HomeMy WebLinkAboutBristol Bay Regional Power Plan Interim Feasibility Assessment Executive Summary 1982BRISTOL BAY
REGIONAL POWER PLAN
DETAILED FEASIBILITY ANALYSIS
INTERIM FEASIBILITY
ASSESSMENT
EXECUTIVE SU MMARY
Bristol Bay
JULY 1982
& Stone & Webster Engineering Corporation
ALASKA PC'WER AU'I'HC'RI'l'l' 1.---__ --'
STONE S WEBSTER ENGINEERING CORPORATION
DENVER OPERATIONS CENTER
GREENWOOD PLAZA. DENVER. COLORADO A AOORESS AL.L. CORRESPONOENCE TO P.O. BOX '406. OENVER. COL.ORAOO 80217
eOSTON
NEW YORK
CHERRY HILL, N.J.
DENVER
CHICAGO
HOUSTON
PORTLAND. OREGON
SAN OI£GO
WASHINGTON. D.C
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
334 West 5th Avenue
Anchorage, Alaska 99501
At tn: Mr. Donald W. Baxter
Project Manager
Dear Mr. Baxter:
INTERIM FEASIBILITY ASSESSMENT
BRISTOL BAY REGIONAL POWER PLAN
TEL.EPHONE: 303-7'0-7100
W.U. TELE.IC:45-4.01
July 31, 1982
Submitted herewith is our Interim Feasibility Assessment for the Bristol
Bay Regional Power Plan Detailed Feasibility Analysis. This 4-volume
report summarizes our work to date under Phase I of the study.
A 3-volume draft Interim Feasibility Assessment report was issued for
review and comment in March 1982. Several revisions have been made to the
draft report as a result of your review. Also, the following important
additions are included:
a) Summaries of the geotechnical and fisheries studies at the
Newhalen site.
b) A new scenario covering local and subregional power developments.
c) Comments by agencies on the draft report and responses by the
Power Authority.
d) A suggested Scope of Work for Phase II.
The underlying conclusion of the Interim Feasibility Assessment is that
there are a number of economically attractive alternatives to continuation
of the present practice of reliance on diesel systems for electrical power
generation in the Bristol Bay region. Two of these alternatives, a
regional run-of-river Newhalen River hydroelectric development and a
scenario consisting of several subregional developments, are recommended
for further study. The subregional alternative is a cost effective mix of
disconnected power supply components which consists of a small run-of-river
hydroelectriC development on the Tazimina River along with wind systems,
waste heat recovery systems and continued diesel generation in various
other subregions.
Mr. Eric P. Yould
July 31, 1982
Page 2
Our principal findings and conclusions are set forth in the Executive
Summary of the report. Details of the energy demand forecasts, alternative
evaluations, site investigations, engineering studies, economic
evaluations, and environmental studies which support the conclusions are
described in detail in subsequent sections of the report and in the
Appendices.
It has been a pleasure working with the Alaska Power Authority on this
challenging study, and we look forward to continuing the effort in Phase II.
DLM/cms
Enclosures
Very truly yours,
D. L. Matchett
Project Manager
ACKNOWLEDGEMENTS
Stone & Webster Engineering Corporation and its subcontractors wish to
acknowledge the important assistance given by many individuals and
organizations to the project team in undertaking the Interim Feasibility
Assessment. Chapter 8 of this report documents many of the contacts made
with the people of Bristol Bay and with state and federal agencies
concerned with energy development. Without the information and support
received from these sources. satisfactory completion of Phase I of the
Bristol Bay Regional Power Plan Study would have been much more difficult.
if not impossible.
Special acknowledgement is given to the following individuals for their
help:
Ted Angasan. Tom Hawkins. William Johnson, and Kay Larsen. Bristol Bay
Native Association
Representative Joe Chuckwuk and his aide, Paula Scavera
David F. Bouker, Nushagak Electric Cooperative
Gordon McCormick, Naknek Electric Association
Trig Olsen and John Adcox, Iliamna-Newhalen Electric Cooperative
Tom Arminski, Dick Russell. and Tina Cunning, State of Alaska. Department
of Fish and Game
Ann Rappaport, U.S. Fish and Wildlife Service
Rick Austin, State of Alaska, Department of Natural Resources
Jim Clark and Don Penner, Bristol Bay Borough
Paul Haertel and Mike Tollefson, Lake Clark National Park and Preserve
Don Anderson, JEVAD, Inc.
The above list is far from complete. While it is not possible to recognize
each participant individually, we wish to thank all those who attended the
public meetings in the villages and the agency meetings in Anchorage. The
questions, comments, and suggestions which resulted from these meetings
were a great benefit to the study.
CERTIFICATIONS
BRISTOL BAY REGIONAL POWER PLAN
DETAILED FEASIBILITY ANALYSIS
INTERIM FEASIBILITY ASSESSMENT
The technical material and data contained in this report and its Appendices
were prepared under the supe~vision of the following individuals and
organizations:
Volume 1 -Report
Appendix A -Engineering/Technical
Considerations
Appendix B -Energy Supply Technolog~
Evaluation
Appendix C -Energy De~and Forecast
Appendix D -Wind Energy Analysis
Apoendix E -Geotechnical Studies -
Tazimina
Appendix F -Geotechnical Studies -
Newhalen
Appendix G -Environmental Report
Appendix H -Newhalen Smolt and
Fry Studies
Appendix I -Hydrologic Evaluations
Theodore Critikos
Project Engineer
Stone & Webster Engineering Corp.
O. Scott Goldsmith
Principal Investigator
Institute of Social and Economic
Research
University of Alaska
Mark A. Newell
President
Wind Systems Engineering, Inc.
Rohn D. Abbott
Vice President
Shannon & Wilson, Inc.
James E. Hemming
Project Manager
Dames & Moore
Manager, Alaska Operations
Anand Prakash
Chief Water Resources Engineer
Dames & Moore
This study was prepared under the supervision and direction of the
undersigned whose seal as professional engineer is affixed below.
Donald L. Matchett
Project Manager
Stone & Webster Engineering Corp.
1.
1.1
1.2
1.3
1.4
1.5
1. 5.1
1.5.2
1.5.3
1.6
1. 6.1
1. 6. 2
1. 6.3
1.7
1. 7.1
1. 7.2
1. 7.3
1.8
1. 8.1
1. 8.2
TABLE OF CONTENTS
EXECu"TlVE SUMMARY
INTRODUCTION
BRISTOL BAY REGIONAL POw~R PL&~
ENERGY DEMA~1)
ENERGY SUPPLY TECHNOLOGY EVALUATION
DEVELOPMENT OF ENERGY PLANS
Data Collection
Energy Production Concepts
Selected Energy Scenarios
EVALUATION OF SELECTED E~~RGY PLANS
Technical
Environmental
Economic
REGULATORY COORDINATION &~D PUBLIC PARTICIPATION
Agency Communication
Regulatory Requirements
Public Participation
CONCLUSIONS &~ RECOMME~1)ATIONS
Conclusions
Recommendations
i
PAGE
1-1
1-1
1-2
1-4
1-5
1-6
1-6
1-12
1-15
1-20
1-20
1-21
1-26
1-29
1-29
1-30
1-30
1-31
1-31
1-35
GENERAL OUTLINE
BRISTOL BAY REGIONAL POWER PLAN
DETAILED FEASIBILITY ANALYSIS
INTERIM FEASIBILITY ASSESSMENT
VOLUME 1 -REPORT
VOLUME 2 -APPENDICES
VOLUME 3 -
VOLUME 4 -
APPENDIX A -ENGINEERING/TECHNICAL CONSIDERATIONS
A. 1 ENERGY NEEDS
A.2 HYDROELECTRIC POWER PROJECTS
A.3 DIESEL POWER
A.4 WASTE HEAT RECOVERY
A.5 ENERGY CONSERVATION
A.6 WIND ENERGY
A.7 POWER TRANSMISSION
A.8 FOSSIL-FUEL ALTERNATIVES
A.9 ORGANIC RANKINE CYCLE
A.10 LOAD MANAGEMENT ANALYSIS
APPENDIX B -ENERGY SUPPLY TECHNOLOGY EVALUATION
APPENDIX C -ENERGY DEMAND FORCAST
APPENDICES
APPENDIX D -WIND ENERGY ANALYSIS
APPENDIX E -GEOTECHNICAL STUDIES -TAZIHINA RIVER
APPENDIX F -GEOTECHNICAL STUDY -NEWHALEN RIVER
APPENDICES
APPENDIX G -ENVIRONMENTAL REPORT
APPENDIX H -NEWHALEN SMOLT AND FRY STUDIES
APPENDIX I -HYDROLOGIC EVALUATIONS -TAZIHINA RIVER
Bristol Bay Regional Power Plan
Detailed Feasibility Analysis
INTERIM FEASIBILITY ASSESSMENT
EXECUTIVE SUMMARY
Prepared for
ALASKA POWER AUTHORITY
July 1982
STONE & WEBSTER ENGINEERING CORPORATION
DENVER, COLORADO
1. EXECUTIVE SUMMARY
This Executive Summary is intended to provide a concise review of the work
performed to date by Stone & Webster Engineering Corporation and its
subcontractors during Phase I of the Bristol Bay Regional Power Plan
study. This phase of the study concludes with a milestone called the
Interim Feasibility Assessment. The Executive Summary highlights the work
accomplished in reaching this milestone and presents major results and
conclusions. The report and its appendices which follow should be
consulted for the detailed analysis which provides the basis for the
summary.
