HomeMy WebLinkAboutKotzebue Coal-Fired Cogeneration, District Heating and Other Energy Alternatives Feasibility Assessment Volume One 1982-
-~-----
'I'J
163.25
A4
K67
v.l
KOTZEBUE
Coal-Fired Cogeneration,
District Heating and
Other Energy Alternatives
Feasibility Assessment
VOLUME ONE
by
A JOINT VENTURE OF
ARCTIC SLOPE TECHNICAL SERVICES, INC.
RALPH STEFANO ASSOCIATES I INC.
VECO, INC.
ANCHORAGE, ALASKA
NOVEMBER, 1982
'----__ ALASKA POWER AUTHORITY __ ____
u
u
u
u
o
u
r 1
U
r i , I
I.j
~ ..
iU
I
JOINT VENTURE
VECO, INC.,
RALPH STEFANO & ASSOCIATES, INC., AND
ARCTIC SLOPE TECHNICAL SERVICES, INC. (ASTS)
November 12, 1982
Mr. Eric P. Yould,
Executive Director
Alaska Power Authority
334 W. Fifth Avenue
Anchorage, Alaska 99501
Attention: Patti DeJong, Project Manager
Subject: Kotzebue Coal-fired Cogeneration, District Heating
and Other Energy Alternatives Feasibility Assessment
Dear Ms. DeJong:
We are pleased herewith to submit the final report on the subject
feasibility assessment.
Kotzebue is a community with a current population of about 2,850.
It is located on the Baldwin Peninsula in Kotzebue Sound, 26
miles north of the Arctic Circle. Electrical power is currently
being supplied by diesel electric generation by the Kotzebue
Electric Association.
The purpose of this study has been to assess all available
options for providing Kotzebue with a feasible', practical, and
proven power generation and heating system. While the original
emphasis of the study was coal-related, we have in fact analyzed
all practical alternatives.
The plan period was twenty (20) years -i.e. from 1982 to the
year 2002; however, the economic analysis has been based on 55
years. The 20 and 55 year periods are consistent with the
overall evaluation process of the State of Alaska. In other
words, load projections are considered for only the first 20
years, after which time they are assumed to be constant.
However, overall system life requires economic analysis over a
longer period, i.e. 55 years.
In analyzing the community's needs we have accomplished:
o an energy balance;
o a population and energy use forecast to the year 2002;
o technology
conceivably
environment;
profiles
could
for
be
those energy
possible in
systems which
the Kotzebue
n ..
~
u
;~
I IU
u
U
L
Alaska Power Authority
Page Two
November 12, 1982
o
o
o
o
an evaluation of these technology profiles with the
purpose of selecting and analyzing in more detail those
technologies which appear practical and possibly
economically viable;
a more detailed analysis of the preferred alternatives;
cost analysis (First Cost Construction)
preferred schemes;
of those
an evaluation of those schemes which appear to be best
suited for the City of Kotzebue, based on the economic
evaluation criteria provided by the Alaska Power
Authority:
o recommendations on future studies.
System~wise, i. e. if only the economics were considered, coal-
fired cogeneration may be the most attractive alternative if coal
(local or imported) can be provided for around $6.00/Mbtu, as is
estimated for the coal source at Cape Beaufort.
Otherwise, the most favorable al ternati ve for the community is
hydropower either with electric resistance heating or with
geothermal district heating:
o
o
For geothermal this assumes that a geothermal resource
of at least 162°P with sufficient flow exists
(currently an unknown, subject to confirmation by
exploration: Dr. Robert Forbes, a noted expert in this
field, agrees with these parameters). The geothermal
resource is felt to be only marginally viable for a
district heating system.
For hydropower this assumes that the environmental
impacts relating to fish, flora and fauna, and that the
problems associated with a large shallow reservoir at
the Buckland site, are acceptable to the community and
regulatory agencies.
Early follow-on into the resource confirmation, prior to detailed
feasibility study and final design phases, would now be in order.
~
\
I
jU
U
! ;
l..
·U
I
U
'U
I
U
I U
iU
I
Alaska Power Authority
Page Three
November 12, 1982
We appreciate the opportunity to have worked with you and thank
you for your cooperation during all phases of this challenging
study.
If you have any questions regarding this report, please do not
hesitate to contact us.
Sincerely,
ARCTIC SLOPE
MJT/tsb
enclosure
SERVICES, INC.
Turner, P.E.
D
jl w
I~
iW
U
U
10
{ .
i I ~
r '
W
r I
W
:U
I
Q
~
W
U
D
KOTZEBUE
Coal-Fired Coge'neration.
District Heating and
Other Energy Alternatives
Feasibility Assessment
VOLUME ONE
by
A JOINT VENTURE OF'
ARCTIC SLOPE TECHNICAL SERVICES, INC.
RALPH STEFANO ASSOCIATES, INC.
VECO, INC.
ANCHORAGE,ALASKA
NOVEMBER, 1982
JUL 1 IS 19M
.ll.A8KA RESOURCES LTBRI
U.S. DEPT. OF INTERIm
.L.--__ ALASKA POWER AUTDORITV __ ----J
~
L
L
L
L
L
L
L
L
L
L
L
L
~
I
i
i
~ ,
vle acknowledge
offered by:
ACKNOWLEDGEMENTS
and appreciate the valuable assistance and advice
the people of Kotzebue
Alaska Power Authority personnel
Kotzebue City officials and Council
Kozebue I.)i"stri,<::t Heat Work Group
Kotzebue Electric Association
NANA Corporation
Maniilaq Association
Arctic Lighterage
Kotzebue Energy Auditors
Federal and State Agencies
u
U
U
:u
I 'u
u
'U I
U
( 1
U
U
r :
I
~
VOLUME I
TABLE OF CONTENTS
TABLE OF BASIC DATA •••..••••• ., •••...••••••.••••..••••••..•••••• i
FOREWORD •••••••••••••••••••••••••••••••••••••••••••••••••••••• i i
SECTION 1 -INTRODUCTION AND SUMMARY ••••••••••••••••••••••••• 1-1
SECTION 2 -PUBLIC AND AGENCY INPUT .•••..•.•••••••••••••••••• 2-1
SECTION 3 -ENERGY BALANCE •••.•••••.•.•••••••••••••••••••••.. 3-1
SECTION 4 -ENERGY DEMAND FORECAST ••••••••••.•••••••••••••••• 4-1
SECTION 5 -TECHNOLOGY PROFILES ••.•••••••••••••••...•••••••.• 5-1
SECTION 6 -EVALUATION OF TECHNOLOGY PROFILES •.•••••••••••.•• 6-1
SECTION 7 -DESCRIPTION OF ALTERNATIVE.PLANS ••••••••..••••••• 7-1
SECTION 8 -COST ESTIMATES ••••••••••••••••••••••••••••••••••• 8-1
SECTION 9 -ENVIRONMENTAL EVALUATION •••..•••...••••••••.••••• 9-1
SECTION 10 -PLAN EVALUATION .•••••..•••••.•••••••••.•••••••.. 10-1
VOLUME II
APPENDICES
TABLE OF CONTENTS
APPENDIX A -LITERATURE RESEARCH ••..••••••.••••.•••••••..••••. A-1
APPENDIX B -PUBLIC COMMENTS AND AGENCY INPUT .••••.•••••••.••. B-1
APPENDIX C -GEOTHERMAL TEST-WELL PROGRAM •••..••••..•.••.....• C-1
APPENDIX D -TECHNOLOGY PROFILES •...••••....•..•••••••...••••• D-1
APPENDIX E -CONSERVATION •••••••••••....•••.•••••..••••••••••• E-1
APPENDIX F -COST ESTIMATES DATA .•.••••.•••••....•.••••••••••• F-1
APPENDIX G -OPERATION AND ~ffiINTENANCE •••.••••••••••••.••••••• G-1
APPENDIX H -FUEL DEMAND .••..••••.•••..•••••.••••••••••••..••• H-1
APPENDIX I -CALCULATION OF PRESENT WORTH OF CAPITAL COST ••••• I-1
APPENDIX J -COAL TRANSPORTATION ANALYSES •.•••••...••••••..•.. J-1
L
L
L
L
L
I
I (1)
TABLE OF BASIC DATA
KOTZEBUE
Location:
Latitude
Longitude
Temperatures:
Mean temperature February
Mean temperature July
r1ean temperature annual
Design Temperature; 97.5%
Degree days per year (base 65°F)
Popul'ation 1981:
Number of households 1981:
Heat values:
Propane
Gaspline
Kerosene (jet fuel)
Fuel oil #1
Fuel oil #2
Conversion factors:
1 kWh
1 gallon of water
Coal ValUes:
Areas,
Nenana
(Usibelli field)
Chicago Creek
Kobuk River
Cape Beaufort
=
=
BTU/lb
8,000
6,500
10,000
14,000
66° 52'N
162° 38'W
-4.3°F
52.9°F
20.7°F
16,151°F days
2,625
660
92,50Q Btu/gallon
120 ,000 Btu/gallon
132,OnO Btu/gallon
136,50G Btu/gallon
138,5QO Btu/gallon
3,413 Btu
8.3453 lbs. of water
TONS(2f
COAL $/MBTU
61,000 8.84
75,000 6.57
49,000 5.52
35,000 5.98
Based on a constant 925 Billion BTU/year.
i
L
L
L
L
L
L
L
L
~
I
I
FOREWORD
The residents of Kotzebue rely almost entirely on oil to meet
their electrical power and space heating needs. Because of
rising prices in recent years, this dependence has had a severe
impact on the community. It is reasonable to assume that this
impact will not lessen in future years.
Recent studies by others have assessed power generation
alternatives for Kotzebue, and have focused on the feasibility of
using hydropower and possibly the region I S coal resources for
space heating and electrical power generation. A separate
investigation has addressed the potential for geothermal district
heating for Kotzebue. Interpretation of these reports indicated
the need. for a more detailed investigation of all viable
alternatives, especially coal and geothermal energy. This
report, then, addresses in some detail the coal and geothermal
energy sources, while also addressing other viable systems
including, but not limited to, hydropower, wind, and
conservation.
To accomplish this very broad and comprehensive task, the
following approach was taken:
o
o
o
o
o
o
o
o
o
o
o
o
o
literature survey and analysis
population forecast (including economic growth where
applicable)
heating and electrical load forecasts
community reconnaissance and public meeting
energy balance
assessment of energy resources and conversion
technologies
screening of energy alternatives to determine those for
which detailed plans and economic analyses should be
performed
preparation of alternative plans
technical, economic, social, cultural and environmental
analyses of the alternative plans
final assessment of alternatives
agency and public review
final report incorporating comments and responses to
comments
suggested future work efforts
This work was carried out under contract (AS44. 56.010) to the
Alaska Power Authority by a joint venture of three Alaskan firms:
VECO, Ralph Stefano & Associates, and Arctic Slope Technical
Services, Inc.
ii
I
'I
" I
I
I
I
I
~
I
I
~
~
~
I
I.
I
I
I
I
1.
INTRODUCTION AND SUMMARY
iW
I , U
I
: U
I
I[J
U
iU
I
U
u
u
u
u
u
u
~
1.0
1.1
1.2
1.3
1.4
Figure
Figure
Figure
Figure
Figure
Figure
Figu're
Figure
Figure
Figure
Figure
Figure
SECTION 1
INTRODUCTION AND SU~~RY
TABLE OF CONTENTS
Background ............................................ 1-1
Approach .............................................. 1-4
Summary of Findings ................................... 1-6
Recommendations ....................................... 1-17
Sensitivity Analysis .••..•.....•••....•.••••.•••••.••• 1-21
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1. 11
1. 12
LIST OF FIGURES
Location and Vicinity Map •••......•••.•.......• 1-2
Kotzebue Area .........................•........ 1-3
Energy Balance, Electrical and Space Energy .•.. 1-7
55-Year Energy Prbjection Concept ...•••..•••.•• 1-8
Variations in Demand for Heat and
Electricity for Kotzebue ••••.•••.•••••••••....• 1-9
Energy Demand, Electrical and
Heating Projection ..•••••••••••.••••••••••.•••. 1-10
Outline of a District Heating Scheme •.•...•..•• 1-12
Buckland River -Energy Availability ..•........ 1-13
Numbers of Windgenerators .........•••••..•...•• 1-15
Base Case Diesel Generation .....••..••.•••••••• 1-18
Simplified Schematic Diagram for
Cogeneration System for Kotzebue ...•.••..•..•.. 1-19
Projected Energy Demand and Deficit
1982-2037 ...................................... 1-24
LIST OF TABLES
Table 1.1 Sensitivity of Benefit-Cost Ratio .••.••••••••••.• 1-23
u
u
u
·u
u
u
u
U
lJ
U
u
u
I~
SECTION 1 INTRODUCTION AND SUMMARY
1.0 BACKGROUND
Since 1973 the world has been watching skyrocketing prices of
energy in general and petroleum products, such as heating oil and
diesel fuel, in particular. Many Alaskan communities rely almost
entirely on oil to meet their electrical power and space heating
needs, and, although .Alaska possesses some of the world's largest
oil reser.ves, the inhabitants of these communi ties are
encountering rapidly escalating energy prices, which are not
offset by similar increases in faMily income.
With its approximately 700 residences ·and 2,850 inhabitants,
Kotzebue is one of the largest communities in. Northwest Alaska.
It is located on the Baldwin Peninsula, 26 miles north of the
Arct{c Circle and is without overland connecting routes to
Fairbanks, Anchorage or other maj or Alaskan communi ties (see
Figure 1.1). Goods and materials (including fuel oil) are
shipped into the community during the three months when Kotzebue
~ound is free of ice. Heavy barges, however, cannot reach
Kotzebue, and shipments must be lightered to shore, thus
increasing the transportation costs of these goods. Kotzebue is
a regional air transportation center wi thregularly scheduled
major airline and bush flights. Also economically and
administratively, the city serves as the regional center of the
NANA Region, which has a total population of about 5,500 (see
Figure 1.2).
Current electrical requirements of the community are met by
Kbtzebue Electric Association (KEA) at an average cost per kWh
of 20¢. Heating is primarily provided through use of fuel oil in
iridividual space· heating stoves.
1-1
LOCA nON AND VICINITY MAP
FIGURE 1.1
\-2
I j w
W
U
U
I 1 U
! l
I i
IIj
u
u
w
w
w
,W
U
u
r I ~
..
..... ..
. ........ . ... . ........................
::;.:;:;:::;:::::;:;:;::":
.. :::::::::::::::;:;:::%:ew.;~ ..
Vi/in!:::::::
........... :.; ..... : ... :;; ..•.. : ..
:::::::::::::::::::::::;::::::::.:
;.·········.·:;.;.:.·;;·······;;;····;·ifoliillltiij·;
::;:;:;:;-:;:;:;:;:;:;:;:;:;:;:;:;:;:;:;:;:;:;:;:::
.••• : •••• :.:.: •••• i ••• • •• i ••••••••••••• ! ••••••• : ••• : ••••••••••••
·~Jw.z1~ ... !.nn.:.·
"'">-~.:I\ ··;·········If.0i··;····.;····.·············'·········
:LEGEND !HI HYDROELECTRIC F!OWERPOTENTIAL. -.'
. '.~ '® GEOTHERMAL POTENTIAL (HOT OR 'W'ARM8PRING8 .OR WELLS)
1111111111 COAL RESOURCE
-TRANSMISSION LINE 138 KV 30
~---~---~-----~~ ------~~~~~
KOTZEB.UE AREA
North
I I I J o 10· 10 10MILEI
FIGURE 1.2
Recent studies by others have assessed power generation
alternatives for Kotzebue and have focused on the 'feasibility of
using ,the ,region's coal rrrfurc~s ,for ,,'space heating and
,electrical power generation • ,Another investigation has
addresseq1)the potehtial for geothermal district heating for
Kotzebue •
Preliminary findings of these previous studies indicated, in part
that:
1) although geothermal generation of electricity or heat did not
appear to be economically beneficial to Kotzebue residents,
district heating using a fossil fuel energy source might be
beneficial;
2) use of coal from Alaskan resources might decrease the cost of
electrical power in gotzebue if by-product heatcould.be
sold as well. For these reasons, this Feasibility Assessment
considers coal-fired generation of electricity with, capture
of by-product heat and, dist~ibution of the heat, by~means of
a city-wide district heating system. The previous studies
also indicated that hydropower was promising. '
Although the primary focus of this study has been coal-fired
cogeneration of heat and 'electricity, it was necessary to confirm
that this option would be less costly to the. consumers than other
eriergy sources and conversion technologies. For this reason, all
feasible energy resources and 'technologies have been considered.
Wher~ previous studies have ad?ffssed ~hese technologies in some
detall (for example hydropower ), thlS report has not 'presumed
it necessary to repeat such feasibility level work in its
entirety but has only updated results and made changes in cost
estimates and other areas as necessary (such changes are further
discussed ~n Volume. II, Appendix A).
Becaus~1)of the' high degree of local interest, in geothermal
energy and the need to further analyze this potential energy
reso~rce ,a greater effort than might otherwise seem appropriate
was directed to the geothermal alternative in this study.
'1 • 1 APPROACH
While, 10r reasons explained above, the primary energy resource
considered has been coal for cogeneration and district heating,
oil, gas, peat, geothermal, et.al. were also considered.
The cost and desirability of using di,esel powered generation to
produce electricity with W<;l.ste heat captur(1)along with oil-fired
individual stoves for heating (base case) , have been compared
to': '
o Cogen~ration (coal-fired) steam electricalge~Ifation
with hot water district heating (Alternative A) ,
(1) See Appendix A, Section 2 for list of relevant reports.
1-4
u
u
u
u
u
u
I
;~
I
o
I
:W
I
IW
i
W
r 1
LJ
u
u
o
o
o
o
Hot water coal-and oil-fired district heating combined
wi th electricah) generation from other resources.
(Alternative B)
Hydropower generation of elecrtficity with and without
space heating (Alternative C)
Geothermal district heating combined wi the 1) power
generation from other resources (Alternative D)
Windpower generation of electricity to supplement other
generation combined with feasible space heating
I
In the course of t.his study unrealistic technologies have been
eliminated (see Section 6), with the most likely alternatives
(Section 7) being evaluated against the base case. This
procedure ensures that the optimal concepts have been identified
for future study by the Alaska Power Authority.
During the study, emphasis was· put on the benefits likely to
arise from energy conservation measures and increased energy
availability by waste heat recovery.
The specific work tasks covered by the feasibility assessment
included:
o Literature review of previous studies, reports, etc.
(See Volume II, Appendix A).
o Performance of site reconnaissance and data gathering
(Volume I, Section 2 and Volume II, Appendhc<B).
·0
o
o
o
Establishment of an energy balance (Volume I, Section
3) •
Forecast of electrical energy and space heating needs
for Kotzebue to the year 2002 (Volume I, Section 4).
Preparation of Technology Profiles for all appropiiate
concepts (Volume I, Section 5 and Volume II, Appendix
D) •
Evaluation of these technology profiles to provide a
basis for a detailed analysis of those concepts judged
to be reasonably feasible, including geothermal and
hydropower (Volume I, Section 6).
(1) Alternatives referred to in Section 8(Cost Estimate)
and Section 10 (Economic Evaluation).
1-5
o
o
o
Those alternatives determined viable or otherwise noted
for further study in Section 6 have been analyzed in
some detail. They comprise the Diesel Base Case;
Cogeneration; District Heating; Hydropower; Geothermal;
Conservation, and Wind (Volume 1, Section 7 and Volume
II, Appendices C, and E).
The environmental parameters have been assessed and are
discussed in Volume I, Section 9.
'Those plans which were reviewed in detail have been
further analyzed on a systems basis. The overall
matrix provides for a common basis on which to assess
all systems. rl'his analysis is discussed in Volume I,
Section 10, (see also Volume II, Appendices F, G, and
H) •
o To e~sure realistic coal prices were used in the study,
an assessment of the regional and Nenana (Healy) coals
cost was made (Volume II, AppendixJ).
We have recogni,zed the' n'eed throughout the project for close
communications with the' regional corporation, the City leaders
and the Kotzebue people themselves in order to incorporate" as
appLicable, their thoughts, concerns, and desires.
1.2 SUMMARY OF FINDINGS
1.2.1 General
The overall assessments of those energy technologies and fuel
resources which have been judged to be viable alternatives in
this study are summarized in this subsection. To assist the
reader in assimilating the report data, tables and figures from
other sections of the report are repeated, in part, herein.
To better understand the present system being used in Kotzebue,
an energy ,balance was developed, where the input, output and
waste energy were noted. This is represented schematically in
Figure 1. 3.
1-6
u
u
w
u
u
I 1 ~
u
u
u
~
D
U
U
W
o
U
r 1 U
U
U
U
IU i
i
iU
u
~
D
W
~
U
WASTE TOTAL
INPUT 100%
'Propane .2
Fuel #1 45.21(.
He.tlng
Fuel #2 :" 11.1" H •• Un
Fuel #2
.35 .. 4"
8.1"
FIGURE 1.3 , " .
ENERGY BALANCE, ELECTRICAL
AND SPACE HEAT ENERGY
1-7
45.1%
.2
RECOVERED
WASTE
31.ft
51.7%
7.S'lll
80ft
OUTPUT
U
rl 1.2.2 Energy Requirements I.
The energy demand was analyzed (see Figure 1.6) for a 20-year W
period (1982 to 2002). Thereafter, i.e. 2003 to 2037, the use
was considered constant (Figure 1.4) -in other words the same as U
for the year 2002. (1) .
FIGURE 1.4 55 YEAR ENERGY PROJECTION CONCEPT
o 20 years
(1) State of Alaska planning requirement.
1-8
66
w
U
U
') U
U
U
U
U
U
o
U
U
I
JU
I
I
U
U
U
U
U
U
U
l
U
r 1
, '
w
While Figure 1.6 shows the yearly projected energy demands
(annual basis), Figure 1.S shows the percentage of yearly demand ,
(electrical versus space heating) on a monthly ~asis.
FIGURE 1.5
VARIATIONS IN DEMAND FOR HEAT AND ELECTRICITY
FOR KOTZEBUE
BASED ON STATISTICS FOR ELECTRICITY AND HEATING DEGREE DAYS FOR HEAT
" c: ..
E • " :lilt -.. .. • :lilt ... o
lfl
5 9 10
month
1-9
II ,
FIGURE 1.6
TOTAL ENERGY DEMAND, ELECTRICAL AND HEATING
PROJECTION
180
'CI t:,'1 0 .... ....
lie ~ .. .. 360 4Q CD • 1 • =--=--.. • • a. a. .c ::I ;: 80 ....
ID JiI,
40
20
1880 1880
year
1-10
light and
appliances
hot water
I ",........ • •••• , cold water
- -8upply ,
'2000
w
u
w
w
u
u
u
u
,w
[1
~
c.
r 1
LJ
u
r :
U
-
1.2.3 ·Energy Sources
Kotzebue. is presently using fuel oil for its electrical
generation and space heating needs (hereafter referred to as the
"base . case") • In addition to this resource, all other viable
options were considered. Those which were utilized in the
preferred plans (i.e •. systems equal to or more competitive than
the base case, or which (even though not state-of-the-art) still
have potential within the 55-year period of the study, are
briefly discussed below:
o
o
o
o
Fuel oil (base case) Imported petroleum products
which are utilized in KEA I S generators and in
individual homes for space heating. While the resource
is not infinite, as are wind or water,it is still a
viable resource.
Coal -As a fuel, coal was analyzed for use in the
cogeneration and district heating systems (see Figure
1.7) • Alaska has bountiful coal resources of which
. ortlytheNenana,Co'al field near Fairbanks is currently
producing cornme!'rcially. There are a number of coal
resources in or near Kotzebue (see also Figure 1. 2) •
These sources have been analyzed from a cost basis.
While they appear to be competitive cost-wise, and in
some cases cheaper .than Nenana Coal, the overall
economics of the energy producing system seems to be
competitive using either local or Nenana Coal as an
energy source.
Water -Where a high head of water, a large water
source (river, lakes, or storage area), or a
combination of these energy bodies can be obtained,
hydropower can be produced. Normally, this renewable
resource should be able to provide low-cost electrical
energy (including space heating) if in fact a large
enough water source is available.
If one assumes that other factors such as environmental
and social concerns (which also, in varying degrees,
,apply to all energy sources) are not objectionable,
this source is 'usually very competitive with other
resource alternatives. In the Kotzebue area the
Buckland River is the only potential· source with the
required capacity range for providing adequate
hydropower (see Figure 1.8).
Geothermal -There isa possibility. that a geothermal
resource may be available in Kotzebue. Without an
extensive drilling program, however, to prove the
adequacy of this resource it would appear that the
temperatures are not high enough for electrical energy
production but at best might be adequate for a district
heating system.
.1-11
4
/'"
/
/
/LIIIJ.I.IoIIIII
I \
\ )
\/
",'/
~ / -------
1-12
u
U
'" U \ 1 .
I U _/
U
. FIGURE 1.7
u
u
OUTLINE ,OF A
DISTRICT.HEATING U
SCHEME . .
HEAT INPUT FROM:
·1. Power plant
2 •. Boiler station
3., Incinerator
4. Industry·
5. Geothermal energy
6. Sewage systeml
heat pump
7. Solar collector
U
W
i U
J D
I
D , u
I u
u
u
r , u
r :
U
c 1
,U
I
W
D
U
,D
U
FIGURE 1.8 BUCKLAND RIVER -AVAILABLE ENERGY·
180.000
80,000 ....
" ents
heat\n g . requ rements
(mean)
I .. "'" . .... electrical r-------~------~------~requlrements
I
I
800ne8t date hydropower
~-could be on line
(mean)
o-. .... __ .. ______ .. ______ ~------~ .... --~
1982 1992 2002 2012 . :2022 2032
year
1-13
o Wind Another renewable resource available in the
Kotzebue area is wind. Since an ample wind source is
available this resource was closely looked at. Figure
1.9 shows how units could be brought on line
incrementally using wind generators. The problem today
is that large units (adequate to serve the needs of
Kotzebue) are not state-of-the-art but are only
experimental or being used on special trial basis.
1.2.4 Preferred Plans
While numerous energy systems concepts were studied (and are
discussed in varying degrees of detail in this Feasibility
Assessment), only those systems judged viable were· assessed in
depth. vlhile we considered all systems, "KNOvlN-STATE-OF-THE-ART"
plants were given highest ratings because of the necessity for
the systems to operate with a high degree of reliability
considering the climate and remoteness of Kotzebue.
Two plans were considered quite competitive, cost-wise. To
better judge the merits of these plans (cogeneration and
hydropower), we have considered them in comparison to the base
case, i. e. Diesel-generated electrici ty and oil stoves.
Additionally, two separate district heating systems were included
to enable us to better assess the component possibilities in
relation to other fuel sources. Those analyzed were:
Capital Cost
(without int3rest)
$ X 10
Distribution
System Plant System Total
Base case; existing diesel
generation and individual
oil stoves for space heating. 12,748.9 6,394.8
Cogeneration (Alternative A):
electricity is generated and
waste heat is utilized with a
district heating system. 29,225.8 14,577.6
Coal-fired low pressure district
heating (Alternative B). 18,908.3 14,274.2
19,143.7
43,803.4
33,182.5
Hydropower (Alternative C):
provides electricity for
electrical and heating needs. 131,479.5 (1) 49,549.5 181,029.0
Geothermal (Alternative D);
has been analyzed here .as a fuel
for a district heating system. 37,463.5 16,023.2 53,486.7
(l)Includes transmission line costs
1-14
I -: U
w
u
w
u
u
u
r 1
W
u
u
u
w
~
u
u
u
u
u
u
u
u
U
r I , U ' .
I
LJ
r i U
U
~
U
D
U
~
FIGURE 1.9 NUMBERS OF WINDGENERA TORS
.~ .:t= .
~
i
Co)
S II· ..
i
'a
C
i
• 85kW 200kW
1-15
1.2.4.1 Base Case
The Base Case considers continued use of ~xisting diesel electric
generation with oil being used as the fuel source in individual
oil stoves.
Capital costs of diesel generation plant are quite low in
comparison to other systems; consequently units in the same size
range of what exists have been planned to periodically be
installed as the need for additional power is evident (see Figure
1. 10) . Fuel costs are not cheap in comparison to other fuels
thereby making this system of questionable desirability in the
long term.
Like diesel electric generators, oil stoves are relatively
inexpensive, but fuel costs are high.
1.2.4.2 Cogeneration (Alternative A)
This is a system worth pursuing in depth in an area· such as
Kotzebue. This single plant concept (see Figure 1.11) which uses
coal as a fuel, with waste heat recovery being used in district
heating systems, ~has :sigriificant merit.
The only real unknowns (or difficulties) are:
o those of coal handling or mining in the Kotzebue area;
o those of developing a new mine, if other than Healy
coal is used; and
o the difficulties associated with utilizing water as a
heating source in the· distribution system (including
houses) in the arctic.
1.2.4.3 Hydropower (Alternative C)
Hydropower appears to be a cost-effective system for Kotzebue.
u
u
u
u
u
u
u
u
u
u
u
The overall estimate is considered conservative at about $4,400 11
per installed kilowatt. With a transmission line, the overall ~
cost·is about $6,000/installed kW.
Ar~as of major concern in this system are: U
o
o
o
o
unknown environmental concerns
unknown geotechnical (foundation) conditions and
availability of building materials
impacts of a large shallow reservoir on overall system
operations and environmental consequences
long transmission line (approximately 90 miles) from
the Buckland site to Kotzebue is a weakness in the
system from a reliability standpoint.
1-16
u
u
u
D
D
u
u
D
U
I
W
r :
I . W
U
U
o the need to supplement hydropower in later years
with diesel electric or another system during periods
in the winter.
o no ability to expand the system beyond the 30 MW of
planned installed capacity.
Conversely, hydropower:
o is an extremely reliable energy system
o has long life expectancy
o requires relatively little maintenance
o is. usually cost effective, i.e. low cost per kWh
o is a clean source of ~nergy.
1.3 RECOMMENDATIONS
While this" feasibi assessment has covered all feasible
systems and resources, t is not realistic to recommend a single
system because of the many resource questions yet unknown.
Consequently, at least two systems should be further analyzed;
they are:
1) Coal-fired cogeneration, and
2) Hydropower
Both of these systems appear to be feasible long-term
alternatives to the existing diesel electric generation and
individual oil stove heating now being used in Kotzebue.
When the cogeneration system is evaluated using the most cost-
effective coal, it is slightly better in terms of net benefit.
This same evaluation using more expensive coal showed hydropower
to be slightly more advantageous. To ensure the best system is
chosen, we believe it desirable to further evaluate the unknowns
of each system in more detail.
1-17
FIGURE 1.10
BASE CASE DIESEL GENERATION
• i 7~ _____ ------:=':-:.-::-;-;;:-rm1l'l'lTl'll1l1T
I r
E
. : : ... :.: .:.. ...... :: 3800KW
..' . :. ". ., .... ~ Firm Capacity
. year
1-18
w
w
w
u
u
u
U
LJ
U
i '
W
i 1
~
·u
r ' U
u
u
u
u
i l
~
W
LJ
U
w
U
r :
W
U
U
r 1 1-
U
r <
I < ~
u
U
I
,U
,
I
~
U
FIGURE 1.11
SIMIPLIFIED SCH.EMATIC DIAGRAM FOR COGENERATING SYSTEM
.FOR KOTZEBUE
turbine -air \ --:--
I--~ generator H electric . power
, boiler ,
fuel, If-iJ-:--~'i-7 ,r-------~ , ..... 1' ~ I 1----...... 7 condenser
steam-water
heat ~xchanger<
~~
\ space r1 I heating ,
't~, ,
I " .:'-:. "
\
\. process I' \ ~ 7
I heating i\
I
\ \.
\ domestic L7 I hot water ,
1-19
u
, ~l i [ Although the identification of a preferred generating and heating •
system is possible, we suggest, before this is done, that:
o
o
o
o
o
o
Coal resources in the Kotz~bue area (especially Kobuk
and Cape Beaufort ) be drilled and tested to see if in
fact sufficient quantities exist, and to further
evaluate the question of opening a new,~ mine for a
Kotzebue coal source.
Investigations be accomplished in Kotzebue to better
define the district heating system utilidors design
environment.
Studies of the environmental impact of both systems at
Kotzebue, Buckland, and along the transmission route
be done'immediately.
Geological and hydrological studies of the Buckland
site should be done as soon as possible.
Social aspects? of, these systems should be readdressed
ill the near , term.:
Proper scheduling and adequate funding of the work
should be' provided in order to prevent valuable time
being lost because of the Federal Energy Regulatory
Commission (FERC) requirements as they apply to a
hydropower system coming on lihe.
Once these resources and
become more clear and more
made. Properly scheduled
enable the project to meet
City of Kotzebue.
environmental and social questions
definitive, systems decisions can be
and timely accomplished they should
the current and future needs of the
In ~ddition to the electrical energy and heating systems
discussed, thermal and electrical energy conservation should be
vigorously pursued.' These conservation measures are most
effective in overall energy costs to the consumer.
Wind generation can also be utilized to save on nonrenewable fuel
sources such as fuel oil and coal. It can compliment other
renewable resource energy, for example hydropower. A wind
generator test program is now being installed in Kotzebue by the
State of Alaska Department of Commerce and Economic Development,
Division of Energy and Power Development. This program will
~roduce valuable information, on the basis of which a possible
inclusion of wind generators in this final system can be
determined.
1-20
u
w
u
u
u
u
u
u
u
u
w
u
f 1
u
u
r ;
U
u
u
w
u
IW
U
U
U
~
U
NOTE:
Once the technology profiles were completed (1), two
1.4
. basic plans evolved. Since district heating is the
major energy requirement, we further evaluated .two
separate systems (i.e. coal-fired low-pressure .. and
geothermal systems) for district heating. These could
possibly be cost-effectively used with hydropower or
the base case, and are referred to in the text as:
(1)
o
o
o
o
o
Base Case
Alternative A (Cogeneration)
Alternative B (Co~~rfired low pressure
district heating)
Alternative C (Hydropower)
Alte:natt~r D (Geothermal district
heat~ng)
Referred to as Cases 1 through 11 in Vol.
Section 10, and in Vol. II, Appendices G,H,and I.
(2) District heating systems only.
SENSITIVITY ANALYSIS
I,
In order to assist in arriving at a recommendation on a system
for the City of Kotzebue some of the basic assumptions,
contingencies, and coal costs were varied and separate analyses
conducted to determine the effect of such"Ych~:mges on project
costs, benefits, and the benefit~bost ratio. The analyses:
(1) Assumed a 2 percent growth in energy demand beyond the
year 2002 (i.e., beyond the 20-year planning period);
(2) .
(3)
Increased the construction
from 15 to 25 percent
hydropower case); and
Increased coal costs from
BTU.
contingency for cogeneration
(i.e., identical to the
$6.00 to $7.00 per million
Table 1.1 shows the results of these additional analyses in
comparison to the plans as evaluated in this document. A 25
percent increase in contingency for the cogeneration facility has
a small effect on the present worth of costs for that system with
a subsequent small effect on the benefit-cost ratio. An increase
in the coal cost for the cogeneration facility has th~ result of
increasing the present worth of costs for the facility by
approximately $26 million and making the hydropower alternative
more attractive. If the cost of coal delivered to Kotzebue were
1-21
to rise to the estimated price of coal delivered from the Nenana
Field (a~proximately $8.84 per million BTU), the present worth of
project costs would increase to an amount in excess of $340
million with the subsequent effect of reducing the benefit-cost
ratio to a level below 1.20. The assumed 55-year planning period
and a 2' per~ent annual increase' in energy demand result in
increased cost-benefit ratios for both systems. The hydropower
case has improved its standing relative to the cogeneration case
because of the reduced fuel costs inherent in hydropower.
Figure 1.12 illustrates the potential energy demand assuming a 2
percent annual increase in usage beyond'the year 2002 as compared
to the level demand normally'assumed by APA procedures for years
beyond the 20-year planning period. The deficit as shown is
reflective of the hydropower case but a similar situation could
be anticipated for the cogenerative case unless additional
generating capacity is installed.
An additional point to be, noted for the hydropower case is that
if additional generating capacity is required beyond the year
2002, .a new:,!:,;anddJff,erent, ,generating system will need to be
installed.'::{TffeBucklanCl Site cannot expand beyond 30 MW. There
are several implications from having two separate systems: First
the operations and maintenance costs will probably be higher for
two systems than for one system of equal capacity; and, second,
economics of size related to one large system will be negated.
However, as shown in Table 1-1, the fuel savings associated with
hydropower can more than offset these issues.
1-22
w
u
w
u
u
u
u
u
u
u
u
u
u
r :
i\.oJ
u
r •
U
r i
W
( ,
W
u
TABLE 1.1
Sensitivity of Benefit-Cost Ratios
to Various Ass~mptions
($ x 10 )
Present Worth of
Plan Evaluation Costs Benefit
Base Case $402,123 $402,123
" Case 2 (Cogeneration) $272,853 $402,123
Case 11 (Hydropower) $273,899 $402,123
With 25% Contingency for Construction(a)
Case 2 (Cogeneration)
Case 11 (Hydropower)
$274,708
$273,899
$402,123
$402,123
(a,), Case 11 t}"s,ed a"25%'ccntiI').,gency figure in the
j Consequeritly, onlyCase~~is increased here.
With Increased Coal Costs (a)
Case. 2 (Cogeneration) $299,652 $402,123
Case 11 (Hydropower) $273,899 $402,123
(a) Assumed coal costs of $7.00 per million BTU.
Benefit-
Cost Ratio
1. 00
1. 47
1. 47
~1. 46
1. 47
plan evaluation.
1. 34
1. 47
With 55 Year Planning: Period and 2% Growth 2003-2037
Case
Case
(a)
2 (Cogeneration)
11 (Hydropower)
$393,227 (a)
$376,502
$673,057
$673,057
1. 71
1. 79
Includes a coal-fired
be developed to meet
hydropower.
cogeneration facility assumed
power demand not supplied
1-23
to
by
FIGURE 1.12 PROJECTED ENERGY DEMAND AND DEFICIT·
u
u . proJected deficit )
willi 2'110 growlh(1 U
(') o ..
lie
i
1
2007 2017 2027
year
potential· .. (3)
hydro8urplu8
2037
(1) would require additional d&esel electric generator,
district heating system or cogeneration plant to
supplement the number of hydroelectric plants or
base cogeneration system~
(2) assumes constant demand beyond year 2002
(3) potential hydropower surplus excluding line losses
(See also figure 1.8)
1-24.
