January 19, 2021
Senate Secretary Chief Clerk
President of the Senate Speaker of the House
Alaska State Legislature Alaska State Legislature
State Capitol Room 211 Thomas Stewart Building, Room 202
Juneau, AK 99801 Juneau, AK 99801
Dear Senate President and Speaker of the House:
As required by Alaska Statute 44.83.085, the Alaska Energy Authority (AEA) provides an update
to the Legislature on the status of the Susitna-Watana Hydroelectric Project each year. Along
with this letter a copy of the 2018 annual report is appended.
On December 26, 2014, the project was halted by Administrative Order (AO) 271 to come to a
complete stop by the end of the calendar year 2017. AEA closed out the project yet preserved
the value of the State of Alaska's investment and maintained the public value of the data
collected through careful, thorough archiving. The Federal Energy Regulatory Commission’s
(FERC) updated Study Plan Determination (SPD) provides the State with certainty on what is
needed for a complete FERC license application if the project is restarted.
With its SPD, FERC reaffirmed the scope of studies necessary for determining impact assessment
and developing protection, mitigation, and enhancement measures. FERC validated the quality
and integrity of work completed to date. To the extent which the project proposal does not
change and the data gathered does not become stale or non-representative of baseline
conditions, FERC ruled AEA would not need to repeat the already-completed Integrated
Licensing Process steps. If restarted, FERC may require additional scoping and/or modifications
to the approved SPD.
The current status of the project is as follows:
Engineering – The completed engineering feasibility report contains the information
necessary for a license application and demonstrates the project is technically feasible.
Economics – The benefit-cost and economic impact analysis concluded that if constructed,
the project would generate billions of dollars in energy savings for the Railbelt and would
provide significant long-term benefit to the economy.
Financing – AEA investigated various financing models, some of which resulted in an
estimated $0.066/kilowatt hour 50-year average real price in 2014 dollars.
Licensing – AEA is approximately two-thirds into the Integrated Licensing Process. Had the
project not been shut down following FERC's issuance of the updated SPD in June 2017, the
next steps would have been the implementation of the second study season, followed by
preparation of final reports and a license application.
On February 22, 2019, Governor Dunleavy issued AO No. 309 rescinding, amongst others, AO
No. 271, which resulted in the removal of the fiscal restraint previously ordered. This order has
not changed the status of the project. At the request of the Legislature on February 11, 2020,
AEA presented an overview of the Susitna-Watana project to the Senate Community and
Regional Affairs Committee (copy provided). The data presented in this presentation to the
Legislature was before 2017. AEA has spent no further state funds during Fiscal Year 2020.
AEA is proud of the work completed to advance the Susitna-Watana Hydroelectric Project. The
effort has yielded significant benefits in terms of knowledge produced and shared, and an
understanding of this resource potential to offer stable, low-cost power to Alaskans over the
100-year life of the project upon completion.
Respectfully Submitted,
Curtis W. Thayer
Executive Director
Cc: Alaska Energy Authority Board
Alaska State Legislature
REPORT TO THE
LEGISLATURE
2018
1 SUSITNA-WATANA HYDRO REPORT
TABLE OF CONTENTS
Letter from the Executive Director ................................................................................................................. 2
Status Summary ............................................................................................................................................. 3
History ............................................................................................................................................................ 4
Engineering .................................................................................................................................................... 5
Economics ...................................................................................................................................................... 6
Financing ........................................................................................................................................................ 7
Licensing ......................................................................................................................................................... 8
Summary of Project Funding ........................................................................................................................ 14
Susitna-Watana Hydro at a Glance
Licensing efforts started: 2011
Location: River mile 184, above Devils Canyon
Size: 705-foot-high dam
Reservoir: ~42 miles long, average width of 1.25
miles
Estimated Supply: About 50 percent of Railbelt
electrical demand
Estimated Cost: $5.655 billion (2014$)
Installed Capacity: 459 MW
Annual Energy: 2,800,000 MWh
Licensing: Federal Energy Regulatory
Commission (FERC)
Anticipated Project Life: 100+ years, providing
long-term, stable rates
Project closed down: 2016-2017
SUSITNA-WATANA HYDRO REPORT 2
3 SUSITNA-WATANA HYDRO REPORT
SUSITNA -WATANA HYDRO PROJECT
STATUS SUMMARY
By the end of 2017 the project
was completely shut-down per
Governor Walker’s June 2016
directive.
FERC issued its Study Plan
Determination (SPD) June 22,
2017, followed by a licensing
abeyance.
