HomeMy WebLinkAboutBristol Bay Regional Power Plan Interim Feasibility Assessment Volume 1 - Report 1982------------------.-----.,-----~
._-------
CONTRACT No. CC -08 -2108 1,;(007 ,i O-v/.!l) ).,
BRIST'()L BAY
REGION.At PlOWER PLi\IN
DEl AILEI) FEASIBllJ"f'V i\I'tAt'~'SIS
INTERI.M FEt\~51IJIL"lrrY
ASSESS"1EN~r
VOLU,MI: 1 -REft)()R,l'
II
: !
I. ::'
r> I:·
J" ~ ::" .: .,-
.J )1.' , .
, ) -"';'
,~ .. <
JULY 1~~82
A Stone & Webster Enginet!ring Corpora1ion
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE -ANCHORAGE, ALASKA 99501
September 19, 1983
To: Concerned Agencies, Public Libraries and Public Schools.
Phone: (907) 277-7641
(907) 276-0001
Enclosed is the complete four volume set of the Bristol Bay
Regional Power Plan -Interim Feasibility Study. These reports
are being distributed to allow anyone concerned with the future of
the Region to see the complete report. To date, anyone interested
has received the Executive Summary to this report (and an interre-
gional report investigating the feasibility of one project for
both the Bethel area and the Bristol Bay Region).
The intent of the study was to find the least costly source
of future electrical power for residents of Bristol Bay. The
economic rankings of the different plans were based on long term
costs as estimated in 1982, and were compared to a Base Case (the
cost of continued use of diesel generation). These rankings, as
well as detailed plan descriptions, technical design, geotechnical
conditions of the site, land status, environmental impacts, social
impacts, etc., are also covered. The complete Table of Contents
is at the beginning of Volume 1.
The rankings of the projects showed that the regional run-of-
river Newhalen project would be the least costly in the long term;
the regional Tazimina dam project was ranked second; and the
subregional run-of-river Tazimina project (to serve Iliamna,
Newhalen and Nondalton), with diesel and wind generation, and
waste heat recovery (for the other regional communities), was
ranked fifth.
New long term costs, according to 1983 economic guidelines,
were calculated for the Bethel-Bristol Bay Interregional Study
(this investigated the feasibility of one project serving both
regions and found that an interregional project was not as cost
effective as separate regional projects). The new calculations,
using lower oil price projections, changed the Bristol Bay project
rankings. The regional Newhalen run-of-river project is still
first ranked, but the subregional run-of-river Tazimina project
with diesel/wind generation and waste heat recovery is now second,
and the regional Tazimina dam plan is now third.
If these plans were recalculated according to 1984 guide-
lines, the subregional and regional Tazimina plans could return to
the 1982 project rankings. As the price of oil rises in the
future, the plans with heavy dependence on diesel fuel (such as
the subregional plan) will be ranked lower.
151/070/D5/F2
The following tables summarize the updated rankings explained
above.
Under 1982 guidelines, the projects were ranked as follows:
Rank Project
1. Regional-Newhalen
run-of-ri ver
2. Regional-Tazimina
Lake dam
Net Present Worth
(Long Term Costs)
$189,900,000
$213,700,000
Benefit/Cost Ratio
(Alternative Plan
Compared to Diesel
Base Case)
1.54
1.36
3. Regional Newhalen $222,200,000 1.31
large diversion canal
4. Regional-Kontrashibuna $226,800,000 1.29
Lake dam
5. Subregional-local $242,500,000 1.20
Tazimina run-of-river
diesel, waste heat,
and wind
20. Base Case-continued $291,700,000 1.00
diesel
Under 1983 economic guidelines, the projects were ranked:
Rank Project Net Present Worth
(Long Term Cost)
1. Regional-Newhalen
run-of-river
2. Subregional-Tazimina
run-of-river, diesel,
waste heat and wind
3. Regional-Tazimina
Lake Dam
4. Base Case-continued
diesel
151/070/D5/F2
$194,052,000
$217,739,000
$233,528,000
$258,574,000
Benefit/Cost Ratio
(Alternative Plan
Compared to Diesel
Base Case)
1.33
1.19
1.11
1.00
The Newhalen project with the large diversion canal (formerly
ranked #3) was dropped because the higher cost did not offer more
protection to the fish, and the Kontrashibuna Project (formerly
ranked #4), because it was within the Lake Clark National
Park/Preserve. As long as there are better alternatives to serve
the people of the Region, there is no need to procede further with
study of these two projects.
These reports are enclosed for your information; a list of
those receiving full reports is also attached. Recently, a letter
was sent to interested individuals and agencies saying that these
reports would be available through the closest school or public
library. We hope that public libraries and schools will make
these documents available to the public who will be requesting to
see them. Thank you for your help and cooperation. If you have
any questions, please contact Merlyn Paine, Project Manager.
Attachments as stated.
151/070/D5/F2
Sincerely,
'"B-~0~~O
~~ Eric P. Yould
Executive Director
BRISTOL BAY DISTRIBUTION LIST
u.S. FISH & WILDLIFE SERVICE
Mr. John Kurtz
BBCMP-EIS Coordinator
U.S. Fish & Wildlife Service
1011 East Tudor Road
Anchorage, Alaska 99503
Ms. Ann Rappaport
(ATTN: Ms. Ann Rappaport &
Ms. Mary Lynn Nation)
U.S. Fish & Wildlife Service
605 W. 4th Avenue, Suite G-81
Anchorage, Alaska 99503
Mr. Keith Schreiner
Regional Director
U.S. Fish & Wildlife Service
1011 E. Tudor Road
Anchorage, Alaska 99503
FEDERAL LISTING -MISC.
Mr. David Simpson
Project Manager
Bristol Bay Cooperative Management Plan
Alaska Land Use Council
P.O. Box 100120
Anchorage, Alaska 99510-0120
Mr. Roger Contor, Regional Director
National Park Service
U.S. Department of the Interior
540 W. 5th Avenue
Anchorage, Alaska 99501
Mr. Dick Dworsky, Chief of Planning
Bureau of Land Management
U.S. Department of the Interior
701 C Street, Box 13
Anchorage, Alaska 99513
Mr. Ronald Morris, Supervisor,
(ATTN: Mr. Ronald Morris and
Mr. Stuart Bigler)
Anchorage Field Office
National Marine Fishery Service
701 C Street, P.O. Box 43
Anchorage, Alaska 99513
143A/077
Revised 9/19/83
ALASKA DEPARTMENT OF FISH & GAME
The Honorable Don Collinsworth
Commissioner
Alaska Department of Fish & Game
P.O. Box 3-2000
Juneau, Alaska 99802
Mr. Dick Russell
(ATTN: Mr. Dick Russell & Mr. Sellers)
Alaska Department of Fish & Game
Commercial Fisheries Division
General Delivery
King Salmon, Alaska 99613
Mr. Mike Nelson
(ATTN: Mr. Mike Nelson & Mr. Bucher)
Alaska Department of Fish & Game
P.O. Box 199
Dillingham, Alaska 99576
Mr. Lance Trasky
(ATTN: Mr. Lance Trasky &
Mr. Kim Sundberg)
Alaska Department of Fish & Game
333 Raspberry Road
Anchorage, Alaska 99502
STATE DEPARTMENT OF NATURAL RESOURCES
The Honorable Jim Barnett
Deputy Commissioner
Department of Natural Resources
Pouch 7-005
Anchorage, Alaska 99510
Mr. Dick Mylius
Land & Resources Planning
Bristol Bay Cooperative Managment Plan
Department of Natural Resources
Pouch 7-005
Anchorage, Alaska 99510
Mr. Tom Hawkins, Director
Land & Water Management
Alaska Department of Natural Resources
Pouch A
Juneau, Alaska 99811
- 1 -
Mr. Roland Shanks, Director
Division of Research & Development
Alaska Department of Natural Resources
Pouch 7-005
Anchorage, Alaska 99510
STATE LEGISLATORS
Ms. Adelheid Herrmann (when in session)
Alaska House of Representatives
Pouch V
Juneau, Alaska 99811
P.O. Box 63 (out of session)
Naknek, Alaska 99633
Mr. Bob Mulcahy (when in session)
Alaska State Senate
Pouch V
Juneau, Alaska 99811
P.O. Box 246 (out of session)
Kodiak, Alaska 99615
STATE OFFICE OF MANAGEMENT & BUDGET
Mr. George Matz
State of Alaska
Office of Management & Budget
Pouch 7-005
Anchorage, Alaska 99510
UNIVERSITY OF ALASKA
Mr. Dave Hickok, Director
Arctic Environmental Information
& Data Center
707 A Street
Anchorage, Alaska 99501
Mr. Jerry Lipka, Field Coordinator
University of Alaska X-CED Program
P.O. Box 10206
Dillingham, Alaska 99576
Mr. O.S. Scott Goldsmith
Principal Investigator
University of Alaska
Institute of Social &
Economic Research
707 A Street, Suite 206
Anchorage, Alaska 99501
143A/on
Revi sed 9/19/83
STATE -MISC.
Mr. Ronald Ripple
Special Assistant to the Commissioner
Department of Commerce & Economic
Development
Pouch D
Juneau, Alaska 99811
Mr. William Beardsley
Director
Division of Finance & Economics
Department of Commerce & Economic
Development
Pouch D
Juneau, Alaska 99811
Mr. Neil Johannsen, Director
(ATTN: Johannsen, Dilliplane & Wiles)
Alaska State Division of Parks
619 Warehouse Avenue
Anchorage, Alaska 99501
Ms. Carolyn Guess, Chairman
Alaska Public Utilities Commission
420 L Street, Suite 100
Anchorage, Alaska 99501
Mr. Robert Martin, Deputy Director
Alaska Department of Environmental
Conservation
437 E Street, Suite 200
Anchorage, Alaska 99501
Mr. Jeff Smith, Director
Alaska Department of Community & Regional
Affa irs
Division of Community Planning
225 Cordova Street, Building B
Anchorage, Alaska 99501
GROUPS/ORGANIZATIONS
Mr. H. Noble Dick, President
Bristol Bay Native Corporation
P.O. Box 220
Anchorage, Alaska 99510
MISC.
Mr. John Isakson
Senior Fisheries Biologist
Dames & Moore
155 N.E. 100th Street, Suite 500
Seattle, Washington 98125-0711
- 2 -
Mr. Pat Poe
Fisheries Research Institute
University of Washington
P.O. Box 8
Iliamna, Alaska 996061
ALEKNAGIK
Aleknagik School Library
General Delivery
Aleknagik, Alaska 99555
CLARKS POINT
Clarks Point -School Library
General Delivery
Clarks Point, Alaska 99569
DILLINGHAM
Dillingham Public Library
P.O. Box 191
Dillingham, Alaska 99576
EGEGIK
Egegik School Library
General Delivery
Egegik, Alaska 99579
EKUK
Available at New Stuyahok
School Library
EKWOK
Ekwok School Library
General Delivery
Ekwok, Alaska 99580
IGIUGIG
Mr. Minicella
Igiugig School
General Delivery
Igiugig, Alaska 99613
ATTN: Library
ILIAMNA
Available at Newhalen School Library
KING SALMON
King Salmon L'ibrary
General Delivery
King Salmon, Alaska 99606
143A/on
KOLIGANEK
Koliganek School Library
General Delivery
Koliganiek, Alaska 99576
MANOKOTAK
Manokotak School Library
General Delivery
Manokotak, Alaska 99628
NAKNEK
Marion Monsen Regional Library
Bristol Bay Borough
P.O. Box 189
Naknek, Alaska 99633
NEWHALEN
Mr. John Davis, Principal
Iliamna-Newhalen High School
P.O. Box 89
Newhalen, Alaska 99606
ATTN: Library
LEVELOCK
Levelock School Library
General Delivery
Levelock, Alaska 99625
NEW STUYAHOK
New Stuyahok School Library
General Delivery
New Stuyahok, Alaska 99636
NONDALTON
Nondalton School Library
General Delivery
Nondalton, Alaska 99640
PORTAGE CREEK
Portage Creek School Library
General Delivery
Portage Creek, Alaska 99576
SOUTH NAKNEK
Available at Naknek (Monsen Regional)
Public Library
- 3 -
STONE & WEBSTER ENGINEERING CORPORATION
DENVER OPERATIONS CENTER
GREENWOOD PLAZA, DENVER, COLORADO ~ ADDRESS ALL CORRESPONDENCE TO p.O. BOX 5406. DENVER. COLORADO 80217
BOSTON
NEW YORK
CHERRY HILL, N.J
DENVER
CHICAGO
HOUSTON
PORTLAND, OREGON
SAN DIEGO
WA.SHINGTON, 0 C
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
334 West 5th Avenue
Anchorage, Alaska 99501
Attn: Mr. Donald W. Baxter
Project Manager
Dear Mr. Baxter:
INTERIM FEASIBILITY ASSESSMENT
BRISTOL BAY REGIONAL POWER PLAN
TELEPHONE : 303-770 -7700
W.U. T ELE X'45-4401
July 31, 1982
J. O. No. 14007.10
Letter No. SWEC/PA-82
Submitted herewith is our Interim Feasibility Assessment for the Bristol
Bay Regional Power Plan Detailed Feasibility Analysis. This 4-volume
report summarizes our work to date under Phase I of the study.
A 3-volume draft Interim Feasibility Assessment report was issued for
review and comment in March 1982. Several revisions have been made to the
draft report as a result of your review. Also, the following important
additions are included:
a) Summaries of the geotechnical and fisheries studies at the
Newhalen site.
b) A new scenario covering local and subregional power developments.
c) Comments by agencies on the draft report and responses by the
Power Authority.
d) A suggested Scope of Work for Phase II.
Mr. Eric P. Yould
July 31, 1982
Page 2
The underlying conclusion of the Interim Feasibility Assessment is that
there are a number of economically attractive alternatives to continuation
of the present practice of reliance on diesel systems for electrical power
generation in the Bristol Bay region. Two of these alternatives, a
regional run-of-river Newhalen River hydroelectric development and a
scenario consisting of several subregional developments, are recommended
for further study. The subregional alternative is a cost effective mix of
disconnected power supply components which consists of a small run-of-river
hydroelectric development on the Tazimina River along wi th wind systems,
waste heat recovery systems and continued diesel generation in various
other subregions.
Our principal findings and conclusions are set forth in the Executive
Summary of the report. Details of the energy demand forecasts, alternative
evaluations, site investigations, engineering studies, economic
evalua tions, and environmental studies which support the conclusions are
described in detail in subsequent sections of the report and in the
Appendices.
It has been a pleasure working with the Alaska Power Authority on this
challenging study, and we look forward to continuing the effort in Phase II.
DLM/cms
Enclosures
Very truly yours,
D. L. Matchett
Project Manager
CERTIFICATIONS
BRISTOL BAY REGIONAL POWER PLAN
DETAILED FEASIBILITY ANALYSIS
INTERIM FEASIBILITY ASSESSMENT
The technical material and data contained in this report and its Appendices
were prepared under the supervision of the following individuals and
organizations:
Volume 1 -Report
Appendix A -Engineering/Technical
Considerations
Appendix B -Energy Supply Technology
Evaluation
AppendiX C -Energy Demand Forecast
AppendiX D -Wind Energy Analysis
AppendiX E -Geotechnical Studies -
Tazimina
AppendiX F -Geotechnical Studies -
Newhalen
Appendix G -Environmental Report
AppendiX H -Newhalen Smolt and
Fry Studies
AppendiX I -Hydrologic Evaluations
~""''''''
~(~~o
Theodore Critikos
O. Scott Goldsmith
Principal Investigator
Institute of Social and Economic
Research
University of Alaska
~.~t/
Mark A. Newell
President
Wind Systems Engineering, Inc.
Er£ .. 0 ... tM-Id
Rohn D. Abbot't
Vice President
S /~nnon & Wilson, Inc,
cP .,-//' ~
.?:." '.({./. / ' ,f1!/(:,"'~-::!.(~'//
James E. Hemmi ng r17
Project Manager
Dames & Moore
Manager. Alaska Operations
.-t.-___ .3o..,
Anand Prakash
Chief Water Resources Engineer
Dames & Moore
_ .... OF Ai"'\'
':":\ ~ ••• • • • •• 4Cf f" \,
#II' r.· * .. "k', ,~.. -:'-d t "" -,. ' ." I 1*': 49ll!' ..... ~
This study was prepared under the supervision
and direction of the undersigned whose seal
as professional engineer is affixed below.
~ •••••••••••••••••••••• ·'t-~
~ to. ·I.i .I Mt.Jdd:I-,: ~ •••••••• ':'\ ••••••••••••• !'~
~ . . ~. ~J ~ e. DONALD L MATCHm : !f ,"
,~. .,~~ t, m.... CE·5204 •• '$;af n-~-? • e •• <'.~ ,., '\ ~() ....... :\.. '" -
\\ PROFESSlOI'4S>' ---\'\.'\,""~
~~~?bZ>l
Donald L. Matchett
Project Manager
Stone & Webster Engineering Corp.
ACKNOWLEDGEMENTS
Stone & Webster Engineering Corporation and its subcontractors wish to
acknowledge the important assistance given by many individuals and
organizations to the project team in undertaking the Interim Feasibility
Assessment. Chapter 8 of this report documents many of the contacts made
with the people of Bristol Bay and with state and federal agencies
concerned with energy development. Without the information and support
received from these sources, satisfactory completion of Phase I of the
Bristol Bay Regional Power Plan Study would have been much more difficult,
if not impossible.
Special acknowledgement is given to the following individuals for their
help:
Ted Angasan, Tom Hawkins, William Johnson, and Kay Larsen, Bristol Bay
Native Association
Representative Joe Chuckwuk and his aide, Paula Scavera
David F. Bouker, Nushagak Electric Cooperative
Gordon McCormick, Naknek Electric Association
Trig Olsen and John Adcox, Iliamna-Newhalen Electric Cooperative
Tom Arminski, Dick Russell, and Tina Cunning, State of Alaska, Department
ofF ish and Game
Ann Rappaport, U.S. Fish and Wildlife Service
Rick Austin, State of Alaska, Department of Natural Resources
Jim Clark and Don Penner, Bristol Bay Borough
Paul Haertel and Mike Tollefson, Lake Clark National Park and Preserve
Don Anderson, JEVAD, Inc.
The above list is far from complete. While it is not possible to recognize
each participant individually, we wish to thank all those who attended the
public meetings in the villages and the agency meetings in Anchorage. The
questions, comments, and suggestions which resulted from these meetings
were a great benefit to the study.
GENERAL OUTLINE
BRISTOL BAY REGIONAL POWER PLAN
DETAILED FEASIBILITY ANALYSIS
INTERIM FEASIBILITY ASSESSMENT
VOLUME 1 -REPORT
VOLUME 2 -APPENDICES
VOLUME 3 -
VOLUME 4 -
APPENDIX A -ENGINEERING/TECHNICAL CONSIDERATIONS
A.I ENERGY NEEDS
A.2 HYDROELECTRIC POWER PROJECTS
A.3 DIESEL POWER
A.4 WASTE HEAT RECOVERY
A.S ENERGY CONSERVATION
A.6 WIND ENERGY
A. 7 POWER TRANSMISSIOJI,T
A.8 FOSSIL-FUEL ALTERNATIVES
A.9 ORGANIC RANKINE CYCLE
A.I0 LOAD MANAGEMENT ANALYSIS
APPENDIX B -ENERGY SUPPLY TECHNOLOGY EVALUATION
APPENDIX C -ENERGY DEMAND FORCAST
APPENDICES
APPENDIX D -WIND ENERGY ANALYSIS
APPENDIX E -GEOTECHNICAL STUDIES -TAZIMINA RIVER
APPENDIX F -GEOTECHNICAL STUDY -NEWHALEN RIVER
APPENDICES
APPENDIX G -ENVIRONMENTAL REPORT
APPENDIX H -NEWHALEN SMOLT AND FRY STUDIES
APPENDIX I -HYDROLOGIC EVALUATIONS -TAZIMINA RIVER
TABLE OF CONTENTS
VOLUME 1 -REPORT
1.
1.1
1.2
1.3
1.4
1.5
1.5.1
1.5.2
1.5.3
1.6
1. 6.1
1.6.2
1. 6. 3
1.7
1. 7.1
1. 7.2
1. 7.3
1.8
1. 8.1
1. 8.2
2.
2.1
2.2
2.3
2.4
2.5
2.6
2.7
3.
3.1
3.1.1
3.1.2
3.2
3.2.1
3.2.2
EXECL~IVE SUMMARY
INTRODUCTION
BRISTOL BAY REGIONAL POWER PLAN
ENERGY DEMAND
ENERGY SUPPLY TECHNOLOGY EVALUATION
DEVELOPMENT OF ENERGY PLANS
Data Collection
Energy Production Concepts
Selected Energy Scenarios
EVALUATION OF SELECTED ENERGY PLANS
Technical
Environmental
Economic
REGULATORY COORDINATION AND PUBLIC PARTICIPATION
Agency Communication
Regulatory Reguirements
Public Participation
CONCLUSIONS AND RECOMMENDATIONS
Conclusions
Recommendations
INTRODUCTION
ENERGY NEEDS IN BRISTOL BAY
PREVIOUS STUDIES
BRISTOL BAY REGIONAL POWER PLAN
STUDY APPROACH AND METHODOLOGY
STUDY PARTICIPANTS
INTERIM FEASIBILITY ASSESSMENT
REPORT ORGANIZATION
ENERGY CONDITIONS AND DEMAND FORECAST
INTRODUCTION
Methodology of Forecasting -Electrical Energy Demands
Methodology of Forecasting -Space Heating Energy Demands
ENERGY FORECASTS
Technical Discussions -Electrical Energy Demands
Technical Discussions -Space Heating Energy Demands
i
PAGE
1-1
1-1
1-2
1-4
1-5
1-6
1-6
1-12
1-15
1-20
1-20
1-21
1-26
1-29
1-29
1-30
1-30
1-31
1-31
1-35
2-1
2-1
2-1
2-2
2-3
2-5
2-6
2-6
3-1
3-1
3-2
3-4
3-5
3-5
3-12
TABLE OF CONTENTS
VOLUME 1 -REPORT
4.
4.1
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
4.1. 6
4.2
4.3
4.3.1
4.3.2
5.
5.1
5.1.1
5.1. 2
5.1. 3
5.1.4
5.1.5
5.1. 6
5.1. 7
5.1.8
5.1. 9
5.1.10
5.1.11
5.2
5.3
5.3.1
5.3.2
5.3.3
5.3.4
5.3.5
5.4
5.4.1
5.4.2
5.4.3
5.4.4
5.4.5
ENERGY SUPPLY TECHNOLOGY
PROFILE OF ENERGY TECHNOLOGIES SURVEYED
Fossil Fuel Resources
Non-Generating Resources
Renewable Resources
Miscellaneous Resources
Nuclear Resources
Advanced Technologies
SELECTED ENERGY TECHNOLOGIES
ASSESSMENT OF SELECTED ENERGY TECHNOLOGIES
Supplementary Resources
Primary Resources
FIELD INVESTIGATIONS AND DATA COLLECTION
GEOTECHNICAL
Introduction
Regional Geologic Setting
Summary of Geotechnical Field Studies, 1981 -Tazimina
Summary of Geologic Conditions -Tazimina Site
Summary of Geotechnical Considerations -Tazimina Site
Summary of Geologic Conditions -Kukaklek Sites
Summary of Geotechnical Field Studies, 1982 -Newhalen
Summary of Geologic Conditions -Newhalen Site
Summary of Geotechnical Considerations -Newhalen Site
Summary of Geologic Conditions -Kontrashibuna Site
Summary of Geologic Conditions -Chikuminuk Site
HYDROLOGIC
ENVIRONMENTAL
Introduction
Water Use and Quality
Terrestrial Ecology
Aquatic Ecology
Air Quality
SOCIOCULTURAL
Historic and Archaeological Resources
Socioeconomic Considerations
Recreational Resources
Aesthetic Resources
Land Use
ii
PAGE
4-1
4-1
4-1
4-3
4-3
4-5
4-6
4-7
4-8
4-8
4-8
4-10
5-1
5-1
5-1
5-2
Site 5-4
5-6
5-7
5-11
Site 5-12
5-14
5-16
5-17
5 -19
5-22
5-26
5-26
5-26
5-27
5-28
5-30
5-31
5-31
5-31
5-32
5-32
5-33
TABLE OF CONTENTS
VOLUME 1 -REPORT
6.
6.1
6.1.1
6.1. 2
6.1. 3
6.2
6.2.1
6.2.2
6.2.3
6.2.4
6.2.5
7.
7.1
7.2
7.2.1
7.2.2
7.2.3
7.2.4
7.2.5
7.3
7.3.1
7.3.2
7.3.3
7.3.4
7.3.5
7.3.6
7.3.7
7.3.B
7.3.9
7.3.10
7.3.11
7.3.12
7.4
7.4.1
7.4.2
7.4.3
7.4.4
7.4.5
7.4.6
ENERGY PLANS
DEVELOPMENT OF ENERGY SCENARIOS
Introduction
Assessment of Energy Resources
Selection of Energy Scenarios
DESCRIPTION OF SELECTED ENERGY SCENARIOS
Introduction
Base Plan, BP-1 Diesel Generation Only
Alternative "A"
Alternative "B"
Miscellaneous Scenario Studies
EVALUATION OF SELECTED ENERGY PLANS
INTRODUCTION
TECHNICAL EVALUATION
Introduction
Safety
Reliability
Availabilit:y
Constructibility
ENVIRONMENTAL EVALUATION
Introduction
Community Preferences
Impact on Community Infrastructure
Timing in Relation to Other Capital Projects
Air Quality
Water Quality
Fish and Wildlife Impact
Land Use Impact and Ownership Status
Terrestrial Impact
Recreational Resource Value
Visual Impact
Summary Evaluation
ECONOMIC EVALUATION
General
Parameters and Assumptions
Method of Analysis
Determination of Annual Costs
Results
Economic Summary
iii
PAGE
6-1
6-1
6-1
6-3
6-15
6-19
6-19
6-19
6-20
6-21
6-36
7-1
7-1
7-1
7-1
7-2
7-2
7-5
7-7
7-10
7-10
7-10
7-1B
7-27
7-34
7-42
7-53
7-65
7-76
7-B7
7-96
7-105
7-10B
7-108
7-108
7-110
7-113
7-122
7-127
TABLE OF CONTENTS
VOLUME 1 -REPORT
8.
8.1
8.1. 1
8.1. 2
8.2
8.2.1
8.2.2
8.2.3
8.2.4
8.2.5
REGULATORY COORDINATION AND PUBLIC PARTICIPATION
REGULATORY COORDINATION
Agency Involvement
Regulatory Requirements
PUBLIC PARTICIPATION
General
Interests
Communications
Records of Comments and Responses
Summary of Significant Events
9.
9.1
9.1.1
9.1. 2
9.1. 3
9.1.4
9.2
CONCLUSIONS AND RECOMMENDATIONS
CONCLUSIONS
10.
10.1
10.2
Introduction
Energy Demand Forecast
Energy Technologies
Evaluation of Energy Plans
RECOMMENDATIONS
SCOPE OF WORK -PHASE II
Introduction
Objective
VOLUME 2 -APPENDICES
A. ENGINEERING/TECHNICAL CONSIDERATIONS
A.1 ENERGY NEEDS
A.2 HYDROELECTRIC POWER PROJECTS
A.3 DIESEL POWER
A.4 WASTE HEAT RECOVERY
A.5 ENERGY CONSERVATION
A.6 WIND ENERGY
A.7 POWER TRANSMISSION
A.8 FOSSIL-FUEL ALTERNATIVES
A.9 ORGANIC RANKINE CYCLE
A.10 LOAD MANAGEMENT ANALYSIS
B. ENERGY SUPPLY TECHNOLOGY EVALUATION
C. ENERGY DEMAND FORECAST
iv
PAGE
8-1
8-1
8-1
8-2
8-3
8-3
8-4
8-5
8-8
8-62
9-1
9-1
9-1
9-1
9-3
9-4
9-11
10-1
10-1
10-1
TABLE OF CONTENTS
VOLUME 3 -APPENDICES
D. WIND ENERGY ANALYSIS
E. GEOTECHNICAL STUDIES -TAZIMINA RIVER
F. GEOTECHNICAL STUDY -NEWHALEN RIVER
VOLUME 4 -APPENDICES
G. ENVIRONMENTAL REPORT
H. NEWHALE~ SMOLT AND FRY STUDIES
I. HYDROLOGIC EVALUATIONS -TAZIMINA RIVER
v
Table
1.5-1
1.6-1
1.6-2
1.6-3
3.2-1
3.2-2
3.2-3
3.2-4
3.2-5
3.2-6
3.2-7
3.2-8
3.2-9
3.2-10
3.2-11
3.2-12
6.1-1
6.1-2
7.3-1
7.4-1
7.4-2
7.4-3
7.4-4
7.4-5
7.4-6
7.4-7
7.4-8
7.4-9
7.4-10
7.4-11
7.4-12
7.4-13
LIST OF TABLES -VOLUME 1
Title
Summary of Alternative B Scenarios
Summary of Economic Analysis Parameters
Economic Lifetimes for Major Equipment
Summary of Present Worth Costs
Bristol Bay Power Plan Overall Electric Energy
Demand Projections
Bristol Bay Regional Power Plan Electrical Energy
Demand Projections by Customer
Preliminary Project Forecast -Electrical Energy
and Power Requirements Based on a Base Plan
Scenario by ISER
Projected Appliance Electricity Consumption
1980 Electricity Consumption in the Bristol Bay
Commercial/Government Sector
Commercial and Government/Community Buildings -1981
Growth in Use Per Customer and Number of Customers
in the Commercial/Government Sector
Electricity Consumption by Bristol Bay
Fish Processors: 1980
Bristol Bay Seafood Processor Electricity Demand
Projections
Space Heating in 1980 in the Eighteen Study-Area
Communities
Space Heating Demand Forecast by Village by Sector
Segregation of Space Heating, Hot Water, and Other
Energy Needs-by Sector
Potential Hydrosites in the Bristol Bay Area
Potential Power Supply Systems
Environmental Evaluation Summary
Summary of Economic Analysis Parameters
Economic Lifetimes of Major Equipment
Discounted Cash Flow Analysis-Scenario B-14A-
Newhalen Regional Hydroelectric Project-Power
Diversion
Diesel Generator and Storage Tank Capital Costs
BP-1 Diesel Generator and Storage Tank Capital Costs
Diesel Fuel Cost
Diesel Generator Fuel Rates
BP-l Diesel Fuel Usage for Selected Years
Diesel Fuel Usage for Scenarios B-15, B-16, and B-17
Waste Heat Recovery Equipment Capital Costs
B-19A and B-19C Waste Heat Recovery Equipment
Capital Costs
B-19A Diesel Waste Heat Recovery Benefit for
Selected Years
Diesel Waste Heat Recovery Benefit for Scenarios
B-15, B-16, and B-17
Table
7.4-14
7.4-15
7.4-16
7.4-17
7.4-18
7.4-19A
7.4-19B
7.4-20
7.4-21
7.4-22
7.4-23
7.4-24
7.4-25
7.4-26
7.4-27
7.4-28
7.4-29
7.4-30
7.4-31
7.4-32
7.4-33
7.4-34
7.4-35
7.4.36
7.4-37
7.4-38
7.4-39
8.2-1
8.2-2
8.2-3
9.1-1
LIST OF TABLES -VOLUME 1 (Cont)
Title
Installed Capital Costs of Wind Turbines
B-19D Organic Rankine Cycle Benefit
Kukaklek (Kvichak Region) Hydroelectric Power Plant
Kukaklek Regional Hydroelectric Power Plant
Newhalen River Local Hydroelectric Power Plant
Newhalen River Regional Hydroelec~ric Power Plant-
Newhalen River Diversion-Power Only
Newhalen River Regional Hydroelectric Power Plant-
Newhalen River Diversion-Power and River Diversion
Tazimina Run-of-River Regional Hydroelectric Power
Plant
Tazimina River (Kvichak River Region) Hydroelectric
Power Plant
Tazimina River Regional Hydroelectric Power Plant
Tazimina Run-of-River Local Hydroelectric Power
Plant
Chikuminuk Lake Regional Hydroelectric Power Plant
Chikuminuk Lake (Nushagak Region) Hydroelectric
Power Plant
Kontrashibuna Lake Regional Hydroelectric Power
Plant
Hydroelectric Plant Annual Sinking Fund and
Operation and Maintenance Costs
Electric Transmission System Installed Capital
Costs
Electric Substation Expansion Capital Costs for
Scenarios B-15, B-16, and B-17
Scenario B-1 Purchased Power Cost
Summary of Bristol Bay Regional Power Scenarios
Summary of Present Worth Costs for Scenarios BP-1
B-15, B-16, B-17, and B-19
BP-1 Variations by Village -Summary of Present
Worth Costs
Present Worth Costs -Wind and Waste Heat Recovery
Variations for Scenario B-14A
Present Worth Costs for Iliamna/Newhalen/Nondalton
Hydroelectric Versus Scenario BP-1
Present Worth Costs for Nushagak River Region Hydro-
electric Versus Diesel Generation
Village Power Supply Options for B-19E Scenario
Summary of Present Worth Costs
Present Worth Ratios-Regional Power Scenarios
Comments and Questions from September and October
Community Meetings
Public/Community Meetings
Chronological List of Significant Events Affecting
the Study Effort
Summary of Present Worth Costs
Figure
1. 2-1
3.2-1
5.2-1
6.1-1
6.1-2
6.1-3
6.2-1
6.2-2
6.2-3
6.2-4
6.2-5
6.2-6
6.2-7
6.2-8
6.2-9
6.2-10
6.2-11
6.2-12
6.2-13
6.2-14
6.2-15
6.2-16
6.2-17
6.2-18
7.4-1
LIST OF FIGURES -VOLUME 1
Title
Bristol Bay Region
Regional Space Heating Needs
Average Annual Runoff
Potential Hydroelectric Sites, Bristol Bay Region
Preliminary Assessment of Alternative Hydroelectric
Sites
Bristol Bay Region Community Grouping
Base Plan Scenario BP-1
Alternative "A" Scenario A-1
Alternative "B" Scenario B-1
Alternative "B" Scenario B-2
Alternative "B" Scenario B-3
Alternative "B" Scenario B-4
Alternative "B" Scenario B-5
Alternative "B" Scenario B-6
Alternative "B" Scenario B-7
Alternative "B" Scenario B-8
Alternative "B" Scenarios B-9 and B-10
Alternative "B" Scenarios B-11 and B-12
Alternative "B" Scenario B-13
Alternative "B" Scenario B-14
Alternative "B" Scenario B-15
Alternative "B" Scenario B-16
Alternative "B" Scenario B-17
Alternative "B" Scenario B-18
Accumulated Present Worth Costs
Table
A.1-1
A.l-2
A.1-3
A.1-4
A.1-S
A.l-6
A.l-7
A.1-8
A.2-1
A.2-2
A.2.3
A.2-4
A.2-S
A.2-6
A.2-7
A.2-8
A.2-9
A.2-10
A.2-llA
A.2-1lB
A.2-l2
A.2-13
A.2-14
LIST OF TABLES -VOLUME 2, APPENDIX A
Title
Demand Forecast by R. W. Retherford, Electric Energy
and Power Requirements, Low Load Growth
Demand Forecast by R. W. Retherford, Electric Energy
and Power Requirements, High Load Growth
Bristol Bay Power Plan Overall Electric Energy
Demand Projections (Megawatt Hours/Year)
Bristol Bay Regional Power Plan Electrical Energy
Demand Projections by Customer
Preliminary Project Forecast, Electrical Energy and
Power Requirements Based on Base Plan Scenario by
ISER
Forecast Electric Energy and Power Needs, Bristol
Bay Study Area-Year 2002
Space Heating Demand Forecast by Village by Sector,
Bristol Bay Study Region
Segregation of Space Heating Energy Needs and Hot
Water & Other Energy Needs-by Sector, Bristol Bay
Study Region
Summary Data, Tazimina River, Regional Hydroelectric
Power Project
River and Generating Flows, Tazimina River,
Regional Hydroelectric Power Project
Average Reservoir Release and Level, Tazimina
River, Regional Hydroelectric Power Project
Monthly Energy Contribution, Tazimina River, 16 MW
Regional Run-of-River Power Project
River and Generating Flows, Tazimina River, Local
Run-of-River Power Project
Summary Data, Kontrashibuna Lake, Regional
Hydroelectric Power Project
Summary Data, Chikuminuk Lake, Regional
Hydroelectric Power Project
Flow Data, Chikuminuk Lake, Regional Hydroelectric
Power Project
Summary Data, Chikuminuk Lake, Local Hydroelectric
Power Project
Flow Data, Chikuminuk Lake, Local Hydroelectric
Power Project
Summary Data, Newhalen River Diversion, Power Only,
Regional Hydroelectric Power Project
Summary Data, Newhalen River Diversion, Power &
River Diversion, Regional Hydroelectric Power
Project
Flow Data, Newhalen River Diversion, Regional
Hydroelectric Power Project
Summary Data, Newhalen River Diversion, Local
Hydroelectric Power Project
Flow Data, Newhalen River Diversion, Local
Hydroelectric Power Project
Table
A.2-15
A.2-16
A.2-17
A.2-18
A.2-19
A.2-20
A.3-1
A.3-2
A.3-3
A.3-4
A.3-5
A.3-6
A.3-7
A.3-8
A.4-1
A.4-2
A.7-1
LIST OF TABLES -VOLUME 2, APPENDIX A (Cont)
Title
Summary Data, Kukaklek Lake, Regional Hydroelectric
Power Project
Kukaklek Lake, Natural-Regulated-Generating Flows,
Regional Hydroelectric Power Project
Kukaklek Lake, Water Surface Elevations,
Regional Hydroelectric Power Project
Summary Data, Kukaklek Lake, Local Hydroelectric
Power Project
Kukaklek Lake, Natural-Regulated-Generating Flow,
Local Hydroelectric Power Project
Kukaklek Lake, Water Surface Elevations, Local
Hydroelectric Power Project
Generator Comparisons-kWh/Gal of Oil
Diesel Units to be Installed, Scenario
Diesel Units to be Installed, Scenario
Percent of Reserve -Scenario B-15
Diesel Units to be Installed, Scenario
Percent of Reserve -Scenario B-16
Diesel Units to be Installed -Scenario
Percent of Reserve -Scenario B-17
Waste Heat Rate per Kilowatt-Hour
Usable and Non-usable Waste Heat
BP-1
B-15
B-16
B-17
Three-phase Transmission Line Capacity -Megawatt -
Miles, 5 Percent Regulation, 0.9 Power Factor
Figure
A.l-l
A.l-2
A.l-3
A.l-4
A.l-S
A.l-6
A.l-7
A.l-8
A.l-9
A.l-lO
A.l-ll
A.l-l2
A.l-l3
A.l-l4
A.l-lS
A.l-l6
A.l-l7
A.l-l8
A.l-l9
A.l-20
A.l-2l
A.l-22
A.l-23
A.l-24
A.l-2S
A.2-l
A.2-2
A.2-3
A.2-4
A.2-S
A.2-6
A.2-7
A.2-8
A.2-9
A.2-l0
A.2-ll
A.2-l2
A.2-l3
A.2-l4
A.2-lS
A.2-l6
LIST OF FIGURES -VOLUME 2, APPENDIX A
Title
Forecasts of Energy Needs
Electricity Demand Ratio Variation, Dillingham.
Electricity Demand Ratio Variation, Naknek Group
Electricity Demand Ratio Variation, Clarks Point
Electricity Demand Ratio Variation, Egegik
Electricity Demand Ratio Variation, Ekuk
Electricity Demand Ratio Variation, Ekwok
Electricity Demand Ratio Variation, Igiugig
Electricity Demand Ratio Variation, Koliganek
Electricity Demand Ratio Variation, Levelock
Electricity Demand Ratio Variation, Manokotak
Electricity Demand Ratio Variation, New Stuyahok
Electricity Demand Ratio Variation, Portage Creek
Electricity Demand Ratio Variation, Iliamna Group
Energy Demand Distribution, Nushagak Electric
Co-op (Dillingham)
Capacity Demand Distribution, Nushagak Electric
Co-op (Dillingham)
Energy Demand Distribution, Naknek Electric
Association (Naknek)
Capacity Demand Distribution, Naknek Electric
Association (Naknek)
Energy Demand Distribution, Rural Villages
Capacity Demand Distribution, Rural Villages
Energy Demand Distribution, Fish Process Villages
Capacity Demand Distribution, Fish Process Villages
Space Heating Needs
Regional Space Heating Needs
Average Monthly Distribution of Degree Days
Tazimina River, Regional Power Project
Tazimina River Development, Regional Power Project
Tazimina River Development, Regional Power Project
Tazimina River Development, Regional Power Project
Tazimina River Development, Regional Power Project
Reservoir Area Volume Curve, Tazimina Lake
Tazimina River, Regional Run-of-River Project
Tazimina River Flow-Duration
Tazimina River, Local Run-of-River Project
Tazimina River Development, Local Power Project
Kontrashibuna Lake, Regional Power Project
Kontrashibuna Lake Development, Regional Power
Project
Kontrashibuna Lake Development, Regional Power
Project
Kontrashibuna Lake Development, Regional Power
Project
Kontrashibuna Storage Reservoir
Chikuminuk Lake, Regional Power Project
Figure
A.2-17
A.2-18
A.2-19
A.2-20
A.2-21
A.2-22
A.2-23
A.2-23A
A.2-24
A.2-25
A.2-26
A.2-26A
A.2-27
A.2-28
A.2-29
A.2-30
A.2-31
A.2-32
A.2-33
A.2-34
A.2-35
A.2-36
A.4-1
A.4-2
A.4-3
A.5-1
A.5-2
A.5-3
A.5-4
Exhibit A
A.6-1
A.6-2
A.6-3
A.6-4
A.6-5
A.6-6
LIST OF FIGURES -VOLUME 2, APPENDIX A (Cont)
Title
Chikuminuk Lake Development, Regional Power Project
Chikuminuk Lake Development, Regional Power Project
Reservoir Area Volume Curve, Chikuminuk Lake
Chikuminuk Lake, Local Power Project
Chikuminuk Lake Development, Local Power Project
Chikuminuk Lake Development, Local Power Project
Newhalen River Canal Diversion, Regional Power
Project (Only)
Newhalen River Canal Diversion, Regional Power
Project
Newhalen River Canal Diversion, Regional Power
Project (Only)
Newhalen River Canal Diversion, River Diversion &
Regional Power Project
Newhalen River Canal Diversion, River Diversion &
Regional Power Project
Newhalen River Canal Diversion, River Diversion &
Regional Power Project
Newhalen River Canal Diversion, Regional Power
Project
Newhalen River Diversion, Local Power Project
Newhalen River Diversion, Local Power Project
Newhalen River Diversion, Local Power Project
Kukaklek Lake, Regional Project
Kukaklek Lake Development, Regional Power Project
Kukaklek Lake Development, Regional & Local Power
Projects
Kukaklak Lake Development, Regional & Local Power
Projects
Kukaklak Lake, Local Power Project
Kukaklek Lake, Local Power Project
System Diagram
System Diagram
Typical Closed Loop Hot Water System
Conservation Investment, 2 Year Life
Conservation Investment, 5 Year Life
Conservation Investment, 10 Year Life
Conservation Investment, 20 Year Life
HUD/FHA Denver Reg/Area Office Thermal Requirements
Village-Located, Wind Turbine Alternative
Village-Located, Wind Turbine Alternative
Village-Located, Wind Turbine Alternative
Grouped Villages, Wind Turbine Alternative
Grouped Villages, Wind Turbine Alternative
Interconnected Bristol Bay Region, Wind Turbine
Alternative
Figure
A.7-1
A.8-1
LIST OF FIGURES -VOLUME 2, APPENDIX A (Cont)
Title ------::..;;;;;
Transmission Line Terrain Construction Cost
Adjustment Factors
Typical Plan Coal-Fired Steam Electric Generating
Station
-
....
-
-
-1. EXECUTIVE SUMMARY
",.
'>.
,.
---
....
1 . EXECUTIVE SUMMARY
'inj £ Executive Summary is intended to provide a concise revh.w of the t·Tolk
r e.rfCJrmed to date by Stone & Webster Engineering Corporation end it ..
s':L1contractors during Phase I of the Bristol Bay Regional Power 1-11'
stu.:i.y. This phase of the study concludes with a milestone calle.:;' ib
Interim Feasibility Assessment. The Executive Summary highlights thf' w·'.~'
accomplished in reaching this milestone and presents major results arld
conclusions. The report and its appendices which follow should be
consulted for the detailed analysis which provides the basis for thL
sum;nary.
1.1 INTRODUCTION
Electric power cost and availability have been identified by the residents
0f the Bristol Bay region as important concerns. Fuel oil is currently t.b.a
primary energy source in the Bristol Bay region, both for electrical
generation and space heating. The cost of energy production. is currently
high and has increased rapidly in recent years, due not only to the
world"wide price escalation of fuel oil, but also to regional factors. The
cost of electrical energy production in remote villages primarily served by
smAll, non-central diesel electric generators is many times that of large).
m0re efficient interconnected central systems in larger population cent,r~
of Alaska and in other parts of the United States.
In recent years the state of Alaska has taken a number of steps to &d~re~~
the energy problems in remote regions of the state. Direct subsidies clJe
in effect which substantially reduc.e the cost of electricity to consumel.'S
in certain villages. In addition, the state has undertaken studies to
evalu:lte potential sources of electrical energy production other than by
diesel generators. Hydroelectric power generation, a renewable ene:cgy
source, has been identified as a source which in the future may pru·'id.,.
reliable low cost electricity for the Bristol Bay re.giun; wind 8Jlergy i
aYJ.otber renewable energy source which Iliay have application.
1 i
In 1980, a "Reconnaissance Study" by R. W. Retherford Associates for the
Alaska Power Authority, evaluated the feasibility of potential
hydroelectric developments in the Bristol Bay region. Projects were
identified which were considered attractive for limited areas. The
Retherford study also evaluated a hydro site on the Tazimina River about
ten miles north of Iliamna Lake and east of Nondalton Village which was
believed suitable for supplying regional needs through the year 2000.
Retherford stated that "development of the Tazimina potential will result
in the lowest power cost for all communities in an integrated, combined
system."
1. 2 BRISTOL BAY REGIONAL POWER PLAN
Based on the Retherford recommendation, the Alaska Power Authority retained
Stone & Webster Engineering Corporation (SWEC) in July 1981 to undertake a
study called the "Bristol Bay Regional Power Plan and Detailed Feasibility
Analysis". The purpose of this study is to assess the technical, economic,
and environmental aspects of alternative electric power generation plans
for the Bristol Bay region. A specific objective of the study is to
evaluate in detail the feasibility of the Tazimina Hydroelectric Project
and to compare it with the current practices of diesel generation and other
promising alternatives.
The Regional Power Plan addresses the needs of an 18-village study area
within the region. The boundaries of the study area are the previously
determined economic limits of the Tazimina Project market area. The
villages included in the study area are Aleknagik, Clarks Point,
Dillingham, Egegik, Ekuk, Ekwok, Igiugig, Iliamna, King Salmon, Levelock,
Manokotak, Naknek, Newhalen, New Stuyahok, Nondalton, Portage Creek, and
South Naknek. Figure 1.2-1 shows the Bristol Bay study region.
The Work Plan for the study divides the work into two phases. Phase I,
called the "Interim Feasibility Assessment", and the subject of this
report, identifies numerous alternatives for energy production and compares
them with respect to technical feasibility, environmental impact, and cost.
1-2
•
•
.,
..
..
..
•
• ..
• -..
.. -
•
..
..
..
..
Based on the outcome of Phase I, the Work Plan calls for the continuation
of the Study with Phase II, when the most promising alternatives will be
evaluated and compared in more detail and a recommendation made regarding
project development.
The central focus of Phase I of the Regional Power Plan is a thorough
evaluation and comparison of the major energy options which are available
for the Bristol Bay region. The following three hypothetical power plan
cases were used as the framework for comparing various options:
• Base Case, which represents the continuation of present practices
of reliance on oil-fired (diesel) generation;
• Alternative "A", which consists of the Tazimina River
Hydroelectric Project as the required power supply;
• Alternative "B", which consists of other energy sources, projects,
or facilities, either alone or in combination.
The primary purpose of the Phase I Report is to present information to the
Power Authority and the people of the Bristol Bay region so that decisions
can be made regarding the next step. The conclusions and recommendations
which follow have taken into account a large body of information obtained
from the residents of Bristol Bay and from State and Federal agencies
interested in natural resource development and protection of the
environment. However, the Phase I work should be viewed as a first s~ep in
the decision-making process. The emphasis is on engineering,
environmental, and economic considerations, with the objective of screening
out concepts which are impractical from these standpoints. A further
evaluation of the most promising energy production scenarios, including
more detailed environmental investigations, and a second level of
engineering and economic comparisons between promising alternatives and the
Base Plan, is planned for Phase II.
1-3
1 . 3 ENERGY DEMAND
Levels of current energy use and predictions of future needs in the Bristol
Bay study region are being evaluated by the Institute of Social and
Economic Research (ISER) of the University of Alaska. An interim report on
future energy demand prepared by ISER is attached as Appendix C. The
demand forecast contained in this report has been used to size and schedule
the new electrical energy supply systems developed and evaluated during the
Interim Feasibility Assessment.
The forecast provided by ISER is based on the "Base Plan" electrical supply
scenario, which is a continuation of the present practice of reliance on
diesel generation. Al though the requirements for other energy needs such
as space heating were predicted, it was assumed that conversion from oil to
electricity would not occur at this time under the Base Plan scenario
because of a lack of economic incentive.
ISER concludes that based on the present price of fuel, conversion to
electrical space heating would not be significant unless the cost to the
consumer approached $. OS/kWh in 1982 dollars. Such low electricity costs
are unlikely for the scale of development needed for the Bristol Bay
region. However, conversion could be attractive at much higher energy
costs as the price of fuel oil rises in response to dwindling world
supplies.
The growth of electrical energy demand over the study period (1982 to 2002)
used in developing the alternative power plans falls between the "high" and
"low" demand scenarios predicted by Retherford, approaching the "low"
scenario. This is due probably to an assumption by Retherford of some
conversion from oil to electricity for space heating, resulting from a low
cost hydroelectric system. The current assumption of no conversion should
be conservative with respect to projected growth in regional energy usage;
this assumption is also believed to be suitable for the first level
comparison of a number of competing energy supply systems. The following
tabulation shows energy and demand values used for power plan
development. The methodology for developing these values, using the ISER
forecast, is explained in Appendix A.1.
1-4
•
.' ..
• .,
.'
..
•
JII
..
..
...
..
.'
•
..
Annual Energy Peak
Year Requirements (MWh/yr) Demand (MW)
1982 32,400 7.9
1987 38,700 8.9
1992 47,600 11. 2
1997 58,900 12.2
2002 74,500 15.0
ISER has completed its examination of the relationship between the cost of
electrical energy to the consumer and energy use. Sensitivity studies have
been made to further quantify the economics of conversion to electrical
energy for space a~d water heating. It is planned to address this subject
in more detail during further evaluation of the most attractive
alternative(s) in Phase II.
1.4 ENERGY SUPPLY TECHNOLOGY EVALUATION
An energy supply technology evaluation was undertaken to review and
evaluate proven and commercially available energy technologies and to
select technologies appropriate for use as elements of alternative power
plans. Twenty-five potential energy supply technologies were evaluated.
The evaluation considered a number of factors related to application in the
Bristol Bay study region. Factors considered for each technology were
commercial availability; technical and regional restraints; environmental
and regulatory considerations; and construction, operation, and maintenance.
The 25 technologies were grouped into the following six basic categories:
• Fossil fuels
• Renewable resources
• Nuclear
• Advanced technologies
• Non-generating alternatives
• Miscellaneous resources
1-5
were found in each category except Nuclear and Promising candidates
Advanced technologies.
and regulatory reasons.
Nuclear was ruled out for a variety of technical
All candidates in the Advanced technologies
category (some of which were renewable resources) were either commercially
unavailable or not technically viable for the remote Bristol Bay region.
Nine energy supply technologies were found to be attractive for application
in the Bristol Bay region. The selected systems were:
Primary Sources Supplementary Sources
• Diesel electric
• Coal gasification (combined cycle)
• Coal-, oil-, and natural
gas-fired steam
electric generation
• Combined cycle (oil)
• Hydroelectric
• Wind
• Energy conservation
• Waste heat recovery
• Organic Rankine Cycle
The nine candidates receiving the "attractive" designation were used as
elements of specific power plan systems for Bristol Bay.
1 . 5 DEVELOPMENT OF ENERGY PLANS
1. 5.1 Data Collection
The objective of the data collection program as defined by the Work Plan is
to collect and compile all technical, environmental, and sociocultural
data necessary to assess project feasibility and to meet any licensing or
permitting requirements of FERC and other federal, state, and local
regulatory agencies. Phase I accomplished this objective with respect to
data required to compare various alternatives. In addition, a much larger
data base was collected as the first step in determining the feasibility of
the regional Tazimina and Newhalen projects. However, additional data will
be required in Phase II to fully satisfy licensing requirements of the
project(s) finally proposed for development.
1-6
• ..
-..
..
..
•
.,
• -
•
...
• -
•
• ..
•
The data collection program was divided into the following subtasks:
• Geotechnical
• Hydrologic
• Environmental and Sociocultural
1.5.1.1 Geotechnical
The geotechnical data collection program analyzed the Bristol Bay regional
geologic setting, investigated in considerable detail geotechnical
conditions at various sites previously proposed for major features of the
regional Tazimina and Newhalen hydroelectric developments, and collected
geotechnical data for other sites considered as promising hydroelectric
alternatives. These latter sites were near Kukaklek Lake, on the Newhalen
River (local project), Kontrashibuna on the Tanalian River, and the
Chikuminuk Lake site. Information gathered on these sites was limited to
literature searches, supplemented in some cases by helicopter overflights
and ground visits.
The detailed geotechnical investigations at the Tazimina and Newhalen sites
were undertaken by Shannon & Wilson, Inc., and are fully reported in
Appendices E and F, respectively, to this report.
The Tazimina field studies were undertaken in the summer and fall of 1981
as part of the original plan to investigate that site because of the
favorable Retherford recommendation. The Newhalen field studies were
undertaken in the spring of 1982 in response to preliminary "findings by
Stone & Webster Engineering Corporation that the technical feasibility and
economics of a hydroelectric development on the Newhalen River might be
more favorable than Tazimina. Detailed geotechnical field studies were
required to test the assumptions upon which the preliminary design of the
proposed Newhalen canal diversion concept was based.
The Tazimina
valley, six
investigations
seismic lines
included geologic mapping along the river
across the valley at possible locations for
structures, four borings to obtain profiles of soil and rock materials,
1-7
hand dug test pits, and laboratory tests. A seismic survey and a boring at
the previously proposed dam site at the outlet of Lower Tazimina Lake
indicated depths of up to 180 feet of highly pervious sand and gravel over
bedrock. An impervious cutoff about 1.2 miles long would be required in
this material to provide an effective storage dam. Because of the
difficulty and cost of constructing such a cutoff, this location is not
recommended for further consideration. In addition, seismic surveys and a
boring at the previously identified Roadhouse Dam Site indicated pervious
outwash material and bedrock sloping downward into the right abutment. It
would be extremely expensive, or perhaps impossible, to provide a
water-tight storage reservoir at this location. Because of the
disappointing results of the investigation at the above sites, a further
search was initiated for a suitabJ.e location for a dam and reservoir. A
location about four miles downstream of the outlet of Lower Tazimina Lake
was found which appears to offer the best prospects for a regulating dam
site. At this location, bedrock outcrops appear in both abutment areas and
seismic refraction surveying has defined the continuous bedrock surface
beneath the valley. However, overburden is up to 170 feet thick, and
requires a positive cutoff to rock to ensure dam stability and eliminate
excessive seepage losses. Suitable locations were identified for a forebay
dam, penstock, and powerhouse. The locations as presently proposed for
these features are shown in Appendix A.2.
For the regional Newhalen River concept, investigations included eight
borings, and seven electrical resistivity profile probes to obtain profiles
of soil and rock materials, installation of four observation wells for
groundwater data, laboratory testing of selected soil samples from borings,
and limited surface geologic observations.
The geologic investigations were performed along the alignment of the
proposed water conveyance canal. Seismic survey and resistivity probes
indicated depths of rock varying from about from about 15 feet below the
surface near the canal intake, to about 60 to 80 feet near the canal outlet
area in the vicinity of the scarp.
1-8
.. ..
•
• ..
• ..
..
., ..
till, ..
., ..
• .' ., ..
•
• .. ..
• ..
•
• ..
..
• -
The depth to bedrock is a factor in the design of the canal. Although some
of the canal would be excavated in rock, a large portion would be
constructed in the soil strata which have been identified as clean sands
and gravels. Because of the existence of these permeable materials, the
canal invert and sides will be lined with roller compacted concrete as a
protective measure against erosion, seepage, and freeze-thaw conditions.
Excavation of the soil material is not anticipated to pose any difficulty
other than that associated with control of groundwater inflows. Special
provisions have to be made for groundwater control, particularly as the
canal approaches its terminus near the older erosional scarp of the
Newhalen River. In this vicinity, and for a distance of about 300 feet
along the canal, special external drainage control systems will be needed
to collect and safely handle seepage flows. Such drainage systems would
preclude seepage outflow from the canal, retaining its stability.
The canal concept and general arrangements considered for the regional
Newhalen River project(s) are shown in Appendix A.2.
Geotechnical investigations for the other technically promising
hydroelectric sites at Kukaklek, Newhalen (local), Kontrashibuna, and
Chikuminuk were of a very preliminary nature. However, based on the data
analyzed, no major adverse geotechnical conditions were identified.
1.5.1.2 Hydrologic
Reasonably accurate predictions of river flows are necessary to determine
the capacity of potential hydroelectric generating sites. Available data
from several sources were collected and analyzed to make such predictions.
The principal sources of data for the hydroelectric sites considered were
water resources atlas, gaging station data from nearby drainage areas, and
in several cases, gaging stations on the river being studied. Using
various techniques, depending upon data availability, storage capacities
and design flows were selected for hydroelectric project development and
comparison.
1-9
USGS flow data for the Kontrashibuna and Newhalen River sites provided
sufficient data for preliminary hydrologic predictions. Because only
limited data were available at the Chikuminuk site, analysis required a
correlation with the USGS gaging data on the Nuyakuk River to develop
sufficient information. Kukaklek Lake has virtually no hydrologic data
available, therefore, discharge estimates were made based on adjustments of
other gaging records in the area.
A gaging station was installed by the USGS on the Tazimina River near the
proposed regulating dam site in the summer of 1981. However, it was
necessary to use simulation methods to predict long-term Tazimina River
flows for use in estimating power generation potential. The predictive
procedures used by Dames & Moore and the results of the simulation are
presented in detail in Appendix I of this report. The current predictions
of flow in the Tazimina River at the proposed hydroelectric site are about
18 percent lower on an annual basis than previous predictions by
Retherford. More importantly from the standpoint of the site's generating
capacity, the current predictions for November through April, the low flow
season, are only about one-third of the previous estimates. This result
has a very important effect on the development potential and economic
attractiveness of Tazimina. In comparison with previous development
concepts, considerably more storage capacity would have to be provided in
order to have the regulated flows needed to produce the same electrical
output in the winter months.
The Newhalen River generating concept is
Studies of the 16 year streamflow gage
a run-of-river power project.
data show that there exists
sufficient flow to generate the power needs of the region through the year
2002. Because of the large drainage area involved, there is sufficient
flow throughout the year to maintain channel flow condition and still
satisfy generating flow needs.
1.5. 1.3 Environmental and Sociocultural
The environmental data collection program was undertaken to obtain baseline
data for comparing alternative plans, including transmission systems, to
1-10
.. ..
• .,
.,
.....
..
..
It< ..
••
' ..
., ..
.,
perform a detailed analysis of the proposed Tazimina project, and to
address on a preliminary basis the question of fish protection at the
intake to the Newhalen Canal. A special effort was made to collect
sociocultural information. Sociocultural data, collected on a regional
basis, provided useful input for defining energy supply concepts which
would be most compatible with local values.
The major elements of the environmental and sociocultural data collection
program were:
• Water use and quality
• Terrestrial ecology, including vegetation, birds, and mammals
• Aquatic ecology
• Historical, archeological, and recreational resources
• Air quality
• Population and demography
• Socioeconomics
• Land use
• Community attitudes
Special emphasis was placed on the collection of data related to the
fisheries within the Tazimina River drainage; an evaluation of the sockeye
salmon fishery and spawning locations below the Tazimina Falls was
particularly emphasized. If a decision is made to proceed in Phase II with
a detailed analysis of the Tazimina hydroelectric concept, further detailed
studies, including an instream flow modeling program, will be required.
Appendix G presents, in detail, the environmental and sociocultural field
data collected for the region in Phase I, and in particular, for Tazimina.
This baseline data and other information, obtained largely from literature
searches and limited field reconnaissance, provided the basis for power
plan scenario development and evaluation. Additionally, the data base
collected at Tazimina is believed sufficient in detail to satisfy the
environmental requirements of a FERC license application for a run-of-river
concept.
1-11
The Newhalen River regional hydroelectric concept diverts on the average
about 1000 cfs through a canal to the power plant. The most important
environmental concern related to this concept is protection of the Newhalen
River sockeye salmon escapement. Downstream migrating smolt and fry would
have to be diverted from the canal intake or collected and returned to the
river to ensure safe passage around the project. Studies at other water
intakes indicate that such diversion can be satisfactorily accomplished.
However, to properly design the diversion facilities and to predict their
effectiveness on the Newhalen River, a field program was undertaken in the
spring of 1982 to characterize the downstream smolt and fry migration.
Appendix H presents the results of field data collected in Phase I on the
Newhalen smolt and fry studies.
If a decision is made to proceed in Phase II with a detailed analysis of
the Newhalen regional hydroelectric concept, further detailed studies,
including testing of methods for diverting and/or collecting downstream
migrants, will be required. Also, studies relating to resident fish within
that portion of the Newhalen River, that may be affected by the canal
diversion would need to be made.
1.5.2 Energy Production Concepts
The development of candidate energy plans for the Bristol Bay study region
followed a systematic approach which began with the identification of a
fairly large number of ideas or concepts. These concepts were then
screened and reduced to a manageable number of scenarios for eventual
comparison and evaluation. The details of the program to develop candidate
energy plans are presented in Chapter 6 of this report. A summary follows
of the methodology employed.
1. 5.2.1 Identification
The basic factors used in identifying energy concepts that might be
applicable to the Bristol Bay region included the following:
1-12
• •
•
• -
• -
•
•
• .. .. -• -
• ..
-
-• -• ..
.. -..
•
•
••
• Energy demand forecasts
• Applicable energy supply technology
• Experience in designing electrical supply systems
• Community attitudes
• Institutional restraints
The initial step was to identify all potentially practical electrical
generating concepts applicable to the Bristol Bay region. The first part
of this step involved a preliminary evaluation of previously identified
hydroelectric sites in Bristol Bay to identify those sites considered
suitable for inclusion in the concepts. Thirty-six hydro sites were
evaluated with r"espect to environmental, socioeconomic, technical, and
economic feasibility. Eight of these sites were initially selected as
being "promising". Comments were solicited from a wide group of state and
federal agencies during the hydro site screening and selection process.
Following this, 48 potential energy supply systems were identified
utilizing the eight selected hydro sites and other applicable energy supply
technologies discussed in Section 1.4. The 48 systems represented numerous
combinations of the basic energy system components. Finally, a matrix was
developed to identify reasonable applications of each supply system for
either the whole Bristol Bay region or one or more subregions. The matrix
revealed more than 100 concepts which were considered suitable for further
evaluation.
1.5.2.2 Screening
The next step required reducing the more than 100 concepts to a manageable
number for further evaluation. Engineering judgement, supplemented by the
subjective consideration of environmental factors, was employed to reduce
the number of concepts to approximately 18. At this point a meeting was
held in Anchorage on November 17, 1981 for the benefit of State and Federal
agencies that had expressed interest in the screening process and
identification of alternatives. At the meeting, the approach to power
system alternatives evaluation was described by the project team, and the
process leading to the identification of the concepts was presented. The
1-13
•
basic characteristics of the concepts, called "primary scenarios" were •
described. As a result of this meeting and from further evaluations of new •
data, a slate of 20 primary scenarios was selected for further evaluation •
and comparison with the Base Plan and Alternative Plan A scenarios. _
Conceptual engineering and economic analyses of the selected scenarios
proceeded to a point where quantitative comparisons could be made. With
the exception of Tazimina and Newhalen, environmental assessments were
generally of a preliminary and qualitative nature. The approach taken was
that it would be most cost effective to initially eliminate concepts on an
engineering or economic basis. Subsequently detailed environmental
analyses would be performed on the remaining most promising scenarios.
However, during thfs evaluation process, the development of the King Salmon
River hydroelectric potential was determined infeasible due to
environmental factors. Accordingly, no cost evaluation was made of
concepts which involved this site. Similarly, local opposition to
development of Kukaklek Lake was voiced. Since development of this concept
had proceeded further, it was decided to continue cost evaluation for
comparative purposes.
•
• --..
• -• •
II
•
In the draft Interim Feasibility Assessment report issued in March 1982, 18 •
primary scenarios were presented as being applicable to Alternative Plan -
B. Subsequent to the draft report, another alternative scenario (B-19) was
added which evaluated a number of subregional concepts consisting of cost
effective mixes of diesel, wind, waste heat recovery and small hydro. This
total of 19 Alternative B scenarios represented many more alternatives than
had been expected when the study began. However, because the Power
Authority, governmental agencies, and the project team all agreed that a
thorough examination of alternatives should be completed before the second
phase of the power plan study went forward, all 19 Alternative B scenarios
are retained in the Interim Feasibility Assessment. Further, as the
economic studies progressed, several variations and combinations of energy
sources were studied as sub-scenarios. This resulted in adding nine more
energy plans to the overall study effort, as Alternative Plan B scenarios.
Considering the Base Plan, Alternative Plan A, and the primary and
sub-scenarios under Alternative Plan B, a total of 30 energy plans were
eventually evaluated.
1-14
• -
• ..
• ..
• •
• -.. -.. ..
• ..
,0"
1.5.3 Selected Energy Scenarios
The 30 energy scenarios selected for evaluation and comparison represent a
variety of electrical generating systems combined in a number of ways.
Basically, the energy scenarios are grouped according to the three main
hypothetical cases previously described. This summary gives only an
overview of the make-up of the scenarios. Reference should be made to
Chapter 6 and Appendix A for detailed descriptions of the individual
elements of the scenarios.
Scenario BP-l, the Base Plan, assumes the continued use of diesel systems
currently in place with the addition of central diesel generation systems
at individual villages as required in the future, but without: any waste
heat recovery units. No new transmission interties are assumed.
Scenario A-I, Alternative Plan A, assumes a 16 MW development at Tazimina
to meet regional needs within the study area. To supply this electrical
capacity, a 65-ft rockfill storage dam would be constructed on the Tazimina
River about 4 miles downstream of the outlet from Lower Tazimina Lake. The
water surface in Lower Tazimina Lake would be raised about 35 ft above its
present level. Main transmission lines would be run to larger population
areas with feeder lines to all villages.
The Alternative Plan B scenarios consider 19 other potential electrical
generating systems with nine variations to some of these scenarios, for a
total of 28. Several of the concepts envision a completely intertied
transmission system similar to Alternative A. However, the majority of the
systems are subregional. Special emphasis was given to the consideration
of subregional systems because some Bristol Bay residents believe that such
systems might be more compatible with regional attitudes and values.
The elements of the Alternative B systems include seven potential hydro
developments and several non-hydro sources. Non-hydro sources, consisting
of the technologies identified in the energy supply technology evaluation,
include fossil systems, diesel systems on an intertied regional and
subregional basis, outside electrical energy generation brought to the
1-15
region by a transmission
diesel systems. A brief
Alternative B scenarios
system, and supplemental wind energy for some
summary of the components which make up the
is provided below. The letter designation after
each component name and Table 1.5-1 show how these components have been
assembled into scenarios.
Kukaklek-Iliamna (B-2, B-5)
This is a 16 MW hydroelectric power plant located at Iliamna Lake.
Regulated flows from Kukaklek Lake, the headwater reservoir, are used for
generation. A transmission line grid would interconnect all study
communi ties located west and south of Kukaklek Lake.
Newhalen River (B-2, B-3, B-4, B-7, B-11, B-12, B-13, B-14)
Three hydroelectric concepts were considered for the Newhalen River. Two
are for regional power development and one is for local power needs. All
are run-of-river partial diversion plans. The regional concepts use a
2.5-mile long diversion canal coupled with a 16 MW power plant
installation. One of the diversion canal concepts allows for bypassing
high river flows around a section of the Newhalen River which has severe
rapids. The flow bypass would reduce river velocities during periods of
high flow for upstream migrant fish. The other diversion canal concept
allows for diverting water needed only for power generation.
The local concept is a low flow diversion scheme. This uses a
channel-tunnel waterway system to bypass a portion of the flow around a
small section of the Newhalen River. The bypassed flow is used in
generating energy in a 1.2 MW plant.
Either regional project would
transmission line grid. The
Newhalen, and Nondalton.
serve all study area communities through a
local project would serve only Iliamna,
1-16
..
• ..
• ..
• ...
..,
• -• --
• ..
• • ---..
., -• •
•
• -
• .,
• .. .. ...
Kukaklek Lake (B-3, B-4, B-6)
This is a 7 MW capacity local hydroelectric power project using regulated
flows from Kukaklek Lake. The plant would be located at the shore of a
group of unnamed lakes found northwest of Kukaklek Lake. Power from this
project would serve only the Kvichak River communities, not including
Iliamna-Newhalen-Nondalton. The concept of utilizing Kukaklek Lake for
providing power to the communities of Igiugig and Levelock only was not
developed.
Chikuminuk Lake (B-3, B-4, B-S, B-6, B-7, B-8, B-13)
Two hydroelectric concepts to develop Chikuminuk Lake were considered.
Both require regulation of Allen River flows, near the outlet of Chikuminuk
Lake. The regional concept would dam the lake outlet, raising the present
lake by some 21 feet. This requires the construction of a 100-ft high dam
about one mile downstream of the lake outlet. Regulated flows would be
conveyed to a power plant through a tunnel to generate 16 MW of peak
capacity. The local concept would have a capacity of 8 MW and only raise
the lake by 4 feet.
The regional project would serve the region through a transmission line
grid, except for the communities of Iliamna-Newhalen-Nondalton. The local
project would serve only those communities located with the Nushagak River
basin, including Manokotak.
King Salmon (B-4, B-6, B-7)
The development of the King Salmon River would require the construction of
a dam across the river within the boundaries of the Becharof National
Wildlife Refuge. Concepts utilizing the hydroelectric potential of the
King Salmon site were not developed due to potential environmental impacts.
Tazimina River (Local) (B-S, B-6, B-8, B-13, B-18, and B-19)
Three hydroelectric power concepts were considered for Tazimina on a less
than regional basis. A concept producing 8 MW to serve only the
1-17
communities in the Kvichak River area (B-8) would require a 30-ft high •
regulating dam which would raise the Lower Tazimina Lake by 5 feet. -
Two run-of-river concepts were also considered. One concept would use a
16 MW installation on a regional basis, but without a regulating dam
(B-18A). The other run-of-river concept would use a small 1.2 MW
installation to serve the Iliamna-Newhalen-Nondalton communities only (B-5,
B-6, B-13A, and B-19E).
Transmission line grids would be constructed, as required, by each type of
development.
Kontrashibuna (B-18)
This hydroelectric development involves a regulating dam on the Tanalian
River with an installed capacity of 16 MW. The project requires a 90-ft
high dam to raise the Kontrashibuna Lake by about 65 feet. Power from the
project would serve the entire study region through a transmission line
grid. Scenario B-18A combines Kontrashibuna with a 16 MW run-of-river
Tazimina development, while B-18B is a regional Kontrashibuna development.
Outside Source, Beluga Area (B-1)
This concept considers the construction of a 138 kV transmission line from
the Beluga area to the study region. A transmission grid would be used to
serve the communities of the study area. The generation source has not
been identified.
Fossil Fuel-Fired Plant at Dillingham or Naknek (B-9, B-10, B-11, B-12)
Under this concept, a 16 MW fossil fuel-fired steam electric power plant
would be developed at either Dillingham or Naknek, but not both. The plant
would supply power to the study area through a transmission line grid.
Three types of plants were considered for Scenario B-9: B-9A, a
conventional coal-fired steam electric plant; B-9B, an oil-fired combined
cycle plant; and B-9C, a coal gasification combined cycle plant. The
1-18
.. -.. .. ..
..
•
•
• -
• •
• •
• ..
• ---
• ..
• -• • .. ..
• ..
• ..
latter system would utilize gas turbines, a waste heat recovery boiler, and
a conventional steam electric generating plant.
Diesel Power (B-15, B-16, B-17)
In addition to the Base Plan, the continuation of diesel power was
considered in several alternative scenarios. These scenarios considered
central diesel installations capable of serving all communities within the
study region by using clustered central installations serving a small
number of communities, or groups of communities. Diesel installed capacity
varied, depending on the power needs and the scenario. Transmiss ion line
grids were developed, as needed, for each specific scenario.
Waste Heat, Wind, and Organic Rankine Cycle ( B-15, B-16, B-17, B-19)
Waste heat recovery (B-19A, B-19C, B-19E), wind generation (B-19B, B-19C,
B-19E), and the organic Rankine cycle (B-19D) were evaluated for use with
the scenarios which utilize diesel generation.
was considered only for the Dillingham and
The organic Rankine cyc le
Naknek communities. Wind
generation was included in the scenarios only for specific communities or
regions where wind sources are considered most reliable. Detailed
information on wind energy potential is found in Appendices A.6 and D.
All of the Alternative B scenarios selected for evaluation were retained
throughout Phase I to better document the extensive effort given to the
consideration of alternatives. As the Phase I work proceeded, several of
the potential hydro sites became less attractive due to institutional or
environmental concerns. However, these sites were not eliminated from the
evaluation in order to present a basis for comparison with the more
attractive sites.
1-19
Table 1.5-1
SUMMARY OF ALTERNATIVE B SCENARIOS
Hydro Developments
Scenario
6-1*
6-2
6-3
6-4
6-5
6-6
6-7
6-8
6-9.<\*
6-96*
6-9C*
6-10*
6-11
6-12
6-13A
6-136
6-1 IlA*
6-146*
6-15
6-16
6-17*
6-18A*
6-186*
6-19A
6-198
6-19C
B-19D
B-19E
Kuka k I ek-
II iamna
x
x
Newhalen
River
x
X
X
X
X
X
X
X
X
Kuka k I ek
Lake
X
X
X
*Completely intertied transmission system
Chikuminuk King
Lake Salmon
X
X
X
X
X
X
X
X
X
X
X
Tazimina
X
X
X
X
X
X
Kont ra sh-
ibuna
X
X
Non-Hydro Sources
Outside Source Beluga Area
Fossi I-Di I I Ingham (Convential Coal)
Fossi I-Di I I Ingham (Combined Cycle)
Fossi I-Di I I ingham (Coal
Gasification, Combined Cycle)
Foss ii-Naknek
Fossi I-Di II inghan
Fossi I-Naknek
Diesel - 4 subregions
Diesel -3 subregions
Diesel -AI I Connected
Diesel -Local Waste Heat
Diesel -Local Wind
Diesel -Local Wind and
Waste Heat
Diesel -Local Organic Rankine Cycle
Diesel -Local Waste Heat and/or
Wind
1. 6 EVALUATION OF SELECTED ENERGY PLANS
The energy plan scenarios described in the previous section were compared
and evaluated with respect to a variety of technical, environmental, and
economic indicators specified in the Alaska Power Authority requirements
for feasibility studies (3AAC94. 060). Several were removed from further
consideration due to environmental factors (B-4, B-6, and B-7), or because
of similar economic characteristics (B-10 and B-12). The result was a
slate of 25 scenarios selected for final comparison.
1.6.1 Technical
Technical indicators used in the evaluation were:
• Safety
• Reliability
• Availability
• Constructability
Constructibility, although not specified in the regulations, was added to
further define technical differences between scenarios. In addition, each
indicator was considered with repect to both energy production facilities
and transmission lines.
Section 7.2 presents details of the evaluation of various energy plan
scenario electrical supply components with respect to technical
indicators. The evaluation of indicators was qualitative, and no attempt
was made to rank scenarios. However, certain energy supply components have
lower ratings than others from the standpoint of technical indicators as
shown on the next page.
1-20
Supply Component
Diesel
Hydro
Wind
Fossil
Transmission
Lower Rating
Reliability
Constructibility
Reliability and Availability
Commercial Development (coal gasification
combined cycle only)
Safety and Constructibility
In general, all scenarios considered in the evaluation were found to be
acceptable with respect to all of the above technical indicators. Those
preliminary concepts which would have been technically unacceptable for
Bristol Bay, or which represent a non-commercial technology, were screened
out prior to selection of the final 25 scenarios. Accordingly, technical
indicators are not a significant factor in comparing the selected scenarios
during Phase I. Further technical comparisons of the most promising
scenarios will be made in Phase II. Special attention will be given to
protection against ice problems for hydroelectric projects, particularly
for run-of-river plants.
1.6.2 Environmental
The environmental evaluation of the selected energy plan scenarios
addresses the ten evaluation indicators specified by the feasibility study
requirements. These indicators are:
• Community preferences
•
•
•
•
•
•
•
Impact on community infrastructure
Timing in relation to other capital projects
Air quality
Water quality
Fish and wildlife impact
Land use impact and ownership status
Terrestrial impact
• Recreational resource value
• Visual impact
1-21
• .. .. -
• -
•
• .. -.. .. ..
., ...
• ..
• •
• .. .. -.. ..
• ---.. --•
•
• ..
Environmental concerns most often associated with power project development
by residents of the Bristol Bay region were:
• Effect on commercial and sport fishing
• Effect on established subsistence practices
• In-migration of people resulting from project construction or
subsequent industrial development
• Easier access to subsistence areas as a result of project road
construction
Details of the environmental evaluation are presented in Section 7.3, which
draws upon Appendix G, the Environmental Report.
An evaluation matrix, which is provided in tabular
subjectively rates each scenario with respect to
form in Section 7.3,
the indicators listed
above. The subjective evaluation criteria used to evaluate environmental
indicators were:
A = Small impact
B = Moderate impact, but believed acceptable with mitigation measures
C = Major impact, possible resulting in a "fatal flaw"
The scenarios
preference due
were not numerically
to the difficulty in
ranked according to environmental
integrating the highly subjective
indicators considered. However, the scenarios were grouped using the same
evaluation criteria used for the indicators; scenarios were not ranked
within a group.
1-22
The following tabulation shows the environmental evaluation of the •
scenarios by group:
GrouE A GrouE B GrouE C
Scenario BP-1 Scenario A-1 Scenario B-1
Scenario B-15 Scenario B-8 Scenario B-2
Scenario B-16 Scenario B-9A Scenario B-3
Scenario B-17 Scenario B-9B Scenario B-4
Scenario B-19A Scenario B-9C Scenario B-5
Scenario B-19B Scenario B-10 Scenario B-6
Scenario B-19C Scenario B-ll Scenario B-7
Scenario B-19D Scenario B-12
Scenario B-13A
Scenario B-13B
Scenario B-14A
Scenario B-14B
Scenario B-18A
Scenario B-19B
Scenario B-19E
Refer to Table 1.5-1 or 1.6-3 for scenario descriptions.
Upon applying the above ten environmental indicators to the scenarios, the
following was found:
•
•
The Group A scenarios, involving diesel-electric generation, exhibit
relatively small environmental and sociocultural impacts.
The hydroelectric scenarios in Group C, which include the Kukaklek
• -
• -
• ..
•
•
• ..
• -
•
•
• ..
• ...
• ...
• ...
•
and/or King Salmon concepts and generation from an outside source -
•
•
(Beluga), exhibit major environmental and sociocultural impacts.
Other hydroelectric concepts exhibit moderate environmental and
sociocultural impacts.
The coal-fired, steam electric scenarios exhibit moderate
environmental and sociocultural impacts.
1-23
-..
-
•
•
The Tazimina (A-I) and Newhalen (B-14A and B-14B) regional hydroelectric
concepts, are of special environmental interest because they are also
attractive from a technical and economic basis. These, unlike other Group
B hydroelectric concepts, do not require the combination of smaller
developments to meet the entire study region's needs.
The development of the Tazimina River regional hydroelectric concept would
create a storage reservoir behind a dam below the outlet of Lower Tazimina
Lake. The following would result from reservoir construction and operation:
• The reservoir would inundate up to 4,100 acres of land around Lower
Tazimina Lake
• Animal habitat would be displaced by creation of the reservoir
• Lake surface area would nearly double when the reservoir is full,
suggesting increased carrying capacity for lake dwelling species
• Water level fluctuation could adversely affect permanent
establishment of shoreline habitats
• Resident and anadromous fish habitat in the Tazimina River below the
falls may be affected positively or negatively from changes in river
flows and temperatures
Other effects from project development would include:
• Access to the river for sport fishermen due to the construction of an
access road
• Changes in nearby community infrastructure during construction
For Tazimina, the major concern is that changes in stream flows downstream
of the project could adversely affect sockeye salmon spawning. Because the
falls are impassable to upstream fish migration, no salmon spawning occurs
in the Tazimina Lakes, or the upper Tazimina River, above the falls.
1-24
•
Cons iderable study regarding the nature of the aquatic habitat in the _
Tazimina River is reported in Appendix G. This information, combined with
future instream flow studies, would be used to develop necessary mitigation
-
•
plans for project design and operation. Flow control or augmentation would _
be considered for potential benefits to spawning areas.
The Newhalen River regional hydroelectric concept would divert water from
the Newhalen River at River Mile 7 into a canal leading to a hydroelectric
plant. Diverted flow would be returned to the river at River Mile 1, just
below the first set of rapids. The following changes would result from
development of this facility:
•
•
Flow reduction in the Newhalen River between the intake and discharge
of the hydroelectric plant. Two concepts were evaluated:
(a) flow diversions averaging about 1000 cfs for power generation
only, or
(b) large flow diversions for the purpose of both power generation
and by-passing high Newhalen River flows to aid upstream salmon
migration.
Elimination of approximately 150 acres of high brush ecosystem at the
location of the canal and ancillary road
• Possible minor displacement of some brown and grizzly bear population
• Changes in nearby community infrastructure
Since no regulating dam would be constructed on the Newhalen River, natural
river flows would not be changed except between the intake and discharge of
the plant. The most important fisheries concern would be to avoid
unacceptable hazards to migrants as they pass the plant site. Two
important requirements would be to: 1) insure adequate flow over the
rapids for upstream fish passage and for resident fish, and 2) avoid
unacceptable hazards at the plant intake for smolt and fry during
downstream migration.
1-25
• .. ..
.,
• -
• ..
• •
• •
• ..
•
•
• -
• ------
-
The first requirement is easily accommodated by allowing sufficient flow to
bypass the plant intake at all times. The second might require the
installation of a fish diversion or screening system to exclude small fish
from the plant intake during downstream migration.
A major environmental benefit might be realized as a result of the Newhalen
River development concept. It has been reported that extreme flows over
the rapids in the lower Newhalen River have caused a blockage at the
river's mouth to upstream fish passage, a problem which on infrequent
occasions has caused extensive mortality in mature adult sockeye salmon as
they move in early summer to freshwater spawning areas in the Newhalen
River-Lake Clark system. The concept mentioned above which could provide
controlled bypass of water around the rapids by means of the large power
intake canal would reduce excessive flows over the rapids, thereby
improving conditions for upstream fish migration.
1.6.3 Economic
A common basis was used to compare and evaluate power supply scenarios in
accordance with Power Authority guidelines. A calculation of the present
worth of all costs and benefits associated with each scenario was the basis
for economic comparisons. The economic parameters and assumptions used in
the calculations were the same for all scenarios evaluated in this study.
Thus, the scenarios can be compared with each other and ranked in terms of
their ability to supply power to the Bristol Bay region at the lowest cost
by comparing present worth cost; the lowest present worth represents the
least costly alternative. Further details on the economic evaluation are
presented in Chapter 7.
The major steps involved in determining present worth values for each
scenario included the following:
Develop conceptual designs for all systems and equipment included in the
scenario
Determine the installed cost, annual operating and maintenance costs,
fuel costs, etc., for all equipment
1-26
Develop the total annual cost (minus any benefits) for each year of the
economic analysis period
Evaluate the present worth of the annual costs
Since detailed designs were not performed for this initial study phase, the
cost estimates are order-of-magnitude prices (± 20 to 25 percent) which
were developed from conceptual designs. The costs for major equipment
items were obtained from vendors, when possible, or from published
material. Additional allowances were made for freight from the factory to
the jobsite. Other cost factors, including those special factors related
to construction costs in Alaska, were determined with the assistance of
Green Construction Company of Anchorage. Finally, allowances were made for
system engineering and design, construction management and on allowance of
about 15% for indeterminants. Interest during construction was also
included.
The economic parameters and assumptions used in calculating present worths
were in conformance with Power Authority guidelines, except for the
economic lifetimes of certain items of equipment. Summaries of the
economic parameters and equipment lifetimes are shown in Tables 1.6-1 and
1.6-2, respectively. In the cases involving diesel generators,
transmission lines, coal gasification, and waste heat recovery equipment,
the economic lifetimes shown in Table 1.6-2 are greater than the values in
the Power Authority's guidelines. These economic lifetime values were
reviewed by the Power Authority, and were considered acceptable for use in
the study.
The base year for the economic analysis was 1982, with a 2l-year planning
period (i. e., Bristol Bay electric demand projections for 1982 through
2002) and a 56-year analysis period. The analysis period resulted from the
assumed installation of hydroelectric plants in 1988 which, when combined
with a 50-year hydroelectric lifetime, extended the analysis period from
the base year of 1982 through the year 2037.
The costs occurring in the years following the planning period from 2003
through 2037 were assigned, as required, by the Power Authority economic
1-27
•
•
•
• -
• -
•
., ..
• -
• ..
• •
• •
• •
•
• -
• -•
.,
• ..
•
-
guidelines. It was assumed that no further load growth or petroleum fuel
cost escalation occurred after 2002. Thus, the costs occurring in 2002
were repeated for each following year to 2037, and the present worth was
calculated based on this cash flow. For those diesel systems which include
waste heat recovery equipment, a benefit was assigned each year for the
waste heat recovered. Calculations were performed to determine the
fraction of the recoverable waste heat that could be used for space
heating. A credit was applied each year for the space heating supplied,
assuming that diesel was the fuel normally burned in homes for space heat.
Lastly, the costs developed in this study represent busbar costs and do not
include costs such as distribution within the villages, administration,
taxes, insurance, depreciation, etc.. The present worth of consumer costs
would be significantly higher.
Table 1.6-3 is a summary of present worth costs for the Bristol Bay
regional power scenarios. It is apparent that a wide variation in costs
results from the several power supply options that were considered.
Overall, the hydroelectric scenarios generally had lower present worth
costs than other power supply technology options. The Newhalen regional
power only concept (B-14A) was lowest, followed by the Tazimina regional
concept (A-I) and the Newhalen regional power and river diversion concept
(B-14B). The regional Kontrashibuna (B-18B) and a plan consisting of a
smaller development of Tazimina combined with local diesel energy
suplemented with waste heat and wind generation were the next most
cost-effective options. By comparison, the Base Plan (BP-l) ranks number
20.
Additional special studies were undertaken to: 1) investigate the economic
benefits of supplemental wind systems and waste heat recovery for diesel
scenarios; 2) determine the most economic local hydro development for
specific subregions; and 3) evaluate the viability of the organic Rankine
cycle for Naknek or Dillingham. In general, the addition of waste heat and
wind to the diesel scenarios
fifth ranking scenario B-19E.
Chapter 7.
results in cost savings as evidenced in the
The results of these studies are reported in
1-28
TABLE 1.6-1
SUMMARY OF ECONOMIC ANALYSIS PARAMETERS
Base Year 1982
Planning Period
Economic Analysis Period
Inflation Rate
21 years, 1982 -2002
56 years,1982 -2037
0% (all costs expressed in 1982
dollars)
Real Discount Rate 3%
Real Petroleum Fuel Escalation Rate 2.6%
Interest Rate 3%
TABLE 1.6-2
ECONOMIC LIFETIMES FOR MAJOR EQUIPMENT
Equipment Item
Diesel Generators
Electric Transmission Lines
Waste Heat Recovery Equipment
Wind Generators
Organic Rankine Cycle Systems
Hydroelectric Plants
Steam Turbines
Combined Cycle Plants
Coal Gasification Equipment
Lifetime, Years
30
30
15
15
25
50
30
30
30
TABLE 1. 6-3
SUMMARY OF PRESENT WORTH COSTS
All Values in 1982 Dollars
Scenario Description
Present Worth,
($1,000) Ranking
Base Plan (BP-1)
Alternative A (A-1)
Alternative B-1
Alternative B-2
Alternative B-3
Alternative B-5
Alternative B-8
Alternative B-9A
Alternative B-9B
Alternative B-9C
Alternative B-11
Alternative B-13A
Alternative B-13B
Alternative B-14
Alternative B-14B
Alternative B-15
Alternative B-16
Alternative B-17
Alternative B-18A
Alternative B-18B
Alternative B-19A
Alternative B-19B
Alternative B-19C
Alternative B-19D
Alternative B-19E
Diesel Only
Tazimina Regional
Beluga Transmission
Newhalen and Large Kukaklek
Newhalen and Medium Kukaklek
Tazimina Run-of-River, Medium
Chikuminuk and
Medium Kukaklek
Medium Chikuminuk and
Medium Tazimina
16 MW Coal-Fired
16 MW Oil-Fired
16 MW Coal Gasification
Coal-fired at Dillingham
and Newhalen
Large Chikuminuk
and Tazimina Run-of-River
Large Chikuminuk and local
Newhalen
Newhalen Regional -Power Only
Newhalen Regional Power and
River Diversion
Diesel Clusters
Diesel Clusters and Transmission
Diesel Regional Transmission
Interconnected
Tazimina Run-of-River
and Kontrashibuna
Kontrashibuna
Diesel Local and Waste Heat
Diesel Local and Wind
Diesel Local -Waste Heat
and Wind
Diesel Local and Organic Cycle
Tazimina Local, Diesel Local,
Waste Heat + Wind
291,700
213,700
279,600
301,000
276,300
270,700
266,000
281,000
388,500
269,300
281,300
261,500
267,100
189,900
222,200
340,400
338,900
367,900
270,200
226,800
249,500
287,900
249,200
283,900
242,500
1. No cost evaluations were made for scenarios B-4, B-6, and B-7, which
included the development of King Salmon.
2. Alternative B-10, a coal-fired plant at Naknek, has the same present
worth as B-9A.
20
2
15
21
14
13
9
16
25
11
17
8
10
1
3
23
22
24
12
4
7
19
6
18
5
3. Alternative B-12, a coal-fired plant at Naknek with a subregional
Newhalen hydroelectric development, has the same present worth as B-11.
1.7 REGULATORY COORDINATION AND PUBLIC PARTICIPATION
A program of regulatory coordination and public participation was
undertaken with the following objectives:
• to ensure the adequate and timely involvement of Federal, State, and
local governmental agencies interested in the study
• to identify regulatory requirements for the licensing of proposed
power plans
• to keep the public fully informed and to provide a means whereby the
public can influence the work effort
A chronological list of significant meetings, communications, and other
events is included in Chapter 8 of this report.
1.7.1 Agency Communication
With respect to the first objective, several formal meetings were held in
Anchorage between August 19, 1981 and June 15, 1982, to explain work
objectives and progress to interested governmental agencies. These
meetings appeared to be beneficial to agency personnel in obtaining a
better understanding of the proj ect; without question these meetings were
beneficial to the project team. At some meetings, packets of preliminary
information were handed out for review and comment. In addition to
progress reporting,
the project team
items discussed included the approach being taken by
to select alternative energy sources and sites,
environmental concerns of various agencies with respect to specific plan
proposals, and possible ways to cooperate and exchange information between
the project and· various agencies who are interested in resource
development. Interested personnel in a number of agencies were routinely
sent copies of the Project
fisheries related agencies
Report.
on the
Special meetings were held with
more promising hydro developments,
particularly Tazimina and Newhalen concepts. Comments received from ·these
communication exchanges were considered during the development and
evaluation of power plan alternatives.
1-29
1.7.2 Regulatory Reguirements
The range of laws and regulations considered during the Interim Feasibility
Assessment was broad because of the large number of alternatives
evaluated. Some of the important regulatory issues considered during Phase
I included land status, land ownership, agency management responsibility
within designated parks and preserves, and provisions of the Alaska Native
Claims Settlement Act and the Alaska National Interest Lands Conservation
Act. Transmission line routing, with respect to land status, was another
important consideration. Because the requirements of the National
Environmental Policy Act would be brought into effect if a proposed project
required federal licensing, much data was collected which was used to
compare alternatives from the regulatory and environmental standpoint.
These data also will be useful in further evaluation of licensing
requirements for the most promising alternative(s) in Phase II.
