2013 Legislature TPS Report 60279v2
$312,
0
0
0
Appro
v
e
d
Agency: Commerce, Community and Economic Development
Grants to Municipalities (AS 37.05.315)
Federal Tax ID: 92-0048310Grant Recipient: Tenakee Springs
Project Title:Project Type: New Construction and Land Acquisition
Tenakee Springs - Indian River Hydroelectric Project
State Funding Requested: $312,000 House District: Juneau Areawide (31-32)
One-Time Need
Brief Project Description:
Construct a new 180 kilowatt run-of-river hydroelectric project on Indian River approximately one mile
east of Tenakee Springs. The hydro project will supply approximately 90% of the city's electricity,
reducing diesel use by 31,400 gallons annually and lowering electric rates to residents and businesses.
Funding Plan:
Total Project Cost: $3,674,000
Funding Already Secured: ($354,000)
FY2014 State Funding Request: ($312,000)
Project Deficit: $3,008,000
Funding Details:
2009 - $100,000 Denali Commission grant plus $25,000 city funds for feasibility study and to start permitting.
2011 - $203,000 Round 4 Renewable Energy Grant Program and $26,000 city funds to complete permitting and final design.
2013 - Applied for $2,988,000 in construction funds from Round 6 Renewable Energy Grant Program. AEA recommended full funding
(AEA ranked this project #1 state-wide). The city has also committed $20,000 as in-kind services for the project.
Detailed Project Description and Justification:
A hydroelectric project at Indian River was first studied in the early 1980s, and a city-funded feasibility study was completed
in 1993. At the time, the city did not further pursue the hydro project due to the affordability of diesel fuel. In 2008, the city
decided to pursue the hydro project to escape spiraling fuel and electricity costs. Since then, the city has completed a new
feasibility study, conceptual designs, and will have final designs and all permits for the project in place by April 2013. The
131-person community has spent $51,000 and committed $20,000 more to the project.
The run-of-river hydro project will divert up to 50 cubic feet per second (cfs) from Indian River above waterfall #4 at a
headwater elevation of 121 feet. The water will be conveyed to the powerhouse via a 1,550 foot long 36-inch penstock.
The powerhouse will be located below waterfall #2 with a tailwater elevation of 58 feet for a gross operating head of 63 feet
and net head of 56 feet. The rated capacity of the turbine-generator set will be 180 kW. Electricity will be transmitted to
Tenakee Springs via a 4,200 foot long mostly underground three phase 7.2 kV power line. The power line will connect to
the existing distribution system near the small boat harbor.
The hydro project is co-located with a series of fish passes the U.S. Forest Service (USFS) built in Indian River over the
past 15 years to establish a Coho run. The city worked closely with the USFS and Alaska Department of Fish and Game
(ADFG) to design the hydro so it is compatible with the fishery. The city designed the hydro diversion structure to enhance
For use by Co-chair Staff Only:
Page 1
Contact Name: Hannah McCarty
Contact Number: 465-4766
2:02 PM 5/9/2013
Total Project Snapshot Report
2013 Legislature TPS Report 60279v2
function of the existing fish pass at waterfall #4. The hydro project will maintain in-stream flows in Indian River for fish
migration through the bypass reach.
The hydro project will supply approximately 90% of the community's electricity, displacing approximately 31,400 gallons of
fuel annually. The existing diesel power plant, upgraded in 2006, will supplement the hydro during low water periods. The
hydro project will also provide a significant amount of excess energy that is available for space heating and/or load growth.
Space heating of community buildings can displace an additional 6,500+ gallons of heating fuel annually. This project will
lower electric rates from current 50 to 60 cents per kilowatt-hour (kwh) down to 20 to 30 cents per kWh. This will encourage
economic development in the community, boosting local residency and sustainability by making the community a more
affordable and better place to live, work and raise families.
Project Timeline:
2013 - Construct trails and access roads for project. Order long-lead equipment (turbine, generator, etc.)
2014 - Complete balance of construction. Includes diversion structure, 1,550-foot penstock, powerhouse, 4,200 foot power
line extension.
Operational date is fall 2014.
Entity Responsible for the Ongoing Operation and Maintenance of this Project:
City of Tenakee Springs Electric Department.
Grant Recipient Contact Information:
Name:Don Pegues
Title:Mayor (ex-officio)
Address:W. Tenakee Trail (PO Box 52)
Tenakee Springs, Alaska 99841
Phone Number:(907)736-2207
Email:citytke@gmail.com
Has this project been through a public review process at the local level and is it a community priority?X Yes No
For use by Co-chair Staff Only:
Page 2
Contact Name: Hannah McCarty
Contact Number: 465-4766
2:02 PM 5/9/2013
City of Tenakee Springs
Indian River Hydroelectric Project
Project Summary Polarconsult Alaska, Inc.
January 2013 1
PROJECT SUMMARY
The City of Tenakee Springs is developing a 180-kW run-of-river hydro project at Indian River,
approximately one mile east of the City. The hydro project will meet 86.2% of the City’s current
electric demand, significantly reducing the community’s fuel consumption and lowering electric
rates in the community.
A hydroelectric project at Indian River was first studied in the 1980s and 1990s, but it was not
pursued because of the availability of affordable diesel for electrical power generation.
