HomeMy WebLinkAboutConcept Design Report and Construction Cost Estimate for Energy Infrastructure Projects Elfin Cove 2006CONCEPT DESIGN REPORT AND
CONSTRUCTION COST ESTIMATE
FOR ENERGY INFRASTRUCTURE PROJECTS
IN THE COMMUNITY OF:
ELFIN COVE
PREPARED FOR:
STATE OF ALASKA
ALASKA ENERGY AUTHORITYI
RURAL ENERGY GROUP
PREPARED BY:
Alaska Energy and Engineering, Inc.
Mailing Adoress -P.O. Box 111405
Anchorage, AK 99511-1405
(907) 349-0100
349-8001 FAX
FEBRUARY 16, 2006
Elfin Cove Energy Infrastructure Projects
Concept Design Report
EXECUTIVE SUMMARY
February 16, 2006
Alaska Energy and Engineering
This report has been prepared by Alaska Energy and Engineering, Inc. (AE&E) for
the Alaska Energy Authority/Rural Energy Group (AEAlREG). The purpose of this
study is to provide a concept design and construction cost estimate for the
following potential energy infrastructure improvement projects for the community
of Elfin Cove:
• Diesel power plant renovation.
• Minor upgrades to existing bulk fuel storage and handling facilities.
• Generation heat recovery system upgrades.
• Community power distribution improvements.
• . Hydroelectric generation facility and transmission cable.
Participants in the project .include the Community of Elfin Cove Nonprofit
Corporation (Community Association) and the Elfin Cove Electric Utility (Electric
Utility).
A site investigation was performed by David Lockard of the Alaska Energy
Authority/Rural Energy Group (AEAlREG) and John Dickerson of Alaska Energy &
Engineering, Inc. (AE&E) on Wednesday April 13, 2005. The purpose of the site
visit was to meet with local residents to identify and discuss potential energy
infrastructure projects within the community as well as to gather reconnaissance
level information for preparation of a Conceptual Design Report (CDR) for any
identified projects.
The existing power plant and electrical distribution system was constructed in the
mid 1980's. The power plant is centrally located in the town site, co-located on a
parcel with the community building. The power plant building will need to be
modified in order to meet IBC fire separation requirements to other buildings and
property lines. The power generation and heat recovery equipment in is in poor
condition and in need of replacement. The proposed power plant renovation will
include three new generators (364kW total), programmable automatic paralleling
switchgear, remote radiators with variable speed control, a fire suppression
system, critical grade exhaust silencers, an automatic fill day tank, a heat
exchanger for generation heat recovery, and all required engine coolant piping
and ventilation equipment.
The existing community tank farm was constructed new in 2000 and is in excellent
condition. There are some minor code-compliance issues that need to be
addressed including security fencing, warning signs, and electrical system
revisions. Proposed fuel distribution pipeline work includes new paint and
supports on the existing fuel dock pipelines as well as a new 2" welded steel
pipeline to supply the power plant automatic fill day tank.
Proposed community heat recovery system upgrades include new heat recovery
equipment for the community building and shop building hydronic heating
systems.
Proposed community power distribution upgrades include one new residential
secondary service transformer for two planned new homes, upgrades to the
harbor electrical distribution and metering system as well as a prepaid electric
meter for the community dry-dock boat grid.
The proposed hydroelectric generation facility would be located approximately one
and one quarter miles southeast of the community of Elfin Cove. The
hydroelectric facility would include: a diversion structure on Crooked Creek; an
approximately 1,000 foot long diversion conduit from Crooked Creek to Jim's
Elfin Cove Energy Infrastructure Projects February 16, 2006
Concept Design Report Alaska Energy and Engineering
Lake, an approximately 1,300 foot long penstock from Jim's Lake to tidewater; a
hydro power house with turgo type turbine and programmable automatic
paralleling switchgear at tidewater; an approximately 9,000 foot long on-ground
transmission line to the renovated diesel power plant; fiber optic communication
cable between the hydroelectric powerhouse and the townsite diesel power plant;
and access trails to the power house and diversion structure.
For scheduling and cost estimate purposes all power plant, tank farm, fuel
pipeline, heat recovery and power distribution work is combined into a single
"Power System Upgrades" project. The proposed project schedule calls for
design and permitting to be completed by November 2006, for construction from
February through April 2007, with the renovated power plant fully functional by
May 2007.
The proposed hydroelectric facility and transmission line scheduling and cost
estimate is included as the "Hydroelectric Facility and Transmission Line" project.
The proposed project schedule calls for design and permitting to be completed by
August 2007, for construction from March through July 2008, with the
hydroelectric facility fully functional by August 2008.
Separate cost estimates have been prepared for the Power System Upgrade
(includ.ing power plant, tank farm, fuel pipeline, power distribution and heat
recovery upgrades) and the Crooked Creek/Jim's Lake Hydroelectric Project. The
estimated total project cost including all design, supervision, inspection,
permitting, and a 15% contingency for each component is:
• $1,016,185 Power System Upgrades
• $1,495,115 Crooked Creek/Jim's Lake Hydroelectric Project
The total installed generation capacity of the renovated diesel power plant is
364kW. The unit cost of the Power Plant Upgrade is $2,792/kW which is below
the Denali Commission benchmark cost range of $3,500 to $2,900 per installed
kW for 201 W to 400kW capacity power plants.
It is assumed that the operation and maintenance costs of the hydroelectric plant
will be comparable to that of the diesel generators. Therefore, the hydroelectric
project cost of $1,495,115 needs to be compared to the primary benefit which is
the avoided fuel cost. It is estimated that the hydroelectric generator would offset
approximately 25,600 gallons of diesel fuel per year. Using the average fuel price
paid by the electric utility in 2005 of $2.52/gallon this equates to an annual savings
of $64,500.
ii
Elfin Cove Energy Infrastructure Projects
Concept Design Report
INDEX
February 16, 2006
Alaska Energy and Engineering
Executive Summary ............................................................................................. Page i
Index ................................................................................................................. Page iii
Acronyms and Abbreviations ............................................................................... Page v
1.0 Introduction ................................................................................................... Page 1
1.1 Program Overview ................................................................................. Page 1
1.2 Community Description ......................................................................... Page 2
1.3 Site Investigation ................................................ : ................................... Page 2
1.4 Code Analysis & Deficiencies ................................................................ Page 3
2.0 Existing Facilities ........................................................................................... Page 4
2.1 Power Plant ........................................................................................... Page 4
2.2 Power Distribution .................................................................................. Page 5
2.3 Heat Recovery System .......................................................................... Page 5
2.4 Fuel Storage .......................................................................................... Page 6
3.0 Community Power Demand .......................................................................... Page 6
3.1 Estimated Future Load Growth .............................................................. Page 7
3.2 Alternative Energy/Efficiency Improvements .......................................... Page 7
4.0 Proposed Energy Infrastructure Project Descriptions ................................... Page 8
4.1 Power Plant Renovation ........................................................................ Page 9
4.2 Power Distribution Upgrades ............................................................... Page 11
4.3 Heat Recovery System Upgrades ........................................................ Page 11
4.4 Tank Farm Upgrades ........................................................................... Page 11
4.5 Crooked Creek/Jim's Lake Hydroelectric Project ................................. Page 12
5.0 Site Selection & ControL ............................................................................. Page 14
5.1 Power Plant Site .................................................................................. Page 14
5.2 IBC Fire Separation Requirements ...................................................... Page 15
5.3 Power Plant Fuel Pipeline Route ......................................................... Page 16
5.4 Tank Farm Site .................................................................................... Page 16
5.5 Fuel Dock Site ...................................................................................... Page 16
5.6 Harbor Site ........................................................................................... Page 16
5.7 Community Dry-Dock Grid Site ............................................................ Page 16
5.8 Hydroelectric Project Site ..................................................................... Page 16
5.9 Hydroelectric Transmission Cable Route ............................................. Page 16
5.10 Site Control ......................................................................................... Page 17
iii
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Engineering
6.0 Permitting and Spill Response ................................................................... Page 17
6.1 Environmental Assessment ................................................................. Page 17
6.2 Fire Code ............................................................................................. Page 18
6.3 Spill Response ..................................................................................... Page 18
6.4 Hydroelectric Project Permitting ........................................................... Page 18
7.0 Construction Plan ....................................................................................... Page 18
7.1 Local Job Skills .................................................................................... Page 19
7.2 Local Equipment .................................................................................. Page 19
7.3 Material Sources .................................................................................. Page 19
8.0 Schedule ....................................................................... ' ............................. Page 20
8.1 Power System Upgrades Schedule .................................................... Page 20
8.2 Hydroelectric Project Schedule ............................................................ Page 20
9.0 Cost Estimate ............................................................................................. Page 21
Concept Design Drawings ................................................................ , .............. Appendix A
Construction Cost Estimate ............................................................................. Appendix B
Site Control Documents ................................................................................. Appendix C
Electrical Data ................................................................................................. Appendix D
Description of Hydroelectric Project ......... , ...................................................... Appendix E
Meeting Summary Letters ............................................................................... Appendix F
iv
Elfin Cove Energy Infrastructure Projects
Concept Desig n Report
February 16, 2006
Alaska Energy and Engineering
ADCCED
ADEC
AEAlREG
AIDEA
API
ANTHC
BFU
CDR
COE
DC
DOT
EPA
F
GPM
HUD
IBC
ICDBG
IFC
MLLW
NEC
NFPA
NFS
RPSU
SHPO
SPCC
USCG
USCOE
USS
ACRONYMS AND ABBREVIATIONS
AK Department of Commerce, Community al)d Econ. Development
Alaska Department of Environmental Conservation
Alaska Energy Authority/Rural Energy Group
Alaska Industrial Development and Export Authority
American Petroleum Institute
Alaska Native Tribal Health Consortium
Bulk Fuel Upgrade
Conceptual Design Report
U. S. Army Corps of Engineers
Denali Commission
(Alaska) Department of Transportation and Public Facilities
U.S. Environmental Protection Agency
Degrees Fahrenheit
Gallons Per Minute
Housing and Urban Development
International Building Code
Indian Community Development Block Grant
International Fire Code
Mean Lower Low Water
National Electric Code
National Fire Prevention Association
Non-frost susceptible
Rural Power System Upgrade
State Historic Preservation office
Spill Prevention Control and Countermeasures
United States Coast Guard
United States Army Corps of Engineers
United States Survey
v
Elfin Cove Energy Infrastructure Projects
Concept Design Report
1.0 INTRODUCTION
February 16, 2006
Alaska Energy and Engineering
This report has been prepared by Alaska Energy and Engineering, Inc. (AE&E)
for the Alaska Energy Authority / Rural Energy Group (AENREG). The purpose
of this study is to provide a concept design and construction cost estimate for the
following potential energy infrastructure improvement projects for the Community
of Elfin Cove:
• Diesel power plant renovation.
• Minor upgrades to existing bulk fuel storage and handling facilities.
• Generation heat recovery system upgrades.
• Community power distribution improvements.
• Hydroelectric generation facility and transmission cable.
Participants in the project include the Community of Elfin Cove Nonprofit
Corporation (Community Association) and the Elfin Cove Electric Utility (Electric
Utility).
1.1 Program Overview
The Alaska Energy Authority (AEA), Rural Energy Group is pursuing grant funds
to upgrade rural bulk fuel tank farms and electric power systems. All project
components are dependent on available funding. Following is a brief outline of
the program:
• Most of the funds are federal and provided through the Denali Commission
(DC). Other federal funding may be available from HUD (ICDBG) and the
Environmental Protection Agency (EPA). Additional funds may be available
from the State of Alaska, USDA, and loan financing.
• In order to receive grant funds, each community must demonstrate that the
proposed facility will be sustainable by accepting a business plan. The
business plan shall describe who will own the facility, and how it will be
operated, maintained and replaced.
• New energy projects are funded, designed, and constructed in three phases:
Phase 1, Conceptual Design; Phase 2, Design Completion; and Phase 3,
Construction.
• During Phase 1, Conceptual Design, staff from AEA will visit a community,
discuss the program, and work with residents and the local government to
select sites for the new facilities.
• At the completion of Phase 1 Conceptual Design, the community will be
requested to review and approve the location, capacity, and basic
configuration of the facilities as well as a draft business plan.
• During Phase 2, Design Completion, the design for the new energy projects
will be completed. An environmental assessment will be prepared and site
control documented. A business plan will be prepared for signing.
• Each community will be requested to provide "in kind" contributions· as
available.
1
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Engineering
• Project may include local hire and construction trade training programs,
subject to Denali Commission funding.
• If the Denali Commission approves the business plan it will be circulated for
signature and construction procurement will start.
• Ineligible Projects: Funding is not available through AEA for buildings,
propane facilities, fuel tank trucks or trailers, fuel to fill the tank farm,
operation & maintenance costs, or residential tank upgrades. Loans for fuel
tank trucks and trailers may be available through USDA.
• Training Available: AEA has several training programs available for
communities.
1.2 Community Description
Elfin Cove is located on the northern shore of Chichagof 1~land, 70 air miles west
of Juneau and 33 air miles west of Hoonah. It lies at approximately 58.194°
North Latitude and 136.343° West Longitude (Sec. 25, T042S, R055E, Copper
River Meridian.) The area encompasses 10.7 square miles of land and 0.1
square miles of water. Elfin Cove has a maritime climate with cool summers and
mild winters. Summer temperatures range from 52 to 63; winters 26 to 39. The
highest recorded temperature is 85, and the lowest recorded temperature is
minus 10F. Total precipitation averages 102 inches a year, with 96 inches of
snow. The population was estimated at 26 residents in 2004. Elfin Cove is a
community association and is not a federally recognized native village. The
community is located in the Sitka Recording District and the Chatham School
District (CSD). The local school is no longer open and has been converted to a
community building.
1.3 Site Investigation
On Wednesday April 13, 2005, David Lockard of the Alaska Energy Authority I
Rural Energy Group (AEAlREG) and John Dickerson of Alaska Energy and
Engineering (AE&E) traveled to Elfin Cove. The purpose of the site visit was to
meet with local residents to identify and discuss potential energy infrastructure
projects within the community as well as to gather reconnaissance level
information.
Mr. Lockard and Mr. Dickerson arrived in Elfin Cove by float plane around noon
and proceeded directly to the community building where they met with power
plant operator Jim Lewis and tank farm operator Jim Wild. After a tour of the
power plant and fuel facilities, a town meeting was held at 4:45 P.M. The
meeting was attended by ten local residents including Community Association
Vice Chairperson Mary Jo Lord-Wild.
Prior to the field investigations, available information was obtained and analyzed,
including aerial photographs, community profile, survey plats, PCE data, Corps
of Engineers wetlands and flood information, and other relevant data. During the
initial field investigation, Elfin Cove Electric Utility electrical distribution system
drawings and power generation operator logs were obtained. Additional
information and input was obtained from the following individuals:
2
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Engineering
• Mr. Gordy Wrobel, Chairman, Community Association
• Ms. Mary Jo Lord-Wild, Vice-Chairman, Community Association
239-2221
239-2222
239-2252
239-2218
239-2222
• Mr. Hap Leon, resident
• Ms. Jane Button, Bookkeeper, Electric Utility
• Mr. Jim Wild, Tank Farm Operator, Community Association
• Mr. Jim Lewis, Power Plant Operator, Electric Utility
• Mr. Raymond O'Neil, VSW Primary Project Engineer
• Mr. J.W. Bean, Professional Land Surveyor, Juneau
• Mr. Brian Olsen, Delta Western Fuel, Juneau
• Ms. Marcy Johnson, Channel Construction, Juneau
• Mr. Doug Trucano, Trucano Construction, Juneau
• Alaska Marine Lines, Seattle
1.4 Code Analysis & Deficiencies
nfa
269-7603
789-0590
586-8000
789-0200
586-2444
(206) 764-8346
The following is a summary of existing power plant, electric distribution, and fuel
system code analysis and deficiencies observed during the site investigations.
