Loading...
HomeMy WebLinkAbout409035 Soldotna to Nikiski Transmission Upgrades 2011adSoldotna to Nikiski 69 kV to 115 kV Transmission Line Upgrade Introduction The Alaska Electric &Energy Cooperative (AEEC)through ARCTEC has been awarded funds to build a 115 kV line between the Soldotna -Tesoro -Bernice and Nikiski substations. This project will complete a Kenai Peninsula industrial area 115kV transmission loop from the Soldotna substation to serve Tesoro,Bernice,and Nikiski substations.This will make Nikiski and Bernice generation more reliable by eliminating the existing single contingency failure of the radial 115kV transmission line from Soldotna-Tesoro-Bernice-Nikiski;and it will prevent the reduction of Bradley power flow to Anchorage due to stability limitations imposed by running other generation.The majority of this transmission path will be created by converting existing 69kV lines and substations to 115kV. Scope of Work Implementation A 115kV loop will be created by constructing a new 115kV line from the Nikiski substation to a new 115kV breaker position in the Soldotna substation.To greatly minimize new easements and right of way (ROW)needs and cost,the new line will use the majority of the existing 69kV line ROW from Soldotna, through the Beaver Creek and Marathon subs,to a point just before the Tesoro refinery site where it will intercept the new line out of Nikiski (refer to the North End Transmission Diagram,Appendix A).To keep all loop line segments the same capacity,the new line will use 556 conductor which will require replacement of the 69kV 4/0 line and structures.This work will also require upgrading the 69kV distribution substations to 115kV (Marathon,Beaver Creek,and Soldotna distribution),and upgrading a short section of 115kV line from 4/0 to 556.This conversion must be done in stages to keep the City of Kenai and surrounding areas energized.This area is presently fed from the existing 69kV system. The overall work will be a design-bid-build process.It is intended that both the line and substation designs will be issued to a single company.Individual construction steps below shall be either by contract,HEA labor,or a combination thereof., Steps of the planned construction are listed below starting at the Nikiski end of the system.The numbers are as noted on the attached North End Transmission Diagram. 1.Nikiski Substation-The majority of work at the Nikiski substation necessary for the 69 to 115 kV conversion is already being performed by AEEC/HEA and will be completed this fall.It will include a breaker position and steel tower for the new line.The remaining work to be covered by the grant award will be adding the requisite relaying for this line position to match the new design,and an upgrade of the existing 4/0 to 556 conductors on the Bernice to Nikiski line segment. 2.Nikiski to South of Tesoro Line Segment -This line segment will meet up with the existing 69kV ROW to the south and east of 69kV switch 29001,a distance of about 2 miles.It is a new line segment with no existing easements or ROW.Since this ROW represents the largest unknown at this point,the first focus of the project will be getting a preliminary design contract out to finalize the route and obtain easements.This line will connect to Nikiski position NB4.Also,a short section of unused line to the old BP substation will need to be removed to make way for the new line. 10. a a ' Tesoro 69kV tap and $W29001 -As the 69kV line will no longer exist south of sw49001,this switch @ will be removed and the existing tap to the 69kV Tesoro sub will become the endpoint of the 69kV ' line from Bernice Lake.The Tesoro 69kV sub will then be a radial feed from Bernice,but with eventual project completion,the Tesoro 115kV sub will be part of the new transmission loop. Tesoro area to Ivanoff Junction Line-The existing 69kV ROW will be used to rebuild the entire line to 115kV using 556 conductor,a distance of about 7.1 miles. Ivanoff to Marathon and Marathon to Beaver Creek Lines-Past construction built these lines for 115kV using 556 conductors,therefore no monies