Loading...
HomeMy WebLinkAboutSusitna Project Supplemental Report Low Watana Dam RCC Concept Cost Evaluation Final November 29, 2010Susitna Project Supplemental Report Low Watana Dam RCC Concept Cost Evaluation FINAL November 29,2010 SRGUTING AND DRAINAGE GALLERIES LORY AATANA CREST EL.2925.9 MAX,OPERATING LEVEL Z .yw Et.Zoe 1 MEG)EL A880 ey LOW WATANA Fea ad VAIN,OPERATINGL EVE!aes pe Eb.1250.0 w EL 18505sre:= an oe)aOTArt ra oF i i wo Se pif EL.1700.0 as ee ia a SE PLATFG!Lee aM no EL.18600 TOP OF DYS COFFEROAM A ldS COFFERDAH on.:4 CREST EL.1476.0 Ml a t s oe we STEP Po,EL_1450.9.BOY ,INSTRUMENTATION a fiiSe,GALLERY o EL.1350.9, !* Ae See ih T rine ees !{|i i i SLURRi j TRENCHCONSOLIDATIONORAINAGE\GROUT i i PePRAP BAGKFILL GROUTING CURTAIN Low Watana Gravity Dam -RCC Concept Prepared by: R&M Consultants Hatch Associates Consultants Jack Linard Consulting R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept EXECUTIVE SUMMARY At the time of the Susitna Project studies for the 1983 FERC License Application and 1985 amendment to the License Application,roller compacted concrete (RCC)technology was not regarded as sufficiently developed to use in the construction of large dams.Over the past 30 years,however,roller compacted concrete has developed as a construction material for dams of increasing size and techniques of material placement and composition of the RCC mix has been refined with experience. R&M Consultants study team (R&M)was engaged by the Alaska Energy Authority (AEA)to develop a conceptual design and perform concept level cost estimates for a RCC dam at the Watana site and Devil Canyon sites that were described in the R&M report dated November 16", 2009.This is an addendum to that report and examines the Low Watana RCC dam options by exploring the cost differential between an expandable option and a non-expandable option,and gravity section vs.gravity arch.Additionally,the advantages and disadvantages of underground vs.surface powerhouse are explored as well as simplified transportation options utilizing updated information on railroad costs in conjunction with "rail only”surface transport to the project. We have found no fatal flaw in Low Watana RCC Gravity Arch Dam or surface powerhouse options,and initial estimates indicate that there may be significant potential savings,particularly with the RCC dam arrangements.RCC dams have been constructed in cold climates and at greater heights than the 700-feet of Low Watana. It is possible that developing the RCC concept to its final design configuration and moving toward construction could result in development opportunities for basic industries in Alaska in producing cement and exploitation of natural pozzolanic sources. Access and logistical considerations including road,rail,and air transport are of concern at a remote site such as the Susitna Project sites.Addition of unrestricted access to undeveloped areas is often controversial.The access alternatives considered have assumed rail only access to the project site. The cost estimate summary,Table ES-1,presents the estimated construction costs of the options, all of which consider surface powerhouses and "rail only”ground transportation. Table ES-1 Summary of Cost of RCC Dams for the Susitna Project Low Watana Low Watana Low Watana Low Watana Embankment RCC RCC Gravity Arch Non-Expandable Non-Expandable RCC $1,000 (1)Expandable $1,000 Non- $1,000 Expandable Description $1,000 Construction Cost Total (Millions of Dollars)$4,500 $3,900 $4,200 $3,600 (1)HDR 2009 Page i November 29,2010 R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept Supplemental Report Low Watana RCC Concept November 29,2010 Table of Contents EXECUTIVE SUMMARY i Table of Contents ii Figures iii Appendices iii 1.0 Introduction 1 2.0 Project Layout 1 2.1 General .......cccecccccescccsscsesescesseencceceacennececeesaecsenseseeeaeseseceaeesneessaeeeeessneeeserssaeeeseesones 1 2.2 Altermative ........cccccccccscesssseseesseessecsceesncesaeceaeeeasesseesaecseeseneeeaneenaeeaeseessessessensseesaaees 2 2.3 Powerhouse Layout .........ccccccscccesscccsseccseccereseceececesseeenneeceanererseecesnesessssnsaseaeessaeeees 3 2.3.1 Surface vs.Underground Powerhouse .............ecccscceseesseeneeeessessessseseenees 4 2.3.2 Surface Powerhouse Configuration...eects eeseeessssesssecceseenseteeseeeeeee 5 2.4 Dam Design Considerations.....cec cece ccccesceseeessaesseesssseseneseseseesceeeestenseeneeenesaes 7 2.4.1 RCC Dam Design...cee eeseccesseceeececseneeeseeceaeecenceceneceeenaeseesdsesansssasersesesaes 7 2.4.2 Low Watana RCC Gravity Dam Expandable...ceeeeeeeesecsrereerenees 10 2.4.3.Low Watana RCC Gravity Dam Non-Expandable........ieeeeee 12 2.4.4 Low Watana Gravity Arch woo...eececeeseeeceeeeeerereceaeeseeesteetnaeseneeseessens 12 3.0 Project Access Issues 13 3.1 Previous Project Access Costs Comparisons ..............ccesseececesseeseeensecrneteenessensens 13 3.2 Rail ACCESS .......ccescccecscceeseceeneersceeeeeseeesanersnseensneeerseserecernaeeonedeesesasnacsdasssessasesseesas 14 3.3 AUIStIIP oo.cceccceseseececeeeeeeeceeeacesseeeeeerneenaceeeeeceeeeseesensseecseeseeesesasseessnessseessressesseeeseas 14 4.0 Cost Estimates 15 4.1 RCC Cots ....ccccccccccccsesseccsereecensccceeceseneeceesnseecescceeasnseteccesdeeesesesauesecssaeesonaeecnsaeeees 15 4.1.1 RCC Unit Cost Analysis for Watana Dam ............eeeeeeeeeeseeeeeeeneteeneeers 15 4.1.2 Sizing of RCC Batching Plant...cee eeeeeeeaeeeeereeneeeseeeeeesereeenes 17 4.2 Camp Cot...cccecceccscccnecseeeseeeseeeeseeersesesesseassssesseeesseassesssassssanessssessesssesseneeneenes 17 4.3 Project Access CoSt 0...eessesssesssesssssssssssesesnssessescseseseascessesensucsaseceeeseeraaseneseesens 17 4.4 Cost SUMMALY ........eceeeeeteeeseeesseeeeseessenneeseeseceeeesecereesesseceseeserneeeeeasenssaseseeseeeseees 17 5.0 Project Schedule 19 5.1 Dat oo..cccccesceecesseenccesseeescecessaeeesaeeessecensneesesenecseeseseneneessenersnseesasseasasnaseseuesesesaneenees 19 5.2 POWETHOUSE ........cceeeeeeeeceseeeseeeeseceseaeeeseeeeseeecesecesetesncersnesesseessnneeaseaseneaseeseesesesees 19 5.3 Combined Dam and Powerhouse Schedule...ceeeseeeceeeseeeneeeseeeeseeneneeenens 20 Page il November 29,2010 R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept Figures 2.2-1 -Low Watana ICRD Expandable Plan 2.2-2 -Low Watana ICRD Expandable Section 2.2-3 -Low Watana ICRD Expandable Stage 2 Section 2.2-4 -Low Watana ICRD Power Facilities 2.4-1 -Low Watana RCC Expandable Plan 2.4-2 -Low Watana RCC Expandable Sections and Details 2.4-3 -Low Watana RCC Expandable Elevation Views 2.4-4 --Low Watana RCC Non-Expandable Plan and Detail View 2.4-5 -Low Watana RCC Non-Expandable Sections and Details 2.4-6 -Low Watana RCC Non-Expandable Elevation Views 2.4-7 -Low Watana RCC Non-Expandable Profile 2.4-8 -Low Watana RCC Non-Expandable Gravity Arch Plan 2.4-9 -Low Watana RCC Non-Expandable Gravity Arch Sections and Details 3.2-1 -Low Watana Rail Access 4.1-1--Borrow Areas Appendices A -Breakdown of Unit Cost Analysis for RCC B -Detailed Cost Estimate Page iii November 29,2010 R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept 1.0 Introduction R&M Consultants,Inc.(R&M)formed a team under the R&M/AEA term agreement that includes Hatch Associates Consultants,Inc.(HACI)and Jack Linard Consulting (R&M/HACI/ILC)to investigate the feasibility of Roller Compacted Concrete (RCC)technology for the Susitna Project as an alternative to impervious core rockfill dam (ICRD)concepts that were developed during the licensing studies which concluded in 1985.Additionally R&M/HACI/JLC performed a review of regulatory and FERC licensing activities and timelines for precursor activities to issuance of a FERC license,and developed and a licensing phase strategy for the project.The results of those investigations were presented in the R&M report dated November 16th 2009 (R&M 2009). The investigation was amended to consider additional alternatives with potentially lower costs. This document presents the results of the further investigations.It is an extension of the previous R&M 2009 report.In an effort to keep the comparison valid,the costs are based on December 2008 USD and are presented in the same format and structure as in the R&M 2009 report.The focus will be on a Low Watana option with the same general project size as described in recent studies (HDR 2009).Concepts focus on RCC dam options exploring the cost differential between an expandable option and a non-expandable option and straight gravity section dam vs.gravity arch dam. The advantages and disadvantages of underground vs.surface powerhouse are also considered. Transportation options utilizing updated information on railroad costs are developed with the alternative of "rail only”surface transport to the project.The cost estimate uses equipment/material prices consistent with the previous Watana cost estimate currently available from AEA. 2.0 Project Layout 2.1 General The following assumptions and technical considerations were included in developing our conceptual project layouts.Replacement of one dam design for another affects more than just the dam.Many features of the project general arrangement may be affected by the selection of dam type.In keeping with our understanding of the dam design and costing task we have included the following considerations: e Hydrology and hydraulics; °Assumed the same reservoir water levels as described for the Low Watana ICRD option; fe)Diversion scheme and tunnel capacities are different as the diversion scheme employs a shorter tunnel due to the smaller footprint of an RCC dam and the consequences of overtopping of RCC dams is lower than with ICRD; fe)The spillway configuration is different than for the ICRD alternative (eliminating the side channel spillway)and incorporating an overflow section into the RCC dam.The spillway configuration requirement included initial examination of energy dissipation and potential for scour and to reduce the potential for total dissolved gas (TDG)production at the project.The hydraulic capacity was taken to be the same as for the current ICRD configuration.The RCC dam Spillway design is conceptual only at this phase without detailed analysis,modeling and in depth review of energy dissipation of potential for rock scour. November 29,2010 Page 1 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept 2.2 The intake structure and water conveyance use similar invert elevations and diameters as for the ICRD dam option; The powerhouse layout uses the same equipment sizes at the same setting as for the ICRD option; Foundation Conditions and Excavation Depth:Foundation conditions and foundation treatment,including the single line grout curtain,will be similar to those for the Full Watana RCC dam concept,which were similar to treatment of the foundation below the impervious core for the ICRD dam scheme; Dam cross section design --RCC dams are designed to the same principles and standards as concrete gravity dams.Design loadings and factors of safety are per FERC guidelines,including;waves and freeboard,earthquake,ice and silt loads.The principles used to develop the Full Watana RCC dam concept are the same as used for the Low Watana RCC dam concept. Alternatives Several RCC alternatives were examined for comparison with previous ICRD expandable and non-expandable Low Watana alternatives.To achieve this,we have focused on the elements of the RCC dam alternative that differ from the existing ICRD alternative. Elements that are similar will remain identical for both alternatives in order to achieve an "apples to apples”comparison to the extent possible.The alternatives