HomeMy WebLinkAboutReconnaissance Study for Togiak Hydroelectric Project 1982Alaska Energy Authority
LIBRARY COpy
Study for
sIM.:I'\. HYDROELECTRIC PROJECT
&a.£ .. ',",-" INEERS
''LI.,.,,,",,,,~E, ALASKA
GINEERING COMPANY
Ni;J:'tBANllil~LO, CALIFORNIA
-
-
-
-
...
"""
--..
-
-
-----
-
Section
FOREWORD
TOGIAK
CONTENTS
I. SUMMARY
II.
II I.
A.
B.
C.
D.
E.
F.
G.
H.
General
Area Description
Power Planning
Description of Recommended
Hydroelectric Project
Base Case Plan
Economic Analysis
Environmental and Social Impacts
Conclusions and Recommendations
INTRODUCTION
A. General
B. Purpose
C. Project Area Description
D. Authority
E. Scope of Study
F. Study Participants
G. Report Format
H. Acknowledgments
STUDY METHODOLOGY
A. General
B. Pre-Reconnaissance Phase
C. Field Study Phase
D. Office Study Phase
NBI-432-9521-TC i
Page
iv
1-1
1-2
1-2
1-3
1-5
1-5
1-7
1-7
II-1
11-2
II-3
II-3
11-4
11-7
II-8
II-9
111-1
I II-1
II 1-1
111-2
IV.
V.
VI.
VIr.
BASIC DATA
A. General
B. Hydrology
C. Geology and Geotechnics
D. Surveys and Mapping
E. Land Status
F. Previous Reports
G. Hydraulics
ALTERNATIVE SITES CONSIDERED
A.
B.
C.
General
Alternative Projects
Description and Evaluation of Alternatives
ALTERNATIVE HYDROELECTRIC PROJECTS
A. General
B. Conceptual Design Considerations
C.
D.
E.
F.
G.
H.
Description of Alternative Projects
Access Road
Transmission Line
Selection of Turbine-Generator
Project Energy Production
Project Operation Scheme and Controls
PROJECT ENERGY PLANNING
A.
B.
C.
D.
E.
General
Projection Considerations
Energy Demand Projections
Base Case Plan
Hydroelectric Project Plan
VIII. PROJECT COSTS
A.
B.
C.
D.
General
Cost Estimating Basis
Base Case Plan
Recommended Project Costs
NBI-432-9521-TC ii
IV-l
IV-l
IV-3
IV-7
IV-8
IV-9
IV-12
V-l
V-l
V-2
VI-l
VI-l
VI-6
VI-9
VI-10
VI-10
VI-14
VI-15
VII-l
VII-l
VII-4
VII-9
VII-16
VI II-l
VIII-l
VII 1-3
VII 1-3
• -
• ..
• •
• -• -
II .. .. ..
• ..
•
---
-• ..
• -
•
• ..
•
• -• •
-..
..
-
..
-
-
-
-
_.
-
--
---..
-
-
IX. ECONOMIC ANALYSIS
A. General
B.
C.
D.
E.
F.
Project Analysis Parameters
Base Case Economic Analysis
Alternative Hydroelectric Project
Economic Analysis
Economic Comparison of Projects
Unit Costs and Project Timing
X. ENVIRONMENTAL AND SOCIAL EFFECTS
A. General
XI.
XI I.
B.
C.
Environmental Effects
Socioeconomic Effects
PROJECT IMPLEMENTATION
A. General
B. Definitive Project Report
C. Project Development Schedule
D. Project Licenses, Permits and
Institutional Considerations
CONCLUSIONS AND RECOMMENDATIONS
A.
B.
Conclusions
Recommendations
BIBLIOGRAPHY
APPENDIX
A.
B.
C.
D.
E.
Project Drawings
Hydrology
Geology and Geotechnics
Detailed Cost Estimate
Environmental Report
F. Letters and Minutes
G. Space Heating Installation and Cost
NBI-432-9521-TC iii
IX-l
IX-l
IX-3
IX-8
IX-12
IX-13
X-l
X-2
X-9
XI-l
XI-l
XI-4
XI-6
XII-l
XII-2
FOREWORD
This volume, Volume E, presents the findings and recommen-
dations of a study intendeo to fully assess the economic,
technical, environmental, and social viability of a hydropower
project for the village of Togiak. Volumes B, C and D present
feasibility studies for hydropower projects for the villages of
King Cove, Old Harbor, and Larsen Bay, respectively. Volume A
is a summary report incorporating the findings, conclusions,
and recommendations of the other four volumes.
NBI-425-9521-FO iv
.. ..
•
.. -.. ..
•
•
III
• ..
•
• • .. ..
• ..
• .. --
• ...
•
•
• ..
-
-
-
-
-
-
...
-
-
---
--------..
--
SECTION I
SUMMARY
A. GENERAL
Several prior studies of alternative means of supplying the
Togiak area with electrical energy had recommended a hydroelec-
tric project as the best source. As a direct result of these
prior studies and recommendations, the Alaska Power Authority
authorized a reconnaissance-level feasibility study to investi-
gate in detail the hydropower potential in the vicinity of
Togiak.
This report summarizes the activities conducted for the
reconnaissance study. These activities included projections of
energy needs, formulation of alternative hydroelectric projects
and a hypothetical base case to meet the electrical energy
needs of Togiak, detailed analyses of economic feasibility, and
preparation of an environmental assessment of the effects of
the project.
The results of the technical studies conducted ind ica te
that a 432 kilowatt (kW) hydroelectric project utilizing a 38-
foot-high concrete dam could be constructed on the Quigmy River
to meet the elect ric demands of Togiak. However, the resul ts
of the economic analyses indicate that the hydroelectric
project would have only marginal feasibility. An additional
project on the Kurtluk River is currently under investigation.
The results of this investigtion will be presented in a
subsequent report.
The total cost of the proposed Togiak hydroelectric project
is $7,047,200 with the 4.6-mile road option and $8,169,600 with
the 11.6-mile road in January 1982 dollars. The project could
NBI-432-9521-I 1-1
be implemented and on-line by January 1, 1985, if a decision to
proceed with the project is made by December 1982. During an
average water year, the proposed project would be capable of
supplying about 99 percent of the electrical needs and about 30
percent of the space heating needs in the project area. The
equivalent savings in diesel fuel in the year 2001 would be
144,000 gallons for direct electrical demand and 44,000 gallons
for space heating.
B. AREA DESCRIPTION
Togiak is a small village located on Bristol Bay about 70
miles west of Dillingham and 400 miles southwest of
Anchorage. The hydroelectric site selected for detailed study
is on the Quigmy River about 12 miles west of Togiak. The
smaller village of Twin Hills, four miles east of Togiak, was
included in the assessment of the future power needs of the
area.
C. POWER PLANNING
Power planning for the Togiak Project was conducted using
standards set forth by the Alaska Power Authority. Previously
recommended potential hydroelectric sites were investigated and
the project area was surveyed to evaluate potential new
si tes. After detailed study, a project was selected and then
compared with a base case plan. The base case plan consisted
of a cont inua t ion of the present diesel generation system,
enlarged as necessary to meet future growth. The installation
of waste heat recovery equipment and wind generators was also
considered as part of the base case plan.
Present energy demands for Togiak for direct electrical
uses and space heating were estimated and future uses in these
same categories were projected. The projections were based on
forecasts of increases in the number of customers and increased
NBI-432-9521-I 1-2
•
" at .. ..
.,
•
• .. ..
• ..
• ., ..
• ..
• -•
• •
•
•
• •
• •
• -• •
-
,-
-
-
-
-
-
-
-
-'
.. --
... -...
...
"' .. ..
.....
'-...
usage rates. Population growth and employment, legislation and
other political influences, life style changes, and other
factors can influence future energy demands but were not
explicitly treated.
The period of economic evaluation used was 53 years, which
starts in January 1982 and extends for the 50-year life of the
hydroelectric project after the estimated on-line date of
January 1985. The energy demands for Togiak were increased for
20 years starting in 1982 through December 2001. The demands
were then held level over the remainder of the economic
eva I ua t ion per iod. As stated, the neighbor ing communi ty of
Twin Hills was included in estimating future energy demands.
For the proposed hydroelectric project, it was assumed that
the first priority of use for the energy produced would be for
the direct electrical needs of the Togiak area, and any remain-
ing energy would be used for space heating.
D. DESCRIPTION OF RECOMMENDED HYDROELECTRIC PROJECT
Hydroelectric power plants transform the energy of falling
water into electrical energy. Generally, a hydroelectric power
project consists of a dam to produce the head or to divert
stream flows so that they can be passed through a turbine-
generator system to produce electric power. In the case of the
alternative projects considered to bring hydroelectric power to
Togiak, three dam conf i gura t ions and two access road opt ions
were evaluated. These are descr i bed below. All three of the
dams considered would divert water from the Quigmy River
through an intake structure and pass the water through a tur-
bine-generator system to produce electric energy. An access
road would be constructed from Togiak to the project facilities
and a transmission line would be constructed along the access
road alignment to transmit the power generated at the plant to
Togiak .
NB1-432-9521-1 1-3
The general plan and features of the recommended hydroelec-
tric project are presented in the plates of Appendix A. Photo-
graphs of the project area are presented in Exhibits VI-1
through VI-3 of Section VI and in pages 2, 10, and 15 of
Appendix E.
The si te selected for investigation was a narrow canyon
sui table for ei ther a concrete or rockfill dam. Since both
types were apparently technically feasible, two concrete dams
(38 and 28 feet high) and one rockfill dam were investigated to
evaluate their economic feasibility and confirm their technical
feasi bi Ii ty. Al though the Quigmy River above the proposed dam
site locations might not be a major spawning area, the
preliminary designs for all three dam alternatives incorporated
fish ladders to allow for fish passage.
An 11.6-mile road would be required to provide access from
Togiak to the proposed facilities. The Alaska State Department
of Transportation and Public Facilities, Division of Aviation,
is investigating the possibili ty of building a road along the
first seven miles of the proposed access road alignment in
order to reach a gravel source needed to construct an airport
to serve Togiak. Two possibili ties exist for obtaining an
access road for the proposed hydroelectric project:
1.
2.
The entire 11.6-mile road would be built as part of
the hydroelectric project.
The Alaska Department of Transportation would build
the first seven miles of the road and the hydroelec-
tric project would build the remaining 4.6 miles.
The investigations conducted during this study indicate
that the most favorable combination, and indeed the only one
tha t could be economically feasible, is the 38-foot-high
concrete dam wi th only 4.6 mi les of the access road being
funded by the project.
NBI-432-9521-1 1-4
• •
•
--•
•
• .. ..
• -..
• ..
•
•
•
• ..
• •
•
• .. .. -
• •
• ... ..
-..
-
-
-
••
. ,
.. '
.". . ,
••
....
--
. -
.. or
••
...
-
...
..... --..
E. BASE CASE PLAN
The base case plan formulated to meet the projected energy
demands of Togiak assumed that the existing diesel system would
continue to be used as the sole source of electric power. It
was also assumed that the system would be modified to incorpor-
ate waste heat recovery that would be used for space heating .
Wind generation would also be installed as part of this plan.
The existing diesel plant's capacity was judged to be adequate
to meet peak demands on the Togiak syst~m throughout the period
of study. The forecasted energy demands for the base case
included the requirements for Twin Hills .
F. ECONOMIC ANALYSIS
The economic analysis was based on the Alaska Power
Authori ty criteria that compare the net present worth of the
base case costs to the net present worth of the al terna ti ve
proposed hydroelectric project costs using specified real price
escalation and discount rates. Net present worth is the
present value of the costs that would be incurred over a
comparable economic evaluation period of 53 years for both
projects .
The net present worths of the base case are as follows:
Base Case Only
Waste Heat Credit
Subtotal
Wind Energy Credit
Subtotal
Space Heating Credit
Total
NBI-432-9521-I
Alternatives A & C
$11,027,600
999,400
10,028,200
540,700
9,487,500
2,463,000
$11,950,500
1-5
Alternative B
$11,027,600
999,400
10,028,200
540,700
9,487,500
1,234,800
$10,722,300
The space heating credi t was shown as an increase in cost
to the base case so that all present worths could be compared
to the hydroelectric project standing alone.
For the three al terna tive hydroelectric projects studied,
the present worth of the costs is as follows:
Alternative A
Alternative B
Alternative C
W /11. 6-Mi le Road
$12,758,400
13,037,400
13,257,700
W/4.6-Mile Road
$11,668,600
11,947,600
12,167,900
As can be noted from the table, the only hydroelectric
alternative with a lower present worth cost than the base case
is alternative A, and then only if the 4.6-mile roadway can be
constructed.
An additional measure of project feasibility is the bene-
fit/cost (B/C) ratio. The B/C ratio is the present worth of
the project benefi ts divided by the net present worth of the
project costs. For the alternative studies for this project,
the calculated B/C ratios were as follows:
Alternative A
Alternative B
Alternative C
B/C Ratio
W /11. 6-Mi le Roap
0.937
0.822
0.982
B/C Ratio
W/4.6-Mile Road
1.024
0.897
0.901
These results indicate that Alternative A, the 38-foot-high
concrete dam with 432 kW installed capacity, is marginally
feasibile only if the Alaska Department of Transportation con-
structs the first 7.0 miles of the required 11.6-mile access
NB1-432-9521-1 1-6
.. ..
• ..
• -
• ..
-
• ..
•
•
•
a
til
• .. -• ..
• --• • ..
•
• ..
• •
-
• •
-
-
---'
-
-
-
-
-
-
--..
--
--.-
••
...
, ....
road. If the entire 11. 6-mile road must be constructed, the
project is a break-even proposition.
G. ENVIRONMENTAL AND SOCIAL EFFECTS
The study results indicate that a hydroelectric project at
the Quigmy site could have potentially serious environmental
impacts, but measures such as fish ladders could likely miti-
gate the most serious effects. Additional studies are recom-
mended to answer questions related to the downstream effects of
the dam impoundment on salmon spawning; coho (silver) salmon
runs; minimum water requirements for fish below the proposed
dam; selection of a suitable access route; and methods to
ensure safe passage of out-migrating young salmon. Additional
study of fish passage facilities is also recommended.
H. CONCLUSIONS AND RECOMMENDATIONS
The studies conducted for this report indicate that a
marginally feasible project consisting of a 38-foot-high
concrete dam with 432 kW installed capacity could be con-
structed at the Quigmy River site. The next step in project
implementation, the preparation of a Definitive Project Report
to optimize the project features, should be pursued only if the
Alaska Department of Transportation constructs the initial 7.0
miles of the necessary 11.6-mile-Iong access road.
A more detailed investigation of a much smaller hydroelec-
tric site on the Kurtluk River three miles from Togiak could be
pursued, but the project would meet only a small portion of the
Togiak electric demands. The site is currently being investi-
gated at a preliminary level and will be addressed in a
subsequent letter report.
NBI-432-9521-I 1-7
_f
....
......
...
.....
.. Of
...
"of
WI
-
-
-
..
--
SECTION II
INTRODUCTION
A. GENERAL
Togiak is a small village located on Bristol Bay about 80
miles west of Dillingham and 400 miles southwest of
Anchorage. The village currently relies upon an Alaska Village
Electric Cooperative (AVEC) diesel generation system for its
electrical energy. The smaller adjacent village of Twin Hills,
located about four miles east of Togiak, is not a part of the
AVEC system. It ut il izes small ind i vidual d iesel generators
for electrical energy. Due to its proximity to Togiak, Twin
Hills has also been included in this assessment of hydropower
potential. Throughout this report, references to Togiak
therefore include Twin Hills and are not limited to the village
of Togiak alone.
Diesel systems for electrical generation have several
serious drawbacks, especially in remote locations--availability
and cost of diesel fuel, expected shortages and increased
expense of fuel in the future, potential maintenance problems,
and the cost and availability of parts or even whole systems.
The installation of hydroelectric generating capacity would
potentially alleviate the major problems inherent in the diesel
systems and would provide dependable generating capacity over a
long time span. This report presents the results of a
reconnaissance study to assess the engineering, economic,
environmental feasibility of such an installation in
vicinity of Togiak .
NBI-384-9521-II II-l
and
the
This particular section of the report describes the purpose
and scope of the study , the physical and economic character-
istics of the project area, and the organizational makeup of
the participants in the study.
B. PURPOSE
The primary purpose of this
determine whether it is feasible
and environmental viewpoints to
project in the vicinity of Togiak.
reconnaissance study was to
from engineering, economic,
construct a hydroelectric
Prior studies of alternative energy sources to serve Togiak
had evaluated energy conservation, waste heat recovery,
hydroelectric generation, wind energy conversion, photovoltaic,
gasification, solar (both active and passive), and fuel
cells. These studies had indicated that hydroelectric
generation was the best available alternative to diesel
generation for Togiak. In particular, a potential dam site on
the Quigmy River was recommended for further study. This
particular study is a direct result of these recommendations.
In conducting the study, several alternative hydroelectric
projects were compared with a base case plan that consisted of
the present diesel generating units supplemented by wind
genera t ion that would be augmented wi th add it ional uni ts as
necessary to accommodate growth. Waste heat would be recovered
and incorporated into the system to the maximum extent
possible.
It is intended that the results of this study be used to
decide whether or not to proceed wi th a defini ti ve project
report, to optimize the project features, and to determine
future funding requirements.
NBI-384-9521-II 11-2
• •
•
• -
• -• -
• •
• •
• .. .. .. -•
..
• -
• -• •
•
•
•
-
• ..
-
-
-
-
-
-
-
-
-
-
-
-
-
-....
-
-
-
C. PROJECT AREA DESCRIPTION
The village of Togiak is located at the head of Togiak Bay,
two miles west of the Togiak River. The entire area is part of
the larger Bristol Bay region of southwest Alaska and also a
part of the Ahklum Mountain physiographic province. The
village population (513 persons in August 1981) remains fairly
stable year-round, and it is generally made up of commercial
fishermen. Th ree f ish processing fac iIi ties are I oca ted near
the vi llage, and commercial and subsistence f ishi ng is
available right in front of the village so that residents do
not have to set up summer fish camps elsewhere.
The general area is located in a climatic transition
zone. The primary influence is mari time; however, the arctic
climate of interior Alaska also affects the region. The area
is characterized by cloudy skies, mild temperatures, and
moderately heavy precipitation.
The proposed Togiak Hydroelectric Project would be situated
on the Quigmy River approximately 11 miles west of the village
of Togiak. The Quigmy River is a clear, moderately swift
stream that generally meanders from north to south. The
proposed d am and powerhouse site are I oca ted in a sect ion of
the stream characterized by 10-to 100-foot rock walls that
constrict the river into a series of 15-to 20-foot-wide gorges
where the fast-flowing water reaches depths of up to 10 feet.
In between these gorges, the river slows and forms gravel
bars. The proposed dam site is in a 75-foot-deep gorge that is
narrow at the crest of the dam and widens to a slower-moving
pool and gravel bar just beyond the downstream toe of the dam.
D. AUTHORITY
The Alaska Power Authority (APA) has authorized studies to
prepare the "Detailed Feasibili ty Analyses of Hydroelectric
NBI-384-9521-II 11-3
Projects at King Cove, Larsen Bay, 01 d Harbor and Togiak."
This particular report, Volume E, summarizes the studies con-
ducted for Togiak. APA is a public corporation of the
Department of Commerce and Economic Development, State of
Alaska.
E. SCOPE OF STUDY
In general the scope of the study consists of an analysis
at a reconnaissance level of the the costs and benefits of
alternative hydroelectric projects, a comparison of these costs
and benefits with those for the base case plan for the village,
and an environmental assessment of the effects of the proj-
ect. To accomplish these goals, the following activities were
necessary.
1. Data Accumulation
Data collected included existing flow records, topographi-
cal mapping, present and future demands for power, applicable
1 aws and regul at ions, exist ing reports, and other appl icable
information that was available.
2. Site Reconnaissance
The purpose of the site reconnaissance was to supplement
and verify the data gathered, to collect topographical, hydro-
logical, environmental, and geotechnical data, and to determine
the accessibility of the site. The conceptual design of
project features was established in the field.
3. Site Surveys
A topographic survey was conducted at the site of the
proposed dam, powerhouse, and transmission line in sufficient
detail to make reconnaissance-level design layouts.
NBI-384-9521-II 11-4
..
• .. ...
..
...
.. ..
.-..
• -
-
• .. .. ..
• ..
•
• ..
• ---,. -•
• -
-
-
....
-
-
-
-
-
-
-
-
-
-
-
-
-
4. Hyd rology
Hydrologic data were developed from the limited available
data. A suitable method was established to prepare a stream-
flow table, a flow duration curve, and a seasonal distribution
of the flow duration curve. A stream gage was installed near
the project site to obtain additional streamflow data.
Diversion and flooding problems were also considered.
5. Geotechnical Investigations
Geotechnical investigations were conducted to determine
mater ial sources, slope stabi lit ies, and load-bear ing charac-
teristics of the foundations for all structures in the project.
6. Base Case Plan
A base case plan was analyzed that assumed a continuation
of the existing diesel generation system, supplemented by wind
generation, and least-cost additions for future generators.
Included in this analysis was an assessment of current ener~y
usage and a forecast for the life of the project. The cost of
continuing the use of the base case plan provided a basis for
determining the value of power at the site. Data regarding the
energy potential and cost of wind generation at the Togiak
sites were provided by another contractor to APA.
7. Power Studies
Several different types of turbines and a range of
installed capaci ties were evaluated to determine the optimal
configuration.
NBI-384-9521-I1 11-5
8. Environmental Overview
The envi ronmental i nvesti gat ion was conducted to i denti fy
any environmental constraints that might prohibit project
development.
9. Design
Layouts of the alternative projects were made and sizes and
capaci ties of water-carrying, structural, and control compon-
ents were determined. All features of the al ternatives were
designed in sufficient detail to allow cost estimates to be
prepared.
10. Cost Estimates ,
Cost estimates, including direct and indirect costs, were
prepared using a present cost base escalated to the anticipated
time of construction.
11. Economic Analysis
The project was analyzed using the economic criteria of the
Alaska Power Authori ty. The general methodology employed was
to compute the net present worth of the costs of the proposed
hydroelectric project over a 50-year project life and to
compare these costs to the net present worth of the costs of
the base case plan over the same 50-year project life.
12. Environmental Assessment
A detailed environmental analysis was conducted based upon
the final design and layout of the project.
NBI-384-9521-11 11-6
•
.. ..
• -----
• -• -
-
• -
• .. -
•
• ..
• --•
• -
•
•
iii -
-
-
.....
-
-
.... -
-
---
-
-
-
-
13. Conclusions and Recommendations
The report presents findings of the reconnaissance study
and recommends a future course of action to be followed.
14. Public Meetings
Public meetings were conducted in Togiak at the beginning
of the projec t stud ies to obtai n comments from local cit i-
zens. Another public meeting was held in Togiak to present the
findings and conclusions of the study and to solici t public
comments • All letters and comments received from federal and
state agencies were answered by APA with changes incorporated
in the text of the final report as required. A copy of the
comments and replies is contained in Appendix F.
15. Report
A draft report was submitted to the APA in February 1982,
and the final report incorporating all comments was submitted
in August 1982.
F. STUDY PARTICIPANTS
DOWL Engineers, of Anchorage, Alaska, was the primary
contractor for the study. DOWL was assisted by two subcon-
tractors--Tudor Engineering Company of San Francisco, Cali-
fornia, and Dryden & LaRue of Anchorage, Alaska. The primary
role played by each of the participants is covered below.
1. DOWL Engineers
DOWL Engineers, an Alaskan partnership, performed the
projec t managemen t funct ion and provided the primary con tac t
with the Alaska Power Authority. DOWL collected basic data,
participated in the hydrology studies, and had the prime
NBI-384-9521-II II-7
responsibility for the local coordination activities, geology
and geotechnics, and environmental, ground survey, stream
gaging, and wind velocity aspects of the investigation.
2. Tudor Engineering Company
Tudor, as principal subcontractor, supplied all hydro-
electric expertise for the project. They directed data
collection and conceptual design of facilities; assisted with
public meetings; assisted and provided direction in evaluating
the base case plan and power values, formulating cost esti-
mates, and making the financial and economic eval ua t ion; and
furnished advice on the aspects of the environmental problems
that are unique to hydroelectric projects. Tudor prepared the
initial draft of the project report.
3. Dryden & LaRue (D&L)
The partners in D&L are electrical engineers registered in
Alaska. Much of the electrical work was accomplished in close
cooperation wi th this firm. Transmission lines and backup
diesel generation facilities were involved as well as questions
related to reliability and integrated operation of the proposed
system wi th existing village systems. D&L and Tudor estab-
lished the value of power and the present and projected power
demands. D&L provided the feasibility designs and cost
estimates for the transmission lines and appurtenant electric
features.
G. REPORT FORMAT
Pages, tables, figures, and exhibi ts in this report are
numbered wi thi n the sec t ions in which they appear. Wi thi n
sections, the tables, figures, and exhibits are placed at the
end of the text. References noted in the text are listed in
the Bibliography.
NBI-384-9521-I1 II-8
•
•
•
-
-.. ..
• ..
-.. -•
• -.. ,.
• -.. ..
• -•
-
• -
.-
-
-
-
-
-
-
-
-
-
--
-
-
H. ACKNOWLEDGMENTS
The cooperation of the many federal, state, and local agen-
cies and local residents contacted during the course of the
study is gratefully acknowledged. This list includes, but is
not limi ted to, the Alaska Power Administration, the Alaska
Department of Fish and Game, the Al aska Department of Trans-
portation, the Alaska Department of Natural Resources, the V.S.
Army Corps of Engineers, the V. S. Geological Survey, and the
V.S. Fish and Wildlife Service. The assistance of the Rockford
Corporation and the Locher Construction Company, a subsidiary
of Anglo Energy Company, is also acknowledged. Individuals who
were especially helpful include Don Baxter of APA, Dan Pavey
and Carl Siebe of the Alaska Department of Transportation, Wes
Bucher of the Alaska Department of Fish and Game, and Andrew
Franklin of Togiak.
NBI-384-9521-II II-9
.-
-
-
-
-
--
-
-
SECTION I II
STUDY METHODOLOGY
A. GENERAL
This section describes the general methodologies employed
and steps taken to complete the project studies and analyses.
In general, the study proceeded in three phases--
pre-reconnaissance, fiel d stud ies, and off ice stud ies. Each
project phase is described briefly below and the resul ts are
covered in detail in the following sections of the report and
the appendices.
B. PRE-RECONNAISSANCE PHASE
This phase consisted of initial data collection and
analyses, obtaining access permits, coordination with resource
agencies, and evaluation of the existing material and reports.
A brief 24-hour visit spanning two days was made to Togiak by
the project team to hold the initial public meeting to inform
the residents of project investigation activities. The initial
field evaluation of available alternative hydroelectric sites
was also made along with preliminary environmental evaluations
of all sites. Office studies of alternative sites and
environmental conditions had preceded the initial field work.
The project team on this initial visit consisted of individuals
wi th geologic, geotechnical, hydroelectric, hydrological,
environmental, and electrical expertise. All individuals
participated in evaluating the alternatives and conducting the
field investigations.
C. FIELD STUDY PHASE
The field studies were conducted several weeks after
initial pre-reconnaissance activities, mobilization, and field
NBI-425-9521-III II 1-1
planning were completed. Detailed site investigations spanning
several days were made by the hydroelectric engineers to define
the location of the project features. They were aided in this
work by the geology and geotechnic team, which also made a
detailed investigation of geology and soil conditions following
final selection of the feature locations. Field environmental
and hydrologic investigations were also conducted in parallel
as the field conceptual design work was completed.
The
electric
field survey team
and geotechnical
immediately followed
teams to the field
the hydro-
to conduct
detailed surveys.
hydrology group.
A stream gage was also establ ished by the
Data were gathered from Togiak regarding the present and
planned generating conditions of the city system.
D. OFFICE STUDY PHASE
The final and most extensive phase of the study was the
office study phase where all data gathered from the field and
all accumulated data and information were analyzed and addi-
tional investigations were conducted to complete the project
activities.
Separate reports were produced for the hydrology, geology
and geotechnical, and environmental activities. They are
i ncl uded wi th th is report as Append ices B, C and E, respec-
tively. The environmental appendix also includes information
on permitting requirements, social impacts, and land status.
Project energy planning studies were conducted to define
the year-by-year electrical and heating demands of Togiak.
'To meet the energy
installed capaci ties were
NB I-425-952l-II I
requirements
analyzed to
II 1-2
at Togiak, various
determine the optimal
.. .. .. -.. ... -...
• ..
• ..
• -• .. .. --
.. -• ..
• -----
•
..
..
-
-
-
-
.....
-
-
-
-,
-
---
----..
--
-
-
project size and the conceptual design of the hydroelectric
project. These tasks were completed with the aid of the maps
prepared from the field activities. Three alternatives were
investigated at a reconnaissance level, two concrete dams and
one rockfill dam. Three detailed cost estimates were then
prepared based on final sizes ranging from 288 to 432 kW and
project layouts were prepared. The economic analysis was then
conducted to complete the project analysis activi ties, and a
draft report was prepared.
Following a preliminary review of the report by the Alaska
Power Authori ty, an additional meeting was held in Togiak to
solicit public comments. The draft was circulated to all
concerned state and federal agencies. After receipt and
consideration of comments, the final report was compiled.
Appendix F contains a copy of all the comments received and the
replies prepared by APA and the Contractor.
NBI-425-9521-II1 II 1-3
-
--
-
-
-
.....
-
-
....
-
------------..
-
SECTION IV
BASIC DATA
A. GENERAL
This section describes in general the basic data used in
the preparation of the Togiak report. Included are hydrologic,
geologic and geotechnical data, surveys and mapping, land
ownership status, and previous reports.
B. HYDROLOGY
The primary thrust of the hydrologic studies for the Togiak
Hydroelectric Project concerned the development of a flow
duration curve, an annual hydrograph, and a flood frequency
curve for Quigmy River. A complete report of the steps taken
to create those items is covered in the hydrology report
included with this report as Appendix B •
No streamflow data were available for Quigmy River except
for a few sporadic point discharge measurements made in connec-
tion with this study. An automatic stream stage recorder has
now been installed. The general methodology employed to
develop the Qu igmy Ri ver f low duration and hydrograph was to
first develop an estimated value for the Quigmy River mean
annual flow. Dimensionless flow duration curves and
hydrographs were then developed from the records of a long-term
stream gaging station, Eskimo Creek at King Salmon. Applying
the Quigmy River mean annual flow to the dimensionless curves
then yielded a specific flow duration and hydrograph for Quigmy
River. These results have correlated closely with streamflow
measurements obtained to date from the stream gage installed
near the project site.
NBI-384-9521-IV IV-l
1. Mean Annual Flow
The mean annual flow was developed using three different
estimating techniques--the modified rational formula, regional
analysis, and the channel geomorphology method. The three
methods yielded similar values and the Quigmy River mean annual
flow was taken as 220 cfs.
2. Flow Duration Curve
The closest gaged stream with an adequate length of record
and characteristics similar to the Quigmy River is Eskimo Creek
at King Salmon (No. 15297900), 150 miles to the east of
Togiak. The Eskimo Creek flow duration curve developed from
six years of daily record was adopted as the type of curve for
moderate-sized open tundra basins in the Bristol Bay area of
Alaska. The Quigmy River flow duration curve presented as
Figure IV-1 is based primarily on Eskimo Creek scaled to the
ratio of its respective mean annual flows.
3. Annual Hydrograph
Based on the same data and reasoning that went into
determining the mean annual flow and the flow duration curve,
an annual hydrograph was developed based on monthly flows at
Quigmy Rive r. The resulting annual hydrograph is presented in
Figure IV-2.
4. Flood Frequency Curve
Estimates of flood discharges are based entirely on
regional analyses. Regression equations obtained through
reg ional anal yses were first appl ied to the gaged st ream to
test their applicability. The basin and climatological
characteristics of the ungaged Quigmy River were then entered
to obtain the following flood frequency values.
NBI-384-9521-IV IV-2
• • --.. --•
• •
• -•
•
•
• ..
• ..
• ..
--.. .. .. -
.. ..
• ...
-
-
-
-
-
-
-
-
-
-----,--
-
-
Q10 = 4300 cfs
Q25 = 5100 cfs
Q50 = 6300 cfs
Q100= 7700 cfs
These data are plotted on a frequency curve and presented as
Figure IV-3.
An interim spillway design flood of 11,000 cfs, equivalent
to approximately a 500-year flood, is recommended for the
purpose of feasibility design sizing.
5. Potential River Ice Problems
A brief evaluation of potential icing at the diversion weir
and penstock intake point indicates that potential problems may
resul t from sheet ice and frazil ice formation. Few data are
presently available to quantify those problems and an in-depth
study of the extent of the problems and an evaluation of
avail abl e measures to avo id , all ev ia te, or mi t iga te the
problems will be necessary during the design phase of this
project.
C. GEOLOGY AND GEOTECHNICS
The purpose of the geologic and geotechnical studies con-
ducted for th i s report was to assess the geol og ic hazard s,
establish appropriate design criteria, explore material borrow
sites, and provide background information for environmental
stud ies. A compl ete Geology and Geotechn ics Report cover ing
these items in detail is included as Appendix C. A summary of
the report is included below.
NBI-384-9521-IV IV-3
1. Site Topography
Togiak is situated near the mouth of the Togiak River on a
broad alluvial plain that extends down to Togiak Bay, part of
the larger Bristol Bay Region of Southwest Alaska. The entire
area is part of the Ahklun Mountains physiographic province.
The potential dam sites on the Quigmy and Kurtluk Rivers are
approximately 11 and 4 miles, respectively, west of Togiak.
Between Togiak and the dam sites the entire area has been
glaciated and is dominated by bedrock hills that have been
sculptured by erosional and depositional glacial processes.
These bedrock hills are mostly between 500 and 700 feet high
and reach a maximum height of approximately 1100 feet wi thin
the project area. In most areas along the Quigmy and Kurtluk
Rivers, the glacial deposits are thick and the rivers have cut
down through these deposits and excavated narrow slots into the
bedrock.
Numerous lakes and wetlands are present locally as a result
of the flat topography on old outwash channels, current
floodplains, and the depressions associated with stagnant ice
topography.
The beach area immediately near Togiak consists of succes-
s i ve beach rid ges that have been accreted to the all uvial
deposi ts of the Togiak River. Further to the southwest of
Togiak, steep beach cliffs range in height from 15 to 200 feet.
2. Regional Geology
The Togiak area is just north of one of the more acti ve
mountain-building, seismic, and volcanic regions in the world.
The Pacific plate of oceanic crust is being subducted beneath
the North American continental crustal plate in the area of the
Aleutian Trench. Associated tectonic forces have caused the
NBI-384-9521-IV IV-4
• -• ..
•
.. -• ...
..
• -• -• ..
• ---• ..
II .. -• -.. ..
• .. --.. -
-
-
-
-
-
-
-
--
-
-
-
-
--
-
-
-
uplift of the Alaska Range and the seismic activity
characteristic of this part of Alaska.
Bedrock in the Togiak area consists of a folded seauence of
sedimentary and volcanic rocks overlain by glacial drift, peat
deposits, modern alluvium, and beach deposits. The bedrock has
been assigned to the Gemuk Group. The sil tstones ran~e from
very well bedded near the mouth of the Quigmy River to massive
and highly silicified at the proposed Quigmy dam site. Chert
is locally present and limestone has been reported in the Gemuk
Group, although it was not observed in the project area.
In various regions of Alaska there have been five major
glacial advances during the Quaternary. The project area has
been subjected to at least two of these events. Glacial drift
in the proj ect area consists of abundant outwash deposits,
till, and ice-contact stratified drift deposits.
3. Site Geology
Gemuk Group rocks crop out at the dam site and are mantled
by stream gravels in the stream bed and talus deposits on one
of the side slopes. Gemuk rocks in the study area are
predominantly silicified siltstones and andesitic
volcaniclastic rocks. The bedrock consists of a silicified
sil tstone with local concentrations of chert. The rock was
fractured and subsequently bonded by quartz vein fillings
approximately one to three millimeters in width. Breakage by
rock blows is across the veins, suggesting excellent bonding.
Silicification extends into the siltstone itself to produce a
very hard, competent rock.
are of no consequence.
Joints and cracks are present but
There is one major crack in the cliffs above the dam. The
isolated block of rock should be blasted away along with any
overhangs of rock.
NBI-384-9521-IV IV-5
Much of the streambed adjacent to the dam site is scoured
to bedrock; sediment thickness greater than three feet is not
expected.
A talus deposit separated from the dam site by a rock knob
may extend below the water line under certain flow conditions
and may require grouting or removal.
Two road routes are optional. Option A is from Togiak to
the dam site. It utilizes the existing road and 10.15 miles of
new road, 5 miles of which would be on gravel with a minimum of
cut and fill. The gravel 1 ies beneath 18 inches to 2 feet of
silty gravel that would require removal. The remaining portion
is on till, and hauling of gravel for fill would be necessary.
Option B presumes the building of a small dock near the
mouth of the Quigmy River. The road would cross 2.5 miles of
till where cutting, filling, and hauling of gravel would be
required. Beyond the till is good clean terrace gravels for
the remaining four miles of road.
4. Construction Materials
Rock sui table for riprap needs can be excavated from the
tal us pile noted above or it can be blasted from the cliff
walls. Seven borrow areas have been identified as potential
sites to borrow sand and gravel.
5. Seismic Hazards
Southwestern Alaska is part of an intense seismic zone that
circumscribes the Pacific Ocean. Most of the more than 150,000
earthquakes that occur worldwide each year occur in this
circum-Pacific belt and in a somewhat smaller belt that extends
through southern Asia and the Mediterranean.
NB I -384-9521-1 V 1V-6
• -• -
III -.. -.. .. .. -• -• •
• ...
• --
• ... .. ..
• --
• -• .. -..
• ..
-
---
-
-
-
-
-
-
-
-
-------------
-
Major and minor faults are present in the Togiak area but
the proposed dam site does not appear to be subject to fault-
slip. The recommended design criteria based upon a 50-year
life of structure is a base acceleration of 10 percent of the
acceleration due to gravity. No major landslides are
expected. Seiches or tsunamis would not affect the proposed
structures.
D. SURVEYS AND MAPPING
During the earliest phase of the study, data collection and
anal ysis, USGS topograph ic maps were used to pI an the field
study and to make conceptual layouts of the project. Once the
field effort had determined the best location for the facility,
gaging locations were establ ished, and stream channel, flood-
plain, and streamflow measurements were made at selected
stations.
A detailed ground survey was made of the Ouigmy River site
between October 10 and 15, 1981. The survey and drawings pro-
duced from them included ground control, topographic mapping (1
inch = 10 feet, 2-foot contour interval) and cross sections in
the vicinity of the dam as marked in the field by the hydro-
electric engineers.
Addi tional channel sections were taken over a 1200-foot
reach to def ine tail water and stream gage cond it ions.
Elevation datum was assumed.
A similar survey was made at the alternative Kurtluk River
site that is located nearer to Togiak.
Pr ior mapping in the area is I imi ted to 15 minute USGS
quadrangles (1:63,360, 50-foot contour interval, 1954). The
site and access route to Togiak are located on the Goodnews Ray
NB 1-384 -9521-1 V IV-7
A-4 and A-5 Quadrangle Maps. High-altitude, false-color
infrared stereo photography was also used.
Previous geological surveys and reports, as well as field
verification and investigation, were used to create a geologic
map of the Togiak area (see Appendix C).
E. LAND STATUS
A map showing the land status in Togiak and the project
area is presented in Figure IV-4. The proposed dam site on the
Quigmy River and the three proposed borrow sites are on lands
selected by Togiak Natives, Limited, as part of their
entitlements under the Alaska Native Claims Settlement Act
(ANCSA), Public Law 92-203, enacted December 18, 1971. The
U.S. Fish and Wildlife Service (USFWS) has the management
responsibility for this area as well as all other land
classified Village Selected in this general area until final
disposi tion is made. All USFWS and Village Selected lands in
the general project area are in the Togiak National Wildlife
Ref uge.
The proposed dam site on the Kurtluk River and two
assoc ia ted borrow si tes are on 1 and s in ter im-conveyed under
ANCSA to Togiak Natives, Limited. Interim conveyance is used
to convey unsurveyed lands. Patent will follow interim
conveyance once the lands are identified by survey. The
subsurface estate for all lands in the proposed project area
conveyed to Togiak Natives, Limited, has been interim-conveyed
to the reg ional nat i ve corporation, Br i stol Bay Na t i ve
Co r po rat ion.
Togiak has a federal townsite, U.S.S. 4905, with the patent
issued to
Tr ustee.
residents
the Bureau of Land Management (BLM) Townsite
The Trustee has deeded occupied parcels to the
and some vacant lots to the city of Togiak. Other
NBI-384-9521-IV IV-8
• •
• .. --• ..
• ..
• •
• ..
• •
• ..
• •
• ..
•
• ..
• -.. ... -..
• -.. -• -
-
.,..,
-
-
-
-
-
-
-
-
-
-
--..
..
.....
subdivided property remains wi th the Trustee. A permit would
be required for the transmission line to cross Trustee land and
it could be issued by the U.S. Department of Interior following
an affirmative resolution by the City Council.
The final transmission route and transportation corridor
has not been selected at this time, but all preliminary
alternatives for both are entirely within interim conveyed
lands of Togiak Natives, Limited, with the exception of a small
portion near the Quigmy River and four parcels classified both
Village Selection and Native Allotment application. Since
final disposition of the Village Selected lands and final
decisions on the project conceptual plan have not been made,
coordination with USFWS, Togiak Natives, Limited, Bristol Bay
Corporation, and BLM is recommended so that delays in acquiring
the needed permits and easements may possibly be avoided.
F. PREVIOUS REPORTS
Hyd roelectr ic poten tial at Tog iak has been the subj ect of
four previous reports. They are listed below, in chronological
order of publ ication, wi th an ind ication of their scope and
major conclusions.
1. "Small Hydroelectric Inventory of Villages Served by
Alaska Village Electric Cooperative," prepared for United
St a tes Departmen t of En ergy, Al aska Power Admin ist ration, by
AVEC Engineers, December 1979.
These studies concentrated on two small streams, two and
one-hal f miles west and northwest of town, thought to have
power potential. Field examination proved the drainage areas
and flows were too small for a feasible project.
NBI-384-9521-IV IV-9
Aerial examination identified the Kurtluk River, four miles
west of town, as the best power site. The estimated power
potential, based upon 10 cfs and 50 feet of head, was 30 kW,
only a small part of the 1978 Togiak demand. The estimated
cost ranged between $0.85 and $4.26 per kWh.
2. "Bristol Bay Energy and Electric Power Potential,"
prepared for U.S. Department of Energy, Alaska Power
Administration, December 1979.
This study was conducted to find (1) energy balance for
1977, (2) electric power requirements to the year 2000, (3)
potential energy and electric power resources, (4) electric
power resources, and (5) recommendations for developments or
future studies for the Bristol Bay Area. Togiak was contained
in the Bristol Bay study area.
In 1977 the Togiak area was shown to have a power demand of
150 kW and an energy demand of 512,000,000 kWh. The
correspond ing 2020 proj ec ted demand s were 1700 kW and
7,402,000,000 kWh.
For the Togiak Bay Area the report concluded that
"Potential resources that could be developed economically
within the foreseeable future have not been found."
3. Northern Technical Services and Van Gulik Associates,
Inc. , "Commun i ty En ergy Reconnaissance of Good news Bay,
Grayl ing, Scammon Bay, and Tog iak ." A repor t to the Alaska
Power Authority, February 1981.
This in-depth study, conducted along Alaska Power Authority
guidel ines, compared the base-case plan with several energy
alternatives. The recommendations for Togiak include:
NBI -384-9521-1 V IV-10
• • -
--
• -... ...
• ..
• -• ...
• ..
• -• •
• -.. -
• .. .. .. -.. .. ..
... -• -
-
...
-
-
-
-
-
-
-
-
-
-
-
..
----
-
a.
g.
c.
Energy conservation
Waste heat capture from diesel generators
Hydroelectric power from Quigmy River
The investigations recommended, as part of the Quigmy River
assessment, that stream gaging, fish habitat and spawning
potential analysis, and site analysis be undertaken, as well as
an attempt to change the land use designation of Quigmy River
area.
4. "Small-Scale Hydropower Reconnaissance Study,
Southwest Alaska," prepared for Department of the Army, Alaska
Dist r ic t, Corps of Engineers, by R. W. Beck and Associ ates,
April 1981.
The report summarizes the results of a reconnaissance-level
study to determine the potential for meeting the energy needs
of 84 communi ties in southwest Alaska by the development of
small-scale hydro power projects.
Two potential si tes were selected for study to serve the
Togiak area. One was a small site west of Togiak at a
waterfall on a tributary of the Kurtluk River. The other site
was located on a tributary of the Quigmy River. The total
output of the two sites combined could be used in the first
year of operation.
The installed capacity at the Kurtluk River Tributary site
would be 50 kW at a cost of $3,258,000. This represents a cost
of $65,200 per kW. The benefit/cost ratio was determined to be
0.31 to 1.
The installed capaci ty at the Quigmy River tributary si te
would be 80 kW at a cost of $6,157,000, or $77,000 per kW. The
benefit/cost ratio was estimated to be 0.27 to 1.
NBI-384-9521-IV IV-11
G. HYDRAULICS
Using data obtained in the field on the river channel and
floodplain characteristics, a computer model of the river was
developed. The model was used to establish a tailwater rating
curve for the Togiak si te (see Figure IV-5). This curve was
checked against actual field measurements of depth, flow and
visible water marks.
A probable maximum flood of 10,000 cfs was used as the
basic criterion to size the spillway and to determine the crest
elevation of the dam.
NB I -384-9521-1 V IV-I?
• ..
• ... ..
-..
• ..
• ..
• ..
• ..
•
• ..
• ...
• ...
• .. .. -
•
.. .. .. ..
• ..
• -
-
..
-
-
-
-
~" -..(
-
'P1M_
-
-
-
-
-
-------
-
1200
1100
1000
900
800
-700 fI)
~
(.) -
~ 600
0
...J
~
500
\
\ ,
400
300
\
\
\.
" ~ MEAr ANN LJAL F LOW ~20 cf~
200
tOO
~ ....... ,
~ r---..-----...... " o 0 10 20 30 40 50 60 70 80 90 100
PERCENT (0'0) OF TIME FLOW EXCEEDED
QUIGMY RIVER DAM SITE
FLOW DURATION CURVE
FIGURE
Br-I
700~~~--~--~--r---~--~--.---.---,---,----,--~ ESTI~ATEDI RANG~ OF LERJGE •••••••••••••••••••••
MONTHLY FLOWS 7 OUT OF 10 YEARS--.. rr~«<
~i;:::::::::::::::l:: 600~--~--+---+---4---~--~---+---4----~~~--+-~ 500~--~--+---+---~.:~:::::~:::::~::::::~:::::~--~--~--+---~I~i~l~I~--+-~
·.iii:i .: •. ~ ..• :: .•. : ••. :.: .• :: .•. : .•.. : .. : .•. :: .•. : .• :: .... : .• :: .• : ... : ••• : •.. :.: ...•. : ..•.. : .•. : •. :.: •. : •. :.: •• :: .•. : •.. :.: •. : .• : ••. : ••..•. : ••.•.•.•. : •. : ••. :1:,
1ft.III·.·······.··.:. -400~~---4--~~~~+.+--~--4---~==~~~~+-~1 ~ j ..••••••••••••••••••••• : .. :; .... :~ .... ::.: ..... :(.: .. :~ ..... :~ .... ::.:: .. :.~:.,·:~.·, .. :~.:.:'r .. :.:~ .. ::·~:::~: .. :::~.::.:~ .. :::~.:;.:: .. :;::.:;.::,.·.:~.·.:i.:· .:.: •. :.:.: .. :.: ••.. :: ••... :: •.. :.: •.•.. : •.. : •.. ::.:.:: •• :.:.::.;.:.::.: •. : .. ~.:: •• ~.:.: .. ::.: •.. : •. : ... ::: .•• :.:.: .• : .. : .•. :.: •. :: ... :.... :.:: •. :::.,:~: •. ~.: •. ::: •. : .. : •. :;: •. ~:.: •. :~:.:~ .. : •. :::.::: •. :~:.:.,: •. :::.:~: •. ::: •. :~:.:.::: •. :~ ..• :~ ...•. :: .•. :~ .••. : •. : .. : •. : •. :~.:.::·.::.: •. : •. : .. l.:.· .. :.:: .• :~ ... ·.:.·:~: •.. :·:~ ...•. :.!,i 3 3Oo~--~--+---~1~~~I~j]4:.:~.~.~I.·~~~~·~~--~--~~~~Hr~~+s.~:--~
--II --
• ... -.. --.. .. .. ..
• ...
• •
• .. .. ..
• ...
• ... .. -• .. -o -JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
MONTH -
QUIGMY RIVER DAM SITE
AVERAGE MONTHLY FLOWS
FIGURE
Bl-2
..
•
•
• ---
----
-
-----
-
-
-
-,,1 -u -
EXCEEDANCE PROBABILITY
90 80 70 10 50 40 30 20 10 5 2 I 0.5 0.1
-----------------,--...,..,..--.,.---,--.--.-.----.-----,:~-~-----'I----.----.
~-----
! -j---:--:-----------;-----,---,. .. --~ --j" -.---
~--~'---------------~1-.~·~·~-+,~··--~~~-4~+-~~~~ -+-~~-+
f--~----+ --------t~----<~...,..:...j.;..:.;..-+-:--+-~~-+-~-+-'--+--'-+'--..;....~~----!..----+-
. • . . ..• : :j.
~~.-~~~~~-+~~-+-~~~,~
!5,OOO------------
~-.--.. -
t-t -~~-------~-. ---~---.:.~__:__~_+_~---l--:4_~,. ~--:--~~--,---:-~_+_~~_+
!
-W 2,000 ri -------_--;.--+-_ .......... _-+_+--+-_4 __ ~----+--i___+_-....._
(.!). . , . -. --a:: f '. j .. -
I ..·.1 -t ... ~ r----. -; -~---t--t--+---+l-.~ .. +--+--4
-u I . .! en I . !
i _
I o 1,000 ~. _________ ~-L ____ -L_~~~_~-L_~-L_~_-L ____ ~_~ ____ ~J-~_~
2 !5 10 20 50 100 1000
AVERAGE RETURN PERIOD IN YEARS
-----= -QUIGMY RIVER DAM SITE FIGURE
PEAK FLOW FREQUENCY CURVE m-3 -
'.'
l
/
~r,'
.~~
~>,
#
/
\., __ ~:t;?' \
'. ,~,
PROPOSED ACCESS ROAD
AND TRANSMISSION LINE
TOG I A K BAY
PROJECT PLAN
EXISTING ROAD AND
PROPOSED TRANSMISSION
0'----___ j------i. ___ ....,j3r-----;.4 ___ --1~ MILES
F':.71 SURFACE LANDS -INTERIM CONVEYANCE OR PATENT TO VILLAGE U CORPORATION
i l
SUB-SURFACE LANDS-INTERIM CONVEYED TO REGIONAL NATIONAL
CORPORATION
(INTERIM CONVEYANCE IS USED FOR THE CONVEYANCE OF UNSURVEYED
LANDS, PATENT WILL FOLLOW I. C, ONCE LAND IS IDENTIFIED BY
SURVEY)
, I VILLAGE CORPORATION SELECTION
1-,-----_ j
~ VILLAGE CORPORATION SELECTION AND INDIAN OR NATIVE ALLOTMENT ~ APPLICATION D INDIAN OR NATIVE ALLOTMENT APPLICATION
D UNENCUMBERED U,S, F AND W, S, LANDS
[J~ITY AND TRUSTEE LANDS
f~ LJ PRIVATE LANDS (GENERAL AREA)
o
TOGIAK HAS A FEDERAL TOWNSITE, U, S. S. 4905, WITH PATENT ISSUED
TO BLM TOWNSITE TRUSTEE. THE TRUSTEE HAS DEEDED OCCUPIED PARCELS
TO RESIDENTS AND SOME VACANT SUB-DIVIDED LOTS TO THE CITY
OTHER SUB-DIVIDED PROPERTY REMAINS WITH THE TRUSTEE, A PERMIT TO
CROSS TRUSTEE LAND MAY BE ISSUED BY THE U, S, DEPT OF INTERIOR,
BUREAU OF LAND MANAGEMENT AFTER A RESOLUTION BY THE CITY
COUNCIL,
STATE OF ALASKA
ALASKA POWER AUTHORITY
ANCHORAGE,ALASKA
TOGIAK HYDROELECTRIC PROJECT
DOWL ENGINEERS
ANCHORAGE, ALASKA
LAND STATUS MAP
TUDOII [_EERllle COlll'MY
SAN ~RANCISCO, CAU~OIIMA
FIGURE ril-5
-VI
10000
5000
3000
2000
1000
500
300
-200 (.) -ILl
c.!) a:: «
I
U en
c 100
178 180 182 184 186 188 190
TAILWATER SURFACE ELEVATION IN FEET (SITE DATUM)
QUIGMY RIVER DAM SITE
TAILWATER RATING CURVE
192
FIGURE
N-5
A. GENERAL
SECTION V
ALTERNATIVE SITES CONSIDERED
The original request for proposals for this project
specified a particular site on the Quigmy River, as recommended
by t he No rthern Techn ical Serv ices/Van Gu I ik and Assoc ia tes
report (1981) for detailed assessment. However, during the
initial phase of the work, the Alaska Power Authority also
requested that other alternative sites in the general vicinity
of Togiak be evaluated on a reconnaissance level to confirm,
prior to more detailed study, that the recommended Togiak site
was actually t he best si te to be further invest i gated. Th is
section summarizes the alternatives considered during this
phase of the work and presents the reasoning that led to the
conclusion that an alternative site, located 1.8 miles down-
stream of the originally recommended site, was, in fact, the
best available alternative for a hydroelectric power project.
B. ALTERNATIVE PROJECTS
Due to the area's topography, locating a physically and
economically viable hydroelectric power project in the vicinity
of Togiak presents some major drawbacks. Basically, while
there are moderate flows in many streams, the stream gradients
are so flat that adequate head may be developed only at great
expense with either a dam or a very long penstock. The geology
of the area does, however, prov id e some good dam si tes. A
total of 11 alternative projects, all in the hilly Quigmy and
Kurtluk River drainages 3 to 14 miles west of Togiak, were
considered prior to selecting the Quigmy River canyon site for
more detailed feasibility study. The locations of the sites
studied are shown in Figure V-I.
NBI-384-9521-V V-I
Four projects identified in previous studies were reconsid-
ered along wi tb seven new projects. Of tbe 11, seven were
subject to ground reconnaissance and two si tes were surveyed.
Table V-1 lists all sites studied and their characteristics.
Power output
developed in
estimates are based on the average annual flow
tbis study which corresponds to tbe 30 percent
flow duration or availability, and on gross bead less penstock
losses. Tbe values tberefore differ from installed capacities
suggested in prior reports.
C. DESCRIPTION AND EVALUATION OF ALTERNATIVES
Prior to proceeding with the field activities, extensive
map studies were made and all previous reports and
,.-
....
...
investigations were evaluated. ~
Final evaluation of the sites and the selection of the
Quigmy Site 3 was made by tbe field team while they were in
Togiak. Selection was based on information similar to the data
in Table V-1 and rough cost estimates. Primary consideration
was given to tbe ability of the project to meet Togiak's
projected power needs versus tbe relative complexity and cost
of the structures. Distance from town (at a potential cost of
$250,000 per mile), reliability of the water supply, and
environmental effects were major considerations. The following
discussion highlights tbat evaluation.
Site 1 on tbe Quigmy River was described in the Request for
Proposal for this feasibility study and was originally proposed
by Nortec/Van Gulik & Associates (1981) as a 60-foot-high by
1000-foot-Iong earth dam developing 55 feet of head and a
minimum of 300 kW. Tbe dam axis is located in a broad alluvial
valley with bedrock exposed only at tbe west abutment. A large
reservoir would extend more tban three miles upstream and
inundate marshlands wi tbin tbe Togiak National Wild life
Refuge. Wbile the dam would provide more than sufficient
NBI-384-9521-V V-2
..
...
storage and head to meet all of Togiak's future needs, it would
be a large structure requiring approximately 170,000 cubic
yards of fill. A large concrete-lined spillway and stilling
basin would be necessary on the left or right abutment.
Furthermore, suitable impervious material is not readily
available and major geotechnical foundation investigations
would be required. Compared to Sites 2 and 3 located less than
two miles downstream, Site 1 would be excessively expensive.
Site 2, located in a moderately narrow rock canyon
approximately one mile downstream of Site 1, is attractive
because it provides two natural spillways. However, as an
embankment dam in this area would probably be constructed of
quarry rock rather than earth, the quarry could be located so
as to provide the spillway at little additional cost.
Site 3 is located approximately 0.8 mile farther downstream
(about 1. 8 mi les below Site 1). It was selected as the most
promising site for more detailed feasibility study. The
narrow, deep canyon, cut entirely in the bedrock that forms the
site, would minimize dam volume and permit flexibility of
design. Either a concrete gravity dam or an embankment of rock
or earth could be const ructed. Power heads of up to 55 feet
could be achieved.
storage capacity
While the site does not provide the power
of Site 1, neither would it have the
environmental impact
storage is also not
of inundating a large marsh area. Its
requi red to meet most of Tog iak' s future
power requirements. A reservoir that provides 30 feet of power
head would extend up the canyon approximately one mile, and it
would be contained within the Togiak corporate limits.
Embankment volume for a concrete-faced rockfill dam would be
only about seven percent of that required for an earth dam at
Si te 1. Unlimited amounts of quarry rock are available from
the abutments where the spillway would be excavated and
adequate foundation conditions for either a rockfill or
concrete dam are evident. The primary disadvantage of the
NBI-384-9521-V V-3
site, which it shares with all other Quigmy River sites, is the
long access road and transmission line to Togiak. This cost
could exceed 30 percent of the total investment.
Si te 4 is located four mi les downstream of Site 3 in a
similar canyon near Togiak Bay. The site was considered in
order to reduce access road costs by utilizing a sea route and
dock near the river mouth. After initial consideration, the
site was discarded on the environmental grounds of reported
large salmon spawns in this lower reach of the Quigmy.
Si te 5, considered by R. W. Beck (1981), is located five
miles north of Site 3. The site was too remote and too small
to be further considered.
Sites 6 and 7 are located in the uppermost reaches of the
Quigmy basin to the north of the village. They provide very
attractive amounts of head by means of diverting Quigmy basin
water over the low divide into the Togiak River drainage. They
were eliminated on the basis of their excessively long
penstocks, less reliable water supply, and remoteness.
Si te 8 located on the Kurt I uk River, four mi les west of
Togiak, is the original site considered in a 1979 Alaska Power
Administration report. Further investigation ind ica ted that
ei ther a large dam or a penstock much longer than 3500 feet
would be required to develop the 50 feet of head indicated in
the report. The site was dropped in favor of Site 11.
Site 9, located on a tributary one mile upstream of Site 8,
is too small for pr imary consideration, but in the future it
may prove to be an economical supplement to the power
developments proposed here.
Sites 10 and 11 utilize essentially the same dam. Site 10
is a trans-basin diversion similar to sites 6 and 7. Water
NBI-384-9521-V V-4
...
...
... ,
must be conveyed 4000 feet across a saddle before dropping to a
powerhouse located on a large pond in the flats west of
Togiak. A good road now extends from the village to the gravel
pit and the proposed site of a new airport is located approxi-
rna tely 7000 feet east of the power plant site. Si te 10 was
f inally eliminated on the basis of penstock and dam require-
ments and the potential environmental impact of delivering 21
cfs into a small ephemeral drainage.
Site 11, while supplying only a fraction of the power
demand, is considered the best alternative to the selected
Quigmy site. Head would be developed both from a dam to be
located in a narrow canyon mouth and from the stream gradient
through the short canyon. A detailed ground survey was made of
the site. The site is obviously attractive due to its
proximity to Togiak but its small size (85 kW) would allow it
to supply only a fraction of the anticipated energy demands at
Togiak.
NBI-384-9521-V V-5
TABLE V-1
ALTERNATIVE PROJECTS
Drainage Avg.
Area Flow Head
No. Stream (sg. mi) (cfs) (it)
1 Quigmy, middle.!/ 88 195 50
2 Quigmy, middle 89 195 30
3 Quigmy, middle 100 220 30
4 Quigmy, lower 124 250 50
5 Quigmy, t rib.~/ 8.1 18 50
6 Quigmy, upper~ 7.9 20 300
7 Quigrny, upper~/ 3.8 10 350
8 Kurtluk, lower±/ 22 35 50
9 Kurtluk, trib.2 /3 / 4.9 7 50
10 Kurtluk, upper 13.1 21 145
11 Kurtluk, upper 13.1 21 62
1/ Nortec/Van Gulik & Associates (1981).
2/ R. W. Beck (1981).
TOGIAK AREA
Penstock Dam
Length Height
(ft) (ft)
200 60
200 40
100 42
200 70
2,000 10
14,000 10
14,000 10
3,500+ 10
200 10
9,000 45
500 55
Length
(it)
1,000
145
100
100
80
80
3/ Indicated dam height is from the diversion weir to the penstock.
4/ Alaska Power Administration (1978).
NBI-384-9521-V-1
Trans-
mission
Line Power
(mi) (kW) Remarks
11. 5 650 Proposed, RFP
12.0 385
12.5 440 Selected
13.5 820
13 48
10 300
10.5 150
4 75
5 23
2.8 140
4.4 85 Alternate
~/'" -, --864 _,--. .
I~
!
'/
. 1 'f -
]0
.; 38 Roc~y Pt'V' '. St. .. " I
~!
(C7 /
./' '17S I
TOGIAK
,.'T 0 G YAK
'5
ALTERNATIVE PROJECTS
BAY
(J ;:) l,
! C
\,' NUJUlt'achB.k
Lake l"~:: (-
,-~j
-,
FIGURE
:2:-1
SECTION VI
ALTERNATIVE HYDROELECTRIC PROJECTS
A. GENERAL
Hydroelectric power plants transform the energy of falling
water (head) into electrical energy. In general, a hydro-
electric power project consists of a dam to produce the head or
to divert stream flows; an intake and conduit to convey the
water to the hydraulic turbine; the turbine itself, which is
coupled to a generator to produce electrical energy; accessory
electrical equipment; and a transmission system to transmit the
energy to a distribution system or user.
This section describes these features as they are specifi-
cally adapted to the alternatives studied for the Togiak
Hydroelectric Project. The conceptual design considerations
leading to the alternative designs investigated are also
covered. Included is the rationale and methodologies used in
selecting the type of turbines and generators, the sizes and
number of units, and the configurations of the dams and power
plants. The power and energy production for the al ternative
projects and project operation and maintenance procedures are
also discussed.
B. CONCEPTUAL DESIGN CONSIDERATIONS
In assessing the overall feasibility of hydropower at the
selected site on the Quigmy River, several different alterna-
tive configurations were studied. At this reconnaissance level
of investigation the intent was to assess overall feasibility
rather than attempting to optimize the project features. It
was felt that if feasibility could be shown for one or more
specific configurations then a "feasibili ty envelope" would
SFNBI-425-9521-VI VI-l
have been established and the actual optimization of the
various project features woul d be accomplished in the next
stage of project development--a definitive project report.
In choosing the alternative configurations to be studied,
various considerations regarding the conceptual designs
utilized were necessary. Those concerned the type of dam to be
constructed, the method of project operation, the type of
turbine to be utilized, the design flow, the installed capacity
of the turbine-generator, and the height of the dam.
1. Type of Dam
The si te selected for detailed investigation is a narrow
canyon wi th competent rock on the bottom and all sides. The
canyon is approximately 150 feet wide wi th the Quigmy Ri ver
confined to a 20-foot-wide channel at all except flood flows.
A relatively flat rocky bench approximately 30 feet wide exists
on the left side of the canyon through the project site.
Photographs of the various site features are included as
Exhibits VI-I, VI-2 and VI-3 and a cross section of the site is
shown in Figure 3 of Appendix C.
The site would be suitable for either a concrete or rock-
fill dam and approximately 55 feet of hydraulic head coul d be
physically developed. Since both dam types were apparently
technically feasible, the type of dam to be used was basically
an economic decision. Since a preliminary design and detailed
cost analysis would be necessary to determine the final project
costs, both types were investigated at this preliminary stage.
A concrete ogee dam at the site would have a central
unga ted ogee spi 11 way wi th hi gher gravi ty sect ions on both
sides. The geology and geotechnical investigations (see
Appendix C) indicate that surface gravel deposits exist in the
SFNBI-425-9521-VI VI-2
,..
... '
area to supply the necessary aggregate for the concrete for
both the dam and powerhouse.
A rockfill dam is the most suitable type of fill dam for
the site because no other suitable fill material exists in the
area for the main embankment. Also, since no suitable imper-
vious material is present, a design utilizing an impervious
core is not practical. An upstream waterproof membrane of
either concrete or asphalt was therefore deemed the most suit-
able for the site. Since a great deal more experience exists
with concrete membranes than asphalt and since the cost would
be approximately the same, the concrete membrane was considered
to be the most practical choice.
2. Method of Project and Reservoir Operation
The project would be a run-of-the-river type of operation
wi th the dam described in the previous section serving to
divert the project flows and to furnish the necessary hydraulic
head. Al though a small reservoi r woul d be formed behind the
dam, no active reservoir storage would be utilized. The
surface area of the reservoir would be approximately 40 acres
for a dam with 20 feet of hydraulic head and 90 acres for a dam
with 30 feet of hydraulic head.
3. Type of Turbine
The turbine most suitable for the site is a tubular pro-
peller turbine. The rationale for this selection from the
various types of commercially available turbines is explained
in the following sUbsection F. This particular type of turbine
is suitable for hydraulic heads between 10 and 60 feet and it
has reasonable efficiency over a range of flows of approxi-
mately 105 percent to 30 percent of design flow.
SFNBI-425-9521-VI VI-3
4. Design Flow
No flow records were available for the Quigmy Ri ver si te
and the hydrology data developed for the site was based on
gages and information from other areas. The confidence in this
unverified information is therefore not high at this time. A
gage established near the site as part of this study will allow
a good check on the hydrology data generated for this study as
the actual on-site information becomes available.
The generated data (see Appendix B) indicated that the
average annual flow is 220 cubic feet per second. It was
thought best to be conservative in the design flow to be
utilized for the study and therefore to stay slightly below the
average flow at 200 cfs. This flow corresponds to about the 38
percent exceedance value on the flow duration curve. Since the
tubular turbine can generate efficiently down to about 30
percent of design flow, or 60 cfs, this allows the lower
monthly flows occurring in January, February,. and March to be
fully utilized. Once the gaged flow data are available for the
Quigmy River, the average annual flow estimate
concei vably be revised upward to as much as 300 cfs.
could
This
woul d permi t a 10-foot reduction in the height of the dam
without reducing the power production estimated on the basis of
a conservative 200 cfs design flow.
5. Installed Capacity
In analyzing the power and energy demands of Togiak (see
Table VI 1-3), it is apparen t that the installed capacity of a
hydroelectric project suitable for this village would most
likely range between 200 kW and 600 kW. The 200 kW value would
be slightly less than the current demand and 600 kW would be
sufficient to meet the projected 2002 demand. However, the
lower capacity would be almost immediately insufficient and the
higher capacity would be underutilized over virtually the
SFNBI-425-9521-VI VI-4
entire life of the project. The optimal capacity was therefore
indicated to be 300 kW to 400 kW.
The actual formula for calculating the power or the
installed capacity (P) of a hydroelectric plant is:
P
where
= Q He
11.8
P = Power in kilowatts
Q = Design flow in cfs
H = Hydraulic head in feet
e = Turbine-generator efficiency
(about 0.85 over the range of projected
flows)
As can be seen, (P) is directly proportional to the design
flow (Q) and the hydraulic head (H), which is the difference
between the water levels upstream and downstream of the dam.
Wi th the design flow (Q) of 200 cfs and the approximate
installed capacity (P) of 300 kW to 400 kW already determined,
the required hydraulic head (H) can be calculated. For 300 kW
the H would be 19.2 feet and for 400 kW H would be 27.8 feet.
Rounding these H values to 20 feet and 30 feet yields installed
capaci ties of 288 kW and 432 kW respect i vel y. These were
therefore chosen as the design values of the hydraulic heads
(H) and the installed capac i ties (P) to be further
investigated.
6. Fish Ladder
Although it has been tentatively determined that the Quigmy
River above the proposed dam site is not a major salmon spawn-
ing I oca t ion, a I imi ted run does occur. Any dam across the
Quigmy would likely require a fish ladder. Therefore a pre-
liminary design of such facilities has been incorporated into
all the alternatives.
SFNBI-425-9521-VI VI-5
7. Spillway Flood
As has previously been covered in Section IV, Basic Data,
and Appendix B, Hydrology, the design flood for all alterna-
tives is 11,000 cfs. Tbis value corresponds to a flood with a
500-year return interval.
C. DESCRIPTION OF ALTERNATIVE PROJECTS
With the above design considerations in mind, three
alternative hydroelectric projects were formulated. Two were
concrete dams with hydraulic heads of 30 feet and 20 feet and
installed capacities of 432 kW and 288 kW respectively. The
third was a rockfill dam with 30 feet of hydraulic head and 432
kW of installed capacity. Tbe operating range of the turbine
for each alternative is shown in Figure VI-2.
The rockfill dam would require a spillway to be excavated
from the rock on the right abutment. The excavated material
from the spillway would be sufficient to construct a dam
developing 30 feet of hydraulic head. A rockfill dam with 20
feet of hydraulic head was therefore not investigated since the
same sized spillway would be required with the same resultant
amount of excavated material and excavation cost regardless of
the dam height. If the material were not used to construct the
dam, it would be wasted.
A more detailed description of the three alternative
projects follows.
1. Alternative A--38-Foot Concrete Dam
Al terna t i ve A woul d be a concrete dam wi th 30 feet of
hydraulic head and 432 kW of installed capacity.
tual layout for this alternative is shown in
Appendix A.
SFNBI-425-9521-VI VI-6
The concep-
Plate I in
.'
...
-
j'->-
...
As shown, the dam utilizes a ~ravity ogee center spillway
section 38 feet high with gravity wingwalls 16 feet higher on
either side. The powerhouse is placed above the river flows on
the rock bench on the left abutment. The powerhouse woul d be
about 35 feet by 15 feet and would utilize concrete walls
extending above the expected flood level. A fabricated metal
structure would be utilized above this elevation.
The flows woul d be conveyed to a tubular turbine wi th a
1500-mm-diameter runner through a 60-in-diameter conduit with a
trashrack and upstream isolation gate. A gate hoist would be
provided on the left abutment to raise and lower the gate.
The swi tchyard woul d be placed out of the canyon on the
bluff above the powerhouse and left abutment. The access road
woul d be placed in a sidehill cut in the left side of the
canyon. A parking area would be provided adjacent to the
powerhouse. A step-type fish ladder would be placed on the
left abutment and would pass between the parking area and the
rocky bluff.
2. Alternative B--28-Foot Concrete Dam
Alternative
hydraulic head
ceptual 1 ayout
Appendix A.
B would be a concrete dam wi th 20 feet of
and 288 kW of installed capaci ty. The con-
for this alternative is shown in Plate II in
All features of Alternative B are essentially the same as
for Alternative A except that the dam height of the gravity
center ogee spillway is 28 feet instead of 38 feet. Again, the
gravity wingwalls on either side of the center ogee section are
16 feet higher than the ogee section.
SFNBI-425-9521-VI VI-7
The powerhouse would also be the same size since the same
sized tubular turbine with a 1500-mm runner diameter would be
utilized. The generator, however, would be 320 Kva instead of
480 Kva as in the case of Alternative A.
3. Alternative C--52-Foot Rockfill Dam
Alternative C would be a concrete-faced rockfill dam with
30 feet of hydraulic head and 432 kW of installed capaci ty.
The conceptual layout for this al ternative is shown in Plate
III in Appendix A.
As shown, the maximum section would be 52 feet high wi th
1.0 vertical to 1.4 horizontal sideslopes and a one-foot-thick
concrete membrane on the upstream face.