U
W
u
w
w
r 1
I
u
o
u
I
&
~
L
~
I
I
I
~
L
L
L
~
I
I
I
m
I
I
2.
PUBLIC AND AGENCY INPUT
0
u
u SECTION 2
PUBLIC AND AGENCY INPUT
u TABLE OF CONTENTS
U 2.0 General ................................................ 2-1
U 2.1 Agency Contacts and Comments ........................... 2-1
2.2 Kotz ebue Reconna i ssance •••••••••••••••••••••••••••••••• 2-1
c 1
W 2.3 Other Contacts and Meetings ............................ 2-1
r ' ~J
U
r J
LJ
U
r ' ~
U
U
U
U
W
0
U
o
[J
u
u
[J
U
u
u
u
u
u
u
SECTION 2 PUBLIC AND AGENCY INPUT
2.0 GENERAL
As part of the Feasibility Assessment, public and agency input
was solicited. Appendix B in Volume II of this report includes
all such written comments and, as applicable, responses thereto.
2.1 AGENCY CONTACTS AND CO~~ENTS
(Please see Volume II, Appendix B)
2.2 KOTZEBUE RECONNAISSANCE
Site reconnaissance of Kotzebue was conducted in January and
February 1982.
2.3 OTHER CONTACTS AND H:EETINGS
Meetings with the City Manager of Kotzebue, Kotzebue District
Heat Work Group (KDHHG), Kotzebue Electric Association (KEA) ,
Maniilaq Association, Arctic Lighterage, NANA Corporation, and
local Energy Auditors were very productive. Considerable time
was spent with the KDHWG in discussions focusing on the
transportation of coal from the source to Kotzebue.
Public meetings were held in Kotzebue on January 20 and June 2,
1982. It was obvious that the people of Kotzebue and their
leaders were very interested in the overall Feasibility
Assessment and were hopeful of a result which will benefit their
community by providing more economical electricity and individual
home heating.
2-1
I
I
I
~
~
I
I
~
~
L
~
I
I
I
I
I
m
I
I
3.
ENERGY BALANCE
u
u
u
u
u
u
r 1 • I I.J
u
r '
W
u
u
SECTION 3
ENERGY BALANCE
TABLE OF CONTENTS
3.0 General. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
3.1 Energy Input at Kotzebue •••••••••••••••••••••••• 3-1
3.2 Energy Output at Kotzebue ••••••••••••••••••••••• 3-2
3.3 Energy Usage at Kotzebue •••••••••••••••••••••••• 3-5
LIST OF FIGURES
Figure 3.1 Energy Balance for all Delivered Energy ... 3-3
Figure 3.2 Energy Balance, Electrical and Space
Heat Energy ••..•••.•••••.•••.••.•••••• · •••• 3-4
LIST OF TABLES
Table 3.1 Energy Balance-Kotzbue •••••••••••••••••• ~ •• 3-6
u
,w
U
:W
I
U
[ ,
W
i I
U
U
D
D
D
SECTION 3 ENERGY BALANCE
3.0 GENERAL
An energy balance was developed from a compilation of existing
energy resource and community data. The balance graphically
depicts the energy forms now entering the village and the major
end uses including energy waste. Specific attention has been
directed at end uses such as space heating, water heating,
lighting and appliances, and industrial processes.·
Kotzebue's total energy balance is depicted graphically in
Figures 3.1 and 3.2 and further tabulated in Table 3.1.
Tabulated components of the energy balance follow in Subsections
3.1, 3.2, and 3.3.
3.1 ENERGY INPUT AT KOTZEBUE
/nergy Equivalence
10 10 6 . . % of
Fuel TYEe Gallons Btu/year kltlli/year Total
Propane 8,500 0.786 .230 0.1
Gasoline 400,000 48.('100 14.064 8.3
Gasoline (av iation) 670,000 80.400 23.557 13.8
Kerosene (aviation) 500,000 66.000 . 19.338 11.4
Fuel #1 1,282,000 174.352 51.085 30.0
Fuel #2 (heating) 310,600 43.018 12.604 7.4
Fuel #2 (electric) 987,200 136.722 40.059 23.5
Fuel #2 USAF 225,900 31. 287 9.167 5.5
Total energy input 580.565 170.104 100.0
3-1
3.2 ENERGY OUTPUT AT KOTZEBUE
Electric Energy·
o Lighting
o Appliances
o Space heating
o Street Lighting
OTHER
Space Heating
Hot Water
Heating cold water supply.
Cooking
Ground Transportation
Aviation
U.S~ Air Force (electric energy)
Energy Equivalence
37.046 10.855
13.471 3.9468
17.287 5.0653
6.118 1.7926
.170 .0408
. .;
145.284 42.568
3.759 1.101
3.264 .956
.638 .187
14.400 4.221
29.280· 8.579
9.518 2.787
Total energy directly utilized (subtotal) 243.189 71.254
Total recovered waste energy
o Space heating
o Hot water
o Heating water supply
Total energy output
(subtotal)
3-2
5.580
.148
6.780
12.508
255.697
3.665
74.919
u
U
L
I 1
~
U
U
U
U
" U
u
u
u
u
u
fl
III
,U
i
'W I
U
r : I
~ ...
u
u
u
u
u
WASTE TOTAL 56%
INPUT. 100%
G.lolln.
G •• olln.
Aviation
K.ro.e ....
Aviation
'Propane
Fuel "'1
He.tlnG
Fuel "'2
Heating
Fue. "'~
Electricity
Fuel "'2 USAF
8.3"-
13.8%
11.4"
0.1,
30.0%
7.4%
23.5%
5.5%
25.9% 30.1%
I ! . ~ 5
t
I
2.1%
RECOVERED
WASTE
7.6%:
TRANSPORT
O~1"---",
21 ..
t----34.3%
ELECTRICITY
AND HEATING
OUTPUT TOTAL
44%
rl FIGURE 3.1
I..J ENERGY BALANCE FOR ALL DELIVERED ENERGY
I~
U
U
3-3
WASTE TOTAL
INPUT 100%
I
'I
45.1%
5 ..
Propane O.2%-----..... IliIi..--?--~~ __
Fuel "" 45.2%-------,--.......:::;;.....---1
Heating
Fuel "'2
Heatln 11..1% ========~=====:-:;
35.4%
Fv,el "'2 8 10L USAF • 7Q
I
FIGURE 3.2 I ' " .
ENERGY BALANCE, ELECTRICAL
AND SPACE HEAT ENERGY
r
i
1 ,
I
, ~
3-4
.2
I '
W
I '
i i
1.1
RECOVERED U
WASTE
JIIII-._~~' rr.---..
31 ••
51.7%
8.n
OUTPUT
! 1
U
U
1
J
I 1
W
U
U
U
U
W
U
U
I '
W
U
U
u
w
u
u
C i
u
u
u
u
r :
U
u
-\
W
u
o
3.3 ENERGY USAGE AT KOTZEBUE
Total energy input
Direct energy utilized
Direct waste energy
Recoverable waste energy
Recovered waste energy
Total energy utilized
(direct + recovered waste)
Total waste energy
(direct -recovered waste)
10 9 Btu/year
580.565
243.189
337.736
74.662
12.508
255.697
325.196
3-5
10 6 kWh/year
170.104
71.254
98.850
21.876
3.665
74.919
95.185
%
100.0
41.9
38.1
12.9
2.1
100.0%
44.0
56.0
100.0%
I
I ,
I
W
I
~
PRODUCT INPUTS
(10' BTU)
TOTAL INPUT
(10' BTU)
PROPANE sa ... "o GAL.ls.s'OI uul
GASOLIHE-REGULAR 4OOpoo GAL. ,<spool
A UNLEADED
"83.440)
GASOLINE-AVIA nON ! nO.DOO G .. L. '10.4,,01
KEROSENE-AVIATION
.JET FUEL
FUEL OfL #1
1,282,000 GAL
$00,000 GAL {6e.oOO)
~--------t-------------
R! SIDE NTlAL
U2.0GDG.L.I .... '12)
COwwf~CI.L~INCLOG. APTB.
~.=-2~.~.~O~0~O~G~A!:L:... -'-':..:.e:.!.'~"~I.:..I-+ ___ ~ ________ _
~-,p:-u"'!!.l,...,.,'C"""'.'."N"'C".l"'G-.C::"c:T"'Y--~ ---.1 I 14 .3521. ----
100.000 G"L. 113.eool
HOSPITAL
1-__ ,:..:.:.o:.":.O_G=";;.L:;... _...;Ic,:';:,3;:,e:.., -i ____________ _
~--------------~-----------F.A.A.
".000 GAL. le.'18)
TABLE 3.1
ENERGY BALANCE-KOTZEBUE
pagel of 2
CONVERSION END USE
J10 ... $'OC£ MU 'NO
"0 .... TER
.170'" SPACE ME:,. nNQ
HOT WAlE ..
S'ACE HEATING
COLO/HOT WATE"
,.-----17o"
&PACE HEllTINO
Hot WATE"
END USf .ENERGY
(10 BTU)
~361)
'''11
(3Q j bC58)
'S801
~e)
13~"I/I'OOI
lUI
111
TOTAL END USE
ENERGY(10' BTU)
(1$01
1122.048,
E"O liSE
'PACE HEATiNG t .... 71
HOT WATE" 11501
[
-----rsoo ..... r--~U~'~.~Q~E-~~.~'~T~E~H~E-.. ~T~'~ .. ~.-U~T~T~0~T:-07L~WA'TEHEAT·"-ft~E~C~0~y~£~.~.~B:cL~E~W~.H~.T.~£~C~O~Y~E~M~ED~.~U-N-"-E-C~O~Y~E~"~E~D--W~.H-.~-~~E~·H .. O: .. U .. SE----
1--_ ... u:-T....:lfi'~oe~B~T,U-'-' ___ -j~~~~~ .. I.'O.aTUI 1'00 BTU} 1.~'~O_e~B:.!'f~U~I _____ -....:I---_____ -l
I f.A.A... C2 ......
(10.205) UNRECOVEAE'O
'-====-"",,0'" pueuc (4.0eOI
S'ACE HE'TlNG
----------------~O~ A[SlDENTfAL (28.'''.) uou, SPACE HEATING
HOT WATER
r
(.oJ
I
-..J
PRODUCT
FUI!L OIL .. a
',508,400 QA-L
(;101,111111
INPUTS
(10' BTU)
~----------~'='=".='.~'~"~l--------~----------
~,=c.=.",;;------+ ---------
"'.:8'00 GAL. It,.70 (O&l. t"."n
'\U.IOO, 1--.-=."'.,::-:,,:-, ... .,-------4 -~ " •. ",
" ....
11.10f;I GaL 1'.,sll
MO:r.~IT"'l
1OUiOI> ".LU1."'J
TABLE 3.1 (cont'd)
ENERGY BALANCE-KOTZEBUE
pall_ :I 01 :I
CO .. YERSION END USE
rr======'> I'.n. LJG.',
r.======= .... ~
I I
I I I I I I
'r-=====> 11'.''''
~r .. --.... ~
r====tf."
.f .....
,. ..
...... LI,uU;:I.
,."elf tilf .. TJll:Q
.. ~ .. lJ.t,.CIE.
,".ell:
'Otl.~"""U,"t.«'
l.fG"'"
U4.
...... l.,.I.CIE.
.... ef _(ATIaco
llOHTS
.... ,,1..I.-c. ...
,,,.CI .. IE ... TUIO
LIG.HTI
.... ~I .. IIC(.
.... Ct NtAllaG
'''.CE Id!o\'l"Q
1..l:U w"ta
'''IioC! H{AnNCo
"Of .AT!.a
END USE " .. ERGY
KWH (10' BTUl-'--'-_K_W_H __ --.::.:.;:...::....;;;:,--l .. ,.-,-
----,j-,JOO
lSl.400 -.-107,JIOO
----.".I!"OC!.. 1".'00 ~-
OJ'
U.lU) ,a,., ••• ..... '
un ••
I ... "alta
u.J'aa)
t",IU)
.n.1
(110'
'loa
,.U)
(l.O'I) . ...
ft.. 1)
~)-'!-!~)
UU. -----i,..l
O •• ,U
u •• l
UI ••
.. os,
n~1
0&.,2111,.
-~ltIl
TOTAL END
USE ENERGY
L ... ' ..... .....r .
............ '''.-Y)
•••• 000 ........
... ..,.. .. ......
'.'.000 ........
"',,,"00 .......
UlACll •• ll£ HIAT ' .... n TOT.t.!.. 111 .. 111[ loI'&l alCO.f_.ILl ...... , a,co •• a"o" "'"" •• CO •••• D
[~:
1'''-U",} 1101 '!~L J1~·.TU' .. M:!~'~~~~TVI
.I.a."
(4,5f4)
END USE ENERGY
KWH itO' BTU)
•• '.1"
.... .1110
".JaCi ....
_CO"~ • """'COW'l:"'I:P 'II'.x. t.O UH~~
t,'-STU)
I
I
I
~
~ 4.
I ENERGY DEMAND FORECAST
I
L
L
l
L
I
i
I
I
I
i
I
i
· r 1 I~
!
[j
I r I IU
i
U
U
r 1 I I U
r '
~
u
U
D
~
SECTION 4
ENERGY DEMAND FORECAST
TABLE OF CONTENTS
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
Past Population Trends •••••••••••••••••••••••••••••••
Present Population •••••••••••••••••••••••••••••••••••
Population Projection ••••••••••••••••••••••••••••••••
Present and Future Household Size ••••••••••••••••••••
Light and Appliances ••••• ~ •••••••••••••••••••••••••••
Space Heating ••••••••••••••••••••••••••••••••••••••••
Hot Water ••••••••••••••••••••••••••••••••••••••••••••
Industrial Processes •••••••••••••••••••••••••••••••••
Summary ••••••••••.......••••.•.••••••••••••••••••••••
Figure 4.1
Figure 4.2
Figure 4.3
Figure 4.4
Figure 4.5
Figure 4.6
Figure 4.7
Figure 4.8
Figure 4.9
Table 4.1
Table 4.2
Table 4.3
Table 4.4
Table 4.5
Table 4.6
Table 4.7
Table 4.8
Table 4.9
Table 4.10
Table 4.11
Table 4.12
Table 4.13
LIST OF PIGURES
Projection of Population and Size
of Households ••••••••••••••• · ••••••••••••••••
Light and Appliances: kWh Consumption
per Capita per year •••••••••••••••••••••••••
Light and Appliances: Total kWh
Consumption per year ••••••••••••••••••••••.•••
Floor Area per Capita Projection •••••••••••••••
Total Floor.Area and Space Heat
Demand Projection •••••••••••••••••••••••••••
Space Heating Demand per Year Projection •••••••
Hot Water, Heat Demand per Year Projection •••••
Cold Water Supply, Heat Demand per
Year, Projection ••••••••••••••••••••••••••••
Total Energy r5em'and, Electrical and
Heating Projection ••••••••••••••••••••••••••
LIST OF TABLES
Past Population Trends, Kotzebue 1909-1981 ••••••
Population Projection •••••••••••••••••••••••••••
Breakdown of Electric Power Usage in 1982 •••••••
KEA Power Generation 1968-1981 ••••••••••••••••••
Light and Appliances Forecast •••••••••••••••••••
Calculation of Space Heating Demand, 1981 •••••••
Heat Lost per Sq. Ft., Forecast 2002 ••••••••••••
Total Floor Area, Forecast 2002 (sq.ft.) ••••••••
Space Heating Demand, Low Forecast to 2002 •• ~ •••
Space Heating Demand, High Forecast to 2002 •••••
Consumption of Hot Water, Residential,
Commercial, and Public Use •••••••••••••••••••
Total Hot Water Consumption, Forecast 2002 ••••••
Heat Demand for Heating Hot Water,
Forecast 2002 ••••••••••••••••••••••••••••••••
Table 4.14 Potable Water Consumption and Heat Demand
4-1
4-3
4-3
4-4
4-7
4-13
4-22
4-25
4-27
4-6
4-11
4-12
4-16
4-19
4-21
4-24
4-27
4-28
4-2
4-5
4-7
4-8
.. 4-9
4-14
4-18
4-18
4-20
4-20
4-22
4-23
4-23
for Freeze Protection, Forecast 2002 ••••••••• 4-26
D
u
u
u
r
U
I ~
( 1 I I
~
(
l..J
( ,
I
-.j
: r;
W
I j' U
U
SECTION 4 ENERGY DEMAND FORECAST
4.1 PAST POPULATION TRENDS
Kotzebue's population has grown steadily since the turn of the
century. U.S Census figures for 1909 indicate a total population
of 193. Through the following decades (see Table 4.1) up until
1940 the population increased at a rate of about 2.2% per annum
(p.a.) showing a gradual acceleration toward the end of this
period. During the years of rapid expansion characterizing the
post-World War II period the population doubled twice, increasing
from 372 in 1939 to 1,290 in 1960. Between 1960 and 1980 the
growth rate remained stable at a more moderate 2.3% p.a. The
U. S. Census figure for 1980 shows a total population of 2,054.
Several population estimates undertaken since 1970, however,
consistently indicate a larger population than the Census. Thus,
for example, the Kotzebue Land Use Plan (1976) estimated the 1976
population to be around 2,000, while City of Kotzebue statistics
and figures used by the Alaska State :Revenue Sharing Program
point to 2,431 people in that year. The latter sources indicate
an annual growth rate between 1970 and 1979 of around 4.2% (as
opposed to the 2% p.a. between 1970 and 1980 implied by the
Census figures). In a report for the Alaska Power Authority
ent i tIed "Assessment of Power Generation Al ternati ves for
Kotzebue," Robert W. Retherford Associates estimated the 1979
population to be around 2,500. In the 1981 Kotzebue Land Use Plan
the City Planning Commission accepted the lQ80 population to be
2,544; this figure, in turn, being based on est ima tes by Quadra
Eng ineering in connection wi th the "Water and Sewer Expansion
Study" (1981). In an October 1981 analysis of the various
population estimates, the City of Kotzebue recognized the 1981
population to be 2,847.
4-1
Year
(1) . (2)
1981
1980 2,054
1979 2,526
1978 2,526
.1977 '2,431
1976 2,431
1975 2,125
1974 2,125
1973 2,12~
1972 1,957
1971' 1,875
1970 1,696 1,696
1960 1,290
1950 623
1939 372
1929 291
1920 230
1909 193
Table 4.1
PAST POPULATION TRENDS
KOTZEBUE 1909-1981
Population
( 3 ) ( 4 ) ( 5 )
2,B47
4,293 2,544
( 6 )
@2,500
Source: (1) U.S. Census
(2) Alaska State Revenue Sharing Program
(3) City of Kotzebue, October 1981
(4) Indian Health Service
(5) City of Kotzebue Planning Commission;
Quadra Engineering
(6) Robert W. Retherford Associates
(7) Alaska Consultants, Inc.
4-2
( 7 )
@2,000
D
U
f i
~
w
w
D
U
n
i I ~
u
u
u
u
r 1
I.j
r
W
w
u
u
( :
u
4.2 PRESENT POPULATION
As can be seen, there is considerable disagreement on the size of
the present popu1at ion of Kotzebue. However, among consul tants
and the City alike there seems to b~ general agreement that the
U.S. Census figures are too low.
Short of undertaking a comprehensive survey -which is outside
the scope of this study -there is no way of accurately and
authoritatively determining which figures are correct. The City
·of Kotzebue currently has plans for a survey in the spring of
1982. Meanwhile, as mentioned above, the City Planning Commission
is using the estimate developed by Quadra Engineering (ref.
"Kotzebue Water and Sewer Expansion Study", January 1981), since
this estimate generally is considered to be based on. the most
exhaustive analysis to date. It is therefore proposed that for
the purposes of the present study the same estimate be used.
Thus, the 1980 population is assumed to be 2,544.
4.3 POPULATION PROJECTION
Over the last decade a number of population projections have been
made for Kotzebue. The most recent (and, therefore, more rele-
vant) ones include a 1980 estimate by Quadra Engineering (ref.
"Kotzebue Water and Sewer Expansion Study", 1981) resulting in a
year 2000 population of 4,000. This projection has been accepted
by the City of Kotzebue Planning Commission as being "the best
available." A review by this Consultant confirms this. The pro-
jection, which forecasts the population to the year 2000,
generally continues the level of growth seen in the 160s and 170s
wi th an average annual growth rate of about 2.3 percent. This
projection seems to adequately reflect two likely opposing --and
to a certain extent mutually neutralizing --factors that may
influence Kotzebue I s population growth· in the next 20 years: a
slowing down of migration from outlying villages due to improved
facilities and housing on the one hand, and an increase in
economic activity resulting from accelerating exploration for and
possible development of natural resources in Northwest Alaska, on
the other.
It is therefore proposed that for the purposes of this study, the
energy consumption forecast be based on Quadra Engineering's pro-
jection. Thus, the year 2000 population is expected to be around
4,000, increasing to 4,200 in 2002.
It should be noted that this projection does not allow for the
possibility that petroleum may be discovered in large commercial
quantities so early in the planning period that major development
will occur in time to significantly impact the year 2002
population of Kotzebue.
4-3
If indeed a major oil discovery were made in the Kotzebue region
soon after the scheduled offshore lease sales in 1985, and if the
development;. phase were to start immediately following this, the
population forecast --and thereby also the energy needs forecast
--.should be revised accordingly.
To attempt to develop a likely scenario for the discovery and
development of natural resources in the Kotzebue area at this
time, and to project the resu~tant population increase, is
irrelevant considering the uncertainties involved. It seems
probable that commercial quantities will be discovered in the
reglon. However, it also seems probable that decades could pass
before this happens and development starts, possibly toward the
very end of the planning period.
4.4 PRESENT AND FUTURE HOUSEHOLD SIZE'
In 'order to establish the future number of residential energy
consumers, it is necessary to estimate the number of households.
As was the case for the current total population, there are also
widely divergent opinions on the present number of persons per
household, or per housing unit: 1970 Census data indicate about
4.8 persons per household. The 1980 Census showed 2.9 persons
per household, which is generally thought to be too. low. In the
same year (1980) the Leslie Foundation through the Maniilaq
Association determined the average household size in the City of
Kotzebue to be 4.25, while a survey by Quadra Eng ineering and
CETA indicated 4.88 persons per household.
In order to resolve the apparent conflict and arrive at a
specific figure, Quadra Engineering in the Sewer and Water
Extension Study used the average of 4.25 and 4.88 --i.e. 4.5. A
household size of 4.5, however, is relatively high when compared
to the state average, which according to the 1980 census was 2.5,
and to other. cities of similar size and population composition,
such' as Nome or Barrow where household size estimates indicate
between 3.4 and 4.0 persons per residential unit.
New information provided by two State energy auditors, who
visited 80 homes in Kotzebue during the period November 1981 -
January 1982 indicates about 3.8 persons per residential unit.
Thus, for lack of better information, the 1980 average household
size in Kotzebue is taken to be 4.0.
However, as a result of' declining birth rates and anticipated
construction of additional housing units, the average number of
persons per household is expected to decline gradually at least
until the year 2000.
Based upon a review of regional trends and relevant projections
mad. for other similar-sized communities with a comparable racial
mix, indications are that within the planning period the average
4-4
r 1
~
U
D
U
i I
I i
1.1
u
; 1 U
U
11 ~
U
D
u
u
r "
r
I
W
L
r
LJ
L
U
household size will approach the
purposes of this study, therefore,
overall a'verage household s-i ze wi 11
1980 t? approximately 3.0 in 2002.
current state average. For
it is assumed that Kotzebue's
graduall~ decline from 4.0 in
Thus, based on the projected increase in total population, the
number of households will increase from approximately 636 in 1980
to about 1400 in 2002, corresponding to an annual rate of
increase in residential consumers of around 3.6%.
Table 4.2
Population Projection
NO. OF PERSONS
YEAR POPULATION HOUSEHOLDS PER HOUSEHOLD(l)
1980 2,544 636 4.0
1981 2,625 660 3.9
1985 2,850 760 3.8
1990 3,200 900 3.6
1995 3,600 1,100 3.3
2000 4,000 1,300 3.1
2002 4,200 1,400 3.0
Growth rate of population: 2.3%/year
Growth rate of number of households: 3.6%/year
The projection of population and households can also be seen
in Figure 4.1
(l)Approximate numbers
4-5
FIGURE 4.1
PROJECTION OF POPULATION AND SIZE OF HOUSEHOLDS
5000
1000
4
3
----
1980
~~
fIIIIIII' fIIIIIII"
__ fIIIIIII" --number of
_---households
1990 2000
years
--.-----. --._--
1980
, ._--.-
1990
years
4-6
persons per
household
2000
· )
.J
r ) w
u
U
U
U
r I
W
i 1 ..
u
u
r ,
I I ..
u
u
4.5 LIGHT AND APPLIANCES
Kotzebue Electric Association has provided a breakdown of the
electric power usage in the community. The breakdown was for the
first eleven months of 1981, but for the purposes of this study,
it has been assumed that the percentage division is the same for
the whole year.
Table 4.3
Breakdown of Electric Power Usage in 1981
103 kWh %
Residential homes 2,541 21.2
Small commercial « 50 kVA) 4,012 33.3
Large commercial (> 50 kVA) 3,635 30.2
Public 531 4.4
Street lighting 50 0.4
KEA office and plant use 86 0.7
Total accounted for 10,855 90.1
Total unaccounted for
(line losses etc. ) 1,192 9.9
Total generated 12,047 100.0
Li ne lossesj etc. amount to 1,192 x 10 3 kWh out of a total of
12,047 x 10 kWh equivalent to approximately 10%.
A portion of the homes in Kotzebue have &lectrical water heaters.
The power consumed by these must be subtracted from the total
used by "residential homes" (see Table 4.3) .to arrive at the
power used for "light and appliances" only. Heating of water is
computed as a separate item later.
Since it has not been possible to visit each individu~l household
in Kotzebue in order to determine the occurrence and nature of
its electrical appliances, information gathered by two local
energy auditors as well as data from KEA were used to establish a
reasonable basis for calculating the power consumed by electrical
hot water heaters. The two energy auditors have visited 80 homes
in Kotzebue, of which 20 (25%) had electric water heaters.
Information from KEA indicates that about 10 (15%) of the
consumers have electric water heaters. The figures provided by
KEA seem to be the more realistic, since the information from the
energy auditors may not represent an average cross section of the
homes.
4-7
For the purposes of this assessment, it is therefore assumed that
approximately 15% of all households have water heaters
(corresponding to 100 homes).
If it is assumed that all major hot .water users, i.e. the
hospital, schools, etc., do not use electricity for hot water
heating and that the persons in the homes with electrical water
heaters use more hot water than the average person -estimates
indicate 5 gallons per day per person -then the electrical power
for heating water from 32°F to 132°F is 179,000 kWh/year or 1.5
percent of Kotzebue's total yearly energy consumption.
KEA has also provided the totals of electrical power generated
for the years 1968 through 1981. Using the above estimated
figures, Le. 10% for losses and 1.5% for hot water heating, in
conjunction wi th column 2 and 5 of Table 4.1: Past Populat ion
Trends, the following figures are arrived at:
Table 4.4
KEA Power Generation 1968-1981
Information fron KEA Light and appliances
Total
genefation Peakload load
Factor(3) Total (19 3 per capita
Year 10 kwh kW kWh kWh
1968 3,353 761 0.50 2,967
1969 3,590 784 0.52 3,177
1970 4,180 969 0.49 3,699 2,181
1971 4,797 1,041 0.53 4,245 2,264
1972 5,019 1,008 0.57 4,442 2,270
1973 5,211 1,030 0.58 4,612 2,170
1974 5,711 1,200 0.54 5,054 2,378
1975 6,822 1,400 0.56 6,037 2,841
1976 7,881 1,568 0.57 6,975 2,869
1977 8,979 1,859 0.55 7,946 3,269
1978 10,610 1,948 0.62 9,390 3,717
1979 10,980 2,032 0.62 9,717 3,847
1980 11,154 2,105 0.60 9,871 3,880 (2) 1981 12,047 2,150 0.64 10,676 4,067
(1) Total generation less 11.5% for losses and hot water heating.
(2) 2,625 persons estimated.
(3) The load factor is computed on the basis of the total
generation:
total generation = load factor
365 x 24 xpeak10ad
These figures indicate that during the period 1970-1981, the
annual rise in electrical consumption for "light and appliances"
was approximately 6% per person.
4-8
w
w
u
u
u
u
u
u
u
u
u
u
u
f )
;U
I
U
U
In "Assessment of Power· Generation Alternatives for Kotzebue"
Robert W. Retherford Associates have estimated an annual per-
consumer rise of 3% from 1980 to the year 2000. If the
"consumer" is equal to or proportional to the. "household", this
translates into a per capita rise of 5% per year, based on
previously madae assumptions on household sizes.
It is anticipated, however, that the per capita consumption will
not continue to grow at this rate throughout the whole planning
period. Therefore, growth rates of 5% and 4 % for 1980-1990 and
1990-2002, respectively, were used. By relating these to the
popula tion projection (see Table 4.2) the following per capi ta
and total consumptions were arrived at. The forecast of
electrical energy demand for light and appliances can be seen in
Table 4.5. As there is presently no. (major) electrical
consumption by industry and as there seem to be no immediate
plans for any new significant industrial activities, the forecast
for light and appliances corresponds to the total electrical
energy demand, less what is needed for heat ing of hot water and
what is lost through line losses.
I n the years from 1968 to 1981 the load factor for the power
plant has increased from 0.50 to 0.64 as can be seen in Table
4.4. However, this load factor increase cannot continue in the
planning period, since a likely limit for the load factor is 0.60
-0.65. Therefore, this study assumes a load factor of 0.60 as a
basis for the peakload forecast for the whole planning period.
Table 4.5
Light and Appliances Forecast (1)
Light & appliances, Light & ap~liances, Peak10ad (2 )
Year Eer ca12ita, kWh tot a I, 10k Wh kW
1980 3,880 9,871 2,105 ( 3 )
1981 4,067 10,676 2,150 (3)
1985 4,952 14,113 3,000
1990 6,320 20,224 4,500
1995 7,689 27,680 6,000
2000 9,335 36,420 8,000
2002 10,119 42,500 9,000
(1) Does not include line loss etc., which is approximately 10%
of total generation.
(2) Peak load is computed for a load factor of 0.60 and allows for
a 10% line loss:
light and appliances = Peak load 0.90 x 365 x 24 x 0.60
(3) Information from KEA
4-9
, I
~
r 1 The per. capi ta and tota 1 consumpt ions are shown in Figures 4.2 I.J
and 4.3.
To illustrate the numbers presented in Table 4.5 and Figures 4.2
and 4.3, a comparison can be made to the total electricity
consumption in the greater Anchorage area in 1980. In Anchorag g
total consumption less line losses was approximately 1.90 x 10
kWh~ with an estimated population of 180,000 persons this yields
a per capita consumption of 10,560 kWh/year. This study shows a
projected consumption for Kotzebue in the' year 2002 of 10,119
kWh/year per capit~l) The 1982 Long Term Energy Plan for the
Stat~ of Alaska projects an annual 6 percent rise in
electricity demand per capita in the state as a whole over the
next 20 years. This would' give an annual consumption of 13.890
kwh per capita in the year 2002. Thus, a saturation curve where
per capita consumption approaches a "maximum" value is not seen
wi thin the 20-year planning period. Saturation would be likely
to occyr within a few years after the 20-year period.
(1) State of Alaska: Long Term Energy Plan, 1982 Report
February 1982.
Alaska Electric Power Statistics 1960-1980
Sixth Edition, August 1981.
4-10
u
w
u
! 1
~
u
II
U
U
I
U
U
r 1
W
r "
U
U
r •
U
r '
,
,W
r 1
U
U
FIGURE 4.2
LIGHT AND APPLIANCES kWh CONSUMPTION PER CAPITA PER YEAR
1
i I 8 ..
til • "" .. e • A
I:.
:I:
.:II. 4
'0 ...
o
1970 1980 1990
year
Consumption used as basis for
subsequent section of report
5~
4~
2000
consumption in the event that annual
increase is 5% from 1990
consumption in the event that annual
increase is 6% from 1981
(1) From KEA records
4-11
FIGURE 4.3
LIGHT AND APPLIANCES
TOTAL kWh CONSUMPTION PER YEAR
(0 o ....
a-
ct • '"
80 -...
qg
1:9
"-
RECORDED
(1)
~
~
••
U; ••
••• 4 ••
• • •• • • •
0
1970 1980
FROM, KEA RECORDS
PROJECTED
"-
. -.-.-
• •• ••
•
•• ••
year
4-12
-------• -• • • -• • • • • • • ••
1990
-' ---------
-------
2000
---
r '
w
r ,
W
U
U
U
U
U
U
U
U
W
r 1
u
r I
LJ
, 1
U
u
u
u
u
4.6 SPACE HEATING
The forecast for space heating demand until 2002 is based on a
.theoretical calculation of the actual space heating demand in
1981. The space heating demand for an individual building is a
function of the floor area and the format and height of the
building and the quality and level of insulation.
4.6.1 Site Reconnaissance
During a site reconnaissance, all buildings have been classified
by visual judgement and some buildings were physically measured.
In addition to the visual classification, information provided by
two local energy auditors, who had visited 80 individual homes in
Kotzebue, was used.
4.6.2 Basic Data for Calculations:
From a calculation of a well-insulated one story building with a
floor area of 960 sq.ft., the basic heat loss per square foot was
computed.
Besides this calculation, information from the energy auditors
has been used in figuring out the most correct basic heat loss
per square foot.
Heat loss not only depends upon floor area and insulation, but
also on the shape and form of the individual building; therefore,
a conformation factor, i.e. total surface divided by floor area,
is used.
The various examples are as follows:
Calculation
Energy .Aud i tors
Energy Auditors
Energy Auditors
Energy Auditors
FLOOR
(sq.ft.)
960
1008
864
960
864
CONFOR-
MATION
FACTOR
3.06
3.04
3.11
3.06
3.11
HEAT LOSS
( Btu
h of sq.ft.
0.252
0.198
0.277
0.232
0.280
HEAT LOSS x 3.00
CONFOR-
MATION FACTOR
0.247
0.195
0.267
0.227
0.270
Average 0.241
These figures were based on information derived from homes that
are well-insulated; however, many houses have very poor insula-
tion. Consequently, all houses have been given an insulation
factor rang ing from 1.00 for well insula ted houses to 2.00 for
old houses with poor or no insulation.
4-13
,
~ i
4.6.3 Calculation of heat loss:
Based on the above, the calculations assume a basic heat loss
f 0 Btu .. h . a .24 h 0 f' lncludlng eat loss for ventl-. x F x sq. t.
lation, for a house wi th a conformation factor of 3.00 and an
insulation factor of 1.00.
The floor areas of individual buildings were taken from recent
aerial mapping of Kotzebue, and the total surface was calculated
on the basis of the actual height of the building.
The heat loss was then determined as follows:
floor area x conf. factor x insulation factor x 0.24/3 =
heat loss { BTU
h x of
In Table 4.~\he total heat loss for all buildings in Kotzebue is
summarized. The buildings are roughly divided into five groups:
Res ident ia 1:
FAA:
School & hospital:
Single residential houses.
.All buildings south of the
airport.
Buildings within the two blocks
where the school and hospital
are located.
Public & commercial: Public buildings, offices,
apartment buildings, churches,
stores, etc.
Warehouses:
Calculation of
Warehouses in connection with
commercial buildings, hangars at
the airport, etc.
TABLE 4.6
SEace Heating Demand, 1981
u
u
! 1
~
u
u
u
I 1
W
Floor. area Heat loss Heat loss Heat Demand Floor area-j
BTU x 106 per capi ta U BTU BTU
Group sq.ft. h x of x sq. ft. h x of YEAR sq.ft
Res~dential 476,407· 0.43 ·204,003
fAA 29,680 0.40 11,8900
79,076 181 W 4,609 11
~chool & Hasp. 216,998 0.36 77 ,485 30,035 83
Public & Commerce 253,625 0.36 87,192
Warehouses 93,625 0.35 33,202
33,798 132 U 12,870
TCYI'AL 1,070,335 ·0.385 (l) 413,772 160,388 408 U
(1) average
W
4-14 u
u
r , I . W
I
r 1 ~U I
r 1 U
: 1
U
r '
ILJ
!
r ,
i W
r .
W
The annual demand is based on 16,151 degree days per year in
Kotzebue (Cold Climate Utility Delivery Design Manual).
The total annual space heating demand is a little higher than the
total output ind icated in the energy balance. However, in the
above calculations, heat gain from light, cooking and people is
not taken into consideration.
,
4.6.4 Forecast to the Year 2002
The forecast to the year 2002 is based upon an evaluation of
population, household size, size of residences, and thermal
efficiency of these residences.
It is assumed that towards the latter part of the plan period a
part of the old and small houses will have been replaced by newer
and larger homes and that the floor area per capita in
residential houses therefore will increase. However, it .is also
assumed that as the number of persons per household is
decreasing, there will be a need for smaller homes --mostly for
the young and the elderly.
The result will be a growth in floor area per capita from 181
sq.ft. in 1981 to approximately 240 sq.ft. in 2002, while the
floor area per household will be almost the same in 2002 as in
1981. .
For the school, hospital and commercial buildings, it is assumed
that there will be a very small increase in area per capita.
These assumptions are based on actual home sizes and floor areas
per capita, and also on information about the trends of home
sizes in the northern latitudes in the last ten years.
Figure 4.4 shows the projection of floor area per capita.
4-15
FIGURE 4.4
FLOOR AREA PER CAPITA PROJECTION
26
... ' o o .....
! ca :110 c::r
----------
, ,
fD . .-.-'" ..... ----.--..... -_.
50
---.-
--"--
commercial
& public --
school,
& hospital ----
FAA -----------------------------------------
1980 1990
year
4-16
2000
u.
