Loading...
HomeMy WebLinkAboutFindings and Recommendations Scammon Bay Hydroelectic Project 1985ALASKA POWER AUTHORITY Summary FINDINGS AND RECOMMENDATIONS SCAMMON BAY December 5, 1985 Development of a hydroel ectri c project at Scammon Bay has been discussed and investigated by the community and State and Federal agencies for over six years. While once considered a feasible project, recent economic trends and advances in diesel generator efficiency now show that a hydroelectric project cannot compete economically with the continued use of diesel generators to supply the electricity needs of the community. Other energy alternatives, including waste heat recovery and wind power generation, have been analyzed, but none appear to have sufficient potential to justify further feasibility studies. Continued improvement in diesel generator and system efficiencies would benefit the community and should be implemented. Background and Previous Studies Scammon Bay is a Native comTIunity with a population of approximate- ly 300 located in the Yukon-Kuskokwim Delta region on the southwest coast of Alaska 150 miles northwest of Bethel and 30 miles north- east of Hooper Bay. The community is served by the Alaska Village Electric Cooperative (AVEC) with three diesel generators (110 kW, 105 kW, and 75 kW). According to records submitted by AVEC over the past year to the Power Cost Equalization Program, the existing total electric load in Scammon Bay is approximately 426,000 kWh/ year. The weighted average diesel generator efficiency is current- ly 9.5 kWh/gallon. The Alaska Power Administration completed the Small Hydroelectric Inventor~ of Villages Served b~ Alaska Village Electric Cooperative in Decem er 1979, concluding, ased on initial calculations, that a site at Scammon Bay had potentiai for hydroelectric development and warranted further investigation. The conclusion was based on an estimated average streamflow of 9 cubic feet per second (cfs). Northern Technical Services and Van Gul ik and Associates, under contract to the Alaska Power Authority, prepared a Reconnaissance Study of Energy Requirements and Alternatives for Togiak, Goodnews Bay, Scammon Bay, and Grayling, dated February 1981, and a "Report Summary" for Scammon Bay dated April 1981. This study recommended energy conservation, coll ection of wind data, continued use of diesel generators, and further investigation of the feasibility of a hydroelectric system. It found that the location of the power plant was not suitable for development of waste heat recovery. 2154/517 C;cA 0":"- Findings and RLJlnmendations: Scammon Bay December 5, 1985 Page 2 The U.S. Army Corps of Engineers, Alaska District, completed its Scammon Bay, Alaska: Small Hydropower Interim Feasibility Study and Environmental Assessment in ~1arch 1982. It further analyzed the energy options presented in the 1981 reconnaissance study and conducted a deta'iled feasibil ity assessment of the hydroelectric alternative. It 'also conducted hydrologic measurements which showed that the actual average annual streamflow at Scammon Bay was 2.5 cfs, significantly below the value assumed in the 1979 analy- sis. The major findings of the Corps' 1982 study were as follows: (1) A 100 kW hydroelectric system with diesel backup would provide the best alternative for electrical generation at Scammon Bay with a benefit/cost ratio of 1.20. (2) Wind power could complement the hydroelectric system by providing an additional alternative source of energy during winter months when hydropower potential is poor due to low streamflows; however, additional wind data would be needed in order to accurately assess this potential. (3) Waste heat recovery from existing diesel generators would not likely be feasible due to the distance between the power house and major potential waste heat users. (4) Improved weatherization through insulation, storm windows, and weather stripping would provide significant savings to the community in reduced heating costs and should be pursued to the maximum extent possible by the community. The