Loading...
HomeMy WebLinkAboutTakatz Creek Project Alaska 1968RLIS TK 1424 .A4 T35 1968 UNITED STATES DEPARTMENT OF THE INTERIOR Stewart l. Udall, Secretary ALASKA POWER ADMINISTRATION Gus Norwood, Administrator TAKATZ CREEK PROJECT ALASKA Alaska January 1968 fimARY RIOR UNITED STATES DEPAR'lMENT OF THE INTERIOR Stewart L. Udall, Secretary AFJLJ!iS Alaska Resources LibrJ-\ :c Information Services Librarv BuiIUI;H! SUIle: HI 3211 PrOl ide!KT Drive Anehorago.:, A;'. 99508--1614 ;ALASKA POWER ADMINISTRATION Gus Norwood, Administrator PLAN OF DEVELOPMENT FOR TAKATZ CREEK PROJECT, ALASKA January 1968 ARtIS 'J;~\"a Rcs()urcc~ I. ,him "'-lnl'ormation Services Libran iluikfill!l. Suite III 321 i Prol'iLlcncc Drive \nrhnm!!c. AK 99'101'-4614 ~l 9 1975 l' if: / ((21' I /1 ,( -; 3 \ r,' ' /." , Location: Authorit~': Plan: SUMMARY SHEETS TilKATZ CREFK PROJECT, ALASKA On Takatz Creek on Earanof I~"land and about 21 airline: miles northeast of Sitka, t.laska. Act of J\ugust 9, 1:755, (69 Stat. 618) and Appropriation J\cts authorizinc: expenditures by the Department of the Interior for engineering and economic investigations, and for related reports, for the development and utili- zation of the water resources of Alaska. Construct a concrete dam on Takatz Creek 205 feet in height, and a concrete dam in a saddle south of the right abutment, 63 feet in height. Drill a pressure tunnel 3,860 feet in length, and construct a surface penstock 1,010 feet long to convey water to a 20 ,000 kilm~att pm,erplant on Takatz Bay. The vaterways construction Hould include a tunnel intake, gate shaft, trashrack, and surge tank. Construct a 115,000-volt transmission line 28 miles in length from a swi tch:>!ard near the powerplant to a SUbstation near Sitka. Project Features Hydrology Drainage area, square miles Annual runoff, average (1946-1963), acre-feet Annual runoff, maximum (1964), acre-feet ll,nnual runoff, minimum (1951), acre-feet Reservoir -Takatz Lake Elevation of normal full-pool water surface, feet (msl) Elevation of minimum operating level, feet (msl) fictive storage capacity, acre-feet Takatz Creek Dam Ty~e -Double curvature, thin arch Height above foundation, feet Elevation of crest, feet Thickness at base on plane of centers, feet Thickness at crest, feet a 10.6 128,800 159,500 91,800 1,040 900 82,400 205 1,048 17 7 Saddle Dam Type -Double curvature, thin arch Height above foundation, feet Elevation of crest, feet Thickness at base on plane of centers, feet Thickness at crest, feet Pressure Tunnel Length, feet Inside diameter, feet Capacity, cubic feet per second, rated head Penstock Length, feet Inside diameter, feet Powerplant Number of units Installed capacity, kilowatts Range of gross head Annual firm energy, kilowatt-hours Average annual secondary energy, kilowatt-hours Elevation of turbine discharge nozzles, feet (msl) Switchyard Capacity Transmission Line Takatz Switchyard to Sitka Type - H wood-pole, and steel tower Length, wood-pole section, miles Length, steel tower section, miles Voltage, volts Conductor size b 63 1,048 10 5 3,860 8.0 328 1,010 5.5 2 20,000 1,02 3.3-88 3.3 97,100,000 9,8:)0,000 16.7 25,600 kva 26 2 115,000 397.5 MCM ACSR Con~truction Costs (July 1967) Feature Production Plant Takatz Creek and Saddle Dams Outlet Works Waterways Powerplant Roads Government Camp Transmission System Switchyard Transmission Line Substation Total Estimated Construction Cost Interest During Construction Total Investment Benefit-Cost Ratio (lOO-Year Period) Annual Benefits Annual Costs Ratio ($19,600,000 ) 5,230,000 410,000 4,670,000 4,100,000 3,600,000 1,590,000 ($ 3,980,000) 420,000 3,060,000 500,000 $23,580,000 1,720,000 $25,300,000 1,352,000 1,039,000 1.30 Average Firm Energy Rate (Excluding operation, maintenance and replacement costs) 12.42 mills/kwh c GOAT LAKE Mt. Kotlion Mt. Ba ssie Bear MI. tt SEAR LAKE I In 0 _ --- SCALE OF MILES VICINITY MAP Mf.Furuhelm KAf'!~'f/lr 7'~ ( V I ~'·~1~' • / / " , ~ CANADA ... TAKATZ CREEK PROJEC KEY ·MAP 160 0 16() 320 -eo M _M SCALE OF MI LES LEGEND • GAGING STATION (Recordi"o) l> GAGING STATION (Disco"li"ued) UNITED STATES DEPARTMENT OF THE INTERIOR ALASKA POWER ADMINISTRATION TA KATZ CREEK PROJ ECT-ALASKA GENERAL MAP SEPTEMBER 15 1967 1113-908-11 IN REPLY REFER TO: 700 AIRMAIL UNITED STATES DEPARTMENT OF THE INTERIOR ALASKA POWER ADMINISTRATION P O. BOX !50 JUNEAU. ALASKA gge01 January 23, 1968 Honorable Stewart L. Udall Secretary of the Interior Washington, D. C. 20240 Dear Mr. Secretary: This letter, with its supporting reports, constitutes my proposed report on the Takatz Creek Project, Alaska. My report has been prepared under the Act of August 9, 1955 (69 Stat. 618), and sub- sequent appropriation acts authorizing expenditures for engineering and economic investigations and related reports on projects for the conservation, development, and utilization of the water resources of Alaska. My report is transmitted as the basis for securing Congressional authorization of this potential project, an economically justified and financially feasible development. The Takatz Creek Project would be a single-purpose, hydroelectric power development which would make optimum use of the flows of Takatz Creek on Baranof Island in Southeast Alaska to furnish needed additional power sup- plies to the Sitka area. Studies of the potential project alterna- tives have established that Federal construction of the Takatz Creel\: Project as an initial step in meeting the long-term power needs of the Sitka area is fully warranted. The plan of development for the project represents the culmination of consideration of the project potentialities by several Federal agencies. A Takatz Creek Project was first reported on by the U.S. Forest Service in 1924. It was again included in inventory-type reports by the Bureau of Reclamation in 1949 and the Corps of Engineers in 1952. The Bureau of Reclamation completed a favorable reconnaissance report on the project in May 1965, and initiated feasibility investigations on the project in the fall of 1965, which have been completed by the Alaska Power Administration (its successor in Alaska). The detailed feasibility investigations are summarized in this report. These investigations have been conducted in full cooperation with the concerned local entities, State agencies, and other Federal agencies. The plan of development contemplates the construction of: (1) Takatz Creek Dam near the outlet of Takatz Lake; (2) Saddle Dam in an aban- doned outlet channel of the lake; (3) waterways from the lake to the powerplant, including a lined pressure tunnel, a surge tank, and a surface penstock; (4) a 2O,OOO~ilowatt, 55 percent plant factor power- plant near tidewater on Takatz Bay containing two 10,000-kilowatt gen- erating units; (5) necessary access roads and maintenance facilities at the project site; and (6) transmission facilities to deliver power to the municipally-owned Sitka Public Utilities system near Sitka. When fully loaded, the average annual project generation would be 106,900,000 kilowatt-hours, including 9,800,000 kilowatt-hours of secondary genera- tion. The plan contemplates installation of both generating units initially, although the predicted load growth indicates that the second unit will not becOOle revenue producing until about four years after first delivery of project power, assumed to be in 1976. Project studies indicate that this initial installation of both units will result in lower total project costs than would deferred installation of the second unit. Prior to project construction, investigations would be made for archeological and historical values. It is proposed that the project be operated and maintained by the Sitka Public Utilities, under agreement with the Secretary of the Interior, and that the project be operated by remote control from Sitka; both in the interest of minimizing project operation and maintenance costs. On this basis, the Federal project costs would be limited to the costs of project construction and repayment contract administration. The appended supporting reports of the other Federal agencies do not propose any special facilities be included as part of the project con- struction for water pollution control, recreation, fish and wildlife purposes, or watershed management. However, in accordance with the proposals of those reports, the plan of development contemplates that appropriate measures will be taken to insure and facilitate free public access to the project area for hunting, fishing and recreation. The plan contemplates that, in accordance with the prOvisions of a March 14, 1962 memorandum of agreement between the Secretary of the Interior and the Secretary of the Army, the U.S. Army Corps of Engineers would have responsibility for design and construction of the authorized project works and the Secretary of the Interior would have responsibility for operation and maintenance of the project upon completion of construc- tion and for marketing of the project power. In light of this agreement, the proposed project plans, estimates, and schedules were reviewed in detail with the Corps of Engineers and their comments were considered in the preparation of this report. The Alaska Power Administration's estimate of the probable construction costs of the various project features, based on July 1967 prices, is summarized below: 2 Talmtz Creek and Saddle Dams Waterways Powerplant Access Road Transmission System Government Camp Total Federal project construction cost $ 5,640,000 4,670,000 4,100,000 3,600,000 3,980,000 .-!.z.29 0 ,000 $23,5 80 ,000 The comparable project installation costs, including interest during construction but excluding an estimated $98,000 of pre-authorization costs, would total $25,196,000. The construction schedule assumes that, following project authoriza- tion and availability of project fUnds, the first three years would be devoted to investigations, design, and the preparation of contract documents, with the first contract to be let in the fourth year. Pro- ject construction would be completed at the end of the seventh year. This would permit delivery of project power at the beginning of the ei gh th year. As the plan of development contemplates that the costs of operation, maintenance, and replacements of the project works will be borne by the Sitka Public utilities, the recurring annual Federal costs would be limited to those related to repayment contract administration. These are estimated to total $10,000 annually. The added costs to the Sitka Public utilities for project operation, maintenance, and replace- ments were estimated to total $le~,OOO annually. On the basis of the estimated installation and operation, maintenance, and replacement costs, a 100-year period of analYSiS, and interest at 3-1/4 percent, the economic costs are estimated to average $1,039,000 annually. Direct project benefits have been estimated on the basis of the cost of the most likely alternative source or sources that would provide an equivalent amount of power at the load center. This was determined to be municipally-financed diesel-electric units located in Sitka. The annual costs for providing power fram this source equivalent to the Takatz Creek Project generation were estimated to average $1,352,000 over a lOO-year period, which is equivalent to about 16.3 mills per kilowatt-hour for the firm power delivered to the load center. Compari- son of the evaluated direct benefits to economic costs indicates a benefit-cost ratio of 1.30 for a 100-year period. 3 The total project construction costs would be allocated to power and reimbursable with interest. In addition, the Federal costs of contract administration would be repayable. Project power supplies have been assumed to be available at the begin- ning of fiscal year 1976 with both units installed. However, on the basis of the forecast power requirements, the second unit would not be required until four years later. Thus the repayment analysis provides for deferral of assignment of one-half of the investment costs to plant- in-service until the beginning of the fifth year and accumulation of simple interest on these deferred costs. It also provides for repayment with interest at 3.253 percent of all investment costs within 50 years of when they are assigned to plant-in-service together with payment of the estimated Federal costs of contract administration. On the basis of the forecast project power requirements and a secondary energy value of 6.0 mills per kilowatt-hour, an average rate of 12.42 mills per kilowatt-hour for firm energy delivered to the Sitka area would provide revenues equal to the reimbursable Federal costs. The evaluated operation, maintenance, and replacement costs averaged about 2.2 mills per kilowatt-hour annually over the payment period. Thus the total cost to the utilities of project power delivered to the load center would be about 14.6 mills per kilowatt-hour. As previously derived, the cost of providing an equivalent amount of power through construction of municipally-financed diesel-electric units has been estimated at 16.3 mills per kilowatt-hour. This estimate is based on current construction costs with interest at 5.0 percent and assumes no escalation of fuel costs. On this basis, the cost to the utilities for Takatz Creek Project power would be slightly less than the costs of power from the most likely alternative source. The project interests consider that other signifi- cant benefits also would accrue to the Sitka area from Federal construc- tion of the Takatz Creek Project. They, therefore, have indicated "rillingness to enter into a repayment contract which would assure return to the Federal government of the reimbursable project costs. It is con- templated that this contract would provide for annual payments based on forecast project power requirements. Recommendations It is recommended that: (a) The Takatz Creek Project be authorized to be constructed by the Secretary of the Army, acting through the Chief of Engineers, and 4 to be operated and maintained by the Secretary of the Interior, sub- stantially in accordance with the plan set forth in this report, with such modification of, omissions from, or additions to the works as the Chief of Engineers and the Administrator of the Alaska Power Adminis- tration may find proper and necessary for the project purpose. (b) Negotiation of an appropriate repayment contract by the Secretary of the Interior with the City of Sitka or other qualified public body, as contemplated by the plan set forth in this report, be a pre-requisite to initiation of construction. (c) Pursuant to the recommendations contained in the Forest Service Multiple Use Survey Report, Stage I, the designated construc- tion agency coordinate the final location of the transmission line and access facilities with the Forest Service. However, upgrading of maintenance and access roads for the purpose of improved public access should not be approved if such work increases the costs to be repaid by the power users. (d) Additional detailed studies of fish and wildlife resources affected by the project be conducted as necessary, after the project is authorized, in accordance with the Fish and Wildlife Coordination Act, 48 Stat. 401, as amended; 16 U.S.C. 661 et seq.; and such reason- able modifications in the authorized project facilities be made by the Secretary of the Interior as he may find appropriate to preserve and propogate these resources. (e) Federal land and project waters in the project area be open to unrestricted use for hunting and fishing, except for sections re- served for safety, efficient operation, or protection of public pro- perty. (f) Leases of Federal land in the project area reserve the right of free public access for hunting and fishing. I fUrther recommend that you approve and adopt this report as your proposed report on the plan of development for the Takatz Creek Pro- ject, Alaska, and that you authorize me in your behalf to transmit copies of the report to the State of Alaska, to the Secretary of the Army, and to the interested Federal agencies for review as required by the Flood Control Act of 1944 (58 Stat. 887), the Fish and Wildlife 5 Coordination Act (48 Stat. 401, as amendedj 16 U.S.C. 661, et seq~; and procedures approved by the President on May 15, 1962 (S. Doc. 97, 87th Congo ). Respectfully , Gus Norwood Administrator Approved and Ad~ed: ll\~R' 5 195b Ci[;;;j'l~9J <X..U.' ~retary of the Interior \ 6 A C K NOW LED GEM E N T S The investigations of the Takatz Creek Project benefited through the cooperation of local, State, and Federal agencies. Officials of the City of Sitka and the Sitka Public Utilities were consulted regarding the project plans and operation and maintenance procedures, and they provided valuable information on system operation, future power needs, and all aspects of the area economy. Throughout the investigation, the interests and views of State and other Federal agencies were solicited and considered. The Federal Water Pollution Control Administration, Bureau of Outdoor Recreation, Fish and Wildlife Service, and the ~t Service reported on their findings, and their reports are appended hereto. The Bureau of Reclamation, prior to establishment of the Alaska Power Administration on June 16, 1967, was responsible for the initiation and accomplishment of the principal project investigations on which this report is based. It has furnished various technical assistance in connection with completion of the project investigations. The U.S o Army Corps of Engineers reviewed the plans, power esti- mates, sizing of project features, construction schedules, and cost estimates for the project. Their comments were considered in the preparation of this report. Computer operation studies prepared by the Corps have been included in the report. Topography, geologic data, and water supply data collected by the Geological Survey, and climatic information from Environmental Science Services Administration publications were used extensively in the investigations. Numerous other agencies and individuals provided information on resources, economy, and needs of the area. SUPPORTING REPORTS Table of Contents REPORT OF THE ALASKA POWER ADMINISTRATION ~ CHAPTER I -GENERAL DESCRIPTION. 1 The Project • 1 History of Investigations • • 1 The Power Market Area • • • • 2 Geography. • • 2 History. 3 Sitka. • • • • • 4 Greater Sitka Borough. • 5 Outlying Districts. 6 Climate • 7 CHAPTER II -AREA ECONOMY AND RESOURCES. 8 Mount Edgecumbe • • • 8 Forestry. • 9 Fisheries . • • 11 Mining. • • • 12 Agri cul ture • • • • • 13 Wildlife. • • • • • • • 13 Shipping. • • • • 14 Transportation. • • • 15 Tourism • • • • 15 Financial Conditions. • • 16 CHAPTER III -POWER SUPPLY AND DEMAND. • 18 History of Power Development. • 18 Existing Power Facilities • • • 19 Sitka Public Utilities • • • 19 Alaska Lumber and Pulp Company. 20 Alaska Native Service. • • • • • 20 Sitka Co~d storage Company • • 2~ Sheldon-Jackson Junior College • • 2~ Estimated Power Requirements. • • 21 Project Power Requirements. • • • • • 26 Interim Measures. • • • • 26 Utility Power Costs · • • 27 CHAPTER IV -WATER AND POWER • • • • 29 Drainage Area • • • • • 29 Water Supply. • • • • • 29 Streamflow and Climate Records · • • • 29 Study Period • • • • • • 31 Streamflow Correlations. • • • • • 31 Inf'low to Takatz Lake. • • • 32 Table of Contents (Continued) Page Water Rights. • • • 32 Reservoir Data. • • 35 Area and Capacity. • • 35 Sediment 35 Reservoir Losses 35 Power Studies 37 Operating Assumptions. 37 Load Characteristics. • 37 Efficiencies. • 38 Power Operation Study. • • 38 Power Capacity • • 38 CHAPTER V -DEVELOPMENT PLANS AND COSTS. • • 41 Geology • • • 41 General. • • 41 Takatz Creek ~ite • • • • 41 Saddle ~ite • 42 Takatz Lake. • • • 43 Tunnel • • 43 Takatz Creek Powerplant. 43 Penstock • 44 Transmission Line. • • 44 Concrete Aggregate • 44 Design and Construction Problems. • 44 Project Works • • • 44 Takatz Creek Dam • • • 47 Saddle Dam • • • 47 Takatz Lake. • 47 Diversion Tunnel • • • 48 Intake Structure • • • 48 Tunnel • • • 48 Gate Shaft • • 49 Surge Tank. • • 49 Penstock • • 49 Takat z Creek Powerp1ant. 49 Switchyard • • • 49 Transmission Line. • 50 Sitka Substation • • 50 Dock and Seaplant Float. 50 Access Road. • 50 Government Camp. • 51 Fish and Wildlife Facilities • 0 • 51 Recreation Facilities. • 51 Right-of-Way and Relocations. • 51 Plan Formulation. • • • 52 i1 Table of Contents (Continued) Economic Criteria for Plan Formulation • Hydroelectric Alternatives • • • • • • • • • • • • Maksoutof River Project • • • • Green Lake Project •••••• Diesel-Electric Alternative. • • • • Analyses of Reservoir Capacity and Project Size. • Other Analyses • • • • • • • • • • • • • Effects on Other Potential Developments. Construction Costs. • • • • • • • • • • • Construction Schedule • • • • • • • • • • • • Operation and Maintenance Costs • • • • • • · . Replacement Costs • • • • • • • • • • • • • CHAPTER VI -ECONOMIC AND FINANCIAL ANALYSIS • . . . Economic Analysis • . . . . . . . . . . . Benefits • • • • • • • • Economic Costs • • • • • • Benefit-Cost Ratio • • • • . . . · . . . . . . . . . . . . . . . · . . Financial Analysis. • • • • • • • • Repayment Requirements • . . · . . Average Rate and Repayment Study Repayment Contract • • • • • • • · . . . . . . • • • • CHAPTER VII -REQUIRED FUTURE ACTIONS. · . . CHAPTER VIII -EXPRESSIONS OF STATE AND LOCAL INTEREST • · . Tables No. Title l------Annual Statistics -Tongass National Forest, National Forest Commercial Sales • • • • • • 2------Financial Condition of Sitka and Greater Sitka · . . 52 52 52 54 54 55 57 58 58 59 59 60 63 63 63 64 64 64 64 65 67 68 69 10 Borough, 1965. • • • • • • • • • • • • • • • • • • 17 3------Sitka Public Utilities -Generating Facilities • •• 20 4------Historic and Projected Annual Power Requirements for Sitka Area • • • • 0 • • • • • • • • • •• 23 5------Takatz Creek Project Power Requirements. • • • • 26 6------Streamflow Records on Baranof Island • • • • • • •• 30 7------Baranof Island Climatic Data • • • • • • • • • • •• 30 8------Recorded and Computed Runoff, Takatz Creek near Baranof, acre-feet. • • • • • • • • • • • • • •• 33 iii Table of Contents (Continued) No. Title 9------Computed Inflow to Takatz Lake • • • • • • • • • •• 34 lO-----~onthly Load Distribution Data • • • • • • • •• 37 ll------Power Operation Study -Annual Summary • • • • • •• 40 12------Summary of Hydroelectric Alternatives. • • • • • •• 53 13------Summary of Analyses of Reservoir Capacity and Project Size • • • • • • • • • • • • • • • • • •• 56 14------Summary of Construction Costs. • • • • • • • • • •• 58 15------Takatz Creek Project Preliminary Power System No. Average Rate and Repayment Study • • • • • • • • • 66 Control Schedule, PF-2 •••• Basic Estimate, DC-l Summary. Drawings Title . . . • • • . . . . . . . . . . . . . . 