HomeMy WebLinkAboutKiseralik-Chikuminuk Hydro Recon and Prelim Hydro Feas.Study 2011 REF Grant 2195447KISARALIK RIVER AND
CHIKUMINUK LAKE, ALASKA
RECONNAISSANCE AND PRELIMINARY
HYDROPOWER FEASIBILITY ST�
O � �
O G® G
Q�- ,NO
�P G
1 Prepared for:
S ati, ry iQ e Council Presidents Regional Housing Authority
GODraft Report
January 2011
EXECUTIVE SUMMARY
The purpose of the study described in this report is to develop, consolidate, and present a body of
information on candidate hydropower projects for serving the electrical demand in the Bethel
and surrounding communities region. If the Client (the Association of Village Council Presidents
Regional Housing Authority, or AVCP RHA) or the grant funding agency (the Alaska Energy
Authority) deems the projects worthy of further study, the next step would be to conduct a
detailed feasibility study and this would include site investigations and formulation of
preliminary designs.
Candidate Sites for Hydropower Development
The study focused on the hydropower development
Allen River draining Chikuminuk Lake. These car
appear to represent the best opportunities for pro
electrical demand in the Bethel and the surroundine c
The hydropower generation potential could
Kisaralik River (Golden Gate Falls, Lowe
Lake outlet. It is possible that the three e6r
two projects, or even a single proje
reasonable projects with the bt et va
environmental constraints, and p deci;
The physical develol
construction of a dam,
of the four sites coul
cut through one ot(th
could provid*rl
within a reash:
evaluation. Dn i
constructing a d
selected to acco
separate tunne<
directly coyrl�N
It
Pik Ri a the
i mast and
meet the
scre e p Tects: three on the
`d at the Chikuminuk
cc old be consolidated into
e intent was to develop
estimate the costs, assess
four candidate sites would involve
ling facilities and a powerhouse. Each
t rockfill dam and a spillway channel
that the spillway channel excavation
R-for.LN don: It is not known if fine grained materials exist
so ncrete faced rockfill type dam was adopted for this
w d g construction of the dam would be accomplished by
iN the dam site. The diversion tunnel configuration has been
oNte us aversion features as part of the power waterway, avoiding a
iainimi<AeNcost. A powerhouse would contain two Francis type turbines
to n or. Each project would need facilities to handle migratory fish
_cXis s for each candidate project are listed below:
rt
Average
Flow
cfs)
Reservoir
Storage
AF)
Dam
Height
ft)
Chikuminuk Lake
1,353
2,008,377
128
Golden Gate Falls
1,757
20,894
118
Lower Falls
1,603
72,502
173
Upper Falls
833
53,963
204
MWH ES-1 January 2011
Kisaralik River and Chikuminuk Lake
Reconnaissance and Preliminary Hydropower Feasibility Study
Energy Generation
The anticipated hydropower generation characteristics of each site, as developed for this study,
are defined below. The Kisaralik River projects have limited storage, and therefore have a
limited ability to regulate flows for delivering firm energy. Firm energy is the amount of energy
per year that can be delivered in a specified pattern (by month) with a specified reliability. The
months of February and March are low flow months, and therefore constrain the quantity of
energy that can be considered firm. For the purposes of this study, the specified reliability for
considering energy as firm is 90% on a monthly basis considering the estimated historical flow
record. `C�)
Site
Min /Rated/
Max Head
(ft)
Generating
Capacityergy
(MW)
Firm Anryell
Aver ag n al
(GW
y
actor
Chikuminuk Lake
70 / 1 14 / 134
13.4
10.J, 8
87:°%
Golden Gate Falls
44 / 75.5 / 85.5
27.0
18.
36%
Lower Fal Is
76 / 130 / 147
34.1
3.2
41 °/u
Upper Falls
96 / 165.2 / 185
86.7
36%
Transmission Interconnection Q� egthe
A major transmission line wou{��1�clLure terc didate projects with the
regional electrical power sr ply id. h t e is to ed as a 138 kV single circuit line
supported on wooden XX- H-s�o es. T��nces from the interconnection in the
Bethel area to each sit r iveain ollowin e:
O
Acces�
The sites are no without existing permanent access. Transport of heavy materials and
equipment ul e during the winter months via ice road from Bethel. During summer months,
small equipm supplies and personnel would be ferried in by aircraft. A construction period
labor camp would be required.