1.1 INTRODUCTION
Electric power cost and availability have been identified by the residents
of the Bristol Bay region as important concerns. Fuel oil is currently the
primary energy source in the Bristol Bay region, both for electrical
generation and space heating. The cost of energy production is currently
high and has increased rapidly in recent years, due not only to the
world-wide price escalation of fuel oil, but also to regional factors. The
cost of electrical energy production in remote villages primarily served by
small, non-central diesel electric generators is many times that of larger,
more efficient interconnected central systems in larger population centers
of Alaska and in other parts of the United States.
In recent years the state of Alaska has taken a number of steps to address
the energy problems in remote regions of the state. Direct subsidies are
in effect which substantially reduce the cost of electricity to consumers
in certain villages. In addition, the state has undertaken studies to
evaluate potential sources of electrical energy production other than by
diesel generators. Hydroelectric power generation, a renewable energy
source, has been identified as a source which in the future may provide
reliable low cost electricity for the Bristol Bay region; wind energy is
another renewable energy source which may have application.
1-1
In 1980, a "Reconnaissance Study" by R. W. Retherford Associates for the
Alaska Power Authority, evaluated the feasibility of potential
hydroelectric developments in the Bristol Bay region. Projects were
identified which were considered attractive for limited areas. The
Retherford study also evaluated a hydro site on the Tazimina River about
ten miles north of Iliamna Lake and east of Nondalton Village which was
believed suitable for supplying regional needs through the year 2000.
Retherford stated that "development of the Tazimina potential will result
in the lowest power cost for all communities in an integrated, combined
system."
1.2 BRISTOL BAY REGIONAL PO\vER PLAN
Based on the Retherford recommendation, the Alaska Power Authority retained
Stone & Webster Engineering Corporation (SWEC) in July 1981 to undertake a
study called the "Bristol Bay Regional Power Plan and Detailed Feasibility
Analysis". The purpose of this study is to assess the technical, economic,
and environmental aspects of alternative electric power generation plans
for the Bristol Bay region. A specific obj ective of the study is to
evaluate in detail the feasibility of the Tazimina Hydroelectric Project
and to compare it with the current practices of diesel generation and other
promising alternatives.
The Regional Power Plan addresses the needs of an 18-village study area
within the region. The boundaries of the study area are the previously
determined economic limits of the Tazimina Project market area. The
villages included in the study area are Aleknagik, Clarks Point,
Dillingham, Egegik, Ekuk, Ekwok, Igiugig, Iliamna, King Salmon, Levelock,
Manokotak, Naknek, Newhalen, New Stuyahok, Nondalton, Portage Creek, and
South Naknek. Figure 1.2-1 shows the Bristol Bay study region.
The Work Plan for the study divides the work into
called the IrInterim Feasibility Assessment lr
, and
two .phas es . 'Phas e I,
the subject of this
report, identifies numerous alternatives for energy production and compares
them with respect to technical feasibility, environmental impact, and cost.
1-2
Based on the outcome of Phase I, the Work Plan calls for the continuation
of the Study with Phase I I, when the most promis ing alternatives will be
evaluated and compared in more detail and a recommendation made regarding
project development.
The central focus of Phase I of the Regional Power Plan is a thorough
evaluation and comparison of the major energy options which are available
for the Bristol Bay region. The following three hypothetical power plan
cases were used as the framework for comparing various options:
o Base Case, which represents the continuation of present practices
of reliance on oil-fired (diesel) generation;
o Alternative "A", which consists of the Tazimina River
Hydroelectric Project as the required power supply;
o Alternative "B", which consists of other energy sources, projects,
or facilities, either alone or in combination.
The primary purpose of the Phase I Report is to present information to the
Power Authority and the people of the Bristol Bay region so that decisions
can be made regarding the next step. The conclusions and recommendations
which follow have taken into account a large body of information obtained
from the residents of Bristol Bay and from State and Federal agencies
interested in natural resource development and protection of the
environment. However, the Phase I work should be viewed as a first step in
the decision-making process. The emphasis is on engineering,
environmental, and economic considerations, with the objective of screening
out concepts which are impractical from these standpoints. A further
evaluation of the most promising energy production scenarios, including
more detailed environmental investigations, and a second level of
engineering and economic comparisons between promising alternatives and the
Base Plan, is planned for Phase II.
1-3
1 . 3 ENERGY DE HAND
Levels of current energy use and predictions of future needs in the Bristol
Bay study region are being evaluated by the Institute of Social and
Economic Research (ISER) of the University of Alaska. An interim report on
future energy demand prepared by ISER is attached as c. The
demand forecast contained in this report has be~n used to size and schedule
the new electrical energy supply systems developed and evaluated during the
Interim Feasibility Assessment.
The forecast provided by ISER is based on the "Base Plan" electrical supply
scenario, which is a continuation of the present practice of reliance on
diesel generation . Although the requirements for other energy needs such
as space heating were predicted, it was assumed that conversion from oil to
electricity would not occur at this time under the Base Plan scenario
because of a lack of economic incentive.
ISER concludes that based on the present price of fuel, conversion to
electrical space heating would not be significant unless the cost to the
consumer approached $. OS/kWh in 1982 dollars. Such low electricity costs
are unlikely for the scale of development needed for the Bristol Bay
region. However, conversion could be attractive at much higher energy
costs as the price of fuel oil rises in response to dwindling world
supplies.
The growth of electrical energy demand over the study period (1982 to 2002)
used in developing the alternative power plans falls between the "high" and
"low" demand scenarios predicted by Retherford, approaching the "low"
scenario. This is due probably to an assumption by Retherford of some
conversion from oil to electricity for space heating, resulting from a low
cost hydroelectric system. The current assumption of no conversion should
be conservative with respect to projected growth in regional energy usage;
this assumption is also believed to be suitable for the first level
comparison of a number of competing energy supply systems. The following
tabulation shows energy and demand values used for power plan
development. The methodology for developing these values, using the ISER
forecast, is explained in Appendix A.l.
1-4
Annual Energy Peak
Year Reguirements (H\.,!h/yr) Demand (MW)
1982 32,400 7.9
1987 38,700 8.9
1992 47,600 11.2
1997 58,900 12.2
2002 74,500 15.0
ISER has completed its examination of the relationship between the cost of
electrical energy to the consumer and energy use. Sensitivity studies have
been made to further quantify the economics of conversion to electrical
energy for space and water heating. It is planned to address this subject
in more detail during further evaluation of the most attractive
alternative(s) in Phase II.
1.4 P;'ERGY STv'?P~Y TECH:mLOGY EVALUATION
An energy supply technology evaluation was undertaken to review and
evaluate proven and commercially available energy technologies and to
select technologies appropriate for use as elements of alternative power
plans. Twenty-five potential energy supply technologies were evaluated.
The evaluation considered a number of factors related to application in the
Bristol Bay study region. Factors considered for each technology were
commercial availability; technical and regional restraints; environmental
and regulatory considerations; and construction, operation, and maintenance.
The 2S technologies were grouped into the following six basic categories:
o Fossil fuels
o Renewable resources
o Nuclear
o Advanced technologies
o Non-generating alternatives
o Hiscellaneous resources
1-5
Promising candidates
Advanced technologies.
and regulatory reasons.
were found in each category except Nuclear and
Nuclear was ruled out for a variety of technical
All candidates in the Advanced technologies
category (some of which were renewable resources) were either commercially
unavailable or not technically viable for the remote Bristol Bay region.