I 1
W
u
u
• 1
I I
W
r ;
W
, 1
I
~
u
. \
W
W
W
U'
W
W
W
U:
W
u
u
·r '
W
u
u
r 1
~
U I
L
U
f J . I W
u
w
As shown in Table 4.7, the resulting calculated heat loss per sq.
ft. ranges as an average from
Btu 0.43 h x of x sq. ft.
for residential buildings to
Btu 0.35 h x ° F x sq. ft.
for commercial, etc.
A part of th is heat loss can,
houses, be decreased by improved
as well as by replacement of
insulated houses.
espec ia lly in the' res ident ia 1
insulation of existing buildings
old houses wi th new and well-
In order to show the effect of improved insulation of existing
buildings and efficient insulation of new buildings, two fore-
casts for space heating demand have been computed: a low forecast
and a high forecast.
For the low forecast it is assumed that improved insulation of
the existing buildings will be carried out, and that efficient
insulation will be installed in the new buildings.
For the high forecast no improvements of insulation in the
existing buildings have been assumed, and low insulation levels
are anticipated in the new buildings.
The heat loss per sq. ft. used as a basis in the two forecasts is
shown in Table 4.7
4-17
l ..
TABLE 4.7
Heat loss per. sq.ft., Forecast 2002
{ I
BTU W h x of x sq. ft.
Calculation
1981
Low Forecast High forecast W
(1) ( 2 ) (1) ( 2 )
Residential 0.43 0.35 0.30 0.43 0.35
FAA 0.40 0.33 0.30 0.40 0.35
School & Hospital 0.36 0.32 0.30 0.36 0.35
Commercial, ~tc. 0.35 0.33 0.30 0.35 0.35
(1) Value used for area equal to existing buildings in 1981.
(2) Value used for additional new buildings.
The forecast for floor areas of buildings up until 2002 can be
seen in Table 4.8 and and in Figure 4.5.
Year
1981
1985
1990
1995
2000
2002
TABLE 4.8
Total Floor Area, Forecast 2002 (sq. ft.)
Residential
476,407
547,000
659,000
792,000
936,000
1,008,000
FAA
29,680
32,000
35,000
40,000
44,000
46,000
School &
Hospital
216,988
240,000
288,000
330,000
392,000
420,000
Public, Comm.
and Warehouse
347,250
408,000
464,000
526,000
592,000
630,000
Total
1,070,335
1,227,000
1,446,000
1,688,000
1,964,000
2,094,000
The forecast fqr space heating demand for the years until 2002
can be seen in table 4.9 and 4.10 and in Figure 4.6.
4-18
II
U
u
i I
U
r 1
I : ~
u
u
W
U'
~
iD
U
U
U
U
I U
r i
U
f '
I ' \.j
r ,
W
r 1
~
r '
W
r :
U
r .
W
D
FIGURE 4.5
TOTAL FLOOR AREA AND SPACE HEAT DEMAND
PROJECTION
,....
I&.
:t 0 .. " aD .c
U)
0 ...
'""
. .. ....
• cr
(I)
U)
0 ...
2,6
2.0
1.5
1.0
0.5
Mea Space
Proj ,tio~ H t'
H' h P .. ,-..........--ea 19 rOJectlon ~~ •.•••...•• Demand
-'t1 ~ ...... ' ..... Btu .... .; .. ••••••• •••• h OF -.............. x ~.-:;r-Ii ••
.. d •• -~ tI Low Projection
0.0-'------'-----+------1----'""""""----......
1980 1990 2000
years
4-19
Floor
YEAR area
sg·ft.x 106
1981 1.07
1985 1.23
1990 1.45
1995 1.69
2000 1.96 .
2002 2.09
".',
Floor
YEAR area
, 6 sq.ft. x 10
1981 1.07
1985 1.23
1990 1.45
1995 1.69
2000 1.96
2002 2.09
Table 4.9
Space Heating Demand, Low Forecast to 2002
Heat loss Heat loss . Space heat
demand
Btu ~tu x 10 3 Btu x 1()9 kWh x 10 6
h x of x 89.ft. h x of year year
0.39 414 160 47
0.37 454 180 53
0.35 509 200 59
0.34 571 220 64
0.33 641 250 73
0.32 671 260 76
Table 4.10
Space Heating Demand, High Forecast to 2002
Heat loss Heat loss Space heat
demand
Btu Btu x 10 3 Btu x 10 9 Kwh x 106
h x of x 8q.ft. h x of year year
0.39 414 160 47
0.38 471 180 54
0.38 548 210 62
0.37 633 250 72
0.37 730 280 83
0.37 780 300 89
4-20
u
w
u
~
U
U
U
U
U
: :
U
W
W
U
W
U
W·
W
I
IU
11
U
U
! I '
W
r ' iU
r !
W
, ,
I '
W
: .,
I • 1.1
FIGURE 4.6
SPACE HEATING DEMAND PER YEAR PROJECTION
..
CD a;.
:::I ... 150 'ID
t> ....
100
80
..
" :. 80 ..
CD
A
.t::
=--'f:
'b 40 ....
20
1980 1990
year
4-21
2000
4.7 HOT WATER
The hospital and the school are the two largest hot water
consumers in the community today.
u
r 1
I.j
The hosp i tal's total consumpt ion of potable water is 4,200,000
gallons per year, of which, roughly estimated, 35% or 1,470,000 II
gallons are used as -hot water. ~
The school's total consumption of potable
gallons per year, of which, again roughly
R90,000 gallons are used as hot water.
water is 4,450,000
estimated, 20% or
The hospital's and t~e school's hot water consumption is, for the
_purpose of, this study, anticipated to grow proportionally with
the population.
At present many residences have no hot water heaters, and hot
water must be heated on stoves.' That will, of course, limit the
usage of hot water, but gradually the usage of hot water will
increase when more new houses with easy access to hot water are
built.
Therefore, the per capita consumption for residential, commercial
and public use additional to the above two large consumers is
est,imated at 5 gallons per day, compared to approximately 10 -15
gallons per day in a fully developed community with reasonably
inexpensi ve access to energy. Toward the end of this study IS
planning period, the per capita consumption of hot water in
Kotzebue is anticipated to reach this level, i.e. 15 gallons per
day.
Tables 4.11 and 4.12 show the hot water consumption of the above
described three sectors:
YEAR
1981
1985
1990
1995
2000
2002
TABLE 4.11
Consumption of Hot Water,
Residential, Commercial, and Public Use
Gallons per capita Gallons x 10 3
per day per year
5 4,800
6 6,300
8 9,400
11 14,500
14 20,500
15 23,000
4-22
u
, 1 lJ
u
[ \ U
u
u
u
I : ~
f 1
W
I !' •
u
u
w-'
u
U
I
U
iu
u
u
U
I U
, 1
U
, ,
I
W
W
r '
LJ
r 1
W
r 1 ,W
I
I
U
U
D
U
I U
Year
1981
1985
1990
1995
2000
2002
Hospital
Table 4.12
Total Hot Water Consumption
Forecast 2002
Residential, comm.
gal x 103/yr
School
gal x 103/yr
and public
gal x 103/yr
1,500 900 4,800
1,600 1,000 6,300
1,800 1,100 9,400
2,000 1,200 14,500
2,300 1,400 20,500
2,400 1,500 23,000
Total
gal x 103/yr
7,200
8,900
12,300
17,700
24,200
26,900
The total consumption of hot water per year is converted to Rtu
and kWh per year by using a temperature rise of 100°F, i.e. from
32°F to approximately 132°F and not taking into consideration any
conversion losses at all.
The heat demand for heating hot water can then be seen in Table
4.13 and in Figure 4.7
Year
1981
1985
1990
1995
2000
2002
Table 4.13
Heat Demand for Heating Hot Water
Forecast 2002
gal x 103/year Btu x 109/year
7,200 6.0
8,900 7.4
12,300 10.3
17,700 14.8
24,200 20.2
26,900 22.5
4-23
kWh x 106/year
1.8
2.2
3.0
4.3
5.9
6.6
-,p
FIGURE 4.7
HOT WA TER t HEAT DEMAND PER YEAR PROJECTION
~ 15 m
G)
>-
~
G)
0.
:1,10 .. m
C»
0 ,..
6
6
~ m
G)
>-4
~
G)
0-
.c ;:
JttI.
(£10 2 ,..
1980 1990
year
4-24
~
~
f 1
W
f :
W
f
~
U
i ;
~
1 1 !
~
,2000
1 ]
~
U
U
~
U
W
U
U·
W
r I
U
( I U
:u I
r
I
r w
~
( 1
! I ~
c~
W
4.8 INDUSTRIAL PROCESSES
Currently no industrial production is taking place in Kotzebue,
and for the purposes of this study none is expected wi thin the
planni ng per iod (1982-2002). However, some energy is used for
heating the cold water supply to prevent freezing in the supply
lines as well as in storage tanks.
The city has indicated that potable water lea~es the water
treatment plant at a temperature of 40-42°F and returns from the
circulation at a temperatur~ close to 32°F. At the water source,
the water is heated by boilers prior to being pumped to the
treatment plant.
The approximate present total water consumption in the community
is 200,000 gallons per day, but since the water is circulating
and thus losing energy continuously, an exact amount of heat to
be added cannot be determined based on consumption. However, in
1982 the. water treatment plant in Kotzebue used approximately
30,000 gallons of fuel for heating the cold water-supply.
Furthermore, it was estimated that approximately 6,780 million
Btu of waste heat was used to heat the city's potable water.
Assuming that the 30,000 gallonsfiof fuel are c;onverted at 80~
efficiency, a total of 6,780 x 10 + 3,264 x 10 = 10,044 x 10
Btu per year is arrived at.
The present consumption of fresh water corresponds to 76 gallons
per day per person. The "Cold Climate rJtilities Delivery, Design
Manual" (Water Pollutio\n Control Directorate, 1979) recommends a
des ign figure of 120 ga lIons per day per person in "coml)lun i ties
totally serviced by a piped water distribution and sewage
collection system". However, in many northern communities, it is
difficult to get adequate amounts of potable water. Therefore,
when the population is growing, it may be necessary to limit the
consumption of potable water.
For the purpose of this study, it is assumed that the per capita
consumption of potable water wilL remain constant through the
planning period at 76 gallons/capita/day.
In Table 4.14 and in Figure 4.8, the energy demand for heat i ng
cold water supply is shown.
4-25
r
Year
1981
1985
1990
1995
2000 '
2002
':~'ahle LJ. 14
Potable Natel: Consu:r.l.ption and Heat Demand
For Freeze Ptotection
Gal. per
cap/day
76
76
76
7(;)
'76
76
Gallons/
day
200,000
220,00'0
240,000
270,000
300,000
320,000
Forecast. 2002
Totftl Total ~nergy per yea~
gal.xl0 /yr Btu x 10 /yr kWh x 10 /yr
73 10.0 2.9
80 11. 2 3.3
88 12.3 3.6
99 14.0 4.1
110 15.4 4.5
117 16.4 4.8
4.9 SUMMARY
Figure 4.9 shows a summary of the total projected energy demand
for Kotzebue to the year 2002.
The high and low forecasts for space heating demand are based on
the' projection for total floor arf~a and on the high and low
forecasts for heat loss per square foot of floor area. These
forecasts are shown in Tables 4.7 and 4.8.
The forecast for ~ight and appliances is based on the population
forecast shown in Figure 4.1 and an annual 4% increase in
population.
4-2G
u
u
i 1
u
; 1
u
u
r 1 ..
W
r', ' ~.
u
u
u
r 1 I I ..
w
u
r :
U
[" 1
LJ
, ,
u
r '
W
U
U
U
W
D
U
FIGURE 4.8
COLD WATER SUPPLY. HEAT DEMAND PER YEAR PROJECTION
26
20
.. ca 16 • ,.. .. ..
D. .a 10
a:J
b -
6
..!.
.-tfIIIII" "".",--
I....!
-
. .J.
1980 1990 2000
year
4-27
FIGURE 4.9
TOTAL ENERGY DEMAND, ELECTRICAL AND HEATING
PROJECTION
550
500
(II
0 400
"t-
M .. 350 '" • >-.. • 300 a.
::::I ..
CD
250
200
50
180
"t-
M ..
'" • 10 >-.. • a.
.c
~ 80
~
1980 1990
year
4-28
light and
appliances
hot water
I
\&01.-----~ ---cold water
-I -supply
2000
i
W
! • ~
u
u
r1
~
w
U
fl
~
W
r, , I
~
W
I
5
,m
L
~
~
~
~
L
~
~
,~
'~
I
'J
m
I
,I
m
5.
TECHNOLOGY PROFILES
~
" w
U SECTION 5
U TECHNOLOGY PROFILES
w TABLE OF CONTENTS
U 5.0 General .................................................. 5-1
5.1 Electrical Generation .......•...•.•.••.•.••••••••.•... ~5-1
r ' U 5.2 District Heating ........................................ 5-1
f ' 5.3
~ 5.4
Cogeneration ........................................... 5-2
Other Systems and Fuels ................................ 5-3
U 5.5 Technology Profile Details ............................. 5-3
U
U
U
-,-1
\ i
U
U
U
D
U
U
U
u
u
u
u
u
u
u
u
r 1
W
u
u
u
,"i
SECTION 5 TECHNOLOGY PROFILES
5.0 GENERAL
Technology Profiles have been prepared for all known energy
alternatives potentially viable in Kotzebue. These profiles are
oriented toward (1) electr I generation and (2) space heating
utilizing, when practicable, cogeneration techniques. The "pure"
power generation and space heating techno log s are included,
because a combination of two or more of these might be the most
favorable solution to the power and heating needs of Kotzebue.
Each technical or resource profile has been structured so that it
can stand by itself. Each profile,· as applicable, contains a
General Description; Performance Characteristics; costs; Special
Requirements and Impacts; and a Summary. All profiles are, in
turn, evaluated in accordance with the matrix outlined in Section
6. Details of each technology's assets may be found in Volume
I I, Appendix D. .
5.1 ELECTRICAL GENERATION
Technology profiles are provided for the most likely systems
possible for the Kotzebue area. Since diesel electric generation
currently is the power source for· Kotzebue, it will be taken as
the base case; the other electric generation alternativ8s
addressed are:
o
o
o
o
o
o
o
Steam-Electric Generating Units
Cogeneration Systems
Coal Gasification Combined Cycle
Old Fashioned Coal Gasification by the "Kopper Totzek"
l'1ethod
Hydropower --Buckland Site
Wind Turbine Electrical Generators
Geothermal Generation
5.2. DISTRICT HEATING
District heating is a collective heating system, supplying energy
for space heating purposes and water heating in urban
communities. The system is comprised of three elements: a
central heat source, a piping system, dnd consumer equipment.
The idea was born in the United States and has been in commercial
use in many parts of the world since the beginning of this
century. Having fewer fossil fuelS, the Northern European
countries have developed hot water district heating stems and
proved them to be economical, efficient and profitable.
Initially, steam was dist.ributed,
hot water was a more convenient
technical and economical advantages.
5-1
but developments showed that
heat medium, offering many
The original
to achieve
However, an
achieved, as
were replaced
background for establishing the schemes was a wish
greater comfort ,'rather than conserving energy.
important improvement of the environment was
a nunber of small, inadequate, individual stoves
by one single efficient heat spurce.
For exan~le; in Denmark today Dore than 400 schemes serve
approximately 750,000 hones allover the country. Approximately
350 of these schemes are privately owned cooperatives serving
mainly the small towns and villages. Thus, a great part of these
serve less than a few hundred onc-family houses. Also many
communities in Greenland have district heating schemes utilizing
waste heat from power plants.
A district heatl~g network' consists of an insulated, double pipe
system, connecting the individual users with one or more central
heat sClurces. From the heating station, hot water of
approximately 200° to 240°F is sent out through the flow pipe
system. In the consumers' houses the heat content of the ~ater
is released in the heating systeMs, and water of approximately
100° to 120°F returns through the return pipe system for
reheating in the station.
Surplus heat from thermal power plant's (diesel' engines, gas or
steam turbines) of s a big potential for district heating and
is easy to recover at low cost, depending on the system and
installation.
A modern low-temperature, water-based district heating system
offers high flexibility I as almost any fuel, combustible waste
material, or waste heat source may be converted into useful
energy. The w~ste heat or central heat source is usually a heat
only boiler, or an electrical power plant which has been
converted for cogeneration.
5.3 COGENERATION
In cogeneration systems, electrical or mechanical energy and
useful thermal energy are produced simultaneously. Such improved
efficiency systems use a combination of mechanisms to utilize
more of the heat' energy iproduced vlhen, conventional fuels are
burned than is possible'with any existing single system. Using
cogeneration rather' than separate systems to produce heat and
electricity will yield net fuel savings 'of 10 to 30 percent.
Production efficiericy of generating electricity is 22, to 34
percent, and recoverable heat is 43 to 63 percent, permitting
total system efficiency of 65 'percent to 8~ percent in
cogeneration cycles. Cogeneration systems include dual-purpose
power plants I waste heat utilization systems, certain types of
district heating systems, and total energy systems.
5-2
, I
~
u
u
u
u
u
i 1
W
U
u
u
u
u
w
w
r .,
u
u
, I
W
U
U
L
u
u
w
L
I
~
Such systems have been applied since the late 1880's and, in the
United States, have been used much more widely in the past than
they are today. In the early 1900's, most U.S. industrial plants
generated their own electricity and many used the exhaust steam
for industrial processes. Many utility companies supplied
cogenerated steam to large industrial users and densely populated
urban areas. By 1909, an estimated 150 utility companies were
providing district heating. Cogeneration operations in the
United States declined largely because of the availability and
low cost of natural gas heating and of relatively low-cost
reliable supplies of electrical power from large generation
plants located in sites remote from densely populated areas.
5. 4 OTHER SYSTE~1S AND FUELS
To ensure that all
combinations as well
studied.
viable concepts were studied, system
as conserva,tion techniques et. aI., were
Examples of some of these concepts further described in Volume II
are:
o Electrical Energy Conservation
o Thermal Energy Conservation
o Organic Rankine Cycle
o Heat Pump System -District Heating
Fuels analyzed for use included:
0 Diesel
0 Water (Hydro)
0 Gas
0 Coal
0 Peat
0 Wood
0 Geothermal
0 Hind
5.5 TECHNOLOGY PROFILE DETAILS
Volume II, Appendix D of this report covers in detail all
technology profiles further evaluated in Section 6.
Consequently, the reader should familiarize himself with the
details in Appendix D, as they apply to the particular technology
being considered.
5-3
I
I
~
~
~
~
~
~
L
L
~
I
m
I
I
I
I
I
I
6.
EVALUATION OF
TECHNOLOGY PROFILES
I
I
IU
I
U
U
U
U
u
r ' u
U
, ,
I
U
r
I ,
~
r 1 ,
u
U
I~
SECTION 6
EVALUATION OF TECHNOLOGY PROFILES
TABLE OF CONTENTS
6.1 Systematic Evaluation Procedures •••••••••••••••••••••• 6-1
6.2 Results Of The Evaluation •••••••.••••••••••••••••••••• 6-6
6.3 Resource Considerations •.••••••••••••••••••••••••••••• 6-9
LIST OF TABLES
Table 6.1 Technology Profiles Evaluation ••••••••••••••••••• 6-4
D
u
u
r '
r ;
U
o
u
D
SECTION 6 EVALUATION OF TECHNOLOGY PROFILES
6.1 SYSTEMATIC EVALUATION PROCEDURE
Sections 5 and fi were utilized to more clearly def.ine those
energy alternatives which are considered realistic for
Kotzebue. This enabled us to analyze only those alternatives
which had proved to be potentially feasible. Consequently
Sections 7, 8, 9, and 10 only address those alternatives.
6.1.1 Categories
The technology profiles discussed in Section 5 (see also Volume
II, Appendix D), have been sorted into several different
categories, Le.:
A
B
C
D
E
Technologies which mainly aim at producing electric
energy.
Technolog ies which produce both electric energy and
heat energy in significant proportions.
Technologies which mainly aim at· producing heat
energy.
Support systems which would
producing electric energy
consumption.
Support systems which would
producing heat energy by
consumption.
support other systems
by reducing cost or
support other systems
reducing cost or
F Geothermal Energy.
The technologies which have the higher ratings .within each
category are then combined into several al ternat i ve scenarios,
each of which is described in Section 1, and evaluated in
relation to one another and to the base case in Section 10.
(Additi6nally geothermal energy conversion has been included).
6.1.2 Criteria Groups
Each technology will b~ evaluated in three criteria groups, each
of which will be assigned a maximum point number.
6-1
_I
-The total of these maximum point numbers will add up to 100 as
follows:
Group No. Criteria Description
1 Economic criteria
2 Environmental criteria
3 Social criteria
4 Penalty for major flaws
Max Points
45
25
30
100
-50
Group 4 enables a penalty to be awarded that-does not adequately
show up in the point system, for instance where the appropriate
energy resource is not available. This technique is helpful
since it is impossible to design a systematic evaluation
methodology which will register all, sometimes conflicting and
subjective, points of view.
The criteria groups are fUrther subdivided as follows:
Group High Points for:
1. Economic criteria (45)
2.
1.1 Low capital cost
1.1 Low energy cost
Environmental criteria (25)
2.1
2.2
2.3
2.4
2.5
Low air quality impact
Low water quality impact
Low floral/faunal impact
Low land use impact
Low aesthetics impact
3. Social criteria (30)
3.1 High level of community acceptance
3.2 High level of local employment
3.3 Low operating technology level,
high safety level
3.4'o High reliability
Point Range
0-15
0-30
0-5
0-5
0-5
0-5
0-5
0-10
0-10
0-5
0-5
The points awarded on each technology are tabulated in Table 6.1.
The basis for the assignment of rating points is shown below:
Price level as of January 1, 1982
Power capacity : 5,000 kW
Heating capacity: 12,500 kW (42 x 10 6 Btu/h)
Landed cost in Kotzebue:
10,000 Btu/lb coal-- - - - -SIOO per ton
No.1 fuel oil-- - - - - - -SI.50 per gallon
6-2
u
u
i 1
I.!
r l
I.J
i 1
U
U
r I
~
D
U
u
u
u
i U
:W
I
r ' U
U
D
6.1. 3 Economic Criteria
Points for economic criteria have
the following scales:
(1) Capital Cost
$ per kW points $ per kW
>6,000 0 4,500
5,700 1 4,200
5,400 . 2 3,900
5,100 3 3,600
4,800 4 3,300
(2) Energy Cost
(a) Power
$ per kWh points $ per kWh
> 0.35 0 0.25
0.33 2 0.23
0.31 4 0.21
0.29 6 0.19
0.27 8 0.17
(b) Heat
$ per $ per
mil. Btu points mil. Btu
> 40 a 30
38 2 28
36 4 26
34 6 24
32 8 22
6-3
been awarded in accordance with
Eoints $ Eer kW points
5 3,000 10
6 2,700 11
7 2,400 12
8 2,100 13
9 1,800 14
< 1,500 15
points $ per kWh points
10 0.15 20
12 0.13 22
14 0.11 24
16 0.09 26
18 0.07 28
<0.05 30
$ per
Eoints mil. Btu 20ints
10 20 ••••• 20
12 18 ••••• 22
14 16 ••••• 24
16 14 ••••• 26
18 12 ••••• 28
<10 ••••• 30
TABLE 6.1 TECHNOLOGY PROFILES EVALUATIONS
CATEGORY
TECH.'iOLOGY PROFILE :10 •
TECH?'OLOGY
RESO[;RCE
CAPITAL COST S/K ....
COST OF ENERGY SlK .... h
S/~cu
CRITERIA (MAX RATI~G)
Grou? HIGH RATI::O<G fOR: Rating Ran~e
1 ECO:m~IC (45)
1.1 LOW CAP [TAl. COST 0-15
1.2 LO\.; E:IERGY COST 0-30
SI,;BTOTAL
2 IT (2S)
2.1 LOW A~~ QUAL rTY I!-'PACT o-S
2.2 LOW WATER OUAL. I~fPACT o-S
2.3 LOloi FLORAL/FAnAt I'rPACT o-S
2 ~ LO\.; LASD USE r~PACT 0-5 2 , LOW rtr.;>,n, .. H." I~'!'AC, o -5
St:BTOTAL
3 SOCnL CRlTBU (20)
].1 HIGH CO~~rIYACCEPT.~'CE 0-10
3.2 HIGH LOCAL E!-'PLO'::-fE::T O-LO
3.) LOW OPSRATr~G TcCH~OLOGY
LEVEL, HIGH SAFETY O-S
3.4 HIGH RELL.l.JHLIl.l O-S
SLIHOTAL
PRELL'!I:;')"R': TOTAL
4 J:E:-IAL TY FOR :-~UOR f:..W -10 co -50
~An;RE OF FLAW
FI~AL RATI:>G
A S
-----
ELECTR rCAL POWER ELECTR. POI."E~ + SPACE HEA TI:;G
5.1 5.2 5.16 5.9 5.4 5.) 5.9
! DIESEL II.P. STEA..'1 ORGA.'HC i1YDROPOI.'ER OAL GASIFI-H.P. STEA..'! HYDROPOI."ER
ELECTRIC ELECTR IC RANKI~E ;,'ITHOLJT CATION. BACKP!tES SURE INCL. EL ECTR.,
BASE CASE (CONDENSATION CYCLE GEN. ELECTR-REAT COMB. CYCLE CO-GP.:ERATICN HEATING
n;REI:-.:q or I DIESEL OIL COAL (COKE). PEAT "ATER COAL COAL, PEAT WATER
WOOD REf11SE 1.'000, REruSE
1250-1600 3.300 3.650 6,000
I
15,000-20,000 ],800 6,000
0.15-0.22 0.18 -0.24 0.25-0,)1 0.35 0.55 0.02-0.12 0.30
see note S ; 16-18 88 . see note 5
15 9 8 0 0 7 0
17 14 8 0 0 25 a
32 2J t6 0 a 32 0 i
) 2 ) 5 2 2. 5
4 2 ) 2 1 2 2
4 2 ) I 2 2 1
4 ) ) 2 2 3 2
3 3 3 3 1 3 3
18 12 15 B
5 1 5 10 see noce ) 1. 1 10
3 10 7 0 see note 4 10 10 0
4 I 2
4 3 ) 5 3 )
16 lS 17 W tf: 15 lS
66 50 48 59 28
-20 -25 -40 see note 7 -25 -25
High tech High tech Imported High tech ~ot fully level level
fuel level develop ed
~& 25 8 33 -) )4 28
Electrical energy conservation can take so many forms, that it is not practical to
evaluate all the different possibilities.
Note 2
Individual heat pumps are unlikely to prove of interest under the soil and air
temperatures prevailing in Kotzebue. No attempt has been made to evaluate this
technology here.
Note 3
The ratings for community acceptance are based on impressions from the first site
visit and comments received during the public review period of the draft Final
Report.
5.1
INDIVIDUAL
OIL STOVES
BASE CASE
?UEL OIL 1
700
15
17
32
2
2
2
)
J
12
17
61
-20
Imported
fuel
41
C o E F
SUPPORT ::;YS7E~!S SPECIAL INTEREST SPACE HEATI~G suP!'on SYSTEMS -SPACE HEATING EL ECTRLCAl t'o\., ER
.).1.\
INDIVIDUAL
SOLID FUEL
FUR..'ACES
COAL, ,,'000
"' .... T
700
23
15
17
32
1
3
)
)
)
13
5
7
5
5
22
&7
-20
In<::on-
venience
47
:l.6 5.5 5.10 5.1 5.6 a 5.6 b 5.7 5.15
LOW PRJ::SSlJ'"RE KOPPERS-TOTZEK WIND ELECTRICAL PASSIVE ACTIVE INDIVIDUAL THER..'1AL
D[STRICT COAL GASI-IGE~ERA TIO:-; E)lERGY SOLAR SOL-I.R HEAT ENERGY
HEATING FICATIO~ CO~Sd\,ATLO'; PUMPS CONSERVATION
I
I I I COAL, 1.1000 COAL IHND NONE SUN SL" + GEO. AIR >.'ONE
PEAT REFUSE I I EL. POWER + EL. POWER
500-2000 5,000
I
1500-3200 Variabl~ 1850 5500 See note 2 275-3300
0.05-0.09 See note 1
12-20 32 23 70 2.5-22
I
IS ] 12 14 2 15
24 8 28 17 0 30
39 8 40 31 2 45
------
4
2
2
3
4
15
<}
8
5
4
26
80
80
2 5 5 5 5
1 5 5 5 5
~ 5 5 5 5
7 4 4 4 5 r I 4 4 5
.-
8 20 23 23 25
9 7 () 2 10
9 2 6 I 7
2 5 5 ) 5
J :3 5 ) 5
23 17 25 9 27
42 77 75 34 97
-25 -30 -30 -30
Sot fully daily handl. resources
High techn:-developed of external lacking
---~---"h !ttF'~"
17 47 45 4 97
Note 4
The ratings for level of local employment are based on the assumption that coal
will ultimately be produced from !!local" coal resources.
The Hydropower Alternative is included in Section 7 and re-evaluated economically
under Section 8. This is being done to ensure the cost of the Retherford preferred
plan in their "Assessment of Power Generation Alternatives for Kotzebue" of June 1980
has been evaluated on a similar overall cost basis to the other alternatives.
Evaluated because of the potential resource in the Kotzebue area.
Systems in range needed at Kotzebue are not commercially available.
6-4
SYSTEM
5.17
GEOTHER.."'.AL
DISTRICT
HEATING
GEOTIlERMAL
+ EL POWER
See l"ote 6
D
u
u
u
u
u
u
6.1.4 Environmental Evaluation
Environmental factors were divided into 5 categories for
evaluation: air quality, water quality, floral/faunal resources,
land use and aesthetic considerations. Each was rated from 0-5,
with 5 and 4 indicating little or no impact, 3 and 2 indicating
moderate impact and 1 and a indicating most adverse impact.
It was assumed that mitigating measures would be used wherever
possible~ actual impacts would be expected to be more severe than
ratings indicate if mitigations are not adopted~ The evaluations
were quite subjective. Each category was evaluated for several
factors, and not all were necessarily of equal weight, but all
were taken into account to some extent where data were available.
Factors considered in each category are given below.
Air quality considerations. Types of air pollutants and their
effects ~ expected volumes and duration of emissions ~ concentra-
tions, odors; location of the emission in relation to the
population.
Water qual i ty considerations. Types and volume of pollutants
expected; volume and water qual i ty parameters affected; type of
water (surface or maririe) and water use (wildlife habitat,
recreational, drinking water, etc.)impacted.
Floral/faunal considerations·. Type of organism(s) affected; size
of habitat affected: value of organisms (sport or commercial
value to man, or importance in ecosystem); legal constraints
(protected, threatened or endangered species).
Land use considerations. Size of area impacted;, effect of the
facility on adjacent areaS1 conflicting uses; consistency with
existing land use.
Aesthetic considerations. Visual> impact of construction or of
emissions/effluents: noise: glare: "presence" or change of
existing atmosphere.
6-5
6.2 RESULTS OF THE EVALUATION
The results of the evaluation as shown in Table 6.1 are:
i 1
6.2.1 Category A: Electrical Power
Technology Prelim.
No. DescriEtion Rating
Penalty Final
Rating
Final
Ranking U
5. 1 Diesel Electric (Base Case) 66 -.20 46
5. 2 High Pressure Condensation
Steam Turbine' 50 -25 25
5.16 . Organic Rankine Cycle
Generation 48 -50 -2
5. 9 Hydropower without
'E;lectrical Space
~eating 33 33
Diesel Electric (Base Case)
The Diesel Electric technology has a penalty of -20 points due to
the necessity to import fuel from outside the district.
Nevertheless, as the base case the technology will be subject to
more detailed description and evaluation in Sections 7 through
10 •.
High Pressure Condensation Steam Turbine
This technology haS a penalty of -25 points due to its high
technology level,' which would necessitate the hiring or training
of licensed boiler operators.' It earns· a final rating of 25
points.
The technology is not included in any future scenarios, since it
is inferior to backpressure steam co-generation by virtue of the
latter making use of waste heat. Technology 5.3, therefore, is
preferred.
Organic Rankine Cycle Generation
This technology has a penalty of -50 points because it is not
fully developed and proven in the capacity range required,
resulting in a final rating of -2. It will therefore not be
included in any scenarios for further evaluation.
Hydroelectric Power without Electric Space Heating
This technology has a final rating of 33 points. In accordance
wi th the wishes of the Alaska Power Authority, the technology
will, together with hydropower with electric space heating, be
dealt with in some more detail in Section 7.0.
6-6
1
3 U
4
U
2
W
i 1 ~
U
U
U
W
0
W
W
W
U
W
U
,
u
u
:U
I
:u
I
IU
I
U
I
U
D
D
6.2.2 Category B: Electrical Power and Space Heating
Technol09Y Prel im. Penalty Final Final
No. Description Ratin9 Rating Ranking
5. 4 Coal Gasification,
Combined Cycle 22 -25 -3
5. 3 Backpressure Steam
Co-generation 59 -25 34
5. 9 Hydropower with
Electrical Space
Heating 28 28
Coal Gasification, Combined Cycle
This technology has a penal ty of -25 due to its high level of
technology. (Consequently, the technology is not included in any
scenario for further investigation.)
Backpressure Steam Co-generation
with a preliminary rating of 59 points this technology ends up
with a final rating of 34 points. The technology will be
included in Alternative "A" for further in~estigation.
Hydropower with Electrical Space Heating
This technology has a final rating of 28 points. As explained
previously this technology will be examined in more detail in
Section 7.
6.2.3 Category C: Space Heating
3
1
2
Technol09Y no.
No. Description
Prelim.
Rating
Penalty Final
Ratin9
Final
Ranking
5. 1 Individual Oil Stoves
5.13 Individual Solid -uel
Fuel Furnaces
5. 8 Low Pressure District
Heating
5. 5 Koppers-Totzek Coal
Gasification
Individual Oil Stoves
61
67
AO
42
-20 41
-20 47
80
-25 17
This base case technology presently in use earns a penalty of -20
points owing to its dependence on fuel oil imported from outside
the district. This technology is the base case for heating and
is therefore the basis for measuring other alternatives for space
heating in Sections 7 through 10.
6-7
3
2
1
4
Individual Solid Fuel Furnaces
This technology has a penalty of -20 points" because of the
inconvenience involved to the home owner compared to District
Heating systems, gIvIng a final rating of, 47 points. (The
technology is not included in any alternative scenario, since the
final rating is considerably lower than·· that of other
technologies.)
Low Pressure District Heating
This technology has a final rating of 80 points,
in Section 7 for further investigation. (In
technology is used to supplement the space
obtained from backpressure steam co-generation.
is also to be considered as the sole means of
heating energy.)
Koppers-Totzek Coal Gasification
and is included
Section 7 the
heating energy
This technology
prov id i ng space
This technology has a penalty of -25 points for a high technology
level. The technology is not included in any scenario for
further investigation.
6.2.4 Category D: Support Systems Producing or Saving
Electrical Power
Wind Generation
This technology earns a preliminary rating of 77, but this is
reduced by a penalty of -30 because the newer machines are not
sufficiently tested in Alaska. The technology is investigated
further in Section 7.
Electrical Energy Conservation
The technology is dealt with again in Section 7, since
conservation should always be considered and practiced.
6.2.5 Category E. Support Systems Producing Savings in Space
Heating Needs.
Techno10~:l Prelim. Penalty Final Final
No. Description Rating Rating Ranking
5.6a Passive solar 75 -30 45 2
5.6b Active solar 34 -30 4· 3
5.15 Thermal energy
Conservation 97 97 1
Passive Solar
This technology "has a penalty of -30 points, because its main
benefit hinges on the use of external shutters, which is believed
to be a limitation on its practical use.
6-8
: 1 ~
: 1 ~
i 1
U
u
u
u
u
u
u
u
w
u
u
u
u
u
u
u
u
u
u
u
u
u
u
I~
I~
Active Solar.
This technology carries a penalty of -30
insufficient resources. The technology is not
alternative for further investigation.
Individual Heat Pumps
points due to
inc luded in any
Individual heat pumps are unlikely to prove of interest under the
soil and air temperatures prevailing in Kotzebue. No attempt has
been made to evaluate this technology here.
Thermal Energy Conservation
This technology has a final rating of 97, and is investigated
further in alternative "E".
6.3 Resource Considerations.
A number of technologies (nos. 5.2, 5.3, 5.8, 5.13, and 5.16) can
function with a variety of solid fuels.
Resource investigation and determination have not been a part of
this feasibility assessment; consequently, assumptions had to be
made. Nevertheless, when proceeding to the in-depth
investigation of the reduced number of alternatives it is
sometimes necessary to focus on a particular type of solid fuel
to be used. This has been done as a matter of overall, but
unspecific, analysis.
The following are the solid fuels alternatives considered which
might be available to Kotzebue from within the region or state.
Coal, Cape Beaufort
Coal, Kobuk River
Coal, Chicago Creek
Coal, Nenana
Wood
Peat
Refuse
Coal sources within the Nana Region are:
Kallarichuk River, 90 miles upstream from Kiana on
the Kobuk River.
Chicago Creek on the Kugruk River 15 miles West of
Candle.
The Kallarichuk coals have a heating value of about 10,500 Btu/lb
(as rece i ved ) • The Chicago Creek coals have a heating va lue of
6,000 -6,500 Btu/lb (as received).
6-9
It is known that there are considerable resources of wood in the (1
Kobuk and Noatak River catchments. These resources can be ~
floated down the rivers to Kotzebue.
The cutting of wood fuel in the quantities required for Kotzebue U
would have a certain environmental impact in the region. Wood
fuel is therefore considered a second choice, which could be
investigated as a resource if local coal sources. fail to prove U
viable.
Peat around Kotzebue is in a class A2 area.
defined as having:
This class is
High ratio of area covered by organic soil
u
Medium probability that the organic soil meets DOE ~
fuel peat requirements.
Reference: Peat Resource Estimation in Alaska. U
U.S. Dept. of Energy
Division of Fossil Energy
The following two factors contribute to making peat a poor choice ( 1
as a main solid fuel for Kotzebue: the shortness of the summer ~
during which time the peat must be harvested and air dried (if
produced as milled peat or sod pe~t),and the environmental impact r 1
of peat production. W
Refuse at present is an environmental nuisance.
which alternative will eventually be the
consideration should be given to supplementing
the main energy source with heat derived from
refuse in a boiler suited for tnat purpose.
