University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
Section 1
Objectives and Methodology
1.1 Background
Alaska has over 300 rural villages that are located near a river. The Electric Power Research
Institute (EPRI) has performed conceptual feasibility studies for sites which showed that the
economics for River In-Stream Energy Conversion are quite promising, potentially reducing the
cost of electricity by 50-70%. The economics of a hydrokinetic energy plant are a direct
function of river velocities and associated power densities at the river sites near these villages.
Velocity data for most of these sites is non-existent.
Hydrokinetic technology manufacturers and energy project developers require information on the
water velocity and depth. This project provides critical information for determining the
feasibility of extracting hydrokinetic energy at 24 rural villages in Alaska. All results will be
available to the public and private entities such as consultants, in-stream tidal companies,
communities and the state of Alaska. Any organization interested in evaluating the potential of
in-stream renewable energy technologies will be able to select a system that is appropriate for the
water body in question. It will also enable a “market pull” by informing device developers of the
site conditions (i.e. water depth, velocity distribution and infrastructure availability) and
therefore allow them to optimize their device technology to meet a majority of the site conditions
in Alaska.
Providing the necessary preliminary information on a large number of sites suitable for
hydrokinetic power generation will demonstrate to the state and the manufacturers the hydro-
kinetic potential within Alaska. This may help the development of small scale hydrokinetic
plants for communities and organizations such as the University of Alaska School of
Engineering (UAA-SOE) Renewable Energy Test Station in Girdwood, Alaska. Similarly, this
study possesses the potential to assist the state in developing a comprehensive hydrokinetic
research, study and implementation plan ultimately improving the state’s ability to become more
self sufficient in the development of its own renewable energy resources.
Currently, this project has acquired data and begun to assess the potential hydrokinetic energy
resources for seventeen sites in rural Alaska (six on the Kuskokwim River and eleven on the
Yukon River). This is being conducted through the analysis of velocity, bathymetric and
topographic data. In addition, fifteen water level gauges were placed at selected locations to
remain for the duration of the open water season to help determine the range of water levels.
Existing gauging stations managed by the United States Geological Survey (USGS) in relative
close proximity to project sites were used to validate the collected data for discharge
2
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
measurements and water levels throughout the year. The collected data will provide the ability
to make estimates of the long term hydrologic (i.e. velocity/depth) conditions at the selected rural
sites. Long-term depth and velocity distribution data obtained will be used to determine the
hydrokinetic energy available for power generation, thus facilitating the development of low
cost, carbon neutral energy technologies, leading to a reduction of energy costs in the future.
1.2 Objectives
The amount of energy that is available for hydrokinetic power generation is a direct function of
river velocities and associated power densities therein. The dynamic nature of river
characteristics vary with water levels, which makes it necessary to predict these characteristics
for varying water levels throughout the year at each prospective site. This can theoretically be
achieved through the use of the Manning’s Equation, which states that velocity is a function of
the river slope, hydraulic radius, and the manning’s roughness coefficient. The velocity,
hydraulic radius and slope of any river can be determined within an acceptable degree of
accuracy by using Acoustic Doppler Current Profilers (ADCP) in conjunction with Global
Positioning Systems (GPS), leaving the roughness coefficient as the only unknown variable. By
making the general assumption that the roughness coefficient will remain constant throughout
the yearly river cycle, predictions pertaining to discharge at various river stages can be made.
The goals of this project are to (1) use average velocity, topographic, and bathymetric data
obtained at each site to determine the Manning’s roughness coefficient, (2) use data from
deployed water level monitors and information from USGS gauging stations to determine a
typical range of river stages, (3) correlate yearly discharge predictions with velocity
distributions, (4) determine the locations of highest energy density, and (5) to evaluate the
economic feasibility of hydrokinetic power generation at each site.
1.3 Methodology
1.3.1 Logistics
Ambitious research such as this hydrokinetic feasibility study requires a great deal of effort and
coordination during the planning phase, due to the remote nature of the project. It was necessary
to initially meet with rural proponents of renewable energy development to decide which sites to
be study. Dr. Nyree McDonald, formerly an Assistant Professor for the UAA-SOE, attended the
Galena Renewable Energy Conference on April 2nd through the 4th of 2009 to establish local
relationships to facilitate potential research. At this conference, flyers were circulated informing
3
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
representatives for each attending community of the intent of the research. Additionally, surveys
were distributed not only for those in attendance but for other local conferences in an effort to
characterize the interest and public opinion of a hydrokinetic project. This survey covered such
topics as the local energy cost, level of interest, and possible concerns of the community. These
surveys coupled with the Galena conference and the rural connections that were forged gave the
research a point of origin. A list of prospective research sites was compiled and evaluated, based
on but not limited to: the site’s proximity to a power grid, anticipated river depth and velocity,
the local need for alternative energy, and general community interest.