Nine energy supply technologies were found to be attractive for appJication
in the Bristol Bay region. The selected systems were:
Primary Sources
o Diesel electric
o Coal gasification (combined cycle)
o Coal-, oil-, and natural
gas-fired steam
electric generation
o Combined cycle (oil)
o Hydroelectric
Supplementary Sources
o Wind
o Energy conservation
o Waste heat recovery
o Organic Rankine Cycle
The nine candidates receiving the "attractive" designation were used as
elements of specific power plan systems for Bristol Bay.
1.5 DEVELOPMENT OF ENERGY PLANS
1.5.1 Data Collection
The objective of the data collection program as defined by the Work Plan is
to collect and compile all technical, environmental, and sociocultural
data necessary to assess project feasibility and to meet any licensing or
permitting requirements of FERC and other federal, state, and local
regulatory agencies. Phase I accomplished this obj ective with respect to
data required to compare various alternatives. In addition, a much larger
data base was collected as the first step in determining the feasibility of
the regional Tazimina and Newhalen projects.
be required in Phase II to fully satisfy
project(s) finally proposed for development.
1-6
However, additional data will
licensing requirements of the
The data collection program was divided into the following subtasks:
o Geotechnical
o Hydrologic
o Environmental and Sociocultural
1.5.1.1 Geotechnical
The geotechnical data collection program analyzed the Bristol Bay regional
geologic setting, investigated in considerable detail geotechnical
conditions at various sites previously proposed for major features of the
regional Tazimina and Newhalcn hydroelectric developments, and collected
geotechnical data for other sites considered as promising hydroelectric
alternatives. These latter sites were near Kukaklek Lake, on the Newhalen
River (local project), Kontrashibuna on the Tanalian River, and the
Chikuminuk Lake site. Information gathered on these sites was limited to
literature searches, supplemented in some cases by helicopter overflights
and ground visits.
The detailed geotechnical investigations at the Tazimina and Newhalen sites
were undertaken by Shannon & Wilson, Inc., and are fully reported in
Appendices E and F, respectively, to this report.
The Tazimina field studies were undertaken in the summer and fall of 1981
as part of the original plan to investigate that site because of the
favorable Retherford recommendation. The Newhalen field studies were
undertaken in the spring of 1982 in response to preliminary findings by
Stone & Webster Engineering Corporation that the technical feasibility and
economics of a hydroelectric development on the Newhalen River might be
more favorable than Tazimina. Detailed geotechnical field studies were
required to test the assumptions upon which the preliminary des ign of the
proposed Newhalen canal diversion concept was based.
The Tazimina
valley, six
investigations
seismic lines
included geologic mapping along the river
across the valley at possible locations for
structures, four borings to obtain profiles of soil and rock materials,
1-7
hand dug test pits, and laboratory tests.
the previously proposed dam site at the
A seismic survey and a boring at
out let of Lower Tazimina Lake
indicated depths of up to 180 feet of highly pervious sand and gravel over
bedrock. An impervious cutoff about 1.2 miles long would be required in
this material to provide an effective storage dam. Because of the
difficulty and cost of constructing such a cutoff, this location is not
recommended for further consideration. In addition, seismic surveys and a
boring at the previous ly identified Roadhouse Dam Site indicated pervious
outwash material and bedrock sloping downward into the right abutment. It
would be extremely expensive, or perhaps impossible, to provide a
water-tight storage reservoir at this location. Because of the
disappointing results of the investigation at the above sites, a further
search was initiated for a suitable location for a dam and reservoir. A
location about four miles downstream of the outlet of Lower Tazimina Lake
was found which appears to offer the best prospects for a regulating dam
site .. At this location, bedrock outcrops appear in both abutment areas and
seismic refraction surveying has defined the continuous bedrock surface
beneath the valley. HOI"ever, overburden is up to 170 feet thick, and
requires a positive cutoff to rock to ensure dam stability and eliminate
excessive seepage losses. Suitable locations were identified for a forebay
dam, penstock, and powerhouse. The locations as presently proposed for
these features are shown in Appendix A.2.
For the regional Newhalen River concept, investigations included eight
borings, and seven electrical resistivity profile probes to obtain profiles
of soil and rock materials, installation of four observation wells for
groundwater data, laboratory testing of selected soil samples from borings,
and limited surface geologic observations.
The geologic investigations were performed along the
proposed water conveyance canal. Seismic survey and
indicated depths of rock varying from about from about
alignment of the
resistivity probes
15 feet below the
surface near the canal intake, to about 60 to 80 feet near the canal outlet
area in the vicinity of the scarp.
1-8
The depth to bedrock is a factor in the design of the canal. Although some
of the canal would be excavated in rock, a large portion would be
constructed in the soil strata which have been identified as clean sands
and gravels. Because of the existence of these permeable materials, the
canal invert and sides will be lined with roller compacted concrete as a
protective measure against erosion, seepage, and freeze-thaw conditions.
Excavation of the soil material is not anticipated to pose any difficulty
other than that associated with control of groundwater inflows. Special
provisions have to be made for groundwater control, particularly as the
canal approaches its terminus near the older erosional scarp of the
Newhalen River. In this vicinity, and for a distance of about 300 feet
along the canal, special external drainage control systems will be needed
to collect and safely handle seepage flows. Such drainage systems would
preclude seepage outflow from the canal, retaining its stability.
The canal concept and general arrangements considered for the regional
Newhalen River project(s) are shown in Appendix A.2.
Geotechnical
hydroelectric
investigations for
sites at Kukaklek,
the other technically promising
Newhalen (local), Kontrashibuna, and
Chikuminuk were of a very preliminary nature. However, based on the data
analyzed, no major adverse geotechnical conditions were identified.
1.5.1.2 Hydrologic
Reasonably accurate predictions of river flows are necessary to determine
the capacity of potential hydroelectric generating sites. Available data
from several sources were collected and analyzed to make such predictions.
The principal sources of data for the hydroelectric sites considered were
water resources atlas, gaging station data from nearby drainage areas, and
in several cases, gaging stations on the river being studied. Using
various techniques, depending upon data availability, storage capacities
and design flows were selected for hydroelectric project development and
comparison.
1-9
USGS flow data for the Kontrashibuna and Newhalen River sites provided
sufficient data for preliminary hydrologic predictions. Because only
limited data were available at the Chikuminuk site, analysis required a
correlation with the USGS gaging data on the Nuyakuk River to develop
sufficient information. Kukaklek Lake has virtually no hydrologic data
available, therefore, discharge estimates were made based on adjustments of
other gaging records in the area.
A gaging station was installed by the USGS on the Tazimina River near the
proposed regulating dam site in the summer of 1981. Hmvever, it was
necessary to use simulation methods to predict long-term Tazimina River
flows for use in estimating power generation potential. The predictive
procedures used by Dames & Moore and the results of the simulation are
presented in detail in Appendix I of this report. The current predictions
of flow in the Tazimina River at the proposed hydroelectric site are about
18 percent lower on an annual basis than previous predictions by
Retherford.· More importantly from the standpoint of the site's generating
capacity, the current predictions for November through April, the low flow
season, are only about one-third of the previous estimates. This result
has a very important effect on the development potential and economic
attractiveness of Tazimina. In comparison with previous development
concepts, cons iderably more storage capacity would have to be provided in
order to have the regulated flows needed to produce the same electrical
output in the winter months.
The Newhalen River generating concept is a run-of-river power project.
Studies of the 16 year streamflow gage data show that there exists
sufficient flow to generate the power needs of the region through the year
2002. Because of the large drainage area involved, there is sufficient
flow throughout the year to maintain channel flow condition and still
satisfy generating flow needs.
1.5.1.3 Environmental and Sociocultural
The environmental data collection program was undertaken to obtain baseline
data for comparing alternative plans, including transmission systems, to
1-10
perform a detailed analysis of the proposed Tazimina project, and to
address on a preliminary basis the question of fish protection at the
intake to the Ne~halen Canal. A special effort was made. to collec~
sociocultural information. Sociocultural data, collected on a regional
basis, provided useful input for defining energy supply concepts which
would be most compatible with local values.
The major elements of the environmental and sociocultural data collection
program Ivere:
o Water use and quality
o Terrestrial ecology, including vegetation, birds, and mammals
o Aquatic ecology
o Historical, archeological, and recreational resources
o Air quality
o Population and demography
o Socioeconomics
o Land use
o Community attitudes
Special emphasis was placed on the collection of d'it:a related to the
fisheries within the Tazimina River drainage; an eva1 113tion of the sockeye
salmon fishery and spawning locations below the Tazimina Falls was
particularly emphasized. If a decision is made to proceed in Phase II with
a detailed analysis of the Tazimina hydroelectric concept, further detailed
studies, including an instream flow modeling program, will be required.
