HomeMy WebLinkAboutTogiak Hydroelectric Project Kurtluk River Alternative Projects Pre-reconnaissance Report 1982-. ..
... .. ..
...
.. ..
"II .. ..
-..
-...
-
...
•
-
...
• ..
,.
-
LOUIS W RIGGS
HOHtRT N IANOPAUI
PAUL I POT TE R
KF ITH 0 BULL
DOUGLAS I MANSFIELD
ORAL I rONHRS
DAVID C WILLER
MICHAH B HARRINGTON
THEODORE H PURCELL
WAL TE R FANTON
ROKfRT W. MYRDAL
TEVIS T THOMPSON.IR
Mr. Melvin Nichols
DOWL Engineers
/\
i
TUDOR ENGINEERING COMPANY
CONSULTING ENGINEERS AND PLANNERS
149 NEW MONTGOMERY STREET
SAN FRANCISCO, CALIFORNIA 94105
TElEPHONE (415) 982-8338 TWX 372 b083
CABLE "TENGCO"
4040 "B" Street
Anchorage, Alaska 99503
Subject: Kurtluk Pre-Reconnaissance Study
Dear Mel:
5t
~
RALPH A. TUDOR (1902·1'11>1)
AS.IOC/A rt 0 (ON.IUL IANT
SlANLH H fROID
snVEN R ALTERS
lACK C BIEDERMAN
HUGH M BROWN
DONALD I CROFT
FRfD B ESTEP
RICHARD W EVERETT
fRITS H FE NGF R
ROBERT W. GANS[
GERALD V GIBNEY
ROBERTO E INIGUEZ
CRANT A. LARSEN
lAMES W MtvlR
THOMAS I O'NEILL
DONALD C ROSI
RAINtR RUNGALDIER
August 13, 1982
At tached you will find 15 copies of the recent ly completed pre-
reconnaissance report for a potential hydroelectric project on the Kurtluk
River near Togiak. The report is intended to amplify the brief information
presented on this alternative site in the report entitled "Reconnaissance
Study for the Togiak Hydroelectric Project" dated August 1982. The
information and analyses in the report are based on existing data gathered by
DOWL, Tudor, and Dryden & La Rue during the preparation of the August 1982
report and no new field work was performed for the study •
Two alternative projects (K-l and K-2) were studied for t~is
report. Both alternatives utilize a common dam site with differing heights on
the Kurtluk River. Alternative K-l would utilize a 40-foot high dam to divert
the Kurtluk flows to a different drainage basin via a 8400 foot penstock to a
340 kW power plant located near a proposed new airport. Alternative K-2 would
ut ilize a 55-foot high dam with a 132 kW power plant located immediately
downstream on the Kurtluk River.
The costs and benefits for the alternative projects were assessed to
provide a preliminary indication of their economic viability. Alternative K-1
would cost $5,810,000 and the 340 kW power plant would generate 1.63 m kWh per
year. Alternative K-2 would cost $4,940,000 and the 135 kW power plant would
generate 0.53 m kWh per year.
For the economic analysis, the base case data for Togiak formulated
for the August 1982 study was utilized. This included consideration of the
base case alone, and also adjustments for waste heat recovery, wind energy
credits and space heating credits .
...----------,'r.II'"-::::----,
, PrG:: '(Jut:" CJC1D
File Code: ~.J .. Di. 03
J, Date':,8~ ___ .~M· L
--
... TUDOR ENGINEERING COMPANY
...
'III
..
•
'III
..
-
,. ..
...
'III ..
..
....
-
Mr. Mel Nichols
August 13, 1982
Page 2
The results of the economic analysis indicate that Alternative K-l
may be potent ially feas ib Ie, but Alternat ive K-2, due to its small power
output is not cost effective. The benefit/cost ratios (B/C) for Alternative
K-l are swmnarized below. All B/C ratios studied for Alternat ive K-2 were
less than 1.00.
Case B/C
1 -Base Case Only 1.30
2 -Adjusted for Waste Heat Recovery 1.18
3 -Adjusted for Waste Heat Recovery
and Wind Energy Credits
1.13
4 -Adjusted for Waste Heat Recovery,
Wind Energy Credits and Space
Heating Credits
1.25
The basic purpose of the pre-reconnaissance study was to investigate
whether or not it was prudent to proceed with a more detailed, and more
costly, feasibility study for the site. Bas"ed upon the results of this study
it is recommended that a cautious but positive approach be taken from this
point. A summary of the report recommendations to implement this approach are
as follows:
1.