61 62 11l3-906-11----General Map ••• Preceding Administrator's Letter 11l3-906-27----Peak Requirements at Load and Supply at Load, Kilowatts • • • • • • • • • • • • • • • . . 24 1113-906-28----Energy Requirements at Load and Supply at Load, Megawatt-Hours. • • • • • • • • • •• 25 1113-906-14----Area-Capacity Data. • • • • • • • • • • • •• 36 1113-906-24----Reservoir and Power Operation • • • • • • •• 39 11l3-906-12----Takatz Creek Works -Plan and Profile. • • • 45 1113-906-13----Dam DeSigns -Plans, Sections, and Elevations 46 Photographs City of Sitka ••••••••••••••••••• FollOwing 7 Pulp Mill near Sitka • • • .. • •. • • • • • • • • • FollOwing 11 Alaska Ferryliner. • • 0 • • • • • • • • • • • • • FollOwing 15 REPORrS OF O'If{ER AGENCIES. • • • • • • • • • • • • FollOwing 69 Letter Report of Federal Water Pollution Control Administration • • • • • • • • • • • • • • • • • •• 1 Letter Report of Bureau of Outdoor Recreation • • • • • 1-2 Letter Report of Fish and Wildlife Service. • • • • • • 1-2 Letter from Alaska Department of Fish and Gam.e • • • • • • • • • • • • • • • Following 2 Stage 1 Multiple Use Survey Report of Forest Service, Department of Agriculture •••••• 0 ••••••• 1-8 iv CHAPTER I-..QENERAL DESCRIPTION Southeast Alaska, mountainous in the extreme, includes hundreds of islands and a narrow strip of mainland between the canadian border and the innermost tidal courses. Its total land area of about 34,000 square miles is dissected into thousands of segments by the deep salt- water channels, inlets, and fiords of the Alexander Archipelago. Baranof Island, with a land area of 1,600 square miles, lies on the ocean, or west Side, of the Archipelago, and about mid-d1stance. The Takatz Creek Project and the city of Sitka are on Baranof Island. The Project The Takatz Creek Project, the subject of this report, takes its name from the perennial stream passing through Takatz Lake to tidewater in Takatz Bay, on the east side of Baranof Island. The relative inac- cessibility of Takatz Lake limits the opportunities for use of the project waters to the generation of electrical energy to serve the Sitka area. This purpose would be accomplished by the construction of a dam on Takatz Creek and diverting the lake waters through a pressure tunnel to a powerplant at tidewater. Project power would be transmitted to Sitka on the west side of Baranof Island by 28 miles of transmission line. The location of the major features of the project are shown on the General Map, Drawing No. 1113-5Q6-ll. The project would not materially affect the fish and wildlife resources of the area, and water pollution would not be a problem. History of Investigations In 1924, J. C. Dart of the Forest Service reported to the Federal Power Commission on potential waterpower sites in Southeastern Alaska, including the Takatz Lake site on Takatz Creek. This development is described in more detail in the 1947 joint report of the Federal Power Commission and the Forest Service, "water Powers, Southeast Alaska". The Bureau of Reclamation report, "Alaska, A Reconnaissance Report on the Potential of Water Resources in the Territory of Alaska for Irrigation, Power Pr'oduction and Other Beneficial Uses," which was com- pleted in 1949, and published as House Document 197, 82d Congress, First Session, in January 1952, included a Takatz Creek Project, based largely on data compiled by the Federal Power Commission and the Forest Service. The Corps of Engineers, in its Interim Report No. 1 on Southeast Alaska, dated February 15, 1952, discussed a similar development on Takatz Creek. In 1957, the Conservation Division of the U. So Geological Survey made a plane-table survey of Ta.katz Lake showing 2O-foot contours on a scale of 1:24,000. This survey included sounding of the lake fran which area and capacity curves were prepared. Topography of the lake was supplemented with topography from. the Sitka A-3 Quadrangle, Alaska, to prepare the map, IITakatz Creek, Alaska, 1957", showing Takatz Lake, Takatz Creek, and Ta.katz Bay. Previous investigations identified six potential powersites on Baranof Island for furnishing power supplies to the city of Sitka and environs. These were Baranof, Carbon, Green, Takatz, and Blue Lakes, and Maksoutof River. The Blue Lake Project was constructed by the Sitka Public Utilities as a 6,000-kilowatt hydroelectric plant and put in service in 1961. At that time, it was recognized that an additional power source, or sources, would soon be needed. In 1964, the Bureau of Reclamation began an inventory of all poten- tial hydroelectric developments in Southeast Alaska. The Takatz Creek Project was among these and was determined to be the most favorable for supplying the Sitka area with a power supply. This potential project was reviewed with representatives of the city of Sitka, who requested that the Bureau of Reclamation expedite its investigation of the project. Additional reconnaissance grade studies of the project were undertaken and a favorable reconnaissance report was completed in May 1965. The findings of this report were then presented to representatives of the city of Sitka, preliminary to the feasibility investigations summarized in this report. The plan formulation studies for the Takatz Creek Project included evaluation of various alternatives, including more detailed studies of the potential Green Lake and Maksoutof River hydroelectric proJects. The Power Market Area The power market area is synonymous with the Sitka Area, or that area that could be served by the Sitka Public Utilities System. It includes the city of Sitka, Japonski Island, and environs accessible by existing and proposed roads. Geography Baranof Island is typical of the majority of islands found in the Alexander Archipelago. They are extremely mountainous, the highest 2 peaks exceeding an elevation of 6,000 feet. Steep slopes rise abruptly from the coastline, which is indented by countless fiords, inlets, and bays. In addition, there are scores of small islets which literally surround the larger islands. Even the smallest of these, unless washed over by high tides, is covered by dense forest. Sitka, about two-thirds of the way up the west coast of Baranof Island, is the largest city and the center of population in this area. It is 860 miles northwest of Seattle and 95 miles southwest of Juneau. The city is protected fram the broad sweep of the Pacific Ocean by Kruzof Island and the many islets that fill Sitka Sound. Tak.atz Lake is about 18 miles due east of Sitka, near the east side of Baranof Island. Takatz Creek flows into Takatz Bay on Chatham Strait. History In the year 1741, Alexei Chirikof, a Russian naval captain, dropped anchor in what is now known as Sitka Sound. This is the first recorded visit of the white man to the area. Captain Chirikof sent a party ashore to investigate, and they were never heard of again. In 1775, a Spanish schooner, only 36 feet in length, under the command of Don Francisco de la Bodega y Quadra, sailed into the broad harbor and dropped anchor. He anchored in what is now known as lCrestof Bay, about six miles northwest of Sitka. Captain Cook, on his Third Voyage of Exploration, passed along the coast and named the round elevated mountain in the bay Mount Edgecumbe. The sea otter, a marine animal, was found abundantly in the passages about Sitka. It was one of the most valuable of the furbearers, but it is now nearly extinct. In 1799, Alexander Baranof, Manager of the Shelikof Russian-American Company, established the trading post of Arch- angel, or Old Sitka, for the purpose of gathering these furs. He secured a charter fram Emperor Paul, under the name of the Russian-American Company, that gave the exclusive right to all profits to be derived from every form of resource in the Russian possessions in America for a period of 20 years. In 1&:>2, the Thlingi t Indians, known as the Kolosh by the Russians, destroyed the settlement and killed most of the garrison. Two years later, Baranof returned from the Russian settlement at Kodiak with a strong contingent of forces and captured the Indian fort at the present site of Sitka. Restoration began and soon the town of New Archangel was established. This was the official name recognized by the Russians, but the term Sitka was frequently used and later adopted. The Shelikof Company headquarters was transferred from Kodiak to Sitka in 1&:>5. Under the guidance of Baranof, Sitka became the leading 3 manufacturing and trading center of the west coast. Here were estab- lished the first west coast shipbuilding yard, sawmill, flour mill, and iron and brass foundry. Gradually increasing disinterest of the Russian government in its American colony led to the sale of Alaska to the United States in 1867. The area was under military and naval control from Sitka until 1884, when a civil government for the District of Alaska was organized, and Sitka became the first capital of the District of Alaska. In 1906, the seat of government was transferred from historic Sitka to the new mining metropolis of Juneau, although the actual move was made gradually over several years. At the outset of World war II, Alaska's strategic military impor- tance was realized. A $60,000,000 naval air base and army defense base was constructed on Japonski Island and three smaller islands in Sitka harbor. Upon termination of hostilities, the bases were no longer required for military security, and the bulk of the facilities were turned over to the Alaska Native Service in 1946. The following year this installation was officially opened as the Mount Edgecumbe Educa- tional and Medical center. Sitka Sitka was incorporated into a first class city in 1920. It is the trading center for all of Baranof Island and Chichagof Island to the north, or that portion of Southeast Alaska extending from Chatham Strait on the east to the Pacific Ocean on the west and from Christian Sound on the south to Icy Strait on the north. The city has progressed from its settlement in 1799 as a trading post, through a succession of Indian skirmishes, to today's modern city. Its school system starts with kindergarten and extends through Sheldon Jackson Junior College. The latter, owned and operated by the Board of National Missions of the Presbyterian Church, began oper- ating in 1880. Sitka also boasts of churches of several denominations, two radio stations, a television station, and a daily newspaper, besides all the shops and recreation facilities found in a modern city. Sitka, because of its historic background, is attractive to many tourists. Among the attractions are the Sitka National Monument, Totem Pole Park, and the old Russian buildings. The magnificient old landmark, St. Michael's Cathedral, constructed in 1848 by the Russians, was destroyed by fire on January 2, 1966. Plans are underway to have the Cathedral restored to its original specifications. Never having been a "boom town", Sitka has not experienced the large influx and exodus of people which is the typical history of many Alaskan cities. The greatest percentage increase in population occurred 4 between 1880 and 1890, owing principally to expansion of the fur sealing trade. With minor fluctuations, the population remained about the same until shortly before World War II when military activities and interest in the area brought new inhabitants to Sitka. In 1959, the Alaska Pulp Company completed a modern pulp mill six miles east of Sitka that brought in many new people, resulting in expan- sion of housing and business facilities. Added to this was the construc- tion of the 6,OOO-kilowatt hydroelectric plant at Blue Lake, completed in 1961. As is typical of cities in Southeastern Alaska, Sitka is largely self-sufficient in business services. Municipal water and electric energy are supplied by the Sitka Public Utilities. Local and long dis- tance telephone service is available. The Alaska Steamship Company makes regular weekly stops in Sitka with freight and mail. Daily air- line service is provided to Seattle and Anchorage and to Juneau, Annette Island and Ketchikan, with connections to all other Southeast Alaska cities. The Alaska Marine Highway, with its ultra-modern ferries, makes two northbound and two southbound stops each week at Sitka. The 1965 population of Sitka Corporate Area was 3,725 persons. A tabulation of recorded population statistics, beginning in 1818, follows: Year Population Year P~ulation 1818 620 1910 1,039 1825 ~ 1920 1,175 1880 444 19~ 1,056 1890 1,190 1940 1,987 1900 1,396 1950 1,985 1960 3,237 Greater Sitka Borough Article 10 of the Constitution of the State of Alaska provides for maximum local self-government with a minimum of government units. Section 3 of Article 10 states: liThe entire State shall be divided into Borough~organized or unorganized. They shall be established in a manner and in according to standards provided by law. The standards shall include population, geography, economy, transportation and other factors. Each borough shall embrace an area and population with common interests to the maximum degree possible. The legislation shall classify boroughs and prescribe their powers and functions. Methods by which boroughs may be organized, incorporated, merged, consolidated, reclassi- fied or dissolved shall be prescribed by law." 5 The Greater Sitka Borough was incorporated as a second-class Borough, September 30, 1963, and has a Borough Assembly for.m of government. Its boundaries include all of Baranof and Kruzof Islands, approximately the southern half of Chichagof Island, and all islands on the western coast included within the limits of the State of Alaska between the southeast- erly end of Lisianski Inlet and the extreme southern tip of Baranof Island. It has an area of about 2,900 square miles and a 1965 population of 7,400 persons. The Takatz Creek Project, the city of Sitka, and the Mount Edgecumbe complex are within its boundaries. Port Alexander, on the southeast tip of Baranof Island, is home for 18 persons. Nevertheless, its requirements for mail service, supplies, and other facilities add to the economic l1fe of Sitka. Its economy is based principally on fishing, and its income fluctuates from year to year. There are only 18.3 miles of roads making up the Highway System about Sitka, and most are along the coastline. They extend six miles north from the city limits to Old Sitka Harbor in Katlian Bay, and 7.0 miles south of the city to Herring Cove. Plans have been formulated to connect Japonski Island and Baranof Island by a bridge, a span of about 1,000 feet. Outlying Districts Several small to¥rrBare located on the islands in the Sitka area and outside the Greater Sitka Borough, but are considered to be within the Sitka trading area. They are accessible from Sitka only by boat or seaplane. Hoonah, with a population of 686 at the 1960 census, is about 75 miles north of Sitka on the northeast side of Chichagof Island. Tenakee Springs, situated on an inlet off the eastern shore of Chichagof Island, had a 1960 population of 60. Both these towns are closer to Juneau than to Sitka, but their trade is divided between the two cities. Pelican, also on Chichagof Island, is about equidistant by air from Juneau and Sitka. It is considerably closer by boat to Sitka tban to Juneau, owing to the nature of the two water routes. Pelican is a company town that came into being in 1938 as a fishing center. The Pelican Cold Storage plant processes halibut, salmon and black cod in its modern plant. The latest census recorded a population of 135 at Pelican. Elfin Cove, with 20 per.manent inhabitants, is 15 miles north of Pelican. 6 Climate The climate of Baranof Island is cool and wet. Sitka has a July mean temperature of 54.9° F. and a January mean of 32.2° F., the latter about the same as that of Denver, Colorado. The coldest temperature ever recorded in Sitka was .8° F. Coastal areas in this region enjoy a temperate climate with relatively war.m winters and cool summers. Average annual precipitation is 89.2 inches, although this varies markedly with little change in altitude or distance. Average annual snowfall recorded at Sitka is 47 inches. Winter rains and mild temperatures limit snow accumulation except in the mountain areas. The prevailing winds are from the east, and this is reflected in the climatological records at Baranof, on the east side of the island, and near Takatz Creek. At Baranof, the average annual precipitation is 152 inches, with an average annual snowfall of 214 inches. The minimum tem- perature recorded in the 22 years of record was _10° F., and the highest was 78° F. Little Port Walter, on the southern tip of Baranof Island, and about 60 miles south of Sitka, has an average annual preCipitation of 220 inches, the highest in the State. 7 The City of Sitka, with Sitka Sound in the background. The Mt. Edgecumbe Education and Medical Center and the airport on Japonski Island adjoin the city in the·upper center of the photo. Photo by Alaska Travel DiviSion, 1966. CHAPTER II --AREA ECONOMY AND RESOURCES Sitka's economic history is one of successive ups and downs. A cannery started in 1878 was moved to Cook Inlet after only two years of operation. Fur sealing provided the community with a major source of income in the 1880's and 1890's until the herds became so small that the industry was restricted by the Federal Government in 1903. The gold rushes to Cook Inlet, the Klondike, and Nome passed through Sitka, taking many of the local residents with them. By 1890, Sitka had reached its lowest economic ebb and began its climb back into Alaskan importance. Establishment of the fishing industry in the late 1890's gave it a basic economy. When the capital was moved to Juneau, the loss was eased by the expanding lumbering industry. The Mount Edgecumbe installation of the Alaska Native Service, the pulp mill of the Alaska Pulp Company, the fishing industry, and tourists constitute the most important sources of base income for Sitka today. Mount Edgecumbe The Mount Edgecumbe Alaska Native Service school and hospital complex is on Japonski and interconnected islands. It is not to be confused with the mountain by the same name on Kruzof Island near the entrance to Sitka Sound. Japonski Island is directly across Sitka Harbor from Sitka proper and is served by a ferry that operates almost continuously. The Mount Edgecumbe complex is a self-contained unit in many respects and exerts a strong impact on Sitka. The school is a boarding high school for native students from towns and villages throughout the State that do not have local high schools. Its present enrollment is 660 students. It is administered by the Bureau of Indian Affairs. A $13,000,000 program for expansion of the Mount Edgecumbe educational facilities is planned with a scheduled construction start in the spring of 1968. During Fiscal Year 1966, there were 135 education positions in the school and a BIA staff of 150 employees, having a total annual payroll of $930,563. The hospital is administered by the Public Health Service of the Department of Health, and has an average daily patient load of 90. During Fiscal Year 1966, there were about 200 employees on the Public Health Service staff at Mount Edgecumbe, and their annual payroll approximated $1,100,000. 8 Prior to July 11 19661 the Mount Edgecumbe complex was admini- stered jointly by the Bureau of Indian Affairs and the Public Health Service. On that date 1 the Bureau of Indian Affairs took over administration of the entire complex1 except the hospital. With this expansion, they estimate their annual payroll at $1,687,690. The Mount Edgecumbe complex has a dial telephone system, fire department, central kitchen and dining ha1l1 laundrY1 bus and boat transportation1 a utilities and maintenance division1 a deep-water dock 1 and a seaplane ramp. The Mount Edgecumbe complex is outside of the corporate limits of the city of Sitka. It had a 1960 population of 1,884 persons, including employees and their families, and students. The employees of the institution spend a substantial portion of their annual pay- roll in Sitka for most of their necessary retail goods and services. Added to this payroll inccme are expenditures of students 1 hospital patients and visitors. Forestry The Tongass National Forest covers about 73 percent of the land area of Southeast Alaska1 or about 161000,000 acres. It consists of a strip along the mainland and 67 islands having land masses of 2,500 acres or more. Four of these islands exceed 1 1000,000 acres in area. Baranof and Chichagof Islands are two of them. About 65 percent of the gross land area in the Tongass National Forest is covered by tree growth. The balance largely lies above timber line and involves high rugged mountains with perpetual snow and ice fields and glaciers. Hemlock represents 62 percent of the Tongass National Forest timbe~with the Sitka spruce comprising the bulk of the remainder. About half of the commercial timber of the Tongass National Forest is best suited for the pulp or wood fiber industry. Ninety percent of the commercial timber is estimated to be within three miles of tidewater and below elevation 2,000 feet. The many tidewater channels1 with their multitude of fiords, inlets and bays, make access and the cost of log transportation by water very reasonable. Prior to 1954, when the Ketchikan Pulp Company began operating, the timber harvest was almost completely Sitka spruce accessible to tidewater. These logging operations supplied the many lumber mills in Southeast Alaska1 the first of which was the water-powered mill built by the Russian~erican Company at Sitka. The Forest Service estimates there are 217741000 acres accessi- ble that contain about 831262 million board feet of commercial ttmber1 9 having an annual a.llowable cut of 824 m1llion board feet. The present cut averages about 440 m1llion board feet per year. It is predicted that the annual cut will equal the a.llowable cut by about 1975. The annual statistics on the National Forest commercial sales are shown in Table 1. The Forest Service has divided the Forest into five working units, with the Sitka Working Circle comprised principally of Baranof, Chicha- gof, Yakobi, and Kruzof Islands, having a total land area of 2,433,000 acres. The Takatz Creek Project is within this working circle. Table l-~ual Statistics--To~ass National Forest !I National Forest Commercial Sales Volume Allowable cut MBF Total Value Average Value Year CUt MBF ~Scaledl ,st!!!'i~e l Per MBF CY 1920 45,609 $ 78,987 $1.73 CY 1925 53,72 3 93,233 1.74 CY 193) 38 ,517 71,212 1.85 CY 1935 3),454 44,761 1.47 CY 1940 585,520 3),861 46,529 1.51 CY 1945 585,520 58 ,268 89,700 1.54 CY 19~ 585,520 54,435 120,48 3 2.21 CY 1955 851,500 21 3,78 5 491,952 2.3) FYl960 879,&:>0 314 ,839 723,64 5 2.3) FY 1965 823,900 424,612 861,543 2.03 Y Appendix, Tiliiber Management Plan, Tongass National Forest, Alaska Region, 1958-1907. The percentage of forest volume within the Sitka Working Circle varies slightly fram the average for the entire Tongass National Forest. The Forest Service Timber Management Plan for the Sitka Work- ing Circle estimates that 65 percent of the accessible commercial forest land area in the Sitka Working Circle is occupied by the hemlock type. The hemlock--Sitka spruce type--ranks next with 22 percent of the accessible commercial forest land. The Sitka spruce type represents eight percent and the Alaska cedar type five percent of the commercial forest land. Prior to 1965, the Columbia Lumber Company operated a sawmill in Sitka with a capacity of 75,000 board feet per 8-hour shift, but it has ceased operations. 