HomeMy WebLinkAboutCity Tribe Biomass Energy Conservation R3 Trip Report Tanana WTP Biomass Assessment 2022
MEMORANDUM
DATE: March 21, 2022
FROM: Utility Operations Specialist IV
SUBJECT: Trip Report, Tanana – Water Treatment Plant/Washeteria Biomass Heating
System Assessment (ZA2) – March 8-10, 2022
TO: FOR THE RECORD
OBJECTIVES:
1. Assess the condition and operation of the water treatment plant (WTP)/washeteria
biomass heating system.
2. Collect and compile information for development of a biomass heat system audit.
3. Develop a rapport with the utility/biomass system operator regarding utility operation.
4. Troubleshoot non-functional remote monitoring (RM) equipment installed in 2020.
5. Assess the operation and condition of the water utility system.
6. Assess heating system improvements associated with the Infrastructure Protection
Funding (IPF) and 2020 Coronavirus Aid, Relief and Economic Security (CARES) Act
work performed in December 2020.
CONTACTS:
Mr. James Roberts, Water Plant Operator, Too’gha Utility Inc.
Ms. Christine Erhart, Finance/Administration, Tanana Tribal Council (TTC)
Mr. Victor Joseph, Executive Director, TTC
ACCOMPANIED BY:
Ms. Bailey Gamble, Mechanical Engineer III, ANTHC
FINDINGS AND ACCOMPLISHMENTS:
Note: Minor repairs and assessments were conducted on the biomass system during a site visit in
December 2020.
We departed Anchorage at 9:10 a.m. through Fairbanks via Alaska Airlines and arrived in
Tanana via Wright Air at about 3:05 p.m. Mr. James Roberts met us at the airport and brought us
to the WTP. We later went to Tanana Commercial store to set up lodging.
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 2
March 8-10, 2022
WTP/Washeteria - Biomass
Mr. Roberts explained that the biomass boiler system was operated as the primary heat source for
the WTP/washeteria this last season and the community hadn’t burned much fuel oil through the
oil-fired boilers. He said he lead a small group of workers last fall to harvest and stockpile wood
for the winter’s biomass fuel supply. They dedicated 20 work days to harvesting dry standing
spruce trees from local forest fire areas. He stressed the importance of getting the wood cut to
length, sized, stacked, and ready to fill the boilers stating: “I haven’t had to touch a saw or axe all
year.” Mr. Roberts demonstrated filling and starting a fire in the boiler units.
We observed another worker hauling wood with a plastic toboggan approximately 80 feet from a
pile under the snow to the inside of the biomass garage. Mr. Roberts said they had already used
up most of the wood that was staged closer to the building. The facility lacks a woodshed or
shelter for bulk wood storage. We discussed different methods of woodcutting, handling, storing
and moving wood from the outside storage area (under the snow/drifts) to inside the facility to
feed the boilers. Handling seasonal wood fuel (90-plus cords) is labor- and time-intensive.
Minimizing handling was discussed.
The following was observed:
1. The Garn boilers’ fresh air intakes were disconnected from a through-wall vent pipe due
to frosting condensation problems. The frosting condensation is primarily caused by
intakes not built and insulated per the manufacturer’s installation directions. Boilers are
designed to draw combustion air directly from the outside. Note: Supply and return
piping installed at each boiler did not provide clearance to refit the intake to the
manufacturer’s recommendation. Rehabbing the faulty intakes will require some creative
alteration to correct.
2. Potential corrosion exists with the Garn boilers.
a) Dielectric isolation between the Garn carbon steel boiler to copper pipe was not
observed during the inspection. The boilers are piped using copper immediately
exiting the boilers after the steel flex lines. No dielectric separation exists. Most
of the copper piping utilizes Pro-Press fittings. Pro-Press fittings are crimped and
rely on an O-ring seal. Fitting and valves cannot be disassembled or reused for
piping alterations. If piping changes are required, new replacement pipe, valves
and fitting would be needed.
b) Existing sacrificial anode rods inside the boiler were observed to be depleted and
require replacement. However, Garn now recommends boiler water filtering and
ensuring electric isolation of the boiler body instead of anode rod replacement for
protecting against corrosion.
c) The system has no filtration. Garn recommends continuous removal of suspended
particulates through a bypass filter and passing flow through the filtration system
when filling.
d) The boiler water was tested with a pH litmus paper with a qualitative result
system. The result indicated high corrosivity.
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 3
March 8-10, 2022
e) Note: Service life for the Garn boilers is dependent on the water condition and
proper maintenance. Upgrading and adding Garn boiler filters and a testing and
treatment plan should be strongly considered.