being compared to the RCC schemes are the ICRD Low Watana Expandable (see Figure 2.2-1 through 2.2- 4)and the ICRD Low Watana Non-expandable. The following alternatives are addressed in this report: Low Watana RCC Gravity Dam Expandable; Low Watana RCC Gravity Dam Non-Expandable; Low Watana RCC Gravity Arch; Additionally,there is a discussion of above ground vs.underground powerhouses for these alternatives. Major considerations are: Dam layout (axis,gravity arch vs.gravity); Intake (integral to the dam or separate,expansion to full height Watana); Spillway sections that could be modified for the expanded option; Powerhouse (location,surface vs.underground,expansion options). Advantages of the RCC dam concept compared to ICRD include:a smaller footprint, lower dam volume,integral spillway,considerably shorter diversion tunnels and no vulnerability to overtopping.Table 2.2 shows a comparison summary of significant features of each alternative. November 29,2010 Page 2 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept Table 2.2:Low Watana ICRD and RCC Alternatives Summary Low Watana Low Low Low Wana Feat Description Non-Watana Watana Watana RCCeaturebescripilExpandable|Expandable |RCC-Non-|RCC-CravitICRDICRDExpandable|Expandable Achy Total Dam Fill Volume (cy)22,000,000 32,000,000 7,600,000 7,600,000 6,000,000 oO Tunnel Diameter 36 36 7 27 7 Average Diversion Tunnel Length (ft)3,700 3,700 2,000 2,200 2,000 Intake Area Excavation (cy)1,970,000 1,970,000 270,000 760,000 270,000 Average Power Tunnel Length (ft)200 200 260 300 330 Average Pressure Tunnel Length (ft)400 400 550 1500 170 Tailrace Tunnel Length 1,500 1,500 N/A N/A N/A ine Concrete Volume |49 400 60,600 62,500 83,000 62,500 Powerplant Excavation 242,000 363,000 1,500,000 |2,200,000 |1,500,000Volume(cy)(3)-64'Tall x |(3)-64'Tall Spillway Gates 44'Wide x 44'Wide N/A N/A N/A Radial Gates |Radial Gates (oy Chute Excavation 2,960,000 |2,960,000 N/A N/A N/A Spillway Chute Conventional 130,300 130,300 99,000 99,000 99,000Concrete(cy) This study does not have the scope for an exhaustive exploration of layout options,so some engineering judgment has been used to develop the configurations used for comparison.We have selected a layout based on general comparisons to existing projects.The Shasta project in California in particular is similar in size and layout to our selected configuration for the RCC Gravity and Gravity Arch dam arrangements (Kollgaard and Chadwick,1988). 2.3 The powerhouse layout was examined to explore potential cost savings associated with the smaller footprint of gravity or gravity arch dams and robust concrete construction which allows configurations that would not be available with an ICRD dam. Powerhouse Layout A common reason for selecting an underground powerhouse is to take advantage of a steep gradient of the river between the dam and the tailrace;however this is not the case at the Watana Dam site.Another important consideration is to minimize the length of the water passage.The smaller footprint of the RCC dam allows shorter water conveyances as well as the option of intakes and water conveyance either through the dam,or in the rock abutments.The geological conditions must be suitable for an underground powerhouse,which they are at Watana.A surface powerhouse requires enough room to place the powerhouse along the river without excessive excavation,which is also the case.Our conclusion is that both an underground and surface powerhouse configuration is feasible at the Watana site and the choice should be based on economics, constructability and serviceability issues. November 29,2010 Page 3 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept 2.3.1 Surface vs.Underground Powerhouses The choice of a surface or underground powerhouse is largely dependent on the project setting and site conditions.The following list compares the two options: e Typical surface powerhouse advantages are: o Elimination of tailrace tunnel; No requirement for tailrace surge chamber; Less expensive excavation; Ventilation is easier; Less geotechnical exploration required (as less geotechnical risk to cost and schedule).0000*Typical underground powerhouse advantages o Location is more flexible; o Shorter headrace tunnels with considerable reduction in length of steel-lined high pressure conduits; o Work area can be more easily separated from dam construction (two separate construction areas and schedules); Powerhouse is not located in or near river bed materials; Exterior shell not needed (rock forms support); Protection against the elements (longer construction season); Turbine setting can be lower; Less concrete needed to control hydraulic uplift; Less maintenance required.000000The 1982 Acres Feasibility report discusses the choice of an underground powerhouse based on general assumptions of less costly installation for underground installations,additional operational flexibility and climatic considerations. The 1985 Harza Ebasco FERC license application (Harza Ebasco 1885)includes a comparison of an underground to a surface powerhouse by major civil mechanical and electrical cost items where the surface powerhouse was shown to be more expensive due to the far greater cost of the power tunnel/penstock (see Table 2.3-1).The comparison in Table 2.3-1 is a simplified comparison and does not include the costs associated with the powerhouse superstructure or the considerable substructure required to insure that the powerhouse is stable against hydraulic uplift. November 29,2010 Page 4 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept Table 2.3-1 Comparison of Surface to Underground Powerhouse (Harza Ebasco Study 1985) TABLE B.2.2.6:SUMMARY COMPARISON OF POWERHOUSES AT WATANA SURFACE ONDERGROUNOD ($006)($000)¢$000) Item 4 x 210 MW 4 x 210 MW 6 x 140 MW Civil Works: Intakes 54,000 54,000 70,400 Penstocks 72,000 22,700 28,600 Powerhouse/Draft Tube 29,600 26,300 28,100 Surge Chamber NA 4,300 4,800 Transformer Gallery NA 2,700 3,400 Tailrace Tunnel NA 11,000 11,0006 Tailrace Portal .NA 1,600 -1,600 Main Access Tuanels NA 8,100 8,100 Secondary Access Tunnels NA 300 300 Main Access Shaft NA 4,200 4,200 Access Tunnel Portal NA 100 100 Cable Shafe NA 1,500 1,500 Bus Tunnel/Shafts :NA 1,000 1,200 Fire Protection Head Tank NA 400 400 Mechanical For Above Items 54,600 55,500 :57,200 Electrical -For Above Items 37,400 37,600 41,200 Switchyard All Work 14,900 14,900 14,900 TOTAL .262,500 246,200 277,000 We have developed a potential project arrangement with a surface powerhouse (loosely based on the Shasta Hydroelectric Plant layout,Development of Dam Engineering in the United States,1988)with an intake on the left abutment,transitioning to a tunnel.The length of the water passage is similar to that of the Low Watana underground option (Harza Ebasco 1985).The tailrace discharges directly into the Susitna River. 2.3.2 Surface Powerhouse Configuration Considerations for the surface powerhouse include:setting of the units,elevation of high tailwater to prevent powerhouse flooding,rock cover over the tunnels and the need for steel lining,stability against hydraulic uplift,construction access, cofferdamming and diversion requirements to accommodate dam,powerhouse foundation,and tailrace channel.Costs of waterways (tunnels,shafts and intakes)are not included in the cost account for powerhouse cost comparisons but are in a separate cost account. The conceptual layout of a surface powerhouse for the Low Watana RCC dam alternative was selected for favorable hydraulic characteristics as well as for cost effective excavation downstream of the proposed dam.The concrete volume for the surface powerhouse is a volume sufficient to ensure that there would be enough mass to prevent powerhouse floatation without installation of anchors. The surface powerhouse is set on the south river bank (left bank)such that the tailrace apron end sill is adjacent to the end sill of the spillway stilling basin,as these two features are at the same elevation of 1450 ft.The tailrace end sill apron creates a downstream control weir for the powerhouse,thus maintaining minimum tailwater conditions.Several design considerations including; November 29,2010 Page 5 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept excavation volumes,effects of discharge on downstream hydraulics,and the effect of spillway discharge on powerhouse operation,must be evaluated to determine the optimum physical setting of the powerhouse.The surface powerhouse for the low Watana RCC alternatives was set to be offset 27 degrees from the stilling basin,which is generally the expansion ratio of 2 longitudinal to 1 horizontal as defined by the USACE (HEC RAS v4.1 Reference Manual).This alignment directs the Low Watana RCC dam surface powerhouse discharge efficiently into the downstream river channel,noting that further downstream of the dam the river bends to the north. For this study,the dimensions of the surface powerhouse were set to accommodate the same equipment layout proposed for the ICRD dam designs. The transformers will be located within the surface powerhouse rather than in a separate cavern as with the underground design.The surface alternative has the transformer deck set above the draft tube outlets and their overall dimensions are similar to those of the underground alternative.The entrance angle of penstocks with respect to the surface powerhouse remains the same 62 degrees as with the underground design. The power intake (for the non-expandable and gravity arch RCC dam alternatives)is integrated into the dam body and transitions into two concrete lined tunnels that lead to vertical shafts and high pressure tunnels that bifurcate and transition into steel lined penstocks that lead into the four Francis units in the powerhouse.The intake invert and size for the RCC dam alternatives are approximately the same as in the ICRD dam alternatives and the overall penstock lengths are similar for the surface and underground alternatives.Although the penstocks are somewhat longer in the surface alternative than in the underground alternative,having sections of the power tunnels integral to the RCC dam may reduce tunnel excavation/support,and concrete lining costs. The significant cost advantage between the conceptual RCC surface powerhouse and previously designed ICRD underground powerhouses is the elimination of surge chambers,tailrace tunnels and access tunnels for the surface powerhouse which are considered in the waterways cost account.Given the limited scope of this study,the surface powerhouse was investigated to determine its feasibility and provide an estimate of comparative costs.With this criteria,the surface powerhouse does show to be a feasible alternative.However,the scope did not include optimization of an underground design for the RCC designs.An underground powerhouse with the RCC dam may have shorter pressure tunnels a hydraulic transient analyses may demonstrate that surge chambers are not required. Further analyses should be performed to evaluate both surface and underground layouts that will improve the configuration of the powerhouse,including; optimizing unit settings considering concrete requirements and excavation costs, optimizing high pressure and low pressure penstock lengths,as well as optimizing the tailrace configuration.Additional study will be required to better define hydraulic effects of the spillway discharge on powerhouse performance, including physical model testing.Indications are that both surface and underground powerhouse configurations are feasible for the Low Watana with an RCC dam,and future analyses will need to be