10 In 1956 the Alaska Pulp Company, a Japanese corporation owned by the Alaska Lumber and Pulp Company, negotiated a contract with the Forest Service for 5.25 billion board feet of timber primarily fram the Sitka Working Circle. Their modern pulp mill six miles east of Sitka is capable of producing 14,000 tons of high alpha. dissolving pulp monthly, for shipment to Japan. This high quality pulp is used in the manufacture of rayon. The plant employs about 500 workers who are directly associated with the plant. Of these, only the top administrators and a few laboratory technicians are Japanese. In addition, there are about 400 woods workers. The logs are "rafted" and towed to the mill by tug boat. The Alaska Pulp Company also buys logs from private land owners throughout Southeast Alaska when avail- able. It is pertinent that they have purchased logs in Haines and transported them 215 miles by -water to Sitka. In 1965, the st. Regis Paper Company negotiated a contract with the Forest Service for 8.75 billion board feet of lumber. However, it relinquished its rights under this contract in April 1967. The contract required that the Company construct a pulp mill in South- east Alaska, submit its plans to the Forest Service by July 1, 1968, and have the plant in operation by July 1, 1971. The timber under this contract is on Admiralty Island and two locations on the main- land. The city of Sitka vigorously promoted a potential industrial site in Kat1ian Bay, ten miles north of Sitka, as a good location for the contemplated pulp mill. Fisheries Fishing is the third most important industry of modern Sitka. Sitka-based boats fish throughout Southeast Alaska. They sometimes sell their catches in other ports, but boats based in other ports also sell to buyers within the Sitka area. During the 1965 season, there were 260 independent vendors issued commercial fishing licenses at Sitka, representing 528 individual commercial fishing licenses. There are presently three fish processing plants in Sitka, and one each at Pelican, Tenakee Springs, and Hoonah. When constructed in 1913, the Sitka Cold Storage plant -was for the exclusive purpose of processing halibut, but in 1965, salmon -was the predominant species, with minor amounts of black cod and king and dungeness crab. Most fish in the Sitka area are fresh-frozen for Shipment to other markets. Only a small percentage of fish are canned. The Alaska Department of Fish and Game reported the wholesale value of salmon processed by the three plants at Sitka during the 1965 season as $3,888,000 and $815,933 for all other species. In addition to the value of fish, wages paid to shore workers in 1965 amounted to $317,516 for the Sitka area proper, and $515,242 for 11 Alaska's second pulp mill, owned by Alaska Lumber and Pulp Campany is located near Sitka. Product is a high grade alpha-dissolving pulp for textile manufacturing, primarilY for the Japanese market. Photo by Alaska Travel Division. the entire Sitka Election District. The average number of employees in the plants was 44 for Sitka and 52 for the entire area, while the maximum numbers were 65 and 190, respectively. Another aspect of the importance of the commercial and salt water sports fisheries to the Sitka area is the investment in vessels and gear. There were 319 outboard boats and cruisers, under five ton, reg- istered as being based at Sitka in 1965. This fleet added to the other pleasure and commercial fishing boats in the Sitka area runs the total investment up to several million dollars. Supplying gas and oil, spare parts, repair services, paint, etc., is a major business in Sitka. There are marine ways, repair shops, outfitters, and small-boat harbor facilities devoted exclusively to meeting the needs of this industry. The two public small-boat harbors within the Sitka area proper have a combined capacity to berth about 625 boats. The communities of Pelican, Tenakee, and Hoonah also have small-boat harbors for both pleasure and cammercial craft. The future of Sitka's commercial fishing industry is not e~ected to change materially. The possible increased usage of lesser species or utilization of different species would probably not be enough to make an appreciable difference in total annual values. As the population of the area increases, it is likely that interest in salt water sports fishing will accelerate. Its economic impact on the Sitka area is well recognized. Mining Chichagof Island has been one of the leading gold-producing areas in the state in the past. Over $20 ,000 ,000 worth of the metal was taken between 1905 and 1941, when operations were discontinued. Same activity has been carried on since 1949, but the operations are of minor importance. Because of the present high costs of operation, it is unlikely that gold mining in the Sitka area will be of any great economic importance at the price of gold now prevailing. Yakobi Island contains one of the largest known nickel depOSits in the state. Other nickel-copper deposits are known to exist on Chichagof and Baranof Islands, but the ore is of low grade. With the ever increasing demand for these minerals, it is e~ected that recovery operations will sameday became a reality. Small deposits of chramite have been reported on the east coast of Baranof Island. Non-metallics found in the Sitka region include pumice, pum1cite, gypsum, marble, and clay. 12 Most of these known mineral deposits are located along the coast where prospecting has been relatively easy. Little is known about the mineral resources of the interior areas. Further prospecting, using geophysical and other modern methods, might disclose important deposits in these unexplored areas. Agriculture The Sitka area has almost no potential agricultural land. Prospects for extensive agricultural development anywhere in Southeast Alaska are slight, owing to the rugged topography, the shallow and generally acidic soils, and the wet and cool climate. A dairy farm near Sitka closed down in 1954 because of the high cost of operations, as grains, food concentrates, and most of the hay had to be imported. Wildlife The industry for which Sitka was originated now contributes prac- tically nothing to her income. Baranof established the Russian-American' capital as a focal point for his fur-gathering activities. Since 1900, trapping in the Sitka area has decreased in importance to its present status as a small winter supplement to the income of a few local fisher- men. The Sitka area offers a real challenge to the hunter. All of the larger islands are inhabited by several species of game birds and animals. Owing to the rugged terrain and dense growth, however, many a hunter ends the season with an empty larder. The Alaska Department of Fish and Game reports that approximately 1,050 hunting licenses were sold in the Sitka area in 1965. Of these, about 500 hunters took about 1,400 Sitka Blacktail deer from Baranof and Chichagof Islands. It is estimated that the deer population on the two islands is about 50 ,000. About 200 mountain goats populate Baranof Island, with only 20-)) being harvested this past year. The brown bear population of the two islands is estimated to be between 1,400 and 1,500. Black bear do not occur on the islands o The legal sport kill of brown bears in the Sitka area in 1965 was 27. It is estimated that expenditures by hunters in the Sitka area during 1965 approximated $125,000. In addi- tion to big game, ducks, geese, grouse, and ptarmigan are prized game birds found in all of Southeast Alaska o 13 Shipping Statistics on waterborne commerce entering and leaving Sitka Harbor are published in the report "Waterborne Commerce of the United States, Calendar Year 1963, Part 4," prepared by the Department of the Army, Corps of Engineers. This report shows that 855,004 short tons of commodities entered and left Sitka Harbor in 1963. This freight traffic is in the following categories: Foreign Traffic Imports Exports 428 161,879 Domestic, Coastwise Traffic Receipts Shipments 68 3,748 7,192 Domestic Local Traffic Total 162,307 short tons 690,940 short tons 1,757 short tons 855,004 short tons Of the exports, 161,875 short tons were wood pulp shipped to Japan, and the remaining four tons were canned fish and products. Rafted logs make up 586,626 short tons of the Domestic Coastwise Receipts, and 4,379 short tons of Domestic Shipments. The Domestic local freight traffic was entirely fresh fish and products. Excluding the export of wood pulp and the receipts of rafted logs, the 1963 freight traffic in Sitka Harbor is compared to other harbors of Southeast Alaska cities as follows: Harbor Sitka Juneau Ketchikan Freight Traffic, short tons 106,503 Y 93,666 385,896 gj !I Includes 24,997 short tons of sodium hydroxide, or caustic soda, for the pulp mill. gj Includes supplies and materials for U.S. Coast Guard. 14 Transportation The principal carrier of supplies and materials to Sitka is the Alaska Steamship Company. Its schedule calls for weekly arrivals from Seattle. On alternate weeks, the routings are to Sitka through Juneau on their Southeast Alaska schedule and enroute to Kodiak and Cordova. Passenger service to Sitka is either by air or water. Alaska Coastal Airlines serves Sitka from Juneau, Ketchikan and Annette Island. Connections are made at Juneau and Annette Island with other airlines for continued travel. With the recently completed Municipal Airport on Japonski Island, Alaska Airlines has included a stop at Sitka each way on their daily jet service between Anchorage and Seattle. One leg of the Alaska Marine Highway System is via Sitka. This state-owned system has three ferryliners, each with a capacity of 108 automobiles and accommodations for 500 passengers. The southern terminous connects at Prince Rupert with British Columbia Highway Route 16, and the British Columbia Ferry System operating between Prince Rupert and Vancouver Island. The northern terminous connects at Haines with the Haines Highway and the Alaska Highway. The system makes vehicular traffic possible to and from Ketchikan, Wrangell, Petersburg, Sitka, Juneau, Haines, and Skagway. The present schedule allows for two weekly trips each way through Sitka. Tourism Having been one of the focal points of history, Sitka holds a fascination for those who are acquainted with its interesting and colorful past. Many relics of yesteryear have been restored, and remnants of the Russian era are scattered throughout the area. The totem poles of the Sitka National Monument and the museum at Sheldon Jackson Junior College are exceptional pOints of interest. Saint Michael's Cathedral, dedicated in 1848, and destroyed by fire January 2, 1966, is to be reconstructed to its original specifications o It was one of Sitka's most noteworthy attractions. Outside the city a beautiful panorama of islands, bays, fiords and waterfalls can be seen and explored by boat, and wilderness trails unfold the beauty of the inland lakes, rivers, and primeval forests. For the sportsman, fishing, hunting, hiking, or boating offer an unlimited agenda. There are three sets of hot springs on Baranof Island. Modest accommodations are available at Baranof Bot Springs, on the east coast 15 One of the three luxurious ferryliners of the Alaska Marine Highway, having a capacity of loB automobiles and accommodations for 500 passengers. Photo by Alaska Travel Division. of the island three airline miles south of Takatz Bay. These hot springs have a very picturesque setting and are well suited to the operation of a deluxe resort. Goddard Hot Springs, 16 miles south of Sitka on the western shore of the island on Hot Springs Bay, were once the basis of a health and recreational resort. They are now owned by the State and leased to the Alaska Crippled Childrens Association. A third set of hot springs, at Fish Bay on the northern end of Baranof Island, has never been developed. Financial Conditions The financial conditions of Sitka and the Greater Sitka Borough are summarized in "Alaska Municipal Directory, 1966", a publication of the Alaska Municipal League. For the year ending December 31, 1965, Sitka had an indebtedness of 38 0 3 percent of assessed valuation, and the Borough 7.3 percent. Other data relating to their financial conditions are summarized in Table 2. 16 Table 2--Financial Conditions of Sitka and Greater Sitka Borough, 1965 Item Population Property Evaluations Real Personal Tax Rate Real Property Personal Sales Bonded Indebtedness General Obligation Bonds Revenue Bonds City of Sitka 3,72 5 $16,6 47,95 4 $ 108,21 3 6.5 mills Combined 2 percent $ 874,900 $ 5,941,000 Major Annual Revenues last fiscal year Property Taxes Sales Tax State-shared Taxes Licenses and Permits Fines and Penalties Interest Parking Meters Sale of Property or Material Amount of Budget last fiscal year 17 $ 90,023 $ 165,62:> $ 32 ,104 $ 3,384 $ 14,103 $ 1,32:> 4> 4,8'jl. $ 6,90 6 $ 508,210 Greater Sitka Borough 7,qoo $17,329,653 $ 5,198,975 9.25 mills 9.25 mills 2 percent $ 1,762,000 o CHAPTER III--POWER SUPPLY AND DEMAND The market for power produced by the Takatz be residential, commercial, and small industrial area. It would include the city of Sitka, Mount accessible by the respective roads in the area. by the Sitka Public Utilities. History of Power Development Creek Project would loads in the Sitka Edgecumbe, and environs It is presently served From 1913 to 1947, power generation for public use at Sitka was supplied for the most part by a small hydroelectric plant located near the mouth of Medvetcha River (known as Sawmill Creek since 1930). The project was constructed in 1913 by the Sitka Wharf and Power Company, Inc., a private enterprise. The company built a small rock-crib dam on the river and diverted water to the powerplant through a 42-inch diameter wood-stave pipe, '1,427 feet in length. A single 160-kilowatt generator was installed and six miles of 12.47-kilovolt transmission line built to Sitka. Repeated flood damage to the project--particularly in the years 1913, 1926, 1936 and 1942--caused frequent outages. Following the flood of 1936, the 42-inch pipeline was replaced with a new 54-inch line that passed through a short tunnel. A second 160-kilowatt gen- erator, purchased second-hand and rebuilt, was installed in the power- house at this same time. To guard against the recurring outages of the power supply, the Sitka Cold Storage Company was forced to seek emergency power fram some other source. Prior to the 1936 flood and in cooperation with the power company, the cold storage plant installed two diesel-electric sets with a total capacity of 385 kilowatts. In 1940 the Sitka Cold Storage Company acquired full ownership of these diesel units. In 1941, the City of Sitka formed the Sitka Public Utilities System and purchased the power facilities owned and operated by the Sitka Wharf and Power Company. The price, based on appraisal of the properties at that time, was $200 ,000. The City also installed a 240-kilowatt diesel unit in the cold storage plant to use as standby for the hydroelectric development. One of the most damaging floods of the Medvetcha River occurred in 1942. The intake flume, about 100 feet of pipe, a trestle that supported the pipe across the river, and a suspension footbridge were 18 washed out, and the powerhouse was flooded to a depth of about eight feet. The facilities were rehabilitated and operation resumed in late 1943. Part of the dam and pipeline were again damaged by floods, and the plant was taken out of service in March 1947. In 1940, the Navy began construction of a 2,950-kilowatt, oil-fired steamplant at its base on Japonski Island. A submarine cable connecting the Sitka Public Utilities System with that of the naval base created a substantial source of standby and emergency power for the utility. Upon te~ination of World War II, the naval base was abandoned as such, and most of the facilitie~ including the steamplant, were transferred to the Alaska Native Service in 1946. The Sitka Public Utilities arranged to obtain steam-generated power from the plant as a supplement to its own production. Following shutdown of the Medvetcha River hydroelectric plant, the Japonski Island steamplant supplied all of the City's power loads. As the population expanded and the load requirements grew, the power available from. Japonski Island (Mount Edgecumbe) was supplemented by installation of diesel-generating units by the Sitka Public Utilities in its powerplant north of the city. The installed capacity of that plant now totals 1,300 kilowatts. In 1961, the Sitka Public Utilities completed the Blue Lake hydro- electric plant with a peaking capacity of 6,900 kilowatts. It produces an estimated 44,000,000 kilowatt-hours of firm energy annually. The Blue Lake generating plant is only a very short distance from the old original Medvetcha River plant. Existing Power Facilities The existing power facilities in the power market area include those owned by the city of Sitka, Alaska Native Service, Alaska Lumber and Pulp Company, Sitka Cold Storage, and Sheldon..Jackson Junior College. Sitka Public Utilities The Sitka Public Utilities has 8,200 kilowatts of peaking capacity in two plants. The Blue Lake hydroelectric plant contains two 3,000- kilowatt units, and their diesel plant contains four units totaling 1,3)0 kilowatts on a standby basis. The estimated peak system demand in 1965, excluding the pulp mill, was 5,500 kilowatts, an increase in demand of about 10 percent over that estimated for 19640 The generating facilities of the Sitka Public Utilities are summarized in Table 3. 19 Table 3--Sitka Public Utilities -Generating Facilities CaEacit~ -Kilowatts Annual Firm Name Energy Plant ~ Plate -Firm Peaking MWH Blue Lake Hydro 6,000 6,000 6,~0 44,000 City Diesel 1,3)0 1,3)0 1,):)0 11,000 The utility system is presently supplying about 2,000 kilowatts to the Alaska Lumber and Pulp Company at a dump rate, but essentially on a demand basis. It will, in all probability, continue to make this block of power available to them until additional generating facilities are installed by the pulp company_ The present requirements of the utility and pulp mill are about equal to the entire capacity of the Blue Lake powerplant. Alaska Lumber and Pulp Company The Alaska Lumber and Pulp Company is the largest power user in the power market area. Their reqUirements approach 110,000,000 kilo- watt-hours annually. The major portion of their energy requirements is generated by its own l5,OOO-kilowatt steamplant. The mill was originally designed to be self-sufficient in regard to its power requirements. However, an alteration in the mill process has resulted in the need for additional power and energy over and above that avail- able from their existing facilities. They are now planning a $30 million plant expansion to again make the mill self-sufficient in regard to their power requirements. The mill does not supply power or energy service to other users. Alaska Native Service The installations of the U.S o Navy on Japonski Island included a diesel-electric system and an oil-fired steamplant for the generation of electricity and heating service. Although the plant has an aggre- gate name-plate rating of 2,950 kilowatts, the maximum available power capacity during heating requirements was only 1,900 kilowatts, because of insufficient boiler capacity to supply maximum heating and power loads simultaneously. An agreement between the Sitka Public Utilities and the Alaska Native Service allowed the Alaska Native Service to purchase all their power and energy requirements fram the utility after completion of the Blue Lake plant. At the present time, Mount Edgecumbe utilizes its steamplant primarily for heating service. It retains 250 kilowatts of steam generation in operable condition for standby purposes. A small emergency diesel unit is also maintained in a standby status at the hospital. Sitka Cold storage Caseany The power requirements of the Sitka Cold Storage Company depend upon the amount of fish under refrigeration. Their requirements are estimated at between 800,000 and 1,000,000 kilowatt-hours annually. The company has used their existing diesel plant to satisfy a portion of its requirements, but, there is no record of their having generated any substantial amount since 1955. A 2OO-kilowatt diesel plant is maintained in a standby status, with all normal requirements being purchased from the utility. It is assumed that this situation will continue to prevail. Sheldon-Jackson Junior College The College operates a 50-kilowatt hydroelectric plant to satisfy a portion of its power requirements. This unit is operated in parallel with the utility system and is interconnected through a 5O-kilovolt- ampere transformer bank. The College purchases power from the utility to supply needs in excess of 50 kilowatts. The water supplies from Indian River utilized for this power production are being considered for municipal use. This report, therefore, assumes that when power from the Takatz Creek Project becomes available, this plant will be retired. Estimated Power Requirements The energy sales of Sitka Public Utilities have increased at an average annual rate of about 7.8 percent over the past 16 years. Annual load growth during this 16-year period. fluctuated a great deal. The addition, or deletion, of just one industrial customer during the year would have drastically affected the load growth for the entire area. These fluctuations can be correlated with specific events occurring in the local area. For example, the minus 10 percent load growth in 1954 can be partially attributed to the change in management of Mount Edge- cumbe, and the decrease in 1966 is due to a fire in the Sitka downtown area in January that destroyed two churches and 21 places of business. The sharp increases in 1958, 1959 and 1960 are coincident with the construction of the pulp mill and power facilities. The next few years after completion of the mill and powerplant are marked by very much slower rates of load growtho This could best be explained as a re-adjustment period. following the construction boom. 21 Records of energy sales have been kept by the utility since 1948, but are incomplete, and not sufficiently detailed to allow any analysis b;' class of customer. An examination of the available records indicates that the period 1955-1965 could be regarded as a t~~icDl period for the basis of future forecasts, a all indications are favorable to an cxtcnsi ve and continuinG grovrth for the Sitka area. Reconstruction of thco business establishments and churches destroyed in the January 1966 fire is well underway. Construetion of the facilities for expansion of the Mount Edgeculnbe native boarding school is scheduled for initiation in the spring of 1968. The planned expansion of the Alaska Lumber and Pu1r Company mill ;'lill result in related new power requirements. It is anticipated that a new lumber mill and a pl;'-'Vlood plant will SOOn be constructed in the area. In addition, longer term planning for the area envisions development of a major industrial development in the Katlian , area north of the city, as it is favored with a good deep water harbor, ample industrial Gites, and easil~r developed fresh water supplies. On the basis of the above, the future load growth in the Sitka area has 'been estimated at an average annual rate of 10.5 percent, as repre- sented b,'i the 1955-1965 period. The historic and projected annual G~,-stem peak capacity and energy requirements are presented in Table 4. These tabulations, with indicated existing and future facilities, are presented in graph form on DrBiolings ll13-9J6-27 and l1l3-9J6-28. 