Power Plant:
• The existing power plant building does not meet IBC required fire separation
distances from other buildings and property lines.
• Antiquated f inefficient diesel gensets -expensive to maintain and operate.
• Older automatic paralleling switchgear that does not respond properly to
current community demand profile.
Distribution System:
• Inadequate secondary service capacity for area of proposed new residential
construction.
• Inadequate service capacity and number of pedestals at small boat harbor.
Fuel Tank System:
A new bulk fuel facility was constructed in Elfin Cove in 2000. The following is a
summary of deficiencies observed at the new facility during the April 13, 2005
site visit:
• Missing Signage -Required signage missing, including emergency switch and
DEC spill information signs.
• Improper Fencing -Fencing does not completely enclose the tank farm and
portions of the existing fencing are less than six feet high.
• Improper Tank Labeling -Tanks are required to be labeled with product and
capacity.
• NEC Violations -Required conduit seal-offs at area classification zone
boundaries are missing.
• Improper Fill Indication-The dispensing tanks lack an audible alarm (whistle
vent) or 85% mark on the liquid level gauge as required by Fire Code.
3
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Engineering
• Improper Piping and Valves -Isolated sections of piping with no pressure
relief.
The concept design for all energy infrastructure projects have been prepared to
meet current code and regulatory requirements, which include:
• The 2003 Edition of the International Building Code (IBC).
• The 2003 Edition of the International Fire Code (lFC) and currently adopted
Alaska State Fire Marshal Fire and Safety Regulations.
• The 2002 Edition of the National Electrical Code (NEC).
• The 2002 Edition of the National Electrical Safety Code (NESC).
• 40 CFR, Part 112.1-12, U.S. Environmental Protection Agency Spill
Prevention Requirements
• 33 CFR, Part 154.30 & 154.1030, U.S. Coast Guard Spill Prevention
Requirements
2.0 EXISTING FACILITIES
The existing community energy infrastructure was evaluated to determine
specific needs and deficiencies. The power plant, distribution system, heat
recovery system and fuel storage were visually examined to determine suitability
for re-use. The following paragraphs summarize findings for the community.
2.1 Power Plant
The existing power plant building was constructed in the mid 1980's. It is located
in the center of town, adjacent to the community building and near several
lodges and residences. The building consists of an original 16'Wx26'L section
with a newer 6'Wx14'L entry/storage addition. The back, both sides and a
portion of the front wall of the original structure are constructed of pre-formed
concrete panels. A portion of the front wall as we" as the new storage
room/entry are wood frame constructed. Roof construction is with wooden
trusses and metal roofing. The building rests on a slab-on-grade foundation.
The noise level in the area of the power plant has been an area of concern due
to the close proximity of the community building, lodges and private residences.
The pre-formed concrete walls are excellent for sound absorption but the existing
exterior mounted exhaust silencers and open wall penetrations reduce the
potential for overall building sound attenuation. The existing building ventilation
system is inadequate, with only a single exhaust fan and no ventilation air intake
ducting. The lack of ventilation makes it necessary to leave the door open in
warm weather which increases the noise in the area.
There are three generators in the existing power plant, one rated at 60kW, one
at 205kW and the third at 195kW (installed used summer 2005 by community,
provided by AEAlREG). The 205kW and 60kW units are high hour antiquated
units near the end of their useful lives.
Engine cooling is with two remote radiators located outside on the south side of
the power plant. All three generators are on a common cooling manifold with the
other two radiators and a she" & tube heat exchanger that provides recovered
heat to the nearby community building and shop. All of the existing engine
4
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16. 2006
Alaska Energy and Engineering
cooling and heat recovery equipment appears to be original equipment and is
near the end of its useful life.
2.2 Power Distribution
Power generation is at 480V 3-phase. The existing automatic paralleling
switchgear includes a section for each of the three generators and a community
feeder/station service section. The switchgear was originally provided by NC
Equipment in the mid 1980's and is due for replacement. A pad-mount 150kVA,
three-phase, 480V to 7.2/12.47kV step-up transformer is located adjacent to the
power plant.
The distribution system is approximately twenty years old and is in good overall
condition. It is sectionalized at the power plant step-up transformer bank with
cable routed throughout the community in conduit underneath the boardwalks.
There is only one three-phase distribution section. which runs to the community
store (Lot 9). All other distribution is single phase. An approximately one mile
long single phase extension delivers power around the perimeter of Elfin Cove.
At the end of the developed townsite boardwalk area this extension converts to
armored cable placed on top of the ground which continues around the cove. It
then converts to a short section of overhead distribution on the western shore of
Elfin Cove where it provides service to several lodges and residences.
New housing construction is planned on the north side of town. an area currently
served by only a single 1 OkVA secondary service transformer.
The small boat harbor is under-served with power. with only six electric meters
located on the main float to serve the entire harbor. This situation forces the use
of long extension cords strung out on the finger floats to serve vessels located
off the main float, with resulting safety issues and low voltage problems.
There is a community small boat dry-dock grid in Elfin Cove where local vessels
can go dry for bottom work and maintenance. There is currently no power
source available in the grid area. A local resident has allowed boat owners to
run extension cords from his private service in the past but is reluctant to
continue this arrangement in the future.
2.3 Heat Recovery System
The community building and shop are currently served by generation heat
recovery from the nearby power plant. The system consists of a shell and tube
heat exchanger installed in the generator coolant system discharge piping in
series with two remote radiators. There is no thermostatic valve in the heat
recovery loop as is standard on AENREG generation heat recovery systems. A
short run of copper supply and return piping runs approximately fifteen feet to the
community building. Due to the limited time available during the site visit no
inspection was made of the community building/shop heating system. Additional
information regarding the existing buildings hydronic heating system will need to
be gathered prior to project design to determine if heating or heat recovery
system upgrades are warranted.
5
Elfin Cove Energy Infrastructure Projects
Concept Design Report
2.4 Fuel Storage
February 16, 2006
Alaska Energy and Engineering
The existing Community Association-'owned tank farm is located on the shoreline
adjacent to the fuel dock. It provides storage for virtually all of the diesel fuel and
gasoline imported into Elfin Cove. The tank farm was fully funded with a loan
taken out by the Community Association. It was constructed new in 2000, is in
excellent condition and, except for a few minor issues observed during the site
visit, appears to be a fully functional and code compliant facility. Some minor
improvements are recommended as part of the proposed energy infrastructure
upgrade projects.
The tank farm contains four each 20,000 gallon horizontal double wall bulk
storage tanks and three each horizontal double wall fire-rated dispensing tanks,
two at 8,000 gallons and one at 5,000 gallons capacity. These double wall tanks
now meet EPA secondary containment regulations due to the elimination of the
single tank capacity and aggregate tank farm capacity size restrictions that were
in effect at the time of the tank farm design and construction. Therefore the dike
with liquid tight membrane liner is no longer required for tank farm secondary
containment.
Three each 4" barge fill pipelines and three each 2" distribution pipelines run
from the tank farm to the fuel dock. The fuel dock has a three product marine
header and marine dispensing of unleaded gasoline, #1 diesel and #2 diesel.
Marine dispensing is from submersible pumps on the three dispensing tanks.
Fuel transfers from the bulk tanks to the dispensing tanks are also from
submersible pumps. A wooden pump house located adjacent to the tank farm
contains controls for the dispensing/bulk transfer pumps as well as a community
fuel distribution system for pumping fuel to the power plant and various heating
oil tanks within the community.
The Elfin Cove Electric Utility purchases fuel from the Community Association
tank farm. The fuel is pumped to the 600 gallon power plant day tank through
above grade community fuel distribution piping routed beside the boardwalk.
According to PCE data the Community Association purchases an average of
approximately 30,000 gallons of diesel fuel per year for power production.
3.0 COMMUNITY POWER DEMAND
Power consumption data was obtained from the Power Cost Equalization (PCE)
program for 1999 through 2005, and from electric utility operator logs. Graphs
are included in Appendix D. According to 1995 through 2005 peE data the
average annual load has ranged between 38.0kW and 45.4kW and annual fuel
consumption averages around 30,000 gallons. According to the power plant
operator logs the highest peak demand in 2004 was 144kW on July 21. The
lowest peak demand in 2004 was 28kW on October 6.
The 2005 peak demand, average demand and total kWh generated are lower
than 2004 due to problems with the power plant's main generator. Several of the
lodges were forced to self-generate during the peak summer demand period due
to the inability of the power plant to carry the peak community load. An
emergency repair project was undertaken to replace the 205kW unit with a low-
6
Elfin Cove Energy Infrastructure Projects
Concept Desig n Report
February 16, 2006
Alaska Energy and Engineering
hour used 195kW unit donated to the community by the AEA but the installation
was not completed until October, 2005, after the peak demand period had
passed.
3.1 Estimated Future Load Growth
It is important to evaluate the impact of planned infrastructure improvement
projects on an existing power generation system. New construction and other
community improvements can adversely impact the adequacy of existing
facilities. The following individuals were contacted about possible future
community improvement projects:
• Mr. Gordy Wrobel, Chairman, Community Association
• Mr. Raymond O'Neil, VSW Primary Project Engineer
239-2221
269-7603
Mr. Wrobel reported that there is currently planned construction of at least two
new residences in Elfin Cove. Mr. O'Neil reported that a feasibility study has
been completed for an improved water collection and distribution system. The
community has not yet requested funding for the project and the system has not
been designed. According to Mr. O'Neil the new system will be predominantly
gravity feed, will have minimum freeze protection requirements and will therefore
have minimal impact on near term future community fuel storage and power
generation requirements.
Unlike most rural Alaska communities, peak electric loads in Elfin Cove occur
between July and September. These summer peak loads are primarily
associated with local lodges that provide sport fish guiding and other recreation
activities as well as the influx of seasonal residents involved in commercial
fishing.
Due to recent reliability problems with the existing 205kW generator some of the
local lodges have been self-generating at peak daily demand times, such as
during meal preparations. The improved reliability of the renovated power plant
will eliminate the need for this self-generation and will likely cause an increase in
peak summer loads. In addition it is estimated that peak summer residential and
other electric loads will increase at a rate of 2% each year. Based on these
factors, it is estimated that the peak summer electric load may increase by
approximately 40kW over the next 5 years to around 185 kW.
Due to the magnitude of both the daily and annual load fluctuations, it is
important to size the generation equipment to maximize fuel economy, yet
provide sufficient redundancy so that any two gensets have the capacity to carry
the projected peak electric load.
3.2 Alternative Energy I Efficiency Improvements
An analysis of a potential hydroelectric project is included in Section 4.5.
Careful sizing and selection of new generators with advanced technology in
conjunction with the installation of new fully automatic paralleling switchgear and
a continuous off-line engine preheat system will likely result in a slight increase in
community power generation fuel efficiency.
7
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Engineering
The proposed improvements to the generation heat recovery system described
in Section 4.3 will maximize the efficiency of the system and the resulting fuel
savings.
The Community Association currently accepts used motor oil from the
commercial fishing fleet as well as other producers within the community,
including the power plant. .. The total quantity of used oil received/produced is
currently approximately 1,000 gallons per year. Used oil accepted directly from
private individuals is at times contaminated with other substances such as
ethylene glycol, water or even gasoline. Since there is currently no means of
testing for or separating out contaminants from the used oil, it is now all shipped
off site for disposal at considerable cost to the community. A settling system or
small centrifuge in conjunction with an end use facility such as a solid waste
incinerator or shop space heater would reduce the amount of used oil shipped
out for disposal, conserve energy within the community, and potentially save
money in the long term. The community should contact AEA Energy Cost
Reduction grant program manager Peter Crimp (888-300-8534) for information
about possible grant funding for this type of project.
The Alaska Energy Authority/Alaska Industrial Development and Export Authority
published a draft Rural Alaska Energy Plan dated December 31, 2002 as a
follow-up report to the previously released Screening Report of Alaska Rural
Energy Plan dated April 2001. The Screening Report evaluated a dozen
alternative energy technologies other than diesel engine heat recovery. Only
wind energy was identified as alternative energy technology warranting further
evaluation in the draft Rural Alaska Energy Plan. According to the Wind Energy
Resource Atlas of the United States the community of Elfin Cove is located
within a class 3 wind regime and is not a viable candidate for a wind energy
program using currently available technologies.
There are no other known practical energy sources, such as solid fuel or natural
gas, currently available at Elfin Cove. At this time, it appears that new, more
efficient diesel generators, supplemental hydroelectric generation and possibly
additional end-use conservation are the only viable fuel-saving technologies
available for Elfin Cove.
4.0 PROPOSED ENERGY INFRASTRUCTURE PROJECT DESCRIPTIONS
The following proposed facility descriptions are separated into five sections:
Section 4.1, "Power Plant Renovation", describes proposed upgrades to the
existing Electric Utility power plant; Section 4.2, "Distribution Upgrades",
describes proposed upgrades to the existing community electrical distribution
system; Section 4.3, "Heat Recovery Upgrades", describes proposed upgrades
to community building/shop hydronic heating systems; Section 4.4, "Tank Farm
Upgrades", describes proposed minor upgrades to the Community Association
tank farm; and Section 4.5 "Hydroelectric Project" describes the proposed
Crooked Creek/Jim's Lake Hydroelectric project and transmission cable.
8
Elfin Cove Energy Infrastructure Projects
Concept Design Report
4.1 Power Plant Renovation
February 16, 2006
Alaska Energy and Engineering
The power plant is located in the heart of the community, only ten feet from a
lodge, less than fifteen feet from the community building and very close to
several residences. Due to the proximity of the power plant to these public and
private facilities, the Community Association has requested that the upgrade
design specifically address the areas of fire safety, noise control and air quality:
• Fire Safety -As mentioned previously, the existing power plant building does
not meet IBC fire separation requirements. Preliminary discussions with the
Deputy State Fire Marshall have resulted in a building renovation plan for
correcting the situation. An as-built survey is required to locate improvements
(buildings and boardwalk) relative to existing property boundaries. The final
design will be reviewed by the State Fire Marshall's office for compliance with
all current code and regulatory requirements. The renovated power plant will
also contain an automatic fire alarm and water mist fire suppression system.
This will be an improvement over the existing facility since there is currently
no fire suppression.
• Noise Control -The existing critical grade silencers will be replaced with
interior mounted hospital grade silencers. The hospital grade silencers
provide maximum noise reduction at the exhaust outlet. Placing all of the
silencer shrouds inside the concrete building structure will maximize resonant
sound absorption. All three exterior exhaust stacks will be routed up to a
height of approximately 20' above grade. Sound attenuation will be provided
at all building penetrations and combustion/ventilation air openings, with all
openings located to minimize the noise impact on nearby buildings.
• Air Quality -The existing generators are not EPA certified for low emissions.
The proposed new generators will be at least EPA Tier I certified and the new
marine jacketed (64kW) generator will be EPA Tier \I certi'fied. EPA certified
engines are not currently required in the State of Alaska for small power plant
installations like Elfin Cove, but due to advances in engine technology these
new EPA certified gensets will be more fuel efficient and will produce lower
emissions than the existing units. Raising the exhaust stacks, necking down
the stack at the tip to increase velocity and terminating vertically will also
allow for better dispersion of the exhaust plume and decrease the impact of
emissions near the power plant. These improvements, in addition to the new
automatic paralleling switchgear and improved power plant ventilation, will all
have a positive effect of reducing emissions. Proper maintenance of the
generators will be necessary to ensure long term clean operation of the
engines.