Corps of Engineers proceeded with its formal approval process in an attempt to acquire funding for the recommended hydroelectric project. However, in May 1984, the Assistant Secretary of the Army recommended to the U.S. Office of Management and Budget that further expenditure of federal funds on the project was not war- ranted and that the project should be the prerogative of local interests. (See Appendix A, letter dated 3 May 1984.) Current Hydropower Analysis Upon the Corps' relinquishment of the project, the Alaska Power Authority reviewed the 1982 feasibility study and updated its economic analysis. (See Appendix B, memo dated September 18, 1984.) The update analyzed the project using both Corps of Engineers and Power Authority evaluation methods and current economic parameters. A major difference between the evaluation methods used by the Corps and the Power Authority is that the Corps analysis includes the effect of local employment benefits resulting from development of the project. The evaluation using Corps methods was performed in the same manner as the 1982 analysis with four changes to economic parameters: (1) all costs were updated from 1982 dollars to 1984 dollars using a 3.5% average annual inflation rate; (2) the cost of 2154/517 Findings and RE:. ,nmendations: Scammon Bay December 5, 1985 Page 3 debt was updated from 7.875% to 8.375% (real), the standard rate currently used by the Corps on federal projects; (3) the base price of diesel fuel was changed from the 1982 price of $1.68/gallon to the July 1984 price of $1.25/gallon; and (4) the fuel escalation factor used to convert the current cost of diesel fuel to an equivalent annual cost for the life of the project was changed from 1.74 to 1.44. Under this method of analysis, the benefit/cost ratio of the recommended 100 kW hydroelectric project decreased from 1.20 using 1982 prices and economic parameters to 0.79 using the updated data. Using Power Authority project evaluation methods and economic parameters, a similar conclusion was reached (Appendix B). The project was analyzed using a 3.5% real discount rate and a real annual fuel escalation rate of 0.0% through 1988 and 3.0% from 1989 to 2005. Other assumptions were the same as those used in the Corps analysis including the cost estimates, a 4.5% annual load growth, and a 7 kWh/gallon diesel generator efficiency. Under Power Authority project evaluation methods and economic parameters, the benefit/cost ratio of the hydropower project was 0.74. The Corps of Engineers was requested to confirm the updated analy- ses and did so in a letter dated May 1, 1985 (Appendix C). The Corps expanded on the Power Authority's update by reanalyzing three sizes for the potential hydropower system (75 kW, 100 kW, and 125 kW). An update of the hydrologic analysis based on additional streamflow data revealed greater potential for power generation than estimated in the 1982 feasibil ity study. However this in- creased potential was not suffi ci ent to overcome the effects of decreased fuel prices, the increased federal-project real interest rate, and increased diesel generator efficiencies. The Corps' updated analysis used the January 1985 diesel fuel price of $1.20/gallon and projected an average diesel generator efficien- cy over the life of the project of 11 kWh/gallon. The 1982 analy- sis was based on an average generator efficiency of 7 kWh/gallon which did not incorporate the efficiency factor of the new 105 kW generator installed that year. The current efficiency with the new generator is 9.5 kWh/gallon and the Corp assumes this efficiency will increase by two percent per year to a maximum efficiency of 13 kWh/gallon in year 2000, resulting in an average efficiency of 11 kWh/gallon over the life of the proposed project. The updated analysis indicated benefit/cost ratios ranging from 0.70 to 0.79 depending on the size of the hydropower system. These analyses clearly show that, using updated economic parame- ters, a hydropower project at Scarrmon Bay is not economically feasible. Since the completion of the updated analyses, the price of diesel fuel at Scarrvnon Bay has continued to decline (the April 1985 price was $1.16/gallon). This price decline would cause a further reduction in the benefit/cost ratio. 