HomeMy WebLinkAboutReynolds Creek Hydroelectric Project Preliminary Draft Environmental Assessment 1997i'~' HAIDA CORPORATION
".:iiI'! .--
----------------------~~~~~------T_----august
TK
1425
.R49
R49
1997d
nineteen-hundred ninety-seven
HAIDA CORPORATION
•
..
-Reynolds Creek Hydroelectric Project
•
FERC Project No. 11480
-August 1997 Draft
-
.. Preliminary Draft Environmental Assessment
-
-
-T"""
8
LO
~
('I) AEJL1S -('I) AIaskaResolJrLC, UI,raf\ ,\: inforrnaliOH Services
Libran BuiiJllH'. SuilC 11.1
321 f Prdvidc;~'Cl Dri\',,: .. Anchorage, A!"': (1)508-4614
•
-
•
•
•
..
•
•
•
•
•
-
-
•
-
-
Preliminary Draft Environmental Assessment
TABLE OF CONTENTS
SUMMARy ................................................................................................................................ 1
1 APPLICATION ...................................................................................................................... 4
II PUKPOSE AND NEED FOR ACTION ................................................................................ 5
II.A PURPOSE OF ACTION ............................................................................................................ 5
II.B NEED FOR POWER ................................................................................................................. 5
II.B.l Hydaburg ............................................................................................................................................. 6
II.B.2 Interconnected Prince of Wales Island .................................................................................................. 6
ILB.3 Load Forecasts ..................................................................................................................................... 6
III PROPOSED ACTION AND ALTERNATIVES .................................................................. 9
III.A APPLICANT'S PROPOSAL ................................................................................................... 9
lILA. 1 Project Facilities ................................................................................................................................. 9
IILA.2 Project Operation ............................................................................................................................... 9
GeneraL ..................................................................................................................................................... 9
Lake Mellen ............................................................................................................................................ 15
Bypass Reach Flow Regime ..................................................................................................................... 15
Lower Reynolds Creek Flow Regime ........................................................................................................ 17
IIIA.3 Proposed Environmental Measures ................................................................................................... 17
Construction Precautions ......................................................................................................................... 17
Lake Mellen Elevation Operating Regime ................................................................................................ 18
Instream Flows in Bypass Reach .............................................................................................................. 18
Powerhouse and Tailrace Location ........................................................................................................... 18
Transmission Line Features ..................................................................................................................... 18
Access Roads ........................................................................................................................................... 19
III.B MANDATORY CONDITIONS .............................................................................................. 19
III.C MODIFICATION OF APPLICANT'S PROPOSAL ............................................................ 19
III.D NO ACTION ALTERNATIVE .............................................................................................. 19
IV. CONSULTATION AND COMPLIANCE .......................................................................... 20
IV.A AGENCY CONSULTATION ................................................................................................ 20
IV.B INTERVENTIONS ................................................................................................................. 20
IV.C SCOPING ................................................................................................................................ 20
IV.D WATER QUALITY CERTIFICATION ............................................................................... 21
IV.E COASTAL ZONE MANAGEMENT ACT PROGRAM ....................................................... 21
V. ENVIRONMENTAL ANAL ySIS ........................................................................................ 22
V.A GENERAL DESCRIPTION OF THE REYNOLDS CREEK WATERSHED ...................... 22
V.B PROPOSED ACTION AND ACTION ALTERNATIVES ..................................................... 23
August 1997 Draft
Reynolds Creek HydroelectriC Project
FERC Project No. 11480
•
-
-
-
-
•
-
-
•
-
-
•
-
•
-
..
Preliminary Draft Environmental Assessment
V.B.l Geology and Soils Resources .............................................................................................................. 23
Affected Environment. ............................................................................................................................. 23
Environmental Impacts and Recommendations ........................................................................................ 24
Unavoidable Adverse Impacts .................................................................................................................. 24
V.B.2 Aquatic Resources ............................................................................................................................. 25
Affected Environment. ............................................................................................................................. 25
Environmental Impacts and Recommendations ........................................................................................ 36
Unavoidable Adverse Impacts .................................................................................................................. 39
V.B.3 Terrestrial Resources ......................................................................................................................... 40
Affected Environment. ............................................................................................................................. 40
Environmental Impacts and Recommendations ........................................................................................ 44
Unavoidable Adverse Impacts .................................................................................................................. 46
Y.B.4 Threatened, Endangered, and Sensitive Species ................................................................................. 46
Affected Environment. ............................................................................................................................. 46
Environmental Impacts and Recommendations ........................................................................................ 46
Unavoidable Adverse Impacts .................................................................................................................. 46
V.B.5 Aesthetic Resources ........................................................................................................................... 47
Affected Environment. ............................................................................................................................. 47
Environmental Impacts and Recommendations ........................................................................................ 48
Unavoidable Adverse Impacts .................................................................................................................. 48
V.B.6 Cultural Resources ............................................................................................................................. 48
Affected Environment. ............................................................................................................................. 48
Environmental Impacts and Recommendations ........................................................................................ 49
Unavoidable Adverse Impacts .................................................................................................................. 49
V.B.7 Recreation and Other Land Uses ........................................................................................................ 49
Affected Environment. ............................................................................................................................. 49
Environmental Impacts and Recommendations ........................................................................................ 50
Unavoidable Adverse Impacts .................................................................................................................. 50
V.B.8 Socioeconomic Resources .................................................................................................................. 50
Affected Environment. ............................................................................................................................. 50
Environmental Impacts and Recommendations ........................................................................................ 51
Unavoidable Adverse Impacts .................................................................................................................. 51
V.C CUMULATIVE EFFECTS ...................................••••...............................•••............................. 52
V.C.1 Geographic Scope .............................................................................................................................. 52
Aesthetic Resources ................................................................................................................................. 52
Recreation and Other Land Uses .............................................................................................................. 53
V.C.2 Temporal Scope ................................................................................................................................. 53
V.C.3 Cumulative Effects Analysis .............................................................................................................. 53
Aesthetic Resources ................................................................................................................................. 53
Recreation and Other Land Uses .............................................................................................................. 54
V.D NO-ACTION ALTERNATIVE ............................................................................................... 54
JlI. DEVELOPMENTAL ANALySIS ...................................................................................... 55
VII. COMPREHENSIVE DEVELOPMENT AND RECOMMENDED ALTERNATIVE ...... 57
VIII. CONSISTENCY WITH COMPREHENSIVE PLANS ................................................... 58
North American Waterfowl Management Plan (NA WJvfP) ....................................................................... 58
Alaska Outdoor Recreation Plan (AORP) ................................................................................................. 58
Hydaburg Coastal Management Program ................................................................................................. 59
IX. FINDING OF [OR NO] SIGNIFICANT IMPACT ........................................................... 60
X LITERA TURE CITED ........................................................................................................ 61
August 1997 Draft II
Reynolds Creek HydroelectriC Project
FERC Project No. 11480
..
•
-
•
•
•
•
•
•
•
•
..
•
•
•
•
•
-
•
Preliminary Draft Environmental Assessment
XI. LIST OF PREPARERS ................................................................................................... 63
XII MAILING LIST. ............................................................................................................. 64
APPENDICES
Appendix A -Agency Letters and Comments
Figure
1
2
3
4
5
6
7
8
9
10
11
12
1
2
3
4
5
6
LIST OF FIGURES
Location Map .................................................................................................................. 2
Hydaburg Historic Energy Sales ...................................................................................... 7
Annual Energy Requirements, Prince of Wales Island (interconnected) ............................. 8
Reynolds Creek Drainage & Location of Project Facilities ............................................. 10
Typical Electric Load Profile ......................................................................................... 12
Weekly Operations Simulation, Phase 1 -1,500 kW Peak Load, Load
Following Operation ..................................................................................................... 13
Weekly Operations Simulation, Phase 1 -1,500 kW Peak Load, Flows
DS of Powerhouse ......................................................................................................... 14
Lake Mellen Elevation Changes, April 15 -September 22, 1996 .................................... 16
Timing ofFish Life History Stages in Reynolds Creek System ........................................ 29
Topography of Lake Mellen Inlet ofInterlaken Pond ..................................................... 31
Topography of Lake Mellen Outlet to Rich's Pond ........................................................ 32
Project Area Wetlands ................................................................................................... 42
LIST OF TABLES
Reynolds Creek Average Monthly Flows ....................................................................... 26
Water Quality Data (1995 to 1996) ................................................................................ 27
Anadromous Fish Counts for Reynolds Creek (Copper Harbor)
from ADFG Records (1963-1996) ................................................................................. 34
Estimated Fill in Wetlands .............................................................................................. 45
Species of Concern ........................................................................................................ 47
Estimated Annual Amounts of Diesel Fuel and Resulting Pollutants
from Equivalent Amounts of Generation from a Diesel-Fired Power Plant.. .................... 56
August 1997 Draft 111
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
-
-
•
•
•
-
•
•
•
•
•
-
•
-
-
Preliminary Draft Environmental Assessment
SUMMARY
The Applicant, Haida Corporation, proposes to construct, operate and maintain a 5.0 megawatt
(MW) hydroelectric project on Reynolds Creek just west of Lake Mellen on Prince of Wales
Island, approximately 10 miles east of Hydaburg, Alaska (Figure 1). The project will be
constructed in two phases. In the first phase, the diversion/intake, penstock, access roads,
transmission line and a 1.5 MW powerhouse will be constructed. In the second phase, the
powerhouse will be expanded and an additional 3.5 MW unit will be installed, increasing the
project capacity to 5 MW. All project lands are owned by Haida Corporation or will be acquired
through a lease or purchase from Sealaska Corporation or the State of Alaska. No federal lands
will be utilized for the project. This project could generate up to 23.5 million kilowatt-hours
(kWh) per year of electrical energy. The project will displace diesel-fueled electric power
generation and, thereby, conserve non-renewable fossil fuels and reduce the emission of noxious
byproducts caused by combustion of fossil fuels.
This Preliminary Draft Environmental Assessment (PDEA) analyzes the benefits of the proposed
project and the effects of project construction and operation on the natural resources of the
Reynolds Creek Basin. Natural resource impacts have been identified as follows:
Construction
• A temporary increase in turbidity and sediment in Rich's Pond and Lower Reynolds
Creek.
• Temporary wildlife displacement due to construction noise and activity.
•
•
Elimination of approximately 2 acres of wetlands for construction of the intake,
transmission line and access road.
Short-term disturbance of approximately 4.5 acres of vegetation and permanent
elimination of approximately 2.5 acres of vegetation.
Operation
• Overhead transmission lines posing a threat to raptors.
• Increased runoff from areas occupied by structures.
• In-lake rearing and spawning altered by the lake level fluctuations in Lake Mellen.
• Visual impacts from the presence of project facilities in the area.
• A decrease in flow in the bypass reach of Reynolds Creek by 30 cfs at 1.5 MW operation.
• Inundation of Rich's Pond area.
August 1997 Draft 1
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
I -. -,
ARCTIC OCCAN
City of
ALASKA
P,lCIFIC OCCAN
LOCATION MAP
----------------"---,,,--
--t -a
VICINITY MAP
Figure 1
Reynolds Creek
Location Mop
--I
•
-
-
•
•
Preliminary Draft Environmental Assessment
The Applicant has proposed the following mitigation measures:
• Installation of a low-level outlet in the diversion structure to continuously release flows
into the bypassed reach of Reynolds Creek.
• Design of the overhead transmission line according to raptor protection guidelines and
installation of collision avoidance devices on the line, if appropriate.
• Implementation of an Erosion and Sediment Control Plan and Best Management Practices
to control runoff and prevent delivery of construction sediment to streams.
• Timing of certain construction activities to minimize disturbance to fish and wildlife.
• Construction ofthe tailrace above the anadromous fish barrier in Reynolds Creek.
• Design and construction of project facilities to minimize aesthetic impacts.
• No threatened, endangered or sensitive species have been found or are expected in the project
area. A list of species of concern provided by the agencies was considered in the analysis of
terrestrial impacts.
•
The amount of any environmental resource affected would either be a small increment of the total
in the project area or mitigation measures that are proposed would render the impact insignificant.
• Thus, on the basis of the overall environmental analysis, a Finding of No Significant Impact
(FONSI) is recommended.
•
•
•
-
•
•
•
•
-
-
August 1997 Draft 3
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
•
•
•
•
•
-
•
•
•
-
-
...
•
•
-
-
Preliminary Draft Environmental Assessment
I. APPLICATION
The Federal Energy Regulatory Commission (Commission) issued a Preliminary Pennit to the Haida
Corporation (the Applicant) effective December 1, 1994, to allow them to study the hydroelectric
potential of Reynolds Creek. This permit expires on November 30, 1997. Haida Corporation is an
Alaskan corporation established under the Alaska Native Claims Settlement Act as the village
corporation for the Native village of Hydaburg. Haida Corporation has retained HDR as its agent for
purposes of this project. Haida Corporation intends to me an application with the Commission for a
Major Water Power Project (18 CFR 4.61). The maximum installed capacity will be 5 MW. The
project would be located on Reynolds Creek just west of Lake Mellen on Prince of Wales Island,
approximately 10 miles east of Hydaburg, Alaska (Figure 1). All project lands are owned by Haida
Corporation or will be acquired through a lease or purchase from Sealaska Corporation or the State of
Alaska. No federal lands will be utilized for the project. The project will consist of a dam/intake near
the outlet of Rich's Pond on the west side of Lake Mellen, a penstock to convey water from the intake
to the powerhouse, a powerhouse on Lower Reynolds Creek, and a transmission line to the City of
Hydaburg. The Commission, under the authority of the Federal Power Act l (FP A), may issue licenses
for up to 50 years for the construction, operation, and maintenance of non-federal hydroelectric
developments.
Under the Commission's regulations, issuing a license for the project first requires preparation of either
an Environmental Assessment (EA) or Environmental Impact Statement (EIS), in accordance with the
National Environmental Policy Act (NEPA) of 1969.2 Pursuant to the authority granted under Section
2403(b) of the Energy Policy Act of 19923 , Haida Corporation, in coordination with the Commission
staff, has prepared this Preliminary Draft Environmental Assessment (PDEA) for the Reynolds Creek
Project consistent with the requirements of NEP A and the Council on Environmental Quality's
guidelines, 40 CFR Part 1500. This document includes descriptions and evaluations of the effects of
the Applicant's proposed action, including an assessment of the action's cumulative effects and project-
specific effects. The PDEA will be submitted to the Commission, in lieu of the Environmental Report
(Exhibit E), as part of the Application for License.
This PDEA will be circulated for review to all interested parties. Following ruing, the Commission staff
will independently review the PDEA and other application material for adequacy and will issue a staff
Draft Environmental Assessment (DEA). The Commission Staffwill consider all comments med on the
Staff DEA for the Final EA The Staff will present conclusions and recommendations for the
Commission to consider in reaching its final licensing decision.
The Applicant will seek benefits under Section 210 of the Public Utility Regulatory Policies Act
(pURPA) of1978. The project will be located at a new diversion as defined in 18 CFR 292.202 .
U.S.C. Section 791(a)-825(r).
2 42 U.S.c. Section 4321 et seq. (1988)
3 Pub.L. No. 102-486
August 1997 Draft 4
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
..
-
-
-
•
•
•
•
-
•
•
•
-
..
..
. -
..
-
-
Preliminary Draft Environmental Assessment
II. PURPOSE AND NEED FOR ACTION
II.A PURPOSE OF ACTION
The Commission must decide whether or not to issue a hydropower license to Haida Corporation
for the project, and what conditions should be placed on any license issued. Issuing a license
would allow Haida Corporation to construct and operate the project for a tenn of up to 50 years,
making electric power from a renewable resource available.
The environmental and economic effects of construction and operation of the project, as proposed
by Haida Corporation, are assessed in this PDEA. The effects of a no-action alternative are also
considered.
II.B NEED FOR POWER
The Reynolds Creek Project would be located approximately 10 miles east of the City of
Hydaburg, Alaska, on Prince of Wales Island (POWl). Power from the project would have an
immediate use in meeting the needs of Hydaburg and would be useful in meeting the island's long-
tenn anticipated power needs. The project would displace diesel-fueled electric power generation
and, thereby, conserve non-renewable fossil fuels and reduce the emission of noxious byproducts
caused by combustion of fossil fuels. Displacing fossil fuels would also reduce the production of
"greenhouse" gases and reduce risk of oil spills associated with the handling and storage of these
fuels. This is particularly important in the pristine environment of southeast Alaska where the
project would be located. If the project license is denied, the project's capacity would likely need
to be replaced with diesel generation.
Hydaburg is located within the service territory of Alaska Power & Telephone (AP&T) who
currently operates and maintains the electric generation and distribution system. 4 The Hydaburg
system is an isolated electrical network with no interconnection to any other utility or
transmission system outside of the existing service territory. AP&T intends to purchase the
power from the project to offset diesel generation in Hydaburg as outlined in a Memorandum of
Understanding (MOU) between the two parties, dated July 17, 1997. As the island becomes
interconnected, the project's energy will be used to meet the energy requirements of all of POWI.