Sit
Distance (miles)
i u
' iuk c
118
o
G to
57
ower
62
U
Is
70
Long-term operation would need to rely on support by air. A permanent road is not planned.
MH ES-2 January 2011
Kisaralik River and Chikuminuk Lake
Reconnaissance and Preliminary Hydropower Feasibility Study
Regulatory and Environmental Constraints
Development of any of the projects would require a FERC license.
The Kisaralik projects would be located within the Yukon Delta National Wildlife Refuge
(YDNWR). Although not typically found in National Wildlife Refuges, hydroelectric projects
may be permissible in the YDNWR, as there are no explicit prohibitions in the National Wildlife
Refuge System Administration Act of 1966 or in the National Wildlife System Improvement Act
of 1997. The permissibility of hydroelectric development construction and operation would be
determined by the Secretary of the Interior on a case -by -case basis under existing Irw
t should
be noted that development and operation of the Terror Lake Hydroelec ect as
determined to be permissible within Alaska's Kodiak National)*ildlife Refdgp, spite Xrig
opposition; a 50-year FERC license for this project was
went into service in 1985, and provides much of the elec
of
The Chikuminuk project would be located within erne Aat d Hof Wood-
Tikchik State Park; the park authorizing legislate � u ne am n o specifically
allow hydroelectric development at Chikuminuk 1 ikL� f is i %0� asPgrficant constraint.
The Kisaralik River is used extensively� alp romo(Is f)s�pis is viewed as a
significant licensing constraint.
�`
Project Development Sche{�
The absolute minimum ti to im`lle of candidate hydropower projects is 10
years. The projects wot uire a F tense construction could begin; the estimated
minimum duration t a F 1 ens candidate projects is 5 years. A minimum
one year period is peetwe ie tim use is issued and construction can begin. The
construction d e at ar . The above stated durations assume favorable
conditions in�f a view pproval in the licensing phase and minimum issues
during the constructioni(ctua evelopment duration could be longer.
Opinion of �b e
The esti d ost o �ai�project, if developed on a stand-alone basis, is as indicated in the
followi> P Thd costs are at the December 2010 price level without escalation or
charges fo inter st ng construction. The construction cost is the estimated amount for project
and transmi construction, plus procurement of the permanent turbine and generating
equipment, t i thout an allowance for escalation of costs beyond 2010 during the course of the
future construction period. The "total project cost" is the construction cost plus the estimated
development costs, such as engineering, management, legal services and reserves, but it does not
include escalation or interest charges. The specific cost is the total project cost divided by the
generating capacity of the facility.
W, H ES-3 January 2011
Kisaralik River and Chikuminuk Lake
Reconnaissance and Preliminary Hydropower Feasibility Study
Site
Construction
Cost
(2010 $ million)
Total
Project Cost
(2010 $ million)
Specific Cost
(2010 $/kW)
Chikuminuk Lake
391.7
483
36,045
Golden Gate Falls
305.5
378
14,000
Lower Falls
329.5
408
11,965
Upper Falls
386.4
479
17,292
Levelized Cost of Energy Output
A "levelized" cost of energy, based on the estimated average annual
for the purpose of determining the candidate project with the to
for determining if the candidate hydropower projects could
generation. The "levelized" energy cost is an index t fle(
production, but since the overall schedule and finane' Ir arel
which can be significant, are not included in the leve St. Th
per kWh that would case the benefit cost ratio o ne
breakeven value (NPV = 0) in an economic c n. Th ac is
be somewhat greater than the levelized cot Vo a count or nci
performance requirements. Various ass s In 1 tj� e c
energy cost are described in the attac r ort. T alculate vVS
in
_`: _ 4
Vhe Z.6st of
awns, I&Z mg costs,
ed V-Ys-The revenue
value to be a
upµ quirement would
band other financial
ition of the levelized
costs are summarized
�,� � • III 1 1
AM
Conclusion Q
ON
All four c e pro ct /ibit specific costs in excess of $10,000 per kW of installed
generati ity, is is somewhat greater than the typical industry average. Calculated
levelizenergy ," the projects ranges from 13.3 to 21.4 cents per kWh. Actual revenue
requireme is fo fin ial feasibility may be greater.
