1.CALL TO ORDER
2.ROLL CALL (for Committee members)
3.PUBLIC ROLL CALL (for all others present)
4.AGENDA APPROVAL
5.PUBLIC COMMENTS
6.APPROVAL OF MEETING MINUTES – January 16, 2026
7.NEW BUSINESS
A.FY27 BPMC Budget
8.OLD BUSINESS
A.AEA Capital Project Financing
B.Dispute Resolution Process – Wheeling Services Agreement
C.CIPLink Update
D.Bradley Lake Expansion Project Update
E.SQ Upgrade Update
9.OPERATORS REPORT
10.COMMITTEE REPORTS
A.Budget vs. Actuals
B.O&D Report Josh Crowell
11.EXECUTIVE SESSION – (Bylaws Section 5.11.4) – To discuss confidential financial matters theimmediate knowledge of which would clearly have an adverse effect upon the finances of theAuthority of the Project.
12.MEMBERS COMMENTS
13.NEXT MEETING DATE – May 1, 2026
14.ADJOURNMENT
___________________________________________________________________________
BPMC Minutes 1/16/26 Page 1 of 9
BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE (BPMC) REGULAR MEETING AGENDA January 16, 2026 1. CALL TO ORDER Chair Tony Izzo called the meeting of the Bradley Lake Hydroelectric Project Management Committee to order at 10:01 a.m. A quorum was established. 2. ROLL CALL (for Committee members) Tony Izzo (Matanuska Electric Association [MEA]); Andrew Laughlin (Chugach Electric Association [CEA]); Travis Million (Golden Valley Electric Association [GVEA]); Larry Jorgenson (Homer Electric Association [HEA]); Brian Hickey (City of Seward); and Curtis Thayer (Alaska Energy Authority [AEA]). 3. PUBLIC ROLL CALL (for all others present) Jennifer Bertolini, Mark Billingsley, Patrick Domitrovich, Pamela Ellis, Josi Hartley, Ryan McLaughlin, Jim Mendenhall, William Price, Robert Varga, Mark Ziesmer (AEA); Joel Paisner (Ascent Law Partners); Chris Koehler, Mike Miller, Paul Millwood (CEA); Sarah Villalon (GVEA); Sarah Lambe, Martin Law, Jessica Spuhler (HEA); Analswad Elm (Koniag Energy & Water); Josh Crowell, Kim Henkel, David Pease, and Tony Zellers (MEA). 4. AGENDA APPROVAL MOTION: A motion was made by Mr. Thayer to approve the agenda. Motion seconded by Mr. Hickey. A roll call was taken, and the motion to approve the agenda passed unanimously. 5. PUBLIC COMMENTS - None. 6. APPROVAL OF MEETING MINUTES – December 5, 2025 MOTION: A motion was made by Mr. Thayer to approve the Minutes of December 5, 2025. Motion seconded by Mr. Hickey. A roll call was taken, and the motion to approve the Minutes of December 5, 2025, passed unanimously. 7. NEW BUSINESS - None.
___________________________________________________________________________
BPMC Minutes 1/16/26 Page 2 of 9
8. OLD BUSINESS A. 2026 BPMC Meeting Schedule Mr. Thayer explained that members were provided the proposed 2026 BPMC meeting schedule at the previous meeting. There were no comments or questions. MOTION: A motion was made by Mr. Thayer to approve the 2026 proposed BPMC meeting dates, as presented in the Board packet under 8A. Motion seconded by Mr. Hickey. Chair Izzo commented that the Committee has been flexible in the past if issues arise. The proposed schedule allows firm meeting dates to be set, and the Committee is willing to address changes throughout the year, if necessary. There were no other questions or comments. A roll call was taken, and the motion passed unanimously. B. 2021 REF Funding for Bradley Expansion Chair Izzo requested Mr. Thayer to give the presentation. Mr. Thayer explained that in 2021, the BPMC, through CEA, applied to the Renewable Energy Fund for a $1 million matching grant for the Dixon Diversion project. The grant was awarded, and the work has begun. Formal action has not been taken to collect the funds from the utilities. Chair Izzo explained that this item is a formal request that the BPMC pay the matching $1 million. He noted that the agreed upon percentage of payment is the same as the percentage of project capacity. MOTION: A motion was made by Vice Chair Laughlin that the utility purchasers under the Bradley Lake Hydroelectric Project provide matching funds in accordance with the Renewable Energy Grant Fund Award Number 7014022 in the total amount of $1 million, allocated based on each utilities’ percentage share of project capacity; Chugach Electric Association at 56.3%, Homer Electric Association at 12%, Matanuska Electric Association at 13.8%, Golden Valley Electric Association at 16.9%, and Seward Electric System at 1%. Motion seconded by Mr. Thayer. A roll call was taken, and the motion passed unanimously. C. CIPLink (Grip 3, Phase 1) Update Jim Mendenhall, AEA, reported on the Cook Inlet Power Link (CIPLink) update. Mr. Mendenhall noted that the process review occurred in May. The approval was conducted in September, which was closely followed by the government shutdown through November 12. 2025. Mr. Mendenhall was happy to report that full engagement has resumed with the Department of Energy (DOE). He discussed that AEA is working closely with Stantec and HDR on the environmental review and the marine survey work that will occur in 2026. In subsequent years,
___________________________________________________________________________
BPMC Minutes 1/16/26 Page 3 of 9
additional geotechnical work will be conducted. The National Environmental Policy Act (NEPA) permit has been obtained. Mr. Mendenhall discussed that Stantec is working on the major equipment procurement, including the HVDC converters and cables. They are expected to provide preliminary procurement documents before the phased procurement approach. A seminar will be given at the end of February for the technical working group and the BPMC. Mr. Mendenhall informed that notice should be given next week. Mr. Mendenhall reviewed that the configuration supports an initial 100 MW installation, while preserving the ability to expand to 200 MW. He noted that Stantec and EPS have focused on the existing AC system, and discussions are ongoing regarding the options for the actual termination point. Mr. Mendenhall reported that AEA has done much work on the financing, and Mark Billingsley, AEA, will provide additional information under Agenda Item 8F. The budget period has been finalized for a two-year period, beginning January 1, 2025. Invoices have been submitted and paid through June 30, 2025. Mr. Mendenhall noted that AEA is in a good position with the DOE to move into the next phase of the project. There were no comments or questions. D. Bradley Lake Expansion Project Update Ryan McLaughlin, AEA, provide the Bradley Lake Expansion Update. Mr. McLaughlin discussed that staff is vigorously working towards submitting the Federal Energy Regulatory Commission (FERC) draft license amendment application. It is on track to be submitted in the first or second week of February. The amendment will include a 16-foot pool raise. Next week, AEA is hosting a workshop with the utilities to compare different raise configurations and operational changes. The invitations have been sent to the Operations and Dispatch(O&D) Committee members. Mr. McLaughlin stated to please contact him if anyone else wants to participate. Additionally, a construction sequencing and scheduling workshop will be held with the engineering team on January 27, 2026. During the meeting, the overall project schedule will be reviewed and refreshed. Mr. McLaughlin noted that AEA is analyzing different procurement strategies, including a Construction Manager / General Contractor (CM/GC) model. Evaluation of the costs and benefits of this strategy is ongoing. The second Board of Consultants (BOC) meeting occurred in October. The report included approximately 61 comments from the BOC. Responses will be submitted to FERC. Most of the comments related to the Probable Maximum Flood (PMF) study and the Seismic Hazard Analysis. Mr. McLaughlin noted that the PMF study is ongoing, and that that the drainage area in Bradley Lake is much larger than the initial 1982 calculations. The current configured spill area would not pass the new PMF. It is likely that in the absence of the Bradley Lake Expansion Project, modifications to the dam and the spillway would be necessary during relicensing in 2035. Mr. McLaughlin explained that AEA’s procurement team is working to purchase a 3-phase transformer. The design for the remaining power upgrades from the powerhouse to the dam is
___________________________________________________________________________
BPMC Minutes 1/16/26 Page 4 of 9
90% complete. Funding options are being reviewed, and the procurement target date is July. Mr. McLaughlin discussed that the 2026 subsurface investigation plan is ongoing, with the drilling of two deep boreholes along the tunnel alignment to occur in late June or early July. The estimated cost is between $2 million and $3 million. The third BOC meeting will be scheduled onsite to overlap with the drilling. AEA is working with the engineers to update the construction cost estimate. It is expected within the next month. The design has progressed significantly since the previous cost estimate and includes the tunnel lining and the 16-foot raise. Mr. McLaughlin commented that staff is reviewing seven environmental reports from 2025. The hope is to publish those reports within a couple of weeks. The picture included in the presentation shows the Battle Glacier, which is upstream of the diversion. There were no comments or questions. E. SQ Upgrade Update Jim Mendenhall, AEA, noted that he will provide a brief introduction, and then Chris Kohler, CEA, will give project specifics. There was no objection. Mr. Mendenhall discussed that the memorandum included in the packet reviews Phase 1 of the SQ, and outlines Phase 2 and Phase 3. The preliminary costs are listed in the memorandum. Additionally, information is included regarding the Soldotna to Sterling Substation Line (SS Line). The SS Line is owned by HEA. The project was planned to be constructed but was postponed due to a substantially higher steel bid cost, and longer than anticipated delivery time. The updated cost is $36 million. The project work is tentatively scheduled for the winter of 2028/2029. This timeline needs to be confirmed with HEA. Mr. Mendenhall reviewed page three of the report and noted the work with EPS on the upgrades for the Soldotna, Sterling, and Quartz Creek substations. Those upgrades total approximately $49 million. This work needs to be finished prior to the completion of the entire upgrade. There were no comments or questions. Mr. Kohler gave the update on the Sterling to Quartz Creek project. In December, the U.S. Fish and Wildlife Service published the final environmental assessment. The final finding issued by both the U.S. Fish and Wildlife Service and the Forest Service was the finding of no significant impact. Additionally, the Record of Decision (ROD) approving the project was issued. This was the culmination of a couple of years of work-in-progress. Work continues with the U.S. Fish and Wildlife Service to obtain the formal permit for construction. Mr. Kohler discussed that the contract was issued for the steel poles for Project 2. The first round of vendor drawings is scheduled to be reviewed and approved on January 26, 2026. The engineering team has submitted all the permit applications to the different agencies for construction approval, with a target start date this fall. Engineering has finalized the bill of materials for Project 2, and it is under review by CEA. Procurement is expected to begin in February.