Originally, the research was to be limited to 8 sites for the first years’ research. However, it
quickly became evident that it would be more efficient and cost effective to pick sites that had a
higher number of surrounding communities that were sequentially located along a river that was
easily accessible by boat. Initially Erin Eggleston, a Research Technician for the UAA-SOE, had
correspondence with Jody Malus of the Bethel Alternative Energy Council to begin making
arrangements for studies on the Kuskokwim River. Another key contributor to the logistical
process for the Kuskokwim project was David Griso, the Executive Director of the Kuskokwim
Watershed Council. He was instrumental in the selection process for locations of potential
research, offering his recommendations as well as providing the necessary contacts for
communication in the various villages.
The inflated expense of travel to rural Alaska deemed it necessary to make as few roundtrips to
and from Anchorage as possible. The result was an effort to orchestrate arrangements to visit 6
sites from Bethel to Napaimute over a span of 14 days, 7 sites from Galena to Holy Cross in 16
days, and 4 sites from Marshall to Mountain Village in 8 days. Not only was this the most
economical solution for personnel transport, but also for the 1000 plus pounds of equipment that
the project required. Because of the relative inaccessibility of many of the sites, the teams’ main
cargo handler, Northern Air Cargo (NAC), could only deliver to certain sites on certain days of
the week. This played a vital role in determining the order of site visits, as it was necessary for
the equipment to be awaiting the arrival of the research team. Other options for equipment
transport were considered and utilized as well. Knowing that the research team was going to visit
Marshall, AK after a short return to Anchorage, Teddy Heckman, the vessel operator for the
Lower Yukon research, was contracted to transport equipment from Holy Cross to Marshall.
This proved a very efficient and economical decision as opposed to shipping the gear back to
Anchorage, as NAC does not directly operate through Marshall.
Once the project sites were determined, it was necessary to begin arranging for accommodations,
travel arrangements, and vessels with skilled operators to perform survey work and provide
transportation. The key requirements for accommodations at each site included relative close
proximity to the project site (the river) and electricity for charging the numerous batteries that
powered the instruments. The high value associated with the equipment being used necessitated
proper storage on a nightly basis. Hand carrying large volumes of equipment to and from
lodgings each day was a last resort option, as it was time consuming and generally inefficient.
4
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
For this reason, it was necessary to also secure ground transportation within each village, where
possible.
In addition to accommodations, travel between the project sites was considered. Due to the high
volume and weight of the equipment necessary to perform the research, flying between sites had
to be minimized, for cost considerations. This meant ensuring that travel by boat was obtainable
to shuttle equipment from village to village, in the required time frame. Ideally, the aim was to
utilize a minimum number of vessel operators, thus using one boat and captain for as many
consecutive project sites as possible. Not only does this ensure that the research team has reliable
transportation available, but it reduces the necessary training time involved in acquainting each
operator with the navigational system and the overall process of collecting bathymetric data.
Ultimately, it was necessary to use air transportation for personnel and equipment between
Kaltag and Grayling, because the distance between the two villages made boat travel impractical
and uneconomical.
When planning for remote projects, communication with supervisors and communities is
essential. With the general lack of infrastructure at a majority of these sites, the only option for
communication is most often a satellite phone. Cellular phone service is still only available in
select locations, and in the case of an emergency, there is an urgent need for a reliable means of
communication. As a general rule for field work, issues with software or hardware are bound to
propagate themselves. Contact with manufacturers and supervisors must be maintained to avoid
costly project delays.
As is the case for any project, unforeseen last minute changes occur where lodging or
transportation arrangements fall through. If this is the case, coordinators must make quick
decisions as to not leave the research team marooned, as field time is a relatively expensive
expenditure. At the end of the day, all of the aforementioned considerations must be
methodically arranged so that the intended work is performed in the most efficient manner
possible.
1.3.2 Equipment
High precision equipment is necessary to accurately measure and position river velocity,
bathymetry, and topographic data. River velocities and bathymetry were measured using an
ADCP. Navigation and positioning was conducted using Real Time Kinematic GPS, as was the
upland topography of the river banks. The integration of these systems requires researchers to
become well acquainted with equipment configuration settings, as well as various data
interchange formats. Equipment trials were conducted prior to field work to ensure equipment
compatibility and operator experience.
5
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
1.3.2.1 Acoustic Doppler Current Profiler
Previous to this study, the UAA-SOE either owned or had access to a single-beam sonar,
Acoustic Doppler Velocimeters, and an ADCP that was allocated for measuring the velocities at
a hydrokinetic site in Ruby, AK for the duration of the summer. It was deemed necessary to
acquire a unit that had all the capabilities of collecting the desired bathymetry and velocity data
in one package. Turning attention to the instruments used by the USGS and from
recommendations from experts in the field, alternatives were considered.