It is proposed that all three existing generators be replaced with new, cleaner
and more fuel efficient units. One generator should be sized to handle the entire
community load during peak load periods. Another generator should be sized to
provide efficient generation during low (winter) loads while maximizing
generation heat recovery. The third generator should be sized to efficiently
handle intermediate loads and to combine with the small generator to provide
peak capacity generation in case the main unit is offline for maintenance or
9
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Engineering
repairs. Therefore it is proposed that one each 190kW (summer peak), one
each 110kW (intermediate load), and one each 64kW (winter load) prime rated
generators be installed, for a total installed capacity of 364kW. The proposed
64kW (winter load) genset will be the prime genset for approximately eight
months out of the year. This unit will be powered by a marine jacketed (water
cooled exhaust manifold) engine to provide for additional generation heat
recovery. The marine jacket will also significantly reduce the noise level of this
genset.
The following proposed upgrades are intended to modernize the existing
community power plant, to bring it into compliance with IBC fire separation
requirements, and to improve the overall fuel efficiency, reliability, fire
prevention/protection, noise control, air quality and operations at the facility:
• Renovate building to meet IBC fire separation requirements.
• Install fire suppression and alarm systems.
• Replace all three existing generators, utilizing marine jacketed unit for winter
loads for improved generation heat recovery and quieter operation.
• Replace existing switchgear and relays with new programmable automatic
paralleling switchgear with hydroelectric intertie expansion capabilities.
• Provide for continuous preheat of off-line generators to allow for immediate
(less than thirty seconds) generator switching during times of sudden sharp
increases in community demand.
• Replace existing exhaust silencers with new interior mounted hospital grade
silencers on all three generators.
• Route new exhaust stacks higher and terminate vertically for improved
exhaust dispersal and reduced noise.
• Provide noise attenuation at all building penetrations.
• Install adequate ventilation with sound-insulated air intake and exhaust fan
ducting.
• Replace existing engine coolant and generation heat systems with new
system including thermostatic valve and brazed plate heat exchanger for
improved efficiency.
• Replace existing radiators with new radiators and variable speed motor
controls.
• Install new 100 gallon automatic fill day tank in power plant with redundant
overfill protection.
• Install new drop tubes on #1 & #2 diesel dispensing tanks. Install new filter,
pump, and electric actuated ball valve at tank farm pump house. Install
dedicated welded steel supply pipeline from tank farm to new day tank.
10
Elfin Cove Energy Infrastructure Projects
Concept Design Report
4.2 Power Distribution Upgrades
February 16, 2006
Alaska Energy and Engineering
Proposed community power distribution upgrades include:
• New pad-mount 10kVA secondary service transformer for planned new
residential construction on north end of town.
• New secondary service and lockable service meter for community small boat .
dry dock grid.
• Replace the existing harbor meters with eight dual service (16 total plugs)
30A 120V single-phase metered marina-style pedestals spaced evenly along
the small boat harbor floats.
• New dedicated single phase feeder and 20kVA pad-mount step down
transformer for 120V service to small boat harbor (assumes 70% feeder
loading and 0.40 demand factor for harbor).
4.3 Heat Recovery System Upgrades
Generation heat recovery from the renovated power plant has the potential to
save approximately 2,800 gallons of fuel use annually in Elfin Cove. The existing
generation heat recovery and delivery equipment is approximately twenty years
old and is due for replacement. The following improvements will be included in
the final upgrade design:
• Replace all heat recovery copper tubing with welded steel arctic pipe.
• Install new heat exchanger, pump, and instrumentation in the power plant.
• Install a recovered heat BTU meter in the power plant.
• Install valves, equipment, and instrumentation as required in the community
building and shop heating systems.
• Install alarms for loss of 'flow and loss of pressure, and no load/backfeed
condition with annunciation in the power plant switchgear.
4.4 Tank Farm Upgrades
The following minor upgrades are proposed for the Elfin Cove Community
Association tank farm:
• Install missing required signage, including emergency shut down switch sign
and DEC spill information signs.
• Provide tank labels with required product and capacity information.
• Install 6' tall chain link fence with a l' high barbed wire top around entire tank
farm perimeter.
• Install NEC required conduit seal-offs at area classification zone boundaries
within tank farm.
• Install pressure/vacuum whistle vents to provide audible overfill alarm on
tanks.
• Provide 85% mark on all tank liquid level gauges.
11
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Engineering
• Install pressure relief valves on isolated piping sections at community fuel
distribution pump house.
• Touch-up paint on existing fuel dock pipelines and provide new supports with
isolation cushions to protect pipe coating.
4.5 Crooked Creek/Jim's Lake Hydroelectric Project
In April, 1984 the Alaska Power Authority (APA) published a study entitled
"Supplement to the Elfin Cove Reconnaissance Study" which analyzed a
proposed 80kW hydroelectric generation facility to be located on Port Althorp
approximately one mile south of Elfin Cove. At the time the report was written
there was no community power generation or distribution in Elfin Cove. The
project as described in the report consists of the following components:
• A three to five foot high diversion dam on Crooked Creek constructed of local
materials (wood, rock and earth).
• A 1,650 foot long diversion conduit from Crooked Creek to Jim's Lake
constructed of 18" diameter corrugated aluminum pipe.
• A sluice gate and trash rack at the upper end of the Crooked Creek diversion
conduit.
• An intake siphon, trash screen and log weir at the Jim's Lake outlet.
• A 2,400 foot long 12" diameter HDPE pipe penstock from the Jim's Lake
outlet to the powerhouse, including intake valve, vacuum relief valve and
pressure relief valve.
• A single 80kW capacity pelton-wheel turbine with automatic governor and
single-phase generator along with required switchgear.
• A 10'x12' powerhouse shed, concrete pad and corrugated aluminum pipe
tailrace.
• A 6,700 foot long single phase transmission line of corflo-encased 15kV #2
XLP cable laid on top of the ground with splice cabinets at 500 foot intervals.
• A single-phase electric distribution system throughout the community.
All available data regarding the potential hydroelectric project, including the
mentioned report, was forwarded to hydroelectric generation specialist Bob
Butera, P.E. at HDR, Inc. Mr. Butera was tasked with analyzing the report along
with available stream data and providing a cursory opinion on the feasibility,
constructability and reliability of the proposed project. He was also tasked with
providing an updated and inflation adjusted cursory budgetary cost estimate for
the hydroelectric project. The HDR, Inc. analysis and revised cost estimate are
based on the original proposed stand-alone hydroelectric generation project as
described in the 1984 APA report and are included in Appendix E of this report.
Following are proposed changes to the scope of the original APA Crooked
Creek/Jim's Lake hydroelectric project due to changes in technology, existing
community infrastructure and increased power demand in Elfin Cove since 1984:
12
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Engineering
• Community Distribution -At the time the 1984 report was written there was
no community diesel power plant or distribution system in Elfin Cove.
Therefore the proposed APA project included all required community
distribution equipment. The community now has a diesel power plant and
electrical distribution system so the distribution component of the original
APA project has been removed from the revised project plan.
• Site Access -The APA project does not provide for skiff access at the
powerhouse site nor does it provide for permanent trails for ease of access to
the penstock intake at Jim's Lake or the Crooked Creek diversion structure.
Access to these sites will be required on a regular basis for inspection and
maintenance operations. Therefore an allowance for construction of a small
floating dock at the powerhouse and access foot trails to the entire
hydroelectric infrastructure has been included in the revised cost estimate.
• Hydroelectric Powerhouse -The APA project calls for a site-constructed
10'x12' wood frame building with slab on grade foundation. In order to
minimize required site work another option may be to import a prefabricated
modular powerhouse. The module could then be placed directly onto a piling
foundation at tidewater by a barge-mounted crane.
• Hydroelectric Turbine Automatic Governor -The proposed APA project
called for an "automatic governor" on the hydroelectric turbine but did not
include an allowance for installation of the required level sensing equipment
at the reservoir or turbine control interface to the powerhouse. The revised
cost estimate includes an allowance for a reservoir head probe and
communication wires in conduit to the powerhouse as well as a solid state
automatic turbine governor.
• Diesel-Hydroelectric Hybrid System Communication & Controls -The
original APA proposal was for a stand-alone single phase hydroelectric
generation and distribution system and therefore did not require a scheme for
integration with an existing diesel plant and three-phase distribution system.
The new project will require a remote control/data communication scheme to
allow the new hydroelectric powerhouse and the existing diesel power plant
to operate as a hybrid paralleling system in order to get maximum benefit
from the available hydro resources without jeopardizing the electrical power
supply. Communication between the hydroelectric and diesel plants will be
through 12-fiber armored fiber optic cable run along side the transmission
line.
• Switchgear & Step-upIStep-down transformers -Generation at the
hydroelectric and diesel plants will be at 480V three-phase. In order to limit
conductor size and line reactance the transmission voltage will be stepped up
to 2.4/4.1 kV at the hydro end for transmission. The voltage will be stepped
back down to 480V at the diesel plant for connection directly to the new 480V
diesel plant switchgear and integration into the existing community
distribution system.
• Transmission Line -The proposed APA project called for a 6,700 foot long
7.2kV single-phase transmission line of corflo-encased 15kV #2 XLP cable
13
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16,2006
Alaska Energy and Engineering
laid on top of the ground from the hydroelectric powerhouse to the south end
of Elfin Cove. The revised project plan is for a 9,000 foot long 2.4/4.1 kV
three-phase transmission line of 5kV #2 CLX armored cable from the
hydroelectric powerhouse to the diesel power plant. The cable will be shallow
buried in hand-dug trenches where possible and run on top of ground where
not possible. The final approximate 1,000 feet will be routed with the existing
community boardwalks.
• Turbine -The original APA proposal was for an 80kW pelton wheel style
turbine. Due to advances in technology since 1984 it appears that a turgo
style turbine with PLC controller is now a more cost effective and efficient
choice for the flow available at the proposed hydroelectric facility. A single
nozzle Turgo unit with a rated output of 107kW at 1200 RPM with a direct
coupled 100kW generator has been proposed for the revised project.
The Hydroelectric Project cost estimate provided in Appendix B incorporates the
above proposed changes along with the inflation-adjusted cost estimate of the
unchanged portions of the original APA project as provided by HDR, Inc.
A step function approximation of availability versus demand was used to
estimate potential fuel savings based on 2004 average electric loads and the
following hydroelectric water flow assumptions:
• Three summer high demand and mean flow months @ 65kW average
hydroelectric production
• One summer drought month @ 20kW average hydroelectric production
• Seven winter low demand and mean flow months @ 30kW average
hydroelectric utilization
• One winter freeze-down month @ 13kW average hydroelectric production
This corresponds to a total of 320,000 kWh of hydro-electric production per year.
Assuming a diesel generation efficiency of 12.5 kWh/galion, the annual fuel
savings is estimated to be approximately 25,600 gallons.
5.0 SITE SELECTION & CONTROL
Work for this project will be performed in seven general areas: (1) The "Power
Plant Site"; (2) The "Power Plant Fuel Pipeline Route"; (3) The "Tank Farm Site";
(4) "The Fuel Dock Site"; (5) The Harbor Site; (6) The Community Dry-Dock Grid
Site; (7) The "Hydroelectric Project Site"; and (8) The "Hydroelectric
Transmission Cable Route". There are no known flood hazards at any of these
locations.
5.1 Power Plant Site
The existing power plant is located on Lot 13A, U.S. Survey No. 2946 as shown
in Appendix A, Sheet M2. The community building (ex-school building) is also
located on this lot, approximately fourteen feet from the power plant. The corner
of the power plant building entry/storage room is over the property line shared
with the adjacent boardwalk easement and is also less than ten feet from the
Eagle Charters Lodge building directly across the boardwalk.
14
Elfin Cove Energy Infrastructure Projects
Concept Desig n Report
February 16, 2006
Alaska Energy and Engineering
5.2 IBC Fire Separation Requirements
The IBC requires minimum separations from buildings to a property line or the
centerline of a public easement (fire separation distance) depending on
occupancy, type of building construction and fire resistance rating of exterior
walls. The power plant falls within IBC occupancy group F-1 (Factory Industrial,
Moderate Hazard), which includes electric light plants and power houses. The
adjacent community building is currently used for public meetings, which falls
under occupancy group A-3 (Community Halls). The adjacent lodge falls under
occupancy group R-1 (Boarding Houses & Hotels). For the purposes of this
study it is assumed that all three buildings are non-fire rated construction
throughout with no automatic sprinkler systems, which classifies them as Type
V-B construction per the IBC. The following table summarizes the IBC fire-
resistance rating and fire separation distance requirements for the previously
mentioned occupancy groups of construction Type V-B only:
I
FIRE-RESISTANCE RATING REQUIREMENTS (TYPE V-B CONSTRUCTION)
OCCUPANCY OCCUPANCY OCCUPANCY
FIRE SEPARATION GROUP F-1 GROUPA-3 GROUP R-1
DISTANCE (POWER (COMMUNITY (LODGE)
PLANT) BUILDING)
less than 5' 2hr 2hr 2hr
greater than or equal to 5' 1hr 1hr 1 hr and less than 10'
greater than or equal to 10' Ohr Ohr Ohr and less than 30'
The existing power plant entry/storage room encroaches into the public
easement and is less than 5'-0" from the easement centerline. The IBC would
require the walls and door in this area to be 2hr rated assemblies, which would
be impractical to meet. Therefore it is proposed to remove the existing
entry/storage room and relocate it so that it does not encroach into the public
easement and is at least 5'-0" from the easement centerline, which would require
only a 1 hr rated door and wall assembly.
The proposed fire separation boundary as shown on Sheet M4 would be less
than 10' from the walls of the existing lodge and community buildings. According
to the State Fire Marshall's Office, this would not immediately impact these
buildings. However, any future major renovations to the affected portions of
these buildings would require a plan review and could require existing structural
assemblies to be improved to a 'I hr or 2hr rating at the time of the future
renovation.
15
Elfin Cove Energy Infrastructure Projects
Concept Design Report
5.3 Power Plant Fuel Pipeline Route
February 16, 2006
Alaska Energy and Engineering
The proposed new day tank fill pipeline will be routed within Lots 3 and 138,
USS 2946 alongside the existing boardwalks from the tank farm to the power
plant. See Appendix A, Sheet M2.
5.4 Tank Farm Site
The existing Community Association tank farm is located within Lot 2, USS 2946.
All tank farm upgrades will occur within the existing tank farm property boundary.
See Appendix A, Sheet M2.
5.5 Fuel Dock Site
The fuel dock and associated fill and distribution pipelines are located within
Alaska Tidelands Survey No. 443 (ATS 443). All fuel dock pipeline upgrades will
occur within the existing tidelands survey property boundary.
5.6 Harbor Site
The small boat harbor is located within ATS 1473, with the access ramp located
within Lot 1 of ATS 442. The electrical service upgrades on the harbor floats will
occur within these existing tideland survey boundaries. See Appendix A, Sheet
M2.
5.7 Community Dry-Dock Grid Site
The community dry dock grid is located within ATS 1473. The electrical service
upgrades at the dry-dock grid will occur within the existing tideland survey
boundary and adjacent upland property. See Appendix A, Sheet M2.