To assess this need for power, AP&T's current resources and the projected regional need for
power were reviewed .
4 AP&T also holds the electrical franchise for the nearby communities of Hollis and Craig and provides wholesale
power to the community of Klawock.
August 1997 Draft 5
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
•
•
•
•
•
-
•
•
•
-
•
•
•
•
..
-
Preliminary Draft Environmental Assessment
n.B.1 Hydaburg
Currently, all electrical generation in Hydaburg is from diesel generators owned and operated by
AP&T. In 1996, the peak demand was 390 kilowatt (kW) and total sales were 1,530 Megawatt-
hours (MWh) (175 kW average). The number of customers totaled slightly less than 200.
However, peak demand has been as much as 490 kW which occurred both in 1992 and 1994.
Energy sales have increased by an average of about 50 MWh over the last ten years as shown in
Figure 2.
n.B.2 Interconnected Prince of Wales Island
The CraiglKlawock area, located 22 miles north-northwest of Hydaburg, is currently served by
AP&T and the Tlingit-Haida Regional Electric Authority (THREA). The majority of generation
is being supplied by the Black Bear Lake Hydroelectric Project (BBL). BBL is estimated to have
an average annual generation capability of25,000 MWh. Generation from BBL, in 1996, totaled
19,000 MWh. At the end of 1996, there was a surplus of hydroelectric generation on POWl.
However, a transmission intertie from BBL west to the City of Thorne Bay, the Goose Creek
Industrial Park and Kasaan has been funded and will soon be constructed. Construction is
estimated to be complete in 1999. With this interconnection in place, BBL will be essentially
100% utilized. AP&T is currently pursuing development of the South Fork Black Bear Creek
project (BBL2) to increase their hydroelectric generating capacity. The output from this project
will largely be consumed by the parallel development of a mineral processing facility near
Klawock.
n.B.3 Load Forecasts
To identify the future need for power on the island, the Applicant worked jointly with AP&T and
the Sealaska CorporationS to develop load forecasts and to identify resource options. As part of
this study, transmission interties to interconnect the communities of Hollis and Hydaburg to the
existing electrical grid system were investigated. A comparison of the load forecasts and the
utilization of resources from this study is shown in Figure 3. Since all energy in excess of
23,000,000 kWh per year must be generated using diesel fuel-fired generators, a clear need for the
project power output to offset this fuel generation would exist by the time the Reynolds Creek
Project could be constructed.
5 Sealaska Corporation is the major private landholder on Prince of Wales Island and is responsible for the
majority of the industrial activity such as logging and mining that is taking place on the island. Sealaska is also
the Regional Cotporation fonned under the Alaska Native Settlement Claims Act (ANSCA) and, thus, represents a
significant number of electrical consumers on the island.
August 1997 Draft 6
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
I I I I • I I • • • • • • • • • • I •
FIGURE 2
Hydaburg Historic Energy Sales
1,600
1,400
1,200
1,000
------------
600 -------------------------------
400
200
o +-------~------_r------_+------~--------+_------~------~------_+------~--------~----~
1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996
Year
I • • • • • I • t I • •
FIGURE 3
Annual Energy Requirements
Prince of Wales Island
(interconnected)
• • • • • •
~.---------------------------------------------------------------------------------------------
40
35
30
... 25
~
i
:E 20
15
5
o +-......,.._..---...,.........J
~
Year
o
N
~
•
•
-
-
-
-
•
•
•
•
•
•
•
•
•
•
-
•
-
-
Preliminary Draft Environmental Assessment
III. PROPOSED ACTION AND ALTERNATIVES
llI.A APPLICANT'S PROPOSAL
m.A.1 Project Facilities
The Reynolds Creek Project would consist of a 20-foot long, concrete weir, diversion dam and
intake at the outlet of Rich's Pond (Lake Mellen); a bypass pipe; a 3,200-foot long, 42-inch
diameter, steel penstock; a powerhouse; access roads (500 feet total), and a 12.3-mile long, 34.5
kV overhead transmission line. The project will be constructed in two phases. In the first phase,
the diversion/intake, penstock, access roads, transmission line and a 1.5 MW powerhouse will be
constructed. In the second phase, the powerhouse will be expanded and an additional 3.5 MW
unit will be installed, increasing the project capacity to 5 MW. The Reynolds Creek drainage is
shown in Figure 4 and general drawings of project facilities are presented in Exhibit F of the
Application for License.
m.A.2 Project Operation
General
The Reynolds Creek Project will operate almost entirely in a run-of-the-river mode, generating
electrical energy from available streamflow. During normal operation, water will be continuously
released into the bypass reach through the low level outlet of the diversion. Any additional water
up to the desired turbine flow will be diverted through the powerhouse and returned to Reynolds
Creek near the anadromous fish barrier. Turbine flow will range from a minimum of about 5 cfs to
a maximum of 90 cfs depending on the electrical load of the system and the installed capacity.
Lake Mellen will be used to synchronize the daily variations in electrical load with the daily
variations in inflow. The water balance of Upper and Lower Reynolds Creek will be the same on
a weekly, ifnot daily, time frame.
Three control modes are planned for the project. In the first control mode, the project would be
responsible for governing the system frequency. As such, the project would be required to react
to load swings ("load following") by increasing or decreasing output from the project. This would
be the control mode in the early years when the project is used to meet the needs of Hydaburg
exclusively. Once the project becomes an integrated resource in the larger Prince of Wales Island
electrical system, the project would likely see two additional modes of operation, "base" loading
and "level control". When base loaded, the project would operate at a desired output level and,
therefore, relatively constant flow level. When under level control, the project would be operated
to maximize the generation from the available water while maintaining a constant pool elevation in
Lake Mellen. In this case, inflow into Lake Mellen will be equal to outflow. In these latter two
modes, governing, or control, of the system frequency would be performed by one of the other
generating resources in the interconnected system.
August 1997 Draft 9
Reynolds Creek Hydroelectric Project
fERC Project No. 11480
I I I
Lower
Re)f1olds Creek
I
Waler Quality
Sampling Slle
RCHDR 1/1
•
I
• •
Mountain Copper
E IN FEET III~A~P~P~R~O~X~IM~;A~TE~S~C~A~L~~~~
-.-. 50~0' r--O' 2500 O' 125
• • •
t.Aiddle \
Reynolds Creek \
Pond Interlaken
• • I I
Summit Lak
1318 fmsl) (Elev.
I
~ Upper Ids Creek
r-J/ I Reyno ~3
Lake Marge
1750 fmsl) (Elev
Figure 4
•
and k Drainage
Reynolds Cree . t FaJ(c~il~it:::ie:.s~ ___ _ of Pro Jec Location
•
•
-
-
•
•
•
Preliminary Draft Environmental Assessment
When the project is operating in either a load following or base loaded mode, storage will be used
when the turbine flow required to meet the load is in excess of inflow. When the turbine flow
required to meet the load is less than the lake inflow, storage will be increased or if the lake
elevation is at the spillway crest, the excess water will be spilled. Due to the limited storage
available in Lake Mellen, the length of time and the frequency of which the project could operate
in these modes is a function of the amount of inflow to Lake Mellen and the magnitude of the load
to be met.
A description of each of these operational modes and the effect on Lake Mellen elevation and
Reynolds Creek flows are discussed in more detail below.
Load Following
In this control mode, the generating unit would be programmed to adjust to increasing or
decreasing system loads and frequency by varying the output, and hence the turbine discharge.
• The typical variation in load in the existing system is characterized by a morning and late
afternoon peak as shown in Figure 5. This would mean that the project would ramp up and down
twice a day according to the system load. Slight, and immediate variations in output would be
• expected at all times in response to instantaneous loads placed on the system, such as when
electrical motors are started or stopped. Figures 6 and 7 show the results of a week-long, hourly
simulation of this mode of operation using Block Loading •
•
•
•
•
•
-
-
-
-
With block loading, the unit would be set to a desired output level and left there for a period of
time. Generally, the desired output from the unit would probably be established weekly and
updated once or twice daily. Actual operations will vary based upon load, hydrology and other
unit availability within the system. During these load blocks, discharge from the unit will remain
constant.
Level Control
When the project is operating under level control, all available inflow up to the rated turbine
capacity is used for generation. Inflow in excess of the maximum turbine flow is passed as spill.
Flows in Lower Reynolds Creek are equal to the naturally occurring inflow. Due to the electrical
constraints of an isolated system, this mode of operation will only be possible when the project is
interconnected to the remainder of Prince of Wales Island. Actual hourly inflow data recorded at
the site.
During the early years of project operation, when the project is used to meet the loads of
Hydaburg only, the project will be able to operate in this mode at all times except for periods of
extremely low inflow. When there is insufficient water to support this mode of operation, the
project will need to operate in conjunction with another generating resource.
August 1997 Draft 11
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
• I • I • • • • • • • • • • • • t • •
FIGURE 5
Typical Electric Load Profile
100%
90%
80%
70%
~ 60%
u
III
Q.
III
(J
50% ~
III
GI a. -0
~ 40%
30%
20%
10%
0%
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour
• I • • • • • • • •
FIGURE 6
Weekly Operations Simulation
Phase 1 -1,500 kW Peak Load
Load Following Operation
• • • I • I
75r-----------------------------------------------------------------------------------------~878.0
50
25
I~v~~ __________ ~
""'---------____ A ~
_ .. -'" _. - _ .. _. _" -.. -... __ -0_ .. _ .. _"_"_" _ '" _. __ ... _ .. _ .. __ .. _ .. _. _._ .. _ .. _. _ .. _ .. _ .. _"_" ___ . __ .. _ .. _" _ .. _ .. _~_._
877.0
876.0
= c o
875.0 ti ,------------~----~~-------------..,.". ... _-------... ------------w~ ----------
,
~, . ,
...........
"
, ,
I . , .
, ,
" .. . .....
. ,
. .
-. , . , .
874.0
873.0
o ~-,---,--_+_ __ _.,__+__.. __ --t__,...__r___t__.___,__+___.___,... ___ --,.__+__.,.._...,.__+__,_ __ _+ ____ ____;--,.__.,__+_..,..__.__!_ ____ __+ ____ _+ 872.0
o 12 24 36 48 60 72 84 96 108 120 132 144 156 168
Hour
L
-----------------
---Bypass Reach Natural Inflow
- -----Turbine Flow - --• lake MelienE':
•
I • I I • I • • • •
FIGURE 7
Weekly Operations Simulation
Phase 1 -1,500 kW Peak Load
Flows OS of Powerhouse
• • • t
75.----------------------------------------------------------------------------------.
~-.... ,". . ... ,', ,--, , . .A ~ ,,"''' ~ ..... ~.~-.• ~~.-,----,~ r--~---7~
, .
' ....... /11
50
25
o 12 24 36 48 60 72
,," * "''' .. "''' ..... '" .
84
Hour
. .
...... If
96 108
'".... ...
~--'~,~-,~----~,~. ~~~~v-_~
--. .. ...... "
120 132 144 156 168
• II
•
-
-
-
-
•
•
•
•
•
. ,.
•
•
-
-
-
-
Preliminary Draft Environmental Assessment
Startup/Shutdown
A typical mode of operation for use of deflectors is to set up the turbine so that if generation shuts
down for any reason, the deflectors are swung into position, and flow is maintained through the
turbine until such time as a plant operator can assess the reason for the plant shutdown. Flows
through the turbine would be reduced to a minimum level when the deflectors are in place. If, as is
often the case, the unit could be restarted within a short amount of time, the deflectors would be
left in place until the unit is restarted. If, however, it is clear that the turbine would have to be
shutdown for an extended period, the flow through the jets would be slowly shut-off. It is
proposed that the turbine for this project be operated in this way to maintain flow downstream of
the powerhouse during unplanned shutdowns. During startup, the process is reversed.
Lake Mellen
Lake Mellen has a surface area of approximately 150 acres at elevation 876 feet mean sea level
(fins!). Average annual inflow to the lake is 43,300 acre-feet. Lake Mellen naturally experiences
elevation changes in the order of two feet due to changes in inflow as recorded and shown in
Figure 8.
During normal operation of the project, the pool elevation will be at or near the crest elevation of
876 fins!' Inflows in excess of the required turbine flow will pass over the diversion as
uncontrolled spill. During periods of extended low inflow, or to account for daily variability in
inflow, storage in Lake Mellen will be used to supplement natural inflow. On a day-to-day basis,
little variation in pool elevation is expected.
Drawdown of Lake Mellen will be limited to a minimum elevation of 872 finsl which equates to
about 600 acre-feet of usable storage, or about 1 % of the average annual yield of the system.
During the months of April and May, the minimum drawdown elevation will be limited to
elevation 874.5 finsl to facilitate resident fish migration upstream into Middle Reynolds Creek. If,
and when, the elevation of Lake Mellen reaches the minimums described above, project
operations will be curtailed until sufficient inflow returns to the system. During any drawdown
times, flow will always be entering the bypass reach via the uncontrolled low level outlet .
Bypass Reach Flow Regime
The bypass reach of Reynolds Creek will extend from the intake location at the outlet of Rich's
Pond approximately 3,500 feet downstream to the tailrace location (Figure 4). The average
gradient in the diversion reach is 23%. Much of the diversion reach is located in incised bedrock
with isolated step pools forming at low flows. During project operation, flow in the diversion
reach will be a combination of releases from the low level outlet, spill and local runoff.
August 1997 Draft 15
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
I • • •
4.00
3.80
3.60
3.40
5:3.20
l! .2'
GI x 3.00
GI
t7I
fa
(!)
2.80
2.60
2.40
2.20
2.00
III ...
• • i I •
FIGURE 8
Lake Mellen Elevation Changes
April 1S-Sep 22, 1996
Days of Record
I • • I • •
•
-
-
•
Preliminary Draft Environmental Assessment
A minimum in stream flow will be released through the low level outlet on the diversion structure.
This flow will be continuous and will be senior and independent of flows used for power
generation. Spill flows will occur anytime the elevation of Lake Mellen is at elevation 876 finsl
and inflow into the lake exceeds the required turbine flow required for generation. The 0.5 square
miles of drainage area of the bypass reach can be expected to contribute on average an additional
6 cfs of flow.
Lower Reynolds Creek Flow Regime
.. Flows in Lower Reynolds Creek immediately below the tailrace will be the sum of bypass reach
flows and power generation flows. These flows will increase with the addition of unregulated
tributary flows which enter approximately 700 downstream of the tailrace. During average and
wet years, and during most dry years, flows in Lower Reynolds Creek under project operation
will generally be the same as are occurring naturally now with the exception of the daily
fluctuation that is described above.
During extreme low flow periods which could occur in any year, water will be drawn from
storage to supplement naturally occurring inflow when required. This will result in an
*' enhancement of flows in Lower Reynolds Creek until such time that the usable storage in the
system has been exhausted. When enhancement flows can no longer be provided by the system,
flows in Lower Reynolds Creek will revert back to natural flows. Following a period of low flow,
flows in excess of the minimum in stream flow and the turbine flow will be used to replenish the
flows that were used previously for enhancement. This will result in a slight "shaving" of the
flows in Lower Reynolds Creek
, ..
-
•
-
-
ID.A.3 Proposed Environmental Measures
Several measures have been built into the project design to ameliorate or mitigate for potential
adverse impacts of project construction and operation. These measures have largely been
incorporated as best management practices (BMPs), as a result of identification of potential
adverse impacts by the Applicant's design team, or by agency comments during scoping or
consultation. To protect and/or mitigate impacts on environmental resources, Haida Corporation
proposes to:
Construction Precautions
•
•
Provide erosion and sediment control measures during construction and operation
of the project by implementing the Erosion and Sediment Control Plan in Appendix
B of the Application for License.
Prohibit hunting, trapping, and fishing by construction personnel during the
construction of the project.
• Minimize area of disturbance for construction of project facilities.
August 1997 Draft 17
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
Preliminary Draft Environmental Assessment
• Lake Mellen Elevation Operating Regime
•
'.
•
..
..
•
-
•
-
• Maintain lake elevation during the potential grayling spawning period (April
through May) above elevation 874.5 finsl to ensure that grayling have normal
access to potential spawning areas.
• Maintain the elevation of Lake Mellen between 876 and 874 finsl during the
remainder of the year, under normal hydrologic conditions and power demand.
Under extreme conditions, lake level may be drawn as low as 872 finsl.
•
•
Monitor grayling spawning in tributaries to Lake Mellen in Years 1 and 2
following construction to ensure that access to spawning areas is not hindered by
lake elevation changes.
Modify the inlet stream to Lake Mellen to provide a somewhat greater flow in an
eastern tributary that currently lacks sufficient flow to allow grayling access for
spawning, as mitigation for potential lost grayling spawning or rearing habitat in
the reach between Lake Mellen and Rich's Pond.
Instream Flows in Bypass Reach
• Install a low-level outlet in the diversion structure to continuously release flows
into the bypassed reach of Reynolds Creek. The outlet would be unregulated and
would be sized to release 5 cfs at a pool elevation of 872 finsl.