2.
3.
A preliminary evaluation of
environmental problems of the
implemented as soon as possible.
the associated
site should be
The streamflow gage currently· installed at the
Quigmy site should be moved to the Kurtluk site and
monitoring of the flows should begin as soon as
poss ib Ie.
The project should be reevaluated in approximately
one year when the addit ionalenvironmental and flow
data are available and a more definitive· decision
made at that time .
..
...
..
•
..
-
...
...
..
. -
-
.. --.. .. ..
...
..
--
·/~ .
TUDOR ENGINEERING COMPANY
Mr. Mel Nichols
August 13, 1982
Page 3
If you desire amplification of any parts of the report or if you have
any questions, please call .
GEL:813.2
Attachment
Very truly yours,
ruDOR ENGINEERING COMPANY
?Jv.LC. ~
Gordon E. Little
Project Manager
.. ..
..
... ..
...
•
... -
',"" ...
... -..
" ...
...
...
...
...
..
•
-
TOGIAK HYDROELECTRIC PROJECT
KURTLUK RIVER ALTERNATIVE PROJECTS
PRE-RECON REPORT
. c
A. INTRODUCTION
1. Background
The draft Togiak Hydroelectric Project Reconnaissance Study
(Reconnaissance Study) concluded that the Quimby River project
site was economically marginal and could not be recommended for
development. During the draft review the APA decided that
alternative sites, previously rejected due to its small power
output, should be reviewed and that a pre-reconnaissance report
be prepared utilizing available information.
2 . Location
The village of Togiak is located on Bristol Bay approxi-
mately 70 miles ~est of Dillingham and 400 miles southwest of
Anchorage. The village itself is located on a marshy flat 10
to 30 feet above sealevel. The Kurtluk River flows across an
elevated bedrock bench 4 miles west of the village. The upper
part of the Kurtluk River Basin contains two potential hydro-
electric projects which share a common diversion dam site .
Their location is shown on Plate I. These projects were
briefly described in the March 1982 draft of the Reconnaissance
Study for the Togiak Hydroelectric Project as Alternative
Projects No. 10 and No. 11. In the following report these
projects are referred to as Alternatives K-1 and K-2, respec-
tively. Project No. 11 (Alternative K-2) was designated in the
Draft Report as the alternate to the selected Quimby River
project .
NBISF-313-9527-KA 1
f?~a i~~=,:l{f{Q .. __ --;
I Fii:J C:;,::' _~t~D7· D3 I J. OJte: ~~L.a . I
· . .. ..
..
..
-
-..
-
.. ..
...
-
..
..
..
..
..
-
3 . Scope
The following report is intended to provide a' brief
. c
analysis of the Kurtluk alternative projects for the purpose of
judging whether one of these projects would prove to be physi-
cally and economically acceptable 'under a detailed feasibility
study. Methods, assumptions, and costs used in preparing this
report, although more general, are consistent with those used
in the previously submi tted Reconnaissance Study. Only pre-
viously existing information was used. This included a topo-
graphic survey and stream flow measurements of Alternative No •
11 made during the September 1981 field reconnaissance.
Information on the Kurtluk projects was included in the
draft report under Chapter V, Alternative Sites Considered; and
Appendices: B -Hydrology, C -Geology and Geotechnical, and
D -Environmental Report •
B. PROJECT DESCRIPTION
1. Alternatives Studied
Two alternative projects were studied for this report and
are presented on Plate I at the end of this report. Both
alternatives utilize a common dam site with differing heights
on the Kurtluk River. Alternative K-1 would divert the Kurtluk
flows to a different drainage basin via a 8400 foot penstock to
a 340 kW power plant located near the proposed new ai rport.
Alterntive K-2 would utilize a dam with a 132 kW power plant
located immediately downstream on the Kurtluk River.
The proposed dam site for both alternatives is located in
the mouth of a narrow 42-foot deep canyon immediately down-
stream of the confluence of the Kurtluk with a major tributary.
Other than the size of the stream the site is very similar to
the Quigmy River Project site in topography and geology.
NBISF-313-9527-KA 2
,-
... ..
1M
...
.. .. ..
.. .. ..
..
... ..
..
-
.-..
.. ..
..
..