There are several ADCP’s available on the market that all promise accurate readings when used
according to their respective design specifications. There are subtle differences in each
manufacturer’s design that may suit the varied needs of the research to be conducted. For this
particular hydrokinetic assessment, two ADCP models offered by two separate manufacturers
were considered: the SonTek M9 RiverSurveyor and the Teledyne RDI Rio Grande Workhorse.
The SonTek M9 River Surveyor features nine transducers, with a dual 4-beam 3.0MHz/ 1.0MHz
Janus arrangement. The remaining transducer is a .5MHz vertical beam. This instrument claims
to have a velocity profiling range from 0.06m to 30m, with a resolution of 0.001m/s. In addition,
it has a depth measurement range of 0.20m to 80m, with a resolution of 0.001m. It has an
internal memory capacity of 8GB and is available with an optional SonTek RTK GPS package,
thus eliminating the need for more costly equipment, when the use of GPS is necessary.
Teledyne’s 600kHz Workhorse Rio Grande ADCP has a single 4-beam Janus transducer array
that is capable of measuring velocity profiles between .7m to 75m with a comparable resolution
of 0.001m/s. It is capable of making depth measurements up to 100m for typical river water
conditions. However, the Rio Grande has only 2GB of internal memory and does not come with
the RTK GPS option.
The final decision on which ADCP to choose was not
determined by the available options that each instrument
offered, but rather the instrument’s availability. SonTek
could not deliver the instrument within a two month
timeframe, whereas Teledyne RDI could have the instrument
assembled and shipped in a matter of weeks.
Due to the anticipation of high sediment conditions in the
Alaskan rivers, the 600 kHz ADCP was preferred over the
1200 kHz model that Teledyne RDI offers. This is due to the
fact that the lower frequency ADCP’s have a greater
capacity to penetrate water with a high concentration of suspended particulates. There are,
however, a number of drawbacks to the lower frequency model. Although the lower frequency
ADCP will measure deeper than the high frequency models, they require larger depth cells and
Figure 1: Teledyne RDI Rio Grande ADCP
(Teledyne, 2009).
6
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
have a larger blanking distance. This may become inconvenient in waters that are relatively
shallow (less than 1m).
The Rio Grande features a user specified input which allows for the modification of critical
settings for data acquisition when default settings result in unsatisfactory results. This input, the
WS mode, modifies the bin size that the ADCP will collect while the instrument is pinging.
River conditions in which the water is relatively deep will require a much larger bin size than
shallow water. As a consequence, choosing the proper WS mode is very site specific. Rivers with
long sweeping banks followed by deep channels are especially challenging. In order for the
ADCP to collect discharge measurements in the shallow banks, the bin size must be relatively
small. Conversely, the deep channel requires a greater bin size. Since the Teledyne Rio Grande
does not have the capacity to automatically adjust the bin size during a transect, often several test
transects must be completed in order to determine the appropriate WS mode. If the bin size is too
small, discharge measurements will not be recorded in the deeper portion of the channel.
Ultimately, it is the responsibility of the researcher to ensure that the data collected is of the
quality that is required.
1.3.2.2 Global Positioning System
Relative positioning of the hydrography and upland topography were critical in accurately
defining the river cross-sections and georeferencing the velocity data. Originally several pieces
of survey equipment were considered for positioning and navigation. A survey level was ruled
out because although it can be quite accurate for vertical control, it does not collect horizontal
data nor provide positioning for the hydrographic work. A total station was also considered for
the project, but for the volume of work to be completed in a small window of time, it was
deemed inadequate. In addition, neither of these instruments allows their direct integration into
the ADCP.
All positioning data for this assessment was completed using Trimble
5700, 5800 and R8 models, utilizing Real Time Kinematic (RTK) GPS
mode. The 5700 and the 5800 receivers as well as the necessary ancillary
equipment was provided by the Geomatics Department of the UAA-SOE,
while the R8 model was purchased in part for this project. For the
required precision needed for this project, standalone GPS was not an
option, as this mode only provides for accuracies typical of handheld
GPS receivers. RTK systems use a single base station receiver and a
number of mobile roving receivers. The base station re-broadcasts the
phase of the carrier that it measures, and the mobile units compare their
own phase measurements with the ones received from the base station.
Figure 2: Trimble 5700 GPS
Receiver (Trimble, 2009).
7
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
This differential in carrier phase allows for accuracies on the order of a few centimeters both
horizontally and vertically.
In addition to their precision capabilities, integration of RTK GPS was
desired for ADCP operations. By streaming the National Marine
Electronics Association’s (NMEA) 0183 string into the ADCP software,
it was possible to geo-reference all the collected bathymetric and
hydrographic data to the upland topography. This was imperative for
interpreting data at a later time.