The lowest c st roject (per unit output, both in terns of cost per kW and cost per kWh) is the
Lower Falls project on the Kisaralik River.
The Chikuminuk Lake project has been favored in previous studies. However, the distance from
Bethel (it is the most distant from Bethel of the candidates considered), its location within a State
park, and the significant alteration to an existing natural lake are significant impediments. The
Chikuminuk Lake project has the advantage over the Kisaralik projects in that it can provide a
(jam MWH ES-4 January 2011
Kisaralik River and Chikuminuk Lake
Reconnaissance and Preliminary Hydropower Feasibility Study
relatively stable month -to -month energy delivery under a wide variety of hydrological conditions
and does not appear to have anadromous fish use.
Therefore, if studies are to continue, the Kisaralik River Lower Falls project should be the first to
be considered, although it should be recognized that the energy output potential during February
and March is constrained. The Lower Falls project reservoir level could be significantly modified
from the concept in this report by raising the Lower Falls dam to combine the Lower and Upper
falls into a single project. This would result in a substantial increase in energy production and
power output at a low incremental cost, and would also provide more reservoir storage to reduce
the February and March energy delivery constraints. (^✓
If the Kisaralik River Lower Falls is developed as an initial pr t, this
potential significant reduction in the cost of the Chikuminuk c did
future development. The substantial cost reduction will trom by
approximately 62 miles of the 118 miles of transm' ' me e
Chikuminuk Lake project with the Bethel area system; i (
We recommend that future studies continue on
River project. The studies should be carried o
economic feasibility. The activities sugg
initial information for evaluating projec
Market study, combined
optimum size of a combi
Pending a favorable qqutc
o Surface ge_Ak,;w
O LIUAK U 8
o InstaiRffli of a
o _ tn'epare an
as
in
tom �mect a
yerPall`s Kisaralik
xmit evaluation of
the next level of
a po�y� operation study, to determine the
Up Fa s project,
Od er� ion study, then
recording station in the vicinity of Lower
of the site for the purposes of supporting a
1'WC Pl00y Appl'tran Document
o Prep o pr nary engineering concept drawings and an AACE Class 4
cost mate. `
The above ' na ion �(fd\r_ovide a definitive basis for determining if it is justified to
proceed y i si mfic ess ments in FERC licensing.
G�
MWH ES-5 January 2011
Kisaralik River and Chikuminuk Lake
Reconnaissance and Preliminary Hydropower Feasibility Study
Remove this page and replace with a copy of the Location Map — this is Exhibit 2 in the Main
Report.
WH ES-6 January 2011
X
.Y' WS590 0
k1
r
Kisaralik and Chikuminuk Lake
Reconnaissance and Preliminary Hydropower Feasibility Study
Table of Contents
EXECUTIVESUMMARY..........................................................................................................1
Candidate Sites for Hydropower Development........................................................................... 1
EnergyGeneration.......................................................................................................................2
TransmissionInterconnection...................................................................................................... 2
Access........................................................................................................................ ............... 2
Regulatory and Environmental Constraints.......................................................... ....✓.......... 3
Project Development Schedule.......................................................... ..... ....
Opinion of Probable Cost........................................................... ...
Conclusion ................ ...%�.�.-.......... ... ........
....�`....... 4
1 INTRODUCTION ............................ .........................�/.....J...... .. �..........�.........1-1
1.1 Scope of Work ................................................. ........... .... . .......... �...........1-1
1.1.1 Hydrology Study .................................. � ....... . ..... 1-1
1.1.2 Assess Existing Conditions.......... .. �......................
LL3 Develop. Feasible Layout........