performed in order to determine the optimum configuration. November 29,2010 Page 6 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept 2.4 Dam Design Considerations 2.4.1.RCC Dam Design The geotechnical information is typically the most influential element for developing a dam design and the Watana site has well developed site information.The RCC dam alternatives were developed on axes similar to that of the ICRD dam axis.This is considered a conservative assumption,adopted to provide a dam axis in the location with the maximum amount of existing information on the foundation subsurface conditions,but not necessarily at the most efficient location.It is possible or even likely that a more efficient dam axis location could be found with further investigation. The site has a foundation and abutments that are well suited to a concrete gravity dam.Concrete gravity dams are relatively straight forward to design,and many computer programs are available to improve the process of initial and final design.The dam design can be initially developed using assumptions for concrete strength based on similar mixes used on other projects.The final configuration of the dam requires accurate material properties for the RCC material that can only be determined by trial mix design using the actual selected cement and pozzolan and the aggregate material available from the site. Foundation treatment for all RCC dam options includes consolidation grouting under the dam footprint and curtain grouting similar to that assumed in the previous RCC dam study. There is a buried channel north of the dam site which has been called the "Relict Channel”.For the RCC alternatives,the treatment for the Relict Channel has been taken to be identical as developed for the Low Watana non-expandable ICRD. It is important to note,particularly with regard to the comparison with the gravity arch alternative that the Low Watana cross-section retains the 1H:1V downstream slope established for the High Watana option (R&M 2009).This face slope was considered to be on the conservative side for the high dam and is even more so for the low dam option. At this stage of proceedings,it is not appropriate to try to refine or optimize the various elements of the different schemes,but it is important to bear in mind that more detailed analyses may well change the relative ranking of project alternatives.By the same token,more detailed analyses can only serve to ensure that the eventually selected alternative will be more attractive than the alternatives indicated herein because of the conservative approach adopted throughout in these comparative studies. A more conventional spillway option for a dam of this configuration and height would be a smooth surfaced chute with forced air entrainment discharging back into the river via a flip bucket into a plunge pool.Such an arrangement would require the dam axis to be relocated to ensure that the jet from the flip bucket impacts in the river with an alignment such that back scour is minimized.The use of flip bucket and plunge pool may also result in hydraulic conditions that could lead to high total dissolved gas (TDG).TDG occurs when air mixes with water and goes into solution at depth,creating water supersaturated with air.If November 29,2010 Page 7 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept fish breathe supersaturated water,air can come out of solution in their blood stream causing gas bubble disease,which can be fatal.The stepped spillway may allow spill without a plunge to depth that could lead to excessive levels of TDG. The design would look to dissipate as much energy as possible and create a spillway that creates skimming flow downstream of the spillway.The present work scope does not cover spillway and dam axis optimization and for that reason,the stilling basin concept,which is compatible with the ICRD axis,has been adopted for present reporting purposes. The conceptual spillway for the RCC alternatives is incorporated in the dam structure.The flood outflows are discharged through an ungated spillway into a stepped,converging chute and terminating in a downstream stilling basin.As discussed in the R&M 2009 Report,the stepped spillway is expected to provide significant energy dissipation and to be compatible with the stilling basin arrangement shown on the drawings.However,a stepped spillway of this size exceeds precedent and details will have to be verified by comprehensive hydraulic model studies. An extensive study,including large scale physical models (not less than 1:40 scale)will be required prior to finalizing the details of spillway configuration. The preliminary hydraulic calculations performed for a stepped spillway indicate that it is a potentially cost effective configuration and should warrant further consideration and analyses during future design studies.Modeling may well show that the optimum stepped spillway and stilling basin is different to the conceptual configuration,or that a different type of spillway may be required. Any modifications may influence not only the spillway costs but also the powerhouse costs as the layout may have to be reconfigured. 2.4.1.1 Steps for RCC Design Development of the RCC dam design will require several steps, comprised of: e Confirming design criteria,including loads and _load combinations,materials and foundation properties,minimum factors of safety and allowable stresses; e Evaluation of site climatic conditions which have a major impact on both construction programming and RCC mix design; e Performing preliminary design --determine required performance,development of basic geometry,preliminary mix design and strength requirements; e Performing three-dimensional finite element analysis (using initial assumed material properties),including dynamic and thermal stress analyses; e Locating and testing aggregate,cement and pozzolan sources that will be used for construction; e Establish RCC placement temperature,maximum allowable interna!temperature and required temperature control measures; and e Developing trial mixes for the full scale trial embankments (FSTE)to fine tune the mix design. November 29,2010 Page 8 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept The trial mix program would be initially oriented towards: e Aggregate gradation optimization; e Selection of two preferred cement types and content; e Selection of two preferred pozzolan types and content;and e Selection of two preferred retarder types and content. The minimum time from beginning the study of the prospective RCC to confirmation of mix details is 16 months.Conservatively,it would be appropriate to allow 18 months.At least 18 months is required to investigate,select,procure,ship and set up the necessary equipment (crushing plant,batching plant,conveyors).Most of this work is done during the trial mix/FSTE phase and the end result is that the RCC production facilities can be ready within 2 years of starting trial mixes. An upper limit would be 2.5 years. 2.4.1.2 Seismic Design Consideration The most important safety concern of concrete dams subjected to earthquakes is excessive cracking,which can lead to potential instability from sliding or overturning.Sliding could occur on an existing plane of weakness in the dam foundation,at the foundation-dam interface or within the dam.Although some major concrete dams have experienced strong ground motion with some damage,it is of note that there has been only one major concrete dam failure in recent times as a result of earthquake induced ground motions.This failure was in Taiwan where the dam was constructed literally over the top of an active fault.In general,instability of gravity dams caused by excessive cracking of the concrete is most likely to occur in the upper half of the dam. The application of defensive design measures when designing a dam is the most dependable approach to alleviate safety concerns.Defensive measures for concrete dams include the following: e Adequate drainage is the first line of defense against foundation instability,in part because it is the most economical; e Designing RCC mixes and construction procedures to ensure that direct tensile and shear strength parameters are always achieved without excessive cement content in the mix. (Increased cement will increase thermal stress problems, which may be more of a concern than the seismic risks); e Use the best geometric design and structural detailing.The dam should have minimum geometric irregularities and gradual variations in structural stiffness.Examples of good geometric design are curved transitions and minimal mass at the crest; e Effective quality control during construction to ensure foundation preparation,strength of the concrete and appropriate cleaning and preparation of lift joints and placement of reinforcement when used;and e Design contraction joints to accommodate displacement. November 29,2010 Page 9 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept 2.4.2.Low Watana RCC Gravity Dam Expandable The Low Watana RCC Expandable dam alternative consists of the Watana dam constructed to a lower height of 700 feet and a four-unit powerhouse with a total installed capacity of 600 MW (see Figures 2.4-1 to 2.4-3).The expandable option allows for a dam raise to the height of the original Watana concept with a dam height of 885 feet and installation of a new intake structure,an additional power tunnel and two additional generating units with a capacity of 1,200 MW. In order to provide for future raising of the dam and expansion of the powerhouse,the location of the powerhouse and power intakes were adjustedfromthenon-expandable alternative.The powerhouse was translated 185 feet downstream compared to the non-expandable RCC gravity dam alternative to allow room for RCC material to be placed downstream of the dam as part of the dam raise. The power intake structure was located on the left abutment as opposed to being integral with the dam for the non-expandable alternative to provide _more flexibility for the dam raise.If the power intake were integral to the dam,a new power intake would be more constrainedandcomplicated by-existing structures. During expansion,a new intake channel could be excavated above the existing structure at the appropriate invert elevation.Intakes for the expanded option could be developed at a higher invert elevation than the first stage intakes.The intakes for the expansion,second stage would be connected to the first stage water conveyances at the vertical shaft,to tap into the lower,high pressure portion tunnels leading to the powerhouse. The powerhouse includes empty bays that can accommodate additional generating units in the future.The gravity section will be raised by placing additional RCC on the dam crest and downstream face of the dam.High strength steel anchors will be installed_on the first stage.dam faces and will tie into the second stage RCC placement.Prior to placement of the second stage RCC the surface of the first stage will be cleaned and scarified using high pressure washers.The spillway for the second stage will be constructed using the same placement procedures and similar design as in the first stage. The gravity dam section was checked using the CADAM program for static and pseudo dynamic stability and found to have adequate safety factors (see R&M 2009 for a description of the analysis,loading and material properties). The process of raising a dam at a later date is not a simple matter.We have included some general considerations,procedures and a potential sequence to provide some indication as to the process involved. GENERAL 1.Planning and design prior to start of Stage 1 are critical.It may be necessary to place some Stage 2 base RCC (up to stilling basin level) during Stage 1 to minimize overall Stage 2 duration. 