, --
2. Alternative Project K-1
This alternative would utilize a 40-foot hig~ concrete
faced rockfill dam to divert the project flows out of the
Kurtluk basin and over an intervening ridge to the power plant.
The diversion woul d ut i 1 ize a 36 inch diameter penstock 8400
feet in length. The powerhouse would be a prefabricated metal
building approximately 30 feet by 30 feet and would be located
a mile beyond the proposed air strip near a large pond (100
acre surface area) that drains south into the bay. An impulse
type turbine would utilize 160 feet of head and a maximum flow
of 36 cfs to develop 340 kW •
3 • Alternative Project K-2
Project K-2 would be contained wi thin the Kurtluk River
canyon and would obtain its head principally by constructing a
concrete faced rockfill dam to a 55 foot height. This would
require that dikes be extended back from the inner rim of the
canyon in order to contain the reservoir. The broad west abut-
ment, 50 feet above the streambed, would serve as the emergency
spillway for the dam. An additional 7 feet of head for a total
of 57 feet can be developed by extending the penstock 250 feet
beyond the dam to a more accessable powerhouse si teo A tube
type turbine would utilize a maximum design flow of 36 cfs and
the 57 feet of head to develop a maximum ouput of 132 kW •
4. Site Access and Transmission Line
Si te access woul d be the same for both al terna t i ves • An
existing road leads from the village across a marshy area to a
gravel pit and the site of a new airstrip proposed by the
Alaskan Department of Transportation. An access road would
follow the high ground beyond the air strip to the K-1 power-
house site and then climbs approximately 160 feet along the K-1
NBISF-313-9527-KA 3
-
.... .. .. ..
•
..
..
-
..
.. ..
.. ..
..
.. ..
penstock route through a broad gentle saddle to the dam site on
the Kurtluk River. The power line would generally follow the
same route and would be mostly above ground on single poles as
for the Quigmy River site. The line would be buried-across and
in the vicinity of the proposed new air strip •
5 • Hydrology
The flows at the Kurtluk project sites were developed using
methods similar to those utilized for the Quigmy project. The
much smaller Kurtluk basin reaches only to the 1300 foot eleva-
tion compared to the 2500 foot elevation for the Quigmy basin.
This reduces the orographic effect of the moisture inflow and
resul ting precipi ta tion. The following table cont rasts the
hydrologic estimates for the two basins.
Hydrologic Comparison
Basin Kurtluk
Drainage Area (sq. mi.)
Annual Precipitation (inches)
Specific Yield (cfs/sq. mi.)
Average Annual Flow (cfs)
Spot Flow Measurement (cfs)
September 15, 1981
October 9-10, 1981
Channel Geometry Estimate (cfs)
13.1
37
1.6
21
48
17
19
Quigmy
100
50
2.2
220
301
131
270
An average annual flow of 21 cfs was adopted as the initial
estimate for the Kurtluk projects. For purposes of this pre-
recon report, the flow duration curve and annual hydrograph of
the Kurtluk River may therefore be assumed to equal approxi-
mately 10 percent of those estimated for the Quigmy project.
These flows are shown on Figures 1 and 2 •
NBISF-313-9527-KA 4
...
..
..
.. .. -
-..
-..
..
...
...
..
...
...
,.
..
.. ..
6. Power and Energy Production
\ ;
/
A turbine design flow of 36 cfs, equal to approximately 15
percent exceedance on the flow duration curve, was selected for
both projects. Project K-1 utilizing an impulse type turbine
would operate efficiently down to 10 percent of its design
capacity (3.6 cfs) and to nearly 100 percent of the flow dura-
tion. Project K-2 would utilize a tube type turbine which has
a low flow range limi ted to about 30 percent of its design
capacity (11 cfs) and would limit its operation to about 70
percent of the duration .
The following table compares the two projects.
Power and Energy Development
Item
Design Flow (cfs)
Gross Head (ft)
Dam Height (ft)
Penstock Length (ft)
Net Head (ft)
Power (kW)
Average Annual Energy (MkWh)
C. ECONOMIC ANALYSIS
K-1
Project
-
36
157
40
8400
132
340
1.63
K-2 -
36
57
55
500
53
136
0.53
The costs and benefits associated with the Kurtluk
Al terna t i ve Projects were assessed to provide a prel iminary
indica tion of the feas ibil i ty of the proposed al terna ti ves.
The results of this analysis indicate that the Kurtluk
Alternative K-1 is potentially an economically viable project,
NBISF-313-9527-KA 5
..