A spillway would be excavated through the right abutment to
accommodate the 11,000 cfs spillway design flood. The spillway
would require a 10-foot surcharge to pass the desi~n flow. The
surcharge height and a residual four feet of freeboard are the
reasons that the rockfill dam is 14 feet higher than the 38-
foot-high concrete dam of Alternative A to develop the same 30
feet of net hydraulic head.
The powerhouse would be located on the left side of this
canyon, the same as for Alternatives A and B. It woul d be the
same size exactly as in Alternative A, but it would be located
about 30 feet farther downstream. The fish ladder, access
road, and switchyard would also be located on the left abutment
in the same general location as on Alternatives A and B.
Since damage to the upstream concrete membrane could
potentially occur over the 50-year project life, a lOW-level
dewatering outlet has been provided for this alternative
through the maximum section at the lowest elevation of the dam.
SFNBI-425-9521-VI VI-8
...
...
...
,..'
...
tw,
...
... '
Ii""~
D. ACCESS ROAD
At present a road extends for about 0.8 mile southwest of
Togiak along the bench. For access to the proposed dam
I oca t ion, an 11. 6-mi Ie road 12 feet wide woul d be necessary
from the end of the exist i ng road (mi leO. 0) to the Quigmy
River site (mile 11.6). The first seven miles of the road
would be on fairly flat to undulating terrain over glacial till
materials. Hauling gravel for fill would be necessary. The
remaining 4.6 miles woul d be on nearly level terrain over
gravel materials and a minimum of cutting and filling would be
required. Typical cross sections of the proposed access road
are shown in Figures 6 and 7 of Appendix C.
A large potential gravel borrow area at mile 7.0 along the
access road has been located as part of the materials explora-
tion program conducted for this study (see Appendix C, Geology
and Geotechnics). As a closely related matter, it was found
during the course of this study that the Alaska State
Department of Transportation and Public Facilities, Division of
Aviation, was investigating the possible construction of a new
airport at Togiak and that this agency was looking for gravel
sources to pave the runway. The material exploration informa-
tion collected for the geotechnical report was then furnished
to the Division of Aviation and a joint visit was made to the
potential borrow si te by DOWL and Di vision of Aviation per-
sonnel. As a result of these activities, the Division of
Aviation is studying the possibility of constructing a road to
the borrow si te. If th is occurs, the hydroelectr ic pro.iect
would require only the construction of the remaining 4.6 miles
of access road. This is a very important consideration for the
project since the first seven miles of road will cost approxi-
mately $1,000,000 and the entire remaining 4.6 miles will cost
approximately $600,000.
SFNBI-425-9521-VI VI-9
E. TRANSMISSION LINE
A 12.5 kV transmission line would be constructed adjacent
to the access road. It woul d extend 13.6 mi les f rom the
switchyard at the powerhouse to the existing diesel generating
plant in Togiak. The configuration would be single pole and
cross arm with three wires and poles on almost 500-foot
centers. The general configuration of the line structures is
presented as Plate VI in Appendix A.
F. SELECTION OF TURBINE-GENERATOR
It was previously mentioned in sUbsection B, Conceptual
Design Considerations, that a tubular turbine was deemed best
for the proposed hydraulic project. This portion of the report
details the reasoning leading to that conclusion.
1. Type of Turbine
Conventional turbine equipment that is commercially
available is classified either as impulse or reaction turbines.
An impulse turbine is one having one or more free jets
discharging into an aerated space and impinging on the buckets
of the runner. The jet size increases as the head on the
turbine decreases. For low-head applications, the cost of the
impulse turbines is generally not competitive with the reaction
type. The impulse turbines can, however, be operated
economically on heads as low as 150 feet.
A reaction turbine is one which passes water under pressure
over the fixed angular vanes of the runner, imparting rotation
and torque to the generator shaft. The conf igura tion of a
reaction turbine consists of a water case, a mechanism for
controlling the quantity of water and distributing it equally
over the runner intake, and a draft tube.
SFNBI-425-9521-VI VI-10
.. '
...
...
..
..
-
There are two principal types of reaction turbines:
Francis turbines and propeller turbines. The propeller tur-
b i nes may have either fixed or ad justable bl ades and several
different configurations of propeller turbines are commercially
available.
A Francis turbine is one having a runner wi th a large
number of fixed blades attached to a crown (top) and a band
(bottom). The dimensional configuration of the runner is
designed to suit the head conditions of the application.
Designs are commercially available to suit head conditions
ranging from 15 to 1500 feet. In general the Francis turbine
is not competi tive with the propeller type below a head of
about 60 feet. The head range of this study is such that
Francis turbines have been eliminated as an economic selection.
A propeller turbine is one having a runner resembling a
propeller with a small number of blades, usually four, five or
six, to which water is supplied in an axial direction. The
blades are attached to the hub of the runner. The blade angle
is adjusted to suit the head and flow conditions of the
application. Runners are available in ei ther fixed-blade or
adjustable-blade designs. The suitable head range of propeller
turbines is from 15 to 110 feet and they are reasonably
efficient over a range of flows of 105 percent to 30 percent of
desi gn flow. Th is is graphically ill ustra ted in Fi gure VI-2
included at the end of this section. This type of turbine is
therefore economically suitable for this study.
Propeller turbines are available for vertical, slant or
hor izontal mount i ng. The vert ically mounted conf igura t ion is
known simply as a conventional propeller turbine. The hori-
zontally mounted and slant-mounted units have been given trade
names that describe the mechanical designs such as tubular,
SFNBI-425-9521-VI VI-ll
bulb and Straflo. These various types have certain differences
both in performance, cost and civil construction costs.
The tubular turbine consists of a propeller-type runner
mounted in a circular water passage. Downstream of the runner,
the turbine shaft passes through the wall of the draft tube at
a shallow elbow and is connected to the generator. The turbine
d rives the genera tor through a gearbox, by means of a long
downstream shaft. The generator is thus located outside the
water passages so that sealing arrangements are simple.
Several manufacturers currently manufacture standardized
designs for tubular turbines, wi th resul tant savings in cost
and fabrication time.
For a bul b turbine conf igura t ion, the water passage and
turbi ne runner are simi lar to those of the tubular turbine.
However, the bulb turbine differs from the tubular turbine in
that the generator is integrally housed in a bulb within the
turbine passageway. The generator is thus si tuated in the
immersed upstream cone and is driven directly by a shaft from
the turbine runner. The operating characteristics and turbine
efficiency of the bulb turbine are similar to the tubular
turbine. The powerhouse of the bulb turbine offers a smaller
plant area but a larger depth than the tubular turbine. The
bulb turbine is less accessible for maintenance than the
tubular turbine. Down time for major repair would probably be
greater.
The Straflow type of turbine is the development of Sulzer
Brothers Lt d. of Swi tzerland. The turbine character ist ics are
similar to those of the bulb turbine discussed above. The
mechanical arrangement differs in that the rotor of the
generator is attached to the rim of the runner. The rim of the
runner has a seal that uses filtered water at a higher pressure
than the effective head of the turbine. The generator operates
in air outside of the passageway. The design has been
SFNBI-425-9521-VI VI-12
..
""
..
..
.....
...
successfully operated in Europe and would appear to offer cost
benefits for certain sized units. To date, no units of the
size contemplated for this development have been installed in
the United States.
With the above cons idera t ions in mi nd, a tubul ar turbine
was selected as best suited to the Quigmy River site.
2. Selection of Number of Units
Every turbi ne is most eff icien t wi th in a range of flows,
with decreasing efficiency occurring beyond this range.
Consequent ly, more power can usually be generated if two or
more small turbines are selected rather than one large unit.
For example, two turbines, each rated at 50 pecent of design
flow, wi 11 produce more energy over the flow range than one
turbine rated at 100 percent of design flow. However, the two
turbines will generally cost 30 percent to 70 percent more than
the single turbine. The extra value of the energy produced by
the two uni ts must therefore make up for the extra cost of
using two units.
In the case of the Quigmy River site for the Togiak
Hydroelectric Project, the efficiency of the recommended
tubular turbine unit is adequate to cover the anticipated range
of flows; the relatively small extra energy that would result
from the use of two units would not justify the extra
expense. A single unit was therefore indicated.
3. Type of Generator
Generators can be of the synchronous or induction type.
Induction generators are often considered more practical for
the smaller turbine-generator installations because they cost
less and require less maintenance. They require no excitation
and need only a squirrel-cage rotor that uses no wire windings
SFNBI-425-9521-VI VI-13
or brushes. Furthermore, they do not run at exact synchronous
speed and complex equipment is not needed to bring them on
line. They cannot be used to establish frequency, however, and
must be connected to a system with synchronous generators
because they take their exci tation from system current. The
generators produce electric energy with a high degree of
efficiency.
Synchronous generators are usually three-phase star or Y-
connected machines with one end of each winding connected
together in common and the other ends used as line terminals.
The al terna ti ng-curren t synchronous generator, or al terna tor,
delivers its induced alternating current directly to the
external circuit. It is used where transmission is to be sent
over long lines. The alternating current can be transformed to
the desired transmission voltage.
For this development, the synchronous generator is used
because it is necessary to establish frequency.
G. PROJECT ENERGY PRODUCTION
Alternatives A and C each have 432 kW of installed capacity
and the average annual energy generated woul d be 2,660,200
kWh. Al terna t i ve B has 288 kW
average annual energy generated
monthly power and energy values
of installed capacity and the
would be 1,773,400 kWh. The
for both the 432 kW and 288 kW
installations are presented in Tables VI-1 and VI-2
respectively and are shown graphically in Figure VI-1.
These values were derived using the Quigmy River flow dura-
tion curve rather than the average monthly hydrograph since the
data used in deriving the flow duration curve were daily values
rather than monthly averages as shown on the hydrograph.
However, the hydrograph values have been used to compute the
available peak power generation that could be expected per
SFNBI-425-9521-VI VI-14
..
...
"',
...
,..
-
II!'
month. Where the hydrograph values exceeded the maximum
turbine design flow, the turbine flow was used for the calcula-
tion. The "available peak power" values were then used on a
monthly percentage basis to distribute the average annual
energy values to monthly energy values. The monthly hydro-
electric energy values from Tables VI-l and VI-2 were used in
Section VII, Project Energy Planning, to meet the projected
present and future energy demands of Togiak.
The plant factor, the ratio of energy that could be pro-
duced by a turbine-generator if continuously operated at its
rating to the annual energy actually produced, is 70.3 percent
for all alternatives studied for the Togiak Hydroelectric
Project.
H. PROJECT OPERATION SCHEME AND CONTROLS
Turbine-Generator
Controls for the turbine-generator unit will load the unit
in response to the connected system demand. A governor wi 11
control the adjustable blade angles of the propeller turbine
and thus match the turbine-generator electrical output with the
connected system load. A small increase or decrease in the
system load will cause the governor to modify the blade angles
and the flow through the turbine will thus change. As long as
the connected load does not exceed the capacity of the turbine-
generator, the electrical frequency can be held wi thin
approximately plus or minus one-tenth of a cycle.
The turbine-generator is being operated on an isolated
system; that is, it is not electrically connected into a grid
wi th other operating genera ti ng uni ts. Any overload in the
unit will gradually decrease the unit's speed and result in a
corresponding lowering of both line voltage and frequency.
Minor overloading, probably up to about ten percent, can be
SFNBI-425-952l-VI VI-l5
tolerated. But an excessive overload can, if continued, cause
protective devices to trip the unit.
It is feasible to have the hydraulic turbine-generator unit
operate in parallel with the diesel generating units now being
used on the Togiak's electrical system. The hydraulic turbine
can be operated to serve as a base load unit and regulate the
system frequency. By proper setting of the diesel unit
governors, the diesel uni ts can be brought on 1 ine and be
operated during unusual system demands. The cost of this
integrated system was included in the economic analysis.
The turbine-generator will be manually started. A manual
start implies that operating personnel are present during
startup. The operating personnel shoul d physical 1 y check the
uni t. This check will include opening the turbine shut-off
valve (if closed) and checking that all supporting systems are
operable. Operating personnel will then actuate a single
control switch and the turbine-generator will automatically
start up. When the uni t reaches synchronous speed, it wi 11
automatically go on line. The provision of enough sophisti-
cated equipment and controls to allow the unit to be started up
from a remote location is not proposed.
Protective devices on the equipment will be capable of
shut ti ng the generating uni t down automat ically, wh ich would
require a manual startup. The automatic protective devices on
the equipment will sense the internal temperature of the
generator, most bearing temperatures, and critical oil
1 evel s. Hi gh temperatures and low 0 i1 levels can trip the
turbine-generator off the line. An alarm will be given before
any control device shuts down the generating unit.
maintenance will be performed on a weekly Routine
schedule. The power generated by the turbine-generator need
not be reduced during this maintenance period. The maintenance
SFNBI-425-9521-VI VI-16
...
...
...
....
-
will include routine checks to verify that (1) all equipment is
operating in a normal condition, (2) none of the equipment is
bei ng operated at a temperature above normal I imi ts, (3) all
lubrication requirements are being met, and (4) no discontin-
uity exists in electrical wiring, relays, or controls.
Overhaul maintenance will be performed on an annual basis
and it will be scheduled during the minimum average river flow,
usually in March. The turbine-generator will have to be
removed from the line and electrical power required by the city
system will be provided by the existing diesel generating
units. This annual maintenance period will not normally exceed
one week. This type of maintenance will include the following
items:
1. Areas of wear on the turbine-generator uni t will be
reviewed and corrective measures will be initiated in
cases where wear beyond the allowable limits set by
the manufacturer has occurred.
2. Electrical insulation checks will be made.
3. Relubrication will be required under the manu-
facturer's recommendations.
4. Verification will be made that all relays and controls
are properly set.
SFNBI-425-9521-VI VI-17
Month
Jan
Feb
Mar
Apr
May
June
July
Aug
Sept
Oct
Nov
Dec
TABLE VI-1
AVERAGE MONTHLY PEAK POWER
OUTPUT AND ENERGY GENERATION -432 kW UNITl/
TOGIAK
Flow
Utilized
for Available
Average Energy Peak Monthly
Flow Generation Power Energy
(cfs) (cfs) (kW) (1000 kWh)
99.0 99.0 215 125
72.0 72.0 156 93
126.0 126.0 243 158
281.0 200.0 432 261
238.0 200.0 432 261
208.0 200.0 432 261
203.0 200.0 432 261
219.0 200.0 432 261
264.0 200.0 432 261
458.0 200.0 432 261
309.0 200.0 432 261
153.0 153.0 330 196
Total 2,660
1/ Net hydraulic head = 30 feet.
NBI-425-9521-VI-1
Percent
of
Total
Annual
Energy
4.7
3.5
6.0
9.8
9.8
9.8
9.8
9.8
9.8
9.8
9.8
7.4
100.0
Month
Jan
Feb
Mar
Apr
May
June
July
Aug
Sept
Oct
Nov
Dec
TABLE VI-2
AVERAGE MONTHLY PEAK POWER
OUTPUT AND ENERGY GENERATION -288 kW UNIT~/
TOGIAK
Flow
Utilized
for Available
Average Energy Peak Monthly
Flow Generation Power Energy
(cfs) (cfs) (kW) (1000 kWh)
99.0 99.0 143 83.3
72.0 72.0 104 61. 1
126.0 126.0 182 106.4
281.0 200.0 288 173.8
238.0 200.0 288 173.8
208.0 200.0 288 173.8
203.0 200.0 288 173.8
219.0 200.0 288 173.8
264.0 200.0 288 173.8
458.0 200.0 288 173.8
309.0 200.0 288 173.8
153.0 153.0 220 131.2
Total 1,773.4
l/ Net hydraulic head = 20 feet.
NBI-425-9521-VI-2
-
Percen t
of
Total
Annual
Energy .. '
.'
4.7
3.5
6.0
9.8 -9.8
9.8
9.8 fill
9.8
9.8
9.8
9.8
7.4
100.0 ...
...
....
-o o o
-
300 r-~-·r---· ,. _."'._,,-._._~~ ....... _, .. , ~ .. ~---... ,.-,----.. .,-.... _-..... __ ._ ..... _-_._ ... _-•.. __ ..... , "-'-.'
I r---' .... -,,, "-.----.-~~-.--~-" .. ---.... ,-~.-'-' "" _·'"""' ... ~_~c'" -.¥-;. .~-----, ~-."'" -_ .. -I ._0--,,"8'~""'"'''' .".~ ..,'.h_~.'_ . .," __ ~·." ... · ~-"-.-,~,."~~,,
,
~.-.-...'~ ..... ~ ____ ~_ ............... _~.~_. -~'_. ______ "_,.~.~>_.'".. __ .. ____ .., .. __ .. _ ~ __ . ___ ~ __ ~,._.,_ .. __ ........ _ ... " .... -__ .~_ .. _. ___ --r-._ .. ,. ______ L-.4
i i
: L_ ,,_~ __ . __ ._~ ___ ~~ ___ .. __ 'A"~·".~ ___ ·' ___ .. _. • •• _,_ .. " '~.'_ . •. ~.,__ .. _ .••• _", .. , .~._~.
i .. --~~----------------------..
r·"-·---~~--'---,,~. ~"-~--~'-'~
i
100·······
., ........ _... AVERAGE ANNUAL ENERGY' ... _ ... -
2,660,200 leW h, 432 kW
---". __ . lNSTALLEO 'CAPACITY
ALTERNATIVES A AND C
-.--~ .... '.'.-.-.-~-~~~ ... -.'.-.~-" .-.. -. -" .. '" ~~
~ .. ~~_ '''. ___ w···A ._ ••• '" .-'-''''.~'''-
-, ..... .. 1_ ....... ,_,_. ___ .~.
~ ...... L.J
r---"~.-."""" ... -'" ....... ----~ .. -.-.. -.---,-~~-.... -." .. ~ . .,. •.... ~~~ .",", ~.--.--,-----'.--:,,-.-.. ~ ..
I
MONTH
ENERGY
_II e • .,
--
WE! M
400
300
200
r'"-'-'-''' .. ~.-.. -.... -..... --.. --~-.. ~.~----. __ ........ __ .... o_"_;~~~. __ ~ -HI 1
t--.... v--.~-~ .. -~ ... --.. -.. -___ ."0_, __ ",,, ~ . < ~ ~ ; ... _ ........ __ ._.-.--_ ... v .. _·_·_· .. _-· .. _ .. ·i .. ·---.. _. i i t
~~~ ___ .~ ___ s "'_.~~"_.........-....,_ ..•. _ ~_ ..... ~. •• _. ,_._ . .--:...-____ . ___ ........... __ ~-~-.• __ .• _.-__ ,_.---.. -.• __ ~._, _____ ""~_~_-+~ ___ ___;
I
I
I
J
! ..-... ~. -·"·TNSTALLED·-.. ·-········-.. -·~------"-~"_" __ " ... ,,_<:APACITY 432 ~ ... ____ .... _ ..... _.. __ ~
I --I
___ --MONTHly
......... _ ... PEAK .GENERATION
.-'1
1
i
... ---.-----.... ".--~---.~ -... --... -,,-~-~
[
_ .. -.~--.--~----.~-----.----"'~--~
(
I !"'""-__ ~~_.".-.. ~". __ ._.'~.~ .. _ e.' ___ ._ .~ __ .~. ___ ~ ....... ___ ..•• , •. ___ . _¥.~ ___ .w· __ -.·_·· -"_' , __ "'_0 o_ ... ~.-... -.~._" __ ---",. ____ ._.C"~ __ ~~ ....... -----'1
i , o i,...... ... """'"-_ ... ___ ..,--. . ......,io;,........,_...,..._.....-...-__ ._.~~ __ . ____ J .. _ ... : ... ''"'"'''""''' ...... ,,_~'"''. __ .... ___...,, __ ~ __ • __ ...... ~ __ ...... _. _ ... _.J
J F M A M J J A SON 0
MONTH
POWER
TOGIAK HYDROELECTRIC PROJECT
MONTHLY HYDROELECTRIC ENERGY AND POWER GENERATION
FIGURE
E-I
1100 f+---+---+---+---+----+---+---I---+---i-----~
1000 ~~--~---4---+---+--~--~--~--~---
900 H---+---+---+---+----+---+--+--+---~--
800
• 700 I~~~--~~--~--~--~--~--~--__ ----
~
(,) -
~ 600 1-4~-_+---~--~-~-+--~-~--~-o
..J
LL
500 i--~--~~~--~--~--~------~-------
400
200
TURBINE FLOW (38% EXCEEDANCE)
I
10 20 30 40 50 60 70 80 90 100
PERCENT (%) OF TIME FLOW EXCE.EDED
kW·h
6MAY INCREASE TO 300cfs WITH A CORRESPONDING 10ft REDUCTION
IN THE HEIGHT OF THE DAM ONCE GAGE.D FLOW DATA ARE AVAILABLE
.. ----------------------------------------------------------------
OPERATING RANGE OF TURBINE FIGURE
ID.-2
TOGIAK'S QUIGMY RIVER DAM SITE; AIR PHOTO LOOKING UPSTREAM.
THE DAM AXIS IS ACROSS THE NARROW CHANNEL IN CENTER OF THE
PHOTO.
-
EXHIBIT VI-1
I
I
I
DAM SITE FROM STREAM LEVEL, LOOKING UPSTREAM.
POWERHOUSE TO BE LOCATED ON ROCK LEDGE IN RIGHT CENTER.
RIGHT ABUTMENT. FLAG AT LEVEL OF 30-FOOT HEAD.
EXHIBIT VI-2
-
LEFT ABUTMENT. PENSTOCK AND POWERHOUSE TO BE CONSTRUCTED ON
ROCK LEDGE IN FOREGROUND.
LEFT ABUTMENT ALONG DAM AXIS. MAN IS AT LEVEL OF
30-FOOT HEAD.
EXHIBIT VI-3
-
,J
-
-
.-
--
-
-
-
-
' ....
.--
-
SECTION VI I
PROJECT ENERGY PLANNING
A. GENERAL
This section presents the projected energy usage for Togiak
over the study period and al ternative means of meeting these
projected demands--the base case plan and al ternative hydro-
electric projects. The potential future demand for power and
energy at Togiak was estimated during this study in order to
establish the electrical requirements that the alternatives
could meet. The alternatives to the base case included
hydroelectric projects involving a rockfill dam and two
different heights of concrete dams. This information was used
to size the al ternatives and was also used for the overall
economic analysis of the project, which is presented in Section
IX.
B. PROJECTION CONSIDERATIONS
The fut ure
function of a
demand
number
for
of
power and
variables
energy at
that are
Togiak is a
difficul t to
forecast and quantify. These factors include the appliance
saturation rate; the effects of cultural factors and tradi-
tional life styles on energy consumption; the rate of moderni-
zation of the Native life style; the amount of employment in
t he fish processing ind ust ry; t he nat ur al var iabil i ty 0 f the
fishery; the amount of new housing buil t in the area; and
numerous political factors such as the 1981 legislation relat-
ing to energy proj ect sand progr ams 0 f the APA. The pr ice 0 f
power at Tog iak will be much cheaper in the fut ure than the
current price; this will almost certainly alter the pattern of
energy and power demand, and the forecast as presented here is
probably conservative.
NB 1-42 5-9521-V I I VII-1
1. Appliance Saturation Rate
The number and type of appliances owned by each household,
as well as the extent to which these appliances are used, may
have a significant effect on the amount of power used in the
village. A definite relationship between appliances wi thin a
househol d and electr ical use character ist ics is very el usi ve.
The actual use of energy is more dependent on the number of
people wi thin a given residence, and their age, habits, and
financial condition. For example, one could predict the annual
energy use of a refrigerator or freezer because this is almost
independent of activity and habits. The rate of energy use for
electric lights, small appliances, and television is very
susceptible to habits. Energy demand for water heaters,
washers, dryers, and dishwashers varies in use primarily
subject to the number and age of users. For example, hot water
use among families with small children or babies is very high.
One method of measuring potential future growth and use of
appliances is through a concept known as the appliance satura-
tion rate. The estimated present percentages of homes having
various types of appliances in Anchorage, the Kenai-Cook Inlet
area, and Togiak are presented in Table VII-l. This informa-
tion for Togiak is very approximate and was obtained through
several interviews with village residents.
The number of appl iances in any given household in Togiak
depends on the desire and ability to obtain the appliances, the
cost of electricity, and the available room for the appliances.
Togiak is a relatively large village for the Bristol Bay region
and it strives to maintain strong cultural values; however,
generally speaking, the older village residents are more
concerned with preserving the native customs and traditions
than the younger generations. It is reasonable to expect that
modern electrical appliances will be assimilated into daily
life to an even greater degree in the future.
NBI-456-9521-VII VII-2
• --..
• --•
• -
•
•
• -
•
• ..
..
• .. --
• --
•
• -----.. -
, ...
, ....
-
.-
-
'-
,-
-
-
-
The purpose of presenting the Anchorage and Kenai-Cook
Inlet data in Table VlI-1 is to provide a compar ison with
largely urbanized areas that have much greater unit consumption
of electrical energy. Appliance saturation rates (and sizes of
appliances) for rural Alaskan villages such as Togiak can be
expected to increase in the future.
The base year 1980 rate of demand for electricity per
residential customer was about 2737 kWh, as discussed subse-
quently. This apparently reflects a very low electric
appliance use. This use was assumed to increase to approxi-
mately 4100 kWh by year 2001. The Ebasco (1980) regional
inventory assumed that households would increase energy
consumption to 6000 kWh per year by the year 1995, exclusive of
electric space heating. The Northern Technical Services and
Van Gulik Associates, Inc., report (1981), predicted the annual
energy use for the year 2000 at Togiak to be about 2600 kWh per
customer. This projection was based on a statistical analysis
of historical use patterns in this area, and is probably
extremely conservative. The new policies permitting opportuni-
ties for reductions in price, discussed in the next section,
indicate that this projected 4100 kWh annual residential use
rate is on the conservative side.
2. The Influence of Price on the Demand for Power
The 1981 legislation relating to the projects and programs
of the APA may result in some reduction in the cost of power to
this village. This decrease in power cost can be expected to
be accompanied by an increase in use.
Data from the Alaska Power Administration have been
developed to show the 1980 individual customer use of electric-
ity versus cost for all towns, cities, and villages for which
information was available in Alaska. This information is
summarized in tabular form in Table VII-2 and graphically in
NBI-456-9521-VII VII-3
Figure VI 1-1. While the data on Figure VII-1 are somewhat
scattered, the trend is evident that low power costs result in
higher usage and high power costs resul t in lower usage. In
economic terminology, this relationship of pr ice to quantity
consumed is referred to as "elasticity" of demand.
As ind ica ted by Figure VII-2, unit ener gy costs of less
than 100 mills per kilowatt-hour are generally accompanied by
high use rates, in excess of 7000 kilowatt-hours per customer
per year. As the unit price of power increases, the per
customer use tends to decrease, with the 48 AVEC Villages
having energy costs in excess of 400 mills per kilowatt-hour
and annual per customer demands of about 2000 kilowatt-hours.
The two different utili ties listed for Fairbanks provide an
even clearer example of the elasticity of the demand for
electrical energy; in this case where the cost of energy was
75.1 mills/kWh the annual demand was 10,519 kWh per customer
and where the cost of energy was 122.2 mills/kWh the demand was
5501 kWh per customer.
The general conclusion is that in the higher ranges of
price there is significant elasticity in demand. Lower energy
costs result in higher energy usage and this can also be
expected to occur in Togi ak with the advent of lower pr ices.
The actual amount of higher usage, however, is very difficult
to quantify. For purposes of this study no attempt has been
made to pred ict the higher usage other than to incorporate a
moderate increase in per customer use of energy in the projec-
tions covered below. These projections are probably on the low
side.
C. ENERGY DEMAND PROJECTIONS
For the economic evaluation, a period of 50 years after the
proposed date for the hydroelectric project to come on-line was
considered. As requested by APA, the period of study was
NBI-456-9521-VII VII-4
-
• ...
• ------•
• -• -• ..
• .. --
• ..
• ..
•
--
---
-
-
-
-
-
-
-
-
-
-
-
started in January 1982. The demand for power was assumed to
increase for 20 years from the beginning of the period of study
and was then held at a constant value for the remainder of the
period of evaluation. The planning period is the 20-year
period during which increased demand for energy was recognized,
from January 1982 to December 2001. The economic evaluation
period extends past the planning period to 2034, 50 years after
the on-line date for the hydroelectric alternative.
The overall energy demand for Togiak for purposes of energy
planning has been broken into two primary categories: direct
electrical demand, which includes residential, small commer-
cial, school, and Twin Hills; and space heating demand.
Projections for both of these categories and the combined
requirements are presented below.
The cannery at Togiak was not considered as a project
energy demand. The canning season is very short and it is
unlikely that the amount of electricity from a hydroelectric
project that could be used by the cannery would justify the
capital cost of connecting the cannery to the village system.
The cannery currently operates its own system. For purposes of
this study, it was assumed that the systems would cont inue to
be independent.
1. Direct Electrical Demand
The general approach followed in estimating direct
electrical demand was to break down the direct ci ty system
demand into general types of customers normally identified by
utilities in projecting electrical users in small villages.
These include the number of residential, small commercial, and
school customers. The electrical demand for Twin Hills was
also included in the direct electrical demand for Togiak,
al though Twin Hills is not currently served by the exist ing
system. Note that the cost of placing an underground rural
NBI-456-9521-VII VII-5
distribution (URD) cable across Togiak Bay, in order to connect
Twin Hills to the Togiak system, was assumed to be a cost
common to all alternatives. Therefore this cost was not
included in the cost estimates and subsequent economic
analyses. However, if the project were to be implemented, the
cable would be necessary at an approximate cost of $300,000.
The public and school demand for Togiak represents the
largest proportion of the direct electrical demand. For 1980,
it was about 44 percent. For this same year, residential use
in Togiak accounted for 36 percent of direct electrical demand,
small commercial accounted for only three percent, and Twin
Hills for the remaining 17 percent. The base year of 1980
demand was taken from actual Alaska Village Electric
Cooperative (AVEC) data on the community of Togiak, and it
provides a reasonable base.
Projections beyond 1980 were not directly tied to estimated
growth in popul a tion. Because of signif ican t changes that
could occur in the number of residential customers as a result
of additional housing units which may be provided through
public programs, it was found that residential demand was more
closely correlated to the number of housing units than to
population growth. This was substantiated by AVEC records of
similar communities. Growth in demand from 1980 through 1985
was heavily influenced by current plans regarding new housing,
which may be furnished by government agencies, with an assumed
annual growth rate of 4.4 percent for that period. The exact
timing and financing of new horne construction in Togiak is
somewhat uncertain; however, it is very likely that new housing
will be built in the future. Between 1986 and 1990 the growth
rate was assumed to be 2.8 percent; from 1990 through 2000 it
was assumed to be 2.3 percent; and 2.0 percent for 2001. After
2001, the growth rate was assumed to be zero.
NBI-456-9521-VII VII-6
.. -.. ..
•
• -
• ..
• -• -• -• ..
• ..
• -•
•
• •
• -
------• -
-
-
-
-
-
.-
.-
-
-
-... ..
..
-
Peak demands were calculated by applying typical load
factors for each type of consumer group. Load factor data were
der i ved from AVEC histor ical data as well as data from other
typical utilities. Historically, the load factor tends to
improve as the load increases. This improvement is explained
by added st reet 1 ighting, refr igera tion, and other loads that
tend to level the power demand. Projected total annual demands
over the planning period to 2001 are shown in Table VII-3.
Values of intermediate demands, for years not shown, can be
obtained through interpolation.
The monthly energy demands for Togiak were based on 1979
AVEC records. Using these data, the monthly percentages of the
total annual energy demand were computed. These values are
presented in Table VII-4 and are used in Tables VII-8A to
VII-8E to compute the projected monthly energy demands from
1980 to 2001.
2. Space Heating Demand
The amount of fuel used for heating at Togiak for 1979 was
taken from the Northern Technical Services and Van Gulick
Associates report (1981). The future increase in the amount of
hea ting oil used over the per iod of study was assumed to be
proportional to the increase in the number of customers.~/ The
annual heating requirements for Togiak are presented in Table
VII-5.
The monthly heating demands over the study period were
computed using the number of heating degree days per month from
the Togiak Community Profile ~/ and applying the calculated
monthly percentages to the annual heat demand values from Table
~/ See Table VII-3.
~/ Currently being prepared by DOWL Engineers .
NBI-456-9521-VII VII-7
VI 1-5. The resul t ing projected monthly heat ing demands for
19S0 to 2001 are presented in Table VII-6.
3. Total Energy Demands
The projected annual energy values for direct electrical
and heating demands are presented in Table VII-7. The projected
monthly energy demands for these same categories are presented
in Tables VII-SA through VII-SE. Also shown in the tables are
the total electrical demand and the total combined demand
(direct electrical plus heating demand).
The
VII-SE
annual energy
are presented
projections
in graphical
from Tables VI I-SA through
form in Figures VII-2 and
VI 1-3, where the energy demands are plotted for each year of
the study period for the two sizes of hydroelectric projects
considered. Also shown is the annual hydroelectric energy
production for the sizes studied (2SS kW and 432 kW). Figures
VII-2 and VII-3 also present two separate graphs of the same
information: overall data and detailed data. The overall data
graph illustrates that a very large proportion of the combined
energy demand is heating demand. The detail data graph presents
in more detail the relative values of the various demands and
available generation values.
The monthly energy projections from Tables VII-SA to VII-SE
for the 432 kW al ternatives are presented in Figure VII-4,
again as an overall data graph and a detailed data graph. These
graphs show the relationship on a monthly basis between the
energy demands and the hydroelectric energy available over the
study period. The graphs illustrate the general periods where
the hydroelectric energy would have to be supplemented by
diesel generation to meet the village needs and when excess
energy would be available for space heating. As shown, during
an average water year the 432 kW hydroelectric plant would be
sufficient to meet 100 percent of the direct electrical needs
NBI-456-9521-VII VII-S
-------
• ---• -• -
• ..
• •
• -• ..
• ..
• ----.. ----
-
-
-
-
-
-
-
-
-
-
-
-
. --
-
and 37 percent of the space heating requirements in 1985. From
2001 to 2034, the same hydroelectric plant would be capable of
supplying 98 percent of the direct electrical needs and 25
percent of the space heating requirements.
D. BASE CASE PLAN
The base case plan, as presented in the draft feasibili ty
report, consisted of continuing the existing diesel generation
scheme, and of supplementing the diesel generation with waste
heat recovery. This plan was later mod i fied to include wind
generation. The original plan is presented below, and is
followed by the wind generation scheme.
1. Original Plan
The base case plan to meet the projected energy demands
presented above was developed assuming that the existing diesel
system would continue to be used as the sole source of electric
power. The existing system would be modified to include waste
heat recovery, which would be used for space heating.
The existing AVEC diesel plant includes one 160 kW unit and
one 300 kW unit, with an additional 300 kW unit currently being
installed (460 kW firm capaci ty) .lJ This capaci ty should be
adequate to meet peak demands on the city system throughout the
period of study, based on the previously stated assumptions
about projected demands for power. The anticipated life of the
existing installation was assumed to be 15 years. After this
time it will be necessary to completely replace the units and
they will have no salvage value. When the equipment is
replaced in 15 years, it was assumed that the total firm
capacity would be increased to 600 kW and the equipment would
lJ In figuring firm capacity, the largest unit is omitted .
NBI -456-9521-VII VII-9
continue to be replaced every 20 years for the entire period of
economic evaluation.
The existing plant has 119,000 gallons of fuel storage. It
was assumed that an additional 50,000 gallons of fuel storage
would be required in 20 years.
In add i tion to the continuation of the exist ing diesel
power supply, the base case would utilize heat recovered from
the diesel generators to the maximum extent feasible. Togiak
has a large school, community buildings, small businesses, and
homes in close proximity to the powerhouse. This represents a
market for most of the heat that could be recovered from the
cooling jacket water and from the exhaust heat. The location
of the heating loads was taken from the Community Profile.
The fuel that the engines use represents energy injected
into the system, which is about 138,000 BTUs for every gallon
of fuel oil consumed. About one-third of this thermal energy
is converted into electrical energy, about one-third is
rejected in the form of heat from jacket water and oil cooling,
and the remaining one-third is rejected, also in the form of
heat, in the hot exhaust gases.
The heat energy f rom the jacket and oi I cool ing water is
the easiest to recover by putting in a simple heat exchanger
and heating water to be used for space heating. The temperature
available is about 180 to 190o F, which is quite usable for
hydronic heating or air plenum radiators.
The temperatures of the exhaust gases are much higher, 600
to 1000o F, but the associated heat energy is much more
expensive and complicated to capture. The exhaust is forced
through what looks like a standard fire tube or water tube
boiler, heating the water to just below boiling or high enough
to produce steam. The hot water is much easier to deal with,
NBI-456-9521-VII VII-10
• -• ..
• ---• -
• -• -• -• ..
• •
• -• -• •
• -• ---
• -
• ---
-
-
-
-
" ...
'MII
-
-
so most systems control the flows to prevent the formation of
steam.
The jacket water heat is almost entirely usable, while the
typical recovery efficiency of the exhaust heat system is
between 30 and 40 percent at full load.
One real problem in waste heat utilization is that the heat
available is directly dependent upon the electrical generation
requirements at any particular time. The requirements for
heating the buildings are, however, dependent upon the weather.
There is no viable method at present to store this heat over
long periods. Therefore, much available heat energy cannot be
utilized simply because there is no need for it at the right
time. This is called coincidence between supply and demand.
For this study it was assumed that about 65 percent of the
available jacket heat and 65 percent of the available exhaust
heat could be utilized each year. As the generation increases
over time, the heat is available more of the time and therefore
somewha t greater usage could be expected. The percentage of
available heat that can be used and the future growth rate of
usable heat are based on experience with similar projects in
Al aska, and are conserva t i ve. Accura te project ions of the
amount of heat that can be recovered are difficult because of
the limited amount of data available on this type of project.
It was assumed that public buildings in the area would be
connected initially and that this arrangement would not change
substantially over time. The utilization by public buildings
was assumed to increase by 1.5 percent per year.
The items associated with waste heat recovery include the
installation of equipment in the powerhouse and the use of
radiators and insulated pipes to convey the water to and from
the point of use. The equipment in the powerhouse would
NBI-456-9521-VII VlI-ll
include two exhaust hot water boilers, manifolded cooling water
piping, fan and pump controls, and a main heat exchanger
(water-water). The outside distribution piping would be 4 inch
diameter insulated pipes from the powerhouse to the school and
2 inch diameter lateral lines to smaller buildings. The
remaining investment would be for building conversions,
radiators, and heat meters. The heat could be used up to 2000
feet from the powerhouse. The heat exchangers for waste heat
recovery from the exhaust gases would have to be replaced every
ten years. This is in accordance with APA cr iter ia. The
remainder of the equipment in the powerhouse would need to be
replaced when the diesels are replaced; interim replacements of
this equipment would not be required as it is simple equipment
wi th no moving parts. The jacket heat recovery equipment is
essentially an extension of the diesel engine cooling system.
The buried pipes and hot water radiators should last for the
entire period of economic evaluation.
The diesel generation system at Togiak current 1 y consumes
about 88,000 gallons of fuel 0 i 1 per year; this rate can be
expected to increase over the next 20 years to more than
146,000 gallons per year. The amount of heating oil that can
be expected to be displaced by waste heat recovery in the year
2001 is more than 33,000 gallons.
2. Wind Generation Plan
The possibility of supplementing the existing diesel system
with wind generation was investigated as part of the base case
analysis. At the direction of the Alaska Power Authority, all
wind data and wind system costs were obtained from a report
entitled "Bristol Bay Regional Power Plan, Detailed Feasibility
Analysis, Interim Feasibility Assessment Report," 1~82, by
NBI-456-9521-VII VII-12
-..
•
--
• -• •
• -•
• -• -• • .. -
• -•
• -----------
.~ ..
, ....
.,..
,,,,.
.-
,..,
••
-,.
••
Stone and Webster. Unpublished data and information developed
by Stone and Webster in conjunction with this report was also
utilized.
Wind energy is an emerging technology, but has, to date,
proved to be economically feasible only under certain
cond i t ions. The investment cost associated wi th wind
generation is very high, and the cost of other energy sources
must be greater than at least 15 cents per kWh to justify the
investment. Standard equipment uses induction generators, and
system stability becomes a problem if more than about 20
percent of the total system power is from wind. For some
limited applications, such as remote cabins and communications
i nstalla t ions, di rec t current generators and banks of storage
batteries may be practical. Some configurations that use
excess wind energy for space heating show good overall
economics.
The only proven wind generators currently available have
capacities of 10 kW or less. However, units of up to 100 kW
are currently becoming commerically available and are expected
to be dependable. The application of this equipment is subject
to some limiting restrictions.
In order to be efficient the wind turbine must operate at
low wind speeds and yet be rugged enough to withstand high
gusting and wind. The gear boxes, towers, and blades must
operate almost continuously under these adverse conditions. At
this time few manufacturers are able to demonstrate the
required reliability under Alaska Conditions.
The electrical interface to the utili ty system is also
fairly complex with some reliability problems. The simpliest
and most reliable systems use induction generators, but these
units introduce another limiting factor, stability problems.
NBI-456-9521-VII VII-13
The wind varies widely in available energy. This variation
can be over seconds, days or months. Energy must be stored to
bridge the periods of low wind. There are many ideas about
possible storage mediums including compressed air, batteries,
hydrogen generation, pumped hydro storage, flywheels, and
thermal.
All of these methods have a reasonable theoretical basis
but are not commercially mature. The efficiency, availability,
reliability and operational requirements of these schemes are
many years from application to present electric power systems.
Storage of heat using water or eutechtic sal ts is a good
system if the energy is to be used ultimately for space heat.
Under rapidly varying wind conditions the energy output of
the unit varies widely. Since the utility system load is quite
stable, the other generation must absorb these wide
variations. The induction generators also introduce a
frequency stabili ty problem, since they do not operate at a
"synchronous" speed, deriving their excitation from the power
system.
These conditions limit the amount of wind driven induction
generation to about 20% at any given moment. This is a very
rough number and will vary with the inherent stability of the
existing system, but will probably never exceed 30%.
Synchronous machines
load are prohibitively
reliable systems.
which could carry much more of the
expensive and not well developed,
Since storage is a major problem, the electrical energy
general I y is generated and consumed in the same i nst ant . At
periods of high wind the loads may be low, while at times of
NBI-456-9521-VII VII-14
• -• ---..
• ..
• -• .. --• .,
• ..
• .. .. -
• ..
• .. --• ---
• ---
"III
....
......
,-
••
...
••
-...
-
high load there may be low wind cond i t ions. Th is coincidence
factor greatly limits the final percentage of energy which can
be generated with wind equipment.
To an electric utility the wind generation represents only
a savings in fuel and some slight reduction in engine
maintenance. A full-sized diesel plant must be maintained
because the wind source may not be available during the system
peak.
This benefit is often overestimated by individual consumers
who have thei r own wind systems because they save the full
billing rate for the electrical power. Actually, they are not
paying for the standby generation, utility equipment and
personnel avai lable to them when the wind doesn't blow. They
are being subsidized by their neighbors.
The communities we have studied fall outside of the wind
class map provided. We have assumed Class 5 winds for all
communities. This provides an average energy of 390 Watts per
square meter.
For this study, two types of wind machines were
considered. Both types are mounted on 60-foot towers and use
induction generators. One unit has seven-foot-diameter blades
and a maximum output of 10 kW, and the other has 20-foot-
diameter blades, with a maximum output of 25 kW. A maximum
power penetration of 20 percent was assumed; this means that at
any given moment, not more than 20 percent of the load can be
met by wind driven generators. Significant data on the
machines investigated are presented as Table VII-12.
For this study, it was assumed that five ten kilowatt wind
generators would be installed at Togiak during 1982, and that
these plants would be operational during 1983 and would require
NBI-456-9521-VII VII-15
replacement every 15 years. A sixth unit would be brought on
line during 1992 and would increase the total installed
capacity to 60 kW; a seventh unit would be added in 2000,
increasing the capaci ty to 70 kW. The usable wind generation
is presented as Table VII-13. Inspection of Table VII-13 shows
that the amount of usable wind generation has been assumed to
be constant as long as the installed capacity remains the
same. The amount of usable wind generation would probably
actually increase slightly with time; however, this increase
would probably be minor, and the accuracy of the energy use and
economic analyses would not be enhanced by this refinement.
The estimates presented here are conservative.
E. HYDROELECTRIC PROJECT PLAN
The hydroelectric project plans investigated for Togiak
would consist of a 432 kW or a 288 kW hydroelectric power plant
suppl emented by diesel generation. The hyd roelect r ic power
plant would become functional in late 1984. An on-line date of
January 1, 1985, has been assumed for this study. The annual
average energy generation for the two options is shown on
Figures VII-2 and VII-3.
The entire existing diesel capacity (460 kW firm capacity)
would be required as standby and backup power. The hydroelec-
tric generation would be adequate to meet the direct electrical
demand during most of the year and it would also meet a portion
of the common load during the peak July to October period;
however, during periods between the end of November and the
first of April it would be necessary to supplement the hydro-
electric generation wi th diesel in order to meet the direct
elect r ical demand. The full capac i ty of diesel generation
required to meet the direct electrical demand would still be
necessary for emergency use. Since the diesel engines would
not operate as much under this plan as they would under the
NBI-456-9521-VII VII-16
-
• ...
•
--• ..
• ..
• ..
• -
•
•
• ...
• -• ..
• -
• •
•
.. ---
• .. .. -
-
-
-
-
-
... ---
base case plan, it was assumed that they would not need to be
replaced for at least 30 years after the initial replacement in
15 years.
Waste heat recovery would not be installed as part of this
plan because the diesels would not operate often enough for the
heat recovery to justify the cost of the necessary equipment.
The average annual energy production for the hydroelectric
power plant would be 2.660 million kWh for the 432 kW option or
1.773 for the 288 kW option, compared to a projected direct
electrical demand for electricity of 0.892 million kWh in 1985
and 1.286 million kWh for the year 2000. The average annual
plant factor would be about 70 percent. Diesel generation
would be required to meet the direct electrical demand for a
small part of the time due to the lack of coincidence between
electrical demand and hydroelectric generation. Hydroelectric
energy not needed to meet the direct electrical demand would be
used for space heating. Appendix G describes space heating
installation and cost for Togiak.
Using the above criteria,
energy that is available over
the amount of hydroelectric
the study period to meet the
direct electrical demands and the heating demands has been
computed on a monthly basis. The resul ts are presented in
Tables VII-9A through VII-9E and VI 1-1 OA throu~h VI 1-1 OE for
the two sizes of projects. The resulting net values of hydro-
electric energy used for the direct electrical and the heating
demands were used in Section IX, Economic Analysis.
Note that the "energy accounting" described above and
presented in Tables VII-9A through VII-9E and VII-lOA through
VI 1-1 OE assumes that 100 percent usage can be made of the
available hydroelectric energy. This usage level may not be
wholly attainable in practice because of the unavailability or
NBI-456-9521-VII VII-17
breakdown of end-use equipment and distribution lines. Also, a
system making use of all of the excess hydroelectric energy for
heat would not be 100 percent efficient. However, any error
resulting from the assumption of a 100 percent usage rate would
likely be small and would be counterbalanced because both the
projected demands and the hydroelectric energy output estimates
are conservative.
The annualized values of energy demand, generation, and
usage are presented as Tabl es VII-11 and VI 1-12. The values
from these tables are used extensively for the economic
analysis presented in Chapter IX.
NBI-456-9521-VII VII-18
• -• • .. -.. -• -• -• •
• ..
• •
• •
• •
• ..
• -
• ..
• .. .. .. .. -• ---
..
...
.-
-
,-
.-
-
.-
-..:..
-
'-
-
',.
...
....
'*
-
TABLE VII-1
ELECTRICAL APPLIANCE SATURATION RATES
TOGIAK
Consumption Kenai-
per House-
Anchorage l.! Cook
Togiak J:.../ Appliance Household 1/ Inlet l.!
(kWh) ---percentage of total households---
Lights 1,000 100 100 100
Small Appliances 1,010 100 100 100
Refrigerator 1,250 100 100 99
Freezer 1,350 42 56 100
Water Heater 3,475 100 94 68
Television 400 156 100+ 100
Video Tape
Recorder 3/ 3/ ~ 76
Washer 70 50 85 68
(Water) (1,050)
Dryer 1,000 71 76 68
Dishwasher 230 50 31 0
(Water) 700
1/ Values are for 1978 from "Electric Power Consumption for the
Railbelt: A Projection of Requirements," Technical Appendices,
Institute of Social and Economic Resources, May 23, 1980.
2/
3/
The percentage of residences having the listed appliances is
based on estimates from several Togiak residents --usage rate
data are not available nor is the mode split between electrical
and other sources of energy known.
Not available.
-NBI-456-9521-7-1
-
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
]j
2/
TABLE VII-2
UNIT COST AND ENERGY DEMANo..!!
ALASKA
Cost
Location (mills/kWh)
5 Villages (Southeast) 298.7
Haines 144.3 Juneau~/ 45.7 Juneau~/ 92.2
Ketchikan 58.4
Metlakatla 31.5
Petersburg 123.5
Sitka 49.8
Skagway 133.9
Wrangell 156.3
Yakutat 152.7 AnChOrag~~ 37.5 Anchorag~ 33.6 Anchorag~/ 45.8
Glenallen, Valdez 131. 5
Homer 35.9
Kodiak 149.3
Seward 54.0 Fairbank~~ 122.2 Fairbank~ 75.1
Fort Yukon 245.3
Tanana 269.9
48 Villages ( AVEC) 422.1
Barrow 129.8
Kotzebue 199.7
Bethel 177.4
Dillingham 151. 9
McGrath 233.5
Naknek 174.5
Data obtained from "Alaska Electric Power
1980," Sixth Edition, August 1981, United
of Energy, Al aska Power Administration.
table on page 40, "Energy Sales, Revenue,
were used to develop this table.
Demand
(kWh/Customer)
3,996
5,680
7,775
7,775
8,528
17,981
6,355
8,483
5,879
4,689
7,170
9,124
11,982
14,800
5,890
12,644
5,871
6,694
5,501
10,519
1,669
5,992
2,044
4,395
5,290
4,590
5,000
1,735
5,524
Statistics, 1960-
States Department
Val ues from the
Customers--1980,"
Juneau, Anchorage and Fairbanks are served by more than one
utility. Each listing is for a separate utility.
NBI-456-9521-7-2
• ---
• --..
• -• ..
• -• -•
• •
• •
• ---
• -• ..
•
• -
• ---
--
-
-
~-
.....
~ ....
....
--
-
-
Type
TABLE VII-3
PROJECTED ANNUAL DIRECT ELECTRICAL DEMAND
TOGIAK
Number Annual Energy ~
of of Demand
Peak
Demand
Year Consumer Customers (1000 kWh) (kW)
1980
1985
1990
2000
2001
1/
Residential 95 260 69
Small Commercial 5 24 7
Public and School 12 316 90
Twin Hills JJ 21 120 36
Total 133 720 202
Residential 105 337 85
Small Commercial 6 42 12
Public and School 12 364 99
Twin Hills 23 149 41
Total T46 892 237
Residential 115 413 98
Small Commercial 7 59 15
Public and School 12 382 104
Twin Hills 25 171 43
Total 159 1,025 260
Total 175 1,286 326
Total 177 1,314 333
Twin Hills is not served in the existing system but it was
included for purposes of the projections. The use and demand of
Twin Hills were assumed to be 20 percent of the Togiak values.
For annualized demand, see Tables VlI-11 and VII-12 .
NBI-456-9521-7-3
TABLE VII-4
MONTHLY LOAD CHARACTERISTICS l!
TOGIAK
Monthly Monthly ~
Monthly Percentage Monthly Percentage
Power of Annual Energy of Annual
Demand Peak Power Demand Energy
Month (kW) Demand (kWh) Demand
January 165 2/ 100.0 56,400 9.4
February 151 91.5 50,600 8.4
March 127 77.0 74,400 12.4
April 139 84.2 52,500 8.7
May 127 77.0 50,100 8.3
June 115 69.7 21,000 3.5
July 131 79.4 35,200 5.8
August 144 87.3 44,900 7.5
September 137 83.0 55,500 9.2
October 163 98.8 47,800 7.9
November 163 98.8 52,500 8.7
December 163 98.8 61,600 10.2
Totals 602,500 100.0
Based on 1979 AVEC data for Togiak. 1/
2/ This value was changed from 192 kW to 165 kW because it
seemed abnormally high compared to other years. This gives
a 41.7 percent annual load factor.
3/ Percentages calculated from demand
NBI-456-9521-7-4
---
-
• .. ..
•
• • ... ... .. .. .. .. ..
•
• .. .. .. .. .. .. .. -..-.. .. .. .. .. .. -
' ....
-
-
-
-
-
...
..
TABLE VII-5
ANNUAL HEATING DEMAND
TOGIAK
Year 1980 1985 1990 2000 2001
Annual Fuel Oil (Gal.) 133,000 146,000 159,000 175,000 177,000
Annual Requirementl/
(1000 kWh)
3,760 4,130 4,500 4,950 5,010
~/ 138,000 BTU/Gal, 70% efficiency, and 3413 BTU/kWh. Values
rounded to nearest 10 gallons
NBI-456-9521-VII-5
TABLE VII-6
MONTHLY HEATING DEMANDs!!
TOGIAK
Heatin~ Percentage
of Annual
Degree Heating
Month Days Degree Days 1980 1985 1990 2000 2001 -----------------1000 kWh-----------------
January 1530 13.6 511 562 612 673
February 1300 11.5 432 475 518 569
March 1390 12.3 462 508 554 609
April 1020 9.1 342 376 410 450
May 720 6.4 241 264 288 317
June 400 3.5 132 145 158 173
July 310 2.7 101 111 121 134
August 340 3.0 113 124 135 148
September 530 4.7 177 194 211 233
October 940 8.4 316 347 378 416
November 1230 10.9 410 450 490 540
December 1560 13.9 523 574 625 688
TOTALS 11,270 100.0 3760 4130 4500 4950
1/ Based on the number of heating degree days indicated in the
Togiak Community Profile multiplied by the Annual Heating
Demands from Table VII-5.
2/ From the Togiak Community Profile (currently being prepared
by DOWL Engineers).
NBI-456-9521-VII-6
681
576
616
456
321
176
135
150
236
421
546
696
5010
..
•
.. -
• •
• ..
• ..
• -•
• •
• .. .. -
• ..
•
•
•
..
--
-
TABLE VII-7
ANNUAL ENERGY DEMAND ..
TOOIAK
-Direct l! Total
Electrical Heating ~ Combined
Year Demand Demand Demand
--------------------1000 kWb-------------------
1980 720 3760 4480 -1985 892 4130 5022
1990 1025 4500 5525
2000 1286 4950 6236
2001 1314 5010 6324 -2031 1314 5010 6324
-
-
...
1/ From Table VII-3 . ..
~ From Table VII-6. -NBI-456-9521-VII-7
..
TABLE VII-8A
1980 MONTHLY ENERGY DEMAND
TOGIAK
Percentage l./
Direct Y of Annual
Heat :Y Direct Electrical Total
Month Demand Demand Demand Demand
-------------------1000 kWh --------------------
January 9.4 68 511
February 8.4 60 432
March 12.4 89 462
April 8.7 63 342
May 8.3 60 241
June 3.5 25 132
July 5.8 42 101
August 7.5 54 113
September 9.2 66 177
October 7.9 57 316
November 8.7 63 410
December 10.2 73 523
Totals 100.0 720 3760
1/ From Table VII-4
Y Based on Annual Direct Demand of 720 MWh from Table
VI 1-3.
:Y From Table VII-6.
NBI-456-9521-VII8A
579
492
551
405
301
157
143
167
243
373
473
596
4480
., -------
• •
• • .. -
• -• ..
• ..
• ..
•
• ..
• -
• ..
•
-
•
--
,-
~"."
.....
....
,-
'"."
-
---
-
' ... ..
-
TABLE VII-8B
1985 MONTHLY ENERGY DEMAND
TOGIAK
Percentage lJ
of Annual Direct JJ
Hea t l.! Direct Electrical Total
Month Demand Demand Demand Demand
--------------------1000 kWh ----------------------
January 9.4 84 562
February 8.4 75 475
March 12.4 110 508
April 8.7 78 376
May 8.3 74 264
June 3.5 31 145
July 5.8 52 111
August 7.5 67 124
September 9.2 82 194
October 7.9 70 347
November 8.7 78 450
December 10.2 91 574
Totals 100.0 892 4130
1/ From Table VII-4
2/ Based on Annual Direct Demand of 892 MWh from Table
VII-3.
3/ From Table VII-6.
NBI-456-9521-VII8B
646
550
618
454
338
176
163
191
276
417
528
665 --
5022
1/
~/
1./
TABLE VII -8C
1990 MONTHLY ENERGY DEMAND
TOGIAK
Percentage 1../
Direct ~ of Annual
Heat 1./ Direct Electrical Total
Month Demand Demand Demand Demand
--------------------1000 kWh ---------------------
January 9.4 96 612 708
February 8.4 86 518 604
March 12.4 127 554 681
April 8.7 89 410 499
May 8.3 85 288 373
June 3.5 36 158 194
July 5.8 60 121 181
August 7.5 77 135 212
September 9.2 94 211 305
October 7.9 81 378 459
November 8.7 89 490 579
December 10.2 105 625 730 -----
Totals 100.0 1025 4500 5525
From Table VII-4
Based on Annual Direct Demand of 1,025 MWh from Table VII-3.
From Table VII-6.
NBI-456-9521-VII8C
-
------• ..
• •
•
.. -.. .. .. ..
• .. ..
., ..
•
• .. .. .. .. ..
• -• .. -.,
••
~"Ii'I1II
,-
'.,""
.....
...
-
-
..
-
-
---
-
TABLE VII-8D
2000 MONTHLY ENERGY DEMAND
TOGIAK
Percentage 1/
Direct 1:./ of Annual
Heat 1./ Direct Elect r ical Total
Month De!,!!and Demand Demand Demand
-------------------1000 kWh ----------------------
January 9.4 121 673 794
February 8.4 108 569 677
March 12.4 159 609 768
April 8.7 112 450 562
May 8.3 107 317 424
June 3.5 45 173 218
July 5.8 75 134 209
August 7.5 96 148 244
September 9.2 118 233 351
October 7.9 102 416 518
November 8.7 112 540 652
December 10.2 131 688 819 -
Totals 100.0 1286 4950 6236
From Table VII-4 1/
2/
1./
Based on Annual Direct Demand of 1,286 MWh from Table VII-3.
From Table VII-6.
NBI-456-9521-VII8D
TABLE VII-8E
2001 MONTHLY ENERGY DEMAND
TOGIAK
Percentage ,lj
Di rect 1:../ of Annual
Heat ~/ Direct Electrical Total
Month Demand Demand Demand Demand
-----------------1000 kWh ------------------------
January 9.4 124 681 805
February 8.4 110 576 686
March 12.4 163 616 779
April 8.7 114 456 570
May 8.3 109 321 430
June 3.5 46 176 222
July 5.8 76 135 211
August 7.5 99 150 249
September 9.2 121 236 357
October 7.9 104 421 525
November 8.7 114 546 660
December 10.2 ~ 696 830
Totals 100.0 1314 5010 6324
From Table VII-4 1./
:l:./
~/
Based on Annual Direct Demand of 1,314 MWh from Table VII-3.
From Table VII-6.
NBI-456-9521-VII8E
--
•
•
•
• -• ..
• ..
•
•
• ..
• ..
• ..
• •
•
• ..
•
•
• ..
•
•
• --..
I , j I I I I t
TABLE VII-9A
TOGIAK ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
1980 ENERGY GENERATION, DEMAND, AND USAGE
i i
Di rect..!)
Electrical Hydr~ Direct Us0 Remaining Heat..!../ Hydro Used Unused Hydro
Month Demand Energy Hydro Energy Hydro Energy Demand For Heat Energy
--------------------------------------------1000 kWh------------------------------------------
Jan
Feb
Mar
Apr
May
June
July
Aug
Sep
Oct
Nov
Dec
68
60
89
63
60
25
42
54
66
57
63
73
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 511 0
0 432 0
0 462 0
0 342 0
0 241 0
0 132 0
0 101 0
0 113 0
0 177 0
0 316 0
0 410 0
0 523 0
Totals 720 0 0 0 3760 0
1/
2/ From Table VII-8A
The proposed hydroelectric project will not go on-line until late 1984 or early 1985.
For purposes of projection, an on-line date of January 1985 has been assumed.
0
0
0
0
0
0
0
0
0
0
0
0
0
]J Energy produced by hydro project that will meet electrical demand currently met by diesel generation.
NBISF-456-9521-7-9A
TABLE VII-9B
TOGIAK ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
1985 ENERGY GENERATION, DEMAND, AND USAGE
Direct!.!
Hydra-Y UseY Heat-!! Electrical Direct Remaining Hydro Used Unused Hydro
Month Demand Energy Hydro Energy Hydro Energy Demand For Heat Energy
--------------------------------------------1000 kWh------------------------------------------
Jan 84
Feb 75
Mar 110
Apr 78
May 74
June 31
July 52
Aug 67
Sep 82
Oct 70
Nov 78
Dec 91
Totals 892
From Table VII-8B
From Table VII-1
125 84
93 75
158 110
261 78
261 74
261 31
261 52
261 67
261 82
261 70
261 78
196 91
2660 892
41 562 41 0
18 475 18 0
48 508 48 0
183 376 183 0
187 264 187 0
230 145 145 85
209 111 111 98
194 124 124 70
179 194 179 0
191 347 191 0
183 450 183 0
105 574 105 0
1768 4130 1515 253
1/
2/
3/ Energy produced by hydro project that will meet electrical demand currently met by diesel generation.
NBISF-456-9521-7-9B
II I. I ••••• I •• ' I ••• II "'111'1 I. I. , •• 1 II
I J I j I i j I j I I t I l I I
TABLE VII-9C
TOGIAK ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
1990 ENERGY GENERATION, DEMAND, AND USAGE
Di rectl.!
Hydro.Y Us~ Hea ill Electrical Direct Remaining Hydro Used Unused Hydro
Month Demand Eneq~y Hydro Energy Hydro Energy Demand For Heat Energl
--------------------------------------------1000 kWh------------------------------------------
Jan 96
Feb 86
Mar 127
Apr 89
May 85
June 36
July 60
Aug 77
Sep 94
Oct 81
Nov 89
Dec 105
Totals 1025
From Table VII-8C
From Table VI-1
125 96
93 86
158 127
261 89
261 85
261 36
261 60
261 77
261 94
261 81
261 89
196 105
2660 1025
29 612 29 0
7 518 7 0
31 554 31 0
172 410 172 0
176 288 176 0
225 158 158 67
201 121 121 80
184 135 135 49
167 211 167 0
180 378 180 0
172 490 172 0
91 625 91 0
1635 4500 1439 196
1/
2/
3/ Energy produced by hydro project that will meet electrical demand currently met by diesel generation.
NBISF-456-9521-7-9C
TABLE VII-9D
TOGIAK ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
2000 ENERGY GENERATION, DEMAND, AND USAGE
Direcd/
HydroY Use-Y Head/ Electrical Direct Remaining Hydro Used Unused Hydro
Month Demand Energy Hydro Energy Hydro Energy Demand For Heat Ener~~
--------------------------------------------1000 kWh------------------------------------------
Jan 121
Feb 108
Mar 159
Apr 112
May 107
June 45
July 75
Aug 96
Sep 118
Oct 102
Nov 112
Dec 131
Totals 1286
From Table VII-8D
From Table VI-1
125 121
93 93
158 158
261 112
261 107
261 45
261 75
261 96
261 118
261 102
261 112
196 131
2660 1270
4 673 4 0
0 569 0 0
0 609 0 0
149 450 149 0
154 317 154 0
216 173 173 43
186 134 134 52
165 148 148 17
143 233 143 0
159 416 159 0
149 540 149 0
65 688 65 0
1390 4950 1278 112
1/
2/
--Sf Energy produced by hydro project that will meet electrical demand currently met by diesel generation.
NBISF-456-9521-7-9D
I • I I " 'I 'I I I I. I I ,. I. " I I •• •• 'I I. I • 'I I •
I I j i t
TABLE VII-9E
TOGIAK ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
2001 ENERGY GENERATION, DEMAND, AND USAGE
Directl!
Hydro0' Usd! Heatl! Electrical Direct Remaining Hydro Used Unused Hydro
Month Demand Energy Hydro Energy Hydro Energy Demand For Heat Energy
--------------------------------------------1000 kWh------------------------------------------
Jan 124
Feb 110
Mar 163
Apr 114
May 109
June 46
July 76
Aug 99
Sep 121
Oct 104
Nov 114
Dec 134
Totals 1314
From Table VII-8E
See Section VI-1
125 124
93 93
158 158
261 114
261 109
261 46
261 76
261 99
261 121
261 104
261 114
196 134
2660 1292
1 681 1 0
0 576 0 0
0 616 0 0
147 456 147 0
152 321 152 0
215 176 176 39
185 135 135 50
162 150 150 12
140 236 140 0
157 421 157-0
147 546 147 0
62 696 62 0
1368 5010 1267 101
1/
2/
3/ Energy produced by hydro project that will meet electrical demand currently met by diesel generation.
NBISF-456-9521-7-9E
Directl/
TABLE VII-lOA
TOGIAK ALTERNATIVE B
INSTALLED CAPACITY = 288 kW
1980 ENERGY GENERATION, DEMAND, AND USAGE
Electrical Hydro~ Direct Use Remaining Hea~/ Hydro Used Unused Hydro
Month Demand Energy Hydro Energy Hydro Energy Demand For, Heat Energy
--------------------------------------------1000 kWh------------------------------------------
Jan
Feb
Mar
Apr
May
June
July
Aug
Sep
Oct
Nov
Dec
Totals
68
60
89
63
60
25
42
54
66
57
63
73
720
From Table VII-8A
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
511
432
462
342
241
132
101
113
177
316
410
523
3760
o
o
o
o
o
o
o
o
o
o
o
o
o
1/
2/ The proposed hydroelectric project will not go on-line until late 1984 or early 1985.
For purposes of projection, an on-line date of January 1985 has been assumed.
NBISF-456-9521-7-10A
o
o
o
o
o
o
o
o
o
o
o
o
o
I • , I • I • I 'I I , • , •• ,. f. ,. " 'I I I ,. I • I I I I I I
I I I , I I t I I j
TABLE VII-lOB
TOGIAK ALTERNATIVE B
INSTALLED CAPACITY = 288 kW
1985 ENERGY GENERATION, DEMAND, AND USAGE
Di rectl.!
Hydro:!:J Us~ Heatl.! Electrical Direct Remaining Hydro Used Unused Hydro
Month Demand Energy Hydro Energy Hydro Energy Demand For Heat Energy
--------------------------------------------1000 kWh------------------------------------------
Jan 84
Feb 75
Mar 110
Apr 78
May 74
June 31
July 52
Aug 67
Sep 82
Oct 70
Nov 78
Dec 91
Totals 892
From Table VII-8B
From Table VI-2
83 83
62 62
106 106
174 78
174 74
174 31
174 52
174 67
174 82
174 70
174 78
131 91
1774 874
0 562 0 0
0 475 0 0
0 508 0 0
96 376 96 0
100 264 100 0
143 145 143 0
122 111 111 11
107 124 107 0
92 194 92 0
104 347 104 0
96 450 96 0
40 574 40 0
900 4130 889 11
1/
2/
3/ Energy produced by hydro project that will meet electrical demand currently met by diesel generation.
NBISF-456-9521-7-10B
TABLE VII-10C
TOGIAK ALTERNATIVE B
INSTALLED CAPACITY = 288 kW
1990 ENERGY GENERATION, DEMAND, AND USAGE
Directli
Hydrob' Us~ Heatli Electrical Direct Remaining Hydro Used Unused Hydro
Month Demand Energ~ Hydro Energy Hydro Energy Demand For Heat Energl
--------------------------------------------1000 kWh------------------------------------------
Jan 96
Feb 86
Mar 127
Apr 89
May 85
June 36
July 60
Aug 77
Sep 94
Oct 81
Nov 89
Dec 105
Totals 1025
From Table VII-8C
From Table VI-2
83 83
62 62
106 106
174 89
174 85
174 36
174 60
174 77
174 94
174 81
174 89
131 105
1774 967
0 612 0 0
0 518 0 0
0 554 0 0
85 410 85 0
89 288 89 0
138 158 138 0
114 121 114 0
97 135 97 0
80 211 80 0
93 378 93 0
85 490 85 0
26 625 26 0
807 4500 807 0
1/
2/
3/ Energy produced by hydro project that will meet elecrical demand currently met by diesel generation
NBISF-456-9521-7-10C
I I I • I I • I 'I • I 'I ,. f. ,I. ,. ,. , I 'I I • I • , • I I I I
I j I • I I j I J i ( I I
TABLE VII-10D
TOGIAK ALTERNATIVE B
INSTALLED CAPACITY = 288 kW
2000 ENERGY GENERATION, DEMAND, AND USAGE
Direct1! Hydr~/ UseY Hea0 Electrical Direct Remaining Hydro Used Unused Hydro
Month Demand Energy Hydro Energy Hydro Energy Demand For Heat Energy
--------------------------------------------1000 kWh------------------------------------------
Jan 121
Feb 108
Mar 159
Apr 112
May 107
June 45
July 75
Aug 96
Sep 118
Oct 102
Nov 112
Dec 131
Totals 1286
From Table VII-8D
From Table VI-2
83 83
62 62
106 106
174 112
174 107
174 45
174 75
174 96
174 118
174 102
174 112
131 131
1774 1149
0 673 0 0
0 569 0 0
0 609 0 0
62 450 62 0
67 317 67 0
129 173 129 0
99 134 99 0
78 148 78 0
56 233 56 0
72 416 72 0
62 540 62 0
0 688 0 0
625 4950 625 0
1/
2/
3/ Energy produced by hydro project that will meet elecrical demand currently met by diesel generation.
NBISF-456-9521-7-10D
TABLE VII-10E
TOGIAK ALTERNATIVE B
INSTALLED CAPACITY = 288 kW
2001 ENERGY GENERATION, DEMAND, AND USAGE
Direct!.!
Hydro.Y Usell Hea t-!.I Electrical Direct Remaining Hydro Used Unused Hydro
Month Demand Energ¥: Hydro Energy Hydro Energy Demand For Heat Energy
--------------------------------------------1000 kWh------------------------------------------
Jan 124
Feb 110
Mar 163
Apr 114
May 109
June 46
,July 76 1
Aug 99
Sep 121
Oct 104
Nov 114
Dec 134
Totals 1314
From Table VII-8E
From Table VI-2
83 83
62 62
106 106
174 114
174 109
174 46
174 76
174 99
174 121
174 104
174 114
131 131
1774 1165
0 681 0 0
0 576 0 0
0 616 0 0
60 456 60 0
65 321 65 0
128-176 128 0
98 135 98 0
75 150 75 0
53 236 53 0
70 421 70 0
60 546 60 0
0 696 0 0
609 5010 609 0
1/
2/
3/ Energy produced by hydro project that will meet elecrical demand currently met by diesel generation.
NBISF-456-9521-7-10E
I I I. I. I I I. I ~ I. I. ,. I. ,. I. J. ,. I. I I I I I I , I
....
.....
....
.....
... "
.....
....
.11
....
••
-
....
••
OIl.
••
....
••
...
YEAR
TABLE VII-11
ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 KW
ENERGY DEMAND, GENERATION, AND USAGE
ANNUAL SUMMARY
TOGIAK
Total ]J Demand Met ~ Required Supplement ~
Demand by Hydro Diesel Generation
(1000 kWh) (1000 kWh) (1000 kWh) --
1980 720 0 720
1981 754 0 754
1982 789 0 789
1983 823 0 823
1984 858 0 858
1985 892 892 0
1986 919 919 0
1987 945 945 0
1988 972 972 0
1989 998 998 0
1990 1025 1025 0
1991 1051 1050 1
1992 1077 1074 3
1993 1103 1099 4
1994 1129 1123 6
1995 1156 1148 8
1996 1182 1172 10
1997 1208 1197 11
1998 1234 1221 13
1999 1260 1246 14
2000 1286 1270 16
2001-
2034 1314 1292 22
1/
2/
3/
From Table VII-3. Intermediate values not shown on VII-3
obtained through interpolation .
