Mr. George Matz
Program Budget Analyst
Division of Budget and Management
Office of the Governor
G
Brent N. Petrie ~
Project Manager
Alaska Power Authority
Phone: (907) 277-7641
(907) 276-0001
July 14, 1982
Haines-Skagway Region
Feasibility Study
Thank you for your memorandum of May 13, 1982 commenting on the
draft report of the Haines-Skagway Region Feasibility Study. We are
aware that your comments are only preliminary and that a formal review
will be performed only after the final report is submitted with a letter
of findings and recommendations. However, we would like to respond to
your comments with the following:
1. All three forecast scenarios attempt to incorporate recent
historical trends in electricity consumption with likely future
conditions which may affect customer usage. The decrease in
residential electricity usage over the past few years has been
attributed to conservation in response to general economic
conditions, the availability of low-cost conservation programs, and
increasing electricity rates. As energy audits and other
conservation programs have already been implemented in both Haines
and Skagway and in view of the fact that there is virtually no
existing electric space heating in these communities, we felt that
it would be unrealistic to assume future dramatic decreases in
usage without major lifestyle changes or capital investments.
However, assuming the conservation efforts already undertaken would
continue, the consultants felt that holding electricity consumption
per customer constant for the next few years was reasonable.
Beyond the next few years, a decade of moderately increasing
residential electricity consumption was included in the forecast
(less than one/third of the rate of increase in the early 1970's).
This increase reflects a rise in the standard of living up to a
point of saturation of major electrical appliances.
2. The uncertainty associated with certain events was dealt with
by developing alternative forecast scenarios. As noted,
construction of the Alaska Natural Gas pipeline is still in
question and a delay to 1987 has been announced by project
sponsors. The consultants projected a 1987-1989 construction
period prior to the project sponsors. Scenario B includes manpower
estimates provided by local townspeople who have been contacted by
the project sponsors regarding impacts on the communities.
Assumptions were made concerning secondary ernployment and workers
remaining beyond construction of the project also based on these
Mr. George A. Matz
July 14, 1982
Page 2
local interviews. A local investor in the barite mine near Haines
was consulted regarding the development of that project and
provided us with current manpower and time schedule estimates.
However, in neither case was a IIprobabilistic" analysis of
occurrence made. This information was necessary to determine
project sizing in the event those loads actually occur. Other
projects considered more speculative such as an iron mine near
Klukwan and electrification of the railroad were not included in
any forecast.
Certainly population growth is an important "driver" behind
the forecast and economic feasibility of the project, which is why
an attempt to present a range of likely growth was made using three
scenarios. A sensitivity analysis of population growth would not
fully explain the effect which each growth scenario has on the
economic analysis, as a number of other assumptions accompany the
population growth rates within each scenario. For instance, in
Skagway under the Scenario B forecast, not only is there additional
population growth due to pipeline workers over that in Scenario A,
but there is also a 20% annual increase in the railroad's
electrical requirements for the duration of the pipeline
construction. Economic analyses were conducted for each growth
scenario and are shown in Section VI of the report. As the result
of information provided during review of the draft report, the West
Creek Project is the least cost alternative for Scenario B and is
almost identical to the riskier wood waste alternative in
Scenario A.
3. The figures "24,924" on page 111-17 of the Draft Report and
"24,711" on 1II-18 refer to kWh, not degree days. Those figures
have been corrected for the final report and read "8,308 11 for
Haines and "8,237" for Skagway. The "24,924" and "24,711" figures
were calculated by multiplying the average annual degree days, by 3
kWh, an average electricity usage rate which the consultants have
found to exist throughout the country in areas where electricity is
used for space heating. Although there are a number of factors
which could influence this average, it has been found to exist in
small towns as well as more metropolitan areas.
Substantial conversion to electricity for space heating is not
necessarily considered a likely result of this project. As pointed
out in the report, substantial conversion to electricity for space
heating, would occur only if cost of electricity were considered
less costly than alternative fuels. However, the impact of
significant conversion was shown in separate Scenario C, in order
to complete a range of growth alternatives for these communities.