from the grant award are needed for this line segment. Marathon Substation -This substation will be changed to receive two incoming lines and corresponding breaker positions.The sub was built using a transformer capable of using either 69kV or 115kV on the high side,so it will be ready to switch to 115kV once the incoming lines are energized. Beaver Creek Substation and 69kV 3-way SW29006/7/8 -This sub will need a new 115kV transformer.Preliminary reviews show that the high side bus and circuit switcher may not need rework,but the 69kV $W29006/7/8 will need to be replaced with a 115kV 3-way switch and a new supporting structure. Beaver Creek to Soldotna Line -The existing 69kV ROW will be used to rebuild the entire line to 115kV using 556 conductors,a distance about 7.3 miles.The line will land on a new 115kV breaker position in the Soldotna substation. Soldotna 115kV Yard -A new 115kV position including breakers,steel,switches,and controls will be needed to expand the breaker and a half scheme to accommodate the new 115kV line.Several new large towers will also be required within the existing ROW for the new line to avoid interference with existing lines and structures. Soldotna 69kV Yard and Distribution Substation -The entire 69kV yard will be removed including the existing distribution transformer,the 115/69kV autotransformer and the terminus of the Soldotna to Quartz Creek 69kV line from.A new 115kV distribution transformer will be required,and will be fed from the 115kV breakers that currently connect to the autotransformer. Reports and Requests for Reimbursement Progress reports and requests for reimbursement will typically be made quarterly during the grant duration. Cost Estimate The attached spreadsheet shows the estimated costs broken down by the above steps.These scope level estimates are by general work items and include material,labor,contract support,etc.New transmission line costs are estimated at $750,000 per mile based on historic construction costs plus any unique costs.Transmission line segments that have existing ROW are estimated at $600,000 per mile based on historic construction costs plus any unique costs.Removal costs are estimated at $50,000 per mile.Substation construction costs are estimated based on recent equipment purchases and 2 construction costs.More refined estimates will be possible once bids have been received for construction. The majority of work at the Nikiski sub necessary for this conversion is already being performed by AEEC/HEA in 2011 thus reducing the estimate significantly.In addition,various site upgrades that would be opportune to perform while working these sites have not been included to keep the estimate closer to the $18M grant cap. Item Description Amount 1 --sCNikiski Sub &Line Reconductor $280,000 2.Nikiski South Line $1,780,000 3.Tesoro 69kV Tap $60,000 4 _Tesoro to Ivanoff Line $4,625,000 5 _Existing 556 115kV Line so 6 Marathon Substation $355,000 7 'Beaver Cr Sub &3-way Switch $1,990,000 8 Beaver Cr to Soldotna Line $4,795,000 9 =Soldotna 115kV Substation $1,725,000 10 Soldotna 69kV Substation $2,945,000 Subtotal |$18,555,000 Total +10%Contingency |$20,410,500 Milestones Steps 1,2,and 9 can be started immediately.The remaining items must be staged to keep the City of Kenai area energized.The majority of construction will be done in 2012,but final completion and tie in will extend into 2013.An attempt has been made to consider material lead times in the below milestones.However,until design details are completed and actual lead times are confirmed at the time of order,material lead times may significantly impact the below milestones.Final scheduling will depend on details worked out once a design contract has been issued and when easements/ROW acquisition is completed and required permits obtained. Rather than interlace all the milestones into a single listing,they have been broken down by the individual steps where appropriate. Deliverables Deliverables for all milestones will be copies of design,permits,construction and other reports,photo documentation,and additional information