Powerhouse and Tailrace Location
•
•
Locate the tailrace between elevation 90 and 95 feet, near the limit of accessibility
of anadromous fish and above the area of significant spawning or rearing habitat;
thus, diversion of water between Lake Mellen and the tailrace will not have a
significant effect on anadromous fish reproduction .
Design the tailrace to prevent access or attraction by fish and to dissipate
remaining hydraulic energy before release of water to the creek.
Transmission Line Features
•
•
Locate the transmission line to maximize the proportion of the route that follows
existing roads; virtually the entire route will cross areas that have been c1earcut
within the last 15 years.
Locate the transmission line in accordance with FAA requirements for aircraft
safety and incorporate in the design state-of-the-art devices for raptor protection
and diverters, where appropriate, for the protection of bird life.
August 1997 Draft 18
Reynolds Creek Hydroelectric Project
fERC Project No. 11480
..
•
•
..
-
Preliminary Draft Environmental Assessment
Access Roads
• Utilize existing timber harvest roads to the greatest extent possible to reduce the
amount of disturbed project area.
m.B MANDATORY CONDITIONS
Haida Corporation is seeking benefits under Section 210 ofPURPA and believes that the project
meets the definition under Section 292.202 (p) of 18 CFR for a new diversion. As such, the U.S .
Fish and Wildlife Service, the National Marine Fisheries Service, and the state agency exercising
authority over fish and wildlife resources of the state (Alaska Department ofFish and Game) have
mandatory conditioning authority under the procedures provided for at Section 30 (c) of the
Federal Power Act.6
m.c MODIFICATION OF APPLICANT'S PROPOSAL
Throughout the development of the PDEA, a variety of measures and modifications were identified
that served to address potential environmental impacts and! or agency comments that were raised
during the agency consultation process. Because the "Applicant-prepared EA" process occurs
simultaneously with the development of the Application for License, these modifications were
incorporated in Haida Corporation's proposed project as they were identified. After the PDEA and
Application for License are reviewed by the Commission staff, other modifications to Haida
Corporation's proposal may be recommended.
m.D NO ACTION ALTERNATIVE
Under this alternative, the Reynolds Creek Project would not be constructed. The City of
Hydaburg would continue to receive power from fossil fuels for the foreseeable future. The noise
and air quality impacts of the existing generation system would continue unabated or at increased
levels as the local demand for power increases. The risk of spills of diesel fuels would likewise
continue at current or increasing levels. No project facilities would be built in the Reynolds Creek
drainage and no new transmission lines would be constructed.
The financial benefits to the residents of Hydaburg in the form of lower electrical rates and to the
Haida Corporation in terms of project operating revenues would not be realized. Ultimately, the
intertie between CraiglKlawock and Hydaburg might be built and Hydaburg could be supplied by
hydroelectric generation from other projects on the central or northern part of the island. This
eventuality could result in elimination of the need for local diesel generation of power but would
not provide the same level of economic benefit to the people of Hydaburg and to the Haida
Corporation that would be derived from the Reynolds Creek Project.
6 U.S.C. Section 797 (e)
August 1997 Draft 19
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
•
•
ill
-
-
•
-
..
Preliminary Draft Environmental Assessment
IV. CONSULTATION AND COMPLIANCE
IV.A AGENCY CONSULTATION
The Commission's regulations require applicants to consult with the appropriate resource
agencies before filing an Application for License. This consultation is the first step in complying
with the Fish and Wildlife Coordination Act, the Endangered Species Act, the National Historic
Preservation Act, and other federal statutes. Pre-filing consultation must be complete and
documented according to the Commission's regulations. Copies of all consultation
documentation as of August 15, 1997, are located in Appendix G of the Application for License.
IV.B INTERVENTIONS
Currently, there are no intervenors on the proposed project. The Sealaska Corporation and the
National Marine Fisheries Service (NMFS) filed motions to intervene on FERC Project No. 11480
during the time the Application for Preliminary Permit was being reviewed by the FERC. Those
motions were granted.
In their motion, the NMFS requested that (1) any permit issued for the project include an article
requiring the permittee to conduct fishery and need for project studies, and (2) that NMFS be an active
party to the development of these studies. Article 9 of the Preliminary Permit requires the permittee
(Haida Corporation) to consult with the NMFS during the pre-filing consultation process to coordinate
any necessary studies for FERC Project No. 11480.
In their motion to intervene, Sealaska Corporation only requested party status.
A notice soliciting interventions wiU be issued when the Commission accepts the Application for
License.
IV.C SCOPING
The First Stage Consultation Package and Proposed Study Plan for the Reynolds Creek Project
was issued on January 26, 1995.
As part of the three-stage consultation process required under Commission regulations, a joint
public/agency/Applicant meeting was held at the Ketchikan City Council Chambers on March 14,
1995.
An interagency overview meeting was also held in Hydaburg on July 20, 1995, followed by a site
visit for representatives of the Alaska Department of Fish and Game (ADFG), U.S. Fish and
Wildlife Service (USFWS), and National Marine Fisheries Service (NMFS) to view the project
site, discuss the project, identity agency data on resources of concern, and discuss their policies
regarding permit application processes. The participants agreed that impacts on terrestrial species
would be minimal and that fish species (grayling and salmonids) would be their primary concern
with respect to potential impacts from the project.
August 1997 Draft 20
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
-
-
..
•
-
•
Preliminary Draft Environmental Assessment
Scoping Document 1 (SOl) was issued on March 15, 1996. Comment letters were received from
various agencies.
Teleconference meetings were held on March 8 and 18, 1996, to discuss spring 1996 survey plans
and subsequent monitoring of the status of grayling populations. The teleconferences included
representatives of ADFG and USFWS.
Scoping meetings were held on May 6, 1996, in Ketchikan and in Hydaburg. Agencies attending
one or both scoping meetings included ADFG and USFWS.
An additional site visit was conducted for the agencies on May 7, 1996.
A project meeting was held in Ketchikan on December 3, 1996, and was attended by
representatives of ADFG and USFWS. At this meeting the Applicant presented details of the
design and operating regime to address agency concerns regarding potential project effects on
grayling spawning.
A site visit was held with ADFG on April 23, 1997, to determine the location of the anadromous
fish barrier on Lower Reynolds Creek.
Scoping Document 2, which was based on SD 1 and addressed the comments and requests for
additional studies received during the NEP A scoping process, and contained copies of all
consultation correspondence and responses developed in reply to concerns identified in agency
letters and at the scoping meetings, was promulgated via a letter dated July 18, 1997.
IV.D WATER QUALITY CERTIFICATION
Haida Corporation will request water quality certification under Section 401 of the Clean Water
Act by submitting to the Alaska Department of Environmental Conservation (ADEC) a copy of
their application for a U.S. Army Corps of Engineers (Corps) permit to discharge dredged or fill
material into navigable waters under Section 404 of the Clean Water Act. By agreement between
the Corps and the ADEC, an application for the Corps permit may also serve as application for
water quality certification. This process will be initiated prior to filing the Application for
License.
• IV.E COASTAL ZONE MANAGEMENT ACT PROGRAM
•
-
-
Under the Coastal Zone Management Act of 1972 (CZMA), as amended, before the Commission
can issue a license for a project, the state must find the project consistent with the state's Coastal
Management Program. State review commences on receipt of a consistency certification which is
presumed in the absence of a state's objection within six months after the state begins its review.
The Alaska Division of Governmental Coordination (ADGe) coordinates the state's consistency
review under the CZMA. This process will be initiated prior to filing the Application for License.
August 1997 Draft 21
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
..
...
•
•
..
-
..
•
..
..
-
-
-
..
-
Preliminary Draft Environmental Assessment
V. ENVIRONMENTAL ANALYSIS
In this section the general environmental setting of the project is described, followed by a
discussion of the site-specific effects on the resources affected by the proposed action, alternative
configurations, and the No Action Alternative. A cumulative effects analysis is also presented for
selected resources.
V.A GENERAL DESCRIPTION OF THE REYNOLDS CREEK WATERSHED
Reynolds Creek is a high gradient stream that originates in mountains to the north and east of
Copper Harbor on the southwest side of Prince of Wales Island (POWI). POWl is part of the
Alexander Archipelago of southeast Alaska islands (Figure 1). The Reynolds Creek drainage
(Figure 4), is a narrow glacial valley. Valley walls are steep and wooded except where rock cliffs
are too steep for vegetation or where avalanche paths limit vegetation to shrub.
Reynolds Creek (Upper Reynolds Creek) flows from Lake Marge at about 1,750 feet above sea
level, down a series of cascades to Summit Lake at about 1,318 feet above sea level, then through
a relatively wide and gently sloping valley to Lake Mellen at about 876 feet above sea level
(Figure 4). From Lake Mellen the stream (Lower Reynolds Creek) flows through a steep narrow
canyon to about the 100-foot elevation. Below this elevation the valley widens somewhat, and
the gradient decreases as the stream flows into the head of Copper Harbor on the east side of
Hetta Inlet.
The Reynolds Creek valley was largely unlogged and had no passable roads until 1997. A portion
of the drainage of a major tributary to Reynolds Creek (entering from the north about 400 feet
above tidewater) was clearcut prior to 1994. Additional areas in the drainage of this tributary
were disturbed in the early part of the century by copper mining activity high on Copper
Mountain, a 3,900-foot peak one mile to the north of the mouth of Reynolds Creek. When
mining began, the small enclave of Coppermount was built on the north side of the head of
Copper Harbor. This town included a smelter that handled ore from Copper Mountain and other
mines in the Hetta Inlet area. The mining and smelting activity was short-lived, and the town site
has been abandoned for over half a century. No permanent structures remain there or anywhere
else in the Reynolds Creek drainage.
In 1997 the major landowner in the Copper Harbor and Reynolds Creek drainage, Sealaska
Corporation, initiated road building and logging in the drainage. Based on conversations with
Sealaska, it is expected that the majority of marketable timber in the drainage will be cut by the
time the Reynolds Creek Project is constructed. Logging roads were constructed near the vicinity
of the proposed powerhouse in 1997 and are planned near the outlet of Lake Mellen.
August 1997 Draft 22
Reynolds Creek Hydroelectric Project
FERC Project No. J 1480
•
..
-
-
•
•
•
•
•
-
•
•
•
•
-
•
-
..
Preliminary Draft Environmental Assessment
V.B PROPOSED ACTION AND ACTION ALTERNATIVES
V.B.1 Geology and Soils Resources
Affected Environment
The project site lies on the contact of a large igneous rock mass (granodiorite) overlain by a thin
layer of soil. Granodiorite is exposed on the glacially scoured cliffs and outcrops of the upper and
middle Reynolds Creek drainage. The gorge between Lake Mellen and Lower Reynolds Creek is
carved into granodiorite by glacial and stream action. The streambed at the outlet to Rich's Pond
is comprised of a large blocky coluvial deposit The granodiorite along Lake Mellen is very hard
and contains tight joints which strike east to west. Grandorite is present along approximately half
of the penstock route and then transitions into homfelsic metamorphosed rocks and to marble
along the lower reach of Reynolds Creek near the powerhouse site.
Soils within the project area have been developed from a variety of organic and inorganic sources.
Inorganic soils developed from glacial deposits, uplifted marine sediments, metamorphic and
igneous rocks. Organic soils developed from deposits of decomposed plant material that
generally collect in poorly drained areas associated with low relief Acidic organic soils that
support open areas of herbaceous vegetation are referred to as muskeg.
The area surrounding Rich's Pond is comprised of exposed bedrock and areas of muskeg. The
soils along the penstock route are generally thin «10 feet) and stable due to the heavy vegetative
cover that is providing additional cohesion to the soil mass. The soils along the lower reach of
Reynolds Creek near the powerhouse site and the outlet of Reynolds Creek are comprised of
alluvium and could have a thickness of 10 feet or more. This soil consists mostly of a granular,
sand and cobble mixture having little to no cohesion. The cohesion that is currently being
provided by the heavy vegetative cover will be reduced significantly as the timber in the basin is
harvested.
Within the basin, the existing slopes are relatively stable. Minor surficial soil creep is occurring
but is limited to the top one to two feet ofloose top soil (clay, silt, and sand) and organic cover
that is in close proximity to steep slopes. This type of movement is common on saturated,
oversteepened soil slopes that are underlain by a rock base. Mass wasting, in the form of large
block failure, has been observed in the creek's canyon vertical cliffs and along steep slopes.
Numerous faults have been mapped in the vicinity of the project. These faults generally have a
northwest to northeast trend. While no major destructive earthquakes have been reported in this
area, southeast Alaska is considered to be seismically active.
August 1997 Draft 23
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
-
-
-
-
•
•
•
..
-
..
•
••
-
..
..
..
-
..
Preliminary Draft Environmental Assessment
Environmental Impacts and Recommendations
Construction
Vegetation removal, excavation, and blasting during project construction would temporarily increase
turbidity and sediment in the project area. Most construction-related sedimentation at the project site
would be the surface runoff However, there is the potential for blasted rock to reach Reynolds Creek
during powerhouse excavation. Construction of the diversion/intake structure and a short reach of the
tailrace will require in-stream construction work In-stream construction work will increase the
turbidity in Reynolds Creek as the streambed is disturbed during excavation and construction and
removal of cofferdams.
The Applicant has developed a draft Erosion and Sedimentation Control Plan (ESCP) that will be
finalized when the project undergoes final design. The ESCP includes measures for capturing
sediment before it reaches Reynolds Creek or Rich's Pond or any of the other small tributaries in
the drainage area. The ESCP measures include using sediment ponds, sediment barriers, soil
erosion matting and mulches, drains, etc. to prevent sediment laden runoff from leaving the
project site. The final ESCP would detail the specific measures to be used at specific locations at
the project site. The ESCP also describes measures to revegetate disturbed areas. The ESCP will
be made part of any construction-related contract package. ESCP measures will be routinely
inspected by the Applicant's on-site field representative to ensure that the objectives of the ESCP
are being met.
Construction activities that will directly involve contact with Reynolds Creek water, such as
construction and removal of cofferdams and connection of the tailrace will occur between June 15
to August 15.
Operation
Localized slope failures may occur along the penstock route or near the powerhouse as the result
of timber harvesting activities in the basin. The tailrace could be blocked or damaged by a debris
torrent or high flood event.
The project will be inspected and maintained on a routine basis. Slope instability that could affect
the integrity of any of the project structures will be stabilized as soon as possible.
Unavoidable Adverse Impacts
Minor, temporary, localized erosion would be unavoidable during project construction until disturbed
surfaced are stabilized and revegetated. Construction of the diversion/intake structure will require in-
stream work to place and remove temporary water retaining structures and flow diversions. This work
may temporarily cause existing sediment in streambed to travel downstream .
August 1997 Draft 24
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
-
-
•
•
•
•
•
•
•
•
-
-
-
-
-
Preliminary Draft Environmental Assessment
V.B.2 Aquatic Resources
Affected Environment
Climate
Climatic conditions at the site are dominated by weather systems originating in the Gulf of Alaska.
Both high and low temperatures are moderated by the proximity to saltwater. Over much of the
year, particularly from September through June, low pressure systems bring extensive moisture to
the region. These systems are often accompanied by strong winds, especially in the fall and
winter. Average annual rainfall usually exceeds 100 inches per year. Near sea level, the majority
of the precipitation falls as rain; increasing amounts of snow fall above about 1,000 feet in
elevation. Infrequent high pressure systems bring colder air to the region for periods of up to 5 or
10 days in winter with temperatures falling into the teens or lower. High pressure and dry periods
are more common in the late summer with high temperatures into the 60s and 70s.
Hydrology
Streamflow data was recorded from two USGS gages on Reynolds Creek. USGS gaging Station
No. 15081995 (located on Reynolds Creek at Lake Mellen outlet, with a drainage area of 5.2
square miles and the gage datum at elevation 860) operated for the period July 1982 through
September 1985. USGS gaging Station No. 15082000 (located on Reynolds Creek near its
mouth to Copper Harbor, with a drainage area of 5.7 square miles and the gage datum at
elevation 50) was in operation for the period June 1951 through September 1956. The Applicant
used a correlation analysis based on the streamflow record of Fish Creek near Ketchikan (USGS
Station No. 15072000) to extend the Reynolds Creek daily streamflow data to a 71-year period
from June 1915 to September 1989, absent 3 years of data from November 1935 to September
1938. Based on this methodology, the average annual outflow from Lake Mellen is estimated to
be 60 cfs. Unpublished flow data has also been recorded by the Applicant for water year (WY)
1996. Table 1 shows the estimated monthly average, high, and low flows in Reynolds Creek at
the point of diversion.
Lake Mellen, with a surface area of 150 acres, drains 5.2 square miles and provides a usable
storage of about 600 acre-feet. Reynolds Creek flows approximately one mile from its natural
outlet at Lake Mellen through Rich's Pond to saltwater in Copper Harbor. Reynolds Creek,
below Rich's Pond to the powerhouse site, has an average gradient of23%.
August 1997 Draft 25
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
•
•
•
•
•
•
..