The favorable FERC SPD,
licensing abeyance, and careful
cataloguing of research, data,
and reporting, will preserve the
State’s investment.
The unobligated balance of
$1.893 million was returned to
the general fund in FY2019.
SUSITNA-WATANA HYDRO REPORT 4
Project History
The hydroelectric potential of the Susitna River has been studied since the early 1950s. The first study was completed by
the U.S. Bureau of Reclamation and subsequent reviews were completed by the U.S. Army Corps of Engineers in the
1970s. Many Alaskans remember the efforts of the Alaska Power Authority (APA)—now the Alaska Energy Authority—to
develop a two-dam project on the Susitna River in the 1980s.
At that time, the APA submitted a license application to FERC in
1983 for the Watana-Devils Canyon Project on the Susitna River.
The license application was withdrawn in 1986, largely due to the
relatively low cost of gas-fired electricity in the Railbelt and the
declining price of oil throughout the 1980s and its impact on the
State budget. The APA concluded that the project’s
environmental impacts could be mitigated, but the project was
not financially feasible at that time.
In 2011, recognizing the potential of a hydroelectric project on
the Susitna River as a solution to the continued need for long-
term, stable sources of energy, the Alaska Legislature authorized
and funded the Alaska Energy Authority (AEA) to once again
explore project feasibility and move through the FERC licensing
process.
Over the last six years, AEA completed data gap analyses, building
on the quality data from the 1980s, and completed several
important milestones in the FERC Integrated Licensing Process.
AEA’s studies have shown the project is technically, and
economically feasible. The 459-megawatt project would be
capable of producing 2,800 gigawatt hours of energy annually, or
about half of the Railbelt’s energy needs.
With the updated FERC Study Plan Determination (SPD) issued in
June 2017, the final licensing milestone in this 2011-2017 period
was reached. State budget challenges prompted Governor
Walker, in June 2016, to call for the project to be shut down,
though in such a way as to ensure preservation of the State’s
investment made to-date. The updated SPD and licensing
abeyance, followed by completion of final reporting and archiving
of all project information, has done just that. All project activity
has ceased.
5 SUSITNA-WATANA HYDRO REPORT
In January 2015, AEA completed the Susitna-Watana Hydro Engineering Feasibility Report, concluding the majority of
engineering work necessary to file for a FERC hydropower license. This effort is the result of several years of
collaboration among engineering contractors, dam-safety experts, utilities, FERC and AEA to design a safe and cost-
effective project, as well as the results from: drilling and geotechnical investigations to test the quality of rock and
measure bedrock for a solid foundation; studies and modeling for maximum probable flood and seismic events; and
modeling to simulate the projected electrical generation to meet Railbelt demand.
The report is a critical milestone and concludes that the project is technically feasible. Noteworthy conclusions are
summarized below.
SAFETY
Active faults have not been found within the dam site. Drilling conducted during the summer of 2014 confirmed that
there is no “Watana lineament” along the Susitna River channel, supporting results from investigations conducted
during the 1980s licensing effort. In addition, the Alaska Division of Geological and Geophysical Surveys (DGGS)
conducted extensive geologic mapping in the Talkeetna Mountains and found no active faults directly in the project
area. In addition, the current dam design, once constructed, would be able to withstand a 50-year flood without having
to open spillway gates and would pass the 10,000-year flood with one spillway gate inoperable.
DESIGN
The structure is designed as a curved gravity dam, constructed using Roller Compacted Concrete (RCC) methodology
with a straight gravity (thrust) section on each abutment. The height of the dam has been optimized to 705 feet above
bedrock, lowered from approximately 730 feet. The nominal crest elevation is 2,065 feet and the crest length is
approximately 2,810 feet. The reservoir would be approximately 42-miles long with an average width of 1.25 miles.
AEA worked with the Railbelt utilities to ensure that the generators are appropriately sized for Railbelt demand,
modeling potential operations and integrating into the Railbelt system to ensure maximum long-term benefits to the
Railbelt. As part of this effort, the overall nominal capacity rating of the three proposed turbines has been reduced to
459 megawatts while maintaining the same energy output of 2,800 gigawatt hours of annual power, or 50 percent of the
Railbelt’s current demand.
The potential access and transmission routes were narrowed down to two alternative north-south routes that extend
from the Denali Highway and the Gold Creek Route that runs east-west and would connect with the Alaska Railroad
(unconnected to the state highway system).