6-10
Depend ing upon
preferred one,
the energy from
the burning of
; I
W
I I J
11 U
{ I
I
~
~
7. ~ DESCRIPTION OF
~ AL TERNA TIVE PLANS
& ,
~
L
~
~
i
I
I
I
~
~
I
~
u
u
u
u
u
f '
!
I -u
i .
U
u
u
u
u
7.0
7.1
7.2
7.3
7.4
7.5
SECTION 7
DESCRIPTION OF ALTERNATIVE PLANS
TABLE OF CONTENTS
General •••••••••••••••••••••••••••••••••••• " ••• 7-1
Base Case Plan •••••••••••••••••••••••••••••••• 7-1
.1 Introduction ••••••••••••••••••••••••••••• 7-l
.2 Base Case Electrical Generation •••••••••• 7-2
.3 Base Case Waste Heat Recovery •••••••••••• 7-2
.4 Fuel Consumption ••••••••••••••••••••••••• 7-4
Cogeneration (Alternative "A") •••••••••••••••• 7-8
.1 Introduction ••••••••••••••••••••••••••••• 7-8
.2 Alternative "A" Development •••••••••••••• 7-8
• 3 80 i 1 e r. • • . • • •. . . • • • • • • • • • • • . . • • • • • •.• • • • • • 7 -11
.4 Turbine Generator ••••••••••••••••••••••• 7-13
.5 Fuel •••••••••••••••••••••••••••••••••••• 7-13
Coal-fired Low-pressure District Heating
System (Alternative "8") ••••••••••••••••••••• 7-18
• 1 Ge n era 1 • • • • • • • • • • • • • • • • • • • •••••••••••••• 7 -18
.2 Coal-fired District Heating Station ••••• 7-20
.3 Water-Antifreeze Transmission Line •••••• 7-25
.4 Distribution Network •••••••••••••••••••• 7-25
.5 Consumer Installations •••••••••••••••••• 7-29
Hydropower -Buckland (Alternative "C") •••••• 7-30
.1 General ••••••••••••••••••••••••••••••••• 7-30
.2 Potential Sites ••••••••••••••••••.•••••• 7-32
.3 Buckland River ••••••••••••••••••••••.••• 7-33
.4 Hydrology ••••••••••••••••••••••••••.•••• 7-37
.5 Geology ••••••••••••••••••••••••••••••••• 7-42
.6 Transmission Facilities ••.••••••••.••••• 7-42
.7 Cost Estimates •••••••••••••••••••••••••• 7-42
.8 Power Production •••••••••••••••••••••••• 7-42
.9 Environmental and Other Concerns •••••••• 7-43
.10 Land Status •••••••••••••••.•••••••••••• '.7-43
.11 Alternative Development Plan •••••••••••• 7,-43
.12 Utilization of Electric Heat •••••••••••• 7-44
Geothermal (Alternative "D I1
) ••••••••••••••••• 7-44
.1 Description of the Potential
Geothermal Resource •••••••••••••••••• 7-44
u
u
u
u
r i
W
u
( I U
j :
W
r ! U
i '
I I
~
u
7.6
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
.2 Geologic Setting •••••••••••••••••••••••• 7-45
.3 Geothermal Resource ••••••••••••••••••••• 7-50
.4 Geothermal Exploration Program ••••••••• ~7-5l
.5 Geothermal District Heating ••••••••••••• 7-5l
.6 Geothermal Power Plant
Organic Rankine Cycle) •••••••••••••••••• 7-55
Other (Alternative "E") •••••••••••••••••••••• 7-60
.1 Energy Conservation ••••••••••••••••••••• 7-60
.2 Electrical Conservation ••••••••••••••••• 7~70
.3 Wind Energy ••••••••••••••••••••••••••••• 7-77
7.1.1
7.1. 2
7.1.3
7.1.4
7 .2.1
7.2.2
7.2.3
7.2.4
7.2.5
7.2.6
7.3.1
7.3.2
7.3.3
7.3.4
7.3.5
7.4.1
7.4.2
7.4.3
7.5.1
7.5.2
7.5.3
7.5.4
7.5.5
7.6.1
7.6.2
7.6.3
LIST OF FIGURES
Base Case Diesel G~neration ••••••••••• 7-3
Projected Total Heat Demand ••••••••••• 7-5
Possible Heat Recovery from
Diesel Generator ••••••••••••••••••• 7-6
Diesel Fuel Consumption Electric
Generation (Base Case) ••••••••••••• 7-7
Schematic Design for
Cogeneration System ••••••••••••••• 7-9
Alternative A. Steam Turbine
Generation •••••••••••••••••••••••• 7-10
Total Heat Demand •••••••••••••••••••• 7-12
Coal Fired Cogeneration
Alternative B ••••••••••••••••••••• 7-l5
Oil Fired Cogeneration ••••••••••••• 7-16
Variation in Demand for
Heat and Electricity •••••••••••••• 7-l7
Arrangement, Plan •••••••••••••••••••• 7-23
Arrangement, Elevation ••••••••••••••• 7-24
Load Basis for District
Heating System •••••••••••••••••••• 7-26
Layout for District Network •••••••••• 7-27
Cross Section •••••••••••••••••••••••• 7-28
Small Hydro-Arctic Conditions •••••••• 7-34
Buckland River Hydroelectric
Potential ••••••••••••••••••••••••• 7-35
Buckland River Area
Capacity Curve •••••••••••••••••••• 7-41
Location Map ••••••••••••••••••••••••• 7-46
Structural Cross Section ••••••••••••• 7-48
Nimiuk Pt. No.1 Test Well Log ••••••• 7-49
Schematic Geothermal District
Heating Concept ••••••••••••••••••• 7-53
Schematic Geothermal Power Concept ••• 7-57
Present Value for Wall
Construction and Heating •••••••••• 7-62
Present Value for Floor
Construction and Heating •••••••••• 7-63
Present Value for Roof
Construction and Heating •••••••••• 7-64
u
u
u
r 1 W
u
i 1
'U
u
r :
W
L.J
u
W
D
D
Figure
Figure
Figure
Figure
Figure
Table
Table
Table
Table
Table
Table
Table
7.6.4
7.6.5
7.6.6
7.6.7
7.6.8
7.4.1
7.4.2
7.4.3
7.6.1
7.6.2
7.6.3
7.6.4
Construction Costs Per Unit
Wall, Roof and Floor •••••••••••••• 7-65
Yearly Consumption of Heating
Oil per Square Foot of
Walls, Roofs, and Floors •••••••••• 7-66
Light and Appliances kWh/Year
with Electrical Conservation •••••• 7-76
Possible Wind System
Configurations •••••••••••••••••••• 7-78
Number of Wind Generators
On Line ••..••....•..•••....••..••• 7-79
LIST OF TABLES
Kobuk River at Ambler Flow in CFS ••••• 7-38
Kobuk to Buckland Synthetic
Flow Record •••••••••••••••••••••••• 7-39
Buckland River Acre Feet x 1000 ••••••• 7-40
Usage with Electrical Conservation •••• 7-73
Energy Reduction Due to .
Electrical Conservation ••••••••••• 7-75
Power Produced by Turbine Diameter •••• 7-81
Annual Power Production by
Wind Generators .................... 7-82
J
U
U
u
I I
1.1
u
f 1
: !
W
f 1 U
D
D
SECTION 7 DESCRIPTION OF ALTERNATIVE PLANS
7.0 GENERAL
A base case plan has been developed to represent a continuation
of present diesel generation of electrici ty and space heating
practices.
All alternative plans will be evaluated to meet the same heat and
electrical energy demand forecast, based on:
1. Specific requests by APA to further look into the feasi-
bility of the geothermal resource with a description of
alternative plans for use of such a resource: and
2. The need to re-evaluate hydropower schemes (done by
others) based on the same energy forecast and cost
analysis as are all other alternative plans.
The base case plan will be used as standard of reference for the
other alternative plans: i.e.:
Alternative(l) "A" (Cogeneration);
Alternative(l) "B" (Coal-fired Low Pressure District Heat);
Alternative(l) "C" (Hydropower -Buckland Site):
Alternative(l) "D" (Geothermal); and
Alternative(!) "E" (Others, e.g. conservation, insulation,
wind etc.).
7.1 BASE CASE PLAN
7.1.1 Introduction
The base case plan is a continuation of the present scheme of
providing electricity to the City of Kotzebue u~ing diesel
generators. In addition to the electricity provided by diesel
generators, the waste heat from these generators is partially
recovered. Currently this waste heat is, for the purpose of this
report, considered industrial process heat and is used to heat
the city water system and the Kotzebue Electric Association
offices. Under this base case scenario it is assumed that this
will continue to be the case.
The electrical energy demand in 2002 is projected to be 42,500
MWh (see Figure 4.3) with peak load being 9 MW. To satisfy these
requirements additional generating units will have to be added.
(1) Alternative is used herein to mean either a complete system
or component of a system.
7-1
7.1.2 Base Case Electrical Generation
Based on the peak load requirements as shown in Figure 7.1.1, a
1200 KW diesel generating unit will be added on line in 1988
which will give the city a total capacity of 6025 KW with a firm
capacity of 5000 KW. With the addition of this unit on line in
1988, the City of Kotzebue' will have excess firm capacity until
about 1991. In 1991 a 2000 KW unit will come on line providing
the ci ty wi th an excess of firm peak load capaci ty until mid
1996. In 1996 another 2000 KW unit would be scheduled to go on
line which will(~fovide firm peak load capacity to the city until
the year 2002.
The two 2000 KW units and the one 1200 KW unit will each be
driven by a diesel engine. The engines will provide a minimum of
.1.5 brake horsepower per kilowatt. These engines will run on DFA
or diesel fuel No~ 2. The total consumption wi 11 be
approximately 485 gph at 100 percent load and will decrease to
about 170 gph at 25 percent load.
The engines will have a plate type heat exchanger and expansion
tank on the jacket cool ing water. This jacket water cool ing
system will also contain a thermostatic temperature control valve
to automatically control the flow rate of the cooling water to
either the heat exchanger or the existing air cooled radiators.
Furthermore, in the cooling water piping to the heat exchanger
there will also be a thermostatic control valve which will
maintain the lubricating oil at the desired temperature.
Each diesel unit will contain an exhaust silencer to attenuate
the exhaust noise.
The electric generators will be of the salient pole synchronous
type, each being rated at 60 Hz. Each generator will be three
phase rated at 2000 KW, 2000 KW, and 1200 KW respectfully with a
power factor of 0.80.
The addition of the new rotating equipment will require careful
analysis to ensure compatability with the exisiting facilities.
7.1.3 Base Case Waste Heat Recovery
Figure 7.1.2 shows the projected total heating load for the City
of Kotzebue through 2002. This figure shows that in the year
(I) Energy projections for this study were made through the year
2002. However, an update of these energy projections should be
made in 1990 to confirm or modify the equipment requirements from
1990 to 2002.
7-2
, 1
~ ! ~
u
u
u
( 1
W
I 1
W
I 1
W
f 1
~
i 1
W
u
u
U
D
U
U
r ' ' u
U
U
U
f :
U
r i
W
r •
~
n
W
I~
FIGURE 7,. 1. 1
BASE CASE DIESEL GENERATION
1_.ur,..-MW' PEAK LOAD>------------'------------
1v~~--------------------------
• i 7~---------==~~ I
E
4826KW
Total Capacity
3800KW
Firm Capacity
year
7-3
2002, a total heat demand (space heat, domestic hot water, and
process heat) is about 352 x 10 9 Btu/year. If the volumetric
heating value of the diesel fuel were about 136,500 Btu/gal and
that about 30 percent of the heating value can be captured for
use, then approximately 48 percent of the city's heating needs
could be suppl ied from the recovery of the waste heat from the
diesel genera tors in 2002. Figure 7.1.3 shows the fraction of
the heating demand that could be supplied by the recovery of the
waste heat, along with the required additional heat. It should
be noted that the present waste heat 6 available at minimum load
(approximately 1200 KW) is 3.8 x 10 Btu/hr, of which only a
fraction is utilized.
7.1.4 Fuel Consumption
The yearly fuel consumption to support the electricity generation
is shown ig Figure 7.1.4.
7-4
i 1
W
u
u
u
D
U
u
u
u
u
I i~
w
11 ..
u
u
u
u
f '
1..J
L
'U
( :
U
f '
LJ
r '
L.J
U
U
W
U
U
10
FIGURE 7.1.2
PROJECTED TOTAL HEAT DEMAND FOR THE CITY OF KOTZEBUE
EXCLUDING ,LINE LOSSES ESTIMATED AT 16"
340
• o ...
1980 82 84 86 88 90 92 9 ,98 98 2000
year
7-5
, I
FIGURE 17.1.3
POSSIB~E HEAT RECOVERY FROM DIESEL GENERATORS
mo ...
" "-ca ., ,..
" :::I ..,
m
450
400
360
total heat demand
300 including linelosses
250
heat recovery with
160 exhaust gas boiler
and Jacket water ••• •••• "':"f//:'!)f~)'//;(iX!// ••• • •••• heat recovery with
•••••• Jacket water
100
50
80 84 88 92 98 2000
year
f 1
w
u
w
w
u
i 1
W
; 1
W
f 1
W
( 1
~
r I
•
u
w
w
[ 1 ~
.~
I
IW
I
D
U
I U
U
U
i '
J
r '
W
, ,
U
w
U
~
W
I~
W
i~
FIGURE 7.1.4
DIESEL FUEL CONSUMPTION ELECTRIC GENERATION
.,
c o -
4
"3 3
G o ....
'i
: =-2 1----,-:a
1
o
85 87 89 91 93 95 97 99 01
year
7-7
7.2 COGENERATION (ALTERNATIVE "A")
7.2.1 Introduction
Alternative "A" would be to provide electricity thtough the use
of a steam turbine generator using the exhaust steam from the
turbine to provide heat energy for the Ci ty. Heat would be
distributed through a district he~ting system based on hot
water. If the turbine is not operating at full capacity, then
steam will by-pass the turbine through a PRV stqtion to be used
for district heat, process heat, and domestic hot water. A
simplified schematic drawing of the overall system is shown in
Figure 7.2.1. In the back-pressure steam turbin~ cycle shown in
this figure, the boiler will produce ,high pressure steam at 890
psig at 905°F. This steam will then be expanded through the
turbine to produce electricity and exhausted at a pressure of
about 5 pslg. Net overall efficiency will be approximately 22 -
27 percent ~ Thus fuel consumption wi 11 be 12,600 -15,500 Btu
per kwh produced. Recoverable waste heat will amount to
approximately 9,000 Btu per kWh produced.
The boiler to provide the steam can either be coal-fired, oil-
fired, or gas fired. Costs for the coal fired and oil fired
boiler are provided in Section 8.0.
7.2.2 Alternative "A" Development
u
u
i I
W
U
The development of Alternative "A" using either a coal-fired r j
boiler or an oil fired boiler is presented below. ~
The electrical requirements shown in Figure 4.3 and 7.1.1 will be
'utilized in this scenario. along with the heat demand shown on
Figure 7.1.2.
To satisfy these demands a single 135,000 lbs per hour steam
boiler (4,022 BPH) system will be installed along with'two (2) -
10MW steam turbine-generators. This system will provide not only
all the electrical requirements for the city but will also
provide all the heating requirements (space heating, process
heating and domestic hot water). The two 10MW units will provide
full peak load capacity during the entire 20 year period.
In case of breakdown of the steam turbine unit due to boiler
failure or auxiliary systems failure the 4825 kw diesel
generation capacity will provide some back-up for average load
condi tions. Furthermore, the diesel uni ts should be kept
operational after year the 2002 to provide peak load capacity
(see Figure 7.2.2).
To provide back-up capacity of the district heating system, a 25
million btu/hr oil-fired boiler will be installed.
7-8
u
u
w
w
, ,
i I ...
r •
U
I '
i ' ,W
iW I
I
r : ;L
I U
'W I ,
,U
I
W
I
i W
I~
I~
FIGURE 7.2.1
SIMIPLIFIED SCHEMATIC DIAGRAM FOR COGENERATING SYSTEM
FOR KOTZEBUE
air \ , boiler
fuel, II
~ 1\"'-~
~.
turbine --,
~'
steam-water
heat exchanger
generator 4 e1ec pO tric
wer
,
I condenser
~t
\ space ;-1 I heating
\
I ,
process \ , " I
I heating ~
L
\
domestic " \ ~ I I hot water ,
7-9
FIGURE 7.2.2
AL T~'RNA TIVE A. STEAM TURBINE GENERA TOR. .
PEAK LOAD REQUIREMENTS.
'a ca o --ca u .-.. .. u • -• ~
:IE
"
:':', ::,',.
projected peak load
94 96 98 2000
year
7-10
i i
W
U
U
U
i i
W
U
U
U
W
W
U
U
U
U
u
u
'w I
'U
I
!u
, 1
U
I 1
U
u
r
l.
~ I
I
W
u
r '
Existing oil stoves and oil-fired boilers should be kept
operational to provide backup capacity in emergency situations.
The amount of heat that would be recovered for space heating,
domestic hot water, and process heat is shown in Figure 7.2.3.
Furthermore, an air condenser will be required to reject the
excess heat in the event the city does not utilize the heat for
district heating purposes, but only f6rthe generation of
electricity.
At times when recaptured heat is not sufficient to supply the
total heating load, the remaining will be supplied from steam
bypassing the turbine.
variations in demand for heat and electricity for Kotzebue are
shown in Figure 7.2.6.
7.2.3 Boiler
The boiler will have a steam capacity for total throttle flow to
the turbine of about 115,000 pound of steam per hour at 890 psig
and 905°F. However, to handle soot blowing, blowdown and
mi~ce~laneous radiation and leakage losses, the size of the
boiler will have a steam capacity of 135,000 lb/hr.
The size of the air and gas handling equipment will depend on the
amount of excess air that would be required for optimum firing.
This, in turn will depend on the characteristics of the coal
(moisture content, carbon content, sulfur content and oxygen
content). However~ if the Point Hope deposits, or Lisburne
deposits are utilized ~t is estimated that the gas flow will be
approx,imately 86.5. x 10 cfm at full boiler output.
The boiler system will require an air heater to furnish
combustion air at approximately 400 o P. This heater will be a two
p~ss vertical tubular type which will permit the installation of
gas bypass damper between stages wi thout the need for spec ial
ducting. In addition to facilitating the bypass of the heating
surface during start-up, the arrangement permits the automatic
controlling of the exit gas temperature to avoid condensation.
The air heater will be installed in the gas duct at the boiler
outlet. The combustion air will enter and leave the unit in a
cross flow pattern.
High furnace temperatures are essential for clean combustion. If
temperatures get too high there is a danger of slagging material
accumulating on tube surfaces. If temperatures are too low the
combustion gases are apt to enter the boiler convection section
wi th some unburned fixed carbon resulting in lower eff iciencies
and a discharge of smoke to the atmosphere.
7-11
FIGURE 7.2.3
KOTZEBUE'S TOTAL HEAT DEMAND FOR ALL PURPOSES INCLUDING
LINE LOSSES AND WASTE HEAT UTILIZATION
THESE DATA HAVE BEEN CALCULATED ON A MONTHLY BASIS
500
450
CI) 400
0 ...
>( ... 350 ca
CD >-" ::J 300 .. m
250
200
150
100
50
••• •••
80 84
••• •• •••
..... utilized waste h, eat
•• y
••••
88 92
year
7-12
96 2000
[,
~
w
u
I i
~
I i
U
U
U
W
W
U
~
U
W
W
W
II ~
II , I ..
u
I I
-.I
r 1
r '
I
l
7.2.4 Turbine-Generators
The turbine-generator will be steam driven with inlet steam
conditions of 890 psig at 905°F and exhausting at 5 psig at
230°F. The generator will be 10 MW. The turbine will be
directly connected to the generator.
The back pressure steam turbine main steam valves shall be
controlled such that they do not exceed 105 percent of the rated
pressure. During abnormal condi tions the pressure may exceed
rated pressure by about 20 percent for brief periods. The
temperature variations should not exceed the rated temperature by
more than 15°F except during abnormal conditions.
The generator will have the following rating:
a. 6250 KVA
b. 0.85 power factor
c. 10.6 MW
d. 3600 RPM
e. 2 poles, 3 phases
f. 4160 volts, 870 amperes, 60 Hz
g. WYE connections
This generator will be an air cooled synchronous unit with four
corner mounted coolers. The unit will also have a static
excitation system direct connected, including excitation cubicle.
7.2.5 Fuel
The fuel for the boiler can either be gas, oil, or coal. This
alternative will consider only the use of a coal-fired boiler or
an oil-fired boiler. ~ .
The possible coals that could be used that are near Kotzebue are
the Kugruk River coals (Chicago Creek area) which are 1 igni tic
coals having a heat combustion of 6200 to 6800 Btu per pound with
an average moisture content of 35 percent. A proximate analysis
of this coal is:
COMPONENTS
Fixed carbon
Volatiles
Moisture
Ash
Sulfur
Total
Composition
(Percent by wt.)
19.2
39.0
33.8
7.1
0.9
100.0
This coal will probably be frozen and the drying of the coal
prior to· use could be accomplished using the excess waste heat
from the boiler.
7-13
Another potential source of coal for use in Kotzebue would be the
Point Hope coal deposits. These coals are low';"volatile
bituminous coals that have a heating value of about 14,000 Btu
per pound. A proximate analysis of a sample of these coals is
presented below:
COMPONENTS
Fixed Carbon
Volatiles
Moisture
Ash
Total
Composition
(Percent by wt.)
79.9
15.6
1.7
2.8
100.0
This coal would also be frozen and would have to be thawed and
dried prior to use.
The coal requirements for the operation of this 135,000 Ib per
hour boiler are presented in Figure 7.2.4.
It should be noted that the coal would have to be mined in the
summer and transported and stock piled for major use during the
winter months. There are other coal reserves which could also
supply such a system, e.g. Kobuk River coal or coal from Healy.
Kobuk coal requirements are also included in Figure 7.2.4.
The amount of diesel fuel or No. 6 fuel oil that would be
required if the boiler were oil-fired instead of coal-fired, is
presented in Figure 7.2.5. This figure is based on fuel having a
volumetric heat of combustion of 136,500 Btu/gallon.
7-14
[ ;
W
u
u
u
i 1
W
w
w
w
w
I
;w
I
!O
I
W
I
I U
I
U I
f ;
I
W
( 1 . u
( i
r !
L.J
, 1
I I W
, 1
U
U
~
W
I
D
D
W
FIGURE 7.2.4
COAL REQUIREMENTS
COAL FIRED COGENERA TION (ALTERNATIVE B)
=80:.....a-__ .-----...... ~ ... -.--.. ---------
72
84
56
M 4..:..;:8:...-a--_
fI) c o .., -ca o u 40
32
24
18
85 87 89 91 93 95 97
year
7-15
Chicago Creek I
Kugruk River
Coal 6,500 Btu/lb.
Nenana Coal
8,000 Btu/lb.
Kobuk River
Coal
10,000 Btu/lb.
pt. Hope Coal
14,000 Btu/lb.
99 01
FIGURE 7.2.5
OIL-FIRED COGENERATION
-·0
2
1
86 87 89 91
:1
93 96 97
year
99 01
u
u
u
u
r I
W
U
U
U
U
U
W
U
w
U
i 1
LJ
I 1
w
r 1
l.J
W
I 1
r I
W
~
o
D
W
o
FIGURE 7.2.6
VARIATIONS IN DEMAND FOR HEAT AND ELECTRICITY
FOR KOTZEBUE
BASED ON STATISTICS FOR ELECTRICITY AND HEATING DEGREE DAYS FOR HEAT
"0
C as
E
GJ
"0
>t -.. as
GJ
>t .... o
~
14
13
12
11
8
7
8
2
1
9 10 11 12
month
7-17
7.3
7.3.1
COAL-FIRED LOW-PRESSURE
(ALTERNATIVE "B")
General
DISTRICT HEATING SYSTEM
Alternative "B" provides for a coal-fired low-pressure district
heating system. In this system it is assumed that all landing,
bulk storing and handling of coal would take place in a location
on or close to the coastline just south of the Kotzebue lagoon in
a position that is compatible witn the emergency North-South
runway and USAF radar facilities.
The'alternative provides only for space heating, domestic water
and potable water heating demands. In the final analysis it
should be combined wi th a system that provides electric power,
i.e. diesel power, high pressure steam generation or hydropower.
Apart from coal landing, bulk storage and handling facilities -
Alternative "B" comprises the following main components:
7.3.2
7.3.3
7.3.4
District heating facility
Water-antifreeze transmission line, approximately 3
miles long, from the district heating facility to the
existing power plant .
Water-antifreeze distr~bution system
Some or all of the above components have been incorporated in
other alternatives, for example:
In Alternative "A", heat recovery from a back pressure steam
generating unit will be used as a partial energy source for a
district heating system. In addition to the steam generating
unit, the complete system will require:
o
o
o
A supplementary coal-fired low-pressure district
heating facility of about 75~80% capacity compared to
that of Alternative "B"
Water-antifreeze transmission line, full capacity
Water-antifreeze distribution system, full capacity
In Alternative "C", 7.4.1, a complete coal-fired low-pressure
district heating system will also be considered as a means to
cover heating needs.
In Alternative "0", 7.5.3, a full capacity district heating
system wi 11 also be considered as a means to cover the heating
needs.
7-18
I ..
I :
W
u
u
u
r 1
W
I J
\ '
1.1
u
u
,I..
;
LJ
,
I~
W
I
~
u
u
u
u
7.3.1.1 Basic Parameters
Plant Capacity designed to meet:
o
o
o
o
Space heating demands (high forecast) are derived from Table
4.10, page 4-21 as follows:
Year Btu x 109/year kWh x 106/year
1981 160 47
2002 300 89
Domest ic water heat i ng demands are derived from Tabl e 4.13,
page 4-24 as follows:
Year
1981
2002
Btu x 109/year kWh x 103/year
6.0 1.8
22.5 6.6
Assuming no significant seasonal demand variation, the above
translates into capacities as follows:
1981
2002
Potable water heating
page 4-27 as follows:
Year
1981
2002
0.69 x 10~ Btu/h
2.57 x 10 Btu/h
demands are derived from Table 4.14,
Btu x 109/year kWh x 103/year
10.0 3.0
16.6 4.8
Assuming no significant seasonal demand variation,
translates into capacities as follows:
the above
1981
2002
1.14 x 10 6 Btu/h
1.87 x 10 6 Btu/h
Summary of plant capacities envisioned are
1981 2002
Btu/h x 10 6 Rtu x 10 6
Space heating 43.06 69.78
Domestic water heating 0.69 2.57
Potable water heating __ ~lr.~1~4~ __________ ~~1~.8~7 __
Totals 44.89 74.22
The district heating system has been dimensioned for 74
MBtu/h.
The design temperatures are 65°F indoors and -39°F
outdoors.
The flow temperature of the district heating fluid is
212°F and the return temperature 176°F.
7-19
, .
I
I
I
o
o
zoning The zoning of the heat demand has been made in
accordance with plan 7.3.2.
Pipe insulation thickness The insulation thickness of the
pipes has been dimensioned on the basis of a thermal
. conductivity of frozen soil of k = 2.2 W/moc and 'of
unfrozen soil of k = 2.0 w/moc. The temperature of the
soil will be about 25°F. Furthermore, it is considered
acceptable that a zone 'of about 6" around the pipes
thaw~. This zone should be wholly within gravel backfill,
in other words permafrost concerns have, in part, been
addressed by this design concept.,
7,.3.2 Coal-F ired Distr ict Heating Stat ion
I
Plant Description. See also Figures 7.3.1 and 7.3.2.
7.3.2.1 Receiving and Transportation of Coal
i '
i I
~
I 1
~
u
The coal is rece i ved from a truck or front loader by way of a
funnel. From there the coal is transported on conveyors to the i ;
coal storage silo and from the coal storage silo to the service I.J
silos at the boilers •
. The silos are fitted with filling control sensors. U
From the service silos the coal is fed directly down into the U'
coal funnels of the boilers.
7.3.2.2 Boilers with Traveling Grates
The three boilers, type ECOCOAL R, each with a maximum capacity
of about 35.7 x 10 6 Btu/h, are delivered with built-in travelling
grates, type Cornelius schmidt.
The boilers consist of a combustion chamber part and a convection
part.
A large combustion chamber secures a good combustion of the coal.
The convection part and the economizer, ·fitted with vertical flue
gas pipes, are divided into sections with throttle valves
controll ing the flue gas temperature at about 500 of wi thin the
load area from 30-100%.
7-20
I
W
i 1
W
I
iW
I
D
I
J
r 1
( ,
1 ,
W
r ,
LJ
: I ·W
I
( ;
w
I
U
:u
I
U
I ,
U
U
u
The grate is dimensioned for Kallarichuk coal with the following
specifications:
Calorific value,
Volatiles
Ash
Sulfur
Grain size
10,500 Btu/lb
30%
8%
0.5%
0-11/i'
The following grain size ratio is assumed:
o -3/64" (culm)
3/64 -111
1 -1 1/4"
About 20%
70%
10%
Varying grain sizes, especially increased contents of a -1/8 11 ,
can reduce the efficiency of the boiler.
Heavy contents of coals of more than 1 1/411 will mean more
unburned cinders.
If an inferior coal quality is used the dimension of the boiler
may have to be increased.
7.3.2.3 Multi Cyclone Filters
The three multi cyclone filters, type RK, are divided into
sections controlled by throttles in order to obtain the best
possible exhaust gas velocity in the individual cyclone at
varying loads.
Particulate matters emi tted from fuel burning equipment do not
exceed 0.5 grai ns per cubic foot of exhaust gases corrected to
standard conditions, depending on the quality of the coal.
7.3.2.4 Exhausters
In order to keep a negative pressure in the combustion chamber of
the boilers, exhausters are installed after each multi cyclone.
7.3.2.5 Stacks
The exhaust gases are led on. to the three stacks, each 100' tall.
The stacks are manufactured in Cor ten steel with about 28 11 core,
411 Rockwool insulation and an external carrying mantle.
The stacks are bolted to a concrete foundation.
7-21
7.3.2.6 Cinders and Ash Disposal
The cinders and the ashes are ejected at the bottom of the boiler
and transported on a conveyor to the cinder-and ash container.
7.3.2.7 Miscellaneous Installations
The pipe installation uses pre-insulated steel pipes with all
necessary valves and fittings.
The two pu~ps are designed with a pumping capacity of 100% load
each.
The expan~ion' tank is provided with fittings for automatic I
pressure control by means of compressed ai r.' W
The raw water is treated in a water treatment system and is fed
to a hold ing tank. U
The conceptual design and section is shown in Figures 7.3.1 and
7.3.2.
7-22
i
W
r '
W
r
W
Circuit
pumps
Control
panel
r ,.....
..... -
Stacks
/\
I I
KOTZEBUE CENTRAL DISTRICT HEATING
ARRANGEMENT, PLAN
1
I I
!Ash cl..llv,=,yvr.L.-1 __ --1
~--+ Ash container
Boile s
Coal silo
Funnel
Coal clonveyor
I I -Service silos -1
r FIGURE 7.3.1
FIGURE 7.3.2
Stack
-. ----
KOTZEBUE CENTRAL DISTRICT HEATING
ARRANGEMENT, ELEVATION
Coal silo
Cyclone 1-----' separator
I A~ Boiler
II I I-se~vice
f--""
\-----i
\ ~ I
;:= , I tl -J! ,'\
t:j
Ash conveyor
7-24
! :
~
1 1
W
silo
I '
I.J
r
~
~
r
1.1
W
~
L
~ I
D
I
D
U
J
u
u
r
IW
u
'U
I
U
U
7.3.3 Water-Antifreeze Transmission Line
The transfer of heating energy to the distribution network will
take place in a triple conduit, each pipe being steel-in-steel
preinsulated piping.
The internal diameter of the piping is designed for the full year
2002 demand:
Internal diameter
External diameter
Insulation thickness
12,75 inches
22,00 inches
4 3/8 inches
The length of the transmission line will depend on the actual
location of the district heating facility and the line chosen.
For the purpose of calculating costs the length has been taken as
3 miles.
One pipe will be for delivery, one for return flow, the third is
standby in the' event of damage to one of the other pipes.
7.3.4 Distribution Network
Figure 7.3.4 contains the lay-out for the distribution network.
The network has been dimensioned on the basis of the conditions
stated in Figure 7.3.3, and with the pipe dimensions chosen the
maximum pressure drop in the network being about 60 psia, i.e. a
maximum operation pressure of 90 psia and a test pressure of 150
psia.
All pipes are underground pipes. Figure 7.3.5 shows the placing
of the pipes in its excavation.
The network is planned as a pre-manufactured stee1-in-steel
system, i.e each pipe (f low and return) consists of two steel
pipes, a medium pipe and a jacket pipe.
In order to obtain an efficient thermal insulation of the pipe
system the room between medium and jacket pipes is filled with
hard polyurethane foam (the heat conductibility is about 0.017
Btu/ft hrOF).
Both jacket and medium pipes are made of mild steel 37.
To protect the jacket pipe against corrosion it is provided with
a 1/8 polyethylene coating.
7-25
9
4,16 x 10' BTUtH
14
4,16)(10' BlUtH
LOAD BASIS FOR DISTRICT HEATING
o
o
SYSTEM
\
FIGURE 7.3.3
KOTZE
DISTRICT HEA ~~~
7-26
TO COAL FIRED PLANT
LAYOUT FOR DISTRIBUTION NETWORK
FIGURE 7.3.4
KOTZEBUE
DISTRICT HEATING
7-27
~
~
D
U
U
U
u
u
, ' I i
iJ
r 1
U
I~
U
I~
W
~
~
~
III
~
'N
CD
-"-
_ .........
L
I
dn inches 2
On inches 5.5
A inches 38
B inches 34
--~BOnd ,--.J(.
1
u
0
CD
-;-'
~ @ I
i ]\
~.
A .. I 0."-._._ ...
.
3 3.5 4 6 8 10 12 14
7
38
34
7.5 10 13 16 18 22 22
40 42 44 47 50 53 53
35 38 40 43 45 50 50
. KOTZEBUE DISTRICT HEATING
CROSS SECTION
FIGURE 7.3.5
7-28
The pipes are delivered ready-mounted
about 40' •
Medium pipe Jacket pipe
inches inches
1 3/8 x 3/32 3 1/2 x 1/8
2 3/8 x 7/64 5 1/2 x 9/64
3 x 7/64 6 5/8 x 5/32
3 1/2 x 1/8 7 5/8 x 11/64
4 1/2 x 1/8 9 5/8 x 13/64
6 5/8 x 5/32 12 3/4 x 13/64
8 5/8 x 11/64 16 x 1/4
10 3/4 x 13/64 18 x 1/4
12 3/4 x 13/64 22 x 1/4
14 x 7/32 22 x 1/4
7.3.5 Consumer Instailations
from factory in lengths of
Insulation
Thickness inches
1 1/32
1 27/64
1 21/32
1 57/64
2 23/64
2 27/32
3 7/16
3 3/8
4 3/8
3 3/4
I 1
W
u
w
u
u
r 1
W
i 1
-.J
The price calculations are based on the individual consumers
being connected to the district heating network by means of heat [1
exchangers with a head of loss of 3 psia. ~
However, if the existing installations are expected to be able to r 1
resist the recommended test pressure of about 150 psia, direct ~
connection should be considered.
The distribution network has been dimensioned for a cooling of r-l
212 -176 = 36°F. ~
In case of direct connection the differential pressure of the r-j
consumer connection will be about 3 psia. ~
As geothermal wells most likely will be no warmer than 162° F, I~l,
size of residential radiator installations will have to be ~
increased if geoth~rmal heat is to provide for all heating needs~
U
W
7-29
u
u
[
u
u
r 1 I I
W
, :
; 1
I 1
.J
I~
7.4 HYDROPOWER -BUCKLAND (Alternative "C")
Taken in total from referenced Retherford report for APAof June
1980 titled "Assessment of Power Generation Alternatives for
Kozebue". RETHERFORD'S ANALYSIS IS INCLUDED TO ASSIST THE REPORT
REVIEWERS BY HAVING ALL BASIC INFORMATION IN ONE REPORT.
BASICALLY ONLY THE COST ESTIMATE, SECTION 8, HAS BEEN REDONE. IN
OTHER WORDS, THERE IS NO NEED AT THIS STUDY LEVEL TO FURTHER
REFINE THIS ALTERNATIVE.
Task 7.4.1 General(l)
Development of hydroelectric sites in the Arctic encounter many
problems wh ich are not present in more tempera te areas of the
world.
Logistics problems associated wi th engineering and construction
of, hydroelectric projects in the harsh Arctic environment are
certainly among the most difficult and challenging of any in the
world. In addition, construction itself is a challenge, since
only in protected locations, such as heated enclosures and under-
ground, can construction proceed with any efficiency during the
cold period.
From the standpoint of annual precipitation, the Arctic is
essentially a desert. Also, the topography ·of the Arctic is
generally not sui table 'for high head installations. Therefore,
for a hydroelectric project to be viable in the Arctic, it must
have a relatively large contributing drainage basin.
Stream flow in most Arctic streams and rivers either disappears
or is greatly diminished during the winter months. Only the
larger riv~rs, for instance, those with over 300 square miles of
drainage area, can be expected to have any flow. Remote tribu-
taries and streams with small drainage basins freeze solid.
Hydroelectric sites must therefore be chosen which have adequate
storage to allow for generation during the cold months when
inflow is diminished, as well as to provide carry-over storage
for dry years.
Large accumulations of surface ice on bodies of water in the
Arct ic further tend to reduce the avai lable storage, and thus
necessitate larger volume reservoirs for a given power production
than would be required in a more temperate climate.
(l)Taken from referenced Retherford report for APA, Section
III (Only section, page, figures, and tables changed to·. reflect
this report's numbering system unless otherwise noted).