7. The interior boiler reservoirs are coated with built-up calcification/sediment. Draining
and pressure-washer cleaning inside all boiler tanks is recommended to remove the
buildup and sediment. Refilling with clean water and proper anti-corrosion additives is
recommended. Buildup inside the boiler could potentially contribute to inefficient heat
transfer.
8. The operator reports adding 70-80 gallons of water to the biomass boiler loop every 7-10
days. This primary cause is likely evaporation through the manway covers where the low
water sensor is inserted. Expected water loss is closer to 50 gallons per year. New, two-
part manway doors with properly sealed low-water sensor penetrations should be
considered.
9. Boilers are piped in parallel such that the supply is a mix of flow from all three
reservoirs. Two out of three boilers were being fired. Isolating unused boilers by closing
the isolation valves will prevent mixing of heated and cold water and increase supply
temperatures. Note: Valves should be opened to allow slow warming of an unused boiler
by the other boilers before firing for the first time after being offline/isolated from the
system.
10. An inline strainer is on the Garn boiler supply line between the boiler and upstream of the
circulation pump. It is unknown when the strainer screen was last cleaned. The strainer is
also positioned downward, making access for cleaning difficult. Rotating it a 1/4 turn
sideways would make cleaning access easier. No pressure gauges exist before or after the
strainer for monitoring differential pressure or pressure at the inlet of the circulation
pump. Monitoring and periodic cleaning of the screen is required if buildup develops and
results in lower pressure to the circulation pump. Minimal inlet pressure at the circulation
pump should be maintained to reduce hot water vaporization and pump cavitation and to
extend the service life of the circulation pump.
11. No pressure gauge exists on the circulation pump discharge or return manifold. Gauges
are recommended to monitor pump performance and operational system pressure.
12. Mr. Roberts expressed concern about the inside temperature of biomass garage getting
too low in severe -40 to -50°F weather conditions. Part of the heat loss can be attributed
to the incorrect boiler combustion air being drawn from inside the facility and replaced
with the cold outside air coming in from wall vents and directly mixing with the inside
air, cooling the room. Correcting the boiler combustion air venting as described above
should help to limit low-temperature conditions inside the garage.
13. Mr. Roberts also mentioned a need for a backup heat source in the event of an electrical
power outage. Backup heat was needed to prevent the biomass boilers/pumps/lines (filled
with water) from freezing. Discussion regarding backup options led to a conversation
about re-establishing operation of the backup generator provided for the WTP/washeteria.
Electrical power service for biomass is provided from the WTP/washeteria electrical
distribution panel, so the backup generator could potentially provide backup power to the
biomass. The generator fuel lines were previously disconnected by the community in
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 4
March 8-10, 2022
2020 when fuel lines to the oil-fired boilers’ automatic day tank were blocked with ice.
The fuel piping lines should be reconnected and the backup generator should be returned
to operational status.
14. Insulation in the biomass boiler garage ceiling was observed limited/lacking. Repairs of
damage from a fire that almost burned down the facility did not add enough replacement
ceiling insulation. Additional blown-in or fiberglass insulation would reduce heat loss
and help to address concerns about low inside temperature.
15. Both gable-end roof vents are damaged. The washeteria side is wide open to blowing
snow and rain. Replacement of both vents is needed.
16. There is fire damage on the northwest corner of building. Snow and drifts made closer
inspection difficult. Investigation after the snow melts is recommended to evaluate
damage. Insulation and siding repair might be required to reduce garage heat loss.
17. The side manway access door (3’ x 6’-8” standard residential exterior door) does not shut
properly or seal. The operator relies on a rag looped through the open door knob hole to
tie off outside to keep door somewhat shut. This contributes to heat loss. It is assumed
that building movement and shifting caused the door closure problems. Door repair or
replacement is required. Since biomass wood is primarily hauled through this door,
building a larger, more robust field-fabricated door was discussed.
18. The biomass garage door is not primarily used to transfer wood into facility. Garage
doors in general typically do not have high R-insulation value. Improvements by better
sealing or adding insulation to the door was discussed.
19. No cooling fan ventilation exists. Observation during a 2019 trip showed the garage door
was left open for cooling during warm weather.
20. Small pop-out air vents are installed high on the exterior walls.
21. Lighting inside the biomass garage is minimal and dim. New LED fixtures would be
beneficial.
22. Huffing by the Garn boilers was observed. Huffing is not unusual during boiler startup
using dry, smaller-sized, fast-burning wood such as that currently used.