Appendix G presents, in detail, the environmental and sociocultural field
data collected for the region in Phase I, and in particular, for Tazimina.
This baseline data and other information, obtained largely from literature
searches and limited field reconnaissance, provided the basis for power
plan scenario development and evaluation. Additionally, the data base
collected at Tazimina is believed sufficient in detail to satisfy the
environmental requirements of a FERC license application for a run-of-river
concept.
1-11
The Newhalen River regional hydroelectric concept diverts on the average
about 1000 cfs through a canal to the power plant. The most important
environmental concern related to this concept is protection of the Newhalen
River sockeye salmon escapement. Downstream migrating smolt and fry would
have to be diverted from the canal intake or collected and returned to the
river to ensure safe passage around the project. Studies at other water
intakes indicate that such diversion can be satisfactorily accomplished.
However, to properly design the diversion facilities and to predict their
effectiveness on the Newhalen River, a field program was undertaken in the
spring of 1982 to characterize the downstream smolt and fry migration.
Appendix H presents the results of field data collected in Phase I on the
Newhalen smolt and fry studies.
If a decision is made to proceed in Phase II with a detailed analysis of
the Newhalen regional hydroelectric concept, further detailed studies,
including testing of methods for diverting and/or collecting downstream
migrants, will be required. Also, studies relating to resident fish within
that portion of the Newhalen River, that may be affected by the canal
diversion would need to be made.
1.5.2 Energy Production Concepts
The development of candidate energy plans for the Bristol Bay study region
followed a systematic approach which began with the identification of a
fairly large number of ideas or concepts. These concepts were then
screened and reduced to a manageable number of scenarios for eventual
comparison and evaluation. The details of the program to develop candidate
energy plans are presented in Chapter 6 of this report. A summary follows
of the methodology employed.
1.5.2.1 Identification
The basic factors used in identifying energy concepts that might be
applicable to the Bristol Bay region included the following:
1-12
o Energy demand forecasts
o Applicable energy supply technology
o Experience in designing electrical supply systems
o Community attitudes
o Institutional restraints
The initial step was to identify all potentially practical electrical
generating concepts applicable to the Bristol Bay region. The first part
of this step involved a preliminary evaluation of previously identified
hydroelectric sites in Bristol Bay to identify those sites considered
suitable for inclusion in the concepts. Thirty-six hydro sites were
evaluated with respect to
economic feasibility. Eight
environmental, socioeconomic, technical,
of these sites were initially selected
and
as
being "promising". Comments were solicited from a wide group of state and
federal agencies during the hydro site screening and selection process.
Following this, 48 potential energy supply systems were identified
utilizing the eight selected hydro sites and other applicable energy supply
technologies discussed in Section 1.4. The 48 systems represented numerous
combinations of the basic energy system components. Finally, a matrix was
developed to identify reasonable applications of each supply system for
either the whole Bristol Bay region or one or more subregions. The matrix
revealed more than 100 concepts which were considered suitable for further
evaluation.
1.5.2.2 Screening
The next step required reducing the more than 100 concepts to a manageable
number for further evaluation. Engineering judgement, supplemented by the
subjective consideration of environmental factors, was employed to reduce
the number of concepts to approximately 18. At this point a meeting was
held in Anchorage on November 17, 1981 for the benefit of State and Federal
agencies that had expressed interest in the screening process and
identification of alternatives. At the meeting, the approach to power
system alternatives evaluation was described by the project team, and the
process leading to the identification of the concepts was presented. The
1-13
basic characteristics of the concepts, called II • • II prlmary scenarlos were
described. As a result of this meeting and from further evaluations of new
data, a s late of 20 primary scenarios was selected for further evaluation
and comparison with the Base Plan and Alternative Plan A scenarios.
Conceptual engineering and economic analyses of the selected scenarios
proceeded to a point where quantitative comparisons could be made. With
the exception of Tazimina and Newhalen, environmental assessments were
generally of a preliminary and qualitative nature. The approach taken was
that it would be most cost effective to initially eliminate concepts on an
engineering or economic basis. Subsequently detailed environmental
analyses would be performed on the remaining most promising scenarios.
However, during this evaluation process, the development of the King Salmon
River hydroelectric potential was determined infeasible due to
environmental factors. Accordingly, no cost evaluation was made of
concepts which involved this site. Similarly, local opposition to
development of Kukaklek Lake was voiced. Since development of this concept
had proceeded further, it was decided to continue cost evaluation for
comparative purposes.
In the draft Interim Feasibility Assessment report issued in March 1982, 18
primary scenarios were presented as being applicable to Alternative Plan
B. Subsequent to the draft report, another alternative scenario (B-19) was
added which evaluated a number of subregional concepts consisting of cost
effective mixes of diesel, wind, waste heat recovery and small hydro. This
total of 19 Alternative B scenarios represented many more alternatives than
had been expected when the study began. However, because the Power
Authority, governmental agencies, and the project team all agreed that a
thorough examination of alternatives should be completed before the second
phase of the power plan study went forward, all 19 Alternative B scenarios
are retained in the Interim Feasibility Assessment. Further, as the
economic studies progressed, several variations and combinations of energy
sources were studied as sub-scenarios. This resulted in adding nine more
energy plans to the overall study effort, as Alternative Plan B scenarios.
Considering the Base Plan, Alternative Plan A, and the primary and
sub-scenarios under Alternative Plan B, a total of 30 energy plans were
eventually evaluated.
1-14
1.5.3 Selected Energy Scenarios
The 30 energy scenarios selected for evaluation and comparison represent a
variety of electrical generating systems combined in a number of ways.
Bas ically, the energy scenarios are grouped according to the three main
hypothetical cases previously described. This summary gives only an
overview of the make-up of the scenarios. Reference should be made to
Chapter 6 and Appendix A for detailed descriptions of the individual
elements of the scenarios.
Scenario BP-1, the Base Plan, assumes the continued use of diesel systems
currently in place with the addition of central diesel generation systems
at individual villages as required in the future, but without any waste
heat recovery units. No new transmission interties are assumed.
Scenario A-1, Alternative Plan A, assumes a 16 MW development at Tazimina
to meet regional needs within the study area. To supply this electrical
capacity, a 65-ft rockfill storage dam would be constructed on the Tazimina
River about 4 miles downstream of the outlet from LOI<.'er Tazimina Lake. The
water surface in Lower Tazimina Lake would be raised about 35 ft above its
present level. Main transmission lines would be run to larger population
areas with feeder lines to all villages.
The Alternative Plan B scenarios cons ider 19 other potential electrical
generating systems with nine variations to some of these scenarios, for a
total of 28. Several of the concepts envision a completely intertied
transmission system similar to Alternative A. However, the majority of the
systems are subregional. Special emphasis was given to the consideration
of subregional systems because some Bristol Bay residents believe that such
systems might be more compatible with regional attitudes and values.
The elements of the Alternative B systems include seven' potential hydro
developments and several non-hydro sources. Non-hydro sources, consisting
of the technologies identified in the energy supply technology evaluation,
include fossil systems, diesel systems on an intertied regional and
subregional basis, outside electrical energy generation brought to the
1-15
region by a transmission system, and supplemental wind energy for some
diesel systems. A brief summary of the components which make up the
Alternative B scenarios is provided below. The letter designation after·
each component name and Table 1.5-1 show how these components have been
assembled into scenarios.
Kukaklek-Iliamna (B-2, B-S)
This is a 16 MW hydroelectric power plant located at Iliamna Lake.
Regulated flows from Kukaklek Lake, the headwater reservoir, are used for
generation. A transmission line grid would interconnect all study
communities located west and south of Kukaklek Lake.
Newhalen River (B-2, B-3, B-4, B-7, B~ll, B-12, B-13, B-14)
Three hydroelectric concepts were considered for the Newhalen River. Two
are for regional power development and one is for local power needs. An
are run-of-river partial diversion plans. The regional concepts use a
2.5-mile long diversion canal coupled with a 16 HW power plant
installation. One of the divers ion canal concepts allows for bypassing
high river flows around a section of the Newhalen River which has severe
rapids. The flow bypass would reduce river velocities during periods of
high flow for upstream migrant fish. The other diversion canal concept
allows for diverting water needed only for power generation.
The local concept is a low flow diversion scheme. This uses a
channel-tunnel waterway system to bypass a portion of the flow around a
small section of the Newhalen River. The bypassed flow is used in
generating energy in a 1.2 MW plant.
Either regional project would serve all study area communities through a
transmission line grid. The local project would serve only Iliamna,
Newhalen, and Nondalton.
