HomeMy WebLinkAboutWater Supply Creek Hydro Construction Progress Report 2nd Quarter 2023 REF Grant 7013010Water Supply Creek Hydro Design
Grant # 7013010
QUARTERLY REPORT FOR PERIOD 2nd QUARTER 2023
Activities during this Period:
During the period covered by this report, the following work was completed.
Alaska Department of Fish and Game continued work on Water Supply Creek Hydro.
o ADF&G extended the stream gauging through August to get better low flow data
due to a wet summer last year.
EPS continued work on Switchgear design.
HDR completed 95% review design draft in June.
o Draft was reviewed and returned to HDR with comments.
Permits:
Permits for the construction of this project will include Land use permit from City of Hoonah,
Lease from Sealaska, 404 Permit, Water Rights, and Title 16 permit.
Budget:
The Design costs are expected to be within budget.
Schedule:
The design is running behind schedule slightly. HDR expects to complete 95% design by 3rd quarter
2023.
Deliverables this Period:
The 95% Design review was completed, comments were made and submitted to HDR.
Activities Planned for Next Period:
Switchgear Design & procurement package, Mechanical and Civil final 95% design, turbine procurement
package and Fish & Game Fish study.