23. Mr. Roberts replaced one of the Garn boiler blower motor units.
24. Mr. Roberts ordered some replacement parts direct from Garn in Minnesota. Cleaning
brushes or spare gasket sets for flue passages was not observed. A critical spare parts list
and maintenance tools specifically for Garn boiler operation should be developed,
ordered and kept on hand. Annual cleaning of the boiler’s flue pipe passages should be
performed and would improve heat transfer efficiencies from biomass fire to the heated
water.
25. Storage/shelving space for spare parts is limited inside garage. Adding more shelving and
potentially a small workbench would be beneficial for biomass and chainsaw operation
and maintenance.
26. The fire chamber bricks inside the boilers are in poor condition, broken or missing.
Replacement should be considered to protect and extend the service life of the fire
chambers.
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 5
March 8-10, 2022
27. All the Garn boilers’ fire chamber door handles and hinge pins are worn and should be
replaced for positive door seal. Handle pins/bolts were added to doors in December 2020
to safely secure the handle latch when boilers are operating during huffing periods.
Huffing creates a risk of unlatching and a slight opening of the door resulting in burning
embers popping out into the garage. This is a fire hazard when wood chips and stacked
firewood is nearby.
28. A short plywood skirt/apron is in front of the Garn boiler doors on top of the foundation
frame. Replacement with sheet metal should be considered to reduce fire hazard from
embers escaping from the fire chambers.
29. There is no moisture meter onsite to test for optimal moisture content of the wood supply.
30. The biomass supply and return lines between the biomass garage and the WTP boiler
room are fed through two 6-inch arctic insulated carrier pipes. The supply and return line
are two sets of 2-inch PEX piping (four pipes total). The lines are run high above the
Garn boilers’ water level and are run even higher within the WTP boiler room into the
mechanical area to the main heat exchanger. This heat exchanger is the interface of the
biomass heat and the heating return line to WTP oil fired boilers. The high elevation of
the piping creates air lock issues for the biomass boiler system, which is open to
atmosphere. High point air reliefs to release trapped air can only be manually operated,
requiring water pressure to evacuate air in the line or use of pressured water flow/velocity
to push air back down into the Garn boiler. Alterations to lower the lines would require a
major mechanical refitting of the biomass piping system between the garage and inside
the WTP. Although not mechanically ideal, the existing system can and does operate well
to transfer heat.
31. The copper 2-inch fitting on the biomass supply line above the No. 1 oil-fired boiler in
the WTP has been leaking since observed in December 2020 and requires repair.
32. The copper 2-inch biomass supply line high point in the mechanical room area (before it
drops into biomass heat exchanger) requires installation of a manual air relief tap and
isolation valve.
33. There are no pressure gauges on the biomass heat lines to the heat exchanger (HX)
supply or return manifold to verify differential pressures and/or a blocked or fouled HX.
34. There is no supply temperature gauge prior to the biomass HX. There is only a return line
gauge.
35. There is no dedicated HX flushing port for the biomass main heat exchanger.
36. The three-way valve stem on the biomass three-way globe valve has developed a small
leak. A calcium-type buildup was observed around the valve near the leak.
37. The actuator for the main HX three-way valve was replaced during the CARES Act work
conducted during December 2020. It was determined at that time the three-way valve
wasn’t required and serves as a redundant control. The heated hydronic side of the HX is
tapped on nodes located on the building’s heat return line with a heat injection pump.
This pump is controlled to start and stop to inject heat based on the available biomass
supply to the HX and the temperature differential of the WTP boiler return. The three-
way valve also operates based on the same differential temperature. The three-way valve
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 6
March 8-10, 2022
and actuator should be considered for removal to eliminate redundancy and simplify the
heat control operation. The three-way valve could be replaced with manual isolation
valves at the HX supply and return ports with a manual bypass valve between supply and
return. Removal would simplify heating control with one less failure point.
38. The main biomass heat exchanger is a plate and frame Ameridex product 95312 with 2-
1/2-inch flanged ports. Plate and frame HX units can be dismantled, cleaned, and rebuilt.
Additional plates can potentially be added or removed to increase or reduce heat transfer
capacity. However, plate gaskets can harden and fail requiring periodic replacement. The
typical design life for the plate gaskets is 7-20 years dependent on heat and service.
Gasket or plate assembly replacement is a relatively simple task. Poor water quality
(corrosive/low pH/ suspended solids) can corrode or erode plates to failure and sediment
buildup can foul and plug passages, reducing heat transfer. Replacement of the heat
exchanger gaskets and pre-gasket plate assembly should be considered as part of the
critical spare parts.