•
•
..
-
..
..
-
-
Preliminary Draft Environmental Assessment
TABLE 1
REYNOLDS CREEK
A VERAGE MONTHLY FLOWS
Average Minimum Maximum
Month (cfs) (cfs) (cfs)
October 83 51 124
November 63 38 93
December 51 19 97
January 58 18 129
February 63 24 107
March 43 15 98
April 49 20 86
May 80 52 124
June 69 38 90
July 38 27 50
August 43 11 79
S~tember 49 20 76
Streamflows peak below Lake Mellen with rains in October and November. A secondary peak
due to snow melt occurs in May and June. Low flows occur in mid-to late summer and mid-
winter.
Water Quality
Water quality in the Reynolds Creek system is generally excellent. However, road building and
logging activity which began in the drainage in 1997 has the potential to alter water quality in
Lake Mellen and Lower Reynolds Creek. It is expected that increased erosion and resulting
sedimentation will enter the system's surface waters at several points and result in some increases
in the very low suspended sediment loads and turbidities seen in the baseline. These increases will
be greatest during periods of high rainfall and in the first few years following completion of
logging. Vegetated hillsides are generally stable and yield little sediment, even under conditions
of heavy rainfall. Numerous lakes, ponds, and areas of muskeg retain suspended materials and the
cascading nature of all streams provides high oxygen levels. The water is generally soft and low
in dissolved minerals with conductivity of 18 to 35 Jlrnhos/cm2 in the lakes and Reynolds Creek.
Water quality data has been and will continue to be collected at two sites: RCHDR #1 near the
tailrace discharge location and RCHDR #2 in Rich's Pond near the outlet of Lake Mellen (see
Figure 4). Table 2 lists water quality data available to date .
August 1997 Draft 26
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
-
-
•
•
-
-
-
•
••
-
-
-
-
-
-
Preliminary Draft Environmental Assessment
TABLE 2
REYNOLDS CREEK WATER QUALITY DATA, 1995 TO 1996
I
Air Water
Temp. Temp. Conductivity DO Turbidity TSS
Date' Sitez (0C) (OC) pH I (Illdhosfeml ) (ppm) (NTU) (ppm)
Jul-95 5 22 16.2 -30 ---
8 25.5 17.8 -30 ---
23-Apr-96 8 -4 -20 --
21-May-96 7 -7.8 7.38 20 9.9 0.39 -
2 -8.5 7.48 77 11.7 0.39 -
7-Jun-96 7 -8 25 ---
23-Apr-97 I RCHDR #1 6.5 3.8 5.8 22 -0.1 U'
RCHDR#2 10.3 3.2 5.1 21 0.27 U
"10 T. -97 RCHDR#1 17.1 15.8 7.6 0 10.1 0.1 0.6
RCHDR#2 17.1 14.6 7.6 0 10.2 0.1 1.1
II Average 6.53 2 .02 0.14 0.43
1 1995 and 1996 data collected by Pentec Environmental; 1997 data collected by HDR Alaska, Inc.
2 Sites 2 and 5 correspond to RCHDR #1. Sites 7 and 8 correspond to RCHDR #2.
3 Undetectable.
The data, although limited, illustrate that the current water quality is unimpaired. Water
temperature exhibits the expected normal seasonal variability, corresponding to changes in air
temperature. Dissolved oxygen in the system has a high concentration and percent saturation
(approximately 80%-100%). This would be expected with the relatively low water temperatures
and high turbulence experienced in the stream channels between lakes. The pH is near neutral.
Turbidity and total suspended solids (TSS) are low or near the method detection limit. This
indicates that there is naturally very little sediment entering the system.
A clearer picture of seasonal changes in water quality parameters IS expected to emerge as
monitoring continues.
Water Rights
On July 27, 1995, the Haida Corporation filed an application with the Alaska Department of
Natural Resources for a water right of 30 cfs from Reynolds Creek to operate the project on a
continuous basis.
Fish and Aquatic Life
The Reynolds Creek system supports both resident and anadromous fish. In 1962 and 1967,
Alaska Department of Fish & Game (ADFG, 1982) introduced Arctic grayling (Thymallus
arcticus) into Lake Marge and Summit Lake in an attempt to establish fish in these lakes, which
had remained barren since the retreat of the glaciers. Since then grayling have become well
established in the three larger lakes (Marge, Summit and Mellen) and in connecting stream
reaches and ponds.
August 1997 Draft 27
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
..
..
-
-
Preliminary Draft Environmental Assessment
Lower Reynolds Creek, below the canyon that begins at the outlet of Lake Mellen, supports
several species of both resident and anadromous fish. Resident cutthroat trout is the only species
collected in the steep pools of the canyon above the limit of anadromous fish migrations. General
timing of the various life history stages of fish in the Reynolds Creek system is indicated in Figure
9. Results of the Applicant's studies on fish and aquatic life in the Reynolds Creek drainage are
provided by Pentec (1997a).
Upper Watershed
• The upper watershed of Reynolds Creek consists of Lake Marge, Summit Lake, Jack's Pond,
Julie's Pond, and interconnecting stream reaches and unnamed ponds. Stream sections of
Reynolds Creek in the upper watershed vary from steep cascades to low gradients (Figure 4).
•
•
•
-
..
-
•
-
-
-
-
•
-
-
Reynolds Creek begins at the outlet of Lake Marge, the uppermost water body in the Reynolds
Creek system. This lake is approximately 96 acres and is about 1,750 finsl (ADFG, 1982). A
large waterfall (26-32 feet) at the outlet of Lake Marge prevents return of any fish leaving that
lake. A senes of shallow ponds provide excellent grayling habitat on a bench between Lake
Marge and Summit Lake; Reynolds Creek leaves this bench via a series of falls and cascades
dropping down to Summit Lake.
Summit Lake (384 acres) lies in a steep mountain valley on the east flank of Copper Mountain
(Figure 4). The lake surface elevation varies naturally from about 1,321 feet to about 1,315 feet.
Fish habitat potential may be limited by the limited accessible inlet stream spawning habitat since
the inlet from Lake Marge is too steep for grayling to ascend. The outlet of Summit Lake flows
through a narrow notch in bedrock directly into a series of cascades that mark the beginning of
middle Reynolds Creek.
A viable population of grayling resides in Summit Lake, although the source of recruitment is
unclear. There is a strong possibility that some fish move downstream into Summit Lake from the
outlet ponds of Lake Marge. It is also probable, based on the 1996 ADFG surveys, that grayling
spawn in the larger of the northwest inlet streams.
Below Summit Lake, Reynolds Creek flows down the northwest side of a relatively broad valley
of gently rolling terrain toward Interlaken and Lake Mellen (Figure 4). Overall the creek in this
reach has a moderate to high gradient that is punctuated with several areas of higher gradient with
waterfalls and cascades. The cascades at the outlet of Summit Lake prevent the return to the lake
of any fish who move downstream.
Interlaken and Lake Mellen
Interlaken is a heart-shaped pond about 13 feet above Lake Mellen and connected to it by a short
(330 feet) reach of Reynolds Creek (Figure 4) Interlaken has a bottom and shores composed
primarily of cobble-size and larger talus. Both inlet and outlet are broad and unconstrained; the
water level does not appear to fluctuate significantly throughout the year. A high waterfall about
650 feet upstream of Interlaken limits the upstream movement of fish from Interlaken. Reynolds
Creek flows into the northern lobe ofInterlaken and two much smaller creeks feed the pond from
August 1997 Draft 28
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-Figure 9 Timing of Fish Life History Stages in Reynolds Creek System
Jan. Feb. Mar. A~ June July Aug. Sept Oct. Nov. Dec.!
-Pink Salmon
Spawning I I
• Incubation I I
Freshwater rearing I C
• Marine rearing 15 To 18 Months
Chum Salmon
Spawning I I
Incubation I I
Freshwater rearing C
Marine rearing 2 to 3 years
Coho Salmon •
Spawning I
Incubation
" -Freshwater rearing 1 to 2 years
Marine rearing 2 to 3 years ..
Rainbow/Cutthroat Trout
Spawning
•• Incubation I
Freshwater rearing 1 to 2 years
Marine rearing 2 to 3 ~ears before first spawning migration
Arctic Grayling
I _I I I I I
Spawning migrations (some fish spend summer in stream) -
Incubation I I ,.
Instream rearing (YOY) I I
Lake residency Uuv.) I -Lake residency (adults)
I
00214'005\append\1lshtimeJds -
•
-
•
-
-
-
•
•
•
•
•
-
-
-
-
-
•
Preliminary Draft Environmental Assessment
the east. These creeks are partially blocked by old beaver dams and are associated with a muskeg
wetland northeast of the pond. Reynolds Creek has built a small deltaic fan of rubble where it
enters Interlaken; at lower streamflows, a lower gradient distributary channel splits from the main
creek channel about 100 feet above the pond. The lower reaches of the Reynolds Creek inlet and
the smaller inlet stream below the older beaver dams are used for spawning by grayling and
Interlaken supports a healthy grayling population.
Lake Mellen is a small, T-shaped sub-alpine lake at an elevation of876 finsl (Figure 4). The basin
is steep-sided and rocky with old-growth evergreen vegetation down to the water's edge. The
shoreline of Lake Mellen is generally composed of talus and bedrock. Shoreline habitat is
enhanced by numerous trees that have fallen from the banks. Although steep in most places, the
lake bed near the inlet is relatively flat, shallow, and strewn with grounded logs. The shoreline
adjacent to the inlet is composed of loose, cobble-sized talus. The inlet of Reynolds Creek to
Lake Mellen is similar to the inlet to Interlaken with a small deltaic fan of rubble and a lower
gradient distributary channel split from the main creek channel (Figure 10). Deep pools and
relatively low velocity areas adjacent to the main channel would appear to offer excellent instream
habitat for grayling for about 100 feet above the lake. At that point a bedrock ledge crosses the
stream creating a drop of about three feet that may prevent or at least limit upstream access; it is
unclear if grayling from Lake Mellen can migrate up to Interlaken.
In July 1997, fyke net and hoop net sampling was conducted to index grayling populations at
three locations in Lake Mellen. The catch rates were very low at all stations and it was concluded
(Pentec 1997a) that this technique would not provide an adequate index.
Rich's Pond is fairly shallow. It has one broad, very shallow lobe with a silty bottom and a single
small island. The rest of the pond shoreline is composed of talus and rock. Yellow pondweed
(Nuphar polysepa/um) is sparsely dispersed throughout the shallow margins ofthe pond.
The outlet of Lake Mellen is formed by a shallow sill that has collected a large quantity of logs
that are aligned across the outlet where they have floated and grounded on the sill (Figure 11).
Grayling were abundant along and among these logs in July 1995 and 1997. Downstream of these
logs, the outlet passes through a broad, shallow channel about 197 feet long into a separate
downstream subbasin (Rich's Pond) that is about six feet lower than the main lake (Figure 11).
This connecting channel has a rock rubble bed that is covered with a dense growth of filamentous
algae during the spring and summer. Apart from the algal growth, this stream segment would
appear to offer excellent habitat for grayling young-of-the-year (YOY) or adults with relatively
quiet water margins, excellent cover, and deep pools.
Except during high runoff conditions, the outlet from Rich's Pond disappears beneath the surface
and flows through boulder-sized talus near the site of the proposed diversion structure. Flow
emerges from the talus into the first of a series of cataracts leading directly into the steep, rocky
canyon. This canyon carries the stream precipitously down to the lower reach of Reynolds Creek.
August 1997 Draft 30
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
..
-
-
-
•
•
•
•
•
iii
,
•
•
-
-
-
•
•
-
Lake Mellen
ELEV. = 876 fmsl
.... Survey monument "0" at elevation 880.3 fmsl
Interlaken
889 fmsl
APPROXIMATE SCALE IN FEET P-t.-__
0' 50'
Figure 10
Topography of Lake Mellen
Inlet of Interlaken Pond
200'
•
-
-
-
•
•
•
-
-
-
•
-
•
Rich's Pond
ELEV.=870
With Vegetation
Lake Mellen
ELEV. = 876 fmsl
Log
Jam
APPROXIMATE SCALE IN FEET
100'
Figure 11
Topography of Lake Mellen Outlet
to Rich's Pond
200'
•
-
-
•
•
•
•
•
•
•
-
-
-
Preliminary Draft Environmental Assessment
Lower Reynolds Creek
Lower Reynolds Creek flows through an old-growth forest typical of lower elevations on POWl.
About 1,300 feet of the stream, to an elevation of approximately 95 feet above sea level, is
accessible to anadromous fish. Stream gradient is relatively constant up to the site of an old
USGS gaging station at about elevation 75 feet. Above this point, gradient increases to about
11 percent for the 90 feet between the 80-and 90-foot elevations. Above the 90-foot elevation,
gradient increases to about 25 percent for the short distance (about 40 feet) up to the anadromous
fish barrier. The ADFG Anadromous Stream Catalogue, Stream 10420 on Craig A-2 quadrangle
(ADFG, 1992), shows use of Reynolds Creek by coho, chum, and pink salmon (Oncorhynchus
kisutch, 0. keta, 0. gorbuscha, respectively).
ADFG has records of aerial counts of salmon spawning escapement to streams in the Copper
Harbor area since at least 1974 (data provided courtesy of S. Walker, ADFG Commercial Fish
Division, Ketchikan). Because of the size of the streams and the dense tree canopy, the data are
primarily from saltwater. Thus, the numbers (Table 3) may represent fish from several streams.
These data show numbers of pink salmon in the harbor peaking from mid-August into early
September and chum salmon present only after mid-September. Peak numbers of pink salmon in
the harbor and lower streams have exceeded 100,000 twice in the last 10 years (ADFG statistics).
Chum salmon have been inconsistently reported because surveys are only infrequently conducted
after the first week in September. The maximum reported number of chum salmon is just over
100 (Table 3) but numbers seen in September 1995 suggest much higher run sizes are likely. No
other adult salmon were reported, but juvenile coho and trout (Oncorhynchus clarki and/or 0.
mykiss) fry were reported by Pentec and ADFG observers.
Pink salmon begin to move into Reynolds Creek in mid-to late August (Figure 9). Initial
spawning probably occurs in lower stream areas; access to areas farther upstream probably
becomes easier as fall rains increase in September. Spawning probably peaks in late August or
early September and extends through September. Fry leave the streambed gravels in early spring
and move quickly to marine areas to rear. Chum generally enter the system somewhat later in the
fall than do pink salmon, but the presence of numerous active spawners and a few spent fish seen
in early September suggests a considerable overlap with pink salmon activity. It is likely that
chum salmon continue to spawn into mid-October; only relatively old carcasses were seen along
the river banks in early November 1994. Like pink salmon, chum fry leave the system quickly
upon emergence from the gravel (Figure 9).
As previously noted, above the old USGS gaging station, stream gradient increases progressively.
Numbers of spawners in September 1995 dropped markedly in proportion to the diminished area
of the stream that had velocities and turbulence in which fish could rest or spawn. Despite this,
pink salmon were visible in each stream margin area without turbulence for about 140 feet
upstream of the log crossing below the gaging station (Figure 4). Fish were moving upstream by
actively jumping cascades or by bypassing the thalweg and moving upstream along the stream
margins. At about 140 feet above the gaging station (elevation 85 feet) is a cascade system 6 to 8
August 1997 Draft 33
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
..
-
-
•
•
-
•
-
•
. ..,
-
-
-
-
-
Preliminary Draft Environmental Assessment
TABLE 3
ANADROMOUS FISH COUNTS FOR REYNOLDS CREEK (COPPER HARBOR)
Date Survey Type
26-Aug-63 Air
07-Se~-66 Field
20-Sep-n Field
09-Aug-73 Air
12-Aug-73 Air
15-Aug-73 Air
20-Aug-73 Air
12-Sep-73 Boat
23-Aug-74 Air
27-Aug-74 Air
07-Aug-75 Air
21-Aug-75 Air
13-Aug-76 Air
15-Aug-76 Air
16-Aug-76 Air
20-Aug-76 Air
04-Aug-77 Air
08-Aug-77 Air
24-Aug-77 Air
22-Sep-77 Air
30-Sep-77 Field
20-Aug-78 Air
26-Aug-78 Air
12-Aug-79 Air
20-Aug-79 Air
05-Aug-80 Air
13-Aug-80 Air
18-Aug-80 Air
29-Jul-81 Air
06-Aug-81 Air
24-Aug-81 Air
02-Sep-82 Air
08-Sep-82 Air
17-Sep-82 Field
17-Sep-82 Field
08-Aug-83 Air
28-Aug-83 Field
21-Aug-84 Air
19-Aug-85 Air
26-Aug-85 Air
08-Sep-85 Field
08-Sep-85 Field
28-Sep-85 Field
28-Sep-85 Field
August 1997 Draft
FROM ADFG RECORDS (1963-1996)
Species Mouth
Pink ---
Pink 90
Pink ---
Pink 2,500
Pink 2,500
Pink 10,000
Pink 13,000
Pink 9,000
Pink 10,000
Pink ---
Pink ---
Pink 15,000
Pink 400
Pink 3,000
Pink 3,000
Pink ---
Pink 4,000
Pink 16,000
Pink ---
Pink 3,000
Pink 500
Pink 3,000
Pink ---
Pink 1,500
Pink ---
Pink Few small schools
Pink 1,000
Pink 5,000
Pink 100
Pink 4,000
Pink ---
Pink ---
Pink 3,000
Pink 1,000
Chum ---
Pink 1,500
Pink ---
Pink 7,000
Pink 18,000
Pink 4,000
Pink ---
Chum ---
Pink ---
Chum ---
34
Tidal Stream Total Count
7,000 700 7,700
75 420 585
420 275 695
------2,500
------2,500
500 ---10,500
------13,000
400 ---9,400
--- ---10,000
20,000 ---20,000
9,000 ---9,000
--- ---
15,000
------400
------3,000
10 ---3,010
1,500 ---1,500
------4,000
------16,000
16,000 ---16,000
------3,000
---6,300 6,800
100 ---3,100
10,000 ---10,000
800 ---2,300
8,000 ---8,000
---------
------1,000
5,000 ---10,000
------100
4,000 ---8,000
11,000 ---11,000
1,000 ---1,000
6,500 ---9,500
440 1,422 2,862
---19 19
------1,500
---20,000 20,000
7,000 ---14,000
16,000 ---34,000
35,000 ---39,000
---1,635 1,635
---5 5
4,000 3,000 7,000
---112 112
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
•
•
•
,
•
•
'.