5.8 Hydroelectric Project Site
If constructed, the hydroelectric project will be located approximately one mile
south of Elfin Cove. The project area encompasses a portion of the Crooked
Creek and Jim's Lake drainages and extends to the powerhouse at the Port
Althorp shoreline. The proposed diversion dam and a portion of the diversion
conduit are located within Section 31, Township 42 South, Range 56 East. The
diversion conduit termination and penstock inlet at Jim's Lake are within Section
6, Township 43 South, Range 56 East. The penstock will also cross Section 31,
Township 43 South, Range 55 East and terminate at the powerhouse within
Section 36, Township 42 South, Range 55 East. See Appendix At Sheet M1.
5.9 Hydroelectric Transmission Cable Route
The proposed transmission cable will be routed cross country within Section 36,
Township 42 South, Range 55 East from the powerhouse to the southern
boundary of the Elfin Cove community. The cable will then follow the existing
single phase at-grade distribution line north across private parcels to the
boardwalk, where it will be supported below the boardwalk in conduit
approximately 1000' to the power plant. See Appendix A, Sheets M1 and M2.
16
Elfin Cove Energy Infrastructure Projects
Concept Design Report
5.10 Site Control
February 16, 2006
Alaska Energy and Engineering
A Certificate to Plat was issued by Southeastern Title Agency effective
December 8, 2005. A copy of the Plat Certificate is included in Appendix C.
Additional independent site control research was conducted to verify title to
existing rights of ways and adjacent lands, which were not identified in the
Certificate to Plat.
The existing power plant, located on Lot 13A, USS 2946, is vested in the
Community of Elfin Cove.
The new power plant fuel pipeline is located on Lots 3 and 138 of USS 2946.
Lot 138 is owned by the State of Alaska. The State of Alaska Department of
Transportation issued a Declaration of Public Right of Way, July 2, 1999, which
includes Lot 3. A copy of the Declaration was not included in the Cert to Plat. A
copy of the Declaration has been requested from the recorders office.
The existing tank farm site, located on Lot 2, USS 2496, is vested in the
Community of Elfin Cove.
The fuel dock site, located within Alaska Tidelands Survey No. 443, is vested in
the Community of Elfin Cove. There is a 1978 reference to a lease of dock
facilities with Pelican Cold Storage Company; however, there is no recorded
document for this lease.
The harbor site is located within ATS 1473 and Lot 1 of ATS 442. Lot 1 of ATS
442 is vested in the Community of Elfin Cove. ATS 1473 is vested in the State
of Alaska.
The community dry dock grid, located within ATS 1473,is vested in the State of
Alaska.
The hydroelectric project site is located within the Tongass National Forest
boundary, which is owned by the United States of America. Should the
hydroelectric project progress to final design, permits and easements/rights-of-
ways will need to be secured prior to construction.
The cross country portion of the hydroelectric transmission cable traverses
Section 36, Township 42 South, Range 55 East, which is owned by the United
States of America. The portion of the cable within the community crosses several
privately held parcels. Easements and/or rights-of-ways will need to be secured
for the transmission cable route.
6.0 PERMITTING AND SPILL RESPONSE
The renovated power plant and existing tank farm are subject to regulations of
both State and Federal agencies including the Alaska Coastal Management
Program, the Alaska Department of Environmental Conservation (ADEC), the
Division of Fire Prevention, and the U.S. Environmental Protection Agency and
U.S. Coast Guard.
6.1 Environmental Assessment
An Environmental Assessment (EA) will be completed prior to construction of the
proposed project. An EA is required for all projects that are federally funded or
require a federal permit (such as a Corps of Engineers Wetlands Permit). The
17
.Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Engineering
EA determines whether there is a significant impact to the environment caused
by the project. As part of the EA, a Coastal Zone Management Project
Questionnaire will be completed and submitted to the Alaska Coastal
Management Program. The Coastal Zone Management Project Questionnaire
helps to identify state or federal permits that may be required.
6.2 Fire Code
A Plan Review permit from the State Fire Marshal is required for the fuel and
power plant portions of the project. Final stamped design drawings will be
submitted to the Fire Marshal for review prior to construction. Plans will be
reviewed for conformance with the International Fire Code and related codes
including the International Building Code and the National Electrical Code. The
review process can take anywhere between 3 weeks to 6 months.
6.3 Spill Response
Because the existing Community Association tank farm has oil storage tanks in
excess of 1,320 gallons and receives delivery by marine vessel, it is subject to
U.S. Environmental Protection Agency and U.S. Coast Guard regulations. If
required, the existing Coast Guard and EPA plans will be reviewed and updated
and additional spill response gear will be purchased as part of this project.
6.4 Hydroelectric Project Permitting
In addition to the EA requirements listed above, the hydroelectric portion of this
project will require the following separate permits/review process if built:
• Alaska Department of Natural Resources
o Water Rights Permit
o Fish Habitat Permit
o Coastal Zone Management Consistency Review
• Federal Energy Regulatory Commission (FERC) license or waiver
• Site control permits and/or easements for access to the site and for
electric transmission cable right of way.
7.0 CONSTRUCTION PLAN
The AEAlREG has a history of administering similar projects on a "modified"
force-account basis. Force-account construction involves the owner or grantee
acting as the employer and utilizing primarily local labor. This method tends to
achieve a higher percentage of local hire and is strongly supported by many
communities and funding agencies. The highly technical nature of power
generation and distribution projects requires a limited number of workers with
spedfic experience and expertise to be brought in for the project when not
available locally. All work must be supervised and managed by a superintendent
with extensive experience in the construction of rural power generation and
distribution systems. All specialty work, such as pipe welding and electrical
installation must be performed by skilled craftsmen with appropriate
certifications. An experienced construction manager will be required to recruit
18
Elfin Cove Energy Infrastructure Projects
Concept Design Report
February 16, 2006
Alaska Energy and Eng ineering
the necessary skilled labor, coordinate the construction team, and oversee
procurement and project logistics. The design engineer will provide quality
control through communication with the construction manager and periodiC on-
site inspections.
The nature of the projects identified will allow most of the projects to be
constructed simultaneously and independently from the other. The power plant,
distribution and tank farm upgrades as well as the hydroelectric project are
separate and will not necessarily need to be constructed using the same
construction management teams.
There is no direct shipping or ferry service into Elfin Cove. All project
construction materials and equipment will be staged in Juneau and delivered to
Elfin Cove using a local barge or landing craft service.
7.1 Local Job Skills
As previously noted, the number of year round residences in Elfin Cove was only
26 as of the 2004 census. The population increases dramatically in the summer
with the influx of commercial fishermen, lodge owners, lodge employees and
tourists .. Few, if any, of these summer residents would be available to work on
the energy infrastructure upgrade projects. Every effort should be made to hire
locally but it should be assumed that many of the project supervisors and
workers will need to be hired outside of the community.
7.2 Local Equipment
There is no locally available heavy equipment in Elfin Cove.
7.3 Material Sources
This project has minor site development so very little fill material will be required.
There is no borrow source for gravel within the community.
19
Elfin Cove Energy Infrastructure Projects
Concept Design Report
8.0 SCHEDULE
February 16, 2006
Alaska Energy and Engineering
The proposed project schedule is separated into two sections: Section 8.1,
"Power System Upgrades Schedule", and Section 8.2, "Hydroelectric Project
Schedule". The "Power System Upgrades" project includes all power plant, tank
farm, fuel pipeline, heat recovery and power distribution work. The schedules
have been set to take advantage of the best seasonal weather for most work. All
schedules are contingent on timely approval of the plan by all project participants
and the Denali Commission.
8.1 Power System Upgrades Schedule
It will be most efficient to manage the power plant, heat recovery system, tank
farm and distribution system upgrade work as one project due to their
interdependence, the similarity of work skills required, and their proximity to each
other. There is no site development work associated with these projects and a
good portion of the work is not weather dependent. Therefore an off-season
schedule was developed to take advantage of better construction personnel
availability and to have the least impact on the local summer tourism and fishing
economies. It is assumed that funding could be available in time for construction
in early 2007. The schedule could be adjusted as required to accommodate
funding availability.
• Mar-Nov 2006: Design, permitting, and site control.
• Oct -Dec 2006: Order generators, switchgear, radiators, materials, etc ..
• Feb 2007: Mobilization and temporary power installation.
• Feb-April 2007: Project construction.
• May 2007: Project completion, power plant commissioning & operator training.
• June 2007: O&M manuals and project close out.
8.2 Hydroelectric Project Schedule
Permitting and design for the hydroelectric project would not likely be completed
in time for summer 2007 construction due to the long expected time frame for
State and Federal permit approval. Therefore, the following schedule has been
developed on the basis of performing the majority of the work for the hydroelectric
project during early spring through summer 2008. This schedule is contingent on
timely approval of the plan by the Elfin Cove Community Association and Denali
Commission as well as on funding availability.
• Mar 2006-Aug 2007: Design, permitting, and site control.
• Sep 2007: Order turbine, switchgear, building materials, etc ..
• March 2008: Project mobilization, startup.
• March-July 2008: Project construction.
• August 2008: Project completion, commissioning & operator training.
• Sep 2008: O&M manuals and project close out.
20
Elfin Cove Energy Infrastructure Projects
Concept Design Report
9.0 COST ESTIMATE
February 16,2006
Alaska Energy and Engineering
The construction cost estimates have been developed based on a "modified"
force-account approach utilizing a combination of local labor, certified craftsmen,
and specialty sub-contractors under the direction of an experienced construction
manager. Labor rates are based on Title 36 equivalent wages for certified
specialty labor and prevailing local force-account wage rates for general labor
and equipment operation.
Detailed cost estimates are included in Appendix B. Separate estimates have
been prepared for the Power System Upgrade (including power plant, tank farm,
fuel pipeline, power distribution and heat recovery upgrades) and the Crooked
Creek/Jim's Lake Hydroelectric Project. The estimated total project cost
including all design, supervision, inspection, permitting, and a 15% contingency
for each component is:
• $1,016,185 Power System Upgrades
• $1,495,115 Crooked Creek/ .. lim's Lake Hydroelectric Project
The total installed generation capacity of the renovated diesel power plant is
364kW. The unit cost of the Power Plant Upgrade is $2,792/kW which is below
the Denali Commission benchmark cost range of $3,500 to $2,900 per installed
kW for 201W to 400kW capacity power plants.
It is assumed that the operation and maintenance costs of the hydroelectric plant
will be comparable to that of the diesel generators. Therefore, the hydroelectric
project cost of $1,495,115 needs to be compared to the primary benefit which is
the avoided fuel cost. It is estimated that the hydroelectric generator would
offset approximately 25,600 gallons of diesel fuel per year. Using the average
fuel price paid by the electric utility in 2005 of $2.52/gallon this equates to an
annual savings of $64,500.
21
APPENDIX A
CONCEPT DESIGN DRAWINGS
I TOWNSHIP 42S
----4-1 ---
TOWNSHIP 43S
1 "=1/4mi
(APPROXIMATE)
PROJECT: ELFIN COVE
ENERGY INFRASTRUCTURE PRO.IECTS
TITLE:
OVERALL PROJECT SITE PLAN
w w
U") I <0
U")IU")
~ ~ z z « « ~ SEE SHEET M2 0::: 0:::
FOR ALL ENERGY . INFRASTRUC~TURE : ~
UPGRADE WORK t::d
IN TOWNSITE
AREA
_BI':
IlESICNED BI':
AI[!WIIE SHEET OF
LfIN-CDR-t.tl M 1 5
25 30
36 31
I HYDROELECTRIC
TRANSMISSION
CABLE ROUTE
POWERHOUSE
DIVERSION ~
DAM ~ HYDROELECTRIC
PROJECT SITE -----
PENSTOCK
DIVERSION
CONDUIT
stat., 01 AlaI"" • DMI nt Deparlqlent of Communl1;)' and EconomIC opme * 1f AIDEA/AEA *,e Rural Ene(gy Gn>up ~ALASKA a'l Wwt Northem Ll9ht. BML '_E"EFIGYAUTHORITY * * -Mc:ttorDte. No.ka n5DJ
FUEL
DOCK
SITE
EXISTING 3"
BARGE FILL AND
2" DISPENSING
PIPELINES TO
RECEIVE MINOR
UPGRADES (SIX
PIPELINES TOTAL)
TANK FARM SITE
-EXISTING TANK
FARM TO RECEIVE
MINOR UPGRADES
1 "=150'
PROJECf: ELFIN COVE
ENERGY INrRASTRUCTURE PROJECTS
ENLARGED AREA SITE PLAN
NEW SECONDARY
SERVICE TRANSFORMER
FOR PLANNED NEW
RESIDENCES
POWER PLANT SITE -
EXISTING POWER PLANT
, TO BE RENOVATED. SEE
\~.EEE1ETS M3. M4 & M5
@)~ , ,
HEAT RECOVERY »
SYSTEM
UPGRADES AT
: COMMUNITY "I "'-
HALL & SHOP I~ I "'-,
® Iv; ,
c:%f-,--"--L..l / HYDROELECTR
Z
1
1
1
\Z
HARBOR X
SITE ,
IJIAWN lit: SCIt£: 1·'" 150'
WIGN!ll lit: DAlE: 2/16/06
Fl£ NII£ SHEET OF
LF'IN-CDR-t.l2 M 2 5
\ ,
\
/ TRANSMISSION
()
UPGRADED
DISTRIBUTION
AND SERVICE
METERS ON "
HARBOR /
FLOATS
CABLE ROUTE
USS
2947
NEW PRE-PAY
METER FOR
COMMUNITY BOAT
DRY -DOCK GRID
I
I (2) PORTI~~ +''-----OF : ,,~ APPROX. LOCATION OF
ENTRY / ' , ~ LINES, TYP
LODGE
EXISTING I ~ ,/ EXISTING PROPERTY
STORAGE -............,
AA~ '~ R-l OCCUPANCY
WOOD FRAME INTO PRE -CAST
ENCROACHING I
®
PROJECT:
PUBLIC CONCRETE "'\
~SEMENT :
& WITHIN
5' OF
CENTERLINE
OF PUBLIC
~SEMENT
I
\
I
I
I
I
I
\
I
I
I
I
I
I @I
I
I
I
I
I
I
I
I
I
POWER PLANT
F-1 OCCUPANCY
/"" WOOD FRAME
CHASE AROUND
EXHAUST RISERS
TO BE REMOVED
PRE-CAST
CONCRETE
TO REMAIN
"-RADIATOR
SHED TO BE
REMOVED
COMMUNITY BUILDING
A-3 OCCUPANCY
WOOD FRAME
CONSTRUCTION
, ELFIN COVE IlIWIIN 81': sr.tI£:'"= 10' SIIlta a/ AIoeIuI , Ooopartrpent of Comiriunlt}! and Econom1c ~
ENERGY INFRASTRUCTURE PROJECTS IESIGNED 81': DATE: 2-16-06 * ~lIr AlOtA/AEA. r-:TIIl.E:.,....,-....;;;.:..=.:..;.:;..;.....;~;....;.;;...;~;....;.;;...;..;.;;;...-~..;.;;;...----f.fl£~IWI£~--+-:6SH==EU,.;;-:-=--:iOf:-t * ftu"" Ifiiei1Dr Group r-!!! ALASKA
. POWE~ PLANT ~J3 * * L e.~ __ """:..~hI. ,1I""EAGYAUTHeAITV
EXISTING SITE/DEMOLrrlON PLAN LFIN-CDR-1A3 M 5
PRO.IECT:
I
I
I
I
: / EXISTING PROPERTY
~ LINE, TYP
-r I ~"
I I -........z
LODGE
R-l
OCCUPANCY
WOOD FRAME
i --~ ~
I.J.... o
w z
~I w
t-
Z
W
U
ELFIN COVE
ENERGY INFRASTRUCTURE PROJECTS
POWER PLANT
PROPOSED FIRE SEPARATION PLAN
lHR
CONSTRUCTION
REQUIRED,
INTERIOR WALL
PROTECTION ONLY
DRAIN 1Ir:
COMMUNITY BUILDING
A-3 OCCUPANCY
WOOD FRAME
CONSTRUCTION
stILE: 1"= 10'
IlESIGIIED 1Ir: DATE: 2/16/06
fl.E NNoE SHEEr OF
lFIN-CDR-t.l4 M 4 5
o TO 5' FROM
POWER PLANT
I; IMAGINARY
I PROPERTY UNE,
TYP
1"=10'
State of Alollka Depar\q1ent 01 Community and _nomic Dortelopment '*'*_ AIDEA/AEA . Rural Ene,tgy Group ALASKA
::-a'3~~ ~503I1rfd. r:ENlERGYAUTHORITY
FIRE SUPPRESSION
CONTROL PANEL &
AGENT RACK
D
AUTOMATIC FILL 100
GALLON DAY TANK
". ....... . .... ' .. , ... -...... .