2.Stage 1 RCC mix will be designed for Stage 2 loads and loading conditions. 3.Foundation excavation for most or all Stage 2 should be performed during Stage 1 works to avoid blasting close to in-service dam and powerhouse. November 29,2010 Page 10 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept 4.Note that same 5.5 months per year is max time available for RCC placement (5 months for conventional concrete). 5.Draw reservoir level down to the minimum operating level at end of winter.Generate during summer to keep reservoir level as close as possible to the minimum level,Note that a critical problem is handling of flood inflows during Stage 2. 6.RCC production rates will be slower for Stage 2 than for Stage 1 due to greater constraints on placement. 7.Dam/spillway expansion construction expected to take approximately 5 years. PROCEDURE 1.Clean existing RCC surface to exposed coarse aggregate. 2.Make sure exposed surfaces are saturated and surface dry and that outer 18 inches is above freezing point. 3.Place bedding mix on horizontal surfaces immediately prior to placing RCC. 4.Use grout enrichment to bond new RCC to sloping surfaces in existing RCC. 5.Otherwise standard RCC procedures will apply (anchors between Stage 1 and Stage 2 RCC are not required). SEQUENCE Year 1: Clean-up and prepare foundation and abutments. Remove concrete from Stage 1 chute and stilling basin. Commence aggregate production and stockpiling. Year 2: Place RCC in base (up to stilling basin level)and on abutments up to approx El.1650. Year 3: Continue RCC placement up to El.1900 approx. Place conventional concrete stilling basin. Remove spillway conventional concrete including bridge and piers (winter). Year 4: Place RCC to underside of stage 2 spillway. Place conventional concrete in chute. Complete RCC to crest El.on right abutment. November 29,2010 Page 11 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept Year 5: Complete RCC to crest El.on left abutment. Construct Stage 2 spillway crest works. 2.4.3 Low Watana RCC Gravity Dam Non-Expandable The Low Watana Non-expandable RCC Gravity dam alternative has the same dam profile and the general configuration is similar to the expandable alternative above with a dam height of 700 feet and a four-unit powerhouse with a total installed capacity of 600 MW (see Figures 2.4-4 to 2.4-7). The major differences that lead to reduced installation costs are the shorter diversion tunnel length and shorter power tunnel length for the surface powerhouse as well as the size of power tunnel and tailrace.The intake structure is shown as being incorporated into the dam on the left abutment.The assumption is that conventional concrete would be used for the intake structure with RCC placed against the conventional concrete. The Powerhouse is shown as close to the dam and spillway as possible in order to minimize the water conveyance length.The powerhouse layout does not consider future expansion options. 2.4.4 Low Watana Gravity Arch A Low Watana gravity arch RCC dam option was also considered (see Figures 2.4-8 to 2.4-10).The axis adopted for these preliminary gravity arch studies was effectively that adopted for the conventional gravity dam option.In turn,this was the axis chosen for the ICRD in the studies carried out in the 1980's.From this background,it can clearly be seen that the axis used for the G-A layout is by no means optimum. This preliminary gravity arch dam configuration was based on several factors. First,the crown cantilever section was selected to be similar to the Hungry Horse (gravity arch)Dam in Montana which is sited in a geometrically similar canyon. The Hungry Horse Dam (Development of Dam Engineering in the United States, 1988)crown cantilever was configured with a vertical upstream face and a 0.6 Horizontal to 1.0 Vertical sloped downstream face.The Low Watana gravity arch crown cantilever section was configured with a vertical upstream face and a 0.7 Horizontal to 1.0 Vertical sloped downstream face.The larger ratio was selected based on the larger expected seismic hazard for the Susitna site and preliminary analysis for a gravity arch RCC dam at the High Devil Canyon site. The stream channel physical dam location,arch (constant)radius and center point was selected based on the qualitative topographical features at the site.In studying the topography of the site,it appears that this site is not as well suited for arch action foundation support over the full 700-foot height of the dam.From about elevation 1850 to the crest elevation of 2025,the cross-valley slope is relatively small compared to the slope below elevation 1850.Therefore,in locating the arch,the topographic contours between elevations 1550 and 1850 on each side of the canyon were collectively examined for orientations that would best provide for arch thrust into the foundation.After the "best"thrust foundation profiles were located on each side of the canyon,the approximate tangent lines to the profiles on each side were laid out on the site plan.Their November 29,2010 Page 12 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept intersection established the radius and center of the upstream arch.Having established the arch radius and center,the remaining geometry of the dam is integrated into the canyon using the basic section geometry of the crown cantilever and the topography of the site. The seismic loading will have a large component of load in the upstream/downstream direction,and a thrust block structure may be required to accommodate this loading.We have assumed for this preliminary estimate (which will need to be confirmed by three-dimensional finite element analysis, when abutment and dam properties are better known)that an additional 25%of the base concrete costs would be sufficient to account for this component of the dam. With the configuration described above,the structural support behavior of the dam is conceived to be primarily arch-gravity action in the lower two-thirds of the dam and gravity only in the upper third.It is to be noted that the preliminary configuration is only the starting point of the comprehensive structural and stability analyses that would include both seismic and PMF loading.Although the configuration is likely to be modified based on such analyses,the preliminary configuration serves to provide a reasonable estimate of dam volumes and construction costs. The gravity arch has a smaller footprint than the gravity section,however the area will remain large enough for equipment to move efficiently.The assumption for this preliminary study has been that placement rates and RCC unit costs would be the same for all alternatives.There will be some difference with the grout treatment at the upstream face that will have a small increased effect on the overall unit cost,but this should be developed in more detail if this alternative is addressed in detail. 3.0 Project Access Issues Access to the construction site for the alternatives considered in this report are by rail link alone to limit access to the site and reduce costs.The Alaska Railroad provided some input on recent costs to develop the rail link along the south side access corridor alignment.An airstrip would be provided near the Watana project to allow use of aircraft up to a C-130 Hercules or equivalent. 3.1 Previous Project Access Costs Comparisons Previous cost estimates for project access infrastructure for the Full Watana RCC dam and High Devil Canyon RCC dam (R&M 2009)assumed both rail and road transportation to the site on alignments in the south side corridor.This alternative was compared to a Watana ICRD concept with only road access from the Denali Highway through a northeasterly corridor (HDR 2009).While it is true that the RCC concept would benefit greatly from the ease of transporting bulk cement and pozzolans and major equipment and logistical access to the site by rail,road transport of these materials equipment and supplies would also be feasible.The different project access and logistical support transportation assumptions between the RCC and ICRD concept studies led to a significant distortion of the comparison of the project costs.For an "apples to apples”comparison of the options,the same basic transportation configuration (road only,road and rail,or rail only)should be assumed for both schemes with logistics costs included to account for transport of imported materials. November 29,2010 Page 13 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept For this immediate report,we are assuming rail access only,during construction.Future considerations regarding access may result in removal of the rails and converting the railroad to use of trucks and other over-the-road vehicles. 3.2 Rail Access The alignment for the rail link only option along the southern alignment (see Figure 3.2- 1)is based on the project access and logistical studies done by R&M.A report on the Access Planning Study by R&M for Acres was issued in January 1982 and a Supplement to the Access Planning Study was issued in September 1982. For the R&M 2009 report on RCC concepts the rail link alignment was assumed to be as shown on Figure 3.2-1 which was drawn from the alignment details presented in the R&M 1982 report.The rail access would connect to the existing Anchorage-Fairbanks alignment of the Alaska Railroad near Gold Creek on the south east side of the Susitna River then would proceed east up the south side of the Susitna River to the Watana site via the north end of Stephan Lake and the west end of Fog Lakes.This alignment requires no new bridge across the Susitna River and only requires a railhead be constructed near Gold Creek from which to stage rail transport of goods and materials to the Watana dam site. A railroad is considered desirable for access to the project for construction of the RCC dam because of the large quantities of bulk materials to be moved to the construction site and weights anticipated for large components such as gates,penstocks,turbines, generators and transformers and structural steel.Also a railroad would lessen the impact of project traffic and heavy haulage on the Alaska highway system.In addition,these material and equipment items will likely be brought to Alaska by barge,rail barge and/or ship from the source either via Seattle or other foreign or domestic port to Anchorage or Whittier for trans-loading onto railcars for movement to the Project site.Shipping possibilities include rail barge for most of the materials which would allow the loaded rail cars to pass through Whittier or Anchorage directly to the project site without trans- loading.Materials shipped in sea containers (CONEX's)could be offloaded from a container ship in Anchorage and loaded onto rail cars for hauling to the project site. Vehicles associated with the project can be moved via rail car to the Watana Project. 