Although integrating the GPS receivers with the ADCP is not always
necessary, certain flow conditions make it preferable. When not using
GPS as navigational reference, the ADCP computes observed velocities
using “Bottom Tracking” (BT). As a consequence of the instrument
vessel moving as the ADCP records measurements, the software must
subtract the speed of the boat to obtain accurate velocity measurements. Under some conditions
BT is an acceptable method for this process. However, if the river bed is dynamic (moving bed),
the vessel velocities observed by BT will be biased low, resulting in inaccurate water velocity
measurements. Due to the uncertainty of such conditions along the Yukon and Kuskokwim
Rivers, it was decided to err on the safe side and integrate GPS into the ADCP software, using
the GGA data as a reference to accurately compute flow velocities.
1.3.2.2 HYPACK- Navigation
A majority of the transects were pre-planned in Anchorage using geo-referenced tiff images.
This allowed the research team to target the areas where the highest flow velocities were
anticipated. These rivers can easily surpass one mile in width, requiring a navigational aid to stay
true-to-course. HYPACK was selected as the navigational tool and was integrated with the GPS
rover receiver to provide RTK quality navigation of the vessel.
Although HYPACK is typically used for port and harbor applications, it is a very versatile
program that works exceedingly well for its intended use for this project. As was the case with
most of the GPS equipment, the UAA-SOE has access to a version of this software, making it the
most economical option for navigation. Use of this software is instrumental in ensuring that the
vessel operator does not venture far from the pre-planned transects, as it provides a real time
location of the vessel and its proximity to the transect being studied. Not only does this
streamline the collection of bathymetric data, it also ensures that the data is as close to a linear
specimen as is intended.
Figure 3: Trimble R8 GPS
Receiver (Trimble, 2009).
8
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
1.3.2.3 HOBO Water Level Gauges
One of the key objectives for this study is to accurately predict flow behavior (i.e. velocity and
discharge) for various river stages throughout a rivers’ yearly cycle. Accurate water level data
must be available in order to make flow predictions. Unfortunately, the USGS has no gauging
stations located near the reaches that are being studied, with the exception of the gauge at Pilot
Station. To obtain the necessary water level information that is needed to create an accurate
model, the research team must place gauges at each site which are to remain for the duration of
the open water season.
A total of 15 HOBO gauges manufactured by Onset were set during the summer of 2009 with the
exception being Pilot Station and Upper Kalskag. Initially, each gauge was inserted through the
end of a 25-30 foot PVC stilling well that was assembled at the project site. The gauge was
tethered to a stationary object on the river bank using vinyl coated non-stretch steel wire.
Typically, a large angular rock was tied to the end of the stilling well meant to be submerged in
the river, so as to resist movement throughout the data collection period. The goal of the process
was to deploy the device in an area where it was unlikely to be disturbed, and in an area of
sufficient depth so as to record data for the entirety of the season.
Being that these rivers are dramatically dynamic, their water
level may drop as much as 20 or more feet from the spring
months to the beginning of ice formation. Reports from
various communities began streaming in that there was very
little water covering the stilling wells as early as late July
and the method above was deemed insufficient.
A revised method was designed to deploy these gauges
involving creating a “basket” using PVC as a frame. The
PVC was then wrapped with wire mesh and the basket was
filled with rocks. The water gauge was then attached to the outside of the basket and the entire
apparatus was tethered to shore using the same wire as mentioned above. This made deployment
much easier, as it enabled the team to drop it from the side of the boat some distance from shore,
ensuring sufficient depth for deployment. The basket design also significantly reduced the
amount of PVC being transported to the sites, and proved to be a much lighter, efficient system.
At each site, contacts were made for retrieval of these devices before ice formed, which would
make recovery unlikely using the described methods. Shipping materials including padded
shipping boxes and prepaid shipping labels were given to each volunteer who were then advised
on the methods for retrieval and told to await word from the research team for when to remove
the gauges. This process was overall the most cost efficient for the water level data that is
required.
Figure 4: HOBO Water Level Logger
manufactured by Onset Computer
Corporation (Onset, 2009).
9
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
1.3.2.4 Laptop
In order to integrate all three systems (GPS, HYPACK, ADCP), it was necessary to purchase a
computer that was adequately robust for field work as well as possessing a parallel port.
HYPACK requires that a hard-lock key be inserted into the parallel port of the computer being
used for the software to run. Unfortunately, most modern laptops no longer come equipped with
this feature. In addition to the parallel port, the field computer had to possess serial, VTG, and
USB ports. With the need of all of these features, it made it necessary to purchase a port
replicator to satisfy all of these requirements.
The VTG port was essential to enable the use of a
second monitor for vessel navigation. HYPACK was
displayed on the second monitor for the vessel operator
to navigate the preplanned transects, while the
researcher simultaneously monitored the status of the
ADCP. The serial port was required for the uplink to the
ADCP, to enable data acquisition. Finally, the 2 USB
ports were required to stream the GPS data into
HYPACK and WinRiver II simultaneously.
