Loading...
HomeMy WebLinkAboutWater Supply Creek Hydro Construction Progress Report 2nd Quarter 2023 REF Grant 7013010Water Supply Creek Hydro Design Grant # 7013010 QUARTERLY REPORT FOR PERIOD 2nd QUARTER 2023 Activities during this Period: During the period covered by this report, the following work was completed.  Alaska Department of Fish and Game continued work on Water Supply Creek Hydro. o ADF&G extended the stream gauging through August to get better low flow data due to a wet summer last year.  EPS continued work on Switchgear design.  HDR completed 95% review design draft in June. o Draft was reviewed and returned to HDR with comments. Permits:  Permits for the construction of this project will include Land use permit from City of Hoonah, Lease from Sealaska, 404 Permit, Water Rights, and Title 16 permit. Budget: The Design costs are expected to be within budget. Schedule: The design is running behind schedule slightly. HDR expects to complete 95% design by 3rd quarter 2023. Deliverables this Period: The 95% Design review was completed, comments were made and submitted to HDR. Activities Planned for Next Period: Switchgear Design & procurement package, Mechanical and Civil final 95% design, turbine procurement package and Fish & Game Fish study.