GEN#3, 64kW
HOSPITAL GRADE
SILENCER, TYP(3)
/
~.,.---,I
~ x EF-1
~cS~~ I ?~N#2
110kW /
. x EF-2
~cS~~ 19~~#1 190kW . --;-,
REt2 I HEAT EXCHANGER, ~;-
PUMP, VALVES, ETC "':;: :
cD . I RELOCATED
ENTRY/
STORAGE 'R~l I ASTE GEN GEN GEN :. -I
M #1 #2 #3 j I
AUTOMATIC
PARALLELING
SWITCHGEAR
PROJECT: ELfiN COVE
ENERGY INfRASTRUCTURE PROJECTS
POWER PLANT RENOVATION PLAN
RADIATOR
VFD PANELS
• " " ••••• p •••• ". " •• ' :....J
INSTALL SHED ~OOF\
OVER RADIATORS
_ BY: JTD SCIL£: 3/16"=1'
DESIlNED BY: BeG DAlE: 2/16/06
AL£ IWoIE SHEET OF
ELFIN-CDR-t.45 M 5 5
APPENDIX B
CONSTRUCTION COST ESTIMATE
ALASKA ENERGY & ENGINEERING ELFIN COVE RURAL POWER SYSTEM UPGRADE
COST ESTIMATE SUMMARY
TEMPORARY GENERATION $9,200
POWER PLANT BUILDING RENOVATION $18,400
POWER GENERATION DEMOLITION $7,800
POWER GENERATION UPGRADES $468,375
TANK FARM UPGRADES & FUEL PIPELINES $65,415
HEAT RECOVERY UPGRADES $22,500
DISTRIBUTION UPGRADES $53,700
MISCELLAN EOUS $14,500
OVERHEAD $51,100
FREIGHT $32,649
CONSTRUCTION SUB-TOTAL $743,639
DESIGN AND CONSTRUCTION ADMIN. $70,000
CONSTRUCTION MANAGEMENT $70,000
PROJECT SUB-TOTAL $883,639
CONTINGENCY $132,546 15 %
TOTAL PROJECT COST $1,016,185
TOTAL INSTALLED KW CAPACITY 364 kW
COST PER KW OF INSTALLED CAPACITY $2,791.72
B-1
FEBRUARY 16, 2006
PRELIMINARY DESIGN REPORT
ALASKA ENERGY & ENGINEERING
ITEM QUAN UNIT UNIT
COST
TEMPORARY GENERA TOR
Set Up Temporary Generator 1 lump $0
Generator Rental 3 month $2,000
POWER PLANT BLDG RENOVATION
Remove Entry & Exhaust ChasE 1 lump $0
Misc Building Modifications 1 lump $3,000
New Entry/Storage 1 lump $5,000
POWER GENERATION DEMOLITION
Provide Temp Station Service 1 lump $0
Remove Three Generators 1 lump $0
Remove Switchgear & Conduit 1 lump $0
Remove Exhaust Silencers 1 lump $0
Remove CoolantlHR/Fuel Pi~e 1 lump $0
Remove Radiators & HX 1 lump $0
Remove Exist Lighting 1 lump $0
POWER GENERATION UPGRADES
190 kW Genset (JD 6081) 1 ea. $48,000
110 kW Genset (JD 6068) 1 ea. $40,000
64 kW Genset (JD 4045) 1 ea. $40,000
Switchgear 1 ea. $140,000
Fire Supression 1 lump $25,000
Major Electrical Equipment 1 lump $5,000
VFD & Day Tank Panels 1 lump $18,000
Wireway 1 lump $3,000
Conduit, Fittings, Wire, Etc. 1 lump $7,000
Feeder & Shielded Cable 1 lump $6,000
Ducts, Fans, Dampers, Etc. 1 lump $16,000
Radiators 2 ea. $9,000
Hydronic Piping, Equip 1 lump $8,000
Day Tank 1 lump $2,000
Day Tank Appurtenances 1 lump $5,000
Fuel Oil Piping 1 lump $2,500
Hoses & Fittings 1 lump $1,500
Exhaust Thimbles, Pipe, Etc 1 lump $3,000
Misc Strut, Hangers, Fasteners 1 lump $4,000
Fill Coolant, Fuel, & Lube 1 lump $5,000
ELFIN COVE POWER SYSTEM UPGRADE
CONSTRUCTION COST ESTIMATE
MATL UNIT LAB LAB LABOR
COST HRS HRS RATE COST
$0 40 40 $80 $3,200
$6,000 0 0 $80 $0
$0 40 40 $65 $2,600
$3,000 40 40 $65 $2,600
$5,000 80 80 $65 $5,200
$0 10 10 $65 $650
$0 40 40 $65 $2,600
$0 20 20 $65 $1,300
$0 10 10 $65 $650
$0 20 20 $65 $1,300
$0 10 10 $65 $650
$0 10 10 $65 $650
$48,000 30 30 $80 $2,400
$40,000 30 30 $80 $2,400
$40,000 30 30 $80 $2,400
$140,000 60 60 $80 $4,800
$25,000 80 80 $80 $6,400
$5,000 50 50 $65 $3,250
$18,000 40 40 $65 $2,600
$3,000 40 40 $65 $2,600
$7,000 140 140 $65 $9,100
$6,000 60 60 $65 $3,900
$16,000 80 80 $65 $5,200
$18,000 20 40 $65 $2,600
$8,000 150 150 $65 $9,750
$2,000 10 10 $65 $650
$5,000 30 30 $65 $1,950
$2,500 40 40 $65 $2,600
$1,500 15 15 $65 $975
$3,000 60 60 $65 $3,900
$4,000 40 40 $65 $2,600
$5,000 20 20 $65 $1,300
8-2
CONTR
COST
FEBRUARY 16, 2006
PRELIMINARY DESIGN REPORT
FREIGHT TOTAL UNIT TOTAL
COST COST WT WT(#)
$3,200 4,000 4,000
$6,000 0
0
$2,600 0
$5,600 0
$10,200 0
$650 0
$2,600 0
$1,300 0
$650 0
$1,300 0
$650 0
$650 0
$50,400 3,000 3,000
$42,400 3,000 3,000
$42,400 2,500 2,500
$144,800 2,000 2,000
$31,400 1,000 1,000
$8,250 500 500
$20,600 300 300
$5,600 500 500
$16,100 2,000 2,000
$9,900 1,000 1,000
$21,200 1,500 1,500
$20,600 400 800
$17,750 2,000 2,000
$2,650 500 500
$6,950 250 250
$5,100 200 200
$2,475 200 200
$6,900 1,000 1,000
$6,600 500 500
$6,300 3,000 3,000
ALASKA ENERGY & ENGINEERING
ITEM QUAN UNIT UNIT
COST
TANK FARM & FUEL PIPELINES
2" Sch 80 Welded Coated 300 lin. ft. $8.00
1" Actuator Valve 1 ea $1,400
2" Pipeline Filter 1 ea $1,200
2" Flanged Ball Valves 4 ea $225
2" Flanged Check Valves 2 ea $175
PressureNacuumIWhistle Vent 7 ea $250
1" Flanged PRV 3 ea $475
New Drop Tubes on Disp Tanks 1 lump $300
Signs 1 lump $500
6' Chain-Link Fence 350 lin.ft. $10.50
Dock Pipeline Supports 1 lump $2,000
Paint Dock Pipelines 1,500 sq.ft. $0.60
Classified Boundary Seal-Ofts 1 lump $1,000
Conduit, Conductors, & Devices 1 lump $4,000
HEAT RECOVERY UPGRADES
Arctic Pipe 1 lum2 $2,000
PP Heat Exchanger 1 ea. $2,500
PP Heat Recov Pipe & Devices 1 lump $1,000
Buildings HX & Pipin9_ 2 ea. $2,000
DISTRIBUTION UPGRADES
10kVA Residential Xfrmr 1 lump $2,000
20kVA Harbor Xfrmr 1 lump $2,500
Drydock Grid Secondary Servic 1 lump $8,000
Harbor Feeder 1 lulllP $2,000
Harbor Pedestals 8 ea. $1,500
MISCEllANEOUS
Spill Response Supplies 1 lump $2,000
SmartAsh with spare parts 1 lump $3,000
Misc Hardware 1 lump $2,000
Misc Tools & Safety Gear 1 lump $5,000
Welding Rod, Gases, Etc. 1 lump $2,500
OVERHEAD
Audit Grants 1 lump
Rent Heavy Equip. 1 lump
Test & Commission System 1 lump
ELFIN COVE POWER SYSTEM UPGRADE
CONSTRUCTION COST ESTIMATE
MATl UNIT lAB lAB LABOR
COST HRS HRS RATE COST
$2,400 0.30 90 $65 $5,850
$1,400 4 4 $65 $260
$1,200 4 4 $65 $260
$900 2 8 $65 $520
$350 2 4 $65 $260
$1,750 2 14 $65 $910
$1,425 4 12 $65 $780
$300 20 20 $65 $1,300
$500 10 10 $65 $650
$3,675 0.50 175 $65 $11,375
$2,000 60 60 $65 $3,900
$900 0.10 150 $65 $9,750
$1,000 40 40 $65 $2,600
$4,000 80 80 $65 $5,200
$2,000 40 40 $65 $2,600
$2,500 20 20 $65 $1,300
$1,000 100 100 $65 $6,500
$4,000 20 40 $65 $2,600
$2,000 30 30 $80 $2,400
$2,500 30 30 $80 $2,400
$8,000 40 40 $80 $3,200
$2,000 40 40 $80 $3,200
$12,000 25 200 $80 $16,000
$2,000 0 0 $65 $0
$3,000 0 0 $65 $0
$2,000 0 0 $65 $0
$5,000 0 0 $65 $0
$2,500 0 0 $65 $0
60 60 $80 $4,800
B-3
CONTR
COST
$6,000
$5,000
FEBRUARY 16, 2006
PRELIMINARY DESIGN REPORT
FREIGHT TOTAL UNIT TOTAL
COST COST WT WT(#)
$8,250 5 1,500
$1,660 25 25
$1,460 20 20
$1,420 30 120
$610 30 60
$2,660 20 140
$2,205 10 30
$1,600 1000 1000
$1,150 100 100
$15,050 15 5250
$5,900 1000 1000
$10,650 0.20 300
$3,600 1000 1000
$9,200 1000 1000
$4,600 1000 1,000
$3,800 500 500
$7,500 1,500 1,500
$6,600 100 200
$4,400 2,000 2,000
$4,900 2,000 2,000
$11,200 50 50
$5,200 500 500
$28,000 50 400
$2,000 600 600
$3,000 200 200
$2,000 500 500
$5,000 500 500
$2,500 1000 1000
$6,000
$5,000
$4,800
ALASKA ENERGY & ENGINEERING
ITEM QUAN UNIT UNIT
COST
Train Local Operators 1 lump
Superintendent Overhd Off-Site 1 lump
Superintendent Overhd On-Site 1 lump
Crew Travel Time 1 lump
Crew Airfares 8 trips
Crew Per Diem 200 mn.dy
Housing Rent 3 mo.
FREIGHT
Barge Freight Seattle-Juneau 48,245 lb. $0.20
Freight & Equip Mob 4 day $3,000
Project De-Mob 2 day $3,000
Misc Small Freight & Gold Strea 1 lump $5,000
CONSTRUCTION SUB-TOTAL
Engineering (Design & CCA) 1 lump
Construction Management 1 lump
PROJECT SUB-TOTAL
Contingency 15 %
ELFIN COVE POWER SYSTEM UPGRADE
CONSTRUCTION COST ESTIMATE
MATL UNIT LAB LAB LABOR
COST HRS HRS RATE COST
40 40 $80 $3,200
40 40 $80 $3,200
40 40 $80 $3,200
80 80 $80 $6,400
$483,300 2,836 $197,390
$483,300 $197,390
CONTR
COST
$6,400
$8,400
$4,500
$30,300
$70,000
$70,000
$170,300
FEBRUARY 16, 2006
PRELIMINARY DESIGN REPORT
FREIGHT TOTAL UNIT TOTAL
COST COST WT WT(#)
$3,200
$3,200
$3,200
$6,400
$6,400
$8,400
$4,500
48,245
$9,649
$12,000
$6,000
$5,000
$32,649 $743,639
$32,649 $883,639
$132,546
ITOTAL PROJECT COST $1,016,185
B-4
ALASKA ENERGY AND
ENGINEERING
CROOKED CREEK/JIM'S LAKE HYDROELECTRIC GENERATION
COST ESTIMATE SUMMARY
WORK ITEM MATERIAL LABOR
REVISED 1984 EST (SEE APPENDIX E)
INCREASE FOR HIGHER LABOR RATE $60,000
LESS 1 0'x12' POWERHOUSE SHED & CONCRETE PAD ($7,500) ($6,700)
LESS PEL TON TURBINE/SINGLE-PHASE GEN ($142,000) ($8,000)
LESS SINGLE-PHASE TRANSMISSION COMPONENT ($58,000) ($8,700)
4,000' OF ACCESS TRAILS $10,000 $30,000
HYDRO POWERHOUSE & FOUNDATION PILINGS $30,000 $10,000
TURGO TURBINE/3-PHASE GEN W/ PLC & SWITCHGEAR $160,000 $20,000
ARMORED FIBER OPTIC DATA CABLE $12,500 $4,500
9,000' 5kV 3-PHASE #2 ARMORED CABLE TRANS LINE $135,000 $65,000
112.5kVA STEP-UP & STEP-DOWN TRANSFORMERS $16,000 $8,000
DIESEL PLANT SWITCHGEAR CONNECTION & PROGRAMMING $10,000 $10,000
CONSTRUCTION SUB-TOTAL
FREIGHT
DESIGN AND CONSTRUCTION ADMIN.
CONSTRUCTION MANAGEMENT
FERC PERMITTING
PROJECT SUB-TOTAL
CONTINGENCY
TOTAL PROJECT COST
8-5
FEBRUARY 16, 2006
PRELIMINARY DESIGN REPORT
TOTAL
$600,000
$60,000
($14,200)
($150,000)
($66,700)
$40,000
$40,000
$180,000
$17,000
$200,000
$24,000
$20,000
$950,100
$40,000
$80,000
$80,000
$150,000
$1,300,100
$195,015 15 %
$1,495,115
APPENDIXC
SITE CONTROL DOCUMENTS
Alaska Energy and Engineering. Inc.
