HomeMy WebLinkAboutMcGrath Central Wood Heating Dev Phase III Progress Report 2013 REF Grant 2195403McGrath Central Wood Heating Project Development Phase III Grant Agreement # 2195403 Attachment 2 Progress Report Form Grantee: McGrath Light & Power Company Grant # 2195403 Period of Report: August 2012 - May 2013 Report 21- Final ML&P Finalization of all reports and development of a briefing paper are under way. Completion occurred March 2013. 1. Project Activities Completed: After a review of the incremental difference report between the current heat capture system and adding a biomass boiler system demonstrated that the best financial solution is already in place with heat capture. ML&P has decided to move forward with developing additional information for management to make a future decision regarding the scale of potential biomass heating systems and is interested in exploring possible electrical generation, however this is not part of the current grant. AWEA has developed a suggested path forward for ML&P to follow to develop the information necessary for management to make decisions on the final design. 2. AEA has stated that the funds in the grant cannot be used to even explore potential electrical options for generating electricity from biomass. Thus ML&P has requested AWEA to: Write a brief on all info collected to date for the MTNT and ML&P Boards that include the following: ➢ Review all of the components of a biomass program including harvest, forest management and boiler operations; ➢ Review potential business structures; ➢ Review harvest methodology; ➢ Review Environmental Impacts; ➢ Compare a district heat utility to a biomass power generation system and what potential technologies available today; ➢ Specifically review putting a Garn system in Captain Snow and what that would take and benefits and understanding if this grant can be used to develop a final design for a Garn installation for the City. Project Activities Completed to finalize ML&P project: The following final reports have been prepared and submitted to ML&P: • A Conceptual design and feasibility report with a supplemnt that compares the financial opportunity of the origianal proposed system, the current heat capture system, and the incremental cost benefit of adding a biomass component and increasing the heat loop; • An environmental assessment support document for wood harvesting; Existing or Potential Problems: The ML&P and grant manager intended to retire and thus moved from McGrath. The communication between the City and ML&P did not move forward until April of 2013 when it was decided that the grant would be closed through ML&P due to lack of interest in continuing the project and shifted to the City of McGrath to install a stand alone heating system at the Captain Snow. Little activity on the project occurred from September 2012 till March 2013 when final reports were filed with ML&P. Based on actual inerest from ML&P and restrictions from AEA on electrical analysis, the final reports were limited to EA support Document and a final feasibility and conceptual/schematic design. Activities Targeted: [None remain for ML&P at this time.