1-16
Kukaklek Lake (B-3, B-4, B-6)
This is a 7 MW capacity local hydroelectric power proj ect us ing regulated
flows from Kukaklek Lake. The plant would be located at the shore of a
group of unnamed lakes found northwest of Kukaklek Lake. Power
project would serve only the Kvichak River com~unities, not
Iliamna-Newhalen-Nondalton. The concept of U~111z1ng Kukaklek
from this
including
Lake for
providing power to the communities of Igiugig and Levelock only Ivas not
developed.
Chikuminuk Lake (B-3, B-4, B-S, B-6, B-7, B-8, B-13)
Two hydroelectric concepts to develop Chikuminuk Lake were considered.
Both require regulation of Allen River flows, near the outlet of Chikuminuk
Lake. The regional concept would dam the lake outlet, raising the present
lake by some 21 feet. This requires the construction of a 100-ft high dam
about one mile do,,-nstream of the lake outlet. Reguli.1ted flows would be
conveyed to a power plant through a tunnel to generate 16 H\v of peak
capaci ty. The local concept ,,-QuId have a capacity of 8 ~1W and only raise
the lake by 4 feet.
The regional project \"ould serve the region through a transmission line
grid, except for the communities of Iliamna-Newhalen-Nondalton. The local
project would serve only those communities located with the Nushagak River
basin, including Manokotak.
King Salmon (B-4, B-6, B-7)
The development of the King Salmon River would require the construction of
a dam across the river within the boundaries of the Becharof National
Wildlife Refuge. Concepts utilizing the hydroelectric potential of the
King Salmon site were not developed due to potential environmental impacts.
Tazimina River (Local) (B-S, B-6, B-8, B-13, B-18, and B-19)
Three hydroelectric power
than regional basis. A
concepts were cons idered for Tazimina on a less
concept producing 8 ~1W to serve only the
1-17
communities in the Kvichak River area (B-8) would require a 3D-ft high
regulating dam which would raise the Lower Tazimina Lake by 5 feet.
Two run-of-river concepts were also considered. One concept would use a
16 NW installation on a regional basis, but without a regulating dam
(B-18A). The other run-of-river concept would use a small 1.2 MW
installation to serve the Iliamna-Newhalen-Nondalton communities only (B-5,
B-6, B-13A, and B-19E).
Transmission line grids would be constructed, as required, by each type of
development.
Kontrashibuna (B-18)
This hydroelectric development involves a regulating dam on the Tanalian
River with an installed capacity of 16 tN. The project requires a 90-ft
high d2m to raise the Kontrashibuna Lake by about 65 feet. Power from the
project would serve the entire study region through a transmission line
grid. Sc.e.nario B-18A combines Kontrashibuna with a 16 ~fW run-of-river
Tazimina development, while B-18B is a regional Kontrashibuna development.
Outside Source, Beluga Area (B-1)
This concept considers the construction of a 138 kV transmission line from
the Beluga area to the study region. A transmission grid would be used to
serve the communities of the study area. The generation source has not
been identified.
Fossil Fuel-Fired Plant at Dillingham or Naknek (B-9, B-10, B-11, B-12)
Under this concept, a 16 MW fossil fuel-fired steam electric power plant
would be developed at either Dillingham or Naknek, but not both. The plant
would supply power to the study area through a transmission line grid.
Three types of plants were considered for Scenario B-9: B-9A, a
conventional coal-fired steam electric plant; B-9B, an oil-fired combined
cycle plant; and B-9C, a coal gasification combined cycle plant. The
1-18
latter system would utilize gas turbines, a waste heat recovery boiler, and
a conventional steam electric generating plant.
Diesel Power (B-15, B-16, B-17)
In addition to the Base Plan, the continuation of diesel power was
considered in several alternative scenarios. These scenarios considered
central diesel installations capable of serving all communities wi~hin the
study region by using clustered central installations serving a small
number of communities, or groups of communities. Diesel installed capacity
varied, depending on the power needs and the scenario. Transmission line
grids were developed, as needed, for each specific scenario.
Waste Heat, Wind, and Organic Rankine Cycle ( B-15, B-16, B-17, B-19)
Waste heat recovery (B-19A, B-19C, B-19E), wind generation (B-19B, B-19C, .
B-19E), and the organic Rankine cycle (B-19D) were evaluated for use with
the scenarios which utilize diesel generation. The organic Rankine cycle
was considered only for the Dillingham and Naknek communities. Vlind
generation was included in the scenarios only for specific communities or
regions where wind sources are considered most reliable. Detailed
information on wind energy potential is found in Appendices A.6 and D.
All of the Alternative B scenarios selected for evaluation were retained
throughout Phase I to better document the extensive effort given to the
consideration of alternatives. As the Phase I work proceeded, several of
the potential hydro sites became less attractive due to institutional or
environmental concerns. However, these sites were not eliminated from the
evaluation in order to present a basis for comparison with the more
attractive sites.
1-19
B-1*
B-2
B-3
B-4
B-5
B-6
0-7
0-8
B-9A*
0-913*
0-9C*
l)-lU*
0-11
U-12
1.l-13A
0-13B
13-15
B-16
U-17*
B-18AIt
0-16U*
U-19A
0-19B
B-19C
0-190
B-19£
KlIkaklek-
lli~~
x
x
Newhalen
River
x
X
X
X
X
X
X
X
X
TABLE 1. 5-1
SUMMARY OF ALTERNATIVE B SCENARIOS
Hydro Developments
KIII(a k I ek
La,-,-k~e~_
X
X
X
Chlkumlnuk King
Lake Sa Imon
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Kontrash-
Ibun_a __
X
X
*Completcly Intertled transmission sysLem
Non-Hydro Sources
Outside Source Beluga Area
Fossl I-Dillingham (Convent/al Coal)
Foss/I-Dillingham (Combined Cyclo)
Fossl 1-0/ Illngham (Coal
Gasification, Combined Cycle)
Foss I I-Naknek
Fossll-Dillinghan
Foss I I-Naknek
Diesel -4 subregions
Diesel -3 subregions
DIesel -All Connected
Diesel -local Waste Heat
Dlese I -Loca I Wi nd
Diesel -Local Wind and
Waste ileaL
Diesel -Local Organic Rankine Cycle
Diesel -Local Waste Ueat Hnd/or
Wind
1.6 EVALUATION OF SELECTED ENERGY PLANS
The energy plan scenarios described in the previous section were compared
and evaluated with respect to a variety of technical, environmental, and
economic indicators specified in the Alaska POIver Authority requirements
for feasibility studies (3AAC94. 060). Several were removed from further
consideration due to environmental factors (B-4, B-6, and B-7), or because
of similar economic characteristics (B-10 and B-12). The result was a
slate of 25 scenarios selected for final comparison.
1.6.1 Technical
Technical indicators used in the evaluation were:
o Safety
o Reliability
o Availability
o Constructability
Constructibility, although not specified in the regulations, was added to
further define technical differences between scenarios. In addition, each
indicator was considered with repect to both energy production facilities
and transmission lines.
Section 7.2 presents
scenario electrical
details
supply
of the evaluation
components with
of various energy plan
respect to technical
indicators. The evaluation of indicators was qualitative, and no attempt
was made to rank scenarios. However, certain energy supply components have
lower ratings than others from the standpoint of technical indicators as
shown on the next page.
1-20
Supply Component
Diesel
Hydro
Wind
Foss il
Transmission
Lower Rating
Reliability
Constructibility
Reliability and Availability
Commercial Development (coal gasification
combined cycle only)
Safety and Constructibility
In general, all scenarios considered in the evaluation were found to be
acceptable with respect to all of the above technical indicators. Those
preliminary concepts which would have been technically unacceptable for
Bristol Bay, or which represent a non-commercial technology, were screened
out prior to selection of the final 25 scenarios. Accordingly, technical
indicators are not a significant factor in comparing the selected scenarios
during Phase I. Further technical comparisons of the most promising
scenarios will be made in Phase II. Special attention will be given to
protection against ice problems for hydroelectric projects, particularly
for run-of-river plants.
1.6.2 Environmental
The environmental evaluation of the selected energy plan scenarios
addresses the ten evaluation indicators specified by the feasibility study
requirements. These indicators are:
o Community preferences
o Impact on community infrastructure
o Timing in relation to other capital projects
o Air quality
o Water quality
o Fish and wildlife impact
o Land use impact and ownership status
o Terrestrial impact
o Recreational resource value
o Visual impact
1-21
Environmental concerns most often associated with power project development
by residents of the Bristol Bay region were:
o Effect on commercial and sport fishing
o Effect on established subsistence practices
o In-migration of people resulting from project construction or
subsequent industrial development
o Easier access to subsistence areas as a result of project road
construction
Details of the environmental evaluation are presented in Section 7.3, which
draws upon Appendix G, the Environmental Report.