Due to the nature of the work, it was necessary to
purchase a Panasonic Toughbook, which is both impact
and water resistant. The process of shuffling equipment on a
daily basis as well as the fact that work was being performed
mostly in open hull vessels on open water necessitated these
features.
1.3.2.5 ADCP Mount
When deploying an ADCP there are several
options available. One method for data
collection is the bow-mounted approach. This
method puts the instrument at greater risk,
being as it will undoubtedly be the first thing to
hit bottom when traversing a transect. This
consideration along with the fact that the bow-
mount mount design would be relatively
complicated encouraged further alternatives.
Another possible method is the stern-mount
concept. This method was quickly
abandoned for two reasons: (1) The
Figure 5: Panasonic Toughbook (shown
without port replicator) (Panasonic, 2009).
Figure 6: UAA-SOE ADCP side mount fitted to research vessel (Yager, 2009).
10
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
cavitations created by the prop on the motor was likely to interfere with data collection and (2)
the battery for the vessel can potentially cause magnetic interference, thus fouling data. The
option that seemed to best suit the needs of the research team was the side-mount deployment.
11
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
Figure 7: Construction schematic of ADCP boat side mount (Harper, 2009).
12
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
After deciding on a concept, research revealed that the mount was required to be made entirely
from non-ferrous material, as to not create a local magnetic field that would interfere with the
instrument. The design was conceived by the research team and was fabricated free of charge by
the UAA Welding Department. The mount featured a telescoping cross beam that allowed for
adjustment to vessels of a broad range of widths. This was an essential feature, as the research
team was to use several different vessels throughout the course of the project. The ADCP was
mounted to the bottom of a vertical post that was joined to the cross beam via a “T” fitting, and
was allowed to slide freely for both easy deployment and removal. In addition, a Zephyr GPS
antenna was co-located on a length of all-thread fitted to the top of the post to reduce the need
for measuring horizontal offsets for post processing considerations. Finally, the entire apparatus
was fixed to the gunwales of the vessel via two large clamps and a tag line running from the top
of the vertical post to the stern, to resist rotation. This design proved to be very reliable and was
quite cost efficient.
1.3.3 Preplanning
Aside from coordinating lodging, transportation, etc., there was a great deal of time spent
analyzing aerial photography of the selected sites. Given the fact that very little, if any data
existed for these sites, decisions had to be made as to where the highest velocities were likely to
be observed. Ideally, it would be most beneficial to plan transects very close together in order to
capture a denser set of data. However, a process such as this would require a great deal of time,
and much more than the research
team would be able to spend at each
site. Following this realization it
was determined that the aim of the
work should be to cover a longer
reach of the river, thus producing
more generalized results.
One of the general criteria for
choosing a set of transects for each
site was that they had to be in
relatively close proximity to one
another. This was mainly due to the
fact that the GPS base station radio
has a limited range to which it can
broadcast GPS corrections, roughly
1.5 to 2 miles with limited Figure 8: Preplanned transects for Aniak, AK (UAA-SOE, 2009).
13
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
obstructions. Using the aerial maps, obvious locations for problematic transects were
immediately ruled out based on this criteria. Another criterion for choosing transects was that
they also had to be relatively close to the actual village, for transmission line considerations. At
many locations, islands and sand bars are clearly visible from the imagery and where possible,
placing transects that traversed straight through these obstructions was discouraged, mostly to
ensure that the team maintained a signal from the base station. This is not to say that these types
of transects weren’t decided on, because at several locations there was no other option. In order
to collect the densest set of data, often several river channels were surveyed. On occasion,
transects were placed based on the recommendations of the local townsmen, as they were more
familiar with the sites.
After relative locations for transects were decided, there was discussion as to how many could be
traversed in the time allotted for each site. Taking into consideration setup time and allowing for
unforeseen complications, it was determined that 7 to 10 transects could conceivably be
completed in a single work day, while yielding the desired quality. With the transects drawn onto
the geo-referenced tiff images, the coordinates could then be keyed into the HYPACK software
for navigation at each site.
There were occasions when the preplanned transects were either impossible to complete or
finished ahead of schedule. In the event that transects were finished early, it became the
responsibility of the research team to determine locations for additional transects. As was often
the case, new transects were placed between the preplanned lines to collect a more dense set of
data. Some reasons for the decision to abandon certain transects included water too shallow for
boat navigation, loss of base station radio contact, and inclement weather that made conditions
unsafe on the river.
Also considered during the preplanning phase were the potential locations for the water level
gauges. This was difficult to plan from Anchorage, as there was little data available for review
that would potentially aid this process. Ultimately, the placement of the HOBO’s was at the
discretion of the research team while in the field and the decision was made after evaluating each
project site.