1.7.3 Public Participation
Public participation, particularly involving the residents of the Bristol
Bay region, was recognized early by the proj ect as a key element of the
study. The Power Authority and the project team have gone on record with a
commitment to determine, and be guided by, local attitudes with respect to
development of electrical power in the region. The inherent difficulty in
any public participation program is the problem of sorting out the wide
range of interests and expectations; the Bristol Bay public participation
program was no exception.
Several steps were taken during the Interim Feasibility Assessment to
provide a chance for Bristol Bay residents to learn about the study. An
initial step was a series of village meetings in September and October
1981, when practically every village in the region was visited by the
Project team to explain the purpose of the power plan study and to request
comments on matters of interest or concern. The many comments and
suggestions received either during the meetings or sent later by mail on
special forms were compiled and considered. In some cases, these comments
resulted in significant changes in plan concepts. Also, community meetings
1-30
...
..
..
.,
.. ..
• ..
• -• .,
• ..
• ..
• -
• ..
• ---.. .. .. -., .. .. ..
were repeated in March 1982 to present the results of the Interim
Feasibility Assessment.
Other steps taken to enhance communication with Bristol Bay residents-
included the distribution of project reports to community leaders, radio
and press releases on the study, and numerous informal meetings and
discussions with local residents as project team members collected
necessary field data. Although the special communications and
transportation in the Bristol Bay region are less than ideal for maximum
public participation, it is believed that a credible effort has been made
to recognize local concerns.
The fundamental community issue appears to be concern about conflict
between accelerated energy resource development and the existing lifestyle
in the Bristol Bay region. Most residents welcome less costly and more
abundant sources of electrical power, if their current lifestyle is not
adversely affected. The most commonly expressed concern relates to the
effect of power projects on the fisheries, both from the commercial and
subsistence standpoint. Decreases in game, increased access to remote
areas, and influx of outsiders are also seen as possible harmful effects.
However, attitudes differ throughout the region regarding perceived
benefits and costs of more energy. These differences from a regional
standpoint may represent unresolvable conflicts. However, understanding
them may permit elements of the study to be tailored somewhat to local
preferences.
More information on the public participation program is presented in
Section 8.2.
1. 8 CONCLUSIONS AND RECOMMENDATIONS
1.8.1 Conclusions
The general conclusion of the Interim Feasibility Assessment is that there
are a number of promising alternatives to the current use of diesel
electric generation in the Bristol Bay region. This conclusion is based on
1-31
-..
an analys is of the technical, environmental, and economic characteristics •
of 25 power development scenarios. These scenarios utilize a variety of -
commercially available power generation systems considered technically
suitable for use in the Bristol Bay region during the planning period from
1982 to 2002.
The economic evaluation in Section 1.6.3 (Table 1.6-3) shows a significant
variation between the scenarios on a present worth basis. The four least
costly alternatives are regional hydroelectric developments: 1) on the
--.. -
• -
Newhalen River (B-14A), 2) on the Tazimina River (A-I), and 3) on the -
Newhalen River (B-14B), and 4) on the Tanalian River near Kontrashibuna ..
Lake (B-18A). The next alternative in order of economic preference is the ..
development of subregional diesel systems, including utilization of waste _
heat recovery and wind supplemental energy, coupled with the development of
a local Tazimina River hydroelectric project (B-19E).
A comparison of the top five scenarios and the Base Plan by present worth
ratios shows the following economic ranking:
Present Worth
Economic Descri]2tion Scenario No. Ratio
Rank
1 Newhalen Regional -Power Only B-14A 1.54
2 Tazimina Regional A-I 1. 36
3 Newhalen Regional -Power and
River Diversion B-14B 1. 31
4 Kontrashibuna Regional B-18B 1.29
5 Local Diesel, Waste Heat, wind,
and Local Taziminina B-19E 1.20
20 Base Plan (Continued Diesel) BP-l 1.00 (Base)
Refering again to Table 1.6-3, there are several other scenarios within a
relatively close grouping which show lower costs than the Base Plan. Many
of these employ disconnected subregional systems. Also, it should be noted
that three scenarios in this grouping, utilizing coal in centralized power
plants, are also slightly less costly than the Base Plan.
1-32
• ..
• ..
• ..
• ..
• -.. ..
• -
• .. --.. -
• ..
• -
With respect to environmental considerations, the ranking is different than
for economics. Continued electrical generation by diesel systems was
judged to result in the least environmental effect to the Bristol Bay
region. The four other most attractive alternatives on a present worth
economic basis all fall within the intermediate environmental category
(Group B), having moderate impacts that are believed to be acceptable with
mitigation measures.
In making choices between power plan candidates on the basis of the data
available at the Interim Feasibility Assessment, a third. factor must be
considered: the level of confidence in the information, or assumptions
used in the evaluation, of individual scenarios. Although an effort was
made to evaluate all scenarios on a consistent level, considerable
differences exist in the quality and quantity of data available.
Considering the top five candidates from the economic evaluation, the best
data on which to make an evaluation is available for the Tazimina and
Newhalen scenarios, due to collection of considerable detailed physical and
environmental data. For Kontrashibuna, because it is a more remote site,
there is a lack of specific data about its environmental setting, and there
are questions concerning the compatible use between the Lake Clark National
Park and Preserve and the site for power generation. These factors combine
to reduce the level of confidence in the assumptions used in the
development of the Kontrashibuna concept. For the local diesel, waste
heat, wind, and local Tazimina scenario (B-19E) the assumptions relative to
the practical levels of wind and waste heat utilization may be questioned.
Confidence in the diesel and hydroelectric components, however, is high.
Considering the above factors, the following conclusions were reached with
respect to the top five candidates:
Technical -
Economic -
All are feasible.
All present attractive
Plan, the continuation
practices.
1-33
cost advantages over the Base
of present diesel generation
Environmental -Subregional diesel power in combination with wind, waste
heat, and the run-of-river Tazimina has the least impact
.. .. .. -
on the Bristol Bay region; the other four candidates, _
Confidence
although exhibiting varying potential environmental
effects, are believed to be acceptable with mitigation.
Confidence is highest for the sub-regional diesel/waste-
heat/wind/Local Tazimina concept, reasonably high for the
Newhalen concepts, and lower for the Tazimina and
Kontrashibuna regional plans.
---.. .. ..
•
These above conclusions lead to the following subjective order of ..
candidates with respect to economic, environmental, and confidence factors:
Economic
Newhalen
(Power Only)
Tazimina
(Regional)
Newhalen
(Power and
River Diversion)
Konstrashibuna
(Regional)
Subregional Diesel
w/waste heat/
wind/Local
Tazimina
Environmental
Subregion Diesel w/waste
heat/wind/Local Tazimina
Newhalen
(Power and River Diversion)
Newhalen
(Power Only)
Tazimina
(Regional)
Kontrashibuna
(Regional)
Confidence
Subregion Diesel w/waste
heat/wind/Local Tazimina
Newhalen
(Power Only)
Newhalen
(Power and
River Diversion)
Tazimina
(Regional)
Kontrashibuna
(Regional)
The intent is not to imply equal weight to the three evaluation factors or
suggest that the ranking is linear from top to bottom of the list.
1-34
... ..
•
• • .. ..
• .. .. .. .. .. .. ... .. -.. -..
.. --...
Furthermore, the ranking of environmental and confidence factors is highly
subjective.
Thus, based on a subjective evaluation of the above lists, it is concluded
that the ranking of alternatives for a completely intertied regional power
plan is in the same order as shown above in the economic listing. However,
since local preferences may favor subregional developments, we suggest
further consideration should be given to the subregional diesel/waste heat/
wind/Local Tazimina Scenario (B-19E).
With respect to regional hydroelectric power developments, it may be
technically and economically feasible to develop some of these projects for
higher capacity and energy. Such projects might be increased in size to
provide electrical energy requirements of not only the Bristol Bay region,
but adjacent areas such as Bethel and Togiak. The merits of such
developments could be considered for study under the Phase II efforts, if
the Power Authority so desires.
1.8.2 Recommendations
Based on the stated conclusions, and in consideration of presently known
factors, Stone & Webster Engineering Corporation makes the following
recommendations for Phase II efforts of the Bristol Bay Regional Power Plan:
a. Continue detailed development of the Base Plan scenario to form a base
for compar ison;
b. Continue detailed feasibility analysis of the regional Newhalen River
hydroelectric power concept (B-14A);
c. Undertake detailed feasibility analysis of the
diesel/waste heat/wind/Local Tazimina scenario (B-19E);
sub-regional
d. Through a public participation program, obtain a better understanding
of attitudes of the people of Bristol Bay regarding a regional power
plan.
1-35
The recommendation to continue studies on the Newhalen River concept stems
from the preliminary conclusion that the project is economically
attractive, technically feasible, and is likely to be environmentally
acceptable with proper mitigative measures. To this end, the following
steps are suggested for early implementation in Phase II efforts:
a. Undertake resident and anadromous fisheries studies to satisfactorily
demonstrate the environmental acceptability of the B-14A concept.
b. Continue geotechnical investigations and surveys at the proposed site
to better define site conditions revealed by initial investigations and
to obtain additional geologic data in the vicinity of the power plant.
-
-
..
-
...'
..
•
•
The following conclusions further support the recommendation to undertake •
further evaluation of the Newhalen River regional concept in Phase II: _
a. The Newhalen regional concept appears more attractive economically than
Tazimina, based on presently available data;
b. The engineering and construction uncertainties relating to this project
appear to be fewer because of its location and nature of the concept;
• ..
• ..
• -
c. There may be some significant mitigative fisheries benefits relating to •
upstream migrants that could be implemented and made part of project ..
development; and
d. Because of high Newhalen River flows during the summer, there exists
the potential for additional electrical energy development during that
period of time coinciding with fish processing energy needs.
should benefit processors within the region.
This
We recommend that a decision be made to evaluate the Newhalen concept and
the sub-regional diesel/waste heat/wind/Local Tazimina concept in Phase II,
and to perform those investigations and studies that are necessary for the
Detailed Feasibility report and, as applicable, for the preparation of a
FERC license application.
1-36
• -
• ----
• .. -..
~ ..
Based on the above recommendations, the scope of work believed necessary
for the Phase II effor~s is outlined in detail in Chapter 10 of this report.
1-37
CIJ w ::.:: < ..J
~
I o ::.::
i= I ..... "" "".r:... o "L __ "'-
o o
~
... J
KOLl~~ ..
• VILLAGES INCLUDED IN STUDY
LOCATIONS
DIESEL POW~~ ~OAJ~~E~ON
6.=HYDRO 0
&. NEWHALEN
&. TAZIMINA
&. KONTRASH I BUNA
& CHIKUMINUK
& KUKAKLEK
& KING SALMON
= COAL-FIRED
OR OTHER
(2] LINE FROM BELUGA
[!] DILLINGHAM
GJ NAKNEK
SCALE
o 10 20 30 40 MILES 50
BRISTOL BAY REGION
~
FIGURE 1.2-1-----
....
... _-,
.... ',.
-
..... -.
.....
-...
.....
2. INTRODUCTION
.....
....
"" ..
....
.....
.....
-
-...
2. INTRODUCTION
2.1 ENERGY NEEDS IN BRISTOL BAY
Energy is high among the important issues in the Bristol Bay Region today.
The following quotation from a study by the Bristol Bay Native Association
puts the subject in focus:
"The current energy problems and needs facing
Bristol Bay res idents are much different than
those issues
1960's and
confronting the
early 1970's.
region in the
Diesel-generated
electricity is no longer the 'key' to the future
deve lopment and prosperi ty of the region.
Al though electricity remains a vi tal element of
the future of the region, its mode of generation
must be re-evaluated and changed" (Ref 1).
The residents of the Bristol Bay region have been concerned with energy
problems for some time. In November 1979, a seminar was held in Dillingham
entitled "Bristol Bay: Energy Policy and Planning Looking for
Directions" . The major energy concern identified at the seminar was relief
from the high electrical and home heating costs currently facing the
village. Village representatives at the seminar felt that some type of
assistance was needed to help villagers meet the increasing costs of
electricity and home heating. Some of the suggestions to reduce energy
costs to consumers included community diesel generators, bulk fuel storage
facilities, the introduction of more energy efficient low-income housing
units, education in energy conservation, and the upgrading of existing
central community diesel systems. It was also recognized that the
development of new energy sources could increase supplies and reduce costs.
2.2 PREVIOUS STUDIES
Several studies have been undertaken in recent years to identify potential
new sources of energy for the region and to further evaluate specific
2-1
promising options (Ref 2, 3, 4). A "Reconnaissance Study" by R. W.
Retherford Associates evaluated the feasibility of
developments at Lake Elva, Grant Lake, and Tazimina Lake
hydroelectric
(Ref 3). The
study considered the attractiveness of transmission interties between
villages and the development of other new electric energy resources,
including wind energy. Based on the study assumptions, the development of
Lake Elva followed by Grant Lake was found to be economically attractive
for the Dillingham area alone when compared with continuing diesel
generation. However, Retherford found that "development of the Tazimina
potential will result in the lowest power cost for all communities in an
intertied, combined system". Retherford recommended a plan to develop the
JIll
•
-
1IIIo. .. -
•
Tazimina site, located on the Tazimina River about ten miles north of •
Iliamna Lake and east of Nondalton Village.
2.3 BRISTOL BAY REGIONAL POWER PLAN
As a result of the R. W. Retherford recommendations, the Alaska Power
Authority retained Stone & Webster Engineering Corporation (SWEC) in July
1981 to undertake a study known as the "Bristol Bay Regional Power Plan
Detailed Feasibility Analysis". The purpose of the Bristol Bay Regional
-
Power Plan study is to assess the technical, economic, and environmental ..
aspects of alternative electric power plans for the Bristol Bay region.
The study has the following general objectives:
• Minimizing market area energy costs
•
•
Minimizing adverse environmental and social impacts whi"le enhancing
environmental values to the extent possible
Maximizing the likelihood of project financing and implementation
The study area is defined as an 18-village area bordering Bristol Bay,
extending inland along the Nushagak and Kvichak drainages, and including
villages in the Iliamna Lake region. This study area was previously
determined to be the economic limit of the Tazimina Project market area.
2-2
• -
..
• ...
..
•
-
..
The villages included in the study are Aleknagik, Clarks Point, Dillingham,
Egegik, Ekuk, Ekwok, Igiugig, Iliamna, King Salmon, Koliganek, Levelock,
Manokotak, Naknek, Newhalen, New Stuyahok, Nondalton, Portage Creek, and
South Naknek.
The scope of services of the study includes resource assessment, field
surveys, and hydrologic, geotechnical, environmental, design, economic,
marketing, and financing studies necessary to assess project feasibility
and to meet any licensing and permitting requirements of the Federal Energy
Regulatory Commission (FERC) and other federal, state, or local agencies.
A specific objective of the study is to evaluate in detail the feasibility
of the previously identified Tazimina Hydroelectric Project and to compare
that project with other promising alternatives. The Bristol Bay Regional
Power Plan Detailed Feasibility Analysis is being performed in compliance
with the requirements of 3AAC 94.060.
The study effort has been divided into two phases. Phase I covers the
period from project initiation to an "Interim Feasibility
Phase II will continue with the development of the Regional
Assessment".
Power
based on the results and recommendations of the interim assessment.
report documents and summarizes the Phase I efforts.
2 . 4 STUDY APPROACH AND METHODOLOGY
Plan,
This
The approach to the Bristol Bay Regional Power Plan study is set forth in
the Work Plan proposed by SWEC and approved, with modifications, by the
Alaska Power Authority (Ref 5). The Work Plan divides the work into the
following tasks to better organize the effort and define the work products:
Task 1 -Demand Forecast -Evaluate present energy use in the region and
predict future requirements
Task 2 Energy Supply Technology Evaluation Review and evaluate
available energy technologies and select those suitable for use in the
development of alternative energy plans
2-3
Task 3 Regulatory Coordination and Public Participation Identify
regulatory requirements, coordinate with governmental agencies having
interest in the study, and maintain communication with Bristol Bay region
residents
Task 4 Al ternative Power Plans Identification -Formulate alternative
power plans based on demand forecasts and suitable energy supply
technologies
Task 5 Field Data Collection Collect geotechnical, hydrologic,
environmental, and sociocultural data to use in evaluating the power plans
Task 6 -Conceptual Design -Develop preliminary design concepts for the
alternative power plans formulated
•
..
•
JIll ...
• ..
Task 7 -Environmental and Socioeconomic Impact Assessment -Evaluate the ..
power plans with respect to environmental and socioeconomic factors
Task 8 -Economic Evaluation -Evaluate the cost, financing, and marketing
aspects of the power plans
Task 9 Base and Alternative Plan Comparison Compare
alternative plans with respect to technical, environmental,
factors
the base and
and economic
Task 10 -Feasibility Report -Prepare an Interim Feasibility Assessment
and a Detailed Feasibility Report documenting the results of Tasks 1
through 9 and presenting conclusions and recommendations
Task 11 -FERC License Application (If Required) -Prepare a FERC license
application if a hydroelectric development
alternative and determined to be feasible
is the most promising
The Work Plan is further designed to consider the following three
hypothetical power plan cases to aid in comparing alternatives:
2-4
• •
-
• .. .. -•
•
• ..
...
..
• A Base Plan, which represents the continuation of present practices of
reliance on oil-fired (diesel) generation
• Alternative "A", which consists of the Tazimina River Hydroelectric
Project as the required regional power supply
• Alternative "B", which consists of other energy sources, projects, or
facilities, either alone or in combination
In order to provide a degree of optimization and to permit the evaluation
of a greater number of alternatives, a number of "scenarios" were evaluated
within Alternative B. These scenarios consider variations in type,
location, and interconnection of energy production systems.
2.5 STUDY PARTICIPANTS
In order to accomplish the complex requirements of the study in the most
efficient manner, SWEC engaged the services of a number of reputable
Alaskan firms to assist in regional data collection and specific field
studies at Tazimina,
technical aspects of
and to
the
serve
work.
as consultants
The following
relative
Alaskan
organizations contributed to the work in the areas indicated:
to certain
firms or
• Dames & Moore -Environmental and sociocultural data collection and
analysis and hydrologic analysis
• Shannon & Wilson, Inc. -Geotechnical data collection and analysis
• Universitv of Alaska, Institute of Social and Economic Research -
Energy demand forecasts
• Bristol Bay Native Corporation Land status and assistance in
regulatory coordination and public participation
• Wind Systems Engineering, Inc. -Wind energy analysis
2-5
• Green Construction Company -Assistance in construction cost estimates
• Dryden & LaRue -Consultation related to electrical transmission systems
2.6 INTERIM FEASIBILITY ASSESSMENT
The prime objective of Phase I of the Bristol Bay Regional Power Plan,
called the "Interim Feasibility Assessment", has been to make an interim
assessment of the previously identified Tazimina Hydroelectric Project and
to compare that project with the Base Plan and other alternatives.
However, during Phase I, sincere efforts have been made to formulate
..
•
alternative plans that might be equal or possibly superior to Tazimina as a •
regional power source. A major effort during the interim assessment has ..
been to develop numerous alternative "scenarios" involving combinations of
the energy supply technologies that are considered viable for the region.
These scenarios have been screened, reduced in number, and compared with
each other and with Tazimina to provide a basis for a recommendation on the
direction to take in Phase II.
Phase I completes Tasks 1, 2, and 4. In addition, Tasks 5 through 10 have
been undertaken on a preliminary basis and in sufficient detail to satisfy
the objectives of the Interim Feasibility Assessment. Task 3, Regulatory
Coordination and Public Participation, required special effort during Phase
I because of the interest the study generated among both the residents of
Bristol Bay and numerous federal, state, and regional organizations
concerned with resource planning and environmental protection.
2.7 REPORT ORGANIZATION
•
-
The first section of the report (Section l, Executive Summary) summarizes •
the work that lead to the Interim Feasibility Assessment presented herein.
The following sections provide more detail and are intended to lead the
reader logically from project initiation through data collection and
several levels of evaluation, screening, and comparison. Energy production
scenarios are developed, evaluated, and compared. Finally, conclusions are
presented regarding the scenarios from the standpoint of technical
feasibility, economics, and environmental compatibility.
2-6 •
Extensive reports have been prepared by SWEC and its subcontractors for
several of the tasks and are summarized in the body of this report. The
complete detailed reports are included as appendicies.
To the extent possible, use was made of data collected by others on the
Bristol Bay region. Principal data sources are referenced at the ends of
two-digit sections. Additional data, drawings, and calculations which are
too voluminous to include in the report are on file in SWEC' s offices
Denver or in the offices of other team members.
2-7
References for Section 2
1. Bristol Bay Native Association, "Energy and Bristol Bay", June 1980.
2. R. W. Retherford Associates, "Bristol Bay Energy and Electric Power
Potential, Phase 1", prepared for the Alaska Power Administration,
December 1979.
3. R. W. Retherford Associates, "Reconnaissance Study of the Lake Elva and
Other Hydroelectric Potentials in the Dillingham Area", prepared for
the Alaska Power Authority, February 1980.
4. R. W. Beck and Associates, "Lake Elva Project Detailed Feasibility
Analysis", prepared for the Alaska Power Authority, January 1981.
5. Stone & Webster Engineering Corporation, "Appendix B Work Plan",
Contract AS 44-83-010, submitted to the Alaska Power Authority, July
1981.
2-8
...
",",
II,,, ..
... '
MI·
...
...
-
....
....
....
...
....
3. ENERGY CONDITIONS
AND
DEMAND FORECAST
3. ENERGY CONDITIONS AND DEMAND FORECAST
3.1 INTRODUCTION
An understanding of the energy uses and energy needs of the 18 Bristol Bay
study area communities is paramount in order to develop reliable forecasts
of future requirements. During Phase I, data necessary for this purpose
was obtained through direct visits to the communities; by direct
discussions with key individuals within communities; by the compilation of
data on community needs, lifestyles, problems, and concerns; by the use of
historical data on the communities and the region; and by research
concerning major planned energy-related activities or projects and other
economic, social, environmental, demographic, and physical conditions which
form strong influencial factors affecting the people of the region and
their needs for energy.
These data were analyzed to develop village energy profiles, addressing
distinguishable features regarding energy movements, household stock, and
prospects for economic and energy growth. The obj ective of this analysis
was to provide a demand forecast through the year 2002 for use in
formulating alternative power plans.
The work required to develop this energy demand forecast was performed for
the project by the Institute of Social and Economic Research (ISER) of the
University of Alaska. Their study efforts were prepared and presented in
two steps. Under the first step, ISER analysed data collected in a
preliminary manner for use in this Phase I Interim Feasibility Assessment
report. The approach and methodology used in developing the preliminary
energy demand forecasts and the results of data analyses are given in
greater detail in Appendix C. This analysis uses an approach and
methodology that is similar to that to be used in the final evaluation of
energy demands. The approach and methodology for expanding the preliminary
energy demand forecast data are given in Appendix A.l. Under the second
step, ISER continued with its data gathering process and analysed the data
collected with a more rigorous approach. The results from this analysis
3-1
are given by ISER' s report entitled "E lectricity Demand Forecast for the
Bristol Bay Regional Power Plan", dated April 1982. A limited number of
copies of this final report are available with the Alaska Power Authority.
...
This final ISER report reflects the data and conclusions for electrical .,.
power demands, as developed under the preliminary report for a Base Case
scenario and, in addition: 1) the electrical power demands for two
Alternative Case scenarios, 2) electric space heating considerations, 3)
methodology for projecting non-space heating electricity use in the region,
and, 4) other data required under contract with ISER. Since this final
report is based on more detailed analyses and data, there exist certain
minor variations in electrical energy and capacity values from those
developed under the preliminary phase of the energy study. These
variations are more applicable to the two alternative case scenarios
studied.
It is the intent of the study for the development of a regional power plan
for Bristol Bay to utilize the data presented by ISER's final report in the
Phase II effort of the study. The data would then be applied to the Base
Case scenario (s) and other scenarios selected under the Phase I efforts as
promising for further detailed study.
The remainder of this section addresses the two major energy needs of the
study region as reflected by the preliminary Phase I energy demand report,
namely:
• Electrical energy for appliance use
• Space heating energy needs, including energy needs for hot water and
some cooking
3.1.1 Methodology of Forecasting -Electrical Energy Demands
...
....
•
•
In assessing the electrical energy needs and developing the demand _
forecasts, the eighteen communities have been grouped into similar
categories; these categories were selected to reflect the pattern of
electricity usage in the 1980 base year. The categories are:
3-2
-...
•
• Central Station Utility: Dillingham, Aleknagik, Naknek, South Naknek,
King Salmon, Egegik, Manokotak, and New Stuyahok
•
•
Seasonal-Central Station Utility: Portage Creek, Ekwok, and Koliganek
(those villages which shut down in the summer)
Non-Central Station Utility: Clarks Point, Ekuk, Levelock, Igiugig,
Iliamna, Newhalen, and Nondalton
The non-central villages of Iliamna, Newhalen, and Nondalton are presently
involved in the installation of a central system with transmission line
interties. This fact has been taken into consideration when energy plan
scenarios were being developed and evaluated.
Electricity demand projections made under the preliminary evaluation are
consistent with the Base Plan scenario. This means that electricity energy
demands are primarily dependent on diesel power generators. Also, under
the base plan scenario, the energy demand projections assume that use
patterns of electrical energy would not change dramatically from observed
trends and, further, that the effects of state intervention to lower
electricity prices will continue throughout the 20-year forecast period. A
further growth-influencing assumption applied to the forecast methodology
is that no electric space heating will be developed over the forecast
period, principally because of the anticipated cost of electrical energy.
These assumptions and criteria result in a conservative (lower) energy
demand forecast.
The purpose of the regional power plan study is to identify possible
electrical energy plans which would result in lower electricity cost for
the consumer than those presently in effect. Recognizing that the
possibility exists for an increase in electricity use resulting from lower
cost, sensitivity analyses will be performed on the energy demand forecast
to reflect the influence of the lower anticipated cost. The results from
these analyses will be used in Phase II to further compare, refine, and
optimize electric energy plans selected for further detailed analysis.
3-3
However, these refinements are not considered necessary for the purpose of ~
comparing the large number of scenarios developed in Phase I.
3.1.2 Methodology of Forecasting -Space Heating Energy Demands
The preliminary analysis assumes that space heating energy demand is
independent of electrical energy demand. This is because space heating
demands are based almost exclusively on heating by use of fuel oil. It is
also recognized that wood is used to some extent for space heating and that
electrical energy is used to a small extent for space heating in the
residential and commercial/government sectors of the region. However, for
the purposes of this analysis it has been assumed that all space heating
needs will be met by fuel oil. This approach should form a complete
measure of space heat demand.
Survey data collected in each community were used in estimating the
residential and commercial/government heating fuel oil base year
consumption. No attempt was made to delineate that portion of oil consumed
for either cooking or hot water heating in the residential and
commercial/government sectors.
""
..
..
..
•
Having established a base year fuel oil need for the communities, it was _
assumed that use per residential customer would grow at an average annual
rate of one percent per year.
floor area, with the base
This reflects an assumed increase in average
remaining
electricity
constant.
demand
customer per village.
The
year levels of
proj ected number
forecasts) was used to
consumption per
of households
square
(from
forecast the consumption
foot
the
per
The space heating energy demand in the commercial/government sector was
derived in the same manner as that in the residential sector. Estimated
base year levels of heating oil used per customer were adjusted to reflect
customers involved to calculate 1980 space heat demand. Consumers' numbers
in each community were allowed to grow at a rate that was assumed for the
corresponding village groupings (that is, central, seasonal central, and
3-4
•
•
•
." -
-
•
non-central). The consumer consumption was assumed to grow at one percent
per year over the 20-year forecast period.
In the industrial sector, space heat demand was based on energy-use data
collected directly from the Bristol Bay region shore-based fish
processors. Space heating is required mostly for bunkhouses and offices.
Space heating average needs per customer were determined from available
data and applied to the 13 identified base-year processors. For the
industrial sector, it has been assumed that space heating consumption per
customer would remain constant over the 20-year study period. The increase
seen in the industrial sector results from the addition of one new process
facility in Dillingham in 1982. Electric space heating was indicated by a
few processors; this is because of the use of residual load from
self-generated electricity, which improves the plant factor for the
processor's plant.
In summary, the key assumption regarding 'the estimates of space heating
energy demand is that it remains non-electric in the base plan preliminary
forecast. Furthermore, the analysis has implicitly assumed that additional
conservation measures are not implemented by either residential,
commercial/government, military, or industrial sectors.
3 . 2 ENERGY FORECASTS
Summarized in this section are the results of energy demand forecast
studies regarding electrical energy for appliance end-use and fuel oil
energy for space heating end-use (including hot water and some cooking) as
determined under the preliminary analyses by ISER and expanded for use in
this iterim report.
3.2.1 Technical Discussions -Electrical Energy Demands
The electrical energy demand forecast for the study region to the end of
year 2002 reflects a conservative load growth scenario believed to be
indicative of the continuation of present use trends, costs, and
3-5
subsidies. The resulting electrical energy demand projections for all
sectors of the study region are summarized in Tables 3.2-1 and 3.2-2.
Data from these tables has been expanded (Appendix A.1) to show needs on a
per-village basis by sector. This is shown on Table 3.2-3.
These energy forecast values represent net energy from the proposed plan
and/or its transmission line grid. It has been assumed that a 10 percent
increase should be made to allow for losses due to power plant energy
..
lit-
needs, transmission line grid losses, and other minor contingencies. The ..
resul ting energy and power demand values used in the interim assessment
study are:
Year (HWh/yr) Power (kW)
1982 32,400 7.9
1987 38,700 8.9
1992 47,600 11.2
1997 58,900 12.2
2002 74,500 15.0
Key parameters, assumptions, and conditions relating to sector projections
considered in the demand study are discussed below.
3.2.1.1 Residential Sector
The more important factors affecting electrical energy projections for the
residential sector were found to be:
•
•
•
Population growth
Concentration over time of census division population in the
18-community study area
Saturation of electric hookups
• Village electrification
• Energy prices
• Household income
• Saturation of electrical appliances
3-6
-..
•
....
•
., .. '.
• ..
...
...
... ..
The preliminary projection of residential customers assumes an overall
population growth rate between 1.5 and 2.0 percent per year. This is lower
than the historical rate 2.4 to 2.5 percent (Appendix C, Table 3), which
reflects, in part, the rapid economic growth from fisheries expansion in
the latter 1970' s. Local population increases are also seen from
intra-regional shifts as well as from in-migration.
Developed average annual population growth rates are adjusted to reflect
the decline of the average household size (Appendix C, Table 4), which is
seen to be more pronounced in rural communities. Assuming that the
declining trends continues, but at the reduced rate of 1.0 percent per year
over the study projection period, it would appear that the average
household size in the year 2002 would be 2.74 persons.
In recognition of the fact that the non-central station residential sector
would grow to reflect the inevitable need and implementation for central
village electrification, the population growth has been adjusted in this
sector by an additional growth factor of 1.023 percent. This factor was
derived from the analysis of appliance saturation studies for household
lights.
Residential appliance saturation rates, defined as the number of residences
in a particular village which own one more of a given appliance divided by
the number of residences in that village, were also used in the projection
forecasts. These rates, coupled with appliance energy demand
characteristics and usage. the desire for addit ional future appliances,
future development plans of electric energy intensive projects, and
anticipated electrification potential of each village, were all evaluated
to derive the annual electricity use for the average residence for each
village category.
An important assumption that affects primarily the annual electricity use
rate of the non-central villages was that all communities will tend to get
central station utility electricity within the forecast period. Further, a
contingency factor of 0.25 percent was added to the calculated growth
3-7
factor in each village category. This was to account for new applicances
and any potential downward bias in the methodology. An adjustment was also
made to the consumption values derived from the appliance saturation
analysis to account for seasonal consumption decreases at villages where a
significant percentage of households are vacated during the fishing season.
The resulting projections of annual electricity consumption per residence
for the three village categories are given in Table 3.2-4.
The data for the residential sectors given in Table 3.2-2 were developed
from data on the growth of customer numbers and on the growth in average
use per customer.
Studies on the effects of electrical energy costs, adjusted to reflect the
subsidy implied by the Power Cost Assistance program, were made to
determine usage trends and mode changes. The studies show that for the
central station communities, that portion of the average projected
household income to be spent on electricity needs would vary from 3.9
percent in 1982 to 7.3 percent in 2002. This group of communities is the
least impacted in comparison to the other two selected study groupings.
The second least impacted group is that groups of communi ties categorized
as seasonal non-central. For these communities, the studies show that
about 8.2 percent of the projected average household income would be spent
on electricity in the year 1982, while this percentage value increases to
17.9 percent in the year 2002. The third category, the non-central station
communities, appear to be affected the greatest amount. The studies
indicated that these communities need to spend some 27 to 28 percent of
their average household income for electrical energy cost; this appears to
be presently occurring in these communi ties. Forecasts for later study
years are more than twice those presently realized. Because of this, it is
believed that these communities would tend to switch over to central
village electric generation.
3.2.1.2 Commercial/Government Sector
Survey data compiled in the study were used to develop baseline estimates
3-8
..
..
-..
• ..
•
of the number of commercial/government customers and average electricity
use per customer for the year 1980. These data are shown on Table 3.2-5.
The type and number of commercial/government facilities in rural villages
is shown on Table 3.2-6 for 1981. The average annual growth rates assumed
to forecast growth in number of customers and in average use per customer
are shown in Table 3.2-7.
As shown in Table 3.2-6, most villages have a service infrastructure
covering utilities, health, education, and village administration.
Al though more growth in the commercial/government sector can be expected
over the next 20 years, it should be noted that baseline estimates of
customer numbers and energy use per customer reflect a rapid growth period
from fisheries activities and public spending.
Because of this, the assumptions about growth have been tempered to relate
to long-term probable growth and not periodic upswings having short-term
duration. Energy use per customer in this sector was assumed to grow at
2.4 percent per year for central station villages. This is based on the
historical pattern of non-residential electricity consumption in several
southwest Alaska utilities (Figures 6 and 7 of Appendix C).
For the commercial/government growth rate in the seasonal-central station
and non-central station villages, a rate equal to the residential use rate
per customer for the seasonal-central villages has been applied. This is a
growth rate of 2.31 percent per year. The studies show that the
commercial/government sectors in these two village groups exhibit similar
characteristics, despite the important variance in the method of power
production. It should be noted that the non-central commercial users
already have relatively large generating facilities; they are not expected
to respond dramatically to electrification.
In determining the number of customers for central station villages, the
growth rate in the number of commercial/government customers was made equal
to the residential rate growth plus a small increment which reflects the
difference in growth between residential and commercial customers for the
3-9
combined Bristol Bay utilities (Appendix C, Table 16). The increment is
120 percent and was applied directly to the residential customers for
central station communities.
The growth rate for the number of customers for seasonal central station
villages and for non-central station communities was assumed equal to the
growth rate of the residential users in the respective community grouping.
3.2.1.3 Industrial Sector
For the energy plan study, analysis of the industrial sector relates
exclusively to the fish activities of the region. In 1980, there were 13
major shore-based processors operating in the study region; approximately
40 shore-based fish camps and fish buyers were also logged for that year.
Offshore processors which serve several Alaska fisheries were not included
in the study because they do not contribute to electricity demand.
All 13 shore-based processors were surveyed by the ISER study team. Data
on these processors and their electricity use is given in Table 3.2-8.
Most processors use their own generators for peak summer months of the
fishing season. Some also purchase electricity from utilities, and only
one processor depends entirely on the electric utility.
The electrical energy needs relating to the industrial sector are assumed
to be essentially constant over the time period 1980-2001. However, there
are indications that the processors with canning facilities will eventually
convert to canning and freezing. This conversion would result in a more
energy-intensive process, but would cause only a small increase in
electricity needs for this sector over the study period. Similarly, with
the exception of one additional processor that will be in operation in
1982, it is believed that energy demands for the sector will remain
essentially unchanged. Projections of electrical energy needs for the
major shore-based processors are shown in Table 3.2-9. The Power Cost
Assistance subsidy was implicitly assumed as relatively unimportant.
Therefore, electricity prices are close to the real marginal cost of oil.
3-10
•
• .. ..
•
...
.,
..
-
... ..
•
The average annual electricity consumption per fish camp and buy station
customer of 24 MWh was based on 1980 data from ten buyers and fish camps in
the study region. Actual consumption varies greatly, since operations vary
in size. For the study, it has been assumed that the average annual
consumption will not change over the study period. However, the number of
buyers will peak in the mid-1980 IS, and retired fish camps will not be
replaced (Table 21 of Appendix C).
3.2.1.4 Military Sector
The Alaska Air Command (AAC) base at King Salmon is the only military
installation in the study region. This base began to purchase its
electricity needs from the Naknek Electric Association (NEA) during
December 1981. The military base has contracted for S, 600 MWh of energy
from NEA. This energy need was used for all years of the study period,
since no changes are expected in the military sector.
3.2.1.5 Electric Space Heating or Increased Usage
Under the present relative price structure of electricity and diesel fuel
in the study region, the cost of using electricity generated by diesel fuel
for residential space heating is considerably greater than that of oil
furnaces. Nevertheless, the regional power plan must consider the
possibility of a shift from oil to electricity for space heating, should
lower cost electrical energy become available.
The sensitivity of electrical energy demands to lower energy cost is to be
analyzed and presented as part of the final energy demand forecast by
ISER. It should be noted, however, that under the present price structure,
where cost of fuel oil to the consumer varies from about $1.42/gal to about
$1.69/gal, the cost of electrical energy would have to be less than
$O.OS/kWh and $0. 06/kWh, respectively, to be competitive with fuel oil at
1982 prices. As the fuel costs escalate at a rate of 2.6 percent per year
above inflation, the corresponding cost of oil in the year 2002 would be
about $2.37/gal and $2.80/gal. At that time, electrical energy cost would
3-11
need to be less than $0. 08/kWh and $0. 10/kWh, respectively, in order to •
compete with fuel oil. This simplified cost comparison does not take into
consideration the investment costs, if any, needed to convert the present
heating systems to electric heating. These costs would not be considered
for future developments, where electric space heating installations would
be a part of the building costs.
3.2.2 Technical Discussions -Space Heating Energy Demands
The space heating energy needs of the region are being met predominantly by
the use of fuel oil energy, and to a limited extent by the use of wood and
some electric space heating. For the interim assessment, it has been
assumed that all space heating, as well as some minor cooking energy needs
and the energy needs for hot water, are all being met by burning fuel oil.
These energy needs are shown in Table 3.2-10 for the 18 study-area
communities and represent estimated values for the 1980 year. These values
form "base line" values for use in projections over the study period.
The space heating needs of the region have been segregated to address the
residential,
the Bristol
commercial/governmental,
Bay study region. The
conservation measures are not performed.
industrial,
analysis
and military sectors of
implicitly assumes that
Using the approach and methodology previously described, the space heating
energy needs, given by village and sector, are summarized in Table 3.2-11
and graphically shown by Figure 3.2-1. The impressive fact concerning the
forecast values of space heating needs is their magnitude: they are five
times or more that of the electrical energy forecasts previously described.
The great:est needs for space heating are in the commercial/government and
the residential sectors.
The space heat values given contain fuel oil needs for hot water heating.
It is estimated that this component of the total fuel needs is about 7 t:o
12 percent in the residential sector and possibly twice that amount in the
remaining sectors. These estimates are given for the appropriate sectors
in Table 3.2-12.
3-12
...
•
.,
..
..
.,
..
...
As previously stated, it appears doubtful that electric energy cost could
be low enough to promote electric space heating. Meeting space heating
energy needs through electrical energy, in addition to the appliance end
use energy needs for the year 2002, would require a generating installation
of about 74 MW capacity (Appendix A.l).
The approach and methodology for responding to these energy needs, whether
from electrical generation or through another energy resource, is not a
part of the study, but could be addressed in Phase II of the study effort.
3-13
TABLE 3.2-1
BRISTOL BAY POWER PLAN OVERALL ELECTRIC ENERGY DEMAND PROJECTIONS
(MEGAWATT HOURS/YEAR)
Commercia1/
Residential Gov't Industrial Militar;t
% of % of % of % of
Year Total Total Total Total Total Total Total Total
1980 4,459 16 9,629 34 8,248 30 5,600 20
1982 4,936 16 10,951 36 8,819 29 5,600 19
1981 6,249 11 15,083 42 8,952 25 5,600 16
1992 1,931 18 20,189 48 9,025 21 5,600 13
1991 10,060 19 28,642 54 9,098 11 5,600 10
2002 12,143 19 39,632 59 9,098 14 5,600 8
1980-2002
Overall Average
Annual Rate
of Growth,
Percent 4.89 6.64 0.45 °
SOURCE: ISER Report, Appendix C
Total
21,936
30,312
35,884
43,351
53,400
61,013
4.06
t i
TABLt:: 3.2-2
BRISTOL BAY REGIONAL POWER PLAN ELECTRICAL hNERGY DEMAND PROJECTIONS bY CUSTOMeR
Number of Customers Elect. Consum~. ~er Customer (kW) Total Electricit~ Consum~tion (MW)
Seasonal Non-Seasonal Non-Seasonal Non-
Central Central Central Total Central Central Central Central Central Central Total
Residential
1980 810 68 82 960 5,152 1,308 2,401 4,113 139 191 4,4':)9
1982 859 11 90 1,020 5,115 3,021 3,062 4,445 215 216 4,936
1981 996 81 114 1,191 5,585 3,413 3,591 5,563 216 410 6,249
1992 1,154 91 145 1,390 6,046 3,829 4,222 6,911 348 612 1,931
1991 1,338 103 184 1,625 6,501 4,214 4,965 8,106 440 914 10,060
2002 1,551 111 234 1,902 6,969 4,808 5,851 10,809 563 1,311 12,14j
Commercial/Government
1980 355 19 69 443 22,413 13,092 20,322 1,918 249 1,402 9,629
1982 386 20 14 480 23,598 13,104 21,212 9,109 214 1,514 10,9':)1
1981 416 22 88 586 26,569 15,362 23,845 12,641 338 2,098 15,083
1992 581 23 106 116 29,914 11,220 25,129 11,560 396 2,833 20,189
1991 124 25 126 815 33,680 19,303 29,963 24,384 483 3,115 28,642
2002 896 21 151 1,014 31,920 21,638 33,581 33,916 584 5,012 39,632
Industriala Processors Processors Processors
Can/ Fish Camps & Can/ Fish Camps & Can/ Fish Camps &
Can onl~ Freeze BU:i Stations Total Can onl~ Freeze Bu~ Stations Can onl~ Freeze Bu~ Stations Total
1980 3 10 40 53 486,000 583,000 24,000 1,458 5,830 960 13,248
1982 3 11 42 56 486,000 583,000 24,000 1,458 6,413 1,008 B,819
1981 2 12 41 55 486,000 583,000 24,000 912 6,996 984 8,9':)2
1992 1 13 40 54 486,000 583,000 24,000 4B6 1,519 960 9,025
1991 0 14 39 53 0 583,000 24,000 0 8,162 936 9,098
2002 0 14 39 53 0 583,000 24,000 0 8,162 936 9,098
aDoes not correspond to village groups for residential and commercial/government.
SOURCE: ISER Report, Appendix C.
;,."
TABLE 3.2-3
PRELIMINARY PROJECT FORECAST
ELECTRICAL ENERGY AND POWER REQUIREMENTS
BASED ON BASE PLAN SCENARIO BY ISER
YEAR
1982 1987 1992
Location
Dillingham
Energy (MWh/year) 8,740 11,550 15,800
Power(kW) 2,045 2,571 3,445
Naknek/King Salmon
Energy (MWh/year) 14,700 16,370 18,650
Power (kW) 2,987 3,327 3,370
Subtotal Dillingham/Naknek
Energy (MWH/year) 23,440 27,920 84,450
Power (kW)* 4,032 5,898 7,235
Clarks Point
Energy (MWh/year) 620 700 775
Power (kW) 184 216 243
Egegik
Energy (MWh/year) 1,300 1,400 1,500
Power (kW) 683 639 599
Ekuk
Energy (MWh/year) 800 800 800
Power (kW) 913 913 767
Ekwok
Energy (MWh/year) 155 210 245
Power (kW) 44 60 68
Igiugig
Energy (MWh/year) 185 255 385
Power (kW) 54 74 108
Koliganek
Energy (MWh/year) 245 310 390
Power (kW) 71 90 107
Levelock
Energy (MWh/year) 190 245 340
Power (kW) 44 70 91
Manokotak
Energy (MWh/year) 430 560 720
Power (kW) 124 162 197
New Stuyahok
Energy (MWh/year) 550 720 930
Power (kW) 217 234 260
Portage Creek
Energy (MWh/year) 90 120 140
Power (kW) 26 35 39
1997 2002
21,000 28,100
4,555 6,095
21,650 25,800
4,400 5,242
42,650 53,900
8,955 11,337
880 1,030
276 323
1,620 1,790
647 715
800 800
593 457
285 370
70 80
500 700
131 149
465 580
115 127
470 670
115 145
930 1,220
230 258
1,210 1,625
297 347
180 215
41 44
TABLE 3.2-3 (cont)
PRELIMINARY PROJECT FORECAST
ELECTRICAL ENERGY AND POWER REQUIREMENTS
BASED ON BASE PLAN SCENARIO BY ISER
YEAR
1982 1987 1992
Location
Subtotal -10 villages
Energy (MWh/year) 4,565 5,320 6,225
Power (kW)* 2,360 2,493 2,479 I
Iliamna/Newhalen/Nondalton
Energy (MWh/year) 1,420 1,935 2,615
Power (kW) 324 442 597
Total
Energy (MWh/year) 29,425 35,175 43,290
Power (kW)* 6,716 8,833 10,311
* Noncoincident power loads.
Note: System losses not included.
1997 2002
7,340 9,000
2,515 2,645
3,570 4,840
795 1,055
53,560 67,740
12,265 15,037
Year
1981
1982
1987
1992
1997
2002
Average
TABLE 3.2-4
PROJECTED APPLIANCE ELECTRICITY CONSUMPTION
(Kilowatts per Year per Customer)
Central Utility Central-Seasonal
5,124 3,968
5,175 3,027
5,585 3,413
6,046 3,829
6,507 4,274
6,969 4,808
Annual
Rate of Growth
(percent/year) 1.48 2.31
Non-Central
2,973
3,062
3,597
4,222
4,965
5,857
3.27
TABLE 3.2-5
1980 ELECTRICITY CONSUMPTION IN THE BRISTOL BAY
COMMERCIAL/GOVERNMENT SECTOR
Total Commercial/
Total Electricity Government
Village Groups Consumption Customers
Central Stations
Dillingham
Aleknagik
Naknek
King Salmon
South Naknek
Egegik
Manokotak
New Stuyahok
All Villages
Seasonal-Central Station
Portage Creek
Ekwok
Koliganek
All Villages
Non-Central Station
Iliamna
Newhalen
Nondalton
Clarks Point
Ekuk
Levelock
Igiugig
All Villages
Total All Villages
(kwh/yr)
4,114,318
2,193,166
82,092
126,118
202,302
1,911,996
41,191
85,530
115,435
248,156
639,121
243,593
186,491
69,631
NA
125,685
131,082
1,402,215
9,628,961
SOURCE: ISER Report, Apendix C
aAll school facilities counted as one customer.
194
136
9
8
8 a
355
6
5
8
19
31
9
10
6
1
8
2-
10
443
Average
Electricity Use
per Customer
(kwh/customer/yr)
24,610
20,538
9,121
15,165
25,288
22,413
1,965
11,105
14,429
13,092
20,636
21,066
18,650
11 ,605
NA
15,111
21,416
20,032
21,681
TABLI:: 3.2-6
COMMEHCIAL AND GOVI::RNMENT/COMMUNITY BUILDlNGS -1981
Clarks New Portage So.
Aleknagik Point Egegik I:;kuk Ekwok 19iugig Iliamna Koliganek LevelocK ManoKotaK ::itu;tahok Newhalen Nondalton Creek Naknek
Commerical
Store 0 2 (a) 2 1 1 0 2 2 0 2 2 2 (g) 0
Bar/restaurant 0 0 1 0 0 0 0 0 0 (b) 0 0 1
Lodge 0 0 0 1 8 (j) 7 0 1 0 0 2 ( 1 =s) 0 0
Other 2 0 1 0 0 0 0 (c) 0 0
Government/Community
Post Office 0 0 0 (n (e) 0
Village Council/
City Office 1 1 0 0 1 0 1 1 1 0 0 1
Commun i t Y tla 11 0 0 0 0 0 0 0 0 ( s) 0 0
Clinic 1 1 ( s) 1 0 1 0 1 (s) 1 1
Clinic/Comm. Hall 0 0 1 0 0 1 0
Fire ::itatiOl1 0 0 0 0 0 0 2 0 0 0 0 0
Wiater & Sewer
Utility 0 0 0 0 0 1 0
Electr1c Ut1l1ty 0 0 0 1 0 0 1 (d,i) 1 (1) 0 0
Warehouse 0 0 0 0 2 1 0 0
Hangar 0 0 0 0 2 0 0 0
liirpor t Ligh ts 0 0 0 0 0 0 0 0 0 0
Church 3 1 2 1 1 1 2 1 1 1 1 (n
School Bldgs 2 1 0 1 1 0 2 2 2 5 2 2
Teacher Housing 2 0 1 1 3 1 6 Ii 3 1
Gymnasium 0 0 0 0 0
HeA/ Alascom
Others 1 (h)(s)
(s) = Seasonal
(a) One store 1s seasonal (n Hes1dence in name bu ilding
(b) Mayor plans to open a coffee shop (19tl3) (8) One store is in residence
(c) Mayor plans to build a laundromat (1983) (h) Corpora tion bldg -"Pool Hall"
(d) Utility building under construction (1) School generator building
(e) Same building as co-op store (j) Across river
SOUHCI::; I::iI::H Report, Appendix C.
.....
TABLE 3.2-7
GROWTH IN USE PER CUSTOMER AND NUMBER OF
CUSTOMERS IN THE COMMERCIAL/GOVERNMENT SECTOR
Central Station
Use per Customer 2.40
Number of Customers 4.28
PERCENT PER YEAR
Community Groups
Seasonal-Central
Station
2.31
1.54
Non-Central
Station
2.31
Total Number of
Processors
Self-Generating
Number With own
Generator
Average MWh
Produced/Year
Number Without
Average MWh
Year/Proc.
Utility Power
Number Using
Average MWh
Purchased/Year
Number Not Using
Average MWh
Year/Proc.
TABLE 3.2-8
ELECTRICITY CONSUMPTION BY BRISTOL BAY
FISH PROCESSORS -1980
Kvichak Fishery Nushagak Fishery
9 4
7 4
913 (2)a 572 (2)a
0 2
710 572
8 2
97 (8)a 62 (2)b
1 2
86 31
Bristol Bay
Study Region
13
11
2
660 b
10
3
69
aN umbers in parentheses indicates number of processors for which data was
available.
bAverages are weighted for number of processors in each fishery.
SOURCE: ISER Report, Appendix C.
TABLE 3.2-9
BRISTOL BAY SEAFOOD PROCESSOR ELECTRICITY DEMAND PROJECTIONS
Number of Customer Use Eer Customer Total E1ectricit~ ComsumEtion
Canning Canning Canning
Canning and/or Canning and/or Canning and/or
Year On1~ Freezing On1~ Freezing On1~ Freezing Total
(MWh/Processor/Year) (MWh/Year)
1980 3 10 486 583 1,458 5,830 7,288
1982 3 11 486 583 1,458 6,143 7,871
1987 2 12 486 583 972 6,996 7,968
1992 1 13 486 583 486 7,579 8,065
1997 0 14 486 583 0 8,162 8,162
2002 0 14 486 583 0 8,162 8,162
SOURCE: ISER Report, Appendix C.
TABLE 3.2-10
SPACE HEATING IN 1980
IN THE EIGHTEEN STUDY AREA COMMUNITIES
Dillingham
Aleknagik
Naknek
King Salmon
South Naknek
Egegik
Manokotak
New Stuyahok
All Villages
Portage Creek
Ekwok
Koliganek
All Villages
Iliamna
Newha1en
Nondalton
Clarks Point
Ekuk
Levelock
Igiugig
All Villages
(1)
Average
Fuel Consumption
Per Customera
ga1,/househo1d/year)
1,080
1,164
1,289
1,100
985
1,103
1,035
1,083
930
991
1,033
1,033
1,033
1,364
1,800
2,009
1,083
1,257
Total All 18 Villages 1,118
(2 )
Number of
Households
505
246
23
57
65
896
13
20
40
73
35
18
42
22
1
28
15
161
1,130
aInc1udes fuel for water heating and some cooking.
SOURCE: ISER Report, Appendix C.
(1) x (2)
Total
Residen. Heating
Fuel Consumption
(ga1./year)
545,400
286,344
29,647
62,700
64,025
988,116
13,455
21,660
37,200
72,315
36,155
18,594
43,386
30,008
1,800
56,252
16,245
202,440
1,262,871
Dillingham
Residential
Comm/Gov
Industrial
Total
Naknek
Residential
Comm/Gov
Military
Industrial
Total
Clarks Point
Residential
Comm/Gov
Industrial
Total
Ekuk
Residential
Comm/Gov
Industrial
Total
Portage Creek
Residential
Comm/Gov
Total
Manokotak
Residential
Comm/Gov
Total
TABLE 3.2-11
SPACE HEATING DEMAND FORECAST BY VILLAGE BY SECTOR
BRISTOL BAY STUDY REGION
(All Values Given in MWh)
YEAR
1980 1982 1987 1992 1997
15,655 17,669 22,704 27,740 32,775
42,763 51,001 71 ,596 92,191 112,786
96 100 111 122 133
58,514 68,770 94,411 120,053 145,694
8,118 9,188 11,862 14,537 17,211
29,978 35,751 50,182 64,614 79,045
13,381 13,381 13,381 13,381 13,381
5,287 5 1287 5 1287 5 1287 5 1287
56,764 63,607 80,712 97,818 114,924
858 946 1,165 1,385 1,604
356 364 383 402 422
674 674 674 674 674
1,888 1,984 2,222 2,461 2,700
51 58 75 92 109
85 85 85 ...§2 85
136 143 160 177 194
377 415 509 603 698
304 311 327 344 360
681 726 836 947 1,058
1,767 2,003 2,595 3,186 3,777
1 1827 11867 1 1 966 2 1066 21165
3,594 3,870 4,561 5,252 5,942
2002
37,810
133,381
144
171,335
19,885
93,476
13,381
5 1 287
132,029
1,824
441
674
2,939
126
...§2
211
792
377
1,169
4,368
21265
6,633
Ekwok
Residential
Comm/Gov
Total
New Stuyahok
Residential
Comm/Gov
Total
Kolifjanek
Residential
Comm/Gov
Total
Efjefjik
Residential
Com/Goy
Industrial
Total
Levelock
Residential
Comm/Gov
Total
Ifjiufjifj
Residential
Comm/Gov
Total
TABLE 3.2-11 (cant)
SPACE HEATING DEMAND FORECAST BY VILLAGE BY SECTOR
BRISTOL BAY STUDY REGION
(All Values Given in MWh)
YEAR
1980 1982 1987 1992 1997
420 681 834 987 1,139
321 328 346 363 381
941 1,009 1,180 1,350 1,520
1,820 2,062 2,666 3,271 3,875
1,230 11257 113 24 1139 1 11459
3,050 3,319 3,990 4,662 5,334
1,040 1,152 1,434 1,715 1,996
534 546 575 604 633
1,574 1,698 2,009 2,319 2,629
828 937 1,209 1,481 1,753
906 926 975 1,025 1,074
113 49 113 49 113 49 113 49 11329
3,083 3,212 3,533 3,855 4,176
1,596 1,756 2,157 2,558 2,959
650 654 689 724 759
2,236 2,410 2,846 3,282 3,718
465 513 631 750 869
432 441 465 489 512
897 954 1,096 1,239 1,381
2002
1,292
398
1,690
4,480
1 1526
6,006
2,277
662
2,939
2,025
1,124
11349
4,498
3,360
794
4,154
988
536
1,524
Newhalen
Iliamna
Nondalton
Residential
Newhalen
Comm/Gov
Iliamna
Comm/Gov
Nondalton
Comm/Gov
Total
Area Total
TABLE 3.2-11 (cant)
SPACE HEATING DEMAND FORECAST BY VILLAGE BY SECTOR
BRISTOL BAY STUDY REGION
(All Values Given in MWh)
YEAR
1980 1982 1987 1992 1997
2,755 3,038 3,746· 4,453 5,161
534 546 575 604 633
2,070 2,115 2,228 2,341 2,454
838 856 902 948 993
4,197 6,555 7,451 8,346 9,241
139,555 158,257 205,007 251,761 298,511
2002
5,868
662
2,567
1,039
10,136
345,263
Sector & Energy Need
Residential
Hot Water/Cooking*
Space Heating
Commercial/Government
Hot Water/Others**
Space Heating
Military
Hot Water/Others**
Space Heating
Industrial
Hot Water/Others**
Space Heating
* Assumes 10 percent
** Assumes 20 percent
TABLE 3.2-12
SEGREGATION OF SPACE HEATING,
HOT-WATER, AND OTHER
ENERGY NEEDS -BY SECTOR
(All Values Given in MWh)
YEAR
1980 1982 1987 1992
3,266 3,672 4,687 5,702
32,664 36,723 46,872 57,020
13,7982 16,164 22,094 28,024
68,962 80,821 110,468 140,116
1,248 1,250 1,250 1,252
6,242 6,246 6,255 6,266
2,230 2,230 2,230 2,230
11,151 11,151 11,151 11,151
of total forecast for sector.
of total forecast for sector.
1997 2002
6,727 7,732
67,169 77,317
33,952 39,882
169,765 199,413
1,254 1,256
6,273 6,282
2,230 2,230
11,151 11 ,151
r-------------------------------------------------------------------------------------------..
0
0 0 ....
)(
.J::.
3:
:!!
>
C!l a: w z w
I-w
Z
I-
Z
W
...J « >
::::>
0 w
400~----------_r----------_r----------_+----------_+----------~
300
G\O~
:-l "'~ c:,~\)O
fO'" ~O~~\..
200
100
RESIDENTIAL
K,MILITARY ~ INDUSTRIAL
0
1980 1985 1990 1995 2000 2005
YEAR
REGIONAL SPACE HEATING NEEDS
FIGURE 3.2-1
~ ... • ... o
t(
....
....
"."
" .. ,
.. '
'"
....
.....
4. ENERGY SUPPLY
TECHNOLOGY
4 .. ENERGY SUPPLY TECHNOLOGY
A variety of energy resources and technologies were evaluated to arrive at
those most suitable for further study in Phase II of the Bristol Bay
Regional Power Plan. The Energy Supply Technology Evaluation, Appendix B,
provided the initial screening which involved investigating the state of
technology, technical restraints, constructibility, environmental impacts,
operating and maintenance aspects, regional restraints, and regulatory
restraints of each of the potentially viable technologies. The
technologies which emerged from the initial screening as viable candidates
for continued investigation were then evaluated with more emphasis toward
economic aspects in this Interim Feasibility Assessment. The economic
implications are addressed more fully in Section 7.4, and are mentioned
only briefly here.
4. 1 PROFILE OF ENERGY TECHNOLOGIES SURVEr"'ED
The potential resources for the Bristol Bay region were divided into six
major energy categories: fossil fuel, non-generating, renewable,
miscellaneous, nuclear, and advanced. Under the major categories, the
energy resources were arranged in 2S technologies for individual
evaluation. A brief description of the findings of the individual
technology evaluations follows. These technologies are discussed in more
detail in Appendix B.
4.1.1 Fossil Fuel Resources
4.1.1.1 Diesel Generation
Reliable, relatively efficient diesel generator sets are commercially
available, and have proven easy to install, operate, and maintain. Diesel
generators can be installed to supply power to individual dwellings,
villages, or the entire region using a central, multi-unit station.
4-1
4.1.1.2 Coal-, Oil-, and Natural Gas-Fired Steam Electric Generation
Conventional stearn electric generating stations are a proven and reliable
means of producing electrical power. Coal, oil, or natural gas are common
fuels for combustion in the plant boilers. These conventional steam
turbine plants are most economical when their size is maximized; a regional
plant serving a major portion of the Bristol Bay area would be most
viable. Coal-firing a stearn electric station's boilers in the Bristol Bay
region would be more economical than firing heavy fuels such as Alaskan
crude (See B.3.2.8).
4.1.1.3 Coal Gasification
Coal gasification plants producing low-and medium-Btu fuels are
commercially available in the sizes necessary for Bristol Bay region use.
The fuel produced by a coal gasification facility could supply a variety of
energy producing plants such as diesel generators, combustion turbines,
conventional stearn electric generating units, or combined cycle units.
4.1. 1. 4 Combined Cycle
Combined cycle is simply the combination of two thermodynamic cycles, the
Brayton (simple cycle combustion turbine) and the Rankine (stearn cycle)
into a fuel-efficient prime mover system. The major components of the
combined cycle unit are the combustion turbine, waste heat recovery boiler,
and steam turbine. The combined cycle system at full load is one of the
most efficient methods of converting petroleum fuels to electrical energy.
This technology is most economically applied in a central station
application.
4.1.1.5 Combustion Turbine
Combustion turbines can be designed to operate with a wide variety of fuels
such as natural gas, petroleum distillates, residual fuel oil, propane,
blast furnace gas, butane, and fuel produced by coal gasification.
Combustion turbines of the size required to meet Bristol Bay region power
4-2
..
.. ..
.,
•
.,
.. ..
l1li ..
•
.11
• ..
• ..
• ..
•
..
..
demands consume grea~er .amounts of fuel than comparably sized diesel
generators. Combustion ~urbine units are usually delegated to providing
peaking or stand-by power due to ~heir thermal inefficiency.
4.1.1.6 Heavy Fuels
Heavy fuels such as Bunker C or crude oil were considered for diesel
generation use since they are available in ~he Alaska area. However,
shipping cost to the Bristol Bay area raise the cost almost to that of
diesel. Also, the difficulties encountered with low temperature and the
increased wear of the engines make heavy fuels unattractive for this area.
Heavy fuels are discussed in more depth in Appendix A.3.2.
4.1.2 Non -Generating Resources
4.1.2.1 Energy Conservation
Energy conservation has been proven to have a direct impact upon utility
system load growth. Potential methods of conserving energy in the Bristol
Bay region must be identified and implemented, as possible. This subject
is discussed further in Appendix A.S.
4.1.2.2 Waste Heat Recovery
The use of rej ected heat from diesel engines, gas turbines, or steam
turbines for space heating or process uses is a commercially proven
concept. In the Bristol Bay region, waste heat from generating units can
be used for space heating. Waste heat recovery is discussed in more depth
in Appendix A.4.
4.1.3 Renewable Resources
4.1. 3.1 Wind Energy
Wind resources in portions of the Bristol Bay region are suitable for
electrical power generation. Wind turbines can provide a renewable energy
4-3
source to
capabilities.
supplement regional and local power system generat ing
Appendices A.6 and D address wind energy in greater detail.
4.1.3.2 Hydroelectric Power
Hydroelectric power generation technology was established shortly after the
advent of electricity. It is a very reliable, renewable resource which has
a proven, successful operating history in climates similar to that of the
Bristol Bay region. Proper site selection and development can minimize the
environmental impact of a hydroelectric proj ect. Economy-of-scale would
benefit a regional hydroelectric power station that serves a major portion
of the region.
4.1.3.3 Tidal Power
Harnessing tidal fluctuations for generating electricity has been
demonstrated in countries other than the United States. The tidal range is
suitable for power generation in certain areas of the Bris"tol Bay region.
However, due to unfavorable climatological, terrestrial, technical, and
economy-of-scale aspects, and the possible impacts on aquatic ecosystems,
tidal power generation is not considered feasible for the Bristol Bay
region.
4.1.3.4 Solar Thermal Energy
Central solar power stations require large areas of reflector or collector
surface to receive the quantities of insolation (radiation per unit area)
necessary for utility power generation. Solar insolation, a measure of
available sunlight, is insufficient in the Bristol Bay region to justify
further consideration of solar thermal energy for either power generation
or space heating. The lack of sunlight in the region would necessitate a
.. ..
•• ..
..
., ..
•
III!
.. ..
.,
.. .. ..
.. ..
III! ..
II;
..
complete power generation and space heating back-up energy supply, which ..
makes solar energy economically uncompetitive with other resources. ..
II' .. ..
...
4-4 •
4.1.3.5 Solar Photovoltaic Electric Systems
For the same reasons listed for solar thermal energy, solar photovol taic
electric systems are not considered a viable Bristol Bay region power
generation resource.
4.1.4 Miscellaneous Resources
4.1.4.1 Organic Rankine Cycle (ORC)
Organic Rankine Cycle technology is not efficiem:ly used as a primary
energy resource with direct combustion of fuels such as coal, oil, wood,
peat, ur gas. The heat available from this direct combustion is at
elevated temperatures more suitable for the conventional steam Rankine
cycle system.
ORC units capable of generating supplementary electricity from relatively
low temperature sources, such as a diesel engine's waste heat, are
commercially available. ORC units merit further consideration as a
potential supplementary energy supply for Bristol Bay.
4.1.4.2 Biomass (Wood) Energy
Wood is the only biomass resource of any significance to power generation
in the Bristol Bay region. However, wood is too scarce to provide fuel for
a central power station, and the adverse environmental impacts associated
with large-scale tree harvesting as well as its detrimental effects upon
subsistence living preclude the use of wood for electricity production in
the region.
4.1.4.3 Energy from Waste/Refuse
The economic feasibility of using refuse as fuel in a steam turbine
generating unit is dependent on an adequate local supply of refuse. Such a
supply does not exist in the Bristol Bay region.
4-5
4. 1. 4.4 Peat Energy
The use of peat as fuel in steam turbine generating units has been
successfully implemented outside the United States. The adverse effects
upon subsistence living and the environmental impacts caused by large-scale
peat harvesting are too severe to consider such a power plant in the
Bristol Bay region.
4.1.4.5 Geothermal
This technology is a proven source of energy in many regions of the Western
United States. However, geothermal resource data indicate that no proven
sites are in the proximity of the Bristol Bay region. Even the
prospective, or unproven, geothermal resources are too distant from the
region to justify a power plant of the size required. Costs associated
with exploring potential geothermal resources are prohibitive.
4.1.5 Nuclear Resources
4.1.5.1 Conventional Nuclear Power
The complexities associated with the design and operation of a safe,
reliable nuclear power station make this technology less practical for
small units. Undesirable seismic conditions, regulatory uncertainty, the
need for highly trained personnel, and costs make nuclear power an
unattractive energy supply option for the Bristol Bay region.
4.1.5.2 Nuclear Fusion and Breeder Reactors
These technologies will not be developed for commercial power generation in
the near term. Nuclear fusion and breeder reactor technologies also
exhibit many of the same features which make conventional nuclear power
generation impractical for the Bristol Bay region.
4-6
..
•
..
..
..
..
..
•
•
..
....
...
4.1.6 Advanced Technologies
4.1.6.1 Fuel Cell
Fuel cells make efficient use of fuel supplies in both central and
dispersed plant applications. However, the technology has not yet been
commercially demonstrated, nor is it expected to be before 1985.
Additionally, fuels cells are not expected to be economically competitive
with more convential energy supply technologies prior to 1990.
4.1.6.2 Magnetohydrodynamics
This technology is a means of producing electricity
electrically conductive gases through a magnetic
hydrodynamics is still in the early development stages
ready for commercial power generation in the near term.
4. 1.6. 3 Wave Energy Convers ion Sys terns
by expanding hot,
field. Magneto-
and will not be
Utilizing the energy in the traveling force or rise and fall in waves has
not been demonstrated as technically feasible.
4.1.6.4 Ocean Current Energy
Ocean current conversion systems use the momentum of ocean currents to
generate electricity. The development of this technology is in the early
stages of feasibility assessment.
4.1.6.5 Salinity Gradient Energy Conversion
Salinity gradients at the interface of an ocean and a fresh water river are
a potential source of energy. Preliminary results of ongoing studies
indicate that utilizing this energy source, which is presently in the early
stages of development, would not be cost competitive with other energy
supply alternatives.
4-7
4.1.6.6 Ocean Thermal Energy Conversion (OTEC) ....
Thermal differences in ocean waters can evaporate and condense binary cycle •
fluids for driving turbine-generators. Ocean thermal differences must be
at least 36 0 F before this technology becomes feasible, and the ocean
thermal differences off the coast of Alaska are insufficient to support an
OTEC system.
4.2 SELECTED ENERGY TECHNOLOGIES
Nine energy resources were identified as viable candidates for further
study in the Bristol Bay Regional Power Plan. Of these nine alternatives, -
four resources are supplementary; that is, they can only be used to
supplement other means of providing the Bristol Bay region total energy ..
requirements. The selected supplementary resources are (1) energy
conservation, (2) waste heat recovery, (3) wind energy, and (4) organic
Rankine cycle. The remaining five viable technologies are primary; that
is, they can be used individually or in combination to supply the full
power requirements of the Bristol Bay region. The selected primary
resources are (1) diesel generation; (2) coal-, oil-, and natural gas-fired
steam electric; (3) coal gasification;
hydroelectric power.
(4) combined cycle; and (5)
4.3 ASSESSMENT OF SELECTED ENERGY TECHNOLOGIES
A presentation of each of the nine energy technologies which were
determined (as discussed in Appendix B)
use in the Bristol Bay region follows.
4.3.1 Supplementary Resources
4.3.1.1 Energy Conservation
potentially viable candidates for
Energy conservation, as explained in Appendix A.5, should be encouraged
throughout the Bristol Bay region. Consumers of electricity and (space
heating) fuel oil are more apt to adopt measures with short-range economic
4-8
..
•
..
..
.. ..
..
...
...
....
...
benefits, such as turning. dm..rn the thermostat to decrease space heating
energy consumption, than activities with long-range benefits. Additional
energy conservation measures become more desirable as fossil fuel prices
continue to rise. In the Bristol Bay region, the relatively high energy
costS have provided consumers a strong incentive to pursue effective
conservation measures. Energy conservation should be encouraged, and
further efforts to promote structure weatherization or equipment
efficiencies should be promoted in the area. Energy conservation is one
form of electrical system load management, which is discussed in more
detail in Appendix A.lO.
4.3.1.2 Waste Heat Recovery
Waste heat recovery encompasses a number of methods to more efficiently
produce electricity and steam, hot water, or hot air simultaneously from a
given fuel source. The relatively low temperature steam, hot water, or hot
air produced as a by-product of electricity generation is usually suitable
for space heating or industrial process use. However, waste heat recovery
is only justif:"ed when the steam, hot water, or hot air recovered can
economically displace existing process and space heating resources. The
most promising source of waste heat in the Bristol Bay region is that
rejected by existing diesel generator facilities. Diesel engine waste heat
recovery is explained in detail in Appendix A.4.
4.3.1.3 Wind Energy
Wind energy is a renewable resource which is potentially suitable for use
in the Bristol Bay region. Storage equipment for wind-generated
electricity is too expensive for present consideration, making wind energy
a supplementary resource only. Thus, wind is considered a topping system
which can supply electricity directly to the power grid when the wind is
blowing within the proper power generating velocity range. Wind energy is
discussed in more detail in Appendices A.6, B, and D.
4-9
4.3.1.4 Organic Rankine Cycle
Organic Rankine cycle (ORC) units provide a unique method of generating
electricity from relatively low temperature sources such as diesel
generator waste heat. As mentioned in Section 4.3.1.2, the most promising
source of waste heat in the Bristol Bay region is that of the existing
diesel generators. However, ORC systems cannot effectively use the diesel
jacket water waste heat, as the temperature is too low; it is the exhaust
system waste heat which must be used. The diesel engine exhaust waste heat
is suitable for energy generation with ORC units, but care must be taken
with this arrangement to ensure that condensate is not formed in the
exhaust system. Due to the Alaska climate, condensa~ion is a common
problem in diesel engine exhaust heat recovery systems, creating additional
maintenance for both the recovery system and diesel engine. ORC uni~s are
discussed in more detail in Appendices A.9 and B.
4.3.2 Primary Resources
4.3.2.1 Diesel Generation
Diesel generators are currently used
electrical power for the Bristol Bay
to produce the majority of the
region. This method of electrical
-
...
...
..
.... ..
..
generation is ideally suited for use in remote areas without transmission -
line interconnection. Diesel generators are relatively efficient, easily
installed, easily operated, and simple to main~ain. The major disadvantage
of the diesel units is their use of expensive diesel fuel. A goal of the
United States and the State of Alaska is to reduce dependence upon
petroleum fuels such as fuel oil, a goal which obviously cannot be realized
with the continued reliance upon diesel generation in Alaska. However, if
economics favor the continued use of fuel oil in the Bristol Bay region,
the most practical method of using fuel oil to generate electricity would
be the diesel generator. The use of residual or heavy oil as an
alternative diesel fuel is discussed in Appendix A.3.2.
Further investigation and optimization of diesel generation in the Bristol
Bay region is assured in Phase II of this study, since diesel generation is
4-10
..
"".
..
•
..
, ..
-~
the base case, BP-l, against which the other alternatives are being
compared.
4.3.2.2 Coal-, Oil-, and Natural Gas-Fired Steam Electric Generation
Of the three fuels considered for direct combustion in the boiler of a
steam turbine plant--coal, oil, and natural gas--the most practical for
Bristol Bay region use is coal. Fuel oil can be more efficiently converted
to electrical energy in either a diesel generator or combined cycle unit.
Crude oil from the Alaska pipeline may be purchased at Valdez for barging
to the Bristol Bay region; however, the crude oil cost is almost twice that
of coal (per Btu). The use of residual or heavy oil as an alternative fuel
for steam electric generation is discussed in Appendix A.B.2.l.
Both liquefied natural gas and propane may be purchased outside the region
(liquefied natural gas from the Kenai Peninsula, and propane and liquified
propane from Prince Rupert, British Columbia) and barged in, but the costs
per Btu exceed that of fuel oil. Oil and natural gas exploration is in
progress in the Bristol Bay region. There have not been any discoveries
yet. Even the most optimistic projections do not predict development of
usable resources until ten years after discovery.
Coal is the lowest cost of the fossil fuels, although a coal-fired steam
electric facility costs more to construct, operate, and maintain. Coal
resources have been identified at the Usibelli mine near Healy, Alaska and
at two separate Canadian locations. The coal would still have to be barged
into the Bristol Bay region for use in the steam electric facility. The
best steam electric facility to be considered for the region is coal-fired:
the fuel is the lowest cost fossil fuel, the technology is well developed,
conventional coal-fired steam turbine plants are currently in successful
operation in Alaska, and the units have been proven to be reliable.
Coal-fired steam electric plants are most economical when approached on a
central plant basis. Considering this and the need for trained operating
and maintenance personnel, the optimum Bristol Bay regional site for such a
plant would be near either Naknek/South Naknek or Dillingham.
4-11
4.3.2.3 Coal Gas ification
As mentioned earlier, the fuel produced by a coal gasification facility can
be used in a variety of electrical power generation combinations. The most
efficient use of this fuel would be made with the combined cycle power ... "
plant. Thus, in this study, coal gasification for the purposes of
generating electricity will be used in conjunction with a combined cycle
generating
have been
unit. Both coal gasification and combined cycle technologies
commercially developed on an individual basis for years.
However, the combination of the two technologies in the size required to
meet the Br istol Bay region's needs has not been attempted before. This
introduces an element of risk into the eventual use of the integrated coal
gasification combined cycle (ICGCC) in the Bristol Bay region, ~lthough for
the purpose of economic evaluation, the ICGCC represents the most efficient
use of the gasified coal fuel to generate electricity. In addition, the
coal gasification facility would retain all of the coal barging, handling,
and storage requirements associated with a coal-fired steam turbine plant.
4.3.2.4 Combined Cycle
At full generating capacity, the combined cycle unit is the most efficient
of the fossil fuel generating alternatives. It will be evaluated using
both fuel oil and fuel from a coal gasification unit. In this section,
only diesel fuel will be considered as the combustion agent in the
combustion turbine or prime mover of the combined cycle assemblage. At
partial loads, the thermal efficiency of the combined cycle unit drops
rapidly; thermal inefficiency at reduced loads coupled with the combustion
of expensive fuel oil could make the combined cycle unit unattractive.
4.3.2.5 Hydroelectric Power
Hydroelectric power would provide a very attractive energy source for the
Bristol Bay region. Being a renewable resource, it would have none of the
problems associated with fuel handling or the environmental impacts
associated with fuel burning. However, the siting of a hydroelectric
facility must take into consideration one of the Bristol Bay region's most
important resources, anadromous fish.
4-12
...
.,..
....
II"
..
• ...
.. ..
·'
-
5. FIELD INVESTIGATIONS
..
..
....
.....
5. FIELD INVESTIGATIONS AND DATA COLLECTION
The objective of the field investigation and data collection program is to
collect and compile technical, environmental, and sociocultural data
necessary to assess project feasibility, and to meet any licensing or
permitting requirements of federal, state, and local regulatory agencies,
including the Federal Energy Regulatory Commission (FERC).
Phase I of the Bristol Bay Regional Power Plan Detailed Feasibility
Analysis accomplished this objective with respect to data required to
compare numerous alternatives. In addition, a much larger data base was
collected for the Tazimina and Newhalen Rivers hydroelectric concepts as an
initial step in determining their feasibility. Additional detailed data
would be required during Phase II to fully satisfy licensing requirements
for either Newhalen and Tazimina if either site is selected for further
evaluation; however, if an alternative hydroelectric site is proposed, the
type of data collected at these
repeated at the new proposed
feasibility.
sites during Phase I would have to be
site in Phase II to fully assess its
The field investigation and data collection program was divided into four
areas:
• Geotechnical
• Hydrologic
• Environmental
• Sociocultural
The work accomplished in these areas during Phase I is summarized in the
following subsections, with detailed back-up information found in
Appendices E, F, G, H, and I, respectively. Appendix G contains both
environmental and sociocultural data collection and analysis.
5. 1 GEOTECHNICAL
5.1.1 Introduction
This section includes a brief description of the regional geology of the
5-1
Bristol Bay region and descriptions of geologic studies, their results, and
geotechnical considerations for potential hydroelectric sites. The data
presented includes information available from the literature as well as
that derived from field studies.
5.1.2 Regional Geologic Setting
The Bristol Bay Regional Power Plan study area encompasses a lowland basin
drained by the Nushagak, Kvichak, Naknek, and Egegik Rivers, and portions
of the surrounding mountains. The basin is bounded on the west by the Wood
River Mountains, on the north by the Nushagak Hills, and on the east by the
Aleutian Range.
The bedrock of the mountains on the west, north, and northeast is primarily
sedimentary rocks with interbedded volcanic rocks, occasionally intruded by
• ...
• ..
• ...
• ., ..
• ..
• -.. ...
igneous rocks of the granitic type. The sedimentary rocks are typically ..
greywackes, siltstones, and shales with occasional minor limestone. Local,
low-grade metamorphism is present, usually associated with the intrusive
(granitic) rocks. The eastern ranges are dominated by volcanic rocks and
contain volcanos which are currently active. Soils are sporadic and are
almost wholly glacial in origin, typically moraines and outwash valley
fill, with recently formed localized organic soils in bogs and muskeg. A
localized basalt flow or flows outcrops immediately north and south of
I liamna Lake.
Sparse rock outcrops indicate that the basin is underlain primarily by
sedimentary rocks similar to, and probably contiguous with, those of the
mountains to the west and north. Unconsolidated soils of the basin are
nearly all of glacial, glaciofluvial, or alluvial origin. Tills and
outwash sands and gravels predominate, with some recent alluvium along
streams. Much of the alluvium is reworked material of glacial origin.
Clays and silts of the Bristol Bay tidal regime occur along the shores of
the bay, while inland, localized deposits of silt and organic soils are
present in bogs and muskeg. Permafrost occurs sporadically in all areas.
5-2
• ..
•
• ..
..
.. .. .. ---
•
Only major structural trends are well known in the area, strongly dominated
by southwest/northeast orientations imposed by the subduction zone between
the Pacific oceanic plate and the North American continental plate. The
boundary between plates is essentially defined by the Aleutian Trench.
Major features, in order from the southeast to the northwest, include:
• The Aleutian volcanic chain and the Bruin Bay Fault, a high-angle
reverse fault -northwest side relative upward motion
• The Castle Mountain Fault (locally the Lake Clark Fault), a high-angle,
strike slip fault -right lateral motion
• The Mulchatna Fault -relative movement is not defined
• The Togiak-Tiukchik Fault, a high-angle, strike slip fault-right
lateral motion
These structures are all part of a major,
trends eastward through Anchorage and the
southward along the Alaskan coast.
arcuate, tectonic belt which
Mt. McKinley area and on
Major glacial activity occurred throughout the area during Pleistocene time
(1,800,000 to 10,000 years ago). Nearly all of the present landforms,
volcanos excepted, and unconsolidated (soil) materials are a direct result
of that activity. In a sense, the Pleistocene has not ended in the Wood
River Mountains and on the volcanos of the Aleutian Range, where active
glaciers persist.
The area is seismically active, lying within the great zone of tectonic
activity produced by the interaction of the Pacific and North American
crustal plates. Although there is no evidence of post-Pleistocene
movements on any of the major faults, these faults are either extensions or
branches of faults considered to be active and which have generated
earthquakes in the past. Most of the seismic activity in the area is
associated with the Benioff Zone and the Aleutian Range volcanos. The
5-3
Benioff Zone is the region of differential movement between the
downward-plunging Pacific crustal plate and the overriding North American
crustal plate. The earthquakes produced by this zone usually occur at
greater depths than those occurring on faults known by their surface
traces. Volcanos rarely produce major seismic events, except very locally,
since most of their energy is vented to the surface.
5.1.3 Summary of Geotechnical Field Studies, 1981 -Tazimina Site
The Tazimina hydroelectric site area is located along the Tazimina River
from the outlet of Lower Tazimina Lake to about 1.9 miles downstream of
Tazimina Falls. As presently envisioned, most of the proposed
hydroelectric project facilities would be included in portions of Sections
8, 17, 18, and 19, R31W, T35, and Sections 24 and 25, R32W, T35 (Seward
Meridan) . Details of all field and laboratory studies are included in
Appendix E.
Geologic mapping was conducted along the Tazimina River valley from the
vicinity of the outlet of Lower Tazimina Lake to about 9 miles downstream.
Data concerning bedrock and surficial stratigraphy and structure were
obtained from this work. The results are shown in Plate 2 of Appendix E.
..
• ..
• ..
",
.' ..
•
•
• ..
•
•
•
Sixteen seismic refraction profiles at nine separate locations were run in •
the Tazimina valley, primarily to ascertain the depths to bedrock at _
various possible locations for project structures. The locations of these
lines were:
•
•
•
The outlet of Lower Tazimina Lake (Line Nos. 1, and 2, and 10)
The possible regulating dam site at river mile 12.9 (Line Nos. 11 and
12)
The "Roadhouse" dam site near the USGS gaging station (Line Nos. 3 and
4)
5-4
JIll ..
--
-
• The "Forebay" dam site (Line Nos. 5 and 6)
• The "Lower" dam site (Line Nos. 7 and 8)
• A possible powerhouse location on the left bank of the river downstream
of the canyon below Tazimina Falls (Line No.9)
• At several locations along the proposed, left bank penstock route (Line
Nos. 13, 14, 15, and 16).
These locations are shown in Plate 1 of Appendix E. Velocity profiles are
included in Appendix E as Figures 3 through 8.
Four borings were taken to obtain continuous profiles of the soil and rock
materials and to obtain samples for laboratory testing. Water pressure
tests were also conducted to obtain data pertaining to the permeability of
the soil and bedrock. In addition, the borings provide data pertinent to
the strength and bearing capacity of these materials. Borings were taken
at:
• The left bank of the outlet of Lower Tazimina Lake (Hole No. B-1)
• The right bank of the river at the "Roadhouse" site (Hole No. B-4)
• The right bank of the river at the "Forebay" site (Hole No. B-2)
• The right bank of the river at the "Lower" site (Hole No. B-3)
The locations of the borings are shown in Plate 1 of Appendix E and the
logs are also included in Appendix E, Figure 2.
Hand-dug test pits were done to obtain bulk samples for laboratory testing
of soil materials. These samples contain larger amounts of material than
those obtained from borings and thus provide a more statistically
representative sampling of the materials. The locations of these test pits
5-5
are shown on Plate 1 of Appendix E and the laboratory test results are also
included in Appendix E.
The various field and laboratory studies are interrelated and provide
..
.,
-
internal cross-checks. \,.
5.1.4 Summary of Geologic Conditions -Tazimina Site
This summary benefits from reconnaissance field investigations which have
been done at the site. These include area geologic mapping, sixteen
seismic refraction lines, four borings, and nine hand-dug test pits. It
also incorporates data from literature research and field studies by
others. A detailed description of these investigations and the results and
conclusions is contained in Appendix E.
-
.. .,
.. -
The bedrock at the site area is almost wholly volcanic in origin. Welded ..
tuffs predominate, varying in their degree of soundness from fair to very
good. Andesites occur, becoming more common upstream of the falls of the
Tazimina River. Basalt flows of limited extent and small basalt dikes are
present. Occasional small intrusive bodies occur, usually of acidic
compositions in the granite-quartz diorite range.
Unconsolidated surficial materials along
primarily of glacial outwash, with a few
suggests that outwash materials comprise
surficial deposits. As anticipated, the
pervious.
the Tazimina valley consist
localized tills. Current data
95 percent or more of the
outwash materials are very
The lack of distinct stratification in the volcanic deposits obscures large
structural features, if present. Jointing is pervasive throughout the
bedrock and ranges from very close (2 in, minimum) to moderately close (3
ft, maximum) and is commonly open at and near the surface. Minor folding,
on the scale of tens of feet, was identified. Nine faults or shear zones
were identified in the site area;
structural features. Because of
none of these can be considered major
the lack of distinct strata in the
5-6
..
..
• ..
• ., .. ..
-.,. ..
JIll'
..
..
volcanic. rocks at the site, displacement across the faults could not be
determined. The widths of the fracture/gouge zones range from only inches
up to several feet. There is no evidence to indicate any post-Pleistocene
movement along any of these faults. There are suggestions that the
Tazimina River valley may be, in part, a fault line valley; however, no
conclusive evidence was encountered during this investigation.
The bedrock surface generally rises fairly abruptly on the southeast
(Roadhouse Mountain) side of the Tazimina valley, approximately paralleling
the existing topography, and s lopes downward to the northwest, away from
the river. On the northwest side of the Tazimina valley and southwest of
approximately Section 8, the land rises in rounded hills. These hills are
composed of glacial outwash materials. Northeast of approximately Section
8, the hills and low mountains bordering the Tazimina valley consist of
bedrock, thinly and discontinuously mantled by soil. Glacial outwash
materials occur in the lower portions of the valley in this area.
The Tazimina site is about 9 miles southeast of the Castle Mountain fault
at its closest approach. The fault is not known to be active. The lack of
historically active faults in the immediate site vicinity precludes
assigning a design earthquake to any specific structural feature. In
addition, the historic record is too brief to conduct a probability
(recurrence) analysis. Consequently, three hypothetical earthquakes based
on events in the overall region were considered. An on-site, shallow event
of a magnitude known to occur in the area produced the peak acceleration.
For the 4.5 to 5.0 magnitude considered, horizontal bedrock accelerations
in the range of 0.2 to O. 3g might be expected. Volcanic hazards are
considered to be nil.
5.1.5 Summary of Geotechnical Considerations -Tazimina Site
Detailed descriptions of possible locations for project structures are
included in Appendix E.
5-7
5.1.5.1 Lower Tazimina Lake Outlet Dam Site
Both seismic refraction surveying and boring results indicate maximum
depths of 300-400 ft below ground surface to the top of rock along this
axis. The overburden is highly pervious glacial outwash sand and gravel.
In order to provide an effective storage dam at this location, an
impervious cutoff, through the outwash materials, would have to be carried
to bedrock. This could be carried to bedrock at both abutments, but
because of the width of the Tazimina valley at this point, it would require
a structure estimated to be about 1.2 miles in length. Accordingly, this
location is not recommended for further consideration.
5.1.5.2 Regulating Dam Site (Mile 12.9 Site)
This site is located about four miles downstream of the outlet of Lower
Tazimina Lake (River Mile 12.9) and appears to offer the best prospects for
a regulating dam site. Bedrock outcrops in both abutment areas and seismic
refraction surveying has defined a continuous bedrock surface beneath the
valley. Overburden is up to 170 ft deep and consists of pervious outwash
sands and gravels, requiring some type of positive cutoff scheme to ensure
the stability of a dam and to prevent excessive seepage losses. A spillway
in rock can probably be located in either abutment.
5.1.5.3 Roadhouse Dam Site
Bedrock is present at or near the surface in the left abutment of this
site. However, the bedrock surface slopes downward in the right abutment,
away from any potential reservoir area, and is overlain by pervious outwash
materials. Till is present at the site, and at one time provided hope for
an impervious layer to which a dam cutoff could be carried. Additional
geologic mapping, seismic refraction surveying, and results of a test
boring indicated that the till stratum was thin and discontinuous and of no
significance as an impervious barrier 0 Soils in the right abutment are
very permeable. It would be difficult or impossible to define the
magnitude of seepage loss of a regulating dam and reservoir at this
5-8
• .. -•
• ..
• -.. -.,
• .. ...
•
.. .. ..
•
• • .. -• ..
•
.... -
• .. ..
location. However, it can be concluded on the basis of the available data
that seepage losses would be very large.
5.1.5.4 Forebay Dam Site
Bedrock outcrops to about 20 ft above the Tazimina River in both abutments
at this location. Although the bedrock surface rises in the left abutment,
seismic refraction surveying and results of a test boring indicate that it
is level or slightly downsloping in and beyond the right abutment area.
Overburden is typically pervious outwash sands and gravels. This site
could readily be developed to accommodate a dam to the height of the rock
outcrop visible in the immediate river channel. Higher dams would be faced
with the problem of an undefinable amount of seepage through the right
abutment and reservoir right bank. A spillway in rock in the left abutment
or an overflow spillway into the existing riverbed would be possible.
5.1.5.5 Lower Dam Site
Seismic refraction surveying and results of a test boring show that the
situation at this location is essentially the same as that at the Forebay
site described above.
5.1.5.6 Penstock Alignment
No significant difficulties due to geologic conditions are anticipated
along the penstock alignment, with the possible exception of slope
stability if the penstock is required to traverse the steeper portions of
the canyon below Tazimina Falls.
5.1.5.7 Powerhouse Location(s)
Since the location of a powerhouse is now considered to be restricted by
environmental considerations to the gorge below Tazimina Falls, any
location chosen will encounter similar conditions. The Tazimina River is
an actively downcutting stream; the walls of the gorge are not standing in
5-9
a stable configuration. Slope protection and stabilization will be
required along any road cuts and on the slopes above the powerhouse
location. This may involve rock bolting, wire mesh, and scaling.
Foundations should be in rock and therefore good. Consideration should be
given to an underground or semi-underground location.
geotechnical consideration, working space in the
limited.
5.1.5.8 Construction Materials
While not strictly a
gorge will be quite
Sand and gravel are readily available anywhere along the Tazimina valley.
The material has been naturally washed and is reasonably clean in situ.
Limited processing should be required, primarily screening and blending.
Potential rock quarry locations occur within 1/2 to 2 miles of any of the
possible sites for project facilities. The suite of andesitic rocks appear
to be the most likely source for larger-dimension stone such as riprap.
Fortuitously, outcrops of this type occur adjacent (1/2 mile) to all of the
damsites under consideration. However, since close jointing is common in
all rock in the area, an actual quarry location for this type material
would be selected based on the results of a detailed joint survey. Since
the tuffs vary widely in soundness over short distances, it is less likely
that an efficient, large volume quarry operation could be developed in
these rocks. The quantities of other rock types present are too small to
provide viable quarry locations.
Tills are present in large amounts in the Lake Clark-Newhalen River valley,
with the deposits beginning about 1 1/2 to 2 miles downstream of Tazimina
Falls. These represent a probable source of impervious fill materials.
Field investigations also indicate till deposits in the Tazimina valley
near the Bid Bend area, downstream of the Roadhouse damsite. The areal
extent of these deposits is not presently known; definition of available
quantities will require additional exploration.
5-10
WI ..
.,.
WI
" ..
•
•
--
...'
-
•
.. -
...
".
5.1.5.9 Seismic and Volcanic Considerations
The location of the site in an area of known seismic activity dictates that
seismic loading be considered in the design of structures. Peak bedrock
accelerations in the range of 0.2 to 0.3 g (horizontal) have been suggested
for the site design earthquake. In addition, the granular nature of
glacial outwash deposits render them possibly susceptible to liquefaction
during seismic loading. This will have to be considered for any structures
founded on outwash materials. There do not appear to be serious potential
rockfall or landslide problems along the walls of the Tazimina valley above
Tazimina Falls or below the outlet of Lower Tazimina Lake. Volcanic
effects at the site are anticipated to be restricted to light ash falls.
5.1.6 Summary of Geologic Conditions -Kukaklek Sites
The Kukaklek hydroelectric site area is included in a corridor trending
northwest between the north-northwest shore of Kukaklek Lake and Iliamna
Lake. The terminal points of the corridor are at about 155 0 30'W, 59 0 12'N
and 155 0 35'W, 59 0 18'N.