A separate (outside of the report) analysis of the cost of power of
West Creek and several energy alternatives was conducted and will
be discussed in the Authority's Findings and Recommendations.
Mr. George A. Matz
July 14, 1982
Page 3
4. The draft report did under-rate the Dewey Lakes hydro project
due to a lack of current information. At the public meetings in
Skagway we were told that the expanded system generated 2915 MWh in
1981, its first year of operation. The 1500 MWh used in the report
was the long term average of the old system which had an installed
capacity of 335 kW instead of the 780 kW in the expanded system.
Since there is no long term average for the new system, the 1981
generation will be used and the economic analysis modified.
However, we should point out that 1981 is an atypical year in that
the new units came on line in June and thus generated through only
a part of the runoff season, but that 1981 was a wet year. Thus,
although 1981 might serve as a reasonable representation of average
generations, the generation in succeeding years needs to be
included in the average as soon as possible.
As mentioned in the report, there are serious questions as to
the long term viability of the wood waste generator in Haines which
were dealt with in the feasibility study by performing a
sensitivity analysis. The question of long term viability of the
wood waste generator does not necessarily mean that the population
and load forecasts are affected. There could be less energy
available from woodwaste because the mill is using more energy or
because there is a better market for the woodwaste. In both cases
the employment at the mill could be unaffected.
5. The criticism that the study did not consider wind generation
is unfounded. Wind generation is discussed in some detail on
pages IV-6 through IV-10. This discussion contains the best cost
information we are able to obtain at this time and shows that wind
generation is now about twice as expensive as the cost of diesel
fuel for generation. For us to speculate that wind generation will
be the most economical alternative in a few years and that Haines
and Skagway should depend on it as its primary source of power is
not responsible engineering, but simply a statement of faith in the
feasibility of wind power. Wind generation, especially large scale
wind generation is still in the experimental stage with many
uncertainties. The comparisons included in the report are based on
currently available technologies and their costs in today's market.
If we were to assume that wind generation will experience an
economic or technological breakthrough in the next few years which
will lower its cost, we could with equal validity hypothesize
similar breakthroughs for the other alternatives which lower their
costs. This sort of speculation will not provide a meaningful
planning tool and thus should be avoided.
A second point which must be kept in mind when discussing wind
power is that it is not a firm power source. It operates only when
the wind blows. To date, it has been largely for a fuel
replacement. In order to make it a firm power source, the entire
Mr. George A. Matz
July 14, 1982
Page 4
system must include either backup generation or an energy storage
system. Thus, in order to make a valid comparison of wind
generation vs. the other generation plans, we would have to include
the wind generators and the backup system as a combination. As a
displacement for diesel fuel a wind system cost of 22¢/Kwh is
compared to lO¢/Kwh for fuel. Inclusion of backup reserve for firm
• energy would increase the 22¢/Kwh figure. Skagway has a wind
system installed under a state grant and although it has already
failed on one occasion, the economic analysis assumes that 25% of
the City of Skagway1s sewage treatment facility consumption will be
served by that wind system.
6. The decline in the diesel operation and maintenance costs
after 1987 in Table VI-2 is due to the mothballing of about half
the existing diesel generation units once the West Creek Project
comes on-line. This can be done because the West Creek will
provide firm power and will require only emergency backup until
1997 when the load requirements of the two communities are
forecasted to exceed the capacity of the Project.
7. The analysis of each alternative was performed as required in
the APAls regulations. The period of analysis extends through the
assumed economic life of the West Creek Hydroelectric Project which
has the longest life. We are confident that the study is a valid
representation of the costs of each alternative and see no reason
to perform other analyses, which if done correctly, will give the
same results.
