HomeMy WebLinkAboutWater Supply Creek Hydro Construction Progress Report 3rd Quarter 2023 REF Grant 7013010Water Supply Creek Hydro Design
Grant # 7013010
QUARTERLY REPORT FOR PERIOD 3rd QUARTER 2023
Activities during this Period:
During the period covered by this report, the following work was completed.
Alaska Department of Fish and Game completed work on Water Supply Creek and issued the
Title 16 Permit in September.
EPS continued work on Switchgear design.
HDR completed 95% design and turbine procurement package in August.
The City of Hoonah issued a Conditional Use Permit for Water Supply Creek Hydro in
September.
Permits:
Permits for the construction of this project will include Land use permit from City of Hoonah,
Lease from Sealaska, 404 Permit, Water Rights, and Title 16 permit.
Budget:
The Design costs are expected to be within budget.
Schedule:
The design is running behind schedule slightly. EPS Expects to be complete with the Switchgear Design
by the end of fourth quarter 2023
Deliverables this Period:
The 95% Design & turbine procurement package was completed, Alaska Fish & Game Title 16 Permit was
received and the City of Hoonah issued their Conditional Use Permit for Water Supply Creek Hydro.
Activities Planned for Next Period:
Switchgear Design & procurement package.