During the preplanning phase the research team investigated the location of any and all NGS
(National Geodetic Survey) monuments that had been placed at the various sites. The hope was
to utilize these control points as a location for the base station, being that their location was well
documented and of control quality. Upon arriving at each site, it quickly became obvious that
most if not all of the NGS monuments would not aid the research team. Most of the control
points were located at great distance from the project site (the river), thus making it an
impractical location for a base station due to the range limitations of the base station radio. One
particular monument in Aniak that was potentially within range of the project site was located
beneath heavy tree cover, making it virtually unusable for GPS applications.
14
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
As part of the control search, researchers obtained magnetic declination adjustments for each site
that was to be visited. This was important for the ADCP measurements as the internal compass
of the instrument must be calibrated at each site. Additionally, at the start of each measurement
WinRiver II prompts the user for a local magnetic declination as to accurately interpret the vessel
course as well as the direction of river flow.
1.3.4 Equipment Trials
When integrating various survey systems, it is paramount to test all equipment before any field
work is commenced. This is even more important for research in rural Alaska, as replacement
parts generally will have to be flown out to the site, which is very costly and inefficient. With the
added uncertainty of communication with technical support, it is essential to become as familiar
as one can be with the various systems in order to significantly reduce the need for such
measures.
As preplanning operations were taking place, the survey team began testing all the various GPS
components from wires to receivers. Researchers spent several days on the phone with technical
support or in the school parking lot running tests and familiarizing themselves with the
equipment. This was instrumental in both troubleshooting procedures and equipment
malfunctions. Several times throughout the course of the research the survey team was required
to rely on knowledge obtained from these very trials, undoubtedly saving both time and money.
The next task for the research team involved integrating the GPS data with both the ADCP
software and the navigational software.
Using a base station located on the roof of the UAA Engineering Building, the team first tested
the navigational software. This was done by attaching a Trimble 5700 receiver and antenna to a
rolling cart serving as the “vessel”. The HYPACK software could then verify its position at a
certain point, which was then compared to the land survey team’s RTK rover. This allowed the
team to be certain that the navigational
software was accurate and could be used as
part of the project.
Being that none of the research team was
familiar with the Rio Grande ADCP, it was
decided that testing the device in the UAA
pool was possibly the best way to become
acquainted with both its hardware and
software. A mount was specifically
constructed for this test which would allow
a research member to pull the ADCP from
one end of the pool to the other. At the same
Figure 9: Research members prepare the ADCP for a trial run in the UAA pool
(Yager, 2009).
15
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
time another member wheeled a cart with the battery and computer for the ADCP alongside and
ensured that data was being collected and that all systems were running properly. This test was
very useful for the researchers performing the bathymetric survey, as it acquainted them with the
setup and user commands for the ADCP.
Finally, it was necessary to test all of the various components together as they would operate
during the field work. The team first considered conducting a full scale test on a local Anchorage
lake, but reconsidered due to the fact that no flow would be measured, nullifying one of the
objectives to the equipment trial. The Knik River was deemed an appropriate test location for the
scope of the research study, as it was the largest and most accessible river for the team. On June
5, 2009 the team set out with a 14 foot inflatable Zodiac and all the necessary equipment to
perform a trial survey on the Knik River. The land survey team set up two monuments, one on
either side of the Glenn Highway Bridge, and performed a static survey. At the same time, the
hydrographic survey team fitted the vessel with the ADCP mount and all the navigational
hardware, as well as the ancillary equipment needed to carry out the research. While the team
was awaiting the results of the static survey, one of the HOBO water gauges was placed to
ensure its proper functioning, as well as the function of the stilling well that it was housed in.
The bathymetric research members quickly realized that something was not operating correctly
with the ADCP. After exhausting all other troubleshooting methods, the manufacturer was
contacted. The information that was conveyed to the research team was that WinRiver II, the
Figure 10: Knik River equipment trial on June 5, 2009 (Mills, 2009).
16
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
ADCP software, has a default bin size setting for the depth at which measurements will be taken.
Since the Knik River is relatively shallow (4 to 5 feet), custom user commands had to be input
which would shrink the bin size down to a point where it would begin reading current velocities.
This piece of information proved useful throughout the summer, as many of the sites had long,
sweeping deposit banks that could not have been surveyed using the default setting. Overall, this
trial run proved to be an enormous step forward and was very valuable for the research that was
conducted throughout the summer.
1.3.5 Data Acquisition
Upon arriving at each site, the first consideration was always where to locate the GPS receivers
for the static survey so that not only did they have they have a clear view of the sky, but also a
clear view of a relatively large reach of the river. Additionally, it was favorable to locate the
receivers at a distance of several hundred meters apart, to achieve the longest baseline possible.