An evaluation matrix, which is provided in tabular form in Section 7.3,
subjectively rates each scenario with respect to the indicators listed
above. The subjective evaluation criteria used to evaluate environmental
indicators were:
A = Small impact
B = Moderate impact, but believed acceptable with mitigation measures
C = Major impact, possible resulting in a "fatal flaw"
The scenarios were not numerically ranked according to environmental
preference due to the difficulty in integrating the highly subjective
indicators considered. However, the scenarios were grouped using the same
evaluation criteria used for the indicators; scenarios were not ranked
within a group.
1-22
The following tabulation shows the environmental evaluation of the
scenarios by group:
Group A Group B Group C
Scenario BP-1 Scenario ."1.-1 Scenario B-1
Scenario B-15 Scenario B-8 Scenario B-2
Scenario B-16 Scenario B-9A Scenario B-3
Scenario B-17 Scenario B-9B Scenario B-4
Scenario B-19A Scenario B-9C Scenario B-5
Scenario B-19B Scenario B-10 Scenario B-6
Scenario B-19C Scenario B-ll Scenario B-7
Scenario B-19D Scenario B-12
Scenario B-13A
Scenario B-13B
Scenario B-14A
Scenario B-14B
Scenario B-18A
Scenario B-19B
Scenario B-19E
Refer to Table 1.5-1 or 1.6-3 for scenario descriptions.
Upon applying the above ten environmental indicators to the scenarios, the
following was found:
o The Group A scenarios, involving diesel-electric generation, exhibit
relatively small environmental and sociocultural impacts.
o The hydroelectric scenar ios in Group C, which include the Kukaklek
and/or King Salmon concepts and generation from an outside source
(Beluga), exhibit major environmental and sociocultural impacts.
o Other hydroelectric concepts exhibit moderate environmental and
sociocultural impacts.
o The coal-fired, steam electric scenarios exhibit moderate
environmental and sociocultural impacts.
1-23
The Tazimina (A-I) and Newhalen (B-14A and B-14B) regional hydroelectric
concepts, are of special environmental interest because they are also
attractive from a technical and economic basis. These, unlike other Group
B hydroelectric concepts, do not require the combination of smaller
developments to meet the entire study region's needs.
The development of the Tazimina River regional hydroelectric concept would
create a storage reservoir behind a dam below the outlet of Lower Tazimina
Lake. The following would result from reservoir construction and operation:
o The reservoir would inundate up to 4,100 acres of land around Lower
Tazimina Lake
o Animal habitat would be displaced by creation of the reservoir
o Lake surface area would nearly double when the reservoir is full,
suggesting increased carrying capacity for lake dweiling species
o \vater level fluctuation could adversely affect permanent
establishment of shoreline habitats
o Resident and anadromous fish habitat in the Tazimina River below the
falls may be affected positively or negatively from changes in river
flows and temperatures
Other effects from project development would include:
o Access to the river for sport fishermen due to the construction of an
access road
o Changes in nearby community infrastructure during construction
For Tazimina, the major concern is that changes in stream flows downstream
of the project could adversely affect sockeye salmon spawning. Because the
falls are impassable to upstream fish migration, no salmon spawning occurs
in the Tazimina Lakes, or the upper Tazimina River, above the falls.
1-24
Considerable study regarding the nature of the aquatic habitat in the
Tazimina River is reported in Appendix G. This information, combined with
future instream flow studies, would be used to develop necessary mitigation
plans for project design and operation. Flow control or augmentation would
be considered for potential benefits to spawning areas.
The Newhalen River regional hydroelectric concept would divert water from
the Newhalen Ri~er at River Mile 7 into a canal leading to a hydroelectric
plant. Diverted flow would be returned to the river at River Mile 1, just
below the first set of rapids. The following changes would result from
development of this facility:
o Flow reduction in the Newhalen River between the intake and discharge
of the hydroelectric plant. Two concepts were evaluated:
(a) flow diversions averaging about 1000 cfs for power generation
only,· or
(b) large flow diversions for the purpose of both power generation
and by-pass ing high Newhalen River flows to aid upstream salmon
migration.
o Elimination of approximately 150 acres of high brush ecosystem at the
location of the canal and ancillary road
o Possible minor displacement of some brown and grizzly bear population
o Changes in nearby community infrastructure
Since no regulating dam would be constructed on the Newhalen River, natural
river flows would not be changed except between the intake and discharge of
the plant. The most important fisheries concern would be to avoid
unacceptable hazards to migrants as they pass the plant site. Two
important requirements would be to: 1) insure adequate flow over the
rapids for upstream fish passage and for resident fish, and 2) avoid
unacceptable hazards at the plant intake for smolt and fry during
downstream migration.
1-25
The first requirement is easily accommodated by allowing sufficient flow to
bypass the plant intake at all times. The second might require the
installation of a fish diversion or screening system to exclude small fish
from the plant intake during downstream migration.
A major environmental benefit might be realized as a result of the Newhalen
River development concept. It has been reported that extreme flows over
the rapids in the lower Newhalen River have caused a blockage at the
river's mouth to upstream fish passage, a problem which on infrequent
occasions has caused extensive mortality in mature adult sockeye salmon as
they move in early summer to freshwater spawning areas in the Newhalen
River-Lake Clark system. The concept mentioned above which could provide
controlled bypass of water around the rapids by means of the large power
intake canal would reduce excessive flows over the rapids, thereby
improving conditions for upstream fish migration.
1.6.3 Economic
A common basis was used to compare and evaluate power supply scenarios in
accordance with Power Authority guidelines. A calculation of the present
worth of all costs and benefits associated with each scenario was the basis
for economic comparisons. The economic parameters and assumptions used in
the calculations were the same for all scenarios evaluated in this study.
Thus, the scenarios can be compared with each other and ranked in terms of
their ability to supply power to the Bristol Bay region at the lowest cost
by comparing present worth cost; the lowest present worth represents the
least costly alternative. Further details on the· economic evaluation are
presented in Chapter 7.
The major steps involved in determining present worth values for each
scenario included the following:
Develop conceptual designs for all systems and equipment included in the
scenario
Determine the installed cost, annual operat ing and maintenance costs,
fuel costs, etc., for all equipment
1-26
Develop the total annual cost (minus any benefits) for each year of the
economic analysis period
Evaluate the present worth of the annual costs
Since detailed designs were not performed for this initial study phase, the
cost estimates are order-of-magnitude prices (± 20 to 25 percent) which
were developed from conceptual designs. The costs for major equipment
items were obtained from vendors, when possible, or from published
material. Additional allowances were made for freight from the factory to
the jobsite. Other cost factors, including those special factors related
to construction costs in Alaska, were determined with the assistance of
Green Construction Company of Anchorage. Finally, allowances were made for
system engineering and design, construction management and on allowance of
about 15% for indeterminants. Interest during construction was also
included.
The economic parameters and assumptions used in calculating present worths
were in conformance with Power Authority guidelines, except for the
economic lifetimes of certain items of equipment. Summaries of the
economic parameters and equipment lifetimes are shown in Tables 1.6-1 and
1.6-2, respectively. In the cases involving diesel generators,
transmission lines, coal gasification, and waste heat recovery equipment,
the economic lifetimes shown in Table 1.6-2 are greater than the values in
the Power Authority's guidelines. These economic lifetime values were
reviewed by the Power Authority, and were considered acceptable for use in
the study.
The base year for the economic analysis was 1982, with a 21-year planning
period (i. e., Bristol Bay electric demand proj ections for 1982 through
2002) and a 56-year analysis period. The analysis period resulted from the
assumed installation of hydroelectric plants in 1988 which, when combined
with a 50-year hydroelectric lifetime, extended the analysis period from
the base year of 1982 through the year 2037.
The costs occurring in the years following the planning period from 2003
through 2037 were assigned, as required, by the Power Authority economic
1-27
guidelines. It was assumed that no further load growth or petroleum fuel
cost escalation occurred after 2002. Thus, the costs occurring in 2002
were repeated for each following year to 2037, and the present worth was
calculated based on this cash flow. Fo~ those diesel systems which include
waste heat recovery equipment, a benefit was ass igned each year for the
waste heat recovered. Calculations were performed to determine the
fraction of the recoverable waste heat that could be used for space
heating. A credit was applied each year for the space heating supplied,
assuming that diesel was the fuel normally burned in homes for space heat.