8. The timing exercise in Table VI-12 was performed by computing
the total present worth for the West Creek Plan in the same way as
shown on Tables VI-2, VI-6 and VI-9, but with the on-line date
changed to 1989, 1991, 1993 and 1995. The analysis assumed that
the existing system of diesel and hydro generation would continue
to meet the electric needs until the West Creek Project came
on-line. In comparing the total present worth costs of dates it
should be noted that the difference in cost between the highest and
lowest costs is less than 2%. This is much less than the
accuracies of the assumptions which went into the calculations.
Thus, one should be careful about drawing too many conclusions from
the table. Also, the analysis does not include escalation of
capital costs. Including a real escalation of capital costs will
change the results and make it difficult to compare them with the
results of the economic analyses performed for the base case and
wood waste alternatives. The Power Authority will discuss the
timing of this project further in its Findings and Recommendations.
PART D: SUMMARY OF GENERATION ALTERNATIVES
SUMMARY OF GENERATION ALTERNATIVES
DIESEL GENERATION FACILITIES
I. CAPITAL COSTS
A. Generation
1. Assumptions
a. Economic Life of Diesel Generators: 20 years
b. Installation Costs: $800/kW
c. Base Year of Estimates: 1982
2. Capacity Additions and Cost Data
a. Year of Additions: 1998
b. Additional Capacity: 600 kW
c. Total Capacity: 8,110 kW
d. Capital Cost: $480,000 (total not annual)
B. Transmission and Substations
1. Assumptions
a. No transmission line or facilities needed.
2. Facility Additions and Cost Data
a. No additional facilities anticipated.
II. OPERATION AND MAINTENANCE COST
A. Generation
1. Assumptions
a. Base Year for Estimates: 1982
b. Fixed Costs: $120/kW
c. Variable Costs: (not part of analysis)
2. Cost Data
SCENARIO B:
(a) (b) (c) (d)
Year Fixed Costs Variable Costs Total Costs
($000) ($000) ($000)
1982 901 901
1987 821 821
1992 798 798
1997 771 771
2001 819 819
Page 2
SCENARIO A:
(a) (b) (c) (d)
Year Fixed Costs Variable Costs Total Costs
($000) ($000) ($000)
1982 901 901
1981 821 821
1992 198 198
1991 111 111
2001 151 151
B. Transmission and SUbstation
1. Assumptions
a. No transmission or substation facilities.
2. Cost Data
a. No transmission or substation facilities.
III. FUEL COSTS
A. Assumptions
1 • Base Year for Estimates: 1982
2. Base Price for Fuel Oil: $1.16/gal.
3. Fuel Escalation Rate: $2.6%/yr.
4. Efficiency: 12 kWh/gal.
B. Annual Cost Data
SCENARIO B:
(1) (2 ) (3) (4) (5)
Diesel Net Fuel Oil Price of
Year Generation Used Fuel Oil Fuel Cost
(MWh) (1,000 gal) ($/gal) ($000)
1982 11,158 980 1.16 1, 131
1981 15,815 1,321 1.32 1,145
1992 19,088 1,590 1.50 2,385
1991 22,982 1,920 1.10 3,265
2001 26,381 2,141 1.94 4,153
Page 3
SCENARIO A:
(1) (2 ) (3) (4) (5)
Diesel Net Fuel Oil Price of
Year Generation Used Fuel Oil Fuel Cost
(MWh) (1,000 gal) ($/gal) ($000)
1982 11,610 967 1.16 1,122
1987 13,304 1,108 1.32 1,462
1992 15,109 1,259 1.50 1,888
1997 16,993 1,420 1. 70 2,414
2001 18,435 1,496 1.94 2,902
HYDROELECTRIC PROJECT
I. CAPITAL COSTS
A. Generation
1. Assumptions
a. Economic Life of Project: 50 years
b. Construction Startup Date: 1984 (summer)
c. Construction Completion Date: 1986
d. Interest During Construction: 3%/year
e. Base Year for Estimates: 1982
2. Capacity Additions
a. No additions anticipated in the form of hydroelectric
power.