2154/517 Findings and Re __ .I1mendations: Scammon Bay December 5, 1985 Page 4 Waste Heat Recovery and Wind Power Potential The potential for waste heat recovery and wind power at Scammon Bay was addressed in the Power Authority's 1981 reconna i ssance study and was discussed in the Corps of Engineers' hydropower feasibility study. A recent site investigation and comparative analysis with waste heat and wind projects in other rural Alaska communities has confirmed that the potential for these energy alternatives is insufficient to warrant feasibility-level analysis. The location of the power house at Scammon Bay is the major impedi- ment to waste heat recovery. Potential customers or users of waste heat are located too far from the power house to economically justify installation of a waste heat recovery system. Although wind is an abundant resource at Scammon Bay, the current state-of-the-art of wind power technology is not capable of provid- i ng sign ifi cant, economi ca 1 power generation for the commun ity. The average load (50 kW) at Scammon Bay is lower than the rated output of cost effective units now marketed. In addition, integra- tion of a wind system into an existing diesel generation system of this size would produce load control problems which cannot be solved with commercially available equipment. Such integration would require a means of handling system frequency and voltage fluctuations and a method for maintaining synchronization or preventing over-acceleration of induction generators. Load control and load dumping systems designed to mitigate these effects have not been adequately tested and approved for commerci a 1 di stribu- tion. Power System Efficiency Improvements to the existing diesel generation and distribution system to increase system efficiency appear to be the best alter- native for reducing energy costs at Scammon Bay. AVEC is currently making improvements and upgrades to the distribution system which should significantly improve its efficiency by decreasing line loss. Other improvements that would increase efficiency would be replacement of generators when necessary with newer more efficient models, installation of remote radiators and variable speed fans, and assurance that power is provi ded by operati ng generators of appropriate size to optimally meet the demand at any given time. Recommendations 1. Discontinue any further investigations, analysis, or studies with respect to hydroelectric development at Scammon Bay. 2. Discontinue any further investigations, analysis, or studies with respect to the feasibi 1 ity of waste heat recovery at Scammon Bay. 2154/517 Findings and Rt ,nmendations: Scammon Bay December 5, 1985 Page 5 3. Discontinue further investigations, analysis, or studies with respect to the feasibility of wind power generation at Scammon Bay unless and until advances in technology improve the potential for development of such systems in remote areas with low power demand. 4. Recommend the completion of the ongoing upgrade of the distri- bution system and the implementation of other improvements to the diesel system that would increase overall efficiencies. 2154/517 APPENDIX A ')EPARTMENT os; THE ARMY OFFICE OF THE ASSISTANT SECRETARY WASHINGTON. DC 20)10 Honorable David A. Stockman Di r ec to r Office of Management and Budqet Washington, D. C. 20503 Dear Mr. Stockman: I am submitting a copy of the report of the Chief of Engineers on Scammon Bay, Small Hydropower Project, Alaska, together with other pertinent reports. Thes~ are furnished in accordance with Executive Order No. 12322 dated September 17', 1981. The report has been prepared in partial response to a Senate Public Works Committee resolution of October 1, 1976. Th e repo rt recommends Fed er al construe tion 0 f a small hydropower plant at Scammon Bay, Alaska. Since the report does not identify ~ny efficiencies to the Nation from Federal implementation of the project, the construction of this plant should be the prerogative of local interests. Accordingly, we propose to advise the Congress that the study has been completed and that expenditure of Federal funds for further planning or implement~tion is not warranted. please provide information regarding the rela- tionship of the report of the Chief of Engineers "nd our pro posed ac tion to the prog r am of the Pr esid en t. A proposed draft of a letter to the Congress is enclosed. 