HomeMy WebLinkAboutWater Supply Creek Hydro Construction Progress Report 1ST Quarter 2023 REF Grant 7013010Water Supply Creek Hydro Design Grant # 7013010 QUARTERLY REPORT FOR PERIOD 1ST QUARTER 2023 Activities during this Period: During the period covered by this report, the following work was completed.  Alaska Department of Fish and Game continued work on Water Supply Creek Hydro. o ADF&G made a trip to inspect field equipment in March.  EPS began work on Switchgear design.  HDR completed work on 65% design and began work on 95% design. Permits:  Permits for the construction of this project will include Land use permit from City of Hoonah, Lease from Sealaska, 404 Permit, Water Rights, and Title 16 permit. Budget: The Design costs are expected to be within budget. Schedule: The design is running behind schedule slightly. HDR expects to complete 95% design by 3rd quarter 2023. Deliverables this Period: The 65% Design was completed. Activities Planned for Next Period: Switchgear Design, Mechanical and Civil 95% design and Fish & Game Fish study.