COST
The anticipated project cost is estimated to be $5.65 billion (2014$ and based on oil prices at $105 per barrel), including
licensing, design and construction, but excluding escalation and interest during construction.
Engineering & Safety Milestones
SUSITNA-WATANA HYDRO REPORT 6
To understand the potential economic impacts from licensing, constructing and operating the Susitna-Watana Hydro
and future workforce needs, AEA worked with Northern Economics on the Benefit-Cost and Economic Impact Analysis.
The report, published in March 2015, concluded that, if constructed, the project would generate billions of dollars in
energy savings for the Railbelt and would be a significant, long-term benefit to the economy.
Based on the 2014 projection of natural gas prices,
the analysis estimated a total energy savings of $11.2
billion (2014$) during the first 50 years of the project,
an annual average of nearly $225 million. When
additional benefits of the dam were factored in,
including the retirement of older generation facilities,
reduction in greenhouse gas emissions and a
reduction in the frequency of power outages, the
energy cost savings surpassed $14 billion. The
benefit-cost ratio from the energy savings and
retirement of older, unneeded generation facilities alone is 2.46.
Construction of the Susitna-Watana Hydro Project would also provide thousands of direct and indirect jobs for many
decades. The
project would
support an average
of approximately
200 non-
construction jobs
annually during
both pre-
construction and
construction phases
as well as an annual
construction
workforce of
approximately
1,200 people during
construction of the
project.
In addition, Susitna-Watana Hydro would generate more than $800 million (2014$) in local spending pre-construction
and a projected $2.6 billion (2014$) in local spending during construction. During operation of the project, an estimated
$26.5 million (2014$) would be spent annually for operations, boosting local and regional economies.
Economic Milestones
Project
Spending
Category
Local
Spending
(million $)
Multiplier Effects
Business
Sales
(million $) Jobs
Labor
Income
(million $)
Licensing/Design;
Other Program
Costs
814.1 551.2 3,870 204.3
Construction 2,658.5 1,837.1 11,305 627.3
Operation 26.5 18.5 105 6.4
Table uses 2014 dollars
7 SUSITNA-WATANA HYDRO REPORT
In 2014, AEA worked with PFM, an international financial advisory firm, to develop financing models for Susitna-Watana
Hydro. AEA received confirmation that Rural Utilities Service (RUS), a division of the U.S. Department of Agriculture that
provides low-cost financing for infrastructure improvements, could provide financing for 50 percent of the project costs.
AEA and PFM developed scenarios that included combinations of state investment, bonds and federal financing
programs (RUS) and private financing. In developing the scenarios, AEA kept three goals in mind: 1) provide affordable
power to Alaskans, 2) protect investments made by the State of Alaska and 3) investigate ways that the State would be
repaid its initial investment.
The combination of AEA Revenue Bonds (30 years, 5% interest, refinanced) and RUS financing the remainder of
construction (35 years, 4% interest) resulted in a $0.066/kWh 50-year average real price (2014$).
Financing Milestones
SUSITNA-WATANA HYDRO REPORT 8
Following authorization in 2011 to advance the Susitna-Watana Hydroelectric Project, AEA pursued a FERC license
application through the Integrated Licensing Process (ILP), FERC’s default licensing process. The ILP is a front-loaded,
iterative, milestone-driven process that provides a defined structure, including timeframes for licensing activities, study
plan development, formal study plan determination, reporting on study implementation, stakeholder engagement and
early National Environmental Policy Act (NEPA) scoping.
Final licensing activities between 2016 and 2017 effectively wrapped up the project as per Governor Walker’s June 2016
directive. Following FERC’s Study Plan Determination, issued in June 2017, the project was put into abeyance, allowing
the State to preserve the investment already made, and no further movement toward licensing is planned at this time.
Licensing Milestones & Timeline
Page 1 of the 254 page FERC Study Plan Determination.
The full document is available at www.ferc.gov.
9 SUSITNA-WATANA HYDRO REPORT
Between 2011 and 2017 AEA
moved the Susitna-Watana
Hydro project through step 14,
approximately two-thirds of the
way through the ILP process.
Had the project not been shut
down, following the SPD
issuance in June 2017, next
steps for the project would
have been implementation of
the second study season;
preparation of the Updated
Study Reports; impact
assessment; preparation of the
Draft License Application;
development of protection,
mitigation and enhancement
measures; and preparation of
the Final License Application.