For monuments at each site, two 2 inch aluminum rebar caps similar to the one shown in Figure
11 were used. The
monuments were labeled
with the project name,
followed by the site and
monument number and
ending with the year.
This method of
monumentation was
used because it required
the minimum amount of
materials when
compared to digging
holes and filling them
with concrete as is
needed for brass
monuments. With the
rebar driven and the caps
placed, the GPS
receivers were set up over the
monuments and the static
survey began.
Figure 11: 2 inch aluminum cap set flush to ground on rebar at Chuathbaluk, AK
(Harper, 2009).
17
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
With the receivers mounted on their respective tripods, they were then leveled and the antenna
heights were measured and recorded. For each control point, a static survey log sheet was filled
out documenting the time, monument name, and approximate location, as well as several other
required fields of information. With the receivers acquiring their position fix p from the satellites
over head, they were left to collect data for a minimum of two hours, although typically they
were allowed roughly four hours to observe.
While the GPS receivers were conducting the static survey, typically the team then evaluated the
most appropriate location for placement of the water level gauge. The gauge should be located
relatively close to the project site, as to provide pertinent water level data to be used in post
processing. Additionally, the location of the gauge must be well documented by taking a survey
shot at its location immediately after deployment, as well as noting the time at which it was
deployed. This survey shot will then serve as a reference water level for further analysis, to be
conducted at a later time. When launching the HOBO prior to deployment, the individual whose
task it was typically took a screen shot of the launch screen, not only as a time reference for post
processing, but to ensure that all the required fields in the launch window were properly filled
out. With the HOBO ready for deployment, the stilling well used to house the instrument was
assembled from various lengths of
PVC tubing using slip couplings
and PVC cement. After
approximately 10 minutes, the
cement was dry enough to insert
the instrument and place the
apparatus into the river. Figure 12
shows the HOBO apparatus used in
Bethel, AK, located on a sea wall
that skirts the Kuskokwim River
there.
Contacts were made at each site
occasionally for the sole purpose of
retrieving these devices. A detailed
set of instructions for removing the
gauge was given to each contact, as
well as prepaid shipping labels and
padded boxes, to send them
back to Anchorage for
processing. This method proved quite effective and surpassed the expectations for the safe return
of the instruments, as there were only two that were lost over the course of the summer. With the
water gauges set and the static survey completed, the receivers were then connected to the
Figure 12: HOBO water level gauge deployed on seawall at Bethel, AK (Yager, 2009).
18
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
computer and their information was downloaded into TGO. After verification that the static
survey was a success the team was able to proceed with the scheduled work for that site.
As the land survey team began conducting
the topographic survey, the bathymetric crew
fitted the vessel with the ADCP mount and
prepared all necessary systems for the
intended work. With the mount in place, the
ADCP was securely fastened to the base plate
of the mount via four nuts and bolts, paying
close attention to make sure that the bolts
were tight enough as to not risk losing the
instrument during deployment. With the
ADCP in place, the Zephyr GPS antenna was
then screwed into its position at the top of the
mount and all the proper cables were
connected to their respective ports. At this
point, the ADCP is lowered into position so
that two important measurements can be
taken. The distance from the water surface to
the center of the transducer face on the
ADCP must be measured and recorded so
that the proper value may be entered when
the configuration wizard prompts the user.
Similarly, the distance from the water surface
to the bottom of the GPS antenna must be
accurately measured and recorded not only
for river slope measurements, but for post
processing considerations. All values are then
recorded in the field book for quality
assurance. After setting up the second
monitor for HYPACK navigation, instrument
calibrations could begin.
Before the process of collecting transect data
can begin, the ADCP must first run through a
general diagnostic test followed by a
compass calibration test. The diagnostic test
ensures that all of the sonar beams are
functioning properly as well as several other
vital systems on the instrument. The compass must be calibrated at each site as well, for reasons
Figure 13: Base station location at Kaltag, AK overlooking the
Yukon River Project Site (mills, 2009).
19
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
discussed previously. With these calibrations completed and after checking to make sure that the
base station is communicating with both HYPACK and WinRiver II, a test transect can be run.
The test transect provides several pieces of information that are used throughout data collection
at each site. From this test, the researcher can observe the maximum depth, water speed, water
temperature, and any problematic sandbars that may be present along the river. At the
completion of this process, this data can be entered into the configuration wizard in WinRiver II
and any user commands may be entered to adjust bin sizes where necessary.