-
-
-
-
-
Preliminary Draft Environmental Assessment
TABLEJ
ANADROMOUS FISH COUNTS FOR REYNOLDS CREEK (COPPER HARBOR)
Date Surve
05-Aug-86 Air
05-Aug-86 Air
12-Aug-86 Air
19-Aug-86 Air
06-Se -86 Air
01-Aug-87 Air
13-Aug-87 Air
19-Aug-87 Air
27-Au -87 Air
ll-Aug-88 Air
15-Aug-88 Air
24-Au -88 Air
Air
Air
Air
Air
04-Aug-91 Air
13-Au -91 Air
12-Aug-92 Air
25-Au -92 Air
10-Aug-93 Air
29-Aug-93 Air
05-Se -93 Air
15-Aug-94 Air
27-Au -94 Air
22-Aug-95 Air
26-Aug-95 Air
02-Se -95 Air
14-Aug-96 Air
Air
August 1997 Draft
FROM ADFG RECORDS 1963-1996
eci
Pink 10,000
Pink
Pink 1,000
Pink 5,000
Pink
Pink 50
Pink
Pink 15,000
Pink
Pink
Pink
Pink
Pink
Pink
Pink
Pink
Pink
Pink
Pink
Pink
Pink
Pink 500
Pink
Pink
Pink 1
Pink
Pink 4,000
Pink 20,000
Pink 10,000
Pink
35
ream Total Count
25,000 35,000
500 500
2,000 3,000
12,000 17,000
110,000 110,000
50
15,000 15,000
33,000 48,000
25,000 25,000
4,000 4,000
2,000 2,000
8,000 8
10,000 I
6,000 8,000 I
700
800 800
500 500
14,000 14,000
6,000 6,000
2,000 2
25,000
65,000
130,000
2,000
7,800
1,000
7,500 2,000
27,000
25,000
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
...
-
-
•
..
...
-
-
•
-
-
Preliminary Draft Environmental Assessment
feet in height. However, this cascade is not a total block to salmon migration; 4 or 5 pink salmon
were found just upstream of the cascade, in a relatively lower velocity stream segment that is a
pool under low flow conditions. These fish likely accessed this area via a lower velocity side
channel that bypassed the main cascade at high flow. However, this segment is at the toe of
another higher and steeper cascade beginning at about elevation 95 feet. No fish were seen in the
limited area of non-turbulent water above this cascade, and there was no apparent way fish could
bypass the cascade at these or any flows. Agency biologists who visited the site in July 1995 and
April 1997 have agreed that this cascade is the ultimate upstream migration barrier for
anadromous fish .
Although a significant number of pink salmon spawners (100s) reached the area of Reynolds
Creek above the USGS gaging station, it is probable that their spawning opportunities there are
limited. ADFG (1979) reported no available spawning habitat above the USGS gage. Surveys
conducted in July 1995 and 1996 assessed salmonid rearing habitat and potential sources of
spawning gravels in this reach. The streambed upstream of the gaging station is boulders and
coarse, angular rubble with very little gravel of a size in which fish could actually construct a. As
a result, spawning probably consists of releasing eggs and sperm among the rubble. Only those
eggs that lodge in cracks among the rubble would have a chance of surviving to the fry stage.
This condition gets increasingly severe with distance upstream of the gaging station. The
potential contribution to the system's production of fry from the reach below the barrier
(beginning at about elevation 85 feet) is likely negligible.
In contrast, Lower Reynolds Creek below the gaging station and its main tributary have good
spawning and rearing habitat in series of pools formed by low cascades, mostly over large organic
debris (LOD). The pools typically had low velocity tailout glides among large cobbles. ADFG
personnel reported capturing coho fry in the tributary (ADFG, 1995).
Environmental Impacts and Recommendations
Construction
Water Quality
Some short-term increases in turbidity and suspended sediments will be experienced in the
diversion reach during construction of the Lake Mellen diversion structure and tailrace, and
potentially from runoff from disturbed forest soils resulting from construction of the penstock.
The Applicant has developed an Erosion and Sedimentation Control Plan (ESCP) that will be
finalized when the project undergoes final design. The ESCP includes measures for capturing
sediment before it reaches Reynolds Creek or Rich's Pond or any of the other small tributaries in
the drainage area. The ESCP measures include using sediment barriers, soil erosion matting and
mulches, drains, etc. to prevent sediment laden runoff from leaving the project site. The final
ESCP will detail the specific measures to be used at specific locations at the project site. The
ESCP also describes measures to revegetate disturbed areas. The ESCP will be made part of any
construction-related contract package. ESCP measures will be routinely inspected by the
Applicant's on-site field representative to ensure that the objectives ofthe ESCP are being met .
August 1997 Draft 36
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
..
..
•
•
"
..
...
-
Preliminary Draft Environmental Assessment
Construction of the dam at the outlet of Rich's Pond would not require significant lake level
fluctuations and would have no significant effect on fish populations in Rich's Pond and none on
those in Lake Mellen .
Operation
Lake Mellen Levels
In Lake Mellen, the primary changes in shoreline will be similar to those from water level drops
that naturally occur, leaving an exposed rocky shoreline. Maintenance of the water level at near
its natural high elevation during much of the year will place the water closer to the surrounding
and overhanging riparian vegetation for more of the time. This may be a positive change for a
species like grayling for which insects are a preferred prey and appear to favor association with
large woody debris in the lakes.
Minor drawdown of Lake Mellen by 1 to 2 feet will occur when power demand exceeds inflow to
the lake and when the lake is not spilling. This is most likely in late summer or early fall and
during long cold spells in winter. Rates of change in lake level will be greater under Phase 2 than
under Phase 1 but extremes of lake level will be similar. Normal lake level changes will be in the
order of one to two inches per day due to project operation. During infrequent drawdowns to the
minimum pool elevation of 872 finsl, Lake Mellen would be about 4 feet below its normal high
level. Such changes in lake surface elevation would be expected to temporarily reduce the
productivity of the littoral zone for less mobile invertebrates, i.e., those that cannot readily adjust
their depth to accommodate lake level changes. To the degree that this productivity supports
prey for grayling, there would be a reduction in prey availability. Grayling stomach analyses
conducted by ADFG (1996) in the Reynolds Creek system suggest that a relatively minor
proportion of grayling prey organisms would be affected by these lake level fluctuations. Limited
drawdown of Lake Mellen is not expected to hinder upstream migration of grayling into Middle
Reynolds Creek.
Some grayling spawning may occur in the stream reach between Lake Mellen and Rich's Pond
although this has not been confirmed (Pentec, 1997a). Planned operating levels, as controlled by
the Rich's Pond diversion structure, will inundate a portion of this possible spawning area. At
elevation 874.5 finsl in Rich's Pond, water depth at the downstream end of this reach (Figure 11)
would be about 2.5 feet as compared to the depth under normal flows of 0.5 to 1 foot. As a
result, flow velocities will be reduced somewhat from the rates under present conditions. At the
upper end of the reach (e.g., at the Lake Mellen outlet sill) a Rich's Pond elevation of 874.5 finsl
would have little effect on normal depths and flows. When Rich's Pond is at or slightly above a
water surface elevation of 876 finsl, as is expected for much of the spawning period, the lower
end of the reach will be inundated to a depth of 4 feet and currents will be slight; at the upper end
of the reach water depth will be about 2 feet (compared to a natural 1 to 2 feet) and currents will
be reduced. Some areas suitable for spawning by grayling may remain .
August 1997 Draft 37
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
-
-
•
•
..
..
-
..
-
-
-
-
-
-
Preliminary Draft Environmental Assessment
Flows in the Bypass Reach
Operation of the project will reduce the amount of flow in the bypassed reach of Reynolds Creek
potentially affecting the small number of cutthroat trout that reside in the reach. In the steep
canyon of the diversion reach, observations during high flows (July 1997) confirm that there is
little pool habitat and that habitat conditions for cutthroat trout is limited. This habitat is expected
to be improved by reduced flows as long as pools containing fish become less turbulent yet remain
filled and flowing. A minimum in stream flow in the bypass reach of 5 cfs, as measured in the
lower end of the bypass reach, will be sufficient to meet this criteria. Lower and more stable flow
of water through the bypass reach is not expected to have any negative effects on the limited
population in the reach and may have a positive effect. High flows will always occur in the bypass
reach several times a year.
Flows Below the Anadromous Fish Barrier
The project will have little adverse effect on the average flow regime or on water quality of the
reach of Reynolds Creek accessible to anadromous fish (Figure 7). Project operation will provide
daily average minimum flows in excess of natural low flows and will reduce slightly the maximum
flows experienced during freshets. At maximum capacity the system will require 30 cfs for 1.5
MW generation during Phase I and 90 cfs for 5 MW generation under Phase 2. Bypassing up to
90 cfs of flow around the canyon reach of Reynolds Creek would have little effect on the water
quality in Lower Reynolds Creek.
Under winter conditions, the project would have its most significant effect on stream water quality
conditions when air temperatures are low and natural flows reduced. Under these conditions, the
bypassed water from Lake Mellen would be returned to the lower reach of Reynolds Creek at a
slightly warmer temperature than water following the natural channel through the canyon and
subject to atmospheric cooling. Warmer water under these conditions could reduce the extent of
freezing in the margins of the lower creek. Reduced risk of freezing could increase egg-to-fry
survival.
Water will be returned to the stream at approximately 90 finsl, near the impassible barrier to
upstream migration. It should be noted that an ADFG survey in 1979 reported no available
spawning habitat for over 200 feet below the proposed tailrace location. The tailrace will release
flows in a manner that will dissipate energy and avoid the possibility of providing an attraction
flow for anadromous fish.
As noted above, it is probable that the potential contribution of fry to the system from the last 50
feet below the final fish barrier is negligible. The return of tailrace flow to this area will not
significantly alter the condition of extreme turbulence that exists here under all but the lowest
flows. These low flow periods (July to mid-August) are not coincident with the spawning or
rearing activities of pink or chum salmon so any increased turbulence will not be detrimental.
Thus, the location of the tailrace just below the anadromous fish barrier is not expected to reduce
the production of pink or chum salmon in Lower Reynolds Creek.
August 1997 Draft 38
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
-
•
•
•
•
•
•
•
•
....
-
-
•
-
-
Preliminary Draft Environmental Assessment
Under low inflow conditions that are likely to be encountered during the middle of winter or later
summer, storage in Lake Mellen will be used to supplement inflow. As noted above, the project
will operate primarily as a run-of-the-river facility and will have only limited Lake Mellen storage
that can provide low flow augmentation. This augmentation would occur early in a low flow
period and would last only until the Lake Mellen storage is exhausted. After that point, combined
flow in the anadromous reach (the sum of project flow and bypassed flow) would equal the
natural inflow to Lake Mellen. Limited low flow augmentation may reduce slightly the potential
for winter freezing losses and improve egg to emergence survival for both coho and pink salmon
(e.g., Bjornn and Reiser, 1991; Sandercock, 1991). Low flow augmentation may also slightly
improve summer rearing conditions for coho, steelhead, and cutthroat. Several researchers have
established a positive correlation between summer streamflows and success of coho and/or
steelhead rearing (e.g., Smoker, 1953; Salo and Bayliff, 1958; see also reviews by Bjornn and
Reiser, 1991; Sandercock, 1991).
Although average flow conditions in Lower Reynolds Creek will be similar to or slightly more
moderate with the project than without, diurnal flow fluctuations in excess of those occurring
naturally will occur under some conditions as a result of diurnal variations in power demand.
When the daily flow requirements for power generation and minimum bypass reach flow exceed
the natural input to Lake Mellen from Reynolds Creek for an extended period, the lake level will
drop below the spillway elevation of 876 finst. Under these conditions, power generation will
draw the lake down below the spillway and the flow in Lower Reynolds Creek will equal the sum
of the bypass flow and the flow through the powerhouse.
Based on the anticipated power demand, the turbine flow could range from a low of 20 in the
predawn hours to 30 cfs at the time of the evening peak under summer conditions in Phase 1
operations and from 60 to 90 under Phase 2 operations. Initially, project flows in the range of 7-
10 cfs will be all that is required to meet the electrical load. The higher flow requirements of
Phase 2 operation will coincide with high inflows. During low inflow periods, the project may not
be able to operate at its rated capacity. For comparison, natural flow variations can also be
significant; increases of as much as 53 cfs (128 percent) and decreases of23 cfs (22 percent) have
been recorded in an 8-hour period in the Applicant's field program.
Unavoidable Adverse Impacts
The following potential adverse effects of construction and operation of the proposed project
would be unavoidable:
• Construction of the access road, dams, powerhouse, tailrace, and penstock will
result in temporary and minor increases in siltation reaching Reynolds Creek.
• Minor effects of level fluctuations in Lake Mellen on certain species of
invertebrates rearing in the lake will be unavoidable; these species are not believed
to comprise a significant proportion of the diet of grayling and it is considered
unlikely that lake level fluctuations will result in a significant decrease in the
availability of prey for grayling.
August 1997 Draft 39
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
«
-
-
•
•
•
•
•
•
•
-
•
•
-
-
-
-
•
•
Preliminary Draft Environmental Assessment
Raising the level of Rich's Pond to control elevation of Lake Mellen will result in
unavoidable loss of the majority of potential (but unconfirmed) grayling spawning
habitat in the reach between the Rich's Pond and Lake Mellen in most years.
Diversion of flow around the canyon of Reynolds Creek below Lake Mellen may
have a slight, but unavoidable, impact (which may be positive) on cutthroat trout
populations in the reach.
V.B.3 Terrestrial Resources
Affected Environment
Vegetation
The Reynolds Creek basin is steep and rocky with old-growth evergreen vegetation down to the
water's edge. Much of the forest is dominated by western hemlock. On areas of thinner soils and
on muskegs, western hemlock is replaced by stunted lodgepole pine and Alaska yellow-cedar. A
variety of shrubs, including salal (Gaultheria shallon), huckleberry (Vaccinium spp.), and fool's
huckleberry are evident in open areas of forest and stream margins and in wetlands.
There are two small subbasins associated with Lake Mellen. The upstream subbasin (Interlaken
Pond) is fed by Reynolds Creek and a much smaller creek entering from the east (Figure 4). These
creeks are partially blocked by old beaver dams and are associated with a muskeg wetland that
opens up the lodgepole scrub forest. A western hemlock-forested wetland occupies a roughly
triangular area that occupies the majority of the flat land at the head of the subbasin between
Reynolds Creek and the unnamed creeks to the east. Characteristic understory plants in this
wetland include devil's club (Oplopanax horridum) and skunk cabbage (Lysichitum americanum),
as well as lady fern (Athyrium filix-femina), deer fern (Blechnum spicant), and sword fern
(Polystichum munitum).
The downstream subbasin (Rich's Pond) is considerably smaller than Interlaken. It is surrounded
by western hemlock forest interspersed with muskeg that supports very small lodgepole pine and
Alaska yellow-cedar as well as typical muskeg mosses and herbs.
Prior to logging in 1997, Lower Reynolds Creek flowed through an old-growth forest typical of
lower elevations on Prince of Wales Island. The overstory consisted of large Sitka spruce and
western hemlock with lesser numbers of western red cedar (Thuja plicata). The spruce were
generally larger than 39 inches in diameter; the hemlock average 20 to 30 inches. Logging has left
only those larger trees within the required 66-foot buffer. A riparian community dominated by
red alder (Alnus rubra) with an understory of salmonberry (Rubus spectabilis) and stink currant
(Ribes bracteosum) remains more or less intact along the stream channel. The understory of the
upland is primarily composed of Alaska huckleberry (Vaccinium alaskaense), with occasional
oval-leaf (V. ovalifolium) and red huckleberry (V. parvifolium). Increasing amounts of devil's club
and fool's huckleberry occur from about the 50-foot elevation upward. A bed of thick mosses,
ferns, and lichens covers the forest floor. Significant changes will occur in the understory in the
August 1997 Draft 40
Reynolds Creek HydroelectriC Project
FERC Project No. 11480
•
..