FERC Integrated Licensing Process (ILP)
SUSITNA-WATANA HYDRO REPORT 10
2011 AEA reviewed existing information, identified potential natural resource issues, performed data gap
analyses and held preliminary discussions with agencies, Alaska Native entities and other
stakeholders.
In October, AEA filed the Preliminary Permit Application (PPA) with FERC, which provided AEA priority
status for licensing the project. The Integrated Licensing Process (ILP) was initiated with AEA filing the
Notice of Intent (NOI) and the Preliminary Application Document (PAD) at the end of the year.
2012 Public scoping meetings were held in Anchorage, Wasilla, Glennallen, Talkeetna, Cantwell and
Fairbanks.
AEA jumpstarted the licensing process by initiating 18 studies designed to gather critical
environmental data, and to help inform the scope and methods of the proposed licensing studies.
A significant amount of the 2012 licensing effort was spent developing the study plan with
stakeholders for FERC’s approval. The study plan is a key part of the licensing process and outlines the
studies that will be conducted to provide a better understanding of the Susitna Basin to assess
potential impacts and develop protection, mitigation and enhancement measures.
AEA performed extensive public outreach with resource agencies, Alaska Native entities, non-
governmental organizations and other stakeholders, holding 34 days of technical meetings to develop
the study plan.
The Proposed Study Plan, consisting of 58 studies, was submitted to FERC in July. Following further
collaboration with stakeholders, AEA submitted an Interim Revised Study Plan and finally, in
December, a Revised Study Plan to FERC for approval.
2013 With a Study Plan Determination (SPD), FERC approved the Susitna-Watana Hydro Environmental
Study Plan, which included 58 studies in resource areas such as geology and soils, water quality,
geomorphology, groundwater, ice processes, instream flow, fish and aquatic, wildlife, botany,
recreation, cultural, subsistence, socioeconomics, transportation, and safety. AEA consulted with
stakeholders and prepared and provided all supplemental information as ordered by FERC in its SPD.
AEA filed 29 technical reports summarizing results from the 2012 studies and commenced the
implementation of the Susitna-Watana Hydro Study Plan, an unprecedented environmental study of
the Susitna Basin, with an estimated 350 biologists, engineers, hydrologists, archeologists, and
scientists of many other disciplines in the field gathering data.
AEA held 22 days of technical meetings from June through December 2013, keeping licensing
participants up-to-date on the results of the 2012 studies and the licensing studies as they were being
implemented.
Licensing activities and all documents were made publicly available via the project website and more
than 100 public meetings and presentations about Susitna-Watana Hydro were held, demonstrating
the commitment of an open, accurate and collaborative approach to managing stakeholder
expectations.
Susitna-Watana Licensing Activities 2011-2017
11 SUSITNA-WATANA HYDRO REPORT
2014 An important milestone in the FERC ILP is the Initial Study Report (ISR), which serves as a progress
report on the implementation of each of the 58 studies and accounts for any variances from the
approved plan; describes plans and schedule for the second year of study; and describes AEA’s
proposed modifications of the FERC-approved plan. As part of the Initial Study Report process, a
series of meetings are held to discuss the findings and requested modifications, by both AEA and
other stakeholders, in order to lead to an updated Study Plan Determination by FERC.
However, budgetary constraints precluded AEA from being able to provide a schedule for completing
the second year of study and finalizing AEA’s proposed modifications to the Study Plan. Accordingly,
AEA adhered to the existing FERC ILP schedule at the time, and filed a Draft ISR in February, which
described the 2013 implementation of the FERC-approved Study Plan and any variances and
presented results. Once the FY15 capital budget was approved, AEA was able to prepare and file the
8,600-page Final ISR in June, which included AEA’s proposed study modifications and plans to
complete the second year of study for each of the 58 studies, per the FERC regulations. In October,
AEA held 6 days of ISR Meetings with stakeholders to review the ISR.
AEA reached a critical land-access agreement in spring 2014 with Cook Inlet Region Inc. and six Cook
Inlet village corporations (CIRWG) to allow AEA access to land in order to further Susitna-Watana
Hydro environmental studies.
2014 marked another year of intensive and specific research involving more than 200 field scientists.
Data collection efforts were prioritized based on the level of funding received, relative importance of
the study, sequencing of interrelated studies, and need for continuous data collection with the goals
of preserving the value of the work completed to date and maintaining as tight a licensing timeline as
possible. Prior to initiating field work, AEA held 12 days of technical meetings with stakeholders to
describe AEA’s plan for 2014 activities and to consult with resource agencies on AEA’s proposed
modifications to the FERC-approved Study Plan.