From Tables VII-9A through VII-9E . Intermediate values not
shown on those tables obtained through interpolation.
Difference between total demand and demand met by hydro .
NBI-456-9521-7-11
YEAR
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
TABLE VII-12
ALTERNATIVE B
INSTALLED CAPACITY = 288 KW
ENERGY DEMAND, GENERATION, AND USAGE
ANNUAL SUMMARY
TOGIAK
Total l.I Demand Met J:j Required Supplement l!
Demand by Hydro Diesel Generation
(1000 kWh) (1000 kWh) (1000 kWh)
720 0 720
754 0 754
789 0 789
823 0 823
858 0 858
892 874 18
919 893 26
945 911 34
972 930 42
998 948 50
1025 967 58
1051 985 66
1077 1003 74
1103 1022 81
1129 1040 89
1156 1058 98
1182 1076 106
1208 1094 114
1234 1113 121
1260 1131 129
1286 1149 137
2001-
2034 1314 1165 149
1/
2/
3/
From Table VII-3. Intermediate values not shown on VII-3
obtained through interpolation.
From Tables VII-lOA through VII-10E. Intermediate values not
shown on those tables obtained through interpolation.
Difference between total demand and demand met by hydro.
NBI-456-9521-7-12
• -
• •
• ..
• ..
• .. ., ..
• ..
• ..
• ..
• .. ..
•
• ---
• ..
• -
• •
• ..
• •
• •
·.iIIII1
... '
..... ,
_ ..
....
....
_.
"" .
.....
••
-.
....
.....
...
...
-.
••
-..
TABLE VII-13
WIND ENERGY EQUIPMENT DATA
TOGIAK
10 kW
Machine
Tower Height (it) 60
Efficiency (%) 20
Mean Power Output (kW) ]J 3.75
Availability (%) Y
Annual Usable Energy
Capital Cost ($)
1/ Mean Power Output
90
Generation (kWh) 1./ 27,900
34,000
~ (Watts/Meters 2 ) X
(0.7854) X (Diameter 2 ) X
(efficiency) / 1000
25 kW
Machine
60
20
7.66
90
60,400
50,000
~/ The availability is the time that the unit can actually
operate and is limited by breakdowns, maintenance, and
repair.
~/ Energy ~ Mean Power Output X Availability .
NBISF-456-9521-7-13
YEAR
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
TABLE VII-14
WIND ENERGY USAGE
TOGIAK
Peak System JJ Installed Wind
Demand Capacity
(kW) (kW)
216 0
223 50
330 50
237 50
242 50
246 50
251 50
255 50
260 50
267 50
273 60
280 60
286 60
293 60
300 60
306 60
313 60
319 60
326 70
Y Usable Wind 11
Generation
(1000 kWh)
140
140
140
140
140
140
140
140
140
140
167
167
167
167
167
167
167
167
195
2001-
2034 333 70 195
JJ From Table VII-3. Intermediate values obtained by
interpolation.
2/
3/
10 kW generators. The maximum penetration of asynchronous
wind generators into the system is 20%; therefore, not more
than 20% of the total peak demand can be met by wind at any
time.
From Stone and Webster Report and Notes.
NBISF-456-9521-7-14
-
• -
•
•
•
..
•
• .. .. ..
•
•
• ..
• ..
• ..
• ..
• ..
• .. .. ..
• .. .. .. .. -
• ..
....
••
_I
,*1
....
.....
.....
... "
....
....
..
...
...
...
20
15h1r~---t---t----=
-10 a:
lJJ
~
.......
0
0
0 ... -
)It
.r;
3=
~ -o
Z
<X
::t
IJJ o
-I
<X :::>
Z
Z
5
<X 00 100
UNIT COST (MILLS / kWh)
200 300 400
-.. ----------------------------------------------------------
.... COST AND DEMAND FIGURE
II. ELECTRICAL ENERGY IN ALASKA EI-
"
P"
'" --. "
.'
.'
Ii",
---... ~ .. -.---"-.-""."--.... "-------_ ..... --".
ANNUAL HYDRO
ENERGY GENERATION: 288 kW
~. ________ ~. _______ ..-. _ .. __ . __ ' _____ • ____ ~~._. . ------,,0.._. _,____ .",_. __
I I. 5 t ,,-""
i
i
/---""'"''
HYDROELECTRIC ENERGY
AVAILABLE TO MEET
""'''''''''" ,,,,,·----HEATINGOEMANO -__ _
DIRECT ELECTRICAL DEMAND
(NOT INCLUDING HEATING DEMAND)
L.~.. -_ .... ~...~ .. ~ DIESEL··ENERGY REQUIRED TO MEET I DIRECT ELECTRICAL DEMAND ( NOT t-,,------------------------_______JNCL l,I01N G. _HE AI LN G OEM A"NO. L"",,, __ , __ _ ... -----------
1.0 r-· ......... ~ ......... ~ • ., ·~·.·~·~HYDROELE:;RIC ENERGY US~:··· ..... .
!" TO MEET ENERGY DEMAND (NOT ~---<11'-----, --------4NCLUOING HEATING DEMAND,·----"
i ~ INSTALLED CAPACITY = 288 kW) i ~~
_.
1980
YEAR
1990 2000 2010 2020 2030
DETAIL DATA
r--"~---------""---,,--.,-----,,--.,-,,_,, '''_''_' __ -.--",-. __ "_,,," __ .<C'. "---'> __ . __ '______.___------
i
I
20.0; ""
o
o o
-
15.0'
!
~-. ~ --_ ..
10.0 '
,
\----,,--
!
I
; r--"" '" --
t
~-,------
TOTAL COMBINED DEMAND",
ANNUAL HYDRO ENERGY GENERAT ION: 288 kW -" ---.. -, ,,------,,' -"-----,,-,"--,, """',,"",,,,',,---"----'''---''''------·--.. -----r-----''
j ~ .... ··--.... ·..COIRECTELECTRI"CAC DEMAND
(NOT INCLUDING HEATING DEMAND) ° :.-_._--------.-~-.,,--'.-~----~~--~~ 1980 1990 2000 2010 2020 2030
YEAR
OVERALL DATA
J
TOGIAK HYDROELECTRIC PROJECT FIGURE
PROJECTED ANNUAL ENERGY GENERATION, DEMAND, AND USAGE
INSTALLED CAPACITY = 288 kW
B-2
"
,
",
If'
p'
, .
"
Ii ..
.. :Ii
-o o o .. o o o
)-
(!)
a:: w
:3 ... -... -.. --.... -.-........ '' .............. -.. -........ -.... --.... -.. .
I ANNUAL ENERGY
! ENERGY GENERATION: 432 kW
..
i ,
~ -..
I
I ~ ...
i
HYDROELECTRIC ENERGY
AVAILABLE TO MEET
-HEATiNG DEMAND .------
DIRECT ELECTRICAL DEMAND
(NOT INCLUDING HEATING DEMAND)
DIESEL ENERGY REQUIRED to
MEET DIRECT ELECTRICAL
DEMAND ( NOT INCLUDING
HEATiNG DEMAND)--
HYDROELECTRIC ENERGY USED
TO MEET DIRECT ELECTRICAL
-.... _.' ..... -....... __ . _____ ._ .... .DEMAND. INSTALLED. .._ .. ____ .. _ .... _ ..... .
CAPACITY = 432 kW -_~
--o o o
~
o o o
-
20
10
• I
TOTAL COMBINED DEMAND
.. -.. . . -. ~ .. ,_.--,-.---.-~~. -,. ---.. ---.. ----,.---~---~--..
ANNUAL HYDRO ENERGY GENERATION: 432 kW
_w /; •• __ .,_ ___ _ _ '''_ .• ""'" ••• • ....... ~n __ ....................... _ .... _. __ ._. ____ .. ___ • __ .. _._ ...
_ •. _ .•• _ ~_ •.• __ •. ,,~.,_w .. ~ ___ ~ ___ • __ ""\'-__ -~. __ •• ___________ ,
~. 0 .... 1. ___________ ._-_. __ ~_ •• __ • __ ~ __ ~_. ______ .---"'___._ r= (NOT INCLUDING HEATING DEMAND) o L-... ____ ... _. _*' __ "'_» ____ U __ ' ___ '''''''_><' __ ·_'''._'__ ..
1980 1990 2000 2010 2020 2030 1980 1990 2000 2010 2020
YEAR YEAR
DETAIL DATA OVERALL DATA
TOGIAK HYDROELECTRIC PROJECT
PROJECTED ANNUAL ENERGY GENERATION, DEMAND, AND USAGE
INSTALLED CAPACITY = 432 kW
r &3S T
2030
FIGURE
B-3
"
,.~
,~
""
,.
",'
...
, .
,.
.. <
...
••
-o o o
270
240
210
180
150
120
60
30
J
HYDROELECTRIC POTENTIAL
HYDROELECTRIC ENERGY
AVAILABLE TO MEET
HEATING DEMAND
DIRECT ELECTRICAL DEMAND I \ . NOT INCLUDING HEATING DEMAND"
I \. ~t 2001 TO /" I '\ " r 2034 7 " ~,-""
(\' / 1990-Y ~
=.If \'--\ / /",-,/ /-.... ....;' '-, \ \ I /. /,,~~
REQUIRED 'DIESEL \\\/ 1/"/ 1985~
GENERAT iOl\! \ 200 I) V //
F M A
\\.,ij'
V
J I
\i A s o N o
1600
/400
/200
1000
~TOTAL COM81NED DEMAND
2001 TO 2034
800~ ,.... ~ '-'/ ~1990 /_ ~'../" 1985 j I,.... g 600 ~---"~ . /.J'/
:. 400 '" h~OTAL .&. ,~ /.. ~ ELECTRICAL ~ HYDROELECTRIC "". ~/ DEMSIA. N. D. .. POTENTIAL ._;;.;>'~",tf_~ ____ _
,. 200 1990 ~:.-.:;:::'/ ........... .
~ _-..-<: -~ .~_20or _----====>=; w -~ =====~~=_ .. _ .. :::;,_=-= ~ 0 . 1985· =-=--.<
J F ... AM J J AS 0 N U
MONTH MONTH
DETAIL DATA OVERALL DATA
TOGIAK HYDROELECTRIC PROJECT
PROJECTED MONTHLY ENERGY GENERATION, DEMAND, AND USAGE
INSTALLED CAPACITY = 432 kW
FIGURE
E[-4
-
-
-
....
.....
-
-
-
-
...
-
...
-
...
-
-
SECTION VIII
PROJECT COSTS
A. GENERAL
The basic assumptions and methodology used to analyze the
total projec-t cost of the three Togiak Hydroelectric Project
alternatives and a summary of unit prices are presented in this
section. A more detailed breakdown of the cost estimate
methodology is contained in Appendix D, Detailed Cost
Estimate. The appendix contains the backup data, including the
project construction schedules and manpower projections for
each alternative.
B. COST ESTIMATING BASIS
Several alternative methods of preparing cost estimates
were considered in preparing this feasibility study. The heavy
construction estimating method was determined to be the most
real ist ic in this case because of the nature and location of
the project .
The three alternatives studied for the Togiak Project are
Alternative A, a 38-foot concrete dam; Alternative B, a 28-foot
concrete dam; and Alternative C, a rockfill dam with a
spillway. Two methods of construction for the access road were
studied and a summary of the possible combinations of project
construction costs is presented in this section.
The approach taken to prepare the construction cost esti-
mate for each al terna t i ve was to determine the costs of the
required permanent materials and equipment, construction
equipment, and labor. Due to the location of the project site,
NBI-410-9521-VIII VIII-l
it was determined that all material and equipment would be
transported by barge. For the purposes of this estimate, the
material prices at Seattle, Washington, were determined.
Shipping costs by barge from Seattle to Togiak were used.
Material prices were based on estimating quotes by various
manufacturers; commercial barge transportation companies, based
at Seat tl e, prov ided shi pping: rate quotations for the
appropriate commodity classifications.
The skilled labor force was assumed to be brought in by the
con tractor.
benefi ts and
Current wages, based on union scale,
premium rates for overtime were used.
including
The con-
struction personnel will be housed in a construction camp set
up specifically for this project. Commercial firms that pro-
vide these services in Alaska were contacted for Quotes on the
cost 0 f this serv ice. The cost s used are based on a cost per
person-day. They are January 1982 prices that include setup
and demobilization.
Alaskan contractors were contacted for construction equip-
ment costs, which are current costs based on ownership, opera-
tion, and main tenance. Th is est imate al so assumes that the
equipment will be barged in from Seattle.
As support to the project, commercial air charter firms
provided current costs for various sized airplanes suitable for
transporting personnel and supplies.
A construction schedule was prepared to allocate manpower,
material, and equipment costs to each major construction cate-
gory. Allowances were made for associated miscellaneous
activities reQuired for completion of each item. The direct
construction cost was determined from the various costs
mentioned above. Along with the various backuD information,
NBI-410-9521-VIII VII 1-2
.. ..
• -
• ..
• -
• -• ..
• •
• -• .. ..
• .. --..
• -
• -
• -
• ., ----
• .,
-
.....
-
-
~
-
.-
-
,.,.
-
....
---
these costs are presented in the Summary of Costs, Tables D-6A,
D-6B, and D-6C of Appendix D .
C. BASE CASE PLAN
Detailed costs were not estimated for the base case plan
because that degree of refinement was not necessary. Costs of
major items are presented in Section IX, Economic Analysis.
D. RECOMMENDED PROJECT COSTS
A rigorous method of cost estimating, known as the heavy-
construction estimating method, was employed to define all
project tasks and then determine the time, materials, quanti-
ties, equipment, and skilled personnel required for each
task. Using up-to-date Alaskan data for skilled craft wages,
equipment ownership and use rates, and material and machinery
costs FOB Seattle, the major direct costs for the project --
project mobilization and transportation of materials, equipment
and labor, permanent material, and construction camp costs --
were determined.
The remote nature of the site will require that construc-
tion materials and equipment be barged from Seattle at the
outset and be returned to Seattle by the same means after
project completion. Barge costs are based on weight and type
of commodi ty. Personnel and supplies will be transported by
air.
It was assumed that the crew will be housed in a catered
construction camp for the duration of the project. Camp costs
were based on a fixed unit cost per man-day of accommodation.
The camp will be large enough to accommodate necessary fluctua-
tions in the size of the work force .
NBI-410-9521-VIII VIII-3
Subcontracted items included in the estimate are for
construction of the transmission line and moving the turbine-
generator assembly into place in the powerhouse. A 15 percent
contingency factor was applied to direct construction costs,
incl ud ing the subcontracts, except for the transmission 1 ine
subcontract which includes a 10 percent contingency. A 10
percent markup by the prime contractor for handling and over-
head was applied to the transmission line subcontract. The
prime contractor's profit was assumed to be 15 percent and was
applied to all construction costs except the transmission line
subcontract. Engineers' fees for surveying, right-of-way,
geology, design, and construction management were included.
The legal and administrative costs borne by APA were set at
three percent of the direct plus indirect costs.
Un it pr ices for the major componen ts of the construction
work and the indirect costs are presented in Table VII1-1.
Total capital costs of the three Togiak Hydroelectric Project
alternatives are summarized in Table V111-2.
NB1-410-9521-V111 VII 1-4
• •
•
•
• -• -•
• .. ..
• •
• ...
• ..
•
• ... --
-
• ..
• ...
• -..
.,
• -
• -
.....
,,"'" TABLE VIII-1A
TOGIAK --38-FT CONCRETE DAM ALTERNATIVE
~'''''-
CONSTRUCTION COST
Unit
Item Quantit~ Unit Price Amount
Mobilization LS $ $ 521,010 ,...
Access Road
Excavation, Rock 3,000 CY 57 172,500 -Dam
Cofferdams 2,500 CY 91 226,460
~ Bypass Line -8' Dia. 200 LF 797 159,370
Foundation Treatment 300 SY 146 43,920
Concrete 2,375 CY 454 1,077,230
Reinforcing Steel 3,000 LB 1. 73 5,170 -Fish Ladder 20 CY 690 13,800
Trim (Rock Exc. ) 325 CY 57 18,690
$1,544,640
" ... Intake
Trashrack 1 EA 5,750 5,750
Slide Gates 8' 2 EA 52,490 104,980
7Jd $ 110,730
.... Bypass Pumping -Discharge Line 60" 330 LF 401 132,490
Pumping 5 WK 40,988 204,940
$ 33'1,430 -Penstock
5' Dia. Line 40 LF 1,427 57,070 -Excavation, Rock 100 CY 57 5,750 -$ 62,820
Powerhouse
Excavation, Rock 200 CY 55 11 ,030 .. Concrete 83 CY 690 57,270
Reinforcing Steel 9,000 LB 1. 73 15,520
Building Construction LS 55,730 .. Turbine and Generator LS 676,200
Auxiliary Systems LS 217,940
$1,033,690 -Transmission Line 13 MI 94,171 $1,224,230
SUBTOTAL $5,007,050
II1II
,,.. -NBI-410-9521-7-1A
-
TABLE VIII-1A (Continued)
Item
(SUBTOTAL)
Contingencies -15%
(Excluding Subcontract
Portion of Transmission
Line)
Contract Cost
Engineering
Right-of-Way and Geology
Design
Construction Management
Owner's Legal and Administrative
TOTAL PROJECT COST
NBI-410-9521-7-1A
Amount
$5,007,050
591,550
$5,598,600
$ 100,000
435,000
215,000
190,400
$6,539,000
• ..
•
• -
•
• ..
•
•
• ..
• •
• .. ---.. -.. -•
• ..
• -
• ..
• ..
.,.
TABLE VllI-1B
,-TOGIAK --28 -FT CONCRETE DAM ALTERNATIVE
CONSTRUCTION COST
-Unit
Item Quantit~ Unit Price Amount -Mobilization LS ~ $466,180
Access Road
Excavation, Rock 3000 CY 57 $172,500 -
Dam
Cofferdams 2500 CY 91 226,460 ,-Bypass Line --8-Foot-Diameter 200 LF 797 159,370
Foundation Treatment 280 SY 157 43,920
Concrete 1,560 CY 595 921,780 -Reinforcing Steel 3000 LB 1. 73 5,170
Fish Ladder 20 CY 690 13,800
Trim (Rock Excavation) 325 CY 57 18 2 690
' ... $1,389,190
Intake
..... Trashrack 1 EA 5750 5,750
Slide Gates 8 Foot 2 EA 52,490 104!980
$ 110,730 -Bypass Plumping
'-Discharge Line 60 Inches 330 LF 401 132,490
Pumping 5 WK 40,988 204 2 940 .. $ 337,430
Penstock
5 Inch Diameter Line 30 LF 1571 47,120 -Excavation, Rock 100 CY 57 5!750 -$52,870
.... Powerhouse
Excava tion, Rock 200 CY 55 11,030 -Concrete 83 CY 690 57,270 -Reinforcing Steel 9,000 LB 1. 73 15,520
Building Construction LS 55,730
Turbine and Generator LS 650,100
Auxiliary Systems LS 209!530 -999,180
Transmission Line 13 ~I 94,171 $1,224,230
.... Subtotal $4,752,310
--
NBI-410-9521-7-1B -
Item
Transmission
Contingencies -15%
TABLE VIII-1B
(Continued)
Subtotal
(Excluding Subcontract Portion
of Transmission Line)
Contract Cost
Engineering
Right-of-Way and Geology
Design
Construction Management
Owner's Legal and Administrative
TOTAL PROJECT COST
NBI-410-9521-7-1B
Amount
$4,752,310
553,290
$5,305,600
100,000
435,000
415,000
181 2 700
$6,237,300
• •
• ..
• -
• -
• -• .. .. -• •
• ..
• .. .. ---.. -
• -
• -
• ..
• .. --.. -
...
.. TABLE VIII-1C
TOGIAK ROCKFILL DAM ALTERNATIVE ...
CONSTRUCTION COST
-Unit
Item Quantity Unit Price Amount
Mobilization LS $ $514,720 ....
Access Road
Excavation, Rock 3,000 CY 18 53,700
Wii!JiII Dam
Cofferdams 2,500 CY 40 98,930
Bypass Line, 8' Dia. 300 LF 787 236,220
Foundation Treatment 1,100 SY 64 70,220 .-Trim (Rock Exc.) 325 CY 18 5,820
Conc. Membrane and Toe Slab 280 CY 1,539 430,850
Reinforcing Steel 32,200 LB 1. 73 55,540 -Rockfill 11,550 CY 40 457,100
Steel Cribbing 75,300 LB 1. 03 77,830
$1,432,510 -Intake
Slide Gate -8' Dia. 2 EA 22,580 45,160
Slide Gate W/Hoist -8' Dia. 1 EA 56,440 56,440
Slide Gate W/Hoist -5' Dia. 1 EA 45,160 45,160
Trashrack 2 EA 9,028 18,060
Concrete 10 CY 1,628 16,280
$ 181,100 ....
Bypass Pumping
Discharge Line 330 LF 383 126,240
Pumping 2 WK 62,531 125,060 .. $ 251,300 -Penstock
5' Dia. Line 93 LF 1,177 109,490 -Excavation, Rock 300 CY 18 5,370
Concrete 10 CY 1,628 16,280
$ 131,140 -Spillway
Excavation, Rock 14,850 CY 18 265,820 .... Concrete 71 CY 1,539 109,250 -Reinforcing Steel 8,165 LB 1. 73 14,090
$ 389,160
Powerhouse -Excavation, Rock 200 CY 18 3,580
Concrete 83 CY 1,539 127,720
Reinforcing Steel 9,545 LB 1. 73 16,470 -
-NBI-410-9521-7-1C
-
TABLE VI II-1C
(continued)
Item Quantity Unit
Unit
Price
Powerhouse (Cont'd)
Building Construction
Turbine and Generator
Auxiliary Systems
Miscellaneous Fish Ladder
Transmission Line
Contingencies -15%
(Excluding Subcontract Portion
of Transmission Line)
Contract Cost
Engineering
Right-of-Way & Geology
Design
Construction Management
Owner's Legal and Administrative
20
13
LS
LS
LS
CY 1,628
MI 94,171
SUBTOTAL
TOTAL PROJECT COST
NBI-410-9521-7-1C
Amount
58,420
676,450
218,040
$1,100,770
$ 32,570
$1,224,230
$5,311,200
637,100
$5,948,300
$ 100,000
460,000
290,000
202,500
$6,950,800
• .,
•
-..
•
•
• -
• -•
• ..
• •
• .. ----
• ---
• -
• -
• -
• -
• -
-
-
,-Project
Alternative
A. 38-Foot Concrete
B. 28-Foot Concrete -C Rockfill Dam
....
.....
-
-
---
-
-NBI-410-9521-8-2
TABLE VIII-2
TOGIAK POWER PROJECT
SUMMARY OF CONSTRUCTION COSTS
WITH ROAD ALTERNATIVES
Total Cost
Site with 4.6 Mile
Construction Road
Cost $508,200
Dam $6,539,000 $7,047,200
Dam 6,237,300 6,745,500
6,950,800 7,459,000
Total Cost
with 11.6 Mile
Road
$1,630 ,600
$8,169,600
7,867,900
8,581,400
-
-
-
-
-
-
-
SECTION IX
ECONOMIC ANALYSIS
A. GENERAL
The economic parameters and methodology used to analyze the
economic feasibility of the Togiak Power Project and the
resul ts of the analysis are presented in this section. The
methodology and criteria used for this analysis are in accord-
ance with the standards set forth by APA. The present worth of
the total costs of the base case as developed in Section VII is
compared to the present worth of the total costs of the pro-
posed hydroelectric project in order to determine the more
advantageous scheme for development. Based on the analyses,
one of the hydroelectric alternatives appears to have marginal
economic feasibility.
B. PROJECT ANALYSIS PARAMETERS
The assumptions that form the basis for this analysis are
founded to as great an extent as possible on the APA standard
criteria. Wherever necessary, additional assumptions were
based on the best available information and on experience.
The data previously developed in Section VII, Project
Energy Planning, and Sect ion VI I I, Project Costs, are exten-
sively utilized in this analysis.
The planning period and the economic evaluation period both
begin with January 1982. The hydroelectric project is assumed
to be on-line by January 1985, and the analysis extends 50
years beyond this time. The last year of the analysis is 2034
and the length of the evaluation period is 53 years. The plan-
NBI-410-9521-IX IX-1
ning period for meeting future demands assumes a leveling of
growth in 20 years, and it includes the year 2001.
For purposes of this analysis, a no-inflation environment
was assumed. The values of diesel fuel and lubricating oil
were escalated at 2.6 percent annually to account for the esca-
lation of oil prices at a rate greater than inflation. The
values were escalated for the duration of the planning period,
with the last escalation occurring in the year 2001. The costs
were held constant at the 2001 value for the remainder of the
period of economic evaluation through 2034.
The discount rate for present worth analysis was assumed to
be three percent. All costs were annualized and discounted to
January 1982. The interest rate for all amortization and sink-
ing funds was assumed to be three percent.
are in accordance with the APA criteria.
These assumptions
The economic life of the hydroelectric project was assumed
to be 50 years. The economic project life for diesels was
assumed to be 20 years for the base case and 30 years for the
hydroelectric alternative; the diesels were given a longer life
for the hydroelectric al ternative because they would operate
significantly less than they would for the base case.
Operation and maintenance costs were assigned to the year
during which they would occur.
Capital costs were assigned to the year in which they would
occur. They were assumed to be equal to the total investment
cost because the construction periods for all items included in
the analysis were less than one year. Thus no interest during
construction was included. The first amortization payment was
shown in the year following the capital cost.
NBI-410-9521-IX IX-2
• ..
.,
., ..
• -.. -
•
•
• •
• ..
• • -
• ..
• -
• -• -.. -
• .. .. -.. -.. -
-
.-
-
-
-
-
-
-
-
--
Amort iza t ion costs, operation and maintenance costs, and
benefits were assumed to occur at the end of the year and were
shown in the year that they actually occurred.
Replacement costs were handled by the use of a sinking
fund. Replacement sinking funds were assumed to occur in per-
petuity.
All costs that were common to all plans, such as local
distribution costs, were excluded. An underground rural
distribution cable would be placed across Togiak Harbor to con-
nect Twin Hills to the Togiak system, at a cost of about
$300,000; however, since this cost would be common to all
cases, it was not considered.
The effects of installing waste heat recovery, and the
benefi t obtainable form wind genera t ion were considered
separately and were applied as a reduction in cost to the base
case. The benefit for space heating use for the alternative
hydroelectr ic cases also was treated separately, and was con-
sidered to be a benefit.
C. BASE CASE ECONOMIC ANALYSIS
The base case plan was originally formulated as a continua-
tion of the existing diesel system supplemented by waste heat
recovery. This plan was later modified to include wind genera-
tion. The base case as originally formulated is presented
below, and is followed by the wind energy analysis.
NBI-410-9521-IX IX-3
1. Original Plan
The base case plan was analyzed to determine the present
worth of the total cost of the base case plan over the entire
period of analysis. The cost of the base case plan would be
the sum of the costs of replacing and expanding the existing
diesel generation system, insurance, operation and maintenance,
lubrication oil, and fuel oil. These costs were all assigned
to the year of their occurrence, and the total annual cost of
the existing system was calculated for each year of the period
of economic evaluation. These annual costs were then discount-
ed at three percent interest to January 1982. They were then
summed to find the total present worth of the base case alter-
native.
The costs of replacing and expanding the plant were assumed
to cover amortization on a new plant every 20 years, with the
first replacement occurring in 15 years. The cost of replace-
ment was taken as $950,000. This cost is consistent wi th the
current market. The plant has a firm capcity of 460 kW (the
largest unit is omitted in calculating firm capaci ty); this
will be increased to 600 kW in 1996. The peak power demand for
2001 as determined in Section VII of this report is 333 kW;
therefore, the firm capacity assumed for this analysis is con-
servative.
The cost of insuring the power
$0.83 per $100 of replacement value.
rent insurance rates for Alaska.
assumed to have a replacement value
plant was assumed to be
This rate represents cur-
The existing plant was
of $800,000 and it was
treated as a sunk cost for all cases. If it were desired to
develop average unit costs representative of total costs in
earlier years, an assumption wi th regard to fixed charges on
the existing plant would need to be made.
NBI-410-9521-IX IX-4
.. .. .. -• -
• •
• -• ..
II
• ...
• •
• ..
-
• ..
• -• ..
• --lit
• ... .. -
-
-
-
.-
-
-
-
-
-
-
---
-
The costs of operation and maintenance reflect experience
and they were assumed to be the sum of the maintenance cost,
calculated as $17 per megawatt-hour of energy produced, and the
cost of an operator, which was taken as $60,000 per year.
The total cost of lubrication oil was calculated from the
unit cost of lubrication oil and the amount of lubrication oil
required. The lubrication oil rate of use was assumed to be
0.60 gallons per megawatt-hour and the cost of lubrication oil
was assumed to be $3.95 per gallon for January 1982. The cost
of 1 ubrica tion oil was also escalated at 2.6 percent for the
duration of the planning period to be consistent with treatment
of all petroleum products .
The total cost of fuel oil was calculated from the cost per
gallon of fuel oil and the anticipated rate of fuel oil con-
sumpt ion. The average energy val ue of fuel oi 1 was taken as
138,000 Btu/gallon and the average overall efficiency of the
diesel generators was assumed to be 22 percent; using these
criteria, one gallon of oil will produce 9.0 kWh of electric-
ity. The fuel oil cost for Togiak was established at $1.55 per
gallon for January 1982 and escalated according to the pre-
viously mentioned criteria for real price changes.
The annual costs over the project economic study period of
the base case diesel generation for operations and maintenance,
lubrication oil, and fuel oil are presented in Tables IX-1, IX-
2 and IX-3, respect i vely, and combined in Table IX-4 to show
the annual cost for the base case for each year of economic
evaluation.
After the annual cost of the base case plan was calculated,
the savings possible from waste heat recovery were estimated.
The total amount of heat available annually for recovery would
be approximately equivalent in heat output to twice the amount
of electrici ty generated annually by the plant. Waste heat
NBI-410-9521-IX IX-5
recovery at Togiak would be from the cooling water jackets, the
oil cooling system, and from the exhaust gases. Waste heat
recovery is addressed in greater detail in Section VII of this
report. The total waste heat available from the cooling water
jackets and oil cooling system would be about equal to the
electrical output of the generator.
of the heat is recoverable. An
Of this amount, almost all
additional equal amount of
waste heat is available from the exhaust heat;
about 40 percent of this heat is recoverable.
however, only
Only about 60
percent of the total recoverable waste heat would have an end
use in 1982 as marketable heat because of beat generated during
the summer when it is not needed for such inst i tut ional users
as the school. The increase in total generation and total
demand over the planning period was assumed to result in an
annual growth rate for the amount of usable waste heat of about
1.5 percent. The percentage of usable waste heat and the
growth rate in the amount of usable waste heat are based on
recent experience wi th projects of this nature in Alaska.
Data for installations of this nature are scarce, and accurate
pred ict ions are d ifficul t to make. The values presented here
are conservative.
The costs associated with waste heat recovery are the cost
of installation and the costs of operation and maintenance.
The installation cost includes the cost of the equipment in the
powerhouse, the cost of insulated, buried pipes from the power-
house to the point of use, and the cost of installing radiators
at the points of use. The waste heat recovery equipment for
heat recovery from the hot exhaust gases would have to be
replaced every 10 years. The rest of the equipment in the
powerhouse would require replacement when the diesel engines
are replaced. The remainder of the equipment for waste heat
recovery would not need to be replaced for the entire period of
economic evaluation. The heat would be avaialble for use up to
2000 feet from the power plant.
NBI-410-9521-IX IX-6
• •
• •
• ..
• •
• -• •
• ..
• -• .. .. ..
• ..
• -• •
• ..
• ..
• ..
• -• •
•
....
....
....
,iOIIlI
.. ~
.....
.. II
.11
.....
The initial cost of the waste heat recovery system would be
$325,000, and the replacement cost would be about $200,000
every time the diesel engines are replaced, plus about $120,000
for the interim replacements of the exhaust heat recovery
equipment. The schedule of replacement costs for the waste
heat recovery equipment is presented as Table IX-5. The opera-
tion and maintenance of the system would be very minimal and
probably would not exceed $1,000 per year. Using these data,
the annual waste heat recovery costs are presented in Table
IX-6.
The annual savings realizable from waste heat recovery for
each year of operation were calculated as a credit for the oil
displaced by waste heat recovery. The resul t was reduced by
the annual costs from Table IX-6 to yield an annual savings
stream for the project, as presented in Table IX-7 .
The annual base case diesel generation costs and present
worth of these costs are presented in Table IX-8 along with the
waste heat recovery savings and the present worth of the sav-
ings. As shown, the total January 1982 present worth of the
costs of the base case would be $11,027,600 and the present
worth of the waste heat recovery savings would be $997,800
yielding a net present worth of the base case costs of
$10,029,800 .
2. Wind Generation Plan
The possibility of installing wind-powered generators as
part of the base case was also considered. Wind powered
generation is discussed in detail in Section VII, including
installed capacities and energy generation.
The benefi ts attributable to wind generation would be a
reduction in the amount of fuel consumed by the diesel genera-
tors, and a slight decrease in the lubrication and maintenance
NBI-410-9521-IX IX-7
costs associated with the diesel generation. These costs are
summarized in Tables IX-lA, IX-2A and IX-3A, which are included
behind Table IX-36. These tables are combined in Table IX-
4A. The costs of install ing, replacing, and maintaining the
diesels would not be affected by the addition of wind genera-
tion because the full standby diesel capacity would always be
required, the diesels would not have enough reduction in opera-
tion to increase their useful 1 i ves, and the operator would
receive the same salary regardless of how often the diesels
operate.
The cost of 10 kW wind turbines and generators was assumed
to be $34,000 each, installed. The operation and maintenance
cost for the wind turbines was assumed as five percent of the
capital cost. The wind turbines were assumed to have a useful
life of 15 years. A summary of costs associated with this
installation is presented as Table IX-5A.
The credits for reduction in diesel generation were then
adjusted by the cost of wind generation to yield the annual
credi t at tainable from wind generation. This credit was dis-
counted to January 1982 at three percent interest. The present
worth of the wind generation credit is $540,700. This present
worth is summarized in Table IX-6A.
D. ALTERNATIVE HYDROELECTRIC PROJECT ECONOMIC ANALYSES
The al ternative hydroelectric project plans were analyzed
to determine the present worth of the total cost of the alter-
na ti ve proj ects over the period of economic eval ua tion. The
cost of the projects would include the costs of building,
replacing, operating and maintaining the new hydroelectric
development and the costs associated with replacing and expand-
ing the existing diesel system, including insurance, operation
and maintenance, lubrication oil, and fuel oil for the diesel
system. It would be necessary to maintain sufficient diesel
NBI-410-9521-IX IX-8
.. .. .. .. .. ..
• ..
• .. .. .. .. ..
•
a
• ..
• ..
• • ..
.. ..
• .. .. .. .. ..
• .. .. .. .. ..
...
....
....
...
...
...
.,.
.... ,
....
••
.....
capaci ty to meet projected power demands in the event of an
outage of the hydroelectric plant. This has been previously
discussed in Section VII and it is illustrated in Table IX-
12. The diesel capaci ty would also be required at times when
the demand on the system is greater than can be met by the
hydroelectric generation.
The cost of the diesel supplement to hydroelectric genera-
tion was calculated in the same manner as for the base case,
with the following differences: the diesels supplied only the
demand that could not be met by the hydroelectric plant; the
plant would be replaced every 30 years instead of 20 years
after the initial replacement in 15 years; only one-half of the
operator's salary would be assigned to the cost of the diesel
after the plant goes on-line in 1985, the other half being
assigned to the hydroelectric project; and the diesels would
not operate often enough to justify waste heat recovery.
A total of three al ternative hydroelectric projects were
considered at Togiak: Al terna ti ve A, a concrete dam wi th an
installed capacity of 432kW; Alternative B, a concrete dam with
an installed capacity of 288kW; and Alternative C, a rockfill
dam with an installed capacity of 432 kW.
The procedures and resul ts of the economic eval ua tion are
presented below for Alternative A. Alternative A appears to be
the most attractive of the three potential hydroelectric proj-
ects. The analysis of Alternatives Band C was similar to the
analysis of Alternative A, and information regarding these two
alternatives is included in the tables at the end of this
section .
The annual costs over the project economic study period of
the supplemental diesel system for the al terna ti ve hydroelec-
tric project for operation and maintenance, lubrication oil and
fuel oil are presented in Tables IX-9, IX-10, IX-11, respec-
NBI-410-9521-IX IX-9
tively. These costs are combined in Table IX-12 to present the
annual cost for the supplemental diesel generation for each
year of the economic evaluation. These costs are applicable to
Al terna t i ves A & C; the diesel costs associated wi th Al terna-
tive B are presented in Tables IX-17 through IX-20. These
costs were all calculated using the previously stated criteria.
The capital cost of $6,539,000 for the hydroelectric power
plant was amortized at three percent over a period of 50 years
from the on-line date of the power project. The cost of the
operation and maintenance was taken as 1.5 percent of the con-
tract cost; this is based on U.S. Bureau of Reclamation
practice.
Two replacement costs were considered for the hydroelectric
power plant: the cost of replacing the turbine runner after 25
years of operation, and the cost of replacing the transmission
line that would tie the plant to the village distribution
system every 30 years. The economic life of transmission lines
was established based on experience with similar projects in
Alaska. The cost of replacing the runner was estimated as
$135,000, and the cost of replacing the lines was estimated as
$1,224,200. Sinking funds were established to meet these
costs.
The annual costs of the hydroelectric portion of the Alter-
native A plan are presented in Table IX-13. This table
includes the amortization, operation and maintenance, and
replacement costs. These costs are then combined with the
annual costs for the supplemental diesel system from Table IX-
12 and presented as the combined diesel and hydroelectric costs
in Table IX-14. The similar costs for Al ternative C are pre-
sented in Tables IX-15 and IX-16 and for Alternative B in
Tables IX-21 and IX-22. The present worth of the annual cost
of each project is presented as Table IX-23.
NBI-410-9521-IX IX-10
• -.. -.. -.. ..
• ..
• .. .. ..
• •
• ..
•
III .. ..
• -.. ..
• ..
•
..
III .. -• • .. -
.,
....
....
....
...
....
....
-
-
-
-
-
-
-
The proposed hydroelectric power plant would also generate
power in excess of the village's direct demand during certain
times of the year. Any excess hydroelectric energy could be
used for space heating in the village. The d istr ibution of
hydroelectric generation is addressed in Chapter VII .
The space heating energy available from hydroelectric gen-
eration would be equivalent to one gallon of oil for every 28.3
kWh of available electricity. This conversion factor is based
on an average ener!!y value for fuel oil of 138,000 BTU/gallon
and 70 percent efficiency. The values used for the demand for
energy for space heating are from Tables VII-9A to VII-9E and
VII-lOA to VlI-10E.
The use of electrici ty for space heating would be con-
trolled automatically in order to take advantage of as much
excess electricity as possible . The system design and cost
estimate are included as Appendix G.
The annual savings for the hydroelectric energy used for
space heating for each alternative are presented in Tables IX-
24 and IX-25. These tables indicate the annual hydroelectric
energy available for the heat demand, the equivalent amount and
cost of the fuel oil displaced, annual cost of the electric
space heating, and the resulting net annual savings. The
present worth of these savings is presented in Table IX-26.
The present worth of the space heating credit would be
$2,463,000 for Alternatives A and C and $1,234,800 for Alterna-
tive B.
The hydroelectric project would require the construction of
a road regardless of which alternative is selected. The total
length of the road would be 11.6 miles. The first seven miles
of road could be used as access to a gravel borrow area; this
gravel could be used for airport construction, and it might be
possible to build part of the road in conjunction with the air-
NBI-410-9521-IX IX-11
port improvements. In either case, maintenance of the road
would be associated with the hydroelectric project. A summary
of the road costs is presented as Table IX-27.
E. ECONOMIC COMPARISON OF PROJECTS
The base case plan and the alternative hydroelectric proj-
ects can be compared on the basis of the present worth of costs
associated with each plan. All plans were formulated to
satisfy the same energy demand, and the plan having the lowest
present worth of costs would be the most advantageous plan for
development.
In addition to costs of diesel generation and costs
associated with the hydroelectric project, costs and benefits
from waste heat recovery, wind energy, and space heating were
also considered. For purposes of determining the relative
economic merit of each hydroelectric project, the costs of each
hydroelectric project, including supplemental diesel genera-
tion, were considered separately from all other costs. The
cost of the base case was considered to be a benefi t. The
savings from waste heat recovery and wind energy were applied
as reductions to this benefit. The credits for the space heat-
ing were added to the benefit. A summary of present worths of
benefits and costs is presented as Tables IX-28, IX-29, and IX-
30. Alternative A appears to be the most attractive project of
the al terna ti ve hydroelectr ic projects. The present worth of
benefits associated with this project, as shown in Table IX-28,
would be $11,950,500. This compares to a present worth of
costs of $11,668,600 with the cost of the 4.6 mile road includ-
ed, or $12,758,400 wi th the cost of the 11. 6 mile road. The
project is marginally feasibile if the first seven miles of the
road are built as part of the airport reconstruction. The
benefit/cost ratio for Alternative A would be 1.024 with the
4.6 mile road and 0.937 with the 11.6 mile road. Benefit/Cost
NBI-410-9521-IX IX-12
--
• ---
• -
• ..
• ..
• ..
• ..
• ..
• ..
.. .. .,
• ..
• ..
• .. .. .. .. ..
• .. .. -
-
ratios for all three al ternatives are presented in Tables IX-
31, IX-32, and IX-33.
F. UNIT COSTS AND PROJECT TIMING
-As requested by APA, the unit energy cost of the base case
-
-
-
-
-
-
-
-
and the Al ternative A hydroelectric project plans were
calculated on an annual basis. These values are presented as
Tables IX-34, IX-35, and IX-36 and are shown graphically on
Figure IX-1.
The optimum timing for project development would occur when
the unit cost of the exist ing system exceeds the unit cost of
the proposed hydroelectric project. Because actual costs are
important for this comparison, the waste heat recovery and wind
energy credits were associated with the base case and consider-
ed to be reductions in cost, while the the space heating
credits were considered as reductions in the cost of the hydro-
electric project. The costs of the two schemes are shown with
and without adjustments.
Inspection of Figure IX-1 reveals a number of discontinu-
i ties. These discontinuities are due to large changes in the
net annual cash flow of each configuration that are caused by
capi tal expenses or increases in generating capacity. A dis-
continuity showing an increase in the unit cost of energy
indicates that the annual cost of a capital expenditure exceeds
the annual value of the increase in generation, if any, result-
ing from that cost. This type of discontinuity normally
accompanies a major investment, such as installation of a
hydroelectric facility or expansion of diesel plant capacity;
this type of discontinuity would also accompany expenses assoc-
ia ted with the power system that do not result in increased
generation, such as construction of fuel storage facilities.
NBI-410-9521-IX IX-13
Downward discontinuities on Figure IX-1 indicate expendi-
tures that result from an annual increase in generation having
grea ter value than the annual cost of the increase. This
si tua tion resul ts from the installation of conservation
methods, such as waste heat recovery.
The general downward sloping trend of the unit cost of the
various levels of the hydroelectric project are the result of a
gradual increase, over time, of the amount of hydroelectric
energy that can be used. These lines ind ica te an advantage
associa ted with hydroelectric projects; al though the ini tial
cost of a project of this nature is high, the variable annual
costs are low.
The general upward trend of the base case unit annual cost
is the result of the increase in total demand for electricity
and the increase in the cost of oil. For the base case plan,
increasing demand must be met primarily by diesel generation,
giving this plan a high variable annual cost.
All plans considered have the same unit cost for 1981 and
1982; the first discontinuity in Figure IX-1 occurs at the end
of 1982. The hydroelectric costs jump upward due to the cost
of road construction and the base case costs move downward due
to installation of waste heat recovery and wind generation.
The hydroelectric project costs jump upward again in 1984 with
the construction of the hydroelectric project.
After the hydroelectric project comes on line in 1985, the
costs associated with the hydroelectric project decrease due to
increased usage of hydroelectric generation while the diesel
costs increase due to increased cost of diesel generation. The
cost of all plans jumps upward in cost in 1996 when the exist-
ing diesel system would be replaced and expanded. All of the
plans reflect an addi tional increase in cost in 2001 that is
caused by the construction of new fuel storage facilities. The
NBI-410-952l-IX IX-14
• ..
• --..
• ..
• ..
• ..
• •
• ..
• ..
• ..
• ..
• -
• ..
• -
• ..
• -• -
• ..
• -
-
-
-
-
-
.-
-
-
.-
'"'"
-
-
-
-
-
cost of the base case al ternative including wind generation
jumps downward in 1998 when the wind generating capacity is
increased. The decrease in the cost of the plans including
waste heat recovery that occurs in 2005 is due to the differ-
ence between the replacement schedule for the diesel engines
and the economic lives assigned to the different components of
the waste heat recovery system; see Table IX-5.
Inspection of Figure IX-1 indicates that the project is
marginal and would be viable for development only if the cost
of seven mi les of the access road can be associated with the
airport reconstruction. The project would become viable for
development by 1995.
NBI-410-9521-IX IX-15
-
-
-
-
-
"'"
.....
-
-
.-
,' ...
-
-
-
-
Year
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002-34
TABLE IX-1
BASE CASE
DIESEL OPERATION AND MAINTENANCE COSTS
TOGIAK
Annuall.!
Energy
Production Maintenance2/ Operation3/
(1000 kWh) ($) ($) -
789 13,400 60,000
823 14,000 60,000
858 14,600 60,000
892 15,200 60,000
919 15,600 60,000
945 16,100 60,000
972 16,500 60,000
998 17,000 60,000
1,025 17,400 60,000
1,051 17,900 60,000
1,077 18,300 60,000
1,103 18,800 60,000
1,129 19,200 60,000
1,156 19,700 60,000
1,182 20,100 60,000
1,208 20,500 60,000
1,234 21,000 60,000
1,260 21,400 60,000
1,286 21,900 60,000
1,314 22,300 60,000
1,314 22,300 60,000
1/ From Table VII-11.
Cost
($)
73,400
74,000
74,600
75,200
75,600
76,100
76,500
77,000
77,400
77,900
78,300
78,800
79,200
79,700
80,100
80,500
81,000
81,400
81,900
82,300
82,300
2/ $17 per megawatt-hour. Values rounded to nearest $100.
3/ $60,000 for operator.
NBI-410-9521-IX-1
Annuaill
Energy
Production
Year (1000 kWh)
1982 789
1983 823
1984 858
1985 892
1986 919
1987 945
1988 972
1989 998
1990 1,025
1991 1,051
1992 1,077
1993 1,103
1994 1,129
1995 1,156
1996 1,182
1997 1,208
1998 1,234
1999 1,260
2000 1,286
2001 1,314
TABLE IX-2
BASE CASE
DIESEL LUBRICATION OIL COSTS
TOGIAK
Lubricatiou.V Lubrication...Y
Oil Oil Cost
(gallons) ($/gallon)
473 3.95
494 4.05
515 4.16
535 4.27
551 4.38
567 4.49
583 4.61
599 4.73
615 4.85
631 4.98
646 5.11
662 5.24
677 5.37
694 5.51
709 5.66
725 5.81
740 5.96
756 6.11
772 6.27
788 6.43
2002-
2034
1/
2/
3/
4/
1,314 788
From Table VlI-11.
0.6 gallons per megawatt-hour.
Cost escalated at 2.6% annually.
Values rounded to nearest $100.
NBI-410-9521-IX-2
6.43
• ..
• .. ----
•
Lubrication.!! ..
Oil Cost
($) lilt
•
1,900 • 2,000
2,100 •
2,300
2,400 •
2,500 ..
2,700
2,800 •
3,000 ..
3,100
3,300 ..
3,500 ..
3,600
3,800 ..
4,000 • 4,200
4,400 •
4,600 • 4,800
5,100 • ..
5,100
• ..
• ..
• ..
•
III
• ..
• -
-
,til
.~-
-
.,.,
...,
, ....
,..,
-
-
--..
' ... --..
TABLE IX-3
BASE CASE
DIESEL FUEL OIL COSTS
TOGIAK
Annua1.ll
Equivalen21 Fuel l! FueL!! Energy
Production Oil Oil Cost Oil Cost
Year (1000 kWh) (gallons) ($/gallon) ($) --
1982 789 87,700 1.55 135,900
1983 823 91,400 1.59 145,300
1984 858 95,300 1.63 155,300
1985 892 99,100 1.67 165,500
1986 919 102,100 1. 72 175,600
1987 945 105,000 1. 76 184,800
1988 972 108,000 1. 81 195,500
1989 998 110,900 1.86 206,300
1990 1,025 113,900 1.90 216,400
1991 1,051 116,800 1.95 227,800
1992 1,077 119,700 2.00 239,400
1993 1,103 122,500 2.06 252,400
1994 1,129 125,400 2.11 264,600
1995 1,156 128,400 2.16 277,300
1996 1,182 131,300 2.22 291,500
1997 1,208 134,200 2.28 306,000
1998 1,234 137,100 2.34 320,800
1999 1,260 140,000 2.40 336,000
2000 1,286 142,900 2.46 351,500
2001 1,314 146,000 2.52 367,900
2002-34 1,314 146,000 2.52 367,900
From Table VII-11. 1/
2/ 111.1 gallons per megawatt-hour.
gallons.
Rounded to nearest 100
3/
4/
Cost escalated at 2.6% annually.
Values rounded to nearest $100 .
NBI-410-9521-IX-3
I •
TABLE IX-4
BASE CASE
DIESEL COSTS
TOOIAK
Schedule ofY
Annua~ Operation!!
Lubricatiot2! Fueill Firm Replacement
Insuranct2!
and Annual
Capacity Investments Costs Maintenance Oil Oil Diesel Cost
Year (kW) ($) ($) ($) ($) ($) ...J.!L ($)
1982 460 6,600 73,400 1,900 135,900 217,800
1983 460 6,600 74,000 2,000 145,300 227,900
1984 460 6,600 74,600 2,100 155,300 238,600
1985 460 6,600 75,200 2,300 165,500 249,600
1986 460 6,600 75,600 2,400 175,600 260,200
1987 460 6,600 76,100 2,500 184,800 270,000
1988 460 6,600 76,500 2,700 195,500 281,300
1989 460 6,600 77,000 2,800 206,300 292,700
1990 460 6,600 77,400 3,000 216,400 303,400
1991 460 6,600 77,900 3,100 227,800 315,400
1992 460 6,600 78,300 3,300 239,400 327,600
1993 460 6,600 78,800 3,500 252,400 341,300
1994 460 6,600 79,200 3,600 264,600 354,000
1995 460 6,600 79,700 3,800 277,300 367,400
1996 600 950,000 6,600 80,100 4,000 291,500 382,200
1997 600 63,800 7,900 80,500 4,200 306,000 462,400
1998 600 63,800 7,900 81,000 4,400 320,800 477,900
1999 600 63,800 7,900 81,400 4,600 336,000 493,700
2000 600 63,800 7,900 81,900 4,800 351,500 509,900
2001 600 125,000 63,800 7,900 82,300 5,100 367,900 527,000
2002-21 600 72,200 7,900 82,300 5,100 367,900 535,400
2022-34 600 63,800 7,900 82,300 5,100 367,900 527,000
~ Replace diesel in 15 years; then replace plant every 20 years. Replace fuel tank in 2001.
Includes plant replacement and fuel tank addition. The fuel tank addition was amortized over the period
3/
4/
5/
6/
2002-2021.
The replacement value for the first 15 years is $800,000, and then
tion period. Insurance cost is $0.83 per $100 replacement value.
From Table IX-I.
From Table IX-2.
From Table IX-3.
NBI-410-9521-IX-4
I I I I I I I I I • . -. , . f • , . I I
$950,000 for the remainder of the evalua-
, I I • • • , I • • II , I I I
... -
'.
-
-
-
.-
-
-
-
-
-
-
---
-
Year
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006-
2034
1/
2/
3/
4/
5/
TABLE IX-5
BASE CASE
WASTE HEAT RECOVERY REPLACEMENT COST
TOGIAK
Schedu1eli
SinkingY
Schedul~ Sinkin~ Tota0
of of Sinking
Investment Fund Investment Fund Fund
($) ($) ($) ($) ($)
11,700 10,500 22,200
11,700 10,500 22,200
11,700 10,500 22,200
11,700 10,500 22,200
11,700 10,500 22,200
11,700 10,500 22,200
11,700 10,500 22,200
11,700 10,500 22,200
11,700 10,500 22,200
11,700 120,000 10,500 22,200
11,700 7,700 19,400
11,700 7,700 19,400
11,700 7,700 19,400
200 OOo.!! 11,700 7,700 19,400 ,
7,400 7,700 15,100
7,400 7,700 15,100
7,400 7,700 15,100
7,400 7,700 15,100
7,400 7,700 15,100
7,400 7,700 15,100
7,400 7,700 15,100
7,400 7,700 15,100
7,400 120,000 7,700 15,100
7,400 4,500 11,900
Replace all heat recovery equipment ~n the powerhouse in 1996, 2006, and
2026, at a cost of $200,000. Timing matches plant replacement.
Sinking Fund for 1983-1996 is $200,000, 3%, and 14
fund is $200,000, 3%, and 20 years, in perpetuity.
Replace exhaust heat recovery equipment after
Replacement included in sinking fund for all
replacement each 10 years after total replacement.
in 1992, 2005, and 2025.
years. After 1996,
10 years (1992);
equipment; interim
Interim replacements
First replacement is 10 years at 3%; then 13 years at 3%; then 20 years
at 3% in perpetuity. This is the interim replacement; maximum time
between replacements of exhaust heat recovery equipment is 10 years.
All values rounded to nearest $100.
NBI-410-9521-IX5
TABLE IX-6
BASE CASE
WASTE HEAT RECOVERY ANNUAL COST
TOGIAK
Schedule of Schedule oi!:...l Operation
Capital
Amortization!!
Replacement Sinking and Annual
Investment Investment Fund Maintenance Cost
Year ($) ($) ($) ($) ($) ($) --
1982 325,000 0
1983 12,400 22,200 1,000 35,600
1984 12,400 22,200 1,000 35,600
1985 12,400 22,200 1,000 35,600
1986 12,400 22,200 1,000 35,600
1987 12,400 22,200 1,000 35,600
1988 12,400 22,200 1,000 35,600
1989 12,400 22,200 1,000 35,600
1990 12,400 22,200 1,000 35,600
1991 12,400 22,200 1,000 35,600
1992 12,400 120,000 22,200 1,000 35,600
1993 12,400 19,400 1,000 32,800
1994 12,400 19,400 1,000 32,800
1995 12,400 19,400 1,000 32,800
1996 12,400 200,000 19,400 1,000 32,800
1997 12,400 15,100 1,000 28,500
1998 12,400 15,100 1,000 28,500
1999 12,400 15,100 1,000 28,500
2000 12,400 15,100 1,000 28,500
2001 12,400 15,100 1,000 28,500
2002 12,400 15,100 1,000 28,500
2003 12,400 15,100 1,000 28,500
2004 12,400 15,100 1,000 28,500
2005 12,400 15,100 1,000 28,500
2006-34 12,400 11,900 1,000 25,300
1/ 52 years at 3%. 2/ From Table IX-5.
NBI-410-9521-IX-5
I • I I I I 'I I I I. f. •• • W " ,. • I ,. ,. I. I. I I I I I I
I j I I I t I i t t t I I I i
TABLE IX-7
BASE CASE
WASTE HEAT RECOVERY SAVINGS
TOGIAK
Oill! of~ Annual~ Net
Credi tY Schedule Annual
Equivalent Oil Cost Investment Cost Savings
Year (gals) ($ gal) ($) ($) ($) ($)
1982 1.55 0 325,000 0 0
1983 25,670 1.59 40,800 35,600 5,200
1984 26,060 1.63 42,500 35,600 6,900
1985 26,460 1.67 44,200 35,600 8,600
1986 26,850 1. 72 46,200 35,600 10,600
1987 27,260 1. 76 48,000 35,600 12,400
1988 27,660 1.81 50,100 35,600 14,500
1989 28,080 1.86 52,200 35,600 16,600
1990 28,500 1.90 54,200 35,600 18,600
1991 28,930 1.95 56,400 35,600 20,800
1992 29,360 2.00 58,700 120,000 35,600 23,100
1993 29,800 2.06 61,400 32,800 28,600
1994 30,250 2.11 63,800 32,800 31,000
1995 30,700 2.16 66,300 32,800 33,500
1996 31,160 2.22 69,200 200,000 32,800 36,400
1997 31,630 2.28 72,100 28,500 43,600
1998 32,110 2.34 75,100 28,500 46,600
1999 32,590 2.40 78,200 28,500 49,700
2000 33,080 2.46 81,400 28,500 52,900
2001 33,570 2.52 84,600 28,500 56,100
2002 33,570 2.52 84,600 28,500 56,100
2003 33,570 2.52 84,600 28,500 56,100
2004 33,570 2.52 84,600 28,500 56,100
2005 33,570 2.52 84,600 28,500 56,100
2006-
2034 33,570 2.52 84,600 25,300 59,300
1/ See text, pages IX-4 through IX-6. 2/ Values rounded to nearest $100. 3/ From Table IX-6.
NBI-410-9521-IX-6
.. -
TABLE IX-8 ..
BASE CASE .' SUMMARY
TOGIAK ..
Wast e Rea ti/ -
Annual Energyl! Annual Diese12/ Present3/ Recovery Present~/ • Demand Cost Worth -Savings Worth
Year (1000 kWh) ($) ($) ($) ($) -
1982 789 217,800 211,500 0 0 •
1983 823 227,900 214,800 5,200 4,900 ..
1984 858 238,600 218,300 6,900 6,300
1985 892 249,600 221,800 8,600 7,600 •
1986 919 260,200 224,400 10,600 9,100 III
1987 945 270,000 226,100 12,400 10,400
1988 972 281,300 228,700 14,500 11,800 •
1989 998 292,700 231,100 16,600 13,100 • 1990 1025 303,400 232,500 18,600 14,300
1991 1051 315,400 234,700 20,800 15,500 ..
1992 1077 327,600 236,700 23,100 16,700 ..
1993 1103 341,300 239,400 28,600 20,100
1994 1129 354,000 241,100 31,000 21,100 • 1995 1155 367,400 242,900 33,500 22,100 • 1996 1182 382,200 245,300 36,400 23,400
1997 1208 462,400 288,200 43,600 27,200 • 1998 1234 477,900 289,100 46,600 28,200 ..
1999 1260 493,700 290,000 49,700 29,200
2000 1286 509,900 290,800 52,900 30,200 ..
2001 1314 527,000 291,800 56,100 31,100 ..
2002 1314 535,400 287,800 56,100 30,200
2003 1314 535,400 279,400 56,100 29,300 • 2004 1314 535,400 271,300 56,100 28,400
2005 1314 535,400 263,400 56,100 27,600 ..
2006-..
2021 1314 535,400 3,308,100 59,300 348,200
2022-..
2034 1314 527,000 1,718,400 59,300 193,400 ..
Totals 11,027,600 999,400 ..
• ...
1/ From Table VII-lt.
2/ From Table IX-4. •
3/ Discounted to January 1982 at 3% interest. Values rounded to nearest ..
i/
$100. Present worth factors accurate to four decimal places.
From Table IX-7. •
ilia
• -
NBI-410-9521-IX-7 --
-
-
-
....
-
-
" .. -
..
Year
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
TABLE IX-9
HYDROELECTRIC PROJECT
ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
DIESEL OPERATION AND MAINTENANCE COSTS
TOGIAK
Annual
Energy.!! Maintenanc~ Operatiord! Production
(1000 kWh) ($) ($)
789 13,400 60,000
823 14,000 60,000
858 14,600 60,000
0 0 30,000
0 0 30,000
0 0 30,000
0 0 30,000
0 0 30,000
0 0 30,000
1 100 30,000
3 100 30,000
4 100 30,000
6 100 30,000
8 100 30,000
10 200 30,000
11 200 30,000
13 200 30,000
14 200 30,000
16 300 30,000
22 400 30,000
Annual
Cost
($)
73,400
74,000
74,600
30,000
30,000
30,000
30,000
30,000
30,000
30,100
30,100
30,100
30,100
30,100
30,200
30,200
30,200
30,200
30,300
30,400
2002-34 22 400 30,000 30,400
1/
2/
3/
From Table VII-11.
$17 per megawatt-hour. Values rounded to nearest $100.
One-half of operator's salary after hydro plant goes on-line
in 1985.
NBI-410-9521-IX-8
Annua0
Energy
Production
Year (1000 kWh)
1982 789
1983 823
1984 858
1985 0
1986 0
1987 0
1988 0
1989 0
1990 0
1991 1
1992 3
1993 4
1994 6
1995 8
1996 10
1997 11
1998 13
1999 14
2000 16
2001 22
2002-34 22
TABLE IX-10
HYDROELECTRIC PROJECT
ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
DIESEL LUBRICATION OIL COSTS
TOGIAK
Lubricatiord! Lubricatio0
Oil Oil Unit Cost
(gallons) ($/gallon)
473 3.95
494 4.05
515 4.16
0 4.27
0 4.38
0 4.49
0 4.61
0 4.73
0 4.85
1 4.98
2 5.11
3 5.24
4 5.37
4 5.51
5 5.66
6 5.81
7 5.96
8 6.11
9 6.27
12 6.43
12 6.43
1/
2/
3/
4/
From Table VlI-11.
0.6 gallons per megawatt-hour.
Escalated at 2.6% annually.
Values rounded to nearest $100.
NBI-410-9521-IX-9
Lubricationi!
Oil Cost
($)
1,900
2,000
2,100
0
0
0
0
0
0
100
100
100
100
100
100
100
100
100
100
100
100
• ...
• -
• -• -
• ...
• -
• •
•
• ...
• ... .. ...
•
III
• •
• ..
• -
• .. --
'. -
-
-
-
-
-
-
-
-
---
.,.
------
Annua:t...!.l
Energy
Production
Year (1000 kWh) --
1982 789
1983 823
1984 858
1985 0
1986 0
1987 0
1998 0
1989 0
1990 0
1991 1
1992 3
1993 4
1994 6
1995 8
1996 10
1997 11
1998 13
1999 14
2000 16
2001 22
2002-34 22
TABLE IX-11
HYDROELECTRIC PROJECT
ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
DIESEL FUEL OIL COSTS
TOGIAK
Equivalendt' Fuel Oill.l
Oil Unit Cost
(gallons) ($/gallon)
87,700 1. 55
91,400 1.59
95,300 1.63
0 1.67
0 1. 72
0 1. 76
0 1. 81
0 1.86
0 1.90
100 1.95
300 2.00
400 2.06
700 2.11
900 2.16
1,100 2.22
1,200 2.28
1,400 2.34
1,600 2.40
1,800 2.46
2,400 2.52
2,400 2.52
From Tables VlI-11.
Fuel Oil.!l
Cost
($ )
135,900
145,300
155,300
0
0
0
0
0
0
200
600
800
1,500
1,900
2,400
2,700
3,300
3,800
4,400
6,000
6,000
1/
2/ 111.1 gallons per megawatt-hour.
gallons.
Rounded to nearest 100
3/
4/
Escalated at 2.6% annually.
Values rounded to nearest $100.
NBI-410-9521-IX-10
! !
TABLE IX-12
DIESEL COSTS
HYDROELECTRIC PROJECT
ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
TOGIAK
o ill Operation.!! Lubricatio~ Fuel§' Annual Firm Schedule and
Capacity Investment AmortizatiorJ! Insurancdl Maintenance Oil Oil Cost
Year (kW) ($) ($) ($) ($) ($) .ilL ($)
1982 460 6,600 73,400 1,900 135,900 217,800
1983 460 6,600 74,000 2,000 145,300 227,900
1984 460 6,600 74,600 2,100 155,300 238,600
1985 460 6,600 30,000 0 0 36,600
1986 460 6,600 30,000 0 0 36,600
1987 460 6,600 30,000 0 0 36,600
1988 460 6,600 30,000 0 0 36,600
1989 460 6,600 30,000 0 0 36,600
1990 460 6,600 30,000 0 0 36,600
1991 460 6,600 30,100 100 200 37,000
1992 460 6,600 30,100 100 600 37,400
1993 460 6,600 30,100 100 800 37,600
1994 460 6,600 30,100 100 1,500 38,300
1995 460 6,600 30,100 100 1,900 38,700
1996 600 950,000 6,600 30,200 100 2,400 39,300
1997 600 48,500 7,900 30,200 100 2,700 89,400
1998 600 48,500 7,900 30,200 100 3,300 90,000
1999 600 48,500 7,900 30,200 100 3,800 90,500
2000 600 48,500 7,900 30,300 100 4,400 91,200
2001 600 125,000 48,500 7,900 30,400 100 6,000 92,900
2002 600 56,900 7,900 30,400 100 6,000 101,300
2003 600 56,900 7,900 30,400 100 6,000 101,300
2004 600 56,900 7,900 30,400 100 6,000 101,300
2005 600 56,900 7,900 30,400 100 6,000 101,300
2006 600 56,900 7,900 30,400 100 6,000 101,300
2007 600 56,900 7,900 30,400 100 6,000 101,300
2008 600 56,900 7,900 30,400 100 6,000 101,300
2009 600 56,900 7,900 30,400 100 6,000 101,300
2010 600 56,900 7,900 30,400 100 6,000 101,300
2011 600 56,900 7,900 30,400 100 6,000 101,300
2012-21 600 56,900 7,900 30,400 100 6,000 101,300
2022-34 600 48,500 7,900 30,400 100 6,000 92,900
Replace plant after 15 years, then every 30 years. Expand fuel storage facilities in 2001. 1/
2/
~/
4/
5/
~
$950,000 plant cost amortized for 30 years at 3% in perpetuity. $125,000 fuel tank expansion amortized for
20 years at 3%.
Replacement value for years 1-15 = $800,000, and then $950,000 for the remainder of the evaluation period.
Insurance cost is $0.83 per $100 replacement value. Rounded to nearest $100.
From Table IX-9.
From Table IX-I0.
From Table IX-II.
NHI-410-9521-IX-11
I II • lit I • lit • • ; I II ; ; I ; ; ; 1 Ii • i • Ii I , .. ~ J .. J' 1 I I I I , I
....
TABLE IX-13
HYDROELECTRIC PROJECT .. ALTERNATIVE A
CONCRETE DAM
INSTALLED CAPACITY = 432 kW
HYDROELECTRIC COSTS
-TOGIAK
Opera tion .. ~l§! Replacementil .. CapitaJ.l} M .. t nd ~chedule ~f
C?~}s Amor(~~atio~Y aln enance nvestmen
-, Year ($) ($)
ilia' 1982
1983
... ' 1984 6,539,000 ., 1985 254,400
1986 254,400
1987 254,400
1988 254,400 .' 1989 254,400
1990 254,400
1991 254,400
.. I 1992 254,400
1993 254,400
-, 1994 254,400
1995 254,400 .' 1996 254,400 _. 1997 254,400
1998 254,400
_I 1999 254,400
2000 254,400
..... 2001 254,400
•• 2002 254,400
2003 254,400
•• 2004 254,400
2005 254,400
., 2006 254,400
2007 254,400
... ·2008 254,400
.-,2009 254,400
2010 254,400
... 2011 254,400
2012-34 254,400
... ,
~.------------------------------
From Table VIII-1A .
50 years at 3%.
1.5% of contract cost .
0
0
0
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000
84,000 135,000
84,000
89,000
84,000 1,224,200
Replacemen0Y
Si~ff~gg Aeg~tl
($) ($)
0
0
0
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
29,400 367,800
1/
• ''2/
-:r/ ... 4/
• '5/ Replace runner in 2009. Replace transmission lines in 2014 .
"·6/
••
Transmission line replacement fund 30 years at 3%; runner replacement fund
25 years at 3%. The two funds are superimposed.
Values rounded to nearest $100 .
NBI-410-9521-IX-12 .-
••
TABLE IX-14
HYDROELECTRIC PROJECT
ALTERNATIVE A
CONCRETE DAM
INSTALLED CAPACITY ; 432 kW
SUMMARY
TOGIAK
Annuall!
Total
-----Ger~ration Mix-----Annual Hyg~o Annual Di~,el Annual
Demand Hydr~ Diesel 11 Cos~ Cos~ Cost
Year (1000 kWh) (1000 kWh) (1000 kWh) ($) ($) ($)
1982 789 0 789 0 217,800 217,800
1983 823 0 823 0 227,900 227,900
1984 858 0 858 0 238,600 238,600
1985 892 892 0 367,800 36,600 404,400
1986 919 919 0 367,800 36,600 404,400
1987 945 945 0 367,800 36,600 404,400
1988 972 972 0 367,800 36,600 404,400
1989 998 998 0 367,800 36,600 404,400
1990 1,025 1,025 0 367,800 36,600 404,400
1991 1,051 1,050 1 367,800 37,000 401,800
1992 1,077 1,074 3 367,800 37,400 405,200
1993 1,103 1,099 4 367,800 37,600 405,400
1994 1,129 1,123 6 367,800 38,300 406,100
1995 1,156 1,148 8 367,800 38,700 406,500
1996 1,182 1,172 10 367,800 39,300 407,100
1997 1,208 1,197 11 367,800 89,400 457,200
1998 1,234 1,221 13 367,800 90,000 457,800
1999 1,260 1,246 14 367,800 90,500 458,300
2000 1,286 1,270 16 367,800 91,200 459,000
2001 1,314 1,292 22 367,800 92,900 460,700
2002 1,314 1,292 22 367,800 101,300 469,100
2003 1,314 1,292 22 367,800 101,300 469,100
2004 1,314 1,292 22 367,800 101,300 469,100
2005 1,314 1,292 22 367,800 101,300 469,100
2006 1,314 1,292 22 367,800 101,300 469,100
2007 1,314 1,292 22 367,800 101,300 469,100
2008 1,314 1,292 22 367,800 101,300 469,100
2009 1,314 1,292 22 367,800 101,300 469,100
2010 1,314 1,292 22 367,800 101,300 469,100
2011 1,314 1,292 22 367,800 101,300 469,100
2012-21 1,314 1,292 22 367,800 101,300 469,100
2022-34 1,314 1,292 22 367,800 92,900 460,700
1/ From Tables VII-II. 2/ Difference between annual demand and hydro. 3/ From Table IX-13. i! From Table IX-12.
NBI-410-9521-IX-13
!I I I I I I I , . I ••• I • I • • II i 11 i t i I i I i i t I f I J I I 1
-
-
Year ..
1982
1983 .. 1984
1985
1986 .. 1987
1988
1989
1990 _,
1991
1992
TABLE IX-15
HYDROELECTRIC PROJECT
ALTERNATIVE C
ROCKFILL DAM
INSTALLED CAPACITY = 432 kW
HYDROELECTRIC COSTS
TOGIAK
3/6/ Replacementi/..§i Oper at ion..=.; -ana Schedule of
Investment
($)
Capi taill..§i C~~rs AmOrt~Jatio~..§i _M_a_i~(~~)~n_a_n_c_e
0
0
6,950,800 0
270,400 89,200
270,400 89,200
270,400 89,200
270,400 89,200
270,400 89,200
270,400 89,200
270,400 89,200
270,400 89,200
~ 1993 270,400 89,200
,..; 1994 270,400
1995 270,400
1996 270,400
1997 270,400 ., 1998 270,400
1999 270,400
2000 270,400
IiIIII 2001 270,400
2002 270,400
"1. 2003 270,400
2004 270,400 ., 2005 270,400
2006 270,400 .... 2007 270,400 ... 2008 270,400
2009 270,400 ... , 2010 270,400
2011 270,400 ., 2012-34 270,400
~. -------------------------------
•• l..I 2/ From Table VIII-1C.
50 years at 3% .
1.5% of contract cost.
89,200
89,200
89,200
89,200
89,200
89,200
89,200
89,200
89,200
89,200
89,200
89,200
89,200
89,200
89,200
89,200 135,000
89,200
89,200
89,200 1,224,200
Repl acement.~ .. /.§j
Sinking AnnuaL§!
Fund Cost
($) ($)
0
0
0
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
29,400 389,000
... 3/
4/
··5/
... 6/
Replace runner in 2009. Replace transmission lines in 2004.