Field reconnaissance at these sites consisted of several overflights by
fixed-wing aircraft and spot ground visits utilizing a helicopter. The
area of the sites is completely covered by glacial tills, with occasional
outwash deposits of sand and gravel. Al though no rock outcrops in the
immediate area of the sites, scattered exposures in the near vicinity
indicate that bedrock is primarily tuff and assorted volcanic (pyroclastic)
rubble, including agglomerate. The depth to bedrock through the glacial
overburden materials is not known, but is probably fairly variable.
The Kukaklek sites are relatively removed from known faults. The closest
approach of a major fault is that of the Bruin Bay fault, about 40 miles to
the southeast. Preliminary attenuation estimates indicate that a Magnitude
8 event with an epicenter 40 miles from the site would produce Modified
Mercalli Intensity VIII effects at the site. Historically recorded events
in the region, not known to be associated with any specific geologic
5-11
structure, could occur at the site and would produce similar effects. This ..
estimate should be considered only as a very general guideline; it does,
however, indicate the necessity of incorporating seismic loading
considerations into designs and considering liquefaction potential when
founding on granular materials.
Sand and gravel, from glacial outwash deposits, and material for impervious
fills, from glacial till, should be readily available in the immediate
area. Sources of sound rock for riprap and other uses requiring large
dimension stone may not be available in the immediate area of the sites.
The most promising of sources are outcrops of quartz diorite at the east
end of Kukaklek Lake.
No significantly adverse geotechnical conditions are presently identified
at the Kukaklek Site.
5.1.7 Summary of Geotechnical Field Studies, 1982 -Newha1en Site
The Newhalen hydroelectric site area includes the immediate course of
Newhalen River from about 2 miles upstream of its outlet into Iliamna Lake
to about 7 miles (along the river) upstream. Preliminary layouts indicate
that most of the possible project facilities would lie in portion of
Sections 6,7, 17, 18, and 20, R33W, T5S (Seward Meridan).
The Newha1en site reconnaissance included eight borings, seven electrical
resistivity profiles, installation of four observation wells, laboratory
testing of selected soil samples from borings, and limited surface geologic
observations. Details of all field and laboratory studies are included in
Appendix F. Also included are data derived from research of available
literature.
The seven electrical resistivity profiles (vertical soundings) were run
primarily as a rapid, inexpensive means to determine depth to top of rock
and to the water table. The locations are all on or near the proposed
5-12
..
.,
•
• -..
•
• ..
• ..
• ..
•
•
• .,
-
•
..
..
canal alignment and at approximately the following stationing:
• VES-l Sta. 46 + 00 (also boring B-3)
• VES-2 Sta. 90 + 00 (also boring B-2)
• VES-3 Sta. 129 + 00 (also boring B-1)
• VES-7 Sta. 26 + 00 (about 200 ft SW of canal)
• VES-8 Sta. 67 + 00
• VES-9 Sta. 109 + 50
• VES-10 Sta. 141 + 00
Resistivity profiles at borings served as a check of the boring and as
calibration for the resistivity method.
Eight borings were made to establish profiles of soil materials, recover
soil samples for laboratory testing, and to determine the depth to the
bedrock surface and the bedrock type. The boring locations are as follows:
• B-1
• B-2
• B-3
• B-4
• B-5
• B-6
• B-7
• B-8
Sta. 139 + 00
Sta. 90 + 00
Sta. 46 + 00
Sta. -2 + 50 (about 200 ft E of intake)
Sta. 149 + 00 (about 300 ft SW of spillway)
Sta. 103 + 00 (about 150 ft NE of canal)
Sta. 98 + 00
(About 1250 ft NE of B-1, in a gully, positioned for lower
collar elevation in an attempt to penetrate bedrock with a
drill of limited depth capability. This was successful.)
All electrical resistivity survey and boring locations are shown on Plate 1
of Appendix F.
Observation wells for monitoring ground water elevations were installed in
Borings B-5, 6, 7, and 8. These consist of slotted PVC screen with PVC
riser pipe.
5-13
Geologic reconnaissance consisted primarily of observations of the location
and volume of springs and seeps emerging from the left (NE) bank of the
Newhalen River. Additional reconnaissance planned for near the close of
the field work was curtailed by heavy snowfall.
Laboratory testing of selected soil samples
classification and mechanical (sieve) analysis.
results and boring logs are shown in Appendix F.
5.1.8 Summary of Geologic Conditions -Newhalen Site
consisted of visual
The laboratory test
..
..
• .f
This summary benefits from the reconnaissance field investigations done at •
the site and described above in Section 5.1.7. A detailed description of l1li;
the site geologic conditions is contained in Appendix F.
In the general area of the site, bedrock outcrops in the bed of the
Newhalen River and discontinuously in the walls of the shallow gorge which
it has cut for about 13 miles upstream from its outlet into Iliamna Lake.
The rock is primarily basalt and andesite, with tuff and assorted volcanic
rubble, including breccias and agglomerates. Localized orientation of
(volcanic) bedding is about N80 0 E, dipping 10 0 to 25 0 SE. Overburden is
primarily glacial tills with lesser amounts of glacial outwash sand and
gravel.
At the site, the bedrock surface slopes from an elevation of about 180 at
t-he intake to about 90-110 at the beginning of the spillway (Sta. 140 +
00), a gradient of about 25 -35 ft/mile. Intermediate borings and
resistivity soundings indicate that this slope is fairly uniform over that
distance. From the beginning of the spillway, the rock surface drops more
• ..
• ..
•
..
.,
•
• -
•
steeply (115-190 ft/mile) to near river level, possibly in stairstep ..
fashion. North of about Sta. 98 + 00, bedrock was found to be andesite ..
volcanics with limited surface weathering. South of about Sta. 130 + 00, ..
the bedrock is a volcanic breccia with indications of more severely and
deeply weathered zones. Jointing was generally very closely to closely
5-14
., ..
spaced in both rock types with some indications of becoming more widely
spaced with depth, an additional sign of increased rock integrity at fairly
shallow depths below the bedrock surface.
All soils appear to be of glacial or proglacial origin. Interbedded clean
to slightly silt outwash sands and gravels, cobble and boulder till, and
silt were encountered on the site. Densities of different strata varied
widely, probably indicative of varying degrees of compaction induced by
repeated glacial advances over the area. Along most of the canal
alignment, the ground surface varies from about El. 180 to El. 200. At
about Sta. 140 + 00 (beginning of the spillway) there is a distinct scarp
from about El. 180 to El. 150, a product of earlier chann~l cutting by the
Newhalen River. From about Sta. 141 + 00 to the river, the ground surface
slopes fairly uniformly to the river.
The general configuration of the groundwater table is indicated to be
similar to that of the ground surface - a gentle slope downward from the
intake to the scarp at Sta. 140 + 00, with a more abrupt gradient from the
scarp to the top of bedrock adjacent to the river. The typical depth to
the water table from Sta. 0 + 00 to Sta. 140 + 00 is 20-30 ft. The
presence of till strata, the locations of some springs, and indications
from several borings suggest that perched water tables may exist throughout
the area. All observed water tables are well above the river level; this
is indicative of a distant water source and probable large groundwater
reservoir. High flow rates in soils are therefore possible.
Only shallow (up to 4 ft) frozen soil was encountered in any of the
borings. This and the absence of surficial indicators (such as polyagonal
ground) suggest that there is no permafrost in the immediate site area.
The closest approach to the site of a major fault (Castle Mountain fault)
is about 15 miles to the northwest. Although the fault is not known to be
active, the effects of a seismic event with an epicenter at this location
would show little, if any, attenuation at the site. If the fault is
considered to be capable of at least a Magnitude 6 event, this would
5-15
correspond to Modified Mercalli Intensity VIII effects at the site. This
is only a general guideline, but indicates the necessity for seismic design
and foundation liquefaction (granular soils) considerations.
5.1.9 Summary of Geotechnical Considerations -Newhalen Site
The depth to bedrock is a major controlling factor in the design of the
canal and spillway. From Sta. 0 + 00 to about Sta. 60 + 00, the invert of
the canal is in or on bedrock. From Sta. 0 + 00 to about Sta. 30 + 00, the
lower portion of a canal will be in bedrock.
from 30 ft at Sta 0 + 00 to 10 ft at 30 + 00.
Rock excavation depths range
Those portions of the canal
in rock would not require lining and side slopes could be near-vertical.
In the area of the beginning of the spillway (about Sta. 140 + 00),
alternative interpretations of data projected from boring B-8 and from
resistivity sounding VES-10 indicate a possible buried channel cut into
bedrock. This low point could be as much as 30 ft deeper than top of rock
indicated by projection between borings B-5 and B-7. Borings have also
indicated zones of increased weathering, possibly requiring additional
excavation to reach sound rock.
The groundwater table appears to be above
except possibly immediately at the intake.
are clean sands and gravels with probable
the canal invert elevation,
Since many of the soil strata
significant permeability, the
possibility exists for significant rates of water flow into excavations.
The possibility of perched and/or confined aquifers complicates the
situation. No tests were performed which would allow quantifying of flow
rates at this time. Excavation schemes in soil materials should include
provisions for groundwater control.
Excavation of soil materials is not anticipated to pose
other than that associated with control of groundwater
any difficulty
inflows. Side
slopes will have to be designed to provide stability during construction as
well as during long-term use. Canal and spillway side s lopes and inverts
will require lining and drainage schemes for long-term erosion protection
5-16
..
.. ..
..
.. ..
• ..
• ..
• •
• ...
• -
•
•
•
.. .. .. .. .. -
and stability. Rock excavation is anticipated to require blasting. Side
slopes should stand successfully at very high angles except, possibly, in
areas of severe weathering.
The stability of natural slopes, primarily as represented by the older
erosional scarp of the Newhalen River, could be disrupted by flow into the
groundwater regime from seepage out of the canal or spillway. These areas
occur in the vicinity of Sta. 80 + 00 and Sta. 140 + 00; the bluff along
the current river channel at about Sta.
situation. The effects of increased
30 + 00 may represent a similar
groundwater flow could include
increased erosion from springs or mass slope failure. Protection could be
provided by drainage systems, canal realignment to increase seepage paths
to scarps, or a combination of the two.
Glacial till deposits are readily available as sources for compacted and
impervious fill materials. Sand and gravel, probably reasonably clean due
to natural washing, should be fairly common in the immediate vicinity of
the slte. The basalts and andesites exposed along the Newhalen River
should provide essentially on-site sources of riprap and dimension stone
for other uses.
5.1.10 Summary of Geologic Conditions -Kontrashibuna Site
The Kontrashibuna hydroelectric site area is located on the Tanalian River
downstream of Kontrashibuna Lake. As currently envisioned, project
facilities would include a dam at about river mile 3.8 and a tunnel to Lake
Clark. Most proj ect facilities would be included in portions of Sections
2,3, 11, 12, 13, and 14, R29W, TIN (Seward Meridian).
Observations concerning the Kontrashibuna site are based on helicopter
overflights and literature research. To date, no ground visits have been
made.
Bedrock in the area consists of mixed volcanic rocks, primarily tuffs with
andesites and basalts, interbedded with greyacke, shale, and some slate.
5-17
Overburden appears to consist mostly of glacial outwash sand and gravel
with occasional minor till deposits.
The relatively narrow valley, the Tanalian River falls in bedrock
downstream of Kontrashibuna Lake, and the steep gradient of the Tanalian
River all indicate moderely shallow bedrock. Topographic maps and aerial
observation suggest 50 to 100 ft overburden depths. Rock abutments for
possible dam sites are probably not widely separated across the valley.
The Castle Mountain fault passes about 5 miles northwest of the site. A
seismic event on the fault with an epicenter at 5 miles would not be
attenuated at the site. Although the fault is not known to be active, for
illustrative purposes a Magnitude 6 event occuring at the point of closest
approach would result in Modified Mercalli VIII effects at the site. A
regional event of the type not yet associated with known geologic
structures occurring at the site, would produce similar effects. This is
only a guideline figure, but demonstrates the need for seismic design
considerations, including liquefaction of granular soils and evaluations of
avalanche, landslide, and rockfall hazards.
Sands and gravel should be abundant throughout the Tanalian River valley
glacial outwash deposits; the material should be fairly clean due to
natural washing. The amount of till present in the valley is more
problematical, but it is not likely to occur in deposits of sufficient size
to be useful in construction. Extensive till deposits are present on the
northwest shore of Lake Clark, directly across from the mouth of the
Tanalian River (2 1/2 miles) and on the southeast shore, southwest of about
Chi Point (9 miles). It should be possible to develop rock quarries at or
within only several miles of any possible project facility locations. Rock
conditions with respect to tunneling probably range from poor to good.
•
• ...
-.. .,
• ..
... .. ..
•
•
•
•
..
In the absence of detailed field studies, the geotechnical aspects of the •
Kontrashibuna Site appear to be favorable. .'
..
•
5-18
5.1.11 Summary of Geologic Conditions -Chikuminuk Site
The Chikuminuk hydroelectric site area is located along the Allen River
downstream of Chikuminuk Lake. Most project facilities would be included
in an area from about 0.5 mile downstream of the lake out let to about 1.6
miles. This area includes portions of Sections 19, 24, 25, and 30, R55W,
TIN (Seward Meridian).
This summary is based on data
examination of aerial photographs.
obtained from literature research
No site visits have been made to date.
and
Bedrock in the site area is primarily interbedded siltstone and mafic
volcanics, with some sandstone and conglomerate. The sequence is generally
discordant. Overburden has been mapped as till. Examination of aerial
photographs shows the following: a) landforms typical of a series to
receeding terminal moraines, and b) very steep valley walls along the Allen
River. The valley walls are clearly not rock but are standing at angles
generally in excess of that of -the angle of repose of outwash sands and
gravels. This evidence also indicates that the overburden is a till.
Glacial outwash sand and gravel appears to be very limited.
Distinct falls and rapids in the Allen River suggest that the riverbed is
bedrock. The till overburden which forms the inner valley of the Allen
River should provide an adequately sound abutment material and should be
moderately to highly impervious.
The Togiak-Tikchik fault passes about 11 miles west of the site. As an
extension of the Denali fault, this fault could be considered potentially
active. The effects of an earthquake with an epicenter at this location
would show essentially no attenuation at the site. In the absence of
detailed studies, the lower limit of a maximum seismic event is assumed to
be Magnitude 6; this corresponds to Modified Mercalli Intensity VIII at the
site. This is only a rough approximation but illustrates the need for
seismic design considerations.
5-19
Till materials for compacted and impervious fills appear to be in abundant
supply at the site. Glacial outwash deposits, sources of sand and gravel,
are scarce or absent in the vicinity of the site. The nearest probable
source of granular fill and aggregate materials is along the valley of the
Tikchik River, about 11.5 miles east of the site. Probable rock quarry
locations are on the slopes of an unnamed mountain 1 to 2 miles south of
the site.
As a preliminary evaluation, the geotechnical aspects of the Chikuminuk
site can be considered fair to good. The degree of permeability of the
till comprising possible dam abutments would have a major influence on
future evaluations.
5-20
•
••
..
.,
•
•
., ..
• .. ..
-
•
..
References for Section 5.1
1. Beikman, Helen M., Geologic map of Alaska: State of Alaska Dept. of
Natural Resources, Div. of Geo1. and Geophys. Surveys, 1980.
2. Beikman, Helen M., Preliminary geologic map of the southwest quadrant
of Alaska: u.S. Geol. Survey Mis~-Field Studies Map MF611, 1974.
3. Coffman, Jerry
Uni ted States:
101-119, 1973.
L. and VonHake,
National Oceanic
Carl A., Earthquake history of the
and Atmospheric Administration, pp.
4. Detterman, Robert L., and Reed, Bruce L., Stratigraphy, structure, and
economic geology of the Iliamna Quadrangle, Alaska: u.S. Geol. Survey
Bull. 1368-B, 1980.
5. Karlstrom, Thor N.V., et al., Surficial geology of Alaska: u.S. Geol.
Survey Misc. Geol. Inv. Map 1-357, 1964.
6. R. W. Retherford Associates, Reconnaissance study of the Lake Elva and
other hydroelectric power potentials in the Dillingham area prepared
for the Alaska Power Authority, 1980.
7. Seldregg, Lidia S., Alaska regional profile, southwest region:
of Alaska, pp. 37-88, 130-148, (no date).
Univ.
8. Shannon & Wilson, Tazimina River hydroelectric proj~ct, geotechnical
studies, prepared for Stone & Webster Engineering Corporation, 1982.
9. Shannon & Wilson, Preliminary Geotechnical Feasibility Study, Newha1en
River, Canal Diversion Proj ect, prepared for Stone & Webster
Engineering Corporation, 1982.
5-21
.. ..
5.2 HYDROLOGIC •
Hydrologic data available for the Bristol Bay region is limited, consisting •
of few river gaging stations with short periods of record. The evaluation ..
of potential hydroelectric sites in the region requires that estimates be
made of the river flow available for power generation. Where gaging
station data is unavailable, estimates of river flow for the screening of
potential hydroelectric sites were made by interpolating runoff rates from
maps of mean annual runoff obtained from "Water Resources of Alaska" (Ref
1). For more detailed site evaluations included in the power plan
scenarios, the average monthly river flows from the nearest available
-..
• .,
gaging station were adjusted in proportion to drainage area and used to •
estimate power
requirements.
and energy production and estimate water storage
Due to insufficient river flow records upon which to base an estimate of
firm power available, the design flows for hydroelectric concepts were
assumed to be the 80 percent exceedence flows. The design flow was
determined for each site by reviewing the available data for the period of
record and selecting the design flow as that which is exceeded with 80
percent probability, or an average of four years out of five.
The determination of the storage capacity required for the Tazimina and
Chikuminuk project reservoirs was made by using a mass balance of inflows
and outflows for a year with the ultimate 2002 generating demands and
having monthly inflows which correspond to the 80 percent exceedence flow.
The storage capacity required at the Kontrashibuna Lake project was
determined by constructing a mass curve of the five-year period of record
and calculating the storage required to meet the year 2002 demand. Based
upon the premise that the five-year period of record is typical, this
.' .. .. -
• .. ..
• .' • ..
• ..
•
technique also yields a storage capacity which is adequate four years out ..
of five and is consistent with the other sites.
The hydrologic data used in the evaluation of the various Newhalen
hydroelectric concepts was based on 16 years of continuously recorded
streamflow at the USGS gage "Newhalen River near Iliamna". The gage is
5-22
., .. .. -
•
•
located approximately 10 miles upstream from the proposed intake canal of
the regional hydroelectric concept. While the gage is currently
deactivated, the facility still remains in place and is readily amenable
for reactivation. In fact, the Newhalen River gage was temporarily
reactivated by the USGS for use and correlation during the spring smolt and
fry study conducted by Dames & Moore. Flow data used in the developments
of the regional and local Newhalen hydroelectric concepts can be found in
Tables A.2-12 and A.2-14 of Appendix A, respectively.
The hydrologic data used in the evaluation of the Kontrashibuna Lake site
is recorded at the USGS gage "Tanalian River near Port Alsworth". This
gage is located at the potential project location and required no
adjustment. Similarly, the hydrologic data used in evaluating the Newhalen
River site is recorded at USGS gage No. 153000 and was also used without
adjustment. For the Chikuminuk site, the three years of data recorded at
USGS gage No. 153015 at the outlet of Chikuminuk Lake was correlated with
26 years of data available at USGS gage No. 153020 located on the Nuyakuk
River, within the same drainage basin. From the correlated data, an
extended period of hydrologic records at the Chikuminuk site was developed
and the appropriate design flows were selected.
The Kukaklek Lake site has no hydrologic data available and required that
flows be estimated by adjustment of other gaging station records in the
area. Kukaklek Lake is drained by the Alagnak River which is a tributary
of the Kvichak River. The Tanalian and Newhalen Rivers are also part of
the Kvichak River system, although they are separated by many miles and
several major lakes. In order to have an approximation of the Kukak1ek
hydrologic records of the Tanalian, Newhalen, and Lake discharges, the
Kvichak Rivers were compared as shown on Figure 5.2-1 and the average
Kukaklek Lake was estimated by interpolating according annual discharge of
to drainage area. A similar interpolation was used to obtain monthly flows
which were reduced in proportion to the flow-frequency data on the Newhalen
River to obtain the design flows for the Kukaklek Lake project.
Estimates of flows for the Tazimina River projects were prepared by Dames &
Moore hydrologists and are contained in Appendix I. In the summer of 1981,
5-23
the USGS began collecting data on the Tazimina River at gaging station No.
152999. However, since only about a year of data is available at present,
the estimates contained in Appendix I were used for evaluating the Tazimina
River projects. Estimates of probable maximum floods (PMF) for use in
sizing project facilities were based on a study prepared by Dames & Moore
contained in Appendix I. The result is in good agreement with the earlier
estimate prepared by R.W. Retherford Associates (Ref 2).
The average annual flow for the 327 square mile Tazimina River drainage
basin was estimated at 1,031,000 acre-ft by R. W. Retherford Associates in
a previous study (Ref 2). This corresponds to an average annual runoff of
59.1 inches, or an equivalent average annual flow of 1423 cfs. A draft
report prepared by the Arctic Environmental Information and Data Center
(AEIDC) (Ref. 3) estimated the average annual flow from the Tazimina River
to be 820 cfs. This corresponds to an annual runoff of 34.0 inches. The
Dames & Moore flow estimate of 856,000 acre-ft (Appendix I) yields a runoff
of 48.5 inches, or an equivalent average annual flow of 1168 cfs. By
comparing these runoff estimates to the "rough" estimate of 43.5 inches,
obtained by using the curve developed on Figure 5.2-1 for the region, the
Retherford estimate appears quite high and should not be used in evaluating
the hydroelectric potential of Tazimina. The Dames & Moore estimate, while
still higher than the estimate obtained from Figure 5.2-1, is thought to be
more representative of the actual runoff.
The AEIDC runoff estimate appears very low; it is even lower than both the
Newhalen and Kvichak River runoff values. We believe that this is contrary
to known runoff-drainage area relationships. Small watersheds which are
located in the upper portions of a large drainage basin generally exhibit
greater runoff in comparison to the basin runoff as a whole. This
relationship is discussed in detail in Appendix I. The runoff from the
Tazimina River basin, based only on the area relationship given by the
formula in Appendix I, is calculated to be 42.1 inches. This corresponds
to an average annual flow of 1014 cfs. It should be noted that his value
does not reflect an upward adjustment which could apply because the
Tazimina River drainage area lies within a high precipitation regime of the
Newhalen River basin.
5-24
..
•
•
•
•
•
•
.. ..
-
• ..
..
.,
Because of the above, it is believed that the average monthly and annual
flow values developed by the Dames & Moore flow simulation model, are
representative of long term conditions, and should be the preferred values
for use in Tazimina power studies.
It should be noted that the Dames & Moore estimate of Tazimina River flows
is the result of a more thorough investigation than either of the other two
flow estimates mentioned; however, it may require adjustment or revision as
more actual gaging records become available.
All hydrologic data used in this study, aside from river gage records
directly applicable at a site, are to be considered preliminary
approximations. They are suitable for relative evaluation of sites, but
have not been refined sufficiently for use in a detailed investigation of
any hydroelectric site which may be selected.
References for Section 5.2
1. U.S. Geological Survey, Water Resources of Alaska: U.S. Geological
Survey Open File Report, 1971.
2. R. W. Retherford Associates, Reconnaissance Study of the Lake Elva and
Other Hydroelectric Power Potentials in the Dillingham Area, prepared
for the Alaska Power Authority, 1980.
3. Arctic Environmental Information and Data Center, Methodology for
Estimating Preproject Stream Flows in the Tazimina River, Alaska, Draft
Report, January 1982.
5-25
55
Ci)
w
::J:
U
Z -u..
50 u..
0 z
:::> a:
-I
~ :::> z z
~ 45 w
" ~ a: w
> ~
40
o
2_
RAINAGE TAZIMINA D
- / KUKAKLEK DRAINAGE
3_/ " 2,000
1,000
/ NEW
ESTIMATES TAZIMINA RUNOFF
W Retherford 1 .• R ..
Dames & Moore 2 .•
3 .• AEIDC
AR = 0.07367 1IN/YE
HAL EN RIVER KVICHAK
/RIVER
5,000
4,000 (Sa MILES) 3.0~~AINAGE AREA -AL RUNOFF
AVERAGE ANNU FIGURE 5.2-1
5.3 ENVIRONMENTAL
5.3.1 Introduction
A program was conducted to collect pertinent environmental baseline data
for a comparison of alternative plans and the preparation of environmental
documents for use in this feasibility assessment. While general
environmental data were analyzed for the entire Bristol Bay study region,
detailed environmental studies were limited, by necessity, to selected
power alternatives only. Two of the more promising power alternatives
identified were regional hydroelectric power sites on the Newhalen and
Tazimina Rivers. Therefore, the primary emphasis of the environmental
program was directed toward evaluating potential impacts of these
developments and their accompanying power distribution systems.
Environmental data collection for the Bristol Bay Regional Power Plan
Detailed Feasibility Analysis is divided into two phases. Phase I of the
study program accomplished a majority of the field data collection in order
to provide input to the Interim Feasibility Assessment. The remainder of
the environmental field data program, to be conducted in Phase II, will
concentrate on completing the environmental assessment for the
alternative(s) selected for further detailed evaluation.
5.3.2 Water Use and Quality
Present and historic uses of
recreation, and water rights
interviewed by field personnel.
the Tazimina River
were investigated
relating to fisheries,
with local residents
Similar uses were investigated for other
water bodies in the study region, however, without field investigations.
Water quality was analyzed for the Tazimina River basin during the summer
of 1981. Several locations, including the Upper Tazimina Lake out let,
Lower Tazimina Lake inlet, Lower Tazimina Lake outlet, Tazimina River above
the falls, Tazimina River lower section, and Sixmile Lake (Tazimina River
mouth) were investigated. Parameters that were measured in the field
included dissolved oxygen, temperature, pH, conductivity, settleable
5-26
solids, and alkalinity. At least three separate measurements of each
parameter were taken at each location. Laboratory samples were also
collected and analyzed for physical, chemical, nutrient, heavy metal,
pesticide, and herbicide parameters. These were composited from at least
three locations at each sample site. A detailed discussion, including data
and laboratory analysis, of the water quality program conducted in the
Tazimina River basin is found in Appendix G, Section 3.1.3.
Water quality analyses were not performed at any other potential
hydroelectric power site in the region. However, published data were
examined for the entire study region for both surface and groundwater
quality.
5.3.3 Terrestrial Ecology
5.3.3.1 Vegetation
A detailed description of the structure and floristic composition of each
vegetation type, and its distribution within the Tazimina River basin, is
given in Appendix G, Section 4.1.1.1. Vegetation types and general
ecosystem classifications were investigated for the remainder of the study
region using published data only.
5.3.3.2 Birds
Observations of birds in the Tazimina River basin were recorded during the
summer of 1981. However, these were made primarily on an opportunistic
basis in conjunction with other field investigations. Considerable data on
the birds of this region, however, were available from previous studies. A
detailed discussion including a species list is found in Appendix G,
Section 4.1.1.2. For the remainder of the study region, only general
published habitat maps were utilized for analyses of specific sites.
5.3.3.3 Mammals
Mammals of the Tazimina River basin and the Bristol Bay region are largely
representative of interior boreal forest ecosystems. While a total of 15
5-27
• -.. .,
• •
• .'
•
• •
• •
• ..
• ..
• ..
• ..
• .. ..
.. --
species were documented within the Tazimina River basin during the summer
of 1981, an additional 20 species could potentially occur in small numbers,
or at least occasionally inhabit the area. A detailed discussion,
including species lists and habitat maps, is found in Appendix G, Section
4.1.1.3. For the remainder of the study region, a generalized habitat map
was prepared from existing data and used in conjunction with published
reports for the purpose of analyzing potential impacts of various energy
plans.
5 . 3 . 3 . 4 Endangered Species
Al though some rare and unusual plant species have been found in the Lake
Clark area, these plants do not fall under the category of endangered
species. Also, no species proposed for protection under the Endangered
Species Act of 1973 were found to occur in the Tazimina River basin during
the 1981 field investigations.
No sightings of endangered animal species were observed during the 1981
field investigations within the potential zone of influence of the Tazimina
River hydroelectric site.
5.3.4 Aquatic Ecology
Fish species from the Tazimina River basin provide important commercial,
sport, and subsistence value, both on-and off-site, that could be
influenced by the proposed hydroelectric development. During the summer
and early fall of 1981, the following investigations took place in the
Tazimina River basin: 1) sockeye salmon spawning locations and numbers, 2)
resident fish distribution and identification of spawning and rearing
areas, 3) physical parameters affecting sockeye salmon use of the
Tazimina River to lay ground work for future instream flow modeling
studies, 4) physical factors affecting resident fish, and 5) a temperature
monitoring program. A detailed discussion of these investigations is found
in Appendix G, Section 4.1.2.
5-28
During the spring of 1982, two additional field investigations were made in
the Tazimina River. In early April, temperature profiles and ice thickness
..
.,
were measured in the section of river below the falls. An investigation of •
fisheries during the same period suggested that fish are driven out of the
Tazimina River by low winter temperatures. In late May, a fisheries
habitat reconnaissance survey was conducted in the Tazimina River
immediately above the falls. Results indicate that the section of river
300-500 feet above the falls is of very limited fisheries habitat use.
A preliminary evaluation was conducted to determine if an impoundment on
the Tazimina River would affect the downstream thermal regime of the river,
which could possibly affect the incubation rates of the indigenous fish
population. A stratified reservoir model was used to predict the outlet
temperatures from the proposed storage reservoir. The results of this
model allowed a qualitative assessment of potential thermal problems
affecting salmonid egg incubation. Site-specific data was limited;
therefore, only a qualitative assessment was made at the time. As more
information becomes available from ongoing field sampling programs, the
analysis will be refined and a quantitative assessment made.
..
.. -.. -
.. ..
•
• •
A spring field investigation was conducted to define the horizontal and ..
vertical distribution of downstream migrating sockeye salmon smolt and fry
in the vicinity of river mile (RM) 7 on the Newhalen River. Sampling was
accomplished by utilizing modified fyke nets and sonar. However, acoustic
sampling with sonar was limited because of higher than anticipated levels
of surface and bottom reverberation. Net sampling schemes were designed to
detect the vertical and horizontal distribution of sockeye salmon smolt and
fry. Length, weight, and scale information was taken on both smolt and
fry, while mortalities were preserved and kept for otoliths.
Preliminary results of the Newhalen sampling program indicated that
downstream migrating smolt favored the use of the main river channel.
While the sampling program lasted 5-1/2 weeks, from early May to mid-June,
the entire run of smol t was not observed. However, the spring smol t peak
was observed from 19 May through 26 May. Salmon fry were observed to have
5-29
•
.. ..
• .. ..
.. .. .. -.. -..
WI·
peaked between 8 June and 10 June and also to have favored the use of the
mid-channel portion of the river.
Details of this study can be found in Appendix H,
and description of sampling site; description
and include: location
of river and weather
conditions; description of equipment; sampling methods; analysis of data;
and results and recommendations for future studies.
While no detailed field investigations were made in any other river basins
within the study region, a literature search and an interview program did
take place. Information, particularly relevant to commercial and sport
fisheries, was collected for a large portion of the study region for the
purpose of analyzing potential hydroelectric power sites. Aerial
reconnaissance was also conducted at several of the potential sites.
5.3.5 Air Quality
Climatologic data were collected and analyzed for both the Tazimina and
Newhalen River basins, as well as for the entire study region. These data
formed the basis, along with terrain analysis, for assessing potential
impacts on air quality from various alternative energy developments. While
no ambient air quality monitoring stations or data exist in the region, a
review of proposed and existing Mandatory Class I (EPA) Areas was
conducted. The assumption was made that while energy development in the
region is not likely to influence any existing or proposed Class I areas,
the region is considered to have pristine air quality.
5-30
5 .4 SOC IOCUL TURAL
5.4.1 Historic and Archaeological Resources
An archaeological reconnaissance of the Tazimina River basin was conducted
by both aerial and ground survey during the fall of 1981. Several sites on
the lower Tazimina River, above and below the falls, and on Lower Tazimina
Lake were investigated. The results of the survey revealed no cultural
resources of obvious significance; however, the survey method was designed
to detect only relatively large and readily visible cultural resources. A
detailed description of the reconnaissance survey is found in Appendix G,
Section 5.2.
• ., .. ..
• •
•
..
..
..
The Tazimina River basin is rarely mentioned in anthropological and ..
historical literature. From the little information that is available, it
appears that the types of historic and late prehistoric sites likely to be
found in the Tazimina River basin will consist of temporary camp sites used
for fishing, trapping, and as travelers I rest stops. Because of the lack
of archaeological information on the Tazimina River basin, a detailed
discussion of the types of sites that have been found in the broader Lake
..
..
•
Clark-Iliamna Lake region are presented in Appendix G, Section 5.1.2, and •
thought to be representative of the types present in the Tazimina River
basin.
5.4.2 Socioeconomic Considerations
Socioeconomic considerations were evaluated for the entire Bristol Bay
study region. Research was conducted during the late fall and winter of
1981-82, primarily gathered in the form of local interviews with residents
of the region. Attitudes of the residents, with respect to the development
of the Bristol Bay Region Power Plan, were addressed.
.. .. .. .. ..
• .. .. .. ..
An investigation into the demography and population trends of the study ..
region was also made. Factors affecting population, such as commercial
fishing, recreational hunting and fishing, and government installations
5-31
..
..
..
were investigated. These are discussed in detail in Appendix G, Section
6.2.
Because the commercial salmon fishing industry forms the economic base of
the Bristol Bay region, residents in each of the 18 study area communities
expressed concern about the effects of hydroelectric development on the
region's fisheries. The major concerns of the residents in each of the
sub-regions (Iliamna, Kvichak River, Kvichak-Egegik Bay, Nushagak Bay, and
Nushagak River) are discussed in detail in Appendix G, Section 6.3.
Generally, most Bristol Bay region residents who were interviewed did not
favor a regional power plan to meet Bristol Bay region energy needs
(Appendix G, Section 6.4.1). Small-scale hydroelectric systems, village
power generation systems, and sub-regional systems are concepts which were
continually inquired about by local residents. Local preferences for such
power development are apparent because of differences in ethnic background,
political differences, and varying degrees of dependence upon commercial
fishing. Attitudes toward various proposed region energy plans are
discussed in detail in Appendix G, Section 6.4.
5.4.3 Recreational Resources
A literature search of the recreational resources of the Bristol Bay region
was conducted during the summer and early fall of 1981. This was augmented
by aerial reconnaissance, primarily as by-product of other field
investigations. The major emphasis of this effort was on the fishing
resource in the Tazimina/Newhalen River region. Data on hunting, river
floating, and fishing were also collected and evaluated for other potential
energy development areas within the study region.
5.4.4 Aesthetic Resources
Information on landscape, including vegetation and landform, was collected
during the summer and fall of 1981 using published data (maps, atlases,
etc.) and reconnaissance surveys (aerial and terrestrial). Factors
comprising form, line, color, and texture were used in analyzing impacts.
5-32
..
A complete discussion of aesthetic resources is found in Appendix G, ..
Se(:tion 8.
5.4.5 Land Use
A field investigation program was conducted in association with the
socioeconomic data collection described in Section 5.4.2 to identify
potential land uses and associated conflicts related to the proposed
hydroelectric development of the Tazimina River basin as well as to other
selected alternative energy plans.
Because of the high percentage of residents in each of the study region
communities relying on the Bristol Bay commercial salmon fishery for the
majority of their yearly income, and because subsistence fishing has
cultural, nutritional, and economic importance throughout the region, the
majority of the residents interviewed were primarily concerned with the
negative effects the various hydroelectric projects might have on salmon
and other fisheries. Also, because the predominant land use in the study
region is for subsistence, a related concern in some of the more isolated
villages centered around potential conflicts between existing land use
patterns and the possible influx of people and increased access resulting
from energy development. A detailed discussion of land use concerns by
subregion is found in Appendix G, Section 9.2.
Land use was
associated with
attitudes of
also
the
the
transmission networks
investigated with respect to transmission lines
various alternative energy plans. The concerns and
residents related to selected energy plans and
were investigated and are presented in detail by
sub-region in Appendix G, Section 9.3.
5-33
• .. .. ., ..
• .. -.. .. .. .. ..
• ..
• .. ..
• .. .. ..
• ..
• -
•
•
•
•
.....
..
..
.. . '
6. DEVELOPMENT
OF ENERGY PLANS
6 . ENERGY PLANS
6.1 DEVELOPMENT OF ENERGY SCENARIOS
6.1.1 Introduction
The nine energy supply technologies that were found to be attractive for
application in the Bristol Bay region have been considered both
individually and in varying combinations for the development and selection
of energy plan scenarios.
The requirements of the study are to address hypothetical power plan cases
that fall under the framework of the following options:
• A Base Case, which represents the continuation of present practices of
reliance on oil-fired (diesel) generation
• Alternative "A", which consists of the Tazimina River hydroelectric
project as the preferred regional power supply
• Alternative "B", which consists of other energy sources, projects or
facilities, either alone or in varying combinations
The approach and methodology leading
scenarios continuously addressed the
study, which are:
to
three
the selection of energy
principal objectives of
• To minimize the energy costs for the market area
plan
the
• To minimize adverse environmental and socioeconomic impacts while
enhancing environmental values to the maximum extent possible
• To maximize the likelihood of project financing and development
The development and selection process for energy plan scenarios considered
the achievement of the above objectives by the use of regional or
6-1
sub-regional energy concepts. In addition, sincere efforts were made to
formulate an energy plan that would prove equal or superior to the Tazimina
River regional hydroelectric power project.
The objective of the Phase I study was to identify a development which
efficiently and responsibly responds to the electrical energy needs of the
area and its people that have been forecast through the year 2002. To this
end, the energy scenario efforts had to continuously consider, address, and
evaluate existing conditions, needs, and impacts in the area, as well as
the desires of the residents and state and federal agencies. The screening
process placed its emphasis not only on the previously described objectives
and guidelines, but also on engineering, environmental, and economic
considerations. Response to these guidelines required the collection of
data necessary to assess project feasibility commensurate with the type or
types of energy forms used in a particular energy scenario. The data
collection program considered four areas:
•
•
Geotechnical, Section 5.1
Hydrologic, Section 5.2
• Environmental, Section 5.3
• Sociocultural, Section 5.4
The extent to which data were collected in these categories is discussed in
each individual section. The development of candidate energy plans for the
study area began with the identification of a large number of ideas or
concepts. The complexity of this task can be realized when one considers
the number of energy plan combinations possible on the basis of having to
address:
•
•
•
•
Energy needs for some eighteen communities
Nine selected energy resources
Numerous transmission line combinations
Community attitudes and institutional restraints
The points considered in the assessment and use of the nine previously
6-2
•
l1li
III .. .. ... ..
•
• .. .. .. .. ..
•
au
III ..
'" III! .. ..
• -
•
•
•
IIIi
•
• ...
identified energy technologies are outlined in the following pages of this
section.
6.1.2 Assessment of Energy Resources
6.1.2.1 Hydroelectric
The most important natural resource in the Bristol Bay study region is
fisheries. The rivers and streams of the region play an important role in
the life cycle of this resource. Because of this, the development of
hydroelectric power projects must consider and evaluate the potential
impacts on fish.
Hydroelectric power development is site-specific. Coupled with the
economies -of-scale, hydroelectric power proj ects are favored for regional
development. However, small hydroelectric developments can be appropriate
and cost effective, given suitable site conditions. Reassessments of this
energy source have shown that within the study region there exist the
possibility for both regional and sub-regional power development.
The early assessment of hydroelectric sites and their associated
transmission line systems resulted in the development of detailed
assessment parameters and guidance criteria. Recognition of, and
continuous reference to, these parameters and criteria was beneficial
during the assessment of other energy resources. The detailed assessment
procedure and methodology applied to hydroelectric power developments is
discussed below.
Selection of Hydrosites
There have been numerous water and hydroelectric resource investigations
which have taken place in Alaska since World War II. Prior to that time,
however, very little was known about the extent of Alaska hydroelectric
resources, except those in Southeastern Alaska. The Bureau of Reclamation
conducted the first state-wide reconnaissance of potential hydroelectric
sites in 1948. A separate series of regional water resources
6-3
investigations was made by the U. S. Army, Corps of Engineers in the late
1950 IS. During the period from 1962 to 1967, the Bureau of Reclamation
.. -.. ..
prepared a comprehensive inventory of state-wide hydroelectric resources •
which has subsequently been updated by the Alaska Power Administration. •
Alaska Power Surveys by the Federal Power Commission in 1969 and 1976
further evaluated hydroelectric resources in a state-wide inventory.
Since 1976, reports specific to the Bristol Bay region have utilized
previous inventories to further evaluate the region I s hydroelectric
potential. The Bristol Bay Regional Power Plan study effort utilized these
previous inventories and investigations to develop a list of potential
• ..
• .. .. -
hydroelectric sites within the study region. These sites are listed, along •
with pertinent specifications, in Table 6.1-1 and shown by location in -
Figure 6.1-1. These sites were designated as "promising" or "sites with
major restraints" based on a preliminary evaluation of technical and
environmental parameters.
Assessment of Selected Hydrosites
Four major categories were selected as the basis for the assessment
..
•
•
process: 1) environmental, 2) socioeconomic and institutional, 3) technical •
and engineering, and 4) economic. ..
:.
A number of considerations were identified under each major category and a •
subjective rating system, using the letters A, B, and C, was devised to
assess each consideration.
Each site was rated with respect to each consideration on a subjective
basis. A summary rating was made for each major category and an overall
.. ..
• ..
qualitative assessment was made for each site based upon the following ,.
criteria: ..
• Existence of a "fatal flaw": Eliminated from further consideration
• Several serious defects (a 1 though none necessarily "fatal" by
.. -themselves): Eliminated from further consideration
• .. . '
6-4 ..
• A number of considerations rated in the C category: Rated overall as
"not promising"
• All other sites: Rated as " .." prom~s~ng
• Sites assessed as "promising" were incorporated into scenarios
The method of analysis employed was, foremost, a relative one. Secondly,
the analysis was subj ective. It was recognized that some considerations
could have been given more weight or been considered more important by
different individuals and organizations. However, it was not the intent to
perform a numerical analysis, but merely to assess, on a qualitative basis,
the identified hydrosites.
It was understood that some sites exhibited undesirable characteristics for
project development or posed a severe defect. In certain cases, these
negative attributes could have been considered a "fatal flaw". If a "fatal
flaw" was found at any identified site, that site was no longer
considered. Rejection of a site, however, was not limited to the presence
of a "fatal flaw": a site could also have been rejected if it exhibited a
number of severe defects or undesirable characteristics, which by
themselves were not "fatal", but which in combination with each other could
preclude the development of that site.
Final assessment came after each site had been analyzed for each
consideration. Those sites which were not rejected, either by a "fatal
flaw" or because of numerous severe defects or undesirable characteristics,
were included in the final assessment. The final assessment judged whether
a particular site was "promising" by assessing it relative to each of the
others, integrating all the considerations discussed below.
Environmental Considerations
Fisheries -This addresses the impact of project development on fisheries.
Facility impact only was considered here. Basis for assessment were
comments submitted by Alaska Department of Fish and Game (ADFG).
6-5
Wildlife Habitat -This addresses the impact of project development on
wildlife, including migratory patterns of birds and large mammals.
Facility and transmission line impacts were considered. Assessment was
based upon location of summer and winter ranges of large mammals, feeding
areas, and rearing areas (from published habitat maps). The greater the
site disturbance, and the greater the number of ancillary facilities, the
greater the impact that is expected to occur on wildlife habitat. Longer
transmission lines are also expected to have a greater impact upon wildlife
habitat.
Terrestrial Ecology -This addresses the impact of project development on
plant life. Facility and transmission line impacts were considered.
Assessment was based upon types of vegetation and ecosystems found in
published habitat maps. As with wildlife habitat, the greater the site
disturbance, the greater the impact that is expected to occur on
terrestrial ecology. Impacts upon forest and tree species were to be
considered more significant than impacts upon grasses and brush.
Visual Impact This addresses the aesthetic considerations of proj ect
development, specifically, transmission line and structures. Facility and
transmission line impacts were considered. The following factors were
considered in assessing the visual impact of a site:
disturbance; 2) number of ancillary facilities; 3)
1) degree of site
type of facility
installed; 4) inundation due to storage; 5) natural screening; 6) effect
upon natural features, e. g., waterfalls; and 7) length of transmission
lines.
Sociocultural and Institutional Considerations
Subsistence -This addresses the impact of project development on the
subsistence lifestyle of the people in the study region. Facility and
transmission line impacts were considered. Assessment was based primarily
upon comments received from public and agency meetings and from letters
received by agencies and public organizations.
Land Status -This addresses the constraint to project development by
designated land. Facility impact only was considered. Assessment was
6-6
.. .. .. .. ..
II ..
• .. .. -
• ... .. ... ..
WI; .. ..
•
-..
..
•
.. ---
based upon land classification maps prepared by the National Park Service
(NPS), the U.S. Fish & Wildlife Service (USFWS), the Bureau of Land
Management (BLM), the Alaska Department of Natural Resources (ADNR), and
the Bristol Bay Native Corporation (BBNC). Sites located within
conservation units were considered to have major institutional restraints.
Community Impact -This addresses long-and short-term effects of project
construction and operation to the community infrastructure and the
community's preference for the development, as presently known. Facility
impact only was considered. Assessment was based upon the following: 1)
proximity to Bristol Bay villages; 2) attraction of villages for leisure
time activities; and 3) accessibility of villages from the site.
Roads and Access -This addresses the long-term impact resulting from the
needs to develop roads and cleared rights-of-way for improved and
continuous access to the development. (Project methodology did not
consider the development of roads for transmission line construction, but
considered local clearing of rights-of-way as may be required for this
work.) Facility impact only was considered. Assessment was based upon the
following: 1) type of access; 2) length of road; 3) usage of land; and 4)
proximity to villages and other forms of access.
Technical and Engineering Considerations
Site Access
This relates to the accessibility of the site for the construction of the
facilities, and the consideration of the methods and means by which project
construction equipment, material,
reasonably available at the site.
Project Structures
and plant equipment can be made
This pertains only to major structures su~h as dams J the powerhouse, the
penstock, and spillways. The qualitative assessment relates to the type,
size, and complexity of development.
6-7
Flow Lines
This assessment relates to flow lines (water conveyance system)
standpoint of size, type, and length-to-head ratio, as well as
complexity of flow line development.
Engineering, Development, and Constructibility
from the
to the
This is an assessment of technical and engineering merits and
considerations such as geology, topography, length of construction season,
availability of local construction material, the ease of construction and
the improvements believed necessary to develop the site.
Power Potent ial
This concerns the potential of the site to supply the power needs of the
region (regional) or the power needs of geographically grouped villages
(local) .
Operation and Maintenance
This relates to the consideration of climatological effects on plant
operation and maintenance, remoteness of site to access for repairs, and
difficulty of ensuring the availability of operating/maintenance personnel
at project.
Transmission Lines
This assessment relates to the relative length of main transmission lines
and feeder lines, considering the amount of power being transmitted and the
area (villages) served.
Relative Project Economics
This considers the relative assessment of the cost for developing the major
project facilities, excluding transmission.
Relative Economics -Transmission
This pertains to the relative assessment of the cost for developing the
transmission facilities of the plan.
6-8
.. ...
• ..
• .... ..
• .. .. ..
•
• .. .. .. .. ... .. ...
• ..
• ..
•
•
.,
.,
.,
Rating System
The following definitions were applied in the rating system used for the
the categories considered under the qualitative assessments of
Environmental, Socioeconomic, and Institutional Considerations:
A
B
C
Small impact
Moderate impact but believed acceptable with
mitigation measures
Major defect, possibly resulting in a "fatal flaw"
The following definitions were applied in the rating system used for the
qualitative assessment of Technical and Engineering Considerations:
A
B
C
Shows favorable characteristics and attributes
Appears acceptable
Exhibits characteristics and attributes
which are less desirable
The following were applied to the Relative Economic assessment:
A
B
C
Good
Acceptable
Poor
The following designations apply to the overall assessment and are based on
a judgment of developed considerations, as follows:
P
N
R
Promising
Not Promising
Rejected
The preliminary assessment of alternative hydroelectric sites, using the
preceeding evaluation, is shown on Figure 6.1-2.
6-9
6.1.2.2 Diesel • •
The development of diesel generation represents a low impact profile. rhe •
compact sizes of required installations, the flexibility available for
their physical location, and the fact that this energy form has been in
use, all relate to its reasonable acceptability as an energy form in the
Bristol Bay region.
The use of diesel fuel is currently the primary source for generation of
electrical energy within the Bristol Bay study region. Continuation of
this energy source complies with the requirements of a Base Plan and
relates to several Alternative liB It energy plan scenarios.
With respect to the Base Plan, use of diesel generation was assumed to be
continued on the same basis as the present. As such, each community having
central electric energy diesel-fired generating facilities would continue
to expand on these facilities by the addition of new diesel units. For the
communities which do not have a central diesel supply, the energy scenario
would allow for the development of such a central station. It has been
assumed that such an energy development would incorporate, as part of the
energy plant, those diesel units
co-op, or central school system.
diesel plants were provided with
belonging to an existing utility, REA,
For all communities, the hypothetical
sufficient back-up to represent 100
-
•
•
• ..
• ..
• -• ...
•
• ..
percent of forecast peak demand capacity. The scenario assumes that ..
additional diesel capacity would be installed at five-year intervals, while
power plant housing facilites would be designed for a ten-year expansion
cycle.
With respect to regional or sub-regional diesel energy scenario
formulation, the energy plan development considered the utilization of
central diesel energy systems, with 50 percent back-up, and a 100 percent
reserve in the individual community diesel installation. Regional or
sub-regional integrity was achieved by the use of transmission line systems
interconnecting the applicable communities.
ten-year power plant housing expansion concept
regional and sub-regional diesel energy scenarios.
6-10
The five-year unit and
was also utilized in the
• ..
• -
• ---
• -
•
-
The diesel scenarios consider use of diesel fuel only. Heavy fuel (crude
oil) did not prove to be a desirable energy source (Appendix A.3).
6.1.2.3 Coal-Fired Steam Electric Generation
There were three primary fossil energy fuels identified in the study for
possible use in energy plan scenarios for steam electric generation. They
were:
• Coal
• Oil
• Natural gas
Further investigation of these fossil fuel resources and their associated
costs resulted in the early elimination of oil-and natural gas-fired steam
electric alternatives. These results became available prior to the
complete life cycle cost analysis (Appendix A.B). As such, only coal-fired
steam electric was considered for energy plan development. Coal from
outside the geographic area was found in adequate quantities for regional
needs. Use of this energy form is based on the assumption that only a
regional or large sub-regional installation would be developed. The
following factors dictated that such plant would best be located near the
communities of Dillingham or Naknek: economy-of-scale; coal would need to
be brought into the region from an outside source; climatological
conditions of the Bristol Bay region; lack of access; and availability and
retention of operating/maintenance personnel.
The central plant concept requires that a network of transmission lines
extend out to the communities served by the plant. Site locations were not
investigated at this time. This type of energy offers some flexibility
with respect to site location, which can be investigated at a later date.
6.1.2.4 Oil-Fired (Diesel) Combined Cycle
The oil-fired (diesel) combined cycle process was considered as an
alternative regional and large sub-regional electrical energy source.
6-11
However, only a single, centralized plant was considered for the same
reasons as given for the coal-fired steam electric plant. The oil-fired
(diesel) combined cycle process relates to a more efficient use of the
diesel fuel, under high loading conditions, for the generating units.
As for any central energy source, a system of transmission lines would be
required in the scenario using this process to supply the generated
electricity to the appropriate communities. While this energy source is
not site-specific, it does have certain limitations. Should this energy
source be found acceptable, appropriate plans would be made for detailed
site investigations.
6.1.2.5 Coal Gasification (Combined Cycle)
Consideration was given to the coal gasification-combined cycle process for
electrical energy generation as a possible contender to other fossil
fuel-fired plants.
Again, for the reasons stated under the coal-fired steam electric
installation, only a single regional or large sub-regional generating plant
was considered. The transmission line needs similar to those anticipated
for the coal-fired scenario would also apply to this scenario for servicing
appropriate communities. Siting aspects and needs are similar to those of
the coal-fired steam electric concept.
6.1. 2.6 Wind
Wind has been considered as a supplemental energy source only. The wind
energy resources of the Bristol Bay study region have been addressed in
detail in Appendix D. The various assumptions and consideration for wind
energy development are given in Appendix A.6.
Wind energy development was only found to be applicable in areas near the
communities of Naknek, Egegik, and Igiugig. These communities were
selected on the basis of having a wind Power Class 4 or better (Appendix
D). Large wind energy generating stations would require the development of
6-12
• -• .. .. -
• -..
•
• ..
• •
• ..
• .. .. ..
• .. .. ..
• .. .. ..
• ..
• ..
• .. .. .. .. -
wind farms at suitable locations near these areas. A 20 percent
penetration value was assumed for determining the installed wind capacity.
Wind generated energy was not considered a viable alternative to meet the
total energy and power needs of the region. As such, wind was only
reviewed as a secondary (or supplemental) form of energy, and only in
combination with the diesel fuel scenarios.
The penetration value was used as follows:
a. If a community suitable for wind generation was considered by
itself in an energy plan scenario (no transmission interties),
then the penetration value of 20 percent was applied directly to
the power needs for that individual community.
b. If a community suitable for wind generation is connected to other
communities by transmission line interties, then the value of the
power needs for the entire group was used to determine wind energy
installation on the basis of 20 percent pentration.
Supplemental wind energy was applied to all the diesel generation scenarios
and for one of the hydroelectric power generating scenarios.
Wind energy generation in conjunction with the hydroelectric power scenario
was done as a test case to assess the cost benefits of wind during the
years prior to the development of the hydroelectric project.
6.1.2.7 Energy Conservation
The reduction of electrical energy needs through energy conservation was
not considered during the Phase I interim assessment study. The electrical
energy benefits resulting from appliance conservation measures will be
assessed and evaluated in Phase II. It is believed that electrical energy
reductions resulting from conservation measures would not be significant
enough to influence present evaluation parameters and study results.
6-13
6.1.2.8 Waste Heat Recovery
This supplemental energy source was applied only in conjunction with diesel
energy generation. Waste heat recovery is not, in itself, an electricity
generator, but an energy needs reducer. The use of waste heat recovery
systems relate to cost benefits gained in fuel usage for space heating
requirements. The study considered waste heat recovery in this form, and
credited the heat produced by an amount reflecting the savings in heating
fuel (Appendix A.4).
In the B-15 scenario waste heat is considered only in the load centers of
Dillingham, Naknek, New Stuyahok and Newhalen. In all cases the waste heat
improves the economics of the plan.
In the B-16 and B-17 scenarios waste heat recovery equipment is used in
Dillingham, Naknek, and Newhalen. The waste heat recovery improves both
scenarios.
.'
•
•
.i
•
••
III' ..
Waste heat is considered in all villages in B-19A and B-19C scenarios. ..
However, it does not appear economically feasible in Ekuk, Egegik, Clarks -
Point or Portage Creek.
Waste heat recovery systems were considered for only one of the
hydroelectric power generating scenarios. Its use in the hydroelectric
project was done as a test case to assess the cost benefits of waste heat
recovery during the years of diesel generation prior to the development of
the hydroelectric project.
6.1.2.9 Organic Rankine Cycle
The treatment of this supplemental energy source was similar to that of
waste heat recovery systems. The source would use waste heat for
generation of electrical energy. The organic Rankine cycle, by its nature,
relates to low temperature energy sources such as those commonly available
from diesel generating systems. High temperature energy sources would more
likely be used with an efficient steam Rankine cycle system (Appendix A.9).
6-14
• ..
..
..
.,
..
..
The economic merits of the organic Rankine cycle were tested for only one
scenario; the installation of a system at Dillingham and Naknek. These two
areas were considered the most likely candidates for an organic Rankine
cycle system, primarily due to their large diesel generating capacity. If
an installation at these two villages proved to be of significant economic
benefit, it would then be investigated for other communities.
6.1.2.10 Transmission Line Systems
It is recognized that transmission lines are not an energy producer but an
energy carrier. However, transmission lines affect considerably the
development and distribution of electrical energy in the study area. The
use of transmission lines offers the flexibility needed to address and
evaluate regional and sub-regional energy scenarios. Their use strongly
affects the technical, economic, and environmental-sociocultural aspects
and other assessment considerations of an energy plan scenario.
The people of the study region, in general, expressed a strong interest
regarding transmission lines and their associated corridors. The scenarios
used in the study take this into consideration, and attempts have been made
to suggest corridors and alignments that reflect the views and comments of
the people.
6.1.3 Selection of Energy Scenarios
6.1.3.1 Introduction
Regional and sub-regional electrical energy plan scenarios were developed
using the previously identified energy resources. The scenarios
numerous combinations of basic energy system components.
ingredients to these energy systems and the proposed uses of
energy sources are discussed below.
represent
The basic
identified
Eight villages were combined into three groups with each group considered
to be a single load demand. These village groups are:
6-15
• Dillingham and Aleknagik
• Naknek, South Naknek, and King Salmon
• Iliamna, Nondalton, and Newhalen
6.1.3.2 Hydroelectric
The selection of energy supply scenarios using hydroelectric power
generation was based on technical restraints, relative economics, and
environmental compatability. Using these criteria, the following
..
...
hydroelectric sites were considered to be the most promising: Tazimina ..
River, Kontrashibuna Lake/Tanalian River, Newhalen River, Chikuminuk
Lake/Allen River, Kukaklek Lake, and King Salmon River.
6.1. 3 . 3 Diesel
The selection of
generation was
energy
based
supply scenarios using diesel-electric
primarily on village grouping
transmission-interconnect concepts as described in Section 6.1.3.7.
6.1.3.4 Fossil-Fired
power
and
..
•
..
.,
The selection of energy supply scenarios utilizing fossil-fired electric ..
power generation was based primarily on such a facility located in either
Dillingham or Naknek.
6.1.3.5 Transmission Intertie
A special energy supply scenario was selected which considered bringing
electric power to the Bristol Bay area from outside the region. This
scenario, designed to meet regional needs only, anticipates using electric
power generated at Chugach Electric's Beluga Plant on the Cook Inlet.
6-16
• ..
• .. ..
•• ..
..
... . '
."
6.1.3.6 Wind, Conservation, Waste Heat, and Organic Rankine Cycle
These technologies were not considered as primary energy sources during the
selection of energy supply scenarios. They were, however, considered as
secondary (supplemental) sources and used in combination with various
diesel scenarios.
6.1.3.7 Village Grouping and Transmission-Interconnect Concepts
Village grouping was believed necessary for the proper development of
sub-regional, as well as regional, energy scenarios. This was accomplished
by developing a five-zone geographic grouping of villages, as shown on
Figure 6.1-3. These zones were:
Zone A Dillingham, Aleknagik, Portage Creek, Manokotak, Clarks
Zone B
Zone C
Zone D
Zone E
Point, and Ekuk
New Stuyahok, Koliganek, and Ekwok
Levelock and Igiugig
Naknek, South Naknek, King Salmon, and Egegik
Iliamna, Newhalen, and Nondalton
In addition, transmission-interconnect concepts were developed utilizing
the various combinations of geographic zones, as follows:
Concept 1
Concept 2
Concept 3
Concept 4
Concept 5
Concept 6
Concept 7
All villages independent with no further transmission
other than presently exists
Three networks: Zones A + B, Zones C + D, Zone E
Four networks: Zone A, Zone B, Zones C + D, Zone E
Four networks: Zones A + B, Zone C, Zone D, Zone E
Two networks: Zones A + B, Zones C + D + E
Two networks: Zones A + B + C + D; Zone E
One network: All villages interconnected
The combinations of each of the identified energy sources, transmission
intertie scenarios, and transmission-interconnections are presented in
Table 6.1-2. This matrix shows numerous combinations of potential power
6-17
supply systems. The matrix was reduced to a manageable number of selected
scenarios on the basis of engineering judgement supplemented by the
subjective consideration of the assessment parameters and guidance criteria
developed during the hydroelectric power assessment process, with
particular emphasis on environmental factors. This resulted in reducing
the number of energy plan scenarios to about 18. Following the further
evaluation of new data, and as a result of agency discussions, three
additional scenarios were selected for further evaluation and comparison.
The addition of these three scenarios, which are included in Table 6.1-2,
resulted in a final slate of 21 energy plan concepts that are described in
the following section.
6-18
..
.,
•
... ..
...
III
• • ..
III ..
..
...
• ... ..
•
...
..
•
TABLE 6.1-1
POTENTIAL HYDROSITES IN THE BRISTOL BAY AREA
No. Site USGS Map Drainage Area Average Annual Average Plant Mean Effective Firm Energy Installed Capacity
1:63360 (sg miles) Flow (cfs) Flow (cfs) Head (cfs) (106KWh/:t:r) (MW)
1 Chikuminuk Lake Taylor Mtns A-8 290 850 850 100 52.6 2 X 6
2 Nuyakuk-Kulik Dillingham D-8 1,490 6,010 515 165 61 2 X 1
Lakes
3 King Salmon River Naknek B-3 110 2,200 1,935 100 122 2 X 12.5
4 Kontrashibuna Lake Lake Clark A-4 200 880 880 220 120 2 X 14
5 Lake Tazimina Iliamna D-5 320 1,li40 1,010 180 122 2 X 12.5
6 Newhalen River Iliamna D-6 3,300 9,303 155 85 8.3 2 X 1.8
1 Kukaklek-Iliamna Iliamna A-1 612 1,800 200 100 88 2 X 10
Lake
8 Kukaklek-Unnamed Iliamna A-1 612 1,800 210 140 24 2 X 3
Lakes
9 Upnuk Lake Taylor Mtns B-8 100 295 295 150 27 .5 2 X 3
10 Tikchik Lake Dillingham D-6 1,490 6,010 900 50 28.6 2 X 3.5
11 Grant Lake Dillingham D-1 31.2 92 92 215 12 1.5
12 Mikchalk-Beverly Dillingham C-8, D-8 180 600 360 50 11 2 X 1.3
Lake
13 Little Togiak Lake GOOdnews Bay C-l 60 200 200 100 89 2 X 10
14 Lake Elva Goodnews Bay C-l 10 50 50 215 8.4 1.5
15 Agulowak Dillingham B-8 350 1,200 100 25 11 1.3
16 Lake Aleknagik Dillingham B-1, B-8 1,100 li,824 4,300 12 33 2 X 4
11 Lake Nunavaugaluk Dillingham A-8 115 300 300 30 5.1 0.65
18 Nushagak River Dillingham C-4 9,850 20,000 145 10 4.1 2 X 1.1
19 Kvichak River Dillingham A-2 6,500 11,130 1,500 25 122 2 X 12.5
20 Kvichak River Dillingham A-2 6,500 11,130 9,315 20 122 2 X 12.5
21 Naknek Lake Naknek C-2 2,120 5,400 2,100 20 35 2 X 3.5
22 Becharof Lake Naknek A-3 1,200 3,000 1,400 10 8.9 2 X 1
23 Twin Lakes Lake Clark C-3 140 280 280 30 5.3 0.6
24 Koksetna River Lake Clark B-6 160 465 180 155 11.5 2 X 2
25 Lachbuna Lake Lake Clark B-3 168 495 115 1,100 122 2 X 12.5
26 Chulitna River Lake Clark A-51 1,100 2,200 2,135 90 122 2 X 12.5
21 Summit Lake Iliamna C-2, C-3 11.4 68.5 68.5 390 16.6 2 X 2
28 Meadow Lake Iliamna C-3 26.6 130 130 100 8.0 1.5
29 Kakhonak River Iliamna B-4 145 400 200 45 5.5 1.5
30 Gibralter Lake Iliamna B-5 145 500 100 150 9.5 1.0
31 Alagnak River Iliamna A-8 480 1,250 410 110 46 2 X 5
32 American Creek Mt. Katmai D-4 98.2 200 200 800 100 2 X 12
33 Idavain Lake Mt. Katmai C-6, D-6 26.6 41.5 41.5 685 11.5 2 X 2
34 Lake Grosvenor Mt. Katmai C-4 630 950 950 85 49.5 2 X 6
35 Savonoski River Mt. Katmai C-3 29·9 85 50 400 12.1 2 X 1.5
36 Lake Brooks Mt. Katmai C-6 NA NA 300 20 3.5 0.4
TABLE 6.1-2
POTENTIAL POWER SUPPLY SYSTEMS
ill
NO. POWER SUPPLIES
ALL
INDEPENDENT
1 Transmission from Beluga
2 King Salmon developed for entire region
3 Tazimina developed for entire region
~ Kukaklek developed for entire region
5 Newhalen-Local/Kukaklek-Region
6 Newhalen-Local/King Salmon-Region
1 Tazimina + Kukaklek-Region
8 King Salmon + Kukaklek + Newhalen-Local
9 Tazimina + King Salmon
10 Kukaklek + King Salmon
11 Tazimina + Konlrashibuna
12 Kukaklek + Chikuminuk + Newhalen
13 Chikuminuk + Newhalen + King Salmon + Kukaklek
l~ Chikuminuk + Kukaklek + Tazimina
15 Chikuminuk + Tazimina + Kukaklek + King Salmon
16 Chikuminuk + Newhalen + King Salmon
11 Chikuminuk + Tazimina
18 Dillingham + Naknek + Upper Nushagak + Newhalen Diesel
19 Dillingham + Naknek Diesel
20 Diesel Only -Individual Villages
21 Dillingham, Naknek Diesel + Newhalen Hydro
22 Dillingham, Naknek, Upper Nushagak Diesel + Newhalen
Hydro
23 Dillingham, Naknek, Upper Nushagak, Igiugig Diesel
+ Newhalen
2~ Dillingham, Upper Nushagak Diesel + Newhalen + Kukaklek
25 Dillingham, Upper Nushagak Diesel + Newhalen + King
Salmon
26 Dillingham, Upper Nushagak Diesel + Tazimina
21 Dillingham, Upper Nushagak, Igiugig Diesel + Newhalen +
King Salmon Hydro
28 Iliamna, Dillingham, Upper Nushagak, Igiugig Diesel +
King Salmon Hydro
29 Iliamna, Dillingham, Upper Nushagak Diesel + Kukaklek
Hydro
30 Kukaklek, Upper Nushagak, Diesel -Newhalen Local
31 King Salmon -Upper Nushagak Diesel -Newhalen Local
32 Dillingham Coal
33 Naknek Coal
3~ Dillingham Coal + Newhalen Hydro
35 Naknek Coal + Newhalen Hydro
x
112
ZONES
A + B,
C + D, E
x
X
X
X
X
X
X
X
X
X
X
X
X
X
X
POWER SUPPLIES
113
ZONES
A, B,
C + D, E
X
X
X
X
X
X
X
X
X
I~
ZONES
A + B,
C, D, E
X
X
X
X
X
X
115
ZONES
A + B,
C + D + E
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
,6
ZONES
A + B +
C + D, E
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
'1
INTERCONNECTED
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
TABLE 6.1-2
POTENTIAL POWER SUPPLY SYSTEMS
POWER SUPPLIES
112 113 ,4
#l ZONES ZONES ZONES
ALL A + B, A, B, A + B,
NO. POWER SUPPLIES INDEPENDENT C + D, E C + D, E C, D, E
36 Di llingham + Naknek Coal
37 Dillingham + Naknek + Newhalen Hydro
38 Dillingham Coal + Tazimina
39 Dillingham Coal + King Salmon
40 Dillingham Coal + Kukaklek
41 Naknek Coal + Tazimina
42 Dillingham + Naknek Coal, Upper Nushagak Diesel,
Newhalen Hydro X X
43 Dillingham Coal, Upper Nushagak Diesel, Tazimina
44 Dillingham Coal, Upper Nushagak Diesel, Ki ng Sa lmon ,
Newhalen X X
45 Dillingham Coal, Upper Nushagak Diesel, Igiugig Diesel,
King Salmon, Newhalen X X X
46 Dillingham Coal, Upper Nushagak Diesel, Kukaklek,
Newhalen X X
47 Chikuminuk + Newhalen
48 Newhalen
49 Diesel/Wind/Waste Heat/ORC/Local Tazimina X X X X
'5
ZONES
A + B,
C + D + E C
X
X
X
X
X
X
X
X
X
X
X
'6
ZONES
A + B +
+ D, E
X
X
X
X
X
X
X
X
X
X
17
INTERCONNECTED
X
X
X
X
X
X
X
X
X
X
X
X
X
X
P------------------------------------------------------------------------------------------,~ o
) ... J
10 ,(
KOLlGAN~ ..
.~.
EGEGIK ~
22
~ PROMISING
A SITES WITH MAJOR
RESTRAINTS
SCALE
o 10 20 30 40 50
MILES
POTENTIAL
HYDROELECTRIC
SITES
BRISTOL BAY REGION
FIGURE 6. 1-1
N • '" ~
-
EtJVIRD~ME.tJTA.L ~O~6IDERATIO~~ ?OClQftOIJDMI{. -IIJ~TITLlTloIJA!. TEl~IJIGA.!. / EU61tJEERltJ6 ('DIJ"DERATION. rlElATIV~
!
.cOIJ~I"ERATIOiJ~ ElOrJOM.I'(,
~lTf DE.61l;IJATION PRDJI!.-'T T~M"'IO'" !.tt.lE06 r'rOJUT • TUIJ"M"'-!>IOIJ UIJK PROJECT I T~'M,"IOIJ LIIJ1i6 Ol/eRALL.. RE.M.,.,RK !. 'T1UIIIt-No. ~~ ~ Nl)l1UT _1.1 EVA.LLI"TIO~ 1"'--~~ ITO:=-V"UAL --.m..ot..a ... I'-~~ = ----s't..~:~ '~ I~-,~ ~t I=~ ~ ,,0,: ......., i -ACT ..... ITAT .. " I I :z ~ 4 6 ~ 7 8 ~ 10 II 12
"
14 16 '''' 17 1& 1"1 20 21 22 n u
I eUIKllMllILlK -1t~IO"'AL A A A ~ A-,. {; G-et A C. A I!J " .. c; c; eo e e (, " :' ... 1& (; " ~"--J IA ,1l.KllNJIJ LlK -L.O('A!. I<. A A ,. A-& , ~ (.+ A &. A ,. ".. &. " 1& .. A (. e fI-e 8 ,. ~"'I~!frt.-...
2 t..ILlyAk,ul( -Jit£610NAl " A A 8 8+ ~ e-e. ,+ l' e. A ". " " " " .. " " G C. e. e. R .AfA~ FI1/UJfJS IMNC-J
"NO _1'£1-1t5fnW.."..~
U !JLI"I"Aw( -!.D'Al & A A f'I &+ ~ e-e-e. .. & , A e I!J " (. " e /I>.. G e e-G-.. It ~Dl!ttfU/J,~s~
~ ",,,..16 4AlN\OiJ -lte61DtJAL. " c; e. e. e. & & '" &-& & & 8 8e. EI " e • .. e c-e-c-c-ft ""-lOll fI~flUU ANb ~ !
KIAItO "AlMO/J -Lo,""!. C. A A e " e A '. ~_'fS_~_-I 9/1>.. & e. c;. c;. G &+ e. &. 15 B e, " " A 8 ., II. i
4 IC.O/J'rRMIII.lJiJA -ICE.&IONAL. A " e • 8-t:. C. t:. c;. G-c;. ~ " ", " C-• e e eo " e-c-It; '" ,:trOl'~'" ""~"SS MIM-I M __ ~_'_ I
~A. l(.oIJTU4111eLlIJA -L.o""'L. '" C. " 8 8 e. 8 8 e-&. e;. e e-8" " " • e " • .. .. 8 8 ,.
I 1; UK! T~~IMI"A -1Il"'~ C. s & eo l!>-e.. t:. e;. t:. 8 8 8 8 S " " 1& " .. e I '" e-& t:. P
6.A UK!. TAZIMIIJA -LO'Al A-e .. i e A A I e 10.& 6 A A 8 ,. 8 e 8 e e eo A • e B A p I
(, /oIEwllALEIJ -LOGAl e A I A , B ~ 6 A A 11.-8 A c.. A B+ /0, 8 • /0, l-/o, ,. ,,-B A P I
7 KLIKAII.!'&K. -RE610lJAl & " ! ,,+ G-~ &-G-e;. &-8 .8 8G-e " " , A 1& c-e-e. t:. N
__ "'~r
I " c.. .---.. ~ 7A KLlK.AK.l!1C. -L.D'AL • G-i " G-B II (, eo " A " • • e. , N
_ WI/JlUn ,,.RI,G-r" I e. e. t:.+ .:;. G-G-e. 8 Be;. ... ~---e KUKAKL.&.~ -LOGAL.. G G-8 I e 8c. s A e 8+ G-G-• e 8&-1& e 1& " A Il A .+ e e ,.
SA KlJIVJ\.~ -,""AL A-t:. & 8 e B A A I.-e.. " B e 8G-• • • A ,. • e I .+ -II A p ., UPNIJ K. L.AI<.£ -L.D'A-L (. A A 6 a+ ,. e;. e. G-+ A &-A 6 e+ I: , G • " " c-c-e. G R FISM~' lif'*' MIO.' ••• rnli
~-~ 10 ""K'U IK. LAK.E -!.Dt.AL. , III " B B-e e e .8 8 e;. A e. 15-(. " " " e " " , e;. 15 lit MDt 'WIiMIU IIfIIMr
II 6ltANT LAKe. -Lot.A!. A B A A 10.-B e B e A G-A G-B , " A • • c-C-it-~ e N J.I1W ".,.... ~
11 M'k(.ilA!.K. -eE"'IU.Y -~ , A A B s· B B B B A G-A &. & , & " • " c-c-I (. ~ ., R ".,.,., ~-~-... ,, __ UJMI/IIftIIrIIIaIf
It LJTTLI To& IAk L.A.II& -I.DGAL & G-t:. c.. c;. • e 8 B B Go A G-B-(. (. A c. '" c; , ,-t:. JJ R
_".116~-__
_~~IM.
14 LAKa ~L.V" -LoU.L , R
~ __ I&S
I, A6L1I.DIIIAK ItIV'" -LoCAL. c; e A
. ,A 8· III e • B 8 ,A .. t:. • (. 10. 10. A It c-e. It 5 ., " II4JIJI ,..-., ~
'" LJ.l(E. ~I(,,"IK.-UIoUL " 8 A e 8 A A A A " A t:. A & A 10. A It it I<. • A-A A R
JIIUDIt __ /IfMCr
17 LAKE .alUIiAVAU6AI.LlK -LDUI. '" , (.. G-t:.. A 8 A A-G-A G-A B It A A 10. , A • ... B 8 R JIIUQ( ,.",.,., HIIfl.T'
1& altJ<M4A6/o,k "IIIU. -L.o('A!. e A ", A M e e 8 8 t:.. A .. " 8 (. (. , • I<. • A 8 G-G-N
UIIIf __ ~
11 IW"UAK IIVf.1l -RUaION.t.L (. 8 & I G-ee. t:. t:.. & t:.. c;. A .:;. B 8-• , A t-A '" , .. Go t:. R ~ ""...,-."."., 1 -
iD kLlltuAK ICIvU -~U'oNAL (. e 8 t:. I!I/:. G-G-e. t:.. t:.. A Co. 8 e-e (. 10. , A ,. c-& c. G R ,...~_~WIIt:T
2,1 NA.JO,\LM. It"'e«. -LDGAL. , e.. B B J£. A A .A A " .:;. G-A Be. A '" A 1& • 10. 10. 10.-A A R ,.. fill ... /IWII:r
12 ~IlA"~F LAKE -loU!. " 8 A It It G-& 8 e-&. &. • ~ ee. e A '" • " • • .. A • R MU'Il ""lIBUa, IIUN!r
" ntuJ LAI<£' -!.O'AL. , Co B & I" G-a a a-& e;. A t:.. 8-, l-I<. f) " (. (. J-t:. G-Il. ....-,..,...---...... rs ... ~
~" 1(0".1.\11"'" 1t.IIU" LDU.L. A e e " (J+ 8 e & e e A A G 8+ " c-/o, • A " l-.-c.. G-N
UIIf _______
t~ .... ~" .. &I .... UICe. -~IOIJAL .. 8 It e .. " .. e ~ & G A G-e-(, (. A , , " " , .. t:.. t:.. It ----...-.., __ UIUf'IIIN ,{, (.1IL1!.ITIIA It...,.,,, -1CU1OWAL. It G-G-c;. c;.. e 1& IJ It c;. A e • • , , (. & • (. , , t:. c:. R ----~-•.. ".-..... ,..,..,..,...."
1;1 4u..wr LAt<& -LoUoL A e It • •• G-• It .~ A A " A A-I. , (. (, A e , e-t:-t:-N ~~ ,. IAUIIOv/ t.AIC& -LoU.L (. A 15 B It t:.. e • it-a A A " AS {, e A e c-(. (. e-c:. t:. R =:::'r'Jm;T.::
«1 MlCJiollAk «NU. -l.DC.AL A A e 15 ... c:. 15 • s-A A A e A-c. • '" A (, • e e • Co. N UJtI __ """'-"""'~
fO 61.,,/IoI.1e-. LAKe -U)UL. e-li II ., 15-&. " e -.. • A A A A-• (. " It & • .. B-• .. It ...... ,.",..,~-
UlW""""~ .1 Al..A&NI-K 1C1V'E1f -&..DC.AL. (. &. G-t:. G-&. & IJ 11-& G-IJ &. G+ e , • B .. (. & &+ c:. IJ It ~1WIIIItI6S""'" _ ~ "'_. _II; .tIIIoM
t2. AA\U,,"'" ,Q&K-CUIGNiL (. c;. c:. c:. c:. c; It; c:: t:. • t:. A c; .-" e " .. B C e it-t:.. t:.. R ---~ ........ .. ''',.,.,AI'' &.AKa. -Lo4AL " A • It , IJ " a • • c:. • c; fk;. , , /0, .. (. It e It t:. e " _~ 1oIIUM .. 1IIlU
.~ UI<£ 61tD6" ..... -LoU.I. (. 15 e a fJ-IJ " e IS e c:. • & 8G-• • '" A e • it JH 8 • It ...... ........, ... .. 4A~.uJ".1C1 !WeR -&.o'''L. • G-G-t:. c;+ &. • IS e-e c.. A c; IS-e • A e (, c. c. e-li c;. R ..... L ... __ ~ ,. LAKe .~1C4 -LDUL (. ~ A '" e II " e • • c;. t:.. c;. t:-'" .. • " I<. c; • • • t:.. • R i'M.IM ~ IIiIIN:r -~AlIIIIrR ~
i ". ~WJ4A1.£N -.IUICNL A & A 15 All , G-t:. t:. G-A c. A • A e;. B 15 A A Co. s· " Co p
EY4 bU ATI PH bE4liND OVERALL.. PRELIMINARY ASSESSMENT OF
AL TERNATIVE HYDROELECTRIC SITES e.!ilvl~""t6~4L. 6I!I12 iQ,lOl"oNbM."-lIIiIl1.!!r.!l2.!ll&... P • """"$,"'r.
A -4rA\A.u. IM"A'i N • NtYr _II'N':' BR.STOL BAY REGIONAL POWER PLAN
• -_'1& ' .. MeT IWT ML.'~\I"" AUU'TAeLE IIITII MITI6ATIOIJ lli .... ~ .. _ R • REJECTfP ALASKA POWER AUTHORITY , . _lit. PAI'&I.T _~y .... LlL'TIW6 IU 'I'ATAL I' ..... w~
:tUY!oI"&L. /. 11;1!IC.I!oIE.~!.IIJ" -StoDe • Web8ter EDcIDeedDa CorponUOD
". ~lIolO/t ,. .. VOIUoel.& """.~TEllIt.TI'" AlJD loTTe'.LIT ...... J.O.14OO7.04 Denver, Colorado •• ,.,.,,1iA1I. "'I.,," "'~f
, • ~1i'1I1.1T. &IWIA&TI!""T"~ AlJp A'T1'Ir •• m~ WII.,,, AIlI! ~ D&., .... L~. 1·18-82
~"Q!.I~~I'~
"'''&oCD ~ ... ""'L~ .... LE e· .. _~
I -FIGURE 6.1 2
} ",J
r /
SCALE
o 10 20 30 40 50
MILES
BRISTOL BA Y REGION
COMMUNITY GROUPING
FIGURE 6.1-3---'
6.2 DESCRIPTION OF SELECTED ENERGY SCENARIOS
6.2.1 Introduction
The major components and concepts considered for the selected energy
scenarios are discussed below. This section addresses scenarios in the
Base Plan, Alternative "A", and Alternative "B".
For each of the hydroelectric power projects that will be subsequently
referenced, it is assumed that these site-specific power developments would
be fully constructed from the onset as required to meet the energy needs
forecast for the year 2002. This was done in order to better assess the
economic, technical, and environmental implications that could result.
Staged construction for a selected scenario will be considered in later
phases of the overall study if such construction shows merit.
The figures referenced throughout this section have a layout showing the
letter "p" encircled. This symbol, when used by itself, designates the
location of a diesel power source. When used in combination with the
"triangle" or "square" symbol, it gives both the location and the type of
power source, depending on the symbol designation used.
6.2.2 Base Plan, BP-1 Diesel Generation Only
There is only one scenario for the Base Plan. This has been categorized as
scenario BP-1, and is shown on Figure 6.2-1. The base plan scenario
considers the continuation of diesel power generation in the individual
communities. Generation at the communities is assumed to be by a central
diesel system that is operational from the beginning of the study period
(1982) . The only transmission lines are the existing lines or the lines
that are now under construction. These transmission line interties are
between: Dillingham and Aleknagik; Naknek, South Naknek, and King Salmon;
and Iliamna-Newhalen-Nondalton.
6-19
...
In this scenario, each village has the diesel generating capacity to meet ..
its own peak demand and energy needs. The scenario also considers a 100
percent backup of peak capacity. Additional diesel capacity as required on
the basis of load and energy demand forecast is to be installed starting in
1982 (if required) and then at five-year intervals. Credit is taken for
existing diesel capacity, provided this relates to an electric company,
REA, co-op, or native school district.
in the decision for additional capacity.
Private generation is not included
.,
•
lit: -..
•
This scenario takes into consideration development of electrical energy ..,
only by use of diesel generators, as previously described. No credit is '.
given to benefits resulting from existing waste heat recovery or from other
secondary energy supplemental systems.
6.2.3 Alternative "A"
The development of the Tazimina River as a regional energy source is the
only scenario considered under this alternative. The investigation of this
concept was required by the study scope. The scenario is defined as
scenario A-l. The electric generating project is to be developed to meet
the regional energy needs through the year 2002. The scenario, shown by
Figure 6.2-2, would require the installation of 16 MW of generating
capacity with a storage reservoir to regulate the flow of the Tazimina
river. The storage reservoir would require the construction of a dam on
the Tazimina River; this dam would raise the present lake level by some 35
ft, and would result in the total regulation of natural lake flows.
Releases from the dam would be regulated as needed for power generation and
downstream flow requirements. Some flow would, on the average, be
by-passed through the ungated spillway. The released and spilled flow
would be carried by the river to a secondary low level forebay dam. This
dam would only serve to pond the flow as needed for the power intake.
Excess flow would be by-passed down the falls. A buried steel penstock
water conveyance system would connect the forebay dam pond and the
powerhouse, located downstream. The powerhouse will contain two
turbine-generator units, each having a generating capacity of 8,000 kW.
6-20
• ..
., ..
• •
• .. .. ..
•
.. -.,
... .. -
• ..
•
.'
The project starting from the powerhouse is located within and upstream of
the Tazimina River rocky gorge (Appendix A.2).
6.2.4 Alternative "BII
6.2.4.1 Introduction
Alternative "BI! scenarios consider several other energy sources, projects,
facilities, alone or in combination, including diesel energy and the
Tazimina River hydoelectric project developed to a lesser than regional
basis.
There is a total of 19 basic energy development scenarios that have been
considered under this category. Some of these also have sub-scenarios
which relate to different energy forms or combinations of energy mixes.
The basic scenarios involve the following energy generating resources:
• Diesel electric
• Coal-fired steam electric generation
• Oil-fired combined cycle
• Coal gasification (combined cycle)
• Hydroelectric
• Organic Rankine cycle
• Wind
• Energy conservation
• Waste heat recovery
The above resources were selected for consideration following a screening
of some 25 technologies (Appendix B).
Three scenarios (B-4, B-6, and B-7) were not completely evaluated because
they included a hydroelectric development on the King Salmon River. After
preliminary consideration, such a development was determined to be
environmentally unacceptable. In addition, one of the scenarios studied
investigates the concept of providing electrical energy to the study region
from a source outside the region.
6-21
6.2.4.2 Scenario B-1
This scenario considers the introduction of a main transmission line from
an electric generating source outside the study region. The source is
considered to be the gas turbine generating electric power plant located
near Beluga. The plant is being operated by the Chugach Electric
Association, Inc.
The concept considers the development of a 138 kV, three-phase transmission
line from Beluga to the Iliamna area. The line would follow a seacoast
route from Beluga to the North Fork of Big River, then over to Lake Clark
pass, following the south side of the pass and Lake Clark. At some point
near the Nondalton-Iliamna area (Figure 6.2-3), the line would enter a
substation and voltage would be reduced to 115 kV. From this point, the
transmission line grid would follow suggested corridors for supplying power
to all of the communities in the study region (Appendix A.7).
Sufficient energy and capacity would be wheeled across the transmission
..
•
• -
• -
• .,
..
• ..
• ..
line to meet the energy forecast needs of the study region. •
6.2.4.3 Scenario B-2
This scenario considers the development of two hydroelectric power projects
which in combination would meet the forecasted energy needs of the study
region for the year 2002. The scenario is shown on Figure 6.2-4. The two
power projects are:
a. A small, two-unit power plant having a total installed capacity of
1,200 kW. The project is on the Newhalen River between river mile 2
and 5, near the community of Newhalen. This installation would be a
diversion concept and would not require a dam across the Newhalen
River. A small amount of water would be taken from the river at a
point between river mile 4 and 5. This water would be conveyed through
an open channel and a 12-ft unlined tunnel to the turbine-generating
units. The units are housed in a powerhouse located on the right bank
of the river near river mile 2 (Appendix A.2). Power generated from
6-22
•
• •
• ..
• .. .. -.. -
•
..
..
...
.....
b.
this project would only supply the communities of Newhalen, Iliamna,
and Nondalton.
A large, two-unit
installed capacity
overflow-type gated
hydroelectric power installation having a total
of 16,000 kW. This installation would have an
structure at the outlet of Kukaklek Lake. This
structure would regulate the lake discharge only as needed to re-adjust
inflow storage for use in power generation. Some of the regulated flow
would then be diverted from Kukaklek Lake to the generating plant at
Iliamna Lake. The water conveyance system would consist of an open
channel and a buried steel penstock (Appendix A.2). Power generated
would be taken through a transmission line system to the remaining
communities of the study region.
6.2.4.4 Scenario B-3
This scenario considers the development of three hydroelectric power
projects, as shown on Figure 6.2-5. The three projects considered relate
to sub-regional energy development plans for meeting the electrical energy
needs of the lakes region, the Kvichak River region, and the Nushagak River
region. Each of the projects have been assigned from the onset to meet the
power needs of these sub-regions as forecast for the year 2002. The
projects are:
a. The small, 1,200 kW, two-unit hydroelectric plant at Newhalen River as
described under Scenario B-2.
b. A medium-sized, two-unit hydroelectric power project of 7,000 kW
installed capacity. This project would divert some flow from a
partially regulated Kukaklek Lake. This flow would be conveyed through
an open channel and a buried penstock to the turbine units. The units
are housed in a power plant which is located on the southeastern shore
of an unnamed lake. This unnamed lake is about two miles northwest of
Kukaklek Lake (Appendix A.2). Power generated would be taken through a
transmission line system to the communities found along the Kvichak
River, including Naknek, South Naknek, King Salmon, and Egegik .
6-23
c. A medium-sized, two-unit hydroelectric power project of 8,000 kW
installed capacity. This project would be located near the outlet of
Chikuminuk Lake. The concept would require the damming of Allen River
with a dam high enough to raise the present lake level by about 4 ft.
A low-level intake would take water from the lake and would convey it
through a concrete-lined tunnel to the two turbine units. The units
are housed in the power plant which is downstream of the dam (Appendix
A.2). Power generated would be taken through a transmission line
system to the communities along the Nushagak River and to Clarks Point,
Ekuk, Manokotak, and Aleknagik.
6.2.4.5 Scenario B-4
This scenario, shown on Figure 6.2-6, was not evaluated. It has been
retained only for continuity as it pertains to previously issued
preliminary data.
6.2.4.6 Scenario B-5
This scenario considers the development of three hydroelectric power
projects, as shown on Figure 6.2-7. The three projects considered relate
to sub-regional energy development plans for meeting the electrical energy
needs of the lakes region, the Kvichak River region, and the Nushagak River
region.
Each of the proj ects has been designed from the onset to meet the power
needs of these sub-regions as forecast for the year 2002. The projects are:
a. The medium-sized, 7,000 kW hydroelectric power project relating to the
Kukaklek Lake flow diversion scheme as described for Scenario B-3.
b. The medium-sized, 8,000 kW hydroelectric power project relating to the
Chikuminuk Lake development as described for Scenario B-3.
6-24
..
• ..
..
.. ..
•
•
..
II' ..
•
IIiIIt
• ..
., ..
-., -... -
• ----
c. A small run-of-river, two-unit,
development on the Tazimina River.
1,200 kW hydroelectric power
This development would generate the
power demand forecast for only the communities of Newhalen, Iliamna,
and Nondalton. This local project would have its powerhouse downstream
of the falls and its penstock intake upstream of the falls. The intake
would be placed directly in the shore line of the Tazimina River.
Water would be taken directly from the river by a steel penstock system
to the generating units at the power plant (Appendix A.2).
6.2.4.7 Scenario B-6
This scenario, shown on Figure 6.2-B, was not evaluated. It has been
retained only for continuity as it relates to previously issued preliminary
data.
6.2.4.B Scenario B-7
This scenario, shown on Figure 6.2-9, was not evaluated. It has been
retained only for continuity as it relates to previously issued preliminary
data.
6.2.4.9 Scenario B-B
This scenario considers the development of two medium-sized hydroelectric
power projects, as shown on Figure 6.2-10. The two projects each involve a
semi-regional energy development. One project would meet the needs of the
lake communities and the communities along the Kvichak River. The other
project would respond to the electricity needs for the communities in the
Nushagak River system. The plants relate to the power needs forecast for
the year 2002 in their respective service areas. The projects are:
a. The medium-sized, B, 000 kW hydroelectric power proj ect involving the
Chikuminuk Lake development as described for Scenario B-3.
6-25
,."
b. The medium-sized, 8,000 kW hydroelectric power project relating to a ..
regulating reservoir on the Tazimina River. Partial regulation of
Tazimina River flows would be required to achieve the capacity and
energy needed by this medium-sized plant. A regulating dam would be
constructed. The dam would raise the Tazimina Lake by approximately 5
ft. Controlled releases from this regulating dam would be taken down
the river and be ponded by a forebay dam. This dam would only serve
for submergence of the power intake. Excess flow would be passed by
the main spillway at the regulating dam and downstream, over the
overflow forebay dam. A buried penstock water conveyance system would
connect the forebay dam pond and the powerhouse, located downstream.
The project is located within and upstream of the Tazimina River gorge
(Appendix A. 2) .
6.2.4.10 Scenarios B-9 and B-I0
These scenarios consider regional electric energy generation by use of a
single fossil-fired power plant. Scenario B-9 assumes the power plant is
located in the Dillingham area, while Scenario B-I0 assumes the plant in
the Naknek area. The plant would be designed to have 16,000 kW of
installed capacity and could generate the energy needs of the region up to
year 2002. Figure 6.2-11 shows the suggested concept. There are three
types of energy generation that have been considered for these scenarios.
These types are:
a. Scenario B-9A would use a 16,000 kW installed capacity coal-fired steam
generating power plant.
..
....
a . .. ..
• .,
•
•
II'
• .. .. .. .. -b. Scenario B-9B would use a 16,000 kW installed capacity fuel oil-fired .'
combined cycle power plant.
c. Scenario B-9C would use a coal gasification and combined cycle process
for generating 16,000 kW of power.
6-26
••
• -
• ..
•
For the coal-fired plants, all coal storage and coal handling facilities,
including ash handling facilities and treatment processes, would be
provided as part of the generating system. The coal is available from
three sources; . Usibelli Mine near Healy, Alaska; B.C. International in
British Columbia; or Essel Resources in British Columbia (Appendix A. 8).
Similarily, oil storage facilities would be made available for the
oil-fired plant. Wharfs and docks would also need to be made available for
handling fuel supplies.
A system of main transmission lines and feeder lines would be provided from
the generating plant to the communities in the study region.