• ..
... ..
.-...
-
-..
..
-
-
...
...
...
III
--
but Project K-2, due to its small power output, is not cost
effective.
. c
1. Economic Criteria
The Kurtluk Alternatives K-1 and K-2 were assessed using
the criteria and methodology presented in Section IX of the
Reconnaissance Study. These cri teria are based on the APA
standard criteria for economic analysis.
2. Cost Estimate
The cost estimates for the Kurtluk sites were based on the
information prepared for. the feasibility studies for King Cove,
Old Harbor and Larsen Bay and the reconnaissance study for
Togiak. Quantity estimates were prepared for each alternative
studied and unit prices derived from the above referenced
reports were then applied. These unit prices were judgement-
ally modified as necessary to suit this particular application.
Detailed est ima tes are presented in Table I (AI ternati ve K-1)
and Table II (Alternative K-2) included at the end of this
report. Summaries of these estimates are presented below:
Cost Estimate
Item
Project
Direct Construction
Contingencies
Contract Cost
Engineering and Administration
Total Project Cost
Power (kW)
Cost per kW
NBISF-313-9527-KA 6
Amount
K-1
$4,165,000
765,000
4,930,000
880,000
$5,810,000
$
340
17,100
K-2
$3,567,000
623,000
4,190,000
750,000
$4,940,000
$
135
36,600
-
•
•
'III
..
-..
-..
-
•
-
...
.. -'.
'.
-
..
-
As the cost effectiveness of Project K-1 based on power
output is twice as great as Project K-2, subsequent economic
analysis was limited to Project K-1. For comparison the total
project cost per kilowatt of the 432 kW Quigmy project includ-
ing 11.6 miles of road was $18,900.
3. Project Energy Planning
The average monthly energy generation that could be
realized from the Kurtluk Alternative K-l was compared to the
monthly direct electrical and space heating demands from the
Togiak report in order to determine the amount of hydroelectric
energy that could be used to meet these demands, and the
required amount of supplemental diesel generation that would be
necessary if the hydroelectric project is built. A detailed
explanation of the methodology used for this energy accounting
is included in Chapter VII of the Reconnaissance Report. This
accounting was performed for 1985, 1990, 2000, and 2001. The
resul ts of the accounting are presented below. The monthly
relationships between energy demand, generation, and usage are
shown graphically on Figure 3.
Energy Demand, Generation, and Usage
Required
Supplemental Hydro Used
Direct Direct Demand Diesel for Space
Demand Met by Hydro Generation Heating
Year (1000 kWh) ,( 1000 kWh) (1000 kWh) (1000 kWh)
1985 892 856 36 774
1990 1025 949 76 681
2000 1286 1118 168 512
2001 1314 1134 180 496
4. Benefit/Cost Analysis
The annual costs associated with the hydroelectric project
were estimated using the energy values presented above. These
NBISF-313-9527-KA 7
-
-..
,.
•
..
• -,.,.
-.. .. ..
...
'. ..
..
..
• -'
oM
costs include the cost of supplemental diesel generation and
were developed in· a manner consistent with the methodology
advanced in Chapter IX of the Togiak Report. The . ~osts were
discounted to January 1982 at three percent interest. The
present worth of the space heating credit associated with the
Kurt luk Al terna t i ve K-1 was determined in a simi lar manner.
The present worth of the base case, the waste heat recovery
credit, and the wind energy credit were taken directly from the
Togiak Report. The present worth of the cost of the hydro-
electric project was considered as a cost • The costs of the
base case, waste heat recovery credit, and wind energy credit
were considered to be benefits. The space heating credit was
considered to be a reduction to the benefit. This methodology
is in accordance to the methodology requested by APA. A
summary of present worths is presented below:
Present Worth Summary
Present Worth of Benefits
Present Worth Base Case Only
Present Worth Waste Heat Recovery Credit
Subtotal
Present Worth Wind Energy Credit
Subtotal
Present Worth Space Heating Credit
Total
Present Worth of Costs
Present Worth Cost of Hydro Project
(Includes Present Worth Cost of
Supplemental Diesel)
$11,027,600
999,400
$10,028,200
504,700
$ 9,523,500
1,051,800
$10,575,300
$ 8,464,500
The present worths presented above were used to determine
benefit/cost ratios for the various levels of project develop-
ment. The benefit/cost ratios for the project are as follows:
NBISF-313-9527-KA 8
...