Transmission line sinking fund, 20 years at 3%. Runner sinking fund
30 years at 3%. The two funds are superimposed .
All values rounded to nearest $100 .
••
-NBI-432-9521-IX-14
••
I I. I •
TABLE IX-16
HYDROELECTRIC PROJECT
ALTERNATIVE C
ROCKFILL DAM
INSTALLED CAPACITY
SUMMARY
TOGIAK
Annuall.! -----Genuatlon Mlx------
Demand Hydro -DieseLY
Year (1000 kWh) (1000 kWh) (1000 kWh)
1982 789 0 789
1983 823 0 823
1984 858 0 858
1985 892 892 0
1986 919 919 0
1987 945 945 0
1988 972 972 0
1989 998 998 0
1990 1,025 1,025 0
1991 1,051 1,050 1
1992 1,077 1,074 3
1993 1,103 1,099 4
1994 1,129 1,123 6
1995 1,156 1,148 8
1996 1,182 1,172 10
1997 1,208 1,197 11
1998 1,234 1,221 13
1999 1,260 1,246 14
2000 1,286 1,270 16
2001 1,314 1,292 22
2002 1,314 1,292 22
2003 1,314 1,292 22
2004 1,314 1,292 22
2005 1,314 1,292 22
2006 1,314 1,292 22
2007 1,314 1,292 22
2008 1,314 1,292 22
2009 1,314 1,292 22
2010 1,314 1,292 22
2011 1,314 1,292 22
2012-21 1,314 1,292 22
2022-34 1,314 1,292 22
1/
2/
3/
From Table VII-II.
if
Difference between annual demand and hydro.
From Table IX-15.
From Table IX-12.
NBI-432-9521-IX-15
• I' • • I • I • I • t I
432 kW
Annual
Hydro Cost.Y
($)
0
0
0
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
389,000
t I • •
Total
Annual Annual
Diesel Cost.!! Cost
($) ($)
217,800 217,800
227,900 227,900
238,600 238,600
36,600 425,600
36,600 425,600
36,600 425,600
36,600 425,600
36,600 425,600
36,600 425,600
37,000 426,000
37,400 426,400
37,600 426,600
38,300 427,300
38,700 427,700
39,300 428,300
89,400 478,400
90,000 479,000
90,500 479,500
91,200 480,200
92,900 481,900
101,300 490,300
101,300 490,300
101,300 490,300
101,300 490,300
101,300 490,300
101,300 490,300
101,300 490,300
101,300 490,300
101,300 490,300
101,300 490,300
101,300 490,300
92,900 481,900
, I I t I • t 11 , . I I , I
...
-
..
..
-
-
-
.-
-'. -..
.... ..
------
''i!IIII!JII
...
-
iIIi
-
• --
Year
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002-34
TABLE IX-17
HYDROELECTRIC PROJECT
ALTERNATIVE B
CONCRETE DAM
INSTALLED CAPACITY = 288 kW
DIESEL OPERATION AND MAINTENANCE COSTS
TOGIAK
Annual 1 /
Energy-
Production Maintenanc~ Operatiord!
(1000 kWh) ($) ($)
789 13,400 60,000
823 14,000 60,000
858 14,600 60,000
18 300 30,000
26 400 30,000
34 600 30,000
42 700 30,000
50 900 30,000
58 1,000 30,000
66 1,100 30,000
74 1,300 30,000
81 1,400 30,000
89 1,500 30,000
98 1,700 30,000
106 1,800 30,000
114 1,900 30,000
121 2,100 30,000
129 2,200 30,000
137 2,300 30,000
149 2,500 30,000
149 2,500 30,000
1/ From Table VII-12. 2/ $17 per MWh . Rounded to nearest $100.
Annual
Cost
($)
73,400
74,000
74,600
30,300
30,400
30,600
30,700
30,900
31,000
31,100
31,300
31,400
31,500
31,700
31,800
31,900
32,100
32,200
32,300
32,500
32,500
3/ Operators salary is $60,000 per year, split cost with hydro
project after 1985.
NBI-432-9521-IX-16
AnnuaIl!
Energy
Production
Year (1000 kWh)
1982 789
1983 823
1984 858
1985 18
1986 26
1987 34
1988 42
1989 50
1990 58
1991 66
1992 74
1993 81
1994 89
1995 98
1996 106
1997 114
1998 121
1999 129
2000 137
2001 149
TABLE IX-18
HYDROELECTRIC PROJECT
ALTERNATIVE B
CONCRETE DAM
INSTALLED CAPACITY = 288 kW
DIESEL LUBRICATION OIL COSTS
TOGIAK
Lubrication.Y Lubricatiord!
Oil Oil Cost
(gallons) ($/gallon)
473 3.95
494 4.05
515 4.16
11 4.27
16 4.38
20 4.49
25 4.61
30 4.73
35 4.85
40 4.98
44 5.11
49 5.24
53 5.37
59 5.51
64 5.66
68 5.81
73 5.96
77 6.11
82 6.27
89 6.43
2002-34 149 89 6.43
1/
2/
3/
4/
From Table VII-12.
0.6 gallons per megawatt-hour.
Escalated at 2.6% annually.
Rounded to nearest $100.
NBI-432-9521-IX-17
-... ..
-... --
-
Lubrication.!! -Oil Cost
($)
•
1,900
2,000 • 2,100
100 • 100 • 100
100
100
200 ..
200 -200 -300
300 -300
400 -
400 • 400
500 -500 • 600
600 .. --..
•
I.
• ..
• ..
-
-
..
.... ..
..
-
...
' ...
>I/fI
..
-
-
-,-..
'.
' ... ..
'~ .. ..
-
•
Year
1982
1983
1984
1985
1986
1987
1998
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
TABLE IX-19
RECOMMENDED HYDROELECTRIC PROJECT
ALTERNATIVE B
Annuall!
Energy
Production
(1000 kWh)
789
823
858
18
26
34
42
50
58
66
74
81
89
98
106
114
121
129
137
149
CONCRETE DAM
INSTALLED CAPACITY = 288 kW
DIESEL FUEL OIL COSTS
TOGIAK
Equivalent1J Fuel Oi0
Oil Cost
(gallons) ($/gallon)
87,700 1. 55
91,400 1. 59
95,300 1.63
2,000 1.67
2,900 1. 72
3,800 1. 76
4,700 1. 81
5,600 1. 86
6,400 1.90
7,300 1.95
8,200 2.00
9,000 2.06
9,900 2.11
10,900 2.16
11,800 2.22
12,700 2.28
13,400 2.34
14,300 2.40
15,200 2.46
16,600 2.52
2002-34 149 16,600 2.52
1/ From Table VII-12.
2/ 111.1 gallons per megawatt-hour. Rounded
3/
gallons.
Escalated at 2.6% annually.
4/ Rounded to nearest $100.
NBI-432-9521-IX-18
Fuel OiL!!
Cost
($)
135,900
145,300
155,300
3,300
5,000
6,700
8,500
10,400
12,200
14,200
16,400
18,500
20,900
23,500
26,200
29,000
31,400
34,300
37,400
41,800
41,800
to nearest 100
I
TABLE IX-20
HYDROELECTRIC PROJECT
ALTERNATIVE B
CONCRETE DAM
INSTALLED CAPACITY = 288 kW
DIESEL COSTS
TOOIAK
Schedule otlf
Operationi!
LUbricatioI2! FueL§! Firm
Amortization-Y Insuranc~ and Annual
Capacity Investment Maintenance Oil Oil Cost
Year (kW) ($) ($) ($) ($) ($) ilL ($)
1982 460 6,600 73,400 1,900 135,900 217,800
1983 460 6,600 74,000 2,000 145,300 227,900
1984 460 6,600 74,600 2,100 155,300 238,600
19H5 460 6,600 30,300 100 3,300 40,300
1986 460 6,600 30,400 100 5,000 42,100
1987 460 6,600 30,600 100 6,700 44,000
1988 460 6,600 30,700 100 8,500 45,900
1989 460 6,600 30,900 100 10,400 48,000
1990 460 6,600 31,000 200 12,200 50,000
1991 460 6,600 31,100 200 14,200 52,100
1992 460 6,600 31,300 200 16,400 54,500
1993 460 6,600 31,400 300 18,500 56,800
1994 460 6,600 31,500 300 20,900 59,300
1995 460 6,600 31,700 300 23,500 62,100
1996 600 950,000 6,600 31,800 400 26,200 65,000
1997 600 48,500 7,900 31,900 400 29,000 117,700
1998 600 48,500 7,900 32,100 400 31,400 120,300
1999 600 48,500 7,900 32,200 500 34,300 123,400
2000 600 48,500 7,900 32,300 500 37,400 126,600
2001 600 125,000 48,500 7,900 32,500 600 41,800 131,300
2002 600 56,900 7,900 32,500 600 41,800 139,700
2003 600 56,900 7,900 32,500 600 41,800 139,700
2004 600 56,900 7,900 32,500 600 41,800 139,700
2005 600 56,900 7,900 32,500 600 41,800 139,700
2006 600 56,900 7,900 32,500 600 41,800 139,700
2007 600 56,900 7,900 32,500 600 41,800 139,700
2008 600 56,900 7,900 32,500 600 41,800 139,700
2009 600 56,900 7,900 32,500 600 41,800 139,700
2010 600 56,900 7,900 32,500 600 41,800 139,700
2011 600 56,900 7,900 32,500 600 41,800 139,700
2012-21 600 56,900 7,900 32,500 600 41,800 139,700
2022-34 600 48,500 7,900 32,500 600 41,800 131,323
1/
2/
}j
4/
5/
6/
Replace plant after 15 years, then every 30 years.
$950,000 plant cost amortized for 30 years at 3% in perpetuity. $125,000 fuel tank expansion amortized for
20 years at 3%.
Replacement value for years 1-15 = $800,000, and then $950,000 for the remainder of the evaluation period.
Insurance cost is $0.83 per $100 of replacement value. Rounded to nearest $100.
From Table IX-17.
From Table IX-18.
From Table IX-19.
NBI-432-952l-IX-19
I • • • I • I I I • • f • • f • • t , . • • I • , t I I .. I J I , .
TABLE IX-21
HYDROELECTRIC PROJECT
ALTERNATIVE B
CONCRETE DAM
INSTALLED CAPACITY = 288 kW
HYDROELECTRIC COSTS
Tcx:JIAK
Operatio~~ Replacementi!~
Capi talLlJ . and Schedule of
Replacemen0~
Sink:i,ng Annual -
.~
Year C~~)s Amortit!)iOn.~/~ Ma(~nenance _I_n....;.(....;.$...;..)_t_m_e_n_t Fund Cost
($) ($)
1982
-1983
_ 1984 6,237,300
1985
-1986
1987
.. 1988
1989
1990
... 1991
1992
-1993
1994
.." 1995
_ 1996
1997
... 1998
1999
2000
2001
-2002 ._ 2003
2004
-2005
2006
-2007
.. 2008
2009
_ 2010
2011
.. 2012-34
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600
242,600 -------------------------------
1/
-2/ From Table VIII-lB.
50 years at 3%.
1.5% of contract cost.
o
o
o
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
79,600
130,000
1,224,200
3/ -4/
-5/
-~
Replace runner in 2009. Replace transmission lines
Sinking fund for transmission lines 30 years at 3%.
runner 25 years at 3%. Both funds superimposed and
Values rounded to nearest $100. -
-NBI-432-9521-IX-20 -
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
29,300
in 2014.
Sinking fund for
perpetual.
o
o
o
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
351,500
TABLE IX-22
HYDROELECTRIC PROJECT
ALTERNATIVE B
INSTALLED CAPACITY = 288 kW
SUMMARY
TOGIAK Total
AnnuaL!/ ------Gy?eration Mix------Annual Hydro.~/ Annual Diesel...~/ Annual
Demand Hydro..:.. DieseL~/ Cost Cost Cost
Year (looo kWh) (1000 kWh) (1000 kWh) ($) ($) ($) --
1982 789 0 789 0 217,800 217,800
1983 823 0 823 0 227,900 227,900
1984 858 0 858 0 238,600 238,600
1985 892 874 18 351,500 40,300 391,800
1986 919 893 26 351,500 42,100 393,600
1987 945 911 34 351,500 44,000 395,500
1988 972 930 42 351,500 45,900 397,400
1989 998 948 50 351,500 48,000 399,500
1990 1,025 967 58 351,500 50,000 401,500
1991 1,051 985 66 351,500 52,100 403,600
1992 1,077 1,003 74 351,500 54,500 406,000
1993 1,103 1,022 81 351,500 56,800 408,300
1994 1,129 1,040 89 351,500 59,300 410,800
1995 1,156 1,058 98 351,500 62,100 413,600
1996 1,182 1,076 106 351,500 65,000 416,500
1997 1,208 1,094 114 351,500 117,700 469,200
1998 1,234 1,113 121 351,500 120,300 471,800
1999 1,260 1,131 129 351,500 123,400 474,900
2000 1,286 1,149 137 351,500 126,600 478,100
2001 1,314 1,165 149 351,500 131,300 482,800
2002 1,314 1,165 149 351,500 139,700 491,200
2003 1,314 1,165 149 351,500 139,700 491,200
2004 1,314 1,165 149 351,500 139,700 491,200
2005 1,314 1,165 149 351,500 139,700 491,200
2006 1,314 1,165 149 351,500 139,700 491,200
2007 1,314 1,165 149 351,500 139,700 491,200
2008 1,314 1,165 149 351,500 139,700 491,200
2009 1,314 1,165 149 351,500 139,700 491,200
2010 1,314 1,165 149 351,500 139,700 491,200
2011 1,314 1,165 149 351,500 139,700 491,200
2012-21 1,314 1,165 149 351,500 139,700 491,200
2022-34 1,314 1,165 149 351,500 131,300 482,800
1/ From Table VII-12. 2/ Difference between annual demand and hydro. "3/ From Table IX-21. 4/ From Table IX-20.
NBI-432-9521-IX-21 , . I • •• I • • • • I I • ., f • .,. • • • I .. • • (/If. • , • , • , •• • I • •
I I I I t I j I l I , ( 4 , t .. , i i i-ii ~
TABLE IX-23
ALTERNATIVE HYDROELECTRIC PROJECTS
HYDROELECTRIC SUPPLEMENTED BY DIESEL COSTS
PRESENT WORTH SUMMARY
TOGIAK
--A1tef?ative A--Annua~ Presen~ --Alte§?ative B--Annua~ Presen~ --Altes?ative C--Annua~ Presen~
Year Cost Worth Cost Worth Cost Worth
($) ($) (~) ($) ($) ($)
1982 217,800 211,500 217,800 211,500 217,800 211,500
1983 227,900 214,800 227,900 214,800 227,900 214,800
1984 238,600 218,400 238,600 218,400 238,600 218,400
1985 404,400 359,300 391,800 348,100 425,600 378,100
1986 404,400 348,800 393,600 339,500 425,600 367,100
1987 404,400 338,700 395,500 331,200 425,600 356,400
1988 404,400 328,800 397,400 323,100 425,600 346,100
1989 404,400 319,200 399,500 315,400 425,600 336,000
1990 404,400 309,900 401,500 307,700 425,600 326,200
1991 404,800 301,200 403,600 300,300 426,000 317,000
1992 405,200 292,700 406,000 293,300 426,400 308,000
1993 405,400 284,300 408,300 286,400 426,600 299,200
1994 406,100 276,600 410,800 279,800 427,300 291,000
1995 406,500 268,700 413,600 273,400 427,700 282,800
1996 407,100 261,300 416,500 267,400 428,300 274,900
1997 457,200 284,900 469,200 292,400 478,400 298,100
1998 457,800 277,000 471,800 285,400 479,000 289,800
1999 458,300 269,200 474,900 279,000 479,500 281,700
2000 459,000 261,800 478,100 272,700 480,200 273,900
2001 460,700 255,100 482,800 267,300 481,900 266,800
2002-
2021 469,100 3,864,300 491,200 4,046,300 490,300 4,038,900
2022-
2034 460,700 1,502,200 482,800 1,574,300 481,900 1,571,300
TOTALS 11,048,700 11,327,700 11,548,000
1/ From Table IX-14.
2/ Discounted to January 1982 at 3%. Values rounded to nearest $100. Present
3/
worth factors accurate to four decimal places.
From Table IX-22.
4/ From Table IX-16.
NBI-432-9521-IX-22
Energy.!.!
OilY
Equivalent
Year (1000 kWh) (gal) --
1982 0 0
1983 0 0
1984 0 0
1985 1,515 53,500
1986 1,500 53,000
1987 1,485 52,500
1988 1,469 51,900
1989 1,454 51,400
1990 1,439 50,800
1991 1,423 50,300
1992 1,407 49,700
1993 1,391 49,100
1994 1,375 48,600
1995 1,359 48,000
1996 1,342 47,400
1997 1,326 46,800
1998 1,310 46,300
1999 1,294 45,700
2000 1,278 45,200
2001-34 1,267 44,800
TABLE IX-24
HYDROELECTRIC PROJECT
ALTERNATIVES A AND C
INSTALLED CAPACITY = 432 kW
SPACE HEATING CREDIT
TOGIAK
Oil Uni2!
Credit!!
Schedule of!!.!
Cost Investment
($/gal) ($) ($)
1. 55 0
1. 59 0
1.63 0 44,000
1.67 89,300
1. 72 91,200
1. 76 92,400
1. 81 93,900
1. 86 95,600
1.90 96,500
1.95 98,100
2.00 99,400
2.06 101,100
2.11 102,500
2.16 103,700
2.22 105,200
2.28 106,700
2.34 108,300
2.40 109,700
2.46 111,200
2.52 112,900
Amortizatio~
($)
0
0
0
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
1,700
Intermediate values by interpolation.
Net Annual
Savings
($)
0
0
0
87,600
89,500
90,700
92,200
93,900
94,800
96,400
97,700
99,400
100,800
102,000
103,500
105,000
106,600
108,000
109,500
111,200
1/
2/ From Tables VII-9A through VII-9E.
28.3 kilowatt-hours per gallon.
Rounded to nearest 100 gallons.
Escalated at 2.6% annually.
Based on 138,000 Btu/ gallon and 70% eff iciency.
3/
4/
7!)/
6/
Rounded to nearest $100.
See Appendix G for system design and cost estimate.
50 years at 3%.
NBI-432-9521-IX-23
I' " •• ,. II II I. f': tt ••• ,.,.I" It t. ,.,' ,.
I l I I L , t , t l • j I I i i l t
TABLE IX-25
HYDROELECTRIC PROJECT
ALTERNATIVE B
INSTALLED CAPACITY = 288 kW
SPACE HEATING CREDIT
TOGIAK
Oi11./
~ I ~ I
Energy..!.!
Oil Unit~./
Credi t±I Schedule o:f~/ Net Annual
Equivalent Cost Investment Amortization2.! Savings
Year (1000 kWh) (gal) ($/gal) ($) ($) ($) ($) ._-
1982 0 0 1.55 0 0 0
1983 0 0 1. 59 0 0 0
1984 0 0 1.63 0 44,000 0 0
1985 889 31,400 1.67 52,400 1,700 50,700
1986 873 30,800 1. 72 53,000 1,700 51,300
1987 856 30,200 1. 76 53,200 1,700 51,500
1988 840 29,700 1.81 53,800 1,700 52,100
1989 823 29,100 1.86 54,100 1,700 52,400
1990 807 28,500 1.90 54,200 1,700 52,500
1991 789 27,800 1.95 54,200 1,700 52,500
1992 771 27,200 2.00 54,400 1,700 52,700
1993 752 26,600 2.06 54,800 1,700 53,100
1994 734 25,900 2.11 54,600 1,700 52,900
1995 716 25,300 2.16 54,600 1,700 52,900
1996 698 24,700 2.22 54,800 1,700 53,100
1997 680 24,000 2.28 54,700 1,700 53,000
1998 661 23,400 2.34 54,800 1,700 53,100
1999 643 22,700 2.40 54,500 1,700 52,800
2000 625 22,100 2.46 54,400 1,700 52,700
2001-34 609 21,500 2.52 54,200 1,700 52,500
1/
2/ From Tables VII-lOA through VII-l0E. Intermediate values by interpolation.
3/
4/
5/
6/
28.3 kilowatt-hours per gallon. Based on 138,000 Btu/gallon and 70% efficiency.
Rounded to nearest 100 gallons.
Escalated at 2.6% annually.
Rounded to nearest $100.
See Appendix G for system design and cost estimate.
50 years at 3%.
NBI-432-9521-IX-24
.. , ,
TABLE IX-26
ALTERNATIVE HYDROELECTRIC PROJECTS
SPACE HEATING CREDITS
TOGIAK
Alternatives A & C Alternative B
Year
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001-34
TOTALS
AnnualY
Savings
($)
o
o
o
87,600
89,500
90,700
92,200
93,900
94,800
96,400
97,700
99,400
100,800
102,000
103,500
105,000
106,600
108,000
109,500
111,200
Present.Y
Worth
($)
o
o
o
77,800
77,200
76,000
75,000
74,100
72,700
71,700
70,600
69,700
68,600
67,400
66,400
65,400
64,500
63,400
62,400
1,340,100
2,463,000
AnnuaJ2.1
Savings
($)
o
o
o
50,700
51,300
51,500
52,100
52,400
52,500
52,500
52,700
53,100
52,900
52,900
53,100
53,000
53,100
52,800
52,700
52,500
Present~/
Worth
($)
o
o
o
45,000
44,300
43,100
42,400
41,400
40,200
39,100
38,100
37,200
36,000
35,000
34,100
33,000
32,100
31,000
30,100
632,700
1,234,800
1/ From Table IX-24. ~/ Discounted to January 1982 at 3% annual interest. Rounded to
nearest $100. Present worth factors acurate to four decimal
places. ~/ From Table IX-25.
NBI-432-9521-IX-25
...
.. -
•
•
•
lit -
--..
• -
• -•
•
• ...
•
lit
•
I::
• •
• .. ..
-
-
...
-
-
-
--
-
-
-
--
".
"' ....
,..
-,-
--
TABLE IX-27
ALTERNATIVE HYDROELECTRIC PROJECT
ROAD COSTS
TOGIAK
11.6-MILE ROAol/
Capital Amorti-1! Annual Presen~/
Cost zation Maintenance Cost Worth
Year ($) ($) ($) ($) ($)
1982 1,630,600
1983-2034 62,300 5,000 67,300 1,709,700
4.6-MILE ROAD~/
Year
Capital
Cost
($)
Amorti-l./
zation Maintenance!/
($) ($)
Annual
Cost
($)
Presen~/
Worth
($)
1982
1983-2034
508,200
19,400 5,000 24,400 619,900
1/
2/
3/
4/
:§../
Build entire road as part of the hydroelectric project.
Build first seven miles of road as part of airport improve-
ments. Hydroelectric project pays for maintenance of entire
road.
52 years at 3%. Values rounded to nearest $100.
The cost of maintenance is for the entire road for both
alternatives.
Discounted to January 1982 at 3%. Rounded to nearest $100.
Present worth factors accurate to four decimal places.
NBI-432-9521-IX-26
TABLE IX-28
PRESENT WORTH SUMMARY
ALTERNATIVE A
TOGIAK
A. BASE CASE (Benefits)
Cost of Base Case Only~/
Waste Heat Recovery Creditl!
Subtotal
Wind Energy Credi~
Subtotal
Space Heating Credi~
Total
B. ALTERNATIVE HYDROELECTRIC PROJECT (Costs)
Cost of Hydro Project Only~/
Jj
1.1 y
i/
~
Cost of 4.6 Mile Road ~
Total
Cost of 11.6 Mile Roa~
Total
From Table IX-8.
From Table IX-6A.
From Table IX-26.
From Table IX-23. Includes supplemental
From Table IX-27.
NBI-432-9521-IX-28
$11,027,600
999,400
$10,028,200
540,700
9,487,500
2,463,000
$11,950,500
$11,048,700
619,900
11,668,600
$ 1,709,700
$12,758,400
diesel.
-
--
• -
• ---------..
..
• ..
• -..
III -
--
• -
....
-
.-
Jill
-,-
...,
-
-
"'"
--,.
-
-
A.
B.
1/
JJ
:Y
4/
5/
TABLE IX-29
PRESENT WORTH SUMMARY
ALTERNATIVE B
TOGIAK
BASE CASE (Benefits)
Cost of Base Case Onlyl!
Wa.ste Heat Recovery Creditl!
Subtotal
Wind Energy Credit!:!
Subtotal
Space Heating Credi0
Total
ALTERNATIVE HYDROELECTRIC PROJECT (Costs)
Cost of Hydro Project Only.!!
Cost of 4.6 Mile Roacei
Total
Cost of 11.6 Mile Roacei
Total
From Table IX-8.
From Table IX-6A.
From Table IX-26.
From Table IX-23. Includes supplemental
From Table IX-27.
NBI-432-9521-IX-29
$11,027,600
999,400
10,028,200
540,700
9,487,500
1,234,800
10,722,300
$11 ,327,700
619,900
11 ,947,600
1,709,700
$13,037,400
diesel.
TABLE IX-30
PRESENT WORTH SUMMARY
ALTERNATIVE C
TOGIAK
A. BASE CASE (Benefits)
Cost of Base Case Onlyl!
Waste Heat Recovery Creditl!
Subtotal
Wind Energy Credi~
Subtotal
Space Heating Credi~
Total
B. ALTERNATIVE HYDROELECTRIC PROJECT (Costs)
Cost of Hydro Project OnlY~
1/
2/
3/
4/
5/
Cost of 4.6 Mile Roa~
Total
Cost of 11.6 Mile Roa~
Total
From Table IX-8.
From Table IX-6A.
From Table IX-26.
From Table IX-23. Includes
From Table IX-27.
NBI-432-9521-IX-30
supplemental diesel.
-.. .. -
• -.. ..
... -.. $11,027,600 -999,400
10,028,200 -540,700 -9,487,500 -2,463,000 ...
11,950,500 --
$11,548,000 ..
619 z900 ....
12,167,900 -1 z 709 z 700 -$13,257,700 ... --..
., -.. ---.. .' ---..,
--
-
-
-
-
-
-
.",
' ...
...
-
..
-
-
-
---
TABLE IX-31
BENEFIT/COST RATIOS
ALTERNATIVE A
TOGIAKli
A. Base Case Only, 4.6 Mile Road
B.
11,027,600
B/C = 11,668,600 = 0.945
Base Case Adjusted for Waste Heat Recovery,
4.6 Mile Road
B/C = i~:~~~:~gg = 0.859
C. Base Case Adjusted for Waste Heat Recovery
and Wind Energy Credit, 4.6 Mile Road
B/C 9,487,500 = = 11,668,600 0.813
D. Base Case Adjusted for Waste Heat Recovery, Wind Energy Credit,
and Space Heating Credit, 4.6 Mile Road
E.
F.
G.
11,950,500
B/C = 11,668,600 = 1.024
Base Case Only, 11.6 Mile Road
11,027,600
B/C = 12,758,400 = 0.864
Base Case Adjusted for Waste Heat Recovery,
11.6 Mile Road
B/C -10,028,200 Q 786
-[2,758,400 = '.
Base Case Adjusted for Waste Heat Recovery and
Wind Energy Credit, 11.6 Mile Road
B/C _ 9,487,500
- -12,758,400 0.744
H. Base Case Adjusted for Waste Heat Recovery, Wind Energy Credit,
and Space Heating Credit, 11.6 Mile Road
11,950,500
B/C = 12,758,400 = 0.937
1/ See Table IX-28 for Present Worth Summary.
NBI-432-9521-IX-31
TABLE IX-32
BENEFITlcOST RATIOS
ALTERNATIVE B
TOGIAK 1./
A. Base Case Only, 4.6 Mile Road
BIC = 11,027,600 = 0 923
11,947,600 .
B. Base Case Adjusted for Waste Heat Recovery, 4.6 Mile Road
10,028,200 Blc = 11,947,600 = 0.839
C. Base Case Adjusted for Waste Heat Recovery and Wind Energy
Credit, 4.6 Mile Road
Blc -9,487,500"= 0.794
-11,947,600
D. Base Case Ad justed for Waste Heat Recovery, Wind Energy
Credit, and Space Heating Credit, 4.6 Mile Road
I 10,722,300,
B C = 11,947,600 = 0.897
E. Base Case Only, 11.6 Mile Road
BIC = 11,027,600 = 0 46
13,037,400 .8
F. Base Case Adjusted for Waste Heat Recovery, 11.6 Mile Road
Blc = 10,028,200 ~ 0 769
13,037,400 -•
G. Base Case Adjusted for Waste Heat Recovery and Wind Energy
Credit, 11.6 Mile Road
Blc -9,487,500 = 0.728
-13,037,400
H. Base Case Ad justed for Waste Heat Recovery, Wind Energy
Credit, and Space Heating Credit, 11.6 Mile Road
11
Blc -10,722,300 0 2
-13,037,400 = .82
See Table IX-29 for Present Worth Summary.
NBISF-456-9521-IX-32
•
•
• -
•
-----
• -
•
•
•
•
•
.. --
-• •
• ..
• .. .. -
.. .,
.-
81111
9[lII
.....
' .... ,-
'IIfI
.....
' ....
'.
--..
TABLE IX-33
BENEFIT/COST RATIOS
ALTERNATIVE C
TOGIAK 1/
A. Base Case Only, 4.6 Mile Road
B.
C.
D.
E.
F.
11,027,600
B/C = 12,167,900 = 0.906
Base Case Adjusted for Waste Heat Recovery, 4.6 Mile Road
10,028,200 .
B/C = 12,167,900 = 0.824
Base Case Adjusted for Waste Heat Recovery and Wind Energy
Credit, 4.6 Mile Road
B/C -9,487,500 0 780
-12,167,900 = •
Base Case Adjusted for Waste Heat Recover, Wind Energy
Credit, and Space Heating Credit, 4.6 Mile Road
B/C -11,950,500 -0 982
-12,167,900 - .
Base Case Only, 11.6 Mile Road
11,027,600
B/C = 13,257,700 = 0.832
Base Case Adjusted for Waste Heat Recovery, 11.6 Mile Road
10,028,200
B/C = 13,257,700 = 0.756
G. Base Case Adjusted for Waste Heat Recovery and Wind Energy
Credit, 11.6 Mile Road
B/C -9,487,500 = 0.716
-13,257,700
H. Base Case Adjusted for Waste Heat Recovery, Wind Energy
Credit, and Space Heating Credit, 11.6 Mile Road
1/
B/C -11,950,500-= 0.901
-13,257,700
See Table IX-30 for Present Worth Summary.
NBISF-456-9521-IX-33
TABLE IX-34
ANNUAL UNIT COSTS
BASE CASE
TOGIAK
Energ}L.!/ Base Cas~./ Waste Heat.!! Uni~/ Wind Energ~/ Annual!/ Unit Energ~/ Recovery Annua~/ Unit!./
Demand Diesel Cost Cost Savings Cost Energy Cost Credit Cost Energy Cost
Year (1000 kWh) ($) (Mills/kWh) ($) ($) (Mills/kWh) ($) ($) (Mills/kWh)
1982 789 217,800 276 0 217,800 276 0 217,800 276
1983 823 227,900 277 5,200 222,700 271 4,&00 217,900 265
1984 858 238,600 278 6,900 231,700 270 5,400 226,300 264
1985 892 249,600 280 8,600 241,000 270 6,200 234,800 263
1986 919 260,200 283 10,600 249,600 272 6,900 242,700 264
1987 945 270,000 286 12,400 257,600 273 7,600 250,000 265
1988 972 281,300 289 14,500 266,800 274 8,300 258,500 266
1989 998 292,700 293 16,600 276,100 277 9,100 267,000 268
1990 1025 303,400 296 18,600 284,800 278 9,700 275,100 268
1991 1051 315,400 300 20,800 294,600 280 10,500 284,100 270
1992 1077 327,600 304 23,100 304,500 283 13,200 291,300 270
1993 1103 341,300 309 28,600 312,700 283 14,300 298,400 271
1994 1129 354,000 314 31,000 323,000 286 15,200 307,800 273
1995 1155 367,400 318 33,500 333,900 289 16,300 317,600 275
1996 1182 382,200 323 36,400 345,800 293 17,400 328,400 278
1997 1208 462,400 383 43,600 418,800 347 18,500 400,300 331
1998 1234 477,900 387 46,600 431,300 350 19,600 411,700 334
1999 1260 493,700 392 49,700 444,000 352 20,700 423,300 336
2000 1286 509,900 397 52,900 457,000 355 30,100 426,900 332
2001 1314 527,000 401 56,100 470,900 358 31,500 439,400 334
2002 1314 535,400 407 56,100 479,300 365 31,500 447,800 341
2003 1314 535,400 407 56,100 479,300 365 31,500 447,800 341
2004 1314 535,400 407 56,100 479,300 365 31,500 447,800 341
2005 1314 535,400 407 56,100 479,300 365 31,500 447,800 341
2006-2021 1314 535,400 407 59,300 476,100 362 31,500 444,600 338
2022-2034 1314 527,000 401 59,300 467,700 356 31,500 436,200 332
1/ From Table VII-ll. '"1J:/ From Table IX-4. 3/ Base case diesel costs only. 4/
5/ From Table IX-6.
Base case adjusted for waste heat recovery credit. 6/ From Table IX-6A. Y..! Base case adjusted for waste heat recovery and wind energy credits.
NBISF-456-9521-IX-34
, I II I • I I I • • I • • • • , • C • • • , . • • , . fl I , ( , , ,
t I t j
Year
19H2
19H3
19H4
1985
1986
19H7
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002-2021
2022-2034
l
Energyli
Demand
(1000 kWh)
789
823
858
892
919
945
972
998
1025
1051
1077
1103
1129
1155
1182
1208
1234
1260
1286
1314
1314
1314
From Table VII-II.
From Table IX-14.
From Table IX-27.
Hydr03.!
Project Cost
($)
217,800
227,900
238,600
404,400
404,400
404,400
404,400
404,400
404,400
404,800
405,200
405,400
406,100
406,500
407,100
457,200
457,800
458,300
459,000
460,700
469,100
460,700
i
TABLE IX-35
ANNUAL UNIT COSTS
ALTERNATIVE A/ll.6 MILE ROAD
TOGIAK
11. 6 MileY Annual.!/
Road Cost Cost
($) ($)
o
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
67,300
217,800
295,200
305,900
471,700
471,700
471,700
471,700
471,700
471,700
472,100
472,500
472,700
473,400
473,800
474,400
524,500
525,100
525,600
526,300
528,000
536,400
528,000
Unit!/
Energy Cost
(Mills/kWh)
276
359
357
529
513
499
485
473
460
449
439
429
419
410
401
434
426
417
409
402
408
402
1/
2/
3/
4/ --5/ Hydro project including cost of 11.6 mile road.
From Table IX-24.
Space Heatin~i AnnuaJ.§!
Credit Cost
($) ($)
o
o
o
87,600
89,500
90,700
92,200
93,900
94,800
96,400
97,700
99,400
100,800
102,000
103,500
105,000
106,600
108,000
109,500
111,200
111,200
111,200
285,100
295,200
305,900
384,100
382,200
381,000
379,500
377,800
376,900
375,700
374,800
373,300
372,600
371,800
370,900
419,500
418,500
417,600
416,800
416,800
425,200
416,800
6/ Hydro project with 11.6 mile road, adjusted for space heating credit.
NUISF-456-9521-IX-35
Unit~/
Energy Cost
(Mills/kWh)
276
359
357
431
416
403
390
379
368
357
348
338
330
322
314
347
339
331
324
317
324
317
TABLE IX-36
ANNUAL UNIT COSTS
ALTERNATIVE A/4.6 MILE ROAD
TOGIAK
Energy .. !.! HydroY 4.6 MileY AnnuaJ.!! Unit~./ Space Hea t in~/ Annual&! Uni t2-./
Demand Project Cost Road Cost Cost Energy Cost Credit Cost Energy Cost
Year (1000 kWh) ($ ) ( $) ($ ) (Mills/kWh 2 ($) ($) (Mills/kWh)
1982 789 217,800 0 217,800 276 0 242,200 276
1983 823 227,900 24,400 252,300 307 0 252,300 307
1984 858 238,600 24,400 263,000 307 0 263,000 307
1985 892 404,400 24,400 428,800 481 87,600 341,200 383
1986 919 404,400 24,400 428,800 467 89,500 339,300 369
1987 945 404,400 24,400 428,800 454 90,700 338,100 358
1988 972 404,400 24,400 428,800 441 92,200 336,600 346
1989 998 404,400 24,400 428,800 430 93,900 334,900 336
1990 1025 404,400 24,400 428,800 418 94,800 334,000 326
1991 1051 404,800 24,400 429,200 408 96,400 332,800 317
1992 1077 405,200 24,400 429,600 399 97,700 331,900 308
1993 1103 405,400 24,400 429,800 390 99,400 330,400 300
1994 1129 406,100 24,400 430,500 381 100,800 329,700 292
1995 1155 406,500 24,400 430,900 373 102,000 328,900 285
1996 1182 407,100 24,400 431,500 365 103,500 328,000 277
1997 1208 457,200 24,400 481,600 399 105,000 376,600 312
1998 1234 457,800 24,400 482,200 391 106,600 375,600 304
1999 1260 458,300 24,400 482,700 383 108,000 374,700 297
2000 1286 459,000 24,400 483,400 376 109,500 373,900 291
2001 1314 460,700 24,400 485,100 369 111,200 373,900 285
2002-2021 1314 469,100 24,400 493,500 376 111,200 382,300 291
2022-2034 1314 460,700 24,400 485,100 369 111,200 373,900 285
1/ From Table VII-II. 2/ From Table 11-14. ~/ From Table 11-27. 4/ Hydro project including cost of 4.6 mile road. Tr/
6/ From Table IX-24.
Hydro project with 4.6 mile road adjusted for space heating credit.
NBISF-456-9521-11-36
, , • • II , I • • , I , , • • • , « , • t I , , . I , • • , I f • • • , .
....
," ...
~-'"';
, ...
,-
,.
,...,
....
, ....
,-
'.
' ..
,,.
,,.
-
-
..
--
TABLE IX-1A
BASE CASE
WIND ENERGY CREDIT
DIESEL OPERATION AND MAINTENANCE COSTS
TOGIAK
Annual 1 /
Energy-
Production MaintenanceY Operatio~
Year (1000 kWh) ($) ($)
1982
1983 140 2,400 0
1984 140 2,400 0
1985 140 2,400 0
1986 140 2,400 0
1987 140 2,400 0
1988 140 2,400 0
1989 140 2,400 0
1990 140 2,400 0
1991 140 2,400 0
1992 167 2,800 0
1993 167 2,800 0
1994 167 2,800 0
1995 167 2,800 0
1996 167 2,800 0
1997 167 2,800 0
1998 167 2,800 0
1999 167 2,800 0
2000 195 3,300 0
2001 195 3,300 0
2002-2034 195 3,300 0
1/
2/
From Table VII-14.
$17 per MWh. Rounded to nearest $100.
Annual Cost
($)
2,400
2,400
2,400
2,400
2,400
2,400
2,400
2,400
2,400
2,800
2,800
2,800
2,800
2,800
2,800
2,800
2,800
3,300
3,300
3,300
1../ Salary for operator, included in base case costs.
NBISF-456-9521-IX-1A
AnnuallJ
Energy
Production
Year (1000 kWh)
1982
1983 140
1984 140
1985 140
1986 140
1987 140
1988 140
1989 140
1990 140
1991 140
1992 167
1993 167
1994 167
1995 167
1996 167
1997 167
1998 167
1999 167
2000 195
2001 195
2002-2034 195
TABLE IX-2A
BASE CASE
WIND ENERGY CREDIT
DIESEL LUBRICATION OIL COSTS
TOGIAK
Lubrication~/ Lubrication3 /
Oil Oil Cost
(gallons) ($/gallon)
84 4.05
84 4.16
84 4.27
84 4.38
84 4.49
84 4.61
84 4.73
84 4.85
84 4.98
100 5.11
100 5.24
100 5.37
100 5.51
100 5.66
100 5.81
100 5.96
100 6.11
117 6.27
117 6.43
117 6.43
~/ From Tables VII-14.
~/ 0.6 gallons per megawatt-hour.
3/ Escalated at 2.6% annually.
~/ Rounded to nearest $100.
NBISF-456-9521-IX-2A
Lubrication4 /
Oil Cost
($)
300
300
400
400
400
400
400
400
400
500
500
500
600
600
600
600
600
700
800
800
----
•
•
•
• -.. -
• -• -• .. ..
•
• ..
• --• -
• ,.
•
• ---• ..
~~
"'.
'AJi!#
.-
'oh"-
.-
.-
iflfilll
....
,-
-....
'iIIIf
-,-
...
-
, ..
--
TABLE IX-3A
BASE CASE
WIND ENERGY CREDIT
DIESEL FUEL OIL COSTS
TOGIAK
Annual.l/
Energy Equivalent ~/ Fuel 3/ Fuel 4/
Production Oil Oil Cost Oil Cost
Year (1000 kWb) (gallons) ($/gallon) ($)
1982
1983 140 15,600 1.59 24,800
1984 140 15,600 1.63 25,400
1985 140 15,600 1.67 26,100
1986 140 15,600 1.72 26,800
1987 140 15,600 1. 76 27,500
1988 140 15,600 1.81 28,200
1989 140 15,600 1.86 29,000
1990 140 15,600 1.90 29,600
1991 140 15,600 1.95 30,400
1992 167 18,600 2.00 37,200
1993 167 18,600 2.06 38,300
1994 167 18,600 2.11 39,200
1995 167 18,600 2.16 40,200
1996 167 18,600 2.22 41,300
1997 167 18,600 2.28 42,400
1998 167 18,600 2.34 43,500
1999 167 18,600 2.40 44,600
2000 195 21,700 2.46 53,400
2001 195 21,700 2.52 54,700
2002-2034 195 21,700 2.52 54,700
From Tables VII-14. 1/
2/ 111.1 gallons per megawatt-bour.
Escalated at 2.6% annually.
Rounded to nearest $100.
Nearest 100 gallons.
1./
i/
NBISF-456-9521-IX-3A
WI! .. -TABLE IX-4A
BASE CASE
WIND ENERGY GENERATION CREDIT •
TOGIAK -
SUMMARY • -
Installedl/ 0reration2/ LUbr6rttiord/ FueJ..~/ Total
Capacity -Ma n enan~ Oil Credit -Year (kWh) ($) ($) ($) ($) -
1982 .,
1983 50 2,400 300 24,800 27,500 -1984 50 2,400 300 25,400 28,100
1985 50 2,400 400 26,100 28,900 • 1986 50 2,400 400 26,800 29,600
1987 50 2,400 400 27,500 30,300 -1988 50 2,400 400 28,200 31,000
1989 50 2,400 400 29,000 31,800 •
1990 50 2,400 400 29,600 32,400
1991 50 2,400 400 30,400 33,200
1992 60 2,800 500 37,200 40,500 • 1993 60 2,800 500 38,300 41,600
1994 60 2,800 500 39,200 42,500 ..
1995 60 2,800 600 40,200 43,600
1996 60 2,800 600 41,300 44,700 •
1997 60 2,800 600 42,400 45,800 ..
1998 60 2,800 600 43,500 46,900
1999 60 2,800 600 44,600 48,000 -2000 70 3,300 700 53,400 57,400
2001 70 3,300 800 54,700 58,800 -2002-2034 70 3,300 800 54,700 58,800 • -
• -]J From Table VII-14.
y From Table IX-1A. •
3/ From Table IX-2A. -4/ From Table IX-3A.
--
-..
NBISF-456-9521-IX-4A ..
• -
,,",
,,'"
""'
....
.-
,-
.-
.....
--.-
-
',,", -
---
Year
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
TABLE IX-5A
BASE CASE
WIND ENERGY GENERATION COSTS
TOGIAK
Installe~/ Schedule of2/
Capacity Investment--Amortization3/
(kW) ($) ($)
170,000
34,000
170,000
Operation4/
Maintenance
($)
o
8,500
8,500
8,500
8,500
8,500
8,500
8,500
8,500
8,500
2001
2002-2034
50
50
50
50
50
50
50
50
50
50
60
60
60
60
60
60
60
60
70
70
70 34,000
o
14,200
14,200
14,200
14,200
14,200
14,200
14,200
14,200
17,100
17,100
17,100
17,100
17,100
17,100
17,100
17,100
17,100
17,100
17,100
17,100
10,200
10,200
10,200
10,200
10,200
10,200
10,200
10,200
10,200
10,200
10,200
1/
2/
~/
From Tables VII-14.
Replace machines every 15 years, build first plant in 1982
and bring on line in 1983. Expand capacity in 1991.
15 years at 3% in perpetvity, rounded to the nearest
$100.
~/ 5% of capital cost. Rounded to the nearest $100.
NBISF-456-9521-IX-5A
Annual
Cost
($)
o
22,700
22,700
22,700
22,700
22,700
22,700
22,700
22,700
22,700
27,300
27,300
27,300
27,300
27,300
27,300
27,300
27,300
27,300
27,300
27,300
Installedl/
Capaci ty
Year (kW)
1982
1983 50
1984 50
1985 50
1986 50
1987 50
1988 50
1989 50
1990 50
1991 50
1992 60
1993 60
1994 60
1995 60
1996 60
1997 60
1998 60
1999 60
2000 70
2001-2034 70
1/ From Table VII-
2/ From Table IX-4A.
3/ From Table IX-5A.
TABLE IX-6A
BASE CASE
WIND ENERGY CREDIT
TOGIAK
Annual2/ Annual3/
CrediT Cost-
($) ($)
27,500 22,700
28,100 22,700
28,900 22,700
29,600 22,700
30,300 22,700
31,000 22,700
31,800 22,700
32,400 22,700
33,200 22,700
40,500 27,300
41,600 27,300
42,500 27,300
43,600 27,300
44,700 27,300
45,800 27,300
46,900 27,300
48,000 27,300
57,400 27,300
58,800 27,300
i/ Discounted at 3% to January 1987.
Net Annual Present.,i/
Cost Worth
($) ($)
4,800 4,500
5,400 4,900
6,200 5,500
6,900 6,000
7,600 6,400
8,300 6,700
9,100 7,200
9,700 7,400
10,500 7,800
13,200 9,500
14,300 10,000
15,200 10,400
16,300 10,800
17,400 11,200
18,500 11,500
19,600 11,900
20,700 12,200
30,100 17,200
31,500 379,600
TOTAL $540,700
Rounded to nearest
$100. Present worth factors accurate to 4 decimal places.
NBISF-456-9521-IX-6A
..
.. ---
• -
• -• -• -•
• ..
•
• .. --
• -• --..
• ---• ..
• -
liiill"
.,..,
til.
,..,
-
-
I-
Cf)
o
<..>
r
(!)
0:::
W
Z w
I-
Z
=>
~
<l:
=>
Z z
<l:
600
500
HYDROELECTRIC PROJECT ON-LINE
,.., .1i) ALTERNATIVE A WITH 11.6 MILE ROAD
I Y -AND NO SPACE HEATING CREDIT
r , ' "
I , .. , ' X,'" 2 ALTERNATIV,E,A WITH 4.6 MILE ROAD I ,AND NO SPACE HEATING CREDIT
: \ "
I " .. " T EXPAND FUEL '-, , ' r, STORAGE <£
I ,,' I 5 I I' "" , ___ _
400 I " ~ ~,~~~~ ~~ ',"~"," :' ~, 2 5", (2) 2.i ',~ ' ... ~~ ___ I._~.
I ~ ,'I 7 I , (4)' 3 r--l.-""-__ _
I I y' I
1(4) I " ~ - - -
IJ-I ""4 EXPAND WIND
• ''" CAPACITY
I 4 ~~-----
EXPAND DIESEL
CAPACITY
® BASE CASE
WITHOUT WASTE
@ ALTERNATIVE A
WITH 11.6 MILE
HEAT RECOVERY ROAD AND SPACE
OR WIND CREDITS HEATING CREDI"f
200 ® BASE CASE @) ALTERNATIVE A
WITH WASTE HEAT WITH 4.6 MILE
RECOVERY CREDIT ROAD AND SPACE
HEATING CREDIT-
(j) BASE CASE
WITH WASTE HEAT
RECOVERY AND
WIND CREDITS
100
1980 1990 2000 2010
YEAR
SEE SECTION IX-F FOR EXPLANATION OF GRAPH
--,.,----------------------------------------------------------------------
..... TOGIAK HYDROELECTRIC PROJECT
PRO,JECTED U!'~IT ENERGY COSTS
FIGURE
:IX. -I
AII'I'
IIW
11111
SECTION X
ENVIRONMENTAL AND SOCIAL EFFECTS
A. GENERAL
An environmental study of the Togiak Hydroelectric Project
vicini ty was conducted to survey the resources in the area,
evaluate potential effects of the project, and formulate
measures to avo id or arnel iora te adverse ef fects. Two field
investigations were made, relevant literature was reviewed, and
representatives of the Alaska Departments of Natural Resources
and of Fish and Game, the U.S. Fish and Wildlife Service, and
the Togiak National Wildlife Refuge were consul ted along with
local residents and the Togiak Village Council. A community
meeting was held with local residents on September 14, 1981, to
discuss the proposed project.
The study results indicate that a hydroelectric project at
the Quigmy si te could have potentially serious environmental
impacts, but measures such as fish ladders could likely miti-
gate the most serious effects. Additional studies are recom-
mended to answer questions related to the downstream effects of
the dam impoundmen t on salmon spawn ing; coho (si I ver) salmon
runs; minimum water requirements for fish below the proposed
dam; sel ect ion of a sui table access route; and method s to
ensure safe passage of out-migrating young salmon. Additional
study of fish passage facilities is also recommended.
If implemented, the project will provide a cheaper, depend-
able source of electric power to the local residents. The
project will bring an enlarged local payroll during construc-
tion and emplo ymen t of some local s both for construct ion and
maintenance activities. Even though Togiak is used to an
influx of outsiders during the herring season, precautions
NBI-384-9521-X X-l
should be taken to ensure that the imported construction
workers do not disrupt the traditional life style of the
community.
The areas considered in the study included fisheries,
wildlife, vegetation, archaeological and historic sites, visual
resources, recreation, air Quality, and socioeconomic
effects. Land status, hydrology, and geology are addressed in
Section IV, Basic Data. The detailed report on the environ-
mental studies conducted is contained in Appendix E and a
summary of the study is presented in this section. The
investigations concentrated primarily on the Quigmy River area
where the selected project is located but the Kurtluk River
area was studied as well.
B. ENVIRONMENTAL EFFECTS
1. Fisheries
a. Qu igmy Ri ver
Local residents of Togiak interviewed in September
1981 indicated that coho, pink, and chum salmon and Dolly
Varden char are found in the Ouigmy Ri ver, the si te of the
proposed proj ect • ADF&G escapemen t estimates for the river
from 1970 to 1981 range from 2,800 to 22,000 chum salmon, the
only known anadromous run of significance in the Quigmy
Ri ver . Co ho and pink salmon may al so spawn in the river but
avail abl e in forma tion is sketchy. Wes Bucher of ADF&G stated
that physical characteristics indicated that the river would
not have a strong pink salmon run but could have a good coho
run. No survey information exists.
During the field investigation in September 1981,
about 40 adul t coho salmon were observed at the mouth of the
Quigmy. During October 1981 about 175 adult coho were observed
NBI-384-9521-X X-2
-...
• -
• ..
• • --• -• •
• ..
• -• ..
• •
• -• •
• -• -• -
• -• -• -
'"' ..
.. , ..
.. '"
".It'
tllil
4111'
liM'
' ....
1111
....
. , ...
in the upper reaches and a school of 50 to 75 adult Do lly
Varden char was seen in the same area. Juvenile Dolly Varden
and coho salmon were collected in minnow traps throughout the
Quigmy River during the October field reconnaissance.
Chum salmon spawning occurs intertidally at the mouth
of the Quigmy and upstream as far as Salutak Creek (about 15
miles upstream of the project site) but it is heaviest in the
lower half of the river.
Estimates of subsistence harvests of salmon for the
entire Togiak district indicate an average annual harvest of
about 6,400 salmon of all types. These are said to be minimum
estimates reported by Togiak villagers. The Togiak Village
Council reported that very little subsistence fishing occurs on
the Quigmy River because of its remote location and the small
numbers of coho present compared to other rivers in the area.
Coho salmon are preferred over chum salmon, the predominant run
in the Quigmy River.
If the project is implemented, effects on the
fisheries of the Quigmy River will result from the construction
of the dam and its operation. Construction of the dam and its
facilities will cause a temporary increase in erosion and
sedimentation downstream. Operation of the dam may alter the
seasonal temperature cycle. This change could affect the
survival rate of the salmon. The dam will incorporate a fish
ladder to allow salmon to pass upstream. The reservoir,
however, will eliminate a small amount of spawning and rearing
habitat. If an access road is constructed to Togiak from the
project facilties, an increase in fish harvest from the Quigmy
River will likely result.
The adverse effects of the project can be minimized by
confining construction activity to a single summer and
u til izing prudent construct ion pract ices. In add it ion, more
NBI-384-9521-X X-3
detailed studies should be conducted to assess the effects of
the dam impoundment on salmon spawning and the timing and
numbers of the coho salmon runs. Al though th is is a run of
river project, resource agencies may request instream flow
studies to determine minimum water requirements for anadromous
and resident fish. Additional studies may also be required to
select an access route and to evaluate methods to ensure safe
passage of out-migrating smolt.
No significant effects on water quality or quanti ty
are expected downstream from the powerhouse outflow.
b. Kurtluk River
Since a number of alternatives were investigated, the
Kurtluk River area was also investigated. The Alaska Fisheries
Atlas indicates that chum salmon are known to spawn in the
Kurtluk River and Dolly Varden and rainbow trout, whitefish,
and northern pike may also be present. ADF&G chum salmon
escapement estimates are 1,200 in 1977, 400 in 1978, and 200 in
1979. These are the only years surveyed. No information is
available on the upstream extent of spawning. The field survey
noted coho salmon, Dolly Varden char, and coast-range sculpin
in the river. The Togiak Village Council reported that almost
no use is made of the Kurtluk River for subsistence or sport
fishing.
2. Wildlife
a. Quigmy River Area
With the exception of the mouth, the Quigmy River has
relatively poor wildlife habitat. No moose or caribou use the
area, and brown bears use it only occasionally. Rabbi ts, red
squirrels, and red fox occur at the river's mouth. Beaver are
not considered to be common along the river but the f iel d
NBI-384-9521-X X-4
--
• ..
• -
•
•
• -.. ---• -• -• -• -• •
• •
• ..
• -• ---
• •
• -
.. ,0
" ..
1111.'
1" ••• '
" ... '
'itt'
...
' ...
-
••
survey did reveal evidence of a beaver population in the
drainage area. A small number of ducks use the river mouth in
the spring and fall. Detailed lists of mammals and birds to be
found in the Togiak National Wildlife Refuge are presented in
Appendix E. The project is located in the refuge area.
The Quigmy River area is not extensively used by local
residents because it is 12 miles from Togiak. Several
residents who tried to boat the river were stopped by three-
foot falls about one-half mile above the proposed dam si teo
Fox hunting occurs throughout the entire area surrounding
Togiak. Beaver trapping near the Quigmy River is concentrated
in the marsh between the Quigmy and Matogak Rivers.
The U.S. Fish and Wildlife Service has no record of
endangered species in the project area.
Wildlife effects from the project will have three
existing habitat, basic origins: loss
disturbances during
intervention.
or alteration of
construction, and increased human
Permanent habitat loss will result from the
construction of roads and the dam and the flooding of the 53-
acre reservoir site. Project features may cause some barriers
to animal movements. And some mortal i ty to birds may resul t
from collisions with the transmission line wires. Borrow pits
will also alter habitat.
Blasting and the operation
create noise and disturb wildlife.
species will be temporary but
interrupted.
of heavy equipment will
The displacement of most
some nesting could be
The improved access due to the construction of a road
from Togiak to the project facili ties will lead to increased
NBI-384-9521-X X-5
wildlife harvests and the increased use of off-road vehicles
will degrade add it ional habi tat. The major species affected
will be brown bears, wolves, foxes, and possibly wolverines.
The effects of the project on wildlife can be
minimized by confining construction to a single summer and
util izing prudent constuction practices. Proper waste
management during construction can also prevent problems,
particularly those associated with marauding bears.
b. Kurtluk River Area
The Kurtluk River area's wildlife
similar to those for the Quigmy River area.
data are very
Most of the data
available relate to the region. Beaver dams and other
indications of animal popul at ions were observed in the f iel d
survey of this area. Trapping activities reportedly occur in
the upper reaches of the Kurtluk River.
3. Vegetation
The Quigmy River is bordered by willows with a grass
understory for most of its length. Near the mouth, individual
willows attain a height of 10 feet and a diameter of approxi-
mately six inches, but farther upstream the willows are only
three to five feet tall with a diameter of approximately one
inch. In the upper reaches of the Quigmy River, low willow
thickets are intermixed with patches of tall grass. In
sections wi th rock cliffs or where old river terraces are
present, these willow thickets continue up draws and other
protected areas.
More exposed slopes are covered by moss, with grasses, low
blueberry, dwarf birch, dwarf willow, and mountain cranberry
interspersed throughout. On bluff tops, the same species are
present, but here the woody vegetation attains a height of only
NBI-384-9521-X X-6
-.... , ----
•
•
• -
• --..
• -. ----• -• ..
• -
• ..
• -
• ---• -
•
.. *1
,-
,..,
,..,
... ,
-
two to three inches and it is so tightly interwoven it almost
completely obscures the moss. Foliose lichens, such as caribou
1 ichen, are qui te common on bluff tops and in some areas are
the dominant ground cover.
Vegetation was quite similar along the Kurtluk River, with
willows along the steambanks and dry tundra on bluff tops.
Willows reached heights of 20 feet in protected spots but were
normall y much shorter . At the dam site, lower areas were
covered with willow, while the upper slopes of the river bluffs
were thickly covered with low blueberry.
4. Archaeologic and Historic Sites
The only known archaeologic or historic site in the project
area is located at the mouth of the Kurtl uk River. However,
additional unidentified sites are likely to exist and the
Alaska Division of Parks has required an archaeologic survey of
the project area before construction can begin.
5. Visual Resources
The dam and powerhouse will not be visible from Togiak or
from Togiak Bay. The transmission 1 ine wi 11 be vis i bl e from
the town, but it will be placed where it will be screened from
view wherever possi bl e. Shoul d road Option A (a road from
Togiak to the dam site) be chosen, it will be visible from the
village to the point where it disappears behind a low hill at
the mouth of the Kurtluk Ri ver about two miles beyond the
existing road. This road was formed through continual use and
was never formally constructed. Road option B (from Togiak Bay
to the dam site) will be visible from a portion of Togiak Bay,
but will be screened from view in the town by low hills .
NBI-384-9521-X X-7
6. Recreation
Since the Quigmy River is 12 miles from Togiak, it does not
receive extensive use by local residents. Fox hunting occurs
throughout the entire region. Beaver trapping in the vicinity
of the Quigmy River is concentrated in the marshy area to the
southwest, between the Quigmy and the Matogak Rivers.
If road Option A is chosen, it will greatly increase the
area a vai lable for recreational use of snow machines, three-
wheelers, and standard vehicles. Village residents indicated
an interest in this route because it would increase access for
berry picking, hunting, and trapping. Road Option B wi 11 not
greatly affect recreational use of the area, since the road
will not provide access from the village. On rare occasions
villagers may bring three-wheeled vehicles by boat to use the
road.
7. Air Quality
During project construction, exhaust fumes from diesel
equipment and dust generated by construction activity may
diminish air quality. Since the proposed dam is 12 miles from
Togiak, this activity should not affect local residents. Winds
are common in this area and should rapidly disperse the air
pollutants.
Electrical power for Togiak is currently provided by diesel
generators. Replacement of diesel power by hydroelectric Dower
should improve air quality due to the elimination of air
pollutants generated by the burning of diesel fuel. Creation
of a dependable source of round-the-clock power will impove the
quality of life of the residents.
NBI-384-9521-X X-8
--
'. --
• --.. --• -• .. --
• -.. ..
• -• -------
• -• -
• -
....
....
.. ..,
.....
••
.....
.-
.... ,
. ..,
...
. ..,
'e
.....
C. SOCIOECONOMIC EFFECTS
Togiak is one of the more traditional villages in the
Bristol Bay area. Even so, socioeconomic effects of the
project will be minimal. The construction force is not
expected to exceed 26 people, and it will probably average
21. Since accommodations are not available at Togiak, trailers
will be brought in (and removed when construction is completed)
and a camp will be set up near the dam site. Working hours
will be 10 hours a day, six or seven days a week so the
imported work force will have little time for recreation. The
project should be completed within one year. Work is scheduled
to begin in May, with completion scheduled in the latter part
of November.
Al though skilled craft labor will be required, an effort
should be made to hire local residents whenever possible •
Otherwise, Togiak residents may resent the importation of
workers. However, since construction would occur during the
summer months, most local residents are likely to be busy with
commercial fishing and not be available for hire .
Togiak is used to receiving a large influx of outsiders
during the herring season. In spite of this, the head of the
project construction crew will have to take precautions to
ensure that the imported workers do not disrupt the traditional
life style of the Togiak community. Some foresight in setting
up the trailer camp to accommodate the imported work force
should be helpful in achieving this objective.
If the project is implemented, the hydropower will provide
cheaper electric power to the local residents. The Togiak
community will also benefit from the enlarged payroll during
construction and from the employment of some locals both for
construction and maintenance activities.
NBI-384-9521-X X-9
' ..
.. ,..
. ,,,,,
iiil
,.,
SECTION XI
PROJECT IMPLEMENTATION
A. GENERAL
This reconnaissance-level study has indicated that a
marginally feasible project could be constructed at the
recommended Quigmy River darn site. Since overall feasibility
has thus been shown, the next step to implement the project, if
so desired, would be the completion of a defini ti ve project
report that would optimize the project features, including the
type of darn, darn height, and installed capacity.
This section covers the steps necessary to complete the
definitive project report and presents a general schedule for
the following design and construction phases. The licenses,
permits, and institutional considerations necessary for project
development are also discussed.
B. DEFINITIVE PROJECT REPORT
Much of the work accomplished on the various activities
during this ini tial study can be utilized for the defini tive
project report. However, some additional data would be
necessary. Following is an appraisal of the information
gathered during this study that is applicable to the final
feasibility study and recommendations for additional data where
necessary .
1. Geology and Geotechnics
The Geology and Geotechnics Report included with this study
as Appendix C has been based on surface investigations, shallow
auger information, and hand dug test pits. A drilling and
testing program will be necessary in the darn site area. Three
NBI-384-9521-XI XI-l
holes approximately 50 feet in depth will be required, followed
by laboratory testing of the drill cores. Detailed soils
mapping should be prepared in conjunction with a drilling and
test pit program along the proposed road alignment. In the
borrow si tes, extensive drill holes or test pits should be
undertaken to determine the best areas to extract gravel. A
test program should also be conducted to determine the
thickness of the alluvium in the stream bed.
2. Surveying and Mapping
The surveys obtained to date are probably 80 percent
adequate for the defini tive project report and final design.
Several additional cross sections and some additional
topographic mapping, however, should be obtained. In addition,
a strip topographic map should be obtained along the route of
the proposed transmission line and access road.
3. Environmental Appraisal
Additional studies are recommended to answer questions
related to the downstream effects of the dam impoundment on
salmon spawning, silver (coho) salmon runs, minimum water
requirements for fish below the proposed dam, selection of a
sui table access route, and methods to ensure safe passage of
out-migrating young salmon. In addition, detailed
investigations of the various types of fish ladder designs
available as a mitigation measure would be necessary. The
recommended additional environmental studies are discussed in
more detail in Appendix E.
4. Energy Planning
The information developed for this reconnaissance study as
modified by any pertinent comments received during the review
process should be adequate for the definitive project report.
NBI -384-9521-XI XI-2
.. -.. -.. -
• •
• -• -• •
• ..
• ..
• ..
• ..
• -
• •
• ----
• -• -• -
.. ,
....
....
••
" ...
' ..
5. Hydrology
Present estimates of power flows available at the Quigmy
River site are based on limited data from areas 75 to 150 miles
distant. These estimates were intent ionally conservative to
compensate for the limited hydrologic knowledge of the Togiak
area. Given the marginal feasibility of the Togiak
Hydroelectric Project, these flow estimates should be carefully
compared with available recorded streamflow measurements. A
flow recorder was installed near the darn site on December 3,
1981. The timely availability of 1982 precipitation and
streamflow records from long-term stations elsewhere in Bristol
Bay is also required.
If some degree of verification is required prior to 1983,
preliminary work could begin in August. At a minimum, records
of the summer snowmelt recession and low flows are required to
materially increase the confidence in present flow estimates.
6. Preliminary Designs
The size of all project features will be optimized. With
the cost information now available and the improved
hydrological data that will soon be gathered, the optimal sizes
and types of project features can be determined. Wi th the
large heat demand of Togiak only partially satisfied by the 432
kW installation, a larger installed capacity of up to 600 kW
should be investigated in detail .
7. Cost Estimates
The cost estimates will be carefully refined to minimize as
many unknowns as possible. The estimates will be worked out
with firms and individuals experienced in construction in
Alaska.
NBI-384-9521-XI XI-3
8. Final Report
All findings of the study will be compiled in a definitive
project report that will contain conclusions and
recommendat ions on the recommended project conf igura t ion and
detailed implementation measures.
C. PROJECT DEVELOPMENT SCHEDULE
A proposed schedule for future project development in the
form of a bar chart is included as Figure XI-1. The schedule
assumes that the APA will decide to proceed with a Definitive
Project Report and then to proceed wi th full project
development.
The schedule is also based on the assumption that three
separate contracts would be awarded for the project
construction. The first would be for fabrication and delivery
of the turbine-generator equipment to the Port of Seattle and
later installation. The second would be for construction of
the project access road, and the third would be for civil work
construction and installation in cooperation with the
manufacturer of the turbine-generator equipment.
The actual controlling activities on the proposed schedule
are the turbine-generator procurement, the project access road,
and the construction period for the dam power plant and
transmission line.
1. Turbine-Generator Procurement
Accord ing to manufacturers' est ima tes , approximately one
year is necessary for turbine-generator fabrication (and
delivery to the Port of Seattle) starting from the time of
cont rac t award. In add it ion, prior to the award a two-month
NBI-384-9521-XI XI-4
----
• -
•
•
• --..
• -• -
.,
.f
• •
• •
• ..
•
•
• ..
• ---
-
-
-
_.
-
-
-
--
..
-
period must be allowed for advertising, bid preparation, and
bid evaluation. This in turn would be preceded by a three-
month period to prepare specifications.
2. Access Road
The access road would ideally be constructed in the summer
of the year preceding dam, power plant, and transmission line
construction. The economic analysis has indicated that the
most desirable option for project development is the
construction of a 4.6-mile access road. This assumes that the
Alaska Department of Transportation has constructed the first
7.0 miles of the 11.6-mile road. If this in fact occurs, the
APA should then fund the remaining 4.6 miles of access road by
the same contractor.
3. Construction Period
The field construction period would require two to three
summer months of on-site acti vi ties, preceded by one to two
months of shipping and mobilization time.
Other critical tasks such as preparation of the civil plans
and specifications, award of the civil contract, procurement of
the necessary permits and license, and coordination of project-
related activities with other affected agencies would be
accompl ished during the turbine-generator procurement phase;
thus they are not directly controlling activities.
As shown, the project construction would be completed about
October 1, 1984. Following three months of commissioning and
debugging time, the project would come on-line about January 1,
1985.
NBI-384-9521-XI XI-5
D. PROJECT LICENSES, PERMITS, AND INSTITUTIONAL CONSIDERATIONS
The following permits may be required for construction of
the Togiak Hydroelectric Project on the Quigmy River site:
l.
2.
3.
Under the authority of Section 404 of the Federal
Water Pollution Control Act Amendments of 1972, the
Army Corps of Engineers (COE) must authorize the
discharge of dredged or fill materials into navigable
waters, which includes adjacent wetlands, by all
individuals, organizations, commercial enterprises,
and federal, state and local agencies. A COE Section
404 Permit will therefore be required for the
diversion weir on Delta Creek.
A Water Quality Certificate from the State of Alaska,
Department of Environmental Conservation (DEC), is
also required for any activity that may resul t in a
discharge into the navigable waters of Alaska.
Application for the certificate is made by submitting
to DEC a letter requesting the certificate, accom-
panied by a copy of the permit application being
submitted to the Corps of Engineers.
The Alaska Department of Fish
Division, under authority of
and Game, Habitat
AS16.05.870, the
Anadromous Fish Act, requires a Habitat Protection
Permit if a person or governmental agency desires to
construct a hydraulic project or affect the natural
flow or bed of a specified anadromous river, lake, or
st ream or use equipment in such waters. A Habi tat
Protection Permit will be required for the diversion
weir, and for any bridging, instream or stream bank
work on the Quigmy or Kurtluk rivers.
NBI-384-9521-XI XI-6
• -
• -.. -
•
• -• --..
• ...
• ..
• ...
• •
• -
• •
• ..
• -
• -
• -• ... .. -
-
.-
-
-
-
-
-
....
-
-
-
-
..
. --
-
4 .
5.
6.
7.
Under authority of AS 16.05.840, the Alaska Department
of Fish and Game can require, if the Commissioner
feels it necessary, that every dam or other obstruc-
tion built by any person across a stream frequented by
salmon or other f ish be provided with a durable and
efficient fishway and a device for efficient passage
of fish. Th is statute will be addressed under the
Habitat Protection Permit.
All publ ic or pr iva te ent it ies (except Federal
agencies) proposing to construct or operate a hydro-
electric power project must have a license from the
Federal Energy Regulatory Commission (FERC) if the
proposed site is located on a navigable stream, or on
U.S. lands, or if the project affects a U.S. govern-
ment dam or interstate commerce. For the Togiak
project a minor license may be required. The question
of whether or not the project is jurisdictional under
the FERC is currently under study.
A Permit to Construct or Modify a Dam is required from
the Forest, Land and Water Management Division of the
Al aska Department of Natural Resources for the con-
struction, enlargement, al tera t ion or repai r of any
dam in the State of Alaska that is ten feet or more in
height or stores 50 acre-feet or more of water.
A Water Rights Permit is required from the Director of
the Di vision of Forest, Land and Water Management,
Alaska Department of Natural Resources, for any person
who desires to appropriate waters of the State of
Alaska. However, this does not secure rights to the
water. When the permi t holder has commenced to use
the appropriated water, he should notify the director,
who wi 11 issue a Cert i fi ca te of Appropriation that
secures the holder's rights to the water .
NBI-384-9521-XI XI-7
8.
9.
Tbe proposed project area is located within the
coastal zone. Under the Alaska Coastal Management Act
of 1977, a determination of consistency wi th Alaska
Coastal Management Standards must be obtained from the
Di vision of Pol icy Development and PI anni ng in the
office of the governor. This determination would be
made during the COE 404 Permit review.
Any party wishing to use land or facili ties of any
National Wildlife Refuge for purposes other than those
designa ted by tbe manager-i n-charge and publ ished in
the Federal Register must obtain a Special Use Permit
from the U. S. Fish and Wi I dl i fe Service. This permi t
may authorize such activities as rights-of-way;
easements for pipelines, roads, utilities, structures,
and research projects; and entry for geologic recon-
naissance or similar projects, filming and so forth.
NBI-384-9521-XI XI-B
• -• ... --
• ...
• ---• ..
• ...
• ...
• ..
• ...
• ...
...
•
• .. --• ---• .. --
, • j 1
Activity
1. Alaska Power Authority Review
2. Definitive Project Report
3. State of Alaska Decision
4. Secure Necessary Permits, License
5. Turbine/Generator Contract
a. Prepare Turbine/Generator Spec.
b. Advertise & Evaluate Bids
c. Fabricate Turbine/Generator
d. Deliver Turbine/Generator to Seattle
6. Access Road
a. Prepare Plans and Specs
b. Construct Road
7. Civil Contract
a. Prepare Civil Plans & Specs.
b. Advertise & Evaluate Bids
8. Construction Activities
a. Mobilization Period
b. Barge Sh ipmen t
c. Site Mobilization
d. Site Construction
9. Power Plant Commissioning,
Debugging Period
10. Plant On-Line
NBI-410-9521-PDS
J F M
t t f
FIGURE XI -1
PROJECT DEVELOPMENT SCHEDULE
--.~
1982 1983 1984
A M J J A S 0 N D J F M A M J J A S o N D J F M A M J J A S o N D
I--
~
-,..