-
•
•
•
Preliminary Draft Environmental Assessment
coming years with the canopy removed and as the area recovers from logging and develops into
second growth.
The south side of the ravine upstream of the USGS station supported a stand of old
second-growth western hemlock with occasional larger Sitka spruce. This area may have been
logged in connection with the mining operation on Copper Mountain. The smelter was located
north of the mouth of Reynolds Creek on the shore of Copper Harbor. The understory of the
second-growth stand was sparsely vegetated with sword fern and deer fern.
The Sealaska Corporation has logged much of the drainage basin downstream of Lake Mellen
during 1997 and will continue to log in the area in 1998. Sealaska's logging activities by 1998
will cover areas that would have been impacted by construction of the transmission line, penstock
and powerhouse for the proposed project. This logging has in essence pre-empted the great
majority of the potential impacts of the proposed project because there will be significantly less
tree removal and road building required.
Wetlands
• Wetlands in the project area were defined from National Wetlands Inventory (NWI) mapping
(Figure 12) and limited on-site ground truthing. Although most of the project area is steep and
well drained, the area surrounding Rich's Pond is muskeg bog and some saturated forest occurs
• along Reynolds Creek.
•
Wildlife
The Reynolds Creek area provides habitat for three big game species: black bear (Ursus
americanus), Sitka black-tailed deer (Odocoileus hemionus sitkensis), and Alexander Archipelago
• wolt' (Canis lupus ligoni). All three species are common in the study area, as numerous tracks
attest. The bear feed on berries and roots in the riparian wetlands and higher elevation meadows
as well as on the abundant runs of salmon in Lower Reynolds Creek. Black-tailed deer follow an
• elevational migration pattern that is common throughout the range (e.g., Schoen and Kirchhoff
1985). Sitka black-tailed deer winter in low elevation stands of heavy timber. Most (about 70
percent in Schoen and Kirchhoff's study) migrate to summer range in alpine meadows, but a
;. non-migratory segment typically remains in the low elevation wintering ground throughout the
year. Wolves principally prey on black-tailed deer but feed extensively on spawning salmon as
well. Beaver are also an important prey species of island wolves.
•
..
..
..
-
-
The habitat in the Reynolds Creek area is suitable for a number of smaller furbearers, including
mink (Mustela vison), beaver (Castor canadensis), and river otter (Lutra canadensis). American
marten (Martes americana) were introduced to islands throughout the Alexander Archipelago
and are now abundant (1. Lindell, USFWS. August 16, 1995. Pers. comm.) .
6 The Alexander ArcbipeJago wolf is a "species of concern" in part because it was once proposed for listing
as a threatened species, but it was found that there is insufficient information to support such a listing (60 FR
10056, February 24, 1995.).
August 1997 Draft 41
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
• • • I • • •
CRAIG (A-2)) ALASKA
!)' 1
r,
, .
~ ,
! 1
• • • • • I I •
NATIONAL WETLANDS INVENTORY
UNITED STATES DEPARTMENT OF THE INTERIOR
REYNOLDS CREEK
HYDROELECTRIC
PROJECT
Project Area Wetlands
FIGURE 12
I •
•
-
-
-
•
•
•
•
•
•
•
!.
..
•
-
-
Preliminary Draft Environmental Assessment
Prior to logging in 1997, the Reynolds Creek area contained potential old-growth nesting habitat
for marbled murrelets (Brachyramphus marmoratus), the Queen Charlotte subspecies of the
northern goshawk (Accipiter gentilis laingi), bald eagles (Haliaeetus leucocephalus), and
olive-sided flycatchers (Contopus borealis). Logging has removed these old-growth trees from
all but a 60-foot buffer along the anadromous stream reach. Marbled murrelets in Alaska tend to
select nest sites within 0.6 mile of saltwater, relatively near creeks or other forest openings, and
choose the largest available (generally 39 inches dbh or larger) Sitka spruce or hemlock trees,
particularly those with a large amount of defect and moss (Hamer and Nelson, 1995). There are a
few remaining large old-growth Sitka spruce trees in the lower reaches of Reynolds Creek that are
potential marbled murrelet nest trees. Many are infected with dwarf mistletoe and have deformed
branches that could serve as nest platforms. Goshawks also nest in large coniferous trees,
primarily in old-growth forests. Bald eagles nest in the upper canopy of large deciduous or
coniferous trees. Olive-sided flycatchers are neotropical migrant songbirds that nests in the upper
canopy of large trees, often near forest openings. Preliminary results of an ongoing study suggest
that, at least in the Anchorage area, olive-sided flycatcher territories are located primarily in
canyons or adjacent to streams (Wright, 1993). Olive-sided flycatchers were heard throughout
the study area in May and June 1996.
The Alexander Archipelago hosts a relatively large summer popUlation of marbled murrelets.
However, in a USFWS small boat transect survey in 1994, murrelets were found primarily in
Iphigenia Bay and the Gulf of Esquibel near the northern end of Prince of Wales Island and in the
ReviIIagigedo Channel near Ketchikan. Relatively few murrelets were seen near southern Prince
of Wales Island and Hetta Inlet in particular (S. Kendall, USFWS. 1995. Pers. comm.). Because
of the nature of this project, which will remove relatively few potential nest trees, and because of
the current status of the marbled murrelet in Alaska (neither listed as endangered or threatened
nor proposed for listing), no surveys of marbled murrelets were conducted in the project area.
A short survey for the presence ( absence) of potentially nesting northern goshawks was
conducted in July 1995. The standard US Forest Service survey protocol was followed (US
Department of Agriculture Forest Service, 1992). This protocol employs the observation that,
although goshawks occupy large home ranges and are generally cryptic, they are very defensive of
nests and responsive to juveniles during the breeding/nesting season and can be induced to
respond to taped calls. Although the probability of goshawk response to taped calls in random
locations is only 1 to 5 percent, response within 1,600 feet of an active nest is as high as 70 to 90
percent (c. Iverson, USFWS. 1995. Pers. comm.). Goshawks were called at intervals along
Reynolds Creek using an amplified, USFS-supplied tape recording of a female wail call that was
appropriate for the nestling feeding period in July. No goshawks responded to the tape broadcast.
Suitable trees in the project area, including the proposed transmission line corridor along the
shore of Copper Harbor and Hetta Inlet, were searched (from helicopter, motorboat, and from the
ground) for bald eagle nests in 1995, before extensive logging in the area, but none were found.
Wolf and bear sign were abundant during 1995 fieldwork. However, deer sign was not found in
the middle elevation area around Lake Mellen in July 1995. This is consistent with the general
-migration patterns of Sitka black-tailed deer, in which deer are expected either near the coast or in
alpine meadows in the summer.
-
August 1997 Draft
•
43
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
-
•
•
•
•
•
•
•
Preliminary Draft Environmental Assessment
The probability of marbled murrelet nesting is lower in the Lake Mellen area than in the lower
watershed as Sitka spruce (Picea sitchensis), a preferred nest tree, is absent. The old-growth
western hemlock, also a suitable nest tree, tends to be smaller and have smaller branches than the
trees in the lower watershed.
Lake Mellen and its associated ponds provide no habitat for harlequin ducks, which require
fast-flowing water for foraging and nesting. Bald eagles are less likely to be found at higher
elevations more distant from saltwater but bald eagles have been observed over Lake Mellen and
Summit Lake in the course of field work. An old beaver dam is located in a small Interlocken
Pond inlet stream and beaver-cut sticks were found in July 1997 in Lake Mellen. Beavers are a
favored prey of Alexander Archipelago wolves (Smith et aI., 1986). It is likely that beaver
distribution and colonization dynamics are strongly influenced by wolf predation.
Black bear and wolf sign were abundant throughout the area in both November and July 1995,
and a single bear was seen just below the USGS gaging station location in September 1995.
Wolves were seen and heard along the north shore of Copper Harbor during the field
reconnaissance in November 1994.
The fruit-laden scat of marten was commonly encountered in July, particularly along the lower
reaches of Reynolds Creek. No other evidence of small furbearers was found in the lower
watershed, although mink are likely to occur here. There were few areas where tracks of
furbearers and other relatively lightweight animals would have registered. Only tracks of bear,
wolf, and deer were found. No evidence of recent activity by beaver was seen along Lower
Reynolds Creek.
Environmental Impacts and Recommendations
Vegetation
Construction
Constructing the project would affect the vegetation at the project site. Riparian vegetation
around the shoreline of Rich's Pond between its current elevation and elevation 876 finsl is
.8 expected to die. Some trees in the riparian buffer strip left by logging along lower Reynolds
Creek may require removal for powerhouse construction and penstock installation.
... No mitigation measures are proposed for vegetation impacts. The Applicant's ESCP includes
measures for revegetating areas disturbed by project construction.
-Operation
No mitigation measures are proposed for vegetation impacts. -
-
-
August 1997 Draft 44
-
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
Preliminary Draft Environmental Assessment
Wetlands
Construction
Constructing the project would affect the wetlands at the diversion/intake site. It appears that
there will not be any impact to the saturated forest wetlands along Lower Reynolds Creek. Some
clearing of saturated forest wetland will be required to install the transmission line across Jumbo
Island in Hetta Inlet. The transmission line corridor will not be grubbed, however, and fill will be
negligible. The muskeg wetland type adjacent to Rich's Pond is designated PUBH on Figure 12,
.. the NWI for the project area. The saturated forest wetland type downstream along Reynolds
Creek and on Jumbo Island is designated PF04R Table 4 lists the estimated fill area in wetlands
for proposed project facilities and access roads . ..
•
'.
..
•
II
..
-
-
..
..
-
TABLE 4
ESTIMATED FILL IN WETLANDS
Estimate Area of
Pro.iect Component Fill in Wetland Wetland Type
• Intake 0.75 acre muskeg bog
Penstock 0.0 -
Powerhouse 0.0 -
i Transmission Line < 0.1 acre saturated forest
Access Road <1.0 acre muskeg, saturated forest
No mitigation measures are proposed for wetlands impacts. The Applicant's ESCP includes
measures for revegetating areas disturbed by project construction.
Operation
No wetland impacts are expected from project operation.
Wildlife
Construction
The presence of a construction work force may increase the hunting and fishing pressure on the
system due to increased access. Flooding the shallow reach of Reynolds Creek between Lake
Mellen and Rich's Pond could interfere with north-south movement of large mammals to some
degree. Animals crossing here would be forced to wade deeper water or potentially swim.
Operation
Project operation will cause only minimal variations in the water surface elevation at Lake Mellen
which is not expected to impact terrestrial fauna. Operation of the diversion will be fully
automated~ however, servicing will require periodic visits via the construction road. These visits
August 1997 Draft 45
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
-
•
•
•
•
I.
-
•
-
-
-
Preliminary Draft Environmental Assessment
may cause minor and temporary disturbance to wildlife in the area. Overhead transmission lines
may pose a threat for electrocution and collision for birds.
Unavoidable Adverse Impacts
Vegetation
Construction of the proposed project and associated access roads, work areas, and permanent
facilities will result in the short-term disturbance of approximately 4.5 acres of vegetation and
permanent elimination of approximately 2.5 acres of vegetation.
Wetlands
As noted previously, project construction would permanently eliminate approximately 2 acres of
wetlands.
Wildlife
Project construction would cause temporary wildlife displacement due to construction noise and
activity. Noise from project operation is not expected to cause long-term adverse effects on
wildlife.
V.B.4 Threatened, Endangered, and Sensitive Species
Affected Environment
As noted previously, no threatened, endangered or sensitive species have been found or are
expected in the study area. An initial list of species of concern (Table 5) was considered in the
analysis of terrestrial impacts. Discussion of the rationale for eliminating three of these species
from the discussion is provided in Pentec, 1997b. The only potentially significant project impacts
on species of concern would be the loss of potential nesting trees for marbled murrelets and the
limited potential for power line collisions by marbled murrelets and goshawks.
Environmental Impacts and Recommendations
The Applicant proposes to design the transmission line using the latest raptor protection
guidelines and install collision avoidance devices on the line when the line crosses migrating bird
flight paths.
Unavoidable Adverse Impacts
None.
August 1997 Draft 46
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
-
•
•
•
•
•
•
•
•
•
•
-
-
-
-
Preliminary Draft Environmental Assessment
TABLES
SPECIES OF CONCERN*
Scientific Name Comments
Olive-sided
fl catcher
Lenticular sedge
Brachyrhamphus
marmoratus
Accipiter gentilis
lain i
Histrionicus
histrionicus
Contopus borealis
Canis lupus ligoni
Rana retiosa
Calamagrostis
"crassi lumis"
Carex lenticularis
doUa
May occur in the Reynolds Creek area
May occur in the Reynolds Creek area
Reynolds Creek does not provide suitable habitat
Common in the Reynolds Creek area
Common in the Reynolds Creek area
Does not occur on Prince of Wales Island**
Unlikely in the Reynolds Creek area; not of conservation
concem**
Not observed in the Reynolds Creek area**
*These species were identified by U.S. Fish and Wildlife or Alaska Department ofFish and Game in
communications to the Applicant.
..... See Pentec 1997b.
V.B.S Aesthetic Resources
Affected Environment
The Reynolds Creek drainage rises from tidewater to alpine tundra on the ridge tops and
mountains surrounding Lake Mellen. Lake Mellen is surrounded by a mix of thick conifer forest,
gray rock cliffs, slide paths from adjacent mountainsides, and limited park-like areas of taiga or
muskeg. Past clearcutting of the side of Copper Mountain on the north side of Copper Harbor
has affected the wilderness aspect of the view from the water and from aircraft flying over the
area or up Hetta Inlet. No other visible signs of human disturbance were evident in the Reynolds
Creek drainage prior to 1997, except for a tailings pile from a small epidote crystal mine high on
the south flank of Green Monster Mountain just north of Summit Lake.
The west flank of Copper Mountain, which would be traversed by the transmission line, is being
logged progressively from the Sealaska base on the west side of Copper Mountain. A road was
built on Sealaska lands south into Copper Harbor and around Lower Reynolds Creek in 1997 and
a floating dock and construction camp at the old Coppermount site. Major logging activity began
in 1997 and it is expected that the entire Lower Reynolds Creek basin will be logged in the next
few years. Logging will also extend into higher elevations on the northwest and southwest flanks
of the Lake Mellen basin. The remainder of the transmission line route across Jumbo Island,
along Deer Creek and the Hydaburg River has virtually all been logged in the past 20 years and
presents a mix of various stages of regrowth.
August 1997 Draft 47
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
•
•
•
•
•
i.
Preliminary Draft Environmental Assessment
Environmental Impacts and Recommendations
Construction
Traffic, noise, dust, and exhaust emissions from construction machinery would be evident along
private roads leading to and at the project site during construction. Construction of the penstock,
powerhouse, and tailrace will require clearing of some old growth timber that will make these
facilities visible from the air or to individuals accessing the site. Clearing of construction staging
areas will be minimized. Some portion of the facilities may also be visible from the water in Hetta
Inlet or Copper Harbor. However, the effects of these actions will be insignificant in comparison
to the associated with logging of the surrounding basin.
Operation
Permanent project features including the diversion/intake structure on Lake Mellen, the penstock,
powerhouse, and access roads will alter the visual quality of the area. Since the surrounding area
will have been recently logged, these disturbances will not greatly affect the aesthetics of the area.
Project operation will not result in fluctuation of Lake Mellen beyond its natural range of variation
and should not affect the aesthetic experience of the few individuals who may access the lake by
float plane to fish.
The transmission line will add an element of permanence and structure to the already disturbed
nature of the hillsides and valleys along the route which have already been clearcut. To the
• degree possible, the line will parallel existing roads. The overhead transmission line will have
visual impacts from the air to those utilizing the road which it will follow, and in the immediate
area where the line will cross Hetta Inlet via Jumbo Island.
• Unavoidable Adverse Impacts
• Construction of the dam at Lake Mellen, the penstock, and the powerhouse will unavoidably and
permanently alter the current wilderness character of the lake and nearby area although this
character will have already been lost due to logging.
V.B.6 Cultural Resources
• Affected Environment
The Applicant conducted a cultural resources survey of the project (Campbell, 1996). No
_ archaeological or historic sites eligible for inclusion in the National Register of Historic Places
were identified. The Coppermount mine facilities which date to the tum of the century are
completely collapsed and deteriorated. Machinery associated with the mine has either been
-removed or significantly altered or vandalized.
•
-
August 1997 Draft 48
•
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
-
-
•
•
•
•
•
•
,.