Lastly, the costs developed in this study represent bus bar costs and do not
include costs such as distribution within the villages, administration,
taxes, insurance, depreciation, etc. The present worth of consumer costs
would be significantly higher.
Table 1.6-3 is a summary of present worth costs for the Bristol Bay
regional power scenarios. It is apparent that a ,,-ide variation in costs
results from the several power supply options that were considered.
Overall, the hydroelectric scenarios generally had lower present worth
costs than other power supply technology options. The Newhalen regional
power only concept (B-14A) was lowest, followed by the Tazimina regional
concept (A-1) and the Newhalen regional power and river divers ion concept
(B-14B). The regional Kontrashibuna (B-18B) and a plan consisting of a
smaller development of Tazimina combined with local diesel energy
suplemented with waste heat and wind generation were the next most
cost-effective options. By comparison, the Base Plan (BP-1) ranks number
20.
Additional special studies were undertaken to: 1) investigate the economic
benefits of supplemental wind systems and waste heat recovery for diesel
scenarios; 2) determine the most economic local hydro development for
specific subregions; and 3) evaluate the viability of the organic Rankine
cycle for Naknek or Dillingham. In general, the addition of waste heat and
wind to the diesel scenarios results in cost savings as evidenced in the
fifth ranking scenario B-19E. The results of these studies are reported in
Chapter 7.
1-28
1.7 REGULATORY COORDINATION AND PUBLIC PARTICIPATION
A program of regulatory coordination and public participation was
undertaken with the following objectives:
o to ensure the adequate and timely involvement of Federal, State, and
local governmental agencies interested in the study
o to identify regulatory requirements for the licensing of proposed
power plans
o to keep the public fully informed and to provide a means whereby the
public can influence the work effort
A chronological list of significant meetings, communications, and other
events is included in Chapter 8 of this report .
..
1.7.1 Agency Communication
With respect to the first objective, several formal meetings were held in
Anchorage between August 19, 1981 and June 15, 1982, to explain work
obj ectives and progress to interested governmental agencies. These
meetings appeared to be beneficial to agency personnel in obtaining a
better understanding of the proj ect ; without question these meetings were
beneficial to the project team. At some meetings, packets of preliminary
information were handed out for review and comment. In addition to
progress reporting, items discussed included the approach being taken by
the proj ect team to select alternative energy sources and sites,
environmental concerns of various agencies with respect to specific plan
proposals, and possible ways to cooperate and exchange information between
the project and various agencies who are interested in resource
development. Interested personnel in a number of agencies (.,ere routinely
sent copies of the Project Report. Special meetings were held with
fisheries related agencies on the more promising hydro developments,
particularly Tazimina and Newhalen concepts. Comments received from these
communication exchanges were considered during the development and
evaluation of power plan alternatives.
1-29
1.7.2 Regulatory Requirements
The range of laws and regulations considered during the Interim Feasibility
Assessment was broad because of the large number of alternatives
evaluated. Some of the important regulatory issues considered during Phase
I included land status, land ownership, agency management respons ibility
within designated parks and preserves, and provisions of the Alaska Native
Claims Settlement Act and the Alaska National Interest Lands Conservation
Act. Transmission line routing, with respect to land status, was another
important consideration. Because the requirements of the National
Environmental Policy Act would be brought into effect if a proposed project
required federal licensing,
compare
These
alternatives from
data also will be
much data was collected which was used to
the regulatory and environmental standpoint.
useful in further evaluation of licensing
requirements for the most promising alternativeCs) in Phase II.
1.7.3 Public Participation
Public participation, particularly involving the residents of the Bristol
Bay region, was recognized early by the project as a key element of the
study. The Power Authority and the project team have gone on record with a
commitment to determine, and be guided by, local attitudes with respect to
development of electrical power in the region. The inherent difficulty in
any public participation program is the problem of sorting out the wide
range of interests and expectations; the Bristol Bay public participation
program was no exception.
Several steps were taken during the Interim Feasibility Assessment to
provide a chance for Bristol Bay residents to learn about the study. An
initial step was a series of village meetings in September and October
1981, when practically every village in the region was visited by the
Project team to explain the purpose of the power plan study and to request
comments on matters of interest or concern. The many comments and
suggestions received either during the meetings or sent later by mail on
special forms were compiled and considered. In some cases, these comments
resulted in significant changes in plan concepts. Also, community meetings
1-30
were repeated in March 1982 to· present the results of the Interim
Feasibility Assessment.
Other steps taken to enhance communication with Bristol Bay residents
included the distribution of project reports to community leaders, radio
and press releases on the study, and numerous informal meetings and
discuss ions with local res idents as proj ect team members collected
necessary field data. Although the special communications and
transportation in the Bristol Bay region are less than ideal for maximum
public participation, it is believed that a credible effort has been made
to recognize local concerns.
The fundamental community issue appears to be concern about conflict
between accelerated energy resource development and the existing lifestyle
in the Bristol Bay region. Most residents welcome less costly and more
abundant sources of electrical power, if their current lifestyle is not
adversely affected. The most commonly expressed concern relates to the
effect of power projects on the fisheries, both from the commercial and
subsistence standpoint. Decreases in game,
areas, and influx of outsiders are also seen
However, attitudes differ throughout the
benefits and costs of more energy. These
increased access to remote
as poss ible harmful effects.
region regarding perceived
differences from a regional
standpoint may represent unresolvable conflicts. However, understanding
them may permit elements of the study to be tailored somewhat to local
preferences.
More information on the public participation program is presented in
Section 8.2.
1.8 CONCLUSIONS AND RECOMMENDATIONS
1.8.1 Conclusions
The general conclusion of the Interim Feasibility Assessment is that there
are a number of promising alternatives to the current use of diesel
electric generation in the Bristol Bay region. This conclusion is based on
1-31
an analysis of the technical, environmental, and economic characteristics
of 25 power development scenarios. These scenarios utilize a variety of
commercially available power generation systems considered technically
suitable for use in the Bristol Bay region during the planning period from
1982 to 2002.
The economic evaluation in Section 1.6.3 (Table 1.6-3) shows a significant
variation between the scenarios on a present worth basis. The four least
costly alternatives are regional hydroelectric developments: 1) on the
Newhalen River (B-14A), 2) on the Tazimina River (A-I), and 3) on the
Newhalen River (B-14B), and 4) on the Tanalian River near Kontrashibuna
Lake (B-18A). The next alternative in order of economic preference is the
development of subregional diesel systems, including utilization of waste
heat recovery and wind supplemental energy, coupled with the development of
a local Tazimina River hydroelectric project (B-19E).
A comparison of the top five scenarios and the Base Plan by present worth
ratios shows the following economic ranking:
Economic
Rank
1
2
3
4
20
Description Scenario No.
Newhalen Regional -Power Only B-14A
Tazimina Regional A-I
Newhalen Regional -Power and
River Diversion B-14B
Kontrashibuna Regional B-18B
Local Diesel, Waste Heat, wind,
and Local Taziminina B-19E
Base Plan (Continued Diesel) BP-1
Present Worth
Ratio
1. 54
1. 36
1. 31
1. 29
1. 20
1. 00 (Base)
Refering again to Table 1.6-3, there are several other scenarios within a
relatively close grouping which show lower costs than the Base Plan. Many
of these employ disconnected subregional systems. Also, it should be noted
that three scenarios in this grouping, utilizing coal in centralized power
plants, are also slightly less costly than the Base Plan.
1-32
With respect to environmental considerations, the ranking is different than
for economics. Continued electrical generation by diesel systems was
judged to result in the least environmental effect to the Bristol Bay
region. The four other most attractive alternatives on a present worth
economic basis all fall within the intermediate environmental category
(Group B), having moderate impacts that are believed to be acceptable with
mitigation measures.
In making choices between power plan candidates on the basis of the data
available at the Interim Feasibility Assessment, a third factor must be
considered: the level of confidence in the information, or assumptions
used in the evaluation, of individual scenarios. Al though an effort was
made to evaluate all scenarios on a consistent level, considerable
differences exist in the quality and quantity of data available.
Considering the top five candidates from the economic evaluation, the best
data on which to make an evaluation is available for the Tazimina and
Newhalen scenarios, due to collection of considerable detailed physical and
environmental data. For Kontrashibuna, because it is a more remote site,
there is a lack of specific data about its environmental setting, and there
are questions concerning the compatible use between the Lake Clark National
Park and Preserve and the site for power generation. These factors combine
to reduce the level of confidence in the assumptions used in the
development of the Kontrashibuna concept. For the local diesel, waste
heat, wind, and local Tazimina scenario (B-19E) the assumptions relative to
the practical levels of wind and waste heat utilization may be questioned.