8 Enclosures (See ~ t tachmen t fo r list of enclosures) Sincerely, 1S~&lled[ ..... -~ Wil1i~m R. Gianelli Assistant Secretary of the Army ( C i v 11 Wo r k s ) A-I APPENDIX B I MEMORANDUM State of Alaska TO THROUGH: FROM. /) Orent N. Petri e O~ Acting Associate Executive Director of Planning' '-I' Dave Denig-Chakroff, / ,.:.../ Proj ect ~'anager ' Robert E. Harris (}AJi.-- Economi 5 t '(!IlIJl DATE FILE NO: TELEPHONE NO: SUBJECT September 18, 1984 Scammon Bay Economic Analysis Comparison of the Alaska Power Authority's April 1981 Reconnais- sance Study of Energy Requirements and Alternatives for Scamnlon Bay with the U. S. Army Corps of Engineers (Corps) ~larch 1982 Scar.:non Bay, Alaska, Small Hydropower Interim Feasibility Study and En- vironmental Assessment report shows that while procedural differ- ences exist in the composition of the economic analysis, the proposed Scammon Bay project, under current project evaluation parameters, is economically unfeasible. Principally, interest rates have risen appreciably since the writing of both of these reports, and oil prices have fallen, rather than increasing, as was assumed would occur. To assess the impact of these actualized conditions, we met with Dennis Wagner and Carl Borash of the Corps to reevaluate the economic analysis based upon current data and forecasts. Their preliminary analysis supported the findings shown in this memorandum. This strongly suggests that the Corps might desire to formally re-evaluate this project and re-issue its findings based upon current and forecast economic parameters. The following table shows the assumptions used in the Corps of Engineers report and compares them to current data and assumptions. Corps of Engineers Analysis Parameters Now (1984) Diesel Costs Diesel Escalation Factor 1 Then (1982) S1.68/gal. 1.74 (on-line in 1984) $ 1.25/gal. 1.44 {on-line in 1987} Interest Costs 2 Inflation 3 7 7/8% N/A 8 3/8% N/A 1. Diesel Fuel Escalation Factor represents the long-term average expected increase in the cost of diesel fuel. These factors are necessarily dependent upon the on-line date of the facility under consideration. 2. Interest costs as used by the Corps are based upon an average of long term {15+ years} bond rates. 3. Inflation is assumed to affect benefits and costs equally and therefore is ignored in the economic analysis. Table 4.1, Project Ccst.s and 8enefits, from pg. 27 of th~ (nrr:s report, is shown below with the analysis perforn~d using the updated parameters shown in the far right column. Table 4.1 Project Costs and Benefits First Cost 1 tl.nnua 1 (os ts interest and AmortiZc3.tiGn 2 1 Interest During Construction Operation and Maintenance 1 Total Annual Cost Annual Benefits Diesel Displacement Benefit 3 Fuel Escalation Benefits 4 1 Operation and Maintenance Benefit Employment 5 Total Annual Benefits Net Annual Benefits 8enefit-Cost Ratio Assumptions 1 ) Escalated at 3.5% per year 1 (10/82) $),483,000 120,000 3,OO(J 22,000 S 145,00(' $ 70,0(10 52,000 23,000 25,000 $ 170,000 4: 25,000 .., 1. 2 to 1 ') , '-i For 10/82, calculated at 7 7/8% for 50 yrs. For 10/84, calculated at 8 3/8% for 50 yrs. 3) For 1('/82, based upon diesel cost of 51.66/9a 1 • For 10/84, based upon diesel cost of 51.25/gal. (fuel efficiency of 7 kWh/gal) 2 (10/84 ) 1,588,000 135,000 3,200 23,500 161,700 52,700 23,200 24,600 26,800 127,300 (34,400) 0.79 tG 4) For 10/82, based upon the Corps diesel fuel escalation factor of 1.74 (1984 on-line date) For 10/84, based upon the Corps diesel fue1 escalation factor of 1.44 (1987 on-line date) 5) Employment benefits are included by the Corps of Engineers to recognize the impact of projects on economically depressed areas. Area must show "persistent end substantial unemploy- ment", i.e unemployment rate in local area must exceed the national average by 100% for one of the previous two years or by 75% for two of the previous three years, or by 50% for three of the previous four yedrs. 