Increasing diesel costs forced the City to reconsider the project in recent years. A new
feasibility study was completed in 2009, indicating the project was technically, environmentally,
and economically feasible. Since then, the City has nearly completed permitting for the project,
and will have all permits in place and final construction plans ready for the 2013 construction
season. Contingent upon receipt of necessary funding, the City plans to construct access roads
and trails to the project site in 2013, and construct the balance of the project in 2014.
Work on this project has been funded through a combination of city, state, and federal funds,
as well as in-kind labor and services contributed by community members.
● The feasibility study, conceptual design, and initial permitting was funded by a $100,000
Denali Commission grant and $25,000 in city funds. The grant was managed by the Alaska
Energy Authority (AEA).
● Final permitting and design is funded by a $203,000 state grant (Round 4 Renewable Energy
Grant Program [RE Program]) and $26,000 in city funds.
● The estimated construction cost of the hydro project is $3,320,000. The City applied for a
$2,988,000 grant for project construction in Round 6 of the RE Program, with $332,000 in
matching funds. The AEA has recommended the construction grant for full funding, and
ranked the project #1 state-wide.
● The City is requesting a $312,000 municipal grant to provide the matching funds for the
City’s pending RE Program grant application.
Technical data for the hydro project is summarized in Table 1, and current permitting status is
summarized in Table 2. Figure 1 shows the project area and layout.
City of Tenakee Springs
Indian River Hydroelectric Project
Project Summary Polarconsult Alaska, Inc.
January 2013 2
Table 1: Summary of Project Technical Data
Major permit applications for the project were filed in August 2010, and most major permits
have been issued. Issuance of outstanding permits is expected in early 2013. The current
status of major permits for the project are tabulated below.
Project maps and photographs of the project site are included on the following pages.
INDIAN RIVER HYDROELECTRIC PROJECT SUMMARY
Static Head 63 feet
Design Flow 50 cubic feet per second
Penstock 1,534' of 36" Pipe
Total Dynamic Head 56 feet
Turbine Type Cross-flow Turbine
Installed Capacity 180 kW
Plant Capacity Factor 76.2%
Estimated Annual Hydroelectric Energy Generation 1,169,000 kWh
Existing Typical Annual Utility Energy Demand 433,000 kWh
Percent of Utility Load Supplied by Hydro 86.2%
Transmission
4,014 feet of
Three-phase 7.2kV buried
cable
Pre-Construction Costs $ 354,000
Estimated Direct Construction Cost $2,560,000
Estimated Construction Engineering, Administration, Management $ 320,000
Contingency (15%) $ 440,000
Estimated Total Installed Cost $3,674,000
Annual Displaced Diesel Fuel for Utility 31,400 gallons
Continuing Annual Diesel Consumption for Electrical Generation 3,500 gallons
Annual Displaced Fuel for Heating Applications 6,500 gallons
Net Present Value of Displaced Fuel & Project Benefits $5,090,000
Net Present Value of Project Capital and Annual Costs $3,180,000
Benefit – Cost Ratio
Calculated with 2012 AEA Renewable Energy Financial Model 1.60
City of Tenakee Springs
Indian River Hydroelectric Project
Project Summary Polarconsult Alaska, Inc.
January 2013 3
Table 2: Status of Project Permits
INDIAN RIVER HYDROELECTRIC PROJECT PERMITTING STATUS
Permit / Decision Status Schedule
Jurisdictional Determination
Federal Energy Regulatory
Commission
FERC has ruled that the project is Non-
Jurisdictional
FERC Order Issued
May 26, 2010
Wetlands Permit
U.S. Army Corps of Engineers
Application filed 8/2010, multiple
supplemental submittals to clarify
project. USACE currently awaiting
applicant response to USFWS and SHPO
comments.
Expected Issuance
first quarter 2013
Easements
Alaska Dept. of Natural Resources
Application filed 8/2010. ADNR Case
#ADL 108047. Early Entry Authorization
issued.
Issued 9/11/2012
Water Rights
Alaska Dept. of Natural Resources
Application filed 8/2010. ADNR Case
LAS #27836. Water use permit issued. Issued 8/7/2012
Coastal Zone Consistency
Determination
Alaska Dept. of Natural Resources
Application filed 8/2010. Coastal
Management Program has been
terminated, no longer applicable.
Not required
Fish Habitat Permit
Alaska Dept. of Fish and Game
Application filed 8/2010. Habitat
permit issued, #FH11-I-0125 Issued 12/15/2011
Access Agreement
U.S. Forest Service
Coordinating with USFS on legal
structure for long term access to
project. Road Use Permit will be used
in interim.
Expected issuance in
first quarter 2013
City of Tenakee Springs
Indian River Hydroelectric Project
Project Summary Polarconsult Alaska, Inc.
January 2013 4
View upstream of existing USFS fish pass
structure at waterfall #4. The hydro project will
divert water from the top of waterfall #4. The
project will also upgrade the fish pass intake,
providing improved protection from flood
debris that frequently clog the fish pass and
block fish migration.
May 17, 2012.
City of Tenakee Springs
Indian River Hydroelectric Project
Project Summary Polarconsult Alaska, Inc.
January 2013 5
View of the powerhouse site looking upstream.
Waterfall #2 is visible in the distance. The
powerhouse will be located on the right side of
Indian River (red box).
April 20, 2011.