... -
""" ..
•
....
•
... ..
..
...
...
•
-
•
..
..
...
Base Case Only
BIC = 11,027,600 =
8,464,500 1.30
Base Case Adjusted for Waste Heat Recovery
BIC 10,028,200 = 8,464,500 = 1.18
. c
Base Case Adjusted for Waste Heat Recovery and Wind
Energy Credits
B/C 9,523,500 = 8,464,500 = 1.13
Base Case Adjusted for Waste Heat Recovery, Wind
Energy, and Space Heating Credits
B/C = 10,575,300 =
8,464,500 1.25
The benefi t/cost ratios presented above indicate that the
project is feasible for any of the configurations considered •
5. Project Timing
Tbe annual unit cost of energy was calculated for the
project configurations being considered.
analysis are sbown on Figure 4 .
Tbe resul ts of this
Tbe optimum timing for project development would occur when
the unit cost of tbe existing system exceeds tbe unit cost of
tbe proposed bydroelect ric project. Because actual costs are
important for this comparison, the waste heat recovery and wind
NBISF-313-9527-KA 9
-
..
....
-
-
..
..
..
..
...
--
,.
..
..
...
--
energy credi ts were associated wi th the base case and con-
sidered as reductions in cost, while the space heating credits
were considered as a reduction in the cost of the hydroelectric
. f project. A detailed explanation of the discontinuities on
Figure 4 is included in Section IX-F of the Togiak Report.
Inspection of Figure 4 indicates that the hydroelectric
project, after adjustment for the space heating credit, would
have a lower uni t cost than the base case adjusted for waste
heat recovery by the time the hydroelectric project goes on-
line in 1985, and that this project would have the lowest unit
cost of all alternatives considered by the end of 1986. The
project appears to be viable for immediate development •
D. ENVIRONMENTAL OVERVIEW
The principal potential impact of the Kurt1uk projects is
on fisheries. Both projects require high dams which may render
a fish ladder installation marginal in value. However, the
isolation of spawning habitat in the upper most reaches of the
Kurt1uk River may not prove to be of major significance on a
regional basis.
More significant is the transbasin diversion proposed for
Project K-1. This would result in a major reduction in stream
flow in the approximate mile and a quarter long reach that lies
between the dam and the next major tributary downstream.
Fishery releases and normal spills from the dam would mitigate'
in part the impact on this reach. In contrast, flows below the
power plant located on the Togiak flats will be significantly
increased. The large pond on which the pow~rhouse is located
will provide an excellent afterbay acting to smooth the diurnal
and weekly fluctuations in power flows. The existing outflow
channel which flows in a relatively direct route southward to
Togiak Bay should handle the increased flow averaging 18 cfs or
less without major problems although some scour is anticipated.
NBISF-313-9527-KA 10
..
...
..
---..
..
.".
...
•
.. ..
--
The selection of this ponds ide powerhouse site mitigates poten-
tially major flooding problems created by the original site.
That site was located 800 feet to north and drained northeast-
ward towards the village through a series pf sloughs~~
E. CONCLUSIONS
1.
2.
3.
4 •
5.
A 340 kW hydroelectric project producing approximately
1.6 MkWh of annual energy is potentially developable
on the Kurtluk River. This project would divert water
from the Kurtluk River basin and return it to a
different drainage basin near Togiak •
The preliminary estimate of project construction cost
is approximately $5,400,000.
The preliminary estimate of the project benefi t cost
ratio is 1.30 based on APA methodology •
An alternate project that would return the power
diversions to the Kurtluk a short distance below the
dam is not cost effective •
Potentially significant environmental impacts created
by transbasin diversion of Kurtluk flows may effect
the ultimate acceptability of the proposed project.
F. RECOMMENDATONS
1.
2 •
The Alaskan Power Authority should consider proceeding
cautiously and on a long term basis with a more
detailed study of the Togiak/Kurtluk River Project.
Preliminary environmental evaluation of the proposed
transbasin diversion should begin immediately. Early
findings could have substantial effect of the direc-
tion of the feasibility study.
.. ..
•
..
.. -...
-
, ...
' ...
,"" .. ..
