HomeMy WebLinkAboutTok Wood Heating Construction -Biomass Progress Report 2011 REF Grant 2195417PROGRESS REPORT FORM GRANTEE: Alaska Gateway School District PROJECT NAME: Biomass Boiler Building and Related Mechanical and Electrical Integration GRANT* 2195417 Period of Report: October - November, 2011 Overview: All construction work relative to the biomass building is complete. Focus during this period is revamping of the heat -exchanger system to accommodate steam to glycol transfer of heat, recalibrate digital controls to a steam configuration, and to address final punch -list items remaining from General Contractor Project Activities Com leted: Phase I: Reconnaissance • Completed. Phase II: Feasibility • Completed. Phase III -Final Design • Design Development Completed • Construction Documents Completed • Construction Bid Process Completed • Construction Bid Negotiations Complete • Shop drawings, Submittals Complete Phase IV Construction • All site work is complete • All sprinkler work is complete • All electrical work is complete • All control work is complete • All mechanical work is complete • All of equipment installation and operation is complete • Final inspection complete, punch list is complete • Controls commissioning complete • O&Ms from GC complete • Refractory modification complete and successful • Open house complete • Received O&M from Messersmith • Received Commissioning report from CTA • Installation of heat exchanger for steam glycol conversion taking place. • Upgrading of the auger feed system from a single auger to a double counter - rotating auger. Existing or Potential Problems: • Reprograming for steam operation • Review and upgrade operations manual to steam operation, including turn -up and turn -down sequencing protocols • Set up wood acquisition protocols for local venders • Evaluate counter rotating auger for feed capacity Activities Targeted for Next Reporting Period: • Quantify combustion rates based on steam generation 7 Signed�— Position: Project Manager Date