HomeMy WebLinkAboutWater Supply Creek Hydro Construction Progress Report 3rd Quarter 2023 REF Grant 7013010Water Supply Creek Hydro Design Grant # 7013010 QUARTERLY REPORT FOR PERIOD 3rd QUARTER 2023 Activities during this Period: During the period covered by this report, the following work was completed.  Alaska Department of Fish and Game completed work on Water Supply Creek and issued the Title 16 Permit in September.  EPS continued work on Switchgear design.  HDR completed 95% design and turbine procurement package in August.  The City of Hoonah issued a Conditional Use Permit for Water Supply Creek Hydro in September. Permits:  Permits for the construction of this project will include Land use permit from City of Hoonah, Lease from Sealaska, 404 Permit, Water Rights, and Title 16 permit. Budget: The Design costs are expected to be within budget. Schedule: The design is running behind schedule slightly. EPS Expects to be complete with the Switchgear Design by the end of fourth quarter 2023 Deliverables this Period: The 95% Design & turbine procurement package was completed, Alaska Fish & Game Title 16 Permit was received and the City of Hoonah issued their Conditional Use Permit for Water Supply Creek Hydro. Activities Planned for Next Period: Switchgear Design & procurement package.