22 1sble 4--Historic and Projected Annual Power Requirements for Sitka Area Calendar Year 19)0 1951 1952 1953 19)4 1955 19)1) 1957' 1950 1959 1900 1901 1902 1903 19G4 1965 1966 ~/ 1967 1968 1969 1970 1971 1972 1973 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 1986 Ener~ (Megawatt-Hours) 6,90 7 7,234 8,344 9,180 8,232 8,935 10,012 10,173 12,0)9 13,787 16,156 16,841 1'7,50'( 19,748 21,821 2/ 24,050 - 21,981 24,3 00 26,900 29,700 32,800 36,200 40,000 44,200 48,800 53,900 59,600 65,900 72,800 80,400 88,800 98 ,100 108,~00 119,800 132,400 146,300 161,700 ~/ Values through 1966 are historic ~/ Estimated 23 Peak Deman4 (Kilowatts) 1,630 1,700 1,885 2,075 2,020 2,46 5 Not Available Not Available 2,820 3,170 Not Available 3,500 3,500 Not Available Not Available 5,500 5,200 5,500 6,100 6,600 7,300 7,900 8,800 9,500 10,500 11,400 12,600 13,700 15,100 16,700 18,400 20,400 22,500 24,900 27,500 30 ,200 33,600 I I I I , 30 2Cl Future Diesel 4000 Ki lowatts 10 9 I c I -Existin~gDiesel 1300 Kilowatts ~-7 -6 ----~b 5 / ~-~ >---\ \ 4 -3 ~ \ ~ Historical Foreca st __ ~ -Demand r Demand I (1 1960 '1962 11964 11966 11968 119"lO I , I , , II //~! / I iii ~ DIesel Standby iiiJv;t J / "" / V /' / /' {'/ '1'''- ",J. or ~ ", ,..... -~ ~xjst;ng Blue Lake Hydrc 6900 Ki lowatt.s , I I S' / / , IIII Ill! 1I I I / W ~ W .' /' / / /!' // Takatz No.2 9600 KilowattS- Tokotz No. I 9600 Ki lowotfs UNITED STATES DEPARTMENT OF THE INTERIOR ALASKA POWER ADMINISTRATIO N TAKATZ CR EEK PROJECT PEAK REQUIREMENTS AT LOAD AND SUPPLY AT LOAD I·N KILOWATTS 1'972 11974 11976 11978 11980 11982 11984 11986 FISCAL YEAR SE PTEMaER 15 1967 1113-906-27 0 0 0 - M (/) a: :::> 0 J: I ~ ~ « 3: « C) w ~ I 15l'l - 100 d' / ,,/ 'nitio' Generation /'/ at Tokotz ----_ ...... -'\)0 ,,1i'J' /~ r'/ // ,,)if (" I , I I I ---;-~/-t-----------I I Tokotz Creek Hydno 93,200 Megowott- Hours at Load 50r-----~----~----~------+_----~----_4------~,~~--~~----+_----~----~------+_+_--~__; ...... ..-i,.--- 10 FISCA L YEA R UNITED STATES DEItAIitTMENT OF THE INTIIUO" ALASKA POWER ADMINISTRATIO N 67 1113-906-28 Project Power Requirements The requirements for power produced by the Takatz Creek Project are the Sitka area requirements presented in Table 4, less the gen- eration by the Blue Lake hydro plant and allowances of four percent of the project generation for project station service use and trans- mission losses. The fiscal year requirements are taken as being the same as the calendar year requirements, and are shown in Table 5 for the period beginning in 1976. This is believed to be the earliest date the Takatz Creek Project power could be available to the Sitka area. Table 5--Takatz Creek Project Power Requirements Fiscal Energy ReqUirements Year Peak Demands ~Kilowatts 2 ~Me~awatt-Hours2 1976 6,100 17,000 1977 7,200 23,500 1978 8,700 '5),600 1979 10,))0 38 ,400 1980 12, ))0 46,700 1981 14,100 56 ,700 1982 16,))0 67,))0 1983 18,700 79,000 1984 20,000 Y 92,000 1985 20,000 97,100 gj fI Installed capacity g; Total of firm energy generation Interim Measures The Sitka Public utilities recognize the city's need for addi- tional power supplies, and various alternatives are being studied. It is assumed that as soon as the expansion of the pulp mill has been completed, the surplus power now delivered to the mill will be made available to meet the anticipated growth of the utility load. Exist- ing powerplants will be fully utilized by 1971 and additional power will be required by that time. 26 One alternative would be the installation of a third 3,000 kilo- watt unit in the Blue Lake powerplant. This unit would be capable of supplying only a limited amount of additional energy, but present load forecasts indicate that the peaking capacity this alternate would provide is the more urgently needed. The original plan of the power- plant included the possible future addition of a third unit, but the pulp mill has a contract with the City for 50 million gallons of water per day at penstock pressure, and an agreement would be necessary to allow further use of this water. With this addition, the maximum peaking capacity of the Sitka Public Utilities system would be 11,650 kilowatts, considering 115 percent rated hydro capacity, plus existing diesel units. It is estimated that this would satisfy their peak power reqUirements through fiscal year 1975, but standby or reserve capacity would not be available during peak load periods. The other and more likely alternative is the installation of additional diesel generating units to supply the peak requirements necessary during the interim period. This would alleviate the need for an additional water contract and/or agreement with the pulp mill. It is estimated that the total additional requirements to just satis- fy the 1975 fiscal year peak would be about 4,000 kilowatts. With this addition, the utility's diesel generating capacity would be 5,300 kilowatts at the time of initial Takatz Creek Project operation (FY 1976). The diesel capacity would then be available as standby reserve. Utility Power Costs The costs of power production are not available for the Sitka Public Utilities. It is probable, however, that the hydro averages around 13 mills per kilowatt-hour and the diesel 20 mills or more. Sitka has a single residential rate schedule and two commercial rate schedules as follows: Residential First 100 kwh @ $0.05 per kwh Next 200 kwh @ $0.04 per kwh Next 300 kwh @ $0.03 per kwh Next 1,000 kwh @ $0.016 per kwh All additional kwh @ $J.03 per kwh 27 Commercial-Demands less than 50 kva First 100 kwh @ $0.05 per kwh Next 2Xl kwh @ $0 .04 per kwh Next 700 kwh @ $0.035 per kwh All additional kwh @ $0.03 per kwh Commercial-Demands not less than 50 kva Energy Charge First 50 kwh per kva demand @ $0.03 per kwh Next 250 kwh per kva demand @ $0 .02 per kwh All additional kwh per kva demand @ $0.0175 per kwh Demand Charge $1.75 per kva of demand These rates are roughly comparable to those prevailing in other Southeastern Alaska cities of similar size. The increase in the residential rate for the last step (all above 1,600 kwh) discourages large residential use. 28 CHAPTER IV--WATER AND POWER Water supplies available for power production were determined using streamflow records for Takatz Creek and for neighboring streams. Reservoir sedimentation and reservoir losses were found to be negli- gible. A monthly operation study was prepared to illustrate reservoir operation, power releases, and project power production. Powerplant capacity was selected on the basis of the project firm energy capability and area load characteristics. Drainage Area The drainage area above Takatz Creek damsite comprises 10.6 square miles of rugged, mountainous terrain typical of Southeast Alaska. Much of the surface is bare rock with the majority of vegetation limited to the valley floor above the lake. Glaciers and ice fields cover about 2.0 square miles and Takatz Lake, 0.6 square mile. Elevations range from 905 feet at Takatz Lake to over 4,000 feet at the drainage area boundary. The mean elevation of the drainage area is 2,482 feet. water Supply Streamflow and Climate Records A recording streamgage has been operated at the mouth of Takatz Creek since July 1951. In addition, streamflow records are available for six other streams on Baranof Island, including Sawmill Creek and Baranof River with drainages adjacent to the Takatz Creek drainage area, as shown on General Map, Drawing 1113-906.11. The Baranof Island gaged streams are listed in Table 6, together with drainage area and period of record for each stream. Runoff records through Water Year 1964 were analyzed for this report. 29 Table 6--Streamflow Records on Baranof Island Drainage Unit Area Period of Record Runoff Station Square Miles From To AF!mi?/yr.Y Takatz Creek nr. Baranof 17.5 July 1951 Present 11,400 Baranof River at Baranof 32.0 July 1915 Jan. 1928 9,600 Oct. 1957 Present Sawmill Creek nr. Sitka 39.0 Sept 192) Dec. 1922 8,700 Feb. 1928 Sept 1942 Oct. 1945 Sept 1957 Green Lake Outlet nr. Sitka 28.4 Sept 1915 Sept 1925 7,500 Coal Creek nr. Baranof 28.5 July 1922 Oct. 1927 12,2)0 (9 months of no record) Maksoutof River nr. Port 26.0 June 1951 Sept 1956 ll,700 Alexander Deer Lake Outlet nr. Port 7.4 June 1951 Present 15,))0 Alexander Y Adjusted to the 1952-1964 period. Precipitation and temperature data have been collected at various locations in Sitka for over 100 years, and two climate stations are now operated in the Sitka area. Climate data have been collected since 1937 at Baranof Warm Springs, three miles to the south of the Takatz Creek Powerplant site. Significant climate records are also available at Little Port Walter and Port Alexander, both located near the south- ern tip of Baranof Island. A summary of the Baranof Island climatic data is presented in Table 7. Table 7--Baranof Island Climatic Data Climatic Data through 1960 Average Years of Precipi-Annual Average Record tation Snowfall Temperature (Precipi- Station Inches Inches Degrees F. tationl Baranof warm Springs 152 214 41.3 22 Sitka (Mag) 97 47 43.3 99 (FAA) 88 45 44.0 13 Little Port walter 22) 126 43.0 24 Port Alexander 169 79 43.8 10 Unit runoff and distribution of runoff for Takatz Creek, Sawmill Creek, and Baranof River vary in surprisingly predictable patterns. Agreement with the precipitation data is shown by the higher runoff rates for streams on the east side of Baranof Island (Takatz, Baranof, Coal) and for the streams near the southern end of the island (Deer, Maksoutof). The higher drainage basins show increased runoff rates and a marked concentration of summer flow as a result of more severe climate and greater precipitation at the higher elevations. Study Period Good indicators of long-term water supply conditions are available. The streamflow records are available for Sawmill Creek or Baranof River for each year since 1916, except for the years 1942-1945. Based upon the long precipitation record at Sitka, the period covered by stream- flow records, 1916 to 1964, appears representative of long-term water supply conditions. Using annual streamflow correlation, Takatz Creek flows were esti- mated for the years 1916-1927, 1929-1942, and 1946-1951. Below-average streamflow 1s indicated for the years 1916-1922 and 1950-1958, with 1951 being the lowest year. The following comparison shows that the more recent period is critical. Item Lowest Year: Low 3-year Average: Average for Period: Takatz Creek Runoff 1916-1922 (7 years) 162 (1920) 174 (20-22) 188 (16-22) (1,000 AF) 1950-1958 (9 lears) 138 (1951) 166 (50-52) 181 (50-58) To incorporate the critical period and to insure a full cycle of reservoir operation, the study period 1946-1964 was selected. The above-average precipitation during the years 1942-1945 would insure a full reservoir at the start of this period. Streamflow Correlations The Takatz Creek runoff record covers the period July 1951 through 1964. The record was extended back to 1946, the start of the study period, by correlation with Sawmill Creek flows. Both monthly and annual correlations were used. The average annual flow for the 1946 to 1964 study period ws found to be 196,700 acre-feet. Minimum and maximum runoff values were 138,000 acre-feet in 1951 (partly correlated) and 241,500 acre-feet in 1964 (recorded). The monthly and annual recorded and correlated runoff at the Takatz Creek gaging station are presented in Table 8. Inflow to Takatz Lake The Takatz Creek gaging station has a tributary drainage area of 17.5 square miles with a mean elevation of 2,213 feet. The drainage area above the damsites is 10.6 square miles or 60 percent of the area tributary to the gage. The mean elevation of this area is 2,482 feet. Using elevation-runoff relationships, the annual runoff for the 10.6 square miles tributary to Takatz Lake was found to be 65.3 percent of that passing the gaging station. On a seasonal baSis, inflow to Takatz Lake was found to be 49.7 percent of the gaged flow for the November to April period, 58.2 percent for May and June, and 73.5 percent for the July to October period. The computed inflow to Takatz Lake is presented in Table 9. The monthly flow values were obtained using the gaged Takatz Creek flows and the seasonal percentages listed above. For the 19-year study period, the average Takatz Lake inflow was found to be 128,800 acre- feet. Minimum. and maximum values are 91,800 acre-feet (1951) and 159,500 acre-feet (1964). Water Rights The Constitution of the State of Alaska provides that surface and subsurface wters are reserved to the people for cammon use, except mineral and medicinal waters, and are subject to appropriation. The Constitution provides: Itpriority of appropriation shall give prior right. Except for public water supply, an appropriation of water shall be limited to stated purposes and subject to preferences among beneficial uses, concurrent or otherwise, as prescribed bY,1 law, and to the general reservation of fish and wildlife." !t The State Legislature passed HE 140, the IIAlaska Water Use Act," in its 1966 session, and the measure was signed by the Governor. The new law is a comprehensive code that assigns to the State's Department of Natural Resources the responsibility of determining and adjudicating water rights. In accordance with procedures established by the f7 Article VIII, Section 13 32 Table 8--Recorded and Computed Runoff of Takat:c; Creek near Baranof Drainage Area: 17.5 Square Hiles Units: 000 Acre-Feet Year Oct. Nov. Dec. Jan. Feb. Mar. Apr. May ,June July Aug. Sept. Total 1946 37.9 7.3 3.4 3.1 1. r( 2.3 2.7 18.9 31.5 29.4 2}+.1 23.7 186.0 1947 29.2 18.7 2.8 4.6 2.7 9.3 '(.6 20·9 23.8 26.3 25.4 }~5. 7 217.0 1948 23.2 15.0 5.8 9.1 2.3 1.9 2.1 20.5 30.9 36.1 26.8 42.3 21b.0 1949 24.3 19.8 3.2 6.2 2.4 3.7 4.4 17.2 35.9 33.9 27·5 25·5 204.0 1950 33.7 13.3 3.3 1.8 1.5 1.6 2.3 10.4 31.1 35.4 23.8 20.8 179.0 1951 14.1 3.8 1.6 2.1 1.2 1.5 3.8 13.8 27.2 29.9 19.0 20.0 138.0 w 1952 17.8 14.5 3.3 1.2 1.2 1.1 4.8 12.9 23·5 38.5 25.8 37·5 182.1 w 1953 32.6 17.5 7.1 3.5 3.3 4.2 5.4 22.9 33.0 32.6 28.1 29.0 219.2 1954 40.1 14.5 7.9 3.1 0 2.2 2.0 14.6 30.1 26.3 22.0 24.3 194.1 1955 21.1 24.7 13.5 3.9 2.6 2.4 3.2 8.9 22.1 33.9 29·9 27.7 193.9 1956 17.4 6.0 2.3 1.4 1.4 1.5 3.8 16.9 29.9 33.3 37.0 17.8 168.7 1957 16.2 13.3 12.8 4.1 2.2 2.1 3.9 18.5 30.5 27.9 22.4 24.1 178.0 1958 14.4 22.7 4.5 8.0 2.5 3.1 7.0 19.6 31.1 23.3 23.7 16.0 175.9 1959 32.8 13.1 6.8 2.9 2.5 3.9 4.6 17.1 37.1 37.2 28.8 17.8 204.6 1960 16.6 11.1 6.7 3.0 3.7 2.9 5.7 22.9 30.7 38.0 23.5 28.5 193.3 1961 37.5 12.2 12.0 5·2 4.0 5.3 6.4 17.6 42.0 30.9 36.2 21.4 230.7 1962 31. 7 7.2 2.8 4.6 2·5 2.3 7.2 9.6 24.3 28.0 29.6 27.6 177.4 1963 33.2 17.6 21.4 12.0 10·9 4.3 5.3 14.9 21.5 21. 7 17.3 57.7 237.8 1964 57.7 11.0 13.2 6.3 5.0 3.0 5.4 11.8 37.8 39.6 31.6 19.1 241.5 Total 531.5 263.3 134.4 86.1 60.6 58.6 87.6 309.9 574.0 602.2 502·5 526.5 3737.2 Mean 196.7 NOTE: Values prior to July 1951 are correlated. Table 9--Co~uted Inflow to Takatz Lake Drainage Area: 10.6 Square Miles Units: 1,000 Acre-Feet Year Oct. Nov. Dec. Jan. Feb. Mar. Apr. Hay June July Aug. Sept. Total 1946 27.8 3.6 1.7 1.5 0.8 1.1 1.3 11.0 18.3 21.6 17.7 17.4 123.8 1947 21.4 9.3 1.4 2.3 1.3 4.6 3.8 12.2 13.8 19.3 18.7 33.6 141.7 1948 17.0 7.4 2.9 4.5 1.1 0.9 1.0 11.9 18.0 26.5 19.7 31.1 142.0 1949 17.9 9.8 1.6 3.1 1.2 1.8 2.2 10.0 20.9 .9 20.2 18.8 132.4 1950 24.8 6.6 1.6 0.9 0.7 0.8 1.1 6.1 18.1 26.0 17.5 15.3 119.5 1951 10.4 1.9 0.8 1.0 0.6 O.'T 1.9 8.0 15.8 22.0 14.0 Ih.7 91.8 1952 13.1 7.2 1.6 0.6 0.6 0.5 2.h r(.5 13.7 28.3 19.0 27.6 122.1 1953 24.0 8.7 3.5 1.7 1.6 2.1 2.7 13.3 19.2 24.0 20.7 21.3 142.8 w 1954 29·5 3.9 1.5 1.1 1.0 8.5 17.5 16.2 ,p-7.2 3·5 19.3 17.9 127.1 1955 15.5 12.3 6.7 1.9 1.3 1.2 1.6 5·2 12.9 24.9 22.0 20.4 .9 1956 12.8 3.0 1.1 0.7 0.7 0.7 1.9 9.8 17.4 24.5 27.2 13.1 112.9 1957 11.9 6.6 6.4 2.0 1.1 1.0 1.9 10.8 17.8 20.5 16.5 .7 114.2 1958 10.6 11.3 2.2 4.0 1.2 1.5 3.5 11.4 18.1 17.1 17.4 11.8 110.1 1959 24.1 6.5 3.4 1.4 1.2 1.9 2.3 9.9 2L6 27.4 21.2 13.1 134.0 1960 12.2 5.5 3.3 1.5 1.8 1.4 2.8 13.3 17.9 26.9 17.3 21.0 124.9 1961 27.6 6.1 6.0 2.6 2.0 2.6 3.2 10.2 24.4 22.7 26.6 15.7 149.7 1962 23.3 3.6 1.4 2.3 1.2 1.1 3.6 5.6 Ih.l 20.6 21.8 21.3 119.9 1963 24.4 8.7 10.6 6.0 5.4 2.1 2.6 8.7 12.5 15.9 12.7 42.5 .1 1964 42.4 5·5 6.6 3.1 2.5 1.5 2.7 0.9 22.0 29.1 23.2 14.0 159·5 (f) .735 .497 .497 .497 .l~97 .497 .497 .582 .582 .735 .735 .735 Total 390.7 130.8 66.7 42.6 29.8 28.6 43.5 180.3 334.0 1+1+1.5 3()9.6 388.3 2446.4 Mean 20.6 6.9 3·5 2.2+ 1.6-1.5 2.3 9.5 17.6 23.2 19. 20.5-128.8 Percent 16.0 5.4 2.7 1.'( 1.2 1.2 1.8 7.4 13.6 18.0 15.1 15.9 100.0 Department of Natural Resources, a water right application for the Takatz Creek Project was filed with that Department in the name of the United States Government on May 19, 1967. In turn, permit No. 16 was issued July 5, 1967 to appropriate the entire outflow from Takatz Lake for the generation of power. In addition, Federal Power Commission Power Site Classification Order No. PSC221, dated May 14, 1929, reserves the Takatz Creek dam and reservoir sites for power generation. Reservoir Data Area1.ud Capacity Area and Capacity curves for Takatz Lake were prepared from reservoir topography obtained by the Geological Survey. The curves are presented as Drawing 1113-906-14. Normal maximum and minimum reservoir elevations are 1,040 and 900 feet, respectively. Active conservation capacity of 82,400 acre-feet would be developed between these elevations. The invert of the power tunnel intake would be at elevation 880 feet, which reflects a 2O-foot allowance for ice cover and minimum head on the intake structure. Inactive capacity between elevation 880 and 900 feet would be 7,400 acre-feet. Sediment There are no sediment data available for Takatz Creek, so evalu- ation of possible sediment deposition in Takatz Lake was based on field observations and comparison with sediment studies for other Alaska streams. From the observations and the comparisons, it is concluded that lOO-year sediment accumulation will be less than five percent of the planned active reservoir capacity and that a reservoir allocation for sediment would not be required. Sedimentation is not a factor in location of the outlet works and the power tunnel intake structure. Reservoir Losses Geological investigations of the reservoir lead to the conclusion that seepage will be no problem. Evaporation records in Southeast Alaska are not available, but the normal high relative humidity, high percentage of overcast days, and relatively cool climate preclude any appreciable water loss through evaporation. Estimates of water supply are based on records of Takatz Creek at the gaging station, and this record would reflect any past evaporation from Takatz Lake. For these reasons, reservoir losses may be termed negligible. 35 SURFACE, AREA, ACRES 1000 900 800 700 600 500 400 300 200 1000 .J en ::E w > 0 CO cr: .... 900 w W 1.1. ~ ~ cr: > w .... w 800 20 40 60 80 100 120 140 160 180 RESERVOIR CAPACITY, 1000 ACRE.·FEET Revised January 17, 1968 ELEV. AREA CAPACITY ( Feet) (Acres) ( Ac.-Ft.) 700 243 0 740 281. 10,400 780 304 22,100 820 336 34,900 860 357 48,700 900 378 63,400 905 403 65,400 940 535 82,200 980 612 105,200 1020 703 131,400 106.0 769 160,900 1100 W348 193,200 "'- ,NOTES: 1. Data source, U. S. G. S. TO!109rapIIJ sheet Takah Creek, Alaska, 1957. 