___________________________________________________________________________
BPMC Minutes 1/16/26 Page 5 of 9
Mr. Kohler noted that Project 3, the remaining field work for geotechnical investigation, was completed in December. A preliminary report is expected to be released in February, which will conclude the geotechnical work for the project. There were no comments or questions. F. Bradley Lake Expansion and CIPLINK Financing Update Mark Billingsley, AEA, provided the Bradley Lake Expansion and CIPLINK Financing Update. Mr. Billingsley discussed that he has been involved in a coordinated team to determine the most cost-effective way to finance the two large capital projects. He showed the current cost estimates for both projects. Approximately $20 million has been raised for the Bradley Lake Expansion project, which leaves a gap of approximately $342 million. Approximately $270 million has been raised for the CIPLINK project, which leaves a gap of approximately $142 million. Mr. Billingsley noted that the third quarter of this year is the target date to secure funding for both projects. He reviewed the construction cost timeline outlined in the presentation. Mr. Billingsley discussed the potential financial partners, and noted that staff is applying through two of the USDA RUS programs to determine the level of eligibility and funding amount. Similarly, efforts are being made with two DOE EDF programs to determine the level of eligibility and funding amount. Mr. Billingsley advised that the Bradley Lake Expansion project is eligible to issue tax-exempt bonds. The allocation of the State of Alaska’s volume cap was received in November of 2025, and was set at $342 million. Mr. Billingsley noted that this option has to be acted upon by the end of 2028. The CIPLINK project is not eligible to issue tax exempt bonds. Mr. Billingsley reviewed the final options of the public market through NRUCFC and taxable bonds. Mr. Billingsley discussed the efforts relating to tax credits, including eligibility and maximization under the investment tax credits. The matrix to determine the optimal solution for the financing is complicated. Mr. Hickey asked if there was a particular reason that CoBank was not listed. Mr. Billingsley commented that he welcomes recommendations of other potential lenders, and he requested that Mr. Hickey email the information. Mr. Hickey agreed. Mr. Hickey asked if the taxable bonds include both the public and private markets. Mr. Billingsley agreed. He noted that the other options are likely cheaper. Mr. Thayer commented that the focus has been on the listed six potential financial partners in the presentation because they all provide below market rates. Any additional potential financial partners would provide at-market rates. Mr. Thayer believes there will need to be some sort of stacking for the financing. Mr. Billingsley noted that the next Bradley Lake Expansion project update will be given to the AEA Board in April. Mr. Billingsley asked Mr. Thayer to walk through the Bradley Lake Expansion project timeline. Mr. Thayer discussed that the BPMC, the utilities, and the AEA Board will
___________________________________________________________________________
BPMC Minutes 1/16/26 Page 6 of 9
approve the draft term sheets. After that process, then an approving resolution will be passed by the AEA Board, and the closing will be finalized. He noted that this is an aggressive timeline and it is the best estimate at this point. Mr. Thayer explained that staff will be working simultaneously on the CIPLINK project. He noted that since the CIPLINK project already has a large commitment from the federal government, there are fewer doors to open for that financing. Chair Izzo expressed appreciation for the progress of these two projects. There were no other comments or questions. 9. OPERATORS REPORT Martin Law, HEA, advised that the Operator’s Report is included in the Committee packet. However, there is an additional item to discuss that is not included in the report because it occurred after the report was submitted. Mr. Law noted that during the week of January 5, 2026, the subzero temperatures reached -16 degrees. On January 9, 2026, the temperature began to rise above freezing. On January 10, 2026, at 2:30 a.m., the water flow fire alarm system was activated for Apartment D. The employee occupying the apartment woke up to the alarm and to water coming down from the living room ceiling. One of the sprinklers in the attic had frozen and failed. It began releasing water when it thawed out. Mr. Law reported that approximately 700 gallons of water was released into the attic before the water was secured. There is damage to the sheetrock, and insulation on both levels, and also damage to flooring on the upper level. The estimated cost of the repairs is $45,000. Mr. Law expects to be able to absorb most of that cost into the existing budget. Chair Izzo asked Mr. Law when the repairs are anticipated to begin, and if the situation presents any challenges in having enough room for employees and visitors. Mr. Law noted that there is some mold in the area, due to a previous incident. That remediation is scheduled to be performed on Monday. A contractor is on standby to come on January 28, 2026, to begin the repairs. The employee that is assigned to that housing is currently on leave for three weeks. When he returns, he will occupy one of the bedrooms in the crews’ quarters. The repairs will not inhibit or prevent any other visitors or contractors from coming onsite. Mr. Million commented that he understands it is rare to experience those types of low temperatures in that area. He asked what types of mitigation efforts are being analyzed during the repair process to prevent the scenario from happening again. Mr. Law commented that Yukon Fire is currently on site completing the control room upgrade of the fire system, he had them inspect the configuration. Mr. Law noted that the fire code has changed since the installation of that fire system in that building. The fire code no longer allows wet systems in attics in cold areas. Mr. Law discussed that the system will be abandoned in place, and the new system will be moved to a soffit ceiling installation. Otherwise, a dry system will need to be installed.
___________________________________________________________________________
BPMC Minutes 1/16/26 Page 7 of 9
Mr. Million asked if there is insurance coverage on the property damage. Mr. Law noted that he has not yet explored the insurance coverage. He gave the report to Mr. McLaughlin, and they will discuss the next steps of reporting the incident. Chair Izzo thanked Mr. Law for the pictures provided in the report. There were no other comments or questions. 10. COMMITTEE REPORTS A. Budget vs. Actuals Mark Ziesmer, AEA, discussed the Bradley Lake Budget to Actual Expenses Report as of October 31, 2025. He explained that there was no FY26 activity recorded for Schedule A and Schedule E, which are Non-R&C Capital Projects for Bradley Lake, Battle Creek, and SSQ. The total O&M expenses were $2,062,193, which is $508,000 below budget. Most of the FERC categories are within or close to budget. Mr. Ziesmer noted that FERC 539 Miscellaneous Hydraulic Power Generation Expenses was over budget by $44,519 in contractual expenses. FERC 544 Maintenance of Electric Plan contractual expenses were over budget by $20,507, mostly due to braker and relay testing work. FERC 545 Maintenance of Miscellaneous Hydraulic Plant was over budget by $21,250 in contractual expenses. FERC 920 & 930 Administrative Expense was over by $35,099 in labor and benefits, due to higher than anticipated expenses. Mr. Ziesmer believes most of variances are related to timing and should normalize over the year. Mr. Ziesmer reviewed Schedule D Renewal and Contingency (R&C) Fund Disbursements and Repayments. The R&C expenses totaled $166,387 and covered the fire alarm system replacement and the Bradley Lake Expansion Project. The cumulative costs for the Bradley Lake Expansion Project since inception total $8,672,754. Mr. Ziesmer reviewed Schedule F Battle Creek O&M expenses. The total amount was $180,811, which is $63,784 below budget. Most of the costs in this section reflect the standard 4% allocation from Bradley Lake. Mr. Ziesmer reviewed Schedule I SSQ Line O&M expenses. The total expenses were $5,264, which is $86,029 below budget. The majority of the costs are related to overhead line maintenance. Mr. Ziesmer reviewed Appendix A, which is related to Bond Series 11 funding. The cumulative spending was $16,309,165. Of this amount, approximately $14 million was directly related to the SSQ Line upgrade work. The total costs for the Oscillation Dampening Service contracts were $1,390,306. There were no comments or questions. B. O&D Report Josh Crowell, MEA, presented the O&D Committee Report. Mr. Crowell indicated that the Dixon Diversion was discussed, and that Mr. McLaughlin gave a good synopsis earlier in the meeting. There were no comments or questions.