''III
-
3. Continuous flow measurements of the Kurtluk River and
uninterrupted daily precipitation measurements at
Togiak should begin as soon as possible. "Due to the
lack of other records in the region these measurements
are cri tical to reliable evaluation of environmental
4.
and power development problems. Due to its easier
access and smaller stream, a Kurtluk stream gage could
be maintained more economically than the recently
installed Quimgy River gage and it is recommended that
the Quigmy gage be moved to the Kurtluk site as soon
as it can be practically accomplished •
When additiona~ flow and environmental information is
available in mid-1983, the project should be reevalu-
ated and a decision made whether or not to proceed
with a more detailed feasibility study.
NBISF-313-9527-KA 12
,..,' ..
--\
I -.. TA~LE I
JWRTLUI< ALTERNATIVE-PROJECT K-1
340 k\41
COl-'STRUCTION COSTS
. c .. Item Ouantity Unit Unit Price Amount
Mobilization LS 450,000
Access Road 3.2 ML 130,000 416,000 ..
Dam (4(\' hi~h)
Cofferdam 1,000 CY 50 50,000
~ypass Line, 48" 300 LF 450 135,000 .. Foundation Treatment 430 SY 75 32,250
Trim (rock) 325 CY 30 9,750
Cone. Membrane & Toe 150 CY 1,200 180,000 ... Reinforcing Steel 17,000 LH 1. 73 29,410 .. Rock Fill 4,300 CY. 50 215,000
... 651,410 .. Intake
Slide Gate, 36" 1 EA 32,000 32,000
Slide Gate, 48" 1 EA 40,000 40,000 .. Trashracks 2 EA 5,000 10,000
Concrete 10 CY 1,400 14,000 -
96,000
Penstock
Steel, 36" 300 LF 175 52,500 -Fiberglass, 36" 8,100 LF 120 972 ,000
Excavation 5,800 CY 17 98,600
Backfill 5,300 CY 9 47,700 ..
1,170,800
Powerhouse
Prefab Building LS 47,000
Turbine & Generator LS 510,000
AuxilIary System LS 120,000
Concrete 110 CY 1,200 132,000
Reinforcing Steel 12,000 LB 1. 73 20,760
829,760
,.
SFNBI-313-9527-T-I
f •
••
....
.,.
,.,.
' .. J.
'.
f.
....
••
...
..
...
....
...
•
'.
' .
.... ..
Item
Spillway
Excavation Rock
Concrete
Reinforcing Steel
Transmission Line
Contingencies
Contract Cost
TABLE I
(Concluded)
KURTLUK ALTERNATIVE PROJECT K-1
340 kW
CONSTRUCTION COSTS
. c
Quantity Unit Unit Price
4,300
30
3,400
2.7
C'{
C'{
LB
MI
SUBTOTAL (rounded)
30
1,200
1. 73
141,000
Engineering & Administration
TOTAL PROJECT COST
Amount
129,000
36,000
5.882
170,882
380,700
4,165,000
765,000
4,930,000
880,000
5,810.000
-
•• TABLE II
' .. KURTLUK ALTERNATIVE PROJECT K-2
135 kW
CONSTRUCTION COSTS . r
••
Item Quant itt Unit Unit Price Amount '.
Mobi lizat ion LS 400,000
Access Road 3.2 MI 130,000 416,000 •
Dam (55' high)
Cofferdam 1,000 CY 40 40,000
Bypass Line, 48" 300 LF 450 135,000
Foundation Treatment 2,200 SY 50 11 ,000
Trim (rock) 325 CY 18 5,850
Conc. Membrane & Toe 400 CY ,·1,200 480,000
Reinforcing Steel 46,000 LB 1. 73 79,580
Rock Fill 11,800 CY 40 472,000
...
..
1,223,430 ..
Intake
Slide Gate, 36" 1 EA 32,000 32,000
Slide Gate, 48" 1 EA 40,000 40,000
Trashracks 2 EA 5,000 10,000
Concrete 10 CY 1,400 14,000
.. ..
•
96,000 -Penstock
Steel, 36" 400 LF 175 70,000
Excavation, Rock 200 CY 30 6,000
Concrete 10 1,400 14,000
... 90,000 -
Powerhouse
Prefab Building LS 47,000
Turbine & Generator LS 250,000
Auxiliary Systems LS 120,000
Concrete 110 CY 1,200 132,000
Reinforcing Steel 12,000 LB 1. 73 20,760
•
..
569,760
..
•
• SFNBI-313-9527-T-II
...
-
... ..
'III
....
•
..
...