2. Capacity bel_ Elev. 700 not _termined. UNITED STATES DEPARTMENT OF THE INTERIOR ALASKA POWER ADMINISTRATION TAKATZ CREEK PROJECT AREA· CAPACITY DATA September .15, 1967 1113-906-14 Power Studies The project was sized using a series of adverse year power studies to determine firm energy capabilities, and shortcut methods for estima- ting secondary energy. Subsequently, the Corps of Engineers, Alaska District Office, as part of its review of the project plans, prepared operation studies for the selected plan and for several alternate plans, using the Corps' computer program No. 24159, "Hydropower Capacity and Regulation -Planning Stage Analysis". These computer analyses provide complete monthly operation studies for the selected study period and were utilized in the project evaluations summarized in this report. Operating Assumptions The normal maximum and minimum reservoir levels would be 1,040 and 900 feet, respectively. The elevation of the turbine discharge nozzles would be 16.7 feet. This would allow for a free flOwing tailrace dis- charge at maximum high tide in Takatz Bay. Thus, the gross head range would be 1,023.3 to 883.3 feet. Combined tunnel and penstock losses were found to average less than one percent of the gross head. Load Characteristics. It is expected that Sitka's future load growth will follow a pattern similar to that of the larger Southeast Alaska cities. Load distribution data adopted for the power studies, Table 10, are based on experienced Ketchikan area loads. Weekly load distribution data from recent experiences in Juneau were also examined. The annual load factor of 55 percent is representative for both areas. The weekly load factors (64 to 68 percent) based on the Juneau hourly data fall within range of the monthly load factors derived using the Ketchikan data. The hourly data show a base load component of 40 percent of peak. The energy during the off-peak hours is a little over 15 percent of total energy. Table 10-~onthly Load Distribution Data Monthly Energy, Monthly Peak, Month ~ of Annual ~ of Annual January 9.0 96 February 8.1 89 March 8.4 87 April 7.9 82 May 7.8 81 June 7.4 77 July 7.6 78 August 7.9 eo September 8.3 eo October 8.9 86 November 9.0 95 December 9.7 100 Annual 100.0 37 Load Factor Percent 60 65 62 65 62 65 63 64 70 68 63 63 55 Efficiencies. The hydraulic and mechanical efficiencies used in the computer studies are expressed as functions of gross head and then combined into a single head versus efficiency relationship. The result- ant overall efficiency varies from about 83.5 to 84.5 percent. Power Operation Study The reservoir and power operation study included the water years 1946 through 1964 and assumed a full reservoir at the start of the period. The entire Takatz Lake inflow would be available for power diversions, as there is no requirement for maintaining a live stream below Takatz Creek Dam. The operation study shows the Takatz Creek Project has an annual firm capability of 97,100,000 kilowatt-hours. In addition, there is an average of 9,800,000 kilowatt-hours of secondary generation each year. The reservoir filled 14 years of the 19-year study, with spills occurring in 9 years. The study is illustrated graphically on Drawing 1113-906-24, and the annual sun:mlB.ry is shown as Table 11. Power Capac! ty The powerplant capacity must be at least large enough for the project to carry a proportionate share of the peak load. Using the average firm generation of 97,100,000 kilowatt-hours per year, and the area annual load factor of 55 percent, a minimum rated capacity of 20,000 kilowatts will be required for the Takatz Creek Powerplant. Overload capacity of 15 percent, or 3,000 kilowatts, would be the project's contribution to system reserve capacity. 40 S pi" s-... ~ -+------+------lRe S e rvoi r I nf low 1000 A. F ---t--------t-------i---+----+----+--- 160 r-----~-----r----~----~------~----~----_r----~----~~----~----~--~----~----~---~----~----~----~----~ 150 Elev. 1040 Content 140~--+-~--~~--~ I Top of Conservation Capacity -~~~ ~ r-~~ ----+---+-- 145 800 A. F. ___ L ________ _ 130 110 100....-----+--+-------+---.-.. -···-++---+-+---+-----a---,I---t--t---/---+---··-+~-~--+---\-4 90 80+-------+--------1 70 -----------... 60~----~----~----~----~----~----~----~----~----~----~----~----~----~----~----~----~----~----~--~ Generation-KWhr 0 6 10 ~----.------r-----.----~------r-----~--~~~~~~~~~--~r-~~~----~-----.----.---,.----,-----,------r-----, 5+--- o 1946 1947 1954 1955 1956 1957 1958 1960 1963 CALENDAR YEARS Revised: JANUARY 17 1968 SEPTEM9ER 19 1967 NOTE: Operation study by Corps , of Engineers program nu m ber 24159. "Hydroprower Capacity and Regulation-Planning Stage Ana lysis. II UNITED STATES DEPARTMENT OF THE INTERIOR ALASKA POWER ADMINISTRATION TAKATZ CREEK PROJECT,ALASKA RESERVOIR AND POWER OPERATION 1113-906-24 Year 194G 1947 1948 1949 1950 1951 1952 1953 1954 1955 1956 1957 1958 1959 1960 1961 1962 1963 196t~ Hescrvoir Ele',ntions Feet (HSL) Maximum :'1iniJrluIn Average 1, 0!~0.00 1,040.00 1,040.00 1,040.00 1,020.40 S)9C .• OO 1,01 5. )~o 1,040.00 1)040.00 1,040.00 l,03(). 1,039.03 1, 01.~0.00 1,040.00 1,040.00 1, OL~O.OO l,G40.00 l,OIW.OO 1,040.00 986.1+] 988.01 979. 983.07 963.37 940.33 900.30 950. O~0 .,./ i,/. 981.9B 901.35 91"(. 980.25 977.38 97G.1t8 9EYr.71:- 965.18 1,008.65 982.59 1,01C.'(2 1,01 5.77 1,01 5. 1, 01,~. 1,000.97 973.17 955.2h 99(';.37 011.88 1,011!-. 1,001. 92 1,011. 52 1,01 5.37 1,013.60 1,013.32 1 01b.c::i+ , ,/ 1,003.04 1,026.58 1,017.03 Average 1,040.00 Avero{(c Head (Feet) 1,002.01 999.10 999.20 999.90 98h.30 .1~5 932.;';2 979. ,S5 995·17 998.15 985.20 994. [V!, 998.65 996.92 996.63 1,001.91 986.33 1,009.91 l,OOO.3 h 990. Ener,:;J ? IGlH x lC,..J 97,099.3 97,099.3 9",380 .2 9'(,099.3 97,099.3 97,099.3 97,3 GO .2 97,099.3 C)7 noo -:: .r ; , --' ",,',. • ..,./ 97, '099. 3 97,3 80.2 97,099.3 97,099.3 97,099.3 97,380 .2 97,099.3 97,099.3 97,099.3 97,3 80 •2 ,170 .0 rO',-er KF 11, GT) 11,0"(9 11,Osn 11,()79 Sec ')ndar~; Er~erfS,;' K'i{H x 1 () o o e,58~.r.: 52Lt. '1',832. o o "", n ,-1 U, 20(,; .,~ 8,461.2 l'T,lS6.5 2],999.3 6,h8,(.7 rr, 190. 5 22,469.1 r' -i 1 ·1 '-'.1:'--- Ac.Ft. o o o 108 o o o o () 1:,17[' r u, o 43,131 13, 5,532 CHAPTER V--DEVELOPMENT PLANS AND COSTS The plan of development provides for the construction of a single- purpose project for the production of electrical energy. Major features of the project include the main dam, a saddle dam, tunnel, penstock, powerplant, transmission line, unloading dock, and access road. These features are shown on Drawing No. 1113-906-11. The plan also includes the investigation for possible archeological and historical values prior to construction. GeoloE'jl A feasibility-grade geological investigation of the dam, reservoir, tunnel, and powerplant sites was made by the Bureau of Reclamation and a geological report prepared summarizing their findings. These investi- gations included surface reconnaissance as well as foundation explorations by core drilling. The report is summarized as follows: General The east coast of Baranof Island is characterized by east-trending deeply glaciated valleys, whose lower parts usually form narrow embay- ments connected to tidewater. The upper part of the valleys are often occupied by deep lakes, such as Takatz Lake. Takatz Creek Damsite Bedrock at the damsite consists of a light gray medium-to-coarse grained biotite quartz-diorite intrusive rock. The intrusive rock is very hard, competent, massive and mostly equigranular. The right abutment consists of a rounded knob of intrusive rock. The upstream relatively gentle slope from which the ice thrust came contrasts sharply with the steeper near vertical ice-plucked slope on the downstream side. The lake outlet stream channel occupies a narrow talus-filled valley between the massive steep-walled abutment slopes. The stream channel ranges in width from 35 to 55 feet and is armored with talus boulders. Two exploration drill boles revealed talus rock with voids partially filled to filled with silty fine sand, to depth of 25 feet, underlain by glacial fluvial silty fine sand to depth of qo and 52 feet. The diorite bedrock core obtained fram the two exploration drill holes was excellent rock. Significant gneissic inclusions were encountered in each hole, but the gneissic rock was of the same hard, competent quality 41 as the surrounding diorite. Jointing was evident in both holes with only slight indications of weathering and same minor slickensiding noted along joint planes. Water testing indicated tight conditions in the bedrock, with no water losses occurring during 5~nute tests under pressures of 50 and 100 pounds per square inch. The left abutment area is covered by a thin soil cover with a thick, heavy brush, spruce and hemlock tree growth. Small outcrops of bedrock occur and an outcrop approximately 50 feet wide occurs at stream level immediately above the sharp eastward trending bend of the outlet stream. The exploration program was aligned across the valley section of the outlet channel to intercept this visible bedrock outcrop along the toe of left abutment slope. This alignment represents the narrowest topographic section between abutments. Examination of high altitude aerial photographs of the Takatz Lake area reveal numerous lineal features that are initially interpreted as fault scarps. Field inspection, however, reveals that these lineal features are ice scoured joint sets. Occasional semidetached weakly conchoidal rock slabs are evident on the massive right abutment slope. No indications of major faulting were observed. Two linear features passing through the damsite suggest the possi- bility of faulting. Above the sharp bend in the outlet stream, the lineations follow a shallow saddle cut in bedrock along the right abut- ment. The lineations can be traced across the stream at the bend into a deep narrow draw that represents an abandoned stream channel now filled with large angular talus blocks, but evidence of crushing, shearing, or other major movement was not found. On the basis of the exploration drill hole water tests, showing no water losses, and the absence of spring flows from occasional bedrock exposures observed along the north end of the abandoned channel course, it is concluded that little or no reservoir seepage loss will occur along the tight jOints passing through and essentially normal to the dam axis along the abandoned channel alignment. Saddle Damsite A prominent talus-filled saddle separates the right abutment from the high steep main valley wall. This saddle is part of a linear feature developed by glacial ice scour along the joint set. Damsite topography indicates the crest elevation of this saddle at an altitude of 1,020:. This saddle is also interpreted to be a former high level lake outlet. A small embayment re-entrant 500 feet upstream from Takatz Lake outlet 42 is connected to the saddle by a small valley. A small lake wi. th water surface elevation of 985 occurs at head of this valley. Sound competent diorite bedrock is e~osed as a sill across the small lake outlet between the saddl.e and Takatz Lake embayment. For a reservoir having a water surface elevation above 990 feet, an auxiliary dam is required to prevent reservoir water from passing through the talus-filled saddle. Takatz Lake The reservoir site is a deep glacially scoured rock basin enclosed, except at the lake outlet, by high mountains composed of hard, competent, impermeable, granitic-type rock. The lower slopes along Takatz Lake shoreline are partially covered by talus deposits up to an average ele- vation of 1,lIOo to 1,500 feet. Above this, the valley walls are steep to near vertical cliffs. At the upper end of the lake, the valley floor is a flat delta deposit of fluvioglacial sand, gravel, and cobbles. Along that part of the lake shore not covered by talus, bedrock is pre- dOminantly a medium-grained biotite quartz-d1orite. An examination of the large glacial cirque basin northwest of the ridge forming the left abutment at the damsite was made to determine if any significant seepage through open joint systems existed. The eleva- tion of the cirque basin floor was estimated to be 225 feet below the water surface of Takatz Lake. Considering the negative water test results e~erienced during damsite e~loration drilling, and the negli- gible observed streamflow from the cirque baSin, it was concluded that the raiSing of Takatz Lake would not develop any significant seepage through the existing, apparently tight joint systems. Rockslides into the reservoir could be a serious problem, but there appear to be no potential slides 'Which would pose threats to the two dams. However, potential massive slides into the upper reservoir basin will re- quire dam design considerations relative to overtopping wave action. TUnnel The proposed tunnel alignment would pass near the saddl.e through the right abutment. The alignment penetrates sound diorite rock similar to that at the damsi te. Some water seepage from joint systems can be anticipated during tunnel boring, but the tight nature of joint systems encountered during the foundation e~lorations indicates this should be of minor nature. Takatz Creek Powerplant The powerplant would be situated on a relatively steep forested slope covered by large angular talus blocks. Core drilling at the site indicated 16 feet of talus partially filled to filled with silty fine sand. Hard, competent, medium-to-coarse grain, biotite quartz-diorite bedrock was found at a depth of about 16 feet. Penstock The surface penstock would traverse a near vertical diorite cliff, with the lower portion in the shallow talus-covered slope. Bedrock is the same as that found at the powerplant site. Transmission Line At elevations below 1,500 feet, the line would traverse heavily wooded areas, with occasional stretches of muskeg and other swampy ground. In these areas it is believed that secure foundations can be found within a reasonable depth. Above elevation 1,500 feet, competent rock is generally exposed. Concrete Aggregate Adequate quantities of concrete aggregate can be obtained from the glacial fluvial delta deposit of sand, gravel, and cobbles at the head of Takatz Lake. An alternate source would be by crushing the abundant supply of large fresh angular talus blocks filling the saddle behind the right abutment area at the damsite. Design and Construction Problems Other than the design and construction problems associated with the relatively remote location of the project site, no unusual problems are anticipated~ Although the dam and powerplant sites are only 21 miles east of Sitka, they are inaccessible except by air or water as there are no roads in the area. By water, they are about 85 miles from Sitka and 95 miles from Juneau. It would be impracticable to construct an access road from Sitka. Both Sitka and the project site are on Baranof Island, but the intervening terrain is steep mountain slopes cut by many fiords, bays and inlets, and mountain passes are steep and subject to heavy snowfall. Project Works The locations and details of the proposed project works are indicated on Drawings 1113-9J6-ll, 1113-9J6.12, and 1113-9J6-l3. Project works are described as follows: 44 ACCESS ROAD ~, Mox.W.S. EI. 1048-,\ Nor. W.S. EI. 1040~, i t _ /~-Min. W.S . EI. 900 / EI. 884 INTAKE STRUCTURE- Sla.I+60 S to. 4 +75 EI. 1057 GATE STRUCTURE TAKATZ CREEK DAM -) Natural W. S . EI. 90' , ...... ",' PROFILE THROUGH WATERWAYS / 100 0 100 200 300 ..... ' ~-'-'...o~,,--__ -,, ___ ~, ___ , SCALE OF FEET ACCESS ROAD -~ • ,J USGS Gaging ... Stollon ":.}'!)\:"':':"': . ".""..", ,,/;-\:;<' PENSTOCK -.--'--- #~ ... , .. , , I /'\ GOVERNMENT CAMP- ,// \. SURGE TANK ,/'/--POWER TUNNEL /'-/ " -------GATE STRUCTURE "\., "-SADOLE DAM 1000 I 0" I PLAN 1000 2000 3000 , , SCALE OF FEET . .. /;;) ~ .. ' S to. 35 +00 __ -SURGE TANK DOCK-, I : ACCESS ( / , \, _/'----PENSTOCK \ . ANCHORS)-_ ',,- \, LEGEND , /_POWERPLANT Max. operating T.W. EI. 11.2-, ...,.r-j //// ;,;/;0 Nonnal W. S. EI. 1040, prapa.ed Takcltz Creek Ret.volr. UNITED STATES DEPARTMENT OF THE INTERIOR ALASKA P.QWER ADMINISTRATION TAKATZ CREEK PROJ ECT-ALASKA TAKATZ CREEK WORKS PLAN AND SEPTEMBER 15, 1967 PRO FI L E 1113-906 -12 Takatz Creek. Dam The Takatz Creek Dam would be a double curvature, thin-arch, con- crete structure about 250 feet downstream from the lake outlet. It would have a maximum height of 205 feet above the lowest foundation excavation and a crest length of 520 feet. The crest would be at ele- vation 1,048 feet, and the top of parapet at elevation 1,052. The thickness at the base on the plane of centers would be 17 feet, and the thickness at the crest seven feet. An ungated spillway would be located at the center of the dam with crest elevation at 1,040 feet. It would have a capacity of 6,800 cubic feet per second at maximum water surface elevation of 1,048 feet, and would protect against the inflow design flood of 8,900 cubic feet per second and a 4-day volume of 20,100 acre-feet. With a plunge pool formed by a natural rock barrier downstream from the dam, a stilling basin for spillway discharge would not be necessary. An outlet works would be provided at elevation 898 feet. It would consist of a trashrack on the upstream face of the dam, two 4-foot by 4-foot conduits through the dam, and 4-foot by 4-foot gates in a gate- house on the downstream face of the dam. Two gates would be provided for each conduit. The downstream gate would be for regulation, and the upstream gate for emergency closure. Access to the gatehouse would be provided by a metal walkway on the downstream face of the dam. The outlets would have a capacity of 710 cubic feet per second at water surface elevation of 910 feet. The outlet works would be used to evacuate the reservoir for maintenance work at the power intake structure, as bypassing water into the creek would not be required. Saddle Dam The saddle dam would be approximately 900 feet south of Takatz Creek. Dam. It would be a double curvature, thin concrete arch structure with crest elevation at 1,048 feet and top of the parapet at elevation 1,052 feet. It would have a maximum height of 63 feet above the lowest foundation excavation and a crest length of 350 feet. The thickness at the base on the plane of centers would be ten feet and the thickness at the top would be five feet. Takatz Lake When full to top of active conservation storage at water surface elevation of 1,040 feet, Takatz Lake would have an area of 736 acres, an increase of 333 acres over that of the present Takatz Lake water surface. This area is mostly bare rock, and vegetation is limited to a minor amount of brush in the valley floor above the lake and some trees near the damsite. The total reservoir capacity of 145,800 acre-feet above elevation 700 feet is allocated as follows: Purpose Surcharge Active Conservation Dead and Inactive Elevation 1040-1048 ~-1040 700-~ Total reservoir capacity Capacity Acre-Feet 5,~ 82,400 63,400 1 45,800 The depth of the present Takatz Lake, with water surface elevation at 905 feet, is 475 feet, and the elevation of the center line of the outlet is 902 feet. Diversion Tunnel A 12-foot diameter, unlined diversion tunnel, 425 feet long, located in the right abutment, would carry streamflows past the damsite during construction. The invert at the entrance to the tunnel would be at eleva- tion 870 feet. The tunnel would pass a 5-year frequency flood having a peak flow of 3,160 cubic feet per second. A concrete closure structure would be located at the intake of the tunnel with provisions for stop- logging when diversion is completed. Permanent closure of the tunnel would be by a concrete plug located near the axis of the dam. Intake Structure The intake for the tunnel would be located 100 feet south of Takatz Creek Dam. It would be a concrete, box-type structure, having an invert elevation of 879 feet. An approach channel 40 feet in width and about 165 feet in length would be required. Tunnel The power tunnel would be located in the right abutment and would have a capacity of 328 cubic feet per second at rated head. Its total length would be 3,860 feet. This would include an 8-foot diameter, concrete-lined section 3,575 feet in length, and 285-foot long section with a 66-inch diameter steel penstock imbedded in concrete. 48 Gate Shaft A gate shaft with a 6-foot by 8-foot roller-mounted emergency gate and bulkhead service gate would be located 315 feet down the tunnel fram the intake structure. The shaft would be 15 feet in diameter and con- crete lined. It would be about 190 feet in height above the tunnel invert and would surface near the left abutment of the saddle dam and adjacent to the access road. Surge Tank The 8-foot diameter concrete-lined surge tank would be embedded in the rock of the mountain 480 feet up-tunnel from the beginning of the exposed penstock. The top would be at elevation 1,055. The tank would contain normal regulating surges, but water would surge over the top with emergency shutdowns of the units. Water spilling from the surge t8nk ,-'ould flow into Takatz Bay via a small stream southeast of the powf'':'plant. Penstock The 66-inch steel penstock would be exposed its entire length of 1,010 feet. Concrete anchors would tie the penstock to the rock slope of the mountain. Before entering the powerplant, it would bifurcate into two sections, each 3-1/2 feet in diameter. Takatz Creek powerplant The powerplant would be of the indoor type with insulated metal superstructure walls. It would contain two units each having a capacity of 10,000 kilowatts operating at an average annual plant factor of 55 percent. The two vertical shaft impulse turbines would each have four jets, rated at 14,000 horsepower at design head of 886 feet, and have a speed of 400 revolutions per minute at a discharge of 164 cubic feet per second. The 10,OOO-kilowatt synchronous generators would be 3-phase, 0.9 power factor, and have a generator voltage of 6,900 volts. The powerplant would be operated by remote control fram Sitka. Switchyard The swi tchyard would be placed on the roof of the powerplant. The two power transformers would be 3-phase, l2,800.kilovolt ampere, 115 grounded Y/66.4-6.6 kilovolt. There would be one Switching bay, 115,000- volt, with two horn-gap disconnect switches and one 2-pole automatic high speed grounding switch. Transmission Line The transmission line would be a 115,OOO-volt line with 397.5 MCM ACSR conductors. Overhead ground wires would not be required. It would include 26 miles of Type H wood-pole construction, and two miles of steel-tower construction over the Blue Lake Pass. The steel tower section would have one set of self-supporting towers for each phase. The towers would be 170 feet in height, have a 75-foot spacing between phases, with spans up to 3tOOO feet. The line would cross through the pass at about elevation 2,~50 feet. The 75-foot right-of-way would be throqgh fairly heavy forested area for the entire length of the wood-pole section, and clearing would be required. The commercial timber would be sold by the Forest Service and transported to tidewater over the transmission line construction road. If the timber cannot be sold in this manner, it would be covered by timber settlement procedures. The route of the transmission line would be so located to avoid to the extent possible all existing and potential outdoor recreation areas. Sitka Substation The Sitka Substation would transform the transmission voltage down to 12,500 volts for delivery to the Sitka Public Utilities. The two power transformers would be 3-phase, 11,OOO-kilovolt amperes, 110-12.5 grounded Y/7.2 kilovolts. There would be one 115,OOO-volt switching bay with two horn-gap disconnect switches and one 2-pole automatic high speed grounding switch. A 12,500-volt switching bay with two horn-gap disconnect switches would also be provided. In addition, there would be a 12,500-volt line bay with a 5OO~egavolt ampere oil circuit breaker. Dock and Seaplane Float A deep-water dock and seaplane float would be constructed in a small bay directly south of Takatz Bay. The dock would be about '3J feet wide and 250 feet in length and of timber construction. A ramp would be provided with the seaplane float to allow for the fluctuating tide. Access Road Access from the dock to the powerplant would be via a 24-foot wide crushed rock surface road approximately 1.6 miles long. A 2O-foot wide crushed rock surface road continues from near the powerplant to Takatz Creek Dam, a distance of approximntely 2.2 miles. This road would pass by the saddle dan and the gate shaft. The plan contemplates that access to the damsites and gate shaft in winter would be by helicopter or snow mobile. Government Camp Under a remote-controlled operation, only two permanent residences would be required. During the construction phase temporary facilities would be provided for 70 government employees. A permanent warehouse and garage, as well a s complete water and sewer systems, would be provided. Temporary facilities include dOrmitories, mess hall, and administration building. These facilities would be located near the powerplant. Fish and Wildlife Facilities The Bureau of Commercial Fisheries has ascertained that construction and operation of the project would not affect significantly the fish and wildlife resources of the area and that the project would not offer feasible opportunities for the improvement of these resources. Therefore, facilities for fish and wildlife are not proposed in the project plan. Recreation Facilities The existing Takatz Lake does not receive any significant recreational use, and there is little likelihood that the project would appreciably . change the recreational potential; therefore, no specific recreational facilities are proposed. Right-of-Way and Relocations All project facilities and most of the transmission line right-of- way are on lands of the Forest Service. Prior to construction, the public lands required would be withdrawn. The last two miles of the transmission line and the Sitka SUbstation are on private lands. Along the transmission line route there exists; 1. Townsite elimination of 9.46 acres at Baranof. 