requested by AEA. Overall 8/13/2011 -4/15/2013 2011-August 13;Completed and Authorized Grant.Commence work on design RFP. 2011-September 15;Issue RFP for design of all line segments and substation work. 2011-October 30;Issue Design Purchase Order and commence design work. 2012-May 15;Commence Bernice 69kV outage for steps 3 and 4.Kenai fed only from B.Creek and radial Soldotna 69kV line. 2012-October 31;With steps 1 thru 6 complete,energize Marathon at 115kV.De-energize all Soldotna 69kV yard,69kV line and Beaver Creek.Kenai being carried by Marathon and new Nikiski 115kV line. 2013-April 15;Beaver Creek sub back in service.Soldotna 25kV work starts. 2013-November 1;Soldotna distribution back online.Project complete. Step #1 Nikiski Substation 2011-October 30;Complete NIK-BNT line reconductoring design. 2011-November 30;Issue PO for line reconductoring and commence work. 2012-April 1;Complete Nikiski sub relaying upgrades. 2012-May 1;Complete NIK-BNT line reconductoring Step #2 New Nikiski Line 2011-October 30;Complete removal of old BP fine. 2011-November 11;Begin Easement/ROW acquisition and permitting as part of preliminary design. 2012-April 1;Order long lead time poles for line construction. 2012-June 1;Complete obtaining ROW,easements and permits.Issue new line design. 2012-June 15;Issue PO for clearing and grubbing of ROW.Issue RFP for line construction. 2012-July 15;Complete ROW clearing and grubbing.Issue line construction PO. 2012-October 31;Line construction complete to Nikiski (same as step #4). Step #3 Tesoro tap and SW29001 2012-May 15;Shift Marathon &B.Creek to Soldotna 69kV line.Commence outage of 69kV from Bernice (same as step #4). 2012-September 15;Complete removal of SW29001 and line to tie point (steps 2,3,4).Restore Bernice 69kvV line. Step #4 Line-Tesoro to Ivanoff 2012-February 1;Issue PO for long lead poles.Obtain required permitting. 2012-March 1;Issue completed line design.Issue RFP for construction. 2012-May 15;Issue construction PO.Remove line from service and commence construction (same as step #3). 2012-October 31;Tie in to lines in steps 2 and 5.Line construction complete to Nikiski (same as step #2). Step #6 Marathon Substation 2011-September 31;Complete foundation work and erect getaway steel and guys when it arrives. 2012-April 1;Complete termination of second line to new getaway.Issue PO for substation construction to add breakers. 2012-July 31;Complete major substation construction and split incoming lines.Use 69kV for final testing. 2012-August 15;Take Marathon offline and convert transformer &relaying to 115kV. 2012-October 31;With steps 1 thru 5 complete,energize Marathon at 115kV. Step #7 Beaver Creek Substation and 3-way Switch 2012-January 20;Design far enough along to order 25kV transformer. 2012-March 20;Design far enough along to order 3-way switch. 2012-May 1;Design complete,issue construction RFPs. 2012-September 31;Issue construction PO and coordinate with transformer delivery and substation outage. 2012-October 31;With steps 1 thru 6 complete,deenergize 69kV line from Soldotna.Marathon now carries Kenai load.Commence 3-way switch and transformer replacement. 2013-April 15;Construction complete Step #8 Beaver Creek to Soldotna Line 2012-August 1;Design complete,issue construction RFPs. 2012-October 31;As dictated by steps 1-6,outage to commence construction. 2013-April 15;Construction complete.When step #9 is completed,substation back online. Step #9 Soldotna 115kV Substation 2012-March 20;Design far enough along to order long lead material. 2012-May 1;Design complete,issue construction RFPs. 2012-June 31;Construction starts for expansion of 115kV yard and line getaway. 2012-October 31;115kV yard line construction complete. 2013-April 15;Tie in to new 115kV line dictated by step 8 completion. Step #10 Soldotna 69kV Substation 2012-July 1;Design complete,issue construction RFPs and order SOD 2SkV transformer. 2013-April 15;Dependent on Beaver Creek back online,with steps 1 thru 7 complete,de-energize 69kV yard for final time.Commence Soldotna 25kV transformer changeout. 