The WTP/washeteria oil fired boilers were never observed to operate during our trip. Sufficient
heat was supplied by the biomass system. The Tanana biomass system, although not perfect,
does work well when operated correctly and has a proven ability to provide heat for the WTP
and washeteria and meet heated water system demands, which defers the purchase or use of
heating oil.
WTP/Washeteria Backup Generator Module
The backup generator is a 55-Kilowatt (kW) three-phase Kohler powered by a John Deere diesel
motor. The generator is not currently operational. The generator is housed inside a small heated,
insulated generator module located west of the WTP/water storage tank (WST). Heat is provided
by a wall-mounted electrical 240 volt X 4000 watt heater. There is an electrical block heater on
the generator engine. There was a total of 154.5 operational hours on generator meter. The fuel
line from the double-walled storage tanks were disconnected in 2020. Filters, engine coolant
fluid, and an oil change are required to return the unit back into service.
1. The disconnected fuel line previously supplied fuel from the large double-walled storage
tank to the automatic day tank located in the module that in turn provides pre-heated fuel
storage to the generator motor. The fuel lines needs to be reconnected.
2. The battery shows corrosion on both terminals and needs replacement.
3. The generator module has settled and requires leveling.
4. The combustion make-up air and cooling system duct and louvers will require functional
testing after the generator unit is started and operated under load.
5. The fluorescent lighting inside the module appeared to struggle to turn on. Replacement
LED lighting is recommended.
6. An automatic double-throw transfer switch is located inside the WTP immediately
outside the boiler room directly next to the C electrical distribution breaker panels.
Functional testing of the transfer switch should be completed after repair/startup of the
backup generator.
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 7
March 8-10, 2022
The backup generator and transfer switch need to be returned to operational service for
emergency events when grid power fails. Having backup electrical power available will prevent
freeze-ups and maintain required heat support systems for the WTP, washeteria, WST, water
distribution and the biomass heating systems.
Solar Panel Photovoltaic (PV) System
A solar array consisting of 42 panels is mounted to the south side of the WTP/washeteria roof.
The 5.5-kW array was installed around 2007. The array is mounted upright with Unistrut
supports fastened to the roof. The array was not covered with snow during the visit. It was
apparently shut off due to the local power company not allowing the PV system to back-feed
power into the local grid power.
1. Each panel is a Kyocera Model KC130TM (ser. 0828HA4860) Pmax 130W. All the
panels look to be in good condition (no rock/other damage observed).
2. The power inverter is a Xantrex Utility Interactive Inverter model GT5.0-NA-240/208
UL-05. The inverter was manufactured in August 2007. The unit is located next to the
backup generator transfer switch outside the WTP boiler room.
3. When placing the system switch into the on position, the inverter indicates a ground fault.
Pending further assessment of the PV array’s functionality, the existing system should be
brought back online or replaced with newer panels in conjunction with a solution to maximize
utilization without back-feeding into the grid. Integration of battery energy storage as well as
utilizing solar power for heat should be evaluated. Applying the electrical energy directly to
water systems, space heat or possibly biomass heat integration could provide useful benefit and
further reduce utility operational costs.
Remote Monitoring (RM) System
The RM system installed during 2020 had not been working or reporting for approximately 180
days prior to our trip. The operator located the modem during the trip and discovered that it was
unplugged in the Too’gha office on the east side of the washeteria. Plugging the modem back in
corrected the problem and connection was re-established. However, sensor readings sometimes
lagged by an hour or two, likely due to poor cellular connection. We discussed with Mr. Roberts
installing additional sensors. The website link for the RM system was provided and set up on the
Too’gha office computer. Note: The office has internet service but no Wi-Fi router. Providing
wall laminates about RM operation and maintenance would be beneficial. Upgrade to a Wi-Fi-
based system is recommended in order to generate more useful real-time output.
IPF Heating Improvements (Continued 2020 CARES Act-Funded Efforts)
Our December 2020 CARES Act efforts resulted in training the operator on replacement of
heating system valves, actuators, and T775 controllers with new sensors for the raw water glycol
loop, raw water heat-add, East and West distribution loops, and the WST heat-add. A spare
replacement heat exchanger was provided for the distribution loops but not installed. (The
existing HX is still functional.) The actuator for the biomass three-way heat control valve was
replaced, including a new T775 controller, and four flush hydrants were provided for the water
distribution system.