...
..
.. ..
..
•
..
... -
Item
Spillway
Excavation Rock
Concrete
Reinforcing Steel
Transmission Line
Contingencies
Contract Cost
TABLE II
(Concluded)
KURTLUK ALTERNATIVE PROJECT K-2
135 kW
CONSTRUCTION COSTS
Quantity Unit Unit Price
12,800
30
3,400
4.2
Cy
CY
LB
MI
18
1,200
1. 73
119,000
SUBTOTAL (rounded)
Engineering & Admin.
TOTAL PROJECT COSTS
SFNBI-313-9527-T-II
. t
Amount
230,400
36,000
5,882
272,282
499,800
3,567,000
623,000
4,190,000
750,000
4,940,000
...
'III
•
..
.. ..
•
..
...
..
..
...
.. ..
..
•
• . -
r\ .
120
110
100
90
80 I-
-70 fh
~
U -
~ 60 o
~
LL
50
40
30
20
10
I
\
\
\~
""-" MEAl ANI'iJAL FLOW 21 ds
......"""'---...-
KURTLUK RIVER DAM SITE FIGURE
..
-
•
..
..
1M ..
•
• ..
...
..
... ..
"Q
70
60
50
-40 en -(,) -
10
ESTIMATED RANGE OF AVERAGE
MONTHLY FLOWS 7 OUT OF 10 YEARS
I ' I
.......................
Ii'·················, iii! i·· .",,·,ililili i·":i1 '.
~; ~ ~ ~ ~ ~ ~ ~: ~ ~~: ~ ~ ~ ~ ~ ~i
o~--~--~--~--~----~--~--~--~----~--~--~--~
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
MONTH
KURTLUK RIVER DAM SITE
H
FIGURE
"" ..
-.. ..
.-..
til
...
.-
... -... .. ..
1M
,.
ill ..
ill ..
• ..
III ..
oil .. .. .. .. ..
• .. .. ..
a I ..
-0
0
0 • -• .I: • M ->-~
W
Z
W
'; .' 1 ~--+---+----1......,....c~. tt:YPROELECTRIC:POrENIi~L.---L_-t--_____
AT QUIGMY RIVfR SITE i .
240 r-.--t---t---,..,.---t---t----t---+----+--t------+-
21 0 ~_-+----+--f:
USO !+---+----irl+-.... --~
120
90 '
80 ~~.....,. ---+--+---t
o ~ F M A
MONTH
D~TAIL DATA
TOGIAK HYDROELECTRIC PROJECT
o N 0
• PROJECTED MONTHLY ENERGY GENERATION, DEMAND, AND USAGE
FIGURE
3
.. ..
•
•
III
...
III
...
... .. ..
•
... -...
• ,
III .,
...
•
... ..
.... -..
III .. ,.
III .. ..
-tI!I
...
.-..
d
• ... ..
600
500
400
-
-
9 KURTLUK ALTERNATIVE WITH
SPACE HEATING CREDIT
HYDROELECTRIC PROJECT ON-Ll~~E
,.., 1T) ALTERNATIVE A W!TH 11.6 M!:"'E RCAa
I Y --AND NO SPACE HEATING CREDii
I , I' . ~'\ X2 ALTERNATIVE A WiTH 4.6 Wi:"!: Ro~r
I AND NO SPACE HEATING CRE::::
" , I .
I , ' " cP EXPAND FUEL. ~, , , ' , r ~ ~ ~ STORAGE cp
I " ' '~ .... ~ .~ ._ .', ~
, .0', :". ~ ® ~) ,~ ' .. €) .,.. ___ .L __
, , I ,
'~", , (-.: .J - - -1 - -
'" "-EXPAND WIND \
~"!II----\ -!)l' ....... ct..ir~~ -~ •
! " 4 ~ II
1;; ES:;::~~~::J~ \ I ~ ® BASE CAS~~~ \ j' ~:::~l/; -
C) WITHOUT WASTE ~ WiTH 11.6 MILE ;"
0: HEAT RECOVERY ROAD AND SPACE/ /
LLI OR Wif\;D CREDITS HEATiNG CREDiT
~ 200 ® BASE CASE @ ALJERNATI~iE~A)
~ WITH WASTE HEAT W!, H 4.6 M: ... ~
Z RECOVERY CREDIT ROAD AND SPACE
:::l HEATING CREDiT
-I
'CI
:::l
Z
® BASE CASE
WIT H WAST E HEAT'
Z
CI 100
..