___________________________________________________________________________
BPMC Minutes 1/16/26 Page 8 of 9
MOTION: A motion was made by Mr. Thayer to enter into executive session to (1) discuss confidential matters the immediate knowledge of which would have an adverse effect on the Authority or the project; and (2) confidential matters discussed with an attorney for the Committee or a member of the Committee, the immediate knowledge of which may have an adverse effect on the legal position of the Committee or the Authority. Motion seconded by Vice Chair Laughlin. A roll call was taken, and the motion to go into executive session passed unanimously. 11. EXECUTIVE SESSION: 10:55 a.m. - (Bylaws Section 5.11.4) –To discuss (1) confidential matters the immediate knowledge of which would clearly have an adverse effect upon the finances of the Authority or the Project; and (2) confidential matters discussed with an attorney for the Committee or a member of the Committee, the immediate knowledge of which could have an adverse effect on the legal position of the Committee or the Authority. The Committee reconvened its regular meeting at 11:46 a.m. Chair Izzo stated that no formal action was taken on matters discussed while in executive session. 12. MEMBERS COMMENTS Mr. Hickey expressed appreciation for the discussion. He is looking forward to moving forward in the future. Mr. Jorgenson echoed Mr. Hickey’s comments. Mr. Million expressed appreciation for the updates on the various projects. Vice Chair Laughlin thanked staff for the excellent reports and for the great information provided today. Mr. Thayer agreed it was very good meeting. He praised the AEA staff, particularly regarding the financing aspects. Mr. Thayer stated there is another trip to Washington, D.C. planned in a couple of weeks. Meetings are scheduled with the U.S. Department of Treasury to discuss tax credits, and meetings are also scheduled with all of the FERC Commissioners. He thanked Mr. Ziesmer for leading that effort and for being aggressive on the timeline that has been set. Chair Izzo echoed the previous comments of appreciation, especially to AEA and staff. He highlighted this significant point in time with the CIPLINK and Bradley Lake Expansion projects being the largest coordinated Railbelt projects in decades. There were no other comments. 13. NEXT MEETING DATE – March 20, 2026
___________________________________________________________________________
BPMC Minutes 1/16/26 Page 9 of 9
14. ADJOURNMENT There being no further business for the committee, the meeting adjourned at 11:50 a.m. ____________________________ Tony Izzo, Chair __________________________ Curtis Thayer, Secretary
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
FY2027 PROPOSED BUDGET
DATE: MARCH 20, 2026
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
2027 PROPOSED Budget Contents
Schedule Description Page #
Summary FY27 PROPOSED Budget Summary 3
Schedule A Bradley Lake Capital Purchases (not funded by R&C) 4
Schedule B Bradley Lake Operations & Maintenance Budget 5 - 7
Schedule C Bradley Lake Monthly Utility Contributions 8
Schedule D R&C Fund Disbursements and Repayments 9
Schedule E Battle Creek Capital Purchases (not funded by R&C) 10
Schedule F Battle Creek Operations & Maintenance Budget 11 - 12
Schedule G Battle Creek Monthly Utility Contributions 13
Schedule H SSQ Line Capital Purchases (not funded by R&C) 14
Schedule I SSQ Line Operations & Maintenance Budget 15
Schedule J SSQ Line Monthly Utility Contributions 16
`
Page 2 of 16
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
2027 PROPOSED Budget Summary
A B C D E F G
FY2024 FY2025 FY2026 FY2027 Inc(Dec) From
FY2024 FY2025 Approved Approved Approved Proposed Prior Year
Bradley Lake (excluding Battle Creek & SSQ Line shown below)Actuals Actuals Budget Budget Budget Budget Budget
Revenues, Expenses & Changes in surplus
Revenues
Utility Contributions (sch C) 19,756,258 20,186,290 22,533,059 21,982,934 22,508,995 23,466,754 957,759
Interest Income 558,494 398,290 - 536,500 229,300 234,900 5,600
Other Revenue - 4,500 - - - - -
20,314,753 20,589,081 22,533,059 22,519,434 22,738,295 23,701,654 963,359
Expenses
Operations & Maintenance (sch B) 6,788,254 7,007,455 7,290,435 7,695,321 7,711,376 8,489,950 778,574
Renewals/Replacements (R&C Fund Repayments) (sch D) 1,134,618 1,336,318 2,234,646 2,580,808 2,490,381 1,927,512 (562,869)
Non R&C Capital Purchases (sch A) 289,857 381,209 948,000 150,000 521,000 1,116,150 595,150
Transfer To(From) R&C - (45,420) - - - - -
Transfer To(From) Operating Reserve 107,019 (57,883) 48,188 80,977 3,211 155,715 152,504
Debt Service 11,995,004 11,967,402 12,011,790 12,012,328 12,012,327 12,012,327 0
20,314,753 20,589,081 22,533,059 22,519,434 22,738,295 23,701,654 963,359
Surplus (Deficit) - - - - - - -
Other Project Costs - Battle Creek
Revenues, Expenses & Changes in surplus
Revenues - Battle Creek
Utility Contributions (sch G) 3,138,548 2,247,866 3,707,875 2,265,097 2,428,860 2,219,229 (209,631)
Interest Income 218,522 162,859 - 218,000 170,800 149,500 (21,300)
3,357,071 2,410,725 3,707,875 2,483,097 2,599,660 2,368,729 (230,931)
Expenses - Battle Creek
Battle Creek Operations & Maintenance (sch F) 441,218 521,650 490,268 600,938 733,784 580,748 (153,036)
Renewals/Replacements (R&C Fund Repayments) (sch D) 934,898 - 1,104,000 - - - -
Capital Purchases (sch E) 88,651 2,621 165,000 5,000 5,000 5,000 -
Transfer To(From) Operating Reserve 22,134 26,569 14,579 22,134 26,569 (30,607) (57,176)
Transfer To(From) Capital Reserve (58,284) (58,285) - (58,284) (58,284) (58,284) (0)
Debt Service 2,948,314 2,890,030 2,948,314 2,890,030 2,831,745 2,773,461 (58,284)
IRS Subsidy (1,019,859) (1,031,450) (1,014,287) (976,720) (939,154) (901,588) 37,566
Transfer to Arbitrage - 59,590 - - - - -
3,357,071 2,410,725 3,707,875 2,483,097 2,599,660 2,368,729 (230,931)
Surplus (Deficit) - - - - - - -
Other Project Costs - SSQ Line
Revenues, Expenses & Changes in surplus
Revenues - SSQ Line
Utility Contributions (sch J) 423,766 571,892 743,555 727,072 684,197 968,197 284,000
Interest Income 104,084 25,890 - 66,200 17,700 16,900 (800)
527,850 597,782 743,555 793,272 701,897 985,097 283,200
Expenses - SSQ Line
SSQ Line Operations & Maintenance (sch I) 77,920 190,998 307,000 343,878 273,878 289,878 16,000
Capital Purchases (sch H) - - - - - 250,000 250,000
Transfer To(From) Operating Reserve 7,376 (14,000) (6,000) 7,376 (14,000) 3,200 17,200
Transfer To(From) Capital Reserve - (21,235) - - - - -
Debt Service 442,555 442,018 442,555 442,018 442,018 442,018 (0)
527,850 597,782 743,555 793,272 701,897 985,097 283,200
Surplus (Deficit) - - - - - - -
Other Information
Operating Reserve * 1,357,651 1,401,491 1,458,087 1,539,064 1,542,275 1,697,990 155,715
Operating Reserve - Battle Creek* 88,244 104,330 98,054 120,188 146,757 116,150 (30,607)
Operating Reserve - SSQ Line* 15,584 38,200 61,400 68,776 54,776 57,976 3,200
Monthly Contributions 1,646,355 1,682,191 1,877,755 1,831,911 1,875,750 1,955,563 79,813
Monthly Contributions Battle Creek 261,546 187,322 308,990 188,758 202,405 184,936 (17,469)
Monthly Contributions SSQ Line 35,314 47,658 61,963 60,589 57,016 80,683 23,667
*Required to be 20% of budgeted operating expense
Page 3 of 16
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
Capital Purchases (not funded by R&C Fund)
Schedule A
FY24 FY25 FY26 FY24 FY25 FY26 FY27
Actuals Approved Approved Approved Proposed
Actuals Actuals @12/31/25 Budget Budget Budget Budget
Install New Bradley Microwave System 45,215 - - 518,000 - - -
Brush Hog for Front End Loader - 111,087 - 150,000 - - -
JLG All Terrain Fork Lift- New Purchase 213,942 - - 190,000 - - -
Replace BL#5 2009 F150 Crew Cab Pickup - 48,995 - 45,000 - - -
Warehouse Heaters x2 (Replace) - - - 5,000 - - -
ISO Shipping Containers x2 (Replace) 30,700 - - 40,000 - - -
Replace 2012 Polaris Side by Side - 62,645 - - 65,000 - -
Crew Quarters Remodel - 84,873 - - 85,000 - -
New Circuit Breaker - Generator #2 - 60,988 - - - -
Contex HD Ultra X 3690 Color Scanner - 12,620 - - - -
Replace DC Station Service Batteries - - - - - 130,000 130,000
Replace Needle Valve Position Arm Bushings - - - - - 95,000 -
Replace ION Meters - - - - - 120,000 120,000
AC unit in powerhouse server room - - - - - 38,000 -
Flooring in powerhouse control room and office - - - - - 28,000 -
Replace Precision Approach Path Indicator lights - - - - - 40,000 -
Limitorque Actuators on fish water valve - - - - - 35,000 35,000
Domestic water tank, controls, and filtration system replacement - - - - - 35,000 -
Crew Quarters Bathroom Remodel - - - - - - 130,000
Crew Quarters Window Replacement - - - - - - 100,000
Replace Powerhouse Main Roll Up Door - - - - - - 50,000
Critical Spare (2) Nozzle Assemblies - - - - - - 400,000
Replace Software and Computer Board in SVC Substation - - - - - - 151,150