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 8
March 8-10, 2022
During the December 2020 work, the associated IPF funding was not available so we did not
finish all improvements. The existing HX piping is not standard throughout the plant and does
not include all the normal pressure relief valves (PRVs), temperature gauges, pressure gauges or
flush ports. The IPF-funded efforts plan to address this to improve HX operation and
maintenance. Efforts made during trip include:
1. Detailed pictures of all HX system piping were taken for improvement development
planning.
2. Mechanical parts left over from CARES work efforts were sorted and inventoried by
taking pictures. Fittings are planned to be used to supplement needed parts.
Planning of work with mechanical isometric drawings of each HX system will need to be
developed, including an associate materials take-off list for the materials and equipment
required. A return trip to Tanana for the work will be tentatively planned for later summer/fall of
2022.
Other WTP/Washeteria Upgrade Work
During the trip, we observed the Fairbanks-based HVAC LLC contractor working to replace the
washeteria dryers. The existing air-to-air heat exchangers and associated ductwork was being
removed in preparation for new hydronic dryers. Other mechanical and heating work for the
tribal council within the community was included. Project materials were hauled by the
contractor’s trucks using the Fairbanks Manley Tanana road. An ice road across the river was
established.
Tanana Raw Water Intake and Treatment System
Tanana’s raw water comes from the river during the winter or the surface-influenced well next to
the river during the summer. The system’s intermittent water-making requires that the operator
make a hole in the river ice about 100 feet from shore to insert the submersible pump, then
remove the pump when water-making is complete. The operator then uses compressed air to
blow out any water remaining in the line from the pump house to the pump to prevent freezing.
The line remains, marked with flags and resting on top of the ice, when not in use. The operator
expressed interest in developing a temporary protective structure at the water access point.
The treatment and associated monitoring falls under the surface water treatment rule. The water
treatment monitoring equipment was observed to be outdated, obsolete and non-functional.
It was again observed that the finished water turbidity meter is not functional. The turbidity
monitoring was originally recognized as non-functional during the December 2020 CARES Act
work. In mid-January 2021 with Mr. Lee Meckel, remote maintenance worker (RMW) with
Tanana Chiefs Conference (TCC), onsite, the Hach 1720D turbidity meter and the old
AquaTrend/SOM linked to the wall chart recorder were re-programmed. This effort required
calling the Hach factory representative for assistance. With the information provided by Hach,
the equipment was restored to operation, however it appears that wasn’t a permanent fix or
solution.
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 9
March 8-10, 2022
Mr. Roberts stated he has repeatedly re-programmed the unit using the literature, but the unit
disconnects and drops out shortly after each re-programming sequence when he leaves the plant.
A solution to correct this should be identified.
We departed Tanana at about 3:20 p.m. March 10 via Wright Air and arrived in Anchorage at
about 8:49 p.m. via Alaska Air.
RECOMMENDATIONS AND/OR CONCLUSIONS:
1. Assist in the development of a Tanana WTP/washeteria biomass heating system audit and
a prioritized list of potential improvements
2. Work with community to provide recommendations to repair the WTP/washeteria’s
backup emergency generator.
3. Research alternative electrical/heat use of the solar panel array/voltaic system.
4. Continue monitoring the RM system to confirm whether operational. Develop RM
laminates to provide operation and maintenance guidance.
5. Develop IPF HX improvements isometrics and material take-off, order materials, and
ship to Tanana. Set up work trip after materials arrive in Tanana (late summer/early fall
2022).
6. Assist community with possible improvement to the non-functional surface water
treatment turbidity monitoring.
Martin Wortman
cc: James Roberts, Water Plant Operator, Too’gha Utility Inc.
Cliff Wheil, President, Too’gha Utility Inc.
Christine Erhart, Finance/Administration, TTC
Victor Joseph, Executive Director, TTC
ec: Lee Meckel, RMW, TCC
Noah Tsigonis, RMW Supervisor, TCC
Oscar Menendez, Village Safe Water Engineer II, Alaska Department of Environmental
Conservation (ADEC)
Susan Randlett, Village Safe Water Engineer I, ADEC
DEHE – Brian Menghini/ Valerie Zeedar/
Bailey Gamble/ Cindy Baldwin
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 10
March 8-10, 2022
Biomass Boiler Building
Garn Biomass Boilers
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 11
March 8-10, 2022
Combustion Air Intake
WTP/Washeteria Backup Generator Module
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 12
March 8-10, 2022
Solar Panel PV System
Trip Report, Tanana – WTP/Washeteria Biomass System Assessment Page 13
March 8-10, 2022
Obsolete/Non-Functional Water Treatment Monitoring Equipment