2013-November 1;Complete connection and integration of new 25kV transformer and re-energize Soldotna distribution. Key Personnel The AEA project administrator will be Bryan Carey,or as designated by AEA.Key AEEC personnel are shown below. Grant Administrator:TBD Project Coordinator:|Mark Peery 335-6207 mpeery@homerelectric.com Finance Coordinator:Kim Marrale 398-7905 kmarrale@homerelectric.com Mike Tracy 235-3329 mtracy@homerelectric.com Appendix A -North End Transmission Diagram _-4 eye coett ae rt |i ee eee)'Ser feaws,- Fatd SN'BERNICE:Ny SWANSON FIELD ED md3 crsNIKISKIwl NIKISKI #2 NIKISKI #1 STG 'CTG 40 MVA 38 MVA _] SOT-MTH/-115kV MTH-BNT SS a |Siep#E MARATHON oKENAI]/ 7>>|STERLINGfey=Steps #9 &10fy:4 we, DAP _=(FUTURE) f OND ;a Xe -L,SOT to!Xe OLDOTNA f Q.Crk 69kVFUTURE)' oe 1 *-et eeRUAIEEsveorā€ James Strandberg From:Tracy,Mike <MTracy@HomerElectric.com> Sent:Friday,August 26,2011 8:34 AM To:James Strandberg Subject:RE:Soldotna to Nikiski Transmission Line Attachments:AEA-Soldotna to Nikiski 69 to 115 kV upgrade prelim budget.xlsx Jim, Here you go,note that this is a preliminary budget. From:James Strandberg [mailto:JStrandberg@aidea.org] Sent:Wednesday,August 24,2011 5:22 PM To:Tracy,Mike Subject:Soldotna to Nikiski Transmission Line Mike, |got this draft scope of work from Butch,who got it from you.There are cost spreadsheets noted in the text of the scope that are not a part of the file.Can you provide?_ Thanks,Jim The Item numbers below match the description numbers in the related implementation plan. Item Description Amount 1 Nikiski Sub &Line Reconductor $280,000 2 Line-Nikiski South $1,780,000 3 Tesoro 69kV Tap $60,000 4 ___Line-Tesoro to Ivanoff $4,625,000 5 Existing 556 115kv Line sO 6 Marathon Sub $355,000 7 =B.Creek Sub &3-way SW $1,990,000 8 Line-B.Creek to Soldotna $4,795,000 9 Soldotna 115kV Sub $1,725,000 10 Soldotna 69kV Sub $2,945,000 Subtotal]$18,555,000 |Total +10%Contingency]$20,410,500 BacktoOverall Description Amount NB3 Line to Bernice-4/0 to 556.$200,000 NB4 Relaying Upgrade to SEL 421 $15,000 Integration into Subnet RTU $5,000 Comm to Soldotna-equip for xfer trip $50,000 Startup testing $10,000 Total $280,000 Back to Overall Description Amount Remove present BP line from NB4 position $50,000 Nikiski tie in and Hwy crossing $80,000 ROW easements $100,000 Document incorporation into HEA accounting system $50,000 2 miles of new line construction $1,500,000 Total $1,780,000 Back to Overall Description Amount Remove 69kV SW29001 &Guy $45,000 Remove 500 yards of 69kV $15,000 Total $60,000 BacktoOverall Description Amount Remove old 69kV line $355,000 Document incorporation into HEA accounting system $10,000 7.1 miles of line in existing ROW $4,260,000 Total $4,625,000 Back to Overall Description Amount Engineering evaluation of Dist Xfrmr $5,000 Tie the second line into the sub $50,000 Convert high side to double line $300,000 Total $355,000 Back to Overall Description Amount 115/24.9kV Transformer $1,200,000 Transformer install &integration $500,000 115kV 3-way switch &structure $130,000 3-way SW design &install $90,000 Startup Testing $70,000 Total $1,990,000 Back to Overall Description Amount 115/24.9kV Transformer $1,200,000 Transformer install &integration $500,000 115kV 3-way switch &structure $130,000 3-way SW design &install $90,000 Startup Testing $70,000 Total]$1,990,000 Back to Overall Description Amount Remove old 69kV line $365,000 Document incorporation into HEA accounting system $50,000 7.3 miles of line in existing ROW $4,380,000 Total $4,795,000 Back to Overall Description Amount New breakers,switches,PTs,etc $450,000 Takeoff steel and line crossover towers $250,000 Substation design &protection integration $250,000 Installation $700,000 Startup testing $75,000 Total $1,725,000 Back to Overall Description Amount 115/24.9kV Transformer $1,200,000 Transformer install &integration $500,000 Removal &disposal of 69kV yard equipment $300,000 Substation design &protection integration $250,000 Metering CTs/PTs &Installation $150,000 Autotransformer removal,storage site &move $450,000 Startup testing $95,000 Total $2,945,000