7-30
To illustrate the effect of reduced winter inflows and reduction
of volume due to ice ~fcumulation, a family of curves was
generated (Figure 7.4.1)( which shows the required live storage
volumes for given average power outputs and heads. The criteria
u~ed in developing the curves were these:
oIt was assumed that there could be usable flow into the
reservoir for only five months per year.
o During the remaining seven months, inflow to the reservoir
would only be enough to balance the volume lost by forma-
tion of ice (assumed to be an average of six feet thick).
o Reservoirs with area and capacity vs. depth characteris-
tics similar to those of proposed reservoirs in the
Ipewik, Kogoluletuk and Buckland Rivers were assumed. The
topography of these areas is considered to be typical of
the Arctic.
The curves show, for· example, that nearly 600,000 acre feet of
storage must be provided for a 10 MW (average power output) plant
where the average net head is 100 feet. This storage would be in
addition to that required to regulate the stream flow over dry
years.
Ice on an Arctic reservoir has effects other than decreasing its
storage volume. Formation of ice on intake structures may
seriously reduce their capacity and consequently the power pro-
duction~ Ice formations also will exert tremendous pressures,
both horizontal and vertical, on intake towers, trash racks,
gates, and other structures, ·with consequent disastrous results
if the structures are not structurally adequate or measures taken
to remove the ice.
Ice fog and spray can also present serious problems. The frozen
fog or spray can increase the load on transmission line conduc-
tors and other structures to the extent that they may fail.
The effect of permafrost on the design of hydraulic structures in
the Arctic is another serious problem requiring specialized
design and construction techniques.
It can be seen from the above discussion that even though a hydro
site may appear promising on paper, there are many factors which
must be considered before a final judgment can be given.
The scope of this study did not allow more than a cursory review
Of dam and reservoir locations in the Kotzebue area. The poten-
tial developments described in the following paragraphs appear to
(2)Figures, tables and numbers changed to reflect this
report's numbering system.
7-31
u
u
w
w
w
u
r 1 I.J
u
r ' U
I )
be more feasible, with the caveat that additional analyses will
be required to firm up project par,ameters and to address in more
detail the problem peculiar to the Arctic noted above.
7.4.2 Potential Sites(1)
General
The City of Kotzebue is located on the northwestern end of the
Baldwin Peninsula, a long, narrow, low lying peninsula
approximately 63 miles in length and from ~ to 11~ miles in
width. Drainage basins on the peninsula are very small and the
highest point is 315 feet in elevation. Consequently, there are
no viable hydroelectric project sites on the Peninsula.
The most northerly point on the Baldwin Peninsula is only 2~'
miles from the Noatak River delta across Hotham Inlet. Large ice
floes passing through this shallow inlet precludes the
feasibility of constructing a submarine cable to connect Kotzebue
with potential hydroelectric projects to the north~ Generation
facilities for Kotzebue that are not on the Baldwin Peninsula
will therefore require lengthy overhead transmission lines~
Due to the requirement of a long transmission line to bring
hydroelectric power to Kotzebue, potentials of less than 5 MW
(approximately twice the present electric power demand in
Kotzebue) have not been considered for der~ropment. Future power
requirements (established in Sfirion 4) ,for Kotzebue, which
indicate a demand of 9 MvJ fff) electrical lights and
appliances with an additional 21 r.1W required for Electrical
Reaction heaters by 2002, dictate a minimum plant capacity for
the combined system of 30 ~m. If then 139 kV is chosen as the
appropriate transmission voltage, (predominant in the state) the
transmission distance is limited to approximately 150 miles due
to voltage drop limitations.
(1) Taken from referenced Retherford report for APA, Section
III (only section, page, figures and tables changed to reflect
this report I s numbering system unless otherwise noted). Only
the Buckland River site has potential for 1 plant to reasonably
serve the power requirements of Kotzebue. l-ihile beyond the
context of this study, several small hydropower plants seem
unreasonable because of limited water storage, periods of almost
no flow and transmission line losses.
(3 ) Changed to reflect the Energy Forecast of this report to
the year 2002.
7-32
As d~~lussed in the introduction and demonstrated on Figure
7.4.1 , large reservoir ~apacity and a large drainage basin are
requirements that limit the number of potential sites to consider
for serving Kotzebue. Four possible sites were examined in this
study: Two only briefly, one moderately and the most promising,
the Buckland River, in more depth.
The general location of the sites is shown on Figure III-12 of
the referenced Retherforf2 )assessment report. The Buckland Site
is shown on Figure 7.4.2 • '
7.4.3 Buckland River(l)
Locations:' Candle Quadrangle, Kateel River Meridian,
T5N, RlOW, Section 21.
Drainage Area:
Average Flow:
Regulated Flow:
Average Head:
Reservoir
Dam Height
Power: (prime)
Energy: (per yr.,
Load Centers:
Distance:
2,220 sq. mi.
2,880 cfs
765 cfs
100 ft.
42,688 acres
125 ft.
16,125 kw
prime) 87,600 MWh
Kotzebue, Candle, Deering, Selawik
98 mi. (transmission to Kotzebue)
(1 )Taken from referenced 'Retherford report for APA, Section
III (only section,' page, figures and tables changed to reflect
this report's numbering system unless otherwise noted).
,(2)Pigures, tables and numbers changed to reflect this
report's numbering system.
7-33
I I
I 1 ~
u
u
u
u
w
w
w
w
....... --
4 •.
,~
4 00
-.
~
lL ......
I
o
3 50
3 00
, ...... :2
:z:: ...
-...J 1&.1
I' Z
W 1&.12
~ ~
a:
1&.1
~
0'"
50
, \ ~
\
\
\
\
....... --. . .. , -----.. ... ." " ~
\
\ \
\ \
\ \
\ \ ~
\ " " ~ ~
'" '" " ~ ~
~ ~ ~ ,
~ ~ ~ ~ ~ ----00 ~ ~ ~ ~
~ -
!SO --
0 o ~ ~ ~ ~ ~ ~ ~ ~ ~ 1000 1100
LIVE STORAGE -(ACRE-FEET I 1,000)
FIGURE 7.4.1'3) SMALL HYDRO-ARCTIC CONDITIONS
~
1200
".
APPROXIMATE LIVE STORAGE REQUFtEMENT A,.fERAGE NET-VS-lIVE STORAGE (ALLOWS FOR 8FT. ICE COVER) ';
. ..
.......
--...
---
1300 1400· I!SOO
· ... -
-.
FIGURE 7.4.2
BUCKLAND RIVER
HYDROELECTRIC
POTENTIAL/16 MW ~~
. ,/
'..-.....:.:=-.:-~_;.I:J· j_ .... :" __ .
;
D
I o
( 1
W
u
The Buckland River flows northwesterly into Eschscholtz Bay, an
extension of Kotzebue Sound. A suitable site for a dam 125 feet
in height creating a reservoir with a normal maximum water sur-
face elevation 150 appears on U.S.G.S quad sheet Candle (D-4)
Alaska in Sect ion 21, T5N, RlOW, Kateel Ri ver Merid ian. The
general location( Ls shown on Figure 1.2. The reservoir is shown
on Figure 7.4.2 2'. An ungated side channel spillway could be
constructed to the north of the right dam abutment. The power-
hous.e would be constructed on the south bank of the river and
preferably cut back into the bluff for added water winter
protection.
The drainage basin above the damsite is about 2,220 squar~ miles
and the average annual runoff is estimated to be 2880 cfs. The
normal maximum water surface area at elevation 150 is 42,688
acres. A drawdown of 32 feet is required for complete regulation.
An average net head of 80 feet during the winter would produce
16,125 kW of firm power. Secondary energy has not been estimated.
The project could be developed in two stages of construction. The
first stage would entail the installation of all project features
with the exception of the powerhouse equipment. An ultimate
installation of 30 MW of capacity in three units is recommended.
Two 20 MW units would be installed in the first stage with a
drawdown valve installed in the third leg of the penstock trifur-
cation. The drawdown valve would permit sufficient drawdown to
allow for ice storage during breakup and permit a regulated
downstream flow in the river channel.
The Buckland River Project meets the requirements for a potential
hydroelectric site for Kotzebue. The damsite is 32 miles from
tidewater and the reservoir capacity is large enough to regulate
the flow and store ice brought in during breakup without reaching
the spillway crest. It is of the proper size. to meet future
forseeable load requirements of the area and is approximately 90
miles transmission distance to Kotzebue.
(2)Figures, tables and numbers changed to. reflect this
report's numbering system.
7-36
7.4.4 Hydrology(l)
There ar~ no known strea~ gauging records on. the Buckland River;
however, there are 13 years of continuous gaug ing on the Kobuk
River near Ambler. The NOAA Technical Memorandum NWS AR-IO "Mean
Monthly and Annual Precipi tat ion" shows about the same annual
precipitation for the two river basins with possibly slightly
more for the Bucklahd River as it appears that more of its
drainage basin is above the 20-inch isohyet line. The l3-year
record on the Kobuk shows an average runoff of 1.348 cfs per
square mile of drainage basin •. For conservative reasoning, an
average of 1.3 cfs per square mile was used for the Buckland
,River. A synthetic 13-year flow (1966-1978) wf~) developed from
the flow data on the Kobuk River, Table 7.4.1 , by determing
the ratio of drainage basin (2,220/6570 = 0.3379) and the ratio
of the ru~?ff per square mile (1.3/1.348 = 0.964) and obtaining a
factor (0.3379 x 0.964 = 0.326) to multiply the monthly recorded
of flow on the Kobuk River (~o, obtain a synthetic flow for the
Buckland River, Table 7.4.2 • The Buckland River' sY~1~etic
flow was then converted to acre feet by month, Table 7.4.3, to
determine the average cfs flow.
The 8,858 cfs average annual flow for the Kobuk River calculates
to 18.30 inches of precipitation runoff. The 2880 average annual
flow for the Buckland River calculates to 17.65 inches of
precipitation runoff annually. Stream gaging is recommended for
the Buckland River to verify the synthetic calculation in this
study.
An Area-Capacity curve r~r developed for the proposed'project and
appears in Figure 7.4.3 • The curve shows the probable maximum
drawdown to elevation 118 leaving 1,216,270 acre feet of capacity
to store ice during spring breakup. This amounts to 58% of the
average annual flow.
(l)Taken in total from Retherford Report for APA, June i980,
titled "Assessment of Power Generation Alternatives for Kotzebue"
Retherford's analysis is included to assist the report reviewers
of having all basic information in one report.
u
D
u
u
I 1
W
u
u
(2 'Figures, tables and numbers, changed to reflect this fl
report's numbering system. ~
7-37
TABLE 7.4.1(2)
KOBUK RIVER AT AMBLER FtOW IN CFS
Water Year·
Year ,Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept Ave.
1966 18,580 3,000 2,400 2,0.0.0 1,60.0 1,0.00 1,2.0.0' 3,945 28,12.0 17,2.00 11,18.0 11,53.0 8,675
1967 9,4.06 3,0.0.0 2,00.0 1,3.0.0 90.0 800 95.0 15,14.0 58,73.0 3.0,980 23,980 12,36.0 13,34.0
1968 6,687 3,597 2,09.0 1,545 1,40.0 1,300 1,3.0.0 5,019 61,31.0 18,400 8,126 4,967 9,601
1969 13,520 3,560 1,500 961 827 8.0.0 1,160 15,550 7,810 5,235 12,520 5,99.0 5,839
1970 ' 4,619 2,460 1,516 1,181 1,.018 99.0 1,017 17,14.0 11,89.0 7,181 16,08.0 9,.037 6,220
1971 2,974 1,85.0 1,297 1,.032 1,.0.00 95.0 9.0.0 24,91.0 45,.01.0 14,63.0 8,119 7,57.0 9,203
1972 6,910 3,833 2,387 1,526 1,152 974 900 20,99.0 36,16.0 10,630 11,38.0 11,47.0 9,.025
1973 5,787 4,133 3,052 2,426 2,057 1,768 1,65.0 30,240 45,730 19,360 39,750 21,92.0 14,890
1974 14,950 .. 4,317 2,123 1,665 .1,436 1,365 1,307 9,484 17 ,580 13 ,070 . 19,610 14,92.0 8,532
-..J 1975 6,565 1,947 1,097 1,00.0 1,000 1,.000 1,113 16,76.0 22,87.0 21,75.0 .9,790 19,830 8,76.0 I
w
':x:> 1976 4,487 1,580 987 900 900 9.0.0 1,001 10,670 20,890 11,090 9,461 9,63.0 6 • .045
1977 6,971 3,800 2,468 1,774 1,389 1,300 1,317 12,55.0 26,640 8,529 6,710 13',870 7,279
19~8 . 1.0 1 14.0 3 1 J07 1 1 839 1,513 1 1 400 1 1 290 1 1 2.07 , 13 1 040 18 1 93.0 16 1 230 9 1 887 13 191.0 71742
111,596 4.0,184 24,756 18,823 16,.079 14,437 15,022 195,438 401,67.0 194,285 186,593 157,.0.04 115,151
Ave. 8,584 3,091 1,904 1,448 1,237 1,111 1,156 . 15,.034 30,898 14,945 14,353 12,.077 8,858
6.,570 sq. mi. Record Ave. 8 .. 858.
= 1,348 cfs/sq. mi.
Min Year (1969) 5,839 cfs = 0.889 cfs/sq. mf.
TABLE 7.4.2(2),
,KOBUK TO BUCKLAND SYNTHETIC FLOW RECORD
Ratio of drainage Areas = 2,220/6,570 = 0.3379
R~tio of runoff per sq. mi. = 1. 3/1. 348 =-0.964 ~
Factor to ,use in deriving Buckland Flow = 0.964 x 0.3379 = 0.326
Water
Year Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
--J 1966 6,057 978 782 ' 652 522 326 ' 391 1,286 9,167 5,607' 3,645 3,759
I
w 1967 3,066 ' '\.0 978 652 424 293 261 310 4,936: 19,146 10,099 7,817 4,029
1968 2,180 1,173 681 504 456 424 424 1,636 19,987 5~998 2,649 1,619
1969 4,408 1,161 489 313 270 261 378 5,069 2,546 1,707 4,082 1,953
1970 1,506 802 494 385 332 323 332 5,588 3,876 2,341 5,242 '2 ;946
1911 970 603 423 336 326 310 293 8,121 14,673 4,769 2,647, 2,468
1972 2,253 1,250 778 497 376 318 293 6,843 11,788 3,465 3,710 3,739
1973 1,887 1,347 995 791 671 576 538 9,858 14,908 6,311 12,959 7,146
1974 . 4,874 1,407 692 543 468 445 426 3,092 5,731 4,261 6,393 4,864
1975 2,140 635 358 326 326 326 363 5,464 7,456 7,091 3,192 6,465
1976 1,463 515 322 293 293 293 326 3,478 6,810 3,615 3,084 3,139
1977 2,273 1,239 805 578 453 424 429 4,091 8,685 2,780 2,187 4,522
1978 3,306 1,013 600 493 456 421 393 4,251 6,171 5,291' 3,223 4,535
TABLE 7.4.3 (2·)
BUCKLAND RIVER ACRE-FEET x 1000
Oct Nov Oec Jan Feb Mar Apr May Jun Jul Aug Sep Total
1966 371. 78 58.09 48.00 40.02 28.94 20.01 23.23 78.95 544.52 344.16 223.73 223.28 2,004.69
1967 188.19 58.09 40.02 26.03 16.24 16.02 18.41 302.97 1,137.27 619.88 479.81 239.32 3,142.25
1968 133.81 69.68 41.80 30.94 25.28 26.03 25.19 .100.42 1,187.23 368.16 162.60 96.17 2,267.31
1969 270.56 68.96 30.01 . 19.21 14.97 16.02 22.45 311.14 151. 32 104.78 250.55 116.01 1.375.98
1970 92.44 47.64 30.32 23.63 18.41 19.83 19.72 342.99 230.23 143.69 -321. 75 174.99 1~465.64
.....,J 1971 59.54 35.82 25.96 20.62 18.07 19.03 17.40 498A7 871.58 292.72 162.47 146.60 i,168.28 I
~. 1972 138.29 74.25 47.75 30.51 20.85 19.52 17.40 420.02 .700.21 212.68 227.72 222.10 2.131. 30 0
1973 115.82 80.01 61.07 48.55 37.20 35.35 31. 96 605.08 885.54 387.37 795.42 424.47 3,507.84
1974 299.17 83.58 42.47 33.33 25.95 27.31 25.30 189.79 340.42 . 261. 54 392.40 . 288.92 2,010.18
1975 131. 35 37.72 21.97 20.01 18.07 20.01 21.56 335.38 442.89 435.25 195.92 384.02 2,064.15
1976 89.80 30.59 29.76 1.7.98 16~24 17.98 19.36 213.48 404.51 221.89 189.30 186.46 1,427.35
1977 139.52 73.60 49.41 35.48 25.11· 26.03 25.48 251.11 515.89 170.64 134.24 268.61 1,715.12
1978 202.92 60.17 36.83 30.26 25.28 25.84 23.34 260.93 366.56 324.76 197.83 269.38 1.824.10·
Total 2,233.19 778.20 495.37 376.57 290.61 288.98 290.80 3.910.73 7,778.17 3,887~52 3,733.74 ·3.040.33 27,104.19
Ave. 171. 78 59.86 38.11 28.97 22.35 22.23 22.37 30t..83 598.32 299.04 287.21 233.87 2.084.94
The Average of 2.084,940 Acre-Feet per year = annual average flow of 2880 cfs.
AREA-ACRES II 1,000 -25 20 15 10 ............
~ ~ ~ ~ ~ 17 ,"' ~ .
~
MAX.NOR •. W~ 150
-. ~~ IIJ ~ iii
AVE. EL.136 ()I
It)
/' IIJ
0
J> 125 V ~ '\ MIN. WS 118
/' It)
""
.... ,...,
0)
UI
100 o.
J> --"-I :'I K '-75 1 ~ ~ ""'-50 1/ ~
25
..
0 o 100 150 200 250 300 350 400 450 500
CAPACITY-ACRE-FEET II 10,000
FIGURE 7.4.3(3) BUCKLAND RIVER AREA -CAPACITY CURVE
r I -
: 1
U
r ' I ' J
f 1
i J
C I
U
, ,
!w
r
W
7.4.5 Geology
The proposed damsite would be located in territory basalt which
apparently covers cretaceous graywacke and conglomerate. Most of
the proposed reservoir area is covered with quaternary unconsoli-
dated sediments. Suitability of the basalt as basement rock for a
water reservoir would have to be determined in a field
investigation.
7.4.6 Transmission Facilities
Overhead transmission at 138 kV, three phase with 795 KCM ACSR
conductor would result in less than 5% vol tage drop and 1.4%
power loss for a peak load of 20 MW. Energy losses are estimated
at 3%.
Transformers at the powerplant would step the generated vol tage
up to the 138 kV level and a step down substation near Kotzebue
would connect to the existing 4.lfi kV distribution system. The
transmission route would lead almost due north to the Kauk River,
then approximately follow the north shore of Eschscholtz Ray and
along the Baldwin Peninsula to Kotzebue. The total length of the
transmission line would be approximately 98 miles. The line
would follow established winter trails and would be constructed
during the winter season to eliminate the requirement for a
permanent access road. Operational maintenance access would be
by helicopter or Rolligan type vehicles.
7.4.7 Cost Estimates
The estimate14fost of constructing the Project is presented in
Section 8.0 , which presents a summary of the direct
construction cost and an estimate of the total capital
investment, using recommended FERC account numbers.
7.4.8 Power Production
The first stage of development with 10,000 kW units would have a
prime capacity of 10 MW and produce 87,600 MWh of firm energy and
an annual average of 53,655 MWhof secondary energy.
The second stage of development with three 10,000 kw units would
have a prime capacity of 20 MW and would produce 141,255 Mwh of
prime and average annual energy.
(4)see Section 8.0 of this report: Cost Estimate.
7-42
t.:, ,
7.4.9 Environmental and Other Concerns
Preliminary investigations indicate that
supports salmon,' char, pike, whitefish,
populations.
the Buckland River
turbot and grayling
The valley is also utilized by caribou and moose. The reservoir
created by a dam at t'he proposed location would inundate this
area and destroy part of the mammal habitat. as well as spawning
and rearing grounds for the fish. It has not been determined
whether archaeological sites are located in the area that would
be inundated. Occurrences of· fossil ized remains of Pleistocene
mammals (mammoth, bison, etc.) have be~n reported in the Buckland
River area, however. A detailed archaeological study is
therefore recommended to locate possible sites.
The topographical data used for this' study indicate that
reservoir would partially flood the communi ty of Buckland.
detailed survey would have to be performed to establish a
height that would prevent inundation of this community.
the
A
dam
with little information available on the environmental impacts of
such a project, a detailed environmental reconnaissance will have
to be performed before an assessment of feasibility can be made.
7.4.10 Land Status
The damsi te is located wi thin a vi llage wi thdrawal and most of
the reservoir within. state selected land. The transmission line
would traverse lands selected by the state and villages and would
have to cross the proposed selawik National Wildlife Refuge
(Federal Land Policy Management Act of November 16, 1978,
Emergency Order 204E) for approximately 60 miles.
7.4.11 Alternate Development Plan
The cost estimates by Retherford show that approximately 38% of
the total cost of construction are allocated to the transmission
line.
Retherford further stated that if single phase, low frequency
generation and transmission would be considered, it is estimated
that s )the cost of transmission lines could be reduced to only
23% ( of the total construction costs. It is assumed that the
generating equipment costs approximately the same as three phase
equipment.
(S)Retherford's write-up modified by removing his cost
estimates from this paragraph.
7-43
i ' ~
u
w
i 1 U
u
u
I 1
U
W
fl .~
u
w
w
u
l'
W
U
I
jU
'W I
IU
iW
r : ~
u
Preliminary investigations into the availability of
a. low frequency, single phase equipment, ann
b. phase and frequency conversion equipment indicate that
Japanese or European firms are building similar
equipment and are interested in supplying it for the
relatively small scale applications under
investigation in Alaska.
7.4.12 Utilization of Electric Heat(6)
This task acknowledges capacity of electric resistance heaters as
a means of satisfying the near terms (next 20 years) heating
requirements.
7.5 GEOTHERMAL (ALTERNATIVE "0")
7.5.1 Description of the Potential Geothermal Resource
The use of geothermal energy as a possible alternative energy
source has been investigated as part of an on-going study of the
future energy needs for the ci ty of Kotzebue. While 'Kotzebue
does not occur in what is normally considered a typical
geolog ical setting for exploi table geothermal energy, two
petroleum exploration test-wells (Chevron Nimiuk Point No. 1 and
Cape Espenberg No.1) discovered that an abnormally high
geothermal gradient occurs· in the area. The findings of these
test-wells, al though not conclusive, suggested that geothermal
waters may exist under Kotzebue that could be used as an
alternative energy source. In addition to drilling the petroleum
exploration wells, Chevron Oil Company also conducted a seismic
reflection survey of the Kotzebue area to determine the
underlying bedrock structure. These seismic data, existing State
of Alaska aeromagnetic and gravity data, and the results of data
obtained from the exploration wells have been previously analyzed
to assess geothermal potential for the region (Energy Systems I
Inc. 1981, Ehm 1981). These analyses were conducted based on the
recommendations in a previous study (Retherford and Associates
1980) prepared for the Alaska Power Authority that suggested that
the utilization of geothermal waters for space heating may be a
viable energy alternative. Ehm (1981) and Energy Systems Inc.
(1981) recommended that geothermal energy was not a likely
economic source for power generation but that district heating
may be feasible.
(6)Added for this report.
7-44
A key element in this recommendation was the interpretation of
the depth to basement given in the Ehm (1981) report. The
validity of this interpretation was reaffirmed in the present
study.
The ini tial depth-to-basement determination was interpreted by
Chevron based on their seismic data. Mr. Ehm reanalyzed this
data himself, and agteed with the Chevron interpretation (Arlan
Ehm, personal communication, 1982). A leading expert on the
geology of northwestern Alaska, Dr. Robert Forbes, professor
emeritus of the Geophysical Institute, University of Alaska, was
also consulted on this matter. Dr. Forbes felt the thinning of
the basin in the direction of Kotzebue was surprising, but, based
on the existing geophysical data, irrefutabl~. Unless the
substantial additional costs (i.e., piping, right-of-way
development, insulation, etc.) associated with a geothermal
development; outside t,he immediate environs of Kotzebue could be
economically borne by the project proponents, feasibility would
depend entirely on the usefulness of water at a temperature
defined by the assumed geothermal gradient above the projected
basement rock interface underlying Kotzebue.
All individuals contacted in the present study agree in principal
with recommendations contained in the Ehm (1981) and Energy
Systems, Inc. (1981) reports. In order to fully analyze the
possibility of any geothermal development at Kotzebue, test
well(s) would need to be drilled. The costs of such a well would
be extensive, and may not be justified by the present
understanding of the likelihood of finding an economically viable
resource. For the purposes of this study, a typical, well
drilling and testing sequence has been specified, and is
described herein. This allows the substantial cost of such an
exploration program to be included in an assessment of the
economic feasibility of geothermal resource usage in the Kotzebue
area, based on present understanding of the subsurface geology.
7.5.2 Geologic setting
Kotzebue lies on the northwestern edge of the Baldwin Peninsula
within the Selawik Basin (Figure 7.5.1). No bedrock is exposed
on the Baldwin Peninsula due to an extensive cover of non-
inundated Quaternary age deposits. For this reason, any
inferences concerning the pre-Quaternary geology of the area are
biased on project ions of geolog ic trends from the surround ing
regions, remote sensing data (i.e., seismic reflection, gravity,
and aeromagnetic), and data collected from two petroleum wildcat
test-wells (Chevron Nimiuk Point No.1 and Cape Espenberg No.1).
The Selawik Basin is bordered on the south by the Seward
Peninsula, a complex geologic terrain' consisting of Precambrian
to Quaternary sedimentary, metamorphic, and igneous rocks. The
Baird and De Long Mountains form the northern boundary of the
basin. These are composed predominantly of lower Paleozoic
metamorphic rocks, and ,middle Paleozoic to Mesozoic sedimentary
r 1 ~
f 1
W
u
u
u
u
[ I
I •
~
u
u
, r l
'~
----------
~.. --I'
""," --0'1
---
POINT HOPE
"
----
CAPE
ESP£NBERG
MISSION
DELONG
DEERING
BENDELe-a EN
MAR6'S IGLOO 41"$
... PILGRIM HOT
SPRINGS
°NOATAK
--
o °KIANA
NOORVIK '" SELAWIK BASIN
°SELAWIK /
)
N
l'
°AMBLER'
°KOBUK o
SHUNGNAK
----
° °BUCKLAND
CANDL.E
o KM 80 ..... __ ...:..::..:. __ ...J.
SCALE
, FIGURE 7.5.1
Location map.'
(from Ehm 1981)
° HUSLIA
and igneous rocks. In the on-land extens ion of the Selawik
Basin, east of the Baldwin Peninsula, Cretaceous sedimentary
rocks and Tertiary volcanic rocks are exposed. In the Hope
Basin, west of the Baldwin Peninsula (Figure 7.5~2), Tertiary age
sediments lie unconformably on Mesozoic sedimentary rocks. The
Hope Basin shallows toward the east and is entirely absent east
of Hotham Inlet.
A seismic reflection survey was conducted by Chevron from
Kotzebue southeast approximately 14.4 miles to Nimiuk Point
(Figure 7.5.2). The results of this survey show that Kotzebue
lies above a basement high within the Selawik Basin and is
underlain . by approximately 2013 feet of sedimentary rocks
overlying metamorphic basement rocks.
The gravity data supports this interpretation. The seismic and
gravi ty data show that the basin deepens toward the east and
south of Kotzebue~ ~his was verified by the tesi-wells at Nimiuk
Point and Cape Espenberg.
The rocks penetrated at the Nimiuk Point test-well consist of
Tertiary age conglomerate, sandstone, siltstone, clay, and minor
lignitic coal (Figure 7.5.3). These unconformably overlie
Cretaceous porphyri tic andesi te and basal t, that in turn
unconformably overlie metamorphic rocks tha.t form the regional
basement. The seismic data suggest that the upper Tertiary
sedimentary stratigraphy is fairly continuous from Nimiuk Point
to Kotzebue. The lower port ion of the sed imentary section and
the volcanic rocks do not appear to occur beneath Kotzebue based
on the seismic data (Figure 7.5.2).
Warm water was found during drill-stem tests at both the Nimiuk
Point No. 1 and Cape Espenberg No. 1 test-wells. At Nimiuk
Point, within the 3557 ft to 3778 ft depth test-interval a net
rise of 3385 ft. of fluid was recorded. The fluid included
drilling mud, muddy salt-water, and clear salt-water. The
recorded temperature for the produced waters was 107 0 F (42 C).
The water encountered in both the Nimiuk Point No. 1 and Cape
Espenberg No. 1 test-wells is connate water, or water that was
included with the sediments during burial and expelled into
subsurface aquifers during diagenesis (the process by which non-
indurated sediments become lithified). This is ancient water and
is not recharged from the surface. The size of the aquifers
within the Tertiary rocks is not known. The Chevron test-wells
tested the most promising hydrocarbon-bearing horizons, not the
water-bearing horizons. For this reason, data concerning the
aquifer size and production rates are not available.
The water that was produced during the drill-stem test at Nimiuk
Point contains 90,000 ppm total dissolved solids. Of this total,
76,263 ppm is NaCl (salt). The formation pressure in the tested
interval was 1,552 psi and was able to push the fluid column to
within 112 feet of the ground surface.
7-47
I : ..
~
w
u
w
u
I !
W
I 1
W
r 1
..J
u
I !
W
[ I ~
U
U
11 ~
u
u
u
r 1
I
~
...J
I
.A
co
A
NW
KOTZEBUE
KOTZCBlle
SOIlNO t'
Sl
~600 III
-J2oo m
-1800 III
SHAllOW stlS",c
McrAIiORPHICS
H 11 H
8
SE
NIMtUK POINT NO. I
NorNAIi
INter
--------j--------
Dt/ArCRNAR'f
8 rellt/Allr
CLASHes
'tt .. d
-1000'
MOO'
-2itOO m <--------------------------------------...:--------.J~.ooo~
o
I .<:iI
I o
I
I SCALE
~--------------------~
KM
SCALE
8 (AFTER CHEVRON)
FIGURE 7.5.2
STRUCTURAL CROSS SECTION FROM
KOTZEBUE TO NIMIUK POINT No. 1
FROM SEISMIC REFLECTION DATA.
(from Ehm 1981)
. ! ,
,
I,
o
300
600
1200
..... :.: ....... : '.:~.
. . _. 0-_·.·-.
1600 --_~~:.:
fjlf#~if;t2
.~:~S6 ~<~i~:: :·:6·-:c;.~:~·.:~.;¢.f.
1800 s~s;ssS'S!;SSS
fr5 s'S r i(: ; .... ~ f <c
TO 1923 m
I .
LE G END
C==:J NO SAMPLES
t:::::::=J CLAY
~ SAND a SANDSTONE
Ie> C> .,.1 GRAVEL a CONGLOMERATE
I J COAL a WOOD
,wvvvv! VOLCANICS
~ SCHIST
e:::t::9 CARBONATES a MARBLE
~ FORMATION TEST
B/PF BASE OF PERMAFROST
FIGURE 7.5.3
Nlmiuk Point No. 1 test-well log.
(from Ehm 1981)
7-49
I
i ...
'j
! I
~
1~1
W
i 1 , I
~
r i
W
J
U
u
u
f 1
( \
L.J
u
r J
W
7.5.3 Geothermal Resource
No actual geothermal exploration investigations have been
performed in the Kotzebue area. The Nimiuk Point No. land Cape
Espenberg No. 1 test-wells were petroleum . test-wells and
penetrated a thick section of Tertiary to Cretaceous age
sedimentary and volcanic rocks prior to entering greenschist
facies metamorphic rocks at total depth. The bottom-hole
temperatures in both wells are approximately the same (72 to 73
C) although the depths are significantly different, 6350 ft. and
8400 ft. respectively. These temperatures are abnormally high
for their depths below the surface. At Nimiuk Point No. 1 the
calculated geothermal gradient is 113.8° F/mile and at Cape
Espenberg No. 1 the calculated geothermal gradient is 96° F/mile,
both of which are higher than the mean value for the worldwide
geothermal gradient of 86° F/mile. While the geothermal gradient
data suggest the possibility of higher temperatures at depth, the
basement metamorphic rocks are incapable of supporting a hot
water system due to their lack of porosity and permeability.
Therefore, any geothermal resource will have to be developed
within the Tertiary age sedimentary section.
The bottom-hole temperatures recorded in the test-wells drilled
at Nimiuk Point and Cape Espenberg appear more related to the
basement metamorphic rocks than the thickness of the Tertiary age
section. It seems unlikely that temperatures similar to those
found in the bottom of the test-wells will occur at the base of
the Tertiary section underneath Kotzebue. The calculated
geothermal gradient for the Nimiuk Point test-well predicts that
the temperature at the base of the Tertiary section under
Kotzebue is approximately 81° F. This would have to be
considered a minimum temperature. The maximum expected
temperature would be 185° F, which is the temperature recorded at
the bottom of the Nimiuk Point test-well. The actual temperature
will most likely fall between these two.
These temperatures are too low for generation of electrical
energy and possibly even too low for district space-heating
considering the severe temperature conditions that occur at
Kotzebue. ·Within the Paris Basin, France, low-temperature (140°
F or 60 C well-head) geothermal water is used for district space-
heating assuming a minimum external temperature of 23° F.
When external temperatures fall below 23° F a back-up system is
necessary. A similar but expanded situation may be possible for
Kotzebue. The geothermal water may be used for start-up water
and thus avoid the cost of heating surface water (approximately
32° F to 41° F) to the tempetature of the geothermal water (80.6°
F to 162° F). This could result in significant fossil fuel
(coal, oil, gas) savings. This is the same conclusion reached by
Retherford and Associates (1980) and Energy Systems, Inc. (1981).
7-50
The quali ty of the geothermal water that is expected to occur
beneath Kotzebue is poor. Discharge of these "brines" onto the
surface could have severe environmental impacts. However, since
the geothermal aqu i fers are not recharged from the surface, it
may be necessary bo re-inject the geothermal water after heat
extraction to keep up the flow-rates and reservoir pressures.
This closed system approach will alleviate the environmental
concerns over the discharge of geothermal waters on the surface
and preserve the geothermal resource.
7.5.4 Geothermal Exploration Program
Data acquisi tion, is necessary on the geothermal resource and
aquifer concitions underlying Kotzebue. The Nimiuk Point No. I
test-well found that low-temperature geothermal waters occur in
the area., The basin characteristics diffe'r, however, between
Nimiuk Point and Kotzebue.
Nimiuk Point is underlain by approximately 6600 feet (2000 m) of
Tertiary and late Cretaceous sedimentary and volcanic rocks
overlying metamorphic basement. The seismic reflection data
indicate that Kotzebue is underlain by only approximately 1980
feet of Tertiary sedimentary rocks. These sedimentary rocks have
a lower thermal conducti vi ty than the metamorphic rocks and act
as an insulator. This probably accounts for the high geothermal
gradients found at Nimiuk Point and Cape Espenburg and the
similarity between the bottom-hole temperatures. At Kotzebue,
the decreased sedimentary cover and reduced insulating effect
could result in an even greater geothermal gradient and a lower
temperature at the top of the metamorphic rocks.
The deep aquifer conditions .in the Kotzebue area are unknown.
The Nimiuk Point No. 1 test-well did not test the most prom-
ising water-bearing horizons. For this reason data on the
aquifer size, temperature, and flow-rates are necessary prior to
fully assessing the geothermal potential. These data may be
gathered from drilling a geothermal test-hole to a depth of
approximately 990 feet to 1980 feet. The deeper depth is
recommended because it will penetrate the metamorphic basement
and thereby provide the maximum amount of information on the
geothermal resource. The test-hole should be drilled at a
sufficient diameter to allow testing of the aquifer flow
characteristics as well as water temperature. A two-phase
geothermal test-well program is described in appendix "C".
7.5.5 Geothermal District Heating
7.5.5.1 General Discussion
Little is known about the geothermal potential at Kotzebue
(exploratory confirmation wells are needed). Because of the
local interest in using geothermal energy if at all possible and
7-51
I : I • ~
w
w
u
u
I '
W
u
u
u
f 1
W
U
I 1
~
u
w
Q
I :
Q
I
n
W
o
u
r 1
W
u
u
u
{ ,
(
LJ
I :
u
:U
I
U
Q
I
Q
I
-, , ,
i I
to justify any exploration to locate and define the potential
resource, all engineering and economic evaluation of a geothermal
alternative for Kotzebue assumes a "best case" scenario. It is
presumed that if a so called "best case" scenario cannot compete
with other alternative heat and electrical power sources, there
will be little application for an extensive exploration program
such as that described in appendix C. Conversely, if geothermal
alternatives for heat and electrical power generation are shown
to be economically feasible of the best case resource, it may be
justifiable to pursue such an eiploration program. This
evaluation is based on the assumption that there is sufficient
formation water available.
7.5.5.2 Design Conditions
o Water temperatures 162°F an optimistic temperature
assiJmption.
o Heating level at year 2002 is 38.81 x 10 6 Btu/Hr. This
heat load value has been adjusted from the yearly averages
to peak load requirements anticipated, including
temperature and seasonal variations a'6dline losses for a
system design heating load of 100 x 10 Btu/Hr.
o Wells 8 Geothermal
4 Injection
o Rate of Flow -each well assumed to be 788 gpm.
7.5.5.3 Conceptual Design
Ba~ed on these assumed design loads, the heat supply using
geothermal energy was evaluated. This design concept is ghown in
Figure 7.5.4. To satisfy the heating demand of 100 x 10 BTU/Hr,
eight geothermal wells would be required each producing 788 gpm
of brine. The output from these wells would be reinjected in
four injection wells.
It is assumed that the eight production wells would be drilled on
two pads,' each containing four wells, and that the injection
wells would all be contained on one pad.
The concept design would require eight boost pumps to bring the
geothermal fluid to the surface (112 feet) and raise its pressure
to a sufficient value such that it could then pass through to the
geothermal filters.
Each well would have a filter which would consist of two 400
micron strainers and a hydroclone separator. These filters would
remove any debris from the fluid before it would enter the main
pumps and heat exchanger.