6.2.4.11 Scenarios B-1l and B-12
These scenarios consider a single, large, coal-fired steam electric energy
generating plant at either Dillingham (B-ll) or Naknek (B-12), and in
addition, a small hydroelectric power plant at the Newhalen River. The
suggested concept is shown by Figure 6.2-12. These two plants are:
a. A coal-fired steam electric power plant of about 16,000 kW installed
capacity similar to that described for Scenario B-9A. This
installation would also include a coal handling system, a wharf/dock,
and ash handling/processing facilities. A system of main transmission
and feeder lines would serve the study region communities, except for
the communities in the lakes region.
b. The small 1,200 kW hydroelectric power plant at the Newha1en River as
described under Scenario B-2 to serve the lakes region.
6.2.4.12 Scenarios B-13A and B-13B
These scenarios consider a large hydroelectric power plant which in
combination with one of two small hydroelectric power plants would provide
the power needs of the study region communities. These scenarios are shown
on Figure 6.2-13.
6-27
The large hydroelectric plant, which is a two-unit installation having a
total installed capacity of 16,000 kW, would be located near the outlet of
Ghikuminuk Lake. The concept would require the damming of Allen River to a
height that would raise the present lake level by about 21 ft. A low-level
intake would take water from the lake and would convey it through a
concrete-lined tunnel to the two turbine units. The units are housed in
the power plant which is downstream of the dam (Appendix A. 2) . Power
generated would be taken through a transmission line system to the
communities. The Ghikuminuk Lake development would be combined with a
small hydro development on either the Newhalen or Tazimina River as
described in Scenarios B-13A and B-13B below.
A transmission line system would be provided to bring power from the plant
to the communities being served.
Scenario B-13A
In addition to the large hydroelectric power plant, described above, this
scenario would have the small 1,200 kW run-of-river Tazimina River
hydroelectric power plant. This suggested plant concept was described
under Scenario B-S. This small installation would respond to the
electrical energy needs of the lake communities of Newhalen-Iliamna-
Nondalton.
Scenario B-13B
In addition to the large hydroelectric power plant described above, this
scenario would have the small 1,200 kW run-of-river Newha1en River
hydroelectric power plant as described under Scenario B-2.
6.2.4.13 Scenarios B-14A and B-14B
These scenarios consider a large, two-unit hydroelectric power project
which has a total installed capacity of 16,000 kW; the project would be
6-28
•
.,
III,'
.. ..
III, .. ..
• ..
• ..
..
• ..
.. .. .. .. ..
..
...
regional and supply the energy needs of all the communities in the study
area. These scenarios are shown on Figure 6.2-14. The power project is
located on the Newhalen River. Power generated from the plant would be
taken through a transmission line system to the communities in the study
area. These scenarios consider the development of two possible concepts.
These concepts are as described in the following paragraphs.
Both of these concepts would utilize a large hydroelectric power plant,
having a two-unit installation with a total capacity of 16,000 kW. The
power plant would be located on the left bank of the Newhalen River, in
that river section which is about 1,500 ft. wide. Both concepts would also
utilize a canal to divert Newhalen River water from a point above river
mile 7 to either the powerhouse or to the Newhalen River at a point
downstream of river mile 2. Neither concept would require construction of
a dam on the river. The concepts would differ with respect to size of the
diversion canal as described below.
Scenario B-14A
In addition to the general features described above, this scenario would
have its flow diversion canal designed to accommodate only those flows
required for power generation. This would limit the canal flow capacity to
about 2,100 cfs which is the maximum flow needed to generate 16 MW.
Scenario B-14B
This scenario, in addition to the general features described above, would
have a flow diversion canal that would serve two functions: the first
would be to divert water around that section of the Newhalen River which
has several severe rapids, from about river mile 7 to river mile 2.
Diversion of river flows would be done as needed, during high flow periods,
to improve the flow conditions within the natural channel for upstream
migrant fish. The second purpose of the canal is to act as and be
connected to the water conveyance system of the suggested power plant.
6-29
6.2.4.14 Scenario B-15
This is a diesel scenario with four load control centers and transmission
feeders to the surrounding villages. Load centers have a 100 percent
reserve. Each village connected to a load center has 100 percent reserve
generation to meet the peak demand if isolated from the load center. The
scenario is shown by Figure 6.2-15.
The Dillingham load center feeds Aleknagik, Manokotak, Clarks Point, Ekuk,
and Portage Creek. One feeder goes to a substation located between
Dillingham and Aleknagik. The substation feeds Aleknagik and Manokotak.
The second feeder goes east to Portage Creek, then west to Clarks Point and
Ekuk. The second load center is in New Stuyahok with feeders to Ekwok and
Koliganek. The third load center is in Naknek with feeder lines to Egegik,
South Naknek, and King Salmon, and a substation to the northeast that feeds
Levelock and Igiugig. The fourth load center is Newhalen with a feeder to
Iliamna and Nondalton.
Waste heat recovery is used in the load center, but not in the village with
reserve generation. Wind generation is considered with the Naknek load
center; this system would not be completed until 1986. Variations
employing waste heat recovery, wind generation, and organic Rankine cycle
are investigated but are not sub-divided as in the base case. The best
combination is ranked near the bottom when compared to the other options,
therefore, no further division is made.
While the new system is being installed, the reserve generation in some of
the villages will not be 100 percent. However, the villages will be able
to meet the peak demand and have some reserve. The percent of reserve
above the peak demand for each village is shown in Table A.3-4 of
Appendix A.
6-30
•
...
....
•
• -• ..
•
•
• ..
• ..
•
•
., ..
6.2.4.15 Scenario B-16
This diesel scenario is very similar to the B-15 scenario with the
exception of a transmission line connecting the Dillingham and Naknek load
centers. This transmission line provides more reliability; therefore, a
reduction is made in the reserve generation to 50 percent in these two load
centers. This scenario is shown by Figure 6.2-16.
Variations employing waste heat recovery, wind generation, and organic
Rankine cycle have been investigated but were not sub-divided as was the
base case. The best combination is ranked near the bottom when compared to
the other options; therefore, no further division is made.
While the new system is being installed, the reserve generation in some of
the villages will not be 100 percent. However, the villages will be able
to meet the peak demand and have some reserve. The percent of reserve
above the peak demand for each village is shown in Table A.3-6 of
Appendix A.
Waste heat recovery and wind generation are considered in this scenario.
Waste heat is considered only in the load center. A wind penetration of 20
percent is considered for the peak demand of the system connected to the
Naknek station.
6.2.4.16 Scenario B-17
In the B-17 scenario, all villages are intertied with transmission lines
and diesel generation. The load centers are in Dillingham and Naknek. The
load centers each have a 50 percent reserve. All other villages have 100
percent reserve generation to meet their own peak demand. All normal
generation is done in the load centers. The generators in the villages are
operated only during emergencies and tests.
6-31
There are three main substations. The first is between Dillingham and
Aleknagik. The substation is fed from Dillingham and feeds Aleknagik and
Manokotak. The second substation is on the north side of the Nushagak
River opposite Portage Creek. This substation has one line that goes south
to Portage Creek, then west to Clarks Point and Ekuk.
The second line goes north to Ekwok, New Stuyahok, and Koliganek. The
third substation is fed from Naknek and is located between Levelock and
Igiugig. One line from the substation feeds Levelock and one feeds
Igiugig. A third line goes north from the substation to feed Newhalen,
Iliamna, and Nondalton. King Salmon, South Naknek, and Egegik are fed from
the Naknek load center. Figure 6.2-17 shows scenario B-17.
Variations employing waste heat recovery, wind generation and organic
Rankine cycle are investigated but are not sub-divided as in the base
case. The best combination is ranked near the bottom when compared to the
other options; therefore, no further division is made.
Waste heat is considered only in the load centers. A wind generation
penetration of 20 percent is considered for the entire peak demand. It is
estimated this system could be installed by 1986. Therefore, until then,
some villages may not have 100 percent reserve.
6.2.4.17 Scenario B-18
This scenario considers two hydroelectric power projects to form two
separate sub-scenarios, B-18A and B-18B. The end capability of these
projects, either singularly or in the combination considered, would be to
serve the communities on a regional basis. The scenario is shown on Figure
6.2-18.
The energy plans which comprise alternative B-18 are 1) a scenario using a
16 MW run-ot-river hydroelectric project on the Tazimina River in
conunction with a 16 MW project at Kontrashibuna Lake, labeled alternative
B-18A; and 2) the 16 MW project at Kontrashibuna Lake with adequate storage
capacity to meet the entire regional energy demand as alternative B-18B.
6-32
..
III,
..
..
•
• ..
•
.,
• ..
•
., -
•
..
Ilk
."
Alternative B-18A utilizes the Tazimina run-of-river project according to
the availability of river flows for generation. The 16 MW installation
would normally meet the year 2002 regional energy needs for the months of
May through October. During the remainder of the year, the river flows are
not sufficient to meet the entire generating demand, and the Kontrashibuna
project would be operated to provide the regional energy needs. The
Kontrashibuna storage reservoir would provide the quantity of water
necessary to generate the required power during the months November through
April.
The Tazimina run-of-river installation would be essentially the same as the
Kontrashibuna 16 MW regional hydroelectric project except that the storage
reservoir is not provided.
be developed in the same
The powerhouse, penstock, and forebay dam would
manner as for the regional project and is
described in detail in Appendix A.2.
The Kontrashibuna proj ect consists of a 90 ft high darn located at the
outlet of Kontrashibuna Lake with a 13 ft diameter power tunnel constructed
to divert water to the powerhouse at Lake Clark. The Kontrashibuna project
is described in detail in Appendix A.2. The Kontrashibuna storage
reservoir capacity required to supplement the Tazimina run-of-river project
for November through April is essentially the same as would be required to
provide the entire annual energy demand of the region from the
Kontrashibuna project alone. This occurs because the storage reservoir is
necessary only to provide for generation in the low flow months. The
situation of developing the Kontrashibuna project to be capable of meeting
the entire regional demand while also developing the Tazimina run-of-river
project is less desirable than developing Kontrashibuna by itself for
regional needs. Thus, alternative B-18B is defined as the development of
the Kontrashibuna project to meet the entire regional energy demand in the
year 2002.
Power from either or both projects would be distributed to all the study
communities through a transmission line grid.
6-33
The study on these two projects, the run-of-river Tazimina and the
regulatory Kontrashibuna, shows that the storage needs at Kontrashibuna for
meeting fall-winter-spring loads totally dictate the size of the proj ect,
and, in fact, result in a project which has the year-round capabilities of
meeting the total regional electrical energy demands. As such, the 16,000
kW Tazimina run-of-river plant is not required for regional loads.
6.2.4.18 Scenarios B-19A, B-19B, B-19C, B-19D, and B-19E
These are subregional scenarios which utilize the Base Plan (BP-l) concept
of localized diesel generation, but differ as they employ waste heat
recovery, wind, organic Rankine cycle and/or hydroelectric combinations.
There is no need for long transmission lines.
B-19A Diesel Generation plus Waste Heat Recovery
This variation considers the benefits which may be derived by the
installation of waste heat recovery systems. Such benefits are converted
to cost credits on the basis of "equivalent" energy replacement needs.
These credits are used to reduce the present worth cost of the scenario.
The treatment of waste heat and recoverable benefits are given in greater
detail in Appendix A.4 and Chapter 7 of the report.
B-19B Diesel Generation Supplemented with Wind Energy Generation
This variation introduces the supplementing of diesel electricity by wind
generated electricity. The methodology and approach for introducing wind
.. ' .. ..
...
• ..
.. ..
•
..
• ..
•
are discussed in greater detail in Appendix A. 6. Economic evaluations and _
present worth costs relating to wind supplements are given in Chapter 7 of
the report.
B-19C Diesel Generation plus Waste Heat Recovery and Wind Generation
This variation combines the utilization of waste heat recovery (B-19A) and
supplemental electrical generation by wind (B-19B) with the diesel
generating concepts considered under the BP-l scenario. Discussions on
6-34
..
•
.. -.' .. -
.,
methodology, approach, and economic evaluations are given in previous ly
referenced sections of the report.
B-19D For Dillingham and Naknek Groups Only; Diesel Generation
Supplemented with Organic Rankine Cycle (ORC) Cogeneration
This variation was selected and developed as a test case. The test was to
determine whether it is more beneficial to use waste heat from electric
diesel generation as a space heating equivalent cost fuel or for
cogeneration of electrical energy. Dillingham and Naknek were selected
since these areas offered the benefits of economy of scale due to their
large electrical energy load and generation of waste heat.
The ORC cogeneration review would have been extended to the smaller
villages had the test results shown economic benefits in comparison to
waste heat recovery.
B-19E Diesel Generation plus Waste Heat Recovery, Wind Generation, and
the Local Tazimina River Hydroelectric Project
This predominatly diesel generation scenario looks at the selective
utilization of the least present worth energy cost concept on a village by
village or group of villages approach. Consideration is given to:
(1) pure diesel; (2) addition of waste heat recovery, if suitable and
beneficial; (3) addition of wind supplemental energy, if suitable and
beneficial; and (4) substitution of diesel generation by hydroelectric
power.
Under this scenario variation, the villages of Newhalen, Iliamna, and
Nondalton would be furnished electricity from a small run-of-river
hydroelectric project on the Tazimina River. The remaining fifteen
villages would be provided with electricity by diesel generation. Where
applicable and appropriate, this energy would be supplemented by wind
generated electricity or by diesel waste heat recovery to supplement
village space heating energy needs.
6-35
6.2.5 Miscellaneous Scenario Studies
During the course of the study, some miscellaneous scenarios were briefly
investigated. The intent of these evaluations was to identify preferred
power supply options for specific Bristol Bay areas.
These miscellaneous scenarios are briefly described below.
6.2.5.1 Alternative B, Scenario B-14
An investigation was made for this scenario to determine whether it would
be economical to install wind generation or waste heat recovery during the
years 1982 through 1987-1988, before the hydroelectric power plant would be
on line.
The results of this brief study are summarized in the report Section 7.4.5.
6.2.5.2 Alternative B, Scenario B-15
A brief study was made to compare the economics
hydroelectric power project (the Chikuminuk Lake
serving the Nushagak River communities versus
generating system for the same villages.
of providing a single
8,000 kW plant) for
a diesel electrical
6.2.5.3 Local Newha1en versus Local Tazimina versus Newhalen Diesel
This exercise was made to compare the economics of the 1,200 kW Newhalen
River or Tazimina River hydroelectric power projects against the diesel
fuel central generation station at Newhalen.
6.2.5.4 Conservation
Conservation is believed to be a viable and economically effective means of
reducing electrical energy needs of appliance end use (Appendix A.5).
6-36
... ..
•
..
• .. .. -..
-
•
.. ..
..
..
The mode of addressing conservation and its effect on energy needs can only
be determined through a detailed energy audit of the present household
stock, a task that is beyond the scope of this study. The effective
implementation of conservation in the present situation and for the future,
however, is totally dependent on an individual's desire and willingness to
participate in a conservation program and to support financial commitments
which must be made. Mandatory conservation programs have been put into
effect in several states. It would appear, however, that regional
conservation measures currently being applied to electrical energy may have
reached their ultimate peak. It was overheard during the village meetings
that "more conservation of electricity would mean closing off the kitchen
light. "
6-37
M·",a', .. " .... ,'. ill "7
LEGEND
TRANSMISSION LINES.
MAIN LINE
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC P()V..IER PLANT
FOSSIL FUEL POWER PLANT
SUB-STATION
® • • •
~ .
. :;. ' -. . '
'--~,
" ,
BASE PLAN SCENARIO BP-1
n
" .. ?
~
lui
n
- -r U ~-
f!
it. ,.
U
" ~
i.-
f" ...
...
_11
~ -
• ~
~ ~
i.;;
1J"II,a'"" II .. J( .,'. lot"" . "';;'~;"''';1~~~~~~'T---~--- - - -
LEGEND
'R.ANSMISSION LINES:
MAIN LINE
,FEEDER LINE --------
® POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUEL POWER PLANT
SU8-STATION
• • •
~''' ..
~ , -~
\. '
., ,
ALTERNATIVE "A" SCENARIO A-1
~
FIGURE 6.2-2
"
"
" .. "
'di
" Ii
"
Ij
II"V, ••• GA.". wi',,"
LEGEND
LINES: TRANSMISSION
MAIN LINE
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUEL POWER PLANT
SUB-STATION
® • • •
-:"1-'·
NEW STU'VAH'OK41>:1
'-1
I
I c I, ' --~--: --~~i ", , ,I
'--;, •• 'r ';'''''~~i 1 !
I' tJ ,,teo' "' ~-;,-" ," ',,--
•. "f I
I
I I
,'c_ 1, ---I t--
., ,
~':', ,.!.. ~--.... .'
','
ALTERNATIVE "8" SCENARIO 8-1
~
FIGURE 6.2-3-....
"
"
,..
...
r-
r ..
LEGEND
LINES:
.~. 1
L_---...,.....,.'
; - -"~j
TRANSMISSION
MAIN LINE
FEEDER LINE -----~--
POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUEL POWER PLANT
SUB-STATION
® • • •
r·····
-I ... +--
!
',,.'
t
1~ .. , r I
I
I
-I
,
I
'I'
.J _
J
1-,
. f--t
I""
\.
I .>."
.L • ..:,"'.
! ".,
• I . -';'-. ~
~ ..
.
~; .. , -.
. . -~'. -
, . ,
··r r· .. ·
ALTERNATIVE "8" SCENARIO B-2
&
FIGURE 6.2-4
"
"
"
" lb.
"
f '
,~"~
,~ -j
~ te··
LEGEND
TRANSMISSION LINES:
MAIN LINE
N·II,.· ... ~A ••
FEEDER LINE ---------
POWER SOURCE
PLANT
PLANT
HYDROELECTRIC POWER
FOSSIL FUEL POWER
SUB-STATION
®
.& • •
, ..
.f~
I'·····
. i'
,~ .
, . ,
-r I--
I ,!
"r : '-t-LT-:LFT"t~T
..1··· f·
ALTERNATIVE "B" SCENARIO B-3
A
FIGURE 6.2-5-......
''" ,
r •
.. C..,-T
l'" :' -i
~,I
,:i
I T, I
ot \
'_ of r 1 _
o
'[ ~. I --\
LEGEND
TRANSMISSION LINES:
MAIN LINE
,.'
11'11 .• 111<11' ... ,.
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC POWER PU~NT
FOSSIL FUEL POWER PLANT
SUB-STATIOO
® • • •
~--t
\ ~
f-r .... '
r··· .. "r'
•• >f'
, '-'7".~
,~ ;-
. '1
'"
"'j, .... ,
~ ..... -"
i '
---;.~-'--I -1--·-
.~.a.y~.
,.
I '
~£'{
"1-; ... , .. '
--------------------------------------------------~~~--~~ o
~;::;r
;$'/
.. \
, '1 .+
\ ~.
(: Of
ALTERNATIVE "8" SCENARIO 8-4
A
FIGURE 6.2-6-.......
"
"
,..
r • ,.
~~'"r L'
.t "" _i' ,,) ,
-?'
LEGEND
~v1ISSI0N LINES:
, I J i INE
.....-
~~ICF'ORTA<lE CREEK
,I
Itf--< LINE --------
iI" '.oURCE
f l [ C TRIC POWER PLANT
~ lH L PUWER PLANT
i .\ r I()N
® • • •
t,
,-.1
i,.
I ,,> '
-k-rv"LT
j I'
/ ,
-.... > j,,.I'·
, I
.,. ("
-"",:",:
....... ,
. --: --.-.
i.
't.
'-a9~
" ,
1
<I
f.,.
•
/1;1 r
ALTERNATIVE "8" SCENARIO 8-5
~
FIGURE 6.2-7
"
"
"
"
~.
•••• >
.. {
-1
t'~'" . ~.I
-; " , ~ --", \
"i i -
,,-< ~ \ \
]I-U,.' ill .. Q J. •• -• .111'''1'
LEGEND
r'-":,!-\NSMISSION LINES:
~v1AIN LINE
''::-EEDER LINE --------
;\NER SOURCE
i'(~)ROELECTRIC POWER PLANT
, '~;SiL FUEL POWER PLANT
)~j2-~)TATION
®
A • •
1-. ~
.~ . -J
t ,
.'.<~. ,--, . '.~. I , . ~-T
.: • I
i·
1
\
" ,
I
I
J.
ALTERNATIVE "8" SCENARIO 8-6
A
FIGURE 6.2 -8
,
,
j
,
.,
j
•
•
LEGEND
TRANSMISSION LINES:
MAIN LINE
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUEL POWER PLANT
SU8-STATION
®
.& • •
, , ,
ALTERNATIVE "8" SCENARIO 8-7
~
FIGURE 6.2-9-----'
" ,
,
''II
,lI
,.j
.j
ut
LEGEND
TRANSMISSION LINES:
MAIN LINE
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUEL POWER PLANT
SUB-STATION
®
.A • •
, ,
I
I , .
.-,.,
i 1
-, .
! -'
i.
1 :~
i ,'.'
-f I -
I
I
t
--------------------~~~~_,o
" ,
ALTERNATIVE "8" SCENARIO 8-8
LA
FIGURE 6.2-10-----
o
"" CO ,-
o
al
oj
"I
••
j
I
I
-r.
, 0'
o
, T
\
I, _ ,
\
--; ~ :.-i \ '\
\'
LEGEND
TRANSMISSION LINES:
MAIN LINE
'\ l -1--.F-
FEEDfR LINE --------
POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUE~ ?OWER PLANT
SUB-STATION
®
A • •
-_--'ir;P('1 r '1'
;~ r )1
-;~
i'
" r
"'T;r""' -,,~'. ~
, ,
'.
/
/
/
/
/
.J,.,
I
,~.
;---1-
I
)
\'
I ~
-",;-j--•
r'""
~ ; •• J':
~ '~~.,:. ' iol." ~"_
~ '.-, ;'
~-. ..... -(~-,. '\_,~~..,.
--,
, \ ,f (;;
r h .J ;
1-.1
\ 1
~ , ,
___ """_", _ I , ___ '
'".~';:f)~
,4" '":.1 ·
i
i
I
• I
• -1-'
.,'
•. "01~.
.< -,\-.",~-~~"-
'~.:;::;:';Tn ~! '
i$~
[ ...
, ..
ALTERNATIVE "8"
SCE~ARIO 8-9, 8-10
~----------............ ~~~---~---..a...----FIGURE 6.2-11
" U
n
b
LEGEND
TRANSMISSION LINES:
MAIN LINE
__ ~ --;:....... • ..L
'-,
I· ·+;·l~~
L-' , , ,
,', . -:,,-..
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUEL POWER PLANT
SUB-STATION
®
.& • •
.r;.
,
I
I
-'~
'". PI,.
./
./ ---:(
., 1/
Y ,
/1'" I 1-........ -•• ,.
l',~~{
:~'" .
/ /"\ ., ,
ALTERNATIVE "8"
SCENARIO 8-11 8-12
FIGURE 6.2-12 41
,
, ,
• .I
•
,
.~ ,
_ 1 •. , i·
, --.'0
j/ (J ....... ill ... " • 1OI''r
LEGaJD
TRANSMISSION LINES:
MAIN LINE
FEEDER LINE --------
POWER SOURCE
':iY~ROEL_E'=-:RIC POWER PLANT
FC)SSIL rUEL POWER P~ANT
:~u 8-:; TAT ION
® • • •
1 --, ._. -•. ~ ..
i···
T
r···--I
··1'
r,.-'.". --r:-:
• t, ", ,i ~
-:.:. I
--1)""'" "-:j-
~. i",·-··
..,~--. -
i
.... ""Imt_ t..~.
,,'-
LEVELOCK..r - --_ -i
"".'
)
"I;
I
L_~'_
" ~ ..
------------------------------~~~~~M
.' ,
ALTERNATIVE "8" SCENARIO 8-13
-o
N
'" ""' o
ID
'1
"
,j ,
...
fl
f'l
LEGEND
"}'-------: ""C
" ... -~." '"" ~,,;-~~:,~,:,,~~~:'~,~~~:: .. -,-,
LINES: TRANSMISSION
MAIN LINE
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUEL POWER PLANT
SU8-STATI0f\J
® • • •
~ .. ~' .. ':I_ ..... ' -
\ ' .
. ___ r:r
.. ,
ALTERNATIVE "8" SCENARIO 8-14
A
L---------.m~~m...........:.;:.;...:::::~~~~~---FIGURE 6.2-14-----
,
,
,
,
J
...
j
..
LEGEND
TRANSMISSION
MAIN LINE
LINES:
:, "
""~~',""_A»'"
",-~,.~"'''''''"''''''''~''''''-'.,~~"", ,-".
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC PONER PLANT
FOSSIL FUEL POWER PLANT
SUB-STATION
®
A • •
» , ,
ALTERNATIVE "B" SCENARIO B-15
A
L-------------------~~~~~~~~~~~~-------FIGURE 6.2-15 ------
I
,
,
j ,
• • ,
iii
.iO ,
; ,
j ,
.i
..
..
LEGEND
LINES: TRANSMISSION
MAIN LINE
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUEL
SUB-STATION
POWER PLANT
® .. • •
/.1'-,
, A ,
ALTERNATIVE "8" SCENARIO 8-16
A
L _________ --'U~~~~::...;.:~~~;;.:::.::..;;:..;.;L ____ FIGURE 6.2-16
I
I
1
.I
[
r • L
f
~~r:"'/: ;;;"J
! 1.-'-,
.. If--...,.....'
".~, '''I( " .
-'i l.
I • ", L~'
' .. ",' , ,
LEGEND
LINES: TRANSMISSION
MAIN LINE
FEEDER LINE --------
POWER SOURCE
HYDROELECTRIC POWER PLANT
FOSSIL FUEL POWER PLANT
SUB-STATION
®
6-• •
'-I
~ --r-; ...... ~ ,~ ..
• • I
'''''>r.
H A "
,
1"""",1. •• 'f ""'of''',. ~
ALTERNATIVE "B" SCENARIO B-17
A
L--________ ~~~~___=:....:.:.:.:..~~~;;.::;:;:::.:..:...;,.,IL..._ ___ FIGURE 6.2-17-.....
,
j
I ,
• ,
j
1
1
j
"
\
"
II
I
LEGEND
TRANSMISSION LINES;
MA~ UNE ~----------~-----FEEDER UNE ---------
POWER SOURCE
HYDROELECT~!-: PCNvER PLANT
FOSSIL FUEL POWER PLANT
SUa-STA ItQ\i
®
.A • • ALTERNATIVE w8-SCENARIO 8-18
A
FIGURE 6.2-18---.
I11III ..
....
,." ...
....
-
In -
...
....
-
-
III
-
7. EVALUATION OF SELECTED
ENERGY PLANS
c
-
-
7. EVALUATION OF SELECTED ENERGY PLANS
7 . 1 INTRODUCTION
The energy plan scenarios described in the previous chapter were compared
and evaluated with respect to a variety of technical, environmental, and
economic categories in accordance with the guidelines specified in Alaska
Power Authority requirements for feasibility studies (3AAC94-060). Various
combinations of alternative energy resources and the timing of these
resources were evaluated to formulate plans for economic assessments.
7.2 TECHNICAL EVALUATION
7.2.1 Introduction
The Alaska Power Authority Feasiblity studies guidelines (3AAC94.060)
stipulate that in an overall feasibility study technical assessment, the
evaluation needs to address the following indicators:
• Safety
• Reliability
• Availability
Because of the fact that many of the energy plan scenarios relate to the
introduction of large and/or complex energy developments, one more
indicator, that of constructibility, has been added. This additional
indicator will permit a further delineation of differences between plan
scenarios.
Many of the plan scenarios utilize one or more energy resources, singularly
or in groups, to respond to individual villages, village groupings, or
regional energy needs. Evaluations were made for each of the nine energy
supply technologies which were found to be attractive for application in
the Bristol Bay study region as discussed in Appendix B. However, because
these many energy resources were used in numerous combinations, it became
difficult to address and assess each resource individually as it related to
7-1
I
each community. Therefore, it was decided to address the energy supply I
technologies under each of the four indicators.
7.2.2 Safety
No adverse safety problems have been identified for the energy technologies
considered. However, the existence of some Ifsafetylf related aspects is
recognized; these would be addressed during detailed design of the energy
producing plans and their energy transmitting lines. For example: proper
precautions must be taken relative to the transportation, handling and
storage of diesel fuel; the transportation, handling and storage of coal,
particularly as it relates to spontaneous combustion; the proper design of
wind energy systems against ice build-up and ice shedding, and for proper
access for good maintenance; the implementation of safety booms and sound
alert devices for hydroelectric plants; and the proper design and
implementation of safety alerting devices on transmission lines, especially
over major river crossings where the rivers are used for airplane
navigation.
A subjective evaluation of the hydroelectric plant safety aspects relative
to earthquake conditions indicates that the projects requiring large dam
structures on alluvial material could exhibit a greater risk. This risk is
reduced for projects having similar structures founded on favorable till
foundations and further reduced for the projects which have no impounding
dams. From the standpoint of minimizing the effects of earthquake loading,
bedrock foundations are preferable for all structures. The lowest risk is
presented by the run-of-river developments, especially those founded on
bedrock.
7.2.3 Reliability
The reliability of each of the energy generating and/or energy conversion
technologies considered in the plan scenarios is believed to be good to
excellent. The reliability of any technologies utilizing mechanical and/or
electrical equipment is strongly influenced by the need for proper
operation and maintenance. The more simple and rugged this mechanical
7-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
III ..
• til
.-..
..
and/or electrical equipment is, the easier it is to service, and the lower
the recurrence intervals for service required. Because hydroelectric power
projects generally consist of rugged and rather simplified mechanical
equipment and electrical systems, they display excellent reliability. Many
hydroelectric power plants have long histories of 100 percent availability
year round. Further reliability is added to the hydroelectric power
developments in that a two-unit generating plant is suggested, with each
unit essentially equal to the average monthly generating capacity for the
year 2002. The reliability of hydroelectric power projects may be
degraded, however, as a result of ice-related problems. Ice build-up in
reservoirs would affect the amount of active storage needed but should not
affect the plan reliability. However, sheet ice, anchor ice, and pack ice
occurring in shallow rivers could result in ice jams and possible diversion
of flow throughout the ice masses and away from power intakes. This
situation could impede the operation of the plant and could be quite severe
for small run-of-river plants, particularly in streams having low natural
winter flows. The development of frazil ice under turbulent flow
conditions could act to block off screened intakes. It is poss ible that
ice sheets could also form within the penstock system, and protective
measures would need to be applied.
The ice problems associated with hydroelectric projects in cold regions
would most likely be minimized for concepts which allow for the withdrawal
of water from a deep reservoir through a protected penstock or tunnel water
conveyance system. The run-of-river plant concepts which use deep, low
velocity flow, canal systems in rivers which are known to have relatively
high natural winter flows would also have the tendency to result in less
severe icing problems.
The reliability of diesel generators is considered good to very good for
central generating systems where proper maintenance is expected to be
performed. The reliability of small non-central diesel units, however, is
found to be fair to poor. It is imperative that these small units be
adequately maintained. The reliability of diesel energy systems is
routinely improved by the addition of extra diesel units acting as
back-up. The scenarios which depend on diesel generation take advantage of
7-3
this practice and provide adequate back-up. Also, other electrical energy
scenarios take into consideration the installation of at least enough
diesel energy in each community to meet the village needs. This practice
offers adequate back-up and/or reliability and also offers the remote
village minimal but adequate energy in the event of loss of a central
system due to a transmission line fault.
Many of the energy plan scenarios would require the construction of
transmission line grids for the distribution of generated power. These
transmission lines would need to be designed not only for meeting
electrical loads, but also structural loads resulting from cable weight and
climatological conditions (icing, wind, etc.). Properly designed
transmission lines exhibit reliability factors of 97 to 98 percent.
Because of these high reliability values, coupled with the availability of
diesel back-up at each community, the scenarios do not employ redundant
transmission line systems. However, reliability could be reduced by line
length and the harsh weather and terrain features through which the line
passes.
In order to provide highly reliable generation by a coal-fired steam
electric station, two identical units, each sized slightly larger than half
of the regional peak electrical demand Were assumed. These dual units were
also backed-up by emergency diesel generation capacity. Thus, a continuous
electrical supply to the region would be assured. Highly trained operating
and maintenance personnel are required to ensure the continued reliability
of most power generating facilities. However, a coal-fired power station
requires the most support personnel of any of the viable technologies in
this study, with the possible exception of the coal gasification combined
cycle plant.
The combined cycle unit investigated consists of one unit with diesel
generation as the emergency back-up. This combination would provide
continuous power for the region, but the reliability of the combined cycle
unit alone would be less than the coal-fired steam electric alternative.
7-4
I
I
I
l
;
I
I
I
I
-I
I
I
I,
I
I
I
I
I
I
I
C
I
..
..
The integrated coal gasification combined cycle (ICGCC) unit has three coal
gasification trains, each 50 percent capacity; two full-size gas scrubbers;
and one combined cycle unit. As with the ,other fossil fuel-fired
technologies, this system is backed up with emergency diesel generation to
prevent the loss of electrical power. ICGCC units of this size have not
been operated to generate electricity on a commercial basis before. The
ICGCC is also dependent upon a coal source which must be barged in from
either Seward, Alaska, or Vancouver, British Columbia. Of the viable
fossil fuel technologies, ICGCC (alone) would be the least reliable.
Problems have been experienced in Alaska with reclaiming waste heat from
diesel generator exhausts. This is primarily due to the exhaust gas
temperature being reduced below its dew point and moisture collecting in
the engine exhaust. The diesel engine exhaust is the primary heat source
for the organic Rankine cycle (aRC) generator. If the aRC is designed and
installed properly to avoid the low exhaust gas temperatures, it should
provide reliabilities equivalent to the diesel generators with which they
must operate in parallel .
One disadvantage to the use of wind generators is the lack of operating
experience necessary to provide information on reliability. Since in
general sites with the best wind regimes are in remote areas, access to the
wind generators for scheduled maintenance or repair is dificu1t. Another
problem in the Bristol Bay region would be icing on the wind turbine
blades, which could cause inbalance in the generators. Because of the
harsh climatic conditions and the limited transportation routes in the
Bristol Bay region, it is expected that maintaining a reliable wind
generator power supply would be costly.
7.2.4 Availability
The technologies evaluated are believed to be immediately available, or
available within the very near future, for meeting the needs of the study
region communities for electrical energy. The technologies for diesel,
fossil, and hydroelectric power, and for transmission lines are available
now.
7-5
These resources can be developed for meeting the energy and power needs
forecast under the preliminary energy demand projections for electric
appliance end-use. Coal-, oil-, and natural gas-fired steam generation
technology has been proven for several decades. Waste heat recovery
methods have and continue to be implemented in the Bristol Bay study region
and other areas of Alaska. Energy conservation is available to the extent
of economic limitations. Hydroelectric power projects identified show
energy capabilities for meeting either regional and/or local needs.
Wind energy generation has become available in smaller installed
capacities. It is recognized that this technology is progressively
improving. Because of this, scenarios utilizing wind energy resources have
been careful to consider low capacity units of 10 kW from 1983 on, up to 69
kW from 1984 on, and larger capacity units of up to 200 kW after 1989.
Trends indicate that these higher capacity units would probably be
commercially available at that time and likely proven under Alaskan
conditions. The Bristol Bay region shows a strong wind resource
availability with areas near Naknek/King Salmon, Egigik and Igiugig ranking
as best candidate sites. As wind is a fluctuating power resource, it can
not solely supply the entire Bristol Bay region energy demands with
continuous availability. For a less variable wind power source. a
dispersion of various size wind generators in differing wind resource zones
allows for a spinning reserve. Depending on how extensively a utility
becomes involved with integrating wind power into their grid, it is
generally assumed that 10 to 70 percent penetration of wind energy into a
total regional energy supply system is potentially available. The 20
percent penetration value is the recommended level for the Bristol Bay
region.
Organic Rankine cycle (ORC) units of the size necessary for use in the
Bristol Bay region are commercially available. The technology associated
with ORC has been known for many years in heat pumps, refrigeration
systems, and similar applications. However, using an organic working fluid
in a Rankine cycle application to capture the energy of waste heat and
generate electricity is relatively new. Some developmental costs are still
encountered in purchasing commercial ORC units.
7-6
o
I
I
I
I
I ,
I
I
I
I
I
I
I ,
I
I
I
...
...
Low-and medium-Btu coal gasification technologies have existed for decades
and are commercially available for use in the Bristol Bay region. The most
efficient use of the effluent gas is to provide fuel for a combined cycle
generation unit. However, the combination of a coal gasification system
with the combined cycle unit has not been demonstrated commercially in the
size needed for the Bristol Bay region (16 MW).
7.2.5 Constructibility
The main components of a diesel fuel-fired generating plant can usually be
shipped fully assembled and ready for use. Units are typically
skid-mounted and can be installed into their respective power plants with a
minimum of difficulty. Hook-up, with respect to piping, controls, and
other support systems, is straight-forward. Plant housings can be
prefabricated, preconstructed, or even made a part of the packaged diesel
unit. Difficulties with respect to the constructibility of diesel
generating plants are not anticipated, even in the more remote
communities. The expansion of diesel generation by additional units and
fuel storage facili tes should not impose any construction problems. Oil
spill holding ponds should be provided with diesel fuel storage tank
installations. It is anticipated that a construction period of about one
year could be required for some of the larger diesel installations.
The constructibility of the hydroelectric power plants is not expected to
present problems. However, most of these installations require
construction of major structures (dams, canals, tunnels, powerhouses),
which entails lengthy schedules and the use of several building materials
not available at the job site. Hydroelectric power plant construction also
requires shipment of large equipment components. Additionally, these
projects need a greater number of construction personnel and longer
construction time. It is anticipated that the small run-of-river
hydroelectric plants would probably require a construction force that would
peak at about 100 to 150 persons, while the larger plants would most likely
need 150 to 300 persons. Construction periods are estimated to be about 2
to 2 1/2 years for the small run-of-river plants and about 3 to 3 1/2 years
for the larger regional plants. Also, because hydroelectric projects are
7-7
Constructing the transmission lines requires special considerations. Many
of the people in the study region are opposed to road construction with
transmission lines; because of this, the lines should be constructed using
helicopters. Earthwork construction should be done in winter to minimize
ground damage.
Constructing wind generators also requires road construction or use of
helicopters. A site area must be cleared and fenced in for safety
reasons. The small wind generators are shop fabricated and pre-assembled
and therefore require minimal erection time and no heavy construction
equipment such as cranes or backhoes. On the other hand, larger wind
generators require piling foundations which must be installed with a pile
driving rig or backhoe. As a relatively small crew can erect a wind
generator unit, no expensive housing or construction office space is
generally necessary.
In summary, the technical evaluation of the energy technologies considered
finds these energy resources to be acceptable with no adverse safety
problems and good to excellent reliability. The technologies are presently
available or are anticipated to be within the very near fu'ture. No
difficulites are expected from the standpoint of constructibility. A
subjective evaluation of the technologies with respect to the technical
evaluation indicators is:
Supply Component
Diesel
Hydroelectric
Wind
Fossil
Transmission
7-9
Lower Rating
Reliability
Constructibility
Reliability and availability
Commercial Development (coal
gasification combined cycle only)
Safety and Constructibility
I
I
~
I
I
I
I
I'
I
I
I
I
I
I
I
I
I
\1
I
I
I
C
I
I
I
S
e
t
site-specific, there is usually a need for improving or providing new means
of access to the project works. In some instances, the sites may be so
remote that access is possible only by airplane or expedient measures such
as snow roads. Construction material for project dams could be found
locally within reasonable haul distance. In summary, the constructibility
of hydroelectric power projects is believed to be more time-and
labor-intensive than some of the other generating technologies considered.
The major plant components of a coal-fired steam electric station can be
shop-assembled outside of Alaska to minimize field assembly. In fact, an
entire coal-fired steam electric plant, excluding coal handling and ash
disposal, can be constructed on a barge outside the state and then brought
in as one unit and mounted on a prepared foundation. An integrated
coal-gasification combined cycle unit would be very similar to the
conventional coal plant constuction. The major field or site work for
either the ICGCC or conventional coal-fired steam electric plant is the
construction of the coal handling, coal storage, and ash disposal
facilties. The barge unloading facility for coal barges could be quite
expensive, depending upon the amount of dredging required and the size of
breakwater needed. It is anticipated that about 2 to 2 1/2 years would be
required for the construction of this type of plant, with a construction
force peaking at about 200 persons.
The oil-fired combined cycle generating facility can be purchased as a
complete packaged unit. The only site work necessary would be electrical
controls, switchyard foundations, fuel tanks and supply systems, and the
make-up water system. The construction requirements would be very similar
to those of diesel generating units. except on a larger scale. It is
anticipated that about one year would be needed to construct this plant,
with a labor force peaking at about 100 persons.
Organic Rankine cycle generating plants are modular, packaged units mounted
on skids which can probably be arranged to share facilites with existing
diesel generators with minor modifications.
7-8
7.3 ENVIRONMENTAL EVALUATION
7.3.1 Introduction
The principal objective of this task is to analyze on a preliminary basis
the environmental and social impacts of the various energy scenarios. The
preliminary analysis of Phase I is intended to provide a basis for
comparison of alternatives. Of course, much more data is available for
evaluating Tazimina and Newha1en. Detailed information is contained in
Appendices G and H, respectively. Further detailed environmental
assessment in Phase II, however, will be required for the alternative
selected for detailed feasibility analysis.
Preliminary impact assessments have been made for the energy scenarios to
determine if each concept can comply with federal, state, and local
regulations. Regulatory reqUirements identified in Chapter 8 have provided
the basis for this evaluation. In addition, specific regional values and
concerns have also been considered.
In order to allow a comparative analysis of alternative power sources, the
Alaska Power Authority requires (3ACC94.060(C)7B) that the following
environmental indicators be used for evaluation in conducting a feasibility
study: 1) community preferences, 2) impact on community infrastructure, 3)
timing in relation to other capital projects, 4) air quality, 5) water
quality, 6) fish and wildlife impact, 7) land use impact and ownership
status, 8) terrestrial impact, 9) recreation resource value, and 10) visual
impact. Each scenario has been evaluated with respect to these
indicators. Section 6.2 contains descriptions of the scenarios.
7.3.2 Community Preferences
The following perceptions of community preference are based primarily on
information obtained during community meetings and from contacts by study
team members while collecting data in the region. In some cases the
information may not be entirely representative. In addition, community
preferences are expected to change as more data on the plan becomes
available.
7-10
I
~ ..•.. ".'. .~
4
I
I
I
".' I
I
I
I
f
J
I
I
I , ,
I
I
I
I
I
I
I,
..
...
7.3.2.1 Scenario BP-1
This energy plan is generally acceptable by all communities in the study
area. For the native people, it presents no threat to their subsistence
lifestyle, and permits them to continue with a life of isolation.
7.3.2.2 Scenario A-I
While the Tazimina River is widely recognized as a potential source of
hydropower, its development may affect the salmon fishery it supports in
its lower reaches. Local residents in Nondalton, Iliamna, and Newhalen are
generally in support of a project being proposed as long as the salmon
fishery is not harmed. Some residents of the lower Kvichak River and Upper
Alaskan Peninsula region are opposed to developing the Tazimina River for
hydroelectric power because of fears that the Kvichak salmon fishery will
be adversely affected.
7.3.2.3 Scenario B-1
This energy plan, importation of power from the Beluga area, is acceptable
by many of the residents of the region and some agencies. There is not
expected to be any significant community impacts associated with
development, and only minor impact from transmission line corridors.
Preference is generally lower than for BP-1, however, because of the
required transmission corridors .
7.3.2.4 Scenario B-2
This energy plan combines a local Newhalen hydroelectric development with a
regional Kukaklek hydroelectric development. The Kukaklek development plan
is not desirable by the villages of Igiugig and Levelock. Also, the plan
has been questioned by the National Park Service (NPS), U.S. Fish and
Wildlife Services (USFWS), and the Alaska Department of Fish and Game
(ADFG).
7-11
I
The development of a local Newhalen hydroelectric project is acceptable to I
most local residents of Newhalen, Nondalton, and Iliamna as long as the
salmon fishery is protected. The Newhalen concept may also be acceptable
to the ADFG.
7.3.2.5 Scenario B-3
This energy plan has the same preferences as expressed in Scenario B-2
(Section 7.3.2.4) for Kukaklek and Newhalen.
Some of the residents of the Upper Nushagak, however, are opposed to the
development of Chikuminuk as a hydroelectric site due to concerns about
subsistence hunting and fishing, and outside access. The Alaska Department
of Natural Resources (ADNR) Division of Parks does not favor the
development of Chikuminuk for hydroelectric power because the site is
located in the Wood-Tikchik State Park, and power development is not
considered in its management plan.
7.3.2.6 Scenarios B-4, B-6 and B-7
A great amount of opposition was encountered to the proposed development of
the King Salmon River hydroelectric site by both the general public, and
federal and state agencies. Accordingly, these energy plans, which contain
King Salmon hydro development, have been dropped from further consideration.
7.3.2.7 Scenario B-5
The development of the Kukaklek site to serve residents of the lower
Kvichak River and Upper Alaskan Peninsula region is opposed by local
residents of Levelock and Igiugig, and questioned by federal and state
agencies, particularly the NPS.
The development of the Chikuminuk site to serve residents of the Nushagak
system with electric power is opposed by some residents of the Upper
Nushagak River and not favored by the ADNR Division of Parks.
7-12
I
I
I
Q
I ,
I
J
,I
I
I
I
• I
J
I
I
I ,
..
-...
The development of the local Tazimina River site may be acceptable to the
local residents if the salmon fishery is protected.
7.3.2.8 Scenario B-8
The development of the Tazimina River to serve the residents of the Kvichak
River system is generally not acceptable by the USFWS and the ADFG unless
it is demonstrated that no significant harm will occur to the Tazimina
fishery. Similarly, the plan would be acceptable by the local residents of
Nondalton, Iliamna, and Newhalen if the salmon fishery in the lower
Tazimina River is preserved.
Upper Alaskan Peninsula are
Some residents of the lower Kvichak River and
opposed to the development of the Tazimina
hydroelectric power site because of fears that the Kvichak salmon fishery
will be adversely affected.
The development of Chikuminuk Lake/Allen River to serve the residents of
the Nushagak system is opposed by some of the residents of the Upper
Nushagak River because of fears relating to subsistence hunting and
fishing. While the proposed development is acceptable to the ADFG, the
ADNR Division of Parks is not in favor of the development because of the
development's non-compatibility with the Park's management plan.
7.3.2.9 Scenarios B-9 and B-IO
Scheme A
The development and implementation of a coal-fired, steam-electric
generating facility in either Dillingham (B-9) or Naknek (B-IO), to serve
the entire study region, is generally acceptable to most residents as long
as acid rain is no threat to fish and wildlife resources. This view is
also held by a number of governmental agencies, particularly the ADFG.
Local residents in Dillingham and Naknek, however, are skeptical about the
availability of economical coal.
7-13
Scheme B
The development and implementation of an oil-fired (diesel) combined cycle
facility in either Dillingham (B-9) or Naknek (B-lO), to serve the entire
region, is expected to be generally acceptable to most residents in the
region.
Scheme C
The development and implementation of a coal gasification combined cycle
facility in either Dillingham (B-9) or Naknek (B-lO) to serve the entire
study region is expected to be generally acceptable to most residents in
the region.
7.3.2.10 Scenarios B-ll and B-12
These scenarios are similar to those presented in Section 7.3.2.11, with
the exception of not tying the Newhalen-Iliamna-Nondalton area with the
rest of the region. This plan is preferred by both Bristol Bay residents
and agencies because it will keep the area north of Iliamna Lake pristine,
with no man-made intrusions.
The local residents in the Newhalen-Iliamna-Nondalton area are generally in
favor of the local Newhalen hydroelectric plan as long as the salmon
fishery is preserved.
7.3.2.11 Scenario B-l3
Scheme A
The development and implementation of the Chikuminuk hydroelectric site to
serve the entire study region, excluding the Newhalen River area, is not
favored by the ADNR Division of Parks, and by some of the residents of the
Upper Nushagak River (Section 7.3.2.5).
7-14
• '.
I
I
I
a
I
I
I
t
I
J
a
I
t
I
I
I
I
I
I
!.
I
The development and implementation of the local Tazimina run-of-river
facility is generally acceptable by both local residents and agency people
as long as the sockeye salmon and sport fisheries are preserved. There is,
however, some opposition from local fishing lodge owners.
Scheme B
The development and implementation of the Chikuminuk hydroelectric site to
serve the entire region, excluding the Newhalen River area, is not favored
by the ADNR -Division of Parks, and by some of the residents of the Upper
Nushagak River (Section 7.3.2.5).
The local residents of the Newhalen River area are generally in favor of
the local Newhalen hydroelectric plan as long as the salmon fishery is
preserved.
7.3.2.12 Scenario B-l4
Scheme A
The development and implementation of the regional Newhalen hydroelectric
site, utilizing a "power only" diversion canal, is opposed by some
residents of the lower Kvichak River and upper Alaskan Peninsula region
primarily because of the concept's potential effects on the salmon
fishery. Local residents in Newhalen, Iliamna, and Nondalton find the
concept acceptable as long as mitigative measures are taken to preserve the
salmon and resident fisheries.
Scheme B
The development and implementation of the regional Newhalen hydroelectric
site, utilizing a large canal to serve as both a power intake and diversion
route for high river flows, is opposed by some residents of the lower
Kvichak River and upper Alaskan Peninsula region. While this concept is
designed to enhance the upstream migration of salmon during high flows, by
lowering the river velocities in the area of the large rapids, a great deal
7-15
of concern has developed (public and agency) regarding the effect of the
canal intake on out-migrating (downstream) salmon smolt and fry.
7.3.2.13 Senario B-15
A general agreement exists among agencies that this energy plan presents
few environmental impacts. Opposition, however, is encountered by the
villages of the Upper Nushagak River, who are opposed to being
interconnected with one another under a diesel-electr ic scheme. Also,
agencies and local residents believe that the proposed transmission
corridor between South Naknek and Egegik should follow the coast if this
energy plan is developed.
7.3.2.14 Scenario B-16
It is generally accepted by agencies that this energy plan exhibits few
adverse environmental impacts. There is, however, opposition by residents
of the Kvichak River system to being interconnected with residents of the
Nushagak River System under a diesel-electric scheme. Some residents of
Naknek resent being connected directly with Dillingham under a diesel
energy plan.
7.3.2.15 Scenario B-17
While there is widespread acceptance of diesel as a source of power
generation, some resentment, questioning, and opposition has been
encountered by having villages interconnected using a diesel energy source.
7.3.2.16 Scenario B-18
Scheme A
The development and implementation of the regional Kontrashibuna concept is
generally opposed by residents of the Village of Nondalton because of the
area I S importance for subsistence hunting and fishing.
the ADFG are generally accepting of development of
Agencies such as
this hydroelectric
project. However, the land status around Kontrashibuna Lake has several
7-16
I
I'
I
I
I ., ,
I
I
t
I
I
I
'1
• I
J
I
I
J
I
I
I
unknowns: 1) In 1915, all lands within one-quarter mile of Kontrashibuna
Lake and all lands within one-quarter mile of the Tanalian River, between
Kontrashibuna Lake and Lake Clark, were withdrawn for the purpose of power
development under Power Site Reserve No. 485 by the Federal Power
Commission; 2) Kontrashibuna Lake, and its entire watershed, are presently
part of a designated wilderness area within the Lake Clark National Park
and Preserve; and 3) The status of native-owned, interim-conveyed, and
native-selected lands is unknown at the present time.
The development and implementation of the regional Tazimina run-of-river
concept is generally of concern to most local as well as Kvichak River and
upper Alaskan Peninsula residents and agency personnel. The primary
concern centers on the effects a hydroelectric facility will have on the
commercial and sport fisheries in the Tazimina River and entire Kvichak
system. The concept is generally acceptable if the salmon fishery is not
harmed.
Scheme B
The community attitudes associated with the development and implementation
of the Kontrashibuna hydroelectric site to serve the entire study region
are the same as those described in Scheme A, above.
7.3.2.17 Scenario B-19
Scheme A
The development and implementation of the Base Plan supplemented by waste
heat conversion is expected to be generally accepted by all communities in
the study region, since it presents no threat to the native subsistence
lifestyle.
Scheme B
The development and implementation of the Base Plan supplemented by wind
systems at Igiugig, Naknek and Egegik is anticipated to be acceptable by
all communities in the study region.
7-17
Scheme C
The development and implementation of the Base Plan supplemented by waste
heat conversion in each village and wind systems at Igiugig, Nanknek and
Egegik is anticipated to be acceptable by all communities in the study
region.
Scheme D
The development and implementation of the Base Plan supplemented by Organic
Rankine Cycle in each village is anticipated to be acceptable by all
communities in the study region.
Scheme E
The development and implementation of the local Tazimina River site for the
Newhalen area, and continuation of the Base Plan supplemented by wind
energy and heat recovery for the remaining Bristol Bay region, is expected
to be acceptable to all communities, as long as the salmon fishery on the
Tazimina River is protected.
7.3.3 Impact on Community Infrastructure
7 . 3 . 3 . 1 Scenario BP-l
No impacts to community infrastructure are expected to occur as a result of
the continuation of present diesel generation practice.
7.3.3.2 Scenario A-I
While the location of the Tazimina site is approximately 15 miles from the
Iliamna-Newhalen area and only about 7 miles from Nondalton, community
impact is expected to be greater in the I liamna-Newhalen area because
transportation and living facilities are located there. Impacts are
expected to be the greatest in the areas of leisure-time activities,
transportation, and schools (if construction workers are permitted to bring
families). Unless special camp facilities are provided, construction
7-18
I
• I
I
I ,
,t
J
t
I
I
I
1
I
• I
I
I
• It
..
••
-
workers will work out of Iliamna. Construction of the regional Tazimina
hydroelectric storage facility is expected to take approximately three
years, with a peak construction labor force anticipated at about 200
personnel. Direct long-term impacts are not anticipated, as the operation
and maintenance of a hydroelectric facility require only a few personnel.
7.3.3.3 Scenario B-1
This energy plan is expected to have no detrimental impacts to the
community infrastructure within the study region.
7.3.3.4 Scenario B-2
The development and implementation of the Kukaklek hydroelectric site to
serve the study region, excluding the Newhalen River area, is not expected
to significantly impact the community infrastructure in any of the study
region villages. The proposed Kukaklek construction site, located
approximately 10 miles east of the village of Igiugig on the south shore of
I liamna Lake, will consist of a barge unloading facility, an airfield
capable of landing Hercules aircraft, an access road to Kukaklek Lake, and
a construction camp. The construction of the Kukaklek facility is expected
to take two years, with a construction labor force anticipated to peak at
150 personnel. The facility is intended to be self-sufficient and isolated
from study region villages.
The development and implementation of a local 0.2 MW) Newhalen River
hydroelectric site is expected to affect the infrastructure of Newhalen and
Iliamna in much the same way as energy Scenario A-I (Section 7.3.3.2), but
to a lesser extent, since there will be fewer workers involved. The
construction of the local Newhalen facility is expected to take two years
to complete, with a peak construction force of 150 personnel. Any direct
long-term impacts are not anticipated.
7.3.3.5 Scenario B-3
The development and implementation of the Kukaklek hydroelectric site to
serve the lower Kvichak River and upper Alaskan Peninsula region is not
7-19
expected to have any significant impact on community infrastructure in any
village in the study region. The construction of this short penstock
concept is expected to be completed in two years, and have a peak
construction labor force of 125 personnel.
The development and implementation of a local Newhalen River hydroelectric
site is expected to affect the community infrastructure in Newhalen and
Iliamna much in the same manner as energy Scenario A-I, (Section 7.3.3.2)
but to a lesser extent. Any direct long-term impacts are not anticipated.
The development and implementation of the Chikuminuk hydroelectic site to
serve the Nushagak River system is not expected to have any significant
impacts upon community infrastructure in the region. Because of the site's
remote location, no road will be constructed for access from existing
villages. An airfield will be constructed to bring in supplies, much the
same as the proposed airfield at the Kukaklek site. A 12 to 13 mile access
road will connect the airfield, which will be located outside the
Wood-Tikchik State Park, to the powerhouse site on the Allen River, near
the Chikuminuk Lake outlet. Possible effects on community infrastructure
could take place in Dillingham during the leisure time of construction
workers. Any direct long-term impacts, however, are not anticipated.
7.3.3.6 Scenarios B-4, B-6, B-7
These energy plans have been dropped from further evaluation (Section
7.3.2.6).
7.3.3.7 Scenario B-5
The development and implementation of. both the Kukaklek and Chikuminuk
hydroelectric sites, because of their remoteness and isolation, are not
expected to significantly impact the community infrastructure of any
villages within the study region. Each site will use aircraft as the
primary means of access, with the construction camps being entirely
self-sufficient. The construction of the Kukaklek (long penstock) concept
is expected to take two years to complete, with a peak construction labor
force of 125 personnel. The construction of the Chikuminuk hydroelectric
7-20
, ..
,
I
I
I ,
I
I
I
I
I
~
I , ...
I
I
I
I
I
1
.. ..
I .. •
t
.-..
I
;
facility is expected to take three years to complete with a peak
construction labor force of 150 personnel.
The development and implementation of a local (1. 2 MW) Tazimina
run-of-river hydroelectric concept is expected to have a similar impact on
the community infrastructure of Newhalen and Iliamna as anticipated for
energy Scenario A-I (Section 7.3.3.2), but to a much lesser extent. The
construction of the local Tazimina run-of-river facility is expected to be
completed in two years, with a peak construction work force of 100
personnel. A direct long-term impact is not anticipated.
7.3.3.B Scenario B-B
The development and implementation of the Chikuminuk hydroelectric site to
serve the Nushagak River system is not expected to have a significant
impact upon community infrastructure in the study region. The only
potential effect would be as a result of extended leisure-time activites
from contruction workers in Dillingham; however, no direct long-term
impacts are expected.
The development and implementation of the Tazimina River hydroelectric site
to serve the Kvichak River and Upper Alaskan Peninsula region is expected
to have a direct short-term effect on the community infrastructure of the
villages of Newhalen and Iliamna. The village of Nondalton, while located
closer to the Tazimina site, is expected to receive little or no impact,
primarily due to its lack of facilities and access . Pr imary impact in
Newhalen and Iliamna is expected to result from transportation and
leisure-time activities. Schools are expected to be affected only if
construction workers are permitted to bring families into the area. New
lodges are expected to be constructed in Iliamna to house the construction
labor force. The construction of the Tazimina hydroelectric facility is
expected to be completed in three years, with a peak construciton labor
force of 175 personnel .
7-21
7.3.3.9 Scenarios B-9 and B-10
Scheme A
The development and implementation of a coal-fired, steam-electric
generating facility in either Dillingham (B-9) or Naknek (B-10) is expected
to result in both short-and long-term effects on community infrastructure
in these villages. The construction of such a facility, with its
appurtenant structures, is expected to involve a considerable work force
which will be housed in, or near, these villages. Considerable imported
skilled labor will be required. As a result, schools, commercial
establishments, and housing are expected to be impacted considerably.
After construction, a minimum of 20 personnel are expected to be required
to maintain and operate the facility. These will be skilled workers and
may have to be imported into the area, requiring additional housing,
schools, and commercial facilities.
Scheme B
The development and implementation of an oil-fired (diesel) combined cycle
facility in either Dillingham (B-9) or Naknek (B-10) to serve the entire
study region, is expected to have less effect on community infrastructure
than anticipated for Scheme A, a coal-fired, steam-electric generating
facility.
Scheme C
The development and implementation of a coal gasification combined cycle
facility in either Dillingham (B-9) or Naknek (B-10) to serve the entire
study region, is expected to. have similar effects on community
infrastructure as anticipated for Scheme A, a coal-fired, steam-electric
generating facility.
7.3.3.10 Scenarios B-11 and B-12
The development and implementation of a coal-fired, steam-electric
generating facility in either Dillingham (B-11) or Naknek (B-12) to serve
7-22
I
I
I
I
f
I
I
J
I
I
I
J
I
I
I
I
I
r
if , . '
r ..
the entire study region, except the Newhalen River area, is expected to
have the same general effects on community infrastructure as anticipated
for Scenarios B~9 and B~10 (Section 7.3.3.11).
The development and implementation of a local Newhalen River hydroelectric
site is expected to have similar effects upon community infrastructure as
Scenar io A -1 (Sect ion 7.3 . 3 .2) , but to a somewhat lesser extent. Any
direct long-term impact is not anticipated.
7.3.3.11 Scenario B-13
Scheme A
The development and implementation of the Chikuminuk hydroelectric site to
serve the study region, except the Newhalen River area, is not expected to
have any significant effects on community infrastructure within the study
region. It is anticipated that a construction camp will be set up near the
site and that material and supplies will be flown in. The construction of
the Chikuminuk hydroelectric facility (16 MW) is expected to be completed
in three years, with a peak construction labor force of 175 personnel.
The development and implementation of a local Tazimina run-of~river
facility is expected to have some effect on the community infrastructure of
the Newhalen River area. Iliamna is anticipated to receive the most impact
since it is the transportation and lodging center for the area. Any
long-term impacts, however, are not anticipated .
Scheme B
The development and implementation of the Chikuminuk hydroelectric site to
serve the study region, except for the Newha1en River area, is not expected
to have any significant effects on community infrastructure within the
study region.
The development and implementation of a local Newhalen River hydroelectric
site is expected to have similar effects upon community infrastructure as
7-23
anticipated for Scenario A-1 (Section 7.3.3.2), but to a lesser extent.
Any direct long-term impact is not expected.
7 .3.3. 12 Scenario 14
Scheme A
The development and implementation of the regional Newhalen hydroelectric
site, utilizing a "power only" diversion canal, is expected to have impacts
on the community infrastructure of Newhalen and Iliamna similar to those
anticipated for the regional Tazimina hydroelectric concept, described in
Section 7.3.3.2. The construction of this facility is expected to be
completed in a somewhat shorter period of time, and require a somewhat
smaller peak construction labor force, than the regional Newhalen
hydroelectric concept, utilizing a large canal, described in Scheme B.
Scheme B
The development and implementation of the regional Newhalen hydroelectric
site, utilizing a large canal which serves as both a power intake and a
divers ion route for high river flows, is expected to have impacts on
community infrastructure in Newhalen and Iliamna similar to those
anticipated for the regional Tazimina hydroelectric concept, described in
Section 7.3.3.2. The construction of this facility is expected to be
completed in three years, having a peak construction labor force of 250
personnel.
7.3.3.13 Scenario B-15
The development and implementation of diesel generating centers at
Dillingham, Naknek, New Stuyahok, and Iliamna are not expected to result in
any significant impacts, short-or long-term, to the community
infrastructure of those villages. The same is expected to hold true for
wind systems to be constructed at Igiugig, Naknek, and Egegik.
7-24
I
I
I
I
I ,
I
I
I
I
I
I
a •
I
I
I
I
I
I
\~
7.3.3.14 Scenario B-16
The development and implementation of a diesel generating center, either at
Dillingham or Naknek, to serve the lower Kvichak and lower Nushagak River
systems may possibly have some minor impact on the community infrastructure
of those villages, but for a short-term, only. No direct long-term impact
is expected. There may, however, be a minor impact resulting from the
installation of wind systems at Igiugig, Naknek, and Egegik, since skilled
labor will be required for the operation and maintenance of these
facilities.
The development and implementation of diesel generating centers in New
Stuyahok and Newhalen are not expected to result in any significant impacts
to the community infrastructure of those villages.
7.3.3.15 Scenario B-17
The development and implementation of two interconnected diesel generating
centers at Dillingham and Naknek, each capable of serving the entire study
region needs, is expected to have only a minor impact on the community
infrastructure of each of those villages. However, this impact may
possibly be long-term, since skilled operators will be required to maintain
the facilities. There may also be a minor impact on the community
infrastructure of Igiugig and Egegik as a result of the installation of
wind energy systems there.
7.3.3.16 Scenario B-18
Scheme A
Community impact is expected to be spread over two areas under this energy
plan. While the majority of the construction will take place on the
Tanalian River near Port Alsworth, there will still be considerable
activity taking place on the Tazimina River. Community impacts are
expected to be less at I liamna than at Port Alsworth, at least during
construction. It is anticipated that a construction camp will have to be
established at Port Alsworth. If construction workers are permitted to
7-25
bring families, it is likely that the school in Newhalen will be affected
considerably. Otherwise, the only other significant effects will result
from leisure-time activities, primarily at Iliamna. There is also the
possibility that barge facilities would have to be constructed at Port
Alsworth and at the terminus of the present Newhalen-Nondal ton Road. The
construction of the Kontrashibuna hydroelectric facility (16 MW) is
expected to be completed in 3 years, with a peak construction labor force
of 250 personnel. Any direct long-term impacts are not anticipated.
Scheme B
The impacts on community infrastructure associated with the development of
the Kontrashibuna hydroelectric site to serve the entire study region are
the same as those described in Scheme A, above.
7.3.3.17 Scenario B-19
Scheme A
There are not expected to be any adverse impacts or community
infrastructure associated with the development and implementation of this
energy plan.
Scheme B
There are expected to be only minor impacts on community infrastructure
resul ting from the development and implementation of wind systems in the
villages of Igiugig and Egegik. Impacts in the remaining villages, as a
result of implementing the Base Plan, are expected to be minimal, including
those for Naknek, where wind systems will also be installed.
Scheme C
The impacts on community infrastructure associated with the development and
implementation of this energy plan are expected to be similar to those
described for Scheme B, above.
7-26
• ..
I
I
I
I ,
I
I
I
I
I
I
t
J
I
I
I
I
I
--, ----------------------------------........ ---------------
I
I
t
I
1
I
t
,. ..
Scheme D
There are not expected to be any adverse
infrastructure associated with the development
individual diesel generating units, supplemented
Cycle, for each village in the study region.
Scheme E
impacts on community
and implementation of
with Organic Rankine
There are not expected to be any adverse impacts on community
infrastructure resulting from the development and implementation of the
Base Plan, supplemented by wind energy and waste heat recovery, for the
study region (less the Newhalen area).
The impact on community infrastructure associated with the development and
implementation of the local Tazimina run-of-river facility for the Newhalen
area is described in Section 7.3.3.7.
7.3~4 Timing in Relation to Other Capital Projects
7.3.4.1 Scenario BP-1
The development and implementation of this energy plan appears to be only
slightly dependent upon the timing of any future capital projects. Some of
these projects are: 1) housing projects planned for Dillingham, Nondalton,
Newhalen and Aleknagik; 2) a new fish processing plant in Dillingham; and
3) the completion of a HUD project in Clarks Point.
7.3.4.2 Scenario A-1
The development and implementation of a regional Tazimina River
hydroelectric storage concept does not appear to be dependent upon the
timing of any identified capital projects proposed for the Newhalen River
area or for the study region in general. A transmiss ion line connecting
Newhalen and Nondalton is assumed to have been constructed prior to
development of this concept. If a road should be constructed between
Newhalen and Nondalton as has been suggested, no timing conflicts are
expected.
7-27
7.3.4.3 Scenario B-1
The development and implementation of this energy plan does not appear to
be dependent upon the timing of any identified capital projects proposed
for the study region.
7.3.4.4 Scenario B-2
The development and implementation of the regional Kukaklek hydroelectric
site does not appear to be dependent upon the timing of any identified
capital projects proposed for the study region.
The development and implementation of the local Newhalen hydroelectric site
may have an effect on the timing of the proposed hous ing project for
Newhalen. The comment under Scenario A-I regarding a transmission line or
road between Newhalen and Nondalton applies to this scenario.
7.3.4.5 Scenario B-3
The development and implementation of the Kukaklek hydroelectric site to
serve the lower Kvichak River and upper Alaskan Peninsula region does not
appear to be dependent upon the timing of any identified capital projects
proposed for the study region.
The development and implementation of the Chikuminuk hydroelectric site to
serve the Nushagak River region does not appear to be dependent upon the
timing of any identified capital projects proposed for the study region.
The development and implementation of the local Newhalen hydroelectric site
may have an effect on the timing of the proposed housing project scheduled
for Newhalen. The comment under Scenario A-I regarding a transmission line
or road between Newhalen and Nondalton applies to this scenario.
7.3.4.6 Scenarios B-4, B-6 and B-7
These energy plans have been dropped from further evaluation (Section
7.3.2.6).
7-28
, iii
I
I ,
I
I
I
I
I
I
I
I
I
I
I
I
I
t
-
".
• ..
7.3.4.7 Scenario B-5
The development and implementation of the Kukaklek hydroelectric site to
serve the lower Kvichak River and Upper Alaskan Peninsula region does not
appear to be dependent upon the timing of any identified capital projects
proposed for the study region.
The development and implementation of the Chikuminuk hydroelectric site to
serve the Nushagak River region does not appear to be dependent upon the
timing of any identified capital projects proposed for the study region.
The development and implementation of the local Tazimina run-of-river site
may have an effect on the timing of the proposed housing projects scheduled
for Newhalen and Nondalton. The comment under Scenario A-l regarding a
transmission line or road between Newhalen and Nondalton applies to this
scenario.
7.3.4.8 Scenario B-8
The development and implementation of the Tazimina River hydroelectric site
to serve the Kvichak River and upper Alaskan Peninsula region may have an
effect on the timing of the proposed housing projects scheduled for
Newhalen and Nondalton. The comment under Scenario A-l regarding a
transmission line or road between Newhalen and Nondalton applies to this
scenario.
The development and implementation of the Chikuminuk hydroelectric site to
serve the Nushagak River region does not appear to be dependent upon the
timing of any identified capital projects proposed for the study region.
7.3.4.9 Scenarios B-9 and B-lO
Scheme A
The development and implementation of a coal-fired, steam-electric
generating facility to serve the entire study region may possibly affect
7-29
the following proposed capital projects if located in or near Dillingham
(B-9): 1) a new fish processing plant in Dillingham; 2) a new housing
project for the city of Dillingham, 3) paving of the runway at the
Dillingham Airport; and 4) paving of the main road into Dillingham.
The development and implementation of a coal-fired, steam-electric
generating facility to serve the entire study region may affect the
following proposed capital projects if located in or near Naknek (B-10):
1) possible airport reconstruction at Naknek, 2) construction of an airport
apron at King Salmon, and 3) a road from Naknek and King Salmon to South
Naknek via a bridge over the Naknek River at Savonoski.
Scheme B
The development and implementation of an oil-fired (diesel) combined cycle
generating facility in either Dillingham (B-9) or Naknek (B-10) to serve
the entire study region, is anticipated to have similar affects on the same
proposed capital projects listed in Scheme A.
Scheme C
The development and implementation of a coal gasification combined cycle
facility in either Dillingham (B-9) or Naknek (B-10) to serve the entire
study region, is anticipated to have similar effects on the same proposed
capital projects listed in Scheme A.
7.3.4.10 Scenarios B-11 and B-12
The development and implementation of a coal-fired, steam-electric
generating facility in either Dillingham (B-ll) or Naknek (B-12) to serve
the study region, except the Newhalen River area, does not appear to be
dependent upon the timing of any identified capital projects proposed for
the study region. However, the development of the energy plan may affect
those capital projects listed in Section 7.3.4.9.
The development and implementation of the local Newhalen hydroelectric site
may have an effect upon the timing of the housing project scheduled for
7-30
I
J
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
t
-
Newhalen. The comment under Scenario A-I regarding a transmission line or
road between Newhalen and Nondalton applies to this scenario.
7.3.4.11 Scenario B-13
Scheme A
The development and implementation of the Chikuminuk hydroelectric site to
serve the study region, except for the Newhalen River area, does not appear
to be dependent upon the timing of any identified capital projects proposed
for the study region.
The development and implementation of the local Tazimina run-of-river site
may have an effect upon the timing of the project housing projects
scheduled for Newhalen and Nondalton. The comment under Scenario A-I
regarding a transmission line or road between Newhalen and Nondalton
applies to this scenario.
Scheme B
The development and implementation of the Chikuminuk hydroelectric site to
serve the study region, except for the Newhalen River area, does not appear
to be dependent upon the timing of any identified capital projects proposed
for the study region.
The development and implementation of the local Newhalen hydroelectric site
may have an effect upon the timing of the housing project scheduled for
Newhalen. The comment under Scenario A-I regarding a transmission line or
road between Newhalen and Nondalton applies to this scenario.
7.3.4.12 Scenario B-14
Scheme A
The development and implementation of the regional Newhalen River
hydroelectric site, utilizing a llpower only" canal, may have an effect upon
the timing of the housing project proposed for Newhalen.
7-31
Scheme B
The development and implementation of the regional Newhalen River
hydroelectric site, utilizing a large canal for both power intake and high
river flow routing, may have an effect upon the timing of the housing
project proposed for Newhalen.
7.3.4.13 Scenario B-15
The development and implementation of a diesel-electric generating center
in Dillingham to serve the lower Nushagak River region may be affected by
the timing of the following identified proposed capital projects: 1) a new
fish processing plant in Dillingham, 2) housing projects for Dillingham and
Aleknagik, 3) completion of the HUD project in Clarks Point, and 4) paving
of the airport runway and main road in Dillingham.
The development and implementation of a diesel-electric generating center
in New Stuyahok to serve the upper Nushagak River region does not appear to
be dependent upon the timing of any identified capital projects proposed
for the study region.
The development and implementation of a diesel-electric generating center
in Naknek, with supplemental wind energy systems in Igiugig, Naknek, and
Egegik, to serve the lower Kvichak River and upper Alaskan Peninsula region
may be affected by the timing of the following identified capital projects
proposed for the region: 1) possible airport reconstruction at Naknek; 2)
construction of an airport apron at King Salmon; and 3) a road from Naknek
and King Salmon to south Naknek via a bridge over the Naknek River at
Savonoski.
7.3.4.14 Scenario B-16
The development and implementation of two independent but interconnected
diesel-electric generating centers in Dillingham and Naknek, with
supplemental wind energy systems in Igiugig, Naknek, and Egegik, to serve
the lower Nushagak River region, lower Kvichak River, and upper Alaskan
7-32
• •
I
I
f
I
I
I
I
I
I
I
I
I
I
I
I
I
,-, ..
r
lit -
Peninsula region, may possibly be affected by the timing of some of the
identified capital projects listed in Section 7.3.4.13.
The development and implementation of a diesel-electric generating center
in New Stuyahok to serve the upper Nushagak River region does not appear to
be dependent upon the timing of any identified capital projects proposed
for the study region.
7.3.4.15 Scenario 17
The development and implementation of two independent but interconnected
diesel-electric generating centers in Dillingham and Naknek, supplemented
by wind energy systems in Igiugig, Naknek, and Egegik, to serve the entire
study region may possibly be affected by the timing of some of the
identified capital projects described in Section 7.3.4.13.
7.3.4.16 Scenario B-18
Scheme A
The development and implementation of this energy plan appears to be only
slightly dependent upon the timing of any identified capital projects
proposed for the study region.
Scheme B
The development and implementation of the Kontrashibuna hydroelectric site
to serve the entire study region is not expected to be affected by the
timing of any other capital projects proposed for the study region.
7.3.4.17 Scenario B-19
Scheme A
The development and implementation of this energy plan appears to be only
slightly dependent upon the timing capital projects scheduled for the
region. These projects are listed in Section 7.3.4.1.
7-33
Scheme B
The development and implementation of this energy plan is expected to
relate to the timing of other capital projects similar to the Base Plan
described in Section 7.3.4.1.
Scheme C
The development and implementation of this energy plan is expected to
relate to the timing of other capital project similar to the Base Plan
described in Section 7.3.4.1.
Scheme D
The development and implementation of this energy plan appears to be only
s lightly dependent upon the timing of other capital projects in the region.
Scheme E
The development and implementation of the Base Plan, supplemented by wind
energy and waste heat recovery, for the study region, except the Newhalen
area, is not expected to be affected by the timing of other proposed
capital projects scheduled for the region. However, the development and
implementation of the local Tazimina run-of-river hydroelectric facility
may have an effect upon the timing of the proposed housing projects
scheduled for Newhalen and Nondalton. The comment under Scenario A-1
regarding a transmission line or road between Newhalen and Nondalton
applies to this scenario.
7.3.5 Air Quality
7.3.5.1 Scenario BP-1
The development and implementation of this energy plan, which involves
individual village diesel-electric generation centers, is not expected to
significantly impact the air quality of the region, except in the immediate
7-34
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
c
r ..
t
• ..
• -
area of the generation center. While individual diesel-electric generators
are not of the size which would trigger a state air pollution permit
requirement, some units with a generation capability in excess of 1,500 kW,
may be large enough to trigger a federal Prevention of Significant
Deterioration (PSD) permit requirement for nitrogen oxide (NO) emissions. x
The largest units considered in this energy plan, however, are 1,500 kW and
these will be located at Dillingham and Naknek only.
7.3.5.2 Scenario A-2
The development of the Tazimina River hydroelectric site for regional power
needs is expected to have some minor impacts on air quality during the
during the construction phase. These impacts are expected to consist of
relatively small
nitrogen oxides
amounts of sulfur dioxide (S02)' carbon
(NO ), hydrocarbons (HC) and particulate x
monoxide (CO),
matter emitted
from gasoline-and diesel-powered construction equipment. Fugitive dust is
expected to result from the
along unpaved roads. Other
clearing of land and movement of
than occasional temporary impacts
equipment
on areas
adjacent to the construction site, ambient air quality outside the site
boundary is not anticipated to be significantly affected by gaseous
emissions from construction equipment.
While fugitive dust emissions may sometimes cause a local impact, the
degree of impact will depend upon day-to-day weather and the intensity of
construction activity. Various control techniques will be implemented as
necessary to meet state criteria, which require that reasonable precautions
be taken to prevent airborne particulate matter. There is expected to be
no impact on air quality from this hydroelectric facility during its
operational phase .
7.3.5.3 Scenario B-1
The development and implementation of a transmission intertie from Beluga
to serve the electrical energy needs of the entire study region is not
expected to create any significant air quality impacts in the Bristol Bay
region .
7-35
7.3.5.4 Scenario B-2
The development of this energy plan is expected to have similar impacts on
air quality during construction as anticipated for the Tazimina River
regional hydroelectric site, described in Section 7.3.5.2. There are
expected to be no significant impacts on air quality resulting from the
hydroelectric facilities during their operational phase.
7.3.5.5 Scenario B-3
The development of this energy plan is expected to have similar impacts on
air quality during construction as anticipated for the Tazimina River
regional hydroelectric site, described in Section 7.3.5.2. There are
expected to be no significant impacts on air quality resulting from these
hydroelectric facilities during the operational phase.
7.3.5.6 Scenarios B-4, B-6, and B-7
These energy plans have been dropped from further evaluation (Section
7.3.2.6).
7.3.5.7 Scenario B-5
The development of this energy plan is expected to have similar impacts on
air quality during the construction phase as anticipated for the Tazimina
River regional hydroelectric site, described in Section 7.3.5.2. There are
expected to be no significant impacts on air quality resulting from these
hydroelectric facilities during the operational phase.
7.3.5.8 Scenario B-8
The development of this energy plan is expected to have similar impacts on
air quality during the construction phase as anticipated for the Tazimina
River regional hydroelectric site, described in Section 7.3.5.2. There are
expected to be no significant impacts on air quality reSUlting from these
hydroelectric facilities during the operational phase.
7-36
I
I
I
I
I
I
I
I
I
I
I
I ,
I
I
I
I
I
I
,.. ...
'!IIi
-•
...
7.3.5.9 Scenarios B-9 and B-IO
Scheme A
The development of a coal-fired steam-electric generating facility in
either Dillingham (B-9) or Naknek (B-IO) to serve the entire study region
is expected to have similar impacts on air quality during the construction
phase as anticipated for the Tazimina River regional hydroelectric site
described in Section 7.3.5.2.
Potential air quality impacts resulting from the operation of a coal-fired
facility are expected to be minimal. However, some pollution control
equipment, probably in the form of wet scrubbers, will be necessary for the
control of particulates and S02' Other gaseous emissions are expected to
only have a minimum effect on the ambient air quality and should not
require control devices. Fugitive dust from both the coal pile storage and
solid waste disposal areas will also require mitigative measures. The
proximity of the Mt. Katmai National Park and Preserve, as a potential
mandatory Class I air quality area, is not expected to be affected by the
emissions from a relatively small coal-fired steam-electric generating
facility located in Naknek. No other Class I areas exist, or are potential
candidates, in or near the Bristol Bay region.
Scheme B
The development and of an oil-fired (diesel) combined cycle generating
facility in either Dillingham (B-9) or Naknek (B-10), to serve the entire
study region, is expected to have similar impacts on air quality as
anticipated in Scheme A. However, S02 stack emissions could be
significantly less, but will be dependent upon the quality of the fuel
oil. Fugitive dust emissions are expected to be minimal since there will
be no coal storage and handling areas.
Scheme C
The development and implementation of a coal gasification combined cycle
facility in either Dillingham (B-9) or Naknek (B-IO), to serve the entire
7-37
study region, is expected to have similar impacts on air quality as
anticipated in Scheme A. However, the combustion of the low BTU gas for
electric generation will result in fewer gaseous pollutants being emitted
to the atmosphere under this concept.
7.3.5.10 Scenarios B-11 and B-12
The development and implementation of a coal-fired, steam-electric
generating facility in either Dillingham (8-11) or Naknek (B-12) to serve
the study region, except the Newhalen River area, is expected to have
similar impacts on air quality during the construction phase as anticipated
for the Tazimina River regional hydroelectric site described in Section
7.3.5.2. Potential air quality impacts resulting from operation of the
facility are expected to be the same as those described in Section 7.3.5.9.
The development of the Newhalen River hydroelectric site to serve the
Newhalen River area is expected to have similar impacts on air quality
during the construction phase as anticipated for the Tazimina River
regional hydroelectric site described in Section 7.3.5.2. There are
expected to be no significant impacts on air quality resulting from the
hydroelectric facilities during the operational phase.
7.3.5.11 Scenario B-13
Scheme A
The development of this energy plan is expected to have similar impacts on
air quality during the construction phase as anticipated for the Tazimina
River regional hydroelectric site described in Section 7.3.5.2. There are
expected to be no significant impacts on air quality resulting from these
hydroelectric facilities during their operational phase.
Scheme B
The development and implementation of this energy plan is expected to have
similar impacts on air quality as anticipated in Scheme A, above.
7-38
I
I
I
I
I ,
I
I
I
I
I
I
I
I
I
I
I
I
I
..
7.3.5.12 Scenario B-14
Scheme A
The development of the Newhalen River regional hydroelectric site,
utilizing a "power only" canal, is expected to have similar impacts on air
quality during the construction phase as those anticipated for the Tazimina
River regional hydroelectric site described in Section 7.3.5.2. There are
expected to be no significant impacts on air quality resulting from this
hydroelectric facility during the operational phase.
Scheme B
The development of the Newhalen River regional hydroelectric site,
utilizing a large canal for both power intake and high river flow routing,
is expected to have similar impacts on air quality during the construction
phase as those anticipated for the Tazimina River regional hydroelectric
site described in Section 7.3.5.2. There are expected to be no significant
impacts on air quality resulting from this hydroelectric facility during
the operational phase.
7.3.5.13 Scenario B-15
The development and implementation of this energy plan, with four
diesel-electric generating centers proposed for the study region, is
expected to have slightly more impact on air quality than the Base Case
energy plan described in Section 7.3.5.1. However, because of the relative
size of the diesel generators (generally less than 1,500 kW) and the small
number required at each generating center, the impact on the ambient air
quality is expected to be confined to a relatively small area near the
generation center. Normal dispersion by wind should be adequate to prevent
the build-up of gaseous emissions.
There may be some noise effects in the immediate area of wind generating
facilities located in Igiugig, Naknek, and Egegik. However, these impacts
are expected to be minor .
7-39
7.3.5.14 ScenarioB-16
The development and implementation of this energy plan, which proposes a
diesel-electric generation scheme as described in Section 7.3.2.14, is
expected to have a similar impact on air quality as anticipated for the
energy plan described in Section 7.3.5.13.
7.3.5.15 Scenario B-17
The development and implementation of this energy plan, with two
independent but interconnected diesel-electric generating centers serving
the entire study region, is expected to have moderate but localized impacts
on the ambient air quality at these centers (Dillingham and Naknek).
Nitrogen oxide emissions are expected to be of primary concern, and could
trigger a PSD if concentrations become high enough.
Noise impacts, associated with wind generating facilities in Igiugig,
Naknek, and Egegik, are expected to be both localized and minor.
7.3.5.16 Scenario B-18
Scheme A
The development of this energy plan is expected to have similar impacts on
air quality during construction as anticipated for the Tazimina River
regional hydroelectric site described in Section 7.3.5.2. Additional
mitigative measures, however, may have to be taken to maintain visibility
requirements because of Kontrashibuna's presence in the Lake Clark National
Park and Preserve designated wilderness area.
significant impact on air quality resulting
facilities during their operational phase.
Scheme B
There is expected to be no
from these hydroelectric
The development and implementation of the Kontrashibuna hydroelectric site
to serve the entire region is expected to have similar impacts on air
7-40
I
I
I
I
I
I
I
I
I
I
I
I
I
I,
I
I
...
-
...
,-
..
" ..
-.. -
quality as anticipated for the regional Tazimina hydroelectric facility
described in Section 7.3.5.2.
7.3.5.17 Scenario B-19
Scheme A
The development and implementation of this energy plan is expected to have
similar impacts on air quality as anticipated for the Base Plan (Section
7.3.5.1).
Scheme B
The development and implementation of this energy plan is expected to have
similar impacts on air quality as anticipated for the Base Plan (Section
7.3.5.1) for the diesel generators, and similar to Scenario B-15 (Section
7.3.5.1) for the supplemental wind energy facilities in Igiugig, Naknek,
and Egegik.
Scheme C
The development and implementation of this energy plan is expected to have
similar impacts on air quality as anticipated for Scheme B, above.
Scheme D
The development and implementation of this energy plan is expected to have
similar impacts on air quality as anticipated for the Base Plan (Section
7.3.5.1).
Scheme E
The development and implementation of this energy plan (Base Plan
supplemented by wind energy and waste heat recovery) is not expected to
have any adverse effects on ambient air quality of the Newhalen area,
except for some localized short-term impacts during the construction phase
of the local Tazimina run-of-river hydroelectric facility. These impacts
7-41
...
are expected to result from fugitive dust from the access road to the site,
gaseous emissions from construction equipment, and noise from construction
equipment and resultant. activities.
The the remainder of the study region, impacts on air quality are
anticipated to be similar to those expected for the Base Plan described in
Section 7.3.5.1.
7.3.6 Water Quality
7.3.6. I Scenario BP-1
The development and implementation of this energy plan is expected to have
no significant impact upon water quality, either surface or subsurface,
within the study region. Mitigative measures, however, such as the lining
and diking of fuel storage areas should be required in the event of leaks
or spills.
7 . 3. 6 . 2 Scenar io A-1
The development of the Tazimina River regional hydroelectric site requires
the construction of a large rockfi11 dam for water storage purposes. While
construction details have not yet been developed, it is anticipated that
short-term. construction-induced erosion will be a source of potential
impact to water quality, and could continue until all areas are
stabilized. Erosion is generally the source of siltation, turbidity, and
increased nutrients in rivers downstream of such activity. The magnitude
and duration of these effects will probably vary from area to area, but are
generally proportional to the amount of erosion, stream gradient, distance
from the disturbance, and erosion control techniques. There exists also,
the possiblity of hydrogen sulfide contamination generated by anaerobic
decomposition of inundated plants. Further detail on the impacts of
construction and operational activity to water quality at the Tazimina
River regional hydroelectric site is contained in Appendix G, Section 3.2.
The following special study was initiated to analyze the effects that a
7-42
• ...
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
... ,
regional storage reservoir located on the Tazimina River above the falls
would have on the temperature regime in the river below the falls .
RESERVOIR TEMPERATURE STUDY
The construction of a water storage reservoir on the Tazimina River is
expected to have some effect on the natural temperature regime in the river
downstream of the impoundment. A preliminary investigation has been
temperature differences undertaken to determine the magnitude of the
between releases from a reservoir and naturally occurring water
temperatures. The mathematical model used in this investigation was the
SWEC version of the "MIT Stratified Reservoir Model", which was originally
developed by Ryan and Harleman (Ref 1). This model uses climatological
data in conjunction with flow rates, inlet water temperatures, and
reservoir geometry to predict the outlet water temperatures and the thermal
stratification within the reservoir.
Little site-specific data were available for use in this study. In the
selection of data sources, efforts were made to use data which most closely
represented the conditions expected to occur at the site. The use of
non-site-specific data introduces a degree of uncertainty in the results of
any investigation. The results presented here are intended solely to
indentify the magnitude of potential temperature problems associated with a
storage reservoir. As site-specific data becomes available, more refined
analyses and predictions of these impacts will be made. Climatological
data used in the model was based on the historical records from King
Salmon, Alaska. The inlet water temperatures used were measured by the
USGS on the Snake River near Dillingham during the 1975 water year. Flow
rates were those reported by Dames & Moore for the Tazimina River, and by
SWEC for the reservoir operation.
Preliminary results indicate that during the spring and early summer months
the reservoir will warm quickly and the outlet temperture will be greater
than the inlet by as much as 30 C. During this time period the only
discharge flow was assumed to be through the penstock .
7-43
During the mid-summer months, water will be discharged through the penstock
as well as over a spillway. The reservoir .will exhibit a distinct
stratification during this time, and as a result, the penstock inlet
temperature will be lower than the ambient temperature while the spillway
inlet temperature will be greater than ambient. The maximum 6T between the
spillway flow temperature and the ambient river temperature is estimated to
be about SoC. The maximum 6T between the penstock temperature and the
ambient river is estimated to be about _2 o C.
During the early autumn months, the stratification in the reservoir begins
to break down and isothermal conditions begin to develop. As a result, the
discharge temperatures for the penstock and spillway begin to approach each
other until finally they coincide when isothermal conditions are reached.
Discharge temperatures normally run slightly below ambient temperatures
during this period until winter conditions set in. The maximum 6T expected
I
I
I
I
I
I
I
during the autumn is estimated to be about -2oC. II
During the winter months when the reservoir will be ice-covered, discharge
temperatures will be close to DoC. This discharge temperature will be
essentially the same as the ambient river temperature.
These findings represent preliminary results based on non-site-specific
data and do not take into consideration heating or cooling of the discharge
water as it travels downstream. When more representative data is available
from on-going site studies, this analysis will be updated and the effects
of heat transfer to the atmosphere as the discharge flows travel downstream
will be included through the use of an instream temperature model.
7.3.6.3 Scenario B-1
The development and implementation of this energy plan is not expected to
have any significant impact on water quality in the study region.
7-44
I
I
I
I
I
I
I
I
I
I
• II
... ..
... ..
.. ..
III ..
..
-
III
7 . 3 . 6 . 4 Scenario B-2
The development of the Kukaklek hydroelectric site to serve the study
region, except the Newhalen River area, will require the construction of a
buried penstock, approximately 9 miles long, from Kukaklek Lake northward
to Iliamna Lake. The construction of this penstock will traverse Pecks
Creek and several of its tributaries and is expected to affect water
quality similar to that described in Section 7.3.6.2 for the Tazimina
River. The construction of a flow regulating structure on the Alagnak
River below the outlet of Kukaklek Lake is also expected to affect
downstream water quality, but only during construction. It is expected to
be less than what is anticipated at either the Tazimina or Kontrashibuna
regional hydroelectric sites. The decreased flow in the Alagnak River
resulting from the diversion of flow through the penstock could result in
effects on water quality similar to those presented in Section 7.3.6.16.
Other operational and maintenance activities are expected to have little
effect on the water quality of Kukaklek Lake and Pecks Creek.
The development of the Newhalen River local hydroelectric site is expected
to result in some short-term impacts on water quality in the form of
increased turbidity, siltation, and increased nutrients. The
construction-induced erosion impacts, as well as other potential impacts on
water quality during the construction phase are expected to be much less
than those impacts described for the Tazimina River, for which a dam is to
be constructed. Division via a tunnel in rock is expected to have only a
minimal impact. No impacts on water quality are expected during the
operation and maintenance phase of this hydroelectric facility.
7.3.6.5 Scenario B-3
The development of the Chikuminuk hydroelectric site to serve the Nushagak
River region requires only a small regulating structure at the outlet of
Chikuminuk Lake, similar to that proposed at the Kukaklek Lake outlet.
Construction-induced impacts on water quality are expected to be similar to
those described for Tazimina. Operation impacts of this hydroelectric
7-45
facility will be similar to those described for the Tazimina run-of-river
concept (Section 7.3.6.16).
The development of the Kukaklek hydroelectric site to serve the lower
Kvichak River and upper Alaskan Peninsula region requires a three-mile
buried penstock from Kukaklek Lake northwestward to two unnamed lakes which
are tributary to Pecks Creek. Construction is expected to cause a
degradation in water quality, namely, increased siltation, turbidity, and
nutrients in these lakes, which will eventually reach lower Pecks Creek.
Because of the volume of water required to be diverted from Kukaklek Lake
for power production and the relatively small size of these two unnamed
lakes as receiving bodies, and the eventual flow into Pecks Creek, it will
be necessary to create a new large lake (reservoir) to regulate outflows.
Flow regulation structures are to be constructed at two strategic
locations: 1) at the outlet to Pecks Creek at the northeast portion of the
reservoir, and 2) at the outlet to Ole Creek at the west end of the
reservoir. During the operation phase of this hydroelectric facility,
increased flows can be expected in both Pecks and Ole Creeks, particularly
during the late autumn. This will result in the delay in the formation of
ice in the channels of these waterways.