Total Non R&C Capital Purchases 289,857 381,209 - 948,000 150,000 521,000 1,116,150
Capital Project Description
Page 4 of 16
FY 26 FY27
Budget Actual
(Over) Under
Budget to Date Budget Actual
(Over) Under
Budget to Date Budget 12/31/2025
Actual to Date
12/31/25
(Over) Under
Budget to Date Proposed Budget
Increase
(Decrease) From
PY
Summary by expense type
Staff Professional Services (Direct) 387,700 325,581 62,119 312,585 501,917 (189,332) 360,000 180,000 257,051 (77,051) 600,000 240,000 Labor & Benefits 2,023,067 1,763,168 259,899 2,054,317 1,435,363 618,954 1,497,414 748,707 646,423 102,284 1,345,868 (151,546)
Travel 78,500 23,515 54,985 51,500 57,509 (6,009) 40,300 20,150 3,388 16,762 115,960 75,660
Training 50,000 10,238 39,762 55,000 7,211 47,789 55,000 27,500 14,987 12,513 129,000 74,000 Contractual 1,181,381 917,237 264,144 1,243,010 1,118,636 124,374 1,392,497 696,249 630,103 66,146 1,545,677 153,180
Consulting-Administrative 265,000 236,601 28,399 315,000 46,433 268,567 155,000 77,500 19,670 57,830 4,000 (151,000) Supplies & Materials 330,332 166,554 163,778 378,500 296,310 82,190 342,000 171,000 64,547 106,453 302,700 (39,300)
Other Costs 79,318 62,747 16,571 112,718 95,087 17,631 77,518 38,759 36,487 2,272 77,538 20
Equipment, Furniture & Machinery 165,000 159,553 5,448 35,000 19,940 15,060 20,000 10,000 8,473 1,527 26,000 6,000 Administrative Costs 1,553,800 1,807,663 (253,863) 1,978,224 2,088,063 (109,839) 2,549,839 1,274,920 911,874 363,046 3,153,839 604,000
Indirect Costs 1,480,105 1,315,396 164,709 1,480,105 1,340,986 139,119 1,543,116 771,558 645,133 126,425 1,543,116 0 O&M 4% Allocation to Battle Creek (303,768) - (303,768) (320,638) - (320,638) (321,307) (160,654) - (160,654) (353,748) (32,441)
Total Bradley Lake Budget 7,290,435 6,788,254 502,181 7,695,321 7,007,455 687,866 7,711,376 3,855,688 3,238,138 617,550 8,489,950 778,574
FERC 535 - Operation Supervision & EngineeringOperations Sup/Eng
Bradley Lake Operating
Labor & Benefits 105,451 106,921 (1,470) 105,451 99,743 5,708 109,196 54,598 53,683 915 109,196 (0) Travel 5,000 1,972 3,028 5,000 668 4,332 5,000 2,500 - 2,500 3,000 (2,000)
Training 5,000 581 4,419 5,000 - 5,000 5,000 2,500 - 2,500 5,000 - Contractual 3,000 - 3,000 3,000 407 2,593 3,000 1,500 - 1,500 1,500 (1,500)
Supplies & Materials 4,000 233 3,767 4,000 - 4,000 25,000 12,500 1,153 11,347 27,000 2,000
Indirect Costs 155,698 149,004 6,694 155,698 139,723 15,975 157,071 78,535 74,502 4,033 157,071 0 Bradley Lake Operating Total 278,149 258,711 19,438 278,149 240,542 37,607 304,267 152,134 129,338 22,795 302,767 (1,500)
FERC 535 - Operation Supervision & Engineering Total 278,149 258,711 19,438 278,149 240,542 37,607 304,267 152,134 129,338 22,795 302,767 (1,500)
FERC 537 - Hydraulic ExpensesHydraulic Expenses
Bradley Lake OperatingLabor & Benefits 95,262 72,310 22,952 95,262 79,042 16,220 81,895 40,947 40,449 498 81,895 0
Contractual 60,000 - 60,000 - - - 15,000 7,500 - 7,500 - (15,000) Supplies & Materials 2,000 2,461 (461) 4,000 1,729 2,271 10,000 5,000 1,310 3,690 4,000 (6,000) Indirect Costs 109,250 100,356 8,894 109,250 108,693 557 113,127 56,564 52,543 4,021 113,127 (0)
Bradley Lake Operating Total 266,512 175,127 91,385 208,512 189,464 19,048 220,022 110,011 94,302 15,709 199,022 (21,000)
FERC 537 - Hydraulic Expenses Total 266,512 175,127 91,385 208,512 189,464 19,048 220,022 110,011 94,302 15,709 199,022 (21,000)
FERC 538 - Electric Expenses
Electric ExpensesBradley Lake Operating
Labor & Benefits 218,044 211,756 6,288 218,044 227,478 (9,434) 235,187 117,594 118,254 (661) 235,187 (0) Travel 7,000 209 6,791 7,000 293 6,707 7,000 3,500 303 3,197 5,000 (2,000)
Training 30,000 9,514 20,486 30,000 3,990 26,010 30,000 15,000 14,512 488 30,000 -
Contractual 5,000 2,506 2,494 10,000 5,255 4,745 18,000 9,000 12,133 (3,133) 31,000 13,000 Supplies & Materials 13,732 11,183 2,549 18,500 5,970 12,530 23,500 11,750 1,294 10,456 21,500 (2,000)
Indirect Costs 262,004 246,564 15,440 262,004 268,318 (6,314) 280,431 140,215 137,942 2,274 280,431 0 Bradley Lake Operating Total 535,780 481,731 54,049 545,548 511,305 34,243 594,118 297,059 284,437 12,622 603,118 9,000
FERC 538 - Electric Expenses Total 535,780 481,731 54,049 545,548 511,305 34,243 594,118 297,059 284,437 12,622 603,118 9,000
FERC 539 - Misc. Hydraulic Power Generation ExpensesMisc Hydro Power Exp
Bradley Lake Operating
Labor & Benefits 105,742 82,466 23,276 107,742 78,868 28,874 130,567 65,283 34,354 30,929 113,567 (17,000) Training 15,000 - 15,000 20,000 - 20,000 20,000 10,000 - 10,000 90,000 70,000
Contractual 360,067 398,523 (38,456) 385,067 410,619 (25,552) 606,317 303,159 298,728 4,430 575,367 (30,950) Supplies & Materials 25,000 34,014 (9,014) 25,000 45,819 (20,819) 30,000 15,000 9,905 5,095 40,000 10,000
Equipment, Furniture & Machinery - - - - 2,563 (2,563) - - - - - -
Indirect Costs 114,320 114,239 81 114,320 111,127 3,193 122,323 61,162 47,748 13,414 122,323 (0) Bradley Lake Operating Total 620,129 629,241 (9,112) 652,129 648,997 3,132 909,207 454,604 390,736 63,867 941,257 32,050
BRADLEY CIRCUITS/RADIO TO BERNICE LK
Other Costs 35,695 34,268 1,427 35,695 34,268 1,427 35,695 17,848 17,134 713 35,695 -
BRADLEY CIRCUITS/RADIO TO BERNICE LK Total 35,695 34,268 1,427 35,695 34,268 1,427 35,695 17,848 17,134 713 35,695 -
BRADLEY CIRCUITS BERNICE LK TO ANCHOther Costs 29,773 28,239 1,534 29,773 28,985 788 29,773 14,887 14,483 404 29,773 -
BRADLEY CIRCUITS BERNICE LK TO ANCH Total 29,773 28,239 1,534 29,773 28,985 788 29,773 14,887 14,483 404 29,773 -
LOWER BRADLEY CIRCUITS/RADIO TO BARGE DOCK
Other Costs - - - 45,000 24,085 20,915 10,000 5,000 4,870 130 5,000 (5,000) LOWER BRADLEY CIRCUITS/RADIO TO BARGE DOCK Total - - - 45,000 24,085 20,915 10,000 5,000 4,870 130 5,000 (5,000)
FERC 539 - Misc. Hydraulic Power Generation Expenses Total 685,597 691,748 (6,151) 762,597 736,335 26,262 984,675 492,338 427,223 65,114 1,011,725 27,050
FERC 541 - Maintenance Supervision & EngineeringMaint Supervision/Eng
Bradley Lake OperatingLabor & Benefits 110,451 112,706 (2,255) 110,451 104,197 6,254 117,056 58,528 55,603 2,925 117,056 (0)
Indirect Costs 155,698 149,940 5,758 155,698 139,723 15,975 157,071 78,535 74,502 4,033 157,071 0
Bradley Lake Operating Total 266,149 262,645 3,504 266,149 243,920 22,229 274,127 137,064 130,105 6,958 274,127 (0)
FERC 541 - Maintenance Supervision & Engineering Total 266,149 262,645 3,504 266,149 243,920 22,229 274,127 137,064 130,105 6,958 274,127 (0)
FERC 542 - Maintenance of StructuresMaintenance of StructuresDefault
Default Total - - - - - - - - - - - -
Bradley Lake OperatingLabor & Benefits 89,710 70,851 18,859 89,710 67,928 21,782 84,789 42,394 30,808 11,587 84,789 0
Contractual 56,000 43,732 12,268 126,000 103,435 22,565 35,000 17,500 14,804 2,696 130,000 95,000
Supplies & Materials 78,000 20,423 57,577 70,000 40,551 29,449 44,000 22,000 8,975 13,025 49,000 5,000 Equipment, Furniture & Machinery 15,000 19,772 (4,772) 20,000 14,623 5,377 20,000 10,000 7,890 2,110 23,000 3,000
Indirect Costs 102,350 95,457 6,893 102,350 94,601 7,749 115,838 57,919 42,717 15,202 115,838 (0) Bradley Lake Operating Total 341,060 250,235 90,825 408,060 321,138 86,922 299,627 149,814 105,194 44,619 402,627 103,000
FERC 542 - Maintenance of Structures Total 341,060 250,235 90,825 408,060 321,138 86,922 299,627 149,814 105,194 44,619 402,627 103,000
FERC 543 - Maintenance of Reservoirs, Dams & WaterwaysMaint Res, Dams, WWays
Bradley Lake Operating
Labor & Benefits 51,783 6,012 45,771 51,783 13,050 38,733 17,992 8,996 1,110 7,886 17,992 (0) Contractual 6,500 - 6,500 39,500 41,306 (1,806) 6,500 3,250 11,162 (7,912) 6,500 -
Supplies & Materials 20,000 - 20,000 85,000 63,338 21,662 20,000 10,000 283 9,717 - (20,000) Equipment, Furniture & Machinery - - - 15,000 - 15,000 - - - - - -
Indirect Costs 58,650 8,664 49,986 58,650 16,000 42,650 22,556 11,278 1,720 9,558 22,556 (0)
Bradley Lake Operating Total 136,933 14,675 122,258 249,933 133,694 116,239 67,048 33,524 14,275 19,249 47,048 (20,000)
BRADLEY POWER TUNNEL MAINT (Dam)Contractual 15,000 - 15,000 15,000 - 15,000 15,000 7,500 - 7,500 15,000 -
BRADLEY POWER TUNNEL MAINT (Dam) Total 15,000 - 15,000 15,000 - 15,000 15,000 7,500 - 7,500 15,000 -
FERC 543 - Maintenance of Reservoirs, Dams & Waterways Total 151,933 14,675 137,258 264,933 133,694 131,239 82,048 41,024 14,275 26,749 62,048 (20,000)
FERC 544 - Maintenance of Electric Plant
Maintenance of Elec PlantBradley Lake Operating
Labor & Benefits 309,110 259,650 49,460 309,110 261,477 47,633 336,995 168,498 121,607 46,890 336,995 (0)
Travel 4,500 354 4,146 4,500 530 3,970 4,500 2,250 108 2,142 4,500 - Contractual 40,000 51,632 (11,632) 75,000 60,276 14,724 24,000 12,000 37,284 (25,284) 64,000 40,000
Supplies & Materials 40,000 36,163 3,837 40,000 35,276 4,724 40,000 20,000 7,809 12,191 40,000 - Indirect Costs 423,178 360,486 62,692 423,178 367,649 55,529 461,361 230,680 169,273 61,407 461,361 0 Bradley Lake Operating Total 816,788 708,284 108,504 851,788 725,208 126,580 866,856 433,428 336,081 97,347 906,856 40,000