•
-~ --
-
~~ ---
-
-
-
--
-
-
-
-
---
-
SECTION XII
CONCLUSIONS AND RECOMMENDATIONS
A. CONCLUSIONS
On the basis of the studies completed for this report, the
following conclusions can be drawn:
1. The energy demands of Togiak are sufficient to utilize
the energy produced by both a 432 kW and a 288 kW
hydroelectric project.
2. A hydroelectric project utilizing a 38-foot concrete
dam with 432 kW installed capacity is marginally
feasible if only 4.6 miles of the access road must be
funded by the project.
3. If a longer 11.6-mile road must be constructed, the
present worth of the project costs for the 38-foot-
high concrete dam and 432 kW installation are
virtually the same as the present worth of the
alternative base case plan costs.
4. A project on the Kurtluk River may be feasible.
5. A hydroelectric project at the Quigmy site could have
potentially serious environmental effects, but
measures such as fish ladders would likely mitigate
the most serious effects.
NBI-384-9521-XII XII-1
B. RECOMMENDATIONS
In view of the conclusions enumerated above, consideration
of the next step for project implementation--the preparation of
a definitive project report--is recommended by the Consultant
only if it appears that the Alaska Department of Transportation
intends to construct a road to the gravel borrow site at mile
7.0 along the proposed project access road. If this next step
is undertaken, additional environmental studies are also
recommended to assess in more detail the possible effects of
the project and to formulate appropriate mitigation measures.
An additional study that could be considered would be to
investigate in more detail the feasibility of constructing a
much smaller installation of approximately 60 to 80 kW at the
Kurtluk site. After the field reconnaissance and initial
hydrology activities were completed during this present study,
work on this site was not pursued since the size was so small
in relation to the Togiak electrical demands.
NBI-384-9521-XII XII-2
--
• .. --
• •
• .. ..
• -..
• •
• ..
• ... .. .. .. -
• .. .. -
• -
•
-.. .. ... --
....
-
-
-
••
References
BIBLIOGRAPHY
TOGIAK
Alaska Department of Fish & Game, Alaska's Fisheries Atlas,
Volumes I and II. 1978.
Alaska Department of Fish & Game, Alaska's Wildlife and
Habitat, Volumes I and II. 1973.
Alaska Department of Fish & Game, Bristol Bay Annual Management
Report, 1980.
Beck, R. W., and Associates. Small-Scale Hydropower
Reconnaissance Study, Southwest Alaska. For the Alaska
District, Corps of Engineers, April 1981.
Cady, W. M., R. E. Wallace, J. M. Hoare, and E. J. Webber.
"The Central Kuskokwin Region, Alaska," U.S. Geological Survey
Professional Paper 268. 1955.
Department of Army, Office of Chief of Engineers, Washington,
D.C. Recommended Guidelines for Safety Inspection of Dams,
National Dam Inspection Act, PL 92-367. 1977.
Department of Commerce. ESSA -Environmental Data Service,
Climatological Data Summary, Alaska.
Ebasco Services, Inc. Regional Inventory and Reconnaissance
Study for Small Hydropower Projects: Aleutian Islands, Alaska
Peninsula, Kodiak Island, Alaska. Vols. 1 and ~, October 1980.
NBI-384-9521-BR
Huber, W. C., D. R. F. Harleman, and P. J. Ryan. Temperature
Predictions in Stratified Reservoirs, Proc. ASCE, 98, HY4, 645-
666. 1972.
Miller, J. F. "Probable Maximum Precipitation and Rainfall
Frequency Data for Alaska," U.S. Weather Bureau, Technical
Paper No. 47, 1963.
Northern Technical Services and Van Gulik Associates, Inc.
Community Energy Reconnaissance of Goodnews Bay, Grayling,
Scammon Bay, and Togiak. A report to the Alaska Power
Authority, February 1981.
Ott Water Engineers. Water Resources Atlas for USDA Forest
Service Region X, Juneau, Alaska, April 197~.
Retherford, H. W., Associates. Bristol Bay Energy and Electric
Power Potential, Phase I, for the U.S. Department of Energy,
December 1979.
Togiak National Wildlife Refuge, Final Environmental Statment.
U.S. Department of Energy, Alaska Power Administration, Small
Hydroelectric Inventory of Villages Served by Alaska Village
Electric Cooperative, December 1979.
U.S. Geological Survey. "Flood Characteristics of Alaskan
Streams," Water Resources Investigation 78-129, R. D. Lamke.
1979.
U.S. Geological Survey. "The Hydraulic Geometry of Some
Alaskan Streams South of the Yukon River (Open File Report),"
William E. Emmett, July 1972.
U.S. Geological Survey. "Water Resources of Alaska (Open File
Report)"; A. J. Feulner, J. M. Childers, V. W. Norman; 1~71.
NBI-384-9521-BR
• .. .. ---
• ..
III .., .. .. -., ..
II ..
•
III! .. ..
• ..
• • .. -.. --.. --• -
• -
"".
....
.....
....
., ...
.....
...
. ". . ..,
••
'fIIII
Watson, G. H., et al. An Inventory of Wildlife Habitat of the
MacKenzie Valley and the Northern Yukon. Environmental and
Social Committee, Task Force on Northern Oil Development,
Report No. 73-27. 1973.
Woodward-Clyde Consultants. Valdez Flood Investigation
Technical Report. February 1981 .
NBI-384-9521-BR
.....
... "
...
•.. ,.:
"1-...
TOGIAK HYDROELECTRIC PROJECT
FEASIBILITY STUDY
APPENDIX A
PROJECT DRAWINGS
....
-.-..
-
..
..
-
-
-
-
..... -
.,
_.
-.
J.il'
TABLE OF CONTENTS
Plate I General Plan
Plate II Alternative A--38 Foot High Concrete Gravity Dam, 432
kW Installed Capacity
Plate III Alternative B--28 Foot High Concrete Gravity Dam, 288
kW Installed Capacity
Plate IV Alternative C--52 Foot High Rockfill Dam, 432 kW
Installed Capacity
Plate V Typical Crossarm Construction Assembly
Plate VI Electric One-Line Diagram
r'
,<
-" ..
\
. PROJECT
"
r ',,"
~~¥
.¥
/ II
TOGIAK BAY
I
I PROJECT PLAN
I ,
I
I
I
'I
I
"J,.'" ),
~I ."
/?:,
o 2 3 4 5 MILES ~~--~i~~i--~I __ _
LOCATION MAP
NOT TO SCALE
BRtS TOL
BAY
VICINITY MAP
NOT TO SCALE
STATE OF ALASI(A
ALASKA POWER AUTH~TY
ANCHORAGE, ALASIIiA
TOGIAK HYDROELECTRIC PROJECT
GENERAL PLAN
DDWL ENGINEERS TUD<lII __ a ~y
ANCHOftAGE. ALASKA SAN ~1ItMICIICO.~
PLATE I
, .
. ,
SHUT-OFF VALVE
-TRANSMISSION
LINE
GENERAL PLAN
SCALE' I"' 20'
~.// ~// -+ ,. / ..
TURBINE (CONTROL PANELS
POWERHOUSE PLAN
NT S
B
j
----------__ GENERATOR
------SPEED INCREASER
/
STB~AhlBEQ _EL. 170
SECTION A
SCALE' I"' 10'
EL. 227
'V FLOOD EL. 224
GATE
'2-EL."'2"'o"'8'-----________ --=::.~nI
~OUNDLEVEL~E~L.~19~2~ ____________ ~~~
SECTION B
SCALE • I"' 10'
o 10 20 30 40 50 60
SCALE I" z 101
o 20 40 60 80 100 120 ~----~--~S~C~A~L~E~~,"-.-2~0~'~----~~-~
-LTW .EL .178
STATE OF ALASKA
ALASKA POWER AUTHORITY
ANCHORAGE,ALASKA
TOGIAK HYDROELECTRIC PROJECT
ALTERNATIVE A
38' HIGH CONCRETE GRAVITY DAM
432 kW INSTALLED CAPACITY
OOWL ENGINEERS
ANCHOItAGE. ALASKA
TUOOA ENGINEERIII5 COIII_y
SAN fRANCISCO, CALlfOIINlA
PLATE
., ,
. ,
.. " ...
.. .
, .
\ \ .' . \ ~-,~~" . '~-( -
---:-.-~-.---.:..~. --~----
\
\
\
.' -",~ .. '
SHUT-OFF VALVE
'CDIoICRETE
FLOW ---
. A
~
.~. ,~ :~~--"115'.' .-' ~:;/ ~~ ... ----... -, ~ -------' \
'\
.. ~ ------------------
GENERAL PLAN
SCALE' I"" 20'
TURBINE CONTROL PANELS
POWERHOUSE PLAN
'NT S
B
j
__ , __ GENERATOR
SPEED INCREASER
..&-FLOOD ~,~1'14~ _______ _
STREAMBED EL 170
~"17~ ___________ __
'V FLOOD EL. 214
GROUND LEIIE,L ~L. 187 ,
0 10 20
SCALE
0 20 40
SCALE
'.
4 !','
30
I" •
60
RETAINING WALL
SECTION A
SCALE I"· 10'
SECTION B
SCALE. I"· 10'
40 ~O
10'
80 100
SPILLWAY
60
120
I"" 20'
TW. EL. 178 -.:&-
TW. EL. 178
STATE 01' ALASKA
ALASKA POWER AUTHORITY
ANCHORAGE,ALASKA
TOGIAK HYDROELECTRIC PROJECT
ALTERNATIVE B
28' HIGH CONCRETE GRAVITY DAM
288 kWINSTALLED CAPACITY
OOWl ENGINEERS
AIICHORAG[, ALASKA
PLATE m
n
..
~~----
TRANSMISSION
UNE
-------/----~.
~ .. ~~-;;--~~--L-
INTAKE-.
" \
\
LOW LEVEL\ /'
RELEASE INTAKE _
SHUT-OFF VALVE
B
L It ---Iy
U ..
FLOW
----------
GENERAL PLAN
SCALE, I"· 20'
TURBINE,
POWERHOUSE PLAN
NTS
(CONTROL PANELS
i
_ ._GENERATOR
SPEED INCREASER
TRASH RACK
It. DAM
GATE HOIST ...............
')---,
/.
~ EL.2OB
/;y ·----·zJ
~/' 14 /'" .
I~
1.4
/
'1
.' ·.(~-LO' CONCRETE GATE-__
~.P
MEMBRANE I ~
~ROCKFILL
e
LEVEL OUTLET~ '0¥~
"-------TOE SLA8
(
SECTION A
SCAL E' I"· 10'
It. DAM
..... 8'-0 DIA. REINFORCED
CONCRETE PIPE
~~.----------~~--~
V FLOOD EL. 218
V RES. EL. 208
TOE SLAB
o 10 20 30 40 :10 60
SCALE 1 II,. 101 '----' -
0~ __ 2~0~_~4~0~_~6JO~~~8~0~_-110~O~_~120
SCALE I"" 20'
TW. EL. 178
STATE OF ALASKA
ALASKA POWER AUTHORITY
ANCHORAGE,ALASKA
TOGIAK HYDROELECTRIC PROJECT
ALTERNATIVE C
52' HIGH ROCK FILL DAM
432 kW INSTALLED CAPACITY
OOWL ENGINEERS
ANCHORAGE, ALASKA
PLATEI2'
, ...
' ...
-
..
..
."" ..
-
-
-
~,.., ....
-
4" 3' -8" 3' -8 1
'
II
0
t\I
= W
1
0
rt)
ITEM NO.
a 3
b I
c :3
d 5
f 2
g I
ek
b
ek-c-d
---~"
a
Position of Guy
when req'd I
d74-t~,
I I I '" bs I I
I I
I I I r"~
. 1
1
I.f~ rt~
ek-d/l ~j "'-ec
t~J
Specify CIA for
offset neutral assembly
MATERIAL ITEM NO.
Insulator, pin type cu 2
Pin, pole top, ZO" i 2
Bolt, machine, ;S" x req d length j I
Washer 2 ~4" ,IZ Y4" ~ 3/16 , 1~16 hale bs I
Pin, crossarm, steel.5/8" x 103~" ee I
Crossarm. 3 '/2" x 4 1/2" x 8' -0 j 3
Locknuts
MATERIAL
Broce, wood, 28"
Bolt, corrioge,3/S" x 4}02'
Screw, log, "2"x 4" (CI only)
Bolt sinQle upset, insuloted(CI only)
Bracket,offset ,insulated (CIA only)
Screw, log. I/Z"x4" (C IA only)
7.2112.5 KV., 3-PHASE CROS SAR M CONSTRUCTION
SINGLE PRIMARY SUPPORT AT 0° TO 5° ANGLE
Jon I, 1962 CI. CIA
PLATE rL
-
-
-
-
...
-
-
--,.
---
l
52S)
-L
STATION
SERVICE
II ~£
SYNCHRONOUS GENERATOR
kV·A, PF-0.9 RPM
3 0, GENERATOR
=
TO DISTRIBUTION SYSTEM
TRANSFORMER
12,470/480 V
GENERATOR BREAKER
ELECTRIC ONE -LINE DIAGRAM
NTS
REVENUE METER
SYNCHRONIZING
____ r!1_
VOLTAGE
REGULATOR
....
I,,,
....
TOGIAK HYDROELECTRIC PROJECT
FEAS IBILITY STUDY
APPENDIX B
HYDROLOGY
-
TABLE OF CONTENTS
-PAGE
-A. GENERAL 1
-B. AREA DESCRIPTION 1
.. C . DATA UTILIZED 4
D. PROJECT STREAMFLOWS 5 ,..,.
E . DIVERSION WEIR FLOOD FREQUENCY 11 ..
F. CONSIDERATION OF POTENTIAL RIVER ICE
-PROBLEMS 14
.....
-
-NBI-427-9524-TC
-
-
-
-
-
-
.....
-
-
-
-
-
-
A. GENERAL
The
ology,
village
Alaska.
fo llowi ng report provi des the est ima tes, the method-
and the background d at a on the river flows near the
of Togiak located on Bristol Bay in southwestern
Also included is a generalized wri te-up of potential
ice problems in the vicini ty of Togiak and elsewhere. Since
the stream flows dictate the amount of energy that can be
produced by a particular dam and power plant configuration,
their accuracy cri tically affects the feasibili ty of the pro-
ject. Although very little hydrologic information is available
on the project area, information from other parts of the
Bristol Bay region permi t acceptable estimates to be made for
the Quigmy dam site. However, these estimates should be com-
pared wi th the actual streamflows now being recorded at the
Quigmy damsite. This report describes the general characteris-
tics of the Togiak region and the basin that feeds the Quigmy
River. The data used in the hydrologic analysis, and
streamflow and flood frequency data from the Quigmy River are
also presented. A list of references th at are cited in the
text is presented at the end of this appendix.
B. AREA DESCRIPTION
1. Regional Setting
Togiak is
miles due west
located on the north shore of Bristol Bay 70
of Dillingham, 150 miles west of King Salmon,
and 70 miles northeast of Cape Newenham. The region is
partially isolated from the comparatively moist, warmer air of
the Gulf of Alaska by the mountains of the Aleutian Range and
islands located 200 miles to the south. As such, the region
forms a transi tion zone between that Mari time climate and the
Arctic and Continental climates further north. Bristol Bay has
a moderate maritime climate characterized by cool summers, mild
win ters, and moderate amoun ts of prec ipi tat ion. Most of the
NBI-384-9521-B* 1
precipitation occurs when moist air from the ocean precipitates
as rain or snow as it is uplifted along the mountains. Strong
winds over 50 mph blow from the south as eastward-moving
Aleutian lows pass through this region from December through
March.
Basin precipitation due to the flow of moist air from
Bristol Bay is expected to exhibit orographic effects, with
moderate amounts falling in the low elevations and heavy rain-
fall in the mountains. There are no long-term precipi tation
and temperature records for the Togi ak area. However, the
weather records from Cape Newenham, King Salmon, and Dillingham
stations would probably straddle the range of values expected
to occur within the lower basin, with higher precipitation
values expected for mountainous areas. Mean annual precipita-
tion isolines prepared by the National Weather Service and USGS
(1971) show an area to the east of the basin of interest that
has a mean annual precipitation of 80 inches, twice the amount
that falls in the coastal areas of Cape Newenham and Togiak
(see Figure B-1). The area enclosed by the 80-inch isoline
contains high mountains (to 5000 feet MSL) and a few small
gl aciers. Therefore the mean annual prec ipi t at ion averaged
over the Quigmy River basin should exceed 40 inches, probably
rangi ng from 40 inches to 60 inches and averagi ng around 50
inches.
It is reported in King Salmon that snowfall averages 45
inches,
inches.
melting.
wi th a maximum depth on the ground of no more than 10
This information indicates the extent of winter snow-
This is reflected on Eskimo Creek hydrograph where
some daily winter flows approach mean annual flows.
Based on regional mappi ng by the U. S. Geological Survey
(1971), the temperatures in the vicini ty of Togiak range from
January mean daily lows of 4°F to July highs of 62 0 F. Annual
runoff varies from two to four cfs per square mile (27 to 54
NBI-384-9521-B* 2
• ..
• ..
• -
• .. -..
•
•
• -
• -
• -
• •
II
•
• -• -
• ..
•
• --..
•
•
•
-
-
-
-
-
-
-,--
..
-----
inches) wi th the lower values estimated for the Quigmy River
area.
2. Basin Description
A potential for hydroelectric development near Togiak
exists within the two adjacent river basins lying west of the
town as shown on Figure B-2. The Qui gmy River basi n drai ni ng
100 square miles is of primary interest with the 13-square-mile
Kurtluk River basin as an al ternate. The headwaters of both
Quigmy and Kurtluk Rivers are in a mountainous area with peaks
rising from 1000 to 2500 feet in elevation. The lower portion
of these basins consists of the marshy flatlands of the coastal
benches and it is per iod i call y dot ted wi th groups of small
lakes. The entire region has been glaciated. A significant
portion of the basin seems to be in the wetlands that run along
the course of the river. These wet lands wi 11 probably mod i fy
streamflow characteristics by providing considerable temporary
storage area for runoff. Vegetation is limi ted to low brush
except for a few pockets of trees in protected river valleys.
The Quigmy Ri ver basin is approximately 26 miles long and
fi ve to six mi les wide, and it drains to the southwest. The
basin relief around Quigmy River indicates that the mid-portion
of the river crossing through the wetlands has a gradient of 20
feet per mile whereas the same river attains a gradient of 37
feet per mi Ie near the proposed dam si te. Here the ri ver has
several natural constrictions, wi th narrow and steep cuts in
the siliceous siltstone bedrock. The proposed dam site sits on
one of these natural constrictions.
c. DATA UTILIZED
Very Ii ttle hydrometeorological information exists in the
Togiak area. Spot stream discharge and gage height measure-
ments were made at the Quigmy and Kurtluk si tes on September
NBI-384-9521-B* 3
14, and October 9, 1981. A stream stage recorder was installed
on the Quigmy on December 3, 1981. Other than this, the
nearest stream gages with past records are located near
Di 11 i ngham. Si nce they measure primari ly 1 ake out flows, they
are useful only in assessing long-term average flow. The
Eskimo Creek gage (No. 15297900, six years of continuous
record) at King Salmon, 150 mi les to the east, is the only
stream gage potentially representative of the relative varia-
tion in flow anticipated at the Quigmy River site.
Except for a few months of partial record at Togiak, the
nearest precipitation stations are located at Dillingham and
Cape Newenham, both 70 mi 1 es d ist ant. However, these records
over the long term are considered to be a reasonable represen-
tation of the variations in sea-level precipitation at Togiak.
Prior reports Northern Technical Services and Gulik
Associates (1971), R. W. Beck (1981), and DOE (1979) on
stream yield near Togiak have depended principally on the USGS
(1971) statewide report.
D. PROJECT STREAMFLOWS
Both Quigmy and Kurtluk Rivers have perennial flow, as
verified by local residents. The flow regime of both rivers is
seasonal. Higher flows occur from April through November from
spring snowmelt and subsequent rainfall that typically peaks in
October. Winter flows are augmented by groundwater flow
emana t i ng from the wet 1 ands and part i al mel t i ng of snow ina
maritime climate as demonstrated by snowfall records from King
Salmon Weather Station.
A comparison of precipitation records from King Salmon and
Cape Newenham (Table B-1) indicates that the time distribution
of precipitation is similar at both stations. Cape Newenham
has a somewhat higher portion of its annual precipi tat ion in
NBI-384-9521-B* 4
---..
• -
• -
• -
• ..
• ..
• ..
• •
• ..
•
• •
• ..
• ..
• ---
• -
• ..
-
-
-
-
-
',," ..
-
..
October and November than at King Salmon. Significant amounts
of precipi tation and concurrent partial snowmel ting in winter
contribute to runoff. Hence, the variabili ty of streamflow
within the basin is not expected to be extreme and the stream-
flow regime should have characteristics simi lar to the gaged
Eskimo Creek near King Salmon. The analysis of daily flows at
Eskimo Creek indicates that the mean annual flow is exceeded
approximately 32 percent of the time. The 90 percent exceed-
ance discharge is about one-third of the mean annual flow.
1. Mean ~nnual Flow
No streamflow data on Quigmy River exist except a few
sporadic point discharge measurements taken by various consult-
ants. As part of this study, a stream gaging station is being
installed approximately 500 feet upstream of the proposed
damsite.
The paucity of available data dictated that the following
estimating techniques be used to determine streamflows within
the region of interest:
• modified rational formula
•
•
regional analysis
channel geomorphology
Each one of these methods was appl ied to the study area to
determine values for mean annual flow.
a. Modified Rational Formula
Application of the modified rational formula is
explained in detail in the Ebasco report (1980). Only the
salient features of the method are provided below. The method
requires that a gaged stream within the study area having
NBI-384-9521-B* 5
similar weather patterns and groundcover to the ungaged stream
be selected. A proportion is then set up, so that
=
where Qg and Qug
streamflow in cubic
area. Factors to
refer respectively to
feet per second and
adjust precipitation
incorporated into this equation as follows:
= (P) + (~H)E
gaged and ungaged
A is the drainage
and elevation are
where P is precipitation adjustment factor between the two
watersheds, ~H refers to the elevation differential and E is
the elevation adjustment factor.
Only Eskimo Creek at King Salmon is fi t to be paired
with Quigmy River due to its proximity, period of record, and
basin and climatological similarity (USGS, 1971). Mean
discharge records of the Eskimo Creek area were analyzed in
conjunction wi th long-term weather records at King Salmon to
determine whether the observed values are "normal" or due to
runoff from wet or dry series of years. A flow adjustment
factor was derived by taking the ratio of average annual rain-
falls during the six-year gaging record to the long-term
average rainfall during the period of weather records. The
resulting factor of 1.05 was applied to the short-term measured
flow of 13.0 cfs. This analysis yields an adjusted mean annual
runoff of 13.7 cfs or a unit runoff of 0.85 cfs per square mile
(Qg/Ag in above equation) for Eskimo Creek.
The precipi tation adjustment factor (P) accounts for
the precipi tat ion difference between the area of gaged and
NBI-384-9521-B* 6
----
• -
• .. -.. --
• ..
• -
• .. ..
• ., .. .. ..
• --..
• -
• ------
-
-
-
-
-
-
-
-
.....
-
.: .... --
-,.
ungaged stream. It is a ratio of long-term average precipi ta-
tion between the two basins. Long-term average precipi tation
for King Salmon is given as 19.62 inches in the Department of
Commerce's Climatological Data Summary. This value would
represent the basin precipitation for Eskimo Creek, whereas
there are no long-term records for Togiak. However, the
Nat ional Weather Service and the U. S. Geological Survey have
drawn mean annual precipi tation isolines for this area. Two
isolines, 40 inches and 80 inches, are indicated on the map in
Figure B-1. The 80-inch isoline is drawn by judgment (based on
three weather stations and runoff from two streams) and corre-
lation between basin glaciers north of Dillingham and similar
data from precipitation and runoff from glaciers on the Alaska
Range. The Quigmy River basin is outside of the 80-inch preci-
pitation and does not contain any glaciers. However, the basin
is mountainous and exposed to the same moist air flow as the
area northwest of Dillingham. The high elevations within
Quigmy River basin are expected to receive precipitation higher
than 40 inches a year. Larry Mayo of USGS, Fai rbanks, has
prepared these precipitation isoline maps and he contends that
the basin precipi tation should be between 40 and 60 inches
(personal communication, November 13, 1981).
No elevation adjustment factors were applied because
the dam site lies below elevation 200 feet MSL according to the
rules established in the Ebasco report (1980). Standard
planimeter procedures were used to calculate the drainage of
100 square miles that contributes runoff to the damsite.
Gi ven the range of prec i pi tat i on adjustment
the mean annual flow for Quigmy River, using the
rational formula, has the following values:
NBI-384-9521-B* 7
factors,
modified
Precipitation
Inches Factor(P)
40 2.03
50
60
b.
2.53
3.04
Regional Analysis
Mean Annual Flow
cfs
173
215
258
The regional method described by Ott Engineers (1979)
was applied first to the gaged stream Eskimo Creek to test its
applicability. The climate in the Bristol Bay area is consid-
ered to be composed of a series of Mari time micro-climates
somewhat similar to the south-central and southeast regions of
Alaska where the method was developed (Miller, 1963); there-
fore, the regional method should provide reasonable estimates.
This method yielded a mean annual flow of 15 cfs with
90 percent confidence limits of 12 and 17 cfs. This predicted
value agrees acceptably with the measured flow of 13 cfs. The
same method applied to the Quigmy River site with a mean annual
precipitation of 50 inches yielded a flow of 290 cfs. The 90
percent confidence limits for 290 cfs were given as 240 and 330
cfs. This range incorporates the higher value calculated
through the rational formula.
c. Channel Morphology
Channel geomorphology can be used to estimate both the
mean annual flow and the mean annual flood by measuring channel
dimensions that have been shaped by these streamflows. The
method is considered to give reliable estimates for some parts
of the Uni ted States where estimating relations have al ready
been defined.
William Emmett (USGS, 1972) applied this method to
bankfull stream geometry along the Trans-Alaska pipeline
NBI-384-9521-B* 8
---
• -
• ---
• -
•
•
• ..
• -
• ..
• ..
• .. .. -
• -
• --...
• -----
-
-
-
-
corridor with reasonable success. His data included four large
streams in the Copper River basin that were potentially appli-
cable to the Bristol Bay area.
As part of the consultant's field work for the concur-
rent feasibility studies, four small streams on Kodiak Island
were measured near st ream gages. The combi ned dat a covered a
range of 19 to 37,000 cfs mean annual flow and bankfull widths
of 27 to 750 feet. Regression analysis of the data established
a consistent relationship between gaged mean annual flows and
the bankfull width of the channels within their vegetated
floodplains. The resulting equation was
Qma ~ .0083 W2 .253 where
coefficient of correlation = .995
standard error of estimate = .12 log units (+32%, -24%)
The width of the Quigmy River was measured in the
field and from an ai r photo of the floodplain two to three
miles upstream of the si teo The average width was 100 feet,
which correlates wi th a mean annual flow of approximately 270
cfs with a standard error range of 200 to 360 cfs.
d. Estimated Flow
A mean annual flow of 220 cfs for the Quigmy River
site is considered to be the best estimate based on available
information and the confidence interval of the various esti-
mates. This value is conservatively low; there is considerable
confidence that the actual flow that is determined by the
recently installed stream gage may equal or exceed 220 cfs, and
possibly be as high as 300 cfs.
The 220 cfs value is also consistent with two current
meter discharge measurements made at the si te and concurrent
NBI-384-9521-B* 9
flows at the Eskimo Creek gage. As shown in the following tab-
ulation these flows bracket the estimated mean annual flows of
220 and 13 cfs respectively.
Date
September 15, 1981
October 9, 1981
2. Flow Duration
Flow (cfs)
Quigmy River
301
131
Eskimo Creek
15
10+
The flow duration curve for a potential hydroelectric site
is the initial tool in sizing the turbine and estimating annual
energy production. Where no continuous record is available at
the site, the information must be transferred from gaged sites
on the basis of their hydrogeological characteristics.
The flow duration curve can be viewed as the time distribu-
tion of flows about the mean annual flow; thus a dimensionless
flow duration curve (the ratio of the flow to the mean annual
flow versus the percentage of time the flow is exceeded) can be
developed for any gaged basin and be directly compared with any
other dimensionless curve. Within certain hydrogeologic
regions, these curves often have remarkable similarity,
particularly within the 15 to 80 percent exceedance interval.
Thus regional curves can be developed. Curves from small,
steep basins with bedrock near the surface and little ground-
water contribution are typically steeper than those from larger
basins that include swamps or lakes and a good aquifer.
The Quigmy site is judged to belong to the latter group and
can be represented by the Eskimo Creek type curve. The Quigmy
River flow duration curve presented in Figure B-3 is based on
an analysis of six years of daily flows measured at Eskimo
Creek. The flows were scaled to the ratio of their respective
NBI-384-9521-B* 10
-
..
• ..
• -
• -
• ..
• ..
• ..
• ..
.,
lit.
• ..
• ---
• --------..
-
-
-
-
-
-
-
-
-
...
--..
-
mean annual flows (220/13). The resulting curve was slightly
steepened to reflect the greater variance in the concurrent
discharges measured at Quigmy and its mountainous upper basin
as compared to the Eskimo Creek basin.
3. Annual Hydrograph
Based on the same data and reasoning that went into
determining the mean annual flow and the flow duration curve,
an annual hydrograph was developed based on monthly flows at
Eskimo Creek.
The Quigmy River annual hydrograph presented in Figure B-4
and Table B-2 was based primarily on the mean and standard
deviations of the logs of the mean monthly flows recorded 'at
Eskimo Creek during the six years of record. The flows were
scaled to the Quigmy site by the ratio of mean annual flows.
Based on the comparison of relative monthly precipitation at
King Salmon and Cape Newenham, limited adjustments were made to
increase the flows in October and November and to decrease the
flows in February and March. The adjusted flows better reflect
the anticipated runoff pattern in the western Bristol Bay
area. The range of monthly means shown in gray corresponds to
roughly seven out of ten years. Thus the average monthly flow
should lie below the indicated range at least one year in ten
and above the indicated flow range at least one year in ten.
E. SPILLWAY FLOOD FREQUENCY
1. Flood Frequency
Estimates of the magnitude and frequency of floods at
remote sites such as the Quigmy River must depend primarily on
regional studies. These studies relate the calculated flood
frequency of measured peak flows at gaging stations to drainage
basin characteristics such as area and precipitation by means
NBI-384-9521-B* 11
of mul t iple regression analysis. The reasonableness of these
estimates can be checked at the remote site by utilizing bank
full channel geometry and high water debris marks in the flood
plain. This type of site evidence is used to make rough esti-
mates of the mean annual flood and the five-to ten-year flood.
Flood discharge at the si te was estimated on the basis of
th ree previous regional hydrology reports: (1) USGS (1979),
Ott Water Engineers (1979), and Woodward-Clyde Consultants
(1981).
The USGS report employs the log-Pearson Type III distribu-
tion to determine flood magni tude and frequency relations on
the basis of data collected at 260 stations throughout
Alaska. The details of the analysis are provided in the
report.
The Ott Engineers report, although developed for the
Chugach and Tongass National Forests on the Gulf of Alaska, is
potentially applicable to the Bristol Bay area.
The Woodward-Clyde Consultants report, written for the City
of Valdez, covers much of the same area of south-central Alaska
as the Chugach National Forest equations developed by Ott
Engineers.
The three sets of flood prediction equations were applied
to both the Quigmy site and Eskimo Creek, the latter providing
an approximate test for this region.
NBI-384-9521-B* 12
--.. -.. ---
• -
• -.. -
• .. .. -• ..
• ..
• ..
• ..
• •
•
• ---
• ---
-
-
-
......
-
-
-
-
-
-
--.. --
BASIN PARAMETERS
Site Area Precipe Temperature Percent of Area
(sq.mi.) (in.) (Jan. mean min.) lake store. -forest
Quigmy 100
Eskimo Cr. 16.1
50
20
o
5
PREDICTED FLOOD FREQUENCY AT QUIGMY SITE
Method Peak Discharge for Recurrence
(years) 2 10 25 50
USGS (cfs) 2300 4300 5100 6300
(Standard error) (77%) (79%) (59%) '(68%)
Ott (cfs) 1900 4600 6350 8100
Woodward-Clyde (cfs) 3500 6200
PREDICTED FLOOD FREQUENCY AT ESKIMO CREEK
5
14
Interval
100
7700
(>80%)
10,100
7700
Method
(years)
Peak Discharge for Recurrence Interval
2 10 25 50 100
USGS (cfs) 130 270 330 420 540
Ott (cfs) 70 230 320 420 540
Woodward-Clyde (cfs) 120 220 280
There is reasonably good agreement among the estimates.
The exception is Woodward-Clyde's Eskimo Creek values, which
are extremely sensitive to even the small percentage of lake
area within the basin.
NBI-384-9521-B* 13
Al though the 12 years of flood crest records at Eskimo
Creek are inadequate to determine reliable flood frequencies,
the mean annual flood of approximately 110 cfs and the maximum
observed flow of 227 cfs (June 1977) agree favorably with the
related two-year and ten-year predicted values respectively.
Near the Quigmy site, a bank full capacity of 1800 cfs was
estimated based on a 100-foot channel width and channel
geometry work of Emmett (USGS, 1972). A highwater mark
surveyed in the power plant tailwater rating section below the
dam site corresponded to a discharge of 3000 cfs. The regional
est imates for the Qui gmy si te therefore appear to be qui te
reasonable.
The adopted flood frequency at the Quigmy site based on the
USGS equations is presented in Figure B-5. A second curve
corresponding roughly to the upper limit of the standard error
of estimate of these equations is also shown for reference.
The st andard error is an ind icat ion of the reI i abi 1 i ty of the
prediction equations. The reference line indicates that there
is roughly an 85 percent chance that the true flood frequency
is less than the standard error. Verification by flood flow
evidence at the si te further increases the confidence in the
adopted flood frequency.
2. Spillway Design Flood
The selection of the spillway design flood involves far
more than estimating the flood frequency at the site. The risk
(flood frequency) that the owner accepts should be carefully
balanced wi th the actual hazard created by dam overtopping.
Based on the Corps of Engi neers ' gui del i nes (COE, 1977), the
very remote Quigmy site, with its lack of downstream develop-
ment, belongs to the lowest hazard classification. In essence,
f ai 1 ure of the dam is a hazard on ly to the owner's invested
capi tal. Furthermore, overtopping of the concrete gravi ty or
NBI-384-9521-B* 14
• -
• -..
• -
• -
•
•
• ..
• ...
• ..
• ..
• ..
• -
• -
• ..
• ..
• ---
• -
•
iii
-
-
-
-
-
-
-
-
-
---
...
--
--...
-
...
rockfill dams being considered at the si te is not synonymous
with failure, even though significant damage would occur with
massi ve overtoppi ng. Depend i ng on the pI acement and design of
the powerhouse below the dam, a major overtopping would risk an
estimated 10 to 30 percent of the total project investment. As
backup diesel power will be required in Togiak in any case, the
liability for power disruption is limited to the fuel costs.
The size of the Quigmy dam and impoundment falls in the
Corps' small to intermediate classification. The Corps
recommends a spillway design flood near the 100-year-recurrence
flow for this size of dam. A more conservative approach would
be to design for a 10 percent chance of incipient overtopping
at any time wi thin the 50-year estimated useful life of the
project. This corresponds to' a 500-year flood or 11,000 cfs
projected on the frequency curve in Figure B-5. Massive over-
topping (five feet over an 80-foot rock crest) would have a
four percent chance of occurring during the project life, or a
0.08 percent chance in anyone year.
The owner should decide the level of risk he wishes to
assume. In the interim, a spillway design flood of 11,000 cfs
is recommended for the purposes of the feasibility study. This
value may be reduced by routing the flood through the reservoir
surcharge storage capacity if detailed topography is available.
F. CONSIDERATION OF POTENTIAL RIVER ICE PROBLEMS
1. Formations of River Ice
The occurrence and condition of the ice on rivers and
reservoirs may require protection of water intake points from
blockage. Several types of ice can form i n natural ri vers.
One is called "sheet ice" and it occurs mostly on stagnant
bodies of water and slowly flowing streams. This ice usually
originates wi th plate or border ice and gradually propagates
NBI-384-9521-B* 15
across the water surface until a continuous sheet is produced.
Another type of river ice is called "frazil ice."
by nucleation of slightly supercooled turbulent
forms of frazi I ice are d ist i nguished: act i ve
It is formed
water. Two
and passive
forms. Passive frazil ice is not considered as detrimental as
active, which sticks to any solid object at or below freezing
temperature in the river. I f the act i ve frazi I ice adheres to
the river bottom, it may contribute to the formation of anchor
ice. One other form of river icing refers to a mass of surface
ice formed by successive freezing of sheets of water that seep
from a river. A river ici n~ (to which the term aufeis is
commonly restricted) is more particularly the mass of ice
superimposed on the existing river ice cover.
2. Estimates of Ice Thickness
The thickness a natural ice sheet can attain depends upon
the cool i ng potent i al of the atmosphere. I n wi nter th is is
often expressed in freezing degree days, and the thickness
reached at any time is expressed in terms of the square root of
the degree days. Al though several reI at ionsh ips have been
developed to estimate ice thickness as a function of the
cooling potential of the atmosphere, Stefan's simple equation
(1889) is presented here to provide rough estimates of ice
thickness. The Stefan equation in its original idealized form
does not include the effects snow cover, wind, surface rough-
ness, and other physical parameters. The following expression
of Stefan's formula
H = a rFT
incorporates a coefficient a that presumably accounts for local
effects such as snow cover and snow conditions. Values of a
are given
index and
in the followi ng tabul at ion. FI is the freezi ng
refers to the number of degree days below freezing
NBI-384-9521-B* 16
• ... ..
III
... .. ..
• .. .. ..
• .. -.. .. .. ..
II ..
• ...
... -.. ..
• ..
• .. --
• -
• •
-
.. -
-
..
-
...
-
-
-
-
-
...
...
-
..
-...
for one year. Freezi ng degree days or freezi ng index values
are obtained from NOAA climatological records.
For the four small hydropower locations studied for this
contract of which the Togiak Hydroelectric Project is a part,
the followi ng values of a and FI have been chosen and the
resulting river ice thicknesses are indicated .
Site a --
Togiak 0.65
King Cove 0.40
Old Harbor 0.40
Larsen Bay 0.40
FI (oF-day)
2225
1400
1500
1400
H (inches)
30
15
16
15
Est ima tes of river ice th ickness are provided to ai d the
design of proper hydraulic structures and protect them from ice
problems such as ice jams, icing, and improper placement of the
intake. Note that these ice thicknesses are theoretical values
and do not include the effects of wind, flowing water, and
currents and snow cover.
3. Frazil Ice
More severe problems could potentially be experienced from
frazil ice formation at the water intake point. Since very
little is known about frazil ice formation, evolution, and
subsequent disposition, rational design methods to avoid
frazil-ice problems are lacking.
Frazil ice formation has been observed at Midway Creek, Old
Harbor, and Humpy Creek darn site in Larsen Bay. Particularly,
Humpy Creek darn site appears to produce considerable frazil ice
under natural flow condi tions. Del ta Creek darn si te at King
Cove may also experience similar ice problems. The Togiak
Quigmy River project si te has been observed to have floating
NBI-384-9521-B* 17
ice blocks and ice jams that develop at naturally constricted
channel locations. During the installation of a stream gage in
December 1981, release of water from an ice-jammed reservoir
upstream caused the stage to rise approximately three feet.
Considerable quantities of floating ice blocks have been
observed following the rise in stage.
While few data are presently available, it is clear that
the potential ice problem cited above must be considered in
depth during the design phase of project implementation. These
in-depth considerations should include an evaluation of condi-
tions that cause ice problems, the extent of the problems to be
encountered, and potential measures to alleviate or mi t iga te
the problems. About 22 percent of the project energy would be
produced during the coldest winter months from December through
March. If a portion of this energy were lost because of ice
problems, the economic feasibili ty of the project might be
affected. Mitigation measures would be implemented, of course,
to control the problem, but the chance remains that some energy
might be lost. As mentioned, this will be studied in detail if
the project proceeds to the design phase.
NBI-384-9521-B* 18
• -
III --
• ..
..
• -•
'* .. ..
• •
• ..
• ..
•
.. ..
• ..
II ..
• ..
--
•
•
I I I I I I I
TABLE B-1
AVERAGE MONTHLY PRECIPITATION
Jan Feb Mar
King Solomonl./ 1.01 .91 1.12
Cape Newenham~./ 1.78 1.24 1. 51
ESTIMATED
Jan Feb Mar
Average 99 72 126
High 137 87 230
Low 72 60 69
~/1942-80 record
~/1970-81 partial record
NBI-384-9521-B-1
(inches)
AEr Mar Jun Jul Au~ SeQ Oct
.96 1.14 1.53 2.15 3.22 2.83 2.12
1.46 1. 72 3.06 3.34 5.45 5.04 4.95
TABLE B-2
AVERAGE MONTHLY FLOWS AND DEVIATIONS
(cfs)
QUIGMY RIVER
AEr Mar Jun Jul Au~ SeE Oct
281 238 208 203 219 264 458
425 510 268 287 355 400 693
186 111 160 144 135 175 302
I I j , I I
Nov Dec Annual
1.41 1. 22 19.62
3.26 2.27 34.55
Nov Dec Annual
309 153 220
490 202
195 116
I j
!
/
I •
, ••. < /.
I~ H
/
;'
/
~.: 1--,
/«
/
/ .'/
/
r
I ,
I'.l"
---------
~
/
I
i .. I
I I I I j .i f I I , I I • I I I
ALASKA
E A
,----------L-c------l -----
I Pl" 16S-I .... • IbLJ~ :">,-
-a~ __ ~r ____ ... ~~~g:~ ____ ... ~====.s. ____ .r~
Figure B-1 Mean annual precipitation.
\ -..-
TOG1A~ QUIGMY AND KURTLUK
R67W 1 "2 RIVER BASINS
TOGIAK, ALASKA
SCALE 1: 250000 TUDOR ENGINEERING COMPANY
o 5 J 0 \:: I--';';;;';;';';;';"~';';;;';;';;";;;;-~----~, -----; . [:1 ============:::iF==============:3===========:=r ~_ Fig u re -B-2
• ..
• ..
• ..
• .. ..
•
• -
II ..
II
•
• ..
•
• .. -
• -• •
•
• -.. -
• ..
III ..
-
---
-
-
-
-
-
-
-
-
-
-
-
-..
-
1200
1100
1000
900
800
-700 en
~
() -
~ 600 0
...J
I.&..
500
\
\ ,
400 ~
\
300 \
" "-MEA~ ANN UAL F LOW ~20 cfs
200
100
........... ...... ~ ~ ............... -----'" o 0 10 20 30 40 50 60 70 80 90 100
PERCENT (%) OF TIME FLOW EXCEEDED
-~--------------------------------------------------------fill
-
QUIGMY RIVER DAM SITE
FLOW DURATION CURVE
FIGURE
B-3
700~--~--~E-S-T-'~~-AT-E-o~1-R-A-NG-l~0-F-~~v-E-R-J~G-E--~--~J!-~ijt-~~~-~~~~--'---'
MONTHLY FLOWS 7 OUT OF 10 YEARS--~t~}tf~~~
I j~;j~~~~~~~:~:l:l:ljl 600~--~--~--~--~--+---+---+---4----m~8----r--~
••.•••.••.•.••.•.•••.•.••.••.•••.••.•.••.•..•••.•..•..•. : •.
500~--b---+---+---~::~:::::*::::::~:::::~:::::~--~--~--+---~~~--~--~
I .::: ..•.... :.: .•....... : •.. : .... :.:: ...... :: .... : .. ::.: •..... : •...... : ..• ~ .. : .... :: .. :: ... : ...... : •.. : ... : •... : .. ~ ..... ::: •... :::: •... : •. :: .... : .. : ... : •.. :: ...... :.:.: •... :.::: .... : .. ~ •.. : .... :~ ...... :;::.l •...... : •....... ::.: .. :: ... : ••........ ::: ... :! •.. : •........ ::: ... :! .. :::.~ ....... ::; ...... :;.:.j ....... :) •....... : •.... :: .. :J ...... ::.\ .... : .. ::~ ........ :· ........ :I.: ..... : ••........ ::
If·!!!I·
=3; 400~--~--+---~I~ri~I~I~~·.~~*n~I~~~--~--r .. :l .. :l .. :l-.. :l .. :l.~.:; .. :l.:::: .. :l-:::: .. :\:l:::.::.:l.-.::.:.:: .. ::.:.: .. : .. :l.:i.:+. .. :l •.. :! .. :j=.i:.:;i .. :.~.:i .. :i:.:: .. ::~i·.:.l .. :I[.:;:.i .. : .. :lm[ .. :!.:.i.! .. :; .. :.::.f~1 .. :!i .. :i .. ::::I~~.~i.:.:·:: .•. ::.:~:::.I .. :l.:!.::: .• i.:.:.:.m:.:i.:J.:J.:.::.:::.~·.::·.·.:.i.:·.::.:::.~:::l.·:i.·::~!!.:;.:::.!.:I.:·:lm·.:.::·.:I.:i:l:i.:~i.::.:;:.:I.:.:~~:.: --~
••• ··I •• •••••• ••• ·.·! ••• !. ~ 300~--~--+---~::*;~;::·~:\:~~::::~;:::~f~~r::~.:f~~f~--~--~~~~~~~~:~:~~:~:~~:}~~<:~~
100 \.:::.~.:1.\.:\.\.:\.\.:\.\.:\.\.:\.\.::.:.:\.\.: ::::::::::;:;';:;:::' :;:;:;::::'::;:::;:;
•••••••••••••••••••• - -.l\;;··:r. - -
. . . . . . . . . . . . . . . . . . . . . .
;:H\::\\\%\\(
OL-__ L-__ ~ __ ~ __ ~ __ -L __ ~ __ -L __ -J ____ ~ __ L-__ ~~
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
MONTH
QUIGMY RIVER DAM SITE
AVERAGE MONTHLY FLOWS
FIGURE
8-4
• -.. ..
-... .. .. -
•
•
• -• ..
• ..
•
.. ...
• ...
-
• ..
..
• -..
I
• ..
-
-
-
-
-20,000
-
.tMI
,-
--
-
'.... i} -U
10,000
5,000
.-
W 2,000
_(9
0::
<t -r o
-~ o 1,000
tMI
--
----
EXCEEDANCE PROBABILITY
90 80 70 60 50 40 30 20 10 5
. , , .
i
UPPER LIMIT,
ST~NOARD ERROR OF ESTIMATE
2 I 0.5 0.1
.-. ----'--,
.... ,-"j
1 ,. "-'1
" . '''1
.•.. --j
./' __ 1 /· .. 1
" -,.j ., . -'1
1
1
J ,
ESTIMATED FLOOD FREQUENCY . i ,
,
2 5 10 20 50 100 1000
AVERAGE RETURN PERIOD IN YEARS
a. ........ ________ .. ____ ...... __________________ .. ________________________ .. ..
-
QUIGMY RIVER DAM SITE
PEAK FLOW FREQUENCY CURVE
FIGURE
8-5
-
-
-
-
-
-
-
-
-
-
-....
-
-------
TOGIAK APPENDIX B
References
Beck, R. W., and Associates. Small-Scale Hydropower
Reconnaissance Study, Southwest Alaska. For the Alaska
District, Corps of Engineers, April 1981.
Department of Army, Office of Chief of Engineers, Washington,
D.C. Recommended Guidelines for Safety Inspection of Dams,
National Dam Inspection Act, PL 92-367. 1977.
Department of Commerce. ESSA -Environmental Data Service,
Climatological Data Summary, Alaska.
Ebasco Services, Inc. Regional Inventory and Reconnaissance
Study for Small Hydropower Projects: Aleutian Islands, Alaska
Peninsula, Kodiak Island, Alaska. Vols. 1 and 2, Octoher 1980.
Grey, B. J. and D. K. MacKay, flAufeis (overflow ice) in
Rivers,ll Canadian Hydrology Symposium Proceedings: 79,
Glaciology DiviSion, Water Resources Branch, Inland Waters
Directorate, Environment Canada. 1979.
Michel, B., "Winter Regime of Rivers and Lakes, II CRREL
Monograph III-BIA, CREEL, Hanover, New Hampshire. 1971.
Miller, J. F. llProbable Maximum Precipitation and Rainfall
Frequency Data for Alaska," U.S. Weather Bureau, Technical
Paper No. 47, 1963.
NBI-384-9521-BR
Northern Technical Services and Van Gulik Associates, Inc.
"Community Energy Reconnaissance of Goodnews Bay, Grayling,
Scammon Bay, and Togiak." A report to the Alaska Power
Authority, February 1981.
Osterkamp, T. and Gosink, J.P., 'Letter written to Dept. of
Commerce and Economic Development', January, 1982.
Ott Water Engineers. Water Resources Atlas for USDA Forest
Service Region X, Juneau, Alaska, April 1979.
Rhoads, E. M., "Ice Crossings", The Northern Engineer, Vol. 5,
No.1, pp. 19-24. 1974.
Stefan, J. "Uber Die Theorien Des Eisbildung in Polarmere",
Wien Sitzunsber, Adad. Wiss., Sere A, Vol. 42, Pt. 2, pp. 965-
983. 1889.
U.S. Department of Energy, Alaska Power Administration, "Small
Hydroelectric Inventory of Villages Served by Alaska Village
Electric Cooperative", December 1979.
u.s. Geological Survey. "Flood Characteristics of Alaskan
Streams," Water Resources Investigation 78-129, R. D. Lamke.
1979.
U.S. Geological Survey. "The Hydraulic Geometry of Some
Alaskan Streams South of the Yukon River (Open File Report),"
William E. Emmett, July 1972.
U.S. Geological Survey. "Water Resources of Alaska (Open File
Report)"; A. J. Feulner, J. M. Childers, V. W. Norman; 1971.
Wahanik, R. J., "Influence of Ice Formations in the Design of
Intakes", Applied Techniques in Cold Environments, Vol. 1, pp.
582-597. 1978.
NBI-384-9521-BR
• ...
• -..
.. -... -
•
•
• ..
• -
• -
• -• •
•
• .. -
•
.. ---
• ..
• ..
-
-
-
-
-
-
-
-
-
-
-
-
-
--
-
Yould, P. E., and T. Osterkamp, "Cold Region Considerations
Relative to Development of the Susitna Hydroelectic Project",
Applied Techniques in Cold Environments, Vol. 2, pp. 887-895.
1978.
Woodward-Clyde Consultants. Valdez Flood Investigation
Technical Report. February 1981.
NBI-384-9521-BR
......
-
-
-
-
....
-
-
-
-
-
-
-
....
-
-
.,.,. -
-
TOGIAK HYDROELECTRIC PROJECT
FEASIBILITY STUDY
APPENDIX C
GEOLOGY AND GEOTECHNICS
-
-
...
-
-
-
-
..
'"," .. ,--
" ... ..
A.
B.
C.
D.
E.
F.
G.
H.
I.
TABLE OF CONTENTS
INTRODUCTION
TOPOGRAPHY
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
REGIONAL GEOLOGY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
ENGINEERING GEOLOGY -QUIGMY . . . .
Dam Site Geology . . . . . . . . . 1.
2.
3.
Construction Materials/Borrow Sites
Road Location
ENGINEERING GEOLOGY KURTLUl{
Dam Site Geology 1-
2.
3.
Construction Materials
Road Location
SEISMIC HAZARDS
. . . . . . . . . .
. ...
. . . . . . ...
. ....
. ..... .
MECHANICAL ANALYSES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
RECOMMENDATIONS FOR FURTHER WORK
REFERENCES CITED ......................................
i
Page
1
2
4
9
9
11
16
22
22
22
22
23
26
34
35
LIST OF FIGURES
Figure
1 Geol 09 ic Time Seal e ............................. .
2 Reconnaissance Geolgoic Map ••••••••.•••••••••••••
3 Geologic Cross-section ••••••••••••••••••••••.••••
4 Road Location and Borrow Site r1ap ••••••••••••••.•
5 Four-Wheel Drive Trail .••••••••••••••••.••••••.••
6
7
8
9
10
11
12
13
14
15
One-Lane Gravel Road . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
One-Lane Gravel Road (Alternate) . . . . . . . . . . . . . . . . .
Seismic Hazard Map . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Gradation Borrow Site A -Test Pit 1 · . . . . . . . . . . . .
Gradation Borrow Site A -Test pit 2 · . . . . . . . . . . . .
Gradation Borrow Site B -Test Pit 3 · . . . . . . . . . . . .
Gradation Borrow Site C -Test pit 4 · . . . . . . . . . . . .
Gradation Borrow Site D -Test Pit 5 · . . . . . . . . . . . .
Gradation Borrow Site E -Test Pit 6 · . . . . . . . . . . . .
Gradation Kurtluk Area -Test Pit 7 · ............
ii
-...
.---...
II -Page -5 ..
7
10 ..
13 ..
18 ..
19 -21 ..
24 -27
28 ..
29 -
30 •
31 ..
32 • 33 -
" -.,
,.. -....
• -
• -
• ... --
• ..
-
-
-
-
-
-
-
-
-
-
-
-
--... -
-
-
APPENDIX C Geology and Geotechnics for the Proposed Togiak
Hydropower project
A. INTRODUCTION
In si ting a hydropower facili ty, it is important to under-
stand the regional as well as the site-specific geology and geo-
technics. Reg ional information is necessary in order to: (1)
assess the geologic hazards; (2) assure that appropriate design
criteria are utilized; (3) discover construction material borrow
sites; and (4) provide background information for environmental
studies. This report discusses reg ional geology and seismici ty
and specific sites which may prove feasible for development. In
accordance with the Scope of Work for this project, the informa-
tion is intended for use at the preliminary feasibility stage.
This work will be of assistance in determining whether there is a
specific site which warrants a detailed feasibility study.
Recommendations for further work are given in Section XI, Project
Implementation.
Geologic and geotechnical field studies were conducted
September 14, 15, 1981, and October 6-10, 1981, by Dr. R.L. Burk,
Project Geologist and Team Coordinator, and J. Finley, Project
Geotechnical Engineer. Regional geologic reconnaissance mapping
was done from aerial photographs (black and white and color infa-
red) with spot field checking.
-1-
B. TOPOGRAPHY
Togiak is situated near the mouth of the Togiak River on a
broad alluvial plain that extends down to Togiak Bay, part of the
larger Bristol Bay Region of southwest Alaska. The entire area
is part of the Ahklun Mountains physiographic province. The
potential dam sites on the Quigmy and Kurtluk Rivers are approxi-
mately 11 and 4 miles respectively west of Togiak.
Between Togiak and the dam sites, the entire area has been
glaciated and is dominated by bedrock hills which have been
sculptured by erosional and depositional glacial processes.
These bedrock hills are mostly between 500 and 700 feet high and
reach a maximum height of approximately 1100 feet within the
project area. In most areas along the Quigmy and Kurtluk Rivers,
the glacial deposits are thin and the rivers have cut down
through these deposits and excavated narrow slots into the
bedrock.
Numerous lakes and wetlands are locally present as a result
of the flat topography on old outwash channels, current flood-
plains, and the depressions associated with stagnant ice
topography.
The beach area immediately near Togiak consists of succes-
sive beach ridges which have been accreted to the alluvial de-
posits of the Togiak River. Further to the southwest of Togiak,
steep beach cliffs range in height from 15 or 20 feet to approxi-
mately 200 feet. Below the high-water line, the bottom profile
is very shallow. Because of the high tidal variation, large
mudflat areas are exposed at low tide. Deltas and longshore bars
-2-
•
• -
• ..
• ... ---•
• ..,
• .. .. -.. -•
•
• ....
• -
• -..
-
-
-
.-
-
-
-
-
-
-
-
-
-
-
---
-
were observed at the river mouths during fall field work; how-
ever, the major part of the coastal zone was still representing
summer conditions. winter storm waves excavate the materials
deposited by the more gentle summer waves and the river mouth
areas probably are modified during winter conditions.
Above the proposed dam site, the Quigmy River has a drainage
basin of 100 square miles. Above the Kurtluk site, the basin is
20 square miles. Although some meander bends are present, both
streams have many relatively straight reaches.
-3-
C. REGIONAL GEOLOGY
The Togiak area is just north of one of the more active
mountain-building, seismic, and volcanic regions in the world.
The Pacific plate of oceanic crust is being subducted beneath the
North American continental crustal plate in the area of the Aleu-
tian Trench. Associated tectonic forces have caused the uplift
of the Alaska Range and the seismic acti vi ty characteristic of
this part of Alaska (see Seismic Hazards Section). Volcanic
activity is concomitant with subduction zones. As the subducted
plate descends below the opposing plate, it partially mel ts and
the melted material finds its way to the earth's surface to form
volcanoes.
Al though the proj ect area is more stable than some of the
adjacent areas, the presence of aerial photo lineaments suggests
that active faul ting may be present. Judging from the bedrock
outcrops, it appears that some 250 million years ago these rocks
were deposited in an environment similar to the Aleutian Trench
of today. The rock uni ts are considered to be Jurassic (see
Figure 1) in age, given the proximity to similar rocks of middle
to early Jurassic Age on Hagemeister Island (Cady, et al., 1955).
Bedrock in the Togiak area consists of a folded sequence of
sedimentary and volcanic rocks overlain by glacial drift, peat
deposits, modern alluvium and beach deposits. The bedrock has
been assigned to the Gemuk Group (Hoare and Coonrad, 1961) ori-
ginally defined by Cady, et al., 1955. Gemuk rocks in the study
area are predominantly silicified siltstones and andesitic vol-
caniclastic rocks. The siltstones range from very well-bedded
-4-
.. -
•• .. -
• -.. -
•
•
•
.. .. .. -.. -..
• .. -
•
• ..
•
.. ..
• ..
• ,.
GEOLOGIC TIME SCALE
Subdivisions of Geologic Time Radiometric Ages .-
(m I I I Ion s of years
Eras Periods Epochs before the present)
-(Recent)
Quaternary Pleistocene
1.8 -0 Pliocene
-6 0
N Miocene 0 z 22 w -0 Tertiary Oligocene
36
Eocene
58
Paleocene
63
0 Cretaceous --145 0
N Jurassic 0
CJ) 210 w
..." ::;: Triassic
255
Permian
.-280
Pennsylvanian
320
0 Mississippian -360 0
.....
N Devonian 0
w 415 ...J
< Silurian Q..
465
Ordovician
520
Cambrian
580
PRECAMBRIAN -(No worldwide subdivisions)
Birth of Planet Earth 4,650
-Figure 1. Geologic Time Scale.
-... ..
--5---....
near the mouth of the Quigmy River to massive and highly silici-
fied at the proposed Quigmy dam site. Chert is locally present
and limestone has been reported in the Gemuk Group although it
was not observed in the project area.
In
glacial
various regions
advances during
of Alaska there
the Quaternary
have been five
(see Figure 1).
major
The
project area has been subjected to at least two of these events
(Coulter, et al., 1965). The first known glaciation during the
Quaternary occurred in early to mid-Pleistocene time. The second
ice advance was probably in middle to late Pleistocene time and
was less extensive than the previous glaciation.
Glacial drift in the project area consists of abundant out-
wash deposits, till, and ice contact stratified drift deposits.
Glacial topography is expressed by bedrock sculpturing, moraines,
kettle and kame topography, and outwash terraces.
Outwash gravels are present principally in the Quigmy drain-
age down almost to the bay (see Geologic Map, Figure 2). Till
deposi ts are present near the Quigmy mouth, suggesting that ice
blocked the outwash stream, sending it over into what is today
called the Matogak drainage. Alternately, a readvance of the ice
may have destroyed evidence of the gravels near the drainage
mouth; however, this hypothesis is rejected because an abandoned
channel appears to exist between the two drainages. Based on the
distribution of outwash deposits in the Quigmy drainage, it is
apparent that both the Togiak River area and the headwaters of
the Quigmy River were sources for this alluvial material.
-6-
•
-
• ..
• ---
•
" -• ..
• -
• --..
• -• --,.It ..
••
•
•• -..
-.,
·'
11
" -: ....
--"---
'.. \. . 'ocr-_ ---
-".,l:! .:
-t:>'-'" --
TOGIAK BAY
SCALE
Quaternary
IQa"
Recent Alluvium
001
Older Alluvium
Of
Terrace gravels-
glacial outwash •
Mesozoic
Silicified siltstone a
volcaniclastic rocks
locally covered with
colluvium 8 till.
EXPLANATION
Floodplain a abandoned
channel depOsits -Includes
numerous accumulations of
peat . • Active a older stabilized
beach deposits
-Qt -Glacial Till -locally
Includes colluvium a
peat deposits •
Qkk -Kettle a Kame deposits •
Contact dashed where location approximate.
Aerial photo lineament dashed where Jacotlon
approximate •
I 1/2 0 2 3 4 MILES SH=H~H6~~H~~~~~========~~~~========='
CONTOUR INTERVAL 50 FEET R.L. BlJRK 1//8/ DASHED LINES REPRESENT 25 FOOT CONTOURS
~ DOWL
-,ENGINEERS RECONNAISSANCE GEOLOGIC MAP-TOGIAK AREA
Peat deposits mostly
greater than 3 I thick.
w £
FIGURE 2
-
-
-
Till and associated kettle and kame deposits are predomin-
antly found in the western portion of the project area. Locally,
greater than six feet of peat has accumulated in kettles and
other depressions.
Alluvial gravels underlie much of the town of Togiak and the
floodplain area of the Togiak River. Peat locally mantles these
deposits. At the beach front southwest of Togiak, beach gravels
form low beach ridges which have successively accreted along the
coast as material has been supplied to longshore transport by the
Togiak River, other rivers, and beach cliffs.
-8-
D. ENGINEERING GEOLOGY -QUIGMY RIVER
1. Darn Site Geology
Gemuk Group rocks crop ou tat the darn site and are
mantled by stream gravels in the stream bed and talus deposits
(see Figure 3) on one of the side slopes. The bedrock consists
of a relatively unweathered silicified siltstone with local con-
centrations of chert. The rock was fractured and subsequently
bonded by vein fillings approximately one to three mm in width.
Breakage by rock hammer blows is across the veins, suggesting
excellent bonding. Petrographic analysis of these rocks in thin
section showed the presence of quartz and zeol i te as the vein
fillings. This is a common association in hydrothermal veins and
in this case probably represents low-grade metamorphic activity.
The siltstone itself has been compressed into a very hard
competent rock which would be expected to have a high shear
strength and a high modulus of elasticity. In the area of the
proposed darn, the siltstone appears massive, although some poorly
defined bedding is present locally. Joints and cracks are
present; however, they are not viewed as limiting for darn
construction. These features are present in all bedrock
materials.
There is one major crack (see Figure 3) in the cliffs
above the darn. While there is no immediate danger of sliding, it
would be consistent with sound engineering practice to blast away
this semi-isolated block of rock, if it appears it might fallon
any structures. Overhangs should also be blasted away.
Gravels in the stream bottom are present; however,
their thickness is unknown. r·1uch of the stream bed adjacent to
-9-
-
--
•
.. .. -... -
III
.. ..
• -.. -.. ..
•
• ..
• -..
• ... ..
-..
••
l j • f I I J I I. l' I , l til I r--------------------------------------------------------------------------. t
A A'
CRACK~
/[
p I
\ I -~ , I
SILlCI~IEI? -
f---............. SILTSTONE-
"""'"
230
-"--,
........... -..... -.. -............ --..
-........... --
--"'\. -"" -
-~---'-. I -"'-I -
SILICIFIED -"\
I -
210
-, -
- -SILTSTONE 'L -
-L-_
---' -
--L~ TALUS, -
r--~ -I -
WATER LINE ,
---, -
190
--L_ ~---I I -
r-------\ QUIGMY R':F -
--APPROXIMATE CONTACTS --\ ,,":,'--,--,--,-. ~
STREAM ( ."", " ',' ~ ,.
-SEDIMENTS ___ ~ ..•. ~. ~ ..• ' '. _ (SEE TEXT) -",._'.' .. " ..... , 170
--------
-----
SCA~ 10'
GEOLOGY BY: R.L.BURK 1//8/ 10' 0
FIGURE 3
DOWL GEOLOGIC CA S
QUIGMY DAM SITE SECTION -8-
ENGINEERS
the dam site is scoured to bedrock and sediment thicknesses
greater than three feet are not expected.
Blocks of rock have fallen downslope from the surround-
ing cliffs and filled a portion of the stream channel adjacent to
a bedrock knob (see Figure 3). These blocks are up to approxi-
mately five feet in length and could be left in place and
grouted. This is not recommended, however, since at high stream-
flow, water passes through the talus and accumulations of sedi-
ment may wash out after the dam was built. Bedrock is exposed at
water level (see Figure 3) at ei ther s ide of th is lense of
talus. Talus may extend deeper away from the stream between the
bedrock knob and the cliff; however, the depth is not expected to
change more than one or two feet from the talus visible at either
side of the bedrock knob at the stream bank.
Discontinuous permafrost is present in this region;
however, no evidence of frozen ground was observed in the immedi-
ate dam site area. Because of the temperatures encountered in
the Togiak area, all construction materials should be tested for
frost susceptibility.
Groundwater did not appear to be issuing from the bed-
rock near the proposed dam abutments. No problems are expected
from perched water tables or other groundwater conditions.
2. Construction Materials
Rock su i table for riprap needs can be excavated from
the talus pile noted above or it can be blasted from the cliff
walls as part of the construction process.
-11-
..
..
.. -..
.. .. .. ..
III ...
lit
III!
,.. ..
• •
.-.,
•
•
lit
• ..
•
tit
III
•
-
-
-
-
Sand and gravel are available from the uni ts marked
Qtg, Qol, Qal, and Qb on the Geologic Map (Figure 2).
Potential borrow site locations are shown on Figure 4.
Gradation resul ts are given in the Mechanical Analyses Section,
Figures 9 through 14. If about 20 to 30 percent s i 1 t can be
tolerated for construction uses, then material marked Qt can also
be utilized. This material is not recommended for road construc-
tion. Figure 15 shows a typical gradation for till.
a. Borrow Site A
This site is northeast of the Quigmy darn site approxi-
-mately one-quarter mile and it consists of a terrace four to five
feet above river level. Ground cover is composed of willows and
-
-
-
...
---
tall grasses in sporadic open areas. The total area is approxi-
mately five acres.
Soil consists of approximately one foot of organic ma-
terial overly ing one to two feet of organic s i 1 t. Th is in turn
overlies approximately one foot of soil grading from gravelly
silt to silty sandy gravel. At a depth of three to four feet,
clean, relatively well-graded sandy gravel is present (see
Mechanical Analyses Section, Figures 9 and 10).
Because of the depth to gravel and the shallow water
table, this potential borrow site is not recommended.
b. Borrow Site B
This site consists
major terraces which extend
of the middle
south from
-12-
and upper of
the darn site
three
for
" .. '
"
.. ,
I. •
"
,,,
... . ,
. '
li
-t
\
BORROW
SrTE B
BORROW
SITE A
..
-'. h' .,.'
\
t \
\
,ROAD
OPTtoNA
BORRCM'
SITE D
LOCATIONS BY: J. FINLEY RL. B1JRK 1//81
;
/
CONTOUR INTERVAL 50 FEET
DASHED LINES REPRESHfT t5 FOOT CONTOURS
/END OF EXISTING ROAD
~ DOWL ROAD LOCATION & BORROW SITE MAP -I ENGINEERS
~-------------------------------------------------------------------------------------------------
w [
FIGURE 4
-
-
-
-
-
-
approximately one mile. Ground cover is predominantly low tundra
vegetation.
Below a layer of silt and organic material one to two
feet thick, alluvial sands and gravels are present (see
Figure 11). This site appears to be a good source of aggregate
for road construct ion and for concrete aggregate, although the
gravel may require more processing than Site C. These terraces
are glacial outwash terraces and more time has elapsed and hence
more weathering has taken place than in the younger gravels at
Sites A and C.
c. Borrow Site C
This site consists of a stream terrace approximately 15
or 20 feet above the present Quigmy River with an area of
approximately 10 acres. It extends to the river bank and is
approximately one mile south of the dam site.
mostly low tundra species with some tall grasses.
Vegetation is
The gradation shown in Figure 12 is thought to be
representative of this site. This is an excellent gravel source
and the quantity of material available exceeds project require-
ments. Because this terrace is younger than the higher terraces,
the gravel may be of better quality for concrete aggregate. The
principal drawback to this site is its distance from the dam
site.
-14-
d. Borrow Site D
This site consists of an old outwash terrace which
extends along an unnamed tributary to the Quigmy River (see
Figure 2 Geologic Map). Ground cover is low tundra vegetation.
Overburden at this si te is one and one-half to three
feet thick and consists of a sandy silt with organic material.
Alluvial sands and gravels (see Figure 13) are encountered below
the overburden.
terial.
This is an excellent source of road construction ma-
lts location along the proposed road alignment makes it
a valuable aggregate resource.
e. Borrow Site E
This site is typical of deposits formed under stagnant
ice cond i tions. There are layers of re la ti vely clean sand and
gravel and layers of sandy gravelly silt. Some clean material is
probably present in this area; however, a backhoe would be neces-
sary to fully explore the poss ibili ties for road construction
materials at this site. It is not known whether the gradation
given in Figure 14 is representative or not.
f. Borrow Site F
Southwest of Togiak within one mile of the townsite is
a series of beach ridges which have been used for fill material
in the village. These older beach materials are gravelly sands
and sandy gravels which could be used for road construction. The
-15-
• ..
• .. --
• .. --..
• ..
• ..
• .,
..
• .,
., ..
• ..
• -
• -• .. ---.. --
-
-
-
-
active beach materials are also a source of aggregate material.
Because of the salt content, washing would be necessary prior to
use of the material in concrete. The lack of fines in the active
beach materials makes them less desirable for road fill.
The State Department of Transportation has looked at the
_ older beach gravels as a source of runway materials and it was
their understanding that villagers did not want those gravels
used for runway construction (Pavey, personal communication,
-
-
.....
-
1981).
3. Road Location
Two road routes are proposed as part of this study (see
Figure 4). One is from Togiak to the Quigmy dam site (Option A)
and the other is from the mouth of the Quigmy River to the pro-
posed dam location (Option B) •
Option A utilizes the existing road extending southwest
from Togiak and approximately three-quarters of a mile of
beach. It would involve 11.6 miles of road construction. Of
this 11.6 miles, five miles would be on gravel and a minimum of
cutting and filling would be necessary. The gravel (see Geologic
Map Figure 2) is beneath one and one-half to three feet of silt
and silty gravel, probably representing a contribution from wind-
blown silts (loes s) • The remaining portion of the route is on
till and hauling of gravel for fill would be necessary. The
Alaska State Department of Transportation and Public Facilities
is studying the possibility of building a road to Borrow Site D
_ to get gravel for a proposed new airport at Togiak.
--16-
-
I f the State bu i Ids th is borrow haul road, then an
additional five miles of access road would be all that would be
needed to reach the proposed Quigmy dam site. The terrain over
the remaining five miles is flat to gently rolling, with one and
one-half to three feet of sil t overburden on top of good clean
gra vel.
struct.
This portion of the route is by far the easiest to con-
Two levels of road construction were investigated. The
first was an eight foot-wide "trail" for four-wheel-drive
vehicles. No design would be provided. The only engineering
input would be field guidance at the time of construction. It
would be constructed by simply stripping the overburden down to
competent soils. No drainage would be provided. The trail
might not be passable in inclement weather and it would require a
significant level of maintenance.
of a four-wheel-drive trail.
Figure 5 shows a cross section
The second level of construction investigated is a good
all-wea ther road su i table for one-lane travel. The 12-foot-wide
roadbed would be constructed by removing overburden and fi 11 ing
wi th gravel to a height of approximately one foot above the
existing terrain. This would allow the wind to blow snow off the
road. The gravel would be excavated adjacent to the roadbed and
the resul t ing trenches would serve as drainage ditches. Over-
burden should be hauled to low areas to prevent it from acting as
a snow fence and to avoid potential erosion problems. Limited
cu ts and fills would be done to improve grades and al ignmen ts.