5048j;'47/d2 B-2 1 Eccnomic Analysis Using Power Authority Methodology Using the evaluation parameter of t.he Power Authority and the cost and load growth estimates of the Corps of Engineers, the following econCJf~';c analysis was performed. Total Present Werth Net l3enefits Benefit-Cost Ratio Assumptions Table 1 Results of Economic Analysis (l98~ Dc 11 a rs ) .?carnmon Bay Hydropower 3,114,000 (798,000) 0.74 The following assumptions were used in this analysis: 1) 3.5 percent real discount rate Non-hydro 2,316,000 2) 0.0 percent real fuel escalation rate through 1988 3.0 percent real fuel escalation rate from 1989 on. 3) Construction cost estimate based on Corps of Engineers 1982 estimate of $1.48 million. 4) Electrical load growth based on Corps of Engineers 1982 report data. 5) 7 kWh/gal. fuel efficiency estimate of existing genera- tors based upon Corps of Engineers 1982 report data. 6) Current diesel fuel price of $1.25/gallon based upon telephone conversatior. cf 07/31/84 with Patricia Stephenson of AVEC. 7) Hydropower project output assumed to meet 50 percent of electrical demand on an annual basis. This assumption was derived from figure 4.1, page 26 of the ~arch 1982 report. (230mWh i-475 mWh = 0.50) 8) Operations and Maintenance for the project ;s based upon Corps report, with 1982 cost of $22,OOO/year, escalated to $23,500/year in 1984. S048/247/d2 B-3 ". ' Scammor, Bay Hydropower A 1 terr.? t i ve PW (construction cost) 1,588,000 PW (operations & maintenance) 36H,GOG PW (use of diesel generation 1,158,000 for 50 percent of lo?d) Total present worth S3,114,000 Non-Hydropower Alternative Tables 2 and 3 show tile annual cos1:~ end the toted rresent worth of uSillg the diesel alternative ilt Scarrm0n Bay. Table 2 Annual Costs of Diesel (Rea 1 ) Annual Real ~1\m ~/mWh Cost Fuel Cost 8 . 5 179 85,025 1. 25 85 500 179 89,500 1. 25 86 525 179 93,975 1. 25 87 550 179 98,450 1. 25 88 575 179 102,925 1. 25 89 600 184 110,400 1. 29 90 625 190 118,750 1.33 91 650 196 127,aoo 1. 37 0" "L, 675 201 135,675 1. 41 93 700 207 14~, 900 1.45 94 725 213 154,425 1. 49 95 750 220 165,000 1. 54 96 775 227 175,9?5. 1. 59 97 800 233 186,400 1. 63 98 825 240 198,000 1.68 99 850 247 209,95G 1. 73 00 875 256 224,000 1. 79 01 900 263 i36,700 1.84 02 925 270 249,750 1.89 03 950 279 265,050 1. 95 04 975 287 279,825 2.01 5048/~47/d2 B-4 Table 3 Total Present Hcrth of Diesel 1984 85,O?5 1985 86,473 1986 87,727 1987 88,796 1988 89,693 1989 92,953 1990 96,603 1991 100,135 1992 103,003 1993 106,318 199 t1t 109,475 1995 113,016 1996 116,424 1997 119, :i84 J 998 122,320 1999 125,317 2000 129,182 2001 131,890 2002 134,456 2003 ]37,891 2004 140,630 PW (Total) = $2,316,491 The total present worth of the diesel costs, from Table 3, is $2,316,491 (not counting 0 & M and unit replacements). Conclusions and Recommendations Both analysis methodologies support one conclusion: Scammon Bay is not economically feasible at this time. The initially favorable analyses of the project are no longer valid, due to changing econonlic conditions, such as rising interest rates and declining fuel costs. As can be scen from Table 4.1 (Corps analysis methodology), the project shows a benefit/cost ratio of less than one (.79}, even when benefits from employment that occurs due to project construction are considered in the analysis. From Table I, (Powcr Authority analysis methodology) we also see that the project has a benefit cost ratio of less than one (.74). Based upon these findings, and subject to sir"ilar findings by the Corps in their review, it is recommended that Scammon Eay not be considered for hydropower development at this time. 5048/247/d2 8-5 "e:~Y TO ATT .... TtON 011'1 APPENDIX C I DEPARTMENT OF THE ARMY u.s. ARMY ENGINEER DISTRICT, ALASKA P.O. BOX 898 ANCHORAGE, ALASKA 995()6.