3.3 Airstrip A permanent airstrip would be constructed at a suitable location near the main construction camp.The runway is assumed to be 6,000 feet in length based on the project final report and should be capable of accommodating the C-130 Hercules aircraft as well as small jet passenger aircraft.If construction personnel transport were to be done by using jet aircraft,such as the Boeing 737-400 or similar,the runway would require greater length and should be constructed to generally higher standards than that serving the C-130 aircraft.Roads will connect the airstrip to the camp,village,and dam site.A small building will be constructed to serve as a terminal and tower and a fuel truck/maintenance facility will be constructed.A helicopter pad will also be provided. A temporary airstrip will be constructed to support the early phases of mobilization and construction.This temporary runway will be 2,500 feet in length and will be located in the vicinity of the main construction camp.The airstrip will be capable of supporting smaller aircraft. The temporary airstrip would eventually be incorporated into one of the main haul roads after the permanent airstrip is in service. November 29,2010 Page 14 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept 4.0 Cost Estimates Cost estimates were developed for the alternatives examined.The cost estimates are intended to extend the information provided previously (HDR 2009 and R&M 2009),and to be as comparable as possible to the previous options. 4.1 RCC Costs Due to the significant influence of the dam costs in the total project costs,the RCC unit cost was developed further. 4.1.1 RCC Unit Cost Analysis for Watana Dam The Watana dam RCC unit cost was analyzed utilizing the contractor estimating approach of itemizing labor,equipment and materials (L,E &M)costs. Furthermore the unit cost was analyzed with the L,E &M approach in respect to three phases;the aggregate production and pozzolan materials delivery;RCC placement;and RCC production.A detailed breakdown of RCC Unit Costs may be viewed in Appendix A. In the 1985 Harza Ebasco study,Borrow Pit E was designated as the conventional concrete aggregate source (see Figure 4.1-1).Borrow Pit E is located approximately 2 miles west of the dam axis on the north bank of the river. Since the proposed site access for the Low Watana Development is from the south and aggregate production is scheduled to commence 12 months prior to RCC production,other borrow pits were reviewed for possible RCC aggregate sources.In review of the Acres,"Susitna Hydroelectric Project -1980-81 Geotechnical Report”,Quarry Site A was of primary interest due to its close proximity to the dam and location on the south bank.The previous geotechnical reports indicate that Quarry Site A contains good quality rock.It has an estimated 23 million cubic yards (mcy)of weathered rock and 71 mcy of good quality rock above elevation 2300 ft.The geotechnical report described the rock as "very resistant to abrasion and mechanical breakdown,seldom losing strength or durability in the presence of water and demonstrating high resistance to breakdown by freeze-thaw.”The requirements for RCC aggregates are different than for conventional concrete and effectively any moderately to slightly weathered,non-reactive rock can be assumed to be worthy of consideration until proven otherwise. The Borrow Pit E source was considered the primary source for aggregate in the 1985 Harza Ebasco study,however there would likely be significant excavation below the Susitna River water line.Due to its close proximity to the dam on the south bank,good rock qualities and abundance of material,Quarry Site A appears to be a very attractive RCC aggregate source.Since Quarry Site A is well above the river level,permitting would likely be less complicated than with Borrow Pit E.Preliminary volume estimates for the Low Watana Gravity Dam indicate that approximately 7.6 mcy of roller compacted concrete would be required.The preliminary RCC mix design requires approximately 80% aggregate by volume,which results in a total required aggregate volume of 6.1 mcy. Due to the limited scope of this study,a detailed cost estimate of an aggregate production facility at Quarry Site A was not done on an itemized basis,rather,the November 29,2010 Page 15 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept costs developed in the 1982 Acres study were utilized and escalated to 2008 dollars.The 1982 unit cost for aggregate production and hauling were escalated using the USBR Construction Cost Index under the category "Concrete Dams”. The 1982 study utilized Borrow Pit E as the aggregate source,and it was assumed that the crushing and screening facilities would be similar for Quarry Site A.The estimated production from Borrow Pit E was 6.2 mcy,while the required production at Quarry Site A is approximately 6.1 mcy or less depending on the selected alternative.The aggregate haul costs were similarly escalated to 2008 dollars,which may be conservative since the round trip distance for Borrow Pit E was 4 miles compared to an estimated 1 mile for Quarry Site A.Another source of conservatism is that Quarry Site A has a much deeper groundwater table and less overburden as compared to Borrow Pit E,which will decrease the dewatering and clearing costs. The cementitous material costs $180/ton ($48.86/cy)as determined in the R&M 2009 study were used in this cost analysis!.Also it was assumed that 4 ARAN Modumix III (MM III)batch plants would be installed to produce an average of 1,000 cy/hr of RCC.The total installation cost of the batch plants was estimated to be $20 million.Each of these assumptions is consistent with the Full Watana RCC Analysis.Other important assumptions used in the Full Watana RCC analysis that were utilized for determining labor and equipment costs are;RCC is mixed in 8 cy batches;each work day consists of two 10 hour shifts;the construction season is 5.5 months;and the total number of working days per season is 165. As previously mentioned,RCC will be delivered to the dam via conveyors and chutes,Standard 10 cy (or larger)rear dump trucks will be used to transport the mixes to various placement locations.The estimated cycle times for dump trucks was calculated in order to determine the total number of trucks required for placement.In order to determine the total amount of placement crews required, the RS Means (RS Means 2010)estimation of cy of RCC placed per day per crew was adjusted to an hourly placement rate.In this manner the total number of haul trucks and placement crews was determined by the average RCC production rate of 1,000 cy/hr.Additional workers including laborers,foreman,operators, and mechanics,etc.,were estimated based on total number of crews and trucks. Hourly labor rates for each trade were taken from the RS Means data.This hourly rate was then prorated to include the overtime for a 10 hr work day and multiplied by the city cost index for Fairbanks. The total pieces of equipment was based on the number of placement crews and batch plant operations.The RS Means (RS Means 2010)Hourly Operational Costs and Monthly Rental Rates were utilized for the analysis.Each was multiplied by the Fairbanks City Cost Index.Using the average production rate,a total number of required work days for placement was determined,which resulted in 3 construction seasons.The overall rental rates were then calculated for operational time and idle time.Based on previous experience,it was assumed that the total equipment operational cost of the batch plant was equal to the total cost of supply of the batch plant,which has been estimated to be approximately $20 million. 'Note that this cost is based on the assumption that all supplementary cementitious materials (pozzolan,fly ash,etc)used in the mix are imported.If suitable sources of pozzolanic materials are identified within Alaska,substantial reductions in this unit price may well be possible. November 29,2010 Page 16 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept The detailed breakdown of the RCC unit cost resulted in a total per cubic yard cost of $97.21,which compares very well to the previous RCC unit cost of $100/cy used in for the Full Watana alternative (R&M 2009).Further analysis of the aggregate production plant and RCC batch plants may show additional reductions in costs,but for the scope of this analysis an RCC unit cost of $100/cy appears valid. 4.1.2 Sizing of RCC Batching Plant The abutments at the Watana Site are ideal for the transportation of the RCC to the dam surface using a 'vacuum chute'.The RCC can be lowered 250 to 350 feet for placement without difficulty.Therefore,based on potential quarry location and using any of the above-mentioned transportation methods,the most appropriate location for the RCC batching plant for Low Watana would appear to be at the intake approach channel.This area is already planned to be excavated for the intake,therefore a separate excavation for a batch plant would not be required.It would also be approximately two-thirds the height of the dam and allow for transport of material to the placement elevations above and below the intake.For the bottom half of the dam,a fixed conveyor could run downwards from the plant to a hopper at about half height near the axis of the dam.This hopper could feed a chute that would load the trucks on the dam surface.As the dam increased in height,sections of the chutes/pipes would be removed.For the placement of RCC in the upper half of the dam,the fixed conveyor could run from the concrete batching plant upwards to a hopper just above the crest of the dam that would then feed a chute for final conveyance to the trucks on the dam surface.This RCC transportation scheme would provide a very simple and reliable (and inexpensive)method that has the potential for reducing the unit costs estimated. 4.2 Camp Cost The 1982 Acres Feasibility Study cost estimate had assumed for the Watana embankment dam a camp for 3,600 workers,a project village,and support facilities.The 2009 HRD report indicated a much smaller camp than anticipated in 1982. When comparing the ICRD to the RCC dam alone,the smaller volume of the RCC dam would logically reduce the workforce required.However is anticipated to be 24/7 for 5.5 months.Embankment fill placement for the ICRD is presumably daylight hours for 8-9 months.For RCC,crews are smaller (more highly mechanized operation)but there are more of them.We have assumed the camp for the RCC dam construction costing about 20 percent less than that for the embankment dam concept (factor of 18.75%was used in calculations). 4.3 Project Access Cost It has been assumed that the rail line can be installed at the average rate of $4.7 million per mile based on Alaska Railroad estimating guidelines. 4.4 Cost Summary A comparison table of the Low Watana options is presented as Table 4.4-1.Detailed cost estimates are presented in Appendix B. November 29,2010 Page 17 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept Table 4.4-1:Cost Comparison of Selected Low Watana ICRD and RCC Alternatives Low Watana Non-Expandable Low Watana Low Watana RCC -Low Watana RCC -Low Watana RCC Line Item Name ICRD (1)Expandable ICRD (1)Non-Expandable Expandable Gravity Arch Total Estimated Const.Costs (Billions $)4.50 5.00 3.90 4.20 3.60 Low Watana Non-Ex pandable Low Watana Low Watana RCC -Low Watana RCC -Low Watana RCC FERC Line #Line Item Name ICRD (1)Expandable ICRD (1)Non-Expandable Expandable Gravity Arch 771A Engineering,Env,and Regulatory (7%)$236,000,000 |$259,000,000 |$203,200,000 |$217,900,000 |$186,600,000 330 Land and Land Rights $121,000,000 |$121,000,000 |$120,900,000 |$120,900,000 |$120,900,000 331 Power Plant Structure Improvements $115,000,000 |$159,000,000 |$121,219,000 |$161,389,000 |]$121,219,000 332.1-.4 Resenoir,Dams and tunnels $1,537,690,000 |$1,718,000,000 |$1,425,110,000 |$1,472,944,000 |$1,220,892,000 332.5-.9 Waterways $590,000,000 |$677,000,000 |$276,342,000 |$387,367,000 |$242,655,000 333 Waterwheels,Turbines and Generators $297,000,000 |$297,000,000 |$297,000,000 |$297,000,000 ]$297,000,000 334 Accessory Electrical Equipment $41,000,000 |$41,000,000 |$40,000,000 |$40,000,000 |$40,000,000 335 Misc Power Plant Equipment $21,000,000 ]$32,000,000 |$21,000,000 |$32,000,000 |$32,000,000 336 Roads,Rails and Air Facilities $232,000,000 |$232,000,000 |$254,700,000 |$254,700,000 |$254,700,000 350-390 Transmission Features $224,000,000 |$224,000,000 |$207,362,000 |$207,362,000 |$207 362,000 63 Main Construction Camp $180,000,000 |$180,000,000 |$123,800,000 |$123,800,000 |$123,800,000 399 Other Tangible Property $16,000,000 |$16,000,000 |$15,800,000 ]$15,800,000 |$15,800,000 71B Construction Management (4%)$135,000,000 |$148,000,000 |$116,100,000 |$124,500,000 |$106,600,000 Total Subtotal Subtotal $3,745,690,000 |$4,104,000,000 |$3,222,533,000 |$3,455,662,000 |$2,969,528,000 Total Contingency [Contingency (20%)$749,138,000 |$821,005,200 |$644,506,600 |$691,132,400 |$593,905,600 Total Total Estimated Const.Costs (Million $)$4,500 $5,000 $3,900 $4,200 $3,600 November 29,2010 Page 18 Final (1)From HDR 2009 R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept 5.0 Project Schedule The ICRD configuration has two basic construction fronts;dam and powerhouse,which are relatively independent of each other.With a surface powerhouse near an RCC gravity or gravity arch,the construction area is less independent and a higher level of coordination would be required during construction operations. 