After the fluid has been filtered from each well, the fluid will
flow into a header system where the main geothermal transfer pump
will then take the combined flow of 6300 gpm and increase its
pressure to 170 psi. This high pressure is required to keep any
7-52
FIGURE 7.5.4
SCHEMATIC GEOTHERMAL DISTRICT HEATING CONCEPT
WASTE
HEAT
BOILER
ENERGY
STORAGE
.... -......... TANK
DIESEL
ENGINES
EXHAUST
PUMP
DISTRICT
HEAT SUPPLY
PUMP
PUMP
DISTRICT
HEAT
RETURN
PUMP
DISTRICT
HEAT
PROCESS HEAT
.... _,.GEOTHERMA
FIL TER
GEOTHERMAL
TRANSFER P--~~~rvln~--"---~--~-----"
PUMP
EOTHERMAL BOOST PUMP
8 WELLS
(PRODUCTION)
7-53
GEOTHERMAL
INJECTION
PUMP
4 WELLS
(INJECTION)
i \
w
w
u
j ,
I i.I
I I
W
f I
~
w
w
u
u
u
w
r ;
.J
u
, ' U·)
r '
W
iU
t 1
: ) u
W
u
dissolved gases (i.e. nitrogen, CO 2 ) above the evolution pressure
to prevent scale deposits. This nigh pressure geothermal stream
then flows into the central plate and frame heat exchanger.
The central heat exchanger will have an area of 34,332 ft2. The
approach temperature on the hot side will be 2°F while on the
cold side. it will be 6 ~F. The temperature of the geothermal
brine entering the heat exchanger will be 162°F.
The brine will leave the heat exchanger at 130°F. The
temperature of the glycol solution (60% by' volume ethylene
glycol, 40% water ---70°F freeze pt.) entering the exchanger
(countercurrent flow) is 124°F. This solution leaves at a
temperature of 160°F. The flow rate of the geothermal fluid is
6300 gpm whereas the flow rate of the glycol solution on the
district heating side will be about 6600 gpm.
The output geothermal fluid from the exchanger will be used to
heat the process buildings and heat water for domestic use at the
facility prior to being reinjected back into the formation. The
geothermal brine is then reinjected into four injection wells
using four injection pumps, each flowing at 1575 gpm at 820 psi.
The district heating side of the central heat exchanger will take
the geothermal heat and distribute it in accordance· with a
specified distribution plan. To distribute this heat, two pumps
will be used, one on the output side of the exchanger and one on
the input side. These pumps will maintain an over-all system
pressure of 70 psi. The flow rate for the glycol system is 6600
gpm.
Since the pumps are large, they can be either driven electrically
or through the use of diesel engines. If these pumps are driven
electrically they would require 5.8 MW of power. If they were
driven using diesel engines, these engines would be adapted for
total waste heat recovery which would be used to supplement the
·geothermal energy used for district heating.
Th~ waste heat recovery from the diesel engines amounts to 22.1 x
10 Btu/hr. The heat is to be stored in a 1000 gallon tank of
ethylene glycol with immersed heating coils to exhaust the
heat. The temperature of the fluid leaving the tank and entering
the heat exchanger in the output district heating line is
200°F. The returning fluid temperature is 165°F.
Using the waste heat from diesel engines, the temperature of the
district Reating line is increased to about 166°F. Approximately
2.2 x 10 gallon of diesel fuel will be l."equired to run the
diesel engine to drive the pumps in the year 2002.
7-54
7.5.5.4
7.5.6'
Major Equipment Requirements for Geothermal District
Heat Source
L Heat Exchanger (Main)................. 34,332 ft 2
2.
3.
4.
5.
6.
7.
8.
9.
Geothermal Transfer Pump ••••••••••••••••• 1040 HP
6300 gpm
170 psi
Geothermal Well Pumps (8) •••••••••••••••••• 100/HP
~ach pump 75 kW/each pump 788 gpm
Geothermal I njection Pumps (4) ••••••••••• 1250/HP
each pump
2892 kW/
each pump
1575 gpm
820 psi
District Heating Pumps (2) ••••••••••••••••• 340 HP
25 kW'
6644 gpm '
50 psi
Heat Recovery Reservoir •••••••••••••••••• 1000 gal
Geothermal Transfer Pipe •••••••••••••••••• 16 inch
District Heating Pipe ••••••••••••••••••••• 15 inch
Wells
8 P .-1 t' 9 5/8" D1' a • . rouuc 10n.~ ••••••••••••••••••••••
4 I , t" 9 5/8 II D1" a • nJec ion ....................•..•.
Geothermal Power Plant (Organic Rankine Cycle)
7.5.6.1 General Discussion
A conceptual design of a geothermal power plant for Kotzebue
using a closed loop organic Rankine cycle with isobutane as the
working fluid is presented in the following paragraphs~
The design of this power plant is based on the assumption that
there is suffidient formation water at 162°F at the basement of
the metamorphic rock.
In the overall design, the isobutane will exchange the heat frOm
the geothermal brine solution, vaporize, and then transfer this
energy to the turbine generator. The geothermal brine is pumped
from various production wells, through a heat exchanger (pre-
heater), and a high pressure boiler, and is then reinjected back
into the reservoir through the injection wells. A simplified
flow diagram is presented in Figure 7.5.5.
7-55
r 1
W
r '
W
I ' W
r ,
U
U
U
U
U
r 1 ~
u
w
u
r ' i I
U
I
I
I
U
D
r J
I \
LJ
! :
U
I ,
LJ
, ;
l.J
, 1
W
I '
I
7.5.6.2 Conceptual Design
The details of the conceptual design will be described as
specific systems within the total plant. These systems are: (a)
isobutane, (b) geothermal, (c) turbine-generator, (d) cooling
water, and (e) support.
(a) Isobutane System
The isobutane is to extract the heat energy from the geothermal
resource'and transfer this energy to the turbine-generator. This
system is a closed loop, two-phase organic Rankine cycle. This
system works in the following manner. The condensate feed pump,
(500 horse power, 4160 volts) takes the condensate from the
condensate tank of 20 psia and 25°p and raises this feed to a
system pressure of 155 psia to enter the pre-heater. In the pre-
heater the isobutane is heated to a saturated liquid at 160°F and
155 psi~~' The vaporized isobutane stream then enters the turbine
where its energy is extracted in perfor~ing work. The isobutane
then exits the turbine in the vapor state at a temperature of
123°F and 20 psia and enters the exhaust condenser where it is
condensed to a saturated liquid at 25°F and 20 psia and flows by
gravi ty into the condensate tank from which the condensate feed
pump takes suction and the cycle is repeated.
This system also includes the necessary vents, drains, and
provls lons for charg ing the system wi th isobutane from 60,000
gallon storage tank. Due to the vol at iIi ty of isobu tane, the
system has extensive gas monitoring equipment to detect any
hydrocarbon leakage.
,(b) Geothermal System
The geothermal system is to provide the thermal energy necessary
for the isobutane system. The geothermal energy is extracted
from four production wells. Each well has a down-hole booster
pump to raise the fluid the final 112 feet to the surface and to
act as a pressure source (90 psi). The geothermal brine is
passed through a geothermal filter which consists of two 400
micron strainers and a hydroclave separator. This filter removes
any of the debris from the fluid before it enters either the
pumps of heat exchangers.
After the brine is filtered, the flow stream is divided each
using a booster pump to bring the system pressure up to 170
psi. One stream supplies the heat for the high pressure boiler
to completely vaporize the isobutane while the other stream is
7-56
FIGURE 7.5.5
SCHEMATIC GEOTHERMAL POWER CONCEPT
r •
GEOTHERMAL
FILTER
GEOTHERMAL RESERVOI R
7-57
TURBINEI-'!!~GENERA OR
AIR CONDENSER
CONDENSATE TANK
L-f-....t INJECTION
PUMPS
u
w
w
w
u
u
u
r)
~
U
W
U
[ 1
~
I I ~
w
w
u
[1
~
W
o
iD
I
U
I
: I
W
u
u
u
used in the pre-heater. to heat the isobutane to a. saturated
liquid. These booster pumps ensure that the geothermal fluid
remains in the fluid state above the gas evolution pressure, thus
ensuring a high heat transfer efficiency· and the prevention of
scale deposi tion. Each of the two geothermal streams are then
reinjected into separate wells with the aid of injection pumps.
(c) Turbine-Generator System
The turbine-generator wi 11 convert . the heat energy into
electrical energy. This system consists of a turbine, generator,
piping and control instrumentation. The turbine is a radial
inflow unit that operates in the isobutane Rankine power cycle.
The unit is designed to expand the isobutane from 155 psia to 20
psia to produce the desired power output.
The isobutane vapor is supplied to the turbine through a 10-inch
header and would be equipped with appropriate throttle valves and
flow meters. The flow control would be regulated by the turbine
governor. The turbine back-pressure is governed by the exhaust
condenser.
After the isobutane is heated and expanded by the geothermal
fluid, it is passed through the turbine and discharged to a
water-cooled condenser for recovery and reuse.
The generated power output of 4160 vol ts would be fed into the
Kotzebue power grid.
(d) Air Condenser
The air condenser will provide a heat sink for the organic
Rankine cycle. Air is used in the turbine exhaust condenser to
remove the waste heat from the isobutane working fluid.
The fluid input to an air-cooled condenser is isobutane vapor.
The design of the finned tube sections will require drip pockets
and pressure equalization lines to maintain equal flow conditions
in the tube bundles. Arrangement for the application may be
vertical, mounted on an integral condensate rank, or arrangement
can also be asembled for a remote condensate tank. A pressure
controlled fan will provide air flow across the condenser tubes.
(e) Support Systems
The support systems required by the facility are: (1) isobutane
flare system, (2) instrument. air and ni trogen systems, and (3)
industrial water system.
The isobutane flare system is to safely dispose of iso.butane
vapors from· the process and from the storage area. This flare
system will dispose of the isobutane vapors during filling and
draining of the system, to receive leakage from isobutane vents
and drains during various operations of the plant, and. to burn
7-58
the contents of the isobutane system 'should an emergency arise.
The vapors to be disposed of are collected in a knockout drum
wher,e liquid is separated from some of the other combustible
gases. From the knockout drum the gases flow to the flaring
unit.
The instrument air and nitrogen system will supply compressed air
for instrumentation, control, and other utility use. The
nitrogen is used for emergency back-up for instrumentation, and
for purging of the piping and various components during initial
start-up and during operation. The nitrogen will be stored in
two 3,QOO-ga111on tanks along with the isobutane.
The industrial water system is to provide water for fire
protection~
7.5.6.3 Major Requirements for Geothermal Power Plant
1.
2.
3.
4.
5 •
6.
7 .
8.
9.
10.
11.
12.
13.
14.
Turbine-generator ••••••••••••••••••••• 10.0 MW
Geothermal pre-heate~ feed pump •••••••• 170 HP
127 kW
1034 gpm
170 psi
Geothermal high pressure boiler pump •• 1730 HP
1290 KW
10,476 gpm
170 psi
High pressure boiler
Heating coi1s •••••••••••••••••••• 6,555 ft;
Vo1ume ••••••••••••••••••••••••• 600,000 ft2
Turbine air condenser ••• ~ ••••••••••• 2,400 ft
Isobutane condensate tank ••••••••• 40,000 gal.
Geothermal boost pumps (14 ea.) ••••••••• 46 HP
34 kW
822 gpm
57 psi
Geothermal injection pumps (10 ea.) •••• 920 HP
682 kW
1151 gpm
820 psi
Condensate feed pump •••••••••••••••••••• 40 HP
30 kW
3525 gpm
20 p:;;i
Pre-heater •••••••••••••••••••••••••••• 800
Geothermal Filter
(Hydroc1one, strainers) •••••••••••• 14 each
Isobutane storage tank •••••••••••• 60,OOO gal.
Cryogenic nitrogen tank •••••••••••• 3,000 gal.
Isobutane Flare system ••••••••••••••••• 1 each
7-59
r I
~
w
u
, I
W
I I
W
u
u
I
U I
U
; 1
I I
~
u
( 1
W
u
• 1
( 1
u
7.6 OTHER (ALTERNATIVE "E")
7.6.1 Energy Conservation
7.6.1.1 General Discussion
In order to demonstrate the potential in energy conservation in
future and existing houses a number of calculations have been
made (see Appendix "E") concerning heat loss from traditional and
improved structures. The results are shown in this section while
the calculations are shown in detail in Appendix E. Insulation
standards of future houses have been investigated by computing
construction costs and heat losses through a number of different
types of walls, floors and roofs. By way of using present worth
methods optimum insulati.on standards have been establ ished as
well as standards for doors and windows. The possible use of
thermal shutters has also been investigated by way of using
present value (worth) method.
For existing structures, an example is given of the possible
gains from addi ng insulation and from general improvements such
as sealing of leaks by doors and windows, etc.
It is obvious that existing structures must be of a reasonably
fair quality to justify the spendings done on improvements. In
each case a house must be carefully audited to determine whether
to improve it or to construct a new house using new standards.
In this study typical housing built in 1976 by the Housing
Authority has been examined as this type represents approximately
10% of the dwellings in Kotzebue and is· considered to be a
traditionally built house at or above average standards regarding
thermal insulation.
A detailed study of the heat losses from recently .constructed
housing has been made and an example of possible improvements is
shown.
wi th these improvements made, the heat losses have once aga in
been calculated in order to show the net savings. The resul ts
should be seen as indications of the potential and not as exact
figures of heat losses, as certain details are not taken into
account.
The study shows that energy savings of up to 50% can be expected
for houses of this type and the necessary investments will have a
pay-back time of approximately 9 years.
It should, however, be noted that less drastic improvements with
smaller investments will have shorter pay~back times and thus for
each house life expectancy should be taken into account to
determine a desired insulation standard.
7-60
•
7.6.1.2 Energy Conservation In New Houses
In order to evaluate the benefits from improving insulation
standards in new houses, calculations were made for construction
costs 'of different types of walls, roofs, and floors.
For each type the yearly heat loss was determined.
For the purposes of economic calculation, real interest was set
at 3.0 percent and real inflation on heating oil was set at 2.6
percent. Thus calculations can be made regardless of current
overall inflation rates.
The price ~f heating oil was set at 1.46 Sigal.
Knowing th,e heat loss per unit of surface, the yearly cost of
maintaining 65° F oJ;l one side of the surface was determined
according 'to the number of heating degree days for Kotzebue.
construction costs per unit of surface were calculated and this
together with the costs of heating formed the basis for
calculating the present worth figures for different surfaces.
Thus the present 'value can be expressed as the total CO!?t of
constructing a square foot of wall (roof, floor) and maintaining
the necessary temperature difference between the outer and the
inner surface over a 20-year period. As the name impl ies, the
value is at present; it is to be paid at the time of
construction.
As some uncertainties do exist in
costs, and in calculating the heat
seen as guidelines to insulating
values.
estimating the construction
losses, the figures should be
standards and not as exact
construction costs have been estimated .using the "Building
Construction Cost Data 1982" published by the Robert S. Means
Company, Inc. with an average multiplier of 2.33 from the lower
48 to Kotzebue.
Conclusions:
As can be seen in Figures 7.6.1 and 7.6.2, the inSUlation in
walls should amount to 8 to 13 inches of fiberglass and in floors
to 9 to 14 inches of fiberglass. Insulating roofs is normally a
rather simple and cheap operation and this, in turn, increases
the optimum insulation thickness to 10 to 20 inches of fiberglass
as seen in Figure 7.6.3. The curve is rather flat which means
,that the gain from increasing insulation thickness to more than
10 inches will be limited.
7-61
I '
I.J
r :
~
i 1
W
! 1
~
I 1 W
u
r I
W
I ;
.J
r ,
W
u
'D I
W
IU
W
r ,
LJ
r
LJ
r '
r '
r
IW
LJ
U
u
I
U
IW
I
:U
I
FIGURE 7.6. 1
PRESENT VALUE FOR WALL CONSTRUCTION AND HEATING
ON A 20 YEAR BASIS
17
18
'0
016 ..
4)
~
CD
::I
C7 en
~
4) 14
Do •
13
12~------~----~----~------~----~----~
6 8 1 8 9 10 11 12 13 14 15 18 11
thickness in inches
7-62
I", '"
FIGURE 7 .6.2
PRESENT VALUE FOR FLOOR CONSTRUCTION
AND HEATING ON A 20 YEAR BASIS
17
....
0 16 0 -CD ..
CO
::I cr en ..
CD a.
(I)
14
13
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
insulation thickness in inches
7-63
I i
~
r I ~
w
w
w
w
w
~
u
u
u
: 1
W
U
W
W
W
W
U
U
1° I
r 1
\~
U
U
r I
!W
U
, ,
l.J
r 1
U
r I
W
i
~
I .
l.J
I
iW
U
D
~
FIGURE 7.6.3
PRESENT VALUE FOR ROOF CONSTRUCTION
AND HEATING ON A 20 YEAR BASIS
17
5 e 7 8 9 10 11 12 13 14 15 16 7 18 19 ,20 21
insulation thickness in inches
7-64
FIGURE 7.6.4
CO~STRUCTION COSTS PER UNIT WALL,
ROOF OR FLOOR WITH· VARIOUS INSULATION STANDARDS
...,
o o -! co
:::I
i .. • a. .,.
14
8
5 8 8 10 11 12 13 14 15 18 17 18 18 20 21
Insulation thickness In Inches
7-65
i '
~
,
W
f I
W
W
U
U
r 1 u
U
U
U
U
U
W
W
~
U
W
U
U
I
w
w
o
U
J
U
U
U
r '
..J
r .
LJ
r ,
U
r '
U
U
U
D
D
U
w
I~
FIGURE 7.S.5
YEARL Y CONSUMPTION OF HEATING OIL PER SQUARE FOOT OF
WALLS, ROOFS AND FLOORS FOR INSULATION STANDARDS.
.... o o ,..
G ..
C\S
:::I .,. .,
0.30
0.25
..
G)
Q. 0.15 .,
C o -'i
CD
..... floors
I __ -+_-!r~oofs
o,_o~~-+~ ___ ~ __ ~~~~~~~~~~~~~~~_
5 6 7 8 9 10 11 12 1 3 14 1 5 16 17 18 1 9 20 2 1
insulation thickness in inches
7-66
Windows should be of the 2-or 3-pane type as this gives energy
savings as compared to single pane windows of 55 and 67 per cent
respectively. Construction is, however, somewhat more expensive
and thus the economic benef i ts are lower. Compared to single
pane windows the economic savings on a 20-year basis are 39 and
42 per cent respectively.
If t~ermal shutteis are used as described, energy savings on 2-
and 3-pane windows as compared to single-pane windows will be 52
and 65 per cent respectively and the economic savings will be 27
and 26, per cent respectively. Thus, it can be seen that if
thermal shutters are used it witl not payoff to install 3-pane
windows. There will still be a small saving of energY1 however,
this saving is not big enough to compensa,te for the added
construction costs.
7.6.1.3 Energy Conservation In Existing Houses
In this section, an analysis was performed on an existing typical
house in order· to determine the possible gains from
retrofitting. Current heat loss was calculated and a
retrofitting program aimed at bringing the house up to the latest
standards was selected. The cost of retrofitting was established
together with the heat loss from the retrofitted house and this
provided the basis for calculating the payback time for the
capital invested in the retrofitting program.
Conclusions:
For a commercial investment such pay-back times would often be
considered unacceptable. However, for residential investments a
pay-back time of 9.3 years could be reasonable.
The above-mentioned improvements would not necessarily have to be
.made all at one time as they do not have the same pay-back times.
The installment of 2-pane windows should be given the highest
priority as should the reduction of infiltration losses.
The utilization of thermal shutters over 2-pane windows would pay
off in approximately 7.1 years and thus should be given high
priority. It is, however, recognized that added thermal comfort
caused by the .shutters is partly offset by the feeling of sitting
inside a box.
Night set-back of temperatures could provide a 7% savings of the
total heating expenses. Adjustments and modifications of stoves
and furnaces could provide savings of the same magnitude at a
relatively low cost.
7-67
i i
U
u
u
• I
W
u
I 1
W
w
w
u
u
u
r ! U
r I
j
U
I •
I •
U
u
D
I
W
The study indicates that improvements should be made in the
following order:
1) Sealing and caulking to reduce infiltration losses.
2) Modification or adjustments of stoves and furnaces.
3) Night set-back of temperatures introduced.
4) Replacement of single-pane windows wi th dual or triple
pane windows.
5) Improvements of doors wi th urethane foam insulation or
equivalent.
6) Insulation of roofs, walls and floors.
7) Installation of thermal shutters.
7.6.1.4 Impacts from Drastic Conservation Measures
Until now it has been common practice to equate a high energy
consumption with a high standard of living. This situation has,
however, changed since the first energy shortage in the early
seventies and new engineering practices have shown that·
decreasing energy consumption can be a way of increasing the
standard of living.
The most obvious example
comfort experienced in
energy consumption is
traditional houses.
of this is the greatly increased thermal
well-insulated and sealed homes where
decreased significantly compared to
where the
justified
existing,
pay their
quality of houses is below certain levels, it may be
to construct new houses instead of improving th~
in order to enable the people living in these ~ouses to
heating bill without sacrificing other necessities.
As the constructioq of a large number of new houses makes. large
investments necessary, it may often be necessary to spend
available funds on ei ther decreasing consumption or on making
supplies cheaper.
The economic
decisions are
simple.
results are
based solely
fairly easily
on these, the
determined
operation
and if
is quite
However, due consideration should be given to other impacts such
as improved health standards, increased satisfaction with life in
general, reduced social tension, and reduced anxiety for the
future as increases in oil prices will have less severe
consequences.
7-68
In Kotzebue a portion of the houses are of such quality that
replacement should be considered. If. a large-scale improvement
plan was carried out during the next 20 years this could result
in a 50% reduction of heating expenses for private residences as
compared to an uncontrolled development with heating demands as
described in the forecast (see Section 4).
In the high forecast it is anticipated that the growing demand
for floor area is met by building more new homes.
In th'e improvement pl~n it is anticipated that the Jo Max type
houses are maintained while new housing is improved as described
in Section 7.6.1.1. Over a 20-year period enough new houses of a
quali ty equal to the recently constructed housing are built to
meet ,the growing demand for floor area and. to completely repl?ce
all houses 'that cannot be brought up to the standards of at le~st
the Jo Max houses. This calls for construction of 835,965 squ~re
feet of new residential floor area.
AnrHal space heat demand for residences in 2002 will be 6.4 x
10. Btu/year which can be provided with approximately 593,000
gallons of oil. This is approximately 140 gallons per person per
year, al though this is obviously disproportiona1ly spli t, and
residents of older housing may expend a significant part of
income on heating bills.
At a cost of $100 per square foot, a total replacement of the old
houses will cost approximately $30 million. Thus it is obvious
that from an economic point of view replacement is an expensive
way of saving energy. As mentioned earlier, however, the
increased standard of living is hard to evaluate economically.
In Kotzebue the. replacement of a large number of houses should be
seen as a joint effort to ease some of the problems caused by
high prices of energy and to give the people of Kotzebue energy
efficient housing.
7-69
I .
.J
u
u
u
u
r 1
U
r 1
W
u
w
u
w
u
1 U
iW
U
iW
I
( ,
l..
I f I
IJ
, ' i
I •
1000II
u
I
U
u
u
u
U
D
D
u
u
7.6.2 Electrical Conservation
General
It is difficult to estimate the impact of electrical conservation
wi thout structural and electr ical systems aud its. The metho-
dology used herein attempts to provide a relative indication of
the impact using broad parameters. A more exacting methodology
is outside the scope of this report.
The parameters used in this analysis are 1) penetration level and
2) a percent energy reduction for each application.
1) Penetration varies from user to user and each
broad class of user as defined in Table 3.1 is
treated as a single entity. The penetration
value is an estimate of the number of devices
that could be retro-f i tted to accommodate the
conservation device under consideration.
For lighting the penetration figure indicates
changing incandescent fixtures to high
efficiency fluorescent units, and replacing
standard fluorescent fixtures with high
efficiency units in existing structures.
Power factor (P.f.) correction devices are used
for inductive devices and thus the "appliance"
load is affected through . their use.
Penetrat ion is 1 imi ted to the number of
inductive devices found under this load
category.
Energy management (EM) systems can have a
penetration level as high as 100% although this
may be a bi t extreme in the study area. The
only case not considered for EM systems is
residential.
2) The percent reduction factors used to determine
load reduction in the various categories are
quite conservative as far as the manufacturers'
1 i terature is concerned. Lighting loads have
been reduced by more than 50% using the task
and available lighting strategies. This result
was obtained on actual use in an Anchorage
office building. A reduction factor of 18-20%
is used in this analysis. The power factor
devices are a little harder to quantify as no
Alaskan testing results have been released as
yet. Testing of power factor devices is
planned to take place in Kotzebue at the water
and sewer treatment facilities this spring. A
conservative value of 6% reduction in energy
use will be assumed pending test results.
7-70
i
I
I'
. !,
. I
Residential
A difference in the kWh allocations exists between values given
in Table 3-1 and the values used in this analysis. An amount of
27% of the total kWh useage will be attributed to lighting and
57% of the total for inductive devices. The penetration for
'lighting is estimated at 50%. This figure represents to some
degree personal preference some people cannot tolerate
fluorescent lighting as well as outside and entrance way
lighting' where extreme temperatures preclude the use of
fluorescent devices.
Power factor penetration is
load. The implementation
indicat~d would provide an
residential sector.
Commercial (incl. A.pts.)
estimated at 75~ Of the inductive
of thes~ devic~s to the degree
overall reduction of 5.4% for the
The lighting penetration is assumed to be 75%. This is due
mainly to the ability of commercial users to . recognize the
economics of lighting load. reduction plus the ability to
implement the installation of these devices. Again, there are
applications where these strategies are not relevant or cost-
effective, i.e.,exterior lighting, etc.
Power factor. penetration for the non-commercial appl iances is
assumed at 50%.
Commercial appliances are considered to be items such as large
pumps, compressors for freezers (walk-in) and large
refrigeration/cooling units, fans, blowers and some resistive
, devices, al though the major portion of the load is considered
inductive. A penetration level of 75% is used.
Energy.management is quite applicable in this area. Large
apartments and hotels are prime candidates for EM systems.
Again, since the application of EM systems are structure-
specific, a modest penetration of 50% is used.
The results indicate a 9.4% reduction in electricl energy.
Industry such as hotels and manufacturing plants have realized
energy reductions as high as 25%. Stores have shown reductions
'of 20-30%.
Public (Including city)
Lighting penetration is
lighting.
75% without consideration for street
u
u
u
u
u
u
. 1
U
W
The power factor penetration level of 80% was developed with the [I
. assumption that the majority of the appliance loads are ~
7-71
~
ID
~
U
r 1
W
u
: 1
'lJ
, 1
U
f
W
U
I
W
D
D
inductive. A factor used in making this assumption is the highly
inductive load developed by the sewage treatment and water
utility systems.
The Energy Management system penetrat ion level of 75% ref lects
the dispersed quality of the public/city loads. This fact also
reduced the percent reduction in energy.
The overall reduction accomplished at the indicated levels of
penetration is approximately 14%.
School
A lighting penetration level of 100% is used in the school system
due to the highly structured and thus more easi ly controlled
environment (At least where electrical energy is considered).
The power factor penetration level of 50% is used due to the
possible existence of kitchen facilities providing a resistive
load which would not be affected by p.f. devices.
Energy management has a penetration of 100%.
to the highly structured environment.
This is due again
The overall reduction produced with these measures at the given
penetration levels is in the vicinity of 20%.
Hospital
The lighting penetration is assumed to be 75%. This follows a
similar rationale in that a structured environment is maintained
in this type of facility.
The penetration level for power factor devices is kept low due to
the abundance of med ical equ ipment used that mayor may not
accept them. A penetration level of 30% is used.
The Energy Management system is rated at 100% penetration.
An overall reduction of 20% is the end result of these measures.
FAA
Lighting penetration is kept low due to the existence of airport
and facility lighting which mayor may not benefit from
conservation measures due to specifications of the type of
lighting necessary to perform specific functions i.e., rotating
beacon. The penetration used is 30%. This reflects the housing
and warehouse/shop lighting load.
The p6wer factor penetration is also comparatively low due to the
energy consumed by the electronic and communications equipment
utilized by the FAA. A penetration of 50% is estimated.
7-72
Energy Management penetration is also reduced. This was done due
to the fact that government faci 1 it ies have been mandated to
reduce consumption of all forms of energy and it is assumed that
"manual" energy management has already been implemented.
An· overall reduction of 6.1% is the predicted result of the
measures described •
. Summary
The reduction in energy levels for each conservation measure have
been purposely kept low due to the extremely si te-and device-
specific requirements necessary to develop accurate power
reduction levels.
Results from testing that
obtained for a more precise
indicating' that the values
conservative.
is currently in progress should be
estimation. Preliminary results are
used in this analysis are generally
Nonetheless, wi th the levels of penetration used and reductions
assumed, the total reduction in energy realized is in the order
of 10% of the total electrical load.
This value could increase if new construction is designed with
energy conservation as a concept and not as a retrofit.
The 10% reduction in energy applied to the energy forecast is
shown below iri Table 7.6.1, and a graph depicting these values
can be seen in Figure 7.6.6.
YEAR
1981
1985
1990
1995
2000
2002
TABLE 7.6.1
USAGE WITH ELECTRICAL CONSERVATION
ENERGY 3 FORECAST
x 10 KWH
10,676
14,113
20,224
27,680
36,420
42,500
7-73
ENERGY FORECAST
WITH ELECTRICAL
CONS~RVATION
x 10 KWH
9,608
12,702
18,202
24,192
32,778
38,250
I \
I
~
! ,
~
I \
W
i i
u
u
( 1 J
w
w
• 1 U
W
I
U
I
U
I
I U
U
r 1
W
I
U
i I
~
I . ~
u
Additional Benefits Not Considered
o The use of the power factors controllers with penetrations
indicated would serve to reduce the reactive component in
the utility grid thus reducing losses in transmission and
switchgear, as well as reducing fuel consumption required
to provide that reactive current.
o The motor~ that operate with p.f. correction would produce
less heat, thus increasing their service life~
o Many p.f. controllers contain loss of phase and brown-out
protection which will also increase motor life in the
event of partial power loss in 3-phase applications.
7-74
TABLE 7.6.2
.ENERGY REDUCTION DUE TO ELECTRICAL CONSERVATION
User
Present
Annual Load End Use
(kWh)
Present·
Annual Load Penetration
By Type (%)
(kWh)
% Load
Reduction
(%)
Annual
Savings
(kWh)
Reduced
Annual Load
(kWh)
Commercial 5.293.000 COM. APPLIANCE 1 445 100 75 5 4.793.987
(Incl Apts) ENERGY 50 5
MANAGEMENT
liGHTS
Public-Inc. STRT. lIGHTS 4
586.000 APPLIANCE 3
City ENERGY
MANAGEMENT
lIGHTS 803,000
School 89S.0q0 APPLIANCE 295000
ENERGY
MANAGEMENT
~T 532400
Hospital 747,000 214600
LIGHTS 562,900
FAA 780,600 APPLIANCE 226600
ENERGY
MANAGEMENT
Total 10P~!:e~~
N/A
80 6
75 8
75 20
50 6
100 10
75 20
30 6
100 10
30 20
50 6
50· 10
122.923·
14794
32,169
90450
8850
. 79,870
79860
63
. 66,328
33,774
6798
.37,000
503,987
718,830
598.949
.703.026
9,551,737
10'l60ver All
Reduction
u
r
W
I I
W
u
This table represents a breakdown of the reductions possible with
r
,
electrical conservation. The penetrations and %. load reductionl i
factors are to be considered conservative indications of load.
reductions.
Percentages of reductions by user are:
0 Residential = 5.4%
0 Commercial = 9.4%
0 Public = 15.9%
0 School = 19.6%
0 Hospital = 20.0%
0 FAA = 9.9%
r 1
W
7-75
FIGURE 7.6.6 LIGHT AND APPLIANCES kWh/YEAR WITH
ELECTRICAL CONSERVATION
80
6 0
• I
0 • ... 4
" PROJECTED l·
~/I
RECORDED I" 00 V. .... ~
,~
... ·1 ~. ~ . ./ / i/ .' .
</ .. .. / . . '
0 ~ .. 2 .0 V~ with electrical
. .... . . 0./ .0
:/ con.,ervatlon. .. . ' .' ~ .. . ' ;;~ .' 0 •• 1 ...... ,.
• ~ .
t ••• •
0
1970 1980 1990 2000
year
7-76
7.6.3 Wind Energy
7.6.3.1 General Discussion
Wind Energy utilization in the Kotzebue Sound Area can take many
forms. Windmills or water pumpers could be utilized for
producing mechanical energy. The illustration below shows the
full menu of possibilities for wind energy conversion systems
using a conventional turbine.
For the purposes of this study, we have confined our discussion
to the simplest and most commercially available technology. We
further required ~he technology to have been successfully
demonstrated in Alaska to date. Through this process grid-
intertied wind generators were chosen as the best systems for
Kotzebue. Even though a resistive heating wind generator looks
extremely' practical,' one gets more economic value by displacing
high quality grid electricity than by displacing demand which can
be satisfied through direct combustion.
The most common grid intertie system uses an induction generator
and is operated primarily as a fuel saver for the base load
facility. Because of the need for the induction system to have a
source from which. to draw a 60 cycle signal it cannot stand
alone. The turbines in the 200 kw or larger class typically are
of a synchronous generator type and thus are capable of stand-
alone power production. However, the cost of controls are high
and their developmental nature today precludes their commercial
use in Kotzebue until the 1990 time period.
Because of this developmental nature of the majority of the wind
industry, it was necessary to estimate the commercial readiness
of the large turbines for the Kotzebue Sound. Several small
machines have been tested in Kotzebue successfully (once the
start-up bugs were worked ou t), but machines larger than 10 kw
should be considered a demonstration project at this time. There
is presently a proposal to use Kotzebue as a test site for larger
wind turbines, which if implemented will eliminate a lot of the
uncertainty surrounding utility scale wind generators in Northern
Alaska.
The following figure assumes a phased introduction of turbines
into the grid, with the smaller units being installed first. At
no time does the total installed capacity of wind generators
exceed 30 % of the average load on the fuel-fired base load
system.
7-77
i
W
• 1
I I ~
u
u
u
w
w
w
I
W I
J
I
J
J
I
J
:w
I
IU
U
1
: I W
u
, l
, 1
~
.. I
ii'
FIGURE 7~6.7 POSSIBLE WIND SYSTEM CONFIGURATIONS
d
c::i
fuel cell
hot water
heating
system
vacuum
pump
A.C.
pumped water
CII Q :§
ell <C
Q) .c ... u
Q)
.!:
"0
D.C. hot battery
water heater bank
hydraulic
storage
A.C.
generator
7--7 P.
switch
Q diesel d
Q engine Q
D.C.
generator
... __ .. compre88ed
storag,
air turbine
A.C.
generator
i
I
I
{
I
I
I
I
-• ~
1 -8
.~
I
!
i
I
FIGURE 7.6.8 NUMBER OF WINDGENERATORS ON-LINE
7-79
j !
W
. 1 ~
i I
W
u
u
u
w
w
w
u
w
w
w
f
J
I
J
I
J
I ,U
I
I i
I W
,
I U
U
I
~
u
l.J
( 1
D
rl I
III
7.6.3.2 Power Production Analysis
The wind data available for Kotzebue has been· collected since
1945 and is sufficient for estimating power production of a wind
system. At the anemometer height (9.4m) the annual average wind
speed is 13 mph (5.8m/s) with a cor2es p onding annual average wind
power availability of 309 watts/m. At a wind generator hub
height of 59m the annual wind speed would be 16 mph (7.3m/s) with
631 watts/m of annual average wind power. This is a significant
resource with slight seasonal variations and very low diurnal
fluctuations (especially during the winter months). The
following table represents the annual energy output of
representative turbines in Kotzebue's wind power class of 5.
7.6.3.3 Conclusions
The results of this study show a reasonable number of
commercially available wind turbines can supply a small portion
of the annual load safely and reliably • The 30% penetration
constraint placed on the wind systems is in fact a conservative
assumption which only actual operating experience can refute.
The problems of intertieing a larger percentage of Kotzebue's
load with wind energy are mostly unknown and beyond the scope of
this work. However, the potential does exist for a significant
fuel savings with wind generators, and the 10% reduction shown in
this analysis should be considered a practical minimum. A
concerted effort to demonstrate wind energy in Alaska would
accelerate the time frame proposed for introduction of the larger
turbines. On the other hand, enough uncertainty exists with the
technology that more optimistic assumptions should be avoided at
this time.
If a district heating system is pursued which involves some
thermal storage, an assessment of the use of asynchronous wind
generators for resistive heat would be important. The resistive
heating techno1goy is simple, more reliable, and has been
demonstrated in cold climates successfully.
7-80
TABLE 7.6.3 POWER PRODUCED' BY TURBINE DIAMETER
(1) Turbine
Diameter (m)
4
7
10
17
25
91
Rated
Power (k.w)
1.8
10
25
65
200
2500
Rated Wind
Speed (mph)
24
25
26
26
30
28
(1) See also volume II, Appendix D
7-81
Annual Production
(10 3 k.wh)
8
35
60
200
580
9000
I '
~
:-1
W
i .
1 ' ~
f 1
W
U
i .
W
,I
W
. i~l
.~
U
LJ
~
~
iU
'W I TABLE 7.6.4 ANNUAL POWER PRODUCTION BY WINDGENERA TORS
U
U
lj
U
r \
r I
W
U
r :
W
YEAR
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
NO. OF TURBINES
65 kw 200 kw
1 0
2 0
3 0
4 0
5 0
6 0
7 0
7 1
8 1
8 1
9 1
7 2
9 2
9 2
10 2
8 3
9 3
10 3
8 4
10 4
TOTAL % OF
ANNUAL PRODUCTION TOTAL ANNUAL LOAD
(10 3 kwh)
200
400
600 4%
800
1000
1200
1400
1980 10%
2180
2180
2380
2560
2960
2960
3160 11%
3340
3540
3740 10%
3920
4320 10%
7-82
8.