{)898 Plan Formulation Section May 1, 1985 _RECEIVED rvi,'; '/ 03 1935 ALASKA POWER AUTHORITY SUBJECT: Scammon Bay, Alaska, Small Hydropower Interim Feasibility Study Mr. Edwin L. Morris Associate Executive Director/Planning Alaska Power Authority 334 West Fifth Avenue Anchorage, Alaska 99501 Dear Mr. Morris: Enclosed is the updated hydrologic and economic data for Scammon Bay as you requested in your letter of February 7, 1985. Analysis of the hydropower potential of the Scammon Bay area using the most recent information resulted in the tentative conclusion that a small hydropower project is not economically feasible. Streamflows appear to be greater than originally estimated in the 1982 Small Hydropower Interim Feasibility Study, resulting in an increase in power generation potential. However, the dollar value of that electrical power has decreased from the earlier study when the present costs of diesel-generated power are applied. The costs and benefits of the three sizes of generating systems analyzed are shown in table 1, enclosed. The smallest size, a 75-kW system, appeared to be the most feasible but still has a benefit-to-cost ratio below unity, 0.79 to 1. This conclusion differs from the 1982 feasibility study, which concluded that a lOO-kW small hydropower system was feasible and the optimum plan. The stream record compiled since the 1982 study indicates that the fall and early spring discharges are higher than originally estimated (shown in table 2, enclosed). The revised streamflows were used to compute the power generation for three different unit sizes: 75-kW, lOO-kW, and 125-kW. Power generation increased by as much as 53 percent for the 75-kW system. The results are shown in table 3, along with our 1982 feasibility study results. The spring snow melt discharges are lower than originally estimated but still higher than the maximum power flow. Therefore, power output for those months would not be reduced. The higher fall and early spring discharges account for the substantial increase in power potential. The energy benefit value used in the 1982 study was based upon the cost of fuel and operation and maintenance costs of diesel- generated power. Alaska Village Electric Cooperative, Inc. (AVEC) 1982 diesel costs of $1.68/gallon, coupled with Scammon Bay's C-1 -2- generating efficiency of 7 kWh/gallon, resulted in a fuel cost of 24.0t/kWh. AVEC's 1982 operation and maintenance cost was 6.85t/kWh. The energy benefit value was revised according to cost of fuel and generation efficiency data enclosed in AVEC's letter of 21 January 1985 (enclosed). The cost of fuel decreased to $1.20/gallon in 1984, and generating efficiency increased. An efficiency rate of 11 kWh/gallon and a fuel cost of $1.20/gallon was used in the most recent analysis, resulting in a fuel cost of 10.91t/kWh. The efficiency of 11 kWh/gal of fuel was developed by determining the present weighted annual efficiency of 9.5, to be increased by 2 percent per year to the year 2000 (16 years), for a projected efficiency of 13 at the year 2000. The combination of a 16-year growth period at 2 percent and a constant period of 34 years at an efficiency of 13 gives an average annual equivalent project efficiency of 11. AVEC's 1984 operation and maintenance cost was 5.75t/kWh. Project construction costs were updated to October 1984 price levels. The interest rate was updated to 8-3/8 percent from the 1982 rate of 7-7/8 percent. Of the three sizes analyzed, 75, 100, and 125 kW systems, the 75-kW system appears the most feasible, but not yet economically viable. Investment costs for the 75-kW system are $1,662,000, including $63,000 for interest during construction. The total annual cost is $165,900, including $24,200 for operation and maintenance. Annual benefits for the 75-kW system are $130,400, including benefits for fuel displacement, fuel price escalation (table 4), operation and maintenance, and employment. The benefit to cost ratio is, therefore, $134,400/$165,900 or 0.79 to 1. Greater detail on costs and benefits for the 75-kW system and the other systems is given in table 1. Questions about this information should be directed to Mr. Harlan Legare of our Plan Formulation Section at 753-2633. Sincerely, (9,1 MuJ~ ~j~ Vining 1 Acting Chief, Engineering Division Enclosures C-2 Table 1 Costs and Benefits Scammon Bay Small Hydropower March 1985 Cost f'l"r"St Costs Interest During Construction Investment Cost Annual Cost Operation & Maintenance Total Annual Costs (Based on 50-year project life, amortized at 8-3/8%) Annual Benefits Fuel Displacement 1/ Fuel Escalation 2/- Operation & Maintenance 3/ Employment - Total Annual Benefits Net Annual Deficit Benefit/Cost Ratio Power s{stem Size 75 kW 00 kW 125 kW $ 1,599,000 63,000 $ 1,632,000 66,000 $ 1,677,000 70,000 $ 1,662,000 $ 1,698,000 $ 1,747,000 $ 141,700 $ 144,800 $ 149,000 24,200 24,200 24,200 $ 165,900 $ 169,000 $ 173,200 =========== =========== =========== 48,000 $ 22,400 26,700 33,300 42,700 $ 19,900 23,700 34,000 42,700 19,900 23,700 34,900 $ 130,400 $ 120,300 $ 121,200 =========== =========== =========== 35,500 $ .79 48,700 $ .71 52,000 .70 1/ Fuel Price $1.20/gal. with 11 kWh/gal. efficiency yielded $.1091/kWh. Energy use = 463,538 kWh, 411,538 kWh, and 411,538 kWh for 75, 100, and 125 kWh systems respectively. Five percent line loss assumed. 2/ Fuel escalation factor of .466 with 1985 POL date. 1/ O&M savings of approximately $.0575/kWh. C-3 Table 2 Average Damsite Discharge in CFS Scammon Bay Small Hydropower Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1982 IFS Disc harge 0.6 0.6 0.9 5.0 10.0 6.0 2.0 2.4 2.0 1.8 0.9 0.6 1985 Revised Discharge 1/ 0.6 1.1 2.0 2.5 5.0 6.0 4.0 2.0 3.0 3.0 2.0 1.0 1/ The 1985 Revised Discharge is based upon the period of record shown below: Synthesized Damsite Average Monthly Discharges in CFS Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1979 8. 1 1980 1.8 2.2 6. 1 1.5 1.2 1.2 Calendar Year 1981 1982 1983 4.7 C-4 4.2 11.8 6.9 7.4 1984 5.7 4.4 4.3 2.8 4.2 4.8 2. 1 2.8 2.2 2.2 1.1 0.6 1985 0.2 Table 3 Power Generation Scammon Bay Small Hydropower Power in MWh Month 75 kW 100 kW 125 kW Jan -0--0--0- Feb 26 -0--0- Mar 52 52 52 Apr 55 62 62 May 57 76 93 Jun 55 73 90 Jul 57 76 93 Aug 52 52 52 Sep 55 73 73 Oct 57 76 76 Nov 50 50 50 Dec 26 -0--0- --------------- Revised Total 542 590 640 Previous Total 354 408 463 C-5 R )' ,< Table 4 Data Resources Incorporated Escalation Rates for Diesel Fuel Costs Years 1982 1984 -- 1980-85 .058 .016 1986-90 .045 .016 1991-95 .031 .036 1996-2000 .017 .034 2001-on .01 7 .016 Fuel Escalation Factor .084 .446 Average Annual Equivalent 1.840 1.446 Factor 1/ 1/ Escalation rates applied for the first 30 years of project life only. C-6 APPROVAL OF FINDINGS AND RECOMMENDATIONS FOR SCAMMON BAY A. Action Item Consideration and transmittal of Findings and Recommendations with respect to hydropower feasibility and other energy alternatives for Scammon Bay. The Power Authority recommends continued use of diesel generators to supply the power needs of the community and implementation of improvements that would increase system efficiencies. The proposed hydroelectric project is not economically feasible based on current economic parameters, and there is insufficient potential for other energy alternatives to warrant additional feasibility analy- sis. B. Background 1. The Alaska Power Administration in 1979 completed an inventory of hydroelectric potential in AVEC villages, concluding that Scammon Bay had good potential for hydroelectric development. 2. Consul tants under contract to the Power Authority com- pl eted the Reconnaissance Study of Energy Regui rements and Alternatives for'Scarrunon Bay in April 1981, recom- mending energy conservation, collection of wind data, continued use of diesel generators, and investigation of hydropower feasibility. Preparation of Findings and Recommendat ions based on the Reconnaissance Study was withheld pending the outcome of a hydropower feasibility study underway by the Corps of Engineers. 