FERC 544 - Maintenance of Electric Plant Total 816,788 708,284 108,504 851,788 725,208 126,580 866,856 433,428 336,081 97,347 906,856 40,000
FERC 545 - Maintenance of Misc. Hydraulic Plant
Maint of Misc Hydr Plant
Bradley Lake Operating
FY 24 FY 25
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
BRADLEY LAKE OPERATIONS & MAINTENANCE
BUDGET
SCHEDULE B
FOR THE PERIOD 07/01/2026 TO 06/30/2027
Page 5 of 16
FY 26 FY27
Budget Actual
(Over) Under
Budget to Date Budget Actual
(Over) Under
Budget to Date Budget 12/31/2025
Actual to Date
12/31/25
(Over) Under
Budget to Date Proposed Budget
Increase
(Decrease) From
PY
FY 24 FY 25
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
BRADLEY LAKE OPERATIONS & MAINTENANCE
BUDGET
SCHEDULE B
FOR THE PERIOD 07/01/2026 TO 06/30/2027
Labor & Benefits 69,297 65,189 4,108 69,297 68,096 1,201 82,339 41,170 31,999 9,171 82,340 1
Contractual 45,000 74,760 (29,760) 45,000 38,420 6,580 45,000 22,500 43,938 (21,438) 45,000 - Supplies & Materials 68,000 53,871 14,129 68,000 56,391 11,609 68,000 34,000 26,890 7,110 68,000 -
Equipment, Furniture & Machinery 150,000 139,780 10,220 - - - - - - - - -
Indirect Costs 98,957 90,687 8,270 98,957 95,152 3,805 113,337 56,669 44,186 12,483 113,338 1 Bradley Lake Operating Total 431,254 424,287 6,967 281,254 258,059 23,195 308,677 154,338 147,013 7,326 308,678 1
FERC 545 - Maintenance of Misc. Hydraulic Plant Total 431,254 424,287 6,967 281,254 258,059 23,195 308,677 154,338 147,013 7,326 308,678 1
FERC 556 - System Control & Load DispatchingSystem Cntl & Load Disp
Bradley Lake OperatingLabor & Benefits 20,174 11,901 8,273 20,174 25,978 (5,804) 20,174 10,087 21,159 (11,072) 20,174 -
Contractual 85,500 44,724 40,776 103,500 49,188 54,312 143,500 71,750 20,757 50,993 148,500 5,000 Supplies & Materials 12,000 438 11,562 12,000 854 11,146 12,000 6,000 - 6,000 12,000 - Bradley Lake Operating Total 117,674 57,063 60,611 135,674 76,020 59,654 175,674 87,837 41,916 45,921 180,674 5,000
Snow Measurement
Bradley Lake OperatingContractual 10,000 9,600 400 10,000 9,600 400 10,000 5,000 - 5,000 10,000 - Bradley Lake Operating Total 10,000 9,600 400 10,000 9,600 400 10,000 5,000 - 5,000 10,000 -
Seismic Service
Bradley Lake OperatingContractual 62,000 60,755 1,245 64,868 62,273 2,595 66,498 33,249 28,649 4,600 68,186 1,688
Bradley Lake Operating Total 62,000 60,755 1,245 64,868 62,273 2,595 66,498 33,249 28,649 4,600 68,186 1,688
Streamguaging Serv
Bradley Lake OperatingContractual 278,014 151,920 126,094 216,275 269,784 (53,509) 221,682 110,841 109,287 1,554 233,224 11,542
Bradley Lake Operating Total 278,014 151,920 126,094 216,275 269,784 (53,509) 221,682 110,841 109,287 1,554 233,224 11,542
Permits
Bradley Lake OperatingOther Costs 350 240 110 350 240 110 350 175 - 175 350 -
Bradley Lake Operating Total 350 240 110 350 240 110 350 175 - 175 350 - FERC 556 - System Control & Load Dispatching Total 468,038 279,578 188,460 427,167 417,917 9,250 474,204 237,102 179,852 57,250 492,434 18,230
FERC 562 - Station Expenses
Station ExpensesBradley Lake Operating
Labor & Benefits 64,043 105,259 (41,216) 58,612 42,859 15,753 61,812 30,906 12,684 18,222 73,575 11,763
Labor & Benefits 38,000 56,843 (18,843) 38,000 92,725 (54,725) 38,000 19,000 4,760 14,240 38,900 900 Travel - 336 (336) - - - - - - - - -
Travel 3,500 - 3,500 2,500 773 1,727 1,800 900 - 900 2,460 660 Contractual 1,800 6,029 (4,229) 4,800 32,843 (28,043) 3,000 1,500 - 1,500 3,400 400
Contractual 78,500 73,058 5,442 75,000 - 75,000 100,000 50,000 53,360 (3,360) 130,000 30,000
Supplies & Materials 9,600 4,392 5,208 11,000 9,034 1,966 8,000 4,000 677 3,323 10,200 2,200 Supplies & Materials 10,000 1,109 8,891 12,000 16,500 (4,500) 37,000 18,500 6,251 12,249 - (37,000)
Other Costs 1,500 - 1,500 1,900 1,536 364 1,700 850 - 850 720 (980) Bradley Lake Operating Total 206,943 247,026 (40,083) 203,812 196,269 7,543 251,312 125,656 77,732 47,924 259,255 7,943
FERC 562 - Station Expenses Total 206,943 247,026 (40,083) 203,812 196,269 7,543 251,312 125,656 77,732 47,924 259,255 7,943
FERC 571 - Maintenance of Overhead LinesMaint of OH Lines
Bradley Lake OperatingLabor & Benefits 16,000 52,998 (36,998) 36,500 23,486 13,014 32,574 16,287 - 16,287 34,202 1,628 Contractual 75,000 - 75,000 70,000 35,229 34,771 80,000 40,000 - 40,000 84,000 4,000
Supplies & Materials 30,000 - 30,000 20,000 11,965 8,035 20,000 10,000 - 10,000 21,000 1,000 Bradley Lake Operating Total 121,000 52,998 68,002 126,500 70,681 55,819 132,574 66,287 - 66,287 139,202 6,628
FERC 571 - Maintenance of Overhead Lines Total 121,000 52,998 68,002 126,500 70,681 55,819 132,574 66,287 - 66,287 139,202 6,628
FERC 920 & 930 - Administrative ExpenseAEA Bradley Fixed Admin Fees
Bradley Lake OperatingStaff Professional Services (Direct) 387,700 325,581 62,119 312,585 501,917 (189,332) 360,000 180,000 257,051 (77,051) 600,000 240,000
Travel - 20,643 (20,643) - 53,177 (53,177) - - 2,978 (2,978) 101,000 101,000
Training - 144 (144) - 3,221 (3,221) - - 475 (475) 4,000 4,000 Consulting-Administrative - 17,374 (17,374) - 2,153 (2,153) - - 1,037 (1,037) 4,000 4,000
Supplies & Materials - 2,268 (2,268) - 8,882 (8,882) - - - - 10,000 10,000 Other Costs - - - - 5,972 (5,972) - - - - 6,000 6,000
Equipment, Furniture & Machinery - - - - 2,754 (2,754) - - 583 (583) 3,000 3,000
Administrative Costs 2,500 186,707 (184,207) 172,500 455,441 (282,941) 240,000 120,000 114,738 5,262 317,000 77,000 Bradley Lake Operating Total 390,200 552,716 (162,516) 485,085 1,033,515 (548,430) 600,000 300,000 376,862 (76,862) 1,045,000 445,000
General & Administrative CostsGeneral & Administrative Costs Total - - - - - - - - - - - -
Operating Committee Exp-Audit
Bradley Lake OperatingAdministrative Costs 22,000 35,030 (13,030) 41,000 38,534 2,466 45,000 22,500 - 22,500 47,000 2,000
Bradley Lake Operating Total 22,000 35,030 (13,030) 41,000 38,534 2,466 45,000 22,500 - 22,500 47,000 2,000
Operating Committee Exp-Legal
Bradley Lake OperatingAdministrative Costs 80,000 149,198 (69,198) 80,000 125,918 (45,918) 80,000 40,000 60,885 (20,885) 150,000 70,000
Bradley Lake Operating Total 80,000 149,198 (69,198) 80,000 125,918 (45,918) 80,000 40,000 60,885 (20,885) 150,000 70,000
Trust & Account Fees
Bradley Lake OperatingAdministrative Costs 13,000 - 13,000 - - - - - - - - -
Bradley Lake Operating Total 13,000 - 13,000 - - - - - - - - -
Battle Creek OperatingBattle Creek Operating Total - - - - - - - - - - - -
Misc AdminBradley Lake Operating
Administrative Costs 13,000 14,110 (1,110) 13,000 14,634 (1,634) 13,000 6,500 15,103 (8,603) 13,000 - Bradley Lake Operating Total 13,000 14,110 (1,110) 13,000 14,634 (1,634) 13,000 6,500 15,103 (8,603) 13,000 -
Professional ConsultantsBradley Lake Operating
Labor & Benefits 730,000 548,307 181,693 744,181 250,437 493,744 148,836 74,418 119,952 (45,534) - (148,836) Travel 58,500 - 58,500 32,500 2,068 30,432 22,000 11,000 - 11,000 - (22,000)
Supplies & Materials 18,000 - 18,000 9,000 - 9,000 4,500 2,250 - 2,250 - (4,500) Other Costs 12,000 - 12,000 - - - - - - - - - Bradley Lake Operating Total 818,500 548,307 270,193 785,681 252,505 533,176 175,336 87,668 119,952 (32,284) - (175,336)
FERC 920 & 930 - Administrative Expense Total 1,336,700 1,299,363 37,337 1,404,766 1,465,107 (60,341) 913,336 456,668 572,802 (116,134) 1,255,000 341,664
FERC 924 & 925 - Insurance Premiums
Insurance Premiums
Bradley Lake OperatingAdministrative Costs 1,100,000 1,166,378 (66,378) 1,300,000 1,094,624 205,376 1,500,000 750,000 714,323 35,677 1,700,000 200,000
Administrative Costs 38,300 52,812 (14,512) 71,724 69,383 2,341 81,839 40,920 - 40,920 81,839 - Bradley Lake Operating Total 1,138,300 1,219,190 (80,890) 1,371,724 1,164,007 207,717 1,581,839 790,920 714,323 76,596 1,781,839 200,000
FERC 924 & 925 - Insurance Premiums Total 1,138,300 1,219,190 (80,890) 1,371,724 1,164,007 207,717 1,581,839 790,920 714,323 76,596 1,781,839 200,000
FERC 923 - Outside Services EmployedOutside Services Employed
Bradley Lake Operating
Consulting-Administrative 265,000 219,228 45,772 315,000 44,280 270,720 155,000 77,500 18,634 58,866 - (155,000) Bradley Lake Operating Total 265,000 219,228 45,772 315,000 44,280 270,720 155,000 77,500 18,634 58,866 - (155,000)
FERC 923 - Outside Services Employed Total 265,000 219,228 45,772 315,000 44,280 270,720 155,000 77,500 18,634 58,866 - (155,000)
FERC 928 - Regulatory Commission ExpensesFERC Admin Fees
Bradley Lake OperatingAdministrative Costs 165,000 155,391 9,609 180,000 213,420 (33,420) 170,000 85,000 - 85,000 225,000 55,000 Bradley Lake Operating Total 165,000 155,391 9,609 180,000 213,420 (33,420) 170,000 85,000 - 85,000 225,000 55,000
Page 6 of 16
FY 26 FY27
Budget Actual
(Over) Under
Budget to Date Budget Actual
(Over) Under
Budget to Date Budget 12/31/2025
Actual to Date
12/31/25
(Over) Under
Budget to Date Proposed Budget
Increase