2. Warm Springs Packing Company site of 5.75 acres at Baranof. 3. Fred Bahovec homesite of 1.13 acres at Baranof. 4. Alaska Lumber and Pulp Company lands at Sawmill Creek. 5. Power transmission line past Heart and Thimbleberry Lakes, covered by FPC License No. 2230. 51 6. Sitka elimination, which has its eastern boundary near Thimbleberry Lake. These areas will be avoided to the extent practical, but it will be necessary to obtain easements or acquire right-of-way for required areas outside of the National Forest. The construction of the Takatz Creek Project would not require the relocation of any existing facilities. Plan Formulation The plan of' development presented in this report evolved through careful consideration of alternative development schemes, including review of the most favorable hydroelectric alternatives, and economic evaluations of various sized Takatz Creek Projects. After a careful review of' the available alternatives, it was concluded that the pro- posed Takatz Creek Project represents the most desirable plan for satisfying the forecast project power requirements. Economic Criteria for Plan Formulation The plan formulation followed economic guidelines provided in S.D. 97, 87th Congress, 2nd Session. The comparative power values used for plan formulation assume Federal financing with interest at 3.250 percent for both the project and the alternative power sources. The cost estimates were based on July 1967 prices. Economic costs for the project and for the alternative sources were compared over a 100-year period. A comparison of the estimated costs of the Takatz Creek Project and the most favorable hydroelectric alternatives is presented in Table 12. In order to provide a conservative appraisal of the relative merit of the Takatz Creek Project, and in light of the reconnaissance data on which the designs of the hydroelectric alternatives were based, the costs of such alternatives were estimated so as to represent reasonable appraisals of their minimal probable development costs. Hydroelectric Alternatives Maksoutof River Project. This project would be about 40 airline miles southeast of Sitka, and have an installed capacity of 24,400 kilowatts at 55 percent plant factor. It would reqUire a 64-mile transmission line that would be constructed below elevation 1,000 feet, 52 Table 12--Summary of Hydroelectric Alternatives Item Installed Capacity, kw Firm Energy Sales, Mw-Hr/Yr Construction Costs, $1,000 Dams Waterways Powerplant Access Roads Transmission System Government Camp Total Interest During Construction Investment Cost Less Pre-Authorization Costs Economic Cost Takatz Creek Project 20,000 93,200 $ 5,640 4,670 4,100 3,600 3,9&:> 1,55X) $23,5&:> $25,202 Green Lake Project 10,700 49,700 $ 6,770 2,160 2,5&:> 2,65X) 1,200 320 $15,7JJ 102 150 $16,8&:> $16,8&:> Economic Comparison, lOO-Year Period, 3-1/4 Percent Interest Annual Costs, $1,000 Equivalent Capital Costs 854 572 OM&R & Administration 185 105 subtotal 1,039 677 Less Secondary Energy Sales -34 -21 Net to be repaid 1,005 65b Equivalent Annual Firm Energy Sales, Mw-Hr &:>,&:>0 46,500 Rate for Firm Energy Mills per kw-hr 12.4 14.1 53 Maksoutof River Project 24,400 110,000 $ 4,220 4,060 4,940 3,5&:> 7,7'3) 1 2 6'3) $ 26,160 1,2920 $ 28,0&:> $ 28,0&:> 947 243 1,15X) -16 1,174 93,000 12.6 and include five major water crossings. Designs and estimates were based upon a field reconnaissance of the site in June 1967, Geological Survey l-inch equals l-mile, lOO-foot contour quadrangle sheets, and detailed topography surveyed in the summer of 1967 by the U,S, Geolog- ical Survey. These designs and estimates indicate that the unit costs of firm energy delivered to the Sitka area to satisfy the forecast power requirements would average about 12.6 mills per kilowatt-hour. This cost is 0.2 mill higher than the estimated 12.4 mill per kilowatt- hour cost of the Takatz Creek Project presented in Table 12. The maxi- mum transmission line elevation of about 1,000 feet for this alternative is more favorable from the standpoint of wind and ice effects on system reliability than the Takatz Creek Project transmission line crossing of Blue Lake Pass at elevation 2,850 feet. However, the Maksoutof River Project transmission line would be more than twice as long as the Takatz Creek Project line and would involve major problems of maintenance and emergency access due to general need to traverse the open ocean in order to reach the five major water crossings. Also, development of a firm plan for this alternative would require extensive additional investiga- tions, including drilling of the dam and powerplant sites. Thus, the Maksoutof River Project appears less desirable than the Takatz Creek Project for immediate development, but it could be an appropriate subsequent development. Green Lake Project. This project would be about 10 miles southeast of Sitka and would have an installed capacity of 10,700 kilowatts with 55 percent plant factor. Designs and estimates based upon the available near-feasibility grade topography indicate that the unit costs of power delivered to the Sitka area would average about 14.1 mills per kilowatt- hour. On this basis, this project is not an attractive alternative to the Takatz Creek Project. However, about two mills of the estimated unit power costs represent an access road to the project site from near Herring Cove, which conceivably could be built in the near future for other purposes. Thus, this project might subsequently merit considera- tion to meet Sitka area power demands after full loading of the TSkatz Creek Project is achieved. Also, it would merit fUrther consideration in any future planning for the MBksoutof River Project in that the transmission line for the Maksoutof River Project would pass by the Green Lake Project powerplant site. Diesel-Electric Alternative In the absence of Federal construction of the Takatz Creek Project, the most likely alternative power source would be diesel-electric units located in Sitka. Fuels other than diesel oil are considered non- competitive because of transportation costs. Cost estimates for diesel-electric units as an alternative to the Takatz Creek Project were based on a 19,200.kilowatt plant having an 54 annual firm generation of 93,200,000 kilowatt-hours when fully loaded. This is equivalent to the Takatz Creek Project firm capability, less one percent for station service and three percent for transmission losses. The estimates assume that the plant would be constructed in two stages, with 9,600 kilowatts installed in each stage. With fiscal year 1976 considered as the first full year of operation of the Takatz Creek Project, the first unit would be installed by that time, and the second unit would be in operation at the beginning of fiscal year 1980. The construction cost for such a plant was estimated to be $3,565,000 for the first stage and $2,065,000 for the second stage. The average cost of fuel delivered to Sitka was considered to be $0.09 per gallon, with an average energy value of 14.0 kilowatt-hours per gallon. The low fuel cost assumed utility-owned fuel storage facilities, no escalation of fuel costs, and use of about 80 percent PS-300 Bunker oil and 20 percent PS-200 light oil. The operation, maintenance and replacement costs, including admini- stration and maintenance of fuel storage facilities, were estimated at 3.99 mills per kilowatt-hour on the basis of recent experience values in the Juneau area. The alternative firm energy costs used in the plan formulation studies were based on the costs of a hypothetical Federally-financed diesel-electric plant in accordance with established procedures for project analysis. The unit firm power costs determined on this basis assumed a usefUl life of 35 years for each unit, 55 percent load factor operation, and interest at 3-1/4 percent. They were estimated to average 14.0 mills per kilowatt-hour over the lOO-year period of analysis. Analyses of Reservoir Capacity and Project Size Table 13 summarizes seven analyses of the effects of variation of the height of Takatz Creek dam and reservoir drawdown. The project costs presented in the table are based on the designs and estimates for the selected project plan. The comparative power values are based on the forecast project energy requirements, the computed 14.0 mill firm energy costs of the hypothetical Federally-financed diesel-electric alternative, and a value of 6.0 mills per kilowatt-hour for non-firm energy. The latter value is slightly less than the computed fuel costs of the diesel-electric alternative. The power value estimates include allowances for line losses and load growth. They assume that the plants would be in service at the beginning of fiscal year 1976. They also assume the requirements for secondary energy will increase at the rate of one million kilowatt-hours per year beginning the second year after fUll utilization of firm energy. 55 VI 0\ Table 13--Summary of Analyses of Re~:ervoir Capacity and Project Size Controlled Reservoir Project Costs Elevation Installed Ultimate Generation (~lzOOO) Comparative Power Value Plan {feet} Capacity (kwh x 106 ) 2/ Average ($lzOOO) Max. Min. (k~T Firm Secondary Investment_ Annual 31 Firm Secondary Total -- 1 1,060 9)0 21,400 103.2 5.5 27,080 1,093 1,193 20 1,21 3 1/ 2 -1,040 9)0 2),000 97.1 9.8 25,300 1,032 1,131 34 1,165 3 1,040 860 21,2)0 102.3 5.6 26,360 1,067 1,18 3 21 1,204 4 99) 9)0 17,000 81.8 16.3 22,410 932 977 53 1,030 5 99) 860 18,000 86.5 12.5 23,100 956 1,025 43 1,068 6 99) 830 18,500 89.2 10.8 23,970 98 5 1,053 38 1,091 7 9)5 730 15,750 75.9 12.0 20 880 , 879 916 43 959 f7 Selected plan. Y Includes interest at 3.2 50 percent on construction costs .. lith 3-year preconstruction period and 4-year construction period. 4/ Comparative Power Value- Cost Ratio 1.110 1.129 1.128 1.105 1.117 1.108 1.091 11 Includes operation, maintenance and replacement costs based on G'peration by Sitka Pu.hlic Utilities. Computed on basis of interest at 3.250 and 100-year period. ~ Based on firm energy at 14.0 mills per kwh and secondary energy at 6.0 mills per kwh. These: analyses confirm that, on the basis of the (:stimated project cost~; and comparative POVIET values, a project with a maximum controlled 'vater surface at elevation 1,01+0 would have the most favorable povler value-cost ratio. Comparison of Plans 1, 2 and 3 indicate that selected plnn reasonably represents optimum development of the site potentials, but the pr<2construction investigations might properly include further con:..;idcl'ation of modif;ying the selected plan to provide for controlled reservoir rc;lcases for power production with pool levels lower than elevation 900. Plan 1 is considered to represent essentially full development of the Takatz Creek damsite. Plans Lt, 5 and 6 represent the maximum con- trolled reservoir elevations practicable without the Saddle Dam. Plan 7 represents reasonably optimum development without the Takatz Creek D&~. Computntions of the average firm power rates required for each plan established that Plans 2 and 3 are also the most favorable from that standpoint. Other Analyses In addition to the plan formulation considerations described pre- viously, comparative studies were made of alternatives to the tunnel, surge tank, penstock, powerplant, and transmission lines included in the plan of development. The tunnel, surge tank, penstock, and powerplant locations were selected so as to minimize length and construction costs of the water- ways. The possible alternative locations involved greater length and, in zome cases, significant snO"l and rock slide problems. 'The alternate routes were dropped from consideration upon the field determination that the selected route was free from the slide problems and entirely suitable for surface penstock and powerplant structures. Tunnel and penstock sizes were determined through comparison of incremental costs and power values. PO'vlerplant installed capacity was selected on the basis of the project firm energy potential and experienced load factors in Southeast- ern Alaska. The adopted capacity would enable the project to carry a proportionate share of the area's peak loads. The possibility of pro- viding for future enlargement of the powerplant for peaking pUl~oses was also considered. However, it was found that incremental costs for this provision would exceed the costs of providing equivalent peaking power from diesel-electric units in Sitka. The selected transmission line route takes advantage of the rela- tively low elevations and easy access of the Baranof River and Blue Lake valleys. Transmission voltage and conductor size were optimized 57 by _~ncremental economic onl11yses. Alternnti ve transmi:;sion routes ('o;l:-,lc!cred involved significantly more severe ,,,cather-related accc,;s and maintenance problems. J\cce8S facili tier; ror construction and maintcnanc0 of the project fire map location;} substantiated by field inspection. The d.ock and :;,~orlan(: :'lont were located outside of Takatz Bay to avoid the lelng "'hi~h oc'_~urr; in that bay in winter due to the fresh ;'later inflcn,!s from Ta~Flt z '~reek! RIlc1 the narrm: approach chanr:el to Takatz Bay. Cc.:m"trt,ction of the preject \\OuLi not preclude tbo;:; ul timatc con- structio:i of any of the a1 t.(;rnative 1'0',101' dcvelo::;:>mcnt,s consid('rcd. Con:>truction Costs '1'h:: construction (;O[,t::; of the prOp'X3e(t l)lan of dcvelcpm~n'~, bas,-"d et! Jill:.' 1967 prices, are estimateci to total $23,580 ,000. 'l'hey are 2U.lnr..arized on the Basic Estimate DC-l Summary. l'he cm;t of each feature inc~lucJcs its share of invc:stigations, service fadli tics, desiGns and Gpccificntiom;, and engineeri:1g and supervision. The construction costs of' the major features are sunl.'narizcd in Table 11+. Tabl',:; l4--Sununary of Construction Costs Feature TDkatz Creek and Saddle Dams POIVorplant f,cc~ss Road Transmission System Government Camp 'fotal Project !7 Includes $98,000 of pre-authorization costs. :$ 5,640,000 4,670,000 4,100,000 3,600,000 3,980,000 . 1,59=>,000 $23,520 JOOO Y Construction Schedule The project will involve no unusual construction problems, and the weather will permit year-round construction, except in the area of the dams where weather conditions will limit the work year to about eight months. In accordance with the March 1962 agreement between the Secretary of the Army and the Secretary of the Interior, the Corps of Engineers would be the construction agency for the project. It is estimated that the preconstruction and construction periods would total seven years. The first three years would be devoted to investigations, design, and the preparation of contract documents, with the first contract to be let in the fourth year. The project would be completed by the end of the seventh year, making power available at the beginning of the eighth year. The Control Schedule PF-2, at the end of this chapter, indicates the schedule of funds required each year to construct the project. Operation and Maintenance Costs It is proposed that the project be operated by remote control fram Sitka, by the Sitka Public Utilities. That utility would also be re- sponsible for all maintenance. Costs to the Federal Government would be limited to administration. Facilities would be provided at the powerplant for housing two employees for minor maintenance and emergency actions. A garage and warehouse would be provided for the storage of eqUipment and spare parts. In addition, all facilities required for remote control operation would be provided. The construction road along the transmission line would be main- tained for use by four-wheel drive vehicles o This road would follow only the wood-pole section. Inspections and maintenance of the steel tower section over Blue Lake Pass would be by helicopter. As the main- tenance road is not continuous fram the powerplant to Sitka, a set of maintenance equipment would be required at each end of the line. The annual cost of operation and maintenance provides for an in- crease in personnel of the Sitka Public Utilities and is estimated to total $155,000. The annual cost to the Federal Government for administration would be $10,000. 59 The present Blue Lake powerplant of the Sitka Public Utilities is a fully automatic plant. With that utility assuming the responsi- bility for project operation and maintenance, it would permit optimum use of maintenance personnel and equipment. The utility has indicated a preference that the project be so operated. Replacement Costs Under the proposed method of operation, the fund for the annual provisions for replacements would be the responsibility of the Sitka Public Utilities. This annual cost, based on the percentage of replace- able items and the useful life of the facility, and interest at 5.00 percent, is estimated to be $20,000. 0 z '" z -:i • 6 10 " 12 13 ,. : 15 i ;6 25 26 27 28 29 30 " 32 ~ I.EGENO: Type. of Activily Preconstructlon ond Other Work Construction , ; x CLASS AND PROGRAM ITEM ACCOUNT POWER DEVELOPMENT CONStRUCTION PROCRAM 01.01 Takata: Cr •• k and. Saddle DUI_ n,.~.l ............ .. !~.~.~u Creek Powarplant D.O! .... T.k.fIit~ Cr*ck. Switch ard 1).02 s 1t'll. .. Slo1bat:at ton 13.03 Takata Cn.k .. Sitk. 11.5 ltv fr.aat.don Line CL 115 Takata: Cr •• '" Govu._nt Cdlp TOTAL CQNST'RUCTlOH COST Cotl_Ud.t~d !!It endltur ••• ad Cradit Total 2xparttUtur* Total ObIts_don Notes QUA NT IiY 20,000 l45,800 20,000 25,600 22,000 2. TOTAL FISCAL YEARS UNIT ESTIMATED TO TOTAL ~w .. ),'4Q.OOO ~w 12~370~OOO KY. 420~OOO ~!! ... ~!?.!.~ H •• l.O60~OOO .... ! .. !.~~~.! 000 2l. 5&0 ,000 ~93.00Q 21~J,42~OOO .442.000 Recommendeld ~'././ Chid. Dhlaio,. of rroJKt ~-I BALANCE ESTIMATED 0 TO COMPLETIO z COMPLETE DATE '" z I. 15 ::J 26 26 29 31 """''''.1 tlnUt nun MARCH 19601 U""'_U' or flU unUUM A1a*. P .... r .... hahtuU.n CONTROL SCHEDULE O ....... Iol'"""'l •• "" ..... • e •• " •• ''''.1111 J .... r' .. "lr~. 1968 AI •• It. 0, ............. . o on •• 7-1720 Previous (6-65) PROJECT TAKATZ CREEK Bureau of Reclamation BASIC ESTIMATE DC-I SUMMARY Date of Estimate January 3, 1968 Estimate Chief Engineer, Bureau of Reclamation Prices as of Julv 1967 Prices as Office Prepared B and Alaska Power Administration Sheet 1 of 1 sheets of )-0)-I-LABOR AND MATERIALS AND LABOR BY 1-"" wI-I-Z MATERIALS BY EQUIPMENT BY GOVERNMENT FIELD COST TOTAL SERVICE OTHER TOTAL TOTAL TOTAL CI:"" iLCI: Z;:) FIELD COST FACILITIES COSTS COST COST COST w..( -w ,,(0 DESCRIPTION CONTRACTOR GOVERNMENT FORCES Q...J I-Q. ~u Zo ..JU wCl: Q.U COST COST COST PLANT IDENTIFIED IDENTIFIED IDENTIFIED IDENTIFIED PROPERTY IDENTIFIED Q. EQ. ..( ACCOUNT PROPERTY PROPERTY PROPERTY PROPERTY CLASS PROPERTY 1 2 3 4 5 6 7 8 9 10 11 12 TAKATZ CREEK PROJECT TOTAL COST J 9.64.5.000 196.000 3,]39,000 23.580.000 01 RESEIlVOIRS ANl1 DAMS 5.6/aO.000 01 TAKATZ CREEK AND SADDLE DAMS 4.700.000 47.000 893.000 .5.640.000 332.2 DAMS 4,700,000 4.700.000 Ol--DAM STRUCTURE (4,360,000) 02--0UTLET WORKS (340.000) 11 POWERPLAMTS--HYDRO 12.370.000 01 TAKATZ CREEK POWERPLA.NT--20.000-kw 10.300.000 103.000 1,961,09L 12 .. 370.000 331 STRth.;TuKr:S AND IKPKOvEKENts 1,480,000 ..... 1,480,900 332.3 WATERWJ.YS 3,890,000 3,890,000 333 WATER WHEElS TURBINES. AND GENERATORS 1,2.50,000 1,250,000 )34 ACCESSORY ELECtRIC EOUIPHENt I-~~ 220.000 280,000 500,000 335 MISCELLANEOUS EOUIPMENT 180,000 ~80.000 336 ROADS AND BRIDGES 3,000,000 3,000.000 13 tRANSMISSION LINES SWITCHYARDS AND SUBSTATIONS 3.910.000 01 TAKATZ CREEK SWITCHYARD·-2000D-kw 350.000 •. 000 66.000 420,000 3~3 STATION EQUIPMENT. ELECTRIC 350,000 350.,000 02 SITKA SUBSTATION--20,OOO.kw 415.000 4.000 81.000 .500.000 352 STRUc.;TUKr:S AND IKPRunnl;N'S 25.000 25.000 353 STATION EQUIPMENT. ELECTRIC 390.000 390.000 03 TAKATZ CREEK··SITKA TRANSMISSION LINE 2.550.000 25.000 48~.000 3.068.000 351 CLW1NG LANDS 580.000 580.000 354 TOWERS AND FIXTURES 470.000 I 470.000 l5~ POLES AND FIXTURES 600.000 600.000 3~6 OVEllHE4P CONDUCTORS AND DEVICES 500,000 500.000 3~9 ROADS AND BRIDGES 400.000 400,000 eL-lS SINIRAL LEDGER ACCOUNT 1.590.000 02 TAKATZ aln. GOVERNKllfT CAHP--r ... u control. 1.330.000 13.000 247.000 1.590.000 with two resident aDloyee. 389.3 CLEARING LANDS 10.000 10.000 390 STRUCTURES AND IMPBOVEKERTS 1 ... 