3. The Corps completed its feasibility study in March 1982, finding that a 100 kW hydroelectric project produced a benefit/cost ratio of 1.20. The Corps recommended development of the hydroel ectri c system and proceeded with its formal approval process in an attempt to acquire funding for the project. The Assistant Secretary of the Army recommended to the U.S. Office of Management and Budget in May 1984 that expenditure of federal funds for the project was not warranted and that the project should be the prerogative of local interests. 4. Upon the Corps' relinquishment of the project, the Power Authority reanalyzed its 1981 Reconnaissance Study and the Corps' 1982 Feasibility Study and updated their technical and economic analyses. The Corps also updated its hydrologic and economic analyses in May 1985. These updated analyses incorporated current diesel fuel prices (which had decreased significantly since 1982), lower fuel escalation factors, an increased standard real 2154A/517 interest rate used for evaluating federal projects. and increased diesel generator efficiency factors. The resulting benefit/cost ratios ranged between 0.70 and 0.79 dependi ng on speci fi c assumptions and hydropower project size. 5. These Findings and Recommendations are based on the updated technical and economic eva1uations of both the Power Authority and the Corps of Engineers. C. Issues 1. The Power Authority has evaluated. with updated economic parameters, the feasibility of hydropower development at Scammon Bay using both the method of analysis followed by the Corps in its 1982 study and the standard Power Authority method. Both analyses resulted in the same conclusion that a hydroelectric project is not economi- cally feasible based on current economic parameters. Changes in economic parameters between 1982 and 1985 which produced the greatest effect on these results were a significant decrease in the price of diesel fuel, a decrease in standard fuel escalation factors, and an increase in the standard real interest rate used in Corps analyses of federal projects. The resulting benefit/cost ratios ranged from 0.74 to 0.79 depending on the method of analysis used. 2. The Corps of Engi neers was requested to reana lyze and update its hydrologic and economic evaluation of the project. The analysis was completed in May 1985. The Corps found a greater hydrologic potential for power generation than previously estimated, but this was not sufficient to overcome the effects of lower fuel costs, the increased federal-project real interest rate, and a higher estimated diesel generator efficiency. The Corps analyzed three sizes of hydropower projects resu1ting in benefit/cost ratios ranging between 0.70 and 0.79. 3. A recent site investigation by Power Authority staff has confirmed the findings of previous studies that waste heat recovery is not a viable alternative at Scammon Bay due to the distance between the power house and potential waste heat users. 4. Recent analysis of the suitability of wind energy conver- sion systems in small t remote villages shows that current wind technology cannot economically meet the electricity needs of SCal11l1On Bay. Cost effective systems in sizes suitable for low power demands are not available, and 2154A/517 equipment has not been perfected to provide adequate load controls for small, integrated diesel/wind systems. 5. Improvements to the existing diesel generation and distribution system appear to be the best alternative for reducing energy costs at Scammon Bay. D. Costs Approval and implementation of these Findings and Recommenda- tions would result in no cost to the Power Authority. E. Options 1. Approve the Findings and Recommendations for Scammon Bay. 2. Modify and approve the Findings and Recommendations. 3. Disapprove the Findings and Recommendations and reassign to staff for further analysis. F. Recommenda t ion Adopt Option 1: Approve the Findings and Recommendations for Scammon Bay. 2154A/517