5.1 Dam The anticipated construction season for RCC or conventional concrete construction is 5.5 months,with a maximum of 165 working days.Certain activities such as aggregate production and underground work may be continuous,year-round operations.The ICRD dam configuration has two basic construction fronts;dam and powerhouse,which are relatively independent of each other.With a surface powerhouse near an RCC gravity or gravity arch,the construction area is less independent and a higher level of coordination would be required during construction. Previous studies (R&M 2009)for the Full Watana RCC option have assumed an average daily placement rate of 20,000 cy/day,which equates to an average monthly placement rate of 600,000 cy/mn.Currently the maximum peak placement observed rate of RCC placement is 525,000 cy/mn (MD&A figures for a single production plant).The significantly higher monthly placement rate for the Watana Dam is due to the plan of installing two separate large RCC production facilities.In order to optimize the RCC construction during the short construction season at the site,significant production facilities will be needed.The nominal production capacity of each of the two RCC plants will be similar to existing recent projects.The Watana site is expected to benefit from aggregate production for more than the 5.5 months assumed for dam placement as well as advantageous location of the Site A quarry.Aggregate production will commence at least 12 months prior to the start of RCC placement. Production are estimated to be double shifts,6 days per week for 8 to 9 months per year and must be planned to ensure that aggregate production does not impact critical path.The ratio of nominal daily production capacity to average production rates will be approximately 2.By factoring the volume of the dam and using average production rates ranging between 20,000-15,000 cy/day,the approximate dam construction time is shown below in Table 5.1 Table 5.1-1 Time Required for RCC Dam Placement Alternative Volume (million)Time to place material Full Watana 15.0 4.5 to 6 years Low Watana Gravity 8 2.4 to 3.2 years Low Watana Gravity Arch 6.5 2 to 2.6 years 5.2 Powerhouse A surface powerhouse would be more subject to climatic constraints than an underground powerhouse and therefore the construction season for exterior work involving concrete placement would have similar limitations to dam placement.Once the powerhouse shell is completed,equipment installation could continue through the winter season. The underground powerhouse is subject to greater geotechnical uncertainty which could result in modifications to design plans and potential project delays. The powerhouse excavation for the surface powerhouse may begin prior to diversion tunnel and cofferdam completion (potentially providing material for the pre-cofferdam and cofferdam).Similarly the south abutment excavation and grouting may be performed concurrently with the diversion construction.Through careful scheduling,it may be possible for the excavation above river level on the south abutment and excavation for the surface powerhouse to be completed at approximately the same time as the diversion completion.After diversion,the dam and surface powerhouse foundation excavation and treatment may continue.The diversion cofferdams may also function for river crossing such that the north abutment excavation and treatment may begin. November 29,2010 Page 19 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept Once the powerhouse shell is completed,equipment installation could continue through the winter season.Therefore the completion of the surface powerhouse shell is a significant project milestone,such that it should have a target completion date that will not cause it to be a critical path item. 5.3 Combined Dam and Powerhouse Schedule The schedule for the ICRD Low Watana dam (HDR 2009)shows similar time for dam construction and powerhouse/transmission lines.More detailed review is required to determine which element is on the critical path.The RCC dam is expected to be constructed in less time than the ICRD dam,which will place the powerhouse onto the critical path for construction. At this point,given the current level of design and schedule we are not able to demonstrate significant schedule advantage for the overall!project with the RCC scheme.However it should be noted that other projects using RCC dams that allowed early completion of the dam construction and impoundment of the reservoir,found the benefit of early generation revenue and availability of additional construction and management resources combined to allow powerhouse construction and equipment installation to be significantly accelerated to significant economic advantage. November 29,2010 Page 20 Final R&M/Hatch/Linard Supplemental Report -Low Watana RCC Concept References 1. 10. 11. 12. 13 Actes,1982.Susitna Hydroelectric Project,Feasibility Report.Volumes 1-7.Prepared for the Alaska Power Authority Harza-Ebasco Susitna Joint Venture,September 1983,"Winter 1983 Geotechnical Exploration Program,Volume 1,Main Report” Harza-Ebasco Susitna Joint Venture,November 1985,"Susitna Hydroelectric Project,Draft License Application,Volume 1,Exhibit A,Project Description. Harza-Ebasco Susitna Joint Venture,November 1985,"Susitna Hydroelectric Project,Draft License Application,Volume 12,Chapter 6 -Geological and Soil Resources” HDR 2009,Susitna Hydroelectric Project,Conceptual Alternatives Design Report,Final Draft, November 23,2009 R&M 2009 Susitna Project,Watana and High Devil Canyon RCC Dam Cost Evaluation Kollgaard,Eric B.and Chadwick,Wallace L."Development of Dam Engineering in the United States,Prepared in Commemoration of the Sixteenth Congress of the International Commission on Large Dams by the United States Committee on Large Dams”1988 USACE,Dec 31,1985."Engineering and Design Hydropower,Engineering Manual 1110-2- 1701” USBR,1958."Hydro-electric Power Plant Costs,Drawing 104-D-701,Series 150 Estimating, United States Bureau of Reclamation,dated:Nov 7,1958” American Society of Civil Engineers (ASCE),1989."Civil Engineering Guidelines for Planning and Designing Hydroelectric Developments.Volume 3 -Powerhouses and Related Topics” USACE,2010."HEC-RAS River Analysis System Hydraulic Reference Manual.Version 4.1. January 2010” USBR,1986,"Engineering Monograph No.3 -Welded Steel Penstocks .USBR,2010."Bureau of Reclamation Construction Cost Trends,Jan 2008 -Jul 2010” 14. 15. 16. USBR,1983."Bureau of Reclamation Construction Cost Trends,Jan 1980 -Oct 1983” Acres,1982.Susitna Hydroelectric Project,1980-81 Geotechnical Report.Volume 1 Acres,1982.Book B -Watana Dam Development of Unit Costs November 29,2010 Page 21 Final Figures NOTICE TO READER-Some of the Figures have been taken from previous Susitna Project reports and the conventions for cardinal direction are inconsistent from report to report in many cases,i.e.North is the top of the page on some figures and the bottom of the page on others.The Figures were not re-drawn for this report.New figures use the convention of North at the top of the sheet.Many old figures use the convention of stream flow from left to right;the Susitna River in the area of the Susitna project flows from east to west. List ofFigures Figure 2.2-1 Low Watana ICRD Expandable Plan Figure 2.2-2 Low Watana ICRD Expandable Section Figure 2.2-3 Low Watana ICRD Expandable Stage 2 Section Figure 2.2-4 Low Watana ICRD Power Facilities Figure 2.4-1 Low Watana RCC Expandable Plan Figure 2.4-2 Low Watana RCC Expandable Sections and Details Figure 2.4-3 Low Watana RCC Expandable Elevation Views Figure 2.4-4 Low Watana RCC Non-Expandable Plan and Detail View Figure 2.4-5 Low Watana RCC Non-Expandable Sections and Details Figure 2.4-6 Low Watana RCC Non-Expandable Elevation Views Figure 2.4-7 Low Watana RCC Non-Expandable Profile Figure 2.4-8 Low Watana RCC Non-Expandable Gravity Arch Plan Figure 2.4-9 Low Watana RCC Non-Expandable Gravity Arch Sections and Details Figure 3.2-1 Low Watana Rail Access Figure 4.1-1 Borrow Areas 11/29/2010 €747,000Ny N3,226,000 -.-- -2 so q .------VP ]: he a AK,oC GALLERY ACCESSThi oe _| 7 RTSAS YN DA RINAGE OUTLET TUNNEL ST"><GALLEAY ACEE:ih EiSy -=a Ss =ge -WAIN ACCESS TUNKEL >.-=a pe -YY = So eag-TTR d 4 C2009syFOUPLETFACILITIES TUNNEL.FZ cg <}SEF tt q is _a”&at y A SG 6”,L-SPILLWAY CHUTE q(fh vom WW A a aN DOWNSTREAM COFFERDAM TOf(\S Saar:S . BE REMOVED AT THE END OFpcaeSsWOoff_°|CONSTRU CTION s CIOONDPOWERINTAKELe"a 7=SsmaeS [)200 400 FEET 5 ei oy,y cess roan |scate See! ;CI x . N,manaacmeast®|ALASKA POWER AUTHORITY PNTROL BUILDING "a5,BUSITNA HYORGELEGTRIG PROJECT-STAGE T (WATANA 7N\end ee[ »GENERAL ARRANGEMENT2399 EXHIGEE-F J EXHIGH t se } ree Ns ! 2-34:TRANSMISSION LINESTQGOLDCREEK | || AUG,1985 rooLo1s00 1800 ITo0 ELEVATION1NFEET1400 ni CEL 202TWOTE STAGE I AXIS |te I Axis ''/ STAGE OE GREST LEVELIMAGINARYLINE(SEE NOTE 4)2018EL.20007,,SSE979 FLow-IMAGINARY LINE (SEE NOTE 4)J EL.9S.3 e.1925 2.4 STRIPPEO GROUNO !SURFACE zCOARSE:STRIP PEOFILTER GROUND SURFACEOVERBURDENEXCAMETION 'TOP OF ROCK =COARSE ---f------.fine FIER FRYER ay ;1 OF ROCKfT4TURTROT,TR t TRO a{roe oF sounp rock |CREST DETAIL LIMITS.OF REMOVAL FROM SCALE 8 OVERBURDEN EXCAVATION DETAIL SCALE C woTes: 1.INCLUDES 2°SETTLEMENT GVERBUILO. 2.DRAINAGE AND GROUTING DETAILS SHOWN ON PLATE Fa. 3.ROCK RAKING WILL BE DONE WITHIN 40 FEETflowDANAXISOFTHEUPSTREAMSLOPETHROUGHOUTTHE ZONES OF PERMANENT RESERVOIRSEECRESTanreFLUCTUATIONANDFREEGOARO.N7:4 IMAGINARY LINES EXTENDED FROM EOGE OFNORMALMAXIMUMOPERATINGLEVEL5t000 /Fb 2027 (NOTE 1)CREST TO LIMITS OF OVERGURDEN REMOVAL =fi 5 DOWNSTREAM COFFERDAM To BE REMDVEO AT G UPSTREAM COFFEROAM(FOR OE TAKS SEE PLATE FIO) SEE OVERBURDEN EXCAVATION OETAIL COARSE FILTER: 18400 UPSTREAM 283° INE FILTER FINE FILTER COARSE FILTER IMPERVIOUS FILL 4, 'SHALLOW AREA GROUTING ANDfSetiTREATMENT(TYPICAL) THE END OF CONSTRUCTION |DOWNSTREAM COFFERDAM:(FOR DETAILS BEE PLATE FIO)ACCESS ROAD SEE OVERBURDEN EXCAVATION DETAILEL1495 (NOTE 5) 4 2000 1800 i700 i600 1334NINOLLYA3T31500 ie OVERBUROEN(SANDS B GRAVELS 1400 41300 >rs ra -DRAIN HOLES |xX'TOP OF SOUND Peo"pour CURTAIN OUTING AND DRAWAGE GALLERY (NOTE 21 BEDROCK SURFACE DRAIN HOLES 1 1 im 1 1 '.1 1 1 1 1 1 1 1 1 !1 L10+00 5400 '000 500 10+00( TYPICAL SECTION -DAM EMBANKMENT (MAXIMUM HEIGHT) SCALE A 100.200 FEET9 9.scALe A eee 1 1 15400 DOWNSTREAM manta gensce |acaska POWER AUTHORITYBUSITNAHYOROELECTAIGPHOJECT-STAGE T(WATANA OAM TYPICAL SECTION AND DETAILS 50 {OO FEET SCALE B 200 S00FEET SCALE C L AUG,1985 jo---DAM AXIS EL.2200 (NOTE1}_£ eL2sa-_x STAGE I OAM AXIS:WORMAL MAKIMUM OPERATING QEVEL EL.21a5 STAGE TE ROCK FILL STAGE IFILL REMOVED: CORE MATERIAL REMOVEO;SURFACESCARIFIEDATTIMEOFSTAGEIIFILL PLACEMENT, FILTER it i CREST DETAILFILTERSCALEC+FINE FILTER 4 }A ATABLE EXCAVATION DETAIL FILL OETAIL 2400 CONNECTION DETAILS 7400 {SCALE 8 :!