•
-
-
-
-
•
Preliminary Draft Environmental Assessment
Environmental Impacts and Recommendations
Construction
Although no known National Register eligible sites would be affected by the project, there is the
possibility that undiscovered archaeological or historic sites may be present, such as buried
archaeological sites, that may be affected by project construction. If sites are discovered, the
Applicant will: 1) consult with the State Historic Preservation Officer (SHPO); 2) prepare a
cultural resources management plan and a schedule to evaluate the significance of the sites and to
avoid or mitigate any impacts to National Register eligible sites; 3) base the plan on the
recommendations of the SHPO and the Secretary of the Interior's Guidelines for Archaeology and
Historic Preservation; 4) file the plan for FERC approval, together with the written comments of
the SHPO; and 5) take the necessary steps to protect the discovered archaeological or historic
sites from further impact until notified by FERC that all of these requirements have been satisfied.
Unavoidable Adverse Impacts
None.
V.B.7 Recreation and Other Land Uses
Affected Environment
Southeast Alaska, an area 500 miles long and 120 miles wide, is characterized by a multitude of
saltwater islands, rugged mountains, and numerous lakes and streams. Heavy precipitation
nurtures towering evergreen forests interspersed with muskeg, icefields, and glaciers. Southeast
has 12% of Alaska's outdoor recreation acreage and 9% of all recreation facilities and trails. Its
coastline is convoluted by fjords and glaciers in the north. Because of this geography, excluding
the usually popular walking/running and driving, water-related activities of motorboating and
fishing have the highest participation rates. In contrast to statewide averages, with the exception
of camping and motorboating, most outdoor recreation in Southeast occurs within one hour of
the community, with less activity further than one hour. The Tongass National Forest and the
Haines State Forest provide over 17 million acres for outdoor recreation pursuits. The Tongass
National Forest alone is 82% of the Southeast's total recreation acreage and provides the majority
of the region's outdoor recreation facilities and trails. (Alaska DNR, 1988)
There are no developed recreation facilities located near the proposed project Recreational use
of the project area is limited by the difficult access and private ownership of all lands in the project
area and adjacent to the project. Access to the lands is strictly controlled by the landowner. Lake
Mellen is only accessible by float plane. However, it is difficult to access via float plane under
many weather conditions because of surrounding terrain factors.
Copper Harbor is accessible by boat and may occasionally be visited for recreational crabbing or
hunting. Past clearcutting of the side of Copper Mountain on the north side of Copper Harbor
has been colonized by an early scrub/shrub community dominated by alder. This habitat provides
August 1997 Drqft 49
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
•
•
Preliminary Draft Environmental Assessment
open ground and forage frequented by deer possibly increasing the desirability of the area for
hunting. A floating dock and temporary logging construction camp were established in this area
in 1997; road building and logging may have reduced deer use of the area. Fishing opportunities
in Copper Harbor are not unique although halibut and rockfish are probably present. Pink and
chum salmon can be caught in the harbor in late summer.
Environmental Impacts and Recommendations
Construction
During construction, machinery and constructed-related activity would produce noise, dust,
exhaust emissions, and additional traffic. These same impacts would detract from the overall
• recreation experience in the project area. However, these impacts would be minor due to the
limited number of people who would be exposed to them and because their duration would be
short.
Operation
Within the project area, the opportunity to engage in recreational activities is constrained by land
ownership patterns. Because the land is under private ownership, access and use by the public is
restricted, limiting opportunities for recreation. With the exception of the transmission line
• crossing ofHetta Inlet, all ofthe land that will be occupied by project facilities is privately owned.
III
-
-
-
-
-
Recreation and tourism in the Hydaburg area are only briefly referenced in the Concept Approved
Hydaburg Coastal Management Program (CH2M Hill, 1983). Tourism was not considered to be
a significant industry in the area and increased tourism was not included by the City as an
economic development goal or objective.
Provision for recreation facilities is not applicable to the project area, where land ownership is
private and where access and land use is controlled. For these reasons, development of a
recreation plan for the proposed Reynolds Creek project is not considered necessary.
Unavoidable Adverse Impacts
None.
V.B.8 Socioeconomic Resources
Affected Environment
Although Alaska is the largest state in the United States by land mass, it is the second smallest
state by popUlation. Southeast Alaska comprises 12 percent of the State's population. The total
population for Alaska in 1990 was 553,600 and is estimated to increase to 716,500 by the year
2000 (Alaska Department of Labor, 1996). The annual growth rate for the state between 1990
and 2000 is anticipated to be about 2.57 percent, while the annual growth rate for
KetchikanlHydaburg area is far below that at 0.87 percent (Alaska Department of Labor, 1992).
August 1997 Draft 50
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
•
•
If!
III
•
•
-
.101,
..
-
-
-
-
Preliminary Draft Environmental Assessment
Hydaburg with a population of about 500, is a first-class city with a city manager form of
government. It is not part of an organized borough.
Population trends are affected by employment opportunities. Natural resource-based industries
have sustained Southeast Alaska's economy in the past and present. They include forestry,
fishing, and mining. For Hydaburg, commercial fishing is the main economic activity and logging
has also been important in the area.
Recreation and tourism also have a strong effect on the economy in Southeast Alaska. Services
needed to keep the tourist industry growing are anticipated to increase. However, Hydaburg is
not yet a tourist destination. Accommodations and support services are fairly limited at this time.
Areas where employment growth is expected to occur are mining, services, and wholesale/retail
trade. Declines are forecasted for construction, seafood processing and government (Alaska
Department of Labor, 1994). Most of these industries experience seasonal swings in employment,
usually peaking in the summer months. For example, unemployment in the Ketchikan area for
1995 ranged from a high of 11.95 percent in January to a low of3.7 percent in August.
Environmental Impacts and Recommendations
Construction
Project construction would require on-site employment of up to 30 workers. Most construction
personnel would be hired from the HydaburgiCraiglKlawocklKetchikan area. Some workers
might commute by ferry from other islands in Southeast Alaska on a weekly basis and stay in
available accommodations or camp near the project site during the week and return home on
weekends. Few, if any, workers are expected to relocate during the construction period. Because
no in-migration of families with school-age children would not occur, the project would have a
discernible impact on local government services.
Short-term benefits to the Hydaburg economy would include reduced unemployment and more
local spending by construction workers. In addition, the project contractor would undoubtedly
purchase some equipment and material from suppliers in the general area, thereby providing
additional short-term benefits.
Operation
The project would not displace any residences or business establishments. Once the proposed
facilities are operational, the project would generate additional revenue for Haida Corporation
through the sale of power to AP&T .
Because the project's socioeconomic impacts would be primarily beneficial, the Applicant is not
proposing any mitigation measures specifically addressing socioeconomics. One to two
permanent, full-time jobs would result from long-term project operation.
Unavoidable Adverse Impacts
None.
August 1997 Draft 51
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
-
Preliminary Draft Environmental Assessment
V.C CUMULATIVE EFFECTS
According to the Council on Environmental Quality's Regulations for implementing NEP A
(§1508.7), an action may cause cumulative impacts on the environment if its impacts overlap in
space and/or time with the impacts of other past, present and reasonably foreseeable future
actions, regardless of what agency or person undertakes such other actions. Cumulative effects
_ can result from individually minor but collectively significant actions taking place over a period of
time, including hydropower and other land and water development activities.
• Scoping Document 2, for the Reynolds Creek Project, identified those resource issues to be
analyzed for cumulative impacts as:
..
if
III
I~
Illil
-
-
-
•
•
V.C.l
Aesthetic Resources
The degree that construction and operation of project facilities would adversely
impact the visual quality of the area.
Recreation and Other Land Uses
Whether project construction and operation would impact recreational
opportunities and what those impacts would be.
Geographic Scope
The Applicant's geographic scope of analysis for cumulatively affected resources is defined by the
physical limits or boundaries of: 1) the proposed action's effect on the resources, and 2)
contributing effects from other hydropower and non-hydropower activities within the project
area.
No hydropower development currently exists in the area and none other than the Reynolds Creek
Project is proposed. Anticipated non-hydro activities potentially affecting resources in the project
area that have been identified are recreation, logging and road construction.
Aesthetic Resources
Water from Lake Mellen, at approximate elevation 876 finsl, flows through a short, low gradient
stream section to Rich's Pond (elevation 872 finsl) and then into Copper Harbor in Hetta Inlet by
way of Lower Reynolds Creek. The proposed project will raise the level of Rich's Pond to 876
finsl and affect flows in the reach of Reynolds Creek from the point of diversion at Rich's Pond
downstream to just below the anadromous fish barrier (elevation 95 finsl). The altered flows in
the bypassed reach of Reynolds Creek, due to project operations, and the existence of project
facilities, including the transmission line, have the potential to affect the aesthetic character of the
area.
Thus, the geographic scope of the cumulative effects for aesthetic resources analysis has been
defined as the Reynolds Creek basin consisting of the reach of Reynolds Creek that enters Lake
Mellen, Lake Mellen, Rich's Pond and Lower Reynolds Creek to tidewater and the transmission
line route to the City of Hydaburg.
August 1997 Draft 52
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
•
•
•
-
•
..
-
-
-
..
Preliminary Draft Environmental Assessment
Recreation and Other Land Uses
The geographic scope of the Recreation and Other Land Uses analysis is the same as that for the
Aesthetic Resources.
V.C.2 Temporal Scope
The temporal scope of the cumulative analysis includes past, present, and future actions and their
effects on each resource that could be cumulatively affected. F or purposes of this analysis, the
temporal scope looks 50 years into the future, concentrating on the effect of the resources from
reasonably foreseeable future actions. The historical discussion is, by necessity, limited to the
amount of available information for each resource. The present resource conditions are based on
the Initial Consultation Document, Scoping Documents 1 and 2, and studies conducted to date.
V.C.3 Cumulative Effects Analysis
Aesthetic Resources
Reynolds Creek Area
As was discussed previously, the Reynolds Creek drainage rises from tidewater to alpine tundra
on the ridge tops and mountains encircling Lake Mellen. Lake Mellen is surrounded by a mix of
thick conifer forest, gray rock cliffs, slide paths from adjacent mountainsides, and limited park-like
areas of taige or muskeg. Past clearcutting of the side of Copper Mountain on the north side of
Copper Harbor has affected the wilderness aspect of the view from the water and air. However,
there were no other visible signs of human disturbance evident in the Reynolds Creek drainage
prior to 1997 with the exception of the tailings pile from a small mine on the south flank of Green
Monster Mountain just north of Summit Lake.
Logging by the land owner, Sealaska Corporation, has begun and will continue to progress
around the west flank of Copper Mountain into Copper Harbor and beyond Reynolds Creek
during the next few years. This logging will transfonn the hillsides around Copper Harbor from
mostly unroaded old growth to mostly roaded and logged. This will be a major transformation.
As a result, the minimal amount of clearing associated with the project facilities (penstock,
powerhouse, and short access road), will not make a discernible contribution to the degradation
of the viewscape.
Looking decades into the future, the logged areas will begin to re-establish through natural
successional processes. Access to the project facilities will be maintained but the regrowth of
surrounding vegetation will help to screen the features from observers except when viewed from
the air or from limited vantage points on the ground. No other hydroelectric installation is known
to be planned for the area and other types of development are not anticipated. Thus, it is
concluded that the construction of the project will not have a significant contribution to the
changes in the viewscape in neither the near-term nor the long-term.
August 1997 Draft 53
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
,.
-
-
•
,.
..
..
•
..
-
-
-
-
Preliminary Draft Environmental Assessment
Transmission Line Route
Approximately 12.3 miles of overhead transmission line will be constructed for the project. The
line will connect the project's powerhouse to electrical facilities in the City of Hydaburg. The line
will be 34.5 kV, consist of four wires (3 phases and a ground wire), and be mounted vertically (no
crossarms) on wooden poles. To the extent possible, the line will follow existing logging roads
along the route except where an aerial crossing of Hetta Inlet via Jumbo Island will be
constructed. The maintained right-of-way for the line will be 30 feet wide. Although some
clearing will be needed for the line, most of the route has been previously clearcut. Grasses and
herbaceous vegetation will not be removed .
The transmission line will be a developmental feature in the already disturbed hillsides and valleys
along the route. Its presence will be apparent to observers in aircraft, to those utilizing the roads
which it will follow, and to those in the immediate area of the Hetta Inlet crossing. Regrowth of
harvestable timber will be precluded on the right-of-way. Thus, the transmission line will
permanently alter the viewscape along its route, but its contribution to cumulative impacts to
aesthetic resources should not be significant given the already disturbed nature of the area and the
absence of other present and future development.
Recreation and Other Land Uses
As was discussed previously, there are no developed recreation facilities located near the project
area and recreational use is limited because of the difficult access and private land ownership. The
State's Comprehensive Outdoor Recreation Plan (SCORP), indicates that Southeast Alaska
communities are small and have limited road systems, making it difficult to go more than one hour
without a boat or aircraft. Because these aspects are not expected to change significantly during
the construction and operation of the project, impacts to recreation and land use attributable to
the project are considered to be minor, project-specific, and not cumulative in nature.
V.D NO-ACTION ALTERNATIVE
Under the No-Action Alternative, the Reynolds Creek Project would not be constructed. The
City of Hydaburg would continue to receive electrical power from fossil fuel-fired generation for
the foreseeable future. The noise and air quality impacts of the existing generation system would
continue unabated or at increased levels as the local electrical demand increased. The risk of spills
of diesel fuels would likewise continue at current or increasing levels.
The financial benefits to the residents of Hydaburg in the form of lower electrical rates and to the
Haida Corporation in terms of project operating revenues would not be realized. Ultimately, the
intertie between CraiglKlawock and Hydaburg might be built and Hydaburg could be supplied by
hydroelectric generation from other projects on the central or northern part of the island. This
eventuality could result in elimination of the need for local diesel generation of power but would
not provide the same level of economic benefit to the people of Hydaburg and to the Haida
Corporation that would be derived from the Reynolds Creek Project.
August 1997 Draft 54
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
• Preliminary Draft Environmental Assessment
-
•
..
•
..
•
•
-
VI. DEVELOPMENTAL ANALYSIS
When the project is fully utilized it could produce approximately 23,000,000 kWh of energy
during an average water year and would generate a maximum power output of 5 MW. The
purpose of the project is to generate energy for sale in the distribution system and to offset the
need to generate energy using diesel-fuel powered generators. For the proposed project to be
economically beneficial, the estimated levelized cost of the project would have to be less than the
current cost of alternative energy from any other sources available that could supply the regional
energy needs. In analyzing the economic benefits of the project, the cost of production and the
value of the project's power were considered. To be viable, the project should be economically
beneficial over a license period of 50 years.
The current energy plan being development for POWl calls for the interconnection of the
communities of Thorne Bay, Kasaan, Hollis, Hydaburg to the existing system serving the Craig!
Klawock areas. The transmission line to Thorne Bay and Kasaan has obtained funding and is
currently being designed. The line to Hollis and then Hydaburg will follow thereafter. The
Reynolds Creek project will be a key generating resource for this interconnected system.
Development of the project will be undertaken in a phased approach. The project will have an
initial capacity of 1.5 MW and will serve the immediate needs of Hydaburg. The project will have
a plant factor of about 12% initially. Once the transmission line system is in place to serve the
rest of the island, the plant factor will steadily increase until the plant is fully utilized. At this time,
the powerhouse would be expanded and a second 3.5 MW generating unit installed. This phased
approach has been adopted to keep the cost of generation from the hydroelectric project at or
below the anticipated cost of diesel generation.
Using this phased development approach, and assuming interconnection of Hydaburg and Hollis
would occur around the year 2003, the 30 year levelized cost of energy from the project would be
a about $0.084 kWh using the current cost method of analysis. In comparison, the levelized cost
of continued diesel generation would be about $0.107 kWh. Therefore, there is a clear economic
benefit to the construction of the project .
Estimates were made of the amount of diesel fuel necessary if diesel generation was used to
generate the 23 million kWh (potential energy production of the proposed project). Estimates
were also made of the amounts of pollutants-oxides of nitrogen, carbon monoxide, carbon
dioxide, and unburned hydrocarbon-that would be produced by burning that diesel fueL The diesel
power plants do not contain state-of-the-art emission control systems such as catalytic converters
and low NOx, but are efficiently operated. Table 6 shows the result of the analysis .
Reynolds Creek Hydroelectric Project
FERC Project No. 11480 55 August 1997 Draft
-
•
...
..
-
-
-
-
-
Preliminary Draft Environmental Assessment
TABLE 6
ESTIMATED ANNUAL AMOUNTS OF DIESEL FUEL AND
RESULTING POLLUTANTS FROM EQUIVALENT AMOUNTS OF
GENERATION FROM A DIESEL-FIRED POWER PLANT
Item
16,100
25
Note: Emissions calculations based on the following estimated engine emissions: NOx-
2.0 rIBHP-hr., CO-4.0 r.lBHP-hr, CO r 3.09lbllb fuel, UHC-0.75 r.lBHP-hr.