320.000 1,320,000 CHAPT~;R VI--ECONOMIC i\I'ID FINANCIAL ANALY:3!S The> project would serve a Gintde purpo~>c, production of power, and all project costs are GO allocated. ScoDomic Analy::::is The useful life of the potential project storage "Horks would exceed 100 years. However, because of the difficulty of defining remote future conditions and the discount of long-deferred values, direct project benefits and costs were analyzed for a 100-year period. Benefits The tangible benefits of Takatz Creek Project would equal the market costs of similar blocks of firm and secondary energy from the most likely alternative source or sources. This is considered to be a municipally financed diesel-electric plant at Sitka, identical to the Federally- financed diesel-electric alternative discussed previously under "Plan FormUlation". Its costs, other than for interest, were considered to be the Game as those of the Federally-financed diesel-electric alternative. The cost of firm energy delivered was estimated on the basis of interest at 5.0 percent to average 16.3 mills per kilowatt-hour. As in the Plan Formulation studies previously discussed, the value of the secondary energy is estimated at 6,0 mills per kilowatt-hour. The average rate and repayment study, Table 15, presented subsequently under "Financial Analysis,1I indicates by years the firm and secondary proj- ect energy which it is estimated would be delivered to the load center. With these estimated energy deliveries and on the basis of a present worth computed with interest at 3.250 percent over a 100-year period, the annual eouivalents of the firm and secondary power reouirements were estimated at 8o,80~ megawatt-hours and 5,700 megawatt~hours, respectively. On this basis theeq~ivalent annual tangible benefits totaled about $1,352 ,000. There appear to be no other measurable benefits that would accrue from the project that would not also accrue to the area if power were supplied from the alternative source. The above figure is therefore considered to be a reasonable estimate of total benefits from Takatz Creek Project. Economic Costs The economic COt;ts of concern in evaluation of proJect justifica- tion include all costs subsequent to project authorization involved in eeneration and delivery of' the project power to the load center. These include the Federal costs involved in project construction and admini- stration plus the costs of project operation, maintenance, and replace- ment:: which would be assumed by the Sitka Public Utilities. The costs of project supervision, operation, and maintenance were estimated on the basis of current prices at $155,000 annually. The eGtimated replacement costs were estimated to average $20,000 annually over the 100 -year period of analysi3. The derivation of annual economic costs of the project is summarized below: Total Project Construction Cost Less Pre-authorization Investigations Interest During Construction (3.250%) Federal Installation Cost Annual Equivalent Cost (100 year, 3.250%) Annual Operation, Maintenance & Replacement Cost Total Annual Costs Benefit-Cost Ratio $23,500 ,000 98,000 $23,482,000 1,714,000 $25,196,000 854,000 1 85,000 $ 1,039,000 The ratio of evaluated tangible benefits to estimated total economic costs is 1.30 as summarized below: Total annual benefits Total annual costs Benefit-cost ratio Financial Analysis Repayment Requirements $ 1,352,000 1.,039,000 1.30 All of the Federal project costs are allocated to power and would be repayable to the United States. The repayment plan, in accord.ance with the plan of development, contemplates that the Sitka Public Utili- ties will assume the full annual operation, maintenance, and replacement costs. Thus, the repaJ~ent obligation would include only the project investment cost estimated at $25,300,000 and the Federal cost of project administration estimated at $10,000 annually. The project investment costs would consist of $23,580,000 of construction costs and $1,720,000 interest during construction. 64 Average Rate and Repayment ~tudy The average rate and repayment study summarized in Table 15 con- templates that payment of the reimbursable project costs would be with interest at 3.253 percent. It indicates by years the estimated firm and secondary project energy to be delivered at the load center. Project power supplies have been assumed to be available at the beginning of fiscal year 1976 with both units installed. However, on the basis of the forecast power requirements, the second unit would not be required until four years later. Thus, Table 15 provides for deferral of assignment of one-half of the investment costs to plant- in-service until the beginning of the fifth year and accumulation of simple interest on these deferred costs as shown below: Interest Total Project Deferred Allocated on Deferr,d Allocated Stage Investment Costs Costs Costs ~ Costs 1 $25,J)0,000 $12,650 ,000 $12,650,000 $12,650 ,000 2 12z650 zOOO 1,650,000 14zJJo zoOO $25,JJQ,000 $26,950,000 f7 3.253 percent simple interest for 4 years. As indicated in Table 15, the non-firm (secondary) energy is assumed to be marketed at 6.0 mills per kilowatt-hour in accordance with the practices followed in the plan formulation and economic analysis stUdies. Table 15 provides for repayment of' all investment costs within 50 years of when they are assigned to plant-in-service, together with payment of the $10,000 annual Federal costs of project administration as they occur. As indicated by Table 15, rates of 12.42 mills per kilowatt-hour for firm energy and 6.0 mills per kilow'att-hour for secondary energy, on the basis of the forecast requirements for the project power, would provide sufficient revenues to satisfy the project repayment reqUirements. The evaluated operation, maintenance, and replacement costs would average about 2.2 mills per kilowatt-hour annually over the payment period. Thus, the total cost over the repayment period of project power delivered to the load center would likely be about 14.6 mills per 1 2 Year of Fi.cal Study Year 0 1 1976 2 1977 3 1978 4 1979 5 1980 6 1981 7 1982 8 1983 9 1984 10 1985 11 1986 12 1987 13 1988 14 1989 15 1990 16 1991 17 1992 18 1993 19 1994 20 1995 21 1996 22 1997 23 1998 24 1999 25 2000 26 2001 27 2002 28 2003 29 2004 30 2005 31 2006 32 2007 33 2006 34 2009 35 2010 36 2011 37 2012 38 2013 39 2014 40 2015 41 2016 42 2017 43 2018 44 2019 45 2020 46 2021 47 2022 48 2023 49 2024 50 2025 51 2026 52 2027 53 2026 54 2029 TOTALS TABLE 15 TAKATZ CREEK PROJECT PRELIHINARY POWER SYSTEM AVERAGE RATE AND REPAYMENT STUDY AVERAGE POWER RATES USED TO COVER REVENUE DEDUCTIONS AND THE RETURN OF COSTS TO BE BORNE BY POWER 3 4 5 6 r 7 8 9 10 II 12 13 14 S.le of Electric Enargy Thou.and. of Kilowatt-Hour. Oper.ting Revenues (SI,OOO) Inve.t .. ent R." • .,......c trom Power R.v.nues Plant in Service at End of Year CompouRd lntar •• t Bearing Net Contract Revenue. Tot.l Firm Nonf irm Total Admini.tration Column. C-ercial Column. Sale" Sales Columns Costs 801.9 Intere.t Electr ic Balanc. to 301.4 12.42 Hills) (6.0 H111.) 601.7 $1,000 $1,000 D.253'%.) Principal Plant be Repaid Fino Monf ir .. 25 300 12 650 15,600 0 15,600 194 0 194 10 184 412 (228) I 12,878 21,900 21,900 272 272 262 419 (157) 13,035 28,800 28,800 358 358 348 424 ( 76) 25,300 13,lll 36,400 36,400 452 452 442 427 15 26,950 27,392 44 400 44 400 551 551 5~~ 891 (350) 27,742 54,100 54,100 672 672 602 902 (240) 27,982 64,400 64,400 800 800 790 910 (120) 28,102 75,800 75,800 941 941 931 914 17 28,085 88,400 88,400 1,098 1,098 1,088 914 174 27,911 93,200 93 200 1,158 1 158 1,148 908 240 27 ,671 0 93,200 0 1,158 1,148 900 248 27,423 1,000 94,200 6 1,164 1,154 892 262 I 27,161 2,000 95,200 12 1,170 1,160 884 276 26,885 3,000 96,200 18 1,176 1,166 875 291 26,594 4,000 97-,200 24 1 182 1 172 865 307 26 287 5,000 98,200 30 1,188 1,178 855 323 25,964 6,000 99,200 36 1,194 1,184 845 I 339 25,625 7,000 100,200 42 1,200 1,190 834 356 25,269 8,000 101,200 48 1,206 1,196 822 374 24,895 9,000 102 200 54 1. 212 1 202 810 392 24,503 9,500 102,700 57 1,215---1,205 --797 408 24,095 784 421 23,674 770 435 23,239 756 449 22,790 741 464 22 326 726 479 21,862 711 494 21,368 695 510 20,858 679 526 20,332 661 544 19 788 644 561 I 19,227 NOTES: 625 580 18,647 607 598 18,049 Colu .... 13: All construction coats are allocated to Column 18: The project would fully repay itself in 587 618 17,431 production of power. Total project 50 years after the second unit beco .... 567 638 16,793 investment, Including intereat during revenue p<oducing. A 5urp1ui of $159,000 546 659 16,134 construction, would be al fo II0w.: would be earned during tb. 54th year. 525 680 15,454 Feature Total Cost 503 702 14,752 Dam and Saddl. Dam $ 5,640,000 480 725 14,027 Powerp1ant 12,370,000 456 749 13,278 Switchyard 420,000 432 773 12,505 Sitka Sub.tation 500,000 407 798 11,707 Tr.n~l.sion Line 3,060,000 361 824 10,883 General Prop.rty 1 1 590,000 354 851 10,032 Subtotal $23,580,000 326 879 9,153 Inter •• t during Con.truction 1,720,000 298 907 8,246 Total Federal Inve.tment $25,300,000 268 937 7,309 238 967 6,)42 206 99" 5,343 174 1,031 4 312 140 1,065 3,247 106 1,099 2,148 93: 200 1 9:500 'f I ., l' I 't 't l,t05 I 70 1,135 1,013 102,700 1,158 57 1,215 10 33 1,172 26,950 0 4,623,800 I 368,000 4,991,800 I 57,448 I 2,208 1 59,056 540 59,116 I 31,996 27,120 26,950 0 January 11, 1966 15 16 17 18 19 20 (SI 000) Si~le Interest Bearina Allowable Earned Deferred Unpaid Surplu. Year R.payment Intereat Balance CUlDUlative Fhcal of Inveat .. ent D.253'%.) $1,000 $1,000 Year Study 12 650 25--<-300 0 I 412 25,940 0 1976 1 823 26,50B 1977 2 12,650 1,235 26,996 1978 3 0 1,646 27,407 1979 4 0 27 757 1980 5 27 ,997 1981 6 28,117 1982 7 1983 8 1984 9 1965 10 1986 11 1987 12 1988 13 1989 14 1990 15 1991 16 1992 17 1993 18 1994 19 1995 20 1996 21 1997 22 1998 23 1999 24 2000 25 2001 26 I 2002 27 2003 28 2004 29 2005 30 2006 31 2007 32 I I 2008 33 2009 34 2010 35 I 2011 36 2012 37 2013 38 2014 39 2015 40 2016 41 2017 42 2018 43 2019 44 2020 45 2021 46 2022 47 2023 48 28,117 2024 49 15 467 2025 50 15,t67 2026 51 2027 52 0 2028 53 0 0 0 159 2029 54 0 I 0 0 J 159 I kilowatt-hour. This would be less than the previously estimated 16.3 mill per kilowatt-hour cost of obtaining an equivalent amount of power, from the most likely project alternative, which is a municipally- financed diesel-electric plant. Hepayment Contract The project interests fully recognize that the estimated unit power costs of the Takatz Creek Project closely approximate the estimated unit power costs of a diesel-electric installation located in Sitka which would furnish power supplies equivalent to the Takatz Creek Project. However, they consider that the project is an essen- tial unit in their long range plans for meeting the power needs of the Sitka area. They, therefore, have expressed willingness to enter into a repayment contract which would assure return to the United States of the reimbursable project costs and provide for the Sitka Pd::.Jlic Utilities to assume operation, maintenance and replacement of the project works as provided for by the plan of development. It is contemplated that repayment of the reimbursable project costs would be through direct annual payments to the United States which would be based on the forecast project power deliveries. CHAPTER VII -REQUIRED FUTURE ACTIONS The investigations on which this report is based have been conducted in sufficient detail to dete~ine the engineering and financial feasibility, as well as the economic justification of the measures proposed under the plan of development. However, certain additional investigations will be necessary before com- mencement of construction. These are the normal pre construct ion activities required to accomplish final plans and specifications. They will include review of the need for concrete lining of the power tunnel and surge tank and possible shortening of the access road to the powerhouse and damsites. On the basis of the presently available geologic data, it is considered likely that sound competent rock prevails throughout the lengths of the power tunnel and surge tank, thus considerable savings in project costs may be possible through elimination of the concrete lining. The plan of development contemplates location of a dock and seaplane float in the generally ice-free bay just south of Takatz Bay to allow year-round water access to the powerhouse site. It also provides for extension of the access road from the powerhouse site to the damsites. The preconstruction activities will include dete~ination of the practicability of location of the dock and seaplane float in Takatz Bay near the powerplant site, and of pro- viding access to the damsites by construction of a cableway or other means in lieu of the access road from the powerplant. The preconstruction activities will also include negotiation of an appropriate repayment contract with the City of Sitka for repayment of the reimbursable project costs and for operation, main- tenance and replacement of the project works as contemplated by the plan of development. The preconstruction activities will also consider possibilities of incorporating an aerial dc transmission system in place of the conventional ac system contemplated in the current plan. The dc system would offer an opportunity for increased transmission relia- bility and may result in scme savings in operation and maintenance costs. The Takatz Creek Project may have areas of possible archeological and historical value. Prior to construction, appropriate investigations, and if necessary, salvage actions would be made. Funds for conducting these investigations have been included as project costs. 68 CHAPTER VIII -EXPRESSIONS OF STATE AND LOCAL IN'YJ!:REST The investigation of the Takatz Creek Project began in 1962 as part of an inventory of all potential hydroelectric developments in Southeast Alaska. It appeared to be the most favorable for supplying the Sitka area with an additional power supply, and on September 21, 1964 at a special meeting, data concerning this potential project was presented to representatives of the City of Sitka. Expressions at the September 21, 1964 meeting indicated that the City of Sitka would favor the Takatz Creek Project. On February 9, 1965, the Council of the City of Sitka passed Resolution No. 420 urging the Bureau of Reclamation (predecessor of the Alaska Power Administra- tion) to expedite its investigation of the Takatz Creek Project and preparation of a report suitable to recommend to Congress Federal devel- opment of the project, so project power could be available to the City not later than 1973-1974. The City of Sitka in December 1965, after review of the favorable reconnaissance report dated May 1965, again urged that completion of the actions essential to project authorization and construction be expedited. After review of the preliminary draft of this report dated Sept- ember 1967, which was transmitted to the City of Sitka, other concerned Federal agencies and the State of Alaska for field level comments, the City of Sitka by Resolution No. 492 dated December 12, 1967 expressed its formal endorsement of the plan of development presented herein, and its intent, when appropriate, to contract for operation and maintenance of the project works and repayment of the reimbursable project costs as contemplated by the plan of development. By letter dated January 10, 1968, the Governor of the State of Alaska indicated the State's endorsement of the Takatz Creek Project plan of development presented herein. Copies of Resolution No. 492 and Governor Hickel's January 10, 1968 letter appear on the following pages. COP Y "RESOLUTION NO o 492 A RESOLUTION OF THE CITY OF SITKA, ALASKA, ENDORSING THE TAKATZ CREEK HYDROELECTRIC PROJECT AND THE EXPECTED COURSE OF ACTION OF THE CITY PERTAINING THERETO WHEREAS, the City of Sitka, Alaska, has already "peaked- out" upon occasion with its existing power sources, and; WHEREAS, the plan of development for the Takatz Creek Project presented in the report of the Alaska Power Administration has been examined in some detail, NOW THEREFORE BE IT RESOLVED by the Council of the City of Sitka, Alaska, as follows: 10 The City of Sitka endorses the plan of development for the Takatz Creek Project presented in the report of the Alaska Power Administration. 2. Indicates its desire to contract, when appropriate, for operation and maintenance of the project works as contemplated by the plan of development. 3. states its willingness to enter into necessary contract or contracts, when appropriate, to cover operation and maintenance of the project works and payment of project costs, both as contem- plated by the plan of development, and 4. Urges the Alaska Power Administration and the Secre- tary of the Interior to expedite processing of the report to the end that authorization and construction of the project as a Federal development may be accomplished at the earliest practicable dates and power from the project be available to the city to meet forecast loads. PASSED AND APPROVED by the Council of the City of Sitka, Alaska, this 12th day of December, 1967. ATTEST: (Signed) Margaret B. Fedoroff City Clerk" (Signed) Richard I. Eliason Mayor WAI.TER ..J. HICKEL t;;OVCRNO'" S TAT E 0 T" A LAS Ii: A OF'F'ICE OF' THE GDVERND R JUNEAU January 10, 1968 ;<r. Gus Norwood, Administrator 1\::"aska Power Administration Department of the Interior Box 50 Juneau, Alaska 99801 Jear Mr. Norwood: : have received your preliminary drafts of the Lake Grace Project and the Takatz Creek Project. The ~evelopment of Alaska is almost entirely dependent u?on ade~uate power. I endorse and hope that these projects ~ecome a reality. 7ind attached the comments of the Department of Xatura::" Resources, the Department of Fish and Game &nd the Department of Health and Welfare. i'larm personal r~gards. Sincerely yours, Governor Attachments FORM FG -1~ '~(\I_ 2-61, 10: I I Office,of the Governor ATTN: W. L. Kubley f,iOM, Ul'ban C. Nelson Comlnissioner DEPARDlENT Or: FISH AND GA."lE FilE NO: DATE SUB :ECT; ~ January 3, 1968 Takatz Creek Project The Department of Fish and Game has been involved since 1964 in investigations regarding the effects of the Takatz Creek project on the fish and game resources of the area. In these investigations we have cooperated very closely with the Branch of River Basins Studies, Bureau of Conunercial Fisheries. The consensus has been that th'e Takatz Creek proj ect would have a minimal effect on the fish an~ game resources. Copies of draft letter reports on the project prepared by the Branch of River Basin Studies together with the Department of Fish and Game letters of concur- rence are attached for your information. Also attached is a copy of a depart- ment letter approving the issuance of a Permit to Appropriate Water to the Bureau of ~eclamation in conjunction with the Takatz Creek project. i=ollowing our review of the Alaska Pmver Administration' 5 draft report on the proj ect", the Department has no further com";lents or observations in addition to those already made. FO~M S·\" I~ 12',,~M a/~l ~ t, "'11 \ " ~ !~~) [\ f\ ~ ~~"'~ r'i ~ ,,) tl ;;~ ~";.VI.V~~.:·..:~~\;WUrlJ" ,<r .. f J' r" ~ ~ ':, ~. !?';i !: tC::I. rr.',: .... /' ~ \ ',If'.: r: f' 1 ~ '-' ........ \;;.i U Ii V-lj. :. 1,;.,:' ..., .a IObt.! Department of Health and Welfare Tv! i Mr. Dick She;:>herd O;(ice of the Governor uecember 19, 1967 ;-,\\ .. ;.1: VV. J. Chapman, M. D. SUBJECT, Tilkatz Creei< and Lake Grace ?rojects Co;-nrTI i::;3~O:iCr We hilve reviewed the preliminary drafts on the above projects for those features with which this Departrrlent is particularly concerned. We have no objections to the projects as proposed. However, it should ; " ;JG; .~. t·;ri 0',,:: tr.a t since construction camps of considerable size and ,:::\",,~u.l;ion '-,'.: .:;~ be; f)l"'ovided :Oor each project, comp"Liance rr.ust be made \:J~ \:--. :")0 ~.") ~',c to of i~ ',!'::;:<2, Construction Safaty Code and the water and ':':-'\":-'~L",iry r0(iW Lr"'::'.-(lt;!C)\:s cC t;-.~:::, u'2;Jart."'Y'lent. fO~M S ... ·I! 12~.SM 4/61 TO: r Richa~d E. Shepherd S~ate-Federal Assistance Coordinator Office of the Governor ""' 1 n'l" \ va e 1'.