The impacts on water quality associated with the development and
implementation of the Newhalen River local hydroelectric site are described
in Section 7.3.6.4.
7.3.6.6 Scenarios B-4, B-6 and B-7
These energy plans have been dropped from further evaluation (Section
7.3.2.6).
7.3.6.7 Scenario B-5
The development of the Kukaklek hydroelectric site to serve the needs of
the lower Kvichak River and upper Alaskan Peninsula region will require a
nine-mile penstock for the purpose of diverting flow from Kukaklek Lake
northward to Iliamna Lake. The construction impacts on water quality
7-46
• ..
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,...
-
-
associated with this concept are similar to those described in Section
7.3.6.4. The impacts on water quality in the Alagnak River are expected to
be less than those of the regional concept because of the lesser amount of
flow diversion from Kukaklek Lake.
The impacts on water quality associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the Nushagak
River region are described in Section 7.3.6.5.
The impacts on water quality associated with the development and
implementation of the Tazimina run-of-river hydroelectric concept to serve
the Newhalen River area are similar to those described in Section
7.3.6.17. Additionally, a preliminary calculation was made to determine
temperature rise of water flowing through a small hydroelectric generator,
including intake and discharge piping. Assuming that all head losses are
converted to heat) a highly conservative approach) and that this heat is
added to the flowing water) the resultant maximum temperature rise in the
river, downstream of the discharge would be O.02 o C. at maximum flow through
the turbine.
7.3.6.B Scenario B-B
The development and implementation of the Tazimina River hydroelectric site
to serve the Kvichak River and upper Alaskan Peninsula region will require
a storage reservoir, but with only about half the effective capacity as the
regional concept. The details describing the impacts on water quality to
the Tazimina River from a storage concept can be found in Appendix G,
Section 3.2.
The impacts on water quality associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the Nushagak
River region are described in Section 7.3.6.5.
7-47
7.3.6.9 Scenarios B-9 and B-lO
Scheme A
The development of a coal-fired, steam-electric generating facility in
either Dillingham (B-9) or Naknek (B-lO) to serve the entire study region
can be expected to cause construction impacts on water quality similar to
those anticipated for the development of a hydroelectric site, e.g.,
induced erosion (siltation, turbidity, and increased nutrients), the
disposal of domestic and process water, and fuel spills or leaks.
The operation and maintenance of a coal-fired facility is generally
expected to have a greater potential for affecting the water quality of
surrounding lakes and streams than a similar-sized hydroelectric facility,
due to surface runoff from coal storage and waste disposal areas. Also,
groundwater is susceptible to leaching from coal pile storage areas, coal
unloading and handling areas, and solid waste (ash) disposal areas.
Significantly more mitigative measures for treatment and disposal of liquid
and solid wastes will be necessary to protect water resources at a
coal-fired, steam-electric facility than at a hydroelectric facility.
Scheme B
The development and implementation of an oil-fired (diesel) combined cycle
generating facility in either Dillingham (B-9) or Naknek (B-lO), to serve
the entire study region, is expected to have similar impacts on water
quality as anticipated in Scheme A, above. However, effects should be
somewhat reduced since there will be no open fuel storage, such as coal
piles, where runoff could contaminate both surface and groundwater. Fuel
storage areas, however, are expected to require I iners and dikes in the
event of a leak or spill.
Scheme C
The development and implementation of a coal gasification combined cycle
facility in either Dillingham (B-9) or Naknek (B-lO), to serve the entire
7-48
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
1: . •
..
.. ...
-
study region, is expected to have similar effects on water quality as
anticipated for Scheme A, above.
7.3.6.10 Scenarios B-11 and B-12
The impacts on water quality associated with the development and
implementation of a coal-fired, steam-electric generating facility are
described in Section 7.3.6.9.
The impacts on water quality associated with the development and
implementation of a local Newhalen River hydroelectric facility are
described in Section 7.3.7.4 .
7.3.6.11 Scenario B-13
Scheme A
The development of the Chikuminuk hydroelectric site to serve the study
region, except for the Newhalen River area, will require a rockfill storage
dam across the entire Chikuminuk Lake outlet valley. Construction impacts
on water quality in the Allen River are expected to be similar to those
anticipated for the semi-regional (Nushagak River region only) development
of Chikuminuk (Section 7.3.6.5).
The impacts on water quality associated with the development and
implementation of a local Tazimina run-of-river facility are expected to be
similar to those anticipated for the regional Tazimina run-of-river
facility described in Section 7.3.6.16, but to a lesser extent.
Scheme B
The development of the Chikuminuk hydroelectric site to serve the study
region, except for the Newhalen River area, will require a rockfill storage
dam across the entire Chikuminuk Lake outlet valley. Construction impacts
on water quality in the Allen River are expected to be similar to those
anticipated for the semi-regional (Nushagak River region only) development
7-49
of Chikuminuk (Section 7.3.6.5).
The impacts on water quality associated
implementation of a local Newhalen River
described in Section 7.3.6.4.
7.3.6.12 Scenario B-14
Scheme A
with the development
hydroelectric facility
and
are
The impacts on water quality associated with the development and
implementation of a regional Newhalen River hydroelectric concept,
utilizing a "power only" canal, are expected to be similar to, but greater
in duration than, the local Newhalen River hydroelectric concept (Section
7.3.6.4).
Scheme B
The impacts on water quality associated with the development and
implementation of a regional Newhalen River hydroelectric concept,
utilizing a large canal for both power intake and high river flow
diversion, are expected to be similar to, but greater duration than, the
local Newhalen River hydroelectric concept (Section 7.3.6.4).
7.3.6.13 Scenario B-15
The development of this energy plan, with diesel-electric generating
centers at four locations, is not expected to have any significant impacts
on water quality. However, the implementation of this energy plan should
require mitigative measures, such as impermeable liners and dikes in fuel
storage areas, to prevent potential leaks and spills from contaminating
surface or subsurface waters.
7.3.6.14 Scenario B-16
The impacts on water quality associated with the development and
7-50
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
(II ...
,...
1iIII.
••
,... .. , -
III.
....
-...
implementation of this energy plan are identical to those described in
Section 7.3.6.13.
7.3.6.15 Scenario B-17
The impacts on water quality associated with the development and
implementation of this energy plan are expected to be similar to those
described in Section 7.3.6.13. However, because this plan has only two
diesel-electric generating centers, the possibility of a spill or leak
occurring at these locations may be greater in magnitude and the resulting
impact on local water quality more serious.
7.3.6.16 Scenario B-18
Scheme A
The development of the Kontrashibuna regional hydroelectric site can be
expected to cause similar impacts on water quality during construction as
anticipated for the Tazimina River regional hydroelectric site (Section
7.3.6.2) . However, because of the shorter downstream length of river at
the Kontrashibuna dam site, approximately 4 miles (the Tazimina dam site
has about 13 miles), the total impact on riverine water quality is expected
to be less .
The operation and maintenance of the proposed hydroelectric facility is
expected to have little effect on the water quality of the Tanalian River .
However, short-term degradation in the form of temperature and conductivity
variations may be experienced in the river because of the wide range in
potential discharge during low-flow periods.
The development of the regional Tazimina run-of-river hydroelectric
facility is expected to have less impact on water quality during the
construction phase than the Tazimina River regional storage hydroelectric
site described in Section 7.3.6.2, which includes the construction of a
large rockfill storage dam.
7-51
The operation and maintenance of the proposed run-of-river hydroelectric
facility is expected to have little effect on the water quality of the
Tazimina River except that reduced streamflows in the late autumn are
likely to accelerate the cooling process, causing stream temperatures in
the gorge, below the falls, to decrease more rapidly and result in ice
forming in the river channel earlier than normal.
Scheme B
The development and implementation of the Kontrashibuna hydroelectric site
to serve the entire study region is expected to have similar impacts on
water quality as anticipated for the regional Tazimina hydroelectric
storage concept described in Section 7.3.6.2. Additional impacts may occur
IJ ..
I
I
I
I
I
I
as a result of drilling through Tanalian Mountain; e.g., the possibility of
encountering groundwater of poor quality which if improperly controlled I
could contaminate local surface waters, or the leaching of drilled material
into surface and subsurface waters.
7.3.6.17 Scenario B-19
Scheme A
The development and implementation of this energy plan is not expected to
have any significant impacts upon water quality anywhere within the study
region. Mitigative measures, however, will be taken and are expected to be
similar to those described in 7.3.6.1.
Scheme B
The development and implementation of this energy plan is not expected to
have any significant impacts upon water quality anywhere within the study
region. Mitigative measures, however, will be taken and are expected to be
similar to those described in Section 7.3.6.1.
7-52
I
I
I
I
I
I
I
I
I
I
I
... "
-
Scheme C
The development and implementation of this energy plan is not expected to
have any significant impacts upon water quality anywhere within the study
region. Mitigative measures, however, will be taken and are expected to be
similar to those described in Section 7.3.6.1.
Scheme D
The development and implementation of this energy plan is not expected to
have any significant impacts upon water quality anywhere within the study
region. Mitigative measures; however, will be taken and are expected to be
similar to those described in Section 7.3.6.1.
Scheme E
The development and implementation of this energy plan (Base Plan
supplemented by wind energy and waste heat recovery) to serve the study
region, except the Newhalen area, is not expected to have any significant
impacts upon water quality anywhere within the study region. However,
mitigative measures will be taken and are expected to be similar to those
described in Section 7.3.6.1.
The impacts on water quality anticipated from the development and
implementation of the local Tazimina run-of-river hydroelectric site to
serve the Newhalen area are described in Section 7.3.6.2 and 7.3.6.7.
7.3.7 Fish and Wildlife Impact
7.3.7.1 Scenario BP-1
The development and implementation of this energy plan is not expected to
have any significant impact on fish or wildlife.
7.3.7.2 Scenario A-1
The development of the Tazimina River hydroelectric storage concept to
serve the entire study region will result in the reduction of 4,100 acres
7-53
of natural wildlife habitat due to the creation of a storage reservoir at
river mile 13.1. The construction of an access road, powerhouse, dam, and
spillway will result in additional losses of wildlife habitat. There are
also expected to be short-term losses of habitat for birds and mammals
associated with the construction of these facilities in adjacent areas as a
result of noise and human activity.
Associated with the operation and maintenance of this facility is the
previously mentioned loss of 4,100 acres of wildlife habitat, which is
expected to affect beaver, moose, small mammals, waterfowl, and brown bear.
Details discussing the impacts of development and implementation of the
regional Tazimina River hydroelectric facility on wildlife habitat are
found in Appendix G, Section 4.2.1.
The development of the regional Tazimina River hydroelectric site is
expected to have some impact on fish downstream of construction as a result
of increased turbidity, nutrients, and siltation. These impacts will be
mitigated to the maximum extent practical.
During the operation and maintenance phase of this facility, fish in the
lower Tazimina River below the proposed powerhouse could be affected
because the flow regime will be altered as a result of regulating the
discharges through the penstock for power production, and sa1monid
incubation rates may be affected by altered thermal regimes.
Fish whose habitat is that section of river between the proposed powerhouse
and forebay (intake) structure are expected to receive some impact because
flows will be highly variable, particularly during low-flow periods.
Between the proposed forebay structure, storage dam flows will be regulated
and the potential for impact on resident fish is reduced.
Above the storage dam the aquatic habitat will be dramatically altered.
The primary impact to fish would be the conversion of 4 miles of riverine
7-54
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
....
....
habitat to lake habitat. There also exists the possible contamination by
hydrogen sulfide generated by the anaerobic decomposition of inundated
plants. The surface of Lower Tazimina Lake would be raised approximately
35 ft, and because of water level fluctuations necessary for power
generation, spawning and rearing areas near the shore could be eliminated.
The Tazimina River "between the lakes II will also be inundated to elevation
690 ft (MSL) and will result in the conversion of approximately 3 miles of
riverine habitat to lake habitat.
Details describing changes to aquatic habitats and impact on fish are found
in Appendix G, Section 4.2.2.
7.3.7.3 Scenario B-1
The development and implementation of this energy plan is expected to have
little or no impact on fish in the study region. The location of the main
transmission line between the Newhalen River area and Levelock could,
however, affect the migration patterns of the ~lulchatna caribou herd. The
feeder line from South Naknek to Egegik is planned to be located along the
coast (as it will be for all energy plans) to avoid the migration pattern
of the Alaska Peninsula caribou herd. Except for these two areas,
transmission corridor location does not appear to have a significant impact
on wildlife habitat within the study region.
A more serious impact, however, may occur outside the study region should
the corridor be constructed through Lake Clark Pass. Because the pass is
an important habitat corridor for brown bear, moose, Dal1 sheep and other
fur bearers, a detailed study (impact analysis) would be necessary if this
scenario was to be selected for Phase II analysis.
7.3.7.4 Scenario B-2
The development of the Kukaklek hydroelectric site to serve the study
region, except for the Newhalen river area, requires the construction of a
large penstock to divert water for power generation from Kukaklek Lake
northward to Iliamna Lake. Construction impacts in the area are expected
7-55
to have a significant effect on wildlife habitats in the immediate area.
The area north of Kukaklek Lake is classified by biologists as prime moose
habitat, with moose concentrating there year-round. Brown bear and grizzly
bear are also known to concentrate along Pecks Creek and the Alagnak River,
and caribou from the Mulchatna herd winter in the area near Pecks Creek;
construction in such a prime wildlife area could have significant effects.
Construction impacts are expected to be similar to those described in
Appendix G, Section 4.2.1, for the regional Tazimina River hydroelectric
site. Wildlife impacts during the operation and maintenance phase of this
hydroelectric facility are expected to be minimal since the penstock will
be buried and the surface revegetated, and there is expected to be no
significant water level fluctuation in Kukaklek Lake.
Impacts on fish are expected to be minimal during the construction phase of
the regional Kukaklek hydroelectric site. The primary impact expected to
occur will result from construction-induced erosion in the form of
siltation, turbidity, and increased nutrient concentration, particularly in
Pecks Creek and the Alagnak River. Kukaklek Lake is the source of the
Alagnak River and supports five species of Pacific salmon plus rainbow
trout, char, whitefish, burbot, and grayling. The operation of the
regional Kukaklek hydroelectric facility is not expected to significantly
impact the lake's aquatic habitat and will allow free movement of fish into
and out of the lake. Because of the lake's large areal extent ,the
fluctuating lake level is expected to be minimal, not seriously impacting
the littoral zone. However, flow diversion, while not affecting the lake,
may affect the stream flows and morphology of the Alagnak River, which
supports a high-density fishery in its lower reach. Another fishery impact
which is not expected to be significant, however, is the diversion of
stream flows across drainage boundaries (in this case, the proportion of
flow from Kukaklek Lake entering Iliamna Lake is not s ignif icant when
compared to the natural inflow to Iliamna Lake).
The development of the local Newhalen River hydroelectric site is expected
to have similar impacts on wildlife and habitat as described in Section
7.3.7.2 for the Tazimina River regional hydroelectric site. Any moose and
7-56
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
II
..
III
-
-
brown and black bear along the Newhalen River are expected to be displaced
during construction. Wildlife impacts resulting from the operation and
maintenance of the facility are not expected to be significant, however.
Impacts on fish during the construction phase of the local Newhalen River
hydroelectric facility are generally expected to be less than those
described for other hydroelectric sites where storage reservoirs are
required. However, it is recognized that the Newhalen River is a critical
link in the Kvichak salmon fishery, because the entire sockeye salmon
population of the Lake Clark region passes through the river both in
juvenile and adult stages. Because the local Newhalen River hydroelectric
concept considers diversion of flow, the impact of the salmon fishery
resulting from the operation and maintenance phase is expected to be
minimal since mitigative measures will be taken to prevent out-migrating
salmon from entering the diversion structure.
7.3.7.5 Scenario B-3
The development and implementation of the Kukaklek hydroelectric site to
serve the lower Kvichak River and upper Alaskan Peninsula region is
expected to have some effect on fish, primarily those effects resulting
from water quality degradation as described in Section 7.3.6.5. The
increase of flow into Pecks and Ole Creeks, coupled with the reduction of
flow in the Alagnak River, is also expected to have an effect on both
resident and anadromous fish. Possibly the most significant impact of this
development concept is the diversion of streamflow across drainage
boundaries, since the introduction of non-indigenous pathogens and
parasites might occur. The proportion of flow diverted from Kukaklek Lake
to the two unnamed lakes and to Pecks and Ole Creeks is significant and may
effect the homing instincts of anadromous fish. The impacts on wildlife
associated with the development and implementation of the Kukaklek
hydroelectric site to serve the lower Kvichak River and upper Alaskan
Peninsula region are expected to be similar to those anticipated for the
regional Kukaklek hydroelectric site described in Section 7.3.7.4.
The impacts on fish and wildlife associated with the development and
7-57
implementation of the Chikuminuk hydroelectric site to serve the Nushagak
River region are expected to be similar to those anticipated at the
Tazimina run-of-river hydroelectric site described in Section 7.3.7.16.
Salmon reportedly migrate only to the mouth of the Allen River, never
reaching Chikuminuk Lake. Principal species of fish found in the
Chikuminuk Lake include rainbow and lake trout, Artic char, grayling,
whitefish, and northern pike. Moose are generally present, but few caribou
inhabit the area. Brown and black bear are common along with small mammals.
The impacts on fish and wildlife associated with the development and
implementation of the local Newhalen River hydroelectric site are described
in Section 7.3.7.4.
7.3.7.6 Scenario B-4, B-6, and B-7
These energy plans have been dropped from further evaluation (Section
7.3.2.6).
7.3.7.7 Scenario B-5
The impacts on fish and wildlife associated with the development and
implementation of the Kukaklek hydroelectric site to serve the lower
Kvichak River and upper Alaskan Peninsula region are described in Section
7.3.7.4. The fishery impact on the Alagnak River is expected to be less,
however, than the regional Kukaklek concept due to the smaller amount of
flow to be diverted for power generation.
The impacts on fish and wildlife associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the Nushagak
River region are described in Section 7.3.7.5.
The impacts on fish and wildlife associated with the development and
implementation of the local Tazimina run-of-river hydroelectric concept are
expected to be similar to the regional Tazimina run-ot-river concept
described in Section 7.3.7.16.
7-58
~
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..-L
7.3.7.B Scenario B-B
The impacts on fish and wildlife associated with the development and
implementation of the Tazimina River hydroelectric storage concept to serve
the Kvichak River and upper Alaskan Peninsula region are expected to be
similar to those anticipated at the regional Tazimina River hydroelectric
storage concept. The smaller quantity of flow required for power
generation, however, will result in a smaller reservoir and less associated
impacts.
The impacts on fish and wildlife associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the Nushagak
River region are described in Section 7.3.7.5.
7.3.7.9 Scenarios B-9 and B-IO
Scheme A
The development and implementation of a coal-fired, steam-electric
generating facility located in either Dillingham (B-9) and Naknek (B-IO) to
serve the entire study region is not expected to have any significant
impacts on fish and wildlife. There are no important large mammal herds
which utilize the areas where these facilities would be constructed and the
use of air-cooled condensers are expected to preclude any impacts on
fisheries that would be expected from a once-through cooling system .
However, specific mitigative measures are expected to be required to
prevent impacts on fisheries at the coal barge unloading facility.
Scheme B
The development and implementation of an oil-fired (diesel) combined cycle
facility in either Dillingham (B-9) or Naknek (B-IO) to serve the entire
study region is expected to have similar impacts on fish and wildlife as
anticipated for Scheme A, above.
7-59
Scheme C
The development and implementation of a coal gasification combined cycle
facility in either Dillingham (B-9) or Naknek (B-10) to serve the entire
study region is expected to have similar impacts on fish and wildlife as
anticipated for Scheme A, above.
7.3.7.10 Scenarios B-11 and B-12
The impacts on fish and wildlife associated with the development and
implementation of a coal-fired, steam-electric facility are described in
Section 7.3.7.9.
The impacts on fish and wildlife associated with the development and
implementation of a local Newhalen River hydroelectric facility are
described in Section 7.3.7.4.
7.3.7.11 Scenario B-13
Scheme A
The impacts on fish and wildlife associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the study
region, except for the Newhalen River area, are expected to be similar to
those anticipated for the regional Tazimina River hydroelectric site
described in Section 7.3.7.2. As is the case with Lower Tazimina Lake,
Chikuminuk Lake will also have to be raised for the purpose of power
generation and consequently, areas critical to the spawning and rearing of
resident fish will be reduced. Additionally, low-lying areas at the
western end of the lake which presently provide habitat for moose and
waterfowl, would be inundated. The construction of an airfield
approximately 10 miles east of the lake outlet and access road connecting
the airfield with the power site is expected to temporarily disturb a large
area heavily used by brown and black bear and moose.
The impacts on fish and wildlife associated with the development and
7-60
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
...
implementation of the local Tazimina run-of-river hydroelectric concept are
expected to be similar to those anticipated for the regional Tazimina
run-of-river concept described in Section 7.3.7.16, but to a lesser extent.
Scheme B
The impacts on fish and wildlife associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the study
region, except the Newhalen River area, are described in Scheme A, above.
The impacts on fish and wildlife associated with the development and
implementation of the local Newhalen River hydroelectric site are described
in Section 7.3.7.4.
7.3.7.12 Scenario B-14
Scheme A
The impacts on fish and wildlife associated with the development and
implementation of the regional Newhalen hydroelectric concept, utilizing a
"power only" canal, are expected to be similar to, but of greater magnitude
than, those anticipated for the local Newhalen hydroelectric concept,
described in Section 7.3.7.4. The exclusion of out-migrating sockeye
salmon smolt and fry is of utmost concern. A special study has been
designed for Phase II which will test various fish screens and deflectors
under varying flow and climatic conditions in order to protect these
out-migrants .
Scheme B
The impacts on fish and wildlife associated with the development and
implementation of the regional Newhalen River hydroelectric concept are
expected to be similar to, but of greater magnitude than, those anticipated
for the local Newhalen River hydroelectric concept described in Section
7.3.7.4. Al though a bridge over the Newhalen River and an access road on
the west side will not be required, construction of a large canal will be
necessary .
7-61
Special canal intake designs will be required to protect sockeye salmon
smolt and fry as they pass the intake during downstream mitigation. The
diversion of river flows during the winter low-flow periods is expected to
have some affect on resident fish, but may also impact sockeye salmon.
However, these effects cannot be fully assessed at the present time. The
diversion of flow through the intake canal during high water periods may
benefit the sockeye salmon fishery by lowering the velocity in the river
channel to allow upstream migration during periods of high flow. It has
been reported that extreme flows over the rapids in the lower Newhalen
River have caused blockage at the river's mouth to upstream passage, a
problem which on infrequent occasions has caused extensive mortality in
mature adult sockeye salmon as they move in early summer to freshwater
spawning areas in the Newhalen River-Lake Clark System. The hydro concept
currently visualized would permit controlled bypass of water around the
rapids by means of the plant's intake canal. This could eliminate
excessive flows over the rapids, thereby improving conditions for upstream
migration.
7.3.7.13 Scenario B-1S
Impacts on fish associated with the development and implementation of this
energy plan are not expected to be significant. However, the location of
transmission lines may create potential impacts. Transmission lines
located along and near the coast may pose some hazard to migrating
waterfowl, while a transmission line between Levelock and Igiugig may have
an effect on the migrating Mulchatna caribou herd.
7.3.7.14 Scenario B-16
The impacts on fish and wildlife associated with the development and
implementation of this energy plan are expected to be the same as those
described in Section 7.3.7.13, except that a main transmission intertie is
proposed between Dilligham and Naknek. This may create a greater impact on
migrating waterfowl in that area.
7.3.7.15 Scenario B-17
The impacts on fish and wildlife associated with the development and
7-62
" III
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Ii. iii
...
...
-
.implementation of this energy plan are expected to be similar to those
described in Section 7.3.7.3 for the Beluga Intertie. Significant effects
are expected to be associated with the transmission lines only and not the
diesel-electric generation centers.
7.3.7.16 Scenario B-18
Scheme A
The impacts on fish and wildlife associated with the development and
implementation of a regional hydroelectric facility at Kontrashibuna are
expected to be similar to those presented in Section 7.3.7.2 for the
regional Tazimina River hydroelectric facility.
While the Tanalian River supports only a small run of salmon, other species
such as lake trout, Artic char, pygmy whitefish, and sculpin can expect to
be affected by the project. Moose, generally present in the area, along
with brown and grizzly bear, which are known to concentrate along the
Tanalian River and lower Kontrashibuna Lake, are also expected to be
affected by project construction.
The development of the regional Tazimina run-of-river hydroelectric concept
is expected to have similar construction impacts as the regional Tazimina
River hydroelectric storage concept described in Section 7.3.7.2. However,
the operation and maintenance phase is expected to have only a minimal
impact on wildlife habitat since there will be no inundation by a storage
reservoir.
The most significant impact on aquatic habitat is expected to occur in the
section of river between the proposed powerhouse and forebay dam. While
there will be a reduction in flow through this section of river year-round,
the reduction of flow during low-flow periods may pose the most severe
impact upon both resident and anadromous fish. Details describing the
impacts on fish and wildlife associated with the development and
implementation of the local Tazimina River run-of-river hydroelectric site
are found in Appendix G, Section 4.2.
7-63
Scheme B
The impacts on fish and wildlife associated with the development and
implementation of the Kontrashibuna hyroelectric site to serve the entire
study region are expected to be similar to those anticipated for the
regional Tazimina hydroelectric storage concept as detailed in Scheme A,
above.
7.3.7.17 Scenario B-19
Scheme A
The development and implementation of this energy plan is not expected to
create any significant impacts on fish or wildlife.
Scheme B
The development and implementation of this energy plan is not expected to
create any significant impacts on fish or wildlife.
Scheme C
The development and implementation of this energy plan is not expected to
create any significant impacts on fish or wildlife.
Scheme D
The development and implementation of this energy plan is not expected to
create any significant impacts on fish or wildlife.
Scheme E
The development and implementation of this energy plan (Base Plan
supplemented by wind energy and waste heat recovery) to serve the study
region, except the Newhalen area, is not expected to create any significant
impacts on fish or wildlife.
7-64
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
• i
.. ..
---
The impacts on fish and .wildlife associated with the development and
implementation of the local Tazimina run-of-river hydroelectric site to
serve the Newhalen area are described in Section 7.3.7.16.
7.3.8 Land Use Impact and Ownership Status
7.3.8.1 Scenario BP-l
The development and implementation of this energy plan is not expected to
have any significant impacts on land use or ownership status in the study
region.
7.3.8.2 Scenario A-l
The development and implementation of the regional Tazimina River
hydroelectric facility is expected to have some effect on land use and
ownership status. While the subsistence usage of the Tazimina Lakes has
been relatively low, both in recent and historic times, the use of the
lower Tazimina River and nearby lakes has been extensive.
trapping, and hunting have been the primary activities.
Fishing,
Essentially all the land in the Tazimina River regional hydroelectric
project area is either owned by, or has been interim-conveyed to local
natives. The lakes, however, are currently part of the Lake Clark National
Park and Preserve, and come under the Park Service jurisdiction. There
appears to be some discrepancy or confusion about the status of the lands
immediately surrounding the Tazimina River and lower Tazimina Lake. All
lands within one-quarter mile of Lower Tazimina Lake and all lands within
one-quarter mile of the Tazimina River, between Lower Tazimina Lake and
Six-mile Lake, have been withdrawn for the purpose of power development.
While the original withdrawal of these lands by the Federal Power
Commission was included under Power Site Reserve No. 485, dated April 1,
1915, a more recent classification was approved on October 22, 1971,
resulting in the issuance of Power Site Classification No. 463. However,
these lands are now included in the Lake Clark National Park and Preserve,
7-65
under the A~aska National Interest Lands Conservation Act (ANILCA) of 1980.
Transmission corridors from the regional Tazimina River site, both main and
feeder lines, are expected to pass through numerous classifications of land
and also have effect on land usage. To the extent possible, transmission
lines will be located on state-owned lands, avoiding native-owned lands and
federal lands designated under ANILCA for conservation. Transmission lines
will also be designed to be located in areas away from known and heavy
subsistence hunting, trapping, and fishing areas, and avoid prime
recreation hunting and fishing areas.
7.3.8.3· Scenario B-1
The development and implementation of this energy plan is expected to have
the same impacts on land use and ownership status within the Bristol Bay
region as anticipated for the transmission corridors for the energy plans
described in Section 7.3.8.16. However, significant impact is expected to
occur north and east of Port Alsworth where the transmission corridor will
traverse designated wilderness areas of the Lake Clark National Park and
Preserve. Such development is not considered acceptable according to the
general management plan of this Alaska conservation unit.
7.3.8.4 Scenario B-2
The development and implementation of the Kukaklek hydroelectric site to
serve the entire region, except for the Newhalen River area, is expected to
have a significant effect on land use and ownership status. Kukaklek Lake
and the area around it presently lie within the preserve boundary of the
Mt. Katmai National Park and Preserve. A corridor, two land sections in
width, from the outlet of Kukaklek Lake northward to Iliamna Lake, has been
withdrawn and is currently owned by the residents of Igiugig. The proposed
development anticipates obtaining a right-of-way over this native-owned
land, thus avoiding impacts to the federally-designated conservation land.
As previously discussed, in Section 7.3.7.4, the area in which the
hydroelectric facility will be developed is prime moose and caribou land.
Therefore, subsistence hunting by local native residents could be greatly
7-66
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,.
! ..
liM
affected. Also, the Alagnak River and Pecks Greek are
subsistence fishing streams which support not only anadromous
important
fish but
numerous species of resident fish. Disturbance from construction
activities and reduced flows during the operation phase of this
hydroelectric facility could have a significant effect on subsistence
fishing.
Another potential impact is the effect of reduced flow on the Wild and
Scenic River portion of the Alagnak River. River usage data, however, are
not currently available to fully evaluate the potential impact.
The transmission corridors from the Kukaklek hydroelectric site will be
located using the same principle described for the regional Tazimina River
hydroelectric facility in Section 7.3.8.2. Because the Kukaklek
hydroelectric facility is not designed to serve the Newhalen River area,
land use and ownership will not be affected by a transmission corridor
north and west of Iliamna Lake.
The development and implementation of a local Newhalen River hydroelectric
facility is expected to have some affect on land ownership status. While
all the land in the area is owned by local native organizations, a
right-of-way will be necessary for project development. The transmission
line corridor may possibly utilize land previously set aside for the
proposed Newhalen to Nondalton transmission intertie (Section 7.3.3.4).
All the lands within one-quarter mile of the Newhalen River, between
Sixmile Lake and Iliamna Lake, have been withdrawn for the purpose of power
generation. This withdrawal was made by the Federal Power Commission on
April 1, 1915, under Power Site Reserve No. 485. However, some of the
proposed hydroelectric appurtenant facilities are expected to be located
outside the reserve boundary.
7.3.8.5 Scenario B-3
The development and implementation of the Kukaklek hydroelectric site to
serve the lower Kvichak River and upper Alaskan Peninsula area is expected
to affect on land use and ownership status similar to that anticipated for
7-67
the regional Kukaklek hydroelectric site described in Section 7.3.8.5.
This concept, however, is not expected to require as much right-of-way land
to be purchased from Igiugig, but will utilize what is primarily Bureau of
Land Management land located south and west.
The development and implementation of the Chikuminuk hydroelectric site to
serve the Nushagak River region is expected to have major effects on land
use and ownership status in the region. While most construction-related
activity will be outside the park the hydroelectric power generation
facility is located within the borders of the Wood-Tikchik State Park.
Such a power generating facility and appurtenant structures are not
considered acceptable to the overali management objective of the state park.
The main transmission line corridor from the facility site to Dillingham is
proposed to be located outside the State Park boundary, utilizing
state-owned lands to the extent possible and avoiding native-owned lands.
Subsistence hunting and fishing areas will be avoided to the extent
possible; however, some impact may occur when crossing the Nuyakuk River.
The impacts on land use and
development and implementation
described in Section 7.3.8.4.
ownership status associated
of the local Newhalen River
7.3.8.6 Scenarios B-4, B-6, and B-7
with the
site are
These energy plans have been dropped from further evaluation (Section
7.3.2.6).
7.3.8.7 Scenario B-5
The impacts on land use and ownership status associated with the
development and implementation of the Kukaklek hydroelectric site to serve
the lower Kvichak River and upper Alaskan Peninsula region are expected to
be similar to those anticipated for the regional Kukaklek hydroelectric
site described in Section 7.3.8.4. However, these impacts are expected to
be considerably less since there will be no transmission line corridor
7-68
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
c
, .., -
-
required to connect the Newhalen River area with the rest of the region,
and the flows in the Wild and Scenic Alagnak River would not be as greatly
reduced.
The impacts on land use and ownership associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the Nushagak
River region are described in Section 7.3.B.5.
The impact on land use and ownership status associated with the development
and implementation of the local Tazimina run-of-river hydroelectric site is
expected to be similar to that anticipated for the regional Tazimina
run-of-river concept described in Section 7.3.B.16, but to a lesser
extent. Impacts from the transmiss ion line corridor are expected to be
similar to those anticipated for the local Newhalen River hydroelectric
facility described in Section 7.3.B.4.
7.3.B.B Scenario B-B
The impacts on land use and ownership status associated with the
development and implementation of the Tazimina River hydroelectric site to
serve the Kvichak River and upper Alaskan Peninsula are expected to be
similar to those anticipated for the regional Tazimina River hydroelectric
storage concept described in Section 7.3.B.2. Less land surrounding
Lower Tazimina Lake is expected to be affected by inundation because of the
smaller energy demand requiring a smaller storage reservoir. While
transmission line corridors are expected to follow the same route as the
regional Tazimina concept within the Kvichak River region, there will be no
line planned to connect the Nushagak River region. The impacts on land use
and ownership status associated with the development and implementation of
th Chikuminuk hydroelectric site to serve the Nushagak River region are
described in Section 7.3.B.5.
7-69
7.3.8.9 Scenarios B-9 and B-I0
Scheme A
The impacts on land use and ownership status associated with the
development and implementation of a coal-fired, steam-electric generating
facility, located in either Dillingham (B-9) or Naknek (B-I0), to serve the
entire study region are expected to be minimal. The facility will be
constructed in or near Dillingham or Naknek and is not expected to affect
any subsistence use. Approximately 15 acres of native-owned land will have
to be purchased to develop the energy plan. Transmission line impacts on
land use and ownership status are expected to be similar to those
anticipated for the regional Tazimina River hydroelectric storage facility
described in Section 7.3.8.2.
Scheme B
The impacts on land use and ownership status associated with the
development and implementation of an oil-fired (diesel) combined cycle
facility located in either Dillingham (B-9) or Naknek (B-I0) to serve the
entire study region are expected to be the same as those anticipated in
Scheme A, above.
Scheme C
The impacts on
development and
facility located
land use and ownership status associated with the
implementation of a coal gasification combined cycle
in either Dillingham (B-9) or Naknek (B-I0) to serve the
entire study region are expected to be the same as those anticipated in
Scheme A, above.
7.3.8.10 Scenarios B-l1 and B-12
The impacts on land use and ownership status associated with the
development and implementation of a coal-fired, steam electric generating
facility in either Dillingham (B-ll) or Naknek (B-12) are described in
7-70
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I ,
I
I
I
I
, ..
-
-
-
-...
Section 7.3.8.9.
The impact on land use and ownership status associated with the development
and implementation of the local Newhalen River hydroelectric site is
described in Section 7.3.8.4.
7.3.8.11 Scenario B-13
Scheme A
The impacts on
development and
land use and ownership status
implementation of the Chikuminuk
associated with the
hydroelectric site to
serve the study region, except for the Newhalen River Area, are expected to
be similar to those anticipated for the Chikuminuk hydroelectric site to
serve the Nushagak River region described in Section 7.3.8.5. There is,
however, expected to be more impact on land use and ownership status,
because the greater electric demand for the region will require raising the
level of Chikuminuk Lake for power generation and increased storage.
Approximately 3700 acres of land will be lost to inundation by the storage
reservoir. The impacts on land use and ownership status associated with
the development and implementation of the local Tazimina run-of-river
hydroelectric concept are expected to be similar to those anticipated for
the regional Tazimina run-of-river hydroelectric concept described in
Section 7.3.8.16.
Scheme
The impacts on land use and ownership status associated with the
development and implementation of the Chikuminuk hyroelectric site to serve
the study region, except the Newha1en River area, are described in Scheme
A, above.
The impacts on land use and ownership status associated with the
development and implementation of the local Newhalen River hydroelectric
facility are described in Section 7.3.8.4 .
7-71
7.3.8.12 Scenario B-14
Scheme A
The impacts on land use and ownership status associated with the
development and implementation of the regional Newhalen River hydroelectric
concept, utilizing a "power only" canal, are expected to be similar to, but
somewhat greater than, those anticipated by the local Newhalen River
hydroelectric concept described in Section 7.3.8.4. The project concept
encroaches on an Indian Allotment. Efforts have been initiated through
appropriate agencies to resolve this matter. The transmission corridor is
the same as for the regional Tazimina hydroelectric concept described in
Section 7.3.8.2.
Scheme B
The impacts on land use and ownership status associated with the
development and implementation of the regional Newhalen River hydroelectric
concept, utilizing a large canal for both power intake and high river flow
diversion, are expected to be similar to, but somewhat grea~er than, those
anticipated by the local Newhalen River hydroelectric concept described in
Section 7.3.8.4. The proj ect concept encroaches on an Indian Allotment.
Efforts have been initiated through appropriate agencies to resolve this
matter. The transmission corridor is the same as for the regional Tazimina
hydroelectric concept described in Section 7.3.8.2.
7.3.8.13 Scenario B-15
The impact on land use and ownership status associated with the development
and implementation of four diesel-electric generating centers is expected
to be minimal. However, the location of the transmiss ion line corridors
may result in a significant impact. From the Dillingham center, the feeder
line to Portage Creek is proposed to cross the Wood River and follow the
north side of the Nushagak River, utilizing state land as much as possible
and avoiding subsistence use areas. From Portage Creek to Clarks Point and
7-72
I
I
I
I
I
I
,I
I
I
I
I
I
I
I
I
I
t
I
I
I
I
Ekuk, the transmission line is proposed to be located adjacent to a winter
trail, avoiding potential impact to native-owned land and subsistence use
areas. Transmission from Dillingham to Manokotak is expected to follow the
existing route to Aleknagik but branch off toward Manokotak, utilizing
state land immediately north of the Togiak National Wildlife Refuge, and
enter the village by utilizing a right-of-way on native-owned land and
avoiding subsistence use areas.
From the New Stuyahok center, one feeder line will run southwest along the
Nushagak River to Ekwok, while the other line will run north to Koliganek
utilizing mostly state-owned land and avoiding subsistence use areas.
From the Naknek center, the feeder line to Egegik will utilize the existing
transmission line to South Naknek and continue southward along the coast,
primarily on state-owned land. The transmission line to Levelock and
Igiugig is proposed to utilize state-owned land to the Alagnak River, cross
the Alagnak River below its \Hld and Scenic Section, and run northeast to
the vicinity of the mouth of Ben Courtny Creek on the Kvichak River,
utilizing primarily state-and BL~-owned land. At this point, one segment
of the line will cross the Kvichak River and double back to Levelock on
state-owned land, avoiding subsistence use areas. The other segment of the
line will continue on to Igiugig, utilizing both state-and BLM-owned land.
From the Newhalen center, transmission feeder lines will follow the route
proposed by the Iliamna-Newhalen Electric Cooperative for connecting
Nondalton to the system.
7.3.8.14 Scenario B-16
The impacts on land use and ownership status associated with the
development and implementation of this energy plan are expected to be the
same as those described in Section 7.3.8.13. However, an additional
transmission intertie is planned to connect the Dillingham and Naknek
centers, and will utilize primarily BLM-owned land between the Nushagak and
Kvichak Rivers.
7-73
7.3.8.15 Scenario B-17
The impacts on land use and ownership status associated with the
development and implementation of this energy plan are expected to be
similar to those of a coal-fired, steam-electric generating facility in
either Dillingham or Naknek. However, less land will be required for the
construction of the facilities.
7.3.8.16 Scenario B-18
Scheme A
The development and implementation of the regional Kontrashibuna
hydroelectric site is expected to have significant impacts on land use and
ownership status. The raising of Kontrashibuna Lake behind the proposed
dam on the Tanalian River for power generation is expected to affect
subsistence hunting in that area by eliminating approximately 2,000 acres
of woodland. Downstream of the dam, the reduced flow in the Tanalian
River, the construction of a road, and the boring of a power tunnel through
the southwest slope of Tanalian Mountain are all expected to have a
significant effect on the subsistence hunting and fishing activities of the
residents of Nondalton and Port Alsworth. Also, the entire reservoir will
be located within the Lake Clark National Park wilderness area. While all
lands within one-quarter mile of Kontrashibuna Lake and all lands within
one-quarter mile of the Tanalian River, between Kontrashibuna Lake and Lake
Clark, have been withdrawn for the purpose of power development, the
present status of these lands are as designated wilderness. As such, the
present management plan of the Lake Clark National Park and Preserve
prohibits hydroelectric power development.
The construction of a transmission corridor from Port Alsworth to the
Newhalen River will traverse native-owned land, avoiding the preserve land
of the Lake Clark National Park and Preserve. From the Newhalen River the
transmission corridors are expected to follow the same routes as
anticipated for the regional Tazimina River hydroelectric facility, and are
expected to have the same impacts as described in Section 7.3.8.2.
7-74
!
I
I
I
I
I
I
I
I
I
I
I
I
I The development and implementation of the regional Tazimina run-of-river
hydroelectric facility is expected to have similar, but somewhat smaller,
impacts on land use and ownership than anticipated for the regional
Tazimina River hydroelectric storage facility because there will be no
storage dam and reservoir.
Scheme B
The impacts on land use and ownership status associated with the
development and implementation of the Kontrashibuna hydroelectric site to
serve the entire study region are described in Scheme A, above.
7.3.8.17 Scenario B-19
Scheme A
The development and implementation of this energy plan is not expected to
have any significant impacts on land use or ownership status anywhere
within the study region.
Scheme B
The development and implementation of this energy plan is not expected to
have any significant impacts on land use or ownership status anywhere
within the study region.
Scheme C
The development and implementation of this energy plan is not expected to
have any significant impacts on land use or ownership status anywhere
within the study region.
Scheme D
The development and implementation of this energy plan is not expected to
have any significant impacts on land use or ownership status anywhere
7-75
within the study region.
Scheme E
The development and implementation of this energy plan (Base Plan
supplemented by wind energy and waste heat recovery) to serve the study
region, except the Newhalen area, is not expected to have any significant
impacts on land use or ownership status.
The development and implementation of the Tazimina run-of-river site to
serve the Newhalen area is expected to impact land use and ownership status
similar to the regional Tazimina storage concept (Section 7.3.8.2) except
that there will be no impacts resulting from an impoundment.
7.3.9 Terrestrial Impact
7.3.9.1 Scenario BP-1
The development and implementation of this energy plan,
individual diesel-electric generating centers in each
transmission interconnection other than what presently
expected to have any significant impact on vegetation
ecology.
7.3.9.2 Scenario A-I
which utilizes
village and no
exists, is not
and terrestrial
The development of the regional Tazimina River hydroelectric storage
concept is expected to result in the direct loss of approximately 150 acres
of vegetation due to the construction of access roads, borrow areas,
powerhouse site, storage dam, and spillway. The access road from the
existing Newhalen road will traverse through open mixed spruce-birch forest
and open low-shrub, with some occasional riparian tall shrub communities.
The road from the powerhouse to the storage dam will cross through exposed
low-shrub communities with scattered spruce trees. While the losses would
be permanent, these vegetation types are widespread throughout the region
and do not represent unique habitat types.
7-76
J
I
I'
I
I
I
I
I
t
I
I
I
I
i
I
I
I
'I
I
I
I
;
I
I
r •
•
I
The major terrestrial impact of this regional concept would be the loss of
approximately 4100 acres of vegetation around Lower Tazimina Lake as a
result of filling the storage reservoir. The zone of inundation and
periodic drawdown is presently covered by a wide range of vegetation
types. Along the south shore of Lower Tazimina Lake, black spruce woodland
predominates. The same is the case along the north shore, but near the
upper end of the lake a more open mixed spruce-birch forest develops. The
vegetation upstream of the lake, between the two lakes, is primarily open
white spruce forest and tall shrub. This area also contains the largest
area of wet land habitat around the lower lake. There are also riparian
habitats present, but they are generally associated with tributaries to the
lower lake.
The construction of transmission line rights-of-way are expected to have
only a minimal impact on terrestrial ecology since trees will only be cut
along the corridors and poles will be placed only during winter months.
Forests will generally be avoided; however, the width of the right-of-way
will only be about 50 ft. In forested areas this right-of-way is expected
to be maintained by periodic cutting.
A more detailed discussion of terrestrial impacts appears in Appendix G,
Section 4.2.1.
7.3.9.3 Scenario B-1
The development and implementation of this energy plan is not expected to
have any greater impact on vegetation and terrestrial ecology than the
transmission line corridor associated with the regional Tazimina River
hydroelectric facility. There will however, be an additional 25 miles or
so of corridor to be cut between Sixmile Lake and Port Alsworth. The
corridor will be located in the upland spruce-birch forest along the
southeast shore of Lake Clark. Once a corridor is cut in a forest area,
brush will be allowed to revegetate the cleared area, with trees expected
to be cut periodically as they mature.
7-77
7.3.9.4 Scenario B-2
The development of the Kukaklek hydroelectric site to serve the study
region, except for the Newhalen River area, is expected to have a
significant impact on vegetation and terrestrial ecology. The major impact
is expected to occur along the penstock corridor between Kukaklek Lake and
Iliamna Lake. Because the penstock will be buried, approximately 60 acres
(a corridor approximately 50 ft wide by 9 miles long) will have to be
disturbed. The penstock will traverse through a predominantly moist tundra
ecosystem, but will also encounter spruce-birch forest in the area of upper
Pecks Creek, sedges and mosses in depressions, and low-growing shrubs on
low, rounded hills. While the access road will utilize the penstock
corridor and the land surface scheduled to be revegetated, the impact from
such a disturbance may remain visible for many years. The proposed barge
facility, construction camp, and powerhouse, located on Iliamna Lake, will
only require a relatively small area. Because of the large surface area of
Kukaklek Lake, the amount of flow diversion through the penstock is
expected to result in only a minimum amount of lake fluctuation, with
minimal impact on shoreline vegetation.
The development of a local Newhalen River hydroelectric facility to serve
the Newhalen River area is expected to have only a minimal impact on
vegetation and terrestrial ecology. Because the location of this site is
on the west side of the Newhalen River, and a bridge will have to be
constructed, with an existing road from the Iliamna Airfield utilized to
minimize the terrestrial impacts. The area is classified a high brush
ecosystem and is dominated by low-growing shrubs and scattered white spruce
and paper birch.
The transmission corridors associated with this energy plan are expected to
be similar to those of a regional Tazimina River hydroelectric facility;
however, the section between the Newhalen and Kvichak Rivers along the
northern and western portion of Iliamna Lake will be eliminated. A
transmission corridor from the Kukaklek site to the Kvichak River will
traverse through moist tundra and bottomland spruce-birch forest.
7-78
I
• •
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
;
I .. •
• ..
I
I
I
7.3.9.5 Scenario B-3
The development of the Kukaklek hydroelectric site to serve the lower
Kvichak River and upper Alaska Peninsula region is expected to have a
significant impact on vegetation and terrestrial ecology. While this
energy plan proposes only a 3-mile penstock to two unnamed lakes northwest
of Kukaklek Lake, rather than a 9-mile penstock to Iliamna Lake for a
regional concept, the area of impact is considerably larger. A new
reservoir is proposed in the area of the unnamed lakes and will inundate
approximately 3,800 total acres. A net loss of approximately 2,600 acres
will occur since the two unnamed lakes currently occupy about 1,200 acres.
This acreage, in addition to the access road from the barge facility and
construction camps, consists of moist tundra and upland spruce-birch forest.
The development of the Chikuminuk hydroelectric site to serve the Nushagak
River region is expected to have some impact on vegetation and terrestrial
ecology. Because of the remoteness of this site, an airfield will have to
be constructed to bring in equipment and supplies. Also, because of the
rugged terrain surrounding Chikuminuk Lake and its location within the
Wood-Tikchik State Park, the airfield is proposed to be constructed outside
the park boundary. Several hundred acres of upland spruce-birch forest
will be permanently removed for construction of the airfield, construction
camp, supply and storage area, and the approximately l3-mile access road
connecting the airfield to the proposed facility site at the outlet of
Chikuminuk Lake. Since no additional water storage is required for power
generation, no terrestrial impacts are expected to occur around the lake,
resulting from inundation and periodic reservoir drawdown for power
generation.
The impacts on vegetation and terrrestrial ecology associated with the
development and implementation of the local Newhalen River hydroelectric
facility are described in Section 7.3.9.4.
The impacts on vegetation and terrestrial ecology associated with the
transmission line corridors of this energy plan are expected to be similar
to those anticipated for Scenario B-2 described in Section 7.3.9.4.
7-79
Because the Nushagak and Kvichak River regions will not be connected in
this energy plan, the main transmission line between the Kvichak and
Nushagak Rivers will not be required. However, a main transmission line
from the Chikuminuk facility to Dillingham is necessary. This corridor
will be approximately 110 miles long and traverse through primarily lowland
spruce-birch forest. A feeder line approximately 35 miles in length will
connect New Stuyahok to the main transmission line in the vicinity of Lake
Beverly. This corridor also will traverse primarily through lowland
spruce-birch forest. As previous ly discussed, main transmission corridors
will be about 50 feet in width, and will only be cut, as required, for
maintenance purposes.
7.3.9.6 Scenarios B-4, B-6, and B-7
These energy plans have been dropped from further evaluation (Section
7.3.2.6).
7.3.9.7 Scenario B-5
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the Kukaklek hydroelectric site to serve
the lower Kvichak and upper Alaskan Peninsula region are expected to be
similar to those anticipated for the regional Kukaklek site described in
Section 7.3.9.4.
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the local Tazimina run-of-river
hydroelectric concept are expected to be considerably less than those
anticipated for the regional Tazimina hydroelectric storage concept. The
major difference in the two developments would be that a local Tazimina
River facility would be a run-of-river concept, while the regional Tazimina
River facility is a storage concept reservoir. The operation of the local
Tazimina run-of-river hydroelectric facility is not expected to have any
significant impact on vegetation and terrestrial ecology resulting from the
intake structure at the forebay dam.
7-80
a
I
I
I
I
I
I
I
I
I
I
I
I
I
,I
I
I
I
I
I
I,
I
I
I
t
t
t
r
II
7.3.9.8 Scenario B-8
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the Tazimina River hydroelectric site to
serve the Kvichak River and Alaskan Peninsula region are expected to be
similar to, but not as extensive as, those anticipated for the regional
Tazimina River hydroelectric facility. The reservoir storage area requires
that only about 2,700 acres be inundated above the present lower Tazimina
Lake level; the regional Tazimina River concept requires that approximately
4,100 acres be inundated.
The transmission line corridors from the Tazimina River hydroelectric
facility Within the Kvichak River and upper Alaskan Peninsula region are
expected be identical to those for the regional Tazimina River
hydroelectric facility. There will, however, be no transmission line
corridor connecting the Nushagak and Kvichak River systems.
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the Chikuminuk hydroelectric site to
serve the Nushagak River region are described in Section 7.3.9.5.
7.3.9.9 Scenarios B-9 and B-10.
Scheme A
The development of a coal-fired steam-electric generating facility in
either Dillingham (B-9) or Naknek (B-10) to serve the entire study region
is expected to have a local impact on vegetation and terrestrial ecology.
Construction at the site, including all appurtenant facilities associated
with a coal-fired, steam-electric generating facility, will require the
permanent removal of approximately 15 acres of vegetation. In the areas
around Dillingham and Naknek, the primary ecosystems are either wet or
moist tundra.
The operation of coal-fired, steam-electric generating facility is expected
to have a minimal impact on vegetation and terrestrial ecology. However, a
7-81
detailed air emission impact study may be necessary to determine if a
significant impact would result.
The effects on vegetation and terrestrial ecology associated with the
construction and maintenance of transmission line corridors of this energy
plan are expected to be similar to those anticipated for the development of
the regional Tazimina River hydroelectric storage facility described in
Section 7.3.9.2.
Scheme B
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of an oil-fired (diesel) combined cycle
facility located in either Dillingham (B-9) or Naknek (B-10) to serve the
entire study region are expected to be similar to those anticipated in
Scheme A, above.
Scheme C
The' impacts on vegetation and terrestrial ecology associated with the
development and implementation of a coal gasification combined cycle
facility located in either Dillingham (B-9) or Naknek (B-10) to serve the
entire study region are expected to be similar to those anticipated in
Scheme A, above.
,7.3.9.10 Scenarios B-11 and B-12
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of a coal-fired, steam-electric generating
facility in either Dillingham (B-11) or Naknek (B-12) to serve the study
region, except for the Newhalen River area, are expected to be similar to
those described in Section 7.3.9.9, except that there will be no
transmission line corridor between Igiugig and Newhalen.
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the local Newhalen River hydroelectric
site are described in Section 7.3.9.4.
7-82
2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
t
" •
I
I
il
t
t
-!
7.3.9.11 Scenario B-13
Scheme A
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the Chikuminuk hydroelectric site to
serve the study region, with the exception of the Newhalen River area, are
expected to be similar to those described in Section 7.3.9.5. Additional
impacts on vegetation and terrestrial ecology are expected to occur when
the level of Chikuminuk Lake is raised to elevation 619 ft (MSL), which is
required for power generation. This will result in the loss of
approximately 3,700 acres of high bush ecosystem around the lake.
A transmission line corridor will be required to bring power from the
Nushagak River region across to the lower Kvichak River and upper Alaskan
Peninsula region. No transmission line corridor will be developed between
Igiugig and Newhalen.
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the local Tazimina run-of-river
hydroelectric concept are described in Section 7.3.9.7.
Scheme B
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the Chikuminuk hydroelectric site to
serve the study region, except the Newha1en River area, are described in
Scheme A, above.
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the local Newha1en River hydroelectric
site are described in Section 7.3.9.4.
7-83
7.3.9.12 Scenario B-14
Scheme A
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the regional Newhalen River hydroelectric
site, utilizing a "power only" canal, are expected to be more significant
than those anticipated for the local Newhalen River hydroelectric site.
While development will be confined to the east side of the Newhalen River,
this concept involves a wide canal for flow diversion, which will require
the removal of approximately 150 acres of high brush ecosystem.
The impacts on vegetation and terrestrial ecology associated with the
transmission line corridors are expected to be the same as those
anticipated for the regional Tazimina River hydroelectric concept described
in Section 7.3.9.2.
Scheme B
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the regional Newhalen River hydroelectric
site, utilizing a large canal for both power intake and high river flow
diversion, are expected to be more significant than those anticipated for
the local Newhalen River hydroelectric site. While development will be
confined to the east side of the Newhalen River, this concept involves a
wide canal for flow diversion, which will require the removal of
approximately 150 acres of high brush ecosystem.
The impacts on vegetation and terrestrial ecology associated with the
transmission line corridors are expected to be the same as those
anticipated for the regional Tazimina River hydroelectric concept described
in Section 7.3.9.2.
7.3.9.13 Scenario B-15
The development and implementation of four diesel-electric generating
centers at Dillingham, New Stuyahok, Naknek, and Newhalen is expected to
7-84
I
I
I
)
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-•
;
;
r .. ...
--..
have no significant impact on vegetation and terrestrial ecology. The
construction and maintenance of transmission line corridors, however, is
expected to have an impact on vegetation and terrestrial ecology.
Transmission line corridors for this energy plan are described in Section
7.3.8.13. Areas of most significant impact are expected to occur in the
area of densest forest: 1) near Portage Creek in the Nushagak River
valley; 2) west of Dillingham on the uplands between the Snake, Weary, and
Igushik Rivers; and 3) in the lower Alagnak River valley.
7.3.9.14 Scenario B-16
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of this energy plan are expected to be the
same for those anticipated for the energy plan described in Section
7.3.9.13. However, a main transmission intertie proposed to connect
Dillingham and Naknek is designed to cross the area between Portage Creek
and Kvichak over tundra.
7.3.9.15 Scenario B-17
The impacts on vegetation and terrestrial ecology associated with the
development of two independent diesel-electric generating centers in
Dillingham and Naknek are not expected to be significant. The construction
and maintenance of the transmission corridors associated with the
development of this energy plan is expected to have similar impacts on
vegetation and terrestrial ecology as anticipated for the regional Tazimina
River hydroelectric facility.
7.3.9.16 Scenario B-18
Scheme A
The development and implementation of the Kontrashibuna hydroelectric site
to serve the study region is expected to have some effects on vegetation
and terrestrial ecology; these effects are expected to be similar to those
anticipated for those at the regional Tazimina River hydroelectric storage
7-85
site described in Section 7.3.9.2. Nearly all of the vegetation in the
Tanalian River valley and around Kontrashibuna Lake is upland spruce-birch
forest. Approximately 2,000 acres will be lost as a result of raising the
level of the lake for meeting power generation needs.
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the regional Tazimina run-of-river
hydroelectric concept are described in Section 7.3.9.7.
The impacts on vegetation and terrestrial ecology associated with the
construction and maintenance of the transmission line corridors for this
energy plan are expected to be similar to those anticipated for the
regional Tazimina River hydroelectric storage facility described in Section
7.3.9.2. However, an additional 25 miles of corridor will have to be
constructed between Port Alsworth and Sixmile Lake through upland
spruce-birch forest.
Scheme B
The impacts on vegetation and terrestrial ecology associated with the
development and implementation of the Kontrashibuna hydroelectric site to
serve the entire study region are described in Scheme A, above.
7 . 3 . 9 . 17 Scenar io B -19
Scheme A
The development and implementation of this energy plan is not expected to
have any significant impacts upon vegetation and terrestrial ecology.
Scheme B
The development and implementation of this energy plan is not expected to
have any significant impacts upon vegetation. and terrestrial ecology.
However, there is expected to be some minor disturbance of vegetation
associated with the development of supplemental wind energy facilities at
7-86
..
II
I
I
I
• ..
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,.
1
, ..
I'" .11
Igiugig, Naknek, and Egegik. This impact, however, is anticipated to be
both localized and short-term.
Scheme C
The development and implementation of this energy plan is not expected to
have any significant impacts upon vegetation and terrestrial ecology.
However, there is expected to be some minor disturbance of vegetation
associated with the development of supplemental wind energy facilities at
Igiugig, Naknek, and Egegik. This impact, however, is anticipated to be
both localized and short-term.
Scheme D
The development and implementation of this energy plan is not expected to
have any significant impacts upon vegetation and terrestrial ecology.
Scheme E
The development and implementation of this energy plan (Base Plan
supplemented by wind energy and waste heat recovery) to serve the study
region, except the Newhalen area, is not expected to have any significant
impact on vegetation and terrestrial ecology.
The impacts on vegetation and terrestrial ecology associated with
development and implementation of the local Tazimina
hydroelectric site to serve the Newhalen area are described
7.3.9.2 and 7.3.9.7.
7.3.10 Recreational Resource Value
7.3.10.1 Scenario BP-1
run-of-river
in Sections
The development and implementation of this energy plan is not expected to
have any significant impacts on recreational resource value in the study
region.
7-87
7.3.10.2 Scenario A-I
The development and implementation of the regional Tazimina River
hydroelectric storage concept is expected to have little effect on the
recreational resource value of the area. The areas where the development
of the hydroelectric site will be most felt are in the area of sport
fisheries. The gorge section of the lower Tazimina River, which presently
supports trophy-size rainbow trout and large grayling, will be affected by
flows regulated during the operation of the facility. Normal high flows
will be reduced and low flows augmented. Reduction in flow in the section
of river above the falls will occur. The creation of a new large reservoir
is expected to reduce the number of presently established rearing and
spawning areas for resident fish.
In the area of wildlife habitat, the only long-term effect the development
is expected to have will be on the moose habitat in the wetland area
between the lakes. Some beaver habitat may also be lost on some
tributaries to the lower lake. Because of the lack of abundance of trophy
game animals in the Tazimina basin, the recreation resource value is not
expected not be significantly affected. However, access into the area will
be greatly improved as a result of the development of a road into the site
from the Newhalen River.
A detailed discussion on recreation impacts can be found in Appendix G,
Section 7.
7.3.10.3 Scenario B-1
The development and implementation of this energy plan is not expected to
have any significant impacts on the recreational resource value of the
study region.
7.3.10.4 Scenario B-2
The development and implementation of the Kukaklek hydroelectric site to
serve the study region, except for the Newhalen River area, is expected to
7-88
I
I
I
I
!
I
I
I
I
I
I
I
I
I
I
I
I
I
I
po
..
•
have some effect on the recreational resource value of the Alagnak River
basin. Because the area to the north of Kukaklek Lake is classified as
prime moose habitat and is a wintering ground for caribou, any development
in that area may affect the habitat of those large mammals. Also, because
of the diversion of flow from Kukaklek Lake to Iliamna Lake the down-stream
habitat of the Alagnak River may be altered, thus affecting all five
species of Pacific salmon and numerous resident species, which inhabit the
river.
While Kukaklek Lake has no formal lodges or camp sites located on its
shores, the area presently lies within the Mt. Katmai National Park and
Preserve, and is readily accessible by float plane. Also, in addition to
the excellent hunting and fishing opportunities available, the Alagnak
River, below the outlet of the Kukaklek Lake is classified as a National
Wild and Scenic River, and is used for recreational float trips .
The development and implementation of the Newhalen River to serve the local
area is expected to have only a minor effect upon the recreational and
sport fishery value of the lower river. The river is currently an
important recreational angling stream, and has many hunting and fishing
lodges located nearby. The lower section of river is noted for its
grayling, sockeye salmon, and trophy rainbow trout. The area also serves
as a staging point for recreational usage of the nearby Lake Clark region.
7.3.10.5 Scenario B-3
The impacts on the recreational resource value associated with the
development and implementation of the Kukaklek hydroelectric site to serve
the lower Kvichak River and upper Alaskan Peninsula region are expected to
be similar to those anticipated for the regional Kukaklek site described in
Section 7.3.10.4.
The development and implementation of the Chikuminuk hydroelectric site to
serve the Nushagak River region is not expected to have any significant
impacts on the recreational resource value of the Chikuminuk Lake! Allen
River area. While access to the area is expected to be enhanced with the
7-89
construction of an airfield near the Tikchik River and a connecting road to
the Chikuminuk Lake outlet, the value of the recreational resource is not
expected to be degraded as a result. With the development of a regulating
structure and powerhouse, only a small section of the Allen River will be
affected by reduced flows resulting from diversion through a short penstock.
The impacts on recreational resource value associated with the development
and implementation of the local Newhalen River hydroelectric site are
described in Section 7.3.10.4.
7.3.10.6 Scenarios B-4, B-6, and B-7
These energy plans have been dropped from further evaluation (Section
7.3.2.4).
7.3.10.7 Scenario B-S
The impacts on recreational resource value associated with the development
and implementation of the Kukaklek hydroelectric site to serve the lower
Kvichak River and upper Alaskan Peninsula region are expected to be similar
to those anticipated for the regional Kukaklek site described in Section
7.3.10.4.
The impacts on recreational resource value associated with the development
and implementation of the Chikuminuk hydroelectric site to serve the
Nushagak River region are described in Section 7.3.10.5.
The impacts on recreational resource value associated with the development
and implementation of the local Tazimina run-of-river hydroelectric concept
to serve the Newhalen River area are expected to be significantly less than
those anticipated for the regional Tazimina River hydroelectric storage
concept described in Section 7.3.10.2. The reduction of considerable
wildlife and fish spawning and rearing habitat will not occur because a
storage reservoir is not required.
7-90
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
-
, ..
-
-
-
-
..
.. -
-
7.3.10.B Scenario B-B
The impacts on recreational resource value associated with the development
and implementation of the Tazimina River hydroelectric site to serve the
Kvichak River and upper Alaskan Peninsula region are expected to be similar
to those anticipated for the regional Tazimina River hydroelectric storage
concept described in Section 7.3.10.2. Because the storage requirement for
power generation will be less, the proposed reservoir is not expected to
affect terrestrial wildlife habitat to the extent a regional concept
would. All other impacts on recreational resource value are expected to be
the same as described for the regional concept.
The impacts on recreational resource value associated with the development
and implementation of the Chikuminuk hydroelectric site to serve the
Nushagak River region are described in Section 7.3.10.5.
7.3.10.9 Scenarios B-9 and B-10
Scheme A
The development and implementation of a coal-fired, steam-electric
generating facility to serve the entire study region, located in either
Dillingham (B-9) or Naknek (B-10), is not expected to have any significant
impacts on the recreational resource value of either of those areas, or the
region.
Scheme B
The development and implementation of an oil-fired (diesel) combined cycle
generating facility, located in either Dillingham (B-9) or Naknek (B-10) to
serve the entire study region is not expected to have any significant
impacts on the recreational resource value of either of those areas, or the
region .
7-91
Scheme C
The development and implementation of a coal gasification combined cycle
facility, located in either Dilingham (B-9) or Naknek (B-10), to serve the
entire study region, is not expected to have any significant impacts on the
recreational resource value of either of those areas, or the region.
7.3.10.10 Scenarios B-ll and B-12
The development and implementation of a coal-fired, steam-electric
generating facility at either Dillingham (B-ll) or Naknek (B-12) to serve
the study region J except for the Newhalen River area, is not expected to
have any significant impacts on recreational resource value.
The impacts on recreational resource value associated with the development
and implementation of a local Newhalen River hydroelectric facility are
described in Section 7.3.10.4.
7.3.10.11 Scenario B-13
Scheme A
The development and implementation of the Chikuminuk hydroelectric site to
serve the study region. except for the Newha1en River area, is expected to
have some minor effects on the recreational resource value of the
Chikuminuk Lake area. Chikuminuk Lake is expected to have some of its fish
spawning and rearing areas reduced because of raising the lake level for
power generation. Also, some moose habitat is expected to be lost from
inundation of the wetlands areas in the western portion of the lake.
Access, however is expected to be enhanced by the construction of an
airfield outside the Wood-Tikchik Park boundary with an approximately
13-mile connecting road along the Allen River to the Chikuminuk Lake outlet.
The impacts on recreational resource value associated with development and
implementation of the local Tazimina run-of-river hydroelectric concept are
described in Section 7.3.10.7 and detailed in Appendix G, Section 7.
7-92
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
-
-.. ..
-
, ..
.. ..
-
-...
Scheme B
The impacts on recreational resource value associated with the development
and implementation of the Chikuminuk hydroelectric site to serve the study
region, except the Newhalen River area, are described in Scheme A, above.
The impacts on recreational resource value associated with the development
and implementation of the local Newhalen River hydroelectric concept are
described in Section 7.3.10.4.
7.3.10.12 Scenario B-14
Scheme A
The impacts on recreational resource value associated with the development
and implementation of the regional Newhalen River hydroelectric concept,
utilizing a "power only" canal, are expected to be greater than those
anticipated for the local Newhalen River concept. The primary reason is
that more flow will be diverted through the proposed canal than through the
local power tunnel, resulting in reduced flows in the portion of the lower
Newhalen River being bypassed.
Scheme B
The impacts on recreational resource value associated with the development
and implementation of the regional Newhalen River hydroelectric concept,
utilizing a large canal for both power intake and high river flow
diversion, are expected to be greater than those anticipated for the local
Newhalen River concept. The primary reason is that more flow will be
diverted through the proposed canal than through the local power tunnel,
resulting in reduced flows in the portion of the lower Newhalen River being
bypassed.
,
There is also the possibility, however, that the recreational fishery
resource may be enhanced, particularly during high flow periods when
extreme velocities have reportedly prevented upstream migration of spawning
7-93
I
salmon. Resident fish species may also benifit from flow diversion at I
these times.
7.3.10.13 Scenario B-1S
The development and implementation of this energy plan is not expected to
have any significant impact on the recreational resource value of the study
region.
7.3.10.14 Scenario B-16
The development and implementation of this enery plan is not expected to
have any significant impact on the recreational resource value of the study
region.
7.3.10.15 Scenario B-17
The development and implementation of this energy plan is not expected to
have any significant impact on the recreational resource value of the study
region.
7.3.10.16 Scenario B-18
Scheme A
The development and implementation of the Kontrashibuna hydroelectric site
to serve the study region is expected to have some effect on the
recreational resource value of the Kontrashibuna Lake/Tanalian River
basin. The raising of Kontrashibuna Lake for water storage and power
generation is expected to reduce the brown and grizzly bear habitat along
the southern shore of the lake. Also, the raising of the lake is expected
to reduce many resident fish spawning and rearing habitats. While there
are no data on the usage of this area, there are many hunting and fishing
lodges located in the region from Port Alsworth to Iliamna. The area is
accessible by float plane and the lake is located in a designated
wilderness area within the Lake Clark National Park and Preserve.
7-94
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
r ..
,.
..
-
-
The impacts on recreational resource value associated with the development
and implementation of the regional Tazimina run-of-river concept are
described in Section 7.3.10.7 and detailed in Appendix G, Section 7.
Scheme B
The impacts on recreational resource value implementation of the
Kontrashibuna hydroelectric site to serve the entire study region are
described in Scheme A, above.
7.3.10.17 Scenario B-19
Scheme A
The development and implementation of this energy plan is not expected to
have any significant impact on recreational resource value anywhere within
the study region.
Scheme B
The development and implementation of this energy plan is not expected to
have any significant impact on recreational resource value anywhere within
the study region.
Scheme C
The development and implementation of this energy plan is not expected to
have any significant impact on recreational resource value anywhere within
the study region.
Scheme D
The development and implementation of this energy plan is not expected to
have any significant impact on recreational resource value anywhere within
the study region.
7-95
Scheme E
The development and implementation of the Base Plan, supplemented by wind
energy and waste heat recovery, to serve the study region, except the
Newhalen area, is not expected to have any significant impact on the
recreational resource value anywhere within the study region.
The impacts on recreational resource value associated with the development
and implementation of the local Tazimina run-of-river hydroelectric site
are described in Section 7.3.10.7 and detailed in Appendix G, Section 7.
7 . 3 . 11 V isual Impact
7.3.11.1 Scenario BP-l
The development and implementation of this energy plan is not expected to
have any significant effect on the visual resource value of the study
region.
7.3.11.2 Scenario A-1
The development and implementation of the regional Tazimina River
hydroelectric storage concept is expected to have some effects on the
visual resource value of the area. The diversion of water through the
hydroelectric plant will reduce flow over the falls and affect its
appearance. While the faci1ites associated with power generation, that is,
the dam, penstock, powerhouse, transmission lines, and access road,
constitute a significant intrusion into an otherwise undisturbed area,
visual quality is expected to be most affected when viewed from the air.
However, because of the visual diversity that naturally occurs in the
Tazimina area, many of the visual intrusions can expect to be absorbed.
Except for shoreline being exposed during periods of drawdown, the new
reservoir created as a result of the storage dam will appear as a large
natural lake.
7-96
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
'" ..
.... ..
..
,.
-
....
-
-
Detailed discussion regarding mitigation of visual impacts, including
transmission lines, are found in Appendix G, Section 8.2.
7.3.11.3 Scenario B-1
The development and implementation of this energy plan is expected to have
a significant impact on the visual resource value of the study region. The
visual impacts associated with the transmission line corridor of this
energy plan, however, are expected to be similar to those of the other
regional energy plans. Anticipated impacts are discussed in detail in
Appendix G, Section 8.2.2.
7.3.11. 4 Scenario B-2
The development and implementation of the Kukaklek hydroelectric site to
serve the study region, except for the Newhalen River area, is expected to
have a considerable effect on the visual resource value of the Kukaklek
Lake area. The feature that is expected to have the most impact is the
penstock. While it is proposed to be buried, the removal of the vegetative
surface may leave a scar which could be evident for many years even after
revegetation. The location of the powerhouse near the shore of Iliamna
Lake is expected to be screened by terrain and vegetation on three sides;
however, it is expected to be visible from the lake. The intake canal and
flow regulating structure are expected to be the only visual intrusions on
Kukaklek Lake.
The development and implementation of the Newhalen River hydroelectric site
to serve the local Newhalen River area is expected to have only a minor
effect on the visual quality of the area. Possibly the most significant
impact would be the construction of a bridge over the Newhalen River at the
first set of rapids upstream from I liamna Lake. The powerhouse will be
located immediately downstream of the bridge below the rapids and will be
screened from three sides. The primary visual impact will occur from the
east bank. The access road is expected to affect aerial views only .
7-97
7.3.11.5 Scenario B-3
The development and implementation of the Kukaklek hydroelectric site to
serve the lower Kvichak River and upper Alaskan Peninsula region is
expected to have a significant impact on the visual resource of the
Kukaklek area. While this concept proposes a shorter penstock route, about
three miles in length, to two unnamed lakes northwest of Kukaklek Lake, it
is also proposed that a six-square-mile reservoir be created to accommodate
the flow diversion. Other facilities are expected to have a similar impact
on visual quality as anticipated for the regional Kukaklek concept
described in Section 7.3.11.4.
The development and implementation of the Chikuminuk hydroelectric site to
serve the Nushagak River region is expected to have some impacts on the
visual quality of the Allen River area. The primary visual impact is
expected to occur from the construction of the airfield near the Tikchik
River and the approximately 13 mile access road to the Chikuminuk Lake
outlet. The construction of the regulating structure at the outlet of the
lake, and the powerhouse immediately downstream of the rapids, is not
expected to significantly impact the visual quality of that area.
The impacts on the visual quality associated with the development and
implementation of the local Newhalen River hydroelectric site are described
in Section 7.3.11.4.
7.3.11.6 Scenarios B-4, 8-6, and B-7
These energy plans have been dropped from further evaluation (Section
7.3.2.6).
7.3.11.7 Scenario B-5
The impacts on visual quality associated with the development and
implementation of the Kukaklek hydroelectric site to serve the lower
Kvichak River and upper Alaskan Peninsula region are expected to be similar
to those anticipated for the regional Kukaklek concept described in Section
7.3.11.4.
7-98
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,...
L
...
-
-
-
-
-
The impacts on visual quality associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the Nushagak
River region are described in Section 7.3.11.5.
The impacts on visual quality associated with the development and
implementation of the local Tazimina run-of-river hydroelectric concept are
expected to be considerably less than those anticipated for the regional
Tazimina River hydroelectric storage concept. The primary visual
intrusions are expected to be a small regulating structure with intake, the
penstock, the powerhouse, and transmission lines.
of these structures is expected to occur from
Tazimina River.
7.3.11.8 Scenario B-8
The major visual impact
locations on the lower
The development and implementation of the Tazimina River hydroelectric site
to serve the Kvichak River and upper Alaskan Peninsula region is expected
to have some effects on the visual quality of the Tazimina area. These
effects are expected to be similar to, but not as extensive as, those
anticipated for the regional Tazimina River hydroelectric storage concept
described in Section 7.3.11.2. A detailed discussion anticipated visual
impacts is found in Appendix G, Section 8.2.
The impacts on visual quality associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the Nushagak
River region are described in Section 7.3.11.5.
7.3.11.9 Scenarios B-9 and B-IO
Scheme A
The development and implementation of a coal-fired, steam-electric
generating facility either in Dillingham (B-9) or Naknek (B-10) to serve
the entire study region is expected to have a significant impact on the
visual quality of those areas. Because the vegetation surrounding both
Dillingham and Naknek is relatively homogeneous and the terrain relatively
7-99
I
flat, the degree of landscape absorption from a 15-acre, coal-fired. II
steam-electric generating facility is expected to be small. While the
greatest visual impact is expected to be from the air. screening at the
surface is also expected to be difficult.
Scheme B
The impacts on visual quality associated with the development and
implementation of an oil-fired (diesel) combined cycle facility located in
either Dillingham (B-9) or Naknek (B-10) to serve the entire study region
are expected to be similar to those anticipated for a coal-fired facility
described in Scheme A. above. However. instead of coal pile areas, oil
storage tanks will be constructed.
Scheme C
The impacts on visual quality associated with the development and
implementation of a coal gasification combined cycle facility located in
either Dillingham (B-9) or Naknek (B-10) to serve the entire study region
are expected to be similar to those anticipated for a coal-fired facility
described in Scheme A, above.
7.3.11.10 Scenarios B-11 and B-12
The impacts on visual quality associated with the development and
implementation of a coal-fired. steam-electric generating facility are
described in Section 7.3.11.9.
The impacts on visual quality associated with the development and
implementation of the local Newha1en River hydroelectric site are described
in Section 7.3.11.4.
7.3.11. 11 Scenario B-13
Scheme A
The development and implementation of the Chikuminuk hydroelectric site to
serve the study region, except for the Newha1en River area, is expected to
7-100
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-..
-
-..
.. -
-
1M -
-
have some effects on the visual quality of the Chikuminuk Lake/Allen River
basin. The primary visual impact is expected to be the construction of an
airfield and access road, described in Section 7.3.11.5. Another visual
impact is expected to occur around the shoreline of Chikuminuk Lake as the
lake is drawn down for power generation from its proposed elevated level.
This impact is expected to be seen most at the western end of the lake
where the terrain is low and flat. The small storage dam and powerhouse
are expected to be relatively well-absorbed by the surrounding terrain.
Visual impact is expected to be the greatest from the air.
The impacts on visual quality associated with the development and
implementation of the local Tazimina run-of-river hydroelectric concept, to
serve the Newhalen River area, are described in Section 7.3.11.7.
Scheme B
The impacts on visual quality associated with the development and
implementation of the Chikuminuk hydroelectric site to serve the study
region, except the Newhalen River area, are described in Scheme A, above .
The impacts on visual quality associated with the development and
implementation of the local Newhalen River hydroelectric site are described
in Section 7.3.11.4.
7.3.11.12 Scenario B-14
Scheme A
The impacts on visual quality associated with the development and
implementation of the Newhalen River hydroelectric concept, utilizing a
"power only" canal, to serve the entire study region are expected to be
similar to those anticipated for both the local Newhalen River concept and
the regional Tazimina run-of-river concept. While there will be no bridge
over the Newhalen River, with an access road and facilities on the west
bank, there will, however, be a longer access road on the east side and a
long canal associated with this hydroelectric concept. Visual intrusion is
7-101
expected to be primarily from the air; however, the access road which will I
be elevated above the existing terrain (utilizing the material excavated
from the diversion canal) will be difficult to screen from the ground.
Scheme B
The impacts on visual quality associated with the development and
implementation of the Newhalen River hydroelectric concept. utilizing a
large canal for both power intake and high river flow diversion, to serve
the entire study region are expected to be similar to those anticipated for
both the local Newhalen River concept and the regional Tazimina
run-of-river concept. While there will be no bridge over the Newhalen
River, with an access road and facilities on the west bank, there will.
however. be a longer access road on the east side and a long canal
associated with this hydroelectric concept. Visual intrusion is expected
to be primarily from the air; however. the access road which will be
elevated above the existing terrain (utilizing the material excavated from
the diversion canal) will be difficult to screen from the ground.
7.3.11.13 Scenario B-15
The development and implementation of this energy plan is not expected to
have any significant impacts on the visual quality of the study region.
However. as discussed in several other energy plans, transmission lines and
their corridors present a visual intrusion into an otherwise natural,
undisturbed landscape. Anticipated transmission line impacts are discussed
in detail in Appendix G, Section 8.2.2.
7.3.11.14 Scenario B-16
The development and implementation of this energy plan is not expected to
have any significant impacts on the visual quality of the study region.
7.3.11.15 Scenario B-l7
The development and implementation of this energy plan is not expected to
have any significant impacts on the visual quality of the Dillingham or
7-102
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
-
-
-
-
-
-
Naknek areas. The impacts on visual quality associated with the
construction and maintenance of the transmission line are expected to be
similar to those anticipated for the regional Tazimina River hydroelectric
storage concept described in Section 7.3.11.2.
7.3.11.16 Scenario B-IS
Scheme A
The development and implementation of the Kontrashibuna hydroelectric site
to serve the study region is expected to have similar impacts on visual
quality as anticipated for the regional Tazimina River hydroelectric
storage concept. Approximately 2,000 acres of upland spruce-birch forest
will be lost as a result of raising the surface level of Kontrashibuna Lake
for power generation. This new inundated zone will be drawn down
periodically for power generation and is expected to cause an impact on the
visual quality of the area from both the water surface and the air. The
other associated hydroelectric facilities are expected to be better
screened from the ground level than at the Tazimina River site because of
the denser forest cover in this basin. The penstock will be tunneled
through Tanalian Mountain, thus minimizing its visual impact. The
diversion of flow through the penstock is expected to be visually evident
by the reduced flows of the Tanalian River between Kontrashibuna Lake and
Lake Clark.
The impacts on visual quality associated with the development and
implementation of the regional Tazimina run-of-river hydroelectric concept,
are described in Section 7.3.11.7.
Scheme B
The impacts on visual quality associated with the development and
implementation of the Kontrashibuna hydroelectric site to serve the entire
study region are described in Scheme A, above.
7-103
7.S.11.17 Scenario B-19
Scheme A
The development and implementation of this energy plan is not expected to
have a significant impact on the visual resource value of the study region.
Scheme B
The development and implementation of this energy plan is not expected to
have a significant impact on the visual resource value of the study region,
except in the areas around Igiugig, Naknek, and Egegik where wind
generating towers are expected to intrude on the horizon.
Scheme C
The development and implementation of this energy plan is not expected to
have a significant impact on the visual resource value of the study region,
except in the areas around Igiugig, Naknek, and Egegik where wind
generating towers are expected to intrude on the horizon.
Scheme D
The development and implementation of this energy plan is not expected to
have a significant impact on the visual resource value of the study region.
Scheme E
The development and implementation of this energy plan (Base Plan
supplemented by wind energy and waste heat recovery) to serve the study
region, except the Newhalen area, is not expected to have a significant
impact on the visual resource quality.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
The impacts on visual quality associated with the development and
implementation of the local Tazimina run-on-river hydroelectric site are I
described in Section 7.S.11.7.
I
7-104 I
" ..
...
lilt
-
-
..
7.3.12 Summary Evaluation
This section is intended to provide a subjective evaluation of each of the
energy plans described in the previous sections. The subjective evaluation
criteria used to evaluate environmental indicators were:
A. = Small impact
B. = Moderate impact, but believed acceptable with mitigation measures
C. = Major impact, possibly resulting in a "fatal flaw"
Table 7.3-1 summarizes the results of subjectively rating each energy plan
with respect to each of the ten environmental indicators.
From Table 7.3-1, the following was found:
• The scenarios involving diesel-electric generation exhibit the least
environmental impacts
• The scenario involving a transmission intertie with another region
•
•
•
exhibits major institutional constraints
The hydroelectric scenarios which include the King Salmon and Kukaklek
sites exhibit the greatest environmental and institutional impacts
The other hydroelectric scenarios exhibit only moderate environmental
impacts
The fossil-fuel scenarios exhibit only moderate environmental impacts
The energy plans were not numerically ranked according to environmental
preference due to difficulty in integrating the highly subjective
indicators cons ide red . However, the energy plans were grouped, us ing the
same evaluation criteria used for the indicators. Further, the energy
plans were not ranked within a group.
The scenarios were subjectively grouped as shown below. Descriptions of
the scenarios are found in Section 6.2.
7-105
GrouE A GrouE B GrouE C
Scenario BP-1 * Scenario A-1 Scenario B-1
Scenar io B -15 Scenario B-8 Scenario B-2
Scenario B-16 Scenario B-9A Scenar io B-3
Scenario B-17 Scenario B-9B Scenario B-4
Scenario B-19A Scenario B-9C Scenario B-5
Scenario B-19B Scenario B-10 Scenario B-6
Scenario B-19C Scenario B-11 Scenario B-1
Scenario B-19D Scenario B-12
Scenario B-13A
Scenario B-13B
* Scenario B-14A
* Scenario B-14B
Scenario B-18A
* Scenario B-18B
Scenario B-19E
*Regiona1 hydroelectric developments
ComEarison of the Four Regional Hydroelectric Scenarios
Using the ten environmental indicators, the following subjective evaluation
can be made by comparing the four regional hydroelectric scenarios
(Tazimina, A-l; Newhalen, B-14A and B-14B; and Kontrashibuna. B-18B):
•
•
•
•
•
•
Newhalen (B-14A) appears to have strongest regional preference
Kontrashibuna is expected to have the least impact on community
infrastructure
All four regional plans appear to have no dependence upon the timing of
other proposed capital projects in the region
All four regional plans are expected to have short-term impacts on
local air quality from construction equipment and land clearing activity
Newhalen (B-14A) appears to have the least potential for affecting
riverine water quality
Kontrashibuna is expected to have the least effect on anadromous
fisheries
1-106
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
...
..
-
-
-
---
-
• Newha1en (B-14A) is expected to have the least impact on wildlife
• Newha1en (B-14A) is expected to have the least impact on land use and
ownership status
•
•
•
Newha1en (B-14A) is expected to have the least terrestrial impact
Newha1en (B-14A) is expected to have the least impact on recreational
resource value
Newha1en (B-14A) is expected to have the least impact on visual quality
Reference Section 7.3
1. Ryan, P.J. and D.R.F. Harleman, "Prediction of Annual Cycle of
Temperature Changes in a Stratified Lake or Reservoir: Mathematical
Model and User's Manual", MIT Hydrodynamics Laboratory Technical
Report, No. 137, April 1971 .
7-107
I J • I r I f 1 f I I I r I f 1 I 1 f 1 lei I 1 f'l
TABLE 7.3-1
ENVIRONMENTAL EVALUATION SUMMARY
TIMING TO
COHM. COMM. OTHER AIR WATER fISH 6. LAND USE TERRES. RECREAT. VIS.
SCENARIO PREf. INfRA. CAP PROJ. QUAL. QUAL. WILD. 6. OWN. ECOL. RES. VAL. QUAL. COMMENTS
BP-l A A A A A A A A A A Host widely acceptable acenario
A-I B B B A B C B C B C Possibility of reduced water level in spawning
grsvels; loss of habitat to inundation; village
acceptance based on neg. fish impact
B-1 B A A A A B C B A B Project not on Bristol Bay land; maximum number
of stream crossings by transmission lines;
wildlife habitat impact through Lake Clark
Pass; transmission corridor through designated
wilderness area.
B-2 C B B A B C C C C C Kukaklek Lake within Preserve area of National
Park; residents of Levelock and Igiugig opposed
to development
B-3 C C B A B C C C C C Kukaklek within Nat'l Preserve; Chikuminuk
within State Park; villages opposed to project
and intertie
B-4 Scenario droeeed from further consideration
B-5 C B B A B C C C C C Kukaklek in Nat'l Preserve; Chikuminuk in State
Park; villages opposed to development and
transmission intertie
B-6 Scenario droeeed from further consideration
B-7 Scenario droeeed from further consideration
B-8 C B B A B C C C B C Chikuminuk in State Park; village acceptance at
Tazimina based upon negative fisheries impact
8-9 B C B C B B B B A C Possibility of some air quality impact with
B-9B B C B B A A B B A C coal; community impact is less in a large
B-9C A C B A B B B B A C villsge; villages opposed to intertie
B-lO B C B C B B B B A C Possibility of some sir quality impact with
coal; community impact is less in a large
village; villages opposed to intertie
f J f I ( J r I f I r 1 I J I I I , II II r-1
TAELE 7.3.1
(continued)
ENVIRONMENTAL EVALUATION SUMMARY
TIMING TO
COMM. COMM. OTHER AIR WATER fISH & LAND USE TERRES. RECREAT. VIS.
SCENARIO PREf. INfRA. CAP PRo]. QUAL. QUAL. WILD. & OWN ECOL. RES. VAL. QUAL. COMMENTS
8-11 8 C 8 C 8 8 8 8 A C Possibility of some air quality impact with
coal; community impact is less in a large
village; villages opposed to intertie; some
fisheries impact with hydro project on Newhalen
River
8-12 8 C 8 C 8 8 8 8 A C Possibility of some air quality impact with
coal; community impact is less in a large
village; villages opposed to intertie; some
fisheries impact with hydro project on Newhalen
River
8-lJA 8 8 8 A 8 8 C 8 8 8 Chikuminuk in State Park; transmission intertie
8-lJ8 8 8 8 A 8 8 C 8 8 8 between Dillingham and Naknek not totally
accepted
8-l4A 8 C 8 A A 8 A 8 8 8 Some fisheries impact on Newhalen River; long
8-148 8 C 8 A A 8 A 8 8 C transmission lines
8-15 8 A A 8 A A A A A A Transmission intertie in Up~er Nushagak area
not totally acceptable by t ose villages
8-16 8 A A 8 A A A A A A Some skepticism re: intertie acceptability
between Dillingham and Naknek
8-17 8 8 8 8 A A A A A A Skepticism re: acceptability of maximum
transmission intertie
8-lBA C 8 8 A 8 C C C 8 C Kontrashibuna reservoir in wilderness area
8-lB8 C 8 8 A 8 8 C 8 8 C subsistence hunting and fishing on Tanalian
River
8-l9A A A A A A A A A A A Variations on Base Plan appear widely
8-198 A 8 A A A A A A A A acceptable; Tazimina site acceptability
8-l9C A 8 A A A A A A A A predicated on protection of salmon fishery
8-l9D A A A A A A A A A A
8-l9E A 8 A A A 8 8 8 8 8
EVALUATION LEGEND
A :: Small impact
8 :: Moderate impact, but believed acceptable with mitigation measures
C :: Major impact, possibly resulting in a "fatal flaw"
-..
II
-... -
-...
-
-.. -
..
-
-
7.4 ECONOMIC EVALUATION
7.4.1 General
As described in the previous sections, a large and varied group of power
supply scenarios has been included in this study. In order to compare the
technical and economic performance of these scenarios, a consistent,
systematic evaluation method was used. The present worth of all costs and
benefits (if any) associated with each scenario was the basis for the
economic comparisons. This evaluation takes into account the differences
between power supply alternatives, including capital costs, operation and
maintenance costs, fuel costs, equipment lifetimes, benefits from
fuel-saving measures (waste heat recovery from diesels, wind energy, etc.),
and the timing of all costs and benefits.
To maintain consistency in the economic comparisons, the parameters and
assumptions used in the present worth calculations were the same for all
scenarios. Thus, the scenarios can be compared with each other and ranked
in terms of their ability to supply power to the Bristol Bay Region at the
lowest total cost by comparing present worth cost. The scenario with the
lowest present worth cost is the least costly alternative on a life-cycle
basis and is the most desirable from an economic viewpoint. The final
ranking of alternatives may vary from the economic ranking, however, when
other factors (such as environmental effects) are taken into account.
7.4.2 Parameters and Assumptions
The economic parameters and assumptions used in calculating present worth
costs were in conformance with Power Authority guidelines (Ref 1) except
for the economic lifetimes of certain items of equipment. Summaries of the
economic parameters and equipment lifetimes are shown in Tables 7.4-1 and
7.4-2, respectively .
In the cases involving diesel generators, transmission lines, coal
gasification, and waste heat recovery equipment, the economic lifetimes
shown in Table 7.4-2 are greater than the values suggested by the Power
7-108
Authority. The lifetimes were extended because the type of equipment
specified and the operating conditions (100 percent diesel generator
backup, for example) indicate probable lifetimes greater than those in the
guidelines. These economic lifetimes were reviewed by the Power Authority
and were considered acceptable for use in the study.
As shown in Table 7.4-1, the base year for the economic analysis was 1982
with a 21-year planning period (i.e., Bristol Bay regional electric demand
projection for 1982 through 2002) and a 56-year analysis period. The
analysis period length resulted from the assumed initial operation of
hydroelectric plants in 1988 which, when combined with a 50 year
hydroelectric lifetime, extended the analysis period from the base year of
1982 through the year 2037.
The parameters listed in Table 7.4-1 were used in the economic analysis for
all scenarios. Since inflation was assumed to be zero, all costs and
present worths were expressed in terms of 1982 dollars with the exception
of petroleum fuels which were escalated at a rate of 2.6 percent per year.
A discount rate of 3 percent was used to calculate the present worth of
annual costs. In addition, an interest rate of 3 percent was used to
determine the interest during construction (for one-year and longer
construction periods) and to calculate the annual uniform interest and
amortization payment for capital cost expenditures (assigned each year from
the project's on-line date to the end of the analysis period). For the
diesel generator and hydroelectric cases, a sinking fund for major periodic
equipment replacement was established using the 3 percent rate.
The costs occurring in the years following the planning period from 2003
through 2037 were assigned in accordance with the Power Authority economic
guidelines. It was assumed that after the last year of the planning period
(2002), no further load growth occurred in the Bristol Bay region, the cost
of petroleum fuels remained constant with no further price escalation, and
any eqUipment items that reached the end of their economic lifetimes after
2002 were replaced with identical units. Thus, all costs and benefits (if
any) that occurred in 2002 were repeated for each following year through
2037. The present worth calculations were then based on the 56-year cash
flow for each scenario.
7-109
...
I
I
I
I
I
I
I
I
I
I
I
I
I
I
...
... -..
..