|NOTES: id z300 : . .2300 J DAM axis 1,INCLUDES 5'SETTLEMENT OVERBUILD. NORMAL MAXIMUM .DRAIN AG!NO GROUTING DETAILS SHOWN||200 OPERATING LEVEL -EL 2210 (NOTE 1)®ON PLATE Ae." 2 aif SEE CREST DETAR.3.ROCK RAKING WILL BE DONE WITHIN 40 FEET e200 iy Flow OF THE UPSTREAM SLOPE THROUGHOUT THEve- EE NOTE 3 /ZONES OF PERMANENT RESEAVOIR 200 MINIMUM OPERATING.s FLUCTUATION AND FREEBOARD.deLEVELEL.2085 7 100 {-/Hh 4.STAGE J CONSTRUCTION SHOWN WITH BOLOrta i \OUTLINE. |2000 Z\i]z 5.DOWNSTREAM COFFEROAM TO BE REMOVED 2000j7--SEE CONNECTION -AT THE END OF CONSTRUCTION.| ih OETALS 245iso[=|71300ry aisn =5§roof .ROCKFILL AOCKFILL:diaoo'z1&oO . z|i 2 &UPSTREAM COFFEROAM aana(FOR DETAILS SEE PLATE FIO}q io |aty&1700 00 5bawhsFINEFILTER]FING PRLTER DAM AXIS PB ta COARSE FILTER'600 COARSE FILTER i ACCESS ROAD 1600MPERVIOUSFILL-: h ectees'300 ms 1500 | '. OVE J aivABURDE” 'Woof /SANDS ongvels- a : .&OVERBUROENtyZ£ta00ener4_- _-verre SANDS 8 GRAVELS. Toe oF SoUuNi "¥,A-DRAINAGE CURTAIN :400 '0 ROCK = "GROUT CURTAIN OUTING AND DRAINAGE GALLERY (NOTE 2)"BEDROCK BURFACE 'I \-ORAINAGE CURTAIN R00 :} 3 1.1 7%1 1 4.4 4 1 4.1 1 1 n 4.A u 1 rm 4 1 tL ai re nm re 4 rm 1 1.=4 4 4 2 1 15+00 UPSTREAM toreo s+00 oreo :5+00 10400 , 15+00 DOWNSTREAM \ ||barre)Jauaska POWER AUTHORITY_!:TYPICAL SECTION DAM EMBANKMENT (MAXIMUM HEIGHT)QUSITNA HYDROELECTRIC PROJECT-ATAGESIT (WATANA)SCALE A OAM it .°100-200 Fret TYPICAL SECTION AND DETAILS |scce Se =EXHIBIT F |.puate 77°50 OO FEETScate-o--nn .9. ;sce ed AUG.1985 ARI ae"s=aan F @ BUS SHAFT GROUTING B DRAINAGE men? %kByaionSe \ nahSTONNEL 2,20=- .-aaayanNef ><-_SURGE CHAMBER |||L_powernouse \ A VENTILATION,GALLER' |SURFACE CONTROL SUILDING i |- v3 ||POWER anal CONTROL BUILDING (PROVECTED)ti e200 CONTROL BUIL!7]2200|ee : ¥|=!2100 2100 EL.2029 ------_--OPERATING LEVELEL,2000oP!'TING LEVEL EL.|rt 2000 is ne 2000 oorby F.6 BUS SHAFT i JECTED) 1900 MINIMOM OPERATING i + A 'SHAFT!yoo ecess ROUNO SURFACE5VevELEt1Bs0i(PRovEC TED)_BEDROCK SURFACE rt||ry EL.I795 1 VENT SHAFT 5JZ4800=i800 & z Cys24!\.0,CONC.LINED TUNNE = <=ole]200 FEET{|Fs w00 =scave anal:4 (700 TRANSFORMER a'|ALLERY OUTLET FACILITIES n -a-|4 TUNNEL (PROJECTED)4RouiNKae1800AaOSSeer7)$i MODIETED HORSESHOE CONC:1600 ||grourma a MINED TAIL \maggacmnens?|ALASKA POWER AUTHORITYl.\s00 A GaLLeRY-+4 |1800 SUSITNA HYDROELECTRIC PROJECT-STAGE T(WATAHA) %Suicaiik, :a:POWER FACILITIES 1 High IpRessURE aens GENERAL ARRANGEMENT|W400 GROUTING 1400 EXHIBIT _F it PLATE F 21. DRAIN HOLES-__J i 1000010-00 18400 00 28400 PROFILE AUG.1985 Plotled:Nov09,2010-9:47amDrawing:P:\CAD_Proj\LIBRARY\PROJECTS\H332639_SusitnaLowWotanaRCCDam\WORK\FIGURES2-4-1TO2-4-3.dwgFULL WATANA OUTLINE EDGE OF CONCRETE owe.WORK\WATANARCCDAMCONTOURangRing=LowwoPOWERHOUSE SL 18D,STEEL FUTURE LINED PENSTOCK (TYP),./.--EXPANSION TS\HRYPRO24 co F 271.D.DIVERSION 7%Z : _f\-""TUNNELS fo fo A ec DIVERSION TUNNEL --INTAKE CONTROLS y a a |"a a"" a ' ra j :|”-a cee van i 4 7 a" ae a Pa .. a va a _p FUTURE EXCAVATION aFOREXPANSION _ STAGE 1 -JNVEL,1785 STAGE 2-INVEL.1970 L TRAINING WALL FOR 2-77 EXPANDED INTAKE "INTAKE ACCESS ROAD ay FUTURE EXPANSION 24"1D.CONCRETE /ee " LINED PENSTOCK- _ a i meeeaSHAFTSyA es Low Watana RCC Expandable -Plana|_ie )400 800 A-SUSITNA PROJECT\AEA a" / I Gi : é i a /U4 we"<.4."a ra .4Loara o " fou Z ,f 4 wa uo a " Z va " FIGURE 2.4.1 BERS MiREMCONSULTANTS,INC, ZHATCH FULL WATANA NyFULLWATANACRESTEL.2210.0 - SPILLWAYEL.2185.0 'Ch _te 4 ey,LE S&B°"a 1 \e7 CI BAFFLEotLOWWATANAoNCRESTEL.2025.0 "At MAX.OPERATING LEVEL WALL 7a yw__EL.2000.0 TVA,r EL.19650 FULL WATANA |\_GROUTING AND LOW WATANA DAM PROFILE y DRAINAGE GALLERIES MIN.OPERATING LEVEL DETAILNso}EL.1850.0 __y_EL.19500 1230 or 20.0'a Tpee ¢ial Qo"o|__EL.1700.0 2 E Av fa P|PyAe 4 sr a ';[BASE PLATFORM at eb.15800 co,|3 an INVENTIONALRIVERBEDTOPOFD/S COFFERDAM ve \US COFFERDAM CONCRETE <EL.1450.0 CREST EL.1470.0 Y/Y =aN EL.1450.0 _|3.0 (TYP)Z INSTRUMENTATIONGyYWfy,GALLERYho SS EL.1350.0peri[pep pope mere \ii idl boi io ii i i SLURRY RIPRAP BACKFILL TRENCH DETAILCONSOLIDATIONDRAINAGE1"=30" GROUTING 915.0" |CREST EL.2025.0 t |_-¥._PMF EL.2026.8 \PIER EL.2019.0 SECTION (A\\ GROUT CURTAIN SPILLWAY CREST Os \EL,2000.01"=200 1-V \ "FLOW |le3ebes4TOPOFWALLA CONVENTIONAL EL.1485.0 7 CONCRETE MAX.TWLVEL.1478.0 ”ale =a c =SPILLWAY ”rs)LL PIERS NORMAL TWL ,|VEL.1457.0 a ua _--___]a .SL rs FIGURE 2.4.2 y .Low Watana RCC Expandable ERS Moe ..REM CONBULTANTE,NC. SCALE:1"=200°SECTION (B DETAIL ax Sections and Details CO 1"=30°1"=50"SUSITNA PROJECT A HATCH'0 -200 400 -er,LOA AEA FUTURE EXPANSION SPILLWAY CREST 2300 aaa 2100 SPILLWAY CREST es =.us :a”aN1900+-/NOTE:me oy 4 444 .4 GROUT CURTAIN NOT SHOWN 1850 =*5 -7 =GROUTING AND FOR CLARITY.CURTAIL WILL ° «o8 ;4 4 DRAINAGE GALLERIES EXTEND TO A DEPTH OF 4 & 4 .(TYP) 4709 |}APPROXIMATELY 2/3 THE 1700 2 <4 DAM HEIGHT 7 2 3 . 4 24°1.D.CONCRETE FUTURE EXPANSION 1500 1550 SE<5WASSESRee LINED PENSTOCKS -)[PENSTOCK 27"L.D.DIVERSION TUNNELS ad SES ESSesSes d \pUISINV.EL 1460°ORS -- DIS INV.EL 1450"SSS INSTRUMENTATION GALLERY1300 BASE PLATFORM ELEVATION THRU GALLERIES SECTION (B 1"=300'\24.V FUTURE EXPANSION 2300 I...CREST2100TRE,WiLLL:ay STEPPED SPILLWAY Y Yi YA Dennenei7.2085 Vide LELLLL LLL 1900 Ste is f-age a vif 1700 --<<_<-_<-=----- --_-------F} a Ht 4 t fe FUTURE EXPANSION \PENSTOCKS 27'L.D,DIVERSION TUNNELS CS_--f /USINV.EL 1460 8 8 ff 7 A = DIS INV.EL 1450 ene 1300 Lote uo.steeL LINED PENSTOCK (TYP) DOWNSTREAM ELEVATION .SECTION (C) 1 1°=300"24.:FLowWatanaRCCExpandable-Elevation Views AEA300 FIGURE 2.4.3 MRoM RGA CONBULTANTE,ING. ZHATCH \ WN SURFACE STORAGE AND PARKING EL.1450 TAILRACE ;c eee /)Sy /a '|.271.0.DIVERSION x y 4 TUNNELS NN a / ."/4 Noe "2200 "a "4 ete 2n <a -88 EL.1965 pw ONG enn ee .a i ,aEL.1850,C\IK ee foo+/>aN a,DY me "ete NO |'\\=/_=DIVERSION TUNNEL ML |)7 INTAKE CONTROLS se,{|i LAN Le &*-_-.we ."a "BL.1850 (|: Ff at (, INTAKES TRASHRACK\p 15'1.0.STEEL LINED PENSTOCK (TYP) 24'1.0.CONCRETE LINED PENSTOCK DETAIL 1 SCALE:1”=200° es 0 200 400 a i ()600 1200 FIGURE 2.4.4 j Low Watana RCC Non Expandable RSM oe #Plan and Detail View meen cones Pe SUSITNA PROJECT - i <HATCH toeIEAas=LomReteBCGROUTING AND DRAINAGE GALLERIES LOW WATANA kot MAX.OPERATING LEVEL Cl 'y EL.2000.0 Cl BAFFLE EL.1965.0 =WALL, LOW WATANA 'TMIN.OPERATING LEVEL EL.1850.0 y_EL.1850.0 200 -DETAIL 2\1"=30°(2.4.4) EL.1700.0 oaEc Ny 15.2")8[BASE PLATFORM EL.1850.0 - RIVERBED TOP OF D/S COFFERDAM \US COFFERDAM ;[e 1450.0 f CREST EL.1470.0 a,aN Et,14500 CONVENTIONAL _J 2 INSTRUMENTATION a CONCRETE < GALLERY 'EL.1350.0 3.0"(TYP) -.Pall t <rf :°.Hy t v .i T :\> :- odo tyro dopo to bt toto bob to}or booted |Jd Poi d dbo db GoGo EG EG ot Gd EG a GLE LG Gg SLURRY RIPRAP BACKFILL \TRENCHCONSOLIDATIONoADRAINAGE'NY \Ny GROUTING i DETAIL 915.0 \1"=30" i 1 \ NO CREST EL,2025.0 I JPME EL.2026.8\ \GROUT CURTAIN PIER EL.2019.0 _--SSECTION(A)oF 1°=200"(24.4)| 'SPILLWAY CREST EL.2000.0 ,__FLOW_ TOP OF WALL A al&al&30 EL.1485.0 oe ale||\_CONVENTIONALMAX.TWL CONCRETE W__&L.1478.0 yi | "ale SPILLWAY V NORMAL TWL a"BIE |"PIERSVv__EL 1457.0 DETAIL (4=va 1230"yy, :LA PEE]eb.1447.5 i ow tt _es 6 ve ete ost FIGURE 2.4.5 SECTION /B\Y Low Watana RCC Non Expandable mERSMom ..REA CONGULTANTS,OC. SCALE:1”=200°1"=30 Le)Sections and Details SUSITNA PROJECT 0 200 400 AEA ZHATCH feranoytans=eeeaeoe2300 "= POWER INTAKE 2100 SPILLWAY CREST /CONTROLee'\I ¢CU I ld ut Ti nit ie =e a I J @ A6!s Fam foods rn1965<=;7 -==;\1900 --|NOTE:none a4 4 4 94 GROUT CURTAIN NOT SHOWN 1850 = = -= 3 5 z 5 al FOR CLARITY.CURTAIL WILL ,¢ee ee a7 a bello GROUTING AND EXTEND TO A DEPTH OF eg:ee <Me DRAINAGE GALLERIES 1700 pm APPROXIMATELY 2/3 THE 1700 a Pra - 4 (TYP) DAM HEIGHT o a \LAo¥.:24 1.D.CONCRETE 1550 st LINED PENSTOCK (TYP) 1500 =g See oeSERRE.27'I.D.DIVERSION TUNNELS SS eeu,/S INV.,SEREENS 25DISINVEL1480SSS INSTRUMENTATION ;GALLERY1300 eee ments BASE PLATFORM ELEVATION THRU GALLERIES SECTION /B) 1"=300"\2.4.4/ 2300 oo STEPPED a2100= SPILLWAY _-TL T ne IL Lif I I I se 7 Ay i ee 1900 Ste ae tt /| 1700 fled bond ini 24'LD.CONCRETE ut LINED PENSTOCK (TYP) 1500 - "1 27 LD.DIVERSION TUNNELS =>>=i U/S INV,EL 1460"mnD/S INV.EL 1450°Tere 1300 LL 15'1.0.STEELDOWNSTREAMELEVATIONLINEDPENSTOCK (TYP)FIGURE 2.4.6 SECTION (C)MRS Mo 300 1"=300"\2.4.4/Low Watana RCC Non Expandable «Elevation Views BOM COMOTANTE SUSITNA PROJECT = 600 aca LZ HATCH300 Drawing:P:\CAD_Proj\LIBRARY\PROJECTS\H332639_SusitnaLowWotanoRCCDam\WORK\FIGURES2-4-7.dwgPlotted:Nov09,2010-9:48amXrefPOWER INTAKE CONTROLS_-__/NORMAL ||I [y CREST EL 2025.00MAX.POOL yy EL 2014 7 GROUTING AND DRAINAGE GALLERY (TYP) EL 1965" NX NORMAL Ree aNMIN.POOL 48"1.0.VENT/D conventiona |INSPECTION SHAFTvyEL1850"(al y EL 1850° r-24'|.D.CONCRETE SILL LINED PENSTOCK TINVERT y Eb 1785"TTTITTEO__wEt 1700 1 305"|TURBINES |78 7 1 46_|32 |48"Q__wEL 1550 ROOF !TRANSFORMER y EL 1830'|TRANSFORMER DECK |TAILRACE TRAINING WALL '[y EL 1485"wer-24'1.D.CONCRETE Xe NORMAL TW. LINED PENSTOCK r-15'1.D.STEEL MIN.T.W.7 yy _EL 1457LINEDPENSTOCK|-w_EL 1450 = . 1=a =|...|----3 oN to Dee?cur OFF WALLyEL1404"AISyBOTTOM OF \EL 1379 \DRAFT TUBE TTT 18"THICK CONCRETE EL 1384 4H:1V SLOPE TAILRACE APRON ORAFT TUBE 225'450° | 200° i SCALE:1”=100°FIGURE 2.4.7 RSM oeie)100 200 REM CONSULTANTE,ING.Low Watana RCC Non Expandable -ProfileSUSITNAeased gz HATCH an Mee saanneremcmens amet a """”oa noe ZC sf i v4 vo " ,4 a" '7 °,a" ene i va "4 -F ee ae Pa </":/a eenenee meee -_.