<1 .... ~ngton <l! I ~ep"'ty Co;nmi::;sioncl\.vv Dept. of Natural Resources DATE SUBJECT: December .15, 1967 Takatz Creek Project, Alaska He have perused the Alaska Power Commission report on 7akatz Creek Project. Since there are no prior appropriators of water from Takatz Creek, a permit has been issued by this department for his project to use all the waters of this stream. We do not anticipate a higher or better use for this ..l.rea in the foreseeable future. Mining will be insignificant "nd there will be very little recreational demand. The use of this water resource for power generation ~s the best use and we, therefore, approve of the project. OTHER AGENCIES REPORTS OF OTHER AGENCIES Letter Report of Federal Ilater Pollution Control . . . . ... . . . . Letter Rel)Ort of Bureau of Outdoor Recreation. IJet·t;er Report 0:::' Fish and IJildlife Service Letter froIn Alaska Department of Fish and Gl'me. • • • • • • Follo1-r.ing staGe 1 Hultiple Use SUl"re;yr Report of Forest Service, I.lcpartment of Aeri culture. • • • • • • • • • • . • • 1 1-2 1-2 2 1-8 FEDERAL WATER POLLUTION CONTROL AIlMlNISTRATION COP Y UNITED STATES DEPARTr,1E}lT OF THE INTERIOR FEDERAL HATER POLLUTION CONTROL ADt{[NISTRATION 1,Ir. George N. Pierce District Manager Alaska Hater Laboratory College, Alaska 99735 Bureau of Reclamation Alaska District Headquarters Post Office Box 50 Juneau, Alaska 99801 Dear Mr. Pierce: September 23, 1966 ulis of~ice has reviewed the information you provided on the Takatz Creek Project, Baranof Island, in Southeast Alaska. Our findings confirm your comments in tl~t there is no projected use of the iiaters either on Takatz Creek or on the intertidal zone which would be adversely affected by anticipated changes in temperature regimes due to the location of the i~take and the fluctuating releases. Thank you for the opportunity to w"Ork .Ti th you on the pre- liminary considerations of this project. Yours truly, lsi Elroy K. Day Director BUREAU OF OUTDOOR RECR&ATION COP Y D6427-AL Memorandum UNITED STATES DEPAR'lMENT OF THE INTERIOR BUREAU OF OUTDOOR REX:RFATION Pacific Northwest Region U. S. Court House Seattle, Washington 98104 January 13, 1967 To: District Manager, Bureau of Reclamation, Juneau, Alaska From: Regional Director, Bureau of Outdoor Recreation, Pacific Northwest Region, Seattle Subject: Takatz Creek Project We are submitting comments on the Takatz Creek Project in accord with the discussion at the meeting in your office on February 23, 1966, with your agency, the U. S. Forest Service, Fish and Hi1dlife Service, and the State of Alaska. We have reviewed reports prepared by the Forest Service and Fish and Wildlife and base our recommendations largely on their conclusions. Conclusions include: (1) Construction of a plant at Takatz Creek to supply power to the city of Sitka would not be detrimental to recrea- tion. Takatz Lake receives very little recreational use at present due to (a) glacial turbidity which restricts productive potential of fish, (b) sparse number of inhabitants in area, (c) proximity of better fishing lakes and recreational areas to population center (Sitka), and (d) inaccessibility. (2) With the construction of a power plant at Takatz Lake, a trans- mission line and gravel surfaced maintenance road will be built along a 75-foot R/H. It is doubtfUl, however, that the central portion of the road will be constructed because of the precipitous nature of the terrain in this area. Proposed plans indicate that the maintenance road will be built from both ends bypassing several of the existing recreation developments at Thimb1eberry Lake and Sawmill Creek, thus neither hindering nor encouraging recreation at these locations. (3) Blue Lake and Baranof Lake both contain good fish popUlations. Blue Lake, located along the proposed transmission line, already receives considerable usage by fishermen due to its prOXimity to Sitka (population, 1960 census, 3,237). The lake is approximately 5-1/2 air miles :['rom Sitka and is currently accessible via the Sitka Highwa;y and a road leading fram the highwa;y to the lake. It is prob- able that portions of the transmission road will make both Blue and Baranof Lakes more accessible to the recreation-minded public. (4) The construction of a transmission maintenance road will have little impact on recreation potential at Takatz Lake since sportsmen currently find fishing more rewarding at other lakes. In all prob- abili ty J the maintenance road "Ifill lead small numbers of the more adventurous and rugged sportsmen to seldom-used primi ti ve areas for hunting and fishing. He appreciate the opportunity to review your report and those of the U. S. Forest Service and Fish and Wildlife Service. Copies of this memorandum are being fUrnished to the Regional Forester of the Forest Service and the Regional Director of the Bureau of Com- mercial Fisheries and the Supervisor of River Basin Planning for the Bureau of' Commercial Fisheries. Copies are also being fUrnished to the State Department of Natural Resources. cc: Regional Forester, FS Regional Director, BCF Administrator, River Basin Planning CommisSioner, Department of' Natural Resources By Fred J. Overly Regional Director Maurice H. Lundy Acting FISH AND WILDLIFE SERVICE COP Y UNITED STATES DEPARTMENT OF THE INTERIOR FISH AND VlILDLIFE SERVICE Bureau of Commercial Fisheries Box 2481 Juneau, Alaska 99801 Hr. George N. Pierce District Manager U.S. Bureau of Reclamation P. O. Box 2567 J~neau, Alaska 99801 Dear Hr. Pierce: February 25, 1966 Your letter of February 18, 1966 advised us of selection of the r,lost desirable plan of development for the Takatz Creek project as discussed in your May 1965 Reconnaissance Report. The changes from the plan referred to in our letter report of February 8, 1966 primarily would involve the construction of a dam at the outlet of Talcatz Lake and a small saddle dam allmring nearly complete regulation of the basin. Construction of the project under this plan of development 'Ylould not cause any Significant additional impact on fish and wildlife resources nor would it offer any feasible opportunity for the imnrovement of the resources. Conclusions reached in our February 8, 1966 report are therefore not changed. We have discussed this ,·lith staff members of the Alaska Department of Fish and Game and have their verbal concurrence. i'ie appreciate being advised of these changes and hope you will inforn us if any further changes in project plans are made. Sincerely yours, /S/ Harry L. Rietze Regional Director COP Y UNITED STATES DEPARTHENT OF THE INT:ERIOR FISH AND w~LDLIFE SERVICE Bureau of Commercial Fisheries Box 2481 Juneau, Alaska 99801 Hr. George N. Pierce District Manager U.S. Bureau of Reclamation P. O. Box 2567 Juneau, Alaska 99801 Dear Hr. Pierce: February 8, 1966 This is our report on the Takatz Creek hydroelectric project at Takatz Bay on Baranof Island and about 21 miles northeast of Sitka, Alaska. It has been prepared under the authority of' the Fish and Wildlife Coordination Act (48 Stat. 401, as amended; 16 U.S.C. 771 et seq.). We have reviewed the project plans described in your reconnaissance report on the project dated May 1965. These plans include a pressure tunnel 5,100 feet long to tap Takatz Lake and a surface penstock 1,400 feet long to convey water to a 15,600 kilowatt power plant located on the shore of Takatz Bay. We have ascertained that construction and operation of the project would not affect significantly the fish and wildlife resources of the area and that the project would not offer feasible opportunities for the improvement of these resources. of the Alaska Department of Fish and Game have reviewed this report and they concur with our views as indicated in the attached copy of a letter from CommiSSioner Walter Kirkness dated January 28, 1966. Please advise us of any changes made in the project plans so that we can re-evaluate the effects of the project on fish and wildlife and prepare a revised report, if necessary. We appreciate the opportunity to comment on the proposed plans. Attachment Sincerely yours, /S/ Harry L. Rietze Regional Director COP Y STATE OF ALASKA vlilliam A. Egan, Governor Department of Fish and Game Office of the Commissioner Subport Building--Juneau January 28, 1966 v~. Harry Rietze, Regional Director Bureau of Conunercial Fisheries Box 2481 Juneau, Alaska 99801 Dear Hr. Rietze: The Department has reviewed the Bureau's draft copy of a report on the Bureau of Reclamation Takatz Creek hydro- electric project on Baranof Is:and. We concur with the Bureau's conclusions with regard to: 1) The affect of the project on fish and wildlife. 2) The lack of feasible opportunities for the improvement of these resources. cc: Parker Heckart Sincerely, ALASKA DEPARTMENT OF FISH AND GAME /S/ Walter Kirkness, Conunissioner FOREST SERVICE COP Y UNITED STATES DEPARTMENT OF AGRICULTURE FOREST SERVICE Box 1631 ,Tuneau, Alaska 99801 Mr. GeorGe N. Pierce, District Manager U.S. Bureau of Reclametion P. O. Box 25G7 Juneau, Alaska 99801 Dcar r·1r. Pierce: In Reply Refer To 1530 (2100) Enclosed are three copies of our Stage 1 Multiple Usc S1.lrvey Report for the proposed Takatz Creek Project. T.~is stage 1 report is a Regional report and does not necessarily contain final recommendations or policy decisions. Such recom- mendations and decisions .. rill be coni~ained in the stage 2 report, ,·rhich '>nll be prepared after your feasibility report has been completed. The stage 2 report will be reviewed by our Washington Office and approved by the Chief of the Forest Service. In spite of the limited nature of the stage 1 report, it should be a definite help to you in determining the design features that will be necessary to fullY coordinate the project with National Forest development and protection. Should you have any questions regarding any items in the report, w-e "rill be happy to discuss them '>nth you. i·lore copies of the report can be made available, should you need them. Enclosures Sincerely yours, /S/ W. H. JOHNSON Regional Forester MULTIPLE USE SURVEY REPORT STAGE I Name of Project: TAKATZ CREEK Sitka Ranger District, North Tongass National Forest, Alaska Region Report Submitted by lsI William B. Roberts Dis trict Ranger Approval Recommended by lsI Vincent N. Olson Forest Supervisor Date;..-..._...;;:2.,/...:...4/i...,;6;;.,;:6 __ _ Date;..-... __ ~2~/...;;:1~1~/6~6~ __ _ Approval Recommended by ~:L/C. /;> 1;/~4:~i Date. __ :_·/_',"""1A;..-...,/'· ..... / .... __ Chief, Brar..ch of Hultiple Use lit Watershed Hanagement Report Recommended by -~~l.I.4.L-:;J-~':.::J!~~~-Date.--' . .:;.~+t .... P~/t ..... ~ ......... (. __ · __ _ Regional Fa ester r 7 of Resource Hanagement Report Approved by ______ ~~~.~~~,~~~~~~~~ __ _ Regi~naCIForester " I; ,I / " Date __ ... )~. __ ._/ ___ ! ... I.:;.· __ __ TAKATZ CREEK NULTIPLE USE SURVEY REPORT STAGE I TABLE OF CONTENTS Page I. INTRODUCTION AND DESCRIPTION 1 II. RECONHENDATIONS 3 III. EVALUATION OF RESOURCE USES AND ACTIVITIES 4 IV. OTHER CONSIDERATIONS 7 APPENDIX S Map Legend Hap I. INTRODUCTION AND DESCRIPTION This impact report was prepared without the benefit of an on-the-ground examination of the proposed transmission route. Available time and winter snow conditions precluded such an examination. A. Nature of Proposed Project: Construction of a power project utilizing water power from Takatz Lake, with a transmission line to Sitka. The project would consist of a tunnel from Takatz Lake to a power plant at Takatz Bay and a power transmission line from Takatz Bay to Sitka. At this time no decision has been made on construction of a dam at Takatz Lake. B. Agencx Responsible: Department of the Interior, Bureau of Reclamation, Alaska District Office, Juneau, Alaska. C. ~~cation and Description: The project is located within the North Tongass National Forest, Sitka Ranger District, on Baranof Island. Takatz Lake would be the source of power and the drainage both above and below the lake would be affected by the project. The transmission line from Takatz Bay would follow the shoreline to the town of Baranof in Warm Springs Bay and would be in the Baranof Lake, Blue Lake and Thimbleberry Creek drainages from the Town of Baranof to the National Forest boundary near Sitka. D. ~: Three plans for power production are discussed in the Bureau of Reclamation reconnaissance report for the project. One plan is to utilize Takatz Lake as it is with no dam. The normal elevation of the lake is 905 feet with a surface area of 403 acres. The second plan is to construct a dam at the outlet, raising the water level to elevation 950 feet and increasing the surface area to about 530 acres. The third plan is to construct a higher dam, which would raise the water level to an elevation of 1,000 feet and increase the surface area to about 650 acres. The project cost estimate in the Bureau of Recla- mation reconnaissance report is based on the plan that includes no dam. With either of the plans, a 5,100 foot concrete lined tunnel, seven feet in diameter, would be drilled to the 700 foot elevation of the lake. This tunnel would terminate at a surge tank constructed of reinforced concrete and embedded within the rock hillside. A pen- stock of steel pipe five feet in diameter would carry the water 1,400 feet from the surge tank to the powerplant on the shore of Takatz Bay. A gravel surfaced road is planned from the powerplant to Takatz Lake, a distance of three miles. A transmission line, 28.4 miles in length, would be constructed from the powerp1ant to the SUbstation near Sitka. This would have a 75 foot right-of-way. A maintenance road is planned 2 along the entire length of the transmission line, according to the reconnaissance report. HO\Olever, discussions with Bureau of Reclamation officials disclosed that it is likely that this road would be built from both ends of the transmission line, with the very rugged central portion of the line not served by road. The transmission line would be on National Forest land for 24.5 miles. E. Land Status: All lands involved in the proposed tunnel, penstock, and powerplant are National Forest. Along the proposed transmission line route there exists: 1. Townsite elimination of 9.46 acres at Baranof. 2. l-larm Springs Packing Co. site of 5.75 acres at Baranof. 3. Fred Bahovec homesite of 1.13 acres at Baranof. 4. Alaska Lumber and Pulp Company lands at Sawmill Creek. 5. Power transmission line past Heart and Thimb1eberry Lakes, covered by F.P.C. License #2230. 6. Sitka elimination, which has its eastern boundary near Thimb1eberry Lake. Takatz Lake and Creek are covered by U.S.G.S. Power Site Classification #221. Baranof Lake and its outlet are also covered by P.S.C. #221. Power Site Classification #188 covers 130 acres to the north of P.S.C. #221 at Baranof Lake. Blue Lake is covered by Power Site Classifica- tion #221 and #427. F. Physical Characteristics of the Area: Takatz Lake is about 1.5 miles long and 0.4 miles wide. The shores are steep with some flat area at the inlet stream. The water is turbid and of glaCial origin. The proposed powerplant location is on a small area at the head of Takatz Bay. The proposed transmission line would be built across a variety of terrain. From Takatz Lake it would run across fairly steep country to the head of Baranof Lake. It would then f0llow up a relatively flat valley until it crosses Mt. Bassie. Then it would descend into the Blue Lake drai- nage. From here the topography varies from flat bottom land to steep hillSides, talus slopes, and cliffs until the Sitka elimination is reached. The map in the appendix shows the topography along the pro- posed location .• G. Multiple Use Zoning: The current zoning is shown on the map in the appendix. Major areas affected would be in the Baranof Lake-Warm 3 Springs Bay, Blue Lake-Sawmill Creek and Heart Lake-Thimb1eberry Lake areas. H. General Location Hap: See Appendix. II. RECOMMENDATIONS A. Recreation and Esthetics 1. The power transmission line and attendant maintenance road should be located to avoid developed recreation sites at Sawmill Creek and Thimbleberry Lake. Potential recreation development sites at Thimbleberry Lake, Heart Lake, the outlet of Blue Lake, and both ends of Baranof Lake should also be avoided. These areas are shown as Occupancy Zones on the map in the Appendix. 2. The power transmission line and maintenance road should be screened from view from the recreation sites mentioned above, to the extent feasible. They should also be screened from recreationists boating on Blue Lake, Baranof Lake, and l~arm Springs Bay, to the extent that this is practical. The topography and vegetation of the country traversed will make complete screening impractical. B. Roads 1. Any portions of the transmission line maintenance road that are accessible from Sitka should be of <l high enough standard to allow rublic use. 2. The maintenance road and the access road to Takatz Lake should be constructed in such a manner that soil erosion is minimized. An erosion control plan will be jointly developed by the Forest Ser- vice and the construction agency before construction begins. This plan should cover erosion problems connected with tunnel, penstock, powerplant, and transmission line construction, in addition to road construction. Provision will be provided for adequate water control structures and revegetation of denuded areas, where needed. C. Timber 1. Timber that must be cut in conjunction with construction of the maintenance and access roads, transmission line, powerplant, and penstock will be sold by the Forest Service under commerc:al sale procedures, if possible. If the timber cannot be sold in this manner, it will be covered by timber settlement procedures. The latter case is most likely to apply. 2. The transmission line and maintenance road locations should be coordinated with possible future ttmber harvest in the areas traversed, to the extent feasible. The Forest Service will cooperate in the on-the-ground location of these facilities. 4 3. If planning for this project is later revised to call for construc- tion of a dam, all timber 4" and over in diameter at breast height within the reservoir area will be cut and disposed of. Any mer- chantable timber will be sold by the Forest Service, if possible. If the timber cannot be sold (which is likely in this case), it will be covered by timber settlement procedures. D. Fire A fire control plan will be developed by the Forest Service and con- struction agency before construction begins. E. \.Jildlife Fish and other wildlife losses as a result of this project are not expected to be significant. No mitigation measures will be required. III. EVALUATION OF RESOURCE USES AND ACTIVITIES A. Outdoor Recreation: Takatz Lake presently receives little or no recreation use. This use would change little in the future without this project. Development of the project would probably attract a few more visitors to the area, particularly if the transmission line maintenance road extended all the way to Sitka (an unlikely possibility) and were of a high enough standard to encourage public traffic. Blue Lake presently receives a considerable amount of use by sport fishermen. This use can be expected to increase, particularly if this project is constructed and a transmission line maintenance road around one side of Blue Lake is available for public use. EXisting recreation developments within the area that would be affected by the project include a campground at Sawmill Creek, a Boy Scouts of America organization site on Thimbleberry Lake, and a cabin at the southwest end of Baranof Lake. Potential recreation sites include areas at Thimbleberry Lake, Heart Lake, the outlet of Blue Lake, both ends of Baranof Lake, and at Manleyville in Warm Springs Bay. This project will have little impact on these sites, if the transmission line and maintenance road bypass them and are screened from them, to the extent feasible. The site at Manleyville is an alternate site in the Recrea- tion Management Plan and would not have to be avoided, if it proves difficult to do so. B. Timber: The proposed project facilities would involve a number of patches of merchantable-size timber. Some of this is within the Alaska 5 Lumber and Pulp Company sale area, but the timber involved can be with- drawn from the sale under terms of the contract. Timbered areas that would be traversed by the transmission line and maintenance road, along with the powerplant site and penstock area, would be removed from timber production, if this project is built. At the same time, the maintenance road, if built to a high enough stan- dard, would aid in timber management by providing access to stands currently lacking access. The location of the transmission line and maintenance road should be planned to avoid conflicts and to compli- ment timber management as much as possible. For example, these facilities should traverse near timber stands, but not through small patches so that they become difficult to harvest. If these facilities are carefully fitted to the ground, it should be possible to enhance timber values and detract little from recreation and esthetic values, without a significant increase in the cost of their construction and maintenance. c. Water: Takatz Lake waters are presently receiving no significant use. Development of this project will put these waters to beneficial use. A potential for soil erosion will exist in conjunction with construc- tion of the project facilities. This problem can be minimized by following an erosion control plan jointly prepared by the Forest Service and the construction agency before construction begins. D. Wildlife: Fishery values in the Takatz drainage are very minor. This project would create no detrimental impact on them. Glacial turbidity severely restricts the productive potential of the lake and its inlet streams. An impassable falls at tidewater prevents salmon from using the outlet stream. The intertidal portion of the stream is not suit- able for salmon spawning. Big game species in the Takatz drainage include Sitka blacktailed deer, brown bear, and mountain goats. The project would have no significant impact on these. Baranof Lake and Blue Lake contain good sport fish populations. These would not be adversely affected by the project, so long as the trans- mission line and maintenance road construction are carefully supervised to avoid soil erosion and sedimentation of the lakes and their tributaries. Portions of the transmission line maintenance road connected to the Sitka road system could provide benefits by making new areas acces- sible to hunters and fishermen, resulting in a better dispersion of their efforts. 6 E. Minerals: No conflict between this project and mining development is expected. Access provided by the transmission line maintenance road would enhance the area for mineral prospecting. F. Land Occupancies: The non-National Forest lands and other occupied lands listed earlier under Land Status can be avoided by proper loca- tion of the transmission line and maintenance road. The same is true of the existing and potential recreation sites listed under Out- door Recreation. A ~lemorandum of Understanding between the Forest Service and Bureau of Reclamation will be needed to cover the transmission line and main- tenance road. The other permanent project features will presumably be covered by a reclamation withdrawal. Any temporary camps or similar facilities can be covered by special use permit. G. Fire Control: Fire problems in the proposed project are presently slight, due to a generally low hazard and a lack of human activity. Construction of the project would result in an increased hazard due to temporary slash accumulations. Fire risk would also increase due to the number of workers involved in the project construction. A fire control plan will be needed to properly recognize potential fire problems and minimize the possibility of wildfire occurring. H. Transportation System: The roads and trails presently existing within the area that would be affected by the project include a road from the Sitka Highway to Blue Lake and a trail past Heart and Thimb1eberry Lakes. Each of these would probably have to be crossed by the trans- mission line. A minor decrease in esthetic values would result. The proposed maintenance road along the transmission line would enhance public travel, if it were built to a high enough standard to permit such use. The central portion of the transmission line would traverse some very rugged terrain, with elevations to 3700 feet. Construction of the maintenance road through this area would be very difficult and expensive. It is reasonable to expect that later planning will exclude the maintenance road from this portion of the line. I. Land Ownership Adjustment: Alaska Lumber and Pulp Company land in the Sawmill Creek drainage would probably have to be crossed by the trans- mission line. There is a reservation in the Alaska Lumber & Pulp deed that provides for future construction of improvements or facilities across their land. If it should prove impossible to avoid all of the tracts of private land in Warm Springs Bay with the transmission line location, rights- of-way would have to be acquired. 7 IV. OTHER CONSIDERATIONS The proposed project is consistent with National Forest management objec- tives, the ~1ultiple Use Management Guide for the Alaska Region, and the Sitka District Multiple Use Plan. It would enhance the development and use of the natural resources of the area affected. Coordination of the project features with public needs and desires would be necessary to realize maximum benefits from the project. APPENDIX Map Legend Map (showing Multiple Use Zones and project features) (Map not duplicated for this Report)