1.1.4 Schedule and Costs ............... 1-2
1.1.5 Geotechnical Analysis.<....�..........�.................... .................... 1-2
1.1.6 Land Status and Trans issi Lin g..... ..... 1-2
1.1.7 Environmental Per naly ' ... .. 1-3
1.1.8 Economic Feasi ilit lalysi 1-3
1.1.9 Regional Wh e le tili gafopment.........................................1-3
1.1.10 Public i n........... .............................
—........
.............................. 1-3
1.2 Organizatio a ep �........................................................................1 3
2 BACKGRO ND UU� S.......................... ...................................... 2-1
3 UNDER IN ES AND CONSTRAINTS.................................3-1
3.1 Infrastructur i e Aot s........................................................................ ..................................................................................3-1
3.2 Land Use a nviro a onstraints......................................................................3-1
3.3 Hydrol tudi etting................................................................:.................. 3-2
-ff
3.3.1 mw.... ... 3-2
3.32 Hy y......................................................................................................3-5
-113.4 cal........................................................................................................3
3�
Leei.............................................................................. ................................. 3-11
3.4.2 Physiology ............................................. ............................... .................. 3-11
3.4.3 eg nal Geology ..................................... ............................................................. 3-12
3.4.4 Regional Tectonics and Seismic Records ...... ......................................... ............... 3-13
3.4.5 Summary............................................................ .................................................... 3-15
3.4.6 Recommendations ........................................ ...... .................................................... 3-16
4 TRANSMISSION LINE PLANNING ................................................... ................... ......... 4-1
5 SITE SPECIFIC PLANNING WORK.............................................................................. 5-1
MWH ES-i January 2011
Kisaralik River and Chikuminuk Lake
Reconnaissance and Preliminary Hydropower Feasibility Study
Table of Contents (continued)
5.1 Hydrological Parameters................................................................................................5-1
5.1.1 Chikuminuk Lake.....................................................................................................5-1
5.1.2 Upper Falls...............................................................................................................5-3
5.1.3 Lower Falls............................................................. ................................................. 5-5
5.1.4 Golden Gate Falls.................................................................................................... 5-7
5.2 Geological Assessment and Construction Materials...................................................... 5-9
5.2.1 Chikuminuk Lake.....................................................................................................5-9
5.2.2 Upper Falls............................................................................................................5-13
5.2.3 Lower Falls............................................................................................. 5-17
5.2.4 Golden Gate Falls............................................................................. ..
-19
5.3 Project Concepts.................................................................
5.3.1 Dam and Spillway ................................................ ...... .. 3
.............. .......... ..
...... ..... .................
5.3.2 Waterways....................................................... ....... ... .. . ... ..5-25
5.3.3 Powerhouse and Major Equipment ............. . . ....... ... 5-26
5.3.4 Switchyard ................................................ . ......... .. 5-27
5.3.5 Access Features ................................... �'�l►....... ......_�� �...............5-27
6 FISH PASSAGE CONSIDERA
6.1 Chikuminuk Lake / Allen River
6.1.1 Fish Passage Design Parap+
6.1.2 Upstream Passage ..... \.
6.1.3 Tailrace Barrier......
6.1.4 Downstream Fish
6.1.5 Fish Passage Fa ility pe
6.2 Kisaralik River
6.2.1 Fish Pass gn P
6.2.2 Upstre age ..
6.2.3 4ishassa
�ul F cM4tva..e
6.2.4'earn sage
6.2.5 ty Opera
......... if
.......................6-1
as ge ............................
6-1
.............................
6-1
...................I....................
6-1
..........................................
6-2
..........................................
6-2
..........................................
6-3
..........................................
6-3
..........................................
6-3
..........................................
6-4
..........................................
6-4
..........................................
6-4
..........................................
6-5
7 OPINION OFWBwABL ROJECT CAPITAL COST .......................
7.1 Estim Metho.........................................................................
7.1.1 uctio.............................................................................
7.1. Pri ing B is ....................................................... I...........................
7.1. stima st ication.......................................................................
7.1.4 Esti at Scheduling Systems.........................................................
7.1.5 ethodology..........................................................................
7.1.6 kltiAating Accuracy..........................................................................