™a settnepeeenneee /JZ "' f ,"a Y1909ee/"Pa :-A THRUST BLOCK DIVERSION TUNNEL a Wo nc *SECTION _/INTAKE CONTROLS.” sect tetee _Pea Lo om a " cet nee ;Pe ee 1800,aan Ny "16, SL ys 20)_S N _ SNe ;Ky'\\\A \4 TAILRACE TRAINING WALL 18°1.D.STEEL LINED PENSTOCK (TYP)a 24'1.0.CONCRETE 4LINEDPENSTOCK---THRUST BLOCK een SECTION eo POWERHOUSE - a an"oo”. Y . ene on \ yOLL a f "- "Z a "// oo f"s" . ven 4 a<- -" a a a" \-=PRE-COFFERDAM va Ko -/-RCC COFFERDAM - --”a yanae4 naa - ao so i - ue }" a ae oO vo FIGURE 2.4.8 BERS MiROMCOMEULTANTE,ING. ZHATCH Low Watana RCC Non Expandable Gravity Arch -Plan SUSITNA PROJECT AEA (ereBCCDiCONTIogPLCAOPre\RRMIYFOECTEAEENGDDSets-LineakeMOCNOAEANBO,tgANOANOUNS2-4-4101-4-brpneLOW WATANA Ny MAX,OPERATING LEVEL Kit oO LAy_£L.2000.0 Ke EL.1965.0 =LJ -sarrte GROUTING AND LOW WATANA WALL arDRAINAGEGALLERIESMIN.OPERATING LEVEL \ EL.1850.0 wv _EL.1850.0 T 20.0! : LOW WATANA DETAIL (1GRAVITYDAMPROFILEmaarNAEL.1700.0 1"=30 \2.4.8/ INSTRUMENTATION BASE es {|______-J GALLERY 'PLATFORM oS PRE-COFFERDAM -a EL.1850.0 RIVERBED TOP OF D/S COFFERDAM |:RIVERBED EL.1450.0 CREST EL.1470.0 |EL.1450.0 30.0 >ala a 7 s x "e oe i oS RIVER ALLUVIL ae : EL,1350.0 ToeeeeeeOeOaSLURRYbobo'to t 4 Va joi ot ot t tf Gt Gf tah ot Gt TRENCH SPILLWAY 3 OoCONSOLIDATION_]DRAINAGE \PIERS 8 GROUTING C 544,02"\\ \SECTION ("A ee DETAIL 21"=200"(2.4.8)|<GROUT CURTAIN \1"=50'\2.4.8/\SCALE:1"=200°i \ 0 200 400 \Nv 'y_PMF EL.2026.8 _ =alt105ale TOP OF WALL TyEL.1485.0 CONVENTIONAL =7 MAX.TWL CONCRET c-W___EL 1478.0 FLOW _|3.0"=NORMAL TWL ra oe WEL.1457.0 /A=A an EL.14475 PT X_CONVENTIONAL Ny Te CONCRETE DETAIL 4\1"=30"SECTION ces FIGURE 2.4.9 Low Watana RCC Non Expandable RSM ...ROM CONBULTANTS,ING.Gravity Arch -Sections and Details SUSITNA ed zZ HATCH' LEGEND mmerwerewn RECOMMENDED ROUTE Fy ree a8Ee4SES3 festaS[4 5 asaLESwre. Tues. eaeean eee Railroad Alignment Dam Sites Gold Creek :* TUN Lom. AUIS ALASKA POWER AUTHORITY :et SUSITNA HYOROELECTRIC PROJECT coaton .ACCESS PLAN RECOMMENDED ROUTE a PLATELowvsMARCH190235 REFERENCE:BASE MAP PROM 503,1:£90,000HEALY,ALASKATALKEETNAMOUNTAGIS,ALASKA |"anesAwCRICANinconrcare| Figure 3.2-1 Low Watana Rail Access LOCATION MAP ceace GomerMEYfts fewer oHELICTCHANNEL QUARRYae,/\queo-a = TANA OAM SITE,LESENDLiYanatfiatTGs'Co]anmnows ouanny sire users rpareat \ : =/BORROW ants *", SITE 0 4 SneuerCHANNEL . ” " O,\ \\. sorrow(js FK\ Ei ron<(¢.iSA?5 i 5 f 2 MAES H SCALE |A WATANA BORROW SITE MAP FIGURE B.4,2,.13 Figure 4.1-1 Borrow Areas Appendix A Breakdown of Unit Cost Analysis for RCC 11/29/2010 Low Watana RCC Dam RCC Unit Cost Analysis November 3,2010 Low Watana RCC Assumptions/Totals USBR Construction Cost Index Total RCC Volume (cyd)7,600,000 USBR Category Concrete Dams Percent of Aggregate by Volume 80.3%Jan 1982 Factor 128 Total Required Aggregate Volume (cyd)6,102,800 Oct 2008 Factor 334 Est.Round Trip Haul Dist.From Borrow Pit A to Processing (mi.)1 Jul 2010 Factor 325 Low Watana Embankment 1982 Assumptions/Totals (Book B -Development of Unit Costs) Total Volume (cyd)6,200,000 Total Production Hours (hr)13,000 Avg Production Rate (cyd/hr)(Not in Book B)476.92 Est.Round Trip Haul Dist.From Borrow Pit E to Processing (mi.)4 *Costs used for 1982 Aggregate Production will be escalated to 2010 costs.Total aggregate volumes are very similar.Also the haul costs will be conservative since haul distance to Borrow Pit A is less than Borrow Pit E. Low Watana Embankment 1982 Aggregate Production Costs (Book B -Development of Unit Costs) Description Labor Materials Equipment Total Aggregate Processing $16,584,230.00 |}$2,930,400.00 |$36,322,000.00 |$55,836,630.00 Install &Removal of Plant $1,650,000.00 |$-$-$1,650,000.00 Total Aggregate Processing Cost ($/cyd)$18,234,230.00 |$2,930,400.00 |$36,322,000.00 |$57,486,630.00 Aggregate Processing Unit Cost ($/cyd)2.941 0.473 5.858 9.272 Aggregate Hauling Unit Cost ($/cyd)1.104 0.01 3.583 4.697 Total Aggregate Production Cost ($/cyd)$4.05 |$0.48 |$9.44 |$13.97 USBR Ratio Jul 2010:Jan 1982 2.54 2.54 2.54 2.54 Jul 2010 Total Agg Production Cost ($/cyd)$10.27 |$1.23 |$23.97 |$35.47 Total Cost of 4 ARAN Modumix {I}Batch Plants incl Installation $20,000,000.00 Total Batch Plant Unit Cost ($/cyd)$2.63 |$2.63 Cement &Fly Ash Cost ($/cyd)$-$48.86 |$:$48.86 RCC Placement Cost ($/cyd)$1.22 |$-$3.22 |$4.44 RCC production Cost ($/cyd)$0.75 |$-$5.05 |$5.81 Final RCC Unit Cost ($/cyd)$12.24 $50.09 $34.88 $97.21 RCC Labor Costs City Cost Index for Fairbanks,AK Division Installation Index 0241,31-34 Site &Infrastructure,Demolition 131.5 03 Concrete 115.3 Adjustment Factor for Overtime RS Means Work Day (hr)8 Low Watana RCC Work Day (hr)10 Pay Rate Increase for Overtime 1.5 Ajustment Factor 1.375 RS Means 2010 -:Total Hourly ;Total HourlyWervorsTradeTotalHourlyRateAdjustmentRateincladreRateatWatana .incl.O &P ($/hr)Overtime ($/hr) 7|Equipment Operator (med.)-Dozer $64.30 1.375]$88.41 131.5|$116.26 5 7|Equipment Operator (light.)-Roller $61.85 1.375!$85.04 131.5]$111.83 a 7|Laborers -RCC Placement $48.45 1.375!$66.62 131.5]$87.60 5 7|Foreman Average,Outside $68.55 1.375]$94.26 131.5|$123.95 5 5|Laborers -Flagman (Directing Truck Traffic)$48.45 1.3751 $66.62 131.5]$87.60 Ee 4|Mechanic -Trucks,Dozers &Rollers $66.75 1.375]$91.78 131.51 $120.69 8 1|Electrician -Converyors &Equipment $72.85 1.375]$100.17 131.5]$131.72 a 25|Truck Drivers (Light)-8 cyd Rear Dump $49.20 1.375{$67.65 131.5]$88.96 2 2|Truck Drivers (Light)-Fuel Trucks $49.20 1.375]$67.65 131.5]$88.96 a4 2|Equipment Operator (light.)-Skid Steer Loader $61.85 1.375]$85.04 131.5|$111.83 1|Site Supervisor $82.26 1.3751 $113.11 131.51 $148.74 68/Total Hourly Wages $1,218.15 Average RCC Production Rate (cyd/hr)1000 Total Labor Costs per Unit ($/cyd)$1.22 S 4|Batch Plant Operator $82.26 1.375]$113.11 131.5}$148.74 8 8|Equipment Operator (med.)-Front End Loader $64.30 1.375]$88.41 131.5]$116.26 8 2|Mechanic-Batch Plant $66.75 1.375]$91.78 131.5}$120.69 Oo 1}Electrician -Batch Plants $72.85 1.375]$100.17 131.5}$131.72 8 7|Laborers -Flagman (At Dishcarge Chutes)$48.45 1.375]$66.62 131.51 $87.60 a 1|Site Supervisor $82.26 1.375|$113.11 131.51 $148.74 23}Total Hourly Wages $753.75 Average RCC Production Rate (cyd/hr)1000 Total Labor Costs per Unit ($/cyd)$0.75 91 Total #of Workers,assumes (2)-10hr Shifts 182 RCC Equipment Costs City Cost Index for Fairbanks,AK Division Installation Index 0241,31-34 Site &Infrastructure,Demolition 131.5 03 Concrete 115.3 Assumptions /Variables Shift Duration (hr)10, Shifts per Day 2 Work Hours per Day 20 Average Production RCC Production Rate (cyd/hr)4,000 Average RCC Production Per Day (cyd/day)20,000 Total RCC Volume (cyd)}7,600,000 Required Days of Production 380 Construction Season (Months/Yr)5.5 Construction Season (Days/Yr}165 Minimum Construction Seasons.2.30 Total Number of Construction Season 3} Rental Rate Adjustment Factor for Unit Down Time Total Months in Operation per Year 5.5 idle Equipment Cost vs Operation 75% Total RCC Construction Seasons 3 Total Months of Operation 16.5 Total Months Idle 13.0 Daily Operation Costs Equipment Rental Costs RS Means 2010 -Hours of Total Equipment Total Equipment |Total Operation + #of Units Trade Total Hourly Rate |Operation Production Operation Cost clan Monthy Rental ar pertal Rentai Cost per Rental Cost per Total Ait Units Total Inct Cost Index incl.O &P($/nr)per Day Days per Unit Unit Unit 7|Dozer 200 hp 68.60 20 380 521,360.00 16.5 9,650.00 13.0 253,312.50 774,672.50 5,422,707,50 7,130,860.36 7{Vibratory Roller 35 hp 10.40 20 380 79,040.00 16.5 275.00 13.0 59,718.75 138,758.75 971,311.25 1,277,274.29 Ee 25|Truck,Dump,2-axle,12 ton,8 cy payload 33.35 20 380 253,460.00 16.5 2,025.00 13.0 $3,156.25 306,616.25 7,665,406.25 10,080,009.22 a 2{Fuel Truck (Used RS Means Water Truck Data}84.65 20 380 643,340.00 16.5 290,00 13.0 490,312.50 833,652.50 4,667,305,.00 2,192,506.08 c 1/Forklift,straight mast,21'lift,4WD 20.20 20 380 153,520.00 16.5 2,225.00 13.0 58,406.25 211,926.25 211,926.25 278,683.02 =2|Skid Steer Loader,1 cyd,78 hp 19.00 20 380 144 400.00 16.5 2,075.00 13.0 54,468.75 198,868.75 397,737.50 523,024.81 d 13|Pickup Truck,4WD.13.50 20 380 402,600.00 16.5 645.00 13.0 16,931.25 419,531.25 1,553,906.25 2,043,386.72 5 7|Laser Level -Grading 1.17 20 380 8,892.00 16.5 700.00 13.0 18,375.00 27,267.00 190,869.00 250,992.74 ®40|Floodlights,trailer mounted w generator -(4)300 watts 4.20 10:380 15,960.00 16.5 795.00 13.0 20,868.75 36,828.75 368,287.50 484 298.06 o 3{Misc Hand Tools 5.00 20 380 38,000.00 16.5 850.00 13.0 22,312.50 60,312.50 180,937.50 237,932.81 °7 Total Placement Equipment Costs 24,498,968.11 Total RCC cyd 7,600,000 Total Placement Equipment Cost per Unit RCC ($/cyd) $3.22 &]Front End Loader,10 cyd,620 hp 129.55 20 380 984 580.00 16.5 23,500.00 13.0 616,875.00 1,601,455.00 12,811,640.00 16,847 306.60 2|Forklift,straight mast,21"lift,4WD 20.20 20 380 153,520.00 16.5 2,225.00 13.0 58,406.25 211,926.25 423,852.50 $57,366.04 &8|Pickup Truck,4WD 13.50 20 380 102,600.00 16.5 645.00 13.0 16,931.25 419,531.25 956,250.00 1,257,468.75 8 8}Floodiights,trailer mounted w generator -(4)300 watts 4.20 10 380 15,960.00 16.5 795.00 13.0 20,868.75 36,828.75 294,630.00 387,438.45 8 2{Misc Hand Tools 5.00 20 380 38,000.00 16.5 850.00 13.0 22,312.50 60,312.50 120,625.00 158.621.88 iw 28 3 19,208,201.71 8 Ls Total sum of ail Batch Piants and Conveyence Systems (Assume Equal to all other Production Equipment Costs)$19,208,201.71 va Total Equipment Costs $38,416,403.43TotalRCCcyd7,600,000|Total Production Equipment Cost per Unit RCC ($/cyd)$§.05 RCC PRODUCTION Full Watana RCC Low Watana RCC Parameter US Standard Metric US Standard -Metric Quantity 45,000,000/Cy 11,468,300"7,600,000|Cy -11,468,300/2 Construction season (months/year)5.5)Mn/yr 5.5|Mn/yr 5.5iMn/Yr §.5|Mn/yr Construction seasons 5iYr 51Yr 3.00/Yr :;51Yr Placing days/year 165/Yr 160]Yr 4165/Yr _ 460/Yr Total required placing days based on avg daily 825|Dy 800/Dy 380]Dy 800)Dy placing rate :A Total placing days 825|Dy 800]Dy 495|Dy '800)|Dy z months 25|Mn 25{Mn 12.66666667|Mn 25)Mn Nominal monthly capacity 600,000/Cy 458,732|)°600,000/Cy 8 458,732)" Average daily placing rate 20,000|Cy 15,2911 Mo 20,000/Cy »15,294] Required daily average capacity 44,920|Cy 34,3441 N48 44,920|Cy 34,344|3 Required maximum month 1,200,000/Cy 917,464]py?1,200,000/Cy 917,464)n3 Required nominal capacity 15,000,000/Cy 11,468,300}n4°7,600,000/Cy 11,468,300) Mixer capacity,8ICy 6/2 8ICy :6ime Total mix time -start charge to complete 2|Min 2|Min 2)Min _2|Min discharge,min oe batches/mixer/hour 30/Per Hr 30]Per hr 30|Per Hr 4,=30/Per hr Vol/mixer/hour 235)/Cy 180)3 235/Cy 18013 Total #of mixers 10}Ea 10/Ea 10/Ea :10/Ea Nominal hourly production 2,350/Cy 1,800]e 2,350|Cy co ee or 800/35 Daily hours 20}Hr 20}Hr 20/Hr 20/Hr Nominal daily production 47 ,000/Cy 36,000/p4°47,000|Cy f 36,000}py3 Nominal monthly 1,175,000|Cy 900,000}y43 1,175,000|Cy :900,000/ye Ratio nominal to average 1.96 1.96 1.96 :1.96 Long term average monthly 600,000;Cy 458,732|M5 600,000}Cy cee 5 468,732 15 Total RCC placed 15,000,000/Cy 11,468,300]p43 7,600,000|Cy 11,468,300)4° Appendix B Detailed Cost Estimate 11/29/2010 SUSITNA PROJECT -LOW WATANA DAM OPTIONS COST SUMMARY Table 4.4-1:Cost Comparison of Selected Low Watana ICRD and RCC Alternatives Low Watana Non-Expandable ICRD Low Watana Low Watana RCC -Low Watana RCC -Low Watana RCC Line Item Name (1)Expandable ICRD (1)Non-Expandable Expandable Gravity Arch Total Estimated Const.Costs (Billions $)4.50 5.00 3.90 4.20 3.60 Low Watana Non-Expandable ICRD Low Watana Low Watana RCC -Low Watana RCC -Low Watana RCC FERC Line #Line Item Name (1)Expandable ICRD (1)Non-Expandable Expandable Gravity Arch 71A Engineering,Env,and Regulatory (7%)$236,000,000 |$259,000,000 |$203,200,000 |$217,900,000 |$186,600,000 330 Land and Land Rights $121,000,000 |$121,000,000 |$120,900,000 |$120,900,000 |$120,900,000 331 Power Plant Structure Improvements $115,000,000 f $159,000,000 |$121,219,000 |$161,389,000 |$121,219,000 332.1-.4 Reservoir,Dams and tunnels $1,537,690,000 |$1,718,000,000 |$1,425,110,000 |$1,472,944,000 |$1,220,892,000 332.5-.9 Waterways $590,000,000 }$677,000,000 |$276,342,000 |$387,367,000 |$242,655,000 333 Waterwheels,Turbines and Generators $297,000,000 |$297,000,000 |$297,000,000 |$297,000,000 |$297,000,000 334 Accessory Electrical Equipment $41,000,000 |$41,000,000 |$40,000,000 |$40,000,000 |$40,000,000 335 Misc Power Plant Equipment $21,000,000 |$32,000,000 |$21,000,000 |$32,000,000 f $32,000,000 336 Roads,Rails and Air Facilities $232,000,000 |$232,000,000 |$254,700,000 |$254,700,000 |$254,700,000 350-390 Transmission Features $224,000,000 |$224,000,000 I$207,362,000 |$207,362,000 |$207,362,000 63 Main Construction Camp $180,000,000 }$180,000,000 |$123,800,000 |$123,800,000 F $123,800,000 399 Other Tangible Property $16,000,000 |$16,000,000 |$15,800,000 |$15,800,000 |$15,800,000 71B Construction Management (4%)$135,000,000 |$148,000,000 |$116,100,000 |$124,500,000 |$406,600,000 Total Subtotal Subtotal $3,745,690,000 |$4,104,000,000 |$3,222,533,000 |$3,455,662,000 |$2,969,528,000 Total Contingency |Contingency (20%)$749,138,000 |$821,005,200 |$644,506,600 }$691,132,400 |$593,905,600 Total Total Estimated Const.Costs (Million $)$4,500 $5,000 $3,900 $4,200 $3,600 Page 1 of 61 (1)From HDR 2009 Page 1 of 61