COST ESTIMATES
n ~
D SECTION 8
r' u COST ESTIMATES
TABLE OF CONTENTS
r 1 U
U 8.1 General .................................................... 8-1
U 8.2 Base Case.................................................. 8-2
8.3 Cogeneration (Alternative A)...... ......................... 8-5
r
.J 8.4 Coal Fired Low-Pressure District Heating System
(Alternative B)...... .........•. ....... ....... .............. 8-8
U 8.5 Hydropower-Buckland Site (Alternative C).. .... ..... ..... ... 8-11
8.6 Geothermal (Alternative D)........ ............. ............ 8-16
U 8.7 SUlllrnary •..... " .................. !It • " ....................... ~ • • • .. 8-19
r "
LJ
, 1
U
U
r '
U
U
J
D
D
D
D
I
W
I
iD
r ' w
;-i
I I ~
r
W
]:
W
u
'~
I
W
D
SECTION 8 COST ESTIMATES
8.1 GENERAL
The following cost estimates were prepared for the systems most likely to
be used in Kotzebue (see Sections 7 and 10). These estimates consist of a
summary and project schedule. There are differences in the degree of
system details available on the various alternatives. Consequently the
estimator, to provide as realistic a comparison as possible, found it
necessary to vary the contingencies to offset differences in some
alternatives. Additionally where detail was not available, other projects
of similar sizes were used as a basis for quantities or plant components.
Overall, the degree of detail provided makes for an adequate confidence
level in the overall alternative comparisons and anticipated costs using
1982 as a general basis. For additional information, please refer to
Appendix F, which includes additional data as used for preparing these
estimates.
As noted in Section'l and elsewhere, Alternatives liB" and liD" relate to
District Heating systems only. In this section, the estimates include
costs for: (1) coal-fired stearn electrical plant for Alternative "B", and
(2) geothermal steam electrical plant for Alternative "D". Consequently
only the Distribution system portion of these alternatives has been used,
when applicable, in Section 10: Plan Evaluation.
8-1
, I
8.2 BASE CASE
For estimating purposes, the following data were assumed:
Plant ~ 60' x 90' X 24'
Foundation -Pilings
Plant Floor -12",concrete
Plant Building Structure -insulated steel structure
Slte Pa~ - 1 acre
Site Pad Thickness -4' ,
This projec~ w'as envisioned as being constructed in a single contract and
in one construction season. The project would, however, have to be
constructed as three simultaneous projects by either one or two general
contractors. The two projects would consist of the new diesel plant,
modificatiol).s to the existing plant, office buildings, the five one-million-
gallon oil storage tanks, 'and the distribution system.
It is entirely feasible to construct the project in one season, which would
resul t in numerous economic gains. Involved in these economic gains are
reduced subsistence costs for labor, higher manpower efficiencies, reduced
equipment standby time, and other overhead costs.
Mobilization of the project would be, by sea with construction requiring six
months for the plant, other structures, and tankage and five months for the
distribution system.
The equipment and construction facilities for the distribution system would
then be demobilized September 1 of the first season, and the balance of the
equipment and construction facilities for the plant demobilizing
September 1 of the following year.
It is anticipated that actual construction of the plant will be completed
within six months with subsequent deactivation of the construction phase to
a caretaking status.
For comparison of other systems, a coal fired district heating system has
been included in the basic estimate.
8-2
I ' ~
u
u
! I
U
u
" 1 : I
~
11
iii
u
D
i 1
W
u
r '
r \
U
( ,
LJ
u
u
l.J
u
D
i -,
SUMMARY -BASE CASE
ITEM
I. MOBILIZATION TO KOTZEBUE
a. Labor
b. Matedal
c. Material Shipping
@ $8.50/100 lb.
(Dieael Generation)
(Distribut ion)
d. Equipment Shipping
@ $6.50/100 lb.
(Diesel Generation)
(DiBtribut ion)
2. JOB COSTS
a. L.abor
b. Equ ipment (Rental,
Maintenance, Parts.
and Fuel)
3. DEMOUIL.IZATION TO SEATTL.E
a. Labor
b. Equipment Shipping
4. ADMINISTRATIVE COSTS (25 wks)
8. Superintendent
b. Field Engineering (2)
c. Administrative (2)
d. l'imekeeper
O. Carotokur (12 wk~)
Subtotal
TOTAl. JOB COST
5. CONSTRUCTOR FEES
a. Contingency (lOX)
b. Bond and Overhead (2%)
c. Profit (12%)
Subtotal
TOTAL. CONSTRUCTION COST
6. ENGINEERING FEES
Professional Services (7%)
7. CONSTRUCTION MANAGEMENT (5%)
Subtotal
TOTAL. PROJECT COST
WEIGHT PLANT
00 3$)
$ 134.4
4,536.8
1,515 tons 257.6
200 tons
215 tons 36.6
230 tons
(See above)
8-3
$
2,201.1
1.334.3
100.8
36.6
8,638.2
110.3
191.1
147.0
58.8
31 •• 4
541.6
U,179.;i
$ 918.0
183.6
1,101.6
2,203.2
$11,383.0
796.8
569.1
1,3b5.9
$12,748.9.
DISTRIBUTION
SYSTEM
(loJ$ )
$ 100.8
1,784.1
100.3
48.8
1,379.9
649.0
75.6
48.8
$ 68.0
117.9
181.4
36.3
13.6
417.2
$4.604.5
$ 460.5
92.1
552.5
1,105.1
$5.709.6
$ 399.7
285.5
685.2
$6,394.8
, I
~
PROJECT SCHEDULE, BASE CASE
1. PRELIMINARY
I 1982 I 1983 I 1984 I 1985 I 1986
IJ J A SON DIJ F M A M J J AS 0 N DIJ FM AM J J A SON DjJ F M AM J J A SO N DjJ F M AM J J AS 0 N f~l
II II II ,I I,', II
DESIGN] I I I I
a. Plant 1------I I I I
b. Diesel I I I 1 1
Generators 1 I 1 I I
c. 011 Tankage] I I I I
d. New Offices I I I I I
e. Remodel I I I I I
EJ!:1sting I I I I I
Of £ices I I I I I
f. Substation 'I I I I
g. Distribu-I ----I I I
Hon System' I "
I I 1 I
2. MATERIAL 1 1 1 I
r 1
W
SUPPLY I 1 I I
CONTRACTS I I I'
PREPARATION 'I I' I
a. ,Diesel' I I'
Generators 1 I I I
u
b. 0:1.1 Tankage I I 1 I
c. Substation I I 1 I
d .. Distribu~ I 1 I I
'tion Systeml I 1 I
I' I I
3. MATERIAL I ' I 1 I
SUPPLY MANU-I 1 1 1 I
FACTURING I 1 I , 1
i I
U
a. Diesel 1 --1--------------1---------I I
Generation I 1 1 I 1
b. '011 Tankage 1 -1------------------1 1 I
<!. Substation I -1-----------------I , 1
d. ,Distribu-I 1---------------1 1 1 u
tion Systeml' 1 , 1
, I 1 I 1 1
4. FINAL DESIGN 1 1 1 1 1
a.'~lant and 1 ---1---------------1 1 ,
,Offices I' I 1 1
u
b. 011 Tankage 1 ----1-------I I I
c. "Substation 1 -----1----------I 1 1
d. ,Distribu-I I I I I
'tion System I -1------------------I 1 1
I I I I I
5. CON~TRUCTlON I I I I' I
a.:Plsnt. 1 1 -1-------------------1------I
:'OUces and 1 1 , 1 1 u
Substation 1 1 I I I
b. 011 Tankage I I ----------1-------------I 1
c. Distribu-'I 1------------1 I
tion System' I I I I
: ~ .
u
8-4
,U
u
D
r '
j I
1.1
r : w
u
I j
U
u
u
o
D
8.3 COGENERATION (ALTERNATIVE "A")
For estimating purposes, the following data were assumed:
Boiler plant -115' x 115' x 50'
Coal processing and ash handling plant -100' x lIS' x 30'
Foundation-pilings
Plant and processing floor -12" concrete
Plant and processing building structure -insulated steel structure
Site pad - 3 acres
Site pad thickness -4'
This project was envisioned as being constructed in a single contract and
in one construction season. This project would, however, have to be
constructed as two simultaneous projects by one general contractor. The
two projects would consist of the steam plant and the distribution system.
It is entirely feasible to construct the project in one seasons which would
result in numerous economic gains. Involved in these economic gains are
reduced subsistence costs for labor, higher manpower efficiencies, reduced
equipment standby time and other overhead costs.
Mobilization of the project would be by sea with construction requiring 12
months for the steam plant and 5 months for the distribution system,
utilizing extensive manpower double shifting.
The equipment and construction facilities for the distribution system would
then be demobil ized September 1 of the first season, and th!= balance of the
equipment and construction facilities for the steam plant demobilizing
September 1 of the following year. .
It is anticipated that actual construction of the steam plant will be
completed within 12 months with subsequent deactivating of the construction
phase to a caretaking status.
8-5
1,'1
SUMMARY, -COGENERATION (ALTERNATIVE "A")
~
STEAM DISTRIBUTION
ITEM WEIGHT GENERATION SYSTEM r i
1. ,MOBILIZATION TO KOTZEBUE
( 10 3$) (10 3$) U
a. Labor $ 134.4 $ 100.8
b. Materi al 10,907.6 1,784.1
c. Material Shipping U @ $8.50/100 lb.
(Coal-Fi red) 2,160 tons 367.2
(Distribution) 590 tons 100.3
d. Equipment Shipping
@ $8.50/100 lb. U (Coal-Fired) 220 tons 37.4
(Distribution) 287 tons 48.8
2. JOB COSTS
a. Labor 5,525.3 1,379.9 U b. Equipment (Rental, 1,765.0 649.0
Mai'ntenanc.e, Parts,
and Fuel)
3. ~EMOBILIZATION TO SEATTLE U a. Labor 100.8 75.6
b. Equipment Sh·i ppi ng (See above) 37.4 48.8
, , 18,875.1 4,ID;1 I 1
I U 4. ADMIN1STRAT/vE ~OSTS (39 wks)
. ·a'. Superintendent $ 172.0 $ 68.0
b. Field £ngineering (4) 596.3 117.9
c. Administrative (4) 458.7 181.4
W d. Timekeeper 91.8 36.3
e. Caretaker {12 wks) 34.4 13.6
Subtotal 1,353.2 417.2 ! I
TOTAL JOB COST $20,228.3 $4,604.5 W
~
5. CONSTRUCTOR FEES U a. Contingency (15%) $ 3,034.2 $ 690.7
b. Bond and Overhead (2%) 404.6 92.1
c. Profit (12%) 2,427.4 552.5
Subtotal 5,866.2 1,335.3 U
TOTAL CONSTRUCTION COST $26 1094.5 $5 1 939.8
6. ENGINEERING FEES· W Professional SerVices (7%) $ 1,826.6 $ 415.8
7. CONSTRUC'TION MANAGEMENT (5%) 1,304.7 297.0
Subtotal 3,131. 3 712.8 U
TOTAL PROJECT COST $29 ,225.8 $6 1 652.6
U
U
fl ~
U
8-6 W'
U
w
w
U
PROJECT SCHEDULE -COGENERATION (ALTERNATIVE "A")
D 1 1982 1 1983 1 1984 1 1985 1 1986 1 1987 1 1988 1 1989 I
1 M J S DI M J S DI M J S DI M J S DI M J s DI M J S DI M J S DI M J S 01
1 I i I I I I I I D 1. PRELIMINARY DESIGN' , , I 1 1 , 1 I
a. Plant 1 1 1 I I I i , i
b. Boilers I 1 1 1 , 1 1 I 1
c. Turbinel 1 I 1 1 1 I I I
D Generators I 1 1 I I I 1 1
I d. Substation I I I I 1 1 I 1
e. Distribution 1 1 I I 1 1 I 1
I System I 1 1 1 I I I 1
U 2. MATERIAL SUPPLY
I I I 1 I 1 I I
I 1 1 I I I I I
CONTRACTS I I 1 I I I I 1
PREPARATION I 1 I 1 I 1 I 1
a. Boilers I I I I I I 1 1
L b. Turbinel 1 I I 1 I 1 1 1
i Generators 1 I 1 I 1 I 1 I
I c. Substation -I I I I I 1 I 1
I d. Misc. Plant 1 I I 1 1 I I 1
r 1
Equipment I I I I 1 I I I
I
e. Distribution I I I I 1 I 1 ,
~ System I I 1 I I I I I
I I 1 I I I 1 1
3. MATERIAL SUPPLY 1 I 1 1 I 1 I 1 U MANUFACTURING I I 1 1 1 I I I
a. Boilers -1-----1--I I I 1 1 I
b. Turbine' 1 I I I 1 1 1 I
Generators 1--1--I I I I 1 I
r 1 c. Substation 1------1 I I I I I I U d. Misc. Plant I I 1 1 I I I I
Equipment -1-----1 1 1 1 I I I
e. Distribution 1 1 I 1 1 1 , ,
1 System -1----1 I I I I 1 I
lJ 4. FINAL DESIGN
1 I I , I I 1 I
I 1 1 I I I , I
a. Plant -1--.:..-----1 I 1 1 I , ,
b. Substation -1------1 I I I 1 I I
( 1 c. Distribution 1 1 I I I I 1 I
LJ System -1-----1 I I I 1 , I
1 I , , I I 1 I
5. CONSTRUCTION I 1 I , I I I I
0 s. Plant and I I I I I I , I
SUbstation I I -----1-----I I 1 1 I
b. Distribution 1 I I I I I I ,
SIstem I I -----, 1 I I I 1
W
D
0
0
D 8-7
8-4 COAL-FIRED LOW PRESSURE DISTRICT HEATING SYSTEM (ALTERNATIVE "B")
For estimating purposes, the following data were assumed:
Boiler plant -100' x 110' x 50'
Coal processing and ash handling plant -100' x 110' X 30'
Foundation -steel pilings
Plant and processing floor -12" concrete
Plant and processing building structure -insulated steel structure
Site paq - 3 acres
Site pad thickness -4'
This project was envisioned as being constructed in a single cont ract and
in one construction season. This project would, however, have to be
constructed as two simultantous projects by one general contractor. The
two projects would consist of the heating plant and the distribution
system. I
It is entirely feasible to construct the project in one season which would
result in numerous economic gains. Involved in these economic gains are
reduced subsistence costs for labor, higher manpower efficiencies, reduced
equipment standby time and other overhead costs.
Mobilization of the proJect would be by sea with construction requiring
nine months for the heating plant and five months for the distribution
system, utilizing extensive manpower double shift ing.
The equipment and construction f~cilities for the distribution system would
then be demobilized September 1 of the first season and the balance of the
equipment and construction facilities for the heating plant demobilizing
June 1 of the following year.
It is anticipated that actual construction of the heating plant will be
completed within 9 months with subsequent deactiviating of the construction
phase to a caretaking status.
8-8
i
I ' W
u
I 1 ~
u
[ 1
~
u
. 1
W
i 1
W
I ,
~
SUMMARY -COAL FIREU LOW-PRESSURE DISTRICT HEATING
D
SYSTEM (ALTERNATIVE "B")
COAL-FIRED UISTRIBUTION
ITEM WEIGHT P!ANT SYS~EM
(10 $) (10 $)
D l. MOBILIZATION TO KOTZEBUE
a. Labor $ 134.4 $ 100.8
b. Material 6.542.4 1,784.1
c. Material Shipping
@ $8.50/100 lb.
W
(Coal-Fired) 1,640 tons 278.8
(Dlstribut ion) 590 tons 100.3
d. Equipment Shipping
@ $8.50/100 lb.
U (Coal-Fired) 217 tons 36.9
(Distribution) 287 tons 48.8
2. JOB COSTS
a. Labor 3.837.9 1.379.9
U
b. Equipment (Rental. 1.145.1 439.0
Maintenance, Parts,
and Fuel)
3. DEMOBILIZATION TO SEATTLE
D a. Labor 100.8 75.6
b. Equipment Shipping (See above) 36.9 48.8
Subtotal 12.113.2 3.977.3
r ~ 4. ADMINISTRATIVE COSTS (36 wks) I U a. Super! ntendent $ 158.8 $ 68.0
b. Field Engineerin9 (2) 275.2 117.9
c. Administrative (4) 423.4 181.4
d. Timekeeper 84.7 36.3
W e. Caretaker (12 wks) 31.8 13.6
Subtotal 973.9 417.2 , :
J TOTAL JOB COST $13 1087.1 $4 1 394.5
5. CONSTRUCTOR FEES
U
a. Contingency (15%) $ 1,963.1 $ 659.2
b. Bond and Overhead (2%) 261. 7 87.9
c. Profit (12%) 1,570.5 527.3
f I Subtotal 3.795.3 1.274.4
I W TOTAL CONSTRUCTION COST $16 1882.4 $5 1 668.9
6. ENGINEERING FEES
U Professional Services (7%) $ 1.181.7 $ 396.8
7. CONSTRUCTION MANAGEMENT
Slush Fund (5%) 844.1 283.4
W Subtotal 2,025.9 680.3
TOTAL PROJECT COST $18 1 908.3 $6 1 349.2
U
D
D
D
U 8-9
i i
W
[1
W
PROJECT SCHEDULE -LOW PRESSURE DISTRICT HEATING SYSTEM W
I 1982 I 1983 I 1984 I 1985 I ~986 :I 1987 I 1988 I 1989 ;J
I M J S DI M J S Dj M J S Dj M J S Dj M J 'S DI M J S DI
I I I I I I I
1. PRELIMINARY DESIGN I I I I I I I
M J s DI M J .s DIU I ,I
I 'I
a. Plant I I I I I I I
b. Boilers I I I I I ,I I
c. Distribution I I I I I I I
,Sys,tem I I I II ~I !I I
I I I I :1 ,I I
I I
I :1
I IU 1 ,I
I ;1
2. MATERIAL SUPPLY I I J I 1 il I .I :1
CONTRACTS I I J ,I I I
PREPARATION I I 'I -I ,I :1
a. -Boilers I I I I 'I :1
I 'IU I :11
I :1
,b. Misc. Plant I I I ,I ~I I ,I I
Equipment 1 I I I I ,I
c. Distribution I J I I ,I I
System I I I I I I
J I I I I I
1 :IU I
I I
1 il
3. MATERIAL SUPPLY I I I I I I I I
MANUFACTURING I I I I >1 I
a. Boilers I -1--------:1----I ,I I
,b. Misc. Plant I I ,I I 'I I
Equipment I I -..--------1--I 1 I I
c. Distribution 1 1 I I I 1 I
System 1 -1---------1 1 I -I I
I I I I I I I
4. FINAl;; DESIGN I I 1 I I I I
a. PJ,:ant I -1-'----1 I I .I J
I IW I :1 :
.I :1
I !I
I :1, 1
I 'I: ,
I :IW_ I
1 'I
,b • Di,stribution 1 1 I I I I 1
System I -1----------1 I I I I
" I I 1 :1 I I I
I :IU I
I :I
5. CONSTRUCTION I I J I I 1 I
a. Plant 1 ,I I -----:----·1,----I I I
b. Distribution I I I' :1 I J I
S'stem I I I ------I I 'I I
I :1
I :1
'I
I
"
,', U
W
U
c,
U
W
U
U<
:,8-:LO
U
D
u
u
u
u
u
u
D
D
D
8.5 HYDROPOWER -BUCKLAND SITE (ALTERNATIVE "C")
General Description:
For estimating purposes, the following data were assumed:
Dam -rockfi 11
Dam he~ght -120'
Dam crest -10'
Reservoir slope -1.7 to 1
Spillway slope -1.7 to 1
Spillw~y slope transitioned into face slope of -1.4 to 1
Concrete reservoir facing -10"
Spillway width -1,200 to 1,000
Spillw~y facing -10"
Dam crest width -2,300'
. Dam crest ~oping wall -5'. high
Powerho~se -70' x 125'
Powerhouse' structure -insulated steel structure
The project was ~nvisioned as being constructed as seven separate maj~r
contracts. These seven contracts would consist of the supply of all major
powerhouse equipment items, all major substation equipment items,. the
construction of the transmission line and substation, the construction of a
runway, the construction of the· dam and dike, and the construction of the
powerhouse.
All dam, dike' and powerhouse construction activities would be mobilized and
demobilized by use of a 5,000'x 150' airstrip. The transmission line
construction equipment and some components would be mobilized over sea to
Kotzebue with some material components being mobilized by use of the
airstrip.
Helicopter support is seen as a requirement from both the Kotzebue and
Buckland River a~rstrip material sites. Demobilization of the transmission
line work would occur by utilizing the Buckland River airstrip.
8-11
SOLE 1.'13360
CONTOUR INTERVAL 50 FEET
045",0 UNES REP~f.~ENT <':.rOOT CONIOURS
OATU~ IS APPFlU(IMAH: M[AN SL\ ~.[',/tL
8-12
< ,,/ ,
,.I _ .J
I 1
I.J
U
U
U
W
U
U
U
U
U
U
W
W
U
W
W
U
U
W
u
r ,
LJ
u
r , u
, I
U
D
HYDROPOWER -BUC<LAND SITE (ALTERNATIVE "C")
Hydraulic Production Plant
Mobiliut ion
Runway
Dam & Sp i llway
Stripping
Quarry Stripping
Earth Excavation
Rock Excavation
Drill Grout Holes
Pressure Testing
Grout Cement
Intake Concrete
Grout Cap Concrete
Spillway Concrete
Headwall Concrete
Sp i llway Fl ip
Concrete
Coping Wall Concrete
Penstock Concrete
Stoplog Metal Work
Penstock, Tri-
udfication
Bleed Valvage
Rockfill Zone I
Rockfill Zone II
Leveling Coarse
Concrete Surface
Powerhouse
25,000,000 lb. @ $.29/1b. + labor
5,000' X ISO' (HERC)
50,000 cy @ $8.50 x 1.55 MF
20,000 cy @ $5.50 x 1.55 MF
200,000 cy @ $7.50 x 1.55 MF
40,000 cy @ $130 x 1.55 MF
25,000 cy @ $40 x 1.55 MF
1,000 crew hr @ $480 x 1.55 MF
5,000 sacks @ $62 x 1.55 MF
200 cy @ $1,650 x 1.55 MF
3,400 cy @ $640 x 1.55 MF
8,000 cy @ $700 x 1.55 MF
300 cy @ $1,400 x 1.55 MF
3,000 cy @ $700 x 1.55 MF
5,500 cy @ $600 x 1.55 MF
500 cy @ $470 x 1.55 MF
20,000 cy @ $4.60 x 1.55 MF
800,000 cy @ $1.50 x 1.55 MF
40,000 cy @ $20 x 1.55 MF
500,000 cy @ $12 x 1.55 MF
20,000 cy @ $30 x 1.55 MF
9,500 cy @ $1,000 x 1.55 MF
Subtotal
61,500 x 1.26 MF Site Excavation
Site Excavation
Rock
Poured Concrete
Metal Building
Complete
Electric Lighting
and Stat ion
Servicing
Electric Distri-
327,800 x 1.26 MF
3,278,700 x 1.26 MF
2,090,200 x 1.26 MF
bution and
Substation
Electric Controle
Turbine and
Generator
Erection - 3 ea.
Mechanical Systems
Crane
Plumbing System
Offices and
Finishes Complete
Operator's House (2)
Turbine and Generators
122,500 x 1.26 MF
327,900 x 1.26 MF
655,700 x 1.26 MF
840,200 x 1.26 MF
369,000 x 1.26 MF
327,900 x 1.26 MF
122,900 x 1.26 MF
82,000 x 1.26 MF
Subtotal
2 -20 megawatt Kaplans
1 -10 megawatt Kaplan
Turbines
Generators and Accessories
Subtotal
DemobiIi zat ion 4,000,000 lhe. @ $.29/1b. + labor
TOTAL HYDRAULIC PRODUCTION PLANT
8-13
3,100,000
3,800,000
2,000,000
6,900,000
$94,760,800
HYDROPOWER -BUCKLAND SITE (ALTERNATIVE "CO)
Transmission Plant
Mobil izat ion
Land and Land Rights
Structures and
Imp rov ernent s
Station Equipment
Transmission Line
$220,000 mile
5,000,000 lb. @ $.29/lb. + labor
500,000 x 1.39 MF
1,400,000 x 1.39 MF
Poles and Fixtures 66% x 98 miles
1,500,000
600,000
695,000
1,946,000
19,780,000
x 1. 39 MF "
$305,800/mlle Conductor and Devices 34% x 98 miles 10,190,000
Demobilization 1,500,000 lb. @ $.29/lb. + labor
TOTAL TRANSMISSION PLANT
1,000,000
Total:
I
Hydraulic Production Plant
Transmission Plant
Contingency 25%
Total Construction Cost
Engineering Fees
a. Professional Services (6%)
b. Construction Management (5%)
TOTAL PROJECT COST
8-14
$35,711,000
$94,761,000
35,711,000
130,472 ,000
32,618,000
163,090,000
9,785,OOO
8,155,000
$181,030,000
r
~
i I
U
i ;
W
W
U
U
U
U
U1
U
U
U
W
U
W
U
W
•
W
W
u
W PROJECT SCHEDULE -HYDROPOWER BUCKLAND SITE (ALTERNATIVE .. C .. )
~ 1 1982 1 1983 I 1984 I 1985 I 1986 I ' 1987 I 1988 I 1989 I
1 M J S 01 M J s 01 M J S 01 M J S 01 M J s 01 M J S 01 M J S 01 M J S 01
I I I I I I I I I
D 1. FERC LICENSING I I I I I 1 I I I
a. Feasibility 1 I 1 1 I I I I I
Study I 1------------1----I 1 I I I I
b. Environmental I 1 I I 1 I 1 I I
U Study I 1 --------1------------1 1 I I I I
c. Application fori I I I I 1 I 1 I
License 1 1--------1----------1 1 I I I I
I I I 1 I I 1 I I
2. DESIGN I I I I I I 1 I I
U a. Air Strip I I 1 1-----I I 1 1 I
b. Preliminary I I 1 I I 1 I I I
1. Powerhouse" I I 1----I 1 I 1 I I
2. Substation I I I I I I I I I
U
3. Transmission 1 I 1 I I I I I I
Line I I 1 1 I I 1 1 I
4. Dam & Dike I I I ----I I I I I I
I I I I 1 I 1 I 1
3. MATERIAL SUPPLY 1 1 I I 1 1 I I I r 1 CONTRACTS 1 1 I I 1 1 1 1 1 U a. Turbine Gene-I 1 1 I I J J I I
rators & Misc. I 1 1 1----I 1 1 I I
b. Substation I I I I --I I I I I
f 1 e. Poles & Con-I I I I I I I I I
LJ ductor I I I I I I I I I
1 1 I I 1 I 1 I I
4. MATERIAL SUPPLY I I 1 I I I I 1 I
MANUFACTURING I I I I 1 I I I 1
U a. Turbine Gene-1 I I I I I 1 I I
rators & Misc. I I "I I -----1-----" -I--I I 1
b. Substation 1 I I I 1--------1 1 I I
c. Poles & Con-I 1 I I 1 1 I I I
r 1 ductor 1 I I I --I-I 1 I I
LJ I I I I I 1 I. 1 1
I
5. FINAL DESIGN I I I I I I I I I
a. Powerhouse I 1 I j -----1--I I I I I I I I I 1 1 I 1 1 I b. Transmission
:--I Line I I I 1---------1 1 1 1 I U c. Dam & Dike I I 1 1---------1 1 1 1 I
1 1 I 1 I 1 I I I
6. CONSTRUCTION I 1 1 I 1 I I I I
U
a. Airstrip 1 1 1 I 1 I I 1 I
b. Powerhouse I I 1 1 1 ------1------------1-----------1 I
c. Transmission I I I I I Transmission Substation I I
Line & Sub-1 1 I 1 1 ----------1----------1-----------1 1
station 1 I I I 1 1 I I 1
U d. Dam & Dike I I 1 I 1--------1-------1------1 I
U
U
~
U
U 8-15
8.6 GEOTHERMAL (ALTERNATIVE "Oil)
For es timat ing purposes, the fo llowing data were assumed:
Plant -JO'xlOO'x24'
Foundation -Pilings
Plant Floor -12" Concrete
Plant Building Structure -Insulated Steel Structure
Site Pad -2.6 acres
Site Pad Thickness -4'
The project was envisioned as being constructed in three contracts and in
two construction seasons. The project would, however, have to be con-
structed as four simultaneous projects by either one or more general
contractors. The four projects would consist of test well program, geo-
thermal well program, constructing the plant and oil storage tanks, and the
distributio~ system.
Mobilization of the project would be by both air and sea with project time
requirements of 6 months for the test well program, 12 months for the
geothermal plant, 12 months for the drilling program, and 6 months for the
distribution system.
The equipment and construction facilities for the distribution system would
then be demobilized September I of the initial season, and the balance of
the equipment and construction facilities for the plant demobilizing
September 1 of the following year.
It is anticipated that actual well drilling and c~nstruction of the plant
will be completed within 12 months. with subsequent deactivation of the
construction phase to a caretaking status.
8-16
u
U,
u
u
w
SUHMARY-COGENERATION (ALTERNATIVE "0").
D STEAM DISTRIBUTION
ITEM WEIGHT GENERATION SYSTEM
003~) 003~)
1-TEST WELL PROGRAM $ 2,150.0 ~ 100.8
2. MOBILIZATION TO KOTZEBUE
a. Labor 434.4 2,415.0
b. Material 8,611.4
c. Material Shipping
@ $8.50/100 lb. D
(Coal-Fired) 1,825 tons 310.2
(Distribut ion) 890 tons 151. 3
d. Equipment Shipping
@ $8.50/100 lb.
(Coal-Fired) 215 tons 36.6
(Distribution) 225 tons 38.3
3. JOB COSTS
a. Labor 8,934.9 1,646.9 u
b. Equipment (Rental, 996.1 318.5
Maintenance, Parts,
and Fue 1)
4. DEMOBILIZATION TO SEATTLE D
a. Labor 100.8 15.6
b. Equipment Shipping (See above) 36.6 38.3
22,211.6 4,184.1
5. ADMINISTRATIVE COSTS (39 wks)
a. Superint endent $ 229.3 $ 68.0
b. Field Engineering (4) 195.1 117. 9
c. AumLllhlfllt LVII (4) ()11.6 181.4
d. Timekeeper 122.4 36.3
e. Caret aker (12 wks) 34.4 13.6
Subtotal 1,192.8 411.2
TOTAL JOB COST ~24,064.4 $5 1201. 9 u
6. CONSTRUCTOR FEES
a. Contingency (25X) $ 6,016.1 $1.300.5
b. Bond and Overhead W,:) 481.3 104.0
c. Profit (12X) 2,887.7 624.2 u
Subtotal 9,385.1 2.028.7
TOTAL CONSTRUCTION COST $33,449.5 $7 1 230.6
7. ENGINEERING FEES
Professional Services (7X) $ 2.341.5 $ 506.1
8. CONSTRUCTION MANAGEMENT (5X) 1 1672.5 361.5
Subtotal 4,014.0 tl67.6 r · W
TOTAL PROJECT COST $37!463.5 $8 1098.2
D
8-17
PROJECT SCHEDULE, GEOTHERMAL (ALTERNATE "D") w
1 1983 I 1984 I 1985 I 1986
I M J S DI M .J " S DI M J S D I M J S U
I I I I I
1. TEST WELL PROGRAM 1-------I 1 1
I I I 1
2. PRELIMINARY I 1 I I
DESIGN 1 I I I .~
a. Drilling Program I --------, I I
b. Plant I' 1 I I
c. Diesel Pumps I I I I
d. 011 Tankage I I 1 I
I
('
~
e. Distribution I I I I
System I I I
I I 1
3. MATERIAL I I 1
SUPPLY I I 1 ~
CONTRACTS 1 1 I 1
PREPARATION I I I
a. Diesel Pumps -I-I I
b. Oil Tankage -I-I I
c. Miscellaneous 1 1 1
U
1
Plant Equipment 1 I I
d. Distribu-I I I
tion System I I I 1 1 I ~
4. MATERIAL I I I I
,SUPPLY MAND-I I I
FACTURING I I I
a. Diesel Pumps I ---------1 I U
b. Oil Tankage 1 ------------------1 I
c. Miscellaneous -1------------------1 I
I
.1,
Plant Equipment 1 I 1
d. Distribu--1-------------------1 1
tion System I I I
1 I 1
i
~
1
5. FINAL DESIGN I 1 I
a. Drilling Program --: 1-------------1-:----I
b. Plant, -1---------------1 I U
c. Distribu--1------------------1 I I
Hon System 1 I I
I I I
6. CONSTRUCTION I 1 I
a. Drilling I I -----------1----------
b. Plant I I ---------------1-----------
~
I
c. Oil Tankage I I -------I
d. Distribu-1 I --------I
tion System I I I
[I \
W
U
U
U
U
W
U
8-18
W
U
D
I
'W
I
U
:U
I
U
c 1 u
u
i'
W
:U
I '
I
U
8.7 SUMMARY
In summary of the estimates as outlined, the following is noted:
1. It is suggested that material supply contracts should be provided
for all long-lead materials for whichever alternative is
selected.
2. The final design should include and incoprorate as many drawings
as possible from the material supply contractors.
3. As few as possible general contractors should be utilized on the
project, and hopefully this would only be one.
4. Economic cost evaluations should be performed evaluating the
concept of a pre-built complete module for the selected alter-
native, which in most cases appears to offer cost advantages.
5. All cost estimates as prepared are average in nature, so to speak,
with each project's possible development cost being capable of
either a lower or higher cost dependent upon the actual design
philosophy and the project's administration procedures. The cost
estimate for the geothermal program, however, is of an extremely
"minimal cost" nature.
6. The geothermal program is of a conservative nature, as outlined in
Item No. 5 above, due to the following:
a.Adequate aquifer flow is assumed as existing.
b. No makeup water system is assumed.
c. Well depth's assumed as 2,000' (shallow).
d. Design temperatures fo~ geothermal water is extremely
optimistic.
e. Well drilling costs are extremely optimistic.
£.. All system construction costs are very optimistic.
In other words. the total plant cost for the geothermal program
could easily be low by a factor of 20%, and if a supply water
system is required by as much as 30%.
7. Contingencies were varied by the estimators, based on the degree
of system detail available and the, as judged, system technology
reliability. These contingencies variances were done with the
concurrence of the Alaska Power Authority.
8. Overall capital cost summary for the most likely feasible
alternatives are:
8-19
System
0 Base Case
0 Cogeneration (AI t. A)
0 Coal Fired Low-Pressure
District Heating
(Alt. B)
0 Hydropower (Alt. C)
w/transmission line
0 GeQthermal (Alt. D)
Capital Costs $ x 10
Distributio~
Plant System
$12,126 $6,103
28,531 6,349
18 t 907 6,349
------
37,464 8,098 .
8-20
<3
al
$18,229
34,980
25,256
181,027
45,562
I 1
~
u
u
u
w
f1 U
;
~
~
~
~
~
~
9.
ENVIRONMENTAL EVALUATION
II
L
~
~
~
I
m
i
m
~
~
.~
~
~
D
U SECTION 9
ENVIRONMENTAL EVALUATION
U TABLE OF CONTENTS
U 9.0 General ............................................. 9-1
U 9.1
9.2
Base Case: Diese1 •••••••••••••••••••••••••••••••••• 9-1
Alternative A -Cogeneration ••••••••••••••••••••••• 9-3
~I 9.3 U Alternative B -Coal-fired Low Pressure
District Heating ••••••••••••••••••••••••••••••••••• 9-5
I ; 9.4
\.j 9.5
Alternative C Hydropower ••••••••••••••••••••••••• 9-7
Alternative D Geothermal •.••••.••.•••.••••••••••• 9-8
f :
W 9.6 Alternative E -Other Energy Measures •••••••••••••• 9-9
9.7 References ............................•..........• 9-10
LIST OF TABLES
( \ W Table 9.1 Coal Pile Drainage Water •••••••••••••••••••••• 9-6
u
u
r:
~
D
r : U
u
( :
W
i 1
D
D
D
,
SECTION 9 ENVIRONMENTAL EVALUATION .
9.0 GENERAL
Numerous energy alternatives for Kotzebue were placed in a matrix
and their environmental impacts· relatively compared in Table
6.1: Technical Profile Evaluations. Relative impact. ratings
were given for air quality, water quality, flora and fauna, land
use, and aesthetics. The ratings were, of necessity, somewhat
qualitative and no attempt was made to describe the impacts.
This section will discuss expected impacts only for the
alternatives felt to be most feasible.
It should be stressed that an evaluation cannot be in-depth at
this time because details concerning location size, in-plant
processes, mitigations, and other factors are unknown. However,
it is possible to discuss the impacts for each alternative in a
general manner. In development of the impact ratings and in the
discussion of impacts below, it was assumed that mitigations will
be used whenever possible.
Facility location plays an important role in impact determi-
nation. It was assumed that a facility utilizing coal or oil
would be placed south of the runway, in the vicini ty of the
landfill, and that a hydropower site would ·be .. located farther
from the village, in an area such as the Buckland River.
Geothermal generating facilities were assumed to be located in
the vicinity of the village. Individual conservation measures or
individual heating measures would be a part of each building in
the area, but would not require construction of an additional
facility.
It is also assumed that no threatened or endangered species exist
in .the vicinity of proposed projects. None are presently known;
should any be identified, impact of a facility at that site would
be greater than discussed below.
9.1 BASE CASE --DIESEL
Diesel fuel may be used for electric generation or for individual
heating by use of oil stoves. . In the latter case, emissions are
essentially nonpoint source in origin because of the number of
sources involved. Both methods are presently used in Kotzebue.
9.1.1 Diesel Electric Generation
Diesel electric facilities should produce somewhat fewer air
pollution impacts than coal facilities because coal dust
generation is not an issue, and oil contains less "ash and sulfur
than coal, resulting. in less sulfur oxide. and particulate
emissions. However, some sulfur and nitrogen oxides as well as
particulates are produced. Some odor and visibility are also
associated with these emissions, and some noise will be produced.
9-1
Diesel facilities would require storage of large quantities ·of
diesel oil,: and a large spill could severely impact intertidal,
and pelagic organisms if it were to reach the water. Containment.
berms and other mi tigating measures, including development of a
spill prevention control and countermeasures plan, would reduce
the likelihood of significant damage. Some small lea~s,
ruptures, or spills are likely to occur from time to time in
~pite of pr.cautions.