Mailing Address -P.O. Box 111405
AnchoraR:e, AK 99511-1405
(907) 349-0100
349-8001 fax
November 22, 2005
Southeastern Title Agency
ATTN: Duane Kauffman, President
P.O. Box 1223
Sitka, AK 99835-7701
Subject: Elfin Cove Certificate to Plat Information
Dear Mr. Kauffman:
(2 Pages Faxed) 907-747-3616
Please find enclosed Sheet M1 of 1 for the Elfin Cove Energy Infrastructure Projects
Certificate to Plat Areas of Interest, ATS 443, ATS 442 & USS 2946. Please prepare a
Certificate to Plat to include the following items:
• Parcel 1: Timber approach pier of ATS 443.
• Parcel 2: Lots 2,3,6,7,13, 13A, & 13B of USS 2946
• Parcel 3: Lot 1 of ATS 442
• Parcel 4: ATS 1473.
Please indicate the estimated lead-time to deliver the Certificate to Plat.
You are authorized to bill up to $500 for this effort. If you anticipate exceeding
this amount, please call me prior to proceeding.
If you have any questions, please call me at (907) 349-0100, or fax your comments to
(907) 349-8001.
Attachments -as noted
1"=200' I
EXHIBIT A
ENERGY INFRASTRUCTURE PRO.IECTS
1JTI.E:
.'v-------------ATS 443
r-----------USS 2946, LOT 2
r-------USS 2946, LOT 3
r------USS 2946, LOT 13
r------USS 2946, LOT 138
~-----USS 2946, LOT 6
.----~.-----USS 2946, LOT 7
.-----:~--USS 2946, LOT 13A
tA;----~-ATS 442
/
I
I
,
'\
~
\ /!;LFIN Cj
'V'
, ,
~ ,
'\
~
SIoI" of Ala.ka O"porbpent of Community and EconomIc Oovelopment
CERTIFICATE TO PLAT
AREAS OF INTEREST ELFIN PLAN M 1
**a. AIDEA/AEA Rural Energy Group ALASKA
81l West Northem u!Jhte Blvd. r: ENERGY AUTHORITY * * ""ehoI'DOe. Nm.ko 99503
S.QUTHEASTERN TITLE AGENCY, INC.
210 LAKE STREET
P.O. BOX 1223
SITKA, ALASKA 99835
Alaska Energy and Engineering, Inc.
Steven J. Stassel, P.E.
P.O. Box 111405
Anchorage, Alaska 99511-1405
Dear Mr. Stassel,
PHONE: (907) 747-3278
FAX: (907) 747-3616
E-MAIL: STAI@PTIALASKA.NET
PLAT CERTIFICATE
Our Order Number: S-05-6720
Your File No.
This is a Plat Certificate as of December 8, 2005 at 8:00 am for a plat on the following property:
(See attached Exhibit 'A')
This company hereby certifies that the record title is vested, as follows, free from any liens, encumbrances, and objections of record
except as follows:
VESTED IN:
(See attached Exhibit 'B')
SUBJECT TO:
1. Provisions and Reservations contained in the Patent from the United States of America.
2. Provisions and reservations as contained in the patent from the State of Alaska.
Affects: Parcel # 1, # 2
3. This property is outside any taxing district.
4. Any adverse claim based on the assertion that any portion of the said land was not tide or submerged land
subject to disposition by the State of Alaska on the effective date of the grant of said land, or that any
portion thereof has ceased to be tide or submerged land by natural causes or imperceptible causes.
(8) Rights and easements for commerce, navigation and fishery.
(C) Any prohibition to limitation on the use, occupancy or improvement of the land resulting from the rights
of the public or riparian owners to use any waters which may cover the land.
Affects: Parcel#1,#2,#3 --(\r';.. 'i'G, ~1{!2., i'f!..;:
5. Plat Note: The natural meanders of the mean high water line forms the true bounds of Fuel Dock
Subdivision. The approximate line of mean high water, as shown, is for area computations only. The true
Fuel Dock Subdivision corners being on an extension of the sidelines and there intersection with the natural
meanders.
Affects: Parcel # 1 i '_. I ". l~:.
6. Declaration of Public Right of Way
Recorded : July 2, 1999
Book/Page : 137/756
Affects Parcel # 2, #4, #5, #8, & #9 ".' . ",:." .-; . .,.. f .. ) /.!?I.-" )--'1 ........ : I.>
EXCEPTIONS CONTINUED
Page {PAGE}
7. Deed qftrust to secure an indebtedness of the amount herein stated and any other amounts payable under
the terms thereof.
Amount : $200,000.00
Dated : June 30, 2003
Recorded : July 8, 2003
Document No. : 2003-001672-0
TRUSTOR : COMMUNITY OF ELFIN COVE, a non-profit corporation
TRUSTEE : SOUTHEASTERN TITLE INSURANCE AGENCY, INC.
BENEFICIARY : ROBERT L. DUDLEY, Jr. and LESLIE DUDLEY, husband and wife
Affects: Parcel # 1 ATS'll-\?.::;;
8. Deed of trust to secure an indebtedness of the amount herein stated and any other amounts payable under
the terms thereof.
Amount : $180,526.20
Dated : November 26,2002
Recorded : December 2, 2002
Document No. : 2002-002261-0
TRUSTOR : SHIRLEY and WILLIAM PERKINS, wife and husband
TRUSTEE : FIRST AMERICAN TITLE
BENEFICIARY : WELLS FARGO FINANCIAL ALASKA, Inc.
Affects Parcel # 6 L?{ C,
9. Right, title and interest of the herein named party because of the circumstances herein noted.
Party : SHIRLEY and WILLIAM PERKINS, wife and husband
Reason : By being trustors on the deed of trust recorded 12/2/2002 as Document
No. 2002-002261-0 Affecting Parcel # 6 1,0 T (,
10. Easement and Agreement for water use
Dated : December 27, 1966
Recorded : May 15, 1967
Book/Page : 12/75 through 77
Affects Parcel # 7 and Parcel # 8 LOI "1 J 13A
11 . Land Use Permit
Recorded : May 14, 1996
Book/Page : 120/778 through 785
Affects Encroachment of house from Parcel # 6 onto a portion of Parcel # 5
12. Encroachments, if any, of the dock, oil warehouse, and oil pipes on Lot 2 U.S. Survey 2946(Parcel # 4) or
Lots 1 and 2 Plat 2002-6 (Parcel # 1), as shown on U. S. Survey 2946
13. Unrecorded Leases, if any
I
So...u1b.eastern Title Agency. #! (:~i)c~",~) ILK·
Duane L. Kauffman .I
END OF EXCEPTIONS
EXCEPTIONS CONTINUED
Page {PAGE}
EXHIBIT "A"
Order Number: S-05-6720
. ,'l
\;(/ ,\", JpARCEL # 1 : Lot One (1) and Lot Two (2), FUEL DOCK SUBDIVISIOI'J, according to the plat
:\ thereof filed February 4, 2002 as Plat No. 2002-6, Sitka Recording District, First Judicial District,
State of Alaska.
PARCEL # 2 : Lot One (1), ALASKA TIDELANDS SURVEY No. 442, according to Plat No. 57,
Sitka Recording District, First Judicial District, State of Alaska .
PARCEL # 3 : Tract A, ALASKA TIDELANDS SURVEY 1473, according to the plat thereof filed
September 14, 2000, Plat 2000-12, Sitka Recording District, First Judicial District, State of
Alaska
PARCEL # 4 : Lot Two (2) , U.S. Survey 2946, Sitka Recording District, First Judicial District,
State of Alaska
PARCEL # 5 : Lot Three (3), U.S. Survey 2946, Sitka Recording District, First Judicial District,
State of Alaska
PARCEL # 6 : Lot Six (6) EXCEPTING THEREFROM the northwesterly 42 feet, U.S. Survey
2946, Sitka Recording District, First Judicial District, State of Alaska.
PARCEL # 7: All of Lot Seven (7), U.S. Survey 2946, ALSO INCLUDING a portion of Lot
Thirteen A (13A), U.S. Survey 2946, Sitka Recording District, First Judicial District, State of
Alaska, more particularly described as follows;
Beginning at a point on the common lines of Lot 7 and 13A from which Corner No.4 of Lot
13A and Corner No.1 of Lot 7, bears S 86°00'00' E 52.96 feet; thence S31°54'57" E, 17.38
feet; thence N 58°05'03", 24.00 feet; thence N 86°00'00' W, 29.63 feet to the point of beginning
PARCEL # 8 : Lot Thirteen A (13A), U.S. Survey 2946, EXCEPTING THEREFROM, the portion
more particularly described as follows;
Beginning at a point on the common lines of Lot 7 and 13A from which Corner NO.4 of Lot
13A and Corner No.1 of Lot 7, bears S 86°00'00' E 52.96 feet; thence S 31°54'57' E, 17.38
feet; thence N 58°05'03",24.00 feet; thence N 86°00'00' W, 29.63 feet to the point of beginning,
Sitka Recording District, First Judicial District, State of Alaska
PARCEL # 9: Lot Thirteen (13), U.S. Survey 2946, Sitka Recording District, First Judicial
District, State of Alaska
LEGAL DESCRIPTION -continued
PARCEL # 10: Lot Thirteen B (13B), U.S. SUNey 2946, Sitka Recording District, First Judicial
District, State of Alaska
VESTING EXHIBIT
Order No: S-05-6720
PARCEL # 1, # 2, # 4, # 8: COMMUNITY OF ELFIN COVE, a non-profit corporation
established and existing under the laws of the State of Alaska
PARCEL # 3 & # 10: STATE OF ALASKA
PARCEL # 5: ALASKA MENTAL HEALTH TRUST AUTHORITY
PARCEL # 6 : SHIRLEY C. PIEDRA
PARCEL # 7 : BARBARA J. BELL and DENNIS A. BELL
PARCEL # 9 : ELFIN COVE EAGLE CHARTERS ALASKA, LLC.
APPENDIX D
ELECTRICAL DATA
Elfin Cove Monthly kWh Generated
7 0000 ~'"~''''"'~''''~''''''''''''''''''''''''''''''''''''''''''''''''''''''''' .............. -.. -...... "" ... ~ ...................... " ...................................... w ••• "" ... • .•.•.• "' .• w ...... • .• • ........ · ...................... "" .... "" ....................... "" ............................... " .• " ................. ,
60000+-----~--------------------------------------------------------~
50000
II1II2001
c 40000 (!)
02002
(!) ~2003
I
~ 30000
[]]2004
.2005
20000
10000
o
Month
D-1
Elfin Cove Peak kW Load
160 ~.~ .............................................................................................. ~ ...................................................................................................................... ,. ............ m ................ •• .. •• .. • .. •• .. • .. •• .... • .. • .. ••••• ........ • .. i
140+-~------------------------------------------------------------------~
120
100
~ 80
60
40
20
o
~<A ~<A ~--s ~--s
)'1> «.~
Month
1DJ2001
02002
11.\12003
.2005
--.... ---....... ~-----------------------------------~---.... --------------------'
D-2
Elfin Cove Average kW Load
100 ............................................................................................................................................................................................................................................................................. .
90 +-------------------------------------------------------------------~
60
~ 50
40
30
20
10
o
Month
D-3
.2001
02002
m2003
.2005
Elfin Cove Annual kWh Gen
410,000
400,000
390,000
380,000
c 370,000 Q)
(9
~ 360,000
350,000
340,000
330,000
320,000
2001 2002 2003 2004 2005
Year
D-4
APPENDIX E
DESCRIPTION OF HYDROELECTRIC PROJECT
L. ~R lONE COMPANY .c-J.A. Many Solutions'"
To: Steve Stassel, AE&E .....
Memo
From: Bob Butera, HDR y~ Project Elfin Cove Hydroelectric Project
CC: . J
Date: December 15, 2005 Job No: 201662/34153
Introduction
Alaska Energy and Engineering, Inc (AE&E) is performing a power and fuel facilities
investigation for the town of Elfin Cove (Blfm Cove). A hydroelectric project was proposed for
this community in the early 1980's. As part of this analysis AE&E requested HDR Alaska, Inc.
(HDR) to:
1. Review existing available hydroelectric study information (April 1984 Supplement
to the Elfin Cove Reconnaissance Study) and J.W. Bean data (to be provided later).
2. Determine availability of existing stream gauge data for nearby streams and adjust
data to simulate available flows for Jims Lake and Crooked Creek.
3. Assess proposed hydro construction scenario and provide opinion of
constructability and reliability. Provide recommendations for improvements to
proposed construction.
4. Review proposed hydro construction cost estimate. Provide a budgetary
construction cost estimate based on proposed improvements
Fllilding for this work was very limited and therefore the extent of this analysis is cursory.
1. Review of Existing Information
A Reconnaissance Study of Energy Requirements and Alternatives for Elfm Cove was prepared
in February 1984 by a consultant on contract to the Alaska Power Authority (AP A). That report
recommended a small hydro facility on Roy's Creek, a small creek in Elfin Cove. The APA later
fOllild Roy's Creek not feasible and recommended a different small hydro facility about one mile
south of the town. This project would use the c,?mbined flow from Crooked Creek and from the
drainage basin of Jim's Lake. The APA prepared a report "Supplement to the Reconnaissance
Study of Energy Requirements and Alternatives for Elfin Cove" in April 1984. This supplement
focused exclusively on a hydroelectric project on Crooked Creek and Jim's Lake (Crooked
Creek Project).
The Roy's Creek project (and potential projects at 2 other small local streams, Ernie's Creek and
Joe's Creek) was judged not feasible because long time residents had monitored the creek and
stated that it was extremely flashy. It would essentially go dry during periods of dry or cold
weather and would turn into a torrent during precipitation events. Based on review of aerial
photography, the drainage basin of Roy's Creek appears to be steep bedrock with little vegetative
cover. 1bis landform would result ill the reported stream conditions. Based on this we concur
with the AP A finding that Roy's Creek would not be suitable for hydroelectric development.
The Crooked Creek Project as proposed by the AP A would divert the flow from Crooked Creek
to Jim's Lake. AP A reports state that Jim's Lake has a surface area of approximately 4 acres and
is reported to be 24 feet deep. The Jim's Lalce drainage basin is very small, but APA noted that
the lake could provide some storage to potentially allow the project to operate during normal
HDR Alaska, Inc.
1
2525 C Sileel
Sulle 305
Anchorage. AK 99503 I
Phone (907) 644-2000
Fax (907) 644-2022
www.hdlinc.com
I Page 1 016
winter and summer low flow periods. The APA Crooked Creek project has the following
characteristics.
Table 1: AP A Crooked Creek Hydro Project Characteristics
Location Crooked Creek and Jim's Lake
Capacity 80kW
Gross Head 350 feet
Net Head 330 feet
Design Flow 4.5 cfs
Flume 1650', 18", Aluminum CMP, lain on ground
Penstock 2400', 12", HDPE
Transmission Line 6700 feet, on ground
Estimated Construction Cost $400,000 (1984 dollars including plant, t-line and
distribution system in town)
One of the recommendations of the AP A supplement was to collect at least one year of
continuous streamflow records for the Crooked Creek proj ect. This streamflow data collection
was initiated in July 1984 and is discussed in the Hydrology section below. Other
recommendations were to confIrm the elevation of the project and to do a detailed
reconnaissance of the flume, penstock and transmission line routes.