3. Construction Costs
a. Investment Cost (Construction Cost Plus Interest During
Construction) Discounted to Base Year: $55,908,000
4. Other Generation Components
a. In addition to the hydroelectric project, other genera-
tion components may be needed to meet demand or reserve
requirements. These are not components in the form of
hydroelectric power, and therefore are not listed here.
B. Transmission and Substations
1. Assumptions
a. 22.8 miles of transmission line categorized as follows:
Description
Buried Transmission Line, 34.5 kV
Overhead Transmission Line, 34.5 kV
Submarine Transmission Cable
Component
Length
(Miles)
1.2
5.0
16.6
b. Three Substations and costs as follows:
Description
Haines Terminal
Switching Stations .
Skagway SUbstation .
Lump Sum Cost
$231,000
231,000
147,000
c. Base Year for Estimates: 1982
2. Facility Additions and Cost Data
a. No facility additions are anticipated.
Cost/Mile
($000)
407
203
648.07
II. OPERATION AND MAINTENANCE COSTS
A. Generation
1. Assumptions
a. Base Year for Estimates: 1982
b. Fixed Costs: $120/kW
c. Variable Costs: (not part of analysis)
2. Annual Cost Data:
SCENARIO B:
(a) (b)
Year Fixed Costs
($000)
1982
1987
1992
1997
2001
o
727
727
727
727
SCENARIO A:
( a)
Year
1982
1987
1992
1997
2001
(b)
Fixed Costs
($000)
o
727
727
727
727
(c)
Variable Costs
($000)
(c)
Variable Costs
($000)
(d)
Total Costs
($000)
o
727
727
727
727
(d)
Total Costs
($000)
o
727
727
727
727
Page 2
3. O&M costs for other generation components not anticipated.
B. Transmission and Substation
1. Assumptions (O&M on Transmission and SUbstation not included
with hydro project cost listed above.)
III. FUEL COSTS
A. Assumptions
1. A hydroelectric project may need supplemental generation to
meet peak and/or energy demand. If the supplemental genera-
tion component uses fuel, fuel costs for the following are to
be included:
a. Fuel consumption needed to meet the difference between
annual energy demand and average annual energy gener-
ated from the hydroelectric project:
•
b.
Page 3
SCENARIO B:
Diesel Fuel Consumption to
Year Meet Supplemental Generation
(1,000 gal)
1982 980
1981 0
1992 0
1991 0
2001 89
SCENARIO A:
Diesel Fuel Consumption to
Year Meet Supplemental Generation
(1,000 gal)
1982 961
1981 0
1992 0
1991 0
2001 0
Fuel consumption needed to meet the difference between
seasonal energy demand and seasonal variations in the
capacity of the hydroelectric project excluding differ-
ences described in (a): None •
B. Annual Cost Data
1. See A.1(a)
IV. RESERVE CAPACITY
NOTE: Reserve capacity is in the form of existing diesel unit generation
(as shown in Table VI-3 of the report) which presently serves both Haines
~d~~wy.
I. CAPITAL COSTS
A. Generation
1. Assumptions
WOODWASTE GENERATOR
(CASE A)
a. Economic Life of Project: 20 years
b. Construction Startup Date: 1982
c. Construction Completion Date: 1983
d. Interest During Construction: Not Available
e. Base Year for Estimate: 1982
2. Construction Costs
a. Investment Cost: $4,300,000 (1982 dollars)
3. Additional Capacity
a. Year of Additions: 2002
b. Capacity Addition to Replace Existing: 4,000 kW
c. Capital Cost: $12,500,000
4. Other Generation Components
a. See IV.
B. Transmission and Substation
1. Assumptions
a. Existing transmission facilities would be utilized.
2. Facility Additions and Cost Data
a. Existing transmission facilities would be utilized, no
additional facilities anticipated.