By the end of the 2014 season, data collection was completed for 13 of the FERC-approved studies.
AEA filed 33 technical memoranda describing 2014 study implementation, proposed study
modifications for consideration in FERC’s updated Study Plan Determination, or additional
information as requested during the October ISR Meetings.
In addition to technical meetings, AEA presented information gathered as part of the environmental
field effort and provided updates on the licensing status during regular meetings with CIRWG; public
meetings in the communities of Wasilla, Fairbanks, Glennallen, Kenai, Anchorage and Talkeetna; and
to numerous professional groups, associations and NGOs.
2015 Administrative Order 271, issued by Gov. Walker in December 2014, halted discretionary spending on
the Susitna-Watana Hydro Project, and to comply, AEA essentially pressed pause in the midst of the
Initial Study Report process in early 2015. FERC granted AEA an abeyance from the licensing process.
AEA received clarification on discretionary spending from the Office of Management and Budget
director in July 2015 and was notified that the project was to use existing funds to advance to the
next licensing milestone, the FERC Study Plan Determination.
In August, AEA filed a request with FERC to lift the licensing abeyance and to submit additional Initial
Study Reports covering all work completed to-date for consideration in FERC’s updated Study Plan
Determination, and proposed a new schedule. AEA’s plan was supported by members of CIRWG,
Railbelt utilities, the Alaska Department of Fish and Game, Alaska Department of Natural Resources,
and the Alaska Ratepayers.
SUSITNA-WATANA HYDRO REPORT 12
Following public comments, FERC ultimately ordered that the vast amount of material filed from 2013
through 2015 in the form of numerous technical memoranda and Initial Study Reports met the ILP
requirements for the Initial Study Report and that AEA satisfactorily provided a roadmap linking the
reports for each study; and therefore, the reports would collectively be considered the Initial Study
Report for purposes of the ILP and FERC’s Study Plan Determination.
The 2015 study implementation was limited to finishing studies near completion; continuing surveys
of collared moose, caribou and other animals; completing analysis of data already gathered; and
removing field equipment installations where possible.
At the end of 2015, AEA filed more than 8,000 pages of reports summarizing implementation of the
FERC-approved Study Plan during 2014 and 2015 in the form of Study Completion Reports for studies
that had been completed or 2014-2015 Study Implementation Reports for incomplete studies. AEA
also filed an Initial Study Report for each of the 58 studies, summarizing the status of implementation,
all variances and AEA’s proposed modifications to the Study Plan, and referencing/linking all related
documents.
2016 The project emphasis in 2016 was to advance the licensing process to FERC’s updated Study Plan
Determination and shut down the project while preserving the State’s investment thus far.
In March, AEA held 5 days of Initial Study Report meetings with FERC and stakeholders, reviewing all
of the technical memoranda and Initial Study Reports filed by AEA between 2013 and 2015 for each of
the 58 studies, describing implementation of the FERC-approved Study Plan, any variances, AEA’s
proposed modifications, and steps to complete each study.
In the next step of the ILP, stakeholders may file with FERC comments on the Initial Study Reports and
can make recommendations for modifications to the FERC-approved Study Plan or request new
studies. In June, nearly 1,600 pages of comments and recommendations for modifications to the
Study Plan or requests for new studies were filed with FERC. Of note, the State of Alaska resource
agencies supported the FERC-approved Study Plan, AEA’s implementation of the Study Plan and AEA’s
proposed modifications to the Study Plan.
AEA responded to all commenters and on October 24, 2016 filed over 1,000 pages refuting nearly all
of the Study Plan modifications and new study requests. The vast majority of the comments were
either not appropriate at the ISR stage of the ILP or the requests did not meet the regulatory criteria
for modification to the existing Study Plan or for new studies. For example, some modification
requests were simply to complete the FERC-approved Study Plan. Other recommendations had been
previously submitted to FERC during the 2012 study planning phase and FERC had already ruled in its
2013 determination that the requests were beyond what is necessary to evaluate project effects and
develop FERC license conditions. Some recommended modifications would be extensive and costly,
such as expanding studies downstream to Cook Inlet, extending the number of years of study, and
modeling climate change to be considered as a future without-project scenario for impact
assessment. The estimated cost of implementing all of the modifications and new studies requested
by stakeholders would add between $260 million and $370 million to the cost of completing the
environmental studies in the ILP process. AEA presented substantial evidence that these Study Plan
modifications were unnecessary to support a license application.
