QUARTERLY REPORT FOR PERIOD 1ST QUARTER 2023
Activities during this Period:
During the period covered by this report, the following work was completed.
Alaska Department of Fish and Game continued work on Water Supply Creek Hydro.
o ADF&G made a trip to inspect field equipment in March.
EPS began work on Switchgear design.
HDR completed work on 65% design and began work on 95% design.
Permits:
Permits for the construction of this project will include Land use permit from City of Hoonah,
Lease from Sealaska, 404 Permit, Water Rights, and Title 16 permit.
Budget:
The Design costs are expected to be within budget.
Schedule:
The design is running behind schedule slightly. HDR expects to complete 95% design by 3rd quarter
2023.
Deliverables this Period:
The 65% Design was completed.
Activities Planned for Next Period:
Switchgear Design, Mechanical and Civil 95% design and Fish & Game Fish study.