(Decrease) From
PY
FY 24 FY 25
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
BRADLEY LAKE OPERATIONS & MAINTENANCE
BUDGET
SCHEDULE B
FOR THE PERIOD 07/01/2026 TO 06/30/2027
FERC Related Prof ServicesBradley Lake OperatingBradley Lake Operating Total - - - - - - - - - - - -
BRADLEY FERC PART 12 INSPECTION
Administrative Costs - - - - - - 300,000 150,000 - 150,000 500,000 200,000 BRADLEY FERC PART 12 INSPECTION Total - - - - - - 300,000 150,000 - 150,000 500,000 200,000
BRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUESAdministrative Costs 120,000 48,036 71,964 120,000 76,109 43,891 120,000 60,000 6,825 53,175 120,000 -
BRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUES Total 120,000 48,036 71,964 120,000 76,109 43,891 120,000 60,000 6,825 53,175 120,000 - FERC 928 - Regulatory Commission Expenses Total 285,000 203,427 81,573 300,000 289,529 10,471 590,000 295,000 6,825 288,175 845,000 255,000
O&M 4% Allocation to Battle Creek (303,768) - (303,768) (320,638) - (320,638) (321,307) (160,654) - (160,654) (353,748) (32,441)
Total Bradley Lake Budget 7,290,435 6,788,254 502,181 7,695,321 7,007,455 687,866 7,711,376 3,855,688 3,238,138 617,550 8,489,950 778,574
- - - - - - - - - - - -
Page 7 of 16
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
Monthly Utility Contributions
Schedule C
A B C D E F
FY2024 FY2025 FY2026 FY2027
Annual Annual Annual Annual FY2026 to
Percent Approved Approved Approved Proposed FY2027
Power Purchaser Share Budget Budget Budget Budget Change
Chugach Electric 56.30%12,686,112 12,376,392 12,672,564 13,211,783 539,218
Homer Electric 12.00%2,703,966 2,637,950 2,701,078 2,816,009 114,931
Matanuska Electric 13.80%3,109,564 3,033,646 3,106,243 3,238,414 132,171
Golden Valley Electric 16.90%3,808,087 3,715,116 3,804,020 3,965,881 161,861
City of Seward 1.00%225,331 219,829 225,090 234,668 9,578
100.0%22,533,059 21,982,934 22,508,995 23,466,754 957,759
FY2024 FY2025 FY2026 FY2027 FY2026 to
Power Purchaser Percent Approved Approved Approved Proposed FY2027
Share Monthly Monthly Monthly Monthly Change
Chugach Electric 56.30%1,057,176 1,031,366 1,056,047 1,100,982 44,935
Homer Electric 12.00%225,330 219,829 225,090 234,667 9,578
Matanuska Electric 13.80%259,130 252,804 258,854 269,868 11,014
Golden Valley Electric 16.90%317,341 309,593 317,002 330,490 13,488
City of Seward 1.00%18,778 18,319 18,757 19,556 798
100.00%1,877,755 1,831,911 1,875,750 1,955,563 79,813
Page 8 of 16
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
R&C Fund Disbursements and Repayments
Schedule D
ACTUAL ACTUAL ACTUAL ACTUAL PROJECTED PROJECTED PROJECTED PROJECTED
TO REPAY TO REPAY TO REPAY TO REPAY
Description Disburse at 06/30/24 Disburse at 06/30/25 Disburse at 06/30/26 Disburse at 06/30/27
R&C FUND PROJECTS
Governor - 4,052,070.14 - 4,052,070.14 - 4,052,070.14 - 4,052,070.14
Replace RFLS - 251,092.69 - 251,092.69 - 251,092.69 - 251,092.69
Replace Runners - 1,946,732.79 - 1,946,732.79 - 1,946,732.79 - 1,946,732.79
Replace Cable from Dam to Power House - 2,321,922.94 - 2,321,922.94 - 2,321,922.94 - 2,321,922.94
Replace Power System Stabilizer - 619,205.10 - 619,205.10 - 619,205.10 - 619,205.10
Replace two RTUs - 86,905.27 - 86,905.27 - 86,905.27 - 86,905.27
Culvert Repairs - 675,966.79 - 675,966.79 - 675,966.79 - 675,966.79
Trans Towers Frost Jacking Repairs - 887,596.62 - 887,596.62 - 887,596.62 - 887,596.62
Replace Plant and SCADA Controls - 1,344,683.05 - 1,344,683.05 - 1,344,683.05 - 1,344,683.05
Vibration Monitoring System - 490.00 - 490.00 - 490.00 - 490.00
Fire Alarm System Replacement 33,941.86 171,338.97 - 171,338.97 1,471,407.00 1,642,745.97 1,471,407.00 3,114,152.97
Battle Creek Diversion - 1,170,000.00 - 1,170,000.00 - 1,170,000.00 - 1,170,000.00
Replace Electro-Mechanical Relays - 1,277,197.06 - 1,277,197.06 - 1,277,197.06 - 1,277,197.06
Fishwater Screen Debris Removal - 312,236.43 - 312,236.43 - 312,236.43 - 312,236.43
Turbine Nozzle Repair - 1,428,861.07 - 1,428,861.07 - 1,428,861.07 - 1,428,861.07
SVC replacement Daves Creek | Soldotna - 8,517,991.11 - 8,517,991.11 - 8,517,991.11 - 8,517,991.11
Equipment Storage Shed - 510,550.13 - 510,550.13 - 510,550.13 - 510,550.13
Emerson Operating System Upgrade - 622,665.00 - 622,665.00 - 622,665.00 - 622,665.00
Generator #2 Replacement - 953,212.71 - 953,212.71 - 953,212.71 - 953,212.71
Road Grader - 342,330.00 - 342,330.00 - 342,330.00 - 342,330.00
Battle Creek Construction - 3,739,590.93 - 3,739,590.93 - 3,739,590.93 - 3,739,590.93
Battle Creek Cash Call - 750,000.00 - 750,000.00 - 750,000.00 - 750,000.00
Repayment through Cash Call - (750,000.00) - (750,000.00) - (750,000.00) - (750,000.00)
Needle Repairs - 1,482,791.23 - 1,482,791.23 - 1,482,791.23 - 1,482,791.23
Construct additional residence 805,515.43 1,000,284.14 75,155.88 1,075,440.02 - 1,075,440.02 - 1,075,440.02
Spillway Raise & Expansion Project (Dixon Diversion) 175,650.59 1,384,822.09 774,356.98 2,159,179.07 - 2,159,179.07 - 2,159,179.07
Needle Valve Rebuild 198,085.70 198,085.70 1,504,126.90 1,702,212.60 - 1,702,212.60 - 1,702,212.60
Barge Dock Rehabilitation - - 401.00 401.00 600,000.00 600,401.00 600,000.00 1,200,401.00
Critical Spare (2) Nozzle Assemblies - - - - - - - -
Change out turbine nozzles units #1 and #2 - - - - - - - -
1,213,193.58 35,298,621.96 2,354,040.76 37,652,662.72 2,071,407.00 39,724,069.72 2,071,407.00 41,795,476.72
4th yr 1,321,708.58
3rd yr 247,054.13 4th yr 247,054.13
2nd yr 197,454.89 3rd yr 197,454.89 4th yr 197,454.89
1st yr 303,298.40 2nd yr 303,298.40 3rd yr 303,298.40 4th yr 303,298.40
1st yr 588,510.19 2nd yr 588,510.19 3rd yr 588,510.19
1st yr 517,851.75 2nd yr 517,851.75
1st yr 517,851.75
2,069,515.99 1,336,317.61 1,607,115.23 1,927,512.09
Page 9 of 16
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
Battle Creek
Capital Purchases (not funded by R&C Fund)
Schedule E
FY24 FY25 FY26 FY24 FY25 FY26 FY27
Actuals Approved Approved Approved Proposed
Actuals Actuals @12/31/25 Budget Budget Budget Budget
Battle Creek Associated Costs - - - 15,000 - - -
Survey and Monument DNR Lease 88,651 2,621 - 150,000 5,000 5,000 5,000
Total Non R&C Capital Purchases 88,651 2,621 - 165,000 5,000 5,000 5,000
Capital Construction Project Description
Page 10 of 16
FY 26 FY27
Budget Actual
(Over) Under
Budget to Date Budget Actual
(Over) Under
Budget to Date Budget
Budget to Date
12/31/26
Actual to Date
12/31/25
(Over) Under
Budget to Date Proposed Budget
Increase
(Decrease) From
PY
Summary by expense type
Staff Professional Services (Direct) 50,000 48,886 1,114 50,000 46,192 3,808 50,000 25,000 22,750 2,250 50,000 - Labor & Benefits - 73,465 (73,465) 10,000 59,807 (49,807) 10,000 5,000 26,934 (21,934) 10,000 -
Travel - 1,411 (1,411) - 3,322 (3,322) - - 141 (141) - -
Training - 427 (427) - 300 (300) - - 624 (624) - - Contractual 125,000 154,741 (29,741) 201,300 243,987 (42,687) 333,477 166,739 184,740 (18,002) 148,000 (185,477)
Consulting-Administrative - 9,858 (9,858) - 1,935 (1,935) - - 820 (820) - - Supplies & Materials - 6,940 (6,940) 5,000 12,346 (7,346) 5,000 2,500 2,689 (189) 5,000 -
Other Costs - 2,614 (2,614) - 3,962 (3,962) - - 1,520 (1,520) - -
Equipment, Furniture & Machinery - 6,648 (6,648) - 831 (831) - - 353 (353) - - Administrative Costs 11,500 81,420 (69,920) 14,000 93,093 (79,093) 14,000 7,000 37,995 (30,995) 14,000 -
Indirect Costs - 54,808 (54,808) - 55,874 (55,874) - - 26,881 (26,881) - - O&M 4% Allocation to Battle Creek 303,768 - 303,768 320,638 - 320,638 321,307 160,654 - 160,654 353,748 32,441
Total Bradley Lake Budget 490,268 441,218 49,050 600,938 521,650 79,288 733,784 366,892 305,448 61,444 580,748 (153,036)
FERC 535 - Operation Supervision & EngineeringOperations Sup/Eng
Battle Creek Operating
Labor & Benefits - 4,455 (4,455) 1,500 4,156 (2,656) 1,500 750 2,237 (1,487) 1,500 - Travel - 82 (82) - 28 (28) - - - - - -
Training - 24 (24) - - - - - - - - - Contractual - - - - 17 (17) - - - - - -
Supplies & Materials - 10 (10) 1,000 - 1,000 1,000 500 48 452 1,000 -
Indirect Costs - 6,209 (6,209) - 5,822 (5,822) - - 3,104 (3,104) - - Battle Creek Operating Total - 10,780 (10,780) 2,500 10,023 (7,523) 2,500 1,250 5,389 (4,139) 2,500 -
FERC 535 - Operation Supervision & Engineering Total - 10,780 (10,780) 2,500 10,023 (7,523) 2,500 1,250 5,389 (4,139) 2,500 -
FERC 537 - Hydraulic ExpensesHydraulic Expenses
Battle Creek OperatingLabor & Benefits - 3,013 (3,013) 1,500 3,293 (1,793) 1,500 750 1,685 (935) 1,500 -
Contractual 70,000 62,923 7,077 145,000 141,077 3,923 277,177 138,589 143,736 (5,147) 86,000 (191,177) Supplies & Materials - 103 (103) 1,000 72 928 1,000 500 55 445 1,000 - Indirect Costs - 4,182 (4,182) - 4,529 (4,529) - - 2,189 (2,189) - -
Battle Creek Operating Total 70,000 70,220 (220) 147,500 148,972 (1,472) 279,677 139,839 147,665 (7,827) 88,500 (191,177)
FERC 537 - Hydraulic Expenses Total 70,000 70,220 (220) 147,500 148,972 (1,472) 279,677 139,839 147,665 (7,827) 88,500 (191,177)
FERC 538 - Electric Expenses