CuI verts would be placed in low areas as needed for drainage.
This road would require a low level of maintenance. The cross
section of the one-lane gravel road is shown on Figure 6.
-17-
--
•
!III
• ... -----• -.
•
•
• •
• ..
• ..
• ...
• -• -
• ..
• ---
• -
• -
I J lj ,j ,. II I j l I
8' ~ I-----------------l_ _ __ _
----GRAVEL
SIDE SLOPE AREAS
~E_XI_S_TI_NG_G_R_OU-N_D~~-____ t ___ ~ __ -1 ____ ----'~ __ __r_o-e-~-~~-~-~-~-iD-N---~
ENGINEERS ~ DOWL
:3 OVERBURDEN Il,....!~~~------=~-=--L--=--:.=::....::..:...~
6"'" , ", ',-" '. , . ~-. '-.-~,'. A .,-':..~'..c;,. . -~::'J>-q. A"""
,. A, '.6 C>'" -' '. .. D' , . ...' 0 --. -" 4 -", -GRAVEL
" '. "', ' , .-,:' ,P : , ... :. ,:, ~ , ',~ ~ "'. ::.' -'<3 _~ , .. J:'" " " -' ....
LEVEL AREAS
NOT TO SCALE
FOUR-WHEEL DRIVE TRAIL FIGURE 5
12'
'. . . -. ~ '--' .
J • J ( ,. --.
: po,;'--I. ....... /:." ';,.'
...
-'
A .. Q .... " "...... .' .L , .--=-.. ".. ,.. ., .. "
. -.... -I
EXISTING GROUND
o -~ ." " '-: ',' ,
. . ..... o· .%.'. .. •
........ " ..... .. , . . \.. ... ..
ENGINEERS
, DOWL
SIOEHILL AREAS
12'
112 " .. ,., .. ~ " ...... I ~" ,.,... '-_--L_-'-=--_
. ~() ~RAVEL.: ,FILL", ~'''' ... '.
" .. " .. -.... ' . ... ~ ... " .. -. ~ ..
." ....... , _ .,. ~ ... \t,". "'-.' .A . 6 a; • \. .... -~ ,. . ... .. '*' ~ ~ b" ~; • ~ ... , ~_
LEVEL AREAS
SECTIONS USED FOR GRAVEL
AREAS WHERE OVERBURDEN
IS 24" OR LESS
--:..
ONE-LANE GRAVEL ROAD
12"to 24' OVERBURDEN
EXISTING GRAVEL
GRAVEL FILL FROM EXCAVATIONS
ADJACENT TO ROAD
NOT TO SCALE
FIGURE 6
I I I • I I I • I I " I' II II II •• • I I. •• II I I I I 'I "
"'"
. '
... ,
-'
,,.,
.... . ,
.-,.,
.,
••
.. ,
As an alternative in areas where the silt layer is
greater than 24 inches, gravel fill could be hauled from borrow
si tes and placed directly on the ground surface after organic
materials had been stripped away (See Figure 7) .
-20-
12' /
__ A :~ ,": EXISTING GRAVEL --,' :' ~ 'p, 6 ,J? ... ,.':. .... ~ .. ..
"t::' ",. .1:> ." , . , .. ~ ...
; GLACIAL TILLf
SIDEHI LL AREAS
EXISTING GROUND
DOWL
ENGINEERS
24" MIN,
..,.-/ GLACIAL TILL j
~, A..', 4, - . -,,' Q' .'. ;. : ,,' ,
~ .. -." • c <l ... 0'
24" to 36' SILTY SOILS
:,-': EXISTING GRAVEL
:. I : ,..-,; u .. :" QI ~ ..,," .. . ....
LEVEL AREAS
SECTIONS USED FOR GLACIAL OR
GRAVEL AREAS WHERE OVERBURDEN
IS GREATER THAN 24"
ONE-LANE GRAVEL ROAD
STRIP ORGANICS IN FILL AREAS
GRAVEL FI LL HAULED FROM
BORROW AREAS
NOT TO SCALE
FIGURE 7
I. I • • • I I • I •• I I ,. I I I. " " ,. I. •• • I • I I. I I
, ....
'.:lP'
-,
.......
....
.....
.... ,
.'
<III,
.. ,
.. ,
E. ENGINEERING GEOLOGY -KURTLUK RIVER
1. Darn Site Geology
Gemuk Group rocks crop out at the darn site and are
mantled by alluvial sediments in the stream bed. The bedrock is
an altered volcan iclas t ic rock wi th simi lar outcrop
characteristics to the silicified siltstone at the Quigmy site.
The volcanic breccia is probably andesitic in composition and is
a competent rock which can be used for an abutment. There are no
apparent geotechnical problems at the darn site itself .
2. Construction Materials
riprap .
The rock at the darn site is suitable for use as
Sand and gravel are not available near this site (see
Figure 2). Some arrangement would need to be made for us ing
older beach deposits or to bring gravel in from near the Quigmy
site.
3. Road Location
Approximately three miles of new road would be needed
to tie the darn si te in wi th the existing road northwest of
Togiak. Some areas
most of the area is
of peat would need to be crossed i
overlain by till (see Figure 2).
however,
Cutting,
filling and hauling of gravel would be necessary over almost the
entire length of this road.
-22-
• ..
•
•
F. SEISMIC HAZARDS .. ..
Southwestern Alaska is part of an intense seismic zone ..
which circumscribes the Pacific Ocean. Most of the more than
150,000 earthquakes that occur worldwide each year occur in this
Circum-Pacific bel t and in a somewhat smaller bel t which extends
through southern Asia and the Mediterranean.
Past earthquake damage in the study area has been
principally manifested in five separate forms which can act
independently or in combination.
•
•
Surface faulting -major and minor faults are present
in the Togiak area; however, the rock and unconsoli-
dated surficial material along the road and transmis-
sion line does not appear to have been subject to
fault slip.
Strong ground motion -over a 50-year design period,
the maximum rock acceleration expected (probabili ty
of exceedance = 10%) is 10%g (see Figure 8). This
figure was prepared using actual earthquake epicenter
and magnitude data for Alaska.
• Ground failure -minor landslides have occurred in
this area in the past; however, no major slides that
would affect the integrity of a dam or road and
transmission I ine are expected. The sites are in
bedrock.
• Seiches these are long-period oscillations of
enclosed water bodies and that could affect the
-23-
• ..
• ..
•
• ..
• ..
• .. .. .. .. .. .. ..
•
• .. --.. -.. ---
il II .. ..
170 '80 170 180 '50
DOWL
ENGINEERS SEISMIC RISK MAP -Peak Rack Acceleration FIGURE 8
o
proposed reservoir. However, because of the
small reservoir size, the destructive impact
would most likely be minor.
Tsunami -seismic sea waves could affect coastal
areas, inc luding the town of Togiak but not the
dam sites.
-25-
.. .. .. -.. .. ..
..
.. .. ..
lilt -..
• ..
• ..
• ..
• .. .. .. .. ---
• -.. .. .. ---
....
iiOj'
.....
--
....
.. ,
.-
-
-
G. MECHANICAL ANALYSES
-
-
-
-
-26--
I i I j I i I ( I I t t
@ Alaska Testlab 4040 "B" Street Anchorage, Alaska 9950] Phone (907) 278-1551 Sheet of~_
w. O. No. D13470
Date 10-14-81
Technician _ ~~ _____ _
Textural Class _Sandy_flrave.L _____________________ _
Frost Class ___ . -NES-------Unified Class --.GW _______ _
Client ______ Alaska _Power Authoxity
Project _______ .1'Qg;!..;:!klIy_dropowE:!r
PlastIc Properties_____ _ _________ _
Date Rect'ived _..1D.::_ll-B.L __________________ _
Sample Number 3829 _._
Location__~9r_:r.9W Site A TP-1
Sample Taken By ___ .J.i' ________ _
US STD cu,,", 0/0
SIEVE PASS -------
0 a i~ 08 ... • .-
! J -IT t
I Lr
-------
-----t 3
---
1 2
1 1/2 100
93 ... 3/4 85 x
!! 76 .. 112 • ----.. 3/8 62 •
c 4 40 .. 21 .. 10 c --c 20 11 0 u .. 40 4 z --w 1.2 u 100
or: 200 1.0 .. .. 0_02 MM
---------
Figure 9
Borrow Site A
Test pit 1
Sheet of
W.O.No. D13470 ® Alaska Testlab Anchorage. Alaska 99503 Phone (907) 278-1551 4040 "8" Street
Date ___ 10-14-81
Technician SN
Client Alaska Power Authority ---'----
Project __ =-=-=-~=Togj.~K3Iyqropo:W~r-'---~~.=.~=-=~-=-==
Textural Class .. ___ Gr~vel ____ .. ____ _________________ _
Frost Class. ____ NFS _____________ Unified Class __ .GW ____ _
Sample Number, 3830 ___ __
Location .~9.!::r()w !:i:i,tE;! A TP -2
PI ast Ie Pro perties __________ ... _ . ___________ ._____ __ __ ___ 'O __
Date Rccl'ived ~-=1J -:-8_1 ___________ _
Sample Taken By ...J:~ ______ ._ _ _______ . ___ .
~~~-----~~~~------------------------~.--------------------------------r-~ ~----__ ------_ ~ ___________________ ~S~IE~V~E~_.~~A~N~A~L~Y~S~IS~~~~~~ __ ~~ __ ~~ __ ~ ____ ~H~Y~D~RONETER ANALYSIS US STD CUM 0/0
5 II [ 0 f OPUIlItG IN INC H [~S ____ .......L __ ~N~UIoI:""..~Ee!'II~Of~ .. ~E:._'!S~H~P£~R~_"'N~C~H~U~S~ST!..!.~N'_""D.l~"~D'___::!-________ --"G~II!!'.,'.'!N.....2S~IZ~[='_" N'!" ~ ~ 8 ~! ~! ~ U 0888 § 8 §-s,.---§:-:---g-'-----1
'00 ~ t t "t j 1-r"; o! • r ~ -·0 ~ + +-tt~\ I . u' t ------·l.·~ ~0r_:_-----+-~----+-~--~-+--+-~--~--+-+----~~+-+-~--+-----~~~~~+---~--~~ ~ ~ ~ . _ _t· . 1 '_ .f·J ... _ _._ f-~== .0 f------++-+---+--+ \-t-+.-t-+--t--+----f--i----++----If-+-l-+--+-+-----JI-+++-+--+-------U-t-l-+--l-+-+---l----·------·----J-zo L1 '. V--J -:: . H-···· l-~ f-f---f--f---t} f-.-~.~ -.::==
... . -I-t -t 't---j r t j --:" ------= ~ lC f----. • t ~ ~ ... ~. +_ __ t I--r-<i>--·----H--I-·+>--+-·f~-+--+---~!Htr++--I-+-.-__ ~t--::--__ -... ~-~-so
; 60 ~~ .:; +··1\ f---f,' t. -t--t . + . ... . t "--" --
k .,+-,--. ... 1 j ... _40 11 -1 .-f---.... + '1" 'O-f--~f-'f--'--f-' .--~ -. .: --r\--'.~ +---+-. ----~--=
:~~-:-~~T~,tHi~++.-.-~t-.+-~~-~+--.~f-~--.• +~-~~rf+.-1~~+.--~++ .. ~~-.-_~-4~~:~~~~~-~---~~
! .. j t -.--. T' ... . ---t 'f_ . -.-u.o ~: .. ~-~~-~--.---~~~~-~~.~~~~--~~----~---~~~-~-·~r--~-~---H~~~-'--~--------·+~~H++-+-·--+---·--~-~
k T' ". } ~Lt-. '~ .. ' . f_. -
::' -+ t· .. + ~'_'.' .. ' t tt .1 f----
. -. _.-_f--1\ . f.-, . ... -----
-~-t__t--~_t--~~t-i_-t---~t----t_+-t__+·--~--1-~---~~-+~r--+----~~+~~-+__+--~--~70
..
l:
!! ... s
»-•
It ... ..
It
C
0
0 .. z ...
0
or: ...
L
K i ~
f--+-~--~~_+~~_+--~_+--~~ __ ~----r= .-:: .=_. ~_-_' ~~=~_.:. __ .'." -,... f-+-=-= eo
1--' .---. " -' . ---
'0 ___ .t . -'-t---.i, -r-'O-. 1-. -. I--t.-__ .....:,r,-. -, ~..t"""'+,-.. -.----".r.-+--~-.t-f----++--+1------*+-i--I-'+-~f---~f+i+·H-~--~c----I-------=~~~
t-":_:l~lII1ilL .~~ . ...1 . ,ir rT trl..Ll 's~T~-r,-~~. --~. pf--b·¥ ..,-,;4,' """",~ .. ,.~ rr~ .. ~++·-:.::--::t_--------!~tCr-t·f-~-f-~-t----.....:..---Jf---:-'...:...'O :..::..-~....:j-i
L or ~ ~ ~ ~-~ ~ . 2 ---L..'o ........ ",-~ .. ~ ~~ . .J.. ..... '" N ~ ~ 8 ~ B ~ 0 § § .. 3" § ~'OO
....... ''If I ... ,LLI .. (TER!_____ . a 0 8
I I I I I I I I .1 • I I • • • I • , , , I .1 , I I I I I I •
StEVE PASS
~-----
--.--~-.--
3
2
1 1/2 100
71
3/4 53'
1/2 36
3/8 27
4 15
10 7
20 2
40 1
100 0.6
200 0.5
0.02 MM
Figure 10
Borrow Site A
Test pit 2
I I , . I I
• j
I I I I I l ( I I t
@ Alaska Testlab 4040 "8" Streel Anchorage. Alaska 99503 phone (907) 278-1551 Sheet of __ _
W. O. No. D13470
Tpxtural Class ___ ...§ra,,~JJ}' __ E)an9 ________________ _
Frost Clas5 __________ . _____ Unified Class __ S~ ____ _
Plastic Prorerties.___ ________________ ._. ___ .. _______ _
Date RecPlved _____ _
Date 10-14-81
Technician SN
Client ________ E\:La..§~a. Power. _Author~ 1:Y==-_~:--
Project ____________ TQSl,.Q.](_ Hydror>.ow~r __ __ ._
SampleNumber_ 3831
Location _ ... Borrow Site B Upper Terrace_
Sample Taken By ----.J:E..______ _ ___ __________________ _
US STO CU'-4 0/0
SIEVE PASS -----
--------
3
2
1 1/2 100
---"-
97
3/4 88
112 83
3/8 71
4 54
10 34
20 20
40 11
100 5
--
200 4.0
0.02 MM
Figure 11
Borrow Site B
Test pit 3
Sheet of
W. O. No. D13470
@ Alaska Testlab 4040 "8" Street Anchorage, Alaska 99503 Phone (907) 276-1551
Date ___ 10-14 -81
Technician $N _______ _
TexLUral Class __ 9angy ___ G:r:a_y~1 ___________________ _ Client________ __ _bJ.g§ka Powet"A,ut.ho_t:it.Y_
Frost Class ___ NfS _________ Unified Class _GE _______ _ Project ___________ 'l'Qgiak . EydrQPQwer _______ .
Plastic Properties________________ _ _ _________ . ____ _ Sample Number _ _ 3836 ____ _
Date Received 10 11.-81.. _________________ _ Location_____ _______ . Borrow SiteC
Sample Taken By ______ ..JE. ____ _
---------------------------~------------~~-------._--, r----~~--~~ -"S~I~E~V~E __ r_--'A:".'N:'-"A:".'L"_'Y'_'S'-'I"cS~-=_=~_=:_:::____c~._____,_:__=__::_::_c__,__::_~---+_--.!.!H..!.Y=OROWETER ANALY SIS us STD CUM %
~--~-~~~NI~-I~"~IN~C~H£[~S--~-~N~~~8~E~R~~~M~E~S~H~~~R,~IN~C~H~U~S~ST~A~N~~~~~O~ __ ~-----~G~R~AI~N~S~IZ~E~IN~-M~M~~~-----L--~ S_IE_V_E ___ ~~_s_s_
~ • 2 !! ~ 0 ~ i ~ ~ ~ ~! 8 !:; Il &88 § 8 § 8 § 0
00' ~J li~J f --TI----"l'i-: ----'-=r--~---=-;~__=,::!,___T.--~--TJ'-----'_T------l .. r-----l-t--T-J. ··-r-------:1~tJ~· ----'tr-T
T
---;:.. -;-r-_ -__ -.-_-_. ----,.......-r-.---T---r----.---T---~.,
"rr-T-r~ -~ 1--~:-+ r-.~~=-=-=.
~ 00 Jt~; F .~ -.. i~f=c -c.:.c-----~r Cc-c: _~_----=-= 20
~ 1C ~'t:-'t: _ L __ "-t-_ ~ __ _ _ 1__ _~_--f+=-~~ ... L~--i+ 1-c=~-fh 1--~~t:.~-.-_~----= )() ~ 1 -\----~---~ t--.. --~~--t-+ t --
., 60 40
" ~ ~ t -N--+-----1_ l-._. ~ _~' -------. =-= ... ! .• --f---j--,-----z • __ _
... ~J~ r--:~ I "-I _, :10 ~ j: --.1"" -._ ~, ... -'--1 ~_.~.l -1-_ 1 ., -~::.:
~.o~......:....:.::.~r' -------'\; -----...... -, .-. ------;I ---;&0
" --~--4-+ -~-:'\; .. -. _ --. 1-i--Lt-}-,-~
· :: _=;-"1--x~, ~1-+----+-+--t·-1!-----#-4. -.+-,_+-+-----+--_--_-_-_-_~-tl-++--_+_-J!---•.. .J. f-+-------I-~ !---=~·----~----:---l10
=:: _ T. -~. -_~.. ----__ --l_ -_t-_---'~_ .... ~~-t-_-_+. _-._-t_-_.--_.+--++--++------*++--+._--l------.+-.-.--------l-<.~H+----I-_t----I----It---:--=--_._---I_.a
---------.. ~ ~'-. t -
----.. ------10-----+---++-+--+--~-~-+-~-_i-t--~~--~~_+--+--+1-_4-t--_*~+_+_4_--+---~~.+_~~+_-~--~~ -~-4-.... ~~ --------------=---=
o :±~[p~-~-i-tJ ---III r I II l.I:_~ lc.....l...._ . ~rl 14' --!T~-~'::--t±~E-b=!~' rl1f~;..--t-!:.::..---=t-....:..---tf-tt-j-fJ---.t--::J;-____ ---_-Ill-----=-~ -.-
L __ 2 8~:l~~~ 2 0....... • ....... N ~~8~8 ~ o§§a~8 § to
eRAI" Sill I. MILLlMlT[~!
3 10_Q
2 91
1 112 79
67 .... 3/4 58 l<
!! 51 ... 112 •
~ 3/8 46 • . ---------_.
I< 4 _35 ... .. 10 23 I< c 20 10 0 u
.... 40 2
OK ... 100 0.7 u
II: 200 0.5 ... ..
0.02 MM
--------
Figure 12
Borrow Site C
Test pit 4
I I I • I I I • I • I • , I , I I I , . I I I • I I I • I • .1 I I .1 I •
I I i I i I E I I l j I I I j • i
® Alaska Testlab 4040 "8" Street Anchorage, Alaska 99503 Phone (907) 278-1551 Sheet of __
W. O. No. D13470
Date ____ 1 Q. -14 -13_1.
Technician SN
T('xtural Class.Gra'l.eLly.S~:md ___ ... _________ _ Client _____ Alask~ .. rQwer Allth()rity "= .. '~=_~
Frost Class. __ ._. __ ._ . ____ " _. __ Unified Class __ .51' _____ _ Project. _______ Togial5.HydropoW~,r
Plastic Properties _______ .. __ . ___ .,._. _______ ., . ___ , __
Date Received _lQ-11-SJ. __________ . _____ _
Sample Number, 3833 ..
Location B0l:':J::'0w Sl.te D
-----_.-------------,-_._-Sample Taken By ~ _______ . ___ _______ .
______ .S~I':':E:_:V'-"E'---T---"':A':':N:::A'=-L y=S~I~S~:_:_=_::_:_:__=_=___=__c::_:::cc__:_:_::__=_=_:_:c_::-:-::-=__-I H Y DR 0 .. ET E R AN A L Y SIS -----l
1------,-5-=,Z·[ Of OPENIItG IN INCHES NUIoIBfll Of lUSH Pt:R INCH, US STANDARD .-+---'-'-GRAIN SIZE IN M M
:!! ~ ...... N ~ ~ 0 0 0 0• 0.8_ &:NO~"O ~ "'0 ~·8"'8l1!"8 X "'8 ~ 0
I 00 T-, -~ "'TN N -n-"'.~~ ---y .. --~ • .:;2'--_.:;!!=---::a~--="'.:___; .. ___,__'; .. ;....;:.-_;..:;:~-! Q _,.Il __ --y-OCS,.-r,--,lIr'--r--rl)---,r--_~ Q
: i ,~, r ! II II _ _ F~ 0
"--:~-'111-1-c~ , .. +-..j -, I ~,~. ~ f--• , r ' -i",1: . --:, '.+ _. -t-,' f-_ I---f--_ ,'tt. r-+,--_. ~_~ f-;~ 10
: • + t . r J\ .. " . ,. -. --t r . --.. --.-! 7C ~ -I It j .+ ~I'-' --+~I_-_+___l_--_'il----I---_+_-+-t__-+-·-·---t-H+_~I-+---__#__+_+__+__+_-I__--I+1H_+_l~-+_____4---------l
• t , ,---r. \ I\. . --1-., '., . L.:: ti . {. i-1-f-f t ~-1"--J:::::.:-~ )()
~60~~ ~;;~"}t---~~-~+---::-~t__-~~~-'+·-·-'~·+,-·-·+~+--~·~!4-4~~-+--~·~~+H~-~~--~
0: t-:-: :; 1 t· ~'. +1~· _+ t-_.f-_. _____ ,_4O
~~~-~-~~~~~J-'~~-+t-·-~~~-,~+~~--~--··+·~~-H---~~--~~++~--~~~t·~·4~-~-'--~-'~
~ • I t --i'< --, : . ' :t .·r .1...--.~. t -t ., --
... I t, ..... , -.+.... t ' ,--
u .0 ~...: t'1 -- ----, +'\1, __ +_-+---+ ___ 1-._.---1' f-+--+---ft-++--+f--·+---l-------·-+i:r-'H--+--1H'--+-----j-----·-~&O
a --+-.. + .j .,. K-· -, T','} . t+ --1r ,L --'" -+ , <.... . , f! [1 t -.-
a )01-_-.1+.-.~j-4--+~-+--~~--.~",-+--4-4----+:~-----~~--4--·r-~-~~--+4-----1~-t--t--+-··-'~~-"'·--·--·-~~i4'~~4-+-~--4---'-~--~~·-10
~or·--~·+i----~1-·--~i-·~+--I__-4--t--_4--I___+~~---~"t_·~-·~-·,'-:t_~~.·_'~-~,_·_·t_-+~_i+----~++-+-+--t--'~-:---·~t~·'~+_~~~-'+_~~'--_~_--~~
--'-'-' ,. .-' '-' ". -. -, , . , . --., 1-. f---
10 ~ ~----f----t-.. ==---. -,-. ' ~~ .. , . '= ~~ .=
--. ~ '.!' ~,., . , c--
o 8-~ ;llllL_ !---J.-! ' Ifr rr 1.L.l tTl 1,!--11_."---+--'1._".J...LT~~: .... ~~.;1:-'--J--=r.JJ. .... '~~'._±_-·'-_±_--·-·-~·'-· ._-----:l,l~ . ..L.!r-~-+-I-..J--L'_--'L~_-'_-LI--_-_-'-......J-
l ___ ~ 8 ~ ~:i! ~ iii 2 0 • ........ ' '-';-.'. ......... -~ ~ 8 ~ S ~ 0 § § § ~ 8 § to'
. ___ -"8""R A 10. SIZE I. II.LL.M[UII! ____ _
... x
!! ... • .. •
It ... ..
It ..
0
0 ... z ...
0
It .. ..
US STD CUM 0/0
SIEvE PASS -._----
3
2
1 112 100
86
314 80
112 72
318 66
~ ---
4 ,~4
10 39
20 24
40 12
100 5
200 3.8
0,02 MM
Figure 13
Borrow Site D
Test Pit 5
@ Alaska Testlab 4040 "8" Street Anchorage, Alaska 9950) Phone (907) 278-1551 Sheet of __
W. O. N o. _--.D_1.3A~
Date 1 0 -1 4 - 8 1
Technician SN ____ _
Textural Class _____ gravelly __ S.arul ______________ _ Client __________ Ala~.k~LPQwer __ Au.thoti:l:¥-----__
Frost Class ________ . _____ Unified Class ----.S.N=-.EM __ _ Project ________ TogiakHydropo_wer __ . ____________ .
Sample Number _ .3832-_ ___ __ _
Location______ --'I'-win Lakes -...,. Borrow Site E--
Plastlc Properties--rO-=-rl:::g-r-------____________ ~ __
Date RecPlved __________________________ _
Sample Taken By _ JF _____ _ __ . ________ _
.----.---------====~_-~Sc-C'.I~E~V~E===~:~:;A;;N!::.-A~-L"-'Y~S~I-S~ -_ -----cc -~-_--=c-=-c-c----c--c:;--c------cc-.,,-_-::-:-,..-_--,:---:-..,,-_-_-_-_--l-r _-_-_-_-_-!.!.H--'-y--~D-R-O-M-E-T-ER==-A-N-AL-y-S-:I s-_-_-~~~~_==~r---., rU-.-S-S-T-O-'--CU-M-o~:to--'
SllE Of OP£NIHCO III INCHES -=r= IIUN8E11 Of YUH PER INCH US STANDARD GII~III SIlt: IN M. M SIEvE __ ~~_SS_
~ .2 0 ~ ~ ~ ~ ~ ~~ 8! C) 8 o§88 § 8 ~ 8 § 0
"'0 ~rr r r rt~ i · I . J 1---;:_ .. ----...;c_t~t~----';1~J--"":;"-'Trc..;:.....:-;-_ -T_ -_-._~-;-._-.. _-__ ---,=;c.:.-.;..;:-;~-r--;-;-·.-·E~·'
90~-:7 t -1-.·----\.~ .--------+-_----+_ -------t----f---_10
-~-. \ -or· . ~-----. - -. - - ----. ---- --~. ----- -.. --c--------
~tf: f-r ~ .-\-:~-=~. ----~-.. ~ ------=: ~----.--.. f~_-t _ -_-=1--_----f--=-----= 20 _ ~ +1---1-1 - \ ~-~l-j--) -------= ~
I--~--+--;>----t-~-+tt _.. i \ --f-~:--L: i -+ 1-~-=-~ 1; t r-I .t.--::-::...:= so ~
-+--j. t---1 -------,-\-------~ . -t---1--:-_.t t --~
~;~l-···~t-~.~ t~~-+~--·~\~-.~~ .. -~~+-i~-~++-:H--~++~-t--+k+~~t~-~~--~:-=~:
j • ~ -t ----- ------t-+---. t -_ _ .-. _-= .. . . • -t. .-.. ... .--.. . t '------+--ffT--j i~_-~ .. --t-_ \_ _ _ =_-.·_:_l_-_-.f --~~ -__ _ 1 j _ ~ _ _ _= $0 ~
]0 I--_+-r--_ -. ~~-_-_t-nn ~~--. ,--~ ~_-~ r---+---.--:--t.~-: +--_Lt-I --+t_-__ -fl-+f-+--+-_--+._-+-_.--_-_--41+: ++-+_+-+-+ __ =_.+=_::.._--=-_-=-_-....jao ~
_.. \ ... ____ 70
-t ~ -
20r~--+jl-:~j----·~---+~~-~--t--~·-4-~-+-~--1~--~+~-~-~-+--+4--+-r-----i4-+-+-4--~----_H~~~--~"-_+--~------~~
... ~ ._------... --.. ~-.. -.. -- -------. _.-
. ~--.. ~-
." ~ . -) r-.... ---==:
10
1 .....
l-
X 7C ~ ..
a
>-. ., 60 ~~
I[ ...
z
~ ~0
I--..
z ...
U
40
• -.-.... --J ... . -f 1'-..
---------------
I 0 =---+t---4-_-j--I-~I-·--r
o ~± ~[f]l!~--WJ-J!-----!~ILt!---!,
a 8~~~~2 Ii: ~.~ ...
N -
.--
L .RAIII SIU I. MllllIUTEII! _____ _
I I I • I I I I I • I I , . I I I. I. , . • I I I I. I I I •
3
2
1 112
100
314 95
112 92
31B 85
4 66
10 42
20 24
40 15
100 7
200 5.5
0.02 MM
Figure 14
Borrow Site E
Test pit 6
, . I I I I
I I • • I I I I I i I I I I i l j 1
@ Alaska Testlab Sheet of __
W. O. No. D13470
Anchorage. Alaska 9950] Phone (907) 278-1 SS 1 4040 "8" Slreel
Date _____ J 0-11-81
Technician CJP SN
Textural Class Silty Sandy Gravel
Frost Class _____ ~F=J~-~~ ___ -=~: U~ified-C1~~--G~L':_--:~-=-~=
Client _________ ?\laska Power Auth<:>rit.:t~-=--=--.:-=~
Project ____________ TQ9:i._.:tK_Hydrop.Qwe r __ _________ _
Plastic Properties_______ _ _ _ ____________________________ .. _ Sample Number _ 3834 _____ _
Date ReCt'ived __ ill:-_U-::-lU ________________ _ Location ___ __ _.Kurtl uk_ River Darn Site_
Sample Taken By __ gK _____________________________ _
US STO CUM 0/0
SIEVE PASS
3
2
1 112 00
94
0-314 84 x
!! .. 112 72 s .. 318 69 • ., 4 61 ... .. 10 52 ., ..
20 45 0 u ... .. 40 40 .. u 100 34 ., 200 30.2 ... .. T9.3 0.02 MM
igure 15
est Pit 7
-
-
..
-
H. RECOHHENDATIONS FOR FURTHER WORK
This report is intended for use at the preliminary feasi-
bility study stage. To fully assess the viability of this
project, a detailed feasibility study is necessary. For a
detailed study, the following geologic and geotechnical analyses
should be undertaken:
Road Location -Detailed soils mapping in conjunction with a
drilling and test pit program along the proposed road alignment.
Borrow Sites -Extens i ve dri 11 holes and/or test pi ts to
-determine the best areas for gravel extraction.
....
-
--
-
-
-
-
Dam Site Location -Estimate the volume and quality of rock
to be removed.
Determine the thickness of alluvium in the stream bed .
-34-
-
-
...
-
-
-
...
-
-
-
-
-
I. REFERENCES CITED
Cady, W.M., R.E. Wallace, J.M. Hoare, and E.J. Webber, 1955, The
Central Kuskokwim Reg ion, Alaska: U. S. Geolog ical Survey
Professional paper 268, 132 p.
Coulter, H.~v., and the Alaska Glacial Map Committee, 1962, Map
showing the extent of glaciations in Alaska: U.S. Geologi-
cal Survey Map 1-415.
Hoare, J.M., and W.L. Coonrad, 1961, Geologic map of the Goodnews
Quadrangle, Alaska: U.S. Geological Survey Map 1-339.
Personal Communication
Pavey, Dan, 1981, Alaska State Department of Transportation and
Public Facilities.
-35-
-----------------------------------------
....
-
....
....
-
....
....
....
-
....
-
-
TOGIAK HYDROELECTRIC PROJECT
FEASIBILITY STUDY
APPENDIX D
DETAILED COST ESTIMATE
-
TABLE OF CONTENTS
-
Page
-A. General 1
-B. Methodology 2
'--C. Mobilization and Support Costs 3
-D. Unit Prices 4
E. Access Road to Togiak 5 -
...
-
-
-
-
-
-
-
-
-
-
.....
-
-
-
-
-
-
-
--
-
-
....
APPENDIX D
DETAILED COST ESTIMATE
A. GENERAL
The Togiak Hydroelectric Project consists of three alterna-
tive construction schemes; Al ternative A, a 38-foot concrete
dam; Alternative B, a 28-foot concrete dam; and Alternative C,
a rockfill dam with a spillway. The access road to the project
site requires an analysis of two separate construction schemes
that are the same for each of the dam al ternati ves. Each
al ternative was treated as a separate construction project in
preparing the cost estimate. The following discussion
describes the methodology and presents the backup data and
assumptions used for all three alternatives.
At the outset of the cost estimating procedure for the
Togiak project, it was determined that the unit-cost estimating
method for material placement and other construction activities
would not provide sufficient accuracy and confidence.
Development of construction cost estimates with this method
uses uni t prices developed from estimates and bid tabulations
on similar projects under similar condi tions in terms of geo-
graphic location, weather, accessibility, and other factors
that may affect the cost. When available uni t prices are not
similar in these respects, they must be adjusted to reflect the
actual cost of the construction items under the specific condi-
tions. For this project, the available data base of uni t
prices was not sui table. Typically, uni t prices on remote
Alaskan construction projects vary widely and seem to depend
heavily on a contractor's approach in scheduling crews, trans-
portation, shipping, and work schedules.
NBI-384-9521-D 1
The cost estimate herein was prepared by using the heavy-
construction estimating method and January 1982 costs. This
method treats the project as a separate entity. The construc-
tion cost computations are based on the use of construction
equipment units, labor rates, labor productivity, working con-
ditions, work schedule and sequence, subcontract prices,
permanent material and equipment prices, and special con-
straints and requirements.
B. METHODOLOGY
The preliminary design and layout of facilities for each of
the three al ternatives was used to establish estimated
quantities of permanent and consumable materials and other
measurable items of work such as excavation and embankment
quanti ties. A construction schedule was prepared for each
major item of work based on assumed production rates normally
attainable under similar conditions. Consideration was given
to the remote location, the 60-hour work week, and the short
construction season. Construction equipment of appropriate
size and type for each operation was selected with a view
toward minimizing the number of pieces of equipment and
maximizing the use of each piece.
The manpower from the standpoint of crafts and the numbers
of persons, hours of equipment operation, quantities of consum-
able supplies and spare parts, subcontracted work, and
permanent materials and equipment was estimated for each work
item. Appropri ate rates and prices were appl ied to produce
direct costs of labor, equipment, and materials.
It was assumed that all skilled construction personnel will
be brought to the site by the contractors since it is not known
whether local labor wi 11 be avai 1 able. Tables D-1A, D-1B and
D-1C list the skilled personnel that will work on the
project. They also tabulate the number of man-weeks required
NBI-384-9521-D 2
• ..
•
• -
• '.
• -
•
• -.. -
•
• ..
• ---• .. --
• ..
• -.. ..
III .. .. ..
-
....
-
-
-
-
-
-
-
-
-
for each craft and indicate the weekly wage for each craft.
The wages are based on union scale, including benefits, current
as of January 1982. A work week (man-week) consisting of six
ten-hour days is assumed. If the contractor chooses to
increase the number of working hours per man-week, the weekly
wage will increase, but the overall labor cost will not because
of the trade-offs involved. The overtime labor cost would
increase but costs for such items as subsistence and equipment
rental would decrease .
Also included
nel. A heavy
in the work force are subcontracted person-
equipment moving crew will transport the
turbine-generator assembly from the barge unloading site to the
project site and install it in the final position.
The transmission line subcontract labor force is not
included in Tables D-1A, D-1B and D-1C and it is excluded from
the labor cost; however, the required camp cost to support this
crew of eight is shown. A detailed breakdown of the transmis-
sion line subcontract is presented in Table D-12. The subcon-
tract amount is based on January 1982 costs for power lines
connecting the potential hydroelectric site to existing village
power pI an ts. Loads and distances can easi ly be hand led with
distribution voltages (12.47 kV). Therefore, popular REA-type
assembl ies and conductors were assumed. A typical cross-arm
construction assembly is shown on Plate V, Appendix A.
Equipment costs presented in Tables D-2A, D-2B and D-2C are
based on an hourly ownership rental for 23 weeks plus an hourly
use rate for the actual hours used. The rates used are from
actual costs of operating, owning, and maintaining equipment.
They include fuel costs at Alaskan rates. Material costs are
current costs for the items delivered to Seattle, Washington,
at a barge departure point.
D-3B and D-3C.
NBI-384-9521-D
They are shown in Tables D-3A,
3
C. MOBILIZATION AND SUPPORT COSTS
Due to the remote location of the site, essentially all of
the equipment, vehicles, and supplies required to construct the
project wi 11 be transported to and from the si te by barge.
Barges can operate from several points, including Seattle and
Anchorage. The actual departure poi nt would depend on the
contractor's particular situation. These cost estimates are
based on having a barge depart from Seattle in late April or
early May and using material prices FOB Seattle and barge rates
from Seattle to Togiak (see Tables D-4A, D-4B, and D-4C).
Barge time to the project si te is approximately two weeks.
Tables D-4A, D-4B, and D-4C summarize barge shipping costs both
to and from Togiak.
The construction workers and supervisory personnel will be
housed in a construction camp set up specifically for the proj-
ect. Tables D-5A, D-5B, and D-5C show the overall costs, based
on a uni t cost per person-day assuming that each man-week of
labor will require support for one person for seven days. The
cost includes mobilization and demobilization of the camp and
all other support costs.
Air transportation support costs are shown
D-5B, and D-5C. These costs cover the trips
required for projects of this nature and
personnel turnover rate of about 20 percent.
in Tables D-5A,
that would be
an anticipated
Tables D-6A, D-6B, and D-6C summarize all direct costs
associated with the construction of the Togiak project alterna-
tives. A contingency of 15 percent and a markup of 15 percent
for contractor overhead and profi t are included. The cost of
the transmission line is based on a subcontract cost that
includes a contingency. As indicated, it is marked up by 10
percent to cover the prime contractor's indirect expenses asso-
ci ated wi th schedul i ng and responsi ble supervision.
NBI-384-9521-D 4
•
•
• -
• -
•
•
• -
• -
• -
• ..
• ..
• -• ..
• -..
•
• •
• ..
• •
• ..
• -
•
-
-
-
-
....
-
-
..
-
-
-
Engineering and owner's legal and administrative costs are
added to produce a total project cost.
D. UNIT PRICES
Figures D-lA, D-lB, and D-lC are construction schedules for
the Togiak project alternatives based on a detailed analysis of
the construction activi ties and the information presented in
Tables D-lA through D-5C. All of the direct costs were
assigned to an appropriate category that represents a major
i tern of work. Unit prices were calculated and these are
presented in Tables D-7A, D-7B, and D-7C. They take into
account the assumptions previously used for production rates,
support equipment, and supervisory effort. Page 2 of Tables D-
7 A, D-7B, and D-7C detai Is the content of the various cost
headings and item descriptions.
Finally, a detailed breakdown of unit prices, quantities,
and total cost is presented in Tables VIII-lA, VIII-lB, and
VIII-lC in Section VIII of the report. These are based on the
average unit costs for major categories presented on Tables
D-7A, D-7B and D-7C and modified to take into account the
quantities, scheduling, and location of the specific items of
work within the project area. Therefore, some unit prices may
vary for the same item used on different phases of the work .
Note that the cost estimates prepared for these project
alternatives were not based on the unit-cost method. The unit
prices presented in this report are intended for use in
presenting the general relationship and magnitude of the major
construction i terns for this particular project. They should
not be used out of context because they may not accurately
represent the cost of performing similar work at other sites or
under different circumstances.
NBI-384-952l-D 5
E. ACCESS ROAD TO TOGIAK
The access road to the Togiak Hydroelectric Project si te
considered here is Option A (see Appendix C). For purposes of
the cost estimate, Segment I is about seven miles long and runs
from the end of the Beach Road near Togiak to proposed Borrow
Site D. Segment II is about 4.6 miles long and runs from the
Borrow Si te D to the 'project si te. The subsurface conditions
used for development of the cost estimate are outlined in
Figure 2 of AppendixC. Table D-8 of this section outlines the
assumed terrain conditions, and calculation of quantities.
For Segment I, it was assumed that the soil conditions are
en ti rely gl aci al ti 11 and that all gravel wi 11 be hauled from
Borrow Site D. Minimal excavation and embankment will be done
after stripping to minimize the amount of gravel to be
hauled. The gravel section assumes an average depth of two
feet wi th 2: 1 slopes on the shoulders. Figures 3 and 4 of
Appendix C show typical sections for the two geologic condi-
tions expected to be encountered.
For Segment I I, it was assumed that the route is roll ing
with little sideslope over good gravel, overlain with 12 to 24
inches of silty soil. Approximately one-half of the route will
have 24 inches or less of overburden and will use gravel from
adjacent borrow sources. The other one-half of the route will
requi re haul from Borrow Si te D or other sources if they are
available.
The costs of the two major stream crossing structures were
taken from the Department of Transportation estimates. If a
bridge is required, pre-drilled, treated timber could probably
be used, or possibly a pipe arch or arches.
Generally, it was assumed that construction conditions are
relatively easy and will progress fairly rapidly. No haul was
NBI-384-9521-D 6
• -
• ..
•
• .. --
• -
• ..
• ...
• ..
• -•
-•
• -• ..
• -
• -
• -
• -• •
....
-
.-
-
-
-
assumed for the material produced from stripping ; it will be
spread out adjacent to the road so it will not interfere with
drainage. Culverts will be field located at positions where it
will be necessary to provide drainage or at approximate 1000-
foot intervals in sections where well defined drainage ways do
not exist.
An overall project cost was developed for the simultaneous
construction of Segments I and II from assumed production and
labor rates and equipment and material costs under Alaskan
conditions. The resultant unit prices are summarized in Table
0-9. The mobilization and demobilization cost is the sum of
the transportation and camp costs. The remaining costs were
spread out in accordance with production rates and labor costs
and adjusted to be in accordance wi th unit price information
available on similar projects in the area: the Airport Project
at Di 11 i ngham and the Ai rport Project at New Stuyahok. The
unit prices include an allowance for contractor profit and
overhead.
Two construction schemes were analyzed for the access
road. The first one assumes that a separate contract will be
issued for the construction of the entire 11.6-mile route
(Segments I and II). Table D-10 summarizes the construction
costs for this scheme. It incorporates the methodology and
assumptions previously outlined for the preparation of the
three dam alternatives.
The second construction scheme assumes that the contractor
who woul d bui 1 d the access road to Borrow Si te D (Segment I)
for the Togiak Airport Project would build the upper portion
(Segment II) on a change order. The unit prices used here were
the ones developed for the 11.6-mile project. Twenty-five
percent was added for mobilization and additional contingencies
anticipated for change order work. The construction costs are
summarized in Table 0-11.
NBI-384-9521-D 7
An annual cost 0 f $5800 ($500 per mil e per year) is used
for normal road maintenance. This assumes that the necessary
equipment for maintenance is available at the local community
in conjuction with the existing airport maintenance program.
It is anticipated that normal annual road maintenance will
include:
Grader/Patrol - 2 days
Repair of Chuckholes, Culvert Maintenance
and Miscellaneous -Materials
-Labor
Total Annual Cost
$2,000
800
3,000
$5,800
Table VIII-2 is an overall summary of the three alternative
construction projects at Togiak, each with the two road
construction alternatives.
NB -84-521-
•
• -•
.. -.. -
• -.. -
• ..
•
•
• ..
•
• ---------
• -.. -
"!l:.Ifi!l
-
-
-
,.~
.-
-
..
-
TABLE D-1A
TOGIAK --38-FT CONCRETE DAM ALTERATIVE
LABOR BASED ON 60 HR WEEK
Labor Cost/
(Man-Weeks) Week
General Superintendent 29 $1,986
Superintendents 41 1,758
Operators 95 1,730
Oilers 23 1,575
Mechanics 23 1,730
Laborers 172 1,571
Driller/Powderman 4 1,730
Electrician 6 1,850
Ironworkers 14 1,840
Carpenters 13 1,637
Apprentice Carpenter 12 1,571
Millwrights 2 1,800
Welders, Fitters 6 1,897
Manufacturer's Rep 3
Line Crew (8) 120 Subcontract
Heavy Equipment Moving Crew 3 Subcontract
TOTALS 558 Man-Weeks
NBI-410-9521-D-1A
Total Cost
$ 57,594
72,078
164,350
36,225
39,790
270,212
6,920
11,100
25,760
21,281
18,852
3,600
11,382
10,000
25,000
$774,144
CAT-08K (2 ea)
Compaction Roller
Front End Loader 9660 (2
Flatbed Truck
Dump Truck (10 yd) (2 ea)
Service/Fuel Truck
Pickup Truck (2 ea)
Backhoe -CAT 225
Welder
Generator
Generator Spare
LoBoy/Tractor
Airtrack/Compressor
Crane -20 Ton
Batch Plant
65,000 GPM Pump (2 ea)
13,000 GPM Pump
Hand Compactors
Small Mixer (2 ea)
Screening Plant
3" Water Pumps (2 ea)
Fuel Tank, Bladder
Cutting Torch, Set
Misc. Equipment
Office Trailer
Pole Setting Truck
Line Truck
NBI-410-9521-0-2A
TABLE 0-2A
TOGIAK --38-FT CONCRETE DAM ALTERNATIVE
EQUIPMENT COST
Ownership Total Hourly
Expense Operating Operating Operating
( 23 wks) Hours Cost Cost
$67,600 ea 300 ea $103.22 $31,000 ea
4,000 50 2.00 100
ea) 18,800 ea 300 30.06 9,020 ea
4,100 400 14.57 5,830
8,350 ea 300 ea 16.87 5,060 ea
10,850 400 17.20 6,880
3,250 ea 400 ea 12.69 ea 5,076 ea
24,900 50 20.37 1,020
1,100 100 5.51 550
510 1,140 .94 1,090
510 200 .94 200
14, 120 200 24.45 4,890
25,350 180 27.00 4,860
23,460 650 22.05 14,330
19,251 420 14.50 6,090
($8,000 x 1.25 mo + $4,000 x 4.75 mo) = 29,000
($4,500 x 1.25 mo + $2,250 x 4.75 mo) = 16,300
1,800 100 ea 1.00 100
250 ea 50 ea 1.00 ea 50 ea
9,300 350 23.75 8,310
500 ea 100 ea 1.00 ea 100 ea
5,000
300
2,000
3,000 1,140 1.68 1,915
Costs contained in transmission subcontract
TOTAL
Total
Cost This
Project
$197,200
4,100
55,640
9,930
26,820
17,730
16,652
25,920
1,650
1,600
700
19,010
30,210
37,800
25,341
ea 58,000
16,300
1,900
600
17,610
1,200
5,000
300
2,000
4 2 915
$578,200
I • I I I I •• I. I I I' 'I " 'I • I ,. 'I I I , I I I •• 'I I I
-
-TABLE D-3A
TOGIAK --38-FT CONCRETE DAM ALTERNATIVE -MATERIAL FOB SEATTLE
......
Unit
Item Quantity Unit Price Amount -
~ 1. Cement Type I 24,780 Bags $ 4.73 $117,209
2. Reinforcing Steel 11,845 Lb 0.35 4,145 -3. Steel Pipe - 8 Ft. Dia. 195 LF 400 78,000
4. Slide Gates -8 Ft. 2 Ea 10,000 20,000
5. Slide Gates -5 Ft. w/hoist 1 Ea 20,000 20,000
~
6. Explosives 4,100 Lb 1.00 4,100
7. Penstock -5 Ft. Dia. 50 LF 200 10,000 -8. Misc. Building Material 1 Lot 25,000 25,000
9. Turbine Generator Assy. -Includes Switchgear LS 540,000
10. Electrical & Mechanical
Accessory Equipment
~ and Materials 1 Lot 92,000 92,000
11. Fuel for Pumps 21,000 Gal 1.25 26,250
12. Pump Discharge Line 330 LF 200 66,000
13. Forming Materials 1 Lot 56,000 56,000
14. Misc. Structural Steel 10,000 Lb 0.30 3,000
.,W 15. Trashrack 1 Ea 4,000 4,000
-MATERIALS FOB SEATTLE DOCK $1,065,700
-
-
-
-
NBI-410-9521-D-3A
-
Haul
Class
A
B
C
D
F
G
I
J
I
J
TABLE D-4A
TOGIAK --38-FT CONCRETE DAM ALTERNATIVE
BARGE SHIPPING COST
Seattle to Togiak
Weight
Commodity (Typical) (lb) ($/cwt)
St ructural Steel 22,454 8.24
Palletized Cement 2,329,000 6.93
Lumber 60,000 8.00
Poles 128,700 8.00
Steel Pipe, Culvert 136,700 8.24
Misc. Wire, Hardware, etc. 49,185 24.32
Large Equipment, Machinery 728,300 12.00
Trailer 12,000 25.00
TOTAL
Togiak to Seattle (Return)
Large Equipment, Machinery
Office Trailer
TOTAL
700,000 12.00
12,000 25.00
NBI-410-9521-D-4A
Cost
($)
1,860
161,400
4,800
10,300
11,260
11,960
87,400
3,000
$292,000
84,000
3,000
$ 87,000
• •
•
•
• -
• -... -
• -• •
• ..
•
..
• .. .. .. -
• -----
• ---... -
• •
-
-
-
-
-
-
-
-
-
TABLE D-5A
TOGIAK --38-FT CONCRETE DAM ALTERNATIVE
ESTIMATE OF CAMP COSTS
558 Man Weeks
Each week the men are supported for seven days
558 x 7 or 3906 days @ $135 per day
CAMP COSTS TOTAL
ESTIMATE OF AIR TRANSPORTATION COSTS
Bring in crew and small tools -assume 6 men per
flight and 24 men with a Beech King Air.
6 Trips Anchorage to Togiak and back
@6 hrs/round trip
6 Trips @ $2500
Approximately 1500 lbs of freight via Reeve
Aleutian and Air Taxi twice a week
3000 lbs @ $0.75/lb or $2250 per week
19 Weeks @ $2250
40 One Way Trips during construction for per-
sonnel changes & supervisor visits
60 Trips @ $282
Misc. Supply Trips
6 Trips Queen Air Cargo
Remove crews at job close
AIR TRANSPORTATION TOTAL
NBI-410-9521-D-5A
$527,310
$15,000
42,750
16,920
15,000
15,000
$104,670
TABLE D-6A
TOGIAK --38-FT CONCRETE DAM ALTERNATIVE
SUMMARY SHEET
Material FOB Seattle
Labor
Transportation -Barge to Site
Transportation -Barge to Seattle
Transportation -Air
Camp Costs -Catered
Equipment Cost
Prime Contractor 15% Profit
Contingency 15%
Transmission Line -Electrical
Labor & Materials Subcontract
Prime Contractor 10% Markup
Surveying, Right of Way & Geology
Engineering Design
Construction Management
Owner's Legal & Admin. Costs 3%
Subtotal
Subtotal
Subtotal
~ubtotal
GRAND TOTAL
NBI-410-9521-D-6A
$1,065,700
774,144
292,000
87,000
104,670
527,310
578,200
$3,429,000
541,350
$3,943,350
$ 591,500
967,000
96,700
$5,598,600
$ 100,000
435,000
215,000
$ 750,000
190,400
$6,539,000
• .. ..
..
• -
• -
• .. .. -•
..
...
• -.. -
• • ..
•
-• -
• -
• -
• -
I
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
1/
2/
3/
4/
I
TABLE D-7A
TOGIAK --38-FT CONCRETE DAM ALTERNATIVE
DEVELOPMENT OF AVERAGE UNIT PRICES FOR MAJOR ITEMS OF WORK
1/ Material Labor Equipment Contractor Total
Item-Cost Cost Cost Profit (15%) Amount
2/
Mobil/Demobilization $255,840-$154,380 $ 42,830 $ 67,960 $ 521,010
Penstock 17,120 28,530 8,980 8,190 62,820
Rock Excavation 4,200 44,720 126,920 26,380 202,220
Foundation Treatment 0 27,490 10,700 5,730 43,920
Concrete 338,610 543,470 134,440 152,480 1,069,000
Cofferdams 0 90,100 106,820 29,540 226,460
Bypass Line 82,180 34,440 21,960 20,790 159,370
Pumping Cost 43,050 38,460 96,700 26,730 204,940
Pump Di scharge Line 70,620 23,850 20,740 17,280 132,490
Trashracks & Slide Gates 45,300 49,060 1,930 14,440 110,730
Turbine & Generator 640,400 133,250 3,860 116,630 894,140
Cover Powerhouse 25,800 20,340 2,320 7,270 55,730
Transmission Lin~ 26,250 113,340 20,940 160!530
TOTALS $514,350 $3,943,35o!i
These items are described on page 2 of this table.
Includes Barge and Air Support Costs only.
Includes costs over and above subcontract amount only
Amount corresponds with second subtotal on Table D-6A.
NBI-410-9521-D-7A
Unit
Quanti t~ Unit Price
LS $
40 LF 1,567
3,525 CY 57
300 SY 146
2,478 CY 472
2,500 CY 91
200 LF 797
LS
330 LF 401
15,700 LB 7.05
LS
LS
LS
Item
1. Mobil/Demobilization
2. Penstock
3. Rock Excavation
4.
5.
6.
Foundation Treatment
Concrete
Cofferdams
7. Bypass Line
8. Pumping Cost
9. Pump Discharge Line
10. Trashracks & Slide Gates
11. Turbine & Generator
12. Cover Powerhouse
13. Transmission Line
Columns
Material Cost
Labor Cost
Equipment Cost
NBI-410-9521-D-7A
TABLE D-7A
(Continued)
Includes general supervision, barge and ai r support costs,
staging equipment, miscellaneous standby equipment, etc.
Installed, including couplings.
All, including structural, road and miscellaneous.
All required.
All, including equipment,
miscellaneous structural
reinforcing steel.
All rockfill.
material,
excavation
Through cofferdams, and concrete dam.
concrete, forming,
(unclassified) and
Including operation, maintenance and installation.
Installed.
Installed.
Installed, including mechanical, electrical, and startup.
All.
Installed -Subcontract plus shipping, and compo cost.
Material cost FOB Seattle plus shipping.
Salary at 60 Hrs/week plus sUbsistence costs.
Ownership rental plus use rental, based on six months.
• I I I I I .1 II II II ,. I. ,. ,. II I. II 11.1 ••• 1 f •
-
-
-
-
.....
-
....
-
-
-
-
-
-
TABLE D-1B
TOGIAK 28-FT CONCRETE DAM ALTERNATIVE
LABOR BASED ON 60 HR WEEK
Labor Cost/
(Man-Weeks) Week
General Superintendent 29 $1,986
Superintendent 41 1,758
Operators 85 1,730
Oilers 23 1,575
Mechanics 23 1,730
Laborers 148 1,571
Electrician 6 1,850
Ironworkers 10 1,840
Carpenters 13 1,637
Apprentice Carpenter 12 1,571
Millwrights 2 1,800
Welders, Fitters 6 1,897
Driller/Powderman 4 1,730
Manufacturer's Rep 3
Heavy Equipment Moving Crew 3 Subcontract
Line Crew (8 ) 120 Subcontract
TOTALS 520 Man-Weeks
NBI-410-9521-D-1B
Total Cost
$57,594
72,078
147,050
36,225
39,790
232,508
11,100
18,400
21,281
18,852
3,600
11,382
6,920
10,000
25,000
$711,780
CAT-D8K (2 ea)
Compaction Roller
Front End Loader 9660 (2
Flatbed Truck
Dump Truck (10 yd) (2 ea)
Service/Fuel Truck
Pickup Truck (2 ea)
Backhoe -CAT 225
Welder
Generator
Generator Spare
LoBoy/Tractor
Airtrack/Compressor
Crane -20 Ton
Batch Plant
65,000 GPM Pump (2 ea)
13,000 GPM Pump
Hand Compactors (10 ea)
Small Mixer (2 ea)
Screening Plant
3" Water Pumps (2 ea)
Fuel Tank, Bladder
Cutting Torch, Set
Misc. Equipment
Office Trailer
Pole Setting Truck
Line Truck
NBI-410-9521-D-2-B
TABLE D-2B
TOGIAK --28-FT CONCRETE DAM ALTERNATIVE
EQUIPMENT COST
Ownership Total Hourly
Expense Operating Operating Operating
(23 wks) Hours Cost Cost
$67,600 ea 300 ea $103.22 $31,000 ea
4,000 50 2.00 100
ea) 18,800 ea 300 30.06 9,020 ea
4,100 400 14.57 5,830
8,350 ea 300 ea 16.87 5,060 ea
10,850 400 17.20 6,880
3,250 ea 400 ea 12.69 ea 5,076 ea
24,900 50 20.37 1,020
1,100 100 5.51 550
510 1,140 .94 1,090
510 200 .94 200
14,120 200 24.45 4,890
25,350 180 27.00 4,860
23,460 650 22.05 14,330
19,251 420 14.50 6,090
($8,000 x 1.25 mo + $4,000 x 4.75 mo) = 29,000
($4,500 x 1.25 mo + $2,250 x 4.75 mo) = 16,300
1,800 100 ea 1.00 100
250 ea 50 ea 1.00 ea 50 ea
9,300 350 23.75 8,310
500 ea 100 ea 1.00 ea 100 ea
5,000
300
2,000
3,000 1,140 1.68 1,915
Costs contained in transmission subcontract
TOTAL
Total
Cost This
Project
$197,200
4,100
55,640
9,930
26,820
17,730
16,652
25,920
1,650
1,600
700
19,010
30,210
37,800
25,341
ea 58,000
16,300
1,900
600
17,610
1,200
5,000
300
2,000
4 2 915
$578,200
• I I I 'I I I • I I I " ,. I I I I 'I ,. •• 'I I. I. •• I' I.
,..",
,.".
,-
-
~"....,a
' ...
-
..
-
-
1.
2.
3.
4.
5.
6.
7.
8.
9
TABLE D-3B
TOGIAK --28-FT CONCRETE DAM ALTERNATIVE
MATERIAL FOB SEATTLE
Unit
Item Quanti ty Unit Price
Cement Type I 16,600 Bags $ 4.73
Reinforcing Steel 11,845 Lb 0.35
Steel Pipe - 8 Ft. Dia. 195 Lf 400
Slide Gates -8 Ft. 2 Ea 10,000
Slide Gate -5 Ft. w/Hoist 1 Ea 20,000
Explosives 4,100 Lb 1. 00
Penstock -5 Ft. Dia. 40 Lf 200
Misc. Building Material 1 Lot 25,000
Turbine Generator Assy.
Includes Switchgear LS
NBI-4l0-952l-D-3B
Amount
$78,520
4,145
78,000
20,000
20,000
4,100
8,000
25,000
520,000
Item
10. Electrical & Mechanical
Accessory Equipment
and Materials
11. Fuel for Pumps
12. Pump Discharge Line
13. Forming Materials
14. Misc. Structural Steel
15. Trashrack
TABLE D-3B
(Continued)
Quantity
1
21,000
330
1
10,000
1
MATERIALS FOB SEATTLE DOCK
NBI-410-9521-D-3B
Unit
Lot
Gal
Lf
Lot
Lbs
Ea
Unit
Price Amount
$90,000 $90,000
1. 25 26,250
200 66,000
50,000 50,000
0.30 3,000
4,000 4,000
$996,860
• .. .. .. .. .. ..
• .. .. -.. .. .. ... .. ..
• ..
• .,
• ..
• .. .. .. .. -.. -.. ..
• -
•
•
-
-
-
-
-
-
-
-
Haul
Class
A
B
C
D
F
G
I
J
I
J
TABLE 0-4B
TOGIAK --28-FT CONCRETE DAM ALTERNATIVE
BARGE SHIPPING COST
Seattle to Togiak
Commodity (Typical) Weight (lb)
Str. Steel 22,545
Cement 1,561,300
Lumber 60,000
Poles 128,700
Steel Pipe 127,420
Misc. Wire, Hardward, etc. 49,186
Large Equipment, Mach. 724,300
Trailer 12,000
Total
Togiak to Seattle
Equipment 700,000
Trailer 12,000
Total
$
Rate/
CWT
8.24
6.93
8.00
8.00
8.24
20.32
12.00
25.00
12.00
25.00
NBI-410-9521-0-4B
Cost
$ 1,860
108,200
4,800
10,300
10,500
11,960
86,916
3,000
$237,600
84,000
3,000
$ 87,000
TABLE D-5B
TOGIAK --28-FT CONCRETE DAM ALTERNATIVE
ESTIMATE OF CAMP COSTS
520 Man-Weeks
Each week the men are supported for seven days
520 x 7 or 3640 days @ $135 per day
CAMP COSTS TOTAL
ESTIMATE OF AIR TRANSPORTATION COSTS
Bring in crew and small tools -assume 6 men per
flight and 24 men with a Beech King Air.
6 Trips Anchorage to Togiak and back
@6 hrs/round trip
6 Trips @ $2500
Approximately 1500 lbs of freight via Reeve
Aleutian and Air Taxi twice a week
3000 lbs @ $0.75/lb or $2250 per week
19 Weeks @ $2250
40 One Way Trips during construction for per-
sonnel changes & supervisor visits
60 Trips @ $282
Misc. Supply Trips
6 Trips Queen Air Cargo
Remove crews at job close
AIR TRANSPORTATION TOTAL
NBI-410-9521-D-5B
$491,400
$15,000
42,750
16,920
15,000
15,000
$104,670
• -
• ..
• ..
• ..
• ..
• -
• -
• ..
•
• ..
• -•
• .,
• .. ------
• ..
-
-
-
-
.....
-
-
-
-
-
-
-
-
-
TABLE D-6B
TOGIAK --28-FT CONCRETE DAM ALTERNATIVE
SUMMARY SHEET
Material FOB Seattle
Labor
Transportation -Barge to Site
Transportation -Barge to Seattle
Transportation -Air
Camp Costs -Catered
Equipment Cost
Prime Contractor 15% Profit
Con t ingency 15%
Transmission Line -Electrical
Labor & Materials Subcontract
Prime Contractor 10% Markup
Surveying, Right of Way & Geology
Engineering Design
Construction Management
Owner's Legal & Admin. Costs 3%
Subtotal
Subtotal
Subtotal
Subtotal
GRAND TOTAL
NBI-410-9521-D-6B
$ 996,860
711,780
237,600
87,000
104,670
491,400
578 2 200
3,207,500 .
481 2 125
3,688,600
553,290
967,000
96 2 700
5,305,600
100,000
435,000
215 2 °00
750,000
181 2 700
$6,237,300
I • I •
1/
TABLE D-7B
TOGIAK --28-FTCONCRETE DAM ALTERNATIVE
DEVELOPMENT OF AVERAGE UNIT PRICES FOR MAJOR ITEMS OF WORK
Material Labor Equipment Contractor Total
Item-Cost Cost Cost Profit (15'.') Amount Quantity
1. Mobil/Demob. $228,92uY $138,130 $ 38,320 $ 60,805 $466,180
2. Penstock 12,840 21,400 6,735 6,150 47,120 30
3. Rock Excavation 4,200 44,720 126,920 26,380 202,220 3,525
4. Foundation Treatment 0 27,490 10,700 5,730 43,920 280
5. Concrete 240,490 511,430 134,440 132,950 1,019,310 1,660
6. Cofferdams 0 90,100 106,820 29,540 226,460 2,500
7. Bypass Line 82,180 34,440 21,960 20,790 159,370 200
8. Pumping Cost 43,050 38,460 96,700 26,730 204,940
9. Pump Discharge Line 70,670 23,850 20,740 17,280 132,490 330
10. Trashracks & Slide Gates 45,300 49,060 1,930 14,440 110,730 15,700
11. Turbine & Generator 616,000 128,200 3,300 112,120 859,620
12. Cover Powerhouse 25,800 20,340 2,320 7,270 55,730
13. Transmission Lin~ 26,250 113,340 20,940 160,530
TOTALS $481,125 $3,688,60oY
1/ These items are described on page 2 of this table. 2/ Includes Barge and Air Support Costs only. 3/ Includes cost over and above subcontract amount only. 4/ Amount corresponds with second subtotal on Table D-6B.
NBI-410-9521-D-7B
I I I I I I I I I. , I I I • I , . , I I I I • I •
Unit
Unit Price
LS $
LF 1571
CY 57
SY 157
CY 614
CY 91
LF 797
LS
LF 401
LB 7.01
LS
LS
LS
, I I I I • I •
l I
ITEM
1. Mobil /Demobil ization
2. Penstock
3. Rock Excavation
4. Foundation Treatment
5. Concrete
6. Cofferdams
7. Bypass Line
8. Pumping Cost
9. Pump Discharge Line
10. Trashracks 8. Slide Gates
II. Turbine 8. Generator
12. Cover Powerhouse
13. Transmission Line
COLUMNS
Material Cost
Labor Cost
Equipment Cost
NHI-410-9521-D-7B
TARLE D-7R
(Continued)
t
Includes general supervision, barge and air support costs, staging
equipment, miscellaneous standby equipment, etc.
Installed, including couplings.
All, including structural, road and miscellaneous.
All required.
All, including equipment, material, cement, forming, miscellaneous
structural excavation (unclassified) and reinforcing steel.
All rockfill.
Through cofferdams, and concrete dam.
Including operation, maintenance and installation.
Installed.
Installed.
Installed, including mechanical, electrical, and startup.
All.
Installed -Subcontract plus shipping, and compo cost.
Material cost FOB Seattle plus shipping.
Salary at 60 Hrs/week plus subsistence costs.
Ownership rental plus use rental, based on six months.
TABLE D-1C
TOGIAK --ROCKFILL DAM ALTERNATIVE
LABOR RASED ON 60 HR WEEK
General Superintendent
Superintendents
Operators
Oilers
Mechanics
Laborers
Driller/powderman
Electrician
Ironworkers
Carpenters
Apprentice Carpenter
Millwrights
Welders, Fitters
Labor
(Man-Weeks)
28
46
135
23
23
192
9
5
22
14
14
2
11
Cost/
Week
$1,986
1,758
1,730
1,575
1,730
1,571
1,730
1,850
1,840
1,637
1,571
1,800
1,897
Total Cost
$55,608
80,868
233,550
36,225
39,790
301,632
15,570
9,250
40,480
22,918
21,994
3,600
20,867
Manufacturer's Rep 3 10,000
Line Crew (8) 120 Subcontract
Heavy Equipment Moving Crew 3 Subcontract 25,000
TOTALS 650 Man-Weeks $917,352
NBI-410-9521-D-1C
• -
• .. .. .. .. -.. .. .. -
• -... ..
• ..
•
• ..
• •
•
.. .. .. -
• -.. -
•
•
, J I
CAT-D8K (2 ea)
Compaction Roller
Front End Loader 966D (2 ea)
Flatbed Truck
Dump Truck (10 yd) (3 ea)
Service/Fuel Truck
Pickup Truck (3 ea)
Backhoe -CAT 225
Welder
Generator
Generator Spare
Vibratory Compactor
Lo-Boy/Tractor
Batch Plant
Airtrack/Compressor (3 ea)
Crane -20 Ton
65,000 GPM Pump
13,000 GPM Pump
Hand Compactors (5 ea)
Conc. Mixer Trailer
Screening Plant
3" Water Pumps (3 ea)
Fuel Tank, Bladder
Cutting Torch, Set
Misc. Equipment
Office Trailer
I t
TABLE D-2C
TOGIAK --ROCKFILL DAM ALTERNATIVE
EQUIPMENT COST
Ownership
Expense
(23 wks)
$67,600
4,000
18,800
4,100
8,350
10,850
3,250 ea
24,900
1,100
510
510
8,000
14,120
19,251
25,350
23,460
($8,000 x
($4,500 x
1,800 ea
2,000
9,300
500 ea
5,000
300
2,000
3,000
Total
Operating
Hours
400 ea
200
300 ea
500
500 ea
400
400 ea
250
100
1,100
220
400
200
300
150 ea
200
Hourly
Operating
Cost
$103.22
2.00
30.06
14.57
16.87
17.20
12.69 ea
20.37
5.51
.94
.94
4.00
24.25
14.50
27.00
22.50
.5 mo + $4,000 x 5.5 mo)
.5 mo + $2,250 x 5.5 mo)
20 ea 1.00 ea
300 2.50
100 23.75
1,000 1. 00 ea
1,320 1.68
Operating
Cost
$41,288 ea
400
9,018 ea
7,285
8,435 ea
6,880
5,076 ea
5,296
550
1,034
207
1,600
4,890
4,350
4,050 ea
4,410
20 ea
750
2,375
1,000
2,217
Pole Setting Truck Costs contained in transmission subcontract Line Truck
SUBTOTAL
*10% Increase due to duration
TOTAL
NBI-410-9521-D-2C
Total
Cost This
Project
$217,800
4,440
55,600
11,385
50,300
17,730
25,000
30,200
1,650
1,544
700
9,600
19,000
23,600
58,800
27,900
26,000
14,625
1,900
2,750
11,675
4,500
5,000
300
2,000
5,200
$634,200
63,400
$697,600
• -
• -TABLE D-3C • TOGIAK -ROCKFILL DAM ALTERNATIVE
MATERIAL FOB SEATTLE --Unit -Item Quantity Unit Price Amount -1. Cement Type I 4,160 Bags $ 4.73 $19,700 -2. Reinforcing Steel 153,000 Lb 0.35 53,655 • 3. Steel Pipe - 5 Ft. Dia. 423 FT 200 84,600 -4. Steel Pipe - 8 Ft. Dia. 300 FT 400 120,000
5. Slide Gates - 8
Ft. Dia 2 Ea 10,000 20,000 -
6. Slide Gates - 8
Ft.w/hoist 1 Ea 25,000 25,000 -
7. Slide Gates - 5
ft.w/hoist 1 Ea 20,000 20,000 •
8. Turbine Generator Assy. -Includes Switchgear LS 540,000
9. Electrical & Mechanical •
Accessory Equipment -and Materials 1 Lot 92,000 92,000
10. Fuel for Pumps 8,400 GAL 1.25 7,560 -
11. Misc. Bldg. Materials 1 Lot 25,000 25,000 -
12. Forming Materials 1 Lot 20,000 20,000 -13. Misc. Structural Steel 10,000 Lb 0.30 3,000 -14. Explosives 19,000 Lb 1.00 19,000 • ..
MATERIALS FOB SEATTLE DOCK $1,052,450 •
-------
• -
NBI-410-9521-D-3C --
-
-
-
-
-
-
....
Haul
Class
A
B
C
D
F
G
I
J
I
J
TABLE D-4C
TOGIAK --ROCKFILL DAM ALTERNATIVE
BARGE SHIPPING COST
Sea ttle To Togiak
Weight
Commodity (Typical) Clb)
Structural Steel 182,000
Palletized Cement 391,000
Lumber 25,000
Poles 128,700
Steel Pipe, Culvert 149,910
Misc. Wire, Hardware, etc. 54,300
Large Equipment, Machinery 767,700
Trailer 12,000
TOTAL
Togiak to Seattle (Return)
Large Equipment, Machinery 688,210
Office Trailer 12,000
TOTAL
($/cwt)
8.24
6.93
8.00
8.00
8.24
24.32
12.00
25.00
12.00
25.00
NBI-410-9521-D-4C
Cost
($ )
15,000
27,100
2,000
10,300
12,350
13,200
92,100
3 2 000
$175,000
82,600
3,000
$ 85,600
TABLE D-5C
TOGIAK --ROCKFILL DAM ALTERNATIVE
ESTIMATE OF CAMP COSTS
685 Man-Weeks
Each week the men are supported for seven days
685 x 7 or 4795 days @ $135 per day
CAMP COSTS TOTAL
ESTIMATE OF AIR TRANSPORTATION COSTS
Bring in crew and small tools -assume 6 men per
flight and 24 men with a Beech King Air.
6 Trips Anchorage to Togiak and back
~6 hrs/round trip
6 Trips @ $2500
Approximately 1500 Ibs of freight via Reeve
Aleutian and Air Taxi twice a week
3000 lbs @ $0.75/1b or $2250 per week
23 Weeks @ $2250
40 One Way Trips during construction for per-
sonnel changes & supervisor visits
76 Trips @ $282
Misc. Supply Trips
6 Trips Queen Air Cargo
Remove crews at job close
AIR TRANSPORTATION TOTAL
NBI-410-9521-D-5C
$647,320
$15,000
51,750
21,430
15,000
15,000
$118,180
•
• -
• -
--..
• -• ..
• -
• .,
•
•
• ., .. .,
• ---
• ---
• -
•
•
...
-
-
-
-
-
-
-
.. ,,.