For those diesel systems which included waste heat recovery equipment, a
benefit was assigned each year for the waste heat recovered. As described
in Appendix A, calculations were performed to determine the fraction of the
recoverable waste heat that could be used for space heating. A credit was
applied each year for the space heating supplied from waste heat. It was
assumed that diesel was the fuel normally burned in homes or other
buildings for space heat in determining the waste heat benefit.
Benefits were also applied for other fuel-saving technologies such as
organic Rankine cycle systems using diesel generator waste heat or wind
generators. These technologies were given credit for diesel fuel not
needed to be burned due to their contribution to the electical energy
generated.
Lastly, the costs developed in this study represent busbar costs (per Power
Authority guidelines) and do not include all costs that would comprise the
true consumer cost. For example, cost allowances were not made for
electricity distribution within the villages, administration, taxes,
depreciation, insurance, etc. The present worth of consumer costs would be
significantly higher than the present worth of busbar costs determined in
this study. However. the inclusion of the additional consumer costs would
not affect the relative ranking of the scenarios since the costs would be
common to all cases.
7.4.3 Method of Analysis
Several steps were involved in determining present worth costs for the
Bristol Bay regional power scenarios. The major steps for each scenario
included the following:
1. Develop conceptual deSigns for all systems and equipment included
in the scenario .
2. For each equipment item, determine the installed capital cost,
annual operating and maintenance cost, fuel requirements and
costs, benefits (if any), equipment replacement sinking fund (used
7-110
for diesel generator and hydroelectric systems only), and the
uniform annual payment for interest and amortization.
3. Develop the total annual cost (minus any benefits) for each year
of the 56-year economic analysis period.
4. Calculate the present worth of the annual cost cash flow.
The development of the annual cash flow and present worth cost was
accomplished as described in the previous section.
To facilitate the economic analysis of the Bristol Bay power scenarios, a
computer program was used to perform the discounted cash flow analysis (Ref
2 and 3). A sample output listing from this program is included in Table
7.4-3. The sample case is scenario B-14A, the Newhalen regional
hydroelectric concept with power diversion only.
The B-14A annual cash flows for the complete economic analysis period from
1982-2037 are included in Table 7.4-3. The items shown in the annual cash
flow include the following:
• Peak Demand -Peak kW required per year for the Bristol Bay region
• Annual Energy Use -The total MWh used annually (excluding space
heat) by the region
• Diesel Generator Capital Costs -The total installed costs (1982
dollars) for diesel generator units which, for scenario B-14A, are
used in individual villages until the region is intertied and
hydroelectric power is available in 1988
• Hydroelectric Capital Costs -The total installed cost (including
interest during construction) of the Newhalen regional
hydroelectric plant
7-111
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
•
•
•
•
•
• -
•
•
•
•
•
Transmission Capital Costs -The total installed cost (including
interest during construction) of the regional electric
transmission system
Amortization Cost of Diesel Generator -The uniform annual payment
for interest and amortization of diesel generator capital costs
Amortization Cost of Hydroelectric -The uniform annual payment
for interest and amortization of hydroelectric plant capital costs
Amortization Cost of Transmission -The uniform annual payment for
interest and amortization of transmission capital costs
Amortization Cost of Hydroelectric Replacement The uniform
annual sinking fund payments for major periodic equipment
replacement
Diesel Overhaul Cost A one-time payment in 1982 which was
assumed to bring all existing diesel generator units in the region
into a near-new operating condition
Diesel Sinking Fund -The uniform annual sinking fund payments for
major periodic diesel generator equipment replacement and overhaul
Diesel O&M Costs -The annual operating and maintenance costs
(excluding fuel) for the diesel generator units
Hydroelectric O&M Costs -The annual operating and maintenance
costs for the hydroelectric plant
Transmission O&M Costs -The annual operating and maintenance
costs for the regional transmission system
Diesel Cost Per Gallon -The annual cost for diesel in cents per
gallon with a 2.6 percent escalation rate per year
7-112
•
•
•
•
•
Diesel Fuel Used -The total gallons of diesel fuel used annually
by the region (none is used in the B-14A scenario after the
hydroelectric plant comes on-line in 1988)
Total Diesel Fuel Cost -The total annual regional payments for
diesel fuel
Total Annual Cost -Summation of the annual cost categories
Annual Cost Present Worth -The total annual cost discounted to
January 1 of 1982
Accumulated Present Worth The year-by-year summation of the
annual cost present worth values, with the total scenario present
worth being equal to the accumulated present worth for the year
2037
The cash flows and computer program listings will vary with each scenario,
depending on the types of energy supply technologies included. However,
the same basic types of cost categories and benefits (if any) were included
for each scenario.
7.4.4 Determination of Annual Costs
The costs and benefits which comprise the annual cash flows described in
the previous sections were based on conceptual designs and estimates of the
expected performance of the power equipment. Since detailed designs were
not performed for this initial study phase, the cost estimates represent
order-of-magnitude prices (± 20 to 25 percent). The costs used in this
study were derived from numerous sources. For example, the costs for major
equipment items were obtained from vendors when possible, or from published
materials. Additional allowances were made for freight from the factory to
the jobsite. Other cost factors, such as labor rates, were determined with
the assistance of Green Construction Company of Anchorage. The labor unit
prices included an allowance for fringe benefits, insurance and taxes,
small tools, travel, overtime, camp cost, etc. Lastly, added to the
7-113
I
I
I
I
I
I
I
'J
I ,
I
I
I
I
I
I
I
I
I
t
.,...
estimates were allowances for system engineering and design, construction
management, and indeterminates, reSUlting in an overall multiplier in the
range of 1.3 to 1.5.
The following subsections provide brief descriptions of the major cost
elements (capital cost. operation and maintenance, etc.) which were used
to develop the annual cash flows. The costs are given (in 1982 dollars)
for each of the technologies used in the Bristol Bay power supply
scenarios. Details regarding the design of the systems or their operation
are contained in Appendix A.
7.4.4.1 Diesel Generators
Five scenarios involved diesel generators as the primary power souce:
BP-1, B-15, B-16, B-17, and B-19. The remaining scenarios used diesel
generators to supply power to Bristol Bay during construction periods of
other central power sources (hydroelectric or fossil-fired plants, for
example) and then as backup to the central plants. Appendix A contains a
detailed description of the diesel power systems.
The diesel generator and storage tank capital costs for BP-1, B15, B16, and
B17 are shown in Table 7.4-4. A breakdown of costs by village for BP-1 is
included in Table 7.4-5. The costs are shown for the years in which they
were assumed to occur. Depending on the size of the unit, the diesel
generators installed cost varied in range of 340 to 1000 $/kW. The
storage tank costs varied widely, with as much as $475,000 per tank.
An annual cost was included for the operation and maintenance of the diesel
generators. The following assumptions were used in determining this cost
for all scenarios:
1. Five full-time operators would be located in Dillingham and Naknek
(only two operators were in Naknek for scenario B-17).
2. Two full-time operators would be located in Iliamna.
7-114
3. Two full-time operators would be located in New Stuyahok (only in
the case where it served as a load center for other villages).
4. The cost for each full-time operator would be $50,000 per year.
5. Villages not serving as load centers would have a part-time
caretaker cost of $5,000 per year.
6. An annual allowance for parts and supplies would be added for each
village: $20,000 to $25,000 for load centers and $3,000 for others
7. A sinking fund would be established for major repairs or overhauls
every 10 years. The dollar amount to be supplied by this fund was
determined by taking the estimated price to overhaul all existing
diesels of various sizes in a particular village (those in
operation as of January 1, 1982) and dividing by the total number
of diesel units in the village.
8. As new diesel units were added each five years, the annual
allowance for parts and supplies would increase by $8,000 in the
load centers.
9. When a central non-diesel plant comes on-line (hydroelectric or
fossil-fired), the sinking fund allowance would be cut in half and
a set annual amount of $5,000 per village would be allotted to
maintain the diesel generators in a backup status.
An additional one-time cost of $879,400 was included in 1982 to overhaul
all existing diesel generators in the Bristol Bay region. This cost was
determined by pricing overhauls for all known diesel generators (not
including privately owned) in each village.
Lastly, the 1982 cost of diesel fuel per gallon is shown for all villages
in Table 7.4-6. The 1981 diesel fuel prices were obtained from several
sources in Alaska and escalated to the 1982 prices shown. The weighted
average 1982 diesel fuel price for the Bristol Bay region was calculated to
7-115
~ ,
I
I
I ,
". I
I
I
I
I
I
I
I
,I
I
I
I
I
" lit
be $1.33 per gallon. The weighted price was obtained by taking the product
of the gallons of diesel fuel used in 1982 with the 1982 diesel price per
gallon for each village, summing these amounts for all villages, and then
dividing by the sum of the gallons of diesel used in all villages. Using
the diesel generator fuel rates in Table 7.4-7, a determination was made of
the total number of gallons of diesel fuel used per year in each scenario
(Tables 7.4-8 and 7.4-9) and the annual fuel cost.
7.4.4.2 Waste Heat Recovery EqUipment
The use of diesel waste heat recovery equipment was evaluated for scenarios
B-14A, B-15, B-16, B-17, and two BP-1 variations (B-19A and B-19C). The
installed capital costs are shown in Table 7.4-10 for the years in which
the sytems were assumed to have been installed (B-14A not shown in Table -
see discussion below). A breakdown of these costs for each village in
B-19A and B-19C is given in Table 7.4-11. The operating and maintenance
costs for these systems was assumed to be 2 percent of the installed
capital cost per year.
For scenario B-14A, a special study was performed of the viability of waste
heat recovery from the diesel generators in individual villages in the
years prior to regional interconnection and startup of the Newhalen
Regional Hydroelectric Plant. After plant startup in 1988, the waste
heat recovery system was assumed to no longer operate since the diesel
generators would be serving as backup. The BP-1 waste heat recovery
capital cost occurring in 1982 ($2,085,000) was used for this study.
In all scenarios, a benefit was used in each year in which a waste heat
recovery system was in operation. For the energy delivered by the recovery
system as space heat, the cost of the equivalent number of gallons of
diesel fuel was the benefit. The waste heat benefit, in gallons, is shown
in Table 7.4-12 for B-19A and in Table 7.4-13 for B-15, B-16, and B-17.
Comparisons of the relative costs of systems with and without waste heat
recovery are presented in Section 7.4.5 and Table 7.4-32 through 7.4-38.
7-116
7.4.4.3 Wind Generators
The use of wind generators as a supplemental energy source to diesel
generation (scenarios B-lS, B-16, B-17, B-19B, and B-19C) or hydroelectric
power (scenario B-14A only) was evaluated in this study (Appendix A). The
wind generator sizes considered, along with their installed capital costs
and annual operating and maintenance costs, are shown in Table 7.4-14. The
annual operation and maintenance cost was assumed to be 5 percent of the
installed capital cost. The primary source of data for the wind analyses
was Wind Systems Engineering, Inc. (WSE) of Anchorage. Although the WSE
final report on the use of wind energy in Bristol Bay is included in
Appendix D, the data in Table 7.4-14 are from the preliminary WSE report
(Ref 4). The capital costs in Appendix D are higher than those used in the
wind analyses for this study. Thus, the results of the wind economic
analyses represent an optimistic assessment of wind energy potential.
During Phase II of the study, any wind systems which show promise will be
cos ted and evaluated in detail.
For each scenario including wind generators, a benefit was applied each
year that the wind system produced energy. The benefit was determined as
the cost of the equivalent number of gallons of diesel fuel required by
diesel generators to produce the electrical energy supplied by the wind
generators. The energy supplied by the wind systems was obtained from the
data in Appendix D.
7.4.4.4 Organic Rankine Cycle (aRC) Systems
A study was performed of the use of an aRC system in scenario B-19D at
Dillingham or Naknek. These locations were selected to illustrate the
viability of an aRC system combined with diesel generators.· Appendix A
describes the system used. For each village, a 750 kW aRC system was
assumed to operate (beginning in 1985) from diesel generator waste heat.
The installed capital cost for the aRC system was $2,050,000. The annual
operation and maintenance cost was assumed to be SO.OlS/kWh produced by the
aRC.
7-117
I
I ,
I
I
I
I
I
I
I
I
Ii ,
I
I
i
I
I
I
....
A benefit was applied each year that the aRC produced electrical energy.
The benefit was determined in exactly the same manner as for wind
generators. The energy supplied by the aRC units was conservatively
assumed to be 10 percent of the total electric output of the diesel
generator plant. The aRC benefit, in gallons of diesel saved, is shown in
Table 7.4-15 for Dillingham and Naknek .
7.4.4.5 Hydroelectric Power Plants
Conceptual designs and cost estimates for twelve different hydroelectric
plant concepts were developed for this study. The plant costs were based
on material takeoffs and other estimates based on the conceptual designs.
Detailed descriptions of the plants considered are contained in Appendix A.
Tables 7.4-16 through 7.4-26 contain summaries of the hydroelectric power
plant installed capital costs. The total costs were broken down according
to the accounting methodology of the Federal Energy Regulatory Commission
(FERC). The following twelve plants were studied:
Table 7.4-16
Table 7.4-17
Table 7.4-18
Table 7.4-19A
Table 7. 4-19B
Kukaklek (Kvichak Region) Hydroelectric Power
Plant, two -3,500 kW units
Kukaklek Regional Hydroelectric Power Plant, two -
8,000 kW units
Newhalen River Local Hydroelectic Power Plant, two
-600 kW units
Newhalen River Regional Hydroelectric Power Plant,
Newhalen River Diversion -Power Only, two -8,000
kW units
Newhalen River Regional Hydroelectric Power Plant,
Newhalen River Diversion Power and River
Diversion, two -8,000 kW units
7-118
Table 7.4-20
Table 7.4-21
Table 7.4-22
Table 7.4-23
Table 7.4-24
Table 7.4-25
Table 7.4-26
Tazimina Run-of-River Regional Hydroelectric Power
Plant, two -8,000 kW units
Tazimina River (Kvichak River Region) Hydro-
electric Power Plant, two -4,000 kW units
Tazimina River Regional Hydroelectric Power Plant,
two -8,000 kW units
Tazimina Run-of-River Local Hydroelectric Power
Plant, two -600 kW units
Chikuminuk Lake Regional Hydroelectic Power Plant,
two -8,000 kW units
Chikuminuk Lake (Nushagak Region) Hydroelectric
Power Plant, two -4,000 kW units
Kontrashibuna Lake Regional Hydroelectric Power
Plant, two -8,000 kW units
These twelve plants were used either individually or in combination to form
the hydroelectric scenarios for Bristol Bay (Section 6.2) . All
hydroelectric power plants were assumed to be on-line in 1988, with 5 1/2
year engineering, design, and construction periods (3 percent interest
during construction).
For each plant, the estimated operation and maintenance costs were based on
prior experience at similar sized hydroelectric plants. These costs are
summarized in Table 7.4-27.
An additional annual cost (also shown in Table 7.4-27) was included for the
hydroelectric plants in the form of a sinking fund for major periodic
equipment replacement. The sinking fund payment varied for each project.
It was assumed that the fund would be set up to provide 0.1 percent of the
plant construction cost (excluding transmission lines) at intervals of five
7-119
I
I ,
I
I
I
t
I
I
I ,
I
t
I
l ,
I
I
I
t
,
,;
years. The minimum amount to be available from the fund each five years
was $40,000 and the maximum amount was to be $80,000.
7.4.4.6 Fossil-Fuel Steam Electric Plants
Coal-fired steam electric plants were included in scenarios B-9A, B-10,
B-ll, and B-12. Scenarios B-ll and B-12 also included the Newhalen Local
Hydroelectric Plant to supply power to Iliamna, Newhalen, and Nondalton.
Appendix A includes a description of the coal plant concept plus
considerations regarding the use of other fossil fuels (oil or natural gas)
for Bristol Bay steam electric power plants.
For all four scenarios, a coal power plant capable of delivering a peak of
16 MW was used as the basis for the evaluations. The installed cost of
this plant was determined to be $57.798,000. The plant was assumed to be
on-line in 1987. The annual operating and maintenance costs for the plant
were comprised of two parts:
l.
2.
Personnel costs for 20 people at $52,000 per year for each, and
A charge dependent on the plant energy output at the rate of
$O.Ol/kWh produced.
The coal used in the plant performance analysis was assumed to contain
11,000 Btu/lb and 0.5 percent sulfur. The delivered coal cost was $75/ton
(FOB cost was obtained from Ref 5 and delivery charges were added). In
addition, the plant was designed with dry scrubbers in order to meet
federal air-quality regulations. The scrubbers used lime costing $375/ton
delivered (FOB cost was obtained from Ref 6 and delivery charges were
added). The overall plant heat rate was 14,400 Btu/kWh produced.
7.4.4.7 Combined Cycle Power Plant
A combined cycle power
scenarios B-9B and B-9C.
plant was evaluated for use in Bristol Bay in
Scenario B-9B used diesel fuel as the energy
source, while B-9C used a coal gasification plant (with the same coal
7-120
parameters and prices as described in the previous section). Descriptions
of these technologies are included in Appendices A and B.
For scenario B-9B, the 16 MW diesel-fuel fired combined cycle plant was
determined to have an installed cost of $25,800,000. It was assumed to be
on-line in 1987. The annual operating and maintenance costs were based on
the following:
1. A total of 16 personnel required at an average cost of $52,000
each per year, and
2. An output-dependent charge of $0.062/kWh produced.
The plant heat rate was assumed to decrease over time as the Bristol Bay
load grew and the plant capacity factor improved. The heat rate was
14,250 Btu/kWh when the plant began operation in 1987 and improved to a
rate of 10,300 Btu/kWh by 2002. The gallons of diesel fuel required each
year were calculated accordingly.
The coal gasification and combined cycle plant used in scenario B-9C had an
installed capital cost of $48,032,000. It was also assumed to be
operational in 1987. The total annual operation and maintenance cost was
determined to be the same as that of the coal-fired steam electric power
plant. In addition, the plant heat rate varied over time in the same
manner as that of the diesel-fuel fired combined cycle plant, establishing
the tons of coal consumed per year (at a cost of $75/ton as for the steam
electric plants). Scrubbers were not required and, thus, no lime cost was
incurred.
7.4.4.8 Electric Transmission Systems
In all scenarios other than BP-1 and B-19, the Bristol Bay region was
interconnected with electric transmission systems on the basis of either
local clusters of villages or a complete intertie of all villages. These
systems are described in Appendix A. In all cases, it was assumed that
power transmission resulted in a 10 percent loss.
7-121
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
t
• .. ,. ..
-• -
The capital costs for the transmission systems were determined based on
conceptual designs of the individual lines. Factors such as the
load-carrying requirements of the line and the local terrain influenced the
installed costs. The transmission system capital costs for those scenarios
involving power transmission are shown in Table 7.4-28. Also included in
the Table are the annual operating and maintenance costs for the systems.
The annual operation and maintenance was determined based on a rate of $250
per mile of transmisson line. The systems were assumed to be operational
in the same year as the central power source in each such scenario. For
B-1, B-15, B-16 and, B-17, the systems were assumed to be operational in
1986. Lastly, scenarios B-15, B-16, and B-17 had the costs of substation
expansion (required as the Bristol Bay load grew) spread out in five-year
increments as shown in Table 7.4-29.
7.4.4.9 Purchased Power
The use of purchased power for the Bristol Bay region was examined in
scenario B-1. It was not possible to obtain a firm commitment from the
utility in the Beluga area regarding either the availability or price of
surplus capacity for transmission to Bristol Bay. Thus, the following
assumptions were made for B-1:
1.
2.
3 .
Sufficient power was available for export from the Beluga area to
meet the needs of Bristol Bay over the entire economic analysis
period.
The cost of the purchased power, shown in Table 7.4-30, was taken
from the Battelle Railbelt Study, Plan lA, page 7.4 (Ref 7) .
10 percent extra power was purchased to allow for transmission
losses.
7.4.5 Results
The results of the economic analyses are summarized in Tables 7.4-32
through 7.4-39. These tables contain present worth costs for the Bristol
7-122
Bay regional and special local power
summary of the Bristol Bay regional
results tables.
scenarios. Table 7.4-31 contains a
power scenarios for use with the
Several variations of diesel generation scenarios BP-1, (denoted B-19A
through B-19D), B-1S, B-16, and B-17 were evaluated to determine if
combinations of alternate technologies with diesel generators resulted in
lower life-cycle costs. The present worth costs for the variations which
were considered are shown in Table 7.4-32. In all of these scenarios, the
use of diesel waste heat recovery equipment for space heating, wind
generators, a waste heat recovery and wind combination, and organic Rankine
cycle systems (evaluated with BP-1 only) were less costly on a life-cycle
basis than diesel generators alone.
Further details of the BP-1 variations are shown in Table 7.4-33 for each
individual village. Al though diesel waste heat recovery (B-19A) has a
lower present worth cost compared to the BP-1 scenario, it is not cost
effective in the villages of Clarks Point, Egegik, Ekuk, or Portage Creek.
This results from the relatively high installation cost for a waste heat
recovery system, the small size of these villages, and the mismatch of
waste heat availability with space heating requirements during certain
times of the year (Section 6 and Appendix A contain further details). Wind
generators show economic benefit in the villages of Naknek, Igiugig, and
Egegik when compared to diesel generators alone. However, a combination of
diesel waste heat recovery plus wind generation is cost effective in
Naknek, but not in Egegik or Igiugig (the combined capital costs outweigh
the benefits in these two villages). Lastly, the organic Rankine cycle
systems installed in Dillingham and Naknek were cost effective compared to
diesel generation alone, but they had higher life-cycle costs than diesel
generation with waste heat recovery in the two villages.
An evaluation was also made for wind and diesel waste heat recovery systems
in combination with a hydroelectric scenario. All hydroelectric scenarios
in this study used diesel generators in each individual village (as in
BP-1) to supply power from 1982 until the assumed hydroelectric plant
on-line date of 1988. Scenario B-14A was chosen as a test economic case
7-123
I
I
I
I
I
I
I
I
I
I
I
t
I
I
I
I
I
I
r ..
t
c
.. iI
C
for installing wind (in Egegik, Igiugig, and Naknek) or diesel waste heat
recovery systems (in all individual villages) during the 1982 through 1987
period.
Two variations were considered: 1) wind systems installed to supply 20
percent of the peak kW demand of Egegik, Igiugig, and Naknek until 1988 and
then operated for the remainder of their 15 -year economic lifetimes in
conjunction with the hydroelectric plant (the wind systems were installed
in the three villages in the same manner as scenario B-19B through 1988,
with no further wind installations after this date), and 2) diesel waste
heat recovery systems installed in all villages between 1982 and 1987,
operated until the hydroelectric plant was on-line in 1988, and then not
used further (since the diesel generators were converted to a back-up
status in 1988). A sensitivity analysis was performed for the diesel waste
heat recovery systems to determine the latest year between 1982 and 1988
that the system for scenario B-14A could be installed and still be
economically competitive with the base B-14A scenario.
The results of this B-14A sensitivity study are shown in Table 7.4-34. The
"B-14A + wind" case is about 2 percent greater in present worth cost than
B-14A alone, indicating that the hydroelectric/wind energy combination has
a s lightly higher life-cycle cost than hydroelectric without wind energy.
However, the "B-14A + Diesel Waste Heat Recovery" cases are competitive
with B-14A alone for waste heat systems installed by 1982, 1983, or 1984
since their present worth costs are lower. The waste heat system installed
by 1985 has a higher present worth cost than B-14A alone. This result
indicates that a waste heat recovery system, when installed by 1985 or
later and operated through 1987, does not have sufficient operating time to
recover the capital cost and O&M expenses through benefits for space
heating. Thus, although the present worth costs in Table 7.4-34 are very
close, it is concluded that the addition of wind systems to hydroelectric
scenarios would not lower the present worth costs, while the addition of
diesel waste heat recovery systems to hydroelectric scenarios by the year
1984 (and operated through 1987) would result in slightly lower life-cycle
costs.
7-124
Additional studies were performed to determine whether local hydroelectric
or diesel generation options were more economical for the Iliamna Region
and the Nushagak River villages. Table 7.4-35 displays present worth costs
for the four options considered for the Iliamna Region: BP-l, B-19A,
Newhalen Local Hydroelectric Plant, and Tazimina Local Hydroelectric
Plant. Tazimina Local has the lowest present worth cost, followed by B-19A
with a 21 percent higher cost. Thus, the Tazimina Local Hydroelectric
Plant is the preferred local option for the Iliamna Region.
Four options were also considered for the Nushagak River villages: central
diesel generation in Dillingham and New Stuyahok (with transmission
interties between all villages), BP-1, B-19A, and the Chikuminuk
Hydroelectric Plant. The present worth costs are shown in Table 7.4-36.
The most cost-effective option is B-19A, diesel generation with waste heat
recovery in each village. The Chikuminuk Hydroelectric Plant has a 24
percent higher present worth cost.
Based upon the studies performed with BP-1 variations and small, local
hydroelectric plants, the lowest cost local power supply option for Bristol
Bay (designated B-19E) was formulated. The local option for each village
is shown in Table 7.4-37. Under the B-19E scenario, four villages have
diesel generation alone, seven
recovery, one village (Naknek)
have
has
diesel
diesel
generation
generation
with waste
with waste
heat
heat
recovery and wind generation, and the Iliamna Region has the Tazimina Local
Hydroelectric Plant with diesel generation as back-up. The only
transmission required is between the Iliamna Region and the Tazimina Local
Hydroelectric Plant site. The B-19E present worth cost is $242,500,000,
which is only about 3 percent lower than scenarios B-19A or B-19C (see
Table 7.4-32). Thus, the slight differences in present worth cost between
scenarios B-19A, B-19C, and B-19E are well within the cost uncertainties
present in this feasibility assessment.
The final tabulation of present worth costs and a ranking of Bristol Bay
power supply scenarios are presented in Tables 7.4-38 and 7.4-39. A wide
variation in present worth costs results from the power supply options that
were considered. The rankings in Tables 7.4-38 and 7.4-39 indicate the
7-125
I
I
I
I
I
I
I
I
I
I
I
I ,
J
I
I
I
I
I
.... •
•
relative cost effectiveness of the scenarios, with the lowest present worth
cost ranked as number one.
Overall, the hydroelectric scenarios generally had lower present worth
costs than other power supply tachnology options. The ranking in Table
7.4-38 shows that the Newhalen Regional Hydroelectric Plant with power
diversion (scenario B-14A) was lowest in present worth cost. This scenario
was followed by Tazimina Regional Hydroelectric Plant (scenario A-I),
Newhalen Regional Hydroelectric Plant with power and river diversion
(scenario B-14B), Kontrashibuna Regional Hydroelectric Plant (scenario
B-18B), and the lowest cost BP-1 variation (scenario B-19E) . In
comparison, continuation of existing diesel generation in each village
(scenario BP-1) ranked as number 20 out of the 25 power supply scenarios
considered. Thus, numerous scenarios, including a coal-fired central power
plant concept, are less cost lyon a life-cycle basis than continuation of
diesel generation under the Base Plan scenario.
The regional power supply scenarios are ranked and compared by present
worth ratio in Table 7.4-39. The ratios were obtained by dividing the
present worth of each scenario into the BP-1 present worth of
$291,700,000. The ratios greater than 1.0 indicate the amount by which the
BP-1 present worth exceeds the present worth of each scenario, and the
ratios less than 1.0 indicate the savings in the BP-1 present worth
compared to those scenarios. Thus, BP-1 is 54% more costly than the lowest
life-cyc Ie cost scenario, B -14A, indicating a significant life-cycle cost
advantage for the Newhalen Regional Hydroelectric Plant with power
diversion. The first four scenarios in the ranking, B-14A, A-I, B-14B, and
B-18B, are within 20 percent of each other in present worth cost, which is
within the cost uncertainty range for this feasibility study. These four
scenarios form the preferred group of power supply options for Bristol Bay
based on life-cycle costs.
The second group of preferred options is comprised of variations on the
base plan scenario, BP-1. This group of three scenarios is within a range
of about 3% in present worth cost, indicating that they are essentially
equivalent on an economic basis. The three scenarios include B-19E (lowest
7-126
cost base plan plus small hydro combination), B-19C (diesel generation +
waste heat recovery + wind generation), and B-19A (diesel generation +
waste heat recovery). The addition of waste heat recovery to the Base Plan
diesel generation scenario results in a reduction in present worth cost of
about 15 percent. However, the further addition of wind generation or a
small hydroelectric plant has only a marginal improvement in present worth
cost.
Lastly, the accumulated present worths for five scenarios are plotted
versus time in Figure 7.4-1. The five scenarios include A-I, BP-l, B-14A,
B-19A, and B-19E. For the first few years, the accumulated present worth
costs are essentially equal since diesel generation is the primary power
source. After the hydroelectric plants are on-line in 1988, however, the
curves begin to diverge, with B-14A becoming the lowest cost scenario. The
accumulated present worth cost for scenario B-14A is equal to that of the
other scenarios in the following years:
A-I
BP-1
B-19A
B-19E
1988
1995
2001
2000
Thus, compared to the other scenarios, savings begin to accrue for the
Bristol Bay Region with scenario B-14A after the breakeven year in
accumulated present worth cost.
7.4.6 Economic Summary
A common economic basis was used to compare and evaluate the varied group
of power supply scenarios included in this study. A calculation of the
present worth of all costs and benefits associated with each scenario was
the basis for economic comparisons.
The economic parameters and assumptions used in calculating present worths
were in conformance with Power Authority guidelines, except for the
economic lifetimes of certain items of equipment. Summaries of the
7-127
• ..
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
... ..
;
C
t
C
t ,.
W
!JIll
f! ..
I
economic parameters and equipment lifetimes are shown in Tables 7.4-1 and
7.4-2, respectively. In the cases involving diesel generators,
transmission lines, coal gasification, and waste heat recovery equipment,
the economic lifetimes shown in Table 7.4-1 are greater than the values in
the Power Authority guidelines. These revised lifetimes were reviewed by
the Power Authority and were considered acceptable for use in the study.
The base year for the economic analyses was 1982, with a 21-year planning
period (i.e., Bristol Bay region electric demand projections for 1982
through 2002) and a 56-year analysis period. The analysis period length
resul ted from the assumed installation of hydroelectric plants in 1988
which, when combined with a 50-year hydroelectric lifetime, extended the
analysis period from the base year of 1982 through the year 2037. The
annual cash flows for the analysis period were developed as required by the
Power Authority economic guidelines.
Tables 7.4-38 and 7.4-39 contain a summary of present worth costs and
present worth ratios for the Bristol Bay regional power scenarios. A wide
variation in costs results from the several power supply scenarios that
were considered. Overall, hydroelectric scenarios generally had lower
present worth costs than other power supply technology options. The
Newhalen Regional Hydroelectric Plant with power diversion (B-14A) was
lowest, followed by Tazimina Regional (A-I), Newhalen Regional with power
and river diversion (B-14B), and Kontrashibuna Regional (B-18B). The
second group of most cost-effective options was comprised of variations of
the Base Plan (BP-1) scenario, including B-19E (BP-1 lowest cost
combination with Tazimina Local hydro), B-19C (BP-1 + waste heat recovery +
wind generation), and B-19A (BP-1 ± waste heat recovery). In comparison,
BP-1 ranks as number 20 out of the 25 scenarios considered.
Additional special studies were undertaken to: 1) investigate the economic
benefits of wind systems and waste heat recovery for diesel and
hydroelectric scenarios, 2) determine the most economic power supply option
for specific subregions of Bristol Bay, and 3) evaluate the viability of
organic Rankine cycle systems using diesel waste heat for Dillingham or
Naknek. The results of these studies are reported in Section 7.4.5.
7-128
References for Section 7.4
1.
2.
3.
4.
5.
6.
7.
Alaska Power Authority, "Economic Analysis for AI-aska Power Authority
Reconnaissance and Feasibility Studies • Standard Procedures and Sample
Cost Calculation· FY 1982", 1981.
Grant, Eugene L. and Ireson, W. Grant, "Principles of Engineering
Economy", Fifth Edition, The Ronald Press Co., New York, 1970.
Stermole, Franklin J., "Economic Evaluation and Investment
Methods", Second Edition, Investment Evaluations Corp.,
Colorado, 1974.
Decision
Golden,
Wind Systems Engineering, Inc., ItBristol Bay Regional Power Plan • Wind
Energy Analysis," Phase 1 Prelimary Report, Prepared for Stone &
Webster Engineering Corporation, 1982.
Personal Communication, Mr. Brian Acton, B.C. Coal, February 16, 1982.
Personal Communication, Mr. Dana Minot, Tacoma Lime Co., February 5,
1982.
Battelle Pacific Northwest Laboratories, "Railbel t Electric Power
Alternatives Study: Evaluation of Rai1belt Electric Energy Plans lt
,
Prepared for Office of the Governor, State of Alaska, February, 1982.
7-129
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
.. TABLE 7.4-1
i ..
SUMMARY OF ECONOMIC ANALYSIS PARAMETERS
• BASE YEAR: 1982
• PLANNING PERIOD: 21 years, 1982-2002
• ECONOMIC ANALYSIS PERIOD: 56 years, 1982-2037
• INFLATION RATE: 0 percent (all costs expressed in 1982 dollars)
• REAL DISCOUNT RATE: 3 percent
• REAL PETROLEUM FUEL ESCALATION RATE: 2.6 percent
• REAL INTEREST RATE: 3 percent
TABLE 7.4-2
ECONOMIC LIFETIMES FOR MAJOR EQUIPMENT
JIll. ,
Equipment Item Lifetime (Years)
Diesel Generators 30
Electric Transmission Lines 30
Waste Heat Recovery Equipment 15
Wind Generators 15
Organic Rankine Cycle Systems 25
Hydroelectric Plants so
Steam Turbines 30
Combined Cycle Plants 30
Coal Gasification Equipment 30
r ..
"""
TABLE 7.4-3
DISCOUNTED CASH FLOW ANALYSIS
SCENARIO B-14A
NEWI~LEN REGIONAL HYDROELECTRIC PROJECT-POWER DIVERSION
PROJECT: ALASKA POHER AUTHORITV--BRISTOL BAY STUDY
CASE: BI'IA--NEIIHALEH REGIOtIAL HVDRO--DIVERSIOU fOR POHER lltI.. Y
1982 1981 198'1 1985 1986 1987 1988
PEAK DEUAUO HH 7150. 7'131. 7531. 7722. 7912. 8103. 8360.
ANNUAL ENERGY USE HI~U 29'125. 30575. 31725. 32875. 3'1025. 15175. 36798.
DIESEL GEtlERATOR CAPITAl COSTS $XIOOO 7159. O. O. O. O. O. O.
HVDROELECTRIC CAPITAL COSTS $XIOOO O. O. O. O. O. O. 79637.
TRAUSIIISSIOH CAPITAL COSTS $XIOOO O. O. O. O. O. O. 70698.
AHORT. COST Of DIESEL GEtlERATOR $X1000 365. 365. 365. 365. 365. 365. 365.
AIIORT. COST Of HYDROELECTRIC $X1000 O. O. O. O. O. O. 3103.
AlIORT. COST Of TRAliStlISSIOH $XIOOO O. O. O. O. O. O. 3617.
AlIOIH. COST Of HYDROELECTRIC REPLACEUEHT $XIOOO O. O. O. O. O. O. 10.
DIESEL OVERHAUL COST $XIOOO 879. O. O. O. O. O. O.
DIESEL SWHING fUIiD $XIOOO U. 16. U. 16. U. U. 8.
DIESEL Or." COSTS $XIOOO 750. 750. 750. 750. 750. 750. 65.
IIYOROELECTRIC OUI COSTS $XIOOO O. O. O. O. O. O. 250.
TRAtiStiISSION OlH COSTS $XIOOO O. O. O. O. O. O. 106.
DIESEL COST PER GAlLON CEtITS 133. 136. 1'10. 1'14. 1'17. lSI. 155.
DIESEL fUEL USED GAlXIOOO 2ll68. 2565. 2660. 2757. 2852. 2950. O.
TOTAL DIESEL fUEL COST $XIOOO 3282. 3500. 3724. 3960. '1203. '1461. O.
TOTAL AllflUAl. COST $XIOOO 5293. lA631. '1855. 5091. 533,.. 5592. 752'1.
AIlI'lUAL COST PRESENT HORTII $XIOOO 5139. 4365. '1'1'13. '1523. 11601. '1683. 6118.
ACCUlIULATED. PRESEtfT HaRTH $XIOOO 5139. 950'1. 139'17. 18'170. 23071. 277511. 33872.
ELI
PAGE 1
1989 1990 1991
8617. 68711. 9131.
38lA2I. 'IOOll'1. 111667.
O. O. O.
O. O. O.
O. O. O.
365. 365. 365.
3103. 3103. 3103.
3617. 3617. 3617 •
10. 10. 10.
O. O. O.
8. 8. 8.
65. 65. 65.
250. 250. 250.
106. 106. 106.
159. 163. 166.
O. o. O.
O. o. O.
7524. 752'1. 7524.
5939. 5766. 5599.
39811. ,.5578. 51176.
r I I J II I I f 1 1'1 1 J I'~ ."1 r I ('1
(
TABLE 7;4-3 (cant)
DISCOUNTED CASH FI.OW ANALYSIS
SCENARIO B-14A
NEWHALEN REGIONAL HYDROELECTRIC PROJECT-POWER DIVERSION
PAGE 2
1992 1991 1994 1995 1996 1991 1998 1999 2000 2001
PEAK DEMAND tot n88. 9735. 10062. 10'129. 10776. 11123. 11621. 12119. 12616. 13116.
ANNUAL ENERGY USE HHH 43290. 453'1't. 47396. 491152. 51506. 53560. 56396. 59232. 62066. 6'19011.
DIESEL GENERATOR CAPIfAL COSTS 'XIOOO O. O. O. O. O. O. O. O. O. O.
HYDROELECTRIC CAPITAL COSTS 'XlOOO O. O. O. O. O. O. O. O. O. O.
TRAliSltISSION CAPITAL COSTS $XIOOO O. O. O. O. O. O. O. O. O. O.
AIIORT. COST OF DIESEL GENERATOR 'XIOOO 365. 365. 365. 365. 365. 365. 365. 365. 365. 365.
AIWRT. COST OF HYDROELECTRIC 'XIOOO 3103. 3103. 3103. 3103. 3103. 3103. 3103. 3103. 3103. 3103.
AlWRT. COST OF TRANSItISSIOti 'XIOOO 3617. 3617. 3617. 3617. 3617. 3617. 3617. 3617. 3617. 3617.
AIWAT. COST OF HYDROELECTRIC REPLACEHEtIT $XIOOO 10. 10. 10. 10. 10. 10. 10. 10. 10. 10.
DIESEL OVERHAUL COST 'XIOOO O. O. O. O. O. O. O. O. O. O.
DIESEL SIflI(ItIG fUtIl $XIOOO 6. 6. 6. 8. 8. 6. 6. 6. 6. 8.
DIESEL OtH COSTS $XIOOO 65. 65. 65. 65. 65. 65. 65. 65. 65. 65.
HYDROELECTRIC O&H COSTS txlOOO 250. 250. 250. 250. 250. 250. 250. 250. 250. 250.
TRAtlSUISSION 0&1t COSTS $X1000 106. 106. 106. 106. 106. 106. 106. 106. 106. 106.
DIESEL COST PER GALLON CENTS 172. 176. 181. 186. 191. 195. 201. 206. 211. 217.
DIESEL fUEL USED GALXIOOO O. O. O. O. O. O. O. O. O. O.
TOTAL DIESEL FUEL COST $XIOOO O. O. O. O. O. O. O. O. O. O.
TOTAL AtllIUAL COST $XIOOO 752't. 752'1, 75211. 752'1. 752". 752". 752". 752'1. 752'1. 752'1.
AUUUAL COST PRESEtfT HaRTH 'XIOOO 5'135. 5277. 5123. 1197't. 11629. '168«). '1552. '1'120. 11291. '1166.
ACCUtIULATED PRESENT HORTit 'XIOOO 56612. 61689. 670ll. 71987. 76816. 81505. 86057. 901176. 9'1767. 98933.
f J 11'1 r1" r~ 1 r~·l f~l
TABLE 7.4-3 (cont)
DISCOUNTED CASH FLOW ANALYSIS
SCENARIO B-14A
NEWHALEN REGIONAL HYDROELECTRIC PROJECT-POWER DIVERSION
2002 200J 2004 2005 2006 2001 2008
PEAK DEHAtIJ tot 13614. 136111. 136111 • 13614. 13614. 13614. 1361ft.
ANNUAl ENERGY USE HUH 611110. 611110. 61140. 61140. 611110. 61140. 611110.
DIESEL GENERATOR CAPITAl COSTS tXI000 O. O. O. O. o. O. O.
HYDROELECTRIC CAPITAl COSTS $XIOOO O. O. O. O. O. O. O.
TRANslIISsION CAPITAl COSTS $XIOOO O. O. O. O. O. O. O.
AlIORT. COST OF DIESEL GENERATOR tXI000 365. 365. 365. 365. 365. 365. 365.
AJIORT. COST OF HYDROELECTRIC tX1000 3103. 3103. 3103. 3103. 3103. 3103. 3103.
AtIORT. COST OF TRANSltIsSION $XIOOO 3611. 3611. 3611. 3611. 3611. 3611. 3611.
AIIORT. COST OF HYDROELECTRIC REPLACEHENT $XIOOO 10. 10. 10. 10. 10. 10. 10.
DIESEL OVERIiAll. COST $XIOOO O. O. o. O. O. O. O.
DIESEL SINKING FUI/O $XIOOO 8. 8. 8. 8. 8. 8. 8.
DIESEL OUt COSTS $XIOOO 65. 65. 65. 65. 65. 65. 65.
HYDROELECTRIC OUI COSTS $XIOOO 250. 250. 250. 250. 250. 250. 250.
TRANSttISsION O&H COSTS $XIOOO 106. 106. 106. 106. 106. 106. 106.
DIESEL COST PER GAlLON CEUTS 222. 222. 222. 222. 222. 222. 222.
DIESEL FUEL USED GAlXIOOO O. O. O. O. O. O. O.
TOTAL DIESEL FUEL COST $XIOOO O. O. O. O. O. O. O.
TOTAL AtiNUAL COST $XIOOO 15211. 15211. 1524. 15211. 15211. 1524. 1524.
ANNUAL COST PRESEUT HORTH $XIOOO 40 115. 3927. 3812., 3101. 35911. 3489. 3381.
ACCUIRLATED PRESENT HORTH $XIOOO 102911. 106904. 110116. 1141118. 118011. 121500. 124681.
PAGE 3
2009 2010 2011
136111. 13614. 136111.
61140. 611110. 61140.
O. O. O.
O. O. O.
O. O. O.
365. 365. 365.
3103. 3103. 3103.
3611. 3611. 3611.
10. 10. 10.
O. O. O.
8. 8. 8.
65. 65. 65.
250. 250. 250.
106. 106. 106.
222. 222. 222.
O. O. O.
O. O. O.
1524. 152ft. 152ft.
3289. 3193. 3100.
128116. 131369. 134468.
r 1 I I , J I 1 f 1 (1 (1 1>1 '" 1 '1 I 1 11 I I r 1
TABLE 7.4-3 (cont)
DISCOUNTED CASH FLOW ANALYSIS
SCENARIO B-14A
NEWHALEN REGIONAL HYDROELECTRIC PROJECT-POWER DIVERSION
£012 201] 2014 2015 2016 2011
PEAK DEHAJt) tot 13614. 1]614. 13614. 136141. 13614. 13614.
AllNUAL EHER6Y USE HliH 67740. 61140. 67740. 677410. 67740. 67740.
DIESEL 6EIIERATOR CAPITAL COSTS $XIOOO O. O. O. O. O. O.
HYDROELECTRIC CAPITAL COSTS $XIOOO O. O. O. O. O. O.
TRAHSIIISSlotl CAPITAl COSTS $XI000 O. O. ,0. O. O. O.
AHORT. COST OF DIESEL GEHERATOR $XIOOO 365. 365. 365. 365. 365. 365.
AUORT. COST OF HYDROELECTRIC $XIOOO 3103. lI03. 1I03. 3103. 3103. lI03.
AIIORT. COST OF TRAHSIIISSIOO $XIOOO 3611. 3617. 3611. 3611. 3611. 3617.
AIIORT. COST Of HYDROELECTRIC REPLACEtlEHT $XI000 10. 10. 10. 10. 10. 10.
DIESEL OVERHAUL COST $XlOOO O. O. O. O. O. O.
DIESEL SIIIHIUG FUUD $XIOOO 8. &. 8. 8. 8. 8.
DIESEL Ol" COSTS $XI000 65. 65. 65. 65. 65. 65.
HYDROELECTRIC Olt. COSTS $XIOOO 250. 250. 250. 250. 250. 250.
TRANSIIISSIOH 0&" COSTS $XIOOO 106. 106. 106. 106. 106. 106.
DIESEL COST PER GALLOO CEHTS 222. 222. 222. 222. 222. 222.
DIESEL FUEL USED GALXIOOO O. O. O. O. O. O.
TOTAL DIESEL FUEL COST $XI000 O. O. O. O. O. O.
TOTAL ANNUAL COST $XIOOO 7524. 7524. 7524. 7524. 7524. 7524.
AtlllUAL COST PRESENT HOATH $XIOOO 3010. 2922. 2837. 2154. 2674. 2596.
ACCUlIULATED PRESENT HORTH $XIOOO 13147&. 140400. 143237. 145991-148665. 151261.
201& 2019 2020
13614. 136141. 13614.
61140. 61140. 67740.
O. O. O.
O. O. O.
O. O. O.
365. 365. 365.
3103. lI03. 3103.
3617. 3611. 3617.
10. 10. 10.
O. O. O.
8. 8. &.
65. 65. 65.
250. 250. 250.
106. 106. 106.
222. 222. 222.
O. O. O.
O. O. O.
7524. 7524. 7524.
2520. 2447. 2376.
153181-156228. 158604.
PAGE 4
2021
13614.
67740.
O.
O.
O.
365.
3103.
3611.
10.
O.
8.
65.
250.
106.
222.
O.
O.
7524.
el01.
160910.
r 1 • 1 (I II fIll ,. f I "1 (1 r 1 I 1 r"' 11
TABLE 7.4-3 (cont)
DISCOUNTED CASH FLOW ANALYSIS
SCENARIO B-14A
NEWI~LEN REGIONAL HYDROELECTRIC P~OJECT-POWER DIVERSION
2022 2021 20211 2025 2026 2021 2028
PEAK DE/WiD HH 136l'l. 13614. 13614. 13614. 13614. 1361'1. 13614.
ANNUAL EI.ERGY USE • Ult 61740 • 61740. 61740. 617,.0. 61740. 61740. 61140.
DIESEL GEflERATOR CAPITAL COSTS $)(1000 O. O. O. O. o. o. O.
HYDROELECTRIC CAPITAL COSTS $XI000 O. O. O. O. O. O. O.
TRAtiStlISSION CAPITAL COSTS $)(1000 O. O. o. O. O. O. O.
A/WRT. COST OF DIESEL GENERATOR $XI000 365. 365. 365. 365. 365. 365. 365.
MWRT. COST OF HYDROELECTRIC $XI000 3103. 3103. 3103. 3103. n03. n03. n03.
A.WRT. COST OF TRAUSHISSION $X~OO 3617. 3617. 3617. 3617. 3617. 3617. 3617.
ANORT. COST OF UYDROElECTRIC REPlACEt-IEtfT $Xl 00 10. 10. 10. 10. 10. 10. 10.
DIESEL OVERHAUL COST $XI000 O. O. O. O. O. o. O.
DIESEL SItilUNG FutlO $XIOOO 8. 8. 8. 8. 8. 8. 8.
DIESEL 0&11 COSTS $)(1000 65. 65. 65. 65. 65. 65. 65.
HYDROELECTRIC O&H COSTS $)(1000 250. 250. 250. 250. 250. 250. 250.
TRArtSIIIS5IOH 0&11 COSTS $XI000 106. 106. 106. 106. 106. 106. 106.
DIESEL COST PER GALLotl CENTS 222. 222. 222. 222. 222. 222. 222.
DIESEL fUEL USED GALXI000 O. O. O. O. O. O. o.
TOTAL DIESEL FUEL COST $XI000 O. O. O. O. O. O. O.
TOTAL AtlllUAL COST $XI000 7524. 752,.. 752,.. 752,.. 7524. 7524. 7524.
AtUIUAl COST PRESENT HORTH $XI000 2239. 217,.. 2111. 2049. 1990. 1932. 1875.
ACCUtIUlATED PRESEUT tlORTH $XI000 163150. 165324. 167435. 169464. 171474. 173405. 175281.
PAGE 5
2029 2030 2031
13614. 13614. 13614.
61740. 61140. 611l lO.
O. O. O.
O. O. O.
o. o. O.
365. 365. 365.
n03. 3103. 3103.
3617. 3617. 3617.
10. 10. 10.
o. O. O.
8. 8. 8.
65. 65. 65.
250. 250. 250.
106. 106. 106.
222. 222. 222.
o. o. O.
O. O. O.
7524. 7524. 7524.
1821. 1768. 1716.
177102. 178669. 180566.
1"' (1 r , "I (1 f '1 f '1 I" f 1 f 1 ('1 r 1 rl I" I 1
TABLE 7.4-3 (cont)
DISCOUNTED CASH FLOW ANALYSIS
SCENARIO B-14A
NEWHALEN REGIONAL HYDROELECTRIC PROJECT-POWER DIVERSION
2032 2011 2014 2015 2016 2017
PEAK DEHAtIJ t<H 11614. 11614. 11614. 13614. 13614. 13614.
AIiUUAL EUERGY USE HtIH 61740. 67740. 67740. 67740. 67740. 67740.
DIESEL GEIiERATOR CAPITAL COSTS $XI000 O. O. O. o. o. O.
HYDROELECTRIC CAPITAL COSTS $XI000 O. O. O. O. O. O.
TRANSIIISSIOU CAPITAl COSTS 'XI000 O. O. O. o. O. O.
AIIORT. COST Of DIESEL GEIIERATOR 'XI000 365. 165. 365. 365. 165. 365.
AtIDRT. COST Of HYDROELECTRIC $XI000 1101. 1103. UOl. 3101. 1101. ]103.
AlIORT. COST Of TRAIiStIISSIOlf 'XI000 3617. 3617. 3617. 3617. 3617. 3617.
AlIORT. COST Of HYDROELECTRIC REPLACEUEIiT $XI000 10. 10. 10. 10. 10. 10.
DIESEL OVERHAUL COST $XI000 O. O. o. o. O. O.
DIESEL SIIiI<IIiG fUND $XI000 8. 8. 8. 8. 8. 8.
DIESEL 0111 COSTS $XI000 65. 65. 65. 65. 65. 65.
HYDROELECTRIC Ot" COSTS $XI000 250. 250. 250. 250. 250. 250.
TRAUSIIISSIOIi 0&" COSTS $)(1000 106. 106. 106. 106. 106. 106.
DIESEL COST PER GALLON CEIiTS 222. 222. 222. 222. 222. 222.
DIESEL fUEL USED GALXI000 O. O. O. O. O. O.
TOTAL DIESEL fUEL COST $XI000 O. O. O. O. O. O.
TOTAl AtlUUAL COST $XI000 7524. 7524. 7524. 7524. 7524. 7524.
AtllUAl COST PRESEIiT tlORTIf $XI000 1666. 1618. 1571. 1525. 1'161. 1437.
ACCUHlILATED PRESENT HORTII $XI000 182252. 183870. 18sq1l0. 186965. 18611116. 189883.
r 1 I I f 1
PAGE 6
,. ..
,. , ..
..
-
TABLE 7.4-4
DIESEL GENERATOR AND STORAGE TANK CAPITAL COSTS
1982 Dollars
Scenario Capital Cost ($1,000)
1982 1987 1992 1997
BP-1 7,159 3,345 6,348 7,014
B-15 7,140 3,848 5,787 5,439
B-16 3,972 4,074 4,550 4,200
B-17 4,263 3,600 2,453 5,461
TABLE 7.4-5
BP-1 DIESEL GENERATOR AND STORAGE TANK CAPITAL COSTS
1982 Dollars
Village Capital Cost ($1,000)
1982 1987 1992 1997
Clarks Point 405 60 158 195
Dillingham 1,718 1,747 2,783 3,405
Egegik 788 67 75 98
Ekuk 1,123
Ekwok 150 120 45 68
Igiugig 157 128 225 128
I liamna Region 308 307 651 621
Koliganek 3,115 67 68 83
Levelock 150 150 172 203
Manokotak 90 173 225 255
Naknek 1,628 390 1,657 1,748
New Stuyahok 282 98 244 165
Portage Creek 45 38 45 45
-
..
..
Note:
..
..
,..
..
-
TABLE 7.4-6.
DIESEL FUEL COST
1982 Dollars
Village Cost ($/Gal)
Clarks Point 1.52
Dillingham 1.25
Egegik 1. 38
Ekuk 1. 39
Ekwok 1. 71
Igiugig 1. 79
I liamna Region 1. 79
Koliganek 1.66
Levelock 1.71
Manokotak 1.59
Naknek 1.25
New Stuyahok 1.58
Portage Creek 1.46
Weighted Bristol Bay Average 1.33
Fuel costs based on village contacts by ISER and others in the Fall
of 1981.
TABLE 7.4-7
DIESEL GENERATOR FUEL RATES
Village Fuel Rate (Gal Diesel/kWh)
Clarks Point
Dillingham
Egegik
Ekuk
Ekwok
Igiugig
Iliamna Region
Koliganek
Levelock
Manokotak
Naknek
New Stuyahok
Portage Creek
0.10
0.08
0.10
0.10
0.125
0.125
0.08
0.125
0.125
0.125
0.08
0.08
0.125
TABLE 7.4-8
BP-1 DIESEL FUEL USAGE FOR SELECTED YEARS
Village Diesel Usage ~12000 Gall
1982 1987 1992 1997 2002
Clarks Point 62 70 78 88 103
Dillingham 700 924 1,268 1,681 2,249
Egegik 130 140 150 162 179
Ekuk 80 80 80 80 80
Ekwok 19 26 31 36 46
Igiugig 23 32 36 63 88
I liamna Region 114 155 209 286 387
Koliganek 31 39 49 58 73 -Levelock 24 31 43 59 84
Manokotak 54 70 90 116 153
Naknek 1,176 1,310 1,492 1,732 2)064 -New Stuyahok 44 58 74 97 130 ... Portage Creek 11 15 18 23 27
TABLE 7.4-9
DIESEL FUEL USAGE FOR SCENARIOS B-15, B-16, AND B-17
-Diesel Usage ~1!000 Gall
Year B-15 and B-16 B-17 -1982 2589 2589
1983 2689 2690
1984 2789 2791
1985 2889 2893
1986 2989 2994
1987 3089 3095 -1988 3233 3238
1989 3377 3381
1990 3522 3524
1991 3666 3667
1992 3810 3810
1993 3991 3991
1994 4171 4171 .. 1995 4352 4352
1996 4532 4532
1997 4713 4713
1998 4912 4963
1999 5112 5212
2000 5311 5462
2001 5511 5711
". 2002 5710 5961
,...
-
-
TABLE 7.4-10
WASTE HEAT RECOVERY EQUIPMENT CAPITAL COSTS
1982 Dollars
Scenario CaEita1 Cost (~lz0002
1982* 1987** 1992 1997 2002
B-19*** 2,085 57 357 2,204 57
B-15 770 183 90 970 183
. g-16 690 183 65 865 183
B-17 525 175 25 850 175
* Since this equipment has a 15-year life, the 1982 equipment is replaced
in 1997.
** The 1987 equipment is replaced in 2002.
*** Two BP-1 variations, B-19A and B-19C, used the capital costs shown.
TABLE 7.4-11
B-19A AND B-19C WASTE HEAT RECOVERY EQUIPMENT CAPITAL COSTS
1982 Dollars
Scenario CaEita1 Cost (~lz0002
1982* 1987** 1992 1997 2002
Clarks Point 148 8 156
Dillingham 275 25 175 325 25
Egegik 180 180
Ekuk 165 165
Ekwok 140 8 140 8
Igiugig 148 8 8 148 8
Iliamna Region 125 20 145
Koliganek 148 148
Levelock 148 8 8 156 8
Manokotak 148 8 8 156 8
Naknek 150 150 175
New Stuyahok 170 170
Portage Creek 140 140
* Since this equipment has a 15-year life, the 1982 equipment is replaced
in 1997.
** The 1987 equipment is replaced in 2002.
TABLE 7.4-12
B-19A DIESEL WASTE HEAT RECOVERY BENEFIT FOR SELECTED YEARS
Village Benefit (l z000 Gal Diesel Fuel2
1982 1987 1992 1997 2002
Clarks Point 3 3 4 4 5 ... Dillingham 157 208 285 378 505
Egegik 6 7 7 8 9
Ekuk 4 4 4 4 4
Ekwok 5 6 8 9 11
Igiugig 6 8 9 15 11
Iliamna Region 28 38 51 70 22
Koliganek 8 10 12 14 18
Levelock 6 8 10 14 21
Manokotak 13 17 22 29 38
Naknek 227 253 288 335 399
New Stuyahok 11 14 18 24 32
Portage Creek 3 4 4 6 6
TABLE 7.4-13 -DIESEL WASTE HEAT RECOVERY BENEFIT FOR SCENARIOS B-15, B-16, AND B-17
...
Benefit (l z000 Gal Diesel Fuel2
Year B-15 and B-16 B-17 -1982 506 506
1983 535 526
1984 546 546
1985 566 566 .. 1986 586 586
1987 607 606 -1988 636 634
1989 665 663
1990 694 691
1991 723 719
1992 753 748
1993 788 784
1994 825 820 -1995 861 855
1996 898 891
1997 934 927
1998 975 977
1999 1015 1026
2000 1055 1076
2001 1095 1125 -2002 1136 1175
...
III
III
..
-
-
TABLE 7.4-14
INSTALLED CAPITAL COSTS OF WIND TURBINES
1982 Dollars
Turbine Diameter, Capital Cost
Meters (Ft) ($1,000)
7 (23) 34
10 (32) 50
17 (56) 127
25 (82) 422
TABLE 7.4-15
B-19D ORGANIC RANKINE CYCLE BENEFIT
Year Benefit (12000
Dillingham
1985 75
1986 79
1987 83
1988 89
1989 95
1990 102
1991 108
1992 114
1993 121
1994 129
1995 136
1996 144
1997 151
1998 162
1999 172
2000 182
2001 192
2002 203
Annual O&M
($1,000)
1.7
2.5
6.4
21.1
Gal Diesel Fuel)
Naknek
113
116
118
121
125
128
131
134
139
143
147
152
156
162
168
174
180
186
--
-
-.. -
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
DESCRIPTION
TABLE 7.4-16
KUKAKLEK
(KVICHAK REGION) HYDROELECTRIC
POWER PLANT
(Two-3,500 kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminants
Interest During Construction
Total Estimated Cost
ESTIMATED
COST (1982 $ )
(Not Included)
1,390,000
31,929,000
2,700,000
925,000
403,000
2,250,000
55,000
550,000
19,324,000
2,225,000
$ 61,751,000
1,730,000
4,940,000
4,014,000
10,865,000
5,123,000
$ 88,423,000
III
..
III! -...
..
-
-
-
-
--
..
-
FERC
ACCT
330
331
332
333
334
335
336
352
353
354·9
71
DESCRIPTION
TABLE 7.4·17
KUKAKLEK
REGIONAL HYDROELECTRIC
POWER PLANT
(Two·8,000 kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines, and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminants
Interest During Construction
Total Estimated Cost
ESTIMATED
COST (1982 $ )
(Not Included)
3,947,000
119,771,000
6,800,000
1,150,000
696,000
300,000
100,000
625,000
48,843,000
2,225,000
$184,457,000
1,760,000
14,757,000
11,990,000
31,945,000
15,062,000
$259,971,000
.. ..
-
-
-
-... ..
..
-..
-...
..
..
-
-..
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
DESCRIPTION
TABLE 7.4-18
NEWHALEN RIVER
LOCAL HYDROELECTRIC
POWER PLANT
(Two-600 kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminants
Interest During Construction
Total Estimated Cost
ESTIMATED
COST (1982 $ )
(Not Included)
1,127,000
7,081,000
1,600,000
570,000
198,000
1,469,000
23,000
250,000
235,000
1,250,000
$ 13,803,000
1,250,000
2,070,000
1,656,000
2,817,000
997,000
$ 22,593,000
--
I11III
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
TABLE 7.4-19A
NEWHALEN RIVER REGIONAL HYDROELECTRIC POWER PLANT
NEWHALEN RIVER DIVERSION -POWER ONLY
(Two-8,000 kW Units)
DESCRIPTION
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminants
Interest During Construction
ESTIMATED
COST (1982 $ )
(Not Included)
5,645,000
35,484,000
8,570,000
1,150,000
576,000
387,000
100,000
625,000
51,375,000
1,800,000
$ 105,712,000
2,440,000
8,460,000
6,870,000
18,520,000
8,733,000
Total Estimated Cost $ 150,735,000
...
.... -...
-
...
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
TABLE 7.4-19B
NEWHALEN RIVER REGIONAL HYDROELECTRIC POWER PLANT
NEWHALEN RIVER DIVERSION -POWER AND RIVER DIVERSION
(Two-8,OOO kW Units)
DESCRIPTION
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminants
Interest During Construction
ESTIMATED
COST (1982 $ )
(Not Included)
5,645,000
63,082,000
8,570,000
1,150,000
576,000
387,000
100,000
625,000
51,375,000
1,800,000
$ 133,310,000
2,440,000
10,664,800
8,665,200
23,262,000
10,968,000
Total Estimated Cost $ 189,310,000
,t
c
... '
r ..
.-..
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
DESCRIPTION
TABLE 7.4-20
TAZIMINA RUN-OF-RIVER
REGIONAL HYDROELECTRIC
POWER PLANT
(Two-8,OOO kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminates
Interest During Construction
ESTIMATED
COST (1982 $ )
(Not Included)
2,893,000
14,000,000
7,080,000
1,150,000
463,000
3,048,000
100,000
625,000
53,539,000
2,000,000
$ 84,898,000
1,400,000
6,792,000
5,518,000
14,791,000
6,985,000
Total Estimated Cost $ 120,384,000
...
-
-
-
..
1M
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
DESCRIPTION
TABLE 7.4-21
TAZIMINA RIVER
(KVICHAK RIVER REGION) HYDROELECTRIC
POWER PLANT
(Two-4,000 kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminates
Interest During Construction
Total Estimated Cost
ESTIMATED
COST (1982 $ )
(Not Included)
2,000,000
23,500,000
4,200,000
925,000
415,000
2,675,000
55,000
550,000
32,417,000
1,000,000
$ 67,737,000
1,000,000
5,419,000
4,403,000
11,784,000
5,565,000
$ 95,908,000
• r· , ! ..
-
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
DESCRIPTION
TABLE 7.4-22
TAZIMINA RIVER
REGIONAL HYDROELECTRIC
POWER PLANT
(Two-8,000 kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminates
Interest During Construction
ESTIMATED
COST (1982 $ )
(Not Included)
2,893,000
54,578,000
7,080,000
990,000
463,000
3,631,000
100,000
625,000
53,539,000
2,325,000
$ 126,224,000
2,000,000
10,098,000
8,205,000
21,979,000
10,363,000
Total Estimated Cost $ 178,869,000
-..
iii
,.
I
c
-
,. ..
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
DESCRIPTION
TABLE 7.4-23
TAZIMINA RUN-OF-RIVER
LOCAL HYDROELECTRIC
POWER PLANT
(TWo-600 kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminates
Interest During Construction
Total Estimated Cost
ESTIMATED
COST (1982 $ )
(Not Included)
816,000
1,795,000
1,240,000
570,000
265,000
2,675,000
23,000
250,000
463,000
1,250,000
$ 9,347,000
1,270,000
1,402,000
1,122,000
1,971,000
611,000
$ 15, 723 , 000
-
fill ..
c
-
-..
III!
iii
!II'
f •
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
DESCRIPTION
TABLE 7.4-24
CHIKUMINUK LAKE
REGIONAL HYDROELECTRIC
POWER PLANT
(Two-8,000 kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminates
Interest During Construction
ESTIMATED
COST (1982 $ )
(Not Included)
4,579,000
53,932,000
8,570,000
1,150,000
576,000
7,168,000
100,000
625,000
63,077 ,000
1,500,000
$ 141,277 ,000
1,910,000
11 ,302,000
9,183,000
36,255,000
12,296,000
Total Estimated Cost $ 212,223,000
,. ..
-
..
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
DESCRIPTION
TABLE 7.4-25
CHIKUMINUK LAKE
(NUSHAGAK REGION) HYDROELECTRIC
POWER PLANT
(Two-4,000 kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
Camp, Mobilization and Demobilization
Subtotal Direct Cost
Studies
Engineering
Construction Management
Allowance for Indeterminates
Interest During Construction
ESTIMATED
COST (1982 $ )
(Not Included)
2,793,000
39,844,000
5,250,000
925,000
415,000
7,178,000
55,000
550,000
37,329,000
2,700,000
$ 97,039,000
1,860,000
7,763,000
6,308,000
16,946,000
7,990,000
Total Estimated Cost $ 137,906,000
.. ..
..
..
,... ..
, ..
-
FERC
ACCT
330
331
332
333
334
335
336
352
353
354-9
71
DESCRIPTION
TABLE 7.4-26
KONTRASHIBUNA LAKE
REGIONAL HYDROELECTRIC
POWER PLANT
(Two-8,OOO kW Units)
Land and Land Rights
Power Plant, Structures and Improvements
Reservoirs, Dams, and Waterways
Waterwheels, Turbines and Generators
Accessory Electrical Equipment
Misc. Power Plant Equipment
Roads and Railroads
Substation and Switching Station,
Structures and Improvements
Substation and Switching Station Equipment
Transmission Plant
ESTIMATED
COST (1982 $ )
(Not Included)
2,729,000
62,399,000
6,000,000
1,150,000
478,000
800,000
100,000
625,000
58,593,000
Camp, Mobilization, and Demobilization 2,300,000
Subtotal Direct Cost $135,174,000
Studies
Engineering
Construction Management
Allowance for Indeterminants
Interest During Construction
Total Estimated Cost
2,000,000
10,814,000
8,786,000
23,516,000
11 ,088 ,000
$191,378,000
•
...
-
-.. -... -
-..
..
,.. --
TABLE 7.4-27
HYDROELECTRIC PLANT ANNUAL SINKING FUND AND
OPERATION AND MAINTENANCE COSTS
1982 Dollars
Hydroelectric Plant Annual O&M ($1,000) Sinking Fund
Kukaklek (Kvichak) 120 8
Two-3,500 kW units
Kukaklek Regional 220 15
Two-8,000 kW units
Newhalen River Local 100 8
TWo-600 kW units
Newhalen River Regional
Two-8,000 kW units
Power Diversion 250 10
Power + River Diversion 250 10
Tazimina Run-of-River 200 8
Two-8,000 kW units
Tazimina River (Kvichak) 106 8
Two-4,000 kW units
Tazimina River Regional 220 14
Two-8,000 kW units
Tazimina River Local 100 8
Two-600 kW units
Chikuminuk Lake Regional 250 15
Two-8,OOO kW units
Chikuminuk Lake (Nushagak) 120 11
Two-4,000 kW units
Kontrashibuna Lake Regional 250 14
Two-8,000 kW units
($1,000)
.. ..
p-
ili
-
-
TABLE 7.4-28
ELECTRIC TRANSMISSION SYSTEM INSTALLED CAPITAL COSTS
Scenario
A-1
B-1
B-2
B-3
B-5
B-8
B-9 and B-lO
B-ll and B-12
B-13
B-14
B-15
B-16
B-17
B-18
1982 Dollars
Capital Costs*
($1,000)
68,740
112,498
62,971
73,428
74,818
92,065
39,475
46,059
81,432
66,280
34,249
41,031
64,540
75,412
Annual O&M
($1,000)
108
146
94
98
100
117
97
76
109
106
62
66
104
115
* Includes substations, but not interest during construction of the systems.
* These
TABLE 7.4-29
ELECTRIC SUBSTATION EXPANSION CAPITAL COSTS
FOR SCENARIOS B-15, B-16, and B-17*
1982 Dollars
Scenario Ca:eital Cost (~120002
1987 1992 1997
B-15 65 65 65
B-16 130 130 130
B-17 130 130 130
costs are in addition to those in Table 7.4-28.
!"II
J
1M
'" " ... .. .. ..
La "
t
[
'" t. -..
.... ,
I..
.... Source:
til
,...
1111
....
III
.... ...
....
lit
till ... -.. -ii.
JIIIII ..
-...
TABLE 7.4-30
SCENARIO B-1 PURCHASED POWER COST
Year Power Cost, ¢/kWh
1986 3.22
1987 3.22
1988 4.70
1989 4.40
1990 4.15
1991 4.70
1992 5.30
1993 5.35
1994 5.40
1995 6.05
1996 6.40
1997 6.68
1998 6.80
1999 7.00
2000 7.10
2001 7.15
2002 7.30
Battelle Pacific Northwest Laboratories, "Railbelt Electric Power
Alternatives Study: Evaluation of Railbelt Electric Energy
Plans", Plan 1A
.. a.
D -;l
IfI
lilt .. ,. ..
C "
filii
f ...
"'" ...
,.. ... ..
! ..
...
! ... ..
III .. ..
,.. ...
.... ...
,..
III
,..
'-,..
~ ...
... ...
Scenario
BP-1
A-1
B-1
B-2
B-3
B-5
B-8
B-9A
B-9B
B-9C
B-ll
B-13A
B-13B
B-14A
B-14B
B-15
B-16
B-17
B-18A
B-18B
B-19A
B-19B
B-l9C
B-19D
B-19E
TABLE 7.4-31
SUMMARY OF BRISTOL BAY REGIONAL POWER SCENARIOS
Description
Diesel generation in each village
Tazimina Regional Hydro
Power purchased from the Beluga area
Kukaklek Regional + Newhalen Local Hydro
Kukaklek + Chikuminuk + Newhalen Local Hydro
Kukaklek + Chikuminuk + Tazimina Local Hydro
Chikuminuk Local + Tazimina Hydro
Coal-fired steam power plant
Diesel-powered combined cycle plant
Coal gasification/combined cycle plant
Coal-fired steam power plant + Newhalen Local Hydro
Chikuminuk Regional + Tazimina Local Hydro
Chikuminuk Regional + Newhalen Local Hydro
Newhalen Regional Hydro -power diversion
Newhalen Regional Hydro -power + river diversion
Four independent diesel generation load centers
Four diesel generation load centers in three
independent groups
Two diesel generation load centers, interconnected
Kontrashibuna Regional + Tazimina Run-of-River Hydro
Kontrashibuna Regional Hydro
BP-1 + waste heat recovery in all villages
BP-l + wind generation in certain villages
BP-l + waste heat recovery + wind generation
BP-1 + organic Rankine cycle in certain villages
BP-1 lowest cost combination + Tazimina Local Hydro
TA8LE 7.4-32
SUMMARY OF PRESENT WORTH COSTS FOR
SCENARIOS 8P-1, 8-15, 8-16, 8-17, and 8-19
(All Values in 1982 Dollars)
8P-1
8-19A -8P-1 + Waste Heat Recovery
8-198 -8P-1 + Wind Generation
8-19C -8P-1 + Waste Heat + Wind
8-19D -8P-1 + Organic Rankine Cycle
8-15
8-15 -With Waste Heat Recovery
8-15 -With Wind Generation
8-15 -With Waste Heat and Wind
8-16
8-16 -With Waste Heat Recovery
8-16 -With Wind Generation
8-16 -With Waste Heat and Wind
8-17
8-17 -With Waste Heat Recovery
8-17 -With Wind Generation
8-17 -With Waste Heat and Wind
Scenario Present Worth ($1,000)
291,700
249,500
287,900
249,200
283,900
340,400
303,200
335,600
301,100
338,900
299,000
334,900
295,800
367,900
326,600
359,000
323,500
.. ..
-
-
, ... -...
TABLE 7.4-33
BP-1 VARIATIONS BY VILLAGE*
SUMMARY OF PRESENT WORTII COSTS
(All Values Expressed in Thousands of 1982 Dollars)
BP-l B-19A B-19B B-19C ------
Clarks Point 6,600 6,700
Dillingham 104,700 86,400
Egegik 10,400 10,500 10,400 10,500
Ekuk 4,800 6,300
Ekwok 3,300 3,000
Igiugig 5,600 4,900 5,400 6,000 .
I liamna Region 26,900 22,100
Koliganek 4,800 4,300
Levelock 5,300 4,700
Manokotak 8,700 7,200
Naknek 101,400 85,200 97,800 83,800
New Stuyahok 7,500 6,400
Portage Creek 1,700 1,800
*BP-1 = Diesel Generation
B-19A = BP-1 + Waste Heat Recovery
B-19B = BP-1 + Wind Generation
B-19C = BP-1 + Waste Heat Recovery + Wind Generation
B-19D = BP-1 + Organic Rankine Cycle
B-19D
100,800
97,500
...
-
--
,... ..
...
TABLE 7.4-34
PRESENT WORTH COSTS
WIND AND WASTE HEAT RECOVERY VARIATIONS FOR SCENARIO B-14A
NEWHALEN REGIONAL HYDROELECTRIC PLANT -POWER DIVERSION
(All Values in 1982 Dollars)
Scenario
B-14A
B-14A + Wind
B-14A + Diesel Waste Heat Recovery*
Recovery equip installed by 1982
Recovery equip installed by 1983
Recovery equip installed by 1984
Recovery equip installed by 1985
Present Worth ($1,000)
189,900
193,200
188,500
189,100
189,600
190,100
*In all cases, the waste heat recovery equipment was not used after the
hydroelectric on-line date of January 1, 1988.
TABLE 7.4-35
PRESENT WORTH COSTS FOR ILIAMNA/NEWHALEN/NONDALTON
HYDROELECTRIC VERSUS SCENARIO BP-l
(All Values in 1982 Dollars)
Scenario
BP-l -Diesel Generation
B-19A -BP-l + Waste Heat Recovery
Newhalen Local Hydroelectric
Tazimina Local Hydroelectric
Present Worth ($1,000)
26,900
22,100
23,900
18,300
i .. -
-
-
-
-
TABLE 7.4-36
PRESENT WORTH OOSTS FOR NUSHAGAK RIVER REGION.
HYDROELECTRIC VERSUS DIESEL GENERATION
(All Values in 1982 Dollars)
Scenario Present Worth ($1,000)
Central Diesel Generation in
Dillingham and New Stuyahok
BP-1 Diesel Generation in Each Village
B-19A -BP-1 + Waste Heat Recovery
Chikuminuk Hydroelectric
160,000
142,100
122, 100
150,800
• Includes the following villages: Clarks Point, Dillingham, Ekuk,
Ekwok, Koliganek, Manokotak, New Stuyahok, and Portage Creek.
TABLE 7. ~-37
VILLAGE POWER SUPPLY OPTIONS FOR BP-19E SCENARIO
Village
Clarks Point
Dillingham
Egegik
Ekuk
Ekwok
Igiugig
Iliamna Region
Koliganek
Levelock
Manokotak
Naknek
New Stuyahok
Portage Creek
Total
.BP-' = diesel generation
Power Supply·
Option
BP-1
B-19A
BP-1
BP-1
B-19A
B-19A
Tazimina Local Hydro
B-19A
B-19A
B-19A
B-19C
B-19A
BP-1
B-19A = BP-1 with waste heat recovery
B-19C = BP-1 with waste heat recovery and wind generation
Present Worth,
$1 ,000
6,600
86,400
10,400
4,800
3,000
4,900
18,300
4,300
4,700
7,200
83,800
6,400
1,700
242,500
TABLE 7.4-38
SUMMARY OF PRESENT WORTH COSTS
All Values in 1982 Dollars
Scenario* Present Worth ($1,000) Ranking
BP-1 291,700 20
A-1 213,700 2
B-1 279,600 15
B-2 301,000 21
B-3 276,300 14
B-5 270,700 13
B-8 266,000 9
B-9A 281,000 16
B-9B 388,500 25
B-9C 269,300 11
B-11 281,300 17
B-13A 261,500 8
B-13B 267,100 10
B-14A 189,900 1
B-14B 222,200 3
B-15 340,400 23 -B-16 338,900 22
B-17 367,900 24
B-18A 270,200 12
B-18B 226,800 4
B-19A 249,500 7 -
B-19B 287,900 19
B-19C 249,200 6 .... B-19D 283,900 18
B-l9E 242,500 5
* -See Table 7.4-31 or Section 6.2
-
-..
-
-
-
-
-
-
-
Scenario·
B-14A
A-I
B-14B
B-18B
B-19E
B-19C
B-19A
B-13A
B-8
B-13B
B-9C
B-18A
B-5
B-3
B-1
B-9A
B-ll
B-19D
B-19B
BP-l
B-2
B-16
B-15
B-17
B-9B
TABLE 7.4-39
PRESENT WORTH RATIOS
REGIONAL POWER SCENARIOS
Ranking
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
* See Table 7.4-31 or Section 6.2.
** Present Worth Ratio = Present Worth BP-l
Scenario Present Worth
= $291,700,000
Scenario Present Worth
Present Worth Ratio··
1.54
1.36
1.31
1.29
1.20
1.17
1.17
1.12
1.10
1.09
1.08
1.08
1.08
1.06
1.04
1.04
1.04
1.03
1.01
1.00
0.97
0.86
0.86
0.79
0.75
II -G)
C
:0 m
~ • ~
I
~
PRESENT WORTH COST, $1,000,000
oM
o o
I\) o o 19820~;q~~~~~~~IIr!-rTi-r;-Ii-rTi-r~rT-rT1
(.,) o o
1985~1~~~----------~--------------~----------~--,
» o o c s::
C r-»
--I m
C1
1990 1 \:.\'=
19951 '" ",,~
2000 1 HI..:fIi"~<---------t---------t
'"C 20051 ______ -L~:.~
lJ-< -~~ I .~~~'<~~---~---
m:U ' Z 2010 ---
... ... ... ...
--I
~ o
lJ
--I
~ ~~~.~~--
o 2020 : \' •• \ --o : \
(J) • -\ -I ': \ --j \
(J) 2025 .. 4
... ... ... ... " \ I . \ :.. ." ----'\-... -'
... ... ... ... ...
2030 I as \ o,~ ~
\ ,. \ \ -'"
-'" \ -'" .; \
.$10 -'" cD cD .; ,. tn" ... .
2035 :
2037
A0782068
...,
...i .,
..I .. ..
II ~
'II ..
~ ...
.., ... ., ..
..., ...
..,
I11III
J
]
l
~
" IIIIIi .,
.J ., ..
" wi
j
lflii ..
.,.
i ..
,...
L
..
i
ill.
....
L
8. REGULATOR Y COORDINATION
AND PUBLIC PARTICIPATION
..
8. REGULATORY COORDINATION AND PUBLIC PARTICIPATION
8.1 REGULATORY COORDINATION
8.1.1 Agency Involvement
A major objective of the study effort has been to ensure an adequate and
timely involvement of the people of the region and the federal, state, and
local agencies interested in the study. Since the study was initiated,
when a number of agencies were sent copies of the Work Plan, progress
information has continually been supplied to interested agencies and
governmental organizations.
Agency information meetings have been held at various intervals throughout
the first phase of the study. The purpose of these meetings has been to
provide information to those agencies who have direct involvement in the
Bristol Bay area. Some agencies that have had a special_interest from the
beginning include the U. S. Fish and Wildlife Service, the National Park
Service, the Alaska Department of Fish and Game, the Alaska Department of
Natural Resources (Division of Lands and Division of Parks), and the
Bristol Bay Cooperative Management Plan Land Use Council. These
organizations, as well as many others, have been invited on a regular basis
to participate in agency meetings for the purpose of expressing their
concerns and ideas with the members of the study team .
Items discussed at agency meetings have included the methodology used to
screen various schemes and sites proposed for regional energy production,
the development of alternative concepts for various sites, the screening of
potential hydroelectric sites, environmental concerns of various energy
development schemes, and land status and ownership regarding the
development of power projects and transmission corridors.
On several occasions during the first phase of the study, large packets of
information were distributed to a number of agencies at various
levels of government. These packets contained information on potential
selected hydroelectric sites, various development concepts, and
8-1
transmission line concepts and recommended corridors. Agencies were asked
to review and comment on these concepts, methodologies" and screening
procedures. Several agencies did respond in considerable detail. Their
comments and ideas have been incorporated, as applicable, into the 21
energy development scenarios presented in this Interim Assessment Report.
In addition to the special information packets, agencies also have received
Project Reports on a regular basis; these reports highlight activities
which have taken place during the preceeding period and include an estimate
of work to be completed in the following month.
Finally, agencies were provided with the draft Interim Feasibility
Assessment Report issued in March 1982. A number of agencies commented on
the report. These comments and Power Authority responses are found at the
end of this chapter.
8.1.2 Regulatory Requirements
A second major objective of the study effort has been to identify various
regulatory requirements as they may pertain to the development of various
energy development plans. An effort was made to collect and compile all
statutes, rules, regulations, and other requirements directly or indirectly
affecting the process of investigating, and subsequently constructing, the
selected energy development plan. Federal statutes having an impact upon
the study effort in Phase I included the Alaska Native Claims Settlement
Act, the Coastal Zone Management Act, the Anadromous Fish Act, the Wild and
Scenic Rivers Act, the Alaska National Interest Lands Conservation Act, the
Fuel Use Act, and the Clean Air Act.
Most agency concern has been over hydroelectric power as an energy source
and the location of potential sites for development. The Alaska Native
Claims Settlement Act (ANCSA) of 1971 and the Alaska National Interest
Lands Conservation Act (ANILCA) of 1980, with their subsequent land
classifications, have been critical to the development of energy plans. A
great deal of effort has been expended identifying land ownership and land
status in the Bristol Bay region as a result of ANCSA's provisions for land
selection and withdrawal. In addition, as a result of the passage of the
8-2
J
t
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
I
I
I
t
t
t
t
ANILCA, conservation units in the region such as Lake Clark National Park
and Preserve, Mt. Katmai National Park and Preserve, Becharof National
Wildlife Refuge, and Togiak National Wildlife Refuge have extended their
boundaries. Many of the potential hydroelectric sites which have been
previously considered are now located within these conservation units.
Also, within each unit are various designations of lands: park, preserve,
wilderness, and wildlife refuge. Guidelines for uses and restrictions
within each designation class have been collected and compiled.
Primary state interest in the development of the regional power plan has
been in the area of fisheries, especially the commercial salmon fishery,
which is vital to the Bristol Bay economy. The fishery interest has been
most directly related to hydroelectric power generation and potential
development sites. Another area of state interest has been directed toward
the Wood-Tikchik State Park and potential development which may take place,
particularly hydroelectric development.
As a result of the passage of ANILCA, an Alaska Land Use Council was
established to conduct studies and advise federal, state, and local
government and native corporations with respect to land and resource uses
in Alaska. As a part of ANILCA, a Cooperative Management Plan was set up
for the Bristol Bay region. The purpose of this plan is set forth in
Section 1203 of the Act. It is the intent of this study effort to work
closely with the Land Use Council in their preparation and implementation
of a comprehensive and systematic cooperative management plan for the
Bristol Bay region.
8.2 PUBLIC PARTICIPATION
8.2.1 General
The basic objectives of a public participation program are twofold: to
keep the public fully informed, and to provide a means whereby the public
can influence the work effort. These objectives have been generally
satisfied during the first phase of the study by conducting a public
information program which has included media exposure, scheduled events,
8-3
public comment opportunities, and dynamic planning provisions. To date, it
has been the intent of the study to not only supply the public with
information regarding the study, but also to provide a means of involving
the public and having them influence the course of work. For an effort
such as the Bristol Bay Regional Power Plan, with impacts extending
effectively into perpetuity, public participation is an imperative.
8.2.2 Interests
While the motivations and objectives of individuals and organizations who
have been involved to date on the Bristol Bay Regional Power Plan are
generally sincere and relatively easily understood, when considered
collectively. they represent clear conflicts. It follows that it will be
virtually impossible to satisfy every desire. Problems arise when
interests in accelerated development of energy resources meet up with
interests to preserve the quality of life in Alaska. Special interests
identified during Phase I of the study effort have included the following:
• Utility interests, including concerns about ability to meet energy
demands, prospects for the recovery of capital expenditures. and others
• Native groups, particularly those whose subsistence lifestyle may be
affected by the development of a power project
• Recent immigrants to the region who wish to preserve the existing
lifestyle
• Fisheries industries and agencies, who are concerned about the impacts
on future catch. particularly of anadromous fish
• Consumers of electric power in the Bristol Bay region
• Marketers of alternative energy resources
• Agencies charged with the maintenance and preservation of Alaskan
wildlife, including the U.S. Fish and Wildlife Service, National Park
8-4
I
I
I .,
I
I
I
I
I
I
1
I
I'
I
I
I
I
I
I
I
I
a
t
;
Service, Alaska Department of Fish and Game, and Alaska Department of
Natural Resources
Many of these interests were expressed during the public meetings discussed
in Section 8.2.3.1, below.
8.2.3 Communications
Factors which combine to create unusual pressures on effective
communications include the large area over which power would be
distributed, the relatively non-existent transportation system, and
remoteness of the area affected by the Bristol Bay Regional Power Plan.
Therefore, the public participation program implemented has afforded
reasonable involvement opportunities, even for those who have no practical
means to attend meetings or make regular visits to the Alaska Power
Authority's office in Anchorage.
8.2.3.1 Public Meetings
Scheduled public meetings were part of the public participation program
during Phase I, and were held in both urban and rural areas of the Bristol
Bay region. The first series of meetings occurred in September and October
of 1981 as the study was just getting underway. The second series of
meetings was held in early March 1982 to report on interim results. Table
8.2-2 lists the villages and dates of public meetings.
These "community" meetings became an important means by which the study
team and the Power Authority could express the overall study methodology as
well as present conceptual schemes for power development. An important
element in each of the public/community meetings was the invitation of
questions or comments regarding the study plan. As previously described,
all comments. oral and written, have been compiled with the detail backup
information contained in the study files. Table 8.2-1 presents a
compilation of interest categories expressed as comments and questions
resulting from the first series of meetings. Participants represented a
broad cross-section of interest groups which included governmental
8-5
agencies, utilities, industry, native organizations, commercial businesses,
and private individuals.
The comments have been considered and incorporated when possible into the
power plan study.
The Spring 1982 public meetings offered the first opportunity to provide
detailed information on the various power generation options which were
being considered for the region. The spring meetings were more regional in
nature, the first occurring at Dillingham during the Beaver Roundup when
people from many smaller villages were gathered for festivities. Other
meetings followed in Iliamna, Igiugig, Levelock, New Stuyahok, Naknek, and
South Naknek.
Public reaction during the spring meetings varied considerably from village
to village. Clearly the most important and repeated concern related to
fears regarding the effect of hydroelectric projects on the fisheries.
Agency fisheries experts emphaSized the need for extensive study to
determine whether the least cost Newhalen and Tazimina concepts would be
environmentally acceptable.
Another important underlying concern, although not always clearly stated,
related to the possibility of undesirable change due to more abundant and
less costly energy. Some see this as an inducement to in-migration and a
threat to existing life styles. In Naknek, where electricity tends to be
more reliable and less costly than in more remote villages, one meeting
attendee stated that he would be willing to pay much more for power if it
would keep conditions the way they are now. However, in South Naknek
strong sentiments were expressed in favor of a regional plan.
The public meeting in Iliamna was particularly interesting. This area has
some of the higher electrical costs in the region and a central diesel
generating system is being built in Newhalen with plans for an intertie to
Nondalton. Also, the lake villages would experience more effects, either
positive or negative, from construction of a hydroelectric project on the
Tazimina or Newhalen rivers. When the question of alternatives was put to
8-6
I
a
I
I
I
I
I
I
t
1
I
I
I'
I
I
I
I
I
I
I
a vote at the request of an attendee, the development of a regional plan
was the overwhelming choice, as opposed to continuing local development of
diesel. Of the least cost alternatives, Newhalen was favored, but Tazimina
had considerable support.
The Kvichak River villages of Igiugig and Levelock had previously indicated
strong opposition to development of Kukaklek Lake as a hydroelectric
source. These villages seemed quite relieved to learn that the Kukaklek
concept was no longer a serious contender. However, these villages
appeared undecided about becoming involved in a regional supply system
using another source, preferring to take a "wait and see" attitude. New
Stayahok also did not seem enthusiastic about a regional plan, probably due
to concerns about fisheries and transmission line effects. The smaller
villages seemed interested in subregional plans requiring fewer
transmission line connections with the rest of the region.
Although the spring meetings provided considerable public comment on the
power plan alternatives suggested as most attractive technically, it was
not possible to determine if the response was representative. It is
believed that a more comprehensive public information and response program
is required to properly evaluate the diverse attitudes of the region with
respect to its general interest in development of a regional power system,
and more specifically identify preferences between the lower cost scenarios.
Numerous other meetings were held during the Phase I effort which were not
formal in nature, but did provide both information about the project and an
opportunity for comment and input. Such meetings involved various native
organizations, utilities, commercial businesses, and private citizens in
the region.
8.2.3.2 Project Reports
An integral part of the study effort has been the issuance of project
reports. These reports have been designed to present to the reader
information on work that has been accomplished in the study during the
preceeding period, as well as a projection of work to be completed for the
8-7
following month. Included in the reports are important meetings and
conferences, as well as a Project Milestone Schedule. The reports have
been given wide distribution, e.g., federal, state, and local agencies,
native organizations, utilities, etc., for the purpose of receiving
comments as to the content and overall direction of the study.
8.2.3.3 Media Exposure
The most effective means of announcing important information and events is
through radio and newspapers. Throughout the first phase of the study,
numerous press releases were made using both local radio and local
newspapers. These were designed to announce scheduled meetings, study
methodologies, and the availability of study information.
8.2.4 Records of Comments and Responses
Records of all study inquiries, whether as a question presented at a public
meeting or as a letter received from an agency, have been kept on file.
A number of formal comments, mostly from Federal and State agencies, were
received on the draft Interim Feasibility Assessment issued in March 1982.
Copies of these letters and Power Authority responses.
8-8
I
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
..
lit .. ..
fl .. ..
~ ,.,
~,
1M ..
II
D 4
t ..
1.
".
\-... .. ..
'* ,. .. ,..
j ..
.-
4 ..
I
;
I
~
II
\
\
. w_ ... ~ __ . .. .. ..'
U ni ted S ta tes Department of the Interior
NATIONAL PARK SERVICE
IN UPLY UJ'I!UI. TO:
DS01S(ARQ-DD)
(X) LS815
Alaska Area Offic:e
540 West Fifth Avenue., Room 202.
Anc:horage, Al;uka. 9950 L
!;~I l"'iC'~'? ",. ... t·· ., ..... '\.._
Mr. Eric P. Yould
Alaska Power Authority
334 West 5th Avenue
Anchorage, Alaska 99501
HOifD IAN Q
\J 1 .... 1282 r. Crltikos
Dear Mr. Yould:
This is in response to your letter of December 16 concerning the
potential development of a hydroelectric project involving
Kukaklek Lake in Kat::::lai National Park and Preserve •
It is our pOSition that without specific Congressional approval
the Kukaklek Lake project could not be permitted '.rithin the
boundaries of Ka t.."'O.ai • This j udger.:z.en t is based on t.'1e a::!endmen t
to the Federal Power Ccmzission ~ct approved in 1921. That ar..~~d
ment states in part, "No per.nit, license, lease or authorization
for dams, conduits, reservoirs, powerhouses, transmission lines
or other work for storage or carriage of ;'/ater or for t."e de'1elop-
ment, transmission or utilization of power" wit...'1in any !'Tat'.ional
Park or Monument shall be granted wit.'1cut specific authority of
Congress. In addition, the National Wild and Scenic :livers Act
contains very similar language ~Y'hich iY'ould pertain to the Alagnak
River.
Regional Director
Alaska Region
8-9
Department Of Energy
Alaska Power Administration
P.O. Box 50
Juneau. Alaska 99802
Mr. Eric Yould
Executive Director
Alaska Power Authority
334 West 5th Avenue, 2nd Floor
Anchorage, AK 99501
Dear Mr. Yould:
RECEIVED
t·tarch 26, 1982
We have reviewed the Interim Assessment Executive Summary for the First
Phase of the Bristol Bay Regional Power Plan Detailed Feasibility Study
by Stone & Webster Engineering Corporation.
We agree with the findings and conclusions and have no specific comments
to offer.
8-10
Sincerely
b(~ ~'<.. -;7 ..7
Robert J. Cross
Administrator
I
I~
I
I
I
,I
J
I
I ,
I
I
,I
I
t
J
I
I
I
.-
iiIa
.... .-
"
flit ...
r .. .. .. ..
II.
.-
" r. ..
I
J
;
i
I
i :~
i
r • ..
! "' III ... ..
...
lit
Departmen t Of Energy
Al,l!)k<l Powt!r Administration
P.O. 00", 50
..... :,.
' ...... \ I ,<I' _,. __
Jl:!1I:i.;U. ,-\Iilska 99802
r·il". Eri c Youl d
Eiecutive Director
Alaska Power Authority
334 West 5th Avenue, 2nd Floor
Anchorage, AK 99501
Dear Nr. Yould:
Z6, 1932
We appreciate Eric ~1archeg;an; sending, en ;'ii!j :0 I :~:h;! Bristol Bay
Regional Pm'ler Plan Detailed Feasibility .<~I:i:.l..'sis dr':dt Int;:rim
Feasibility Assessment, March 1982, by Stone and ~ebster ~ngineering
Corporation. Hr. :'Iarche~iani asked for cerr.:;:cnts by June 13.