Electric ExpensesBattle Creek Operating
Labor & Benefits - 8,823 (8,823) 1,500 9,478 (7,978) 1,500 750 4,927 (4,177) 1,500 - Travel - 9 (9) - 12 (12) - - 13 (13) - -
Training - 396 (396) - 166 (166) - - 605 (605) - -
Contractual - 104 (104) - 219 (219) - - 506 (506) - - Supplies & Materials - 466 (466) 1,000 249 751 1,000 500 54 446 1,000 -
Indirect Costs - 10,273 (10,273) - 11,180 (11,180) - - 5,748 (5,748) - - Battle Creek Operating Total - 20,072 (20,072) 2,500 21,304 (18,804) 2,500 1,250 11,852 (10,602) 2,500 -
FERC 538 - Electric Expenses Total - 20,072 (20,072) 2,500 21,304 (18,804) 2,500 1,250 11,852 (10,602) 2,500 -
FERC 539 - Misc. Hydraulic Power Generation ExpensesMisc Hydro Power Exp
Battle Creek Operating
Labor & Benefits - 3,436 (3,436) 1,500 3,286 (1,786) 1,500 750 1,431 (681) 1,500 - Contractual - 16,605 (16,605) - 17,109 (17,109) - - 12,447 (12,447) - -
Supplies & Materials - 1,417 (1,417) 1,000 1,909 (909) 1,000 500 413 87 1,000 - Other Costs - 2,604 (2,604) - 3,639 (3,639) - - 1,520 (1,520) - -
Equipment, Furniture & Machinery - - - - 107 (107) - - - - - -
Indirect Costs - 4,760 (4,760) - 4,630 (4,630) - - 1,990 (1,990) - - Battle Creek Operating Total - 28,823 (28,823) 2,500 30,681 (28,181) 2,500 1,250 17,801 (16,551) 2,500 -
FERC 539 - Misc. Hydraulic Power Generation Expenses Total - 28,823 (28,823) 2,500 30,681 (28,181) 2,500 1,250 17,801 (16,551) 2,500 -
FERC 541 - Maintenance Supervision & EngineeringMaint Supervision/Eng
Battle Creek OperatingLabor & Benefits - 4,696 (4,696) 2,500 4,342 (1,842) 2,500 1,250 2,317 (1,067) 2,500 -
Indirect Costs - 6,247 (6,247) - 5,822 (5,822) - - 3,104 (3,104) - -
Battle Creek Operating Total - 10,944 (10,944) 2,500 10,163 (7,663) 2,500 1,250 5,421 (4,171) 2,500 -
FERC 541 - Maintenance Supervision & Engineering Total - 10,944 (10,944) 2,500 10,163 (7,663) 2,500 1,250 5,421 (4,171) 2,500 -
FERC 542 - Maintenance of Structures
Maintenance of StructuresBattle Creek Operating
Labor & Benefits - 2,952 (2,952) 1,500 2,830 (1,330) 1,500 750 1,284 (534) 1,500 - Contractual - 1,822 (1,822) - 4,310 (4,310) - - 617 (617) - -
Supplies & Materials - 851 (851) 1,000 1,690 (690) 1,000 500 374 126 1,000 -
Equipment, Furniture & Machinery - 824 (824) - 609 (609) - - 329 (329) - - Indirect Costs - 3,977 (3,977) - 3,942 (3,942) - - 1,780 (1,780) - -
Battle Creek Operating Total - 10,426 (10,426) 2,500 13,381 (10,881) 2,500 1,250 4,383 (3,133) 2,500 - FERC 542 - Maintenance of Structures Total - 10,426 (10,426) 2,500 13,381 (10,881) 2,500 1,250 4,383 (3,133) 2,500 -
FERC 543 - Maintenance of Reservoirs, Dams & Waterways
Maint Res, Dams, WWaysBattle Creek Operating
Labor & Benefits - 250 (250) - 544 (544) - - 46 (46) - - Contractual - - - - 1,721 (1,721) - - 465 (465) - - Supplies & Materials - - - - 2,639 (2,639) - - 12 (12) - -
Indirect Costs - 361 (361) - 667 (667) - - 72 (72) - - Battle Creek Operating Total - 611 (611) - 5,571 (5,571) - - 595 (595) - -
FERC 543 - Maintenance of Reservoirs, Dams & Waterways Total - 611 (611) - 5,571 (5,571) - - 595 (595) - -
FERC 544 - Maintenance of Electric PlantMaintenance of Elec Plant
Battle Creek OperatingLabor & Benefits - 10,819 (10,819) - 10,895 (10,895) - - 5,067 (5,067) - -
Travel - 15 (15) - 22 (22) - - 4 (4) - -
Contractual - 2,151 (2,151) - 2,511 (2,511) - - 1,554 (1,554) - - Supplies & Materials - 1,507 (1,507) - 1,470 (1,470) - - 325 (325) - -
Indirect Costs - 15,020 (15,020) - 15,319 (15,319) - - 7,053 (7,053) - - Battle Creek Operating Total - 29,512 (29,512) - 30,217 (30,217) - - 14,003 (14,003) - -
FERC 544 - Maintenance of Electric Plant Total - 29,512 (29,512) - 30,217 (30,217) - - 14,003 (14,003) - -
FERC 545 - Maintenance of Misc. Hydraulic PlantMaint of Misc Hydr Plant
Battle Creek Operating
Labor & Benefits - 2,716 (2,716) - 2,837 (2,837) - - 1,333 (1,333) - - Contractual - 3,115 (3,115) - 1,601 (1,601) - - 1,831 (1,831) - -
Supplies & Materials - 2,245 (2,245) - 2,350 (2,350) - - 1,120 (1,120) - - Equipment, Furniture & Machinery - 5,824 (5,824) - - - - - - - - -
Indirect Costs - 3,779 (3,779) - 3,965 (3,965) - - 1,841 (1,841) - -
Battle Creek Operating Total - 17,679 (17,679) - 10,752 (10,752) - - 6,126 (6,126) - -
FERC 545 - Maintenance of Misc. Hydraulic Plant Total - 17,679 (17,679) - 10,752 (10,752) - - 6,126 (6,126) - -
FERC 556 - System Control & Load Dispatching
System Cntl & Load DispBradley Lake Operating
Bradley Lake Operating Total - - - - - - - - - - - -
FY 24 FY 25
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
BATTLE CREEK OPERATIONS & MAINTENANCE
BUDGET
SCHEDULE F
FOR THE PERIOD 07/01/2026 TO 06/30/2027
Page 11 of 16
FY 26 FY27
Budget Actual
(Over) Under
Budget to Date Budget Actual
(Over) Under
Budget to Date Budget
Budget to Date
12/31/26
Actual to Date
12/31/25
(Over) Under
Budget to Date Proposed Budget
Increase
(Decrease) From
PY
FY 24 FY 25
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
BATTLE CREEK OPERATIONS & MAINTENANCE
BUDGET
SCHEDULE F
FOR THE PERIOD 07/01/2026 TO 06/30/2027
Battle Creek OperatingLabor & Benefits - 496 (496) - 1,082 (1,082) - - 882 (882) - - Contractual - 1,864 (1,864) - 2,049 (2,049) - - 865 (865) - -
Supplies & Materials - 18 (18) - 36 (36) - - - - - - Battle Creek Operating Total - 2,378 (2,378) - 3,167 (3,167) - - 1,746 (1,746) - -
Snow Measurement
Battle Creek Operating
Contractual - 400 (400) - 400 (400) - - - - - - Battle Creek Operating Total - 400 (400) - 400 (400) - - - - - -
Seismic Service
Battle Creek Operating
Contractual - 2,531 (2,531) - 2,595 (2,595) - - 1,194 (1,194) - - Battle Creek Operating Total - 2,531 (2,531) - 2,595 (2,595) - - 1,194 (1,194) - -
Streamguaging Serv
Battle Creek OperatingContractual 55,000 59,930 (4,930) 56,300 67,541 (11,241) 56,300 28,150 19,304 8,846 62,000 5,700 Battle Creek Operating Total 55,000 59,930 (4,930) 56,300 67,541 (11,241) 56,300 28,150 19,304 8,846 62,000 5,700
Permits
Battle Creek OperatingOther Costs - 10 (10) - 10 (10) - - - - - - Battle Creek Operating Total - 10 (10) - 10 (10) - - - - - -
FERC 556 - System Control & Load Dispatching Total 55,000 65,249 (10,249) 56,300 73,713 (17,413) 56,300 28,150 22,244 5,906 62,000 5,700
FERC 562 - Station Expenses
Station Expenses
Battle Creek OperatingLabor & Benefits - 6,754 (6,754) - 5,649 (5,649) - - 727 (727) - -
Travel - 14 (14) - 32 (32) - - - - - - Contractual - 3,295 (3,295) - 1,368 (1,368) - - 2,223 (2,223) - -
Supplies & Materials - 229 (229) - 1,064 (1,064) - - 289 (289) - -
Other Costs - - - - 64 (64) - - - - - - Battle Creek Operating Total - 10,293 (10,293) - 8,178 (8,178) - - 3,239 (3,239) - -
FERC 562 - Station Expenses Total - 10,293 (10,293) - 8,178 (8,178) - - 3,239 (3,239) - -
FERC 571 - Maintenance of Overhead LinesMaint of OH Lines
Battle Creek OperatingLabor & Benefits - 2,208 (2,208) - 979 (979) - - - - - -
Contractual - - - - 1,468 (1,468) - - - - - - Supplies & Materials - - - - 499 (499) - - - - - - Battle Creek Operating Total - 2,208 (2,208) - 2,945 (2,945) - - - - - -
FERC 571 - Maintenance of Overhead Lines Total - 2,208 (2,208) - 2,945 (2,945) - - - - - -
FERC 920 & 930 - Administrative Expense
AEA Bradley Fixed Admin Fees
Battle Creek OperatingStaff Professional Services (Direct) 50,000 48,886 1,114 50,000 46,192 3,808 50,000 25,000 22,750 2,250 50,000 -
Travel - 1,291 (1,291) - 3,142 (3,142) - - 124 (124) - - Training - 6 (6) - 134 (134) - - 20 (20) - -
Consulting-Administrative - 724 (724) - 90 (90) - - 43 (43) - -
Supplies & Materials - 94 (94) - 370 (370) - - - - - - Other Costs - - - - 249 (249) - - - - - -
Equipment, Furniture & Machinery - - - - 115 (115) - - 24 (24) - - Administrative Costs - 7,793 (7,793) - 18,977 (18,977) - - 4,781 (4,781) - - Battle Creek Operating Total 50,000 58,794 (8,794) 50,000 69,268 (19,268) 50,000 25,000 27,743 (2,743) 50,000 -
Operating Committee Exp-Audit
Battle Creek OperatingAdministrative Costs - 1,460 (1,460) - 1,606 (1,606) - - - - - - Battle Creek Operating Total - 1,460 (1,460) - 1,606 (1,606) - - - - - -
Operating Committee Exp-Legal
Battle Creek OperatingAdministrative Costs 5,000 6,217 (1,217) 5,000 5,247 (247) 5,000 2,500 2,537 (37) 5,000 -
Battle Creek Operating Total 5,000 6,217 (1,217) 5,000 5,247 (247) 5,000 2,500 2,537 (37) 5,000 -
Operat Committee Exp-Arbitrage
Battle Creek OperatingAdministrative Costs - 1,690 (1,690) 2,500 1,690 810 2,500 1,250 - 1,250 2,500 -
Battle Creek Operating Total - 1,690 (1,690) 2,500 1,690 810 2,500 1,250 - 1,250 2,500 -
Trust & Account Fees
Battle Creek OperatingAdministrative Costs 5,500 4,170 1,330 5,500 4,400 1,100 5,500 2,750 - 2,750 5,500 -
Battle Creek Operating Total 5,500 4,170 1,330 5,500 4,400 1,100 5,500 2,750 - 2,750 5,500 -
Misc AdminBattle Creek Operating
Administrative Costs 1,000 588 412 1,000 610 390 1,000 500 629 (129) 1,000 -
Battle Creek Operating Total 1,000 588 412 1,000 610 390 1,000 500 629 (129) 1,000 -
Professional ConsultantsBattle Creek Operating
Labor & Benefits - 22,846 (22,846) - 10,435 (10,435) - - 4,998 (4,998) - -