When beginning a transect it is of utmost importance to have the vessel operator maneuver onto
the start of the preplanned line and maintain position in an area of sufficient depth until the
ADCP has acquired 2 “good” bins. At this time, it is important to remain stationary with the
ADCP pinging for at least 10 seconds observing those 2 bins so that the instrument can calibrate
itself for flow conditions and make more accurate estimations of the discharge on the starting
bank where the water is too shallow to take measurements. It is also necessary at this time to key
in an “edge estimate” into WinRiver II. At that point in data collection it is merely a rough
estimate. During post processing these estimates are corrected by using the topographic survey
information coupled with the bathymetric data in TGO, yielding much more accurate outputs
from the software. With this achieved, the vessel can then begin traversing across the river. In
doing this it is equally important to monitor the vessel speed as indicated by WinRiver II to
ensure that the boat is not traveling any faster than the velocities that are being observed by the
instrument. Not only does this provide a more dense data set for a transect, but it make velocity
calculations more accurate in the software. Much like the process undertaken at the beginning of
each transect, at the conclusion of a run the vessel must remain stationary for at least 10 seconds
while observing 2 bins, as to better estimate the discharge in the section that cannot be observed
by the ADCP. At the end of each transect WinRiver II also prompts the user for another “edge
estimate” for the distance to the water line, and is handled precisely as stated above. It was
typically the practice of the researcher to make two passes on a single transect to obtain an
average for the sought values, as well as to identify any obviously erroneous data. After
completing a transect and before moving on to the next, an ADCP log sheet is filled out and any
notes were recorded for future review.
While the hydrographic survey is being conducted, the topographic survey was also being
undertaken on the river banks. With the base station set over one of the two placed monuments,
the survey team records an initial check shot over the unused monument. This will serve as
quality check at the conclusion of the survey when the very same point is observed again and the
two shots are compared and analyzed for any misclosures. With the initial check shot recorded in
the data logger, the survey team set out to start observing on the river banks by staking out to the
preplanned lines, first taking a shot at the water line to provide a reference water level and
working up the banks from there. Typically 4 to 5 survey shots were taken for each bank on each
transect observing any and all major grade changes and noting the height of the cut banks where
present. This method was used throughout the summer and provided the topographic information
20
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
that was needed. At each survey point, the name of the point and a brief description were
recorded for cross-reference at a later time where needed. After completing one river bank, the
survey team was shuttled across the river by the boat crew to begin work on the opposite side of
the river. Where the depth of the river allowed, shots were taken in knee deep water in an attempt
to complete the bathymetry that could not be recorded by the ADCP, due to shallow conditions.
At some locations this was not possible due to the abrupt drop in river bed elevation, making it
unsafe to wade into the river.
Usually the final step in data collection involved “floating” the vessel downstream to acquire the
data necessary for determining the river slope at each location. This was done by attaching the
data logger to the Zephyr antenna atop the ADCP mount, keying in the vertical offsets, and
setting it to record data points at 100 foot intervals. This was conducted over a distance of 7500
to 8000 feet with boat at idle speed to obtain enough data points to accurately determine the
slope of the river. During this process, the occupants of the vessel were sure to be as still as
possible as to maintain stability of the boat in the water so as to not disturb the height of the
antenna during acquisition.
With the topographic data
collected, the survey team
set out to locate
landmarks and permanent
structures to be used as
control shots, in the event
that a research team
returned to the site in the
future. This would allow
any future data collected
to be tied to the same
coordinates and as well as
serving as a check shot.
Lastly, a final check shot
on the unoccupied
monument set earlier was taken for quality assurance. At the conclusion of work at a particular
site, the base station was taken down, the ADCP was dismounted and all equipment was stowed
in its respective hard cases. Upon returning to the lodgings for the night, all GPS receivers and
data loggers were downloaded and the information was backed up using an external hard drive.
The ADCP data was likewise copied to the external hard drive and the various batteries used
were plugged in to their respective chargers for work the following day.
Figure 14: Survey team locating local permanent control monuments (Butterer, 2009).
21
University of Alaska Anchorage Alaska Energy Authority
School of Engineering Preliminary Report
Throughout the process of both the land survey and the bathymetric survey, researchers were
faced with many challenges. On the hydrographic side, long, sweeping, shallow deposit banks
made it very difficult to set user commands that captured not only the shallow portions of the
river, but the deepest portions as well. This can be overcome to a certain extent with the
previously mentioned test transects, but ultimately it is left to the judgment of the researcher to
determine an appropriate course of action for capturing the data that best represents flow at a
particular location. Likewise, the land survey crew had many challenges on the river banks.
Often times, the banks were nearly impassable due to very soft silty clay, making for very
exhausting conditions and slow data collection. Also, the land survey team was occasionally
forced to cut their own view of the sky due to a dense tree canopy. Additionally, a small number
of transects had to be abandoned due to loss of base station radio contact as well as inclement
weather that posed substantial risk to the equipment and research team.
Using the methods described above, the research team was able to collect a wealth of
information at each one of these sites, where little or none existed before. The following steps in
the research involved the task of combining all the data and resolving it into a product that may
be used for a variety of analysis.