II. OPERATION AND MAINTENANCE COSTS
A. Generation
1. Assumptions
a. Base Year for Estimates: 1982
b. Fixed Costs: $67.75/kW per year
c. Variable Costs: (not part of analysis)
Page 2
2. Annual Cost Data
SCENARIO B:
(a) (b) (c) (d)
Year Fixed Costs Variable Costs Total Costs
($000 ) ($000) ($000)
1982 0 0
1987 289 289
1992 289 289
1997 289 289
2002 289 289
SCENARIO A:
(a) (b) (c) (d)
Year Fixed Costs Variable Costs Total Costs
($000) ($000 ) ($000)
1982 0 0
1987 289 289
1992 289 289
1997 289 289
2002 289 289
3 • O&M Costs for other generation components:
•
SCENARIO B:
(a) (b) (c) (d)
Year Fixed Costs Variable Costs Total Costs • ($000 ) ($000) ($000)
1982 901 901
1987 901 901
1992 901 901
1997 901 901
2002 937 937
SCENARIO A:
( a) (b) (c) (d)
Year Fixed Costs Variable Costs Total Costs
($000) ($000) ($000)
.' 1982 901 901
1987 901 901
1992 901 901
1997 901 901
2002 901 901
Page 3
III. FUEL COSTS
A. Assumptions
1. Wood waste can be considered an economical fuel for meeting
Haines' requirements for the five-year period of agreement
between Schnabel and HLP. After that time the plant cannot
be considered a firm resource beyond that point. As for
prices, availability, and escalation, there are questions as
to future costs for the community.
B. Same as "A".
C. Supplemental Costs
1. Supplemental generation fuel costs would be for diesel gener-
ation:
SCENARIO B:
(a) (b) (c) (d)
Year Fixed Costs Variable Costs Total Costs
($000) ($000) ($000)
1982 1 ,137 1 ,137
1987 880 880
1992 1,088 1,088
1997 1,550 1,550
2002 2,023 2,023
SCENARIO A:
(a) (b) (c) (d)
Year Fixed Costs Variable Costs Total Costs
($000) ($000) ($000)
1982 1,122 1,122
1987 678 678
1992 890 890
1997 1,150 1,150
2002 1,396 1,396
IV. RESERVE CAPACITY
A. Assumptions
1. To assure firm power reserve capacity will be in the form of
diesel generation as shown previously in I, II and III for
this alternative.
B. Annual Cost Data
1. See Sections I, II and III.
,
WASTE HEAT FACILITIES
I. UTILIZATION
A. Demand
For purposes of this study, it was assumed that 100% of the poten-
tial waste heat could be used. The potential customers in Haines
include two hotels and other small businesses in the vicinity of
the generating plant.
B. Thermal Availability
1. Not Studied
II. CAPITAL COSTS
A. Base Year of Cost Estimate: 1982
B. Capital Costs
1. NOTE: For Haines only, Scenario B, approximately $90,000 of
heating oil could be displaced annually at 1982 price
levels. The cost of installing such a recovery system can
only be estimated at this time based on a similar installa-
tion and is assumed to be $600,000.
III. OPERATION AND MAINTENANCE COSTS
A. No studies have been done pertaining to O&M.
IV. FUEL AND COST SAVINGS
A. No studies have been done on this subject other than as mentioned
in Part II, Capital Costs.
i
•
HAINES -Diesel Generators
EXISTING FACILITIES
(SCENARIO B)
HLP - 7 units with total capacity of 4,320 kW:
(1)
(1)
(1)
(4 )
2,070-kW machine
800-kW machine
600-kW machine
Others ranging in
or early 1950's.
1973 installation
Late 1960's
Late 1960's
size from 150 kW to 300 kW date from the 1940's
SKAGWAY -Combination of hydroelectric turbine-generators and diesel genera-
tors owned and operated by AP&Tj total capacity is 4,130 kW:
(3) Pelton turbines with 100-kW, 410-kW and 270-kW installed capacity
(reconditioned in 1981)
(5) Diesel units which supplement existing hydropower:
(3) 1,250-kW units installed in the late 1970's
(3) Older units ranging from 250 kW to 300 kW