-
-
TABLE D-6C
TOGIAK --ROCKFILL DAM ALTERNATIVE
SUMMARY SHEET
Material FOB Seattle
Labor
Transportation -Barge to Site
Transportation -Barge to Seattle
Transportation -Air
Camp Costs -Catered
Equi pmen t Co st
Prime Contractor 15% Profit
Contingency 15%
Transmission Line -Electrical
Labor & Materials Subcontract
Prime Contractor 10% Markup
Surveying, ~ight-of-Way & Geology
Engineering Design
Construction Management
Owner's Legal & Admin. Costs 3%
Subtotal
Subtotal
Subtotal
Subtotal
GRAND TOTAL
NBI-410-9521-D-6C
$1,052,450
917,350
175,000
85,600
118,180
647,320
697,600
3,693,500
554,000
4,297,500
637,100
967,000
96,700
5,948,300
100,000
445,000
255,000
800,000
202,500
$6,950,800
TABLE D-7C
TOGIAK --ROCKFILL DAM ALTERNATIVE
DEVELOPMENT OF AVERAGE UNIT PRICES FOR MAJOR ITEMS OF WORK
1/ Material Labor Equipment Contractor Total Unit
Item-Cost Cost Cost Profi t (15'1) Amount Quanit~ Unit Price
1. Mobil/Demob. $271,65o'Y $128,750 $ 47,180 $ 67,140 $514,720 LS $
2. Penstock 18,600 64,310 12,300 14,280 109,490 93 LF 1,177
3. Rock Excavation 23,620 84,430 182,640 43,600 334,290 18,675 CY 18
4. Rockfill 0 237,360 246,150 72,520 556,040 14,050 CY 40
5. Steel Cribbing 32,550 35,130 0 101,150 77,830 75,300 LB 1.03
6. Foundation Treatment 0 54,270 6,790 9,160 70,220 1,100 SY 64
7. Concrete 101,330 517,040 93,850 106,830 819,050 503 CY 1,628
8. Bypass Line 126,430 61,560 17,420 30,810 236,220 300 LF 787
9. Trashracks 8. Slide Gates 66,680 70,250 6,390 21,500 164,820 20,400 LB 8.08
10. Pumping Cost 26,800 20,870 60,580 16,310 125,060 LS
11. Pump Discharge Line 70,620 23,850 15,300 16,460 126,230 330 LF 383
12. Turbine 8. Generator 640,400 133,180 4,340 116,690 894,610 LS
13. Cover Powerhouse 25,800 20,340 4,660 7,620 58,420 LS
14. Transmission Lin~ 26,250 113,340 20 1 940 160 1 530 LS
TOTALS $554,000 $4,247,50o.Y
1/ These items are described on page 2 of this table. 2/ Includes Barge and Air Support Costs only. 3/ Includes cost over and above subcontract amount only. 4/ Amount corresponds with second subtotal on Table D-6C.
NBI-410-9521-D-7C
.1 I • I • I I I I I • I • • • , . I • , I I • • I I • I I I • I I • I I I
I l , I , 1
Item
1. Mobil/Demob.
2. Penstock, Steel
3. Rock Excavation
4. Rockfill
5. Steel Cribbing
6. Foundation Treatment
7. Concrete
8. Bypass Line
9. Trashracks & Slide
10. Pump Cost
11. Pump Discharl!:e Line
12. Turbine & Generator
13. Cover Powerhouse
14. Transmission Line
Columns
Material Cost
Labor Cost
Equipment Cost
NBI-410-9521-D-7C
Gates
I i 1
TABLE D-7C
(Cont'd)
I , I I i l
Includes general supervision, barge and air support costs, staginl!: equipment,
miscellaneous standby equipment, etc.
Installed, including couplings.
All, including structural, road and misc.
All, including dam & cofferdams.
In rockfill section.
All.
All, including equipment, material, cement, forming, miscellaneous structural
excavation (unclassified) & reinforcing steel.
All, through cofferdams and main dam.
Installed.
Installed, including operation and maintenance.
Installed.
Installed, including mechanical, electrical, and startup.
All.
Installed, subcontract plus shipping and camp costs.
Material cost FOR Seattle plus shipping.
Salary at 60 Hrs/week plus subsistence costs.
Ownership rental plus use rental, based on six months.
i ~
Terrain Conditions
Segment I: Mile
Segment I I: Mile
Quantities
Segment I:
TABLE 0-8
TOGIAK -ROAD OPTION A
0-1.3 Flat
1.3-2.0 ~20% Sides lope
2.0-2.7 Flat (Kurtluk River)
2.7-3.5 ~20% Sides lope
3.5-6.2 Flat to Rolling
6.2-7.0 ~15% Sides lope
7.0-11.6 Flat to Rolling
1.
2.
Stripping - 7 miles x 5280' x 30' wide = 25.5 Ac
Cut & Fill -Section is balanced Cut & Fill
3.
4.
5.
6.
18' wide
1 1/2:1 Cut & Fill Slopes
15% Runs: 8 mi x 5280 x 34
100' CY = 1436 CY
20% Runs: 1.5 mi x 5280 48
x 100' CY = 3800 CY
Gravel 7 mi 5280' 12 + 20 2' deep -x x 2 x 27 =
Culverts -Assume 30 LF each 1000'
(18" or 24") 7 x 5280
1000 = 37
37 x 30' = 1100 LF
1000 SF Bridge -From DOT Estimate
80' x 5' iJ Culvert -From DOT Estimate
NBI-384-9521-D-1
43,800 CY
-
•
•
• ..
• -
•
• -
• -
• -
• ..
• ..
•
•
• -
• ..
• -
• -
• -
• -
• -
•
•
-
-
-
-
-
-
-
-
-
-
.M
...
....
-
-
-
-
TABLE 0-8
(Continued)
Segment II:
2.
3.
Stripping: 4.6 mi x 5280 x 30' wide = 16.7 Ac
Gravel: Average section to produce traveled way ±2'
above stripped surface will require ±111 CY/100' (30
sq. ft.)
4.6 mi x 5280 x 111 = 27,000 CY
Assume: 1/2 (27,000) = 13,500 CY
1/2 (27,000) = 13,500 CY
Culverts: Assume 30 LF each 1000'
(18" or 24") 4.6 x 5280
1000 x 30 = 750 LF
Onsite
Haul
NBI-384-9521-D-1
TABLE 0-9
TOGIAK -ROAD OPTION A
CONSTRUCTION COSTS
Mobilization and Demobilization
Organic Stripping 42.2 Ac @ $4000/Ac
Excavation and Embankment
Mile 0 - 7
Mile 7 -11.6
Gravel Fill
Mile o -7
Mile 7 -11.6
Culverts 18" & 24"
60"
1000 SF Bridge
Contingency 20%
5250 CY
13,500 CY
@ $6/CY
43,800 CY @ $ll/CY
13,500 CY @ $9/CY
1950 LF @ $50/LF
80 LF @ $300/LF
Subtotal
Subtotal
Engineering, Surveying and Inspection 10%
Total
Ave = 140,600 $/mi
* January 1982 costs
NBI-384-9521-0-2
$190,000
168,000
112,500
481,800
121,500
97,500
24,000
40,000
$1,235,300
247,000
1,482,300
148,300
$1,630,600*
•
iii
• •
•
•
• ...
• ..
• ..
• -.. -.. ...
•
•
• ..
• .. -...
•
• ..
•
l1li ..
• .. -
• •
-
-
-
-
...
-
-
...
-
-
-' ..
Materials
Labor
TABLE 0-10
TOGIAK ROAD -OPTION A
OVERALL PROJECT COST FOR 11.6 MILES
Transportation (Barge Cost)
Transportation (Air Support)
Camp Cost
Equipment Cost
Subtotal
Contractor Overhead & Profit @ 20%
Contingency @ 20%
Total Construction
Engineering/Survey & Insp. =10%
Total
NBI-384-9521-D-4
$ 108,700
425,000
93,000
60,000
40,000
289,000
1,015,700
203,000
244,000
$1,463,000
167,000
$1,630,000
TABLE 0-11
TOGIAK ROAD -UPPER 4.6 MILES
(Change Order on Airport Contract)
Organic Stripping 17 Ac @ $4,000/Ac
Excavation and Embankment 13,500 CY @ $6/CY
Gravel Fill (Haul) 13,500 CY @ $9/CY
Culvert 18" & 24" 750LF @ $50/LF
Subtotal
Contingency 20%
Mobilization & Demobilization 25%
Total Construction
Engineering, Surveying and Inspection
Total
Ave = 110,478 $/mi
NBI-384-9521-D-3
$ 68,000
81,000
121,500
37,500
308,000
61,600
92,400
462,000
46,200
$508,200
• .. .. ..
• ..
• ..
•
•
• .. -.. -----.....
.. -..
--
-.. ... .. .. -
"IIIIi.
• -
-
-
-
-
-
-
-
-
-
-
-
-
-
TABLE 0-12
TOGIAK
BREAKDOWN OF TRANSMISSION LINE SUBCONTRACT
Item
Poles
Crossarms, insulators, and guys
Wire
Materials
Cost
$46,800
34,775
38,438
Subtotal, Overhead 120,013
Transformers, Pads and
Sectionalizing Equipment
Subtotal
Contingency: 25% Labor
10% Material
Subtotal
Equipment Mobilization
Misc. Crew Transportation and
Supervision
Total
SAY
42,800
$162,813
Laborli
Cost
$198,900
205,920
527,970
22,100
$550,070
Total
Cost
$245,700
325,933
647,983
64,900
$712,883
137,517
16,281
$866,681
50,000
50,300
$966,981
$967,000
l! Based on 75$/man-hour and 425$/crew hour for a 5-man crew,
including: 1 backhoe, 1 line truck with digger, 1 crew
cab pickup, and wire stringing equipment.
NBI-410-9521-D-12
I I , I
IIctlvlty
I. Barge Travel
2. Mobllization/Denobllization
a. Set Up Camp/Denobl Ilze
b. Stage Material & Set Up s..tch Plant
3. Road Construction & Miscellaneous Site Iklrk
4. Cofferdam & Bypass line
5. Install Pump Dlsch8rge line & Pumps
6. Bypass Pumping
7. Dam
a. Foundation Treatment
b. forming, Stage I
c. Concrete, Stage
d. form, Stage " e. Concrete, Stage " 8. Trashracks, Gates, etc.
9. Powerhouse & Fish ladder
a. Structura I Excavation
b. Concrete
c. Penstock, Equ Ipment
d. Cover Powerhouse
e. MeChanical & E lectr I ca I
f. Startup
10. Cleanup
II. Transmission line
NBI-425-9521-FD-III
I
2 4 5 6 8 9
I ( i I
FIGLRE 0-111
TOGIAK--38-FOOT CONCRETE DAM IILTERNATIVE
CONSTRUCTl~ SCHEDULE
Week
10 II 12 14 15 16 17 18 19 20 21 22 23 24 25
Activity
2
1. Barge Travel
2. Mobilization/Demobilization
a. Set Up Camp/Demobllize
b. Stage Material & Set Up Batch Plant
3. RolId Construction & Miscellaneous Site Work
4. Cofferdam & Bypass LI ne
5. Install Pump Discharge Line & Pumps
6. Bypass Pumping
7. Dam
a. Foundation Treatment
b. Forml ng, Stage I
c. Concrete, Stage
d. Form, Stage II
e. Concrete, Stage II
8. Trashracks, Gates, etc.
9. Powerhouse & Fish Ladder
a. Structura I Excavat Ion
b. Concrete
c. Penstock, Equ Ipment
d. Cover Powerhouse
e. Mechan I ca I & E lectrlca I
f. Startup
10. Cleanup
11. Transmission Line
NBI-425-9521-FD-IB
• I I I • :I r I I • •
3 4 5 6 8 9
I J , , , I I •
FIGLfiE D-IB
TOGIAK--28-FOOT CONCRETE DAM ALTERNATIVE
CONSTRUCTION SCHEDULE
Week
10 11 12 13 14 15 16
, . I I , . I •
17 18 19 20 21 22 23 24 25
• I I • , I • I I •
I ,
Activity
2
I. Bllrge Trllvel
2. Moblllzlltion/Demobi IlzIItlon
a. Set Up Cllmp/Demobllize
b. Stage Mater III I & Set Up BlItch Plllnt
3. Road Construction & Miscellaneous Site Work
4. Cof lerd"", & BYPllss LI ne
5. Instill I Pump Discharge Line & Pumps
6. Bypass Pumping
7. Dam
a. Foundlltlon Trelltment
b. Exc. Spillway & Pillce Rockflll
c. Spillway Cone. Wing Wa II
d. Toe Slab & Membrllne Concrete
8. Penstock & Bypass Headworks
9. Trashracks, Gates, etc.
10. Powerhouse & Fish Llldder
a. Structura I E XCII vllt I on
b. Concrete
c. Set Equipment
d. Cover Powerhouse
e. Mechlln I CII I & Electrical
I. Startup
II. Cleanup
12. Transmission Line
NBI-425-9521-FD-1
t I
3 4 6 8 9 10
i.
F IGLRE D-IC
TOGIAK--ROCKFILL ~ ALTERNATIVE
CONSTRUCTION SCHEDULE
Weak
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
...,.
.....
....
.....
-
.....
TOGIAK HYDROELECTRIC PROJECT
FEASIBILITY STUDY
APPENDIX E
ENVIRONMENTAL REPORT
-
-
-
-
-
.-
-
-
....
-
-
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
Q.
R.
S.
T.
U.
V.
w .
x.
Y.
Z.
TABLE OF CONTENTS
PROJECT DESCRIPTIO~
SCOPE OF WORK
HYDROLOGY
FISHERIES
1.
2.
QUIGMY RIVER
Spawning ..........
Rearing
PHYSICAL STREAM DESCRIPTION -QfJIGMY RIVER
1. Section 1
2. Section '2
3. Section 3
4. Section 4
FISHERIES KURTLUK RIVER
PHYSICAL STREAM DESCRIPTION -KURTLUK RIVER
CURRENT
FISHERY
UTILIZATION OF
IMPACTS
FISHERY MITIGATION
WILDLIFE . ......... .
FISHERY RESOURCES
CURRENT UTILIZATION OF WILDLIFE RESOURCES
ENDANGERED SPECIES
WILDLIFE IMPACTS
1.
2.
3.
Loss or Alteration of Habitat
Disturbance During Construction
Increased Human Presence
WILDLIFE MITIGATION
VEGETATION
ARCHAEOLOGIC AND HISTORIC SITES
POTENTIAL VISUAL IMPACTS
IMPACT ON RECRE~TIONAL VALUES
AIR QUALITY
SOCIOECONOMIC IMPACTS
LAND STATUS
PER.."'1ITTING REQUIREMENTS
RECOMMENDATIONS
REFERENCES CITEO
PERSONAL COMMUNICATIONS
i
. ..
. .
Page
1
1
3
4
9
12
12
13
13
16
16
17
17
17
20
22
23
32
33
35
35
35
36
37
37
38
38
39
39
40
41
43
46
47
47
Figures
1
2
3
4
Sampling Sites
Stream Reaches
vic ini ty ~1ap
LIST OF FIGURES
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
General Land Status Map . . . . . . . . . . . . . . . . . . . . . . .
LIST OF TABLES
Page
6
14
34
42
Tables
1 water Quality Data, 1981 . . . . . . . . . . . . . . . . . . . . . . Page
5
7 2
3
4
5
6
7
8
9
Photograph
Churn Salmon Escapement Estimates ••••••••.•••••
Species and Number of Fish Caught
in the Quigmy River ••••••••••••.•••••••••.••••
Freshwater and Anadromous Fish of
the Bristol Bay Region .•••••••••••••••••••••••
Species and Number of Fish Caught
B
10
in the Kurtluk River • • • • • • • • • • • • • • • • • • • • • • . • • • 18
Subsistence Salmon Harvest . . . . . . . . . . . . . . . . . . . . 19
Mammals of the Togiak National wildlife Refuge. 24
Checklist of Birds from Cape Newenham National
Wildlife Refuge and Nushagak Bay ••••••••••••.• 26
Seabird Colonies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
LIST OF PHOTOGRAPHS
1 Proposed Darn Site, Quigmy River ............... 2
2
11
11
15
15
2
3
4
5
6
Proposed Darn Site, Kurtluk River ••••••••••••••
Gravel Bar Deposited During Low Flow Conditions.
Stream Sampling, Quigmy River •••••••••••••.•••
Upper Quigmy River, Section 1 .................
Aerial View of Section 2 of the Quigmy River
ii
• .. -
•
• .. .. ...
• --... --.. --•
• ...
• ---
• ...
• .. --
•
• ..
" .. "
-
-
-
-
-
-
.-
A. PROJECT DESCRIPTION
The Quigmy River, about 12 miles west of Togiak, has been
investigated as a potential site for hydropower development. A
dam with a spillway and adjacent powerhouse are envisioned,
wi th a a small reservoir. A transmission I ine would be buil t
from Togiak to the dam site. Access would be provided through
one of two routes. Option A is a road from Togiak to the dam
site. Option B includes a barge landing at the Quigmy mouth,
with a road from the mouth of the river to the dam site.
(These roads are considered in some detail in Appendix B,
Geology. )
The Kurtluk River, about four miles from Togiak, has been
considered as an alternative site for hydropower development.
Preliminary project plans are similar to those proposed for the
Quigmy River, with a dam, small impoundment, road from Togiak,
and transmission line.
The proposed dam sites on the Quigmy and Kurtluk rivers are
shown in Photographs 1 and 2.
B. SCOPE OF WORK
As contracted with the Alaska Power Authority, environmen-
tal studies were to include an initial two-day reconnaissance
visit, followed by a three-to four-day trip for more detailed
studies. Literature review and discussion with local residents
and agency members were to be combined with field studies to
obtain information on fish and wildlife resources in the area,
and effects of the project on these resources.
Hydrology, land status, archaeologic and historic sites,
and permitting requirements were to be briefly discussed in
-1-
N ,
~
PROPOSED DAM SITE, QUIGMY RIVER
DAM SITE VICINITY, KURTLUK RIVER
this preliminary assessment as well as impacts on recreational
values, air quality, socioeconomics and scenic viewpoints.
The reconnaissance visit occurred on September 14-15,
1981, and a more detailed site investigation occurred October
6-11. Work at the site was not possible on two of these days
due to weather and mechanical problems with the hel icopter.
The rivers were flown in their entirety, with minnow traps sel-
ecti vely placed throughout their lengths. Hook and I ine sam-
pling was unsuccessful. Numbers and locations of wildlife and
wildlife sign were noted. Local residents were contacted
through a community meeting on September 14, and through dis-
cussions with individuals during both visits.
The Alaska Power Authority held an informational meeting
to discuss four potential hydropower sites, including Togiak,
with interested federal, state, and local organizations in
Anchorage on October 21, 1981. Additional contacts were made
by DOWL with state and federal agencies on an individual basis
during September, October and November.
c. HYDROLOGY
The Quigmy River originates in the mountains northwest of
Togiak and drains an area of 100 square miles at the dam site.
A considerable portion of the drainage area is in wetlands
which contribute to the river base flow. No streamflow data
exist. A stream gage was installed in December, and flows will
be monitored for one year. Estimates of mean annual flow range
from 200 to 300 cfs. Flow regime is seasonal, with high flows
due to heavy rainfall in June and some snowmelt in April. The
average peak runoff is expected to be 2000 cfs. Low flows in
winter are augmented by runoff from partial snowmelt and
groundwater from wetlands. Additional information on hydrology
can be found in Appendix B.
-3-
water quality information for the Quigmy River is given in
Table 1, and locations are shown in Figure 1. No changes in
water quality are anticipated to occur in the free flowing
river for any significant distance due to project construction
and operation.
D. FISHERIES -QUIGMY RIVER
The Quigmy River is a clear, moderately swift stream mean-
dering through 10-to 100-foot bluffs. Local residents of
Togiak indicated that silver (coho), pink and chum salmon, and
Dolly Varden char are found in the stream. Rainbow trout,
grayling, whitefish and northern pike may also be present
(Alaska Fisheries Atlas, ADF&G 1978a).
Alaska Department of Fish & Game chum salmon escapement
estimates for the Quigmy River (1970-1981) are given in Table
2. Wes Bucher, Assistant Area Biologist for ADF&G, Commercial
Fisheries, in Dillingham, could not comfirm spawning of either
pink or silver salmon in the Quigmy River (personal communica-
tion, 1981). On the basis of the physical characteristics of
the river, Bucher believes the Quigmy River would not have a
strong pink salmon run, perhaps several hundred, but could have
a good silver salmon run. Bucher also confirmed the presence
of rainbow trout in the Quigmy River.
Juvenile Dolly Varden, char and coho salmon were collected
in minnow traps throughout the Quigmy River during a field
reconnaissance in October 1981 (Table 3).
In September, approximately 40 adult silver salmon were
observed at the mouth of the Quigmy and during October approxi-
mately 175 adult silvers were observed in the upper reaches of
the river. A school of 50 to 75 adult Dolly Varden trout was
observed in the same area as the silvers.
-4-
TABLE 1
WATER QUALITY DATA, 1981
Temp. D.O. Conductivity
Date Location (oC) ~ (mg/l) (micromhos/ em)
10/8 Mouth of the 1.5 6.7 70.0
Quigmy River
10/10 proposed dam site, 0.75 7.0 54.0
Quigmy River
12/3 Proposed dam site, 0.0 8.7 9.6
Quigmy River
10/10 proposed dam site, 0.5 7.0 74.5
Kurtluk River
-5-
EXPLANATION -
o Minnow Trap Location.
• Minnow Trap Location
And Wat.r Quality
8 'a ... pllng 8~t •
.... Propo •• d Da. lit.
Mtn
Hagemeister
Island
o
TOGIAK BAY
SCALE I : 250000
~=--===:JI_.:=:::5o _____ ...... 5 MILES
.SAMPLING SITES I FIGURE 1
I
I
TABLE 2
CHUM SALMON ESCAPEMENT ESTIMATES*
Year QuiSffi:t River Kurtluk River
1970 3,400
1971 6,800
1972 7,400
1973 4,400
1974 2,800
1975 3,600
1976 13,200
1977 11,600 1,200
1978 18,800 400
1979 22,000 200
1980 5,400
1981 21,600
* ADF&G aerial survey reports, 1970-1981
-7-
TABLE 3
SPECIES AND NUMBER OF FISH CAUGHT IN THE QUIGMY RIVER
October 8-10, 1981
DATE LOCATION* JUVENILES
10/9 Upper Intertidal 1 Coho Salmon
10/9 Below First Left Tributary 41 Dolly Varden,
2 Coho Salmon
10/9 Below Second Left Tributary 27 Dolly Varden
10/10 Dam Site 18 Dolly Varden,
4 Coho Salmon
10/9 2 Miles Above the Dam Site 31 Dolly Varden,
1 Coho Salmon
10/9 4.5 Miles Above the Dam Site 31 Dolly Varden,
1 Coho Salmon
10/10 Quigmy River "y" 61 Dolly Varden
10/10 Sulutak Creek-Quigmy River 110 Dolly Varden
Junction
* See also Figure 1 (location map)
-8-
A list of freshwater and anadromous fish of the Bristol
Bay region is given in Table 4. Photographs 3 and 4 show a
gravel bar and stream sampling in the Quigmy River.
1. Spawning
Chum salmon frequently spawn in intertidal zones but
will often ascend short rivers. Chum spawning occurs intertid-
ally at the mouth of the Quigmy River up to Sulutak Creek, but
it is heaviest in the lower half of the river. Peak spawning
occurs in the first week of August (Bucher, personal communi-
cation, 1981). The preferred substrate for spawning is fine
gravel (0.3 to 0.16 inch) but chum salmon will use coarser
material. Optimum stream flow velocity for spawning is in the
range of 0.33 to 3.28 feet per second (fps) (ADF&G, 1978a).
Sil ver salmon generally spawn at the head of riffles in
shallow, swift-flowing river tributaries, but they may spawn in
the main channels of large rivers. Optimum stream flow ve-
loci ty during spawning is 3.4 feet per second (fps) (ADF&G,
1978a). Based on limited observations in the Quigmy River,
sil ver spawning appeared to occur in the upper reaches and
tributaries and probably occurred to a lesser extent throughout
the river. Judging from other streams in the Togiak district,
spawning is likely to begin in the second week in September and
extend through mid-October (Bucher, personal communication,
1981).
Pink salmon generally spawn intertidally or in the lower
reaches of short coastal streams. Medium-sized gravel (0.6 to
0.3 inch) is preferred, with an optimum stream flow velocity of
0.1 fps or greater (ADF&G, 1978a). No pink salmon were ob-
served in the Quigmy River, but they probably spawn intertid-
ally and in the lower reaches of the river (Bucher, personal
communication, 1981).
-9-
TABLE 4
FRESHWATER AND ANADROMOUS FISH OF THE BRISTOL BAY REGION*
COMMON NAME
Arctic grayling
Lake trout
Dolly Varden
Arctic char
Rainbow trout
Sockeye salmon
Coho salmon
Chinook salmon
Chum salmon
Pink salmon
Round Whitefish
Humpback Whitefish
Broad Whitefish
Arctic Cisco
Bering Cisco
Northern Pike
Burbot
SCIENTIFIC NAME
Thymallus arcticus
Salvelinus namaycush
Salvelinus malma
Salvelinus alpinus
Salmo gairdneri
Oncorhynchus nerka
Oncorhynchus kisutch
Oncorhynchus tshawytscha
Oncorhynchus keta
Oncorhynchus gorbuscha
Prosopium cylindraceum
Coregonus pidsehian
Coregonus nasus
Coregonus autumnalis
Coregonus laurettae
Esox lucius
Lota Iota
* Common and scientific names after McPhail and Lindsey (1970).
Adapted from Togiak National Wildlife Refuge Final Environmental
Statement.
-10-
o
I
GRAVEL BAR DEPOSITED DURING LOW FLOW CONDITIONS
STREAM SAMPLING, QUIGMY RIVER
Rainbow trout are reported to spawn in moderately swift,
clear water usually in fine gravel (0.3 to 0.16 inch) on a
riffle above a pool. Rainbows are likely to spa\m throughout
the Quigmy River, but the majority spawn in the upper reaches
and tributaries. Dolly Varden char spawn in medium to large
gravel (1.3 to 0.3 inches) in a fairly strong current, usually
near the center of the stream in at least a foot of water.
Spawning probably occurs throughout the main stem of the Quigmy
River, and to a lesser extent in larger tributaries.
2. Rearing
Minnow trap data indicate that rearing occurs in
backwaters and quiet areas throughout ·the river. When first
emerged, juvenile coho salmon frequent near-shore areas with
gravel substrate. Older juveniles prefer deeper pools and
avoid riffle areas. They are strongly territorial and will
defend their space from other juvenile cohos and salmonids.
Juvenile rainbow trout are found along stream margins or
protected lakeshores. ,Juvenile Dolly Varden trout are rela-
tively inactive, often remaining on the stream bottom in pools
or eddies under rocks and logs or undercut banks. Dolly Varden
occur in both anadromous and nonanadromous populations. ~nad
romous juveniles spend three to four years in their natal
stream before entering saltwater.
E. PHYSICAL STREAM DESCRIPTION -QUIGMY RIVER
The Quigmy River generally flows from north to south
except for the last three miles which flow southeasterly. It
can be divided into four general sections, based on physical
stream characteristics: 1) Headwaters to about one-half mile
above the proposed dam site; 2) a three-mile section of river
flowing through rock walls, including all proposed dam sites;
-12-
3) the second left tributary shown on the map to the river
mouth; and 4) the estuarine area (see Figure 2). Views of
Sections 1 and 2 of the Quigmy River are presented in Photo-
graphs 5 and 6 on page 15.
Togiak residents occasionally
distance below the proposed darn.
stopped by a 3-foot high falls.
1. Section 1
take a jet boat to a short
At this point they are
In this section the Quigmy River flows at a moderate
velocity through low willow and grass-lined banks. Numerous
small side channels are present, but they are often obstructed
by beaver dams. The main channel is triangular to U-shaped,
with a pebble and cobble gravel bottom. Bedrock outcrops occa-
sionally occur and large rocks, 12 to 24 inches, are sparsely
scattered in the streambed.
2. Section 2
From the original dam site to the second left tribu-
tary from the mouth, rock walls ascend to 100 feet and con-
strict the Quigmy River into a series of 15-to 20-foot-wide
gorges, with faster flowing water reaching depths of 10 feet.
Several falls up to three feet, and one-foot standing waves are
present in portions of this section. In between these gorges,
the river slows and forms a gravel fan, ranging from 60 feet to
150 feet wide. The river bed varies from pebble and cobble
gravel to bedrock.
Just below the original darn site, the stream was 100 feet
wide, with a minimum depth of 30 inches. The substrate ranged
from one-half to six inches, but the predominant size was from
-13-
EXPLANATION
-Stream Reach Divisions
...... Proposed Dam Site
Mtn
Hagemeister
Island
o
TOGIAK BAY
SCALE I: 250000
5 0 5 MILES CI =--==--==-________ _
1~£4$ .........
i:::f:::fl:;·;·~::·· FIGURE 2 I STREAM REACHES
I
~
I
UPPER QUIGMY RIVER, SECTION 1
AERIAL VIEW OF SECTION 2 OF THE QUIGMY RIVER
N
i
-
-
-
-
-
-
-
-
-
-
-
-
-
.I/ill
one to two inches. Caddis fly larvae were numerous in shal-
lower waters. On September 14, 1981, the flow was measured at
301 cfs. The stream channel was "V" shaped in cross section.
The banks were two to four feet high, vegetated with willow and
grass, and occasionally undercut.
3. Section 3
Below this three-mile section, the bank substrate
changed from rock to soil. The banks were four to eight feet
high and vegetated with willow. The stream generally has a
meandering channel with a width of 75 to 100 feet and maximum
depths of three to five feet. The channel was primarily "V"
shaped in cross section, but in straight sections resembled a
nUn. The bed consisted of unsorted gravel ranging in size from
sand to six-inch cobbles, but averaging one to two inches. In
one section, brown filamentous algae covered the deepest por-
tion, while green filamentous algae were present in a side
channel. In short sections, the channel split and flowed be-
tween gravel bars which were densely vegetated with willow.
4. Section 4
About one-hal f river mile from saltwater, the river
makes a tight "S" turn before entering saltwater. The north-
bank of the upper loop consists of a low marshy area with nu-
merous small ponds. It appears to be inundated by high or
storm tides. The first tributary joins the Quigmy River at
this point, and it may create the nearby marsh. The southbank
is covered with rye grass. The lower loop flows through un-
vegetated, intertidal sandbars, and it has a mud substrate.
Two cabins, reported ly used by fox hunters and winter
travelers, are found in the area. One is at the river's mouth
and another is approximately one mile to the northeast.
-16-
F. FISHERIES -KURTLUK RIVER
The Kurtluk is a clear, moderately swift stream draining a
marshy area about six miles southwest of Togiak (see Figure 1).
The Alaska Fisheries Atlas, Volumes I and II (ADF&G, 1978a),
shows that chum salmon are known to spawn in the Kurtluk River
and that rainbow trout, Dolly Varden trout, grayling, whitefish
and Northern pike may also be present. Alaska Department of
Fish & Game chum salmon escapement estimates for the Kurtluk
River are given in Table 1. It is not known how far upstream
spawning occurs. Three adult silvers were seen in the river in
October, and juvenile Dolly Varden trout, rainbow trout and
coast range sculpin were collected in minnow traps throughout
the Kurtluk River (Table 5).
G. PHYSICAL STREAM DESCRIPTION -KURTLUK RIVER
The Kurtluk generally flows from north to south through
willow and grass-covered banks ranging from 2 to 60 feet in
height. Above the dam site, numerous small tributaries enter
the river, which braids and then reforms into one channel
several times. The substrate is primarily cobble and pebble
gravel, with two exceptions. At the dam site, the streambed
consists of large boulders, with small patches of pebble gravel
between the rocks. Two miles below the dam site, the substrate
consists of small boulders and cobbles. In areas of low flow
velocity, an algal scum covers the rocks.
H. CURRENT UTILIZATION OF FISHERIES RESOURCES
Subsistence salmon harvest figures for the entire Togiak
district are given in Table 6. The figures are based on a
small number of harvest reports and therefore represent minimum
estimates of the subsistence salmon harvest by Togiak villagers
( AD F &G , 1980).
-17-
• ..
•
•
• ..
• .. .. -.. .. .. -
• ..
• -•
• .. -
• .. .. .. -.. .. -.. ---.. ..
-
~'
.-
-
-
-
-
-
. ..,
..
-
TABLE 5
SPECIES AND NUMBER OF FISH CAUGHT IN THE KURTLUK RIVER
October 10-11, 1981
DATE LOCATION* JUVENILES
10/11 Upper Intertidal 1 Dolly Varden
1 Coho
10/11 1.5 Miles from Mouth 12 Dolly Varden
3 Coho
1 Coastrange Sculpin
10/11 2.5 Miles from Mouth 5 Dolly Varden
9 Coho
10/11 Dam Site 1 Dolly Varden
6 Coho
10/11 1 Mile above Dam Site 10 Dolly Varden
5 Coho
* See also Figure 1 (location map).
-18-
Number of
Subsistence
Year Permits
1965 36
1974 68
1975 41
1976 30
1977 41
1978 29
1979 25
1980 46
8-Year
Total 316
8-Year
Average 39
TABLE 6
SUBSISTENCE SALMON HARVEST
Togiak District (ADF&G, 1980)
HARVEST
Sockeye King Chum Pink
4,600 100 1,600 100
7,400 1,200 2,000 500
4,600 800 1,600 +
2,800 500 900 100
2,100 400 800 +
900 300 700 300
800 200 300 0
3,600 900 300 300 ---
26,800 4,400 8,200 1,200
3,400 500 1,000 300
-19-
Coho Total
2,200 8,600
1,800 12,900
2,800 9,800
500 4,800
1,100 4,400
500 2,700
700 2,000
1,200 6,300
10,800 51,500
1,300 6,400
• -• •
•
• -
• ..
• -
• -
• -
• -
• -
• -
• --------.' ------
,..,.
-
-
..
...
-
-
-
-
-
-
-
According to Robert Nanalook (Togiak Village Council, per-
sonal communication, 1981), very little subsistence fishing
occurs on the Quigmy River due to the distance from the village
and the small numbers of silvers present compared to other
rivers in the area. In fact, almost no use is made of either
the Quigmy or Kurtl uk Rivers. This would clearly change if
road access was made available.
I. FISHERY IMPACTS
Construction activity may cause increased erosion, and
subsequent sedimentation of spawning gravels. Major impacts
from sedimentation incl ude decreased vigor or death of incu-
bating salmonid eggs by interfering with or preventing respira-
tion, loss of spawning gravel, and physical disturbance to both
adul t anadromous fish and resident species. However, proper
construction techniques and timing constraints should minimize
this impact .
Construction and operation of the Quigmy River dam may
cause a change in water temperature in the river below the dam.
The reservoir may dampen the natural seasonal temperature
cycle, slightly increasing fall-winter temperatures near the
powerhouse intake, and decreasing spring-summer temperatures.
Should these changes occur, early fry emergence at a time when
food is not available, and a resultant lower survival rate, is
likely. However, the effect of this slight temperature in-
crease probably would not be felt for any significant distance
downstream of the outlet and the streambed in this section of
the river is primarily bedrock, boulder and cobble with only
about 30 percent suitable for spawning.
Thermal stratification, if any at all occurs wi thin the
impoundment, will be minimal because:
-20-
The ratio of total annual inflow to reservoir
volume is more than 100, resulting in a water
residence time of two to three days.
The intake elevation has been raised to compen-
sate for the deposition of sediment.
The normal mixing of reservoir water with incom-
ing river water before discharge.
Based on earlier mathematical models (Huber et al., 1972),
an estimate of the temperature change within the reservoir
would be within a degree or so of present conditions.
Water discharged from the tailrace may have a slightly
lower di ssol ved oxygen (DO) content then would be normal for
this section of the river. However, DO is expected to return
to normal shortly after the discharge reenters the river.
Scouring to bedrock is likely to occur for a short dis-
tance downstream of the dam. Streambank erosion due to altered
stream flow may al so occur, but such erosion would be minimal
in the gravel banks.
I f proper facil i ties for fish passage are not provided,
migration of adult salmon will be blocked, considerably reduc-
ing the available spawning and rearing habitat. The reservoir
will flood some rearing habitat and may flood spawning habitat.
Salmonid smolt may be injured or killed by passage through the
turbines, or over the spillway.
Road construction would allow increased access to the area
and could lead to increased subsistence and sport fish harvest
in the Quigmy River. Since chum salmon have the only known run
of significance and are not a highly sought-after fish, a large
-21-
• -• •
•
• -
•
• -
• -
• -
• -..
•
• -
•
• -
• -
• -
• -
•
•
•
•
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
, ....
-
-
increase in sUbsistence harvest in the Quigmy River is not
likely. Some increase in sportfishing efforts and harvest may
occur during project construction due to project personnel but
this will be of short duration and minor importance.
J. FISHERY MITIGATION
The following measures should be followed to reduce ero-
sion and sedimentation of area streams:
construction should be done during a single
summer. This should reduce the opportunity for
erosion of exposed soil.
To avoid the introduction of suspended solids by
road traffic, the access road should cross as
few tributary streams as possible. Streams
should be crossed with small log bridges or cul-
verts, whichever would provide the best protec-
tion to streamside vegetation.
A vegetated buffer zone should be left between
all access roads and the streambank.
All areas disturbed during construction activ-
ities should be stabilized to reduce erosion.
Any organic soils excavated during construction
should be stockpiled and spread over disturbed
sites to encourage revegetation.
Waste petroleum and wastewater should be dis-
posed of in an environmentally sound manner and
a plan for safe storage, use, and clean-up of
oil and gas used in project construction, and
-22-
K.
operation should be prepared following state and
federal oil spill contingency plans (40 CFR
112.38, December 11, 1973).
WILDLIFE
A list of mammals for the Togiak National Wildlife Refuge
is given in Table 7, and a list of birds found at the Cape
Newenham National Wildlife Refuge is given in Table 8. Cape
Newenham National Wildlife Refuge has been incorporated into
Togiak National Wildlife Refuge, which includes the project
area.
The following information was obtained from a conversation
with Frank Logusak, a local resident familiar with the Quigmy
River. with the exception of the mouth, the area surrounding
the river is relatively poor in wildlife. No moose or caribou
use the area, and brown bears use it only occasionally. Rab-
bits, red squirrels, and red fox occur at the river's mouth.
Beaver are not common along the Quigmy River. A small number
of ducks use the river mouth in the spring and fall.
The following wildlife or sign was noted in the project
vicinity. Ten ducks (unidentified species) were flushed from
the mouth of the river, and four were flushed from the original
dam site. About 25 mallards were flushed from the Quigmy River
about two miles below Sulutak Creek. Several family groups of
swans were seen on ponds about five miles to the east of the
river during the reconnaissance trip in September. Brown bear
tracks were located on a sandbar about two miles from the river
mouth, and red fox tracks were observed at the original dam
si te. Old beaver cuttings and a mink den were noted in a
willow thicket about two miles from the river's mouth. Beaver
dams and houses 'Illere scattered in ponds and streams througout
the drainage, but they appeared to be particularly numerous on
-23-
..
•
• •
• .. --
• •
•
•
• -
•
•
II
•
..
•
• -
•
• -
-
• -.. -
•
•
•
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TABLE 7
MAMMALS OF THE TOGIAK NATIONAL WILDLIFE REFUGE
COMMON NAME
Common Shrew
Tundra Shrew
Little Brown Bat
Tundra Hare
Snowshoe Hare
Hoary Marmot
Arctic Ground Squirrel
Red Squirrel
Beaver
Greenland Collared Lemming
Northern Bog Lemming
Brown Lemming
Red-backed Vole
Meadow Vole
Tundra Vole
Muskrat
Meadow Jumping Mouse
Porcupine
Gray Wolf
Arctic Fox
Red Fox
Black Bear
Brown/Grizzly Bear
Marten
Short-tailed Weasel
Least Weasel
Mink
Wolverine
River Otter
Lynx
-24-
SCIENTIFIC NA~1E
Sore x cinereus
Sorex tundrensis
Myotis luncifugus
Lepus othus
Lepus americanus
Marmota caligata
Citellus parryi
Tamiasciurus hudsonicus
Castor canadensis
Dicrostonyx groenlandicus
Synaptomys borealis
Lemmus trimucronatus
Clethrionomys rutilis
Microtus pennsylvanicus
Microtus oeconomus
Ondatra zibethicus
Zapus hudson ius
Erthizon dorsaturn
Canis lupis
Alopex lagopus
Vulpes vulpes
Ursus americanus
Ursus horribilis
Martes americana
Hustela erminea
Hustela rixosa
Mustela vison
Gulo gulo
Lutra canadensis
Lynx canadensis
COMMON NAME
Alaska Fur Seal
Steller Sea Lion
Pacific Walrus
Harbor Seal
Ribbon Seal
Ringed Seal
Bearded Seal
Moose
Barren Ground Caribou
TABLE 7
Continued
SCIENTIFIC NAME
Callorhinus ursinus
Eumetopias jubata
Odobenus rosmarus
Phaca vitulina
Histriophoca fasciata
Posa hispida
Erignathus barbatus
Alces gigas
Rangifer arcticus
From Manville and Young, Distribution of Alaskan Mammals, BSF&W
Circular 211
-25-
..
•
• -
•
•
•
•
-
•
,.
..
•
• -.. ..
• •
• -• -
• -
• ..
• -
• -
• ..
...
-
-----
-
-
-
-
-
-
-
,_.
-
.-
-
-
TABLE 8
CHECKLIST OF BIRDS FROM
CAPE NEWENHAM NATIONAL WILDLIFE REFUGE AND NUSHAGAK BAY
Birds which have been observed at Cape Newenham and Nushagak
Bay are listed below with keys to their abundance or status
there. Abbreviations used to indicate abundance or status are:
A -Abundant
C -Common
U -Uncommon
R -Rare
SPECIES
Common loon
Arctic loon
Red-throated loon
Red-necked grebe
Horned grebe
Double-crested cormorant
Pelagic cormorant
Red-faced cormorant
Whistling swan
Canada goose
Black brant
Emperor goose
White-fronted goose
Snow goose
Mallard
Gadwall
Pintail
Green-winged teal
Blue-winged teal
American wigeon
N -Nesting
M -Migrant
P -Resident All Seasons
V -Status as Nesting
Species Uncertain
SCIENTIFIC NAMES STATUS
Gavia immer C
Gavia arctica C
Gavia stellata C
Podiceps auri tus U
PodiceEs auritus U
Phalacrocorax auritus C
Phalacrocorax Eelagicus U
Phalacrocorax urile U
Olor columbianus A
Branta canadensis A
Branta bernicla A
Philacte canagica A
Anser albifrons A
Chen caerulescens A
Anas platyrhynchos A
Anas streEera U
Anas acuta A
Anas crecca C
Anas discors C
Anas americana C
-26-
N
N
N
V
V
N
N
N
N
M
N
M
M
M
N
V
N
N
N
V
• ..
• -
TABLE 8 •
Continued ..
• ..
SPECIES SCIENTIFIC NAMES STATUS ..
Shoveler Anas clypeata U V -Greater scaup Aythya marila C N -Bufflehead Bucephala albeola U M ..
Common goldeneye Bace,Ehala clangula C M
Barrow's goldeneye Bucephala islandica U M •
Oldsquaw Clangula hyemalis C M -
Steller's eider Polysticta stelleri A M ~
King eider Somateria spectabilis A N -Harlequin duck Histrionicus histrionicus C M • Common eider Somarteria mollissima A N ..
White-winged scoter Melanitta deglandi C P
Surf scoter Melanitta perspicillata U V • ..
Common scoter Melanitta nigra C N
Common merganser Mergus merganser C V •
Red-breasted merganser Mergus serrator U V •
Goshawk Accipiter gentilis U V III
Marsh hawk Circus cyaneus A M -Rough-legged hawk Buteo lagopus A N
Golden eagle Aquila chrysaetos U • V ..
Bald eagle Haliaeetus leucocephalus C N
Osprey Pandion haliaetus U N •
Gyrfalcon Falco rusticolus C N -
Peregrine falcon Falco pereginus C V •
Merlin Falco columbarius U V '. Sparrow hawk Falco sparverius C M • Spruce grouse Canachites canadensis P U N -Willow ptarmigan Lagopus lagopus P U N
Rock ptarmigan Lagopus mutus P U N •
Sandhill crane Grus canadensis A -N
Semi-palmated plover Charadrius semipalmatus C N • -
-27-•
•
-
-
---
..
..
-
-
-
-
-
-
-
-
SPECIES
American golden plover
Black-bellied plover
Ruddy turns tone
Black turnstone
Common snipe
Whimbrel
Bristle-thighed curlew
Wandering tattler
Spotted sandpiper
Terek sandpiper
Solitary sandpiper
Greater yellowlegs
Lesser yellowlegs
Surfbird
Rock sandpipe r
Sharp-tailed sandpiper
Red knot
Pectoral sandpiper
Baird's sandpiper
Least sandpiper
Western sandpiper
Dunlin
Short-billed dowitcher
Long-billed dowitcher
Semi-palma ted sandpiper
Bar-tailed godwit
Sanderling
Hudsonian godwit
Red phalarope
Northern phalarope
TABLE 8
Continued
SCIENTIFIC NAMES
Pluvialis dominica
Pluvialis squatarola
Arenaria interpres
Arenaria melanocephala
Gallinago gallinago
Numenius phaeopus
Numenius tahitiensis
Heteroscelus incanus
Actitis macularia
Xenus cinereus
Tringa solitaria
Tringa melanoleuca
Tringa flavipes
Aphriza virgata
Calidris ptilocnemis
Calidris acuminata
Calidris canutus
Calidris melanotos
Calidris bairdii
Calidris minutilla
Calidris mauri
Calidris alpina
Limnodromus griseus
Limnodromus scolopaceus
Calidris pusilla
Limosa fedoa
Calidris alba
Limosa haemastica
Phalaropus fulicarius
Phalaropus lobatus
-28-
STATUS
C
A
C
A
A
A
U
C
C
R
U
C
U
C
A
C
U
U
U
A
A
A
A
A
U
U
C
A
U
C
v
V
V
N
N
V
M
M
V
M
V
N
N
M
N
M
V
V
V
N
N
N
M
M
V
V
M
M
V
N
SPECIES
Pomarine jaeger
Parasitic jaeger
Long-tailed jaeger
Glaucous gull
Glaucous-winged gull
Mew gull
Bonaparte's gull
Sabine's gull
Black-legged kittiwake
Red-legged kittiwake
Arctic tern
Aleutian tern
Common murre
Pigeon guillemot
Parakeet auklet
Horned puffin
Tufted puffin
Marbled murre let
Great horned owl
Snowy owl
Short-eared owl
Boreal owl
Belted kingfisher
Say's phoebe
Cliff swallow
Tree swallow
Bank swallow
Barn swallow
Gray jay
Black-billed magpie
TABLE 8
Continued
SCIENTIFIC NAMES
Stercorarius pomarinus
Stercorarius parasiticus
Stercorarius longicaudus
Larus hyperboreus
Larus glaucescens
Larus canus
Larus philadelphia
Xema sabini
Rissa tridactyla
Rissa brevirostris
Sterna paradisaea
Sterna aleutica
Uria aalge
Cepphus columba
Cyclorrhynchus psittacula
Fratercula corniculata
Lunda cirrhata
Brachyrarnphus marrnoratus
Bubo virginianus
Nyctea scandia
Asio flarnrneus
Aegolius funereus
Megaceryle alcyon
Sayornis saya
Petrochelidon pyrrhonota
Iridoprocne bicolor
Riparia riparia
Hirundo rustica
Perisoreus canadensis
-29-
STATUS
P
P
p
P
C
C
A
A
A
A
U
A
A
U
A
A
A
A
C
C
A
U
U
U
C
C
U
C
U
C
A
C
A
C
V
N
N
N
N
N
M
N
N
M
N
V
N
N
N
N
N
V
P
P
N
V
V
N
M
N
N
N
N
N
• •
• -
• .. .. -
----
•
•
• ..
• -
• •
• -
• -
• -
•
• •
• •
-
-
-
,,....
-
-
-
....,
-
-
-
-
-
-
-
-
-
SPECIES
Cornmon raven
Black-capped chickadee
Boreal chickadee
Robin
Varied thrush
Hermit thrush
Swainson's thrush
Gray-cheeked thrush
Golden-crowned kinglet
Ruby-crowned kinglet
Arctic warbler
Yellow wagtail
Water pipit
Bohemian waxwing
Cedar waxwing
Orange-crowned warbler
Yellow warbler
Willow warbler
Myrtle warbler
Blackpoll warbler
Northern waterthrush
Wilson's warbler
Rusty blackbird
Gray-crowned rosy finch
Pine grosbeak
Hoary redpoll
Common redpoll
Red crossbill
White-winged crossbill
Savannah sparrow
TABLE 8
Continued
SCIENTIFIC NAMES
Corvus corax
Parus atricapillus
Parus hudsonicus
Turdus migrator ius
Ixoreus naevius
Catharus guttatus
Catharus ustulatus
Catharus minimus
Regulus satrapa
Regulus canendula
Phylloscopus borealis
Motacilla flava
Anthus spinoletta
Bombycilla garrulus
Bombycilla cedrorum
Vermivora celata
Dendroica petechia
Phylloscopus sibilatrix
Dendroica coronata
Dendroica striata
Seiurus noveboracensis
Wilsonia pus ilia
Euphagus corolinus
Leucosticte tephrocotis
Pinicola enucleator
Carduelis hornemanni
Carduelis flammea
Loxia curvirostra
Loxia leucoptera
Passerculus sandwhichensis
-30-
STATUS
P
P
P
P
A
C
C
A
C
U
C
C
U
C
U
C
U
C
U
C
C
R
C
C
U
C
C
C
C
C
A
U
C
A
N
N
N
N
N
N
N
N
V
V
V
N
N
M
V
N
N
V
N
N
V
N
N
N
M
V
N
V
V
N
SPECIES
Slate-colored junco
Tree sparrow
White-crowned sparrow
Golden-crowned sparrow
Fox sparrow
Song sparrow
Lapland longspur
Snow bunting
TABLE 8
Continued
SCIENTIFIC NAMES
Junco hyemalis
Spizella arborea
Zonotrichia levcoEhr:;r:s
Zonotrichia atricapilla
Passerella iliaca
Melospiza melodia
Calcarius lapponicus
Plectrophenax nivalis
STATUS
U M
C N
C N
C N
C V
C N
C N
C N
Source: Togiak National Wildlife Refuge Final Environmental
Statement
-31-
• •
• -• -
• ..
• ---
• -
• -
• ---
• ..
• -• ..
• -
• --
• -• •
-
-
-
-
-
-
,~
-
-
-
-
--
-
-
the Quigmy River between the upper east tributary shown on
Figure 1 and Sulutak Creek. Two beaver dams and a house were
observed in the upper drainage area of the Kurtluk River, and
it is likely that other dams were present.
Ken Taylor (ADF&G personal communication, 1981) reported
that wildlife information specific to the Quigmy drainage is
not available. There are no caribou and very few moose. Brown
bear populations are high, and they receive very little hunting
pressure. Three to four bears per year are taken between
Manokotuk and the Quigmy River drainage. No black bears are
present (Alaska I s Wildlife and Habitat, ADF&G, 1973). Robert
Nanalook, (Togiak Village Council, personal communication,
1981) reported two bear dens on the northwest slope of Aeolus
mountain. He was not aware of any other denning activity in
the project vicinity.
Beaver populations are high, and beaver are the major
furbearer taken. Other furbearers, including wolf, wolverine
and marten, are reported to be rare.
This area also supports
Alaska I s Wildlife and Habitat,
high ptarmigan populations.
Volume II (ADF&G, 1978), lists
four seabird colonies within five miles of the mouth of the
Quigmy (Table 9). ,~ddi tional colonies exist on Hagemeister
Island, Summit Island, and the Walrus Islands (Figure 3).
L. CURRENT UTILIZATION OF WILDLIFE RESOURCES
Since the Quigmy River is 12 miles from Togiak, it does
not receive extensive use by local residents. Several resi-
dents stated that they had boated the river, but were stopped
about one-half mile above the proposed dam site by three-foot
falls.
-32-
Fox hunting occurs throughout the entire area. Beaver
trapping in the vicinity of the Quigmy River is concentrated in
the marshy area to the southwest, between the Quigmy and the
Matogak River. Trapping may also occur in the upper reaches of
the Kurtluk River.
Colony No.
43AA
43X
43Y
43Z
TABLE 9
SEABIRD COLONIES
5 Miles from Mouth of Quigmy River
Location
Hill "365"
N. Aeolus Mt.
Aeolus Mt.
Offshore Island
Species Present
Cormorant and Glaucous
winged gull
Pelagic cormorant and
Black-legged Kittiwake
Cormorant and Black-legged
Kittiwake
Glaucous-winged Gull
M. ENDANGERED SPECIES
There are no records of peregrine falcons or other en-
dangered species in this area (D. Money, 1981, personal com-
munication, USFWS). The endangered subspecies of the peregrine
falcon normally nests in rock cliffs along interior rivers and
it is not likely to occur within the project area.
-33-
• ..
• -
--
• --.. ---
•
•
• --..
-
-
• -
• ---
• •
• -
-
-
-
--
-
-
-
-
-
-
-
-
-
EXPLANATION
.... Propo •• d D ... 81t.
laland
TOGIAK BAY
SCALE I: 250000
o
VICINITY MAP
Summit laland
Walrus Islanda
I FIGURE 3
N. WILDLIFE IMPACTS
wildlife impacts will have three basic origins:
1.
Loss or alteration of existing habitat;
Direct disturbance during construction;
Increased human presence and usage during and
after construction.
Loss or Alteration of Habitat
Permanent habitat loss will result from construction
of the dam and subsequent flooding of the reservoir. Road con-
struction will al so result in the loss of wildl ife habitat.
Addi tionally, in areas where there is no perceptible surface
flow, near surface drainage through sloping peatlands may be
impeded by the roadbed. This could cause a gradual change in
the vegetative composition of the immediate area.
Some minor mortality to birds may result from colli-
sions with the transmission line.
Wildlife may be adversely impacted by gravel quarry
operations. The impact will result from removal of overburden,
erosion and sil tation. Small mammals and nesting birds may
suffer direct mortality but over very limited areas. Species
such as bear, fox and arctic ground squirrel will be affected
through loss of habitat but the overall impact should be mini-
mal.
2. Disturbance During Construction
Blasting and operation of heavy equipment will create
considerable noise and may resul t in disturbance of wildlife.
This could cause nesting failure in birds, and it may alter the
-35-
• -.. -
•
• -
•
• --• -
• .. .. -
• -.. -• ..
• -
• -
• -
• -
• -.. -
• -
-
-
--
-
-
-
-
-
-
-
distribution patterns and movements of nearby species. Dis-
turbance of raptors in early April or May when they are estab-
lishing territorities may lead to desertion of sites, and
disturbances of very short duration during the egg-laying and
incuba tion period (May to June) may lead to the loss of eggs
and young (Watson et ~., 1973). Swans are also very sensitive
to human disturbance. Canid and bear denning areas may be
vacated. Most other species present in the QuigmY-Togiak area
would vacate local areas near noise sources only temporarily.
Marine mammals and seabirds may be affected by con-
struction and operation of the barge site should this access
route be chosen. The impact will result from increased boat
traffic and the discharge of wastes which could alter movements
and food supplies.
3. Increased Human Presence
Ease of access to the area due to road construction
could lead to increased wildlife harvest by construction work-
ers and local residents. Species most likely to be impacted
would be red fox, beaver and moose. Since the project vicinity
is predominantly vegetated with low tundra, construction of a
road from the village will in all likelihood lead to use of
areas adjacent to the road by off-road vehicles. This may lead
to additional habitat destruction and disturbance of wildlife.
Refuse dumps or food stores created by cons truction
activity may attract bears and other scavengers. Such animals
qui te frequently become habituated and dangerous and must be
removed or destroyed for reasons of publ ic safety. The major
species affected would be brown bears, wolves, foxes and pos-
sibly wolverines.
-36-
O. WILDLIFE MITIGATION
The proposed project is on such a small scale that most
impacts such as disturbance of wildlife during construction
will be minor and short term. To further minimize impacts, the
following guidelines should be followed:
P.
No feeding of wildlife should occur and all re-
fuse should be placed in metal containers with
heavy lids and removed regularly from the con-
struction sites.
If problems with bears or other wildlife do
arise, the appropriate Alaska Department of Fish
& Game officials should be contacted and han-
dling of the problem should follow their recom-
mendations.
Hunting and fishing in the project area should
not be permitted by the contractor or construc-
tion workers during construction.
VEGETATION
The Quigmy River is bordered by willows with a grass
understory for most of its length. Near the mouth, individual
willows attain a height of 10 feet and a diameter of approxi-
mately six inches, but further upstream the willows are only
three to five feet tall with a diameter of approximately one
inch. In the upper reaches of the Quigmy River, low willow
thickets are intermixed with patches of tall grass. In sec-
tions with rock cliffs or where old river terraces are present,
these willow thickets continue up draws and other protected
areas.
-37-
• -,.
• -..
• ... --
• .. -
• -
• ..
• •
• -
• -
• ...
•
• --
•
•
• -
.-
---
-
-
-
-
-
-
-
-
More exposed slopes are covered by moss, with grasses, low
blueberry, dwarf birch, dwarf willow, and mountain cranberry
interspersed throughout. On bluff tops, the same species are
present, but the woody vegetation only attains height of two to
three inches, and it is so tightly interwoven it almost com-
pletely obscures the moss. Foliose lichens, such as caribou
lichen, are quite common on bluff tops, and in some areas are
the dominant ground cover.
Vegetation was quite similar along the Kurtluk River, with
willow along the streambanks and dry tundra on bluff tops.
Willows reached heights of 20 feet in protected spots but were
normally much shorter. At the dam site, lower areas were cov-
ered with willow, while the upper slopes of the river bluffs
were thickly covered with low blueberry.
Q. ARCHAEOLOGIC AND HISTORIC SITES
The only known archaeologic or historic site in the proj-
ect area is located at the mouth of the Kurtluk River where an
Eskimo village was formerly located. However, additional
unidentified sites are likely within the project area (Ty
Dilliplane, 1981) and the Alaska Division of Parks has recom-
mended an archaeologic survey of the project area before con-
struction begins on either the Quigmy River or Kurtluk River
dam sites.
R. POTENTIAL VISUAL IMPACTS
The dam and powerhouse will not be visible from Togiak or
from Togiak Bay. The transmission line will be 'risible from
the town, but it will be placed so that it will be screened
from view where possible. Should road Option A (a road from
Togiak to the dam site) be chosen, it will be visible from the
village until it disappears behind a low hill at the mouth of
-38-
the Kurtl uk River, about two mile s beyond the existing road.
This road was formed through continual use and was never for-
mally constructed. Road option B will be visible from a por-
tion of Togiak Bay, but it will be screened from town by low
hills.
S. IMPACT ON RECREATIONAL VALUES
If road Option A is chosen, it will greatly increase the
area available for recreational use of snowmachines, three-
wheelers and standard vehicles. Village residents indicated an
interest in this route as it would increase the accessibility
of this area for berry picking, hunting, and trapping.
Road Option B will not greatly affect recreational use of
the area, since the road will not provide access from the vil-
lage. On rare occasions villagers may bring three-wheeled
vehicles via boat and use the road in this manner.
T. AIR QUALITY
During project
equipment and dust
affect air quality.
construction, exhaust fumes from diesel
generated by construction activity may
This activity will be centered in the
vicinity of the proposed dam, about 12 miles from Togiak, and
should not affect local residents. Dispersion of air pollu-
tants is expected to be adequate to prevent any significant
effects on air quality in the area.
Electrical power for Togiak is currently provided by
diesel generators. Particulate emissions from the combustion
of diesel fuel have a high proportion of particles with a very
small size fraction. These smaller particles penetrate deeper
into the lungs and are therefore more hazardous to health than
emissions from the combustion of other hydrocarbon products.
-39-
• • .. -
•
• ---
-.. ---
•
., --
• -
• -
• -
• -
---
• -
• -
-
-
-
-
-
-
-
-
-
-
-
-
-
Replacement of the diesel generating facilities should lower
the discharge of hydrocarbon pollutants.
U. SOCIOECONOMIC IMPACTS
Togiak is one of the more traditional villages in the
Bristol Bay area, but even so socioeconomic impacts will be
minimal. The construction force is not expected to exceed 30
people, and it would probably average 20. Since accommodations
are not available in Togiak, trailers will be brought in (and
removed when construction is completed) and a camp will be set
up near the dam site. working hours would be 10 hours a day,
six or seven days a week. The project should be completed
wi thin one year, beginning in May and finishing in the latter
part of November. Since skilled craft labor will be required,
local hire is possible, but not likely. Some Togiak residents
may resent this. However, since construction would occur
during the summer months, most local residents are likely to be
busy with commercial fishing and not be available for hire.
Togiak has a large influx of people during the herring
season, so local residents are accustomed to large groups of
strangers in the village. Exchanges between villagers and
workers may be limited due to the limited free time on the part
of the construction workers and the 12 to 15 miles between the
camp and the village.
The potential does exist for alcohol-related problems
between villagers and construction personnel. Togiak is com-
pletely dry. Past experiences have shown that despite rules to
the contrary alcohol will be present in construction camps.
Intoxicated workers could create problems for the locals. The
proximi ty of alcohol may al so lead to the purchase or barter
(particularly for local products) of alcohol from construction
workers by local residents.
-40-
Hydropower may affect the cash flow within the village and
for individual families. Cheaper electric bills should result
in a net cash increase for the householder. Residents may
elect to switch from oil heat to electric heat, which will
require an initial, cash output for conversion. Maintenance on
the road to the dam will provide part-time employment for vil-
lage residents, and a skilled resident will be needed for
periodic maintenance of the power generation equipment.
v. LAND STATUS
A generalized land status map of the Togiak area is shown
in Figure 4. Note the two proposed dam site alternatives on
the Quigmy and Kurtluk Rivers and the five proposed borrow
sites. The impacts of the proposed hydroelectric project on
land status is dependent on the final selection of dam, trans-
portation and borrow site locations.
The proposed dam site on the Quigmy River and borrow sites
A, Band C are on lands selected by Togiak Natives, Ltd., as
part of their entitlements under the Alaska Native Claims
Settlement Act (ANCSA), Public Law 92-203 enacted December 18,
1971. The U.S. Fish and Wildlife Service (USFWS) has the
management responsibility for this area as well as all other
land classified village Selected in this general area until
such time as final disposition is made. All USFWS and Village
Selected lands in the general project area are in the Togiak
National Wildlife Refuge.
The proposed dam site on the Kurtluk River and borrow
sites D and E is on lands interim conveyed under ANCSA to
Togiak Natives, Limited. Interim conveyance is used to convey
unsurveyed lands. Patent will follow interim conveyance once
the lands are identified by survey. The subsurface estate for
all lands in the proposed project area conveyed to Togiak
-41-
• -
• ..
•
•
.. -
• -
---
• ..
• -
• ..
• -
• ..
• -
• ..
• ---
• ..
• ..
I I
I •
-
.-
....
-
-
,-
-
-
-
-
-
-
--
':J -....
T 15 S.
-.
~ -.t -,0: --
I -.hlO l
T. i 4 S.
SCALE I: 250000
5_==-_==-_=='0-_____ .....;;5 MILES
EXPLANATION
D USFWS Management Area
a Togiak Natives Ltd. Lands
@] • .....
Native Selected Landa
Private Landa Within Section
Propoaed Borrow Site
Propoaed Dam Site
GENERAL LAND STATUS MAP FIGURE 4
Natives, Ltd., has been interim conveyed to the regional Native
corporation, Bristol Bay Native Corporation.
Togiak has a federal townsite, U.S.S. 4905, with the
patent issued to the Bureau of Land Management (BLM) Townsite
Trustee. The Trustee has deeded occupied parcels to the resi-
dents and some vacant lots to the City of Togiak. Other subdi-
vided property remains with the Trustee .A permit would be
required for the transmission line to cross Trustee land and it
may be issued by the U. S. Department of Interior following an
affirmative resolution by the city council.
The final transmission route and transportation corridor
have not been selected at this time, but all preliminary alter-
natives for both are entirely within interim conveyed lands of
Togiak Natives, Ltd., with the exception of a small portion
near the Quigmy River and four parcels classified both village
Selection and Native Allotment application. Since final dis-
position of the Village Selected lands and final decisions on
the project conceptual plan have not been made, coordination
with USFWS, Togiak Natives, Ltd., Bristol Bay Native Corpora-
tion and BLM is recommended so that timely delays in acquiring
the needed permits and easements may possibly be avoided.
W. PERMITTING REQUIREMENTS
The following permits will be required for construction of
the Togiak hydropower facility:
Under the authority of Section 404 of the Fed-
eral Water Pollution Control Act, Amendments of
1972, the Army Corps of Engineers (CaE) must
authorize the discharge of dredged or fill mate-
rials into U.S. waters, by all individuals,
organizations, commercial enterprises, and fed-
-43-
• -• -• -
•
• -..
• ..
•
• ..
..
• -
• -
• ---
• -
• ..
• -
•
•
• -
.... '
-
-
-
-
-
" .. "
-
-
-
.-
-
-
eral, state and local agencies. A COE Section
404 Permit will therefore be required for the
Quigmy River dam and may be required for por-
tions of the road •
A Water Quality Certificate from the State of
Alaska, Department of Environmental Conservation
(DEC), is also required for any activity which
may result in a discharge into the navigable
waters of Alaska. Application for the certifi-
cate is made by submitting to DEC a letter re-
questing the certificate, accompanied by a copy
of the permit application being submitted to the
Corps of Engineers.
All public or private entities (except federal
agencies) proposing to construct or operate a
hydroelectric power project must have a license
from the Federal 'Energy Regulatory Commission
(FERC) if the proposed site is located on a nav-
igable stream, or on U. s. lands or if the pro-
ject affects a U.S. government dam or interstate
commerce.
A Permit to Construct or Modify a Dam is re-
quired from the Forest, Land, and Water Manage-
ment Division of the Alaska Department of Nat-
ural Resources for the construction, enlarge-
ment, al teration, or repair of any dam in the
State of Alaska that is ten feet or more in
height or stores 50 acre-feet or more of water.
A Water Rights Permit is required from the
Director of the Division of Forest, Land and
Water Management, Alaska Department of Natural
-44-
Resources for any person who desires to appro-
priate waters of the state of Alaska. However,
this does not secure rights to the water. When
the permit holder has commenced to use the ap-
propriated water, he should notify the director,
who will issure a Certificate of Appropriations
which secures the holders' rights to the water.
The Alaska Department of Fish & Game, Habitat
Division, under authority of AS16.05.870, the
Anadromous Fish Act, requires a Habitat Protec-
tion Permit if a person or governmental agency
desires to construct a hydraulic project or
affect the natural flow or bed of a specified
anadromous river, lake, or stream, or use equip-
ment in such waters. A Habitat Protection Per-
mit will be required for the Quigmy River dam
and for any work in or proximate to other anad-
romous streams (such as the ~urtluk River).
Under authority of AS16.05.840, the Alaska
Department of Fish and Game can require, if the
Commissioner feels it necessary, that every dam
or other obstruction built by any person across
a stream frequented by salmon or other fish be
provided with a durable and efficient fishway
and a device for efficient passage of fish. A
Habi tat Protection Permit will, therefore, be
required.
The proposed project area is located within the
coastal zone. Under the Alaska Coastal Manage-
ment Act of 1977, a determination of consistency
with Alaska Coastal Management Standards must be
obtained from the Division of Policy Development
-45-
• ..
• ..
•
• -
• -
• -
•
• ...
•
• --
• -• ..
III ..
• ---
• ---
• ..
-
'-
-
-
-
-
-
.-
-
-
-
-
-
-
-
-
and Planning in the Office of the Governor.
This determination would be made during the COE
404 Permit review.
Any party wishing to use land or facil i ties of
any National Wildlife Refuge for purposes other
than those designated by the manager in charge
and published in the Federal Register must ob-
tain a Special Use Permit from the u. S. Fish &
Wildlife Service. This permit may authorize
such activities as rights-of-ways; easements for
pipelines, roads, utilities, structures, re-
search projects; entry for geologic reconnais-
sance or similar projects, filming and so forth.
x. RECOMMENDATIONS
A fish pass should be designed and incorporated
into preliminary project plans, based on the
apparent need to pass both chum and silver sal-
mon •
The timing and number of the silver salmon runs
should be determined.
More detailed studies should be conducted con-
cerning the possible downstream effects from the
impoundment, with particular reference to spawn-
ing reaches.
Al though this is a run of river project, re-
source agencies may request instream flow stud-
ies may be necessary to determine minimum water
requirements for resident and anadromous fish.
-46-
Addi tional studies of the access route may be
required.
It may be necessary to incorporate some means of
safe passage for resident fish and outmigrating
smolt into the project design.
Y. REFERENCES CITED
Alaska Department of Fish & Game, 1980, Bristol Bay Annual Man-
agement Report, Appendix, Table 47.
Alaska Department of Fish & Game, 1978a, Alaska's Fisheries
Atlas, Volumes I and II.
Alaska Department of Fish & Game, 1978b, Alaska's Wildlife and
Habitat, Volume II.
Alaska Department of Fish & Game, 1973, Alaska's wildlife and
Habitat, Volume I.
Huber, W. C., D. R. F. Harleman, and P.J. Ryan, 1972, Tempera-
ture Predictions in stratified Reservoirs, Proc. ASCE, 98,
HY4, 645-666.
Togiak National Wildlife Refuge, Final Environmental statement.
watson, G. H., et al., 1973, An Inventory of Wildlife Habitat
of the MacKenzie Valley and the Northern Yukon. Environ-
mental social Committee, Task Force on Northern oil Devel-
opment, Report 73-27.
z. PERSONNAL COMMUNICATIONS
Dilliplane, Ty. Alaska Department of Natural Resources, Divi-
sion of Parks. 1981.
-47-
• ..
• ..
•
• -
• -• ..
• -• ..
•
• -----
• .. --• -
• -
• -
• •
• •
-
-
-
-
.....
-
-
-
..
-
-
.-
Bucher, Wes, Fisheries Biologist,
sion, Alaska Department of
Alaska. 1981.
Logusak, Frank, Togiak Resident.
Commercial Fisheries Divi-
Fish and Game, Dillingham,
1981.
Money, Dennis, U.S. Fish and Wildlife Service, Endangered Spe-
cies. 1981.
Nanalook, Robert, Togiak Village Council. 1981.
Taylor, Ken, Game Biologist, Game Division, Alaska Department
of Fish & Game, Dillingham. 1981.
-48-
~--.----.--.-.-... -.--.. --... -----.~-.---------------------------------
TOGIAK HYDROELECTRIC PROJECT
FEASIBILITY STUDY
APPENDIX F
LETTERS AND MINUTES
" ..
.-
-
-
-
-
-
-
-...
-
--
Public Meeting Questions and Answers
A public meeting was held on March 25, 1982 in the community
of Togiak to discuss the results of this study. The
following questions were asked and answers given during the
meeting •
1. Where is the project site?
2.
On the Quigmy River approximately 7 miles upstream from
Togiak Bay.
How much fuel oil will be displaced?
until approximately the year 2000 all diesel fuel used
for electrical energy production would be displaced.
Diesel fuel would be needed for back-up generation.
3. How much will the road and powerline cost?
4.
The transmission line would cost $1,224,230. If the
Department of Transportation builds part of the road
then the cost to the project would be approximately
$500,000. If the entire road cost is assigned to this
project the cost would be approximately $1,600,000.
Who will the road belong to?
The State of Alaska.
5.
6.
What will happen to the small game in the area?
It will be driven out by the water or die. However, it
is important to point out that this is a run of the
river project with only a very small inundated area.
What about use of wind?
Wind may be useful for a small amount of the power
needed for Togiak. See text for an analysis.
7. Who will own the project?
8.
9.
The State of Alaska.
What would the environmental effects be?
More road access would create greater hunting and
gathering pressure on the area between Togiak and the
site. A fish ladder would be provided at the dam but
not all fish would be able to make it up the river.
Is there any priority for the development of this
project?