A December 6, 1990 AEA memorandum from Eric Marchegiani addressed the project. This
memorandum stated that there was a 1990 cost estimate of $532,000 to construct the project.
This memorandum suggested the following steps to further this project:
1. Review and analysis of the collected streamflow data
2. Site visit and preliminary design to verify the constructability of the project and cost
estimate.
3. Prepare an economic analysis
4. Prepare a financial analysis
S. Initiation of permitting
6.. Finalize design
7. Finalize permits
8. Finalize fmancing
9. Construction manager
10. Construction contract
A rough estimate for the above work was $571,000 including a 10% contingency.
Elfin Cove now has a central diesel power plant and an electrical distribution system
No other known work has been done regarding a hydroelectric project at Elfin Cove.
2. Hydrology
The AP A estimate of power was based upon a rough estimate of streamflow made by comparing
the drainage area of the Project with the unit discharge of other U.S. Geological Survey gaged
streams on Chichagof Island. The AP A report recommended that stream gages be installed on
Crooked Creek and on Jim's Lake and a year of data collected.
HDR Alaska, Inc.
1
2525 C Street
Suite 305
Anchorage. AK 99503 I Phone (907) 644-2000
Fax (907) 644-2022
www.hdrinc.com
1 Page2of6
This streamflow data collection was done by the Alaska DGGS. In a December 6, 1990 ABA
memorandum it was stated that the DGGS collected l'l2 to 2 years of streamflow data (July 1984
to April 1986) but data for the period of July 6, 1984 to May 3D, 1985 was all that was found by
Mr. Marchegiani in 1990 or at the time of this review. This data includes daily mean, minimum
and maximum flow for the period of record at Crooked Creek and at Jim's Creek. There is also a
combined daily discharge record for the combined Crooked Creek and Jim's Creek. sites. This
combined data includes mean, minimum and maximum daily flows and also includes median
daily flows. The methodology or quality of this data is unknown as there is no rating curve or
summary of measurements. Of the 328 days of record, 66 days (20%) were estimated. Table 2
is a summary of this combined flow data.
Table 2: Crooked Creek/Jim's Creek Streamflow Data
Mean Minimum Maximum Median
Year Month Flow Flow Flow Flow
(cf& (efs) Jcfs) Jcfs)
July 2.87 1.09 24.74 1.81
August 2.46 0.96 38.10 1.42
September 2.1l 0.76 19.26 1.18
October 2.94 0.89 32.28 1.29
November 1.95 0.76 26.38 1.18
December 2.74 0.59 17.82 1.66
January 4.33 0.96 38.74 3.01
February 1.94 1.81 2.65 1.86
March 1.35 0.72 3.87 1.18 I
April 1.64 1.09 2.03 1.70
May 3.20 1.33 13.48 2.84
1984 July-Dec 2.48 0.59 38.1 1.42
1985 Jan-May 2.95 0.72 38.74 2.19
July 84-May 85 2.64 0.59 38.7 1.70
The closest USGS streamgage that was operational on ChichagofIsland in 1984 and 1985 was
located on Tonalite Creek near Tenakee. It was located on the south side of Tenakee Inlet across
from Tenakee, approximately 55 miles south of Elfin Cove. Comparison of this site to the
project site is shown in Table 3. This comparison shows that the two basins have different
aspects. The Crooked Creek basin is also much smaller, and has less forested area, two
characteristics that would tend to make the flows flashier.
Table 3: Comparison of Basin Characteristics for Crooked Creek and Tonalite Creek
Crooked Tonalite Site Characteristic Creek/Jim's
Lake Creek
Drainage Area, square miles 0.55 14.5
Lake Area, percent 1 0
Area of Forest, percent 72 88
Range of Basin Elevation, feet 350 -2048 50-3075
Mean Basin Elevation, feet 1100 950
Basin Aspect west north
The collected Crooked Creek/Jim's Creek streamflow data was converted to runoff (cfs per
square mile) and compared to Tonalite Creek. This is shown in Table 4.
HDR Alaska, Inc.
1
2525 C Sireet
sune 305
Anchorage, AK 99503 I
Phone {907} 644-2000
Fax (907) 644-2022
www.hdrinc.com
1 Page30f6
Table 4: Comparison of Runoff for Crooked Creek and Tonalite Creek
Location Drainage Period of Record Mean Runoff
Area Daily Flow (cfs/sq mil
(sq mi) (cfs)
Crooked Creek 0.55 July 6, 1984 -May 30, 1985. All data 2.4 4.4
Crooked Creek 0.55 July 6,1984 -May 30, 1985. Estimated 2.6 4.8
data not used.
Tonalite Creek near Tenakee 14.5 1968 to 1988 98.3 6.8
Tonalite Creek near Tenakee 14.5 July 6, 1984 -May 30, 1985. All data 105 7.3
Tonalite Creek near Tenakee 14.5 July 6, 1984 -May 30, 1985. Estimated 95 6.6
data not used.
Analysis of Table 4 shows that:
• For comparable periods of record the runoff per square mile for Crooked Creek was
approximately 70% of the nmofffrom Tonalite Creek.
• The mean daily flow in Tonalite Creek for the July 6, 1984 to May 30, 1985 period was
similar to the long term average at this station. It can be reasoned that the gage record at
Crooked Creek represents an average year.
A flow duration curve for Crooked Creek is shown below. This curve was prepared from 20
years of data from Tonalite Creek adjusted for drainage area and multiplied by 70% to account
for the variation in nmoff between the two sites observed between July 1984 and May 1985.
Flows above 5 cfs are truncated to improve the readability of the chart.
-t;
;;::
~ u...
HDR Alaska, Inc.
ODD ....,.,.,,===
5DO
4DO
3DD
2DO
1DO
o DO -F'-'==r
Crookedl.Jim·s creek
Flow Duration Curve
O~ 10"' 20"' 30-' 4Il";t 50-' 00"' 70"' 80"'-go", 100"'
% Exceedance
1
2525 C Street
Suite 305
Anchorage. AK 99503 I
Phone (907) 644-2000
Fax (907) 644-2022
lWIW.hdrinc.com
I Page 4 016
3. Review of Project Layout and Constructability
The genera11ayout of the AP A project appears to be practical although access considerations do
not appear to be addressed. A four wheeler trail would need to be constructed from town to the
powerhouse and to the intake and the diversion. A landing dock for powerhouse boat access
may also be required.
Depending on soils and slopes, an open channel between the diversion structure and Jim's Lake
may be feasible and would save the cost of pipe at this location. The diversion structure and
channel would be designed to limit flows and peak flows would be bypassed down Crooked
Creek.
The idea of using Jim's lake to provide storage to even out the flows from this small creek is a
good one. Verification of usable volumes was not done as part of this review.
The AP A report noted that the anadromous fish catalog did not include either of the project
streams. HDR verified this, but non-inclusion in the catalog does not mean there are no fish in
the streams. This would need to be field verified.
A site reconnaissance would be necessary to confirm the viability of the remainder of the project.
4. Review of Estimate of Cost
In 1984 the APA provided a sketch of the project and estimated costs for the project. The APA
project had the following components and assumptions:
• An 80 KW project was the most appropriate size for Elfin Cove, Project included power
generation, transmission line to town and distribution system in town
• 3 foot tatllog crib diversion structure
• CMP or open channel flume to Jim's Lake. Estimated length x 1.4 for contingency.
• Siphon from Jim's Lake
• 12" HDPE penstock on ground surface. Estimated length x 1.4 for contingency.
• Wood frame powerhouse
• Pelton turbine
• Power line lain along the ground from powerhouse to town. Estimated length x 1.4 for
contingency.
• Force account local labor with average rate, including fringe benefits of$20 per hour
• Work completed mostly with hand tools
• Access via trails, staging of materials with helicopter
• 25% contingency factor.
• Engineering not included. CM at $40,000, administration at $15,000.
• FERC permitting costs not included
• Agency permitting costs not included.
• The cost estimate was completed March 1984.
HDR has updated this estimate based on the following assumptions:
• The concept project will be as recommended by AP A.
• The original estimate and contingency factors by AP A are reasonable and accurate.
HDR Alaska, Inc.
1
2525 C Sireet
Sufte305
Anchorage, AI< 99503 1
Phone (907) 644-2000
Fax (907) 644-2022
www.hdrtnc.com
1 Page 5 015
• The project will pay force account wage rates. An average wage rate of $35 per hour
including base wage, fringe, WC, and overtime @ seven 10-hr days/week was provided
by AE&E as typical for rural projects.
• The project will be constructed in 2005.
• Inflation factor of 1.86 based on Engineering News Record construction cost index.
(March 1984=4118, December 2005=7647).
• Electrical distribution system costs will not be included.
• Estimate does not include the costs of design, permitting, contract administration,
construction fmancing, project financing, and construction management.
With the above assumptions the estimated direct construction cost for the project is $600,000.
Summary and Conclusions
This project appears to be laid out in a practical manner. Almost one year of streamflow
information has been collected during a year that appears to represent average flow conditions
for this area. The data shows that this creek has a low but consistent streamflow. Future studies
should include:
1. A reconnaissance investigation to determine project layout, access routes, verify
elevations of project facilities and determine lake depth and volume.
2. An investigation to determination whether fish are present in Crooked Creek or the Creek
that drains Jim's Lake. This may affect project feasibility and layout.
3. A feasibility study to select the optimum size of project component, determine the
potential available power and estimate project cost and economic feasibility.
HDR Alaska, Inc.
1
2525 C Sireel
SuJIB305
Anchorage, AK 99503 I
Phone (907) 644-2000
Fax (907) 644-2022
www.hdrinc.com
I Page6of6
APPENDIX F
MEETING SUMMARY LETTERS
,AlalkIIlndultrlal DewIopment and Export AutharIty
May 4, 2005
Mary Jo Lord-Wild,CECNPC Vice-Chair
Community of Elfin Cove Nonprofit Corporation
P.O. Box 1
8flnCOve, AK 99825
A1 .. kII Energy Authortty
'Subject: 4114105 site visit, observations and recommendations
Dear Ms. Lord-Wild:
, ,
,I have attached for your review a trip report and preliminary recommendations for the proposed
energy intrastructure project in Eltin Cove. In order to keep the design ot this project on
schedule, please provide comments tromresidents and interested parties on this 'report to me
by August 1, 2005. -'
I encourage you to also review the Denali Commission's poliCies and guidelines for energy
projects. These are available on-line at wWw.denali.gov, or I can send them to you on request.
, "
Sincerely. ' " '
D~·~
David Lockard, P.E.
Attachment: as stated,
Co Steve Stassel, Alaska Energy and Engineering
813 WEST NORTHERN LIGHTS BOULEVARD· ANCHORAGE, ALASKA 99503
907/269-3000 • FAX 907/269-3044 • www.aldea.org
TOLL FREE (ALASKA ONLY) 888/300-8534
Alaska Energy ~nd Engineering
Re: Elfin Cove Energy Infrastructure Projects
4114/05 Trip Report & Preliminary Recommendations·
On Wednesday April 13, 2005, David Lockard of the Alaska Energy Authority IRLIral
. Energy Group (AEAlREG) and John Dickerson of Alaska Energy and Engineering
. (AE&E) traveled to Elfin Cove. The purpose of our site visit was to meet with local
residents to identify and discuss potential energy infrastructure projects within the
community as well as to gather reconnaissance . level information for preparation of a
Conceptual Design Report (CDR) for any identified projects.
We anived in Elfin Cove by float: plane around noon. We proceeded directly to the·
community building where we met with power plant· operator Jim' Lewis and tank fann
. operator Jim Wild. After a tour of the power plant and fuel facilities a town meeting was
'held at 4:45 p.m., which was attended by ten local residents, including Community of
Elfin Cove Nonprofit Corporation (CECNPC) Vice Chairperson Mary Jo Lord-Wild.
The following summary report is based on preliminary Information gathered during this
site visit. Ilincludes information and preliminary recommendations on:
1) Status of existing community power plant
2) Description of proposed power plant and distribution upgrades
. ,
3)· Status of existing community fuel storage facilities
4) Alternative energy
This report along with comments from project participants will be the basis for the CDR.
1) Status of Existing Community Power Plant:
The' existing power plant building is located on Lot 13A, U.S. Survey No. 2946, which is
owned by the CECNPC.The community building (ex-school building) is also located on
this lot, approximately fourteen feet from the power plant. The comer of the power
plant building appears to be very nearty on or possibly over the property line shared
with the adjacent boardwalk easement and is also less than ten feet from the Eagle
, Charters Lodge building directly across the boardwalk. The lntemationalBuilding Code
(leC) requires minimum fire separation distances between buildings· and public
easements depending on use, occupancy and building construction. A preliminary
analysis indicates that the power plant does not meet required fire separation distances
and will need to be· relocated. Further investigation into this issue is required and a
conclusion will be included in the Concept Design Report.
There are three generators in the existing power plant, two of which are rated at 6Ok.W
. and the third at 205kW. All of the generators are near the end of their useful lives.
According to 1995 through 2003 peE data the average· annual load has ranged
between 3B.OkW and 45.4kW .. Copies of daily power plant logs for the past three years
were obtained during the site visit. The logs include a current demand reading taken
approximately between 6 AM and 11 AM as well as a last 24· hour peak demand
reading. An analysis of this data will be included in the CDR along with the proposed
new generator capacities. .
Elfin Cove Energy Infrastructure Projects . Preliminary Recommendations
2) Description of Proposed New Power Plant and Distribution Upgrades:
It is our recommendation that the existing power plant be abandoned and replaced with·
a new power plant module with generators sized to match existing community loads
and to be located on community council property with adequate area to meet required
setbacks anclfire separation distances. One possible location for the power plant is the
area just to the north of the tank farm near the fuel dock. This site has barge access for
. ease of placement and keeps the power plant out of the center of the community. . . . . .
The proposed. power plant will include two peak rated generators and one smaller
. nighttimeJwinter load rated generator, programmable automatic paral.leling switchgear,
remote radiators with variable speed control, a fire suppression system, critical grade
exhaust silencers, .an automatic fill day tank, a used 011 blender, a heat exchanger for
generation heat· recovery, and all required engine coolant piping and ventilation
equipment. It will come pre-assembled in a 14'-8"W X 38'-8"L modular skid-mounted
building. Proposed power distribution upgrades include a new step-up transformer
bank as well as additional meter bases and other upgrades on the dock to address
current low voltage problems.
3) Status of Existing Community Fuel Storage Facilities:
The existing tank fa"" was constructed new in 2000, is in excellent condition and,
except for a few minor issues observed during this site visit, appears to be a code
compliant facility. The CDR will include a complete code analysis of the fuel facility as
well as a list of suggested upgrades and improvements.
4} Alternative Energy:
The community building is currently served by generation heat recovery from the
adjacent power plant. The new power plant location will be approximately 250' from the
community building. This may make the heat recovery system installation marginally
cost effective due to. the added distance and the lower generation heat recovery
expected. A more rigorous analysis will be included in the CDR based on actual
generator selections and power plant location. A final detennination of feasibility will be .
. made atthat time.
. " : . . .
All available data regarding the potential Jim's Lake/Crooked Creek hydroelectric
project, including infonnation gathered on our April 14, 2005 site visit, has been
forwarded to hydroelectric generation specialist Bob Butera, P.E. of HDR, Inc •. for
review. An analysiS of his findings and a preliminary cost estimate will be included in
the CDR. No other potential alternative energy projects have been identified for Elfin
Cove. .