Data collection in 2016 was limited to ice thickness and water surface elevation to fill data gaps for
the ice processes model; final aerial surveys of collared moose, caribou and ptarmigan and aquatic
furbearers to finish those nearly complete studies; and final data acquisition and
maintenance/removal of hydrology equipment installations to support project shutdown. Analysis
and final reporting of data already gathered continued during 2016.
13 SUSITNA-WATANA HYDRO REPORT
All field equipment installations were removed from the field or transferred to other State agencies
by October 2016. Removal of equipment adhered to all relevant permits, and where applicable, sites
were restored to pre-installation conditions. Permit close-out reports were submitted for 16 of the 23
permits.
2017 FERC reviewed the ISR, stakeholders’ comments to the ISR and AEA’s responses and issued an
updated Study Plan Determination (SPD) on June 22, 2017. FERC overwhelmingly endorsed the
previously approved Study Plan, with minor modifications to 16 of the 58 studies, many of which were
proposed by AEA. FERC did not adopt any of the study modifications as requested by stakeholders
and rejected each of the four new study requests. Of note, FERC rejected nearly all of the
recommendations to expand numerous studies farther downstream into the lower river. FERC
rejected recommendations to add more years of data collection, agreeing with AEA’s analysis showing
that 2012 - 2015 environmental conditions were within the normal range of environmental variation.
FERC also rejected recommendations for a comprehensive climate change study of the entire Susitna
basin, endorsing AEA’s proposed approach that capitalizes on FERC’s conventional hydrological
approach, the hydrologic climate change study conducted by DGGS for AEA in the upper Susitna basin
above the proposed dam site, and an assessment of future trends based on planned sensitivity
analyses and common sense.
By the end of calendar year 2017, all work on the Susitna-Watana Hydro Project had come to a full
stop. Permit close-out reports were submitted for all field permits. All equipment was inventoried and
stored at the AEA warehouse or transferred to other State agencies. All contracts were terminated. To
preserve the value of the State’s investment and provide the data in the most usable format for
future licensing, as well as for resource managers, researchers, developers of other projects, and the
public, analysis and final reporting of data already gathered was completed. Final reporting was
completed for 8 FERC-approved wildlife and botanical studies, including those conducted by ADF&G
(i.e., moose, caribou, and ptarmigan). Calibration and validation reports were prepared for each of
the riverine physical process models, as well as a model integration report, to support the feasibility
of the approach in the FERC-approved Study Plan for assessing project impacts and developing
protection, mitigation and enhancement measures. All research and data was catalogued and stored
in publicly accessible databases on AEA’s project website, ARLIS and GINA.
FERC’s SPD provides the State with certainty on what is needed to file a defensible FERC license
application should the project be restarted. With its SPD, FERC reaffirmed the scope of studies
necessary for determining impact assessment and developing protection, mitigation and
enhancement measures, and FERC validated the quality and integrity of work completed to date.
As requested by Governor Walker in his August 4, 2016 letter to FERC, the licensing process was put
into abeyance following FERC’s SPD. To restart the project, FERC will need a firm commitment from
the State to pursue a license. Of the 58 studies, 19 have been completed as required by FERC and
significant progress has been made in completing the remaining 39 studies. To the extent the project
proposal does not change and the data gathered does not become stale, FERC ruled that AEA would
not need to repeat the already-completed ILP steps. If restarted, FERC may require additional scoping
and/or modifications to the approved Study Plan.
2018 No work was done on the Susitna-Watana Hydro Project in calendar year 2018.
SUSITNA-WATANA HYDRO REPORT 14
Below is a summary of project funding as of October 9, 2018 ($ in thousands)
Authorized Funds - State of Alaska Appropriations
FY2009 $1,528.1
FY2011 $9,644.8
FY2012 $65,700.0
FY2014 $95,200.0
FY2015 $20,000.0
Total Authorized Funds - State of Alaska Appropriations $192,072.9
Expenditures to Date, Encumbered and Committed Funds ($190,179.9)
Funds returned to the State General Fund in FY2019 $1,893.0
Balance of Authorized Funds $0.0
Summary of Project Funding
Information about the Susitna-Watana Hydroelectric Project is archived and publicly available via the following:
www.susitna-watanahydro.org
www.gis.suhydro.org
www.arlis.org/susitnadocfinder/
This publication of the Susitna-Watana Hydroelectric Project status and financial condition is submitted by AEA in
accordance to AS 44.83.085. This document was designed and created in-house and distributed in electronic format.