Confidence in the diesel and hydroelectric components, however, is high.
Considering the above factors, the following conclusions were reached with
respect to the top five candidates:
Technical -
Economic -
All are feasible.
All present attractive cost advantages over the Base
Plan, the continuation of present diesel generation
practices.
1-33
Environmental -Subregional diesel power in combination with wind, waste
heat, and the run-of-river Tazimina has the least impact
on the Brist:ol Bay region; the other four candidates,
although exhibiting varvin o _ 0 potent:ial environmental
eff2cts, are believed to be acceptable with mitigation.
Confidence is highest for the sub-regional diesel/waste-
heat/wind/Local Tazimina concept, reasonably high for the
Newhalen concept:s, and lower for the Tazimina and
Kontrashibuna regional plans.
These above conclusions lead to the following subjective order of
candidates with respect to economic, environmental, and confidence factors:
Economic Environmental
Ne\'lhalen Subregion Diesel w/wast~
(Power Only) heat/wind/Local Tazimina
Tazimina Newhalen
(Regional) (Power and River Diversion)
Newhalen Newhalen
(Power and (Power Only)
River Diversion)
Konst:rashibuna Tazimina
(Regional) (Regional)
Subregional Diesel Kontrashibuna
w/waste heat/
wind/Local
Tazimina
(Regional)
Confidence
Subregion Diesel w/w~s~~
heat/Wind/Local Tazimina
Nelvhalen
(Power Only)
Newhalen
(Power and
River Diversion)
Tazimina
(Regional)
Kontrashibuna
(Regional)
The intent is not to imply equal weight to the three evaluation factors or
suggest that the ranking is linear from top to bottom of the list.
1-34
Furthermore, the ranking of environmental and confidence factors is highly
subjective.
Thus, based on a subjective evaluation of the above lists, it is concluded
that the ranking of alternatives for a completely intertied regional power
plan is in the same order as shown above in the economic listing. However,
since local preferences may favor subregional developments, we suggest
further consideration should be given to the subregional diesel/waste heat/
wind/Local Tazimina Scenario (B-19E).
With respect to regional hydroelectric power developments, it may be
technically and economically feasible to develop some of these projects for
higher capacity and energy. Such proj ects might be increased in size to
provide electrical energy requirements of not only the Bristol Bay region,
but adjacent areas such as Bethel and Togiak. The merits of such
developments could be considered for study under the Phase II efforts, if
the Power Authority so desires.
1.8.2 Recommendations
Based on the stated conclusions, and in consideration of presently known
factors, Stone & Webster Engineering Corporation makes the following
recommendations for Phase II efforts of the Bristol Bay Regional Power Plan:
a. Continue detailed development of the Base Plan scenario to form a base
for comparison;
b. Continue detailed feas ibility analysis of the regional Newhalen River
hydroelectric power concept (B-14A);
c. Undertake detailed feasibility analysis of the
diesel/waste heat/wind/Local Tazimina scenario (B-19E);
sub-regional
d. Through a public participation program, obtain a better understanding
of attitudes of the people of Bristol Bay regarding a regional power
plan.
1-35
The recommendation to continue studies on the Newhalen River concept sterns
from the preliminary conclusion that the project is economically
attractive, technically feasible, and is likely to be environmentally
acceptable with proper mitigative measures. To this end, the following
steps are suggested for early implementation in Phase II efforts:
a. Undertake resident and anadromous fisheries studies to satisfactorily
demonstrate the environmental acceptability of the B-14A concept.
b. Continue geotechnical investigations and surveys at the proposed site
to better define site conditions revealed by initial investigations and
to obtain additional geologic data in the vicinity of the power plant.
The following conclusions further support the recommendation to undertake
further evaluation of the Newhalen River regional concept in Phase II:
a. The Newhalen regional concept appears more a~tractive economically than
Tazimina, based on presently available data;
b. The engineering and construction uncertainties relating to this project
appear to be fewer because of its location and nature of the concept;
c. There may be some significant mitigative fisheries benefits relating to
upstream migrants that could be implemented and made part of proj ect
development; and
d. Because of high Newhalen River flo,,'s during the summer, there exists
the potential for additional electrical energy development during that
period of time coinciding with fish processing energy needs. This
should benefit processors within the region.
We recommend that a decision be made to evaluate the Newhalen concept and
the sub-regional diesel/waste heat/wind/Local Tazimina concept in Phase II,
and to perform those investigations and studies that are necessary for the
Detailed Feasibility report and, as applicable, for the preparation of a
FERC license application.
1-36
Based on the above recommendations, the scope of work believed necessary
for the Phase II efforts is outlined in detail in Chapter 10 of this report.
1-37
• VILLAGES INCLUDED IN STUDY
A 0 LOCATIONS OF MAJOR NON
D DIESEL POWER SOURCES
6. = HYDRO 0 = COAL-FIRED
OR OTHER
.& NEWHALEN
&TAZIMINA
&. KONTRASHIBUNA
A CHIKUMINUK
&. KUKAKLEK
&. KING SALMON
(2] LINE FROM BELUGA
[!] DILLINGHAM o NAKNEK
SCALE
o 10 20 30 40 50
MILES
BRISTOL BAY REGION
FIGURE 1.2-1
A
TABLE 1.6-1
SUMMARY OF ECONOMIC ANALYSIS PARAMETERS
·Base Year
Planning Period
Economic Analysis Period
Inflation Rate
Real Discount Rate
Real Petroleum Fuel Escalation Rate
Interest Rate
1982
21 years, 1982 -2002
56 years,1982 -2037
0% (all costs expressed in 1982
dollars)
3%
2.6%
3%
TABLE 1.6-2
ECONOMIC LIFETIMES FOR MAJOR EQUIPMENT
Equipment Item
Diesel Generators
Electric Transmission Lines
Waste Heat Recovery Equipment
Wind Generators
Organic Rankine Cycle Systems
Hydroelectric Plants
Steam Turbines
Combined Cycle Plants
Coal Gasification Equipment
Lifetime, Years
30
30
15
15
25
50
30
30
30
TABLE 1. 6-3
SUMMARY OF PRESENT WORTH COSTS
All Values in 1982 Dollars
Scenario Description
Present Worth,
(Sl,OOO) Ranking
Bas e P I an ( B P -1 )
Alternative A (A-1)
Alternative B-1
Alternative B-2
Alternative B-3
Alternative B-5
Alternative B-8
Alternative B-9A
Alternative B-9B
Alternative B-9C
Alternative B-11
Alternative B-13A
Alternative B-13B
Alternative B-14A
Alternative B-14B
Alternative B-15
Alternative B-16
Alternative B-17
Alternative B-18A
Alternative B-18B
Alternative B-19A
Alternative B-19B
Alternative B-19C
Alternative B-19D
Alternative B-19E
Diesel Only
Tazimina Regional
Beluga Transmission
Newhalen and Large Kukaklek
Newhalen and Medium Kukaklek
Tazimina Run-of-River, Medium
Chikuminuk and
Medium Kukaklek
Medium Chikuminuk and
Medium Tazblina
16 MW Coal-Fired
16 MW Oil-Fired
16 MW Coal Gasification
Coal-fired at Dillingham
and Newhalen
Large Chikuminuk
and Tazimina Run-of-River
Large Chikuminuk and local
Newhalen
Newhalen Regional -Power Only
Newhalen Regional Power and
River Diversion
Diesel Clusters
Diesel Clusters and Transmission
Diesel Regional Transmission
Interconnected
Tazimina Run-of-River
and Kontrashibuna
Kontrashibuna
Diesel Local and Waste Heat
Diesel Local and Wind
Diesel Local -Waste Heat
and Wind
Diesel Local and Organic Cycle
Tazimina Local, Diesel Local,
Waste Heat + Wind
291,700
213,700
279,600
301,000
276,300
270,700
266,000
281,000
388,500
269,300
281,300
261,500
267,100
189,900
222,200
340,400
338,900
367,900
270,200
226,800
249,500
287,900
249,200
283,900
242,500
1. No cost evaluations were made for scenarios B-4, B-6, and B-7, which
included the development of King Salmon.
2. Alternative B-10, a coal-fired plant at Naknek, has the same present
worth as B-9A.
20
2
15
21
14
13
9
16
25
11
17
8
10
1
3
23
22
24
12
4
7
19
6
18
5
3. Alternative B-12, a coal-fired plant at Naknek with a subregional
Newhalen hydroelectric development, has the same present worth as B-11.