We agree with the Stone and Webster Engineering Cor~oration
recommendations for next steps of investigation.
It appears that a lot of good 'f/ork has .been done and is I'fell documEl1ted.
An obvious power plan is not easy to identify ;n this regiQIl, but C1H~
pros and cons of the various possibilities are I'ieil laid out for p~opl;
to con side r .
One small editorial item--reference 1 on page A.1-9 should read
" ..•. Administration" rather than " .... Authority.1I Retherford's original
energy balance, pO\'ier projections (Table A.1-2) and potential reSOl.l?'C':
inventory were presEnt=d in this report, then selected data used in ;;11e
1980 Reconna i ssance Study for the Power Authority.
As Floyd Summers disCUSSE:d \'/ith ~tr. Harchegiani, (and loJe !i~enti(jned ill an
earlier letter), Y/~ wOUld like to USe the anergy projec~iol1s for til~S
study as a target for analySiS of the '(lind rtlanitol"ing undenlClj ~Jr!';s a~
Dillingham, Naknek, and King Salmen, by Aero Vironment, Inc. The
appropriate data are ill Appendix A.I. Specifically, we propose to
utilize the jear 2002 data in Ta:Jl<i: A.l-5 for Dillingham and ;idkn~~,,;:~r:~
Salmon with the monthly distributi~n of Figures A.I-IS, -16, -17,
and -18.
If these are not appropriate, please let us know.
P~/d' ("lL Robert ,J. eros s T-' Administrater
8-11
j~,.
" . ~
I
ALASKA POWER AUTHORITY I
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501 Phone: (907) 277·7641
(907) 276-0001 1
Mr. Robert J. Cross
Administrator
U.S. Department of Energy
Alaska Power Administration
P.O. Box 50
Juneau, Alaska 99802
August 5, 1982
Subject: Bristol Bay Regional Power Plan Detailed Feasibility Analysis
Draft Interim Assessment Report.
Dea r Mr. Cross:
Thank you for the comments provided in your letters of March 26 and
May 26, 1982, regarding the above referenced report. We are pleased to
hear that you agree with the findings and conclusions of the Assessment.
The Power Authority is awaiting a revised analysis of the alternative
project plans, to be included in the final Interim Feasibility Report,
and an analysis currently underway utilizing the Chikuminuk and Newhalen
Project concepts to individually satisfy the interregional energy
requirements of both the Bethel Area and the Bristol Bay Area, prior to
making final recommendations. The error you pOinted out on page A.1~9
of Appendix A has been corrected.
We have no problem with your utilizing the energy projections
derived in the study as a target for analysis of your wind monitoring
program, however. we recommend that you use the revised forecasts which
will be included in the final Interim Feasibility Assessment Report
which will be sent to you in the near future. Please bear in mind that
the effects various state power cost subsidy programs could have a
significant effect upon energy demand.
Thank you again for your review comments and timely input. ~Ie
appreCiate your continued interest in the Bristol Bay Studies.
8-12
I
I
I
I
I
I
I
I
I
I
J
'I
I
I
I
I
,-
",
I
BURR. PEASE 8c KURTZ
A pROnss,_ ... CORPORATION
E. L. ARNELL UU3.tgea
O.A.SURR
THEODORE M. PEASE. JR.
L. S. KURTZ. JR.
EOWARD G. aURiON
CHARLES P. FLYNN
RICHARD A. HELM
ARDEN E. PAGE
J. W. SEDWICK NELSON G. PAGE
RONALD H. BUSSEY PETER J. MAASSEN
RUSSELLYN S. CARRUTH JAMES A. SARAFIN
RALPH E. CUERRE PAMELA L.SHORT
ANN C. LISURD
ROBERT A. MINTZ
JOHN C. SIEMERS March 29, 1982
JAMES R.PETERSON
MARK L. FIGURA
810 N STREET
ANCHORAGE. AL.ASKA 99501
'907) 270 ? 4 .. 1
TELEX: ,(090) 26·405
(907) 216-6100
f~OTED APR ,,../' r
'.. l:oiv':: r. Cntikos
Stone and Webster
Engineering Corporation
Bristol Bay Regional Power Plant
Interim Feasibility Assessment
P.o. Box 5406
Denver, Colorado 80217
Attention: Don Matchett, project Manager
File No.: 642-4011
Dear Sir:
Borm""t-RESHAllDfl AP;1 2. 2 1982
I am writing on behalf of the Igiugig Native Corpora-
tion with regard to the public hearings which were held in
Igiugig on March a, 1982. Several comments were made at the
hearing which I would like to re-affirm in this letter on behalf
of the corporation and to supplement prior comments which our
firm previously sent to Stone and Webster.
First, it is my understanding from what was stated at
the hearing at Igiugig that the Lake Kukaklek power projects are
no longer being considered as viable alternatives in the regional
plan. As a result these alternatives will no longer be seriously
studied and are essentially being scrapped at this stage. This
would include scrapping both the large scale regional project for
Lake Kukaklek and several al ternati ve small scale proj ects. I
feel that this was a very wise decision. The local feeling in
Igiugig was very strongly against any use of Lake Kukaklek as a
source for a hydro-electric project. The lake is very important
to the local villaqers for fishing and subsistance activities and
any significant alteration to that environment would be consi-
dered highly detrimental the villagers. Since the Kukaklek pro-
jects are no longer being seriously considered I feel that there
is no need to comment any further on this except to say that it
was a wise decision to scrap those alternatives •
. 8-13
'. ". ,
Don Matchet, Project Manager
March 29, 1982
Page 2
There were several points that I would like to re-
affirm which were raised at the hearing concerning possible
regional projects especially the two projects which are
apparently getting the greatest attention right now --Tazimina
Lakes and the New Halen ri 'ler diversion proj ect. There are
several general areas of concern which we would like your firm to
consider very carefully in further assessments of these regional
proj ects. First, there is a great deal of concern about trans-
mission lines running from New Balen or Tazimina to the various
villages in the southwest. ':'he lines must be designed in such
away as not to interfere with migrating caribou, moose and other
wild life. Further, since much of the area involves wet tundra,
careful engineering will have to be used to insure that the
transmission lines are carefully installed and will not collapse
in the spring thaw.
The construction canps will also be a problem, and some
careful planning must be considered. The villagers are very much
concerned that the construction workers will be allowed to have
guns at the construction camps and will do some hunting in the
region. I strongly urge that the possession of guns at the con-
struction camps be forbidden and that the only firearms allowed
be those for designated emplo:'ees to be used solely for the pro-
tection of the workers from any wild life which presents a sub-
stantial threat to the safety of the workers. The camp should
also be isolated from the villages so that there will be as
Ii t tIe impact a possible upon normal village life. I would
strongly suggest that alcohol and drugs be strictly forbidden in
the camps.
There also is some serious concern about the effects
which any proj ect in Tazimina or New Balen may have upon migrat-
ing fish. The Lake Iliamna ... ater shed is an important habitat
for a number of migrating fish upon which Igiugig villagers
depend for subsistance. A careful study should be given to the
effects which dam construction or river diversion would have upon
the ability of the fish to migrate and the effects of such pro-
jects on spawning grounds. I would also hope that any construc-
tion projects in New Halen or Tazimina would not create an exces-
8-14
I
I
I
I
I
I
I
I
I
I
I
I
'I
I
I
I
I
...
! III
~
lilt
JIll
--.. ..
... .. .. a.;
t
r
fill! ..
t .. .. ..
" II
[
.-a-
t
t
r ..
!fII'1I .. -till
.. .
Don Matchet, Project Manager
March 29, 1982
Page 3
-sive amount of barge traffic which would produce pollution on the
l(vichak River or on Lake Iliamna and otherwise interfere with
fish habitat and fish migration. I will hope that you give these
matters careful consideration in future planning for power pro-
jects in the region •
Very truly yours,
BURR, PEASE & KURTZ
JCS/vlm
p.~. !YI/f~"",,-1. __
rJOhn C. siJmers
8-15
STONE & WEBSTER ENGINEERING CoRPORATION
DENVER OPERATIONS CENTER
GREENWOOC PL-AZA. DENVER, COL-ORACO • ADDRESS ALL CORRESPONDENCE TO P.O. BOX 5408. DENVER. COLORADO 80217
eOSTON
NEW YORK
CHERRY HILL. N.J.
OIENV!R
CHICAGO
HOUSTON
PORTLAND. OREGON
SAN OU!GO
WASHINGTON, C.C.
Burr, Pease & KUrtz
810 N Street
TIEL£PHONE;: 303-770-7'00
W,U. TIL£X:4S"4401
April 13. 1982
J~chorage. Alaska 99501 J. O. No. 1~007.03
Attn: Mr. John C. Sieroers
Dear Mr. Siemer~:
INT£RIl-1 F£ASIBILI!Y ASSESSH£UT
DRISlOL BAY REG IOllhl.. fOi·:E.R PLAN
ALASKA POHER AUT~OnITY
We received ycur letter of ~~rch 29, 1982 containing co~~ents on the
village ceetings held in ISiuSiS cn ~~rch 8, 1982. Our unoerstandir.G 1s
that you represent the position of the Igiu~iS l;ative Corpo~ation as being
in concurrencp. ~ith the conclusions of the Interim Feasibility Assessment
with respect to development of hydroelectric power projects involvir.g Lake
Ku1:aklek. The conclusion at this tioe is that development of Lakc Kukaklek
is not one of the ~ore promising electrical supply alternatives for the
Bristol llay rebion or for small scale local cevelopment.
The e'nvirorJl!ental concerns you raised were mentioned durin; the village
meetings held in the Bristol Bay region during P~rch. You will find that
some of the points were addressed 1n general te~s in the Interim
Feasibility ~ssesz~ent report. A copy of the 3-vol~e report was sent to
t1ary Ann Olyt::pic, frezic.ient of IGiugiG t;a ti ves Ltd. Environmental concerns
will be further addressed 1n the next phase of tIlE: study in relation to the
specific plan which is selected for detailed feasibility analysis.
We appreciate your effort in bringinG these catter~ to our attention. If
you should have further cOC'.:::lcnts on the Iuterim Feasibility As~essr.lentt
please feel free to direct them to the Alaska Po\~er Authority or to us.
DU1/sh
cc: D. W. Baxter
8-16
Very truly yours,
HOlBl APR 1 5 l~bL D.lIlte •• tt
D. L. Hatchett
Project fJ'.anaser
NOrm S. IIEBNAtlO'Z f -~
• il-'II ~ ~ 19~2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WI , ..
r
fill
United States Department of the Interior
NATIONAL PARK SERVICE
N40
LAKE CLA.RK :"IATIONAL PARK &lid PRESERVE
701 "C'" STREET BOX 61 ROOM £.561
ANCHORAGE. ALASKA 99513
April 19 s 1982
Alaska Power Authority
334 West Fifth Avenue
Anchorages AK 99501
Attention: Don Baxter
Dear Don:
Bi:C=l~IU:1
A?R20l982
~ POWER AUTHORITf
Following are our comments on the alternative energy plans as presented at
the March 12 s 1982 meeting and in the Interim. Feasibility Assessment Executive
Summary. We are keeping our CO'llllDellts very brief.
The Newhalen scenario appears to have potential as a regional project.
Engineering and enviromnental feasibility should be determined. The aquatiC
concerns for salmon out migrants and unknOW'll use by resident fish must be
determined through indepth studies. There are many factors to consider in
this scenario, but the primary elements at this point seem to be the impact
on the fishery s the feasibility of construction of the ca:a.al and the year
round impact on river flow. trle feel studies should begin to determine
feasibility or potential problems with this scenario.
Stone and trlebster Engineering Corporation and their sub-contractor s Dames
and Moore. have gathered valuable data on the 'I'azim.1na Project. The flow
and temperature data collecting should continue. Alsos fisheries studies
should be maintained for at least another year to maintain continuity.
Rave the sub-regional and local scenario been given enough consideration?
Your short response time has not allowed us the time to totally view the
voluminous data gathered to answer this question to our satisfaction.
Both the Kontrashibuna site and the Beluga transmission line would have
a heavy impact on Lake Clark National Park and Preserve. Both the projects
would fall within areas designated Wilderness by the U. S. Congress. Because
of the park and wilderness status s the Kontrashibuna or Beluga transmission
line through Lake Clark Pass should not be considered for future study.
We appreciate the opportunity to comment on the Executive Summary.
~erelY: I _
V(, ... Lj~~
Paul F. RaVtel
Superintendent
8-17
ALASKA POWER AUTHORITY
I
I
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501 Phone: (907) 2n·7641
(907) 276-0001 I
Mr. Paul F. Haertel
Superintendent
U.S. Department of the Interior
National Park Service
August 4, 1982
Lake Clark National Park and Preserve
701 C Street
Box 61, Room E-561
Anchorage, Alaska 99513
Dear Mr. Haertel:
We appreciate the comments in your letter of April 19, 1982, on the
draft Interim Feasibility Assessment of the Bristol Bay Regional Power
Plan. Several additional activities, which relate to your comments, are
being undertaken or planned.
1. Geotechnical studies and borings were made at the Newhalen
site in April to further determine engineering feasibility of
the canal diversion concept.
2. A spring study of smolt and fry out-migration on the Newhalen
River has been completed in order to determine what mitigation
measures may be required in connection with a canal diversion.
3. Plans are being developed, subject to budget limitations, to
continue Newhalen River fisheries studies, including a field
test of canal intake diversion and screening systems.
4. The draft Interim Feasibility Assessment report is being
revised to give further consideration to sub-regional and
local scenarios.
5. Temperature and flow data collection is continuing on the
Tazimina River and additional limited fisheries data has been
collected above the falls. However, budget limitatiens have
not permitted an extensive field program on the Tazimina or
the Newhalen in 1982.
6. Investigations of energy plans to serve both the Bristol Bay
Region and the Bethel Area will be conducted for the Newhalen,
Chikuminuk and Kisaralik (near Bethel) hydroelectric' projects.
These alternatives will be compared with centralized and
decentralized approaches for each of the regions.
8-18
I
I
I
I
I
I
• I
I
I
I
I
I
I
I
I
I
t
Paul F. Haertel
August 4, 1982
Page 2
Your concerns have been noted regarding impacts on the Lake Clark
National Park and Preserve from development of the Kontrashibuna site or
from a Beluga transmission line. These alternatives are being reevalu-
ated and are not likely to be candidates for further analysis.
Additional information on the above items will be presented in the
revised Interim Feasibility Assessment report scheduled for publication
in early August. Again, we appreciate your comments and look forward to
continued cooperation in development of the Bristol Bay Regional Power
Plan.
DB/RM:js
Sincerely,
f\<..· ~~ ~ Ro~ert MOh~
Director of Engineering
8-19
v~v"" IJ-...... ~ ..... -
I
I
Ilji.?! ~ J ..... ,;
~.
DEP . .\RTl1ENT OF COMMERCE &
ECO~Ol'tIC DEVELOP~IENT
DIVIs/ON OF eNeRGY & ~R DEVELOPMeNT
JIJN 1., .. 198'2.
April 22, 1982
Eric P. Yould, Executive Director
Alaska Power Authority
334 West Fifth Avenue
Anchorage, Alaska 99501
JAY 5 HAMMONO
7TH FLOOR MACKA Y BLDG.
338 DENAl.I STREET
ANCHORAGE.Al.ASKA 99501
PHONE: 19071 21SoOSOR
.Rec:;rveti~
Subject: Bristol Bay Regional Power Plan Detailed
.' Feasibility Analysis -Interim Feasibility
Assessment Executive Summary -March 1982
Dear Eric:
We have revie'N'ed the subject report.
It appears that all reasonable options were addressed. ~';e
find no obvious omissions and have no fault with the
procedure used or the conclusions reached for this level of
study. We believe projected cost per kilowatthour woulc be
a more identifiable comparison than present worth but
realiz~ that because of the preliminary nature of the
assumptions, this could lead to problems.
'iVe acknowledge the busbar comparison of the costs. 'iVe are
aware that diesel operation entails 0 & H costs not incurred
by the other sources. We assume that proper adjustments
were made so that the Base Plan (BP-l) was not unfairly
assessed some costs that are not included in the other
scenarios.
8-20
• ..
I
I ,
I
I
I
I
I
I
I
I
I
I
I
I
I
...... / .. ">: -..
• >
•
,. ..
Eric P. Yould, Executive Director
A'pril 22, 1982
Page Two
We are most interested in the project and would appreciate
being k.ept up to date. If we can help let us' k.now.
Director
Enclosure
L.."1P : DWR: j h
.',
8-21
ALASKA POWER AUTHORITY
I
I
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501 Phone: (907) 277·7641
(907) 276-0001 I
Mr. William Beardsley
Director
State of Alaska
August 4, 1982
Department of Commerce & Economic Development
Division of Energy & Power Development
7th Floor, Mackay Building
338 Denali Street
Anchorage, AK 99501
Dear Mr. Beardsley:
Thank you for your divisionis letter of April 22, 1982, commenting
on the draft Interim Feasibility Assessment for the Bristol Bay Regional
Power Plan. We offer the following response to your comments:
The Power Authority's standard procedure for preliminary evaluation
of alternative projects requires a present worth comparison of
alternatives. A cost of power analysis can be misleading at this stage
of development due to the uncertainties regarding alternative financing
schemes, and possible cost reductions which may occur due to state
assistance programs. Phase 2 of the study ;s expected to analyze these
factors in more detail.
The cost estimates did not include distribution systems within
villages since these costs are common to all alternatives and not a
factor in determining the relative merits of a particular alternative.
Operation and maintenance costs were included in the estimates for all
power sources. Information for estimating diesel operation and
maintenance costs was obtained from the Naknek Electric Association and
Nushagak Electric Cooperative. Operation and maintenance costs for
other systems (principally wind, hydro, and transmission lines) were
obtained from sources believed to be equally reliable in order to fairly
compare alternatives. The cost of existing equipment for the base case
analysis is treated as a sunk cost.
We appreciate your interest in the project and will provide you a
copy of the revised Interim Feasibility Assessment report when published
in the near future.
8-22
Sincerely,
Eric P. Yould
Executive Director
I
I
I
I
I
I
I
I
I
I
I
I
I
,I
I
I
•
". ..
...
,/'
i
I
I JAY .t HAMMOND, GOYERNOR
DEPARTMENT OF NATURAL RESOURCES 555 Cordova Street
P.ouch 7-005
ANCHORAGE. ALASKA
PHONE: (9071276-2653 DIVISION OF FOREST; lAND AND WATER MMlAGEMENT
April 22, 1982
Mr. Eric P. Yould
Executive Director
Alaska power Authority
334 West 5th Avenue
Anchorage, Alaska 99501
•
Dear Mr. Yould:
ftlOllVI~
i"\;"~ 2 3 1982
'AlJSKA f.Qwai Alffif0BI:L1 .
A review has been made of the Bristol Bay Regional Power
plan, Detailed Feasibility Analysis! Draft Interim
Feasibility Assessment, dated March 1982 and prepared by
Stone and Webster Engineering Corporation (SWEC). My
comments follow.
SWEC should be commended. It is felt that they did a fine
job at preliminarily analyzing the many energy generation
scenarios available to the Bristol Bay region. It appears
that information presented in volume 1, Chapter 7 should
provide the basis for deciding which plans shall be pursued
in the Phase II study. This chapter is summarized in Tatle
7.3-1 "Environmental Evaluation Summary" and Table 7.4-30
"Summary of Present Worth Costs".
The ABC type, evaluation used in Table 7.3-1 ind icates it is
intended as a preliminary analysis only. Also, page 7-102
of Vol ume 1 states that II ••• the cost estimates represent
order-of-magnitude prices (:I: 20 to 25 percent)." Thus, as a
result of the Phase I environmental and economic analyses,
it is not obvious which one generation scenario is the best
for the region. Considering the uncertainty of the economic
analysis! it is felt that neither alternative B-14 (Newhalen
Regional) nor A-l (Tazimina Regional) can be considered
economically superior over the other at this time. For this
reason! it is recommended that both alternatives B-14 and
A-I be studied in Phase II to refine estimates of energy
costs to consumers as well as environmental and social
imp'acts. Also, if time and dollar constraints allow, a
similar analysis of alternative B-1 (Beluga Transmission)
may be worthwhile, since it is indicated as having the least
amount of environmental impacts and also ranks fourth in the
economic analysis. However, since environmental impacts
outside the Bristol Bay region do not appear to be
considered in this analysis, this plan may have more
environmental impacts than indicated. Thus, further study
may not be warrar.ted .
8-23
'-.
, 1
When determining details of Phase II w~rk to be done, please
recall the the Division of Land and Water Management has the
responsibility for issuing both a permit to construct or
modify a dam and a water rights permit.
a. Permit to Construct or Modify a Dam
Prior to issuing the permit, this office must be
assured that the dam will not create a public
safety hazard. A certification tc this effect
after the state of the art techniques that
analyze the design and construction as well as
the proposed operation and maintenance schedules
of the dam will be acceptable. If the Federal
Energy Regulatory Commission (FERC) is involved
in licensing the project, dam safety
certifications by them will be accepted. For
~ams not reviewed by FERC, we will review work
done by the applicant such that this office may
certify to the dam's safety. As the project
develops, please send to this office, dam safety
certifications by the FERC, or the appropriate
documents allowing such to be made.
b. Water Rights Permit
According to AS 46.15.080, a water rights permit
shall be issued if it is found that:
1. The proposed appropriation will not
unduly affect the rights of a prior
appropriator. From a revi~w of our files
on April 21, it appears that no water
rights exist in the areas to be impacted by
alternatives B-14 (Newhalen Regional), A-l
(Tazimina Regional) and B-18B
(Kontrashibuna) •
2. The proposed means of diversion or
construction are adequate.
3. The proposed appropriation is in the
public interest. To evaluate this, among
the items to be considered are changes in
the following as a result of the proposed
water appropriation:
(a) economic activity,
(b) fish and game resources,
(c) public recreational
opportunities,
(d) public health,
8-24
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
I
I
I
,. ..
r ..
..
•
.-..
r ..
(e) Loss of alternate uses of water
that might be made within a reasonable
time,
(f) harm to persons,
(g) access to navigable or public
waters •
To process the water rights application, the above items
must be addressed for each project stage, including
construction, reservoir filling and operation. If negative
impacts are noted, mitigation strategies and the associated
costs should also be discussed.
It is understood that it is not the intent of this Phase I
study to present detailed information as described above.
However, please be informed that this information is
necessary to adjudicate the application to construct or
modify a dam and the application for water rights according
to our legal responsibilities •
Sincerely,
J. W. Sedwick
Director
by: paul Janke
Civil Engineer
Water Management Section
8-25
I
ALASKA POWER AUTHORITY I
Phone: (907) 277·7641 334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
(907) 276-0001 I
Mr. Jack W. Sedwick
Director
State of Alaska
Department of Natural Resources
Division of Forest, Land and
Water ~lanagement
555 Cordova Street
Pouch 7-005
Anchorag~, Alaska 99501
Dear Mr. Sedwick:
August 4, 1982
The comments in your letter of April 22, 1982, on the Bristol Bay
Regional Power Plan draft Interim Feasibility Assessment report are
appreciated.
As you pointed out, the current assessment is preliminary in
nature, with the objective of identifying the most promising alterna-
tives for further evaluation in Phase 2. We agree that the order-
-of-magnitude economic comparision between the regional Tazimina and
Newhalen projects does not indicate a clear choice. However, because it
potentially has less environmental impact on fisheries resources and is
located closer to nearby population and transportation centers, in
addition to,demonstrating a minor cost savings over Tazimina based upon
our most recent cost estimates, we have selected the Newhalen Project as
that most worthy of detailed study, from among the regional
alternatives. The Tazimina project will be further evaluated as a local
run-of-river project.
The Beluga Alternative (B-1) is being reevaluated in light of
concerns by the National Park Service and updated cost estimates. It
appears that this scenario is unlikely to be a candidate for detailed
analysis.
Thank you for the specific guidance on the responsibilities of your
Division with respect to permits. The factors you listed would be
addressed in the final analysis of the most attractive development
candidate(s).
We appreciate your interest in the Bristol Bay Regional Power Plan
and look forward to continued cooperation.
RM:js
Sincerely,
P~. ~) .. ~~
¥ Robert Mohn 0
Director of Engineering
8-26
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
•
..
III ,. ..
...
) ...
IN REl"L Y WA~~ TQ:
United States Department of the Interior
IOJRJ--
FISH AND WILDLIFE 5ER VICE'" HEBNAND£Z
Western Alaska Ecological Services
733 W. 4th Avenue, Suite 101
Anchorage, Alaska 99501
(907) 271-4575
APR 2 9 1982
Eric yould
Executive Director
Alaska Power Authority
334 W. 5th Street
27 APR 1982
Anchorage, Alaska 99501
Dear Mr. Yould:
By reviewing the draft Interim Feasibility Assessment for the Bristol Bay
Regional Power plan, the U.S. Fish and Wildlife Service (FWS) is pleased to
continue our participation in Bristol Bay power development. Our review
comments are intended to assist you in planning Phase II studies and inform
you of our major concerns. Due to the voluminous nature of the Assessment
and abbreviated time frame for review, these comments should be considered
preliminary. The Interim Assessment will be repeatedly scrutinized as
additional information becomes available.
We are impressed with the magnitude of this report. Within the allotted time
and scope, your consultants have done an admirable job of technically
evaluating the Ta:im1na power alternative, qualitatively assessing environ-
mental project features, and preliminarily identifying the advantages and
disadvantages associated with a broad range of energy alternatives. More-
over, we have appreciated efforts to involve government agencies throughout
early planning stages of this project.
To enhance agency review of the Interim Assessment, the FWS organized a
meeting, March 25, 1982, among involved natural resource agencies and project
consultants (see attached list). Reviewing environmental aspects of the
proposed Ta:imina hydroelectric project, exchanging information on agency
concerns, and discussing future study needs were the meeting's purposes.
Based on that meeting and the Interim Assessment, the FWS recommends that you:
(1) Initiate environmental studies of the Newhalen run-of-the river
hydropower concept.
(2) Continue and expand on environmental studies of the Tazimina River.
(3) Consider the Chikuminuk Lake hydro site not feasible because of
severe environmental and legal constraints.
(4) Consider the Kontrashibuna hydro site not feasible because of severe
legal and environmental constraints.
(5) Consider subregional and local power plans as an alternative to
regional power plans to better satisfy local power desires.
8-27
Our primary concerns at this time are that you not prematurely eliminate
alternatives. and with limitations to the data provided thus far. As in our
earlier comments (our November 4, 1981 letters to Don Baxter, Alaska Power
Authority (APA), and Ted Critikos, Stone and Webster Engineering Corp), we
remain concerned that field studies were limited to the Tazimina alternative
before all other po~er alternatives had been adequately evaluated.
Our concern about data limitations causes us to disagree with the Executive
Summary statement:
The data base collected at Tazimina is believed sufficient
in detail to satisfy the environmental requirements of FERC
for a license application, when supplemented by the instream
flow program (page 1-11).
Although environmental features of the Tazimina area have been thoroughly
assessed in a qualitative manner, there has been little to no quantification
of fish and wildlife numbers, habitat values, or anticipated impacts. The
report identifies numerous unknowns in understanding Tazimina River system
hydraulics and associated fish and wildlife resources. Design. construction,
and operational details for the Tazimina project, much less for any other
alternative, are insufficient for determining mitigation requirements. Nor
are fish and wildlife enhancement options considered. Moreover,
construction, operation, and maintenance costs of alternative mitigative
measures are not provided. Such quantification of impacts, development of
mitigation plans. and consideration of mitigation costs are requisite to the
Exhibit E which accompanies any applications for Federal Energy Regulatory
Commission (FERC) licenses (44FR(229)67652-67654). Even though project
details are still of a general nature, mitigation must be considered in all
accounting of alter-native project costs and benefits. As an integral
project cost. mitigation may affect the economic feasibility of an
alternative. With cost estimate uncertainties of up to 25 p~rcent and no
consideration of mitigation costs. several lower ranked alternatives may
become more feasible.
Further details on necessary studies and the favorability of alternative
power plans follow.
(1) The Newhalen run-of-river power concept has been identified as a
technicnlly 4nd ~conomlcnlly proml~ln8 powor nlt~rnntlve. Wltll
effective mitigation, the Newhalen alternative may have less impact
on fish and wildlife resources than the Tazimina alternative.
Immediate study needs include timing of fry and smolt movements and
locating of fish throughout and across the river channel. By com-
paring smolt counts on the Newhalen with those at Iguigig, the
contribution of the Newhalen to the Kvichak fishery can be
determined. The USGS gaging station on the Newhalen should now be
reactivited to help determine flows when fish passage problems
naturally exist. A secondary information need is to establish a
short channel for testing the effectiveness of screen and baffle
designs which allow fish passage yet prevent fish from entering
power turbines. Because movement patterns vary with numbers of
fish, fish abundance and distribution studies should be conducted
from low populations expected in 1983, to high populations expected
in 1985, and through resultant 1986 and"1987 smolt and fry
production.
8-28
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
r
It
(2) Flow and temperature data collections should continue on the
Tazimina River; resident fish spawning habitats should also be
evaluated during the coming field season. Because environmental
studies of the TaziMina alternative were initiated so late in the
1981 field season, spawning habitats of resident fish were not
studied. Stream flow and temperature data are limited.
Unfortunately, it is too late to determine the relative importance
of mainstream as compared to side charmel sockeye production for
th:! s :..... T .... ·stigatf.on of sockeye spawning should be continued
since last year was a low for sockeye runs. Project impacts on
resident and anadromous fish spawning habitats cannot be determined
without these studies. A count tower and fyke nets should be
established and maintained on the Tazimina River to confirm adult
escapement and fry outmigration as compared to the Newhalen and
Kvichak River at Lake Iliamna. Due to the physical proximity of
Newhalen and Tazimina River systems and gaging stations, it will be
relatively easy to fill these data gaps for the Tazimina River. If
mitigation proves ineffective, the Tazimina regional power alter-
native will less significantly impact the Kvichak fishery than would
the Newhalen power alternative. Until comparative fisheries data is
gathered, the Tazimina alternative should not be dropped. Valuable
study starts should not be interrupted.
Detailed instream flow studies can be delayed until a more informed
power source deciSion can be made. If the Tazimina alternative is
pursued for FERC licensing, a detailed instream flow assessment of
resident and anadromous fish habitat should be undertaken. Then,
spawning habitats between Upper and Lower Tazimina Lakes should be
assessed as should impacts of water fluctuations on invertebrate
populations serving as fish food.
(3) The NPS is adamantly opposed to the Kontrashibuna hydro alternative,
finding it incompatable with National Park Service Wilderness lands
on which it is located. OppOSition from local residents of Port
Alsworth also makes Kontrashibuna an impractical alternative.
(4) The State Division of parks is opposed to the Chikuminuk alternative
because it is located on the Wood-Tikchik State Park. In addition,
access difficulties which would result in significant impacts to
terrestrial habitats make the Chlkuminuk alternative impractical.
(5) During public meetings, local opinion on Bristol Ray power alter-
natives has been mixed. The Stone and Webster Assessment documents
numerous concerns that additional power may not be necessary and
that no alternative be developed which would negatively affect the
fish and wildlife resources integral to area lifestyles. At the
March 25 interagency meeting. questions were raised about the source
and immediacy of projected increases in power demands. We are
concerned about committing to a major power development in the area
without coordinating with the Bristol Bay Cooperative study mandated
by tne Alaska National Interest Lands Conservation Act (P.L. 96-487).
8-29
Area populations have not substantially increased in the last 10 or
20 years. No dramatic increases are expected for any of the three
main area employers --the military, fishing industry, or govern-
ment. Therefore it may be more cost-effective and less environ-
mentally damaging to develop a subregional power alternative(s) for
the central area villages (Dillingham, Aleknagik, Naknek, King
Salmon, Egigik, Manokotak, and New Stuyahok as identified in the
Stone and Webster Energy Demand Forecast) where power demands have
most in~~~~Q~rl. Wind, continued diesel, energy conservation, and
passive solar may be v~luable supplemental power sources and more
viable alternatives for the remaining villages. Justification for
more detailed studies of energy conservation and wind as supple-
mental power for single villages or even individuals are found
throughout the report (e.g. Appendix A, page 6-3; Appendix B, pages
3-34 and 3-5]). No locally initiated nor wide-spread support has
been documented for a large regional power system (page 2-2 of main
report) •
The agencies have expressed strong interest in a poll or vote
allowing full public participation as to whether local, subregional,
or regional power sources should be developed. We recommend
conducting more detailed surveys to confirm local opinions and then
using survey results in power planning.
We also have several specific comments on Appendix E, the Environmental
Report in the Draft Assessment,as well as on the main report and other
appendices.
Appendix E -Environmental Report
Chapter 4, Existing Resources -Although an excellent description and map of
existing vegetation types is provided, there is no consideration of how that
vegetation is changing succe~sionally. Nor is there a correlation of natural
resource values and use patterns depicted on Plate 1 with the wildlife
habitats delineated in Figures 4-2 through 4-5.
Further information is necessary on how FW5' 1980 Terrestrial Habitat
Evaluation Criteria Handbook -Alaska habitat parameters listed in Table 4-3
were combined and evaluated to map "optimum quality habitat."
S~cr10n 4-2, Anticipnted Impacts. -Impacts to fish Rnd wildlife have not
I
I
I
I
I
I
I
I
I
I
I
I
I
been quantified. Values placed on wildlife habitat should be carried over to I
the impact analysis.
Pages 4-49 to 4-51 -The issue of disturbance and how noise and human
activity will decrease adjacent habitat values, not only cause a short-term I
loss of habitat, should be discussed in greater detail. Disturbance zones
should be delineated and quantified.
Page 4-51, paragraph 6 -With the presence of project workers during con-II
struction, additional significant adverse impacts will likely include fish
and wildlife population disturbance and habitat alterations from increased I
and geographically changed uses, as well as greater possibility for
human/bear conflicts. Conflicts with the subsistence resource base of
existing area residents should also be discussed.
8-30 I
-• .. ... -
-
..
..
-.. ..
II
Page 4-54 -Again, impacts to terrestrial wildlife are not quantified~ This
section should address how much of the inundation area was classified as high
quality moose habitat; information on numbers of moose and their seasonal
uses of the inundation as compared to adjacent area; and the ability of
adjacent ranges to support animals displaced from the reservoir site •
Intraspecific strife could result from crowding of brown bears displaced from
inundation and adjacent disturbed areas.
Section 4.2.1.4, Page 4-55 -Selective clearing of trees and tall shrubs
could enhance production of moose browse. Road construction along the trans-
mission line should be prohibited to minimize and contain the terrestrial
impacts and satisfy local views. North of King Salmon the line should follow
the coast to minimize impacts on caribou.
Section 4.2.2, Aquatic Habitats -Although a cursory description of the
aquatic resources between the falls and lower Tazimina Lake is included in
the previous section, 4.1.2, there is no parallel description of aquatic
impacts in that portion of the river.
Page 4-62 -Presence of the Tazimina dam will create a migration barrier
isolating resident fish in either the lake or the river between the falls and
the lake. This impact and mitigation, e.g. fish ladders, should be addressed •
Chapter 6, Socioeconomic Considerations -Strong local reservations over
development of a regional Bristol Bay power source, as documented here,
provide sufficient reason to continue considering alternatives to the
Tazimina and Newhalen regional power plans. The report on socioeconomic
considerations also clearly documents (1) lack of local interest in a
regional plan; (2) social. economic, and political factors which may make
local and subregional power plans more locally desirable and environmentally
practical; and (3) overwhelming resident concerns that fish and wildlife
resources not he harmed to produce electric power. Conflicting views among
area residents further justify a more detailed study of local opinions and
evaluation of subregional and local power plans, continued diesel, no pro-
vision of electricity, and wind before proceeding with regional power
development plans.
Main Report
Page 7-114 -Order of magnitude costs (up to 25 percent) presented in Che
main body of the report include no costs for fish and wildlife mitigation
(e.g. fish passage structures, necessary monitoring and follow-up, etc.)
Given these omissions, ranking project alternatives on the basis of their
estimated economic feasibility is nearly meaningless (Table 1.6-3) .
Section 9 -Conclusions
We concur with the Assessment's general conclusions (1) that there are a
number of promising alternatives to current diesel power generation; (2) to
continue feasibility studies of the Tazimina River; and (3) to undertake
further evaluation of the Newhalen River. We have described fishery study
8-31
needs associated with those latter two recommendations, as well as the need
to more fully consider local preferences, project viabilities, and mitigation
costs. The report acknowledges that the best data available is for the
Taz1mina River alternative. Unless several alternatives are equally
investigated, it will not be possible to make an informed choice.
Appendix A -Engineering and Technical Considerations -Energy conservation
as discussed in Appendix A.S must be an essential part of any Bristol Bay
power plan. The minimal impact of structure weatherization on area fish,
wildlife, and cultural resources, coupled with the economic benefits of
several State programs mean conservation can satisfy a valuable portion of
area energy needs. Energy savings of up to 30 percent in the residential and
15 percent in the commercial and industrial sectors are projected in this
report.
Page A.5-2 -As. indicated here, conservation for all electrical, not only
space heating, needs should be evaluated 1n greater detail. We urge state
implementation of education programs and technical assistance to overcome
identified financial and informational obstacles to energy conservation.
Appendix G -Hydrologic Evaluations
We have consulted with the U.S. Geological Survey on the Hydrologic
Evaluations. Their preliminary assessment 1s that methods used were appro-
priate to the available data and time. Stone and Webster estimated stream-
flows are higher that USGS measurements. Because those measurements are for
only one wetter than normal year, report estimates may be somewhat high.
Continued flow measurements of both Tazimina and Newhalen are necessary.
The consultants, FWS, and Alaska Department of Fish and Game have previously
documented the importance of Bristol Bay fish and wildlife to local economies
and lifestyles, as well as to the state economy and world salmon harvest.
Given those values, the instability of world oil and gas prices, incon-
clusiveness of resident attitudinal surveys, lack of imminent large scale
increases in area power demands, and gaps in the technical, economical, and
environmental data base, it is premature and contrary to the intent of the
National Environmental Policy Act (P.L. 91-190) to now concentrate on only
one, or even twO power alternatives. A broad range of energy resources was
found promising (Appendix B, page 5-1). We look forward to working further
with you in fully considering those alternatives and finalizing a power plan
:or the Br1stol Ray region.
Attachment
cc: FWS-ROES
Tom Arminski, ADF&G, Anchorage
Dick Russell, ADF&G, King Salmon
John Taylor, Becharof NWR
Glen Elison, Alaska Peninsula NWR
8-32
Sincerely,
jJ~~/k-~
Field Supervisor
Dave Morris, Katmai National Park
Paul Haertel, Lake Clark National Park
Brad Smith, NMFS
Jim Hemming, Dames & ~oore
Don ~atchett, Stone & Webster
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
II
-
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Mr. Robert Bowker
Field Supervisor
United States Department of the Interior
Fish and Wildlife Service
Western Alaska Ecological Services
733 W. 4th Avenue, Suite 101
Anchorage, Alaska 99501
Dear Mr. Bowker:
August 2, 1982
Phone: (907) 277·7641
(907) 276-0001
The Alaska Power Authority has reviewed the Fish and Wildlife
Service's comments on the draft Interim Feasibility Assessment for the
Bristol Bay Regional Power Plan contained in your letter of April 27,
1982. We appreciate your timely input and your staff's participation in
several agency meetings on this project.
With respect to your five principal recommendations, we have taken
the following action:
1. Fisheries studies on the Newhalen River were initiated about
May 1, 1982 to obtain baseline data on the downstream
migration of smolt and fry in connection with the proposed
run-of-river Newhalen hydroelectric concept.
2. A spring reconnaissance study was undertaken on the Tazimina
River to continue elements of the data collection program
instituted in 1981. Also an aquatic habitat survey of the
Tazimina River above the falls was undertaken in early May
1982, primarily to identify resident fish habitats in the
section of the river that might be effected by water diversion
to a hydroelectric plant.
3. The Chikuminuk hydroelectric site has been dropped from
further consideration in this study. However, it is being
evaluated as an interregional alternative for both the Bethel
Area and Bristol Bay by the Harza Engineering Company as part
of the Bethel Area Power Plan Feasibility Assessment.
4. The Kontrashibuna hydroelectric site ;s not being given
further consideration at this time due to a) opposition by
the National Park Service and b) lower economic and
environmental ratings.
5. Subregional and local power plans will be further evaluated.
8-33
United States Department of the Interior
August 2, 1982
Page 2
Work undertaken with respect to the above items, with the exception
of the additional work at Chikuminuk, will be reported in the final
Interim Feasibility Assessment report. Results of the work at
Chikuminuk will be reported as part of a separate report for the Bethel
Area. .
With respect to your concerns about data limitations for a
quantitative environmental assessment of the Tazim;na project, we agree
that further information is required to adequately assess impacts and to
design mitigation measures. This would be a major future work effort,
should Tazimina be selected as an alternative for further evaluation in
Phase II. Mitigation costs were not specifically estimated for any of
the alternatives evaluated in Phase I because in most cases plans had
not been developed to a pOint where such requirements were well defined.
However, an allowance for indeterminants of at least 15 percent was
added to all cost estimates to account for such unknowns.
Your specific suggestions for further environmental studies on the
Newhalen and Tazimina Rivers are being seriously considered. However,
because it potentially has less environmental impact on fisheries
resources and is located closer to nearby population and transportation
centers, in addition to demonstrating a minor cost savings over Tazimina
based upon our most recent cost estimates, we have selected the Newhalen
Project as that most worthy of detailed study, from among the regional
alternatives. We have decided, therefore, to allocate most of the
remaining project funds to studies on the Newhalen River during the
spring downstream migration of smolt and fry. The Tazimina Project will
be further evaluated as a local run-of-river project.
The Power Authority is aware that local opinion in Bristol Bay has
been mixed relative to power alternatives. A public participation
program to further determine local preferences and concerns is being
considered as a high priority task for the next phase of the program.
We will be sending you a separate letter in the near future describing
our public participation program. Our studies to date have been fully
coordinated with the Bristol Bay Cooperative r'1anagement Plan.
Appendix E -Environmental Report, focused mainly on the Tazimina
Project. If that alternative should be proposed for regional
development, clearly much additional analysis will be required for
preparation of Exhibit E for a FERC license application and other state
approvals. Your comments are appropriate to preparation of Exhibit E
which would occur during the latter part of Phase II.
With respect to energy conservation as discussed in Appendix A, we
agree that energy conservation is an essential part of any Bristol Bay
power plan. Although significant reductions in space heating energy
consumption can occur through appropriate conservation measures, it is
not clear to us that the present usage of electrical energy in Bristol
Bay can be significantly reduced through conservation. We believe that
resource conservation is, however, a more fundamental and productive
goal for Bristol Bay. Resource conservation can be achieved through
development of renewable energy sources.
8-34
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
lit
United States Department of the Interior
August 2, 1982
Page 3
Tazimina River hydrologic evaluations are continuing based on
1981-1982 stream flow and meteorological data. The Newhalen gage has
been reactivated and measurements at the new Tazimina gage are
continuing by the USGS. An updated discussion of hydrology will be
presented in the Interim Report.
Further discussion may be in order regarding the intent of NEPA
with respect to the appropriate time to concentrate on a limited number
of alternatives. As you are no doubt well aware, 40 CFR 1500-1508
provides agency guidance on NEPA implementation. We heartily support
the concept that a discussion of alternatives including the proposed
action "is the heart of the environmental impact statement ll (40 CFR
1502.14). The NEPA process is intended to help public officials make
decisions. We must reach agreement on when sufficient data is available
to make necessary decisions, taking into account the costs related to
extended studies and indecision.
We appreciate the comments of the Fish and Wildlife Service on the
draft Interim Feasibility Assessment and we look forward to further
cooperation in developing the Bristol Bay Regional Power Plan. We
encourage you to direct additional comments to us as they become
available and to have your staff discuss any concerns and suggestions
with Don Baxter of my staff. Thank you again for your timely input.
Sincerely,
p\., ~~~
~Robert r~ohn
Director of Engineering
Attachment
cc: FWS-ROES Dave Morris, Katmai National Park
Tom Arminski, ADF&G, Anchorage Paul Haertel, Lake Clark National
Dick Russell, ADF&G, King Salmon Park
John Taylor, Becharof NWR Brad Smith, NMFS
Glen Elison, Alaska Peninsula NWR Jim Hemming, Dames & Moore
Don Matchett, Stone & Webster
8-35
DEP."RT "'E~T OF FISH . .\ ~D Gr\ .lIE
OFFICE OF THE COMMISSIONER
Apri 1 28, 1982
JA 'f .i. HAMMOMD. GOVERMOR
p.o. SOX 3-2000
JUNEA U, A~SKA 99802
PHONE: 460-4105
BECE1VEQ
I
I
I
I
Alaska Power Authority
334 W. 5th Avenue
Anchorage, Alaska 99501
APR.3 0 1582 I
~ POWER AImiO,
Attention: Mr. Eric P. Yould, Executive Director
Gentlemen:
Re: Bristol Bay Regional Power Plan Detailed Feasibility Analysis Draft
interim Feasibility Assessment
The Alaska Department of Fish and Game has reviewed the subject report and
submits the following comments.
As a matter of policy, the Department of Fish and Game discourages the
construction of dams on any of the major salmon producing drainages in
Bristol Bay. This would include both the Tazimina and Newhalen River
Projects. Our concern stems from the fact that dams have been the major
factor in the decline of the Columbia River salmon runs and the salmon
fishery in the Northwest United States. Adverse impacts from dams include;
barriers to fish migrations, water temperature changes, water level
fluctuations, entrainment and impingment of fry and smolt in turbines,
nitrogen supersaturation, and loss of spawning and rearing areas. 8ecause
the entire economy and culture of Bristol Bay is based on the production and
harvest of pacific salmon, the Department believes it is imprudent to
construct dams which may degrade the local socioeconomic structure. Our
preference would be to either reevaluate dam sites on non-salmon producing
streams in Bristol Bay or alternative energy systems including coal burning
power generation, and transmission lines from other dams. The economics of
the different alternatives should also be reevaluated now that the price of
oil has declined and it has been predicted that its real price may stabilize
at a considerably lower level than used in the existing economic evaluation.
The Department of Fish and Game also recognizes the need for lower cost
electrical power in the Bristol Bay Region and is willing to work with APA
in evaluating the potential effects of the Tazimina and Newhalen River
projects on salmon production. If pre-construction studies can conclusively
demonstrate that either of these projects will not have any adverse impact,
the Department will not oppose their construction. However, we will expect
rigorous stUdies, field demonstrations, and conclusive results before
changing our minds.
8-36
I
I
I
I
I
I
I
I
I
I
I
I
I
-
-
..
..
-
-
Gentlemen -2-Apri 1 28, 1982
Enclosed are specific comments relating to the Interim Feasibility
Assessment. If you have any questions or comments, please to not hesitate
to ca 11 us.
Si~luJ
Richard Logan, Dlrector
Habitat Division
Enclosure
cc: Commissioner Skoog
Carl Yanagawa
8-37
1
Specific comments: Bristol Bay Regional Power Plan Detailed Feasibility
Analysis -Interim Feasibility Assessment
5. FIELD INVESTIGATIONS
5.3.4 Aquatic Ecology
Page 5-24, para. 2
Evaluation of changes in thermal regimes are required to evaluate
possible influence on salmonid egg incubation rates rather than
spawning habits.
6. DEVELOPMENT OF ENERGY PLANS
6.1.2 Assessment of Energy Sources
Page 6-9, Relative Economics Project
We realize that APA has developed a specific methodology related to
economic assessment of projects and that assessment does not address
the possible cost of lost natural resources. We do not disagree with
the methodology but believe that in cases where projects could impact a
significant fishery {we estimate that the SO-year worth of the Kvichak
sockeye salmon fi shery to be about 2.3 b i 11 ; on do 11 a rs } that thi s
possible cost must be somehow considered.
8-38
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
tilt ..
til
, .. -
, -
2
6.2 DESCRIPTION OF SELECTED ENERGY SCENARIOS
Page 6-20, 6.2.2 Base Plan
From a fish and wildl ife conservation viewpoint, the most favorable
concept is the Base Plan. If adopted, even partially, it would allow
further long term studies to be directed toward hydro development
offering greater reassurance that fisheries resources will not be
adversely affected. In addition, falling oil prices may make this
alternative more attractive.
Page 6-21, 6.2.3 Alternative "All
With respect to this Tazimina alternative, our concern is with the
impact of regulated flows, thermal impacts, fluctuations of impoundment
level and inundation of habitats.
Development of Tazimina hydropower with a regulating dam wi11 be
acceptable to this Department ~ if there are no adverse impacts to
downstream Tazimina fisheries resources.
Page 6-23, 6.2.4.2 Scenario 8-1
Transmission 1 ines described in the Beluga power scenario would go
through Lake Cl ark Pass, a very important habitat corridor for brown
bear, moose, Dall sheep and furbearers, and would cross important
anadromous fish waters.
8-39
3
Page 6-23, 6.2.4.3 Scenario B-2
Newhalen River diversions are ~ acceptable if downstream fish
migrants can be prevented from pasSing through turbines.
With respect to a large project at Kukaklek, free movement of salmon,
trout, grayling, char, lake trout, whitefish and burbot into and out of
Kukaklek Lake must be maintained. We are also concerned that modified
flow and thermal regimes and fl uctuati ng 1 ake 1 evel s not impact fi sh
habitat in Kukaklek Lake and Alagnak River. In addition, provisions
would have to be made to prevent fish passage through turbines. There
may be othe!," problems associated with this project related to false
imprinting and transference of pathogens and parasites from one system
to another.
Page 6-24, 6.2.4.4 Scenario B-3
Newhalen River diversions are acceptable only if downstream fish
migrants can be prevented from passing through turbines.
With respect to a 7000 kw Kukaklek project, our concerns are the same
as those expressed for page 6-23, Scenario B-2 including additional
concern over the poss i b 1 e effect on fi sheri es in Pecks Creek and 01 e
Creek whi ch apparently drai n the two unnamed 1 akes menti oned ; n thi s
scenario.
8-40
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
III
...
. ! ..
,..
i
..
-
4
From a salmon fisheries perspective, the Chikuminuk Lake site does not
appear to have overwhelming fisheries constraints. There are severe
rapids in the Allen River that salmon cannot pass. Only small number
of sockeye salmon spawn below the rapids. In some years, however,
large numbers of sockeye spawn in the area where Allen River enters
Lake Chauekuktul i • Regul ati on of A 11 en River flows may have some
effect on spawning in this area .
Page 6-25, 6.2.4.5 Scenario 8-4
With respect to 7000 kw Kukaklek hydropower, same comment as for page
6-24, Scenario 8-3.
A Taziminaproject'discharge immediately below the falls would probably
not have a serious impact on downstream fisheries resources.
Page 6-26, 6.2.4.8 Scenario 8-8
With respect to 8000 kw Chikuminuk hydropower, same comment as for page
6-24, Scenario B-3.
With respect to 8000 kw Tazimina hydropower, same comment as for page
6-21, Alternative "AII.
Page 6-28, 6.2.4.10 Scenarios 8-11 and 8-12
8-41
5
With respect to 1200 kw Newhalen River hydropower, same comment as for
page 65-23, Scenario B-2.
Page 6-28, 6.2.4.11 Scenario 8-13
Wi th res pect to 16,000 kw Chi kumi nuk hydropower, same comment as for
page 6-24, Scenario B-3.
Page 6-28, Scenario 8-13A
With respect to 12,000 kw run-or-river Tazimina hydropower, same
co"~nt as for page 6-24, Scenario 8-4.
Page 6-28, Scenario B-138
With respect to 12,000 kw run-of-river Newhalen hydropower same as for
page 6-23, Scenario 8-2.
Page 6-29, 6.2.4.12 Scenario B-14
With respect to 16,000 kw Newhalen hydropower, the same concerns exist
as with the smaller Newhalen projects respective to prevention of fish
entrainment in turbines. There is also the additional concern that
less than acceptable flaws may occur in the Newhalen between the points
of diversion and discharge during low water periods. This may have an
adverse effect on resident and/or migrating fish.
8-42
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
-
III
..
III
-
-
6
Page 6-32, 6.2.4.16 Scenario B-18
With respect to a 16,000 kw run-af-river (riverdiversion through
turbines without construction of large dam) Tazimina hydropower
project, this project may be acceptable with respect to fisheries
provided the tailrace discharge is located near the base of the falls.
A 16,000 kw regulating dam project on Kontrashibuna Lake would probably
have little impact on area salmon resources. Salmon are limited from
ingress to the lake by a waterfall and spawning in the Tana1ian ;s
light and confined to the area where it enters Lake Clark •
7. EVALUATION OF SELECTED ENERGY PLANS
7.2.3 Reliability
Page 7-3, para. 1
We are also concerned with blockage of screened intakes with ice. The
most obvious solution to the problem is to remove the screens which
will allow fish to pass through turbines.
7.3 ENVIRONMENTAL EVALUATION
Page 7-12, 7.3.2.7 Scenario B-S
8-43
7
This scenario appears to have been omitted from the text in 6.2
DESCRIPTION OF SELECTED ENERGY SCENARIOS. However, Kukaklek site same
comment as for page 6-23, Scenario B-2 and page 6-24, Scenario B-3.
Wi th respect to Tazimi na run-of-river, same comment as for page 6-25,
Scenario 8-4.
With respect to Chikuminuk hydropower, same comment as for page 6-24,
Scenario 8-13.
Is the inclusion of local Newhalen run-of-river here an error? Other
descriptions of this scenario include Tazimina run-of-river rather than
a Newhalen project.
Page 7-14, 7.3.2.12 Scenario 8-14
F.R.E.D. ;s not a special study group within the Alaska Department of
Fish and Game but is the Fisheries Rehabilitation & Enhancement
Development Division (acronym F.R.E.D.) responsible for salmonid
research, and rehabilitation and enhancement of stocks.
general comment
As a general comment regarding wildlife associated with the sites and
transmission corridors, we are concerned that construction operation,
and maintenance will impact resources proporti onate ly to the magnitude
of those actions and the amount of habitat disturbed, inundated. etc.
8-44
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
.. ..
II
iii
... ..
-
8
We also expect that secondary impacts rel ated to improved access may
occur •
7.3.6 Water Quality
Page 7-39, general comment
We bel ieve that an assessment regardi ng the potential for hydrogen
sulfide (H 2S) contamination is indicated for those projects with
regulating dams. It was recently noted that waters impounded by the
Solomon Gulch hydroproject near Valdez are contaminated with hydrogen
sulfide, presumably generated by anaerobic decomposition of inundated
plants. Undissociated H2S concentrations in excess of 2.0 ug/1 could
constitute a long term' hazard to most fish. The undissociated
concentration is, of course, dependent upon temperature, pH, dissolved
oxygen concentrati on, etc. The current water quality standard for
Department hatcheries and rearing facilities limits H2S to 2.0 ug/I.
7.3.7 Fish and Wildlife Impact
Page 7-48,7.3.7.2 Scenario A-l
Below the proposed powerhouse, salmonid incubation rates may be
affected by altered thermal regimes.
Same comment as for page 7-39, 7.3.6 Water Qual ity 't'lith respect to
hydrogen su1fide.
8-45
9
Page 7-49, 7.3.7.4 Scenario B-2
Same comment as for page 6-23, Scenario B-2 with respect to fisheries
impacts. In addition, despite its large areal extent, fluctuating lake
levels could severely impact the littoral zone which is exceeding
important for aquatic organisms and rearing-fish and page 7-39, Water
Quality.
With respect to a Newhalen diversion, a significant fishery impact will
occur if efforts to prevent downstream mi grants from paSSing through
turbines fail. If prevention of entrainment downstream migrants cannot
be assured, this Department cannot support this project.
Page 7-50. 7.3.7.5 Scenario B-~
In addition to concerns regarding across system diversion affecting
homing, we are concerned that introduction of non-indigenous pathogens
and parasites ;s a possibility.
Page 7-51, 7.3.7.7 Scenario 8-5
With respect to Kukaklek, same comments as for page 6-23, Scenario B-2,
page 7-49, Scenario 8-2, page 7-50, Scenario 8-3.
Page 7-52, 7.3.7.8 Scenario 8-8
8-46
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
!IIIIII -... ..
!/III ..
!IIIIII
III
filii
l1li
... ... ,.
iii
JIIIII
l..
I!IlII ... -.. --...
iIII .. --III
...
III -..
-..
-.. -..
10
For Tazimina regulating dam project, same comment as for page 7-48,
Scenario A-l.
Page 70-53, 7.3.7.10 Scenario B-11 and B-12
For Newhalen diversion, same comment as for page 7-49, Scenario B-2.
Page 7-54, 7.3.7.13 Scenario B-13 Scheme B
For Newhalen diversion, same comment as for page 7-49, Scenario B-2
Page 7-55,7.3.7.12 Scenario B-14
The statement that diversion of low winter flows will have little or no
effect on salmon cannot be confirmed at this time. Downstream salmon
migration may occur year long but peak during summer months. If this
is the case, wi th ; nci dence of low flows to concentrate fi sh and
problems with ice collection on screening devices necessitating their
removal, we believe the possibility of salmon being entrained exists •
Page 7-56, 7.3.7.16 Scenario B-18 Scheme A & B
With respect to Kontrashibuna, same comment as for page 7-39,
Water Quality.
Page 7-93, 7.3.12 Summary Evaluation
8-47
11
We believe, that until it can be demonstrated that downstream migrants
can be effectively prevented from being entrained in turbines, the
Newhalen diversion projects should be placed in the "major impact
possibly resul ting in fatal flow category. II
7.4 ECONOMIC EVALUATION
Page 7-96, 7.4.1 General
Same comment as for page 6-9, Relative Economic Project.
9. CONCLUSIONS AND RECOMMENDATIONS
9.1.4 Evaluation of EnerQY Plans
Page 9-7,9.1.4.4 Hydroelectric Power
We believe the Newhalen diversion projects may result in severe rather
than moderate fi sheri es impacts, especi a 11y the regi ana 1 concept.
9.2 RECOMMENDATIONS
I f the Power Authori ty accepts the SWEC recommenda t i on to conti nue
evaluation both Tazimina and Newhalen regional concepts, we suggest the
following fisheries studies be conducted:
Tazimina River
8-48
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
lit
... -
-
...
...
-
1.
12
Install and operate a salmon counting station as close to the
mouth of Tazimina River as practical to determine the magnitude of
annual adult sockeye escapements entering the river. This project
should be operated for at least four years (1982-1985) and
possibly longer. Data collected here can be compared to Kvichak
River salmon counts to determine the percentage of the Kvichak
escapement that returns to Tazimina River. It can also be related
to aerial index surveys of Tazimina River to determine how
descriptive aerial surveys are of the total Tazimina escapement.
Further, it will also be useful in evaluating escapement magnitude
versus spawner distribution and density by river area.
2. Continue the aerial index survey presently conducted by F.R.I. of
Tazim;na River. This project should continue for at least the
years 1982-1985. The data generated will be compared to Tazimina
River tower counts which will give a measure of aerial survey
index efficiency in describing the total Tazim;na River
escapement. This relationship could then be applied to previous
year1s aerial index surveys and will tighten our understanding of
previous years Tazimina River sockeye spawning populations.
3. Conduct continued on-site sockeye spawning distribution studies in
Tazimina River over the above four year period (1982-1985). This
data will tell us whether in years of larger escapements sockeye
utilize greater portions of the river, sloughs, and side channels
for spawning or simply concentrate more heavily in areas preferred
at lower densities. If they use additional more marginal areas it
8-49
13
wi 11 be important to document these and evaluate them agai nst
proposed post project flow regimes.
4. Conduct a fry outmigration study yielding estimates of total
sockeye fry produced in Tazimina River by brood year for the years
1982-1985. This information will be related back to parent
spawning escapements, spawning di stributi on data t and river flow
parameters and will assist in determining the optimum escapement
levels for Tazimina River.
5. Conduct a study of over winter sockeye egg survival in selected
areas of Ta~'imina River with emphasis on spawning. areas presently
being naturally surface dewatered during low winter flows. This
will tell us if these particular areas. are presently contributing
to fry producti on uti 1 i zi ng sub-surface perco 1 a ti on and whether
augmented wi nter flows mi ght provi de greater egg-to-fry survival
in some spawning areas·.
6. Complete an instream flow analysis of Tazimina River. The flow
data from such a study will be compared to data regarding sockeye
spawner distribution, egg sur/ival, critical habitat for resident
species, fry emergence, migration timing, etc. to provide insight
into possible post project fisheries effects.
7. A year-round study of resident fish species inhabiting Tazimina
River should be completed. Its goals should include:
8-50
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
•
!fill ..
..
-
-
,...
-
-
14
a. The "identification of resident fish spawning areas.
b • Identification of the timing of resident fish spawning.
c. Identify migration patterns and timing by species.
d. Document fry emergence timing by species.
e. 'Oocument instream rearing habitat requirements by species.
Thi s data wi 11 reveal what months of the year resi dent fi sh
species inhabit the river and where their important spawning and
rearing areas are. It will also indicate what time periods are
critical for spawning, incubation, emergence, and migration •
These data can be used to evaluate proposed post project effects
on resident species.
8. An aquatic invertebrate species distribution study in Tazimina
River should be completed. Species present should be identified
and their preferred habitat described for future use in
forecasting potential post project flow impacts on important fish
food organisms.
If the above studies are constructed, a reasonably complete
understanding of the Tazimina River fishery will be available and
potential impact forecasts will be possible and based on fact
instead of supposition.
8-51
15
Newha 1 en River
1. A salmon counting station should be installed in the vicinity of
the upper end of the Newhalen River "rapids l
•• It should be
operated beginning in 1982 and continuing at least through 1985 to
determine the number of adult sockeye salmon migrating up the
Newhalen River.
This information when compared to similar data collected annually
at Igiugig on the Kvichak River will allow us to determine what
percentage of the Kvi chak escapement is contri buted by the Lake
Clark-Newhalen River system. It will also be used to relate
Newha 1 en Ri ver sockeye fry and smo 1 t outmi grati ons back to thei r
parent brood years providing information on production rates and
optimum escapements.
2. A complete Newhalen River juvenile sockeye salmon downstream
migration study covering at least the years 1982-1985 will have to
be conducted. It should include the following elements:
a. A total annual outmigration estimate of both sockeye trJ and
smelt by time period for the Newhalen River.
b. A study of the outmigration distribution characteristics that
defi nes sockeye fry and smo 1 t mi gra ti ona 1 tendenci es across
the river water col umn 1 atera l1y and throughout the water
column vertically.
8-52
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
• ..
..
l ..
16
c. A winter sampling program as part of element "all (above) to
determi ne whether sockeye fry and pre-smo 1 t juveni 1 es
outmigrate down the Newhalen River during the ice forming
periods of the year and if so what the magnitudes of these
migrations are.
These study elements regarding downstream migration of
juvenile sockeye salmon are very important to the assessment
of any proposed Newhalen River power projects. The data
gathered wi11 indicate what time periods are critical in
terms of juvenile downstream migrations and whether
migrations occur during the winter months when channel
screening devices might not be usable due to ice problems.
We will also have information as to where in the Newhalen
River water column these fish move (near shore, mid channel,
etc.) and at what depths they travel. This will be helpful
in the evaluation of potential intake sites, designs, and
f10w strategies with the object being minimizing fish entry_
The studies will also provide total sockeye fry and smolt
outmigration estimates which will be important in:
a. Assessing the Lake Clark runs' contribut·;on to the
Kvichak run.
b. Determining characteristics of the Lake Clark cycle •
c. Evaluating Lake Clark escapement requirements.
8-53
17
d. Determine economic value of the Lake Clark-Newhalen
sockeye runs.
e. Evaluating post project impacts on the run.
f. Assessing potential mitigation scenarious.
g. Determining cost-benefit ratios.
h. Evaluating impacts of natural environmental fluctuations
such as the occasional velocity barrier problems in
Newhalen River.
Additional data on resident Newhalen River fish species
movements will also be gathered during the above studies.
The two year old smolts produced from the large 1979
escapement to Lake Cl ark shou 1 d be outmi gra t; ng du ri ng the
late spring 1982. We suspect the earliest date that a full
complement of gear could be assembled to adequately monitor
the total outmigration numbers over a full year would be in
early 1983. We envision this program employing gear such as
a full set of sonar arrays (for use in determining total
outmigration estimates) fyke nets, fyke traps, incline plane
traps, minnow traps, seines, and possibly electrO-fishing
apparatus (for determining species distribution and winter
migration occurrence).
8-54
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
...
18
3. The Newhalen River flow monitoring program· should be
continued indefinitely.
4. A small bankside study channel should be constructed and full
array of fi sh screeni ng devi ces tested under actual flow
conditions similar to what would exist in any proposed
diversions. The study should include winter as well as
summer testing to identify the devices that prove to be most
efficient in preventing fish entry into the channel at
varying flows, velocities, depths, and in spite of problems
such as ice, debris, a buildup of salmon carcasses, etc.
5. A winter study of the "rapids l' area itsel f should be
i. conducted duri ng the wi nter low flow peri od to determi ne what
,.
!
.... ..
if any resident species reside there at that time. These
might be the fish most impacted by the proposed diversion
during the winter months.
8-55
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Mr. Richard Logan, Director
Habitat Division
State of Alaska
Department of Fish & Game
Office of the Commissioner
P.O. Box 3-2000
Juneau, Alaska 99802
Dear Mr. Logan:
August 4, 1982
Phone: (907) 277·7641
(907) 276-0001
The Alaska Power Authority has reviewed your letter of April 28,
1982, and the attached specific comments by the Department of Fish and
Game on the draft Interim Feasibility Assessment of the Bristol Bay
Regional Power Plan. We are aware of the difficulties the Department
faces in establishing policies which both protect fish and game and
accommodate the need to develop lower cost electrical power in the
Bristol Bay Region. We also appreciate the willingness of the Depart-
ment to work with the Power Authority in evaluating various power
generation alternatives.
Several comments follow with respect to statements made in your
1 etter:
1. We are aware of the impacts from dams on the Columbia River, and we
share your concern about avoiding similar problems in major salmon
producing drainages in Bristol Bay. There are, however, signifi-
cant differences between hydroelectric projects on the Columbia
which employ dams across the river and the concepts being evaluated
for the Taz;mina and Newhalen Rivers. These differences include:
a. The Tazimina development would not provide a barrier to
salmon migration because of the presence of the falls
directly above the powerhouse location.
b. The Tazimina "run-of-river" concept has no dam and is
unlikely to cause any of the adverse impacts cited.
c. The Newhalen diversion concept has no dam. Exclusion of
migrants from the diversion canal ;s believed to be the
major fisheries concern.
8-56
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
.. •
Richard Logan
August 4, 1982
Page 2
2. We agree that it would be imprudent to construct dams or any other
type of power system in Bristol Bay which would degrade the
region1s socioeconomic structure. We do not believe that a judg-
ment should be made on the socioeconomic effects of a specific
project, including one involving a dam, prior to evaluating both
its costs and benefits. Obviously cultural values and preferences
of the inhabitants are important factors to be considered.
3. We believe the Interim Feasibility Assessment has considered all
electrical power supply alternatives that are likely to be attrac-
tive for the region. Further evaluation is planned only for those
alternatives (other than the Base Plan) which appear to offer the
best possibility of lower cost electricity and are environmentally
acceptable. Unfortunately, we found no attractive dam sites on
non-salmon producing streams, and coal-fired power plants, or
transmission lines from other dams do not appear to offer the best
possibilities in Bristol Bay.
4. The cost of fuel oil for diesel electric generation was based on
prices recently paid for delivery to various specific villages in
Bristol Bay. Because transportation costs are a significant
factor, temporary declines in world oil prices do not result in
proportional reductions in costs to the consumer. We intend to
assess the effect of world oil price changes on Bristol Bay and
revise the economic evaluation, if appropriate, in Phase II.
With respect to your specific comments, we offer the following
clarifications:
General:
6. DEVELOPMENT OF ENERGY PLANS 6.1.2. Assessment of Energy Sources
Page 6-9, Relative Project Economics
The Power Authority does not intend to support projects which would
adversely impact significant fisheries resources and does not
intend to promote such projects. Minor fisheries impacts would be
offset by appropriate mitigation measures resulting in "no net
fisheries losses." Therefore, an analysis of the total worth of
the fishery resource is unnecessary.
7. EVALUATION OF SELECTED ENERGY PLANS 7.2.3. Reliability
Page 7-3, para. 1
We are aware of the problems associated with icing of screened
intakes. A critical piece of data required in evaluating this
potential problem will be the timing of late fall and early spring
fry and smo1t outmigrations with respect to the onset of winter
icing conditions.
8-57
Richard Logan
August 4, 1982
Page 3
Various Energy Plans:
1. Base Plan - A concept involving several subregional developments
WTTTbeiPresented in the final Interim Feasibility Assessment
report. Some subregions would essentially follow the Base Plan
development scenario.
2. Scenario B-1 -The Beluga transmission line scenario is being
re-evaluatea and a revised analysis will be presented.
3. Scenarios B-2, B-3, and B-14
Page 6-23, 6-24, and 6-29 -Studies are underway to define
Newhalen smolt and fry migration, and methods are being evaluated
to divert fish from entering the power canal. Furthermore, studies
will be initiated to determine which flows would be considered
minimally acceptable to sustain existing fisheries in the Phase II
study program, should a decision be made to pursue this alterna-
tive.
The Kukaklek alternative does not appear to be economically attrac-
tive and it is doubtful that any additional work will be conducted
on this alternative in the future.
Chikuminuk will be re-evaluated as a larger project to serve both
the Bethel Area and Bristol Bay as part of another concurrent
study. Your comments will be considered in future analyses of this
alternative.
4. The description of Scenario 6-5 appears in Section 6.2.4.5, incor-
rectly labeled as Scenario B-4. The description of Scenario B-4
was omitted. This will be corrected in the final report.
The other specific comments will be considered as we update the
report and as we undertake further environmental assessment of selected
scenarios in the next phase of the study.
Over the past few months Fish and Game personnel have participated,
along with other agencies, in a number of meetings and workshops that
addressed the development of a power plan for the Bristol 8ay Region.
Your specific comments were discussed at a meeting in Anchorage on May
11, 1982, attended by personnel from Fish and Game, Fish and Wildlife
Service, the Power Authority, and Stone & Webster Engineering Corpor-
ation and their environmental consultants. The results of this meeting
were very helpful in planning near-term environmental studies.
8-58
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
.. -..
..
II
..
-
II
-
Richard Logan
August 4, 1982
Page 4
Your suggestions for fisheries studies in conjunction with the
Tazimina and Newhalen regional concepts are, of course, well beyond what
can be accommodated by current project funding. In our opinion, their
scope and duration exceeds that appropriate to this preliminary
feasibility level investigation. After completing an analysis of the
Chikuminuk Interregional Project, we expect to have sufficient
information to determine the apparent preferred alternative and proceed
with more detailed fisheries studies of that alternative. There may be
opportunity for cost-effective cooperation between the Department of
Fish and Game in future detailed fisheries studies undertaken by the
Power Authority on the preferred alternative. We would welcome the
opportunity to explore such opportunities.
Thank you for your extensive review. We look forward to continued
cooperation in developing the Bristol Bay Regional Power Plan •
cc: Commissioner Skoog
Carl Yanagawa
~e~elY'y. ~
Eric P. Yould ~
Executive Director
8-59
!1ay 13, 1982
File No. 1130-13
Mr. E.P. Yould
Executive Director
~, Power Authority
334 W. 5th Avenue
Anchorage, .~ 99501
DIVISION OF PA1fICS
Subject: Draft-Bristol Bay Regional Power Plan.
Dear M:. Yould:
•
JAY S. HAMMONO, GOVERNOR
619 WAREHOUSE DR •• SUITE 210
ANCHORAGE. I4L.ASKA 99501
PHONE: 274-4616
BECEl,Veo.
MAY 2 0 1982
Al.AsKA POWER AUTH0RI7Y.
We. have reviewed the subject proposal and would like to offer the
following comments:
STATE HISTORIC PRESERVATION OFFICER
We are concerned that significant cultural resources will likely be
impacted by the proposed project. In order for the Alaska Power
Authority to llI.eet it's responsibilities. per 36 cn 800, cultur.al re-
sources conce~s llI.USt be addressed under consultation w~:h the State
Historic Preservation Officer. Following the Power Authority's decision
as to which alternative energy plan to study. subsequent reports should
include consideration of the illI.pact of the sed projects . on
cultural resources. /'
'----+---:?"----:f1i':'tJ':-----<--__
Officer
STATE PARK. l."I..A..'lNING
No comment.
LAI.'ID Ii ~JAT!R CONSERVATION i:lJND GRA.:."IT PROGRAM
No comment.
Sincerely,
-~~~~ ~~-' ",anial Rob ins on
!)R/blh
8-60
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
...
,.
j ...
..
I
MIl
-
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Ms. Judy Marquez
Director
State of Alaska
Department of Natural Resources
Division of Parks
619 Warehouse Drive
Suite 210
Anchorage, Alaska 99501
Dear Ms. Marquez:
August 2, 1982
Phone: (907) 277·7641
(907) 276·0001
Thank you for the comments in Mr. Ty Dilliplane's letter of'May 13,
1982 regarding significant cultural resources in connection with the
Bristol Bay Regional Power Plan. Following a decision on which alterna-
tive energy plan will be studied in more detail, we will consult with
the State Historic Preservation office regarding project concerns.
We appreciate your continued interest in the project.
Sincerely,
p~. Dc., )~(j
¥ Robert Mohn
Director of Engineering
8-61
8.2.5 Summary of Significant EVents
Table 8.2.3 is a chronological listing of
upon the course of the Phase I study effort.
8-62
events which have had an impact
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I J 11
TABLE 8.2-1
Comments and Questions from Selltemher and October Community ~Ieetlngs
Bristol Hay Regional Power Plan
---.-----------------------
VILLAGE
~
CATEGORY u 3: ~ a .8 &::: ! -rt ... ! ..101 ~ 0 u I!S ~ -rt p.. ~ til
bIl till U til g ." !i ." ] .:l tJI) u ~ U) .a I!S ..!II U) till III rl 0 k ..101 u ! "rf .a tJI)
.--J .. S ." ] k t .--J ~ ..-f :;! d 0 t2 ." t:'I W p.. Z Z
ENVIRONMENTAL CONCERNS
Fish & Wildlife in General 1 1 4
Fish Production/Catch 1 1
Fisb Spawning Grounds 1 1 3
Flsb Species 1n Tazimina Lake 1
Impact (of Plant) on Tazimina River 2 2
Fish Ladders 1 1
Fish Cycle 1 1
Impact of Dam on Kukaklek Lake Outlet
Temperature Changes 1
Kukaklek Diversion
Impact of Penstock
Gas Intusiol1 1
Effect of Dams on Other Rivers 3
Subsistence Fishing & lIunting 1
Long-Term Effects of Jlydro
Total
(". 1
~
III ~ &::: ..101 e 0 Z cJ till ." U
..101 0 -rt .~ ';;I .--J .r. "rf .--J bII ." .--J u bII til :l 'S 'U lIS :l III t "rf P u
0 till bII rl III 0 0
U) W ...:t H H Z Z f-t
1 2 2 10
2
6
2 3
1 5
2
2
1 1
1 2
3 2 5
2 2
1
3
1
1 1
46
I 1 ( I f 1 I I
TABLE 8.2-1 (Cant)
Comments and QuestIons [rolll September and October Community tleetings
UrlBtol 8ay RegIonal Power Plan
VILLAGE
~
CATEGOI~Y
.., CII ~ t:S III ,g tl J ..... ... ~ ~ ..!.I 0 U III ..!.I ..... III p.. '"' Q/
Il«I bIl .., III ::J g ~ III .s JJ Il«I .., ..!.I II) .e III ~ II) Il«I III ..-t 0 ... ~ u i ..... .e ClO ..... \II S III .a ... ~ ..-t ~ ..... '~ ..... 0 t2 III Q U Id p.. W Z Z
------
PROJECT DESIGN. CONSTRUCTION & OPERATION
Hydroelectric Concepts in General
Local vs. Regional Hydr.o I
Hydro with Regulation I
Run-oE-River Hydro 1
Back-up/Standby I 1
Dams 1 3
Diversion of Flow
Penstock in General
Size of Penstock 3
Cost of Penstock 1
Construction of Penstock 2
Fluctuation of Water Levels
Energy Supply/Allotment 3 I 1 2
How Much Flow for Run-of-River?
Generator Size
Power From Tazimina 1
Effects of Ice
Improvement of Local System for Tie-In I
River Flows-Adequate for. Spawning 1
Present Diesel Capacity 1
Effect of 30~M on Lower. L. Tazimina 1
Electrical Demand Fluctuation 1
Other Hydro 1n Alaska 1
New System Similar to Local Power Grid I
Total
r 1 II
..!.I
III .e tl III ..!.I tl 0
I"': tJ 00 III III u
..!.I 0 ..... H ~ ..-t .r. ..... ..-t ClO III ..-t u ClO \II ::J .a::: v III ::J \II t ..... ..... ~ tl ..,
0 Il«I ClO ..-t 0 0 II) W ..:l H H Z Z f-I
-----'
I I
I
1
1 2
2
3 1 8
I 1
I 4
1
2
1 1
7
1 I
1 I
I
1 I
1
I
I
I
1
I
I
42
r 1 1'1 1'1 "I r 1 .,
TABLE 8.2-1 (Cont)
COlDments and Questions from September and October ComlDun:lty tteetlngs
Bristol Bay Regional Power Plan
------~~-'-------------'-------~-------
VILLAGE
CATEGORY ~
!oJ II ~
~ !I II 0 Q .... .r:l ] ~ ~ 0 u '" ~ ...... '" Po ~ II bIl bIl !oJ II ::J fa '" !i '" 1l III bIl !oJ ~ tI)
11 ~ '" ~ tI) bIl II
rl 0 .... ~ !oJ j ...... 11 tl(l
rl II S '" a .... t .... ~ ...... :;f ..... 0 t2 ~ A U Po td ~
TRANSmSSlON LINES & SUBSTATIONS
Transmission Lines in General 1
Line Sizing 1 1
Construction 1
Length 1
Distribution Systems 1
Right-Of-Way 2 4 1
Maintenance 1 1 1
Line Loss 1
River Crossings
Feeder Lines
SuBstations in General 1
Size of Substation
Who Operates Substation
Total
f I I 1
~
II
Ji Q '" ..!oI ~ 0 z () bIl '" !oJ
..!cI 0 "M I .... ....
.r:l ...... .... tl(l ~ '" ....
!oJ tl(l II .;.I "d III ::J II t .... ~ P !oJ
0 bIl bIl rl 0 0
tI) lsi ..... H H Z Z H
2
2 4
1 2 5
1
1
1 8
3 7
1 2
2 2
5 5
1 2
1 1
1 1
41
f I £ "I
TABLE 8.2-1 (Cont)
Comments and Questions [rom September alld October Community tleetings
nristol 8ay RegIonal Power Plan
------------------.---------~----
VILLAGE
CATEGORY .!J4
t.J IV .!J4
J .!l IV 0 j ... .c
.!J4 .!J4 0 u t'II .!J4 -ri t'II "" Ei IV
tJO tJO u
.!l J IV ~ t'II .e .tl tJO u .!J4 Ul
t'II .!J4 Ul 00 IV .-t 0 tJ .!J4 t.J ~ ~ Jl tJO
.-t IV ~ a ... ~ .-t ~ ~ :;f .-t 0 e2 t'II t:l u "" w z z
ALTERNATIVES
Local VB. Regional Development 2 1 1 1
Criteria 1
Alternative Energy in General 1 1 2
Hydro Other Than Tazimina 1 3
Geothermal 1 3
Wind 1
Need for Alternative Power 1 1
Natural Gas 1
Coal 1
Intertie With Susitna Project 1
Total
1:'1 £ 1 '"1
.!J4
J s:J ~ .!J4 ~ 0
0 00 g u
.!J4 0 -ri ~ .-t .r. .... .-t tJO t'II .-t
t.J tJO IV .;: g t'II ::t IV t ~ ~ u
0 00 00 .-t 0
Ul W ..l H H Z Z 1-4
5
1
4
2 1 5 12
4
1
2
1
1
1
32
( I (1 r I I I ["cl
TABLE 8.2-1 (Cont)
Comments and Questions from September and October Community tfeetinr,s
BrIstol Ray Regional Power Plan
---------~------.-.~----------.------------------------
VILLAGE
CATI~GORY ..!<I
4.J III ..!<I ;J II 0 Jl
=
... ~ ~ ..!<I ..!<I 0 U 111 ..!<I ~ ~ 111 /1.0 ~ II
bO Ill! U GI ~ ;J 111 .s XA bO U ..!<I (I)
JJ 111 ..!<I (I) Ill! GI r-I j ... ..!<I u
A
~ JJ bO r-I II 111 .a ... ~ r-I ~ ~ :;;;! d 0 ~ ~ 0 Jd /1.0 Z
ROADS & ACCESS
Right-or-Way 2 " 1
Roads in General 1 1 1
Ancillary to Transmission 1 2 1
Network 1
Permafrost 1
Land Status 1 1
Total
..!<I
II
JJ Jl 111 .Yo ~ 0 Z U Ill! 111 U ..!<I 0 "ri B ~ r-I
~ ~ r-I !:>O .~ 111 r-I
U !:>O II :;j '3 111 ;:1 GI ~ ... 1 ~ a u
0 bO bO ~ III 0 0
ttJ Jd ..... H H Z Z H
1 8
1 1 5
1 5
1
1
1 3
23
f 1
TABLE 8.2-1 (Cont)
Comments and Questions from Septemher and October Community t1eetJngs
Bristol Ray Regional Power Plan
11
-----------------------------------
VILLAGE
CATEGORY
~ .u GI ~ ~
J s:1 GI .8 J:l GI
.l<I
.... ... ! 11 .l<I 0 u III ~ J:l .... III Ilo ~ GI III ~ bO bO tJ GI ~ t1 0
!l III ] .:I bO ~ III Z (J tID III GI u .u \'J) ~ 0 .,.4 ! .-t .-t li III ~ \'J) tID GI .c: .... .... tID III III .-t .... g ... ~ tJ ! ..-t .fI tID .u 00 GI :::I .d "d :.1 GI III .a ... ~ .... ~ :::I GI ~ III
:;! ~ d 0
.... ~ s:1 .u
Q ~ ~ 0 00 tID ..-t 0 0 Cal Ilo Z \'J) Cal H H Z Z f-t
COST
Cost in General 1 1
Analysis of Project 1 1 2
Tazimina FacUity 1 1
Transmission 1 1
To Consumer 3 3 1 1 1 9
Return on Investment 1 1 2
State Assistance 1 I
Subsidy on Petroleum Products 1 1
Surplus Diesel At Naknek 2 2
Total
2()"
r 1
r 1 I"""" r""'l
TABLE 8.2-1 (Cont)
Comments and Questions from Septemher and October Community Heetings
Bristol Bay Regional Power Plan
VILLAGE
CATEGORY .lII
'-' \II .lII
~ !t \II 0 ~ ~ .c: 0 .lII .lII 0 u lit .lII ~ ..-t lit p.. I>-. \II
bO bO '-' \II ::J ~ lit !t B 0 JJ bO '-' .lII II)
.lII lit .lII II) bO \II r-I 0 ~ .lII ... 0 ..-t Jl bO
r-I \II 'p 111 .a ~ ~ ~ r-I ~ • ..! :;! ::! d 0 ~ ~ Q w p.. z
INSTITUTIONAL & REGULATORY CONCERNS
Concerns of Agency People 1
Who Will Operate System?
Exclusion of Pedro Bay
Centralized Power 1
Licensing 1 2
Who Would Own Plant?
Who Would Sell Electricity? 2
Impounded Lands
Need for Ancillary Facilities
Who Initiated Study
EIS Necessary
Chance of Fund. Many Projects? 1
Legislation Funding Distribution 1
Total
r' 1
-101
\II .e ~ lit .lII P 0
Z I.J tlO lit \II '-' .lII 0 ..-t S r-I r-I .c: • ..! r-I bfI lit 111 r-I
'-' bO \II ::J .c: 'tI 111 ::J \II t ..-t ..-t ~ P '-' 0 bO bO r-I 0 0 II) Jol t-l H H Z Z H
,------
1
1 1
2 2
1 2
3
1 1
2
1 1
1 1
1 1
1 1
1
1
18
F'I
TABLE 8.2-1 (Cant)
Comments and Questions from September and October Community tleetings
HrlstoJ Day Regional Power PJan
... ,
.--------------------------~------------.. -----------.-..
VILLAGE
CATEGORY ~
t-J CII ~ .!II .!l CII ~ c:: CII ~ ~ 0 11 ~ ~ 0 U III ~ .!t c:: ..... III p., I>-CII III .!II tl 0 bO bO U CII ::t tl lit Z U bO III CII u c:: III .fJ UI bO U III ~ III oM 0 ..... ~ r-t r-t ..... Jl .!II III ~ III bO CII ..t: "rl .-i bO III lit r-t .--t 0 ~ ~ t-J 0 ..... Jl bO t-J bO CII ::t ~ "tj lit .--t CII ~ lit .a J..o ~ ~ .--t ~ ::J CII ~ ..... "rl c:: u ..... ;! .--t 0 ~ III 0 bO bO .-1 0 0 0 u w p., w z Z III ILl H H H Z Z f-'
COHHUNICATION ABOUT PROJECT
Communications about Project 1 1 1 1 4
Language Problems 1 1
Notices about meetings 1 1 2
Technical Language 1 1 2
Opinions o£ Other Villages 1 1 1 3
Opinions o£ Other Agencies 1 1 2
Opinions o£ Other UtiHties 1 1
Total 15
TABLE 8.2-1 (Cont)
Comlllents and Questions from September and October COlnlRunity Meetings
Ur lstol nay Regional Power l'ian
CATEGORY
PROJECT BENEFITS
Energy Supply/Allotment
Participation in Project
Hydro Electric for Heating
Manpower Requirement for Tazimina
Total
!
00
~
M
M ....
~
3
1
~ ....
00
J
III
~
1
~
nj
u
JJ
0 ~
1
1
u
tt ....
0
P.
VI
..!.II ... ~
--~ d
VILLAGE
..!.II
III ~
III 0 tl ... ..c: ! u --~
I>-> III
III =' e nj
00 U ~ Ul
nj ..!.II Ul 00 III ... 0 .... 1l 00 ... ~ t M ~ 0 t2 --p. w z z
2
~
III
1l
--
~ z 0 00
~ 0 .... ..c: .... M 00 u 00 III =' :t III ~ ....
0 00 00
Ul W t-l H
nj
M ....
M H
c::
III
M
nj ..c: ~
Z
1
1
c::
0
I" M
nj
"tl
tl
0
Z
.-1
nj
\oJ
0
H
7
2
1
1
11
£1 r''I ~''''I "'~'1
TABLE 8.2-1 (Cont)
Comments and Questions [rom Sept(>lIIher and October Community tleetings
Bristol Bay Regional I'ower Plan
VILLAGE
CATEGORY ~ .., ., ~ ~ ., ,g p
! ... ~ ~ ~ 0 u 111 .!II .... 111 f1t J;>-, .,
bO bO .., ., ::J ~ !i 111 ] JJ bO 0 .!II l/)
Jj 111 .!II l/) bO .,
..-f 0 ... .!II .., 0 .... Jl bO
:;I QI ~ 111 .a ... .a ~ ..-f ~ :;J ..-f 0 ~ 111 Q U ld f1t ld Z Z
STATUS OF PREVIOUS STUDU:S
Previous S~udies in General 1
Retherford Study 1
Lake Elva Study 1
Grant Lake Study 2
Why Study Not 40 Years Ago 1
Total
r, '1
~ .,
Jl Jj
111 .!II t1 0 Z U bO 111 ., ..,
~ 0 .~ g r-I r-I .t: ..-f bO 111 111 r-I .., bO ., ~ i -a III ::J QI t .... R ..,
0 bO bII rl QI 0 0 l/) ld H H H Z Z ....
2
1 2
1
2
1
8
TABLE 8.2-1 (Cont)
Comments and Questions from September and October Community Meetings
Bristol Bay Regional Power Plan
CATEGORY
STUDY APPROACH
Interim Assessment
Demand Forecast
Adequate Time to Study Tazimina Flows
When Will Study End
What is Definition of Feasibility Report
Total
J
CIO ~ .....
;1
A
I
u ~
..14 ~ 0 ..... Po tID U
i .9 ]
0 a ..14 j a :;I
VILLAGE
..14
II .!oil II 0 j lj -; ..14 t; .. .. ~ tID U ..14 Ul
1\1 .!oC (J) CIO j u ~ ..... tID ~ t ..... a 0 t2 Po l24
..14
II
! ..14
U tID
~ 0 .....
.Q ..... tID
U CIO .. .:l ::t II t 0 tID tID
Ul JI.I o-l H
I
i ..... .....
H
ti
j
l24
2
I
I
g
u .....
1\1
'3 0
l24
.....
1\1 u
0
f--4
2
I
1
I
.1
6
,..
-
-
..
TABLE 8.2-2
PUBLIC/COMMUNITY MEETINGS
Location
Nondalton
Dillingham
Clarks Point
Aleknagik
Ekuk
Manokotak
Portage Creek
New Stuyahok (including Ekwok)
Koliganek
Newhalen (including Iliamna and Nondalton)
Igiugig
Levelock
Naknek (including King Salmon)
South Naknek
Egegik
Iliamna (including Newhalen and Nondalton)
Dates
Fall Series Spring Series
7/22/81
9/23/81
9/24/81
9/24/81
9/24/81
9/25/81
9/25/81
9/25/81
9/26/81
10/17/81
10/19/81
10/19/81
10/19/81
10/20/81
10/20/81
3/5/82
3/9/82
3/9/82
3/9/82
3/10/82
3/10/82
3/8/82
1M
-•
TABLE 8.2-3
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Study Awarded
SWEC meeting w/APA regarding definition of scope and
agency contacts
Agency information meeting at D&M office in Anchorage
regarding study effort
Work Plan finalized
First field trip to Bristol Bay region by members of
Study Team -visit with local people
7/21-23/81Meeting w/Nondalton people by APA and SWEC
Meeting w/NPS -Lake Clark National Park & Preserve
personnel (Port Alsworth)
Meeting w/BBNA (Dillingham) by APA and SWEC
Meeting w/Nushagak Electric Cooperative
(Dillingham) by APA and SWEC
Meeting w/Naknek Electric Association (Naknek) by APA & SWEC
Special Use Permit Issued by NPS to APA for Tazimina
field work
Meeting w/Nondalton people by D&M regarding land use
permit for field work at Tazimina
Press Release-describing course of study (KDLG radio -
Dillingham)
Letter sent to SWEC from BBNC regarding identification of
presidents of ANCSA Village Corporations
Letter sent to SWEC from BBNC regarding potential Indian
allotment conflicts in Tazimina area
SWEC meeting w/APA regarding agency contacts
Date
7 f7 /81
7/8/81
7/13/81
7/13/81
7/22/81
7/22/81
7/23/81
7/23/81
7/23/81
7/23/81
7/24/81
7/24/81
7/29/81
8/3/81
8/4/81
-
..
I
t
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Letters of invitation sent to agencies (federal and state)
regarding agency information meeting in Anchorage
Federal Register notice of land selection
by Nondalton (Tazimina Lake outlet area)
Telcon w/ADF&G regarding location of Kukaklek Lake in Katmai
National Park and preserve
Agency meeting w/Study Team in Anchorage
Telcon w/ADFG regarding identification of important
salmon rivers in Bristol Bay region
SWEC meeting w/Alaska Department of Commerce and Economic
Development regarding study description
SWEC meeting w/ADFG regarding data availability
for sockeye salmon in Bristol Bay
Bristol Bay Cooperative Management Plan workshop
in Dillingham
Letters sent to all interested agencies not invited to
agency meeting 8/17
Letters sent to all villages, native groups, etc. from
BBNC regarding BBRPP study efforts and announcements of
village meetings
Meeting w/NEC (Dillingham) on system loads, demands, etc.
Meeting w/NEA (Naknek) on system loads, demands, etc.
Meeting w/ADFG (King Salmon) personnel regarding potential
hydroelectric sites in Bristol Bay region
Meeting w/ADFG (Dillingham) personnel regarding potential
hydroelectric sites in Bristol Bay region
Date
8/11/81
8/12/81
8/12/81
8/19/81
8/20/81
8/20/81
8/21/81
8/26/81
8/31/81
9/1/81
9/2/81
9/2/81
9/2/81
9/2/81
, •
I
t
r
II.