Stormwater runoff from the facili ty and surrounding area will
impact adjagentwaters to some extent. Stormwater is likely to
carry some grease and oi Is, sed iments, and traces of metals clOd
chemicals.
A . number of materials are often present in power plants,
including strong acids and bases, solvents, pblychlorinated
biphenyls . '( PCB IS) , and wastes from chemical cleaning,
demineraliz;ation and other in-plant processes. Accidents may
result in discharge of these materials unless spill containment
measures are present. Some effluent may also be produced from·
drains and processes within the plant which, without mitigation,
could affect surface waters.
If the existing facility were enlarged, some noise, dust:
generation, construction equipment emissions and increased solid,
waste generation would result.
Impact is often associated wi th disposal of heated water from
power plants. The present facility utilizes waste heat when
possible. Facilities which do not use this heat generate heated'
cooling water, which tends to range between 100-160° F. Disposal,
of this water has great impact on the surrounding environment,
even in tropical areas where water is naturally warm. Environ-
mental impact is greatly reduced by utilization of waste heat,.
and in cold areas, an energy savings also results.
9.1.2 Individual Oil Stoves
The impact from the use of individual oil stoves is, in effect('
nonpoint source in orig in. Nonpoint sources are trad i tionally
more difficult to control and regulate than point sources, as
control measures feasible for a single large facility are often
not feasible for small ind i vidual installations. Many of the
impacts normally associated with a diesel burning facility,
located outside of the city are also generated by these
individual sources within the city. Oil stove emissions are.
released within the town itself, and the air pollution impact on
the population is immediate and direct. In contrast, a single
facility could be located south of· the town and prevailing winds
would normally carry the emissions westward, away from the town.
Should the wind shift, there would still be dilution due to the
distance from town and the stack height.
9-2
I 1
W
U
J
u
u
[)
~
u
u
[1
D
o
u
u
u
.U
!
IU
r ;
l.J
u
. \
, (
~
u
w
A number of cleaning and other in-plant processes utilized in a
large facility would not be required for oil stoves, and water-
.related impacts, with the exception of spills, should be minimal.
Oil storage problems and oil spills associated with individual
. stoves are also essentially a nonpoint source problem, and
therefore difficult to control or regulate. In addition, it is
probable that a number of small installations have lower overall
efficiency than for a single large facility.
9.2 ALTERNATIVE A --COGENERATION
This alternative would require coal-fired steam cogeneration
supplemented by coal-fired low pressure district heating. It
would be accomplished by a single plant with a common dispersion
system.
Impacts of both the steam co-generation and the low pressure
district heating would be similar, because although both systems
could burn various fuels, the main fuel would likely be coal in
both cases.
A major consideration for all coal-fired technology will be the
environmental impacts of coal extraction. Stripping of over-
burden, stockpiling of that material in a manner to control
erosion until it is used in rehabilitation of the mine, aspects
of hydrOlogy and water quality that are associated with mining,
revegetation of disturbed a~eas, and other considerations of
providing the feedstock will have to be assessed. Although they
are not addressed in the analysis, they are recognized as
important factors that will weigh heavily in considering coal-
fired alternatives.
Coal transport and storage ·facilities would be required, and
construction of the transport system could impact land use,
drainage, and aesthetics. Fugitive dust generated from coal
piles and during unloading, crushing, and other coal handling
operations is a major concern in coal-fired facilities, but a
number of mi tigations can be implemented to reduce dust
generation. Location of the facility south of the town will
prevent prevailing winds. from carrying dust over the town, thus
minimizing direct impact from the facility.
Stack emissions would result in additional air pollution impacts;
sulfur and nitrogen oxides as well as particulates would be
produced in somewhat greater amounts than from an oil-fired
facility, and radioactive trace metals and fluorides may possibly
be found in emissions if proper control technology is not used.
Coal pile storage may also result in water pollution. Various
elements in the coal enter thin films of water that exist· when
the coal is damp and exposed to air. Rainfall will wash off this
film, producing an initial runoff that is often acidic, and
9-3
I , ,.
~
usually high in concentrations of iron, copper, and/or zinc. W
Analysis of coal pile drainage water are shown in Table 9.1.
Actual characteristics and contaminant concentrations present in ; 1
coal pile leachate will vary depending upon the source of the ~
coal, the coal pile size and residence time, temperature, coal-
water contact time, method of coal preparation prior to storage,
and other factors. ~
While not
impacts.
disturbed
spoil, the
a local impact, each coal mining area has significant
A few more obvious areas are runoff control in
areas, reqlamation of disturbed areas, handling of
resource, etc.
Coal burning also results in production of large quantities qf
ash and possibly sludges from S02 scrubbers. Space would be
required for storage, of these materials. Coal ash can contain
significant quantities of aluminum, iron, silicon, calcium,
magnesium," sodium, potassium, lead, boron, and titanium, as well
as trace metals including mercury, arsenic, selenium, cadmium,
copper, nickel, vanadium, and zinc (US EPA 1979). In addition,
contamination of ground or surface waters may result if heavy
metals, acids, bases and other compounds contained in the ash are
leached from uncovered storage areas by rainfall or surface
runoff. Runoff from coal storage· pi les, ash piles, and the
facility in general can be minimized and treated before
discharge, to meet NPDES discharge limitations. Discharge to the
ocean would be preferable to discharge in the nearby lagoon;
dilution would be greater and sea water tends to act as a buffer,
minimizing the impact of solutions 'having extreme pH ranges.
A number of materials are often present in power plants including
strong acids, PCBs, strong bases, and solvents. Accidents may
resul t in discharge of these hazardous materials unless proper
spill containment measures are constructed.
Some cooling water may also be discharged from the plant. This
will affect the ecology of the surface waters to which it is
discharged. However, it is possible that this could, in some
instances, be considered a beneficial effect, depending on volume
and temperature of the discharge water. Careful consideration Of
the thermal effects should be made prior to implementation of the
operation.
The size of the facility, the high stacks, and the stack
emissions would produce visual impact. Location of the facility
south of the town would minimize direct aesthetic impact on the
population, and would seem to be consistent with existing use of
the area, which presently includes the town landfill. (This
landfill site may also prove to be a disposal site for some types
of ash, if it can be used as cover or fill material and if runoff
from the site can be contained.)
9-4
u
w
u
u
u
u
w
u
u
u
r 1
I.J
u
o
u
u
u
,lJ
r '
, I
, 1
I
W
D
D
D
9.3 ALTERNATIVE B --COAL-FIRED LOW PRESSURE DISTRICT HEATING
Alternative B would utilize the coal-fired low pressure district
heating system, which is a portion of Al ternati ve A, described
under Section 7.2. Impacts would be similar to those described
for the coal facilities in Section 7.2, but the magnitude of
stack emissions and other impacts would be reduced because coal
would be used only for heating and not for electricity.
Dust and leachate from coal storage and handling areas, coal
leachate and ash storage, runoff from the faci Ii ty si te, aesthe-
tic impacts, and air pollution impacts of sulfur and particulate
emissions will still be issues with low pressure district
heating, but mitigations are possible and impacts should not be
insurmountable.
9-5
TABLE 9.1
COAL PILE DRAINAGE WATER:
ANALYSES FROM NINE COAL-FIRED STEAM ELECTRIC GENERATING PLANTS
Contaminant
Alkalinity
Acidity
BOD
COD
Total Solids
Total Diss9lved
Solids
Total Suspended
Solids
Ammonia (N)
Nitrate (N)
P
Turbidity
Hardness (CaC03)
Sulfate
Chloride
Al
Cr
Cu
Fe
Zn
High Sulfur
Coal
'(Avg. of 3
Range (mg/l)
o
8
o
85
1,330
247
22
82
-27,810
10
1,099
-45,000
-44,050
3,302
o 1.8
0.3 -2.2
0.2 -1.2
3 505
130 1,850
133 -21,920
4 481
825 1,200
o 16
1.6 -3.4
0.1 -93,000
0.01-23
NA = Not available.
Low Sulfur
Coal
Plants) (1 Plant)
0 24
24,800 6
NA NA
NA NA
NA NA
26,500 NA
NA NA
NA NA
NA NA
NA NA
NA 6
NA NA
16,000 NA
NA NA
1,012 NA
8 NA
2.6 NA
48,000 1
18 NA
i i
U
r 1
W
i '
, I
\.j
u
u
w
I '
LJ
r 1 ~i
Source: U.S. Environmental Protection Agency, 1974. Development fl
document for 'eff luent gu idel ines and new source perfor-III
mance standards for the steam electric power generating
point source category. EPA 440/1-74 029-a. Effluent il
Guidelines Division, Office of Water and Hazardous ~
Materials, Washington, D.C.
9-6
u
u
u
u
u
L
U
u
u
u
D
W
U I
9.4 ALTERNATIVE C --HYDROPOWER
Hydropower projects provide several advantages over other energy
sources: they utilize a. renewable domestic resource; they
require relatively simple equipment; they have low operation and
maintenance; they have 2-3 times the life of a fossil fuel plant;
and environmental impacts are relatively well· understood and
predictable. Because of the distance between Kotzebue and the
project location, the impacts would be removed from the immediate
vicinity of the community,and therefore less noticeable.
However, it whould not be assumed that because they are less
noticeable, these impacts are of less importance to the
environment.
Air pollution impacts will tend to be negligible once
construction is completed. However, like coal mining,
construction of roads, transmission lines, and the dam itself, a
number of air pollution impacts including dust generation,
exhaust emissions, and noise associated wi th construction
equipment should be expected. Erosion and sedimentation problems
would also be likely.
Aesthetic impacts include such items as the transmission 1 ines,
access roads, clearing of the construction site, construction of
the reservoir and dam, noise, and possibly odors. resulting from
impoundment drawdown and plant growth of the reservoir.
The magni tude of these aesthetic changes will be determined by
such factors as the relative ~niqueness of the aesthetic
characteristics altered or created, the distance from which the
structures are visible, height and construction material, the
extent and magnitude of vegetation change along the shoreline,
and the extent of other physical/chemical alterations that may
cause odor and plant growth problems (Battelle 1974).
Among the impacts will .be the flora and fauna ·of the affected
reservoir area, . because of changes in aquatic and terrestrial
habitat. These may tend to be as great as those of oil or coal-
fired plants and resource capture. The facility would affect
spawning and rearing habitat for anadromous fish, including
salmon, char, sheefish, and other species. Because anadromous
fish are part ·of the marine ecosystem as well, impacts on fish
may extend to mar ine consumers such as the beluga wh.ales.
Terrestrial habitat would also be impacted; formation of the
large, shallow reservoir would result in loss of moose and
caribou feeding and migration areas.
A new habitat, the "drawdown zone", will· likely be created
because water input seldom coincides exactly with water output.
As a result, a belt of periodically inundated terrestrial
habitat, sometimes described as a "bathtub ring" is formed, which
9-7
may result in vegetation changes. The importance and
relationship of this new habitat to the ecosystem including area
permafrost will vary with the reservoir.
Reservoir formation may include additional impacts such as a
decrease in downstream nutrients due to sediment entrainment: a
change from a flowing to a lake habitat; a change in water
qual i ty , includ ing an increase in organic ma-terials, a reduction
in dissolved oxygen levels, and changes in water temperature;
changes in riparian' habitat: stimulation of shoreline erosion;
and alteration of fish distribution.
Impacts of hydropower projects
reason, there is need for
collection, and permitting and
long and complicated compared to
can be significant. For this
extensive environmental data
licensing procedures are often
other types of projects.
As stated previously, because of the long transmission line and
unknown hydrological inflows, a 100 percent backup system shoulq
be provided. This would likely consist of continuation and
expansion of diesel electric qenerators. Continued impacts from
diesel electric generation (Section 9.1) should thereforealsb
be considered when evaluating the alternative of hydropower. How-
ever, positive benefits in terms of non-renewable resources
savings would still occur when hydropower facilities are
operational. 'Impacts from hydropower will be the same whether it
is used to provide electrical power, or whether it is used for
space heating as well.
9.5 ALTERNATIVE D --GEOTHERMAL
Geothermal projects, once in operation, are likely to have
negligible air quality impacts. During construction, dust
generation, construction equipment emissions, and noise would be
expected. There may be some 1 imi ted land and water-related
impacts, including erosion/sedimentation and materials spills.
Once construction is completed, the main impacts are likely to be
water-related. The geothermal system will probably be a liquid-
dominated system which would, utilize heated subsurface water to
transfer heat energy. Hot, deep-seated igneous rocks which
produce very hot water do not appear to be present, so a large
volume of warm water would be, necessary to provide sufficient
heat for system operation. Data from Nimiuk Point well #1
indicate this water is also likely to be very saline, having
total dissolved solids of about 90,000 ppm (Alaska Power
Authority 1981).
Once heat is removed from the water, a large volume of warm
saline water will require disposal, either through reinjection or
surface discharge. Disposal to either fresh water or marine
environments would impact the habitat to varying degrees
depending upon the volume of water discharged, the salinity,
9-8
i
I ,.
~
i 1
I.J
u
u
i .
~
il
ill
u
w
U"
W
u
U
D
D
U
U
U
r 1
U
r '
U
r
i l.J
I,
I
r '
W
r
U
U
U
W
U
D
U
D
mineral content, and temperature. It is possible that moderate
temperature change could, in some instances, be beneficial to
wild 1 i fe, although habi ta t changes would result. so 2 forma tion
can cause significant odors which are quite objectionable.
Removal of large volumes of subsurface water could potentially
cause land subsidence, which could be of concern as Kotzebue is
only 10 feet above sea level (Energy Systems Inc. 1980). Poten-
tial for both surface water pollution and subsidence would be
substantially reduced if water were reinjected into the ground
after use.
Development of a geothermal facility would also probably result
in generation of some stormwater runoff. However, the facility
would be relatively small, and would not be likely to contain
material stockpiles or other undesirable contaminants which could
be leached or carried from the site by stormwater. Stormwater
impacts could be mitigated if. necessary by use of an oil water
separator, holding pond, or other means.
9.6 ALTERNATIVE E --OTHER ENERGY MEASURES
9.6.1 Thermal and Electrical Conservation
Energy can be conserved by both thermal and electrical means.
Thermal conservation measures include retrofitting of existing
structures through caulking, sealing, increased insulation, and
other measures, as well as use of heat-conserving practices and
materials during new construction. Electrical energy conserva-
tion includes measures such as load management and use of
efficient lighting.
Both of these types of conservation measures have important
positive environmental impact because they minimize energy loss,
regardless of the energy resource used. In addition, there is no
negative impact associated with 'use of these conservation
measures. They should be considered as support systems, because
in themselves they do not sufficiently meet Kotzebue needs.How-
ever, individuals should be encouraged to utilize both thermal
and energy conservation measures. to the extent feasible,
regardless of the energy source ultimately utilized by the city.
9.6.2 Wind Systems
Like hydropower, wind generators have the advantage of using a
renewable domestic resource which has little pollution potential.
Traditional impacts associated with energy production are nearly
absent in wind generation facilities. Minimal impacts involving
noise, construction equipment emissions, dust generation,
erosion, and increased traffic would be expected during
construction. Once in operation, no appreciable air or water
impacts would be expected.
9-9
However, several other less-trad i t ional impacts should be
considered. At present, large turbines have not yet proven
reliable in the Arctic, so a large number of generators would be
required, at least at first. They would have greater aesthetic
impact than other energy producing facilities, because they must
be raised and placed in open areas free from turbulence caused by
other struptures. Operation of the generators will also result
in two less obvious, but potent ially important impacts. Wind
generation systems h~ve been known to produce radiomagnetic
interference. They may also produce some low frequency sound,
which could cause impact of an undetermined degree to both
wildlife and human populations.
As stated previously, until demonstrations show qifferently, 100
percent backup power should be provided by the ut~lity. The back-
up facility would likely be a continuation and expansion of
diesel electric generation, discussed in Section 7.1. Impacts
from this backup syst:em should therefore also be considered in
addition to impacts from the wind generators themselves, when
evaluating the windpower alternative. However, positive benefits
in terms of non-renewable resources savings would sti 11 occur
during periods when the wind facilities were operational.
9.7 REFERENCES
Alaska Power Authority, 1981. Kotzebue geothermal project:
biologic analysis. Prepared for Alaska Division of Energy
and Power Development, authored by Arlen Ehm. .
Battelle Columbus Laboratories, 1974. An assessment methodology
for the environmental impact of water resource projects,
prepared for the Off ice of Research and Development US EPA,
contract no. 68-01-1871.
Energy Systems, Inc~, 1980. Kotzebue geothermal project:
analysis of currently available information and report of
advisory group meetings.
U.S. Environmental Protection Agency, 1979. Environmental impact
assessment guidelines for new source fossil fueled steam
electric generating stations, EPA 130/6/79-001.
9-10
I I
~;
r l
~
u
i 1
W
10.
PLAN EVALUATION
o
u
IU
iO
I
U
U
I
i 1 I !~
u
r 1 ,W
I
U
W
SECTION 10
PLAN EVALUATION
TABLE OF CONTENTS
10.0 General ........................................... 10-1
10.1 Basis for Economic Analysis ......••.•.....•••••••. 10-1
10.2 Summary of Economic Analysis .•...•.•.•.•••••••••.. 10-3
LIST OF TABLES
Table 10.1 Summary Economic Evaluation 55-Year
Present \vorth ................................... 10-4
Table 10.2 Cost-Benefit Summary .. ~ ......................... 10-5
Table 10.3· Detail Summary -Case 1: Base Case ............•. 10-6
Table 10.4 Detail Summary -Case 2: Coal-fired
Cogeneration .................................... 10-7
Table 10.5 Case 10 -Hydropower with Geothermal
District He~ting •.••••.••..••..••.••••••••.••••• l0-8
Table 10.6 Case 11 -Hydropower with Electrical
Space Heating ................................... 10-9
fl , i
~
u
r \
W
u
u
( ,
U
U
Q
D
SECTION 10 PLAN EVALUATION
10.0 GENERAL
This section provides the basic matrix for evaluating which plan
or plans would best serve the electrical and heating needs of
Kotzebue. with the technologies described in Sections 5 and 7,
eleven (11)' plans (or cases) were considered to be viable schemes
and evaluated with respect to economic and technical
characteristics only. The environmental and social criteria
should be further addressed in the follow-on studies, i. e. the
Detailed Feasibility Study and Final Design phases.
Each plan was designed to be capable of providing Kotzebue with
the forecasted demands of heat and electricity; a reasonable
amount of back-up capacity was incorporated.
For geothermal alternatives it should be noted that a well head
temperature of 162°F, which may be optimistic, has been
theorized as possible. This would allow for direct utilization
in district heating systems with an anticipated cooling of 36°F.
It should be noted, however, that this will require larger
radiator sizes in residences and direct connection of residential
systems to the district heating system without the use of heat
exchangers.
The results of the evaluations are summarized and tabulated in
Table 10.2. The case evaluation procedures are covered in
Appendices G, H, I, and J. Appendix G provides computations of
O&M costs for each plan, Appendix H provides the computations of
fuel costs, and Appendix I provides the calculations of capital
costs for each plan.
A year-by-year breakdown of costs and benefits is provided in
Section 10.3, Tables 10.3 through 10.6 for the following cases:
C'ase 1:
Case 2:
Case 10:
Case 11:
Base Case (Table 10.3)
Coal-fired cogeneration (Table 10.4)
Hydropower with geothermal district heating
(Table 10.5)
Hydropower with electrical space heating
(Table 10.6)
10.1 BASIS FOR ECONOMIC ANALYSIS
The economic evaluation performed for the Alternatives considered
in this study is based upon the Alaska Power Authority's
recommended standard procedures for reconnaissance and
feasibili ty studies. These procedures use a standard set of
assumptions, some of which are presented below:
1. Zero general inflation;
2. Real escalation of petroleum fuels at 2.6 percent
annually and coal at 2.0 percent annually for twenty
years.
10-1
3. The interest rate for purposes of present worth
calculations, for interest during construction
calculations, and for interest and amortization
calculations is 3 percent; and
4. Operation, maintenance, and fuel costs are assigned to
the year in which they occur.
Determination of the total present value or
project involves two primary calculations:
the annual uniform interest and amortization
a home mortgage payment), and discounting of
the base year.
present worth of a
The calculation of
payment (similar to
the future costs to
Calculatiqns of the annual uniform interest and amortization
payment are handled in the following manner: First, the total
investment. cost of the project is summed from estimates for
construction costs, equipment costs and the like, plus interest
costs accrued during construction. The average, annual cost (or
payment) is then calculated over the· project I s economic life
(e.g., 50 years for hydroelectric projects, and 20 years for
diesel generators) using an interest rate of 3 percent. The
process described above is similar to the calculations performed
by banks and mortgage companies to arrive at a mortgage payment
for homes.
The discount rate is an economic concept which says that the
value to a recipient of $20.00 received ten years from now is
less than the value the recipient would place on $20.00 received
tomorrow and subsequently, that the value of $20.00 received
twenty years from now is less than the perceived value of $20.0Q
received ten years from now. The same concept exists for
payments; a person would place a greater value on $20.00 he had
to spend tomorrow to make a house payment than on the $20.00 he
had to pay thirty years from now to make the same payment. The
rate at which the value of that $20.00 diminishes over time is
called the discount rate. A. discount rate of 3 percent would
establish that the present value of $20.00 received ten years
from now is $14.88 and for $20.00 received twenty years from now
it is $11.07.
Discounting of the future costs of the project is calculated by
summing the capital cost payments (annual uniform interest and
amortization payment), operation and maintenance costs, fuel
costs, and similar items for each year and discounting the total
annual cost back to the base year. Discounted costs for each
year are then summed to give the present worth of plan costs.
10-2
r 1
U
I i ~
u
w
u
u
r 1 I : ~
fJ U.
I 1 ~
11 I t ..
11 ~
W
D
U
D
D
u
u
U
I
:U
I
U
u
u
u
u
D
D
D
Benefits from a project are handled in a similar manner; they are
assigned in the year they occur and are discounted in the same
way as costs.
Plans are compared in terms of total net benefits and benefit-
cost ratios. Net benefits are equal to the discounted total cost
of the base case plan (benefits) less the cost of the alternative
being considered. The benefit-to-cost ratio shown in this
evaluation is the ratio of the present worth of the project
benefits to the present worth of project costs. A number less
than 1.00 means that the costs of the project are larger than the
benefits to be derived from it, while a number greater than 1.00
states that benefits outweigh the costs. Net benefits and
benefit-to-cost ratios are often used to evaluate alternatives,
with the largest total net benefits or benefit-to-cost ratio
implying the best project from an economic basis. However, in
the final analysis of alternatives and selection of a preferred
project a number of other criteria have to be considered.
10.2 SUMMARY OF ECONOMIC ANALYSIS
The ensuing text, tables and graphics summarize the overall
economic parameters for each plan (Tables 10.1 and 10.2).
Tables 10.3 through 10.6 show a detailed summary of estimated
costs and benefits per year for each case. This tabulation shows
(1) capital cost; (2) operation and maintenance cost; (3)
replacement cost of equipment; (4) fuel costs; (5) diesel
generation displacement benefit; oil stove heating displacement
benefit; and, (6) fuel escalation benefit.
As presented in Table 10.2, Cases 2 (Coal-fired Cogeneration) and
11 (Hydropower with electrical resistance heating) are almost
equal in net benefit and benefit-cost ratio. Case 10 (Hydropower
with geothermal district heating) has a much lower net benefit
and benefit-cost ratio.
10-3
-,
I
W
Ii
W
TABLE 10.1
Summary ~
Economic Evaluation I' 55 Year Present Worth . I
Revised For Price of Coal at $6.00/MBTU ..
(All figures are $ x .10 6 ) U
FUEL SINKING
W CASE CAPITAL COST O&M FUND TOTAL
1. Base case .18.2 341. 8 27.6 14.6 402.2
2. Coal-fired ' 1
cogeneration 62.0 177.1 33.6 0.1 272.8 U
3. Hydropower,
oil stoves 199.6 220.3 28.8 1.5 450.2 r '
4. Diesel generation W oil-fired district
heating 33.5 217.6 24.1 11.7 286.9 n 5. Oil-fired
cogeneration 40.6 285.4 25.4 0.1 351. 5 I..-
6. Diesel generation,
coal-fired district U heating 68.3 183.2 29.5 11. 7 292.7
7. Coal-fired power,
oil stoves 35.0 301. 0 37.4 1.5 374.9 1'0 )
8· Hydropower, coal-U ..
fired district ,
heating 250.2 95.7 47.5 0.1 393.5
U 9. Diesel generation,
geothermal district
heating 142.6 172.4 24.8 11.7 351.5
10. Hydropower, geo-U thermal dis.trict
heating 309.2 25.0 32.6 0.1 366.9
11. Hydropower, with Oi electrical heating 202.2 41.4 28.8 1.5 273.9
U
~
U
U
.10-4
[ 1
o
u
u
u
c , u
U
f .
W
r I
IW
I
:U
I
'D
u
o
[J
TABLE 10.2
Cost/Benefit Summary
PRESENT WORTH IN $ X 10 3 BENEFIT-TO-GENERAL
CASE COSTS BENEFITS BENEFITS COST RATIO RANKING
1 (Base Case) $402,123 $402,123 $ 0 1. 00 (a)
2 (Cogeneration) $272,853 $402,123 $129,270 1. 47 1 (b)
10 (Hydropower/
geothermal
district heating) $366,810 $402,123 $ 35,313 1.10 3
11 (Hydropower
w/electric resi-2 (c) stance heating) $273,899 $402,123 $128,224 1. 47
(a) Not Applicable
(b) Economic analysis uses Cape Beaufort Coal (currently not a produ-
cing mine) which is the cheapest source estimated to be available.
(c) Hydropower system utilized contingency of 25% in
10% for base case and 15% for cogeneration. On
gency percentage both Case 2 and 11 appear to be
10-5
comparison to
similar con tin-
near equal.
'1'ABLE 10.3 -01::'rAIL SUMMARY -CIISI, 1: LlASE CASe:
BASE CASE
1. Diesel Gencrution and Wnste fleut
Capital Costs
a " M
Fuel (SI.28/gal.)
Replacement of r;xistiflg Systems
2. oil Stoves" Furnaces
Capital Costs
a " M
Fuel (SI.46/gal.)
Replacement
Total Cost
Total Discounted Cost
Prescnt worth of plan cost 19U3 -2002:
Present worth of plan cost 2003 -2037:
Total present '.orth ot. plan cost:
ESTlMA'l'ED COSTS ($1,00(1)
1983 1984
o o
775 775
1,497 1,649
488 488
18 18
142 147
2,906 3,135
56 56
!l,882 6,26B
5,711 5,908
$164,922,000
237,201,000
$402,123,000
1985
o
775
1,804
488
18
152
3,579
56
6,lrl2
6,289
I SJ H 6 1987
o
775
~,0()2 :G,206
488 488
2() 20
158 163
J,7U6 4,083
56 56
7,285 7,791
6,473 6,721
1988
512
800
2,431
488
20
169
4,207
56
8,683
7,272
1989
512
800
2,679
488
20
175
4,421
56
9,151
7,441
1990 1991
512 680
800 800
2,938 3,222
488 488
20 28
180 188
4,607 4,911
56 56
9,601 10,373
7,579 7,950
1992
680
800
3,519
488
28
196
5,190
56
10,957
8,153
1993
680
800
3,842
488
28
204
5,480
56
11,578
8,364
1994 1995 1996
680 680 848
800 800 800
4,194 4,573 4,998
488 488 488
28 28 28
212 220 228
5,741 6,074 6,358
56 56 56
12,199 12,919 13,804
8,556 8,797 9,126
1997
848
800
5,455
488
28
236
6,673
56
14,584
9,361
19<JU
848
800
5,956
488
28
244
6,979
56
15,399
9,596
1999
848
800
6,501
488
28
252
7,363
56
16,336
9,884
2000 2001
848 848
800 800
7,095 7,744
488 488
28 35
260 270
7,763 8,208
56 56
17,338 18,444
10,184 10,51B
10-6
2002
848
800
8,405
488
35
280
9,026
56
19,938
11,039
2003
-2037
848
800
8,405
488
35
280
9,026
56
19,938
'l'AIlL!:: 10.4 -Dt:'1'AIL SUMMARY -CAS!:: 2: COAL-FIHBD COGENBRATION
CASE COMPONENT
1. Coal-fired CO<lcnl!r<.llion:
Capital Cost, Plant
Capital Cost, Distribution
Fuel
o & M
2. Diesel Generation:
Capital Cost
Fuel
o & M
J. Oil Stove:;:
Capital Cost
Fuel
o & M
Replacement
'rotal Cost
Total Discounted Co:;t
Present worth of plan co~t 1983 -200~:
Present worth of plan cost 2003 -2037:
Total present worth ot plan C05,t:
5. Bcnefits
Displacement of BdSD Ca:;ll:
Net Benefits:
Benefits
Cost
Net
Benefit -Cost Ratio:
ESTlMATt:D COSTS ($1,000)
1983 1984
o o
o o
o
o o
o o
1,497 1,649
775 775
18 ]8
2,906 3, ] 3~
14~ 147
56 56
5,394 5,780
5,237 5,448
$124,256,000
148,597,000
$272,853,000
5402,123,000
5402,123,000
-$272,853,000
$129,270,000
1985
1,551
1,015
3,040
1,200
o
o
100
o
50
o
6,956
6,366
1986
1,551
1,015
3,200
1,200
o
o
100
o
o
50
o
7,116
6,322
1987
1,551
1,015
3,373
1,200
o
o
100
o
50
o
7,289
6,288
5402,123,000 + $272,853,000 = 1.47
1988
1,551
1,015
3,560
1,200
o
o
100
o
o
50
o
7,476
6,261
1989
1,551
1,015
3,746
1,200
o
o
100
o
o
50
o
7,662
6,230
1990
1,551
1,015
3,946
1,200
o
o
100
o
o
50
o
7,862
6,206
1991
1,551
1,015
4,173
1,200
o
o
100
o
50
o
8,089
6,200
1992
1,551
1,015
4,413
1,200
o
o
100
o
o
50
o
8,329
6,198
1993
1,551
1,015
4,667
1,200
o
o
100
o
o
50
o
8,583
6,201
1994
1,551
1,015
4,933
1,200
o
o
100
o
o
50
o
8,799
6,171
1995
1,551
1,015
5,226
1,200
o
o
100
o
o
o
o
9,112
6,205
1996
1,551
1,015
5,523
1,200
o
o
100
o
o
o
o
9,389
6,207
1997
1,551
1,015
5,867
1,200
o
o
100
o
o
o
o
9,733
6,247
1998
1,551
1,015
6,240
1,200
o
o
100
o
o
o
o
10,106
6,298
1999
1,551
1,015
6,667
1,200
o
o
100
o
o
o
o
10,533
6,373
2000
1,551
1,015
7,173
1,200
o
o
100
o
o
o
o
11,039
6,484
2001
1,551
1,015
7,706
1,200
o
o
100
o
o
o
o
11,572
6,599
10-7
2002
1,551
1,015
8,267
1,200
o
o
100
o
o
o
o
12,128
6,715
2003
-2037
1,551
1,015
8,267
1,200
o
o
100
o
o
o
o
12,133
148,597
TI\BI.I: 10.5 -CI\:J1~ 10: IIYDJ(UI'OY/J';1< WITII C!':O'J'JlI'l<MI\I, LH5'l'IUC'l' Il!;;l\'l'lNG
CA!JE 10: IIYIlHOI'()\'iLH WI 'I'll CLO'!'IIJ:HMAI. IJI ::;'J'j(J C'l' lil':A'l'l NG
CASE COMPONENT
1. IIYDHOPOWEH:
Capital Cost, Plant
Capitdl Co,:t, Gas Turbine
Fuel
o Iii M
2. GEOTHERMAL DISTRICT HEATING:
Capitul Co~t, Geothermal Sy~l'~1ll
Capital Cost, Distribution
o Iii M
3. DIESEL CI':NI:I<I\'I'[O[J:
Capital CO~:t
FUQl
o & M
4. OIL STOVES:
Capital Cost
Fuel
Total Cost
Tota I D1 scountl.!U l'l.I!> I
Pre~ent wurth or ,,1.111 .',,:,1 I~B3 -;!002:
Present worth at 1'1.11\ "U':\ 2003 -2037:
Total present worth at pId" cost:
5. Ucnofits
Displacement of lid:,,' l: .. ",e:
Net Benefits:
Benefits:
Cost:
Net:
llcncfit-COBt H...Itio!
1983 1984
o o
o o
o o
o o
o
o o
o o
o
o o
o
1,497 1,649
775 775
18 18
142 147
2,906 3,135
5,338 5,724
5,l!:l 3 5,395
5187,17tl,000
179,632,000
5366,810,000
5402,123,000
5402,123,000
-53611,8]0,000
$ 35,313,000
1985
o
o
o
o
3,272
1, 123
175
436
o
1,604
775
o
50
o
7,635
6,987
$402,123,000 • $Jbb,U10
1986
o
o
o
o
o
3,272
1,123
175
436
o
2,002
775
o
50
o
7,833
6,960
l. 10
E5'l'lMII'I'I::D COSTS (51,000)
1987
o
o
o
o
3,27£
1,123
175
436
o
2,206
775
o
50
o
1988
5,312
3,470
186
o
1,025
J,272
1,12 J
175
436
o
o
100
o
50
o
8,037 15,149
6,933 12,687
1989
5,312
3,470
186
o
1,025
3,272
1,12 J
175
436
o
100
o
50
o
15,149
12,318
1990
5,312
3,470
186
1,025
3,272
1, 123
175
436
o
o
100
o
50
o
15,149
11,959
1991
5,312
3,470
186
o
1,025
3,272
1,123
175
436
o
o
100
o
50
o
15,149
11,610
1992
5,312
3,470
186
o
1,025
3,272
1,123
175
436
100
50
15,149
11,273
1993
5,312
3,470
186
o
1,025
3,272
1,123
175
436
o
o
100
o
50
o
15,149
10,944
1994
5,312
3,470
186
1,025
3,272
1,123
175
436
o
o
100
o
o
o
15,099
10,590
5,312
3,470
186
o
1,025
3,272
1,123
175
436
o
100
o
o
15,099
10,282
1996
5,312
3,470
186
o
1,025
3,272
1,123
175
436
o
o
100
o
o
o
15,099
9,982
1997
5,312
3,470
186
o
1 ,025
3,272
1,123
175
436
o
100
o
o
o
15,099
9,691
199H
5,312
3,470
186
o
1 ,025
3,27 :2
1,123
175
436
o
o
100
o
o
o
15,099
9,409
1999
5,312
3,470
186
o
1,025
3,272
1,123
175
436
o
o
100
o
o
o
15,099
9,135
2000
5,312
3,470
186
o
1,025
3,272
1,123
175
436
o
o
100
o
o
o
15,099
8,869
2001
5,312
3,470
186
o
1,025
3,272
1,123
175
436
o
o
100
o
o
o
15,099
B,611
10-8
2002
5,312
3,470
IB6
o
1,025
3,272
1,123
175
436
o
100
o
o
o
15,099
B,360
2003
-2037
5,312
3,470
186
o
1,025
3,272
1,123
175
436
o
o
100
o
o
o
15,099
8,360
TAIILE 10.& CASt:: 11: I!Yl.JHOPUWEh I'II'rH ELECTHICAL SPACE IlEA'rING
CASE CUMPONEIJ'~'
1. Hydropower:
Capital Cost, 1'1dilL
Capital Cost, Transrnis~ion LilHl
Capital Cost, Gas Turbine
Fuel
o & M
2. Diesel Generilt.lon:
Capital Cost
Fuel
o & M
3. oil Stoves:
Capital Cost
o & M
Fuel
Total Cost
Total Uiscounted Cost
Present worth of plan cu~t 1983 -2002:
Present worth of plan cost 2003 -2037:
Total prosent worth ot plan cost:
4. IICl\llfit!.l
Displacument ot BilSU Cil!.l(.!:
Net Benefits:
Benefits
Cost
Net
Benefit-Cost Ratio;
!';S'l'IMATED COSTS {$1, 000 I
19B3
o
o
o
o
1,497
775
18
142
2,906
5,338
5, 183
1984
o
o
o
o
o
1,649
775
111
147
3,135
5,724
5,345
$137, €lOU, 000
136,291,000
$273,899,000
$402,123,000
$402,123,000
-$273,899,000
$128,124,000
1985
o
o
o
o
1,804
775
18
152
3,579
6,328
3,591
1986
o
o
o
o
2,002
775
20
158
3,786
6,741
5,989
$402,123,000 + $273,899,000
1987 19118
o 5,312
3,470
322
o o
o 1,025
o
2,206 o
775 100
20
163 50
4,083
7,247 10,279
6,251 8,609
1. 47
1989 1990 1991 1992
5,312 5,312 5,312 5,312
3,470 3,470 3,470 3,470
322 322 322 322
o o o
1,025 1,025 1,025 1,025
o o o o
o o a
100 100 100 100
o o o o
50 50 50 50
o o
10,279 10,279 10,279 10,279
8,358 8,114 7,878 7,649
1993
5,312
3,470
322
60
1,050
o
o
100
o
50
o
lO,J39
7,469
1994
5,312
3,470
322
131
1,050
o
o
100
o
50
o
10,410
7,801
1995
5,312
3,470
322
215
1,050
a
o
100
o
50
o
10,494
7,146
199b 1997 1998
5,312 5,312 5,312
3,470 3,470 3,470
322 322 322
302 414 527
1,050 1,050 1,050
o o o
o o o
100 100 10(1
o o o
5u 50 50
o o
10,58 J 10,693 10, HOb
b,995 6,863 6,734
1999 2000
5,312 5,312
3,470 3,470
322 322
664 793
1,050 1,050
o
o o
100 100
o o
50 50
o
10,943 11,072
6,621 6,504
2001
5,312
3,470
322
970
1,050
a
o
100
o
50
1 1,249
6,415
10-9
2002
5,312
3,470
322
1,177
1,050
o
100
50
o
11,456
6,343
2003
-2037
5,312
3,470
322
1,177
1,050
o
o
100
o
50
o
11,456