The Alaska Power Authority has yet to make a
determination of priority, however due to the low
benefit/cost ratio this project is not likely to have a
very high priority.
• • ..
•
• •
• -
• ---
• ..
• -• -• -
• -
• ..
• -----
• ..
• -
• •
•
•
-
-
-
-
-
-
....
-
10. What would have to happen to make this project
feasible?
The price of fuel would have to rise significantly or
the electrical demand would have to increase or
construction costs would have to go down.
11. Could Togiak own the project later?
It is possible. No determination has been made.
12. Has this work been shown to the legislators?
Yes, they received copies of the Draft Report.
.. ~-.. -~ :r
'I I:
'j
,J
T09 I ~ k M Q."'+I"kC;' -Ma...t"C!.t.. LS'~ 17'5)..
2'.3<: PM
• ..
• ..
• ..
• -
• -
• -• ..
• ..
•
• -
• .. --.. ..
• -
• -
•
• -
• •
• •
---. -_._-------------------..
...
-
--
....
-
-
-
-
-
lAY S. HAMMOND, GOYCRNOR
431 E. STREET
SECOND FLOOR KJ ANCHORAGE. ALAS~A £1950'
(90l) 214·2533
SOUTHCENrRAL REGIONAL OFFICE 0 P.O. 80X 6'5
KODIAK. ALASKA 996'5
{SOl} 4863350
P.O. BOX '101
March 26, 1982 0 SOLDOTNA. ALASKA 99669
Mr. Don Baxter
Project Hanager
Alaska Power Authority
334 W. 5th Avenue
Anchorage, Alaska 99501
RECEIVED
0
APR -11982 0
ALASKA POWER AUTHORITY
(SOl) 251·52'0
P.O. BOX 1709
VALDEZ. ALASKA
(SOl) 8354698
P.O. 80X '054
WASILLA. ALASKA
{P071 376·5038
RE: Larsen Bay, Old Harbor, King Cove, and Togiak Hydro Studies.
Dear Mr. Baxter:
Having had the opportunity to' review the hydro feasibility studies for
these projects, we find no apparent major or permanent environmental impacts
related to these improvements with the exception of the Togiak proj ect.
With the implementation of the recommended environmental procedures speci-
fied in the former three hydro studies, the projects should be able to
substantially comply with all necessary environmental requirements.
As regards Togiak, our concerns relate to measures necessary to mitigate
anticipated changes in water quality, including temperature, dissolved
oxygen, and pH. In relation to recommended environmental procedures out-
lined in the report, we advise that in-stream flow investigations address
the relative impacts of likely changes in water quality and potential
mitigation measures. We would be happy to discuss these observations with
you. Thank you for the opportunity to comment.
Sincerely •
~~foZ/'
Bob Martin
Region~l Supervisor
BM/vh/ccs
99686
99687
i
·1 I
I
!
I
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
~1r. Bob ~1a rt in
Regional Supervisor
State of Alaska
Oepartment of Environmental Conservation
437 E Street
Second Floor
Anchorage, Alaska 99501
July 28, 1982
Phone: (907) 277·7641
(907) 276·0001
Subject: Draft Feasibility Reports on Hydroelectric Projects at
King Cove, Old Harbor, Larsen Bay; Draft Reconnaissance
Report of a Hydroelectric Project at Togiak.
Dear Mr. Martin:
Thank you for your March 26, 1982, letter to Mr. Don Baxter of my
staff regarding the above referenced reports. We appreciate your
participation and timely input in reviewing the draft reports and are
pleased to hear that you find no apparent major or permanent
environmental impacts related to the projects, with the exception of
Togiak.
The project at Togiak appears to be marginally feasible from an
economic standpoint and the likelihood of proceeding with additional
studies is questionable. However, if the project is carried forward,
appropriate mitigation measures will be taken to preserve Quigmy River
water quality. An instream flow study program would become an integral
part of any additional study programs.
Thank you again for your consideration and timely input. Should
you have further questions regarding these projects, please contact
myself or Mr. Don Baxter of my staff.
c\? --M
Eric P. Yould ~
Executive Director
• ..
• • .. ..
• -
• ..
• -
• -• -
• -
• -
• ..
• ..
• -
• -
• -
• -.. .. ..
•
-
-
-
'W
-
-
-
-
I
I JAY S. HAMMOND, GOVERNOR
DEPARDIE~T OF NATURAL liES01JRClES tN. WAREHOUSE OR .• SUITE 210
ANCHORAGE, ALASKA 99501
April 12, 1982
File No. 1130-13
Laurel A. Ben~ett
DOWL Engineers
4040 liB" Street
Anchorage, AK 99503
DIVISION OF PAttKS /'HONE: 274-4676
Subject: Togiak dam sites on Kurtluk River and Quigmy River to
include road or barge landing site, transmission line.
Dear }OIr. Bennett:
We have reviewed the subject rroposal and yould like to offer the
folloYing comments:
STATE HISTORIC PRESERVATION OFFICER
Our review indicates that significant cultural resources may be im-
pacted. The terrain in question may yell contain currently unknown
prehistoric sites. Numerous sites are presently known to exist through-
out the surrounding region. AHRS site No. GDN-205, a former Eskimo
Village, is located at the mouth of the Kurtluk River. Therefore, per
36 CFR 800, and AS 41.35.070, a preconstruction culturai resources
survey is recommended.
. Dilliplane
Historic Preservation
STATE PARK PLANNING
No probable or significant impact on existing, proposed or potential
state park or other public recreation values, although outdoor rec-
reation opportunities nlight be increased as a result of new road access.
LAND & WATER CONSERVATION FUND GRANT PROG~~1
No conunent.
Sincerely,
~~ _j~ Chip Dcnnerlcin
Y-Director
cn/bIh
,00JlI LIt
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Ms. Judy Marquez
Director
State of Alaska
Department of Natural Resources
Division of Parks
619 Warehouse Drive, Suite 210
Anchorage, AK 99501
July 28, 1982
Phone: (907) 277·7641
(907) 276·0001
SUBJECT: Draft Feasibility Reports on Hydroelectric Projects at
King Cove, Old Harbor, Larsen Bay; Draft Reconnaissance Report
of a Hydroelectric Project at Togiak.
Dear Ms. Marquez:
Thank you for your letters of April 12, March 30 and March 31,
1982, to Ms. Laurel Bennett of DOWL Engineers regarding the above
referenced feasibility and reconnaissance reports. We appreciate your
participation and timely input in reviewing the draft reports.
In response to the concerns voiced in your letters,
preconstruction cultural resource surveys would be accomplished prior to
the initiation of construction activity on any of the projects. Any
work associated with the scoping and implementation of such surveys
would be fully coordinated with your office. Furthermore, the project
at Togiak does not appear to be attractive at this point in time due to
economics, and it is doubtful that it will be carried forward into
developmental stages.
Should you have further questions regarding these studies, please
contact myself or Mr. Don Baxter of my staff.
Sincerely,
~;. y~ l\Jl
Executive Director
• •
• •
•
• -
• ..
• ..
•
• ..
• .. --
• --., -----
• -
• -
• ..
-
-
.....
-
-
-....
.-
-
,-
-
-
/
I
DlVlSJCW OF FOREST, LAND AND WATER AWlAGEMENT
April 12,
Eric P Yould
Executive Director
Alaska power Authority
334 West 5th Avenue
Anchorage, Alaska 99501
Dear Mr. Yould,
/ JAr $. HAMMOND, GOYERNOA
555 Cordova Street
Pouch 7-005
ANCHORAGE. ALASKA
PHONE: (907}276-2653
1982
RE01:::IVt;u
f?R ! 3 138'2
AlASKA rO'fER AUTIJI;!\iff
A review has been made of Volumes A, B, C, D and E
regarding the Feasibility Studies for the King Cove
Hydroelectric project, Old Harbor Hydroelectric Project,
Larsen Bay Hydroelectric Project and the Reconnaissance
Study for the Togiak Hydroelectric Project.
As mentioned, for each project the Division of Land and
Water Management has the responsibility for issuing both a
permit to construct or modify a dam and a water rights
permit. Comments follo'll that appear to apply to all four
projects.
a. permit to Construct or Modify a Dam
Prior to issuing the permit, this office must be assured
that the dam will not create a public safety hazard. A
certification to this effect after the state of the art
techniques that analyze the design and construction as well
as the proposed operation and maintenance schedules of the
dam will be acceptable. If the Federal Energy Regula tory
Commission (FERC) is involved in licensing the project, dam
safety certifications by them will be accepted. For dams
not reviewed by FERC, we will review work done by the
applicant such that this office may certify to the dam's
safety. As the projects develop, please send to this
office, dam safety certifications by the FERC, or the
appropriate documents allowing such to be made.
b. Water Rights Permit
According to AS 46.15.080, a water rights permit shall
be issued if it is found that:
1. The proposed appropriation will not unduly affect
the rights of a prior appropriator. From a review of
our files on April 8, it appears that no water rights
exist in the areas to be impacted.
2. The proposed means of diversion or construction are
adequate.
3. The proposed appropriation is in the public
interest. To evaluate this, among the items to be
considered are changes in the following as a result of
the proposed water appropriation:
(a) economic activity,
(b) fish and game resources,
(c) public recreational opportunities,
(d) public health,
(e) loss of alternate uses.of water that might be
made within a reaso~able time,
(f) harm to persons,
(9) access to navigable or public waters.
To process the water rights application, the above items
must be addressed for each project stage, including
construction, reservoir filling and operation. If negative
impacts are noted, mitigation strategies and the associated
costs should also be discussed.
The feasibility study discusses some of the above items.
Some statements, however, have limited, if any, supporting
evidence and are therefore considered inadequate for the
adjudication of a water rights application.
It is understood that it is not the intent of this
feasibility study to present detailed information as
described above. However, please be informed that this
information is necessary to adjudicate the application to
construct or mOdify a dam and the application for water
rights according to our legal responsibilities.
Sincerely,
J. W. Sedwick, Director
{-i
by: Paul J nk;
Civil Engineer
Water Management Section
• •
• •
• • .. -• .. .. ..
• ..
•
.. ..
• .. .. ..
• .. .. -
•
.. -
•
-..
• •
• ..
......
-
-
-
-
-
-
-
-
-
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Mr. Jack W. Sedwick
Director
State of Alaska
Dept. of Natural Resources
Division of Forest, Land and Water
Management
555 Cordova Street
Pouch 7-005
Anchorage, AK 99501
July 28, 1982
Phone: (907) 277·7641
(907) 276·0001
SUBJECT: Draft Feasibility Reports on Hydroelectric Projects
at King Cove, Larsen Bay and Old Harbor; Draft Reconnaissance
Report of a Hydroelectric Project at Togiak.
Dear Mr. Sedwick:
Thank you for your letter of April 12th regarding the above
referenced reports. The following letter addresses issues and answers
questions contained in your letter. We appreciate the participation and
timely input of you and your staff in reviewing the draft reports.
Our responses to your comments are included below:
a. Permit to Construct or Modify a Dam
For King Cove, Old Harbor and Larsen Bay, plans will
be submitted during the design phase of these projects,
however, we understand that a permit will not be
required because the proposed dams are less than 10 feet
in height. The dam proposed for the Togiak site is
greater than 10 feet in height, but the project does
not appear to be economically attractive. It is therefore
doubtful that the project would ever be developed.
b. Water Rights Permit
Except for the QUigmy River near Togiak, there are no
established navigable uses for any of the streams or rivers
under consideration. The text has been modified to reflect
this comment.
In a meeting with Paul Janke, some concern was expressed about
minimum flows. This issue is addressed in our letters to the
u.S. Fish & Wildlife Service (USFWS), copies of which are attached.
Mr. Jack W. Sedwick
July 28, 1982
Page 2
Discussions of impacts during operations and maintenance, water
quality issues, and loss of alternative uses have been incorporated into
the final report text. Furthermore, ADEC concerns regarding fish and
game resources have also been addressed in the final report text and in
the attached letters to USFWS.
Thank you again for your consideration and timely input. The
Power Authority looks forward to a successful working relationship with
the Department of Natural Resources in bringing these projects forward.
Should you have further questions, please contact myself or
Mr. Don Baxter of my staff.
Attachments as noted
C~·ll~
Eric P. Yould '1
Executive Director
• ..
• • ..
•
• -•
•
• -
•
• -
•
• -
• -
• -
• -
• -
• -• -
• -
• -
• ..
..."
-
-
-
-
-
rvl E l\~ 0 R A [\J D U f\~
DEPl\lnHENT or NI\ TU R/\L RESOUHCES
TO Eric P. Yould
Executive Director
Alaska Power I\uthority
fHOM Reed It-tilhp/ DireJt~~V
State of Alaska
DIVISION OF RES[/\RCH AND DEVELOP~tENT
DATe April 12, 1982
FILE NO
TElEPHONE NO 276-1653
SUElJECT DNR comments
The Department of Natural Resources has no comments on the draft
feasibility reports listed below.
Draft feasibility study for King Cove Hydroelectric Project
Draft feasibility study for Old Harbor Hydroelectric Project
Draft feasibility study for Larsen Bay Hydroelectric Project
Draft feasibility study for Togiak Hydroelectric Project
RECEIVED
.' ~12 1 1982
'ALASKA POWER AUTHORITY
(u-·" '". ::.-] ; i : -,
I i r
I ' ~:U
1)I~IJt;\nl"a:~T OS-' ... ~SJl ;\ ~n (j.\ :ll.:
Apri 1 14, 1982
Alaska Power Authority
334 West 5th Avenue
Anchorage, Alaska 99501
OFFICE Of THE COMMISSIONER
Attention: Eric P. Yould, Executive Director
Gentlemen:
JA r s. HAMMON~. GOVERNOR
P.O. BOX 3-2000
JUNEAU, ALASKA 99802
PHONE: 465-4100
RECEIVt:.D.
P.?R 1 91322
PO'"E''' ~IITlIN"IT'\( tLP.SK.t.. ;. il , .... , .~'1" .
Re: Feasibility Studies for King Cove Hydroelectric Project, Old Harbor
Hydroelectric Project, Larsen Bay Hydroelectric Project and
Reconnaissance Study for Togiak Hydroelectric Project
The Alaska Department of Fish and Game has reviewed the subject documents
and generally concurs with the contents. There are, however, several
informational needs and statutory requirements that need to be addressed.
These are ou t 1 i ned ~Jith in the enc 1 osed spec i fi c comments.
If you have any questions or comments, please do not hesitate to contact me.
Sincerely,
~
Ronald O. Skoog
Commissioner
cc: C. Yanagawa
R. Logan
• •
• •
•
• -
•
• -
• -• -..
--
• -
• -.. -
• -
• -
• ---
• ..
•
•
-
-
-
-
-
-
Volume B -Feasibility Study for King Cove Hydroelectric Project -Draft Report
SECTION X -ENVIRONMENTAL AND SOCIAL EFFECTS
B. ENVIRONMENTAL EFFECTS
1. Fi sheries
Page X-2, para. 3
Alaska Statute 16.05.840 requires that, if the Commissioner feels it
necessary, dams be fitted with fishways and devices for passage of fish.
This may necessitate a minimum flow release thro.ugh the stream reach below
the diversion weir.
SECTION XI -PROJECT IMPLEMENTATIONS
B. PROJECT LICENSES, PERMITS, AND INSTITUTIONAL CONSIDERATIONS
Page XI-l, general comment
Absent from the list of permit requirements ;s that pertaining to
AS 16.05.840 as follows:
"Sec. 16.05.840. Fishway required. If the commissioner considers it
necessary, every dam or other obstruction built by any person across a
stream frequented by salmon or other fish shall be provided by that person
with a durable and efficient fishway and a device for efficient passage for
downstream migrants. The fishway or device or both shall be maintained in a
practical and effective manner in the place, form and capacity the
commissioner approves, for which plans and specifica-
• ..
• •
• ...
• ..
tions shall be approved by the department upon application to it. The ..
fishway or device shall be kept open, unobstructed, and supplied with a
sufficient quantity of water to admit freely the passage of fish through it .
(Par. 30 pat 1 ch 94 SLA 1959).11
A Habitat Protection Permit constitutes approval under AS 16.05.840.
SECTION XII -CONCLUSIONS AND RECOMMENDATIONS
B. REcOt1r~ENDA TI OH
Page XII-l, general comments
We recommend that a determination of a minimum flow requirement to pass fish
between the weir and powerhouse be made. Knowledge of this figure and its
impact on power production will aid in making the detel~minatiol1 of necessity
to provide fish passage relative to AS 16.05.840.
APPENDIX E ENVIRONMENTAL REPORT
D. FISHERIES
Page 8, para. 1 & 2, page 9, para. 1
..
• .. .. ..
..
• ..
• -
• -..
•
•
.. ...
• -.. ...
III -.. -• •
-
-
-
-
-
-
....
-
-
-
-
We question the accuracy of some of the statements regarding substrate sizes
and other optimum spawning conditions, including those obtained from the
ADF&G 1978, Fisheries Atlas. Some work has already been conducted and other
is ongoing regarding development of species suitability curves for several
river systems in Alaska. While it should be recognized that curves
developed for species in one system cannot be directly applied to those in
another, they may be used in making qualified generalizations.
G. FISHERIES IMPACTS
Page 13, para. 3
Any habitat improvement accrued by retention of sediments will be negated by
loss or absence of flow.
H. FISHERY MITIGATION
Page 14 & 15, general comments
The fisheries mitigation section fails to address measures other than
reduction of sedimentation. Other impacts such as loss of habitat in
dewatered streams reaches and impediment to fish migration must also be
addressed.
M. WILDLIFE MITIGATION
Page 24, para. 7
The 330 foot buffer cited here is a USFS recommendation for minimum
separation for falling of trees. In instances where there is flexibility to
locate camps, material sites, etc. at a distance greater than 330 feet, we
•
• •
•
•
recommend it be done. In addition, we suggest a minimum separation of 500 •
feet and strongly discourage siting within one-quarter mile. • -
With respect to aircraft separation, we recommend 1500 feet separation • •
for helicopters and 500 feet for fixed wing craft. ..
•
Pages 24, general comments •
•
The wildlife mitigation section fails to address mitigation measures related -
to restoration of material sites, abandoned camp sites and utilization of
transmission lines designed to minimize large raptor electrocution.
U. PERMITTING REQUIREMENTS
Pages 28-29, general comments
Absent from the list of permit requirements is that pertaining to
AS 16.05.840 as follows:
"Sec. 16.05.840. Fishv.[ay required. If the commissioner considers it
necessary, every dam or other obstruction built by any person across a
stream frequented by salmon or other fish shall be provided by that person
with a durable and efficient fishway and a device for efficient passage for
downstream migrants. The fishway or device or both shall be maintained in a
•
• ..
•
• •
•
III
• • ..
..
•
• -
•
•
l1li
-
-
-
-
-
-
....
-
-
-
-
practical and effective manner in the place. fonn and capacity the
commissioner approves, for which plans and specifica-
tions shall be approved by the department upon application to it. The
fishway or device shall be kept open, unobstructed, and supplied with a
sufficient quantity of water to admit freely the passage of fish through it.
(Par. 30 pat 1 ch 94 SLA 1959)."
A Habitat Protection Permit constitutes approval under AS 16.05.840.
V. RECOMMENDATIONS
Page 31, general comments
We recommend that a determination of a minimum flow requirement to pass fish
between the weir and powerhouse be made. Knowledge of this figure and its
impact on pOYJer prl)duction will and in making the determination of necessity
to provide fish passage .
Volume C -Feasibility Study for Old Harbor Hydroelectric Project -Draft Rej10rt
SECTION X -ENVIRONMENTAL AND SOCIAL EFFECTS
B. ENVIRONMENTAL EFFECTS
Page X-2. 1. Fisheries
•
•
. Was any effort expended towards sampling for fish between the powerhouse and
diversion weir site and above to ascertain use by fish? If not (as can be -
concluded from the report), there is no way to predict the consequences of
habitat lost through dewatering or the impact of impeding fish migrations.
Page X-2, 2. Wildlife
.. -
• •
• ...
Bear confrontations are likely to be the most serious wildlife consequence ..
of the project. Confrontations would be most likely from August through
October when bear are feeding on salmon in Big Creek. If construction were .
executed other than in this time period, likelihood of this problem would be
considerably reduced. Precautions with disposal of garbage and other food
scraps (lunches, etc.) during construction will also reduce the potential
for bear problems.
Owing to the large number of bald eagles in the area, transmission line
designs which minimize large raptor electrocution must be e~ployed.
SECTION XI PROJECT IMPLEMENTATION
B. PROJECT LICENSES, PERMITS, AND INSTITUTIONAL CONSIDERATIONS
Page XI-l, general corr~ent
Absent from the list of permit requirements is that pertaining to
AS 16.05.840 as follows:
...
... ..
• .. ..
• • ..
•
... ..
• -
•
•
•
•
• •
• ..
-
-
-
-
,-
-
'"*
-
-
-
-
"Sec. 16.05.840. Fishway required. If the commissioner considers it
necessary, every dam or other obstruction built by any person across a
stream frequented by salmon or other fish shall be provided by that person
with a durable and efficient fishway and a device for efficient passage for
downstream migrants. The fishway or device or both shall be maintained in a
practical and effective manner in the place. form and capacity the
commissioner approves, for which plans and specifi-
cations shall be approved by the department upon application to it. The
fishway or device shall be kept open, unobstructed, and supplied with a
sufficient quantity of water to admit freely the passage of fish through it.
(Par. 30 pat 1 ch 94 SLA 1959)."
A Habitat Protection Permit constitutes approval under AS 16.05.840.
SECTION XII -CONCLUSIONS AND RECOMMENDATIONS
B. RECOMMENDATIONS
Page XII-l, general comments
We recommend that it be determined whether fish utilize that portion of the
stream that will be dewatered below the weir for either residence or as a
migration route. If it is used for either or both, a fishway and/or minimum
release may be required.
APPENDIX E -ENVIRONMENTAL REPORT
D. FISHERIES
Page 4-6 general comments
We question the accuracy of some of the statements regarding substrate sizes
and other optimum spawning conditions, including those obtained from the
ADF&G 1978, Fisheries Atlas. Some work has already been conducted and other
is ongoing regarding development of species suitability curves for several
river systems in Alaska. While it should be recognized that curves
..
• .. .. .. .. -
• •
• ..
•
developed for species in one system cannot be directly applied to those in •
another, they may be used in making qualified generalizations.
H. FISHERY MITIGATION
Page 9 & 10, general comments
The fisheries mitigation section fails to address measures other than
reduction of sedimentation. Other impacts such as loss of habitat in
dewatered streams reaches and impediments to fish migration must also be
addressed.
M. WILDLIFE MITIGATION
Page 22, para. 1
The 330 foot buffer cited here is a USFS recommendation for minimum
• ..
• ..
• ..
• .. .. -
• •
• .. ..
.. ..
separation for falling of trees. In instances where there is flexibility to •
•
• •
-
-
-
-
-
-
-
-
-
-
--
-
-
-
-
locate camps, material site, etc. at a distance 9~eater than 330 feet, we
recommend it be done. In addition, we suggest a minimum separation of 500
feet and strongly discourage siting within one-quarter mile.
With respect to aircraft separation, we recommend 1500 feet separation
for helicopters and 500 feet for fixed wing craft.
Pages 21 & 22, general comments
The wildlife mitigation section fails to address mitigation measures related
to restoration of material sites, abandoned camp sites and utilization of
transmission lines designed to minimize large raptor electrocution.
U. PERMITTING REQUIREMENTS
Pages 26-28, general comment
Absent from the list of permit requirements is that pertaining to
AS 16.05.840 as follows:
"Sec. 16.05.840. Fishway required. If the commissioner considers it
necessary, every dam or other obstruction built by any person across a
stream frequented by salmon or other fish shall be provided by that person
with a durable and efficient fishway and a device for efficient passage for
downstream migrants. The fishway or device or both shall be maintained in a
practical and effective manner in the place, form and capacity the
commissioner approves, for which plans and specifi-
cations shall be approved by the department upon application to it. The
.. ..
• •
•
fishway or device shall be kept open, unobstructed, and supplied with a ..
sufficient quantity of water to admit freely the passage of fish through
(Par. 30 pat 1 ch 94 SLA 1959)."
A Habitat Protection Permit constitutes approval under AS 16.05.840.
V. RECOMMENDATiONS
Page 28, general comments
• of-, "'.
We recommend that it be determined whether fish utilize that portion of the
stream that will be dewatered below the weir for either residence or as a
• •
• ...
• •
• ..
• ...
• ..
•
migration route. If it is used for either or both a fishway and/or minimum ..
release may be required.
Volume 0 -Feasibility Study for Larsen Bay Hydroelectric Project -Draft Report
SECTION X -ENVIRONt-1ENTAL AND SOCIAL EFFECTS
B. ENVIRONMENTAL EFFECTS
1. Fi sheri es
• -
•
• --.. --
• -
•
•
-•
III
-
..
-
-
-
-
-
-
Page X-3, para. 3
Alaska Statute 16.05.840 requires that, if the Commissioner feels it
necessary, dams be fitted with fishways and devices for passage of fish.
This may necessitate a minimum flow release through the stream reach below
the diversion weir.
Dolly Varden are identified as being trout. They are chars.
SECTION XI -PROJECT IMPLEMENTATION
B. PROJECT LICE~SES, PERNITS, AND INSTITUTIONAL CONSIDERATIONS
Page XI-l, general comment
Absent from the list of permit requirements is that pertaining to
AS 16.05.840 as follows:
"Sec. 16.05.840. Fishway required. If the commissioner considers it
necessary, evel'y dam or other obstruction built by any person across a
stream frequented by salmon or other fish shall be provided by that person
with a durable and efficient fishway and a device for efficient passage for
downstream migrants. The fishway or device or both shall be maintained in a
practical and effective manner in the place, form and capacity the
commissioner approves, for \<Ihich plans and specifica-
tions shall be approved by the department upon application to it. The
fishway or device shall be kept open, unobstructed, and supplied with a
sufficient quantity of water to admit freely the passage of fish through it.
(Par. 30 pat 1 ch 94 SLA 1959)."
A Habitat Protection Permit constitutes approval under AS 16.05.840.
SECTION XII -CONCLUSION AND RECOMMENDATIONS
B. RECOMMENDATION
Page XII-l, general comments
We recommend that a determination of a minimum flow requirement to pass fish
between the weir and powerhouse be made. Knowledge of this figure and its
impact on power production will aid in making the determination of necessity
to provide fish passage relative to AS 16.05.840.
APPENDIX E -ENVIRONMENTAL REPORT
D. FISHERIES
Page 5, general comments
An assessment of the fisheries resources present between the weir and
pm"erhouse should be made to determine the necessity of maintaining a
minimum flow and the advisability of constructing fish passage structures.
Page 6, para. 1-3
• • ..
• ., ..
-
• -
• -.-..
• ..
• •
• -• ..
• ---
• ..
..
•
•
• •
• -
• ..
.. *""
-
....
-
-
-
.-
-
-
G.
We question the accuracy of some of the statements regarding substrate sizes
and other optimum spawning conditions, including those obtained from the
ADF&G 1978, Fisheries Atlas. Some work has already been conducted and other
is ongoing regarding development of species suitability curves for several
river systems in Alaska. While it should be recognized that curves
developed for species in one system cannot be directly applied to those in
another, they may be used in making qualified generalizations.
FISHERIES IMPACTS
Page 7, general comments
The presence of the weir and lack of flow will impede fish passage
throughout the affected reach.
H. FISHERY MITIGATION
Page 9 & 10, general comments
The fisheries mitigation section fails to address measures other than
reduction of sedimentation. Other impacts such as loss of habitat in
dewatered stream reaches and impediment to fish migration must also be
addressed.
M. WILDLIFE MITIGATION
Page 22, para. 7
The 330 foot buffer cited here is a USFS recommendation for minimum
separation for falling of trees. In instances where there is flexibility to
locate camps, material sites, etc. at a distance greater than 330 feet, we
• -• ... .. ..
recommend it be done. In addition, we suggest a minimum separation of 500-
feet and strongly discourage siting within one-quarter mile.
With respect to aircraft separation we recommend 1500 feet separation
for helicopters and 500 feet for fixed wing craft.
Pages 24, general comments
The wildlife mitigation section fails to address mitigation measures related
to restoration of material sites, abandoned camp sites and utilization of
transmission lines designed to minimize large raptor electrocution.
U. PERMITTING REQUIREMENTS
Pages 26-29, general comments
Absent from the list of permit requirements is that pertaining to
AS 16.05.840 as follows:
"Sec. 16.05.840. Fislw/ay required. If the commissioner considers it
necessary, every dam or other obstruction built by any person across a
stream frequented by saimon or other fish shall be provided by that person
with a durable and efficient fishway and a device for efficie~t passage for
downstream migrants. The fishway or device or both shall be maintained in a
• -..
III;
•
•
-•
• -
• ..
• -• ..
• -
• ..
• •
• -
•
•
• -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
pr(lctical and effective manner in the place, form and capacity the
commissioner approves, for which plans and specifica-
tions shall be approved by the department upon application to it. The
fishway or device shall be kept open, unobstructed, and supplied with a
sufficient quantity of water to admit freely the passage of fish through it.
(Par. 30 pat 1 ch 94 SLA 1959)."
A Habitat Protection Permit constitutes approval under AS 16.05.840.
V. REcor"r~ENDATIONS
Page 31, general comments
We recommend that a determination of a minimum flow requirement to pass fish
between the weir and powerhouse be made. Knowledge of this figure and its
impact on power production will aid in making the determination of necessity
to provide fish passage relative to AS 16.05.840.
Volume E
Reconnaissance Study for Togiak Hydroelectric Project -Draft Report
SECTION VI -ALTERNATIVE HYDROELECTRIC PROJECTS
Page VI-5, 5. Fi sh Lndder
In addition to provisions to pass fish upstream consideration must be given
to a means of providing passage of dO\,instream migrants (fry, smolts and
resident fish) without incurring significant mortalities. In many
• ..
••
•
•
...
instances, fish are unable to survive passage through turbines. In response ..
to this problem, a number of devices such as traveling screens and baffled II
intakes have been developed.
SECTION X -ENVIRONMENTAL AND SOCIAL EFFECTS
A. GENERAL
Page X-I, para. 2
B.
With respect to recommendations for additional study, the upstream effects
of the impoundment on salmon and resident spawning and rearing habitat need
to be addressed. We also assume that downstream impacts to all salmon and
resident species will be addressed.
ENVIRONMENTAL EFFECTS
Page X-3, para. 1
Dolly Varden are referred to as trout, they are char.
Puge X-4, para. 1
•
• ..
• ..
• -•
• •
• •
• -• ...
• -
• ..
• -
• •
• •
• -
-
-
-
-
...
-
....
-
-
-
Although it is generally known that chum salmon spawning is heaviest in the
lower one-half of the Quigmy River, distribution of all salmon species
should be verified in subsequent studies. This is an important factor when
determining requirements for minimum flows. In addition, it is recognized
that chum salmon typically spawn in areas of groundwater upwelling. If this
can be verified in the Quigmy River, it may have great significance
respective to flow release for fisheries.
SECTION XI -PROJECT IMPLEMENTATION
B. DEFINITIVE PROJECT REPORT
Page XI-3, 5. Hydrology
Statement is made that estimates are based on data from areas 75 to 150 feet
distant. Perhaps the distance is actually 75 to 150 miles.
D. PROJECT LICENSES, PERMITS, AND INSTITUTIONAL CONSIDERATIONS
Page XI-6, 3. ADF&G Permits
Statement is made that a Habitat Protection Permit is required for
Delta Creek. Should this refer to Quigmy River instead?
Absent from the list of permit requirements is that pertaining to
I
AS 16.05.840 as follows:
"Sec. 16.05.840. Fishway required. If the commissioner considers it
necessary, every dam or other obstruction built by any person across a
stream frequented by salmon or other fish shall be provided by that person
with a durable and efficient fishway and a device for efficient passage for
downstream migrants. The fishway or device or both shall be maintained in a
practical and effective manner in the place, form and capacity the
commissioner approves, for which plans and specifi-
cations shall be approved by the department upon applicaticn to it. The
fishway or device shall be kept open, unobstructed, and supplied with a
sufficient quantity of water to admit freely the passage of fish through it.
(Par. 30 pat 1 ch 94 SLA 1959).11
A Habitat Protection Permit constitutes approval under AS 16.05.840.
APPENDIX E -ENVIRONMENTAL REPORT
0.1. Spawning
Page 11, para. 2
Optimum stream velocity for coho salmon is cited as being 3-4 cubic feet
second (cfs). This is a discharge quantity rather than one of velocity.
Page 12, para. 1
Dolly Varden are properly refer-red to as char rather than trout.
per
• ..
••
•
• ..
• ..
• ..
• -
• ..
•
--• •
• •
• -• -.. -
• ..
• ..
•
'lit
• •
• -
-
......
-
-
-
-
-
-
-
-
.....
Page 11 & 12, general comments
I.
We question the accuracy of some of the statements regarding substrate sizes
and other optimum spawning condition, including those obtained from the
ADF&G 1978 Fisheries Atlas. Some work has already been conducted and other
is ongoing regarding development of species suitability curves for several
systems in Alaska. While it should be recognized that curves developed for
a species in one system cannot be directly applied to those in another, they
may be used in making qualified generalizations.
FISHERIES IMPACTS
Page 21, para. 3
There may be streambed morphology changes associated with the project due to
attenuation of some flood events and lack of material recruitment from
reaches above the dam.
J. FISHERY MITIGATION
Page 22, para. 2
Is the inference here that improving the road as little as possible will
reduce the erosion potential? If so, we believe this to be an erroneous
conclusion. A maintained gravel surface of adequate dimensions will produce
far fewer fines than an unimproved surface.
• -••
•
Page 22, general conments .. ..
This discussion fails to address fisheries mitigation other than ..
sedimentation and erosion control. There is no mention of flow maintenance, ..
provision for safe passage of downstream migrants, provisions for passage of ..
upstream migrants, etc.
Q. WILDLIFE MITIGATION
Page 36 & 37, general comments
Discussion should also address mitigation measures related to restoration of
disturbed areas, prohibition of vehicular access to project roads,
scheduling of construction events to minimize disturbance to wildlife, etc.
-
•
•
• •
• -
• -• -
• ---.. -
•
• -
• -• ..
'-
-
-
-
---
-
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Mr. Ronald Skoog
Commissioner
Alaska Department of Fish & Game
P.O. Box 3-2000
Juneau, AK 99802
July 28, 1982
Phone: (907) 277-7641
(907) 276-0001
Subject: Feasibility Studies for King Cove Hydroelectric project,
Old Harbor Hydroelectric Project, Larsen Bay Hydroelectric
Project and Reconnaissance Study for Togiak Hydroelectric
Proj ect
Dear Commissioner Skoog:
This letter is in response to your letter of April 14, 1982 and the
subsequent meeting of April 28, 1982 discussing ADF&G1s concerns about
the above referenced projects. Note that this meeting included several
representatives from the U.S. Fish & Wildlife Service as well as our
consultant, DOWL Engineers. We appreciate the constructive nature of
the comments and the time members of your staff spent in review and
discussion of these projects.
GENERAL COMMENTS APPLICABLE TO KING COVE, OLD HARBOR AND LARSEN BAY ARE:
The Habitat Protection Permit required by Section 16.05.840,
Fishway required, has been included in the list of permit
requirements. (Volume B, XI-2 and page 29, Appendix E; Volume C,
XI-2 and page 27, Appendix E; Volume D, XI-2 and page 27, Appendix
E).
The ADF&G 1978, Fisheries Atlas was and is used at this time by
DOWL biologists as a basic reference for fisheries spawning
conditions. References provided by your staff and others relative
to on-going work in the development of species suitability curves
will be utilized for any future work at the project sites and
certainly in future projects to augment the basic information
currently available in the Fisheries Atlas for making qualified
generalizations for each river system.
o ADF&G1s recommendations concerning minimum separation from active
bald eagle nests have been incorporated into the text (Volume B,
Appendix E, page 24; Volume C, Appendix E, page 22; and Volume D,
Appendix E, page 22).
o Restoration of material sites and abandoned camp sites has been
addressed in the final report (Volume B, Appendix E, pages 16 and
24; Volume C, Appendix E, page 21; Volume D, Appendix E, page 22).
Commissioner Ronald Skoog
July 28, 1982
Page 2
o Utilization of transmission lines designed to mlnlmlze large raptor
electrocution has been included as a mitigation measure (Volume B,
Appendix E, page 24; Volume C, Appendix E, page 22; Volume D,
Appendix E, page 22).
COMMENTS SPECIFIC TO KING COVE:
Page XII-I; Appendix E, p. 14, 15, & 31
Delta Creek
Mean annual flow is 24 cfs for a dr~inage area of 3.63 square miles
resulting in a unit runoff of 6.6 cfs/mi. Drainage area between the
proposed dam site and powerhouse is 0.4 square miles. Sizing for
turbine generator is set at the 15 percent exceedance point which
corresponds to a flow of 44 cfs in the flow duration curve for
Delta Creek. This is the maximum turbine design flow. Any flows in
excess of design flow will be routed through the diversion weir spillway
and will flow into the stream channel below the dam. Flows less than
the maximum design flow will be completely diverted into the penstock.
This may result in short reaches of Delta Creek devoid of any observable
streamflow just below the dam although the tributaries and the
groundwater seepage from the valley slopes will maintain some estimated
minimum flows (less than 2 cfs) in most of that stream channel between
the dam site and the powerhouse. A flow duration curve is provided to
indicate the percent of time that streamflow in excess of maximum
turbine design flow (44 cfs) will be let go through an unregulated
spillway. See comments on Appendix E, page 13, below, for additional
discussion.
Appendix E, page 13, para. 3. Habitat improvement accrued by
retention of sediments: DOWL feels that sufficient flow from
groundwater and small tributaries will allow maintenance of resident
populations and that the decreased velocity and sediment load will
improve the available habitat. Additional field work to be performed by
DOWL Engineers in 1982 will address the actual utilization of the upper
portions of the system and minimal flow requirements between the weir
and powerhouse locations, as well as potential hatitat loss.
During our meeting of April 28, 1982 two concerns were stressed by
ADF&G: (1) provision of sufficient flows between the diversion weir and
the powerhouse to maintain the existing Dolly Varden population
(addressed previously in this letter) and (2) insurance of some
transport of sediment from above the diversion weir back into the stream
channel below the weir to provide for recruitment of spawning gravels.
DOWL feels that this would be possible but would require considerable
investigation to assume compliance with DEC w~ter quality standards.
•
• •
•
• ..
• -
•
• •
• ..
• -• •
• -• -• -• ----
• -
• .. ..
• -
-
...",
-
Commissioner Ronald Skoog
July 28, 1982
Page 3
COMMENTS SPECIFIC TO OLD HARBOR:
Page X-2, I & XII-I. Fisheries:· Location of trap sites. Two
traps were set above the proposed powerhouse location. The report has
been corrected to reflect this effort (Appendix E, page 6).
Page X-2, 2. Wildlife: bear confrontations. Assuming no
unexpected delays, it should be possible to avoid construction for most
if not all of the time when bear concentrations will be present.
Precautions will be taken with the handling of garbage to avoid
attracting bears (Appendix E, page 21).
Appendix E, pages 9, 10, & 28.
The drainage area for Midway Creek above the proposed diversion
weir is 2.2 square mile~. Mean annual flow for this drainage are~ is
estimated to be 10.5 ft /sec resulting in a unit runoff of 4.8 ft /sec/mi 2 .
The drainage area for that reach of the creek between the diversion weir
and powerhouse is computed to be 0.08 square miles. From this small
drainage basin, the creek could drain on an annual basis some 0.4 ft 3/sec
of water.
Sources of streamflow below the proposed diversion site will
include:
D a significant tributary draining a small area to the east and
discharging 200-300 feet downstream of the proposed diversion weir.
D ground-water seepage from the valley slopes into the creek.
D seepage from the diversion weir.
D runoff from the valley slopes during snowmelt and rainstorm events.
3he turbine generator is sized for a maximum design flow of
19 ft /sec and any surplus will spillover the diversion weir during
periods of high flows.
It is conceivable that short reaches of Midway Creek just below the
diversion weir may be devoid of surface flow certain periods during the
year, (e.g. late winter low-flow periods). However, the streambed will
most likely remain saturated even during low flow periods and may
contain shallow ground water flow in the coarse bed materials. Some
loss of habitat for resident Dolly Varden could occur during these
periods. .
Commissioner Ronald Skoog
July 28, 1982
Page 4
COMMENTS SPECIFIC TO LARSEN BAY:
Page X-3, para. 3. Dolly Varden: corrected.
Page 5, Appendix E. Fisheries resources above the powerhouse. The
minnow trap set above the existing dam and proposed powerhouse captured
one Dolly Varden. Additional trapping may be done in the future in
connection with on-going hydrologic studies.
As discussed in our meeting of April 28, 1982, consideration will
be given to removal of the old dam as a possible mitigation for the
current project impacts.
Page XII-I, Recommendation, Page VII-I, Appendix E, page 7,9, 10,
and 31.
The drainage area for Humpy Creek above the proposed diversion weir
is 6.28 square miles. ~ean annual flow for this drainage area is
estimated to be 13.0 ft /sec resulting in a unit runoff of 2.1 ft 3/sec.
The drainage area for that reach of the creek between the diversion weir
and powerhouse is computed to be 0.09 squ~re miles. The creek within
this reach could potentially drain 0.2 ft /sec on a mean annual basis
although this estimate is considered conservative due to the excess
streamf10ws which must be spilled over the diversion weir during periods
of high flows.
Sources of streamflow for that reach of the creek between the
diversion weir and powerhouse include:
o Considerable ground-water seepage from the narrow valley slopes.
o Several rivulets and overland flow channels on the left valley
banks.
o Runoff from the valley slopes during snowmelt and rainstorm events.
o Seepage from the diversion weir.
Th3 turbine generator is sized for a maxim~m design flow of
23.8 ft /sec. Streamf10ws in excess of 23.8 ft /sec will spillover the
diversion weir during periods of high surface flows.
It is conceivable that short reaches of Humpy Creek below the
diversion weir may go dry during periods of minimum flow-late winter and
early spring. However, the streambed itself is expected to remain
saturated throughout the year. Some loss of habitat for resident
Dolly Varden could occur during these periods.
• ..
• ..
•
•
• -
• ..
• -• -
• ..
• •
• -
• -
•
• --
•
• .. -..
• -
.....
-
-
.-
-
-
-
Commissioner Ronald Skoog
July 28. 1982
Page 5
COMMENTS SPECIFIC TO TOGIAK:
Please note that the work at Togiak was intended to be only at the
reconnaissance level. It was previously indicated that additional
studies would be required including a detailed analysis of potential
impacts and possible mitigation but that these studies would only occur
if the project were to be taken into a more detailed feasibility study.
Resource agencies would be invited to participate in scoping these
additional studies if this were to occur. Due to the apparent marginal
economic feasibility of this project. we feel that any discussion of
additional studies at this time is certainly premature. In fact. some
consideration is being given to a location on the Kurtluk River.
Page VI-5, para 5. Fish ladder. DOWL's recommendation has been
altered to more clearly state this need (Appendix E, page 46).
Page X-I. para 2. No discussion on additional studies.
Page X-3, para 1. Corrected.
Page X-4, para 1. No discussion.
Page XI-3, para 5. Hydrology corrected.
Page X I -6, para 3. ADF&G Permits corrected.
Appendix E. page 11. Corrected.
Appendix E, page 12. Corrected.
Appendix E, page 11 and 12, general comments. See discussion under
comments on King Cove. Old Harbor and Larsen Bay.
Appendix E, page 21, para 3. True. The potential changes have been
mentioned. Should this project be funded, additional studies and
discussion would occur.
Page 22, para 2. That statement was deleted.
Pages 22,36, and 37, general comments. Note the opening statement
to this section.
Thank you again for your timely response and your agencies
comments. We look forward to a successful working relationship with the
Alaska Department of Fish and Game in bringing the King Cove, Old Harbor
and Larsen Bay Projects forward.
cc: C. Yanagawa, ADF&G
R. Logan. ADF&G
SinCerely\) ~
. J\' ~
Enc P. Yould
Executive Director
"Department Of Energy
Alaska Power Administration
P.O. Box 50
Juneau. Alaska 99802
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
334 West 5th Avenue
Anchorage, AK 99501
Dear ~lr. Yould:
RECEIVt:D
t,?R 1 9 J982
~tASKA PO'!.'E1J AUTHORITY
Apri 1 15, 1982
These are our notes on the studies for King Cove, Old Harbor, Larsen Bay,
and Togiak hydro projects. We found the studies to be very complete "nd
well done. They certainly rank among the best we have recently reviewed.
We agree with the conclusion and l'ecommendations that actions be
initiated to implement projects at King Cove, Old Harbor, and Larsen Bay.
All of the projects except Larsen Bay are based on synthesized hydrology
which should be carefully reviewed before a construction commitment is
made. Even Larsen Bay data is very minimal with one YEar n:~cord. As the
studies acknowledge, significant local micro climates exist throughout
the region, especially o~ Kodiak Island.
We question whether or not energy could be sold for electric heat at the
same price as electric energy for other purposes, especially when
compared to the present and projected costs of oil.
We also question the space heating efficiency rates used from heating
oil. The reports are using 70 percent efficiency. From our experience
and other recent reports, 60 percent may be a more realistic figure for
planning purposes.
For Larsen Bay, will the high growth rate occur even with new HUD houses
'in light of the cannery being closed? A couple small items--page IV-9,
the 22kWh/gal. should be 11 kWh/gal. and on line 5, page IV-9 of the
Draft Report--"flay, 1978" should be "January, 1980".
Thanks for the opportunity to comment.
;g~/LL:
~Robert J. Cross TV -Adm i n i s t ra to r
.. ..
•
• -
• ..
• -
•
,.
" ....
-
•
•
• -
• -
•
• -
• -
• -
• -
• -• -
-
-
-
-
-
-
-
-
-
.,.,..
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Mr. Robert J. Cross
Administrator
Alaska Power Administration
P.O. Box 50
Juneau, Alaska 99802
July 28, 1982
SUBJECT: Draft Feasibility Reports of Hydroelectric Projects
Phone: (907) 277·7641
(907) 276·0001
at King Cove, Larsen Bay and Old Harbor; Draft Reconnaissance
Report of a Hydroelectric Project at Togiak.
Dear Mr. Cross:
Thank you for your letter of April 15th regarding the above
referenced reports. The following letter addresses issues and answers
questions contained in your letter. We appreciate the participation and
timely input of you and your staff in reviewing the draft reports.
Our responses to your comments are included below:
Paragraph III
Although we feel fairly comfortable with the synthesized hydrology
which resulted in close correlations utilizing three independent methods,
there is no substitute for actual field measurements over an extended period
of time. A stream gaging program has been initiated, and will continue
indefinitely on streams recommended for weir construction. Each project
will be re-evaluated based upon updated hydrology resulting from stream
gage recordings prior to making any construction commitment. Such a
commitment could occur as earlly as spring, 1983, at which time over one
full year of stream gage data would be available.
Paragraph IV
In this type of analysis, the dollars relate only to the value of
the oil that is displaced, and not to the projected sales price of the energy.
Paragraph V
Since this analysis relates to the value of displaced oil, using 70%
as a heating efficiency is a more conservative assumption than using
60%. 70% assumes that less oil is used and hence a lower quantity of
oil would be displaced by hydropower.
Pa ragraph VI
Demand forecasts are difficult to make, however, we believe that we
have made a reasonable estimate. See text for the other suggested
changes.
Thank you again for your comments and timely input. Should
you have further questions regarding these projects, please contact
myself or Mr. Don Baxter of my staff.
~er~lY'
Eric P. Yould
Executive Director
• .. .. ..
• .,
• ..
•
• ., .. -
• -
• -• -
• -
•
--
• -
• -• ..
• •
• -
-
--
IN REPLY REFER TO:
WAES
United States Department of the Interior
FISH AND WILDLIFE SERVICE
1011 E. TUDOR RD.
ANCHORAGE, ALASKA 99503
(907) 276-3800
Eric P. Yould RECJ:1VED 15 APR 1982
Executive Director
Alaska Power Authority
334 W. 5th Avenue
Anchorage, Alaska 99501
Attn: Don Baxter
f',PR 2 1 1982
~KA POWER AUTHORITY
Re: Togiak Hydroelectric Project
Reconnaissance study
Dear Mr. Yould:
The U.S. Fish and Wildlife Service (FWS) has reviewed the above referenced
draft report submitted by DOWL Engineers. It is our intent in the following
comments and recommendations to: 1) provide information which will enable
you to avoid or minimize fish and wildlife losses associated with the
project; 2) identify information needs which are necessary for objective
project planning and decision-making; and 3) to identify those concerns
which, if adequately addressed, would make the project acceptable to us, and
determine our response to anticipated Federal permits and/or licenses
associated with this project.
General comments:
In general, we find the conclusion of project feasibility based almost
entirely on economic and engineering information.
We feel the credibility of this conclusion could be greatly enhanced by
comprehensively addressing the following issues:
1)
2)
Significantly expanding your data base regarding fish use
(populations) and habitat.
The identification and incorporation of appropriate mitigation
measures (clearly developed from the data base in #1).
3) Diversifying the types and scope of alternative electrical power
production systems.
Specific comments:
Section I, page 1 --The $8.1 million net cost figure does not include
costs of further fish and wildlife stadies or
necessary mitigation measures.
¥Z2a:azl4W1ft!fii.ti~a, WiiUJZtUtt!i8¢ttGjJ@tti £ZJ CM¥TtlmJ4f.4 auwt4&@&t& =
~ Section VI, page 5 -
Section X, page 1 --
Section X, page 2 --
Section X, page 3 --
Section XI, page 3 -
Appendix E, page 21-
Appendix E; page 22-
Summary comments:
Other fisheries mitigation measures, such as baffled
intakes, adjustable blade turbines, or additional
smolt emigration releases may be needed.
Spawning habitat to be lost to the reservoir should
be quantified.
Spawning habitat for pink, coho and chum salmon
should be mapped and numbers of each species surveyed.
Dolly Varden are char.
Flow projection should be based on at least one
year's recorded discharged data. These data will
also be needed to determine instream flows for
maintenance of fish habitat below the dam.
Substrate distributions will change below the dam.
Impacts and possible spwwning habitat losses need to
be addressed.
Fisheries mitigation measures that should be
discussed include maintenance of instantaneous flows
below the dam, fish passes, baffled intakes,
additional smolt emigration releases, etc.
According to the Fish and Wildlife Service mitigation policy, the fish and
wildlife in the Togiak vicinity fall into Resource Category 3, which means
habitats are of high to medium value to the species there, and habitats are
abundant. The corresponding mitigation planning goal for Resource Category 3
is no net loss of habitat value, while minimizing the loss of in-kind habitat
value. Our future actions regarding various Federal permit and license
applications will be to ensure that fish and wildlife resources in the project
area are ade~uately described, that all significant impacts to those resources
are identified, and that all adverse impacts are mitigated to reach our goal
of no net loss.
We look forward to continuing working with the Alaska Power Authority and
providing technical assistance in the planning stages of this project. Thank
you for the opportunity to comment on the report.
JIi;tsbnt Regional Director
cc: Fl-lS-ROES, WAES
ADF&G, NMFS, ADEC, OCM, Juneau
ADF&G, NMFS, ADEC, EPA, Anchorage
til
•
• ..
-• ..
• ..
• ..
•
Ill·
•
..
u·
•
-..
..
• ...
-'
.-
-
-
-
--
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Mr. Keith Schreiner
Regional Director
U.S. Fish & Wildlife Service
1011 E. Tudor Road
Anchorage, Alaska 99503
July 30, 1982
Phone: (907) 277·7641
(907) 276-0001
Subject: Draft Feasibility Reports on Hydroelectric Projects at
King Cove, Old Harbor, Larsen Bay; Draft Reconnaissance
Report of a Hydroelectric Project at Togiak.
Dear Mr. Schreiner:
This letter has been prepared in response to Mr. Gerald Reid's
letters of April 14 and April 15, 1982, regarding the above referenced
projects. We appreciate your timely input and your staff's
participation in several agency meetings relating to these projects.
GENERAL COMMENTS:
At our request, DOWL Engineers (DOWL) has carefully reviewed the
letters and has responded to your comnents, many of which were quite
constructive. However, the general comments and closing paragraphs of
the letters appear to be in a format and of a nature that sets a
generalized U.S. Fish and Wildlife Service (USFWS) policy for all
hydroelectric projects, does not take into account the presence of
existing data or local knowledge that is site specific, and assumes that
all hydroelectric projects cause or have the potential to cause similar
losses in fish and wildlife resources, habitat or both. It should also
be noted that personal contact was made with refuge personnel and staff
members of your Ecological Services several times over the course of the
studies and that in addition to these contacts, two formal agency
meetings were held to consider the implications of the projects. The
draft reports were not prepared without the input of knowledgeable field
personnel from both USFWS and the Alaska Department of Fish & Game
(ADF&G). Additionally, the nature and size of the projects must be
considered in any such evaluation, as well as consideration of the site
specific determinants.
Further, DOWL met on April 28, 1982, with representatives from your
office and ADF&G to discuss the project on a site specific basis. In
part, the specific comments provided below reflect the results of that
meeting.
Keith Schreiner
July 28, 1982
Page 2
SPECIFIC COMMENTS:
King Cove:
Section I, Page 5. Based on other comments provided below, the possible
cost of additional studies and mitigation measures is considered minor.
The space heating credit is taken only for the dollar value of the
heating oil being displaced. Deductions from this credit were taken as
you have indicated they should have been.
Section 1, page 6. Several additional field trips are planned to
confirm the comment noted under Appendix E, page 5.
Section IV, page 1. The hydrological data you noted is currently being
collected. Preliminary winter streamflow data collected on Delta Creek
appear to indicate that the measured flows utilized for energy
generation are consistent with the estimates in the hydropower
feasibility report. This conclusion is based on limited periodic
discharge measurements, which will be used to develop rating curves for
this creek as part of a one-year long stream gaging effort. Continuous
streamflow data are being collected and will be made available as soon
as the field study is completed. The range of estimated winter flows
(December through April) utilized for energy generation and the observed
flows are as follows:
Estimated flow range: 8.8 to 14.5 cfs
Observed flow range: 16 to 20 cfs
It should be noted that that range of observed flows may change slightly
as stream stage records are analyzed on the basis of completed rating
curves. Spillage and projected discharges will be a function of final
design.
Section VI, page 12. This will be accomplished following the collection
of the one year of actual discharge data.
Section VI, rage 16. Schedules for cleaning and alternative methods of
disposal wi1 be considered during final design and in determining
operational procedures. The expected decrease in turbidity and sediment
loads will in general enhance downstream conditions.
Section VII, ~age 4. The demand analysis presented has been
standardizedy APA for comparison of all hydroelectric projects and is
thought to be realistic. The Power Authority's purview does not extend
to denying rural Alaskans an improvement in their standard of living
through the availability of reliable, stable-priced power.
Appendix E, pare 5. Surveys of Delta Creek have been taken on a yearly
basis for the ast 21 years by experienced ADF&G observers. Surveys are
flown close to the normal time of peak spawning, so as to obtain maximum
escapement counts.
•
•
• ..
• -
• --
•
• --
•
8:
• -• -
• -
• ---• -
• -• -• ...
-
-
-
c-.%i!JII
-
Keith Schreiner
July 28, 1982
Page 3
The fisheries resources and upward extent of salmon spawning in
Delta Creek were discussed with Arnie Shawl, the ADF&G fisheries
biologist in Cold Bay, on three occasions and with several long time
local residents. All were in agreement that pink salmon in the project
area spawn in a tributary below the airport, and that chum salmon rarely
reach the airport area, and have never been seen above it. No other
species of salmon have been observed in or above the airport area.
Little local information was available on silver salmon but ADF&G
biologists did not believe that the run was very large or that spawning
occurred very far above the extent of tidal influence. With the close
proximity of the stream to the airport and the amount of recreational
activity occurring at or near the airport, it seems unlikely that
silvers would be present in any numbers (especially in a stream near a
community of commercial fishermen), with the local residents not being
aware of it.
Appendix E, page 8. Field investigations will be conducted in 1982 to
confirm the upper limits of chum, pink, and coho spawning, as noted
above (Comment on Section I, page 5).
Appendix E, page 14. The studies suggested appear to be unnecessary
based on site specific knowledge of the potential for losses due to this
project. If a significant number of coho salmon were to be found above
the project site, then appropriate mitigation measures would be included
in the final design.
Through interviews and discussions with local residents, local city
administrators, ADF&G biologists, staff members from Ecological Services
and the input from several site visits, existing knowledge of wildlife
and fisheries resources in the project area was incorporated into the
report.
With the exception of the confirmation of the upper limits of
spawning and the completion of the collection of the hydrological data
previously discussed, no additional environmental studies for this site
are contemplated.
Old Harbor:
Section I, page 5. The Old Harbor Hydroelectric Project does not appear
to warrant additional terrestrial habitat studies and/or mitigative
measures that could not be accomplished within the estimated project
cost.
Section I, ~age 6. The road is one half mile long and will be built
primarily t rough a sparse meadow community (with very little topsoil on
mostly alluvial deposits). The transmission line is 3 miles long and
crosses Big Creek. This crossing does present the potential for
collision by waterfowl that utilize the area. Appendix E, Sections I
through M, of the Feasibility Study, discussed wildlife utilization
impacts and mitigation in an adequate level for this study.
Keith Schrei ner
July 28, 1982
Page 4
Section II, page 5. During the recent meeting with ADF&G and USF&WS
personnel, it was generally agreed that consideration of mitigative and
replacement measures were premature for the Old Harbor Project and that
the fish and wildlife studies to date are sufficient for the present
level of project evaluation.
Section X, page 2. Good spawning gravel occurs only on the alluvial
fan. The remainder of the stream is steep and rocky. Above the weir,
the gradient flattens out and the gravel is potentially good for
spawning. However, it is doubtful many fish, particularly pink salmon,
would make it to this portion of the stream.
Section X, pages 3 & 4; Section XII, page 1. The small size and limited
potential impacts of this project do not warrant the extensive studies
outlined.
Enclosed with this letter is a reply to specific questions raised
in a memorandum dated April 16, 1982 from the acting Refuge Manager,
Kodiak NWR, to the staff of the Western Alaska Ecoloqical Services,
which provides further site specific information. -
Through interviews and discussions with local residents, ADF&G
biologists, Kodiak NWR personnel, staff members from Ecological Services
and the input from numerous site visits, existing knowledge of wildlife
in the project area was incorporated into the report. This level of
information appears sufficient for project evaluation at this time.
Larsen Bay:
Section I, paae 5. The Larsen Bay Hydroelectric Project does not appear
to warrant ad itional environmental studies and/or mitigative measures
that could not be accomplished within the estimated project cost.
Section X, ~a~e 1. Due to the location of the existing cannery dam and
the marg;naabitat existing between the proposed diversion weir and
the dam, it appears that fish passage structures would not be required.
Section X, page 3. The typographical error concerning Dolly Varden Char
has been corrected.
As noted above, fish habitat above the existing cannery site dam is
marginal with a bedrock and boulder substrate, no pools, and very little
quiet water. At this time, the possible upper limit for pink salmon
spawning is the face of the cannery dam. However, as can be seen from
the photo provided on Page 8 of Appendix E, conditions for about
100 yards below the dam are marginal for spawning.
The drainage area for Humpy Creek above the proposed diversion weir
is 6.28 square miles. ~ean annual flow for this drainage area is
estima 3ed to b2 13.0 ft /sec, resulting in a unit runoff of some
2.1 ft /sec/mi . The drainage area for that reach of the creek between
• ..
• ..
• -• -
•
•
•
• ..
• -
• -
• •
• -
• -
• -
• ..
• .,
• -
• -
• -
-
-
-
-
Keith Schreiner
July 28, 1982
Page 5
the diversion weir and powerhouse is computed to b~ 0.09 mi 2 . The creek
within this reach could potentially release 0.2 ft /sec on a mean annual
basis; although, this estimate is conservative due to excess
streamflows, which must be spilled over the diversion weir during periods
of high flow.
Sources of streamflow for the reach of creek between the diversion
weir and powerhouse include:
Ground-water seepage from the narrow valley slopes.
Several rivulets and overland flow channels on the left valley
banks.
Runoff from the valley slopes during snowmelt and rainstorm events.
Seepage fro~ the diversion weir itself.
Al~o, the turbine generator is sized for a maxim~m design flow of
23.8 ft /sec. Stream flows in excess of this 23.8 ft /sec will spill
over the diversion weir. This situation would obviously only occur
during periods of high surface flows. Ultimately, spillage and
projected discharges will be a function of final design.
It is conceivable that short reaches of Humpy Creek below the
diversion weir may go dry during periods of minimum flow-late winter and
early spring. However, the streambed itself is expected to remain
saturated throughout the year.
Section X, page 4. The extent of wildlife habitat and its present use
are outlined in Appendix E, pages 10 through 20. With the project area
being located in such close proximity to Larsen Bay itself, it would not
have much additional impact relative to fish and wildlife resources,
other than that which has already occurred.
Enclosed with this letter is a reply to specific questions raised
in a memorandum dated April 16, 1982 from the acting Refuge Manager,
Kodiak NWR, to the staff of the Western Alaska Ecological Services,
which provides further site specific information.
Through interviews and discussions with local residents, ADF&G
biologists, Kodiak NWR personnel, staff members from Ecological
Services, and the input from numerous site visits, existing knowledge of
wildlife in the project area was incorporated into the report. This
level of information appears sufficient for project evaluation at this
time.
Keith Schreiner
July 28, 1982
Page 6
Togiak:
Section 1, page 1. Mitigation measures such as a fish passage are
included in this cost. If this project were to receive additional
funding, further work would need to be accomplished in order to scope
both impacts and possible mitigation measures.
Section VI, page 5. A recommendation for additional studies on
techniques to insure safe passage of outmigration smolt was included in
the draft report in Appendix E, page 46. This recommendation has been
clarified to show the potential need for changes in design.
Section X, page 1 & 2. It should be pointed out that Togiak was
intended to be only a reconnaissance study. It was understood that
additional studies would be required should this project be funded. At
that time, resource agencies would be invited to participate in scoping
these additional studies. Due to the marginal f~asibility of this
project, we feel that any discussion of additional studies at this time
is premature.
Section X, page 3. This change has been incorporated into the text.
Section XI, page 3. A one year program to collect stream discharge data
is presently being conducted.
Apeendix E, page 21. The potential for changes in stream morphology was
pOlnted out on this page. Due to the preliminary nature of this study,
a detailed analysis of potential impacts was not necessary at this
stage. Future or continued studies of this project would discuss these
potential changes in more detail.
Appendix E, page 22. Mitigation measures will be discussed in more
detail in any future studies of this potential project.
Because of the uncertain project status in regard to the Togiak
Reconnaissance Study and because some consideration is being given to a
different location on a different river, no further environmental
activities are contemplated for Qu;gmy River.
•
• ..
• ..
• -
• -.. -
•
• -
• ..
• -
• ..
• ...
• -
• ---
• ..
•
• -
•
Keith Schrei ner
July 28, 1982
Page 7
Thank you again for your consideration and timely input. The
Power Authority looks forward to a successful working relationship with
the U.S. Fish and Wildlife Service in bringing this project forward.
Enclosures:
c?
Eric P. Yould ~
Executive Director
USFWS memo of April 16, 1982
APA reply of July 28 to the above memo
cc: FWS-ROES, WAES
ADF&G, NMFS, ADEC, OCM, Juneau
ADF&G, NMFS, ADEC, EPA, Anchorage
United States Department of the Interior
NATIONAL PARK SERVICE
Alaska Regional Office
540 W. Fifth Avenue
IN JJ£PLY RE'ER TO: Anchorage, Alaska 99501
.. _, '" " .. MAC $ 40.4 (
L76l5(ARO-P) a-ecelVEQ
19 APR 1982
/ln~
", 1\ 2 1 1982
AlASKA POWER A,,,.,. '""" "rORITY
~tr. Eric P. Yould
Executive Director
Alaska Power Authority
334 W. 5th Avenue
Anchorage, Alaska 99501
Dear Mr. Yould:
We have reviewed the March" 1982, Draft Feasibility Recon-
naissance Studies for hydroelectric projects at King Cove,
Old Harbor, Larsen Bay and Togiak and have the following
comments:
We have no objection to further planning for the proposed
projects if the following concern is given consideration.
It is not clear whether the State Historic Preservation
Officer (SHPO) has been consulted about the proposed pro-
jects; we sugg~st further planning documents give evidence
of coordination with the SHPO.
Thank you for the opportunity to comment ..
Regional Director
Alaska Region
Fe $ • at $
•
•
• --
WI -• ..
,.
-
• .,
.. .. -..
•
..
.. -.. ..
•
.. -.. -
• -
,iNlIi
. ..,
-
. -
-
-
-
-
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE -ANCHORAGE, ALASKA 99501
Mr. John E. Cook
Regional Director, Alaska Region
U.S. Department of the Interior
National Park Service
Alaska Regional Office
540 W. Fifth Avenue
Anchorage, Alaska 99501
July 28, 1982
SUBJECT: Draft Feasibility Reports of Hydroelectric Projects
Phone: (907) 277-7641
(907) 276-0001
at King Cove, Larsen Bay and Old Harbor; Draft Reconnaissance
Report of a Hydroelectric Project at Togiak.
Dear Mr. Cook:
Thank you for your letter of April 19th regarding the above
referenced reports. We appreciate your participation and timely input
in reviewing the draft reports .
In response to the question raised in your letter, the
State Historic Preservation Office was contacted and has commented on
the proposed projects. Copies of all relevant correspondence will be
included in the final feasibility reports.
Should you have further questions regarding these studies, please
contact myself or Mr. Don Baxter of my staff.
EPY:jls
{:~elS? l \ JJ.
Eric P. Yould '\
Executive Director
TOGIAK HYDROELECTRIC PROJECT
FEASIBILITY STUDY
APPENDIX G
SPACE HEATING INSTALLATION
AND COST
-
-
-
-
-
-
-
-
-
APPENDIX G
UTILIZATION OF EXCESS ELECTRICAL ENERGY
FOR SPACE HEAT
During much of the year the hydro unit can provide all of
the electrical needs for the community. In addition there will
be times when the hydroelectric energy production is in excess
of these direct electrical needs. This excess electrical
energy could be used to displace substantial amounts of fuel
oil.
SYSTEM PARAMETERS
In order to utilize this excess energy the following system
parameters must be met:
1. The system must use only hydro generated power which is in
excess of direct electrical demands. It must be
deacti va ted whenever diesel genera tors are on the line,
because this indicates that the hydroelectric energy
production is less than the village demand.
2. The system must use as much of the excess as possible.
3. The system must not overload the hydro unit electrically or
mechanically.
4. It must not force the hydro to draw more water than the
stream can provide.
5. It must have remote capability to control the loads,
adjusting the heating loads to the available energy.
NBISF-456-9521-AG 1
6. It must be compatible with existing heating systems.
7. It must be reliable because service is not readily
available.
IMPLEMENTATION
A very simple method would be to install a separate meter
at each user, connect heaters and limiting thermostats, and
then switch them off and on manually. This approach would work
reasonably well at times of very high water flow, but would
require a good deal of effort from the operator at periods of
marginal flow. In all probability this would lead to greatly
reduced use of the resource.
A more automatic system is probably justified. This system
is envisioned as follows:
The main control would be a control computer programmed in
control basic language and capable of storing its programming
in a non-volatile media, eliminating battery backup. Interface
systems would allow the unit to interpret a water level signal
from the dam, drive a keyboard and monitor, interpret dry
contact closures, and run a line driver capable of
communicating with the remote heating loads.
Operation
At the user end would be a control which would respond to
the computer command to turn on heaters. The user equipment
could take several forms as described below.
1. The control would sense that only the hydro unit is on the
line by checking the diesel unit circuit breakers.
NBISF-456-9521-AG 2
• ..
• ..
• •
• ..
• ..
• ..
• ..
• ..
• -
• -• -
• ..
• •
• ..
• -
•
•
• -• •
• -
-
-
2. The water level behind the dam would be checked to see that
excess water was available and going over the spillway.
3. The hydro is checked to see that it has excess generation
capacity.
4. The control begins sending signals to turn on hea ters at
_ the user locations rechecking items 1, 2, and 3 after each
-
-
-
-
"""
, ...
-
-
-
-
-
5.
increment. This is a slow process, perhaps over 10
minutes.
If the water level drops or the generator approaches full
load, the controller reduces the heating load. This can
happen quickly.
This same control computer could also be used to limit the
hydro water flow by regulating the governor setting and to
start the diesels if more generation was required. It could
control up to 64 remote units in its basic form.
COST ESTIMATE
The design of this system is qui te preliminary and highly
dependent on final hydro design and nature of heating systems
to be served. The system designs for small and large users are
shown on Figures G-1 and G-2.
I t is assumed that the first priority heat loads would be
the schools and other public buildings. This tends to spread
the benef i ts evenly among the tax payers and are more cost
effective to connect.
Major components are estimated as follows:
Dam Water Level Sensors,
Cable, and Transducers
NBISF-456-9521-AG 3
This item is part of
hydro estimate.
Control Computer and Inter-
face Installed
Electric Heating Equipment,
Boilers or Baseboard Heat
Control Signal Wiring to
Connect Computer to Users
Software Development and
Field Installation
User Controls, kWh Meters,
Cost for Entire System
$10,000
Installed cost -
$40 per kW
$ 5,000
$ 5,000
Assumes $15,000
spread over three
projects
$12,000
Tbe cost estimate for the Togiak Project is summarized on
Table G-l.
NBISF-456-9521-AG 4
•
•
• -• ..
..
•
.. .. .. .. ..
•
••
• .. ..
•
.. ..
• ..
•
.. ...
• •
• ..
... -
-
-
jii8f
-
~ ....
.-
-
-
-
-
-
-
1.
2.
3.
4.
5.
TABLE G-1
SPACE HEATING INSTALLATION
TOGIAK HYDROELECTRIC PROJECT
Item Quantity Unit Unit Price .
Control Computer 1 LS $10,000
and Interface
Electric Heating 300 KW 40
Equipment
Control Signal Wiring 1 LS 5,000
Software Development 1 LS 5,000
and Installation
User Controls and 1 LS 12,000
Meters
TOTAL
NBISF-456-9521-G-1
Amount
$10,000
12,000
5,000
5,000
12,000
$44,000
..
...
-
-
, ...
-
..,
..
-
-
-
-
-
--...
-
SPACE HEAT USER'S REGULAR
kWh METER
TELEPHONE
kWh METER
INTERFACE
WITH CONTROL
COMPUTER
DIGITAL
RECORDER
THERMOSTAT
RESISTANCE HEATERS
(BASEBOARD OR IN HYDRONIC LINES)
THE HYDRO~IC SYSTEM OPERATES IN A NORMAL FASHION
EXCEPT THAT ALL RETURK WATER FLOiS THROUGH THE ELECTRIC BOILER.
HEAT ADDED BY THE ELECTRIC BOILER REDUCES THE FUEL REQUIRED BY
THE OIL FIRED BOILER. NO CONTROL INTERFACE IS REQUIRED.
SCHEMATIC OF HEATING SYSTEM
INDIVIDUAL HOME OR SMALL BUILDING
FIGURE
G-I
SPACE HEAT ~ONTROL 0 USER'S REGULAR
kWh METER COMPUTER kWh METER
r----DIGITAL RECORDER AND RELAYS
....................... -----... ' .... ,
MULTIPLE
CONTACTORS
CIRCULATING
PUMP
I
I
I
I
I THERMOSTAT
ELECTRIC BOILER
OIL FIRED
BOILER
WITH MULTIPLE ELEMENTS
~-----------~II IIIIII~-------------
THIS CONTROL SYSTEM IS NOT CONNECTED TO THE EXISTING HEATING
SYSTEM. IF THIS SYSTEM DOES NOT KEEP THE BUILDING WARM, THE
EXISTING SYSTEM WILL HEAT ONLY AS REQUIRED. THIS IS COMPATIBLE
WITH WOOD STOVES, OIL BURNERS, OR FULLY CONTROLLED FURNACES.
•
..
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
• -
• ..
• ..
• ..
•
•
I
SCHEMATIC OF HEATING SYSTEM
LARGE BUILDINGS
FIGURE.