1980
YEAR
RECOVERY AND .~
WIND CREDITS------·
1990
® KURTLUK ALTERATIVE
WITHOUT SPACE
HEATI NG CREDIT
2000 2010
TOGIAK HYDROELECTRIC PROJECT
PROJECTED UNIT ENERGY COSTS
FIGURE
4
.-------------------:---------.---~.
/
/
240
1&0
120
:::; ..
:II
z: 110
2 ..
~ ...
-' 40 ...
l
249
::; I!OO
EL~
I
~ .. 0 2
~ >-...
.J ItO ...
bJ
'~,
PLAN
o 1000 2000 3000 '1000 5000 &000
VE/tS1C)Ij DAM 4Q FT ~
~&. OlAMETER PENSTOCK
~Ur ~VE)I'
POWERHOUSE
POND SURFACE El 38
8400'
PfIOFLE AL 1. PROJECT K-I
IVERSION twII !li FT HIQH
• DIAMt TDI PENSTOCK
PROFILE ALl. PROJECT K-2
15 n
r'-
I
PROJECT 1(-1
TYPICAL IMPLUSE TURBINE POWERHOUSE
..!:l!!.
PROJECT 1(-2
TYPICAL REACTION TURBINE POWERHOUSE
J!L
, . ~ECT AItEA
r ~
LOCATION MAP
HOT TO SCALE
I TOGIAK
T061AI(
VICINITY MAP
STATE OF ALASI(A
8 II Y
ALASKA POWER AUTHORITY
NDtOItAGE. ALASItA
TOGIAK HYDROELECTRIC PROJECT
I(URTLUI( RiVER ALTERNATIVE PROJECTS
.. ..
...
* ...
•
III ...
... ..
... ..
'OIl ..
-.. .. .. .. .. ..
.-.. .. ..
I
..
I
I -! • I
....
ill .. .. .. ..
, .. I ..
... ..
,
1. ()~ .
Mr. Melvin R. Michols
Project Manager
DOWL En91"""
4040 -8-Street
Ancho .. a~. Alaska 99503'
Dear Mel:
/~ r.,~rl
April 9. 1982
w. "a.e CGIIpleted our review of the ff.e .01_ feasibility study
report for hydroelectric projects .t King Cove. Old HartJor. lant!ft Bay •
and r@connaissanee stady of hydroelectric POtential at Togiat. In
gene ... '. we weN quite pleased .ith the reports. but do have I f1UIIlN" of
ca..ents to offer •
General coaments relating to .11 four studies a~ as 'ollows:
I. The results of the .nalysis of the base else pl.n supple.ented
wfth .ind should be folded into each volume at IPproorfate
locations. Results of the ecoftOll1c analysis of this .,11 ..
should be 1ncof1X)'f"at@d irita tables s111111ar to those used fo,"
ot"er plans. --
b. PY'O\'isfOftS shauld be incorporated into project conceptual
designs to offer protection .!ainst vanda11~ •
c. An analysis MUSt be conducted for each one of the
projects to dlttenD1"e optil!tll t1trfng IS laid out in t~
~r8n~ recently sent to you •
d. Lette" of concurrence to P1"Oceed wi th f1 nal proj ect
desi~n and construction should be obtained fro. each of the
resource aln8geleftt agencies re.i~"g the f@asfbi1~ty
stud1es.
Also. the possibility of utilizing the aband~ cannery at larsen 8ay
fn place of I separate construction ea., should be addr@ssed •
Significant sa.ings may be realized by using this .aeil1ty. Other
COMIents we haye to offer have been annotated in red in the
attached reports •
'PrOl. C;de: _ 'l9Q I
File Code: _31.1:L7. D3
J. D;;ta: :-~~j---d
....
•
.....
• .. ..
'II! .. .. ..
...
• ..
1M .. ..
'II! ..
...
•
II1II
•
... .. .. ..
-.. .. .. ..
iIII ..
•
...
II1II
... ..
• •
,
Mr. Melvin R~ .• chols
Apr1l 8, 1982
Page 2
Please address all of our cOIInents, including those dfscussed at
the April 9th lleeting. in the final report which is scheduled to be
ccapleted by April 21. 1982. Sbould you have Iny questions, plelse let
_ know. •
FOR THE EXECUTIVE DIRECTOR'
DWB:sh