7.1.7 Direct Cost Development...................................................................
7.1.9 Indirect Cost Development................................................................
7.1.9 Estimate Adders.................................................................................
7.1.10 Labor Rate Development................................................................
7.1.1 l Equipment Rate Development........................................................
T1.12 Escalation........................................................................................
...................... 7-1
...................... 7-1
...................... 7-1
....I ................. 7-1
...................... 7-1
...................... 7-1
...................... 7-1
...................... 7-2
...................... 7-2
...................... 7-2
...................... 7-3
...................... 7-3
...................... 7-3
...................... 7-3
W H ii November 2010
Kisaralik River and Chikuminuk Lake
Reconnaissance and Preliminary Hydropower Feasibility Study
Table of Contents (continued)
7.1.13 Allowances and Contingency...............................................................................7-3
7.1.14 Market Conditions................................................................................................7-3
7.2 BASIS OF ESTIMATE..................................................................................................7-3
7.2.1 Introduction.............................................................................................................. 7-3
7.2.2 Project Scope...........................................................................................................7-4
7.2.3 Project Status...........................................................................................................7-4
7.2.4 OPCC Background...................................................................................................7-4
7.2.5 OPCC Reference Documents........................................................................... 7-4
7.2.6 OPCC Quantity Basis............................................................................. .7-4
7.2.7 OPCC Classification......................................................................... .. 4
...........
7.2.8 OPCC General Assumptions ..................................... /..►
7.2.9 OPCC Specific Assumptions ................................. ..... .............V -5
7.2.10 OPCC Labor Assumptions .......................... ..`�� ... . �. / 7-5
7.2.11 OPCC Exclusions/Exceptions ................. ... 7-6
..........
7.2.12 OPCC Allowances ................................. ........... .. 7-6
7.2.13 OPCC Bidding Assumptions .............. ........ .. .. ... 7-6
................
7.2.14 OPCC Contingency Recommen...........�......} 7-6
7.2.15 Project Risks/Opportunities........... ... ........ .......................7-7
............ ...........................
7.3 Opinion of Probable Cost............ „r.........r..... .....................................7-7
8 ENVIRONMENTAL AND
8.1 Introduction ...................
8.2 FERC Preliminary Perri g ......
8.3 FERC Licensing .......................
8.3.1 Project Ma and
8.3.2 Early Lic c ctiv' ' .....
8.3.3 Pre -A I n Doc t, Sch�
8.3.4 Scorii St } 'l Apr v
8.3.5 C En i and
8 3 6 Pre ina mg rop
YSIS'SW VIMARY .......................... 8-1
.......... 8-1
........................................... .
.......%.�...................................................... 8-1
.1.....................................................
8-3
`........................................................
8 3
....................................................................
8 4
Ynd Notice of Intent....................................8-5
..................................................
8-6
iStudies...................................................8-6
8-10
.............................................................................
8.3.7 Develo 7he i License Application.....................................................8-10
8.3.8 Post-FL�ection 401 Water Quality Certification .......................8-14
8.4 Other&SIG
s ? als....................................................................................... 8-15
9 SCHEY..............................................................................................9-1
10 EL BC \1 BILITY REVIEW.........................................................................10-1
11 REGIONAL Wj3`OLESALE UTILITY PLANNING AND DEVELOPMENT .......... 11-1
12 REFER N( ES..................................................................................................................12-1
12.1 Hydrology..................................................................................................................12-1
12.2 Geology.....................................................................................................................12-2
13 Attachments.......................................................................................................................13-1
W H iii November 2010
Kisaralik River and Chikuminuk Lake
Reconnaissance and Preliminary Hydropower Feasibility Study
Table of Contents (continued)
Exhibits
I. Kisaralik Regional Map
2. Kisaralik Location Map
3. Kisaralik Drainage Basin Boundaries
4. Kisaralik Regional Geological Map ,(
5. Chikuminuk Lake Conceptual Project Plan
6. Upper Falls Conceptual Project Plan
. Lower Falls Conceptual Project Plan
8. Golden Gate Falls Conceptual Project Plan 2 e
September 2010 Site Visit Summary Memorand N
Photos` ® C�
® C' O
Q�
YV
Q4
4� 0 �
Go
W H iv November 2010