Carbon dioxide is considered to be a prime contributor to global warming, and the oxides of
nitrogen and unburned hydrocarbons are considered to be prime contributors to the production of
acid rain and photo-chemical smog. Carbon monoxide is a poison. It was concluded that
construction and operation of the Reynolds Creek Project would benefit air quality and the
environment because the need for fossil-fueled generation would be avoided or minimized.
In previous sections of this PDEA, the environmental benefits of several resource mitigation
measures proposed by the Applicant and recommended by the agencies were assessed. Some of
the measures proposed are operational measures that would not have significant effects on cost or
generation. The project, as proposed by the Applicant, includes all these measures .
Reynolds Creek Hydroelectric Project
FERC Project No. 11480 56 August 1997 Draft
-
•
•
-
-
•
-
-
-
-
-
-
Preliminary Draft Environmental Assessment
VII. COMPREHENSIVE DEVELOPMENT AND RECOMMENDED
ALTERNATIVE
Sections 4(e) and lO(a)(l) of the FPA, 16 U.S.c. §§ 797(e) and 803(a)(1), respectively, require
the Commission to give equal consideration to all uses of the waterway on which the project is
located. When the Commission reviews a hydropower project, the recreational, fish and wildlife,
and other non-developmental values of the waterway are considered equally with its electric
energy and other developmental values. In determining whether, and under what conditions, a
hydropower license should be issued, the Commission must weigh the various economic and
environmental tradeoffs involved in this decision.
Based on review and evaluation of the proposed project, and the no-action alternative, the
proposed project is the preferred option.
August 1997 Draft 57
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
..
-
-
•
•
..
•
•
..
,0
•
•
-
-
-
Preliminary Draft Environmental Assessment
VIII. CONSISTENCY WITH COMPREHENSIVE PLANS
Section 10(a)(2) of the FPA requires the Commission to consider the extent to which a project is
consistent with federal and state comprehensive plans for improving, developing, and conserving
waterways affected by the project. Twenty-two plans are currently on the Commission list of
comprehensive plans for the state of Alaska. Three of these plans address resources relevant to
the Reynolds Creek Project, and are discussed below.
North American Waterfowl Management Plan (NAWMP)
The NAWMP set goals for conserving North American waterfowl through cooperative planning
and management. The plan provides the framework for a waterfowl conservation effort by
describing population and habitat goals and suggesting recommendations to resolve problems of
international concern through the year 2000. The plan's intent is to set the stage for the
development of national, flyway, provincial, territorial, and state plans that contain specific
management measures for waterfowl conservation in the United States and Canada. The plan
recognizes that habitat loss and degradation is the major waterfowl problem in North America and
sets habitat conservation as a top priority.
The only foreseeable impact that the Reynolds Creek Project could have on waterfowl would be
temporary displacement due to noise and other human activity during the construction phase.
However, this impact would be minor since Lake Mellen is not important habitat for waterfowl.
Therefore, the project would be consistent with the NAWMP .
Alaska Outdoor Recreation Plan (AORP)
The AORP is the State's Comprehensive Outdoor Recreation Plan (SCORP) and identifies citizen
preferences and suggested actions to address outdoor recreation issues in the state. The plan
identifies the following issues:
• The state needs to maintain its recreational land base.
• The outdoor recreation needs of urban Alaskans must be met with sites near
people's home.
•
•
Cooperation among agencies is essential to successfully meeting state recreation
needs.
Preserving and protecting Alaska's culture and history is critical in maintaining the
state's distinct identity.
• High quality outdoor recreation experiences must be perpetuated and enhanced.
The Reynolds Creek Project would have little, if any, noticeable effect on outdoor recreation.
Current access opportunities would not change significantly. The minor road additions (less than
500 feet total) associated with the project could encourage some additional use of the project
area. However, the available information indicates that demand for using this area is low. No
Reynolds Creek Hydroelectric Project
FERC Project No. 11480 58 August 1997 Draft
•
-
-
•
•
•
•
•
..
-
-
-
-
-
Preliminary Draft Environmental Assessment
known cultural resources would be affected, and the project is not close enough to cities of the
size of Ketchikan, to meet the needs of urban Alaskans. Thus, the project would be consistent
with the AORP.
Hydaburg Coastal Management Program
The project lies within Alaska's coastal zone and the City of Hydaburg's coastal resource district
Coastal management policies for the district are presented in the Concept Approved Hydaburg
Coastal Management Program (CH2M Hill, 1983). The planning area is divided into three
subareas: the City of Hydaburg corporate limits, the general coastal planning area, and Area's
Meriting Special Attention (AMSA). The Hydaburg coastal management district has no direct
authority over actions occurring within the planning area. However, land managers are
encouraged to consult with the district over actions that may affect the planning area.
Reynolds Creek Hydroelectric Project
FERC Project No. 11480 59 August 1997 Draft
-
Preliminary Draft Environmental Assessment
IX. FINDING OF [OR NO] SIGNIFICANT IMPACT
On the basis of the independent environmental analysis presented in this document, issuance of a
license for the project would not constitute a major federal action significantly affecting the quality of
the human environment. Therefore, a Finding of No Significant Impact (FONSI) is appropriate and an
-environmental impact statement (EIS) is not required.
-
•
•
II
-
..
II
..
..
-
-
-
August 1997 Draft 60
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
-
•
•
•
..
•
-
-
-
-
Preliminary Draft Environmental Assessment
X. LITERATURE CITED
ADFG. October 17, 1995. Letter from J. Durst, Klawock Habitat Manager, to J. Houghton, Pentec
Environmental, Inc.
ADFG. 1992. Anadromous stream catalog. Stream 10420 on USGS Craig A-2 quadrangle. ADFG,
Juneau.
ADFG. 1982. Partial report provided by ADFG 1995.
ADFG. 1979. Survey field data sheet provided by ADFG 1995.
Alaska Department of Labor, Administrative Services Division, Demographics Unit. 1991. Alaska
Population Projections, 1990-2010. November 1991, Second Printing March 1992. 105 pp .
Alaska Department of Labor, Research and Analysis Section. 1994. Alaska Economic Trends, 1994-
95 Forecast. Volume 14, Number 5. May 1994. 20 pp.
Alaska Department of Natural Resources, Division of Parks, 1988. Outdoor Recreation: Alaska.
Bjornn, T. c., and D. W. Reiser. 1991. Habitat requirements of salmonids in streams. Pages 83-138
in W. R. Meehan, editor. Influences offorest and rangeland management on salmonid fishes
and their habitats. American Fisheries Society Special Publication 19. Bethesda, Maryland.
Campbell, C. R. 1996. An Archaeological Survey of the Lake Mellen Hydroelectric Project, South
Prince of Wales Island, Alaska.
CH2M Hill. 1983. Concept Approved Hydaburg Coastal Management Program.
Clarke, R. 1991. Fielding Lake studies report. Alaska Department ofFish and Game.
Hamer, T. E., and S. K. Nelson. 1995. Characteristics of marbled murrelet nesting trees and nesting
stands. Pages 69-82 in C. J. Ralph, et al., technical editors. Ecology and Conservation of the
marbled murrelet. Gen. Tech. Rep. PSW-GTR-152. Pacific Southwest Research Station,
Forest Service, US Department of Agriculture, Albany, California.
Iverson, C. 1995. U.S. Fish and Wildlife Service. Personal communication.
Kendall, S. 1995. U.S. Fish and Wildlife Service (USFWS). Personal communication.
Lindell, J. August 16, 1995. US Fish and Wildlife Service (USFWS). Personal communication.
-Pentec, 1997a. Fisheries and Aquatic Studies in the Reynolds Creek Drainage.
-
-
•
Pentec, 1997b. Additional Species of Interest in the Reynolds Creek Drainage.
August 1997 Draft 61
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
Preliminary Draft Environmental Assessment
• Salo, E. 0., and W. H. Bayliff 1958. Artificial and natural production of silver salmon (Oncorhynchus
•
•
•
•
•
•
•
•
II
II
-
..
".
,~
-
-
kisutch) at Minter Creek, Washington. Washington Department of Fishery Resources, Bulletin
4, Olympia.
Sandercock, S. K. 1991. Life history of coho salmon (Oncorhynchus kisutch). Pages 397-445 in
Groot, C., and L. Margolis, editors. Pacific salmon life histories. UBC Press, Vancouver,
Canada.
Schoen, J. W., and M. D. Kirchoff 1985. Seasonal distribution and home range patterns of Sitka
black-tailed deer on Admiralty Island. Journal of Wild life Management 54:371-378.
Smith, C. A, R. E. Wood, L. Beier, and K. P. Bovee. 1986. Wolf-deer-habitat relationships in
southeast Alaska. Alaska Department ofFish & Game, Juneau.
Smoker, W. A 1953. Streamflow and silver salmon production in Western Washington. Washington
Department of Fishery Resources Paper 1, Olympia.
U.S. Department of Agriculture Forest Service (USFS). 1992. Goshawk inventory protocol, Alaska
Region. Juneau, Alaska.
U.S. Fish and Wildlife Service and Canadian Wildlife Service. 1986. North American Waterfowl
Management Plan.
Walker, S. 1994. Unpublished Data. Alaska Department ofFish & Game, Commercial Fish Division,
Ketchikan.
Wright, 1. M. 1993. Abundance, timing, and demography of neotropical migratory birds during
migration; and preliminary study of olive-sided flycatchers in Alaska. Alaska Department of
Fish & Game Division of Wildlife Conservation, Endangered Species Research Final Report.
August 1997 Draft 62
Reynolds Creek HydroelectriC Project
FERC Project No. 11480
,.
•
•
•
•
..
•
-
•
-
-
-
-
-
-
Preliminary Draft Environmental Assessment
XI. LIST OF PREPARERS
Paul Berkshire -(HDR) -Project Manager, Purpose and Need for Action, Applicant's Proposal,
Geology and Soils Resources, Developmental Analysis (B.S. Civil Engineering, M.S. Civil
Engineering, P.E. Civil Engineering -Alaska and Washington)
Sally Boggs -(HDR) -Threatened and Endangered Animals, Terrestrial Resources, Aquatic Resources
(B.S. Zoology, M.S. Hydrogeology/Aqueous Geochemistry)
Mark Dalton -(HDR) -Environmental Manager, Overall PDEA Reviewer (B.S. Biology/Geology)
Bonnie Lindner -(HDR) -Cultural Resources, Overall PDEA Reviewer (B.S.B.A)
Michael V. Stimac -(HDR) -Licensing Manager, Socioeconomics, Cumulative Effects, Overall PDEA
Coordination (B.S. Electrical Engineering, M.S. Fisheries, P.E. Nuclear Engineering -Washington)
Susan Walker -(HDR) -Recreation (B.S. Psychology, M.S. Industrial Psychology)
John Wolfe -(HDR) -Land Use (B.A WritinglEnvironmental Studies)
Jonathan P. Houghton -(pentec) -Fish and Aquatic Life, Aesthetics (AB. Biology, Ph.D. Fishery
Biology)
Margaret M. Glowacki -(pentec) -Fish and Aquatic Life (B.S. Biology, M.S. Fishery Biology)
Julie L. Stofel -(pentec) -Threatened and Endangered Species, Terrestrial Resources (B.S. Biology,
M.S. Wildlife Biology)
HDR -HDR Engineering, Inc.
Pentec -Pentec Environmental, Inc.
August 1997 Draft 63
Reynolds Creek HydroelectriC Project
rERC Project No. 11480
-
•
•
•
•
•
•
•
III
•
•
•
•
..
..
XII. MAILING LIST
Steve Zimmerman
Protected Resources Management Division
National Marine Fisheries Service
P.O. Box 21668
Juneau,AJC 99802
Nevin D. Holmberg, Field Supervisor
Attn: Duane Petersen
U.S. Fish & Wildlife Service
3000 Vintage Blvd., #201
Juneau,AJC 99801
Dale Kanen, District Ranger
Attn: Barbara Stanley
U.S. Forest Service
Craig Ranger District
P.O. Box 500
Craig, AJC 99921
Larry Brockman
Environmental Review Coordinator
MS WD-124
Environmental Protection Agency
1200 6th Avenue
Seattle, W A 9810 1
Larry Wright
Alaska Regional Office
National Park Service
2525 Gambell Street
Anchorage, AJC 99503-2892
Michiel Holley, Unit Coordinator
Permit Processing Section, Regulatory Branch
U.S. Army Corps of Engineer, Alaska District
P.O. Box 898
Anchorage, AJC 99506-0898
Bruce Bigelow, Chief Hydrologist
U.S. Geological Survey
P.O. Box 21568
Juneau,AK 99802
J eonifer Garland
State of Alaska, Office of the Governor
Division of Governmental Coordination
Southeast Regional Office
P.O. Box 10030
Juneau, AJC 99811-0030
August 1997 Draft 64
Preliminary Draft Environmental Assessment
Joan Hughes
Alaska Dept. of Environmental Conservation
Southwest Regional Office
410 Willoughby, Suite 105
Juneau, AJC 9980 I
Jack Gustafson
Area Habitat Biologist
Alaska Department of Fish & Game
Habitat and Restoration Division
2030 Sea Level Drive, Suite 205
Ketchikan, AJC 99901-6067
Jim Durst
Alaska Department of Fish & Game
Habitat and Restoration Division
P.O. Box 271
Klawock, AJC 99925
Lana Shea Flanders
Alaska Department of Fish & Game
Habitat and Restoration Division
Mail Stop 1120
P.O. Box 240020
Douglas, AJC 99824-0200
John Dunker, Water Office
Alaska Department of Natural Resources
Division of Water
400 Willoughby, Suite 400
Juneau, AK 99801-1724
Jim Anderson, Land Officer
Department of Natural Resources
Division of Land
400 Willoughby, Suite 400
Juneau,AJC 99801-1724
Bill Gary, Regional Manager
Alaska Department of Natural Resources
Division of Parks & Outdoor Recreation
400 Willoughby, Suite 400
Juneau,AJC 99801-1724
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
-
-
•
•
..
-
•
'.
-
-
•
-
•
Judith Bittner
State Historic Preservation Officer
Alaska Department of Natural Resources
Office of History and Archaeology
3602 "c" Street, Suite 1278
Anchorage, AK 99503-5921
Douglas Mathena, Jr., Mayor
City of Hydaburg
P.O. Box 49
Hydaburg, AK 99922
Steve Brockmann
Ecological Services
U.S. Fish & Wildlife Service
624 Mill Street
Ketchikan, AK 99901
Nan Allen, OHLIDLC
Federal Energy Regulatory Commission
888 First Street NE, Room 62-44
Washington, DC 20426
Robert W. Loescher
Sealaska Corp.
One Sealaska Plaza, Suite 400
Juneau,AJC 99801-1512
Bob Lohr, Executive Director
Alaska Public Utilities Commission
1016 W. Sixth Avenue, Suite 400
Anchorage, AJC 99501
Christopher Estes
Alaska Department of Fish & Game
333 Raspberry Road
Anchorage, AK 99518-1599
Steve Hoffman
Ketchikan Area Management Biologist
Alaska Department ofFish & Game
Division of Sportfish
2030 Sea Level Drive, Suite 205
Ketchikan, AK 99901
Glenn Freeman, Fishery Biologist
Alaska Department ofFish & Game
Division of Sportfish
2030 Sea Level Drive, Suite 205
Ketchikan, AK 99901
August 1997 Draft 65
Preliminary Draft Environmental Assessment
Reuben Yost
Project Environmental Coordinator
Alaska Department of Transportation
6860 Glacier Highway
Juneau, AK 99801
Harry Han, Director
Portland Regional Office
Federal Energy Regulatory Commission
101 S.W. Main Street, Suite 905
Portland, OR 97204
Robert S. Grimm, President
Alaska Power & Telephone
P.O. Box 222
Port Townsend, W A 98368
William M. Bumpers
Baker & Botts, Attorneys at Law
1299 Pennsylvania Avenue N.W.
Washington, DC 20004-2402
Rick Harris
Sealaska Corporation
One Sealaska Plaza, Suite 400
Juneau,AK 99801-1512
Craig Public Library
500 Third Street
Craig, AJC 99921
Constance Sathre
National Oceanic & Atmospheric Admin.
Office of General Counsel
P.O. Box 21109
Juneau,AK 99802-1109
Reynolds Creek Hydroelectric Project
FERC Project No. 11480
•
..
-
-
•
•
•
•
•
•
•
-
-
-
-
-
-
,.
August J 997 Draft
Preliminary Draft Environmental Assessment
APPENDIX A
AGENCY LETTERS AND COMMENTS
Reynolds Creek Hydroelectric Project
FERC Project No. J 1480
,.
-
•
•
•
•
-
•
•
,.
•
-
-
•
•
,.
Preliminary Draft Environmental Assessment
AGENCY LETTERS AND COMMENTS
WILL BE PROVIDED IN THE
PRELIMINARY DRAFT ENVIRONMENTAL ASSESSMENT
FILED WITH THE FERC IN NOVEMBER 1997
August 1997 Draft
FOR THE REYNOLDS CREEK PROJECT
Reynolds Creek Hydroelectric Project
FERC Project No. 11480