-
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Letters from BBNS sent to Native group leaders in
Bristol Bay regarding study effort and community meeting
announcements
News release regarding Community meetings of 9/23 to 9/25
(Bristol Bay Times and KDLG Radio)
Hunting season ends in Nushagak River region
First Project Report issued
Study Team Meeting (Anchorage)
Agency Information Meeting -Anchorage
D&M Meeting w/ADFG (King Salmon) regarding adequate field study
time for Tazimina
Community Meeting in Dillingham
Community Meeting in Aleknagik
Village Meeting in Clarks Point
Village Meeting in Ekuk
Telcon w/NPS regarding uses and restrictions
within National Parks in Alaska
Community Meeting in New Stuyahok (Ekwok included)
Community Meeting in Manokotak
Village Meeting in Portage Creek
Village Meeting in Koliganek
Hunting season ends in Kvichak River region
Letter sent to all villages and native groups in Bristol Bay
regarding invitations to community meetings and
solicitation of comments about study
USFWS letter to APA regarding hydroelectric projects in Alaska
Date
9/3/81
9/3/81
9/15/81
9/16/81
9/16/81
9/17/81
9/23/81
9/23/81
9/24/81
9/24/81
9/24/81
9/24/81
9/25/81
9/25/81
9/25/81
9/26/81
9/30/81
10/2/81
10/2/81
! ..
I ..
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Telcon to D&M from USFWS regarding concern for level of
treatment for alternate sites
ADNR letter sent to APA regarding historic sites and state parks
News release (by BBNC) of Community meetings for
10/17 to 10/21 (Bristol Bay Times)
Letter sent to Alaska Land Use Council from BBNC regarding
BBRPP and community meetings
Letter sent to NPS (Lake Clark Nat'l Park) and other agencies
regarding specific concerns on Tazimina project and
invitations to community meetings
Letter from APA sent to agencies regarding agency information
meeting to take place on 10/21 in Anchorage
Letter from APA sent to SWEC regarding distribution list
for monthly Project Reports
ISER meeting w/Rural CAP regarding Community Energy Profiles
Letter from ADNR (Div. of Parks) sent to SWEC regarding
comments and concerns on potential hydroelectric sites
for the Bristol Bay region
Second Project Report issued
Community Meeting in Newhalen regarding progress of
study effort (Iliamna and Nondalton included)
Community Meeting in Igiugig regarding progress of
study effort
Community Meeting in Levelock regarding progress of
study effort
Community Meeting in Naknek regarding progress of
study effort (King Salmon included)
Date
10/5/81
10/7 /81
10/7 /81
10/8/81
10/9/81
10/9/81
10/12/81
10/14/81
10/15/81
10/15/81
10/17/81
10/19/81
10/19/81
10/19/81
fIIIIII
I -
-
TABLE 8.2-3 (cont)
CHRONOLOGICAL'LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Community Meeting in South Naknek regarding progress
of study ef fort
Community Meeting in Egegik regarding progress
of study effort
Agency Information Meeting with Study team in Anchorage
Telcon from ISER to DEPD regarding Power cost assistance
program
Letter from ADNR Division of Lands sent to SWEC regarding
comment on potential hydroelectric sites in
Bristol Bay region
Telcon from USFWS regarding comments on potential
hydroelectric sites and the Study team's approach to
alternative energy plans
Letter sent by SWEC to USFWS regarding alternative
studies of BBRPP
Notice in Federal Register regarding BBCMP intent
to prepare on EIS
News release by ISER in Dillingham for BBRPP study (KDLG radio)
ISER meeting w/Bristol Bay planners (ADTPF)
Letters from APA sent to all agencies regarding
invitation to agency information meeting on 11/17
Informal Meeting in Dillingham by ISER regarding general
economy and effects of changing energy demands in region
Te1econ from Igiugig representative to BBNC regarding no
installation of stream gage at Kukaklek
Letter from ADFG sent to SWEC regarding comments on potential
hydroelectric sites in Bristol Bay region
Date
10/19/81
10/20/81
10/21/81
10/22/81
10/23/81
10/23/81
10/27/81
10/29/81
10/30/81
10/30/81
11/2/81
11/2/81
11/2/81
11/3/81
..
..
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Telcon w/ ADNR and SWEC regarding status of oil and gas
resources in Bristol Bay region
Letter sent to SWEC from USFWS regarding comments on alternate
hydroelectric sites in Bristol Bay region
Letter sent to APA from USFWS regarding comments on alternate
hydroelectric sites Bristol Bay region
Press release to Denver Post by SWEC regarding BBRPP study
contract to SWEC from APA
Telcon w/ISER (University of Alaska) regarding peat resource
in Bristol Bay
Telcon from SWEC to Attorney regarding people of Igiugig
reaction to the Kukaklek concepts
Telcon w/Alaska Railroad regarding the transport coal from
the Healy mines to Seward
Telcon from BBNC regarding a public easement which exists at
the outlet of Kukaklek Lake
Third Project Report issued
Study team Meeting in Anchorage
Agency Information Meeting in Anchorage (w/Study Team)
Written comments received by SWEC from school children
in Igiugig regarding concerns about various study concepts
ISER information meetings in Dillingham regarding energy use
Meeting w/FRI regarding salmon and hydroelectric power
in Bristol Bay region
ISER information meeting in Manokotak regarding energy use
Date
11/3/81
11/4/81
11/4/81
11/9/81
11/9/81
11/9/81
11/12/81
11/12/81
11/13/81
11/16/81
11/17/81
11/17/81
11/17/81
11/18/81
11/18/81
-
..
! .. -
.. ..
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Informal ISER meetings in Ekuk regarding energy use
Informal ISER meetings in Portage Creek regarding energy use
Informal ISER meetings in Clarks Point regarding energy use
Informal ISER meetings in New Stuyahok regarding energy use
Informal ISER meetings in Koliganek regarding energy use
Informal ISER meetings in Portage Creek regarding energy use
Informal ISER meetings in Egegik regarding energy use
Conference at BBNC regarding Tazimina exclusion from
Lake Clark Preserve
Distribution of tabulated comments from community
meetings by SWEC to select native groups
Letter to NPS from BBNC proposing a land exchange at
Tazimina site
Telcon w/BIA and ISER regarding native land allotment
information
Letter from SWEC to Attorney representing Igiugig people to
explain Kukaklek concepts
Scope of Service issued to FRI by D&M to provide data on
salmon in Bristol Bay
Informal ISER meetings in Levelock regarding energy use
Informal ISER meetings in King Salmon regarding energy use
Informal ISER meetings in Nondalton regarding energy use
Informal ISER meetings in Igiugig regarding energy use
Submission of Kukaklek Hydroelectric Concepts to ADFG
for comments
Date
11/18/81
11/18/81
11/18/81
11/20/81
11/22/81
11/23/81
11/23/81
11/23/81
11/24/81
11/25/81
11/30/81
11/30/81
12/1/81
12/2/81
12/2/81
12/2/81
12/3/81
12/3/81
!I'll
III
r
II
..
-
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
NPS (Denver) notified to review potential power alternatives
for Bristol Bay
Informal ISER meetings in Iliamna regarding energy use
Informal ISER meetings in Newhalen regarding energy use
Telcon from Alaska House of Representatives to SWEC
regarding economic limit of study (status of Pedro Bay)
Letter to APA from ADNR (Division of Parks) regarding status
of "promising" hydroelectric sites in Bristol Bay region
Letter to USFWS from SWEC regarding potential
hydroelectric sites in Bristol Bay region
Meeting at APA office w/representatives from Igiugig
Meeting at BBNC office w/representatives from Igiugig
Telcon w/Bristol Bay Borough and ISER regarding seafood
operators in Bristol Bay
APA letter sent to NPS regarding Kukaklek concepts
(solicitation of comments)
Letter from Corps of Engineers regarding status
Navigable Waters in Bristol Bay region
Fourth Project Report issued
Letter from ADFG sent to SWEC regarding NPS
regulations concerning Kukak1ek Lake
Meeting w/ADFG and ISER regarding the fishing industry
in Bristol Bay
Meeting w/BIA and ISER regarding native land allotments in
Naknek, South Naknek, and King Salmon
Meeting w/Heinz Noonan and ISER regarding the Alaska Power
Cost Assistance Program
Date
12/3/81
12/4/81
12/6/81
12/9/81
12/10/81
12/10/81
12/14/81
12/14/81
12/15/81
12/16/81
12/17 /81
12/18/81
12/18/81
12/22/81
12/22/81
12/22/81
-
"..
* ..
-
-..
filii
I ..
-..
-
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Letter from Attorney to SWEC regarding definite requirements
that should be enforced if Kukaklek is developed
Meeting with ISER and APA regarding end use analysis of the
electrical demand forecast
Telcon w/Alaska Division of Energy and Power Development
regarding commercial forests in Alaska
Letter sent to APA from NPS stating a Kukaklek Project
cannot be developed without an Act of Congress
Telcon w/JEVAD, Inc. and BBNC regarding IC documents for
surface estate (Iliamna, Newhalen, and Nondalton, DOTPF
right-of-way
News article in Anchorage Daily News regarding
financing of hydroelectric plants (by State)
Telcon by ISER to Naknek Electric Association regarding
electrical consumption by military at King Salmon
Telcon by ISER to Public Affairs Office, Elmendorf AFB,
regarding future of King Salmon AFB relative to
energy consumption
Preliminary Electric Demand Forecast for BBRPP (from ISER)
Project Meeting (Denver)
Te1con by ISER to Nushagak Electric Cooperative regarding
monthly KWH sales to 4 fish processors
Letter from ADNR to APA regarding Concerns and issues
identified at public meetings of the Bristol Bay Cooperative
Management Plan
Telcon between SWEC and BBNG regarding other capital
projects in the Bristol Bay region
Date
1/4/82
1/4/82
1/5/82
1/5/82
1/7 /82
1/12/82
1/18/82
1/18/82
1/19/82
1/20-22/82
1/26/82
1/27/82
2/1/82
i ..
..
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Press release by APA regarding the Energy Supply
Technology Evaluation
Fifth Project Report issued
Telcon w/BBNC and SWEC regarding the Alaska Land Use
Council Five Year Plan for Bristol Bay
Telcon to RurAl CAP from BBNC regarding the Residential
Energy Audit
Telcon w/National Research Council of Canada and SWEC
regarding space heating alternatives
Letter from BBNC to BBNA regarding capitol projects which
would enhance the fisheries of Bristol Bay
Letters sent by BBNC to Bristol Bay native organizations,
villages, special interest groups and local agencies
regarding public meeting to be held in Dillingham on
March 5, 1982 to discuss interim assessment
Letter from BBNC to Bristol Bay village representatives
and various agencies regarding March village meetings
Telcon to North Pole Refinery in Fairbanks by SWEC regarding
cost and availability of crude oil
Letter from APA to SWEC regarding future cost of
power in Bristol Bay area
Letters from SWEC to all its subcontractors regarding
announcement of March village meetings
Telcon w/Green Construction Co. and SWEC regarding length of
construction time and peak construction labor force for
various hydro projects
Date
2/2/82
2/2/82
2/3/82
2/8/82
2/10/82
2/11/82
2/12/82
2/16-18/82
2/17/82
2/17/82
2/17/82
2/19/82
..
" ..
... -
---
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Telcon from SWEC to Green Construction Company regarding
length of construction period and peak labor force estimates
on various Tazimina and Newhalen hydro concepts
Telcon from SWEC to Chugach Electric Association, Inc.
regarding cost of power to Bristol Bay
Letter from APA to SWEC regarding review of Energy Supply
Technology Evaluation
Letter from APA to SWEC regarding review of Hydrologic
evaluations
Letter from SWEC to APA regarding Phase I cost analysis
Copy of Findings and Conclusions, Bristol Bay Coastal
Management Program, received by SWEC from APA
Paper on "Considerations of River Ice Problems for Proposed
Hydropower Projects" received by SWEC from APA
Sixth Project Report issued
Letter from APA to various state, federal and local agencies
regarding a March 12, 1982 informational meeting on
Interim Feasibility Assessment
Revised report: ~Preliminary Electricity Demand Forecast
for the Bristol Bay Regional Power Plan" received by SWEC
from ISER
Community meeting in Dillingham regarding Interim
Feasibility Assessment
Letter to the Editor (Anchorage Times) regarding Bristol
Bay hydro studies
Community meeting in Iliamna regarding Interim Feasibility
Assessment
Community meeting in Igiugig regarding Interim Feasibility
Assessment
Date
2/19/82
2/22/82
2/23/82
2/24/82
2/24/82
2/24/82
2/25/82
2/26/82
2/26/82
3/1/82
3/5/82
3/8/82
3/8/82
3/9/82
, ..
c
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING TIlE STUDY EFFORT
Description
Community meeting in Levelock regarding Interim
Feasibility Assessment
Community meeting in New Stuyahok regarding Interim
Feasibility Assessment
Community meeting in Naknek regarding Interim
Feasibility Assessment
Community meeting in South Naknek regarding Interim
Feasibility Assessment
Letter from FRED Division of ADF&F to SWEC regarding
comments by biologists on Newhalen River regional
hydroelectric concept
Agency meeting with project team in Anchorage regarding
Interim Feasibility Assessment
Telcon from APA to SWEC regarding new work scope for
Tazimina and geotechnical work scheduled for Newhalen site
Telcon from SWEC to BBNC regarding status of Indian
Allotments at Newhalen
Telcon from SWEC to D&M regarding spring field work at
Tazimina and Newhalen sites
Description of Optimum Project Timing issue sent to
SWEC by APA
Telcon from BBNC to State of Alaska regarding Newhalen
City Charter
Issuance of draft Interim Feasibility Assessment,
Executive Summary
Letter from APA to SWEC regarding comments on draft
Interim Feasibility Assessment Executive Summary
Letter from Manokotak resident to APA regarding wind
power feasibility to Bristol Bay
Date
3/9/82
3/9/82
3/10/82
3/10/82
3/10/82
3/12/82
3/15/82
3/15/82
3/16/82
3/17/82
3/17/82
3/19/82
3/19/82
3/21/82
-.. ..
fill
....
--
..
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Issuance of draft Interim Feasibility Assessment report
Letter from BBNC to APA regarding the Newhalen Hydroelectric
Project subsurface permit
Letter from APA to SWEC authorizing the geotechnical field
program for the Newhalen site
Letter from SWEC to APA enclosing Amendment No. 1 to
Phase I of contract AS44~83-010
Letter from SWEC to S&W authorizing to proceed with
preliminary subsurface exploration at the Newhalen site
Telcon from SWEC to D&M regarding detailed fisheries
studies on Newhalen River
Telcon from BBNC to SWEC regarding access permission at
Newhalen site for geotechnical field work
Letter to the Editor (Anchorage Times) regarding Bristol
Bay hydro studies
Interagency meeting in Anchorage regarding Interim
Feasibility Assessment
Letter from APA/DOE to APA regarding comments on draft
Interim Feasibility Assessment report
Letter from Burr, Pease & Kurtz to SWEC regarding
community meeting at Igiugig on March 8 and the Interim
Feasibility Assessment
Telcon from SWEC to APA regarding geotechnical conditions at
Newhalen and receiving authorization for preliminary design
and cost estimates of constructing a canal in sand and gravel.
Telcon from SWEC to S&W authorizing additional borings
at Newhalen
Date
3/22/82
3/22/82
3/22/82
3/23/82
3/23/82
3/23/82
3/23/82
3/23/82
3/25/82
3/26/82
3/29/82
3/31/82
4/1/82
.. ..
..
..
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Telcon between SWEC and APA, with APA authorizing S&W to
perform resistivity work at Newhalen site
Telcon between SWEC and APA, with APA authorizing funds for
acoustical equipment for Newhalen sockeye salmon smolt and
fry sampling program
Letter from SWEC to APA with revisions to Amendment No. 1 of
contract AS44-83-0l0
Letter from the Newhalen City Council to APA regarding the
Newhalen Hydroelectric Project -Surface Estate Geotechnical
Exploration permit
Telcon from SWEC to BBNC regarding Newhalen land status
Meeting with APA and BBCMP regarding Interim Feasibility
Assessment
Letter from NPS to APA regarding interim Feasibility
Assessment
Seventh Project Report issued
Letter from DNR, Div. of Forest, Land and Water Management
to APA regarding comments on draft Interim Feasibility
Assessment report
Memo from APA to SWEC regarding items USF&WS recommend
having in feasibility studies
Bristol Bay Regional Energy Demand Analysis, final
report by I SER
Project meeting at APA
Letter from USF&WS to APA regarding draft Interim
Feasibility Assessment report
Date
4/2/82
4/2/82
4/6/82
4/6/82
4/8/82
4/15/82
4/19/82
4/20/82
4/22/82
4/22/82
4/23/82
4/26/82
4/27/82
.. .. TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Letter from ADF&G to APA regarding comments on draft Interim
Feasibility Assessment report
Letter from BBNC to BIA regarding Newha1en Hydroelectric
Indian allotment conflict
Letter from APA/DOE to APA regarding use of electrical
energy forecast data and wind systems data in a DOE wind study
BBCMP meeting at APA leading to follow-up study of
transmission line corridors in Bristol Bay
Letter from APA to SWEC regarding comments on draft Interim
Feasibility Assessment report
FAA approval for Newha1en environmental field work
Newha1en fisheries study commences
Letter from Alaska Peninsula Corporation to APA regarding
Newha1en Hydroelectric Project surface permit for fish
related studies.
Interagency meeting regarding Bristol Bay fisheries and
hydro studies
Letter from ADNR, Division of Parks regarding comments on
draft Interim Feasibility Assessment report
Letter from USGS to SWEC containing recent Tazimina River
low-flow discharge measurements
Letter from BIA to BBNC regarding Newha1en land status
Letter from APA/DOE to APA regarding comments on draft
Interim Feasibility Assessment report
Letter from SWEC to APA regarding Amendment No. 2 to
contract CC08-2108
Letter from SWEC to APA regarding geotechnical investigation,
conceptual engineering, and cost study for Newha1en
Date
4/28/82
4/28/82
4/28/82
4/29/82
4/30/82
5/6/82
5/10/82
5/10/82
5/11/82
5/13/82
5/19/82
5/25/82
5/26/82
6/7 /82
6/10/82
-..
•
-., ..
TABLE 8.2-3 (cont)
CHRONOLOGICAL LIST OF SIGNIFICANT EVENTS AFFECTING THE STUDY EFFORT
Description
Eighth Project Report issued
Memo APA to SWEC regarding cost estimates on Bristol Bay
Regional Power Plan
Meeting of SWEC and APA in Anchorage regarding Newhalen
fisheries study
Interagency meeting with project team in Anchorage regarding
Newhalen fisheries studies, and intake and fish screen
technologies
Meeting of SWEC, APA, and BBCMP in Anchorage regarding
transmission line planning
Meeting of SWEC and APA in Anchorage regarding a public
opinion survey on revised Interim Assessment
Date
6/11/82
6/14/82
6/14/82
6/15/82
6/16/82
6/16/82
,. ..
".. ..
-
9. CONCLUSIONS AND
RECOMMENDATIONS
9. CONCLUSIONS AND RECOMMENDATIONS
9.1 CONCLUSIONS
9.1.1 Introduction
The investigative efforts performed during Phase I and reported herein have
resulted in the following conclusions. These conclusions are based on data
and information gathered during the study, on preliminary engineering and
technical investigations, and on environmental, sociocultural, and economic
evaluations.
The conclusions presented address each of the major portions of the study
efforts and the overall objective of the study, which has been to develop
and evaluate alternative energy plans for meeting the electrical energy
needs of the Bristol Bay study region to the year 2002.
9.1.2 Energy Demand Forecast
The electrical energy demands of the region have been forecast on a
preliminary basis through the year 2002. The forecast shows that the
region's electrical needs will continue to grow at an average overall rate
of 4.06 percent per year. This rate reflects the total energy needs of the
residential, government/commercial, industrial, and military sectors. The
regional electrical energy needs have been determined as 30,372 MWh for the
year 1982 and 67,073 MWh for the year 2002. These energy values are
believed to be conservative in that they reflect the past and present
lifestyles and growth for the region. It is believed that the forecast
reflects the extent to which this growth is governed by energy price
structures, industrial and commercial interests, population, and appliance
end-use trends of the region.
The largest and fastest energy growth is seen in the commercial/government
sector. This growth is forecast at a rate of about 6.6 percent per year.
This is followed by the electrical energy growth for the residential sector
of about 4.9 percent per year. Very little growth (less than 0.50 percent)
9-1
is anticipated in the industrial sector, and no growth is predicted for the
military sector. The
resulting principally
forecast responds to an electrical energy growth
from electrical needs for' appliance end-use.
Electrical energy needs are principally for "appliance" needs and not for
space heating load requirements. This fact is primarily due to the
electrical energy costs in the region. It is our judgment that this
condition will continue to exist in the future. Electrical energy for
space heating in the lower energy cost sections of the region would have to
be available to the consumer at $0. 05/kWh or less to be competitive with
I
I
I
I
I
diesel fuel space heating energy, for fuel costing $1. 45/ gal. These prices I
are in 1982 dollars (weighted average cost of $1.33/gal).
Based on the preliminary energy demand forecast, including an allowance for
losses which could occur in the energy production and distribution system,
the following tabulation shows the presently anticipated energy and peak
power demands for the region.
Annual Energy Peak Power
Year Reguirement ~MWhJ Demand (MW2
1982 32,400 7.9
1987 38,700 8.9
1992 47,600 11.2
1997 58,900 12.2
2002 74,500 15.0
The above energy and power demand predictions were used as the basis, with
minor adjustments, for the engineering and cost studies for energy plan
scenarios developed under Phase I of the study.
The preliminary energy demand forecast study has been updated and a final
report issued presenting a more detailed evaluation of future electrical
and space heating needs. These data will be considered in the Phase II
effort. Adjustments to the present Phase I study will be made, as
necessary, in the Phase II detailed feasibility analysis report.
I
I
I
I
I
I
I
I
I
I
I
I
I
-..
r .. -
-
9.1.3 Energy Technologies
The study identified only two primary energy sources that are presently
available for use within the Bristol Bay Study area. These sources would
provide the electrical energy and power needs, on a firm basis, as forecast
through the year 2002. The sources are hydroelectric power and the
presently used diesel fuel. While several other primary energy resources
were identified, for example; wood, peat, geothermal, oil, and natural gas,
the study showed that: 1) full development of these resources for the
purpose of meeting regional or subregional energy needs would not be
compatible with the environmental and sociocultural restraints; 2) the time
and monies that would need to be expended for proving the availability of
these resources is not justified on the basis of meeting just the limited
energy needs of the region; and 3) these resources could not be
cost-effectively developed within the near future for use in the Bristol
Bay study region.
Wind energy has also been identified as an available and proven resource
for certain areas of the study region. However, wind energy is of an
intermittent nature. Cost-effective methods for storing wind energy were
not found by the study for the Bristol Bay region, and wind energy was
considered only as a supplementary energy source.
An array of 25 energy technologies in all was considered. From this, a
total of nine primary and supplementary energy technologies were selected
for consideration in electrical energy plan generation, including
hydroelectric power and wind power resources. The nine energy technologies
were:
Primary Energy
• Diesel Generation
• Coal-, Oil-, and
Natural Gas-fired
Steam Electric
• Coal Gasification
• Combined Cycle
• Hydroelectric Power
Supplementary Energy
• Wind Energy
• Waste Heat Recovery
• Energy Conservation
• Organic Rankine Cycle
9-3
The above were investigated, and if found to be promising, were used as
elements of specific energy plan concepts for the Bristol Bay study region.
9.1.4 Evaluation of Energy Plans
Originally, 48 schemes for power development were considered. These were
reduced to 21 power development scenarios that were analyzed and evaluated
on the basis of technical, environmental, and economic characteristics.
Several variations of these scenaraios were also studied and are also
included in this report. The evaluation took into consideration the
indicators outlined by the Power Authority in its guidelines 3AAC94.060.
Based on these evaluations, conclusions were reached with respect to energy
type and use. These conclusions are summarized in the following paragraphs.
9.1.4.1 Diesel Generation
Diesel generation is the only prime electrical generating system currently
used in the Bristol Bay region. It was found technically acceptable for
continued use by this study. It offers flexibility with respect to energy
growth needs on a village-by-village basis, on a sub-regional basis, and on
a regional basis. Diesel generating technology is commercially available
and has proven to be reliable. All the diesel generating scenarios were
judged to result in the least environmental impact on the study region.
However, the regional diesel scenarios did not compare favorably with most
hydroelectric systems on the basis of cost. The present worth costs of the
diesel scenarios are given in Table 9.1-1.
9.1.4.2 Outside Transmission Line
The scenario, importation of electrical energy into the study area from a
power plant located at Beluga, was found to be technically acceptable with
respect to safety, availability, reliability, and constructability. This
alternative, however, resulted in major environmental and institutional
impacts relating to the Lake Clark National Park and Preserve. The
economic evaluation ranked this scenario fifteenth in a group of 25.
9-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
r ..
r
III
The overall evaluation for imported power must, however, be tempered with
the following considerations: the study was not able to obtain a firm
commitment on the cost of power from the Beluga source. Therefore, the
bus-bar cost of energy developed for the Railbelt Power Alternative Study
(Battelle Report) was used in the economic evaluation of this scenario.
Because of its low rating, we believe that further studies of this scenario
are not warranted.
9.1.4.3 Fossil Fuel-Fired Plants
Coal and oil were identified as two presently acceptable and readily
available fossil fuels for use in the study region. The use of crude oil
as fuel a source was found uneconomical. Natural gas has not been found in
the study area. However, exploratory work for this energy source is very
costly. If found, development of natural gas resources could take at least
ten years. Because of the uncertainties associated with natural gas
development in Bristol Bay, it was not included as an energy source in the
power supply plans.
The three fossil fuel-fired electrical energy generating systems
investigated were: 1) a coal-fired steam electric plant, 2) an oil-fired
combined cycle plant, and 3) a coal gasification combined cycle plant
utilizing a gas turbine, a waste heat recovery boiler, and a conventional
steam electric generating plant.
The coal-fired steam electric plant and the oil-fired combined cycle plant
are technically proven and commercially available. The coal gasification
combined cycle plant is technically acceptable, but has not been proven
commercially in the size required for the Bristol Bay study region. From
an environmental standpoint, the fossil fuel plants demonstrate a moderate
but acceptable impact on the environment, provided that mitigation measures
are taken. The present worth economic evaluation of fossil fuel-fired
plant scenarios, as shown on Table 9.1-1, places these energy plans
essentially in the same catagory as the diesel fuel-fired plants, which is
in the lower two-thirds of the ranking order.
9-5
9.1.4.4 Hydroelectric Power
Ten hydroelectric power generating concepts were evaluated in the study.
These concepts represent both regional and sub-regional energy
developments; the latter used in combination with other energy forms to
supply the total regional needs.
Technically, all hydroelectric power projects are considered acceptable and
feasible. With respect to environmental considerations, the ranking is
different within the hydroelectric power groups. Although exhibiting
varying potential environmental effects, it is believed that in most cases
these effects are of a moderate nature and could be made acceptable with
mitigation measures. The present worth economic analysis of energy plans
(Table 9.1-1) shows that the four least costly alternatives are regional
hydroelectric developments. These are the two Newhalen River regional
concepts, the Tazimina River regional concept, and the Kontrashibuna Lake
regional concept. The fifth ranking energy scenario also uses
hydroelectric power development, namely, the small run-of-river Tazimina
River concept. This scenario combines the hydroelectric concept with
sub-regional diesel, waste-heat, and wind.
9.1.4.5 Supplementary Energy Sources
The study findings show that all four
suitable for inclusion in energy plan
supplementary energy
scenarios for the
sources are
Bristol Bay
region. Scenario B-19 evaluates several combinations of these sources as
supplements to the Base Plan (Continued Diesel).
As stated above, wind energy development is possible in the Bristol Bay
region. Five areas identified by the study for consideration are Naknek,
King Salmon, South Naknek, Egegik, and Igiugig. These areas were selected
because they constitute a wind power potential ranking of class 4 or
better. Wind energy developments were found to be technically acceptable
if low capacity units are used for the present, reserving higher capacity
units for future development. The environmental impacts of wind will
depend largely on the magnitude of wind energy systems developed and their
9-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
r .,
-
specific location. Economic evaluations of supplementary wind energy
installations show that cost benefits would be realized for selected diesel
energy scenarios as a result of wind installations.
Waste heat recovery systems are acceptable from all three evaluation
catagories. Cost benefits from waste heat recovery, however, are only
available and applicable to fossil fuel and diesel energy generating
systems. Economic studies of hydroelectric energy-related scenarios showed
that overall benefits would be realized if waste heat recovery systems were
installed in the early planning years of the suggested development.
The economic benefits resulting from waste heat recovery systems were found
more favorable than those resulting from wind generation. The economic
benefits of a combined waste heat and wind generation supplemental energy
scenario were found to be about the same as for waste heat alone.
Energy conservation, whether applicable to electrical or space heating
needs, was found to be technically acceptable and environmentally
desirable. From an economic standpoint, however, the cost benefits to be
derived from the implementation of conservation measures are variable, and
greatly depend on the attitude of the people, the present building stock of
the region, the type of electrical or space heating appliances in use, and
the impact of educational programs on the implementation of conservation
measures. The benefits from conservation on reducing the electrical and
space heating energy needs were not evaluated here, but would need to be
addressed in Phase II of the study. It is believed that electrical energy
reductions resulting from conservation measures would not be significant
enough to influence present evaluation parameters and study results.
Another form of energy conservation investigated is that of load
management. The assessment of this approach found that the likelihood of
success in implementing currently available load management technologies,
whether for the presently existing or anticipated energy systems, was
slight to none at all.
In reaching conclusions or making choices between candidate energy plans on
the basis of results, the level of confidence in the data and assumptions
9-7
I
used for the evaluation of individual scenarios was also considered. The I
best data available are those for the Newhalen and Tazimina River plans.
More detailed physical and environmental data were available for these
concepts, especially in comparison to other hydroelectric power sites
investigated.
The Kontrashibuna concept has presented some concerns about its
environmental setting and its compatibility for use as a power site with
the Lake Clark National Park and Preserve. Similar concerns apply to
energy scenarios involving the Chikuminuk Lake hydroelectric concepts.
9.1.4.6 Summary Evaluation
All twenty-one power plan scenarios and variations on several of the
scenarios were compared on the basis of present worth costs. A summary and
ranking of present worth costs for the scenarios evaluated is given in
Table 9.1-1.
On the basis of present worth cost, the five most promising energy plan
scenarios are:
0 Scenario B-14A The Newhalen River Regional Plan (Power Only)
0 Scenario A-I The Tazimina River Regional Plan
0 Scenario B-14B The Newhalen River Regional Plan (Power & River
Diversion)
0 Scenario B-18B The Kontrashibuna Lake Regional Plan
0 Scenario B-19E A small run-of-river Tazimina River plant used in
conjunction with local diesel generation
complemented with waste heat and wind energy
Comparing these five scenarios to the Base Plan, on the basis of present
worth cost ratios, the following economic ranking was developed:
9-8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
..
c
Present
Economic Worth Cost
Rank Description Scenario Ratio
1 Newhalen Regional B-14A 1.54
2 Tazimina Regional A-1 1.36
3 Newhalen Regional B-14B 1.31
4 Kontrashibuna Regional B-18B 1.29
5 Local Diesel, Waste Heat,
Wind, and Local Tazimina B-l9E 1.20
20 Base Plan (Continued Diesel) BP-l 1.00 (Base)
Based on the data available at the completion of the Interim Feasibility
Assessment, the following order developed for the five most favorable
(economic) candidates with respect to other evaluation catagories:
Environmental
Confidence
All are feasible and reflect an equal ranking
Local Diesel/Waste Heat/Wind/Local Tazimina
Newhalen (River Diversion)
Newhalen (Power Only)
Tazimina (Regional)
Kontrashibuna (Regional)
Local Diesel/Waste Heat/Wind/Local Tazimina
Newhalen (Power Only)
Newha1en (River Diversion)
Tazimina (Regional)
Kontrashibuna (Regional)
The ranking of environmental and confidence factors is highly subjective.
Furthermore, it was not the intent to assign equal weight to these
evaluation catagories or to suggest that the ranking within catagories is
linear from top to bottom.
Based on a subjective evaluation, it was concluded that the ranking of
9-9
alternatives for a Bristol Bay regional power plan would be the same as
shown above for the economic listing. This ranking may, however, be
influenced by local preferences or other factors in favor of sub-regional
developments such as the local diesel/waste heat/wind and local
run-of-river Tazimina plant.
With respect to regional hydroelectric power developments, it may be both
technically and economically desirable to consider development of these
scenarios on a multi-regional basis. Thus designed, certain projects might
serve not only the Bristol Bay region, but also adjacent regions such as
the Bethel and Togiak areas. Under such a development, the projects would
be sized to accommodate higher capacity and energy needs. The merit of
such a development could be investigated in Phase II, if the Power
Authority desires.
In summary, the general conclusion of the Interim Feasibility Assessment is
that there are a number of promising alternatives to the current use of
diesel electric generation in the Bristol Bay region.
9-10
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
-
Scenario
Base Plan (BP-1)
Alternative A (A-I)
Alternative B-1
Alternative B-2
Alternative B-3
Alternative B-5
Alternative B-8
Alternative B-9A
Alternative B-9B
Alternative B-9C
Alternative B-11
Alternative B-13A
Alternative B-13B
Alternative B-14
Alternative B-14B
Alternative B-15
Alternative B-16
Alternative B-17
Alternative B-18A
Alternative B-18B
Alternative B-19A
Alternative B-19B
Alternative B-19C
Alternative B-19D
Alternative B-19E
TABLE 9.1-1
SUMMARY OF PRESENT WORTH COSTS
All Values in 1982 Dollars
Description
Present Worth,
($1,000)
Diesel Only
Tazimina Regional
Beluga Transmission
Newhalen and Large Kukaklek
Newhalen and Medium Kukaklek
Tazimina Run-of-River, Medium
Chikuminuk and
Medium Kukaklek
Medium Chikuminuk and
Medium Tazimina
16 MW Coal-Fired
16 MW Oil-Fired
16 MW Coal Gasification
Coal-fired at Dillingham
and Newhalen
Large Chikuminuk
and Tazimina Run-of-River
Large Chikuminuk and local
Newhalen
Newhalen Regional -Power
Divison
Newhalen Regional Power and
River Diversion
Diesel Clusters
Diesel Clusters and Transmission
Diesel Regional Transmission
Interconnected
Tazimina Run-of-River
and Kontrashibuna
Kontrashibuna
Diesel Local and Waste Heat
Diesel Local and Wind
Diesel Local -Waste Heat
and Wind
Diesel Local and Organic Cycle
Tazimina Local, Diesel Local,
Waste Heat + Wind
291,700
213,700
279,600
301,000
276,300
270,700
266,000
281,000
388,500
269,300
281,300
261,500
267,100
189,900
222,200
340,400
338,900
367,900
270,200
226,800
249,500
287,900
249,200
283,900
242,500
Ranking
20
2
15
21
14
13
9
16
25
11
17
8
10
1
3
23
22
24
12
4
7
19
6
18
5
No cost evaluations were made for scenarios B-4, B-6, and B-7, which
included the development of King Salmon.
Alternative B-10, a coal-fired plant at Naknek, has the same present .worth
as B-9A.
Alternative B-12, a coal-fired plant at Naknek with a subregional Newhalen
hydroelectric development, has the same present worth as B -11.
-
9.2 RECOMMENDATIONS
Based on the stated conclusions. and in consideration of presently known
factors, Stone & Webster Engineering Corporation makes the following
recommendations for Phase II efforts of the Bristol Bay Regional Power Plan:
a. Continue detailed development of the Base Plan scenario to form a base
for comparison;
b. Continue detailed feasibility analysis of the regional Newhalen River
hydroelectric power concept (B-l4A);
c. Undertake detailed feasibility analysis of -the sub-regional
diesel/waste heat/wind/Local Tazimina scenario (B-l9E);
d. Through a public participation program, obtain a better understanding
of attitudes of the people of Bristol Bay regarding a regional power
plan.
The recommendation to continue studies on the Newhalen River concept stems
from the preliminary conclusion that the project is economically
attractive, technically feasible, and is likely to be environmentally
acceptable with proper mitigative measures. To this end, the following
steps are suggested for early implementation in Phase II efforts:
a. Undertake resident and anadromous fisheries studies to satis factorily
demonstrate the environmental acceptability of the B-l4A concept.
b. Continue geotechnical investigations and surveys at the proposed site
to better define site conditions revealed by initial investigations and
to obtain additional geologic data in the vicinity of the power plant.
9-11
I
The following conclusions further support the recommendation to undertake I
further evaluation of the Newhalen River regional concept in Phase II:
a. The Newhalen regional concept appears more attractive economically than
Tazimina, based on presently available data;
b. The engineering and construction uncertainties relating to this project
appear to be fewer because of its location and nature of the concept;
c. There may be some significant mitigative fisheries benefits relating to
upstream migrants that could be implemented and made part of proj ect
development; and
d. Because of high Newhalen River flows during the summer, there exists
the potential for additional electrical energy development during that
period of time coinciding with fish processing energy needs. This
should benefit processors within the region.
We recommend that a decision be made to evaluate the Newhalen concept and
the sub-regional diesel/waste heat/wind/Local Tazimina concept in Phase II,
and to perform those investigations and studies that are necessary for the
Detailed Feasibility report and, as applicable, for the preparation of a
FERC license application.
Based on the above recommendations, the scope of work believed necessary
for the Phase II efforts is outlined in detail in Chapter 10 of this report.
9-12
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
...
..
,. ..
,. ..
...
..
. -
,.
.. -
-...
10. SCOPE OF WORK
PHASE II
-
c
c
..
10. SCOPE OF WORK -PHASE II
10. 1 INTRODUCTION
The Interim Feasibility Assessment Phase I efforts of the Detailed
Feasibility Analysis for the Bristol Bay Regional Power Plan have been
identified and a regional and subregional power plan has been recommended
for detail evaluation and comparison with the Base Plan.
The plans to be evaluated are:
•
•
•
The Base Plan, which is the continuation of present electrical
generation practices, using diesel fuel, throughout the region
(BP-1).
An alternative regional hydroelectric power development on the
Newhalen River (B-14A) using a river diversion concept for power
generation only.
An alternative subregional energy plan utilizing the development
of. centralized diesel generating systems, within each village or
village group, supplemented by use of waste heat recovery systems,
wind generating systems, and a small run-of-river hydroelectric
power facility on the Tazimina River (B-19E), hereinafter called
Diesel-Tazimina.
10.2 OBJECTIVES
The objectives of Phase II are to perform a detailed feasibility analysis
on the selected alternative energy plans, compare the results of these
analyses to the Base Plan, and make appropriate recommendations for the
development of the preferred plan.
Accordingly, the Phase II work will: 1) establish the electrical energy
demand bases through the year 2002; 2) develop and analyze the Base Plan
10-1
and Alternative Plans, and 3) perform field and engineering studies and
collect data necessary for the plan optimization process, needed to respond
to the technical, environmental, and economic aspects of the analyses.
In addition, the Phase II effort will study the space heating energy needs
of the region and develop a plan that will respond to these needs; in full
consideration of appropriate energy conservation measures.
Should the selected plan include a hydroelectric power development, the
Phase II work will include the preparation for submittal of a license
application to the Federal Energy Regulatory Commission (FERC), if the
Power Authority so directs. In developing this scope of work, it has been
assumed that a FERC application will be prepared.
A further objective of the Phase II study will be to evaluate, in detail,
the acceptability of the three primary study indicators, namely: economic;
environmental; and technical.
Finally, a Detailed Feasibility Report will be drafted and, upon approval,
issued as directed by the Power Authority.
The work to be conducted during Phase II has been divided into specific
tasks to better define the scope, assign responsibility, and establish
schedules and budgets. Each task is developed in terms of objective,
approach, discussion of work details, schedule, and costs. The tasks
reflect project development responsibility to the Bristol Bay regional
needs only, and not a multi-regional energy development.
The tasks for Phase II are described on the following pages.
10-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
.. ..
".
II.
..
TASK 1 -ENERGY DEMAND ANALYSIS
OBJECTIVE
To review and ascertain the electrical and space heating energy
requirements of each village and/or groups of villages in the Bristol Bay
study area for use in the development and evaluation of the selected energy
plans.
APPROACH
The energy demand data developed by ISER and reported in its final report
entitled "Electricity Demand Forecast for the Bristol Bay Regional Power
Plan", dated April 1982, shall be used. These data relate to:
• Electricity energy demands and projections
• Space heating energy demands and projections
For the electrical energy requirements, the task will consider the
appropriate sensitivity scenarios developed by ISER, and utilize these
scenarios in the development of electricity power values applicable to each
of the selected plans. For each scenario, capacity and energy load curves
will be developed, and will consider appropriate distribution losses, plant
losses, and needed power reserves. These data will be used in sizing
local, subregional, and/or regional generating plants and for determining
transmission line requirements and characteristics .
The electrical energy benefits resulting from appliance conservation
measures will be identified and evaluated. Sensitivity studies will be
made to further quantify the economics of conversion as it relates to
electrical energy for space heating and hot water needs.
Space heating energy consumption, as projected over the years, including
the application of appropriate conservation measures, will be assessed.
Energy resources applicable to space-heating requirements will be selected
10-3
and evaluated to determine which combination of technologies and resources
best responds to the technical, environmental, and economic criteria.
WORK PRODUCTS
The work products of this task include:
•
•
•
•
The electricity demand capacity and energy load characteristics
for each of the study villages, and for the region.
The space heating energy characteristics for each of the study
villages, and for the region.
A plan for the timing and development of alternative energy
sources, including, size, type, and location.
A plan for the implementation of conservation measures applicable
to electrical and space heating energy needs.
DISCUSSIONS
Electrical energy demand forecast developed by ISER indicates that an
inverse sensitivity relationship exists between electrical power needs
(capacity/energy) and the cost of electrical power. Three sensitivity
studies were made by ISER. The first, classified "Business as Usual",
relates to the Base Plan (BP-l) energy scenario. The second, classified
"Regional Diesel", relates closely to the Diesel-Tazimina (B-l9E)
scenario. The third, classified "Newhalen Regional", relates to the
scenario for which it is named (B-14A). For each of these sensitivity
studies, capacity-energy load curves will be developed for use in sizing
the power systems applicable to each of the three sensitivity scenarios.
For those energy plans which relate to the use of diesel generation,
studies will be made to establish the size and timing of diesel
installations for meeting power needs and for reserve. For those energy
10-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
..
-
plans which relate to hydroelectric power generation, studies will be made
to establish the merits of single or mUltiple unit installations, including
the timing for installation of such units.
With respect to space-heating, studies will be made to determine
alternative fuel types for use in meeting this energy need. Technical,
environmental, and economic parameters will be considered, as required, for
the selection process.
Data on identified energy resources will be reviewed to ascertain the
viability of utilizing such resources in meeting the space-heating energy
needs of the study area, as forecast by ISER. Present studies indicate
that coal, wind, waste heat recovery, and conservation measures are energy
resources most applicable to space-heating needs. Secondary electrical
energy, as available from run-of-river hydroelectric power plants, will
also be assessed for use in space-heating needs. Identified resources will
be evaluated with respect to economic implications, applicability,
environmental impact, and the flexibility by which they can readily respond
to space-heating needs. Technical restraints, manufacturing technologies,
constructability, operating and maintenance aspects, long-term useable
availability, and replacement factors, will also be determined and utilized
in space-heating scenarios for the selection of the most applicable and
long-term cost effective space-heating energy needs system. Regional and
regulatory restraints will be identified and addressed .
Conservation studies will consider cost/benefit aspects of attempting to
improve presently existing conditions, both in the electrical appliance
area and with regard to space heating. Also, the implications of future
conservation measures will be determined, and a plan will be developed
outlining specific recommendations and suggestions.
The efforts relating to this task will be performed by SWEC.
10-5
SCHEDULE
The work will begin immediately upon authorization of Phase II.
anticipated that this task will require about three months to complete.
COST
The anticipated expenditure for Task 1 is estimated at $ 49,640.
10-6
It is
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-...
",.
...
...
...
TASK 2 -REGULATORY COORDINATION
AND PUBLIC PARTICIPATION
Task 2 has been subdivided into three subtasks to better identify the wide
range of activities included.
Subtask 2.1 -Interagency Coordination
OBJECTIVE
To ensure adequate and timely involvement of Federal, State, and local
government agencies interested in the study.
APPROACH
Federal, State, and local agencies having interest in the study will be
kept continuously informed of study conditions. Contacts and interagency
coordination will be the responsibility of SWEC. Communications will be
established, to the extent practical, with those agency representatives
that have interest in data collected during various activities. All
interagency coordinations (and attempts at coordination) will be documented.
DISCUSSION
This subtask will consider all three energy plans but will relate primarily
to the Newhalen Regional and Diesel-Tazimina energy plans. The Base Plan,
which represents a continuation of present practices will require only a
minimal level of effort of agency involvement. Some studies relating to
space heating energy resources may require agency contacts. While several
members of the study team will be involved indirectly, SWEC will serve as
the coordinator for team interfaces with regulatory agencies.
SCHEDULE
Interagency coordination will take place, as appropriate, throughout the
Phase II study period .
10-7
Subtask 2.2 -Regulatory Requirements
OBJECTIVE
To respond to regulatory requirements in order to satisfy licensing and
compliance procedures.
APPROACH
Statutes, rules, regulations, and other requirements directly or indirectly
affecting the investigation and construction of selected energy projects
will be addressed. A regulatory plan, including a schedule, will be
prepared indicating the steps which will be required for compliance. Some
Federal statutes which may have an impact on the project, and which will be
reviewed under this subtask include:
• Federal Water Power Act of 1920
• Endangered Species Act (P. L. 93-205)
• Historical Preservation Act (P. L. 89-665)
• Federal Land Policy and Management Act (P. L. 94-579)
• Alaska Native Claims Settlement Act (85 Stat. 706)
• Coastal Zone Management Act (P. L. 93-612)
• Clean Water Act of 1977
• Clean Air Act of 1977
• Fuel Use Act of 1978
• Wild and Scenic Rivers Act (P.L. 90-542)
• Anadromous Fish Act of 1965
• River and Harbor Act of 1899 (Section 10)
Within the State of Alaska rules, numerous regulations and procedures for
permits will apply. The following governmental departments and agencies
may have direct responsibilities or significant interests Within the State.
•
•
•
Bureau of Indian Affairs
Bureau of Land Management
Fish and Wildlife Service
10-8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
--
•
".
..
.. ..
..
• US Geological Survey
• National Park Service
•
•
•
Heritage and Conservation Service
Department of Commerce:
National Marine Fisheries
NOAA
Weather Bureau
Department of the Army (Corps of Engineers)
• U.S. Environmental Protection Agency
•
•
•
•
•
•
Federal Communication Commission
Department of Agriculture
Department of Energy (FERC and Alaska Power Administration)
Department of Treasury
State of Alaska:
Dept. of Fish and Game
Dept. of Environmental Conservation
Commission on Economic Development
Divison of Energy and Power Production
Department of Natural Resources
Division of Parks
Division of Forest Lands and Water Management
Department of Community and Regional Affairs
Department of Transportation and Public Facilities
Office of the Governor
Division of the Budget
Division of Policy Development and Planning
Department of Labor
Department of Public Safety
Department of Commerce and Ecomonic Development
Department of Revenue
University of Alaska
University of Washington, Division of Fisheries (FRI)
Local and Regional:
City of King Salmon
City of Naknek
10-9
City of Dillingham
Each of the Native Villages (include Nondalton)
Chogging Ltd. (Dillingham Corp.)
Aleknagek Natives Ltd.
Bristol Bay Borough
Bristol Bay Native Association
Bristol Bay Corporation
Bristol Bay Health Corporation
King Salmon Air Force Station
Rur Al CAP (rural Alaskan Community Action Program)
Local Electric Coops
Additional requirements may also be imposed by municipalities and Native
Organizations. These will be identified, analyzed, and plans will be drawn
up for compliance as may be required for each of the three energy plan
scenarios selected for study.
DISCUSSION
There will be a complex web of permits and procedures to be satisfied.
Because time requirements tend to be lengthy (e.g., public notice and
comment and public meetings and hearings) it is important that early
attention be given to licensing and regulatory requirements. While much of
the effort involved in completion of this subtask will contribute to the
work of other subtasks, it follows that identification of appropriate laws
and procedures for compliance are important first steps. Essential in this
proposed approach is to identify FERC requirements as soon as possible and
to initiate contacts with all concerned local, state, and federal agencies,
and individuals early in the study. While several permitting processes
will need to be executed, the main thrust of the efforts will most probably
be the collection of data in support of a FERC license application.
Of special concern is the issue of land rights, particularly as they relate
to the alternative scenarios. Restrictions on access to potential hydro
sites may be imposed where the land is federally owned or owned by
natives. If this is the case, a Temporary Use Permit or special access
10-10
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
, ..
-
permission would likely be required. Construction and other usage may
present special problems, particularly as they relate to the complex Alaska
native land rights.
Stone & Webster Engineering Corporation, assisted by the Bristol Bay Native
Corporation, will take the lead responsibility for this subtask.
SCHEDULE
Regulatory coordination will occur, as appropriate, throughout Phase II.
Subtask 2.3 -Public Participation
OBJECTIVE
The objectives of the public participation program are to keep the public
fully informed, and to provide a means whereby the public can express its
point of view and influence the results of the study effort.
APPROACH
The overall goal of the Public Participation Program is to facilitate
two-way communication between the project and the public. The program will
provide specific means for the public to become involved in and influence
the course of work as it related to the three energy plans. Communication
methods will include: public meetings, workshops, newsletters, news
releases, and other appropriate means of communications between interested
parties. Specific products may include, but not limited to: proceedings
of public meetings, written comments, proposed action lists, progress
reports, records of workshop meetings, responses to letters of inquiry,
news releases, popular vote ballots, and visual displays. With respect to
dissemination of information, it may be possible to cooperate with the
information office of the Department of Natural Resources is planning for
the Bristol Bay region.
Public meetings will be a principle method for public participation where
specific comments and concerns will be presented. Questions will almost
10-11
ceFtainly arise in determining what hierarchy of concerns is to be
established. Some special interests may include: utility interests,
Alaska native groups, fisheries industries, consumers of electric power,
conservationists, industrial and commercial interests, employment
opportunities, wildlife preservation, and alternative energy sources. With
respect to employment opportunities, local residents will be hired for
appropriate work, if possible. The Bristol Bay Native Association will
assist SWEC regarding contacts in individual Bristol Bay villages.
DISCUSSION
Public participation will be integral in evaluating the Base Plan and the
selected Alternatives for the Detailed Feasibility Analysis. In order to
provide an effective public participation program, counsel will be obtained
from the Power Authority and local organizations, including the Bristol Bay
Native Association and the Bristol Bay Native Corporation.
Effective public participation requires that provisions be made to permit
time for review and comment at various points during study development and
that legitimate concerns be incorporated into the work. Flexibility will
be a key element of the plan of study to allow for accommodation of a
reasonable number of changes to be introduced through the involvement of
the public.
Public meeting programs will be simple and informative. News releases,
including radio announcements, will proceed meetings. Care will be taken
not to start local work before activities are explained to local leaders
and permission for access obtained, if necessary.
A particular constraint to public involvement is the extensive area of the
region. To accommodate the remoteness of many of the native villges and
the limited transportation to them, meetings will be scheduled, as
appropriate, for each study area village or groups of villages. The intent
is to afford reasonable involvement opportunities for those who may have no
practical means to attend meetings in the region's larger villages.
10-12
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
..
-
... -
SCHEDULE
Public participation efforts and involvements will proceed throughout Phase
II.
COST
The anticipated expenditure for Task 2 is estimated at $156,140.
budget estimate is based on the following:
This
ITEM
2.1
2.2
2.3
*
SWEC
Involvement
Interagency Meetings,
Coordination letters, &
phone calls
Regulatory Meetings,
Requirements letters, &
phone calls
Public a) Meetings/
Participation workshops
b) News letters/
announcements
c) Letters/
responses to
to questions
d) Analysis/
documentation
of concerns
Location
Anchorage,
Dill ingham,
King Salmon,
Denver
Anchorage
and Denver
Villages
Villages/
Anchorage
Villages
Anchorage/
Denver
Anchorage/
Denver
Quantity
130 MH
Expenses*
130 MH
Expenses i :
400 MH
Expenses*
Total
Cost
$ 7,020
10,000
7,020
10,000
21,600
100,500
$156,140
Expenses include a total of $ 40, 000 for assistance by Bristol Bay
Native Corporation, $ 20,000 for public opinion poles, and $ 30,000 for
land status investigations .
10-13
TASK 3 -GEOTECHNICAL STUDIES
OBJECTIVE
To perform supplemental geotechnical studies, investigations, and field
surveys, including control and topographic mapping, for the Newhalen or
Tazimina run-of-river generating concepts.
APPROACH
Newhalen River Regional Plant (B-14A)
Continue with the compilation and review of available published and
unpublished literature and reports that cover the region, and project
site. Review presently available geotechnical investigations data and
implement further geotechnical studies as outlined below.
The Phase II geotechnical investigative program for the Newhalen concept
relates to three primary needs:
• Collection of additional data in the vicinity of the powerhouse
and tai lrace
• Collection of data for the conceptual optimization of the
development
• Collection of data for designs commensurate with FERC licensing
application needs
The geotechnical program consists of the following:
•
•
Development of detailed topographic base maps of the project area.
Drilling, sampling, and logging three exploratory borings to
bedrock, with depths of about 70 to 80 feet.
10-14
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
!III
•
..
iii
-
III
•
•
•
Running about 4,500 linear feet of seismic refraction profiles
with target depths of about 100 feet.
Running a total of nine vertical resistivity profiles, in
conjunction with the seismic refraction work.
Performing geologic mapping of the project area at a
reconnaissance level.
Topographic mapping will include ground control (USGS) or other control
datum now used in the project area. Base map(s) will be prepared at a
scale of one inch equals 200 feet, with contours at five foot intervals .
Area to be mapped is approximately 3-1/2 miles long by 1-1/2 miles wide.
In addition, three profiles of the river bottom will be developed at each
end of the canal alignment. These profiles will extend a minimum of 100
feet from the bank into the river.
The three exploratory borings, totaling 240 feet, would be located in the
anticipated powerhouse area. Split spoon drive samples will be taken at
five-foot intervals in each boring. Where appropriate, thawed fine-grained
soils will be sampled by undisturbed thin-wall tube techniques. Samples
will be laboratory tested for classification and other properties. Borings
will extend five to ten feet into rock. Core samples will be taken and
logged. Observation wells for groundwater levels will also be installed in
all borings.
The seismic refraction profi1e(s) will be made using small charges of
explosives. Present patterns of seismic lines are intended to
cross-section the anticipated canal alignment.
Resistivity surveys will be made at 500 feet intervals. These data will
supplement the seismic refraction data.
Following the completion of subsurface explorations and geophysical
studies, the project area will be geologically mapped at a reconnaissance
10-15
level. This will include mapping 1) the nature and structure of exposed
bedrock along the Newhalen River, 2) the nature of surficial soil deposits
exposed in bluffs, and 3) the location of any springs or seeps which
indicate the groundwater regime in the area.
A report will be prepared which would summarize the geology of the area,
field and geophysical explorations, subsurface conditions, laboratory
testing, and a brief summary of the engineering implications of the data.
Tazimina River Local Power Plant (B-19E)
Geotechnical investigations relating to a run-of-river hydroelectric power
project at the Tazimina River will be minimal. There already exists
substantial geotechnical data from the Phase I work that will be utilized.
These data will be reviewed with the run-of-river concept in mind.
Additional geotechnical information, should this site be considered for the
run-of-river development, would consist of:
a.
b.
A field visit to the project area to review and better assess the
areas of suggested civil structures.
Development of a detailed topographic base map of the project area.
c. An engineering field reconnaissance survey along the suggested
access road route.
The field visits to project and access road areas will be made concurrently.
Topographic mapping will include ground control (USGS) or other control
datum now used in the region. Base map(s) will be prepared at a scale of
one inch equals 200 feet, with contour intervals of five feet. The area to
be mapped is approximately three to four miles long by about one mile
wide. River channel profiles will be made, as these relate to civil
structures designs and to plant hydraulic operating conditions.
10-16
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
....
•
iii
....
..
DISCUSSIONS
The previously described geotechnical exploration efforts will be conducted
by Shannon & Wilson, including surveys and topographic mapping. SWEC will
have the overall responsibility for the management of these study efforts
and for the engineering analysis of data compiled from these efforts.
Due to the remote location and restricted access to the project sites, it
is anticipated that most transportation of personnel and equipment will be
by air. It is expected that the base for personnel and supplies would be
at Iliamna.
The geotechnical and survey services outlined above will be made only on
the selected hydroelectric power sites.
SCHEDULING
The geotechnical investigations will start as soon as authorization for
Phase II is given, and as soon as the required permits are obtained. The
actual scheduling and time durations for these efforts will depend upon
what season of the year the authorization is given. It is estimated that
the longer Newhalen River program would take about three months. The
Tazimina River run-of-river plant program would be much shorter .
Cost
The anticipated expenditure for Task 3 is estimated as follows:
a. Newhalen River geotechnical Studies $ 187,500
b. Tazimina River geotechnical Studies $ 40,796
10-17
TASK 4 -HYDROLOGIC STUDIES
OBJECTIVE
To review and update streamflow simulation data for the Tazimina River, if
appropriate, and to compile and evaluate for use in the technical,
environmental, and economic evaluation process hydrologic data for the
Newhalen River. To review) compile, and evaluate ice-related data and its
influence and/or impact on project engineering and design needs.
APPROACH
Tazimina River
The streamflow simulation data developed for the Tazimina River in Phase I
will be reviewed and updated, as necessary, to consider: provisional USGS
streamflow data; a drainage area adjustment; updated precipitation and
temperature data; and other characteristics of the drainage basin.
The upgraded flow simulation data will be used in power studies for the
run-of-river plant. Ice studies of the river, relating to plant design and
possible remedial measures, will also be performed. Plant energy/capacity
studies will consider dry years as well as long-term flow conditions to
ascertain power back-up and purchased power needs.
Newhalen River
Published streamflow records will be used for evaluating the use of
Newha1en River diversions in meeting regional energy needs. The 16-year
Newha1en River continuous streamflow record will be compared to
precipitation and temperature records to determine if any correlation
exists between these data, and whether the 16-year record can be
characterized as a dry, average, or wet period. The results of this
comparison will determine whether it would be appropriate to repeat the
16-year record as a cyclic event for the development of long period of
streamflow data, or whether to utilize available long-term precipitation
10-18
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
...
-
...
and temperature data for calculating simulated flows to supplement the
16-year record. Monthly and yearly flow duration curves will be developed
and will be used in determining the firm and secondary power
characteristics of the proposed run-of-river regional plan, as well as the
possible need for purchased and back-up power.
Ice Studies
Natural icing phenomena, characteristic of cold regions, will be evaluated
to ensure that icing problems will not interfere with the operation of the
hydroelectric facility, wind facility or other proposed ice-sensitive
energy sources. Conditions such as ice shelving, ice build-up, ice
jamming, and the formation of frazil ice will be carefully investigated
both in the field and by office studies, including literature review .
Engineering technologies proven as effective in minimizing ice problems
will be considered and applied where appropriate.
Spillway Design
Neither of the hydroelectric power projects being considered for evaluation
would require a spillway. Since both concepts use run-of-river plants, the
natural stream channel characteristics are not being altered by impoundment
dams. Floods will be contained within the natural topographic boundaries
of their respective drainage areas and river channels. Because of this,
probable maximum flood flow conditions will not be determined. However, a
"standard design" flood condition will be determined with results being
used in the engineering considerations for sizing the plant's civil and
other affected structures.
DISCUSSIONS
The detailed hydrologic efforts, ice studies, and standard design flood
studies, will be performed for both projects. This is because the results
of these studies, alone or in combination, may strongly effect the ranking
of these plans from a technical, environmental, and/or economic
10-19
standpoint.
affected.
Also, the reliability and safety of the projects may be
The above study and evaluation efforts will be performed by SWEC.
SCHEDULING
Since the ranking of proposed hydroelectric power projects is dependent on
the results and findings of the hydrologic studies, the task will need to
be started as early as possible, pending authorization for Phase II work.
Specific scheduling of field related efforts may be affected to some extent
by seasonal restraints (winter-summer). It is anticipated that parallel
efforts can be implemented (Tazimina -Newhalen) with the study being
completed in about 3 to 4 months.
Cost
The anticipated expenditure for Task 4 is estimated at $ 58,080.
10-20
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TASK 5 -ENVIRONMENTAL STUDIES
OBJECTIVE
The objective of this task is to collect pertinent environmental baseline
data, analyze the environmental and social impacts, and prepare impact
assessments for the preferred energy plan. The purpose of the analyses and
assessments will be to: a) minimize adverse impacts and enhance
environmental values; b) identify unavoidable impacts and aid in developing
mitigating measures; c) develop the data needed to compare the
socioeconomic and environmental aspects of the selected plans for the
Detailed Feasibility Analysis; and d) provide the information necessary to
prepare a FERC license application, if required.
APPROACH
Environmental and socioeconomic impact assessments will be undertaken by a
multidisciplinary team of scientists who are experienced in planning and
analysis of energy generation and transmission facilities. Dames & Moore
will have primary responsibility for collection and analysis of
environmental data, while the Institute for Social and Economic Research
will provide SWEC consultation in the area of socioeconomic analysis and
the Bristol Bay Native Corporation will assist SWEC in the area of land
use. SWEC will provide overall management of the study efforts and develop
environmental design review and mitigation measures.
Environmental concerns will be addressed throughout the planning process as
the Detailed Feasibility Analysis evolves. Environmental assessment will
be directed toward issues that are significant to each of the selected
energy plans. The project team will work closely with all relevant
agencies in this task to facilitate an efficient and integrated approach to
project development from the environmental standpoint.
10-21
Impact assessment will be undertaken for the Base Plan and the two
Alternative Plans identified. Regulatory requirements identified in Task 2
will provide the basis and extent of this evaluation. In addition,
specific regional values and concerns will be considered. Details of plans
or facilities will be adjusted if there appears to be opportunity to
further minimize impacts or enhance environmental values without excessive
economic penalties.
The environmental and socioeconomic data collected in Phase I will be
used. Some additional data collection may be necessary for the
run-of-river Tazimina concept and for the Base Plan. A supplementary data
collection program with subsequent analysis will be performed for the
Newhalen concept and its associated transmission line corridors.
Assessment of environmental and social impacts will be prepared for each
plan and will form the basis for the environmental evaluations of each plan
to be presented in the Detailed Feasibility Analysis. Environmental
indicators to be considered, where appropriate, will include:
• Community preference
• Impact on community infrastructure
• Timing in relation to other capital projects
• Air qual i ty
• Water quality
• Fish and wildlife impact
• Land use impact and ownership status
• Terrestrial impact
• Recreation resource value
• Visual impact
In addition to the above, assessment and analysis under this task will
address the specific requirements of a FERC license application (Exhibit E).
Stone & Webster will coordinate the effort between consultants under this
task and take responsibility to include in the Detailed Feasibility
Analysis and FERC License Application, if required, the appropriate data,
analysis, and comparisons.
10-22
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~ ~,' ..
-
Following data collection and analysis, and if applicable, an Environmental
Report will be prepared for the preferred project. Information and
analysis resulting from the environmental study program will be presented
along with other relevant information. Detailed field data will be
included as an appendix.
The following areas will be specifically addressed during Phase II of the
Detailed Feasibility Analysis.
General Area Description
A general description of the environment for the Tazimina and Newhalen
River areas, the diesel generation centers, and wind farm areas, and their
transmission corridors will be made. This description will include
location and general geographic setting, along with other general
information helpful in understanding the environment of these areas.
Fish and Wildlife
The hydroelectric project area(s) supports a diverse compliment of fish and
wildlife. However, none of the mammals, birds, fish, or plants in the area
are considered endangered (Murray, 1980; Taylor, 1979).
Existing information pertaining to aquatic and terrestrial biology of the
project area(s) will be compiled from scientific literature, unpublished
data from resource agency files, and interviews with resource agency field
personnel.
This information will be compiled and analyzed.
impacts of the project(s) will be based on
Analysis of the potential
the habitat mapping in
combination with wildlife use data. Appropriate mitigation measures will
be developed along with an analysis of relative costs and benefits.
10-23
Wildlife Surveys
Project facilities for the regional Newha1en concepts and associated
transmission corridors will traverse portions of the seasonal range of both
the Mu1chatna and Alaska Peninsula caribou herds (Hemming, 1971) as well as
prime moose habitat (ADF&G, 1973). Each of the above species are
especially important for subsistence use and fine sport hunting.
General habitat types based on plant communities will be mapped with the
aid of aerial photographs. The exact area of coverage will be defined
during initial scoping sessions with the Power Authority and resource
agencies.
Both ground and aerial surveys will be conducted to locate key wildlife
habitat and define areas of usage, and will concentrate on the areas
proposed for surface disturbance. Survey transects will be established
where practical, habitats will be characterized (to supplement the habitat
mapping program) and wildlife usage will be documented. Wildlife
observations will emphasize large mammals, raptors, and waterfowl, although
all animal observations will be recorded. Ground surveys will include
observation of scats, tracks, and other signs of use and abundance.
Fish Surveys
Fisheries are the primary biological issue in relation to the proposed
hydroelectric projects. It will be necessary to verify the occurrence and
relative abundance of fish population in Newhalen River between the power
intake and Iliamna Lake. In this reach, a qualitative survey of the
riverine habitat will be conducted in order to characterize the general
productivity. Emphasis will be on identification of high quality habitat,
such as spawning and rearing areas.
Salmon will continue to be visually enumerated. Sample reaches of the
stream will be characterized as to spawning potential, and basic physical
parameters will be noted (e.g., depth, width, flow, velocity, substrate,
etc.).
10-24
I
I
I
I
I
I
I
I
I
I
I
I
-I
I
I
I
I
I
I
c
Stream habitat types, primarily characterized by variations in substrate,
depth, width, and water velocity, will be mapped for the Newhalen River. A
classification system employing four to six habitat types (e. g., riffles,
pools, rapids, etc.) will be established.
The need to provide protection for downstream sockeye salmon migrants
(smolt/fry) has been identified as an important aspect. Existing
information on available fish protection systems indicates that several
options are available which should be highly efficient in diverting or
collecting sockeye fry/smolt for preventing their passage through the power
canal and turbines. However, the information is limited to species other
than sockeye salmon. Discussions and correspondence with the Alaska
Department of Fish and Game (ADF&G) indicate the need for an on-site
evaluation of any proposed fish protection system to determine its
efficiency with sockeye salmon under ambient environmental conditions in
the Newhalen River. Therefore, a scope of work has been developed and
given to the Power Authority for review, which presents a study effort
designed to provide critical information on the effectiveness of several
fish protection systems which appear, at this time, to offer the best
potential for achieving a high degree of efficiency in protecting sockeye
salmon juveniles. Included in this study will be the following:
•
•
•
Construction of a test flume apparatus for modeling
Collection of sockeye salmon smolt and fry for use in test flume
Testing of water diversion systems in the test flume to determine
sockeye salmon smolt and fry protection efficiency
In major streams, such as the Newha!en, Kvichak, Naknek, Egegik, Nushagak,
and Wood Rivers, to be crossed by transmiss ion corridors, aerial
observations, will be conducted with emphasis on salmon and rainbow trout
use in the vicinity of transmission line cross ings.
will be surveyed from the ground.
10-25
Selected waterways
Analysis of impacts and development of
conducted for each potential impact element.
mitigation measures will
Emphasis will be as follows:
be
•
•
Potential effects of river flow change on fish between river mile
RM-7 and RM-1 on the Newhalen River and in the vicinity of the
falls on the Tazimina River
Potential effects and mitigation measures relative to tailrace
discharge on both the Newhalen and Tazimina Rivers
• Potential effects and mitigation measures relative to transmission
line stream crossings
All information will be compiled and analyzed relative to potential project
impacts. Emphasis will be as follows:
• Potential water quality impacts on both the Newhalen and Tazimina
Rivers between the intake and tailrace discharge, including
possible mitigation measures
• Potential fisheries impact and mitigation (information to be
integrated with the results of fish studies)
Hydrology and Temperature Regime
As soon as possible during the field program, stream flow will be measured
at selected river sites on the Newhalen River. Staff gages will be
established on the Newhalen River, and will be read periodically during the
field program. Thermometers will be placed on the Newhalen River near the
proposed site. In most cases, thermograph locations will correspond with
staff gage locations.
Water Quality
Existing information pertaining to water quality of the Tazimina River and
the Newhalen River will be compiled from a review of both published and
unpublished data as well as interviews with resource agency field personnel.
10-26
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
r-
III
f!!!! L ..
c
c
A field data collection program will be conducted in conjunction with the
fisheries studies.
collected:
It is proposed that the following information be
• Baseline water quality of Tazimina River below the intake area
• Baseline water quality of Newhalen River below the intake area
Baseline water quality parameters to be collected and analyzed are given in
the following table.
MEASURED IN FIELD
pH
Dissolved Oxygen
Temperature
Conductivity
CO 2
Alkalinity
BASELINE WATER QUALITY PARAMETERS
MEASURED IN LAB
Turbidity
Total Dissolved Solids
Total Suspended Solids
Total and Ortho Phosphate
Total Nitrogen
Ammonia Nitrogen
Nitrate Nitrogen
Nitrite Nitrogen
Kj ehldahl Nitrogen
Hardness
Chloride
Sulfate
10-27
Arsenic
Barium
Calcium
Cadmium
Chromium
Copper
Iron
Mercury
Potassium
Magnesium
Manganese
Silver
Sodium
Nickel
Lead
Selenium
Silicon
Strontium
Zinc
Air Quality
Power generation, vehicular traffic, and possibly home and' office heating
may produce substantial concentra·tions of hydrocarbons, carbon monoxide,
and nitrogen oxides. An emissions inventory will identify Prevention of
Significant Deterioration (PSD) monitoring or permitting requirements.
In addition, an analysis of diesel emissions will be made at the major
I
I
I
I
I
proposed locations. An analysis of wind generating facilities for noise
and other air quality impacts will also be made. I
Socioeconomics
The social and economic impacts of the Alternative Plans and specifically,
the proposed Newhalen River hydroelectric concept, will involve the
short-term affects caused by construction of the project, notably
employment generation, and the long-term affects related to the increased
availability of less expensive electric power and probably minor affects of
operation and maintenance of the facilities, and the affects of regional
interconnection of presently isolated villages.
Published literature on the economy and culture of the Bristol Bay Region
will be reviewed. Other projects that may have socioeconomic impacts
during the same time frame as the project, or which could cause long-term
changes in the social and economic infrastructure (oil and gas leasing in
federal waters of Bristol Bay is scheduled to commence in 1982, and the
State of Alaska has proposed an onshore "Bristol Bay Uplands" sale for
1982) will also be reviewed. Demographic, social, and economic trends
without and with the project will be discerned.
In addition to the office literature review and telephone contacts in the
area, field trips will be conducted to gain first-hand information and
opinions from the Bristol Bay Region, native groups, residents, and
business leaders on the social and economic infrastructure of the area,
dangers that my occur as a result of the project, and mitigation measures
that should be adopted. Key socioeconomic issues will be identified and
10-28
I
I
I
I
I
I
I
I
I
I
I
I
I
..
• ,. ..
[
-
prioritized. Information on subsistence and recreational activities in the
area of the project will also be collected .
Preliminary analysis will involve review of the three energy plans to
ascertain such factors as employment generation (timing, skills, extent of
local hire, etc.), amount of local purchases of materials and services,
housing of construction workers, logistics, and transportation of men and
materials.
Data and opinions obtained in the field will be compared with the published
data base and rationalized. The key socioeconomic issues will be
identified and possible mitigation measures formulated. Emphasis will be
on an analysis of the following potential impacts:
• The short-term employment effects of the project, including the
timing, nature and amount of employment generated by construction,
and the extent of local hire as well as any competition between
various labor markets
• Secondary employment effects in the transportation and service
sectors
•
•
•
•
The housing and interaction of outside construction workers with
the residents of Nondalton, Newhalen, and Iliamna
Any disturbance or disruption to the local residents or their
culture and subsistence activities caused by construction
activities or the presence of non-resident workers
The long-term effects on the economy of the Bristol Bay region
through the availability of less expensive electric power
Interconnection of isolated communities
10-29
Historic and Archaeological Resources
Preliminary field investigations suggest no known sites of archaeological
or historic importance exist in the Tazimina or Newha1en areas. However,
more extensive field surveys of potentially impacted zones, particularly
along the Newha1en River, will be conducted to confirm or deny the above
indication. A reconnaissance level survey will also be made prior to the
selection of diesel and wind generating sites, and space heating fuel
storage areas.
I
I
I
I
I
I
If a site of cultural importance is discovered, an appropriate program of
investigation will be initiated to determine the steps to be taken to I
either preserve or clear the area for development.
Recreation and Aesthetic Impacts
The Bristol Bay area supports numerous hunting and fishing lodges. The
area also contains the extensive Wood-Tikchik State Park, Mt. Katmai
National Park and Preserve, Lake Clark National Park and Preserve, Togiak
National Wildlife Refuge, and Becharof National Wildlife Refuge. Each
year, an increasing number of tourists and Alaska residents travel to the
region for their recreation.
The analysis will include study of recreational use patterns and visual
impacts of industrial structures, roads, and powerlines. This analysis
will include a description of any area within, or in the vicinity of,
proposed projects, and areas crossed by transmission corridors that are
included in, or have been designated for study for inclusion in:
• The National Wild and Scenic River System
• The National Trails System
• A wilderness area designated under the Wilderness Act
10-30
I
I
I
I
I
I
I
I
I
I
I
I
t· ...
c
Maps and reports will be prepared, as appropriate, indicating existing
conditions, existing use, constraints, and opportunities. This information
will be compiled through cooperation with the Alaska Department of Natural
Resources, Planning Division.
At the present time, there appears to be a demand for recreation in both
the Newhalen and Tazimina areas, and the close proximity to the Lake Clark
National Park assures increasing potential in the future.
A majority of the Newhalen and Tazimina study sites are open, low-growing
spruce forest and offers no visual screening. Present and future use
patterns, natural contours, and visual horizons will be important analysis
data in regard to transmission line location.
Similarly, the sites for potential wind farm locations, in the Igiugig,
Naknek, and Egegik areas, offer little to no visual screening. Efforts
will be made to minimize this impact to the maximum extent possible.
Land Use
Existing land uses within, and adjacent to, the proposed project areas will
be described, including those land uses which would occur if the project is
constructed. The description will include the identification of wetlands,
flood areas, and lands owned or subject to control by government agencies.
Aerial photographs, maps, and other graphics will be used to identify the
location, extent, and characteristics of these land uses.
Transmission Lines
The objective of transmission line environmental impact analysis will be to
guide plan development, minimize adverse impacts, enhance environmental
values, and aid in developing mitigation measure if impacts are unavoidable.
10-31
In general, the first step in transmission environmental analysis will be
to identify present level use along technically preferred routes. Specific
factors to be considered include:
•
•
•
•
•
•
•
•
•
•
Wildlife habitat
Timber and agricultural resources
Recreational use
Visual sensitivity
Demographic trends
Transportation systems
Archaeological significance
Hydrology
Land ownership
Special uses which are not compatible with transmission lines
After present land use factors have been determined, analysis will be
undertaken to predict the environmental effects of transmission
construction, operation, and maintenance. A proposed route will be judged
with respect to each evaluation factor.
Certain values identified as important to residents of the region will be
given special weight. Identification of these values will be an important
element of the public participation program of Phase II described in Task
2. An example of such a value is Native concern about access along
transmission routes to hunting and fishing grounds.
DISCUSSION
The environmental studies out lined above relate to all three study plans,
with the greater emphasis being on the regional Newhalen hydroelectric
concept.
Dames & Moore will undertake the environmental data collection work from
their Anchorage office, while SWEC will assist in the feasibility
assessment. A project management organization and plan will be used that
is based on successful experience on similar projects to ensure control of
technical activities, schedule, and budget for the project. Dames & Moore
10-32
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
c
-..
will maintain an open line of communication with Stone & Webster
Engineering Corporation and the Power Authority throughout the duration of
the study. Their Project Manager and Permits Coordinator will be available
for frequent communications with the government and will assist in
interagency meetings.
The primary management goal will be to complete a comprehensive, objective
environmental feasibility analysis that meets the objectives of FERC, NEPA,
and the relevant regulations. The approach to managing the study will be
structured to achieve this objective. Technically competent managers will
provide the guidance necessary to ensure that project team members have at
hand all the information' needed to accomplish their assigned evaluations.
Upon receipt of authorization to proceed, the Dames & Moore Project Manager
will prepare
background of
a detailed project plan. This
the project, identify relevant
plan will outline the
guidelines and documents,
define project responsibilities, and assign time and budget constraints in
which the work must be performed.
SCHEDULE
Environmental studies will be ready to start as soon as Phase II work is
authorized. However, because of climatological restraints, certain
activities may be delayed until warmer weather. There will be literature
reviews and reconnaissance surveys that can, and must, take place during
the winter months. Upon commencement of field activities, all
environmental baseline data will expect to be completed within one year.
BUDGET
The anticipated expenditures for Task 5 are estimated at $ 739,900,
including the following components:
• Water Use and Quality $ 24,400
• Wildlife Surveys and Terrestrial Ecology $ 103,800
• Historic and Archaeological Resources $ 13 ,400
10-33
I
• Recreational and Aesthetic Resources $ 24,400 I
• Socioeconomics $ 30,000 I
• Land Use $ 6,000 I
• Air Quality $ 5,800
I
• Fisheries Studies
I
• Diversion Studies $ 307,300
• Resident Fisheries Studies $ 202,400 I
-Habitat Characterization $ 22,400 I
It is believed that the above described program will provide sufficient I
information for the purpose of preparing an environmental report and/or
Exhibit E for a FERC License. Not included in the above estimate for the I
Phase II scope of work are the extensive fisheries studies suggested by the
Alaska Department of Fish and Game (ADF&G) if a regional hydroelectric
scheme is to be cons idered on the Newhalen River. However, should it
become necessary to develop a program which will respond to the suggestions
of the ADF&G (see Section 8.2, letters of comment, for details), the scope
of work will have to be increased considerably. Some of these specific
suggestions include: 1) adult salmon upstream enumeration (4 years); 2)
juvenile sockeye salmon downstream enumeration (4 years); 3) distribution
characteristics of outmigrating juvenile salmon; and 4) a winter juvenile
salmon studies program. The development and implementation of these
specific studies would increase the budget estimate by about $3.5 to $4
million. Because of the amount of time required for such studies, and the
expenses involved, it is recommended that as soon as practically possible,
the Power Authority and SWEC meet with the ADF&G to determine the actual
study requirements and when these studies should be conducted.
10-34
I
I
I
I
I
I
I
I
I
r
It
..
..
TASK 6 -CONCEPTUAL DESIGNS & PLAN COMPARISONS
OBJECTIVE
To provide the conceptual designs for detailed comparisons of selected
plans and perform detailed design on the preferred plan for the purpose of
the feasibility analysis.
APPROACH
Phase II of this task will consist of engineering and design studies for
the Base and selected Alternative Power Plans. Various combinations of
structures, systems, and equipment will be considered for each plan. These
studies will be performed concurrently with: 1) environmental studies; 2)
economic evaluation studies and; 3) Base and Alternative Plan comparison
studies. The purpose of these efforts is to allow for an assessment of
findings for use by Power Authority in its decision making process.
Work will concentrate on conceptual designs to establish physical concepts
and arrangements of the structures, equipment, and systems required in
providing the energy needs of the region. These will include, as
appropriate: 1) hydorelectric power generating facilities and structures;
2) wind electric generating facilities and structures; 3) transmission
facilities, including line routing, towers, foundations, substation and
switchyard facilities; 4) access roads, bridges, and culverts; 5) land
clearing requirement; 6) construction material borrow and spoil sites; 7)
camp site location (required by future construction efforts), 8) diesel
generating plants, facilities, and corresponding waste heat recovery
systems; and 9) other civil/environmental-related physical arrangements.
Designs, sketches, and drawings will be prepared in such detail as is
necessary to ensure feasibility level details for use in quantity take-off
for cost estimating, and for depicting the intent and method of the concept
being presented .
10-35
A comprehensive list of economic, environmental, and technical indicators
will be prepared, based on the evaluations and analysis of tasks. The
selected Alternatives will be compared to the Base Plan with respect to a
number of factors which fall within the three primary indicator groups.
Comparisons will be quantitative to the extent possible. Such comparisons
should be possible for project cost and for other engineering
characteristics. Some environmental comparisons will be qualitative,
reflecting the judgment of the evaluator. Public input will also be an
important consideration in making qualitative comparisons.
All of the factors that fall within a major indicator group (economic,
environmental, or technical) will be considered as a whole, and the
selected Alternative Plans will be compared to the Base Plan with respect
to that indicator. This conclusion will be reached regarding the
feasibility of the selected Alternative Plans as compared to continuation
of existing practices in the Bristol Bay Region.
DISCUSSION
Data developed will be provided to the Power Authority, if required, at
appropriate time periods, along with progress status reports for review and
comment.
The conceptual efforts will be performed by SWEC. Other group members of
our project team will participate in an advisory or "data supply" capacity.
It is anticipated that work products from the conceptual design efforts
will need to be provided to Federal, State, and local agencies and/or group
for appraisal or review and comment. An appropriate time limitation for
review and comment by agencies and/or groups will be required.
10-36
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,. ..
-
Conceptual designs will be done at different times and at a Level III
effort, as required, for the Phase II study analysis which is the detailed
assessment of the selected alternatives. The classification of this level
is as follows:
• Level III -At this level, the selected plans are to be optimized
with respect to environmental, technical, and cost aspects.
Detailed field investigations and data collection will be
performed, as required, for use in the optimization process. At
this level, detailed conceptual engineering and design will be
performed, including preliminary stability analyses, power plant
sizing, and optimization of the equipment and systems evolved as a
result of previous conceptual efforts. Optimization would include
varying the combinations of power generation concepts, power
equipment, plant structures, transmission facilities, and other
plan components.
The technical and economic aspects relating to the transmission lines and
substations for the Base and selected Alternative Plans will be developed .
SWEC will coordinate with existing and planned Rural Electric Cooperative
systems (REA) as well as Federal, State, and local agencies. The
objectives of coordinating efforts are to ensure the direct participation
of agencies, and the exchange of information of common interests. Design
criteria and parameters will be established. Coordination efforts will
consider: type of construction and line design; line routing and
reliability; grid system interties and substation locations; and the all
important'phases of construction and line maintenance.
Transmission line cost, which relates to the above described consideration
as well as to considerations for enVironmental/socioeconomic aspects, will
be developed. The detail of conceptual designs I and resultant physical
products and cost estimates, will reflect a Level III detailed assessment
which is defined as:
• Level III, -At this level, the selected Alternative Plan, along
with its transmission line corridor and substation requirements I
is to be optimized. Detailed field investigations and data
10-37
I
collection, as required for use in the optimization process, will II
be performed. At this level, engineering and design studies will
be made to develop line profile and to refine line design, tower
design, design(s) for crossings, and foundation conditions.
It is unlikely that one plan will be found superior to others for all
factors or indicators. Accordingly, in making comparisons, it may be
necessary to assign weights to various factors to indicate importance. In
addition, acceptability criteria can be established to prescribe the limits
within a particular factor must lie for a plan to be considered viable.
Such subjective evaluation methods must be employed with great care. SWEC
will consult with the Power Authority prior to implementing such techniques.
This task will provide the basis for the conclusions and recommendations of
the Detailed Feasibility Analysis.
SCHEDULING
The Phase II Conceptual Design Task is scheduled to begin upon
authorization of Phase II work. Plan comparisons shall be performed
essentially in parallel with conceptual studies, and other tasks relating
to economics, technical data collection, environmental data collection, and
public and agency coordination.
COSTS
The anticipated expenditures for Task 6 are estimated at $114,820. This
I
I
I
I
I
I
I
I
I
I
I
budget is based upon the following: I
a. Conceptual Optimization
Efforts
b. Plan Comparisons
$ 76,500
$ 38,320
10-38
I
I
I
I
I
... ..
...
II
-.
..
TASK 7 -ECONOMIC EVALUATION
OBJECTIVE
To establish the economic feasibility, a plan of financing, and a plan of
marketing for the Base Plan and for each of the selected Alternative Plans.
APPROACH
General
The economic feasibility, financing, and marketing evaluations will be
closely coordinated with, and based upon, many other tasks performed in
Phase II. Each Alternative Plan will be evaluated with respect to:
1) present worth of plan cost, as compared to the Base Plan; and 2) cost of
power.
Economic Studies
These studies will be designed to establish the cost of each of the
selected power plan concepts for the purpose of making feasibility
comparisons.
Economic evaluation studies will consider various assumptions which can
affect the economic feasibility of each study plan, including such items as
discount rate, relative price trends. the electric load growth assumptions.
and the planning period. Also, the economic studies will consider project
construction costs, operating-maintenance costs, administrative costs, the
possible effect of the power plans on the environment, and estimates of
major indirect cost and benefits. Hypothetical financing conditions for
cost-of-power estimates,
interest rate(s), and
including debt-equity ratio,
inflation rate(s), will be
term of financing,
addressed. Data
applicable to the economic studies supplied by the Power Authority will be
used in these efforts.
Cost estimates will be made during the conceptual design and during the
performance of other cost impacted early tasks. Concepts and drawings of
optimized plant structures will be developed to that detail that will
10-39
result in an order-of-magnitude cost estimate and economic studies having
an accuracy in the range of plus or minus 15 to 20 percent.
Financial Studies
Financial requirements and alternate modes of financing will be studied for
the three power plans to determine the most feasible financial plan.
Financial analysts will research the various entities in Alaska that might
undertake financing for any, or all, of the viable power plans. Various
forms of financing, as well as their likely cost, will be investigated.
Existing entities in Alaska that might finance the project will be
determined and reviewed with the Power Authority. Potential candidates
will be studied to determine whether there are any impediments (legal,
financial, or otherwise) to their involvement. Articles of incorporation
and indentures would be researched for any restrictive convenants which
might impair the financing of a project.
Other forms of financing will be investigated for each project such as
formation of new agencies, project financing, high-debt power supply
corporation (investor-or state-owned), and conventional financing
alternatives by cooperative-, municipal-, or investor-owned companies.
Consideration of such important factors as revenue versus general
obligation bonds, and On-versus Off-Balance Sheet treatment of debt, will
playa dominant role in any such analysis.
I
I
I
I
I
I
I
I
I
I
I
I
Scenarios considering no state appropriation and 100 percent debt
financing, and minimum state appropriation with no return on investment I
will be considered.
Marketing Studies
The three selected power plans will be studied to identify strategies
necessary to properly market the electric power produced under each plan.
The marketing strategies will address the value of electric energy relative
to other substitute energy forms, existing and future regional
constituencies for electric power, and the impact of alternative electric
10-40
I
I
I
I
I
.. ..
.. ..
-
-.. .. ..
..
..
energy delivery systems. The goal of each strategy will be to -deliver
electric power to the customer at the lowest possible cost .
DISCUSSION
The study task will conform to Power Authority I s feasibility regulation 3
AAC 94-06, and the guideline outlined in the Cost Calculations-FY 1983
procedures.
Input, as it may relate to energy demand forecasts for the region or
regional sectors, will be based on the work done by ISER.
Stone & Webster Management Consultants will be responsible for the
performance of the financial and marketing studies, and for the preparation
of a financial and marketing plan for the most feasible alternative for
developement.
Considering the magnitude of the proposed undertaking, any analysis may
require joint utilization of mUltiple sources of funds. Such an approach
would necessarily require guarantees from involved parties such as
sponsoring agencies, consumers, and government agencies. The financial
institution will then be consulted as to probable terms and conditions and
the cost to carry out the particular financing plan.
Each selected power plan will have a specific financing plan or may have
common financing plans. Those options requiring special consideration due
to size or complexity, however, will be identified and their specific plan,
including basic terms, conditions, and costs will be detailed in the final
report .
SCHEDULE
The Economic Evaluation effort is scheduled for a period of about four
months. During this period, the economic, financial, and marketing aspects
of the power plans will be evaluated -considering direct and indirect
costs, technical and environmental data, and socioeconomic data compiled at
the time .
10-41
I
COST I
The anticipated expenditures for Task 7 is estimated at $77,688. I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
10-42 I
III
..
-
-
TASK 8 -FEASIBILITY REPORT
OBJECTIVE
To prepare a Detailed Feasibility
technical, and environmental aspects
relation to the Base Plan.
APPROACH
Report that
of the two
compares the
Alternative
economic,
Plans in
The results of the Interim Feasibility Assessment will be compiled and
presented in summary form in the detailed feasibility report identified
above. The Interim Feasibility Report documents the studies which lead to
the interim assessment of the scenarios. The detailed report will describe
approaches taken and methods used, outline study assumptions, summarize
pertinent facts and data, and compare the selected Alternative Plans in
relation to the Base Plan. Power Authority regulations (3AAC 94.060) will
be followed in the preparation of this report. The Detailed Feasibility
Report will document both Phase I and II of the study and will present
recommendations with respect to further studies, data collection to support
FERC and definitive engineering-design requirements, and future actions for
licensing and/or design-construction.
The Detailed Feasibility Report will be prepared and issued first as a
draft for review and comment, and second in its final form. SWEC
anticipates publishing a minimum of 40 copies in draft form and 100 copies
of the final report. The final report will contain responses to review
comments received on the rough draft .
DISCUSSION
Compilation and formulation of data and information for the report, as well
as the preparation and publication, will be SWEC t S responsibility. Other
project team groups will participate by contributing individual reports on
their assigned tasks and findings.
10-43
Individual reports will be prepared on each of the major tasks, as
necessary. Such reports will be of sufficient detail to allow for their
use, with minor revisions to the format, for permit and FERC licensing
application.
As presently envisioned, the Detailed Feasibility Report will be
supplemented by appendices covering power demand forecasts, al ternati ve
power plan studies, engineering and technical data, and an Environmental
Report.
A general outline proposed for the Detailed Feasibility Report follows:
Detailed Feasibility Report Outline
Executive Summary
Introduction
Demand Forecast
Electric Energy Supply Technology
Alternative Power Plans
Comparison of Alternatives
Technical
Economic
Environmental and Socioeconomic
The Selected Plan
Technical
Economic
Environmental and Socioeconomic
Conclusions
Appendices
SCHEDULING
Scheduling of report initiation and completion will greatly depend on the
timing and collection of needed data. This process, in turn, will
10-44
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
..
.. .. ..
-..
... .. ..
.. .. .. .. ..
-..
-.. .. -
-•
-
depend upon the timing (with respect to season) of authorization to proceed
with the Phase II Studies. It is anticipated that about six months will be
required for the preparation of the report as a continuous task effort .
COST
The anticipated expenditures for Task 8 are estimated at $73,500.
10-45
TASK 9 -FERC LICENSE APPLICATION
OBJECTIVE
To prepare a license application,as required, for one of the Alternative
Plan Scenarios in accordance with current requirements of the Federal
Energy Regulatory Commission (FERC).
APPROACH
A FERC license application will be prepared if either the Newhalen Regional
or the Local Tazimina River plan is determined to be feasible, and if the
Power Authority so directs. Most of the data required for the application
will be developed as part of the previous tasks. Certain exhibits (e. g. ,
Environmental Report) will be prepared as part of another task. Other
exhibits will require the assembly into the required format.
Stone & Webster Engineering Corporation will take responsibility for
assembling and publishing the information for the FERC application.
SCHEDULE
It is assumed that the decision to prepare a FERC application will follow
acceptance of the Detailed Feasibility Report. The projected schedule is:
• Decision to Proceed with a
Hydroelectric Project
• Submitted FERC License
Application
COST
Two months after issue of Final
Detailed Feasibility Report
Three months after decision to
"Proceed with a Hydroelectric
Project"
The anticipated expenditures for Task 9 are estimated at $63,010. This does
10-46
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
•
not include response to questions during the review process after
acceptance of the application .
10-47
TASK 10 -GENERAL ADMINISTRATIVE
OBJECTIVE
To establish a task for which various administrative charges are controlled.
APPROACH
Charges relating to administrative matters will be accumulated under one
single task rather than prorated to all other tasks.
Administrative charges consist of time and expenses not directly identified
with the engineering or technical tasks of the project. These charges
include activities of the Project Manager, a portion of the time of the
Project Engineer, contract administration, project reports, and accounting.
SCHEDULE
Throughout the duration of Phase II efforts.
COST
The anticipated expenditure for Task 10 is estimated at $141,480.
10-48
I
I
I
I
I
I
I
I
I
I
I
I
I ,
I
I
I
I
I
liliiii
.-..
IIIIlII ..
BUDGET SUMMARY
The estimated budget required for the Scope of Work in Phase II is
$1,702,554. This estimate is based on the work being accomplished in 1983.
Task
1
2
3
4
5
6
7
8
9
10
Title
Energy Demand Analysis
Regulatory Coordination and
Public Participation
Geotechnical Studies
Hydrologic Studies
Environmental Studies
Conceptual Designs and Plan
Comparisons
Economic Evaluation
Feasibility Report
FERC License Application
General Administrative
TOTAL PHASE II BUDGET
10-49
Phase II Budget
$ 49,640
$ 156,140
$ 228,296
$ 58,080
$ 739,900
$ 114,820
$ 77 ,688
$ 73,500
$ 63,010
$ 141,480
$1,702,554