Please review the. issues presented and can David Lockard at 269-4541 to discuss or
fax your comments to 269-3044. In order to keep the CDR on schedule we need to
receive all community comments no later than August 1, 2004. I look forward to
working.with you on this project. . .
Sincerely.
. A1 •• ka En~rtng.lnc. ~Cke~on .
. Alaska Energy & Engineering
Project Engineer .
PaRe 2 of2
December 14, 2005
Sent by email to:
(7 Pages Total)
Alaska Energy and Engineering, Inc.
P.O. Box 111405
Anchorage, AK 99511-1405
Phone (907) 336-8031 Fax 336-7527
David Lockard, AEA Project Manager
dlockard@aidea.org
Re: Elfin Cove Energy Infrastructure Projects
Power Plant Site Investigation
Dear Mr. Lockard, .
The majority of community responses to the Elfin Cove Energy Infrastructure Projects
. Preliminary Recommendations report issued in early May, 2005 indicate a desire to
keep the power plant in its eXisting location rather than relocate it to a site near the tank
farm as suggested in the report. Our initial concept was based on preliminary
information that would have precluded the existing power plant from a potential
renovation project due to inadequate property setbacks. Further investigation and
discussions with the State Fire Marshall's office indicate that the existing power plant
building can be modified to meet International Building Code (IBC) fire separation
requirements. See attached Sheets M1 through M5 for additional information.
1) Power Plant Site Fire Separation Distances:
The IBC requires minimum separations from buildings to a property line or the
centerline of a public easement (fire separation distance) depending on occupancy,
type of building construction and fire resistance rating of exterior walls. The power plant
falls within mc occupancy group F-1 (Factory Industrial, Moderate Hazard), which
includes electric light plants and power houses. The adjacent community building is
currently used for public meetings, which falls under occupancy group A-3 (Community
Halls). The adjacent Lodge falls under occupancy group R-1 (Boarding Houses &
Hotels). For the purposes of this study it is assumed that all three buildings are non-fire
rated construction throughout with no automatic sprinkler systems, which classifies
them as Type V-B construction per the IBC. The following table summarizes the IBC
fire-resistance rating and fire separation distance requirements for the previously
mentioned occupancy groups of construction Type V-B only:
FIRE-RESISTENCE RATING REQUIREMENTS (TYPE V-B CONSTRUCTION ONLY)
OCCUPANCY OCCUPANCY OCCUPANCY
FIRE SEPARATION DISTANCE GROUP F-1 GROUPA-3 GROUP R-1
(POWER PLANT) (COMMUNITY (LODGE)
BUILDING)
less than 5' 2hr 2hr 2hr
greater than or equal to 5' 1 hr 1hr 1 hr and less than 10'
greater than or equal to 10'
and less than 30' Ohr Ohr Ohr
The existing power plant entry/storage room encroaches into the public easement and
is less than 5'-0" from the easement centerline. The IBC would require the walls and
door in this area to be 2hr rated assemblies, which would be impractical to meet.
Therefore it is proposed to remove the existing entry/storage room and relocate it so
that it does not encroach into the public easement and is at least 5'-0" from the
easement centerline, which would require only a 1 hr rated door and wall assembly.
Elfin Cove Energy Infrastructure Projects Power Plant Site Investigation
The proposed fire separation boundary as shown on Sheet M2 would be less than 10'
from the walls of the existing lodge and community buildings. According to the State
Fire Marshall's Office, this would not immediately impact these buildings. However, any
future major renovations to the affected portions of these buildings would require a plan
review and could require eXisting structural assemblies to. be improved to a .1 hr or 2hr
rating at the time of the future renovation.
2) Heat Recovery:
The community building is currently heated with generation heat recovery from the
power plant. The relocation of the power plant to the tank farm property would have
reduced .the efficiency of the heat recovery system and would have increased the
project costs. The power plant renovation will include new generation heat recovery
equipment if it proves economically justifiable.
3) Power Plant Noise Level:
The noise level from the current power plant is acceptable to the community, largely
due to the extensive use of pre-formed concrete walls in the existing building. The
proposed renovations to the existing power plant should maintain or reduce the noise
level. Improvements will include additional drywall in the exterior wall of the entry room
and an upgrade to hospital grade silencers on all three engines. All new ventilation
openings will utilize sound linings within interior and exterior ducts and will be located to
minimize noise transmission. It is difficult to predict the community noise level impact of
a new modular power plant located at a site near the tank farm due to the unknown
sound characteristics of a new location and the foam sandwich panel construction of
the module.
4) Emissions:
The soot level from the new generators will be better than the existing generators due
to advances in engine technology. New automatic paralleling switchgear will allow for
better matching of online generation to community demand, which will also improve
emissions. With continuous preheat, offline generators can be brought online by the
new switchgear in less than thirty seconds. This will eliminate the sudden demand
problems experienced with the prior generation automatic paralleling switchgear.
These improvements will be the same regardless of the power plant site selected.
5) Project Costs:
The estimated installed cost of a new modular power plant in El'fin Cove is
approximately $1,200,000, including a 20% contingency. It is estimated that renovation
of the existing power plant will reduce the cost of the project by at least $200,000.
6) Conclusion:
A renovation design for the existing power plant appears to be technically feasible.
Prior to developing the CDR for a renovation project we need confirmation from the
community that this is the preferred option. It should be noted that the construction of
either option is contingent upon future construction funding availability. Renovating the
existing power plant rather than installing a new power plant module is likely to reduce
the total project cost and improve the chances of funding for and operation of the heat
recovery system. However, a disadvantage to using the existing building is that the
new switchgear would remain in the same room as the generators rather than in a
separate control room.
Sincerely,
Alaska Energy & Engineering
John Dickerson
Project Engineer
SEE SHEET M5 --"(\
FOR PROPOSED
MODULAR POWER
PLANT PLAN
1"=150'
PRO.IECT: ELFlN COVE
ENERGY INrRASTRUCTURE PROJECTS
COMt.4UNITY SITE PLAN
DESIlN!D BY:
FU: twlE
LFIN-"1
SCo\l£: 1"= 150'
SHEET Of
M1 5
, ,
'\ ,
/~
SEE SHEET M4 FOR PROPOSED
POWER PLANT RENOVATION PLAN
/,'/\ ,'/ \'\
/
I
/
/
I
I
. DeparIQMont ." Com="'" ~Ic DeYeIopmont * ~. ,,·AIOEA/AEA * Rural Eii.iV Gtoup ALASKA .'3 w.t NcwtIwn lJght8 ... /E,ENERGY A.U'THORITY * -.-......
I
I
~==========~r-PO-RTI~~~--~
OF : ,,~ APPROX. LOCATION OF
EXISTING I ~ ./ EXISTING PROPERTY
ENTRY/ "~LlNES, TYP
STORAGE "
AREA : ~ LODGE
R-1 OCCUPANCY
WOOD FRAME ENCROACHING I
INTO PRE-CAST,
PUBLIC CONCRETE,
EASEMENT :
& WITHIN
5' OF
CENTERLINE / WOOD FRAME
CHASE AROUND
EXHAUST RISERS
TO BE REMOVED i g;S:~~~~C
POWER PlANT
F-1 OCCUPANCY
PROJECT: ElfiN COVE tRAWN BY:
ENERGY INF'RASTRUCTURE PROJECTS DESIGNED BY:
flll: NIK
LFIN-M2
POWE~ PLANT
EXISTING SITE/DEtotOUTION PLAN
PRE-CAST
CONCRETE
"--RADIATOR
SHED TO BE
REMOVED
COMMUNITY BUILDING
A-3 OCCUPANCY
WOOD FRAME
CONSTRUCTION
stILE: ,"= , o·
Ml!:
SHEET Of
M2 5
1"=10'
: / EXISTING PROPERTY ----1 LINE, TYP
-r I ~"
I I ~
LODGE
R-1
OCCUPANCY
WOOD FRAME
i --~ ~
PROJECT;
f-
Z w
:::i: w
~
u
::::JI
CD
~
0...
u... o
w z
~I
~ z w u
ELFIN COVE
ENERGY INFRASTRUCTURE PROJECTS
POWER PLANT
PROPOSED FIRE SEPARATION PLAN
1HR
CONSTRUCTION
REQUIRED,
INTERIOR WALL
PROTECTION ONLY
COMMUNITY BUILDING
A-3 OCCUPANCY
WOOD FRAME
CONSTRUCTION
DRAII'I II't: 5C.Il£:1"= 10'
D~B'f: DlI!:
ALENN.E SHEET OF
LFIN-t.l3 M3 5
o TO 5' FROM
POWER PLANT
I; IMAGINARY
I PROPERlY LINE,
lYP
1"=10'
~---------16'--~----~~
AUTOMATIC FILL 100 f GALLON DAY TANK
........... , .................. ,., ...... , ....... "_ ..... , .... -----------r-
FIRE
SUPPRESSION
CONTROL
PANEL~
D
Il
GENERATOR #3, 64kW
G ~ I"
#1
HOSPITAL GRADE-./
'.
:. .1--/
SILENCER, TYP(3) EF -1 ~ ~ x
GENERATOR #2, 110kW I ;:_ ~
G ~
I >--/
GENERATOR #1, 190kW
I
:
RELOCATED ~,~ -.... ------FIRE SUPPRESSION ; ~ R-2
....l...--_ L.::::::::~=~6=~=1=GE==~·:~ AGENT .R .. A ... C.K .............. 1..,,-.. i'.:,.=.} .. ,:,: r-m fD ~ 6-6" -:iMA;I~7 ~. ~~~~~ ~ nllJ
PARALLELING PANEL &
SWITCHGEAR TRANSFORMER
PROJECT: ELFIN COVE DRAWN Br: BeG SCIU: 3/16'=1'
ENERGY INFRASTRUCTURE PROJECTS DESlIJIIlI BY: BCG DAm
SII£ET OF
POWER PLANT RENOVATION PLAN ELFIN-t.l4 M4 5
to
I
10
N
co
I
1-1 .. ------15' -8" -------11
{J-----(CONTROL ROOM J
D~DAY
TANK
o
GENERATOR #1, 190kW
[
o
o
AUTOMATIC
PARALLELING
SWITCHGEAR
FIRE
SUPPRESSION
CONTROL PANEL
FIRE
SUPPRESSION
AGENT RACK
PANEL SS-1
D4=====lWITH STATION
SERVICE
TRANSFORMER
BELOW
o
o
RADIATOR VFD
CONTROL
PANELS
RADIATOR,
1YP(2)
"x/ 1-.. ---VENTILATION
~/_"....::.I..-J~ HOOD, 1YP(4)
SCU: 3/16"=1' PRC>J£CT: ELFI N COVE DRAWN BY: 8eG f-;;;-;:_EN_E_RG_Y_I_NF'_RA_S_TR_U_CT_U_RE_P_R_OJ_E_CT_S_----r.;I]fl;«HJ)~.;::;BY::..::;8CG::::....--+-;;IJIIire;;".,...--~ • l if· ~AiT> .~-
1I11E: ru: !WE SHEET OF * Rural £no Group III ALASKA
GENERATOR t.tODULE PLAN ELF'IN-M5 M5 5 * .'~""".;..~...... ENERGY AlJTHOfl'TY
From: "Gordy Wrobel" <gordywrobel@covelodge.com>
To: "john dickerson" <jdickerson@acsalaska.net>; "david lockard"<dlockard@aidea.org>
Sent: Saturday, December 24,20057:14 AM
Subject: Elfin Cove Powerhouse Site Selection
David Lockard and John Dickerson,
We have solicited input from our community concerning the generator plant site proposal you
developed. We gathered input via person-to-person conversati on, telephone and emai I. The
process used to reach the recom mendation below was inclusive of more community members
than typically participate in our formal meetings. The Board believes that a clear position
on the matter has been reached and that this pos ition reflects the opinions and wishes of a
large majority of the community members.
Of those partic ipating in this process a clear majority indicated that we shoul d make
improvements to the existing site. There were 3 major concerns regarding this site and it is
hoped that the final design can specifically address each of these poi nts. Given that the
estimate for the current site is $200,000 below the alternative site, it is hoped that some of these
savings may be used to address each of the following:
1. Fire. Both sites raised this concern. The community would like the planning process to
explore redund ant systems or other means of fire prevention, containm ent and abatement.
2. Noise. Given that the current location is in the heart of the community and with proximity to
other buildings and the boardwalk we request the design to include effective noise dampening
strategies beyond just mufflers and resonators.
3. Emissions. Given the location and proxim ity to other buildings there should be speci al
attention given to emmisions for obvious reasons. We assume new engines wi II reduce the
current problem but we would like to explore additional measures to further reduce emissions.
On behalf of the Com munity of Elfin Cove, and its Board of Directors I want to thank both of you
for supporting us in this effort. T his component of our energy plan is vital to our community at
this time. We would like to assist you in any way we can so that the work can be com pleted as
soon as possible. We remain committed to developing alternative renewabl e energy resources.
Any assistance you might provide with our alternative energy efforts wi II be greatly appreciated.
Sincerely.
Gordy Wrobel, Chair
Community of Elfin Cove
Non-Profit Corporation
December 30,2005
Sent by email to:
(1 Page Total)
Alaska Energy and Engineering, Inc.
P.O. Box 111405
Anchorage, AK 99511-1405
Phone (907) 336-8031 Fax 336-7527
David Lockard, AEA Project Manager
dlockard@aidea.org
Re: Elfin Cove Energy Infrastructure Projects
Power Plant Design Concerns
Dear Mr. Lockard,
Based on the December 24, 2005 e-mail from Elfin Cove Community Association
Chairman Gordy Wrobel titled "Elfin Coye Powerhouse Site Selection", we will now
proceed with a conceptual design for renovation of the existing power plant building as
part of the Energy Infrastructure Upgrade Projects CDR. In the conceptual design we
will address the three major community concerns as follows:
1) Fire:
The renovated power plant will contain an automatic fire alarm and water mist fire
suppression system. This will be an improvement over the eXisting facility since there is
currently no fire suppression.
2) Noise:
The eXisting critical grade silencers will be replaced with interior mounted hospital grade
silencers. The hospital grade silencers provide maximum noise reduction at the
exhaust outlet. Placing all of the silencer shrouds inside the concrete building structure
will maximize resonant sound absorption. All three exterior exhaust stacks will be
routed up to a height of approximately 20' above grade. Sound attenuation will be
provided at all building penetrations and combustion/ventilation air openings, with all
openings located to minimize the noise impact on nearby buildings.
The proposed small (64kW) winter load genset will be the prime genset for
approximately eight months out of the year. This unit will be powered by a marine
jacketed (water cooled exhaust manifold) engine to provide for additional generation
heat recovery. The marine jacket will also significantly reduce the noise level of this
genset.
3) Emissions:
The existing generators are not EPA certified for low emissions. The proposed new
generators will be at least EPA Tier I certified and the new marine jacketed (64kW)
generator will be EPA Tier" certified. These certifications are not required for small
power plant installations like Elfin Cove but will guarantee that the new gensets meet
Federal emissions standards. Due to advances in engine technology these new EPA
certified gensets will be more efficient and will produce lower emissions than the
existing units. Raising the exhaust stacks and necking down the stack at the tip to
increase velocity will also allow for better dispersion of the exhaust plume and decrease
the impact of emissions near the power plant. These improvements, in addition to the
new automatic paralleling switchgear and improved power plant ventilation, will all have
a positive effect of reducing emissions. Proper maintenance of the generators will be
necessary to ensure long term clean operation of the engines.
Sincerely,
Alaska Energy & Engineering
John Dickerson
Project Engineer