HomeMy WebLinkAboutKiseralik-Chikuminuk Hydro Progress Report 2011 REF Grant 2195447Progress Report Form
Grantee: Association of Village Council Presidents Regional Housing Authority
Project Name: Kisaralik/Chikuminuk Hydro
Contractor: MWH
Grant #: 2195447
Period of Report: 1-Jan-11 to 28-Jan-11
Project Activities Completed:
Preliminary Review Draft Report Completed and Submitted 'IZ f
Preliminary Results Presented to AVCP RHA, AEA, Calista and others January 26, 2011.
Existing or Potential Problems:
Activities Targeted for Next Reporting Period:
Receipt of regional and wholesale utility planning information from subcontractor
Internal Reviews of Preliminary Review Draft Report %
Receipt of AVCP RHA and AEA comments on the Preliminary Review graft Report
Preparations for Public Meeting in Bethel (tentatively March 9, 2011) l
Support of legislative hearing, if necessary //
Progress Report Form
Grantee: Association of Village Council Presidents Regional Housing Authority
Project Name: Kisaralik/Chikuminuk Hydro
Contractor: MWH
Grant #: 2195447
Period of Report: 29-Jan-11 to 25-Feb-11
Project Activities Completed:
Received regional and wholesale utility planning information from subcontractor
Received Calista and legislative'staff comments on the Preliminary Draft Report
Completed and submitted a Draft Report (second version) to support legislative hearings
Began preparations for March 9th Public Meeting in Bethel
Existing or Potential Problems:
Activities Targeted for Next Reporting Period:
Present findings at March 9th Public Meeting in Bethel
Complete and submit Final Report f
Progress Report Form
Grantee: Association of Village Council Presidents Regional Housing Authority
Project Name: Kisaralik/Chikuminuk Hydro
Contractor: MWH
Grant #: 2195447
Period of Report: 26-Feb-11 to 1-Apr-11
Project Activities Completed:
Presented findings at March 9th Public Meeting in Bethel
Completed and submitted Final Report
Existing or Potential Problems:
Activities Targeted for Next Reporting Period:
No Remaining Tasks