Travel - - - - 86 (86) - - - - - - Battle Creek Operating Total - 22,846 (22,846) - 10,521 (10,521) - - 4,998 (4,998) - -
FERC 920 & 930 - Administrative Expense Total 61,500 95,764 (34,264) 64,000 93,341 (29,341) 64,000 32,000 35,907 (3,907) 64,000 -
FERC 924 & 925 - Insurance PremiumsInsurance Premiums
Battle Creek OperatingAdministrative Costs - 50,800 (50,800) - 48,500 (48,500) - - 29,763 (29,763) - -
Battle Creek Operating Total - 50,800 (50,800) - 48,500 (48,500) - - 29,763 (29,763) - -
FERC 924 & 925 - Insurance Premiums Total - 50,800 (50,800) - 48,500 (48,500) - - 29,763 (29,763) - -
FERC 923 - Outside Services Employed
Outside Services EmployedBattle Creek OperatingConsulting-Administrative - 9,134 (9,134) - 1,845 (1,845) - - 776 (776) - -
Battle Creek Operating Total - 9,134 (9,134) - 1,845 (1,845) - - 776 (776) - -
FERC 923 - Outside Services Employed Total - 9,134 (9,134) - 1,845 (1,845) - - 776 (776) - -
FERC 928 - Regulatory Commission Expenses
FERC Admin FeesBattle Creek Operating
Administrative Costs - 6,475 (6,475) - 8,893 (8,893) - - - - - - Battle Creek Operating Total - 6,475 (6,475) - 8,893 (8,893) - - - - - -
FERC Related Prof ServicesBRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUES
Administrative Costs - 227 (227) - - - - - - - - - BRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUES Total - 227 (227) - - - - - - - - -
Battle Creek OperatingAdministrative Costs - 2,002 (2,002) - 3,171 (3,171) - - 284 (284) - -
Battle Creek Operating Total - 2,002 (2,002) - 3,171 (3,171) - - 284 (284) - -
FERC 928 - Regulatory Commission Expenses Total - 8,703 (8,703) - 12,064 (12,064) - - 284 (284) - -
O&M 4% Allocation to Battle Creek 303,768 - 303,768 320,638 - 320,638 321,307 160,654 - 160,654 353,748 32,441
Total Bradley Lake Budget 490,268 441,218 49,050 600,938 521,650 79,288 733,784 366,892 305,448 61,444 580,748 (153,036)
- - - - - - - - - - - -
Page 12 of 16
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
Battle Creek Monthly Participating Purchaser Contributions
Schedule G
A B C D E F
FY2024 FY2025 FY2026 FY2027
Annual Annual Annual Annual FY2026 to
Percent Approved Approved Approved Proposed FY2027
POWER PURCHASER Share Budget Budget Budget Budget Change
Chugach Electric 30.40%1,127,194 688,590 738,373 674,646 (63,728)
Homer Electric 37.90%1,405,285 858,472 920,538 841,088 (79,450)
Matanuska Electric 13.80%511,687 312,583 335,183 306,254 (28,929)
Golden Valley Electric 16.90%626,631 382,801 410,477 375,050 (35,428)
City of Seward 1.00%37,079 22,651 24,289 22,192 (2,096)
100.00%3,707,875 2,265,097 2,428,860 2,219,229 (209,631)
FY2024 FY2025 FY2026 FY2027 FY2026 to
Percent Approved Approved Approved Proposed FY2027
POWER PURCHASER Share Monthly Monthly Monthly Monthly Change
Chugach Electric 30.40%93,933 57,382 61,531 56,220 (5,311)
Homer Electric 37.90%117,107 71,539 76,711 70,091 (6,621)
Matanuska Electric 13.80%42,641 26,049 27,932 25,521 (2,411)
Golden Valley Electric 16.90%52,219 31,900 34,206 31,254 (2,952)
City of Seward 1.00%3,090 1,888 2,024 1,849 (175)
100.00%308,990 188,758 202,405 184,936 (17,469)
Page 13 of 16
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
SSQ Line
Capital Purchases (not funded by R&C Fund)
Schedule H
FY24 FY25 FY26 FY24 FY25 FY26 FY27
Actuals Approved Approved Approved Proposed
Actuals Actuals @12/31/25 Budget Budget Budget Budget
Dave's Creek & Soldotna SVC Upgrades - - - - - 250,000
Total Non R&C Capital Purchases - - - - - - 250,000
Capital Project Description
Page 14 of 16
FY 26 FY27
Budget Actual
(Over) Under
Budget to Date Budget Actual
(Over) Under
Budget to Date Budget
Budget to Date
12/31/26
Actual to Date
12/31/25
(Over) Under
Budget to Date Proposed Budget
Increase
(Decrease) From
PY
Summary by expense type
Staff Professional Services (Direct) 15,000 34,357 (19,357) 40,000 7,086 32,914 10,000 5,000 2,079 2,921 15,000 5,000 Labor & Benefits 50,000 - 50,000 50,000 47,722 2,278 50,000 25,000 - 25,000 52,500 2,500
Travel - 338 (338) - 63 (63) - - - - - - Contractual 175,000 - 175,000 150,000 58,795 91,205 150,000 75,000 4,269 70,731 157,500 7,500 Permitting 40,000 2,969 37,031 36,878 72,223 (35,345) 36,878 18,439 3,032 15,408 36,878 -
Supplies & Materials 25,000 567 24,433 20,000 52 19,948 20,000 10,000 - 10,000 21,000 1,000 Other Costs - 1,250 (1,250) - - - - - - - - -
Equipment, Furniture & Machinery - - - - - - - - - - - - Administrative Costs 2,000 38,439 (36,439) 47,000 5,059 41,941 7,000 3,500 754 2,746 7,000 - Total Bradley Lake Budget 307,000 77,920 229,080 343,878 190,998 152,880 273,878 136,939 10,134 126,806 289,878 16,000
FERC 540 - Rents
FERC Land Use FeeSSQ Line Operating
Other Costs - 1,250 (1,250) - - - - - - - - -
SSQ Line Operating Total - 1,250 (1,250) - - - - - - - - -
FERC 540 - Rents Total - 1,250 (1,250) - - - - - - - - -
FERC 556 - System Control & Load Dispatching
PermitsSSQ Line Operating
Permitting 40,000 2,969 37,031 36,878 72,223 (35,345) 36,878 18,439 3,032 15,408 36,878 - SSQ Line Operating Total 40,000 2,969 37,031 36,878 72,223 (35,345) 36,878 18,439 3,032 15,408 36,878 -
FERC 556 - System Control & Load Dispatching Total 40,000 2,969 37,031 36,878 72,223 (35,345) 36,878 18,439 3,032 15,408 36,878 -
#N/AMaintenance of Station Equip
SSQ Line Operating
SSQ Line Operating Total - - - - - - - - - - - -
#N/A - - - - - - - - - - - -
FERC 571 - Maintenance of Overhead Lines
Maint of OH LinesSSQ Line Operating
Labor & Benefits 50,000 - 50,000 50,000 47,722 2,278 50,000 25,000 - 25,000 52,500 2,500 Contractual 175,000 - 175,000 150,000 58,795 91,205 150,000 75,000 4,269 70,731 157,500 7,500
Supplies & Materials 25,000 - 25,000 20,000 - 20,000 20,000 10,000 - 10,000 21,000 1,000
SSQ Line Operating Total 250,000 - 250,000 220,000 106,517 113,483 220,000 110,000 4,269 105,731 231,000 11,000
FERC 571 - Maintenance of Overhead Lines Total 250,000 - 250,000 220,000 106,517 113,483 220,000 110,000 4,269 105,731 231,000 11,000
FERC 920 & 930 - Administrative ExpenseAEA Bradley Fixed Admin FeesBattle Creek Operating
Battle Creek Operating Total - - - - - - - - - - - -
SSQ Line OperatingStaff Professional Services (Direct) 15,000 34,357 (19,357) 40,000 7,086 32,914 10,000 5,000 2,079 2,921 15,000 5,000
Travel - 338 (338) - 63 (63) - - - - - -
Supplies & Materials - 567 (567) - 52 (52) - - - - - - Administrative Costs - 36,439 (36,439) 20,000 3,059 16,941 - - 754 (754) - -
SSQ Line Operating Total 15,000 71,701 (56,701) 60,000 10,259 49,741 10,000 5,000 2,833 2,167 15,000 5,000
General & Administrative Costs
General & Administrative Costs Total - - - - - - - - - - - -
Trust & Account FeesSSQ Line Operating
Administrative Costs 2,000 2,000 - 2,000 2,000 - 2,000 1,000 - 1,000 2,000 - SSQ Line Operating Total 2,000 2,000 - 2,000 2,000 - 2,000 1,000 - 1,000 2,000 -
FERC 920 & 930 - Administrative Expense Total 17,000 73,701 (56,701) 62,000 12,259 49,741 12,000 6,000 2,833 3,167 17,000 5,000
FERC 928 - Regulatory Commission ExpensesFERC Related Prof Services
BRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUES
Administrative Costs - - - 25,000 - 25,000 5,000 2,500 - 2,500 5,000 - BRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUES Total - - - 25,000 - 25,000 5,000 2,500 - 2,500 5,000 -
FERC 928 - Regulatory Commission Expenses Total - - - 25,000 - 25,000 5,000 2,500 - 2,500 5,000 -
Total Bradley Lake Budget 307,000 77,920 229,080 343,878 190,998 152,880 273,878 136,939 10,134 126,806 289,878 16,000
- - - - - - - - - - - -
FY 24 FY 25
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
SSQ LINE OPERATIONS & MAINTENANCE
BUDGET
SCHEDULE I
Page 15 of 16
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
SSQ Line
Monthly Utility Contributions
Schedule J
A B C D E F
FY2024 FY2025 FY2026 FY2027
Annual Annual Annual Annual FY2026 to
Percent Approved Approved Approved Proposed FY2027
Power Purchaser Share Budget Budget Budget Budget Change
Chugach Electric 56.30%418,621 409,342 385,203 545,095 159,892
Homer Electric 12.00%89,227 87,249 82,104 116,184 34,080
Matanuska Electric 13.80%102,611 100,336 94,419 133,611 39,192
Golden Valley Electric 16.90%125,661 122,875 115,629 163,625 47,996
City of Seward 1.00%7,436 7,271 6,842 9,682 2,840
100.00%743,555 727,072 684,197 968,197 284,000
FY2024 FY2025 FY2026 FY2027 FY2026 to
Power Purchaser Percent Approved Approved Approved Proposed FY2027
Share Monthly Monthly Monthly Monthly Change
Chugach Electric 56.30%34,885 34,112 32,100 45,425 13,324
Homer Electric 12.00%7,436 7,271 6,842 9,682 2,840
Matanuska Electric 13.80%8,551 8,361 7,868 11,134 3,266
Golden Valley Electric 16.90%10,472 10,240 9,636 13,635 4,000
City of Seward 1.00%620 606 570 807 237
100.0%61,963 60,589 57,016 80,683 23,667
Page 16 of 16
AEA BPMC Capital Project Finance Update | March 20, 2026
AEA has secured initial
funding for both projects,
which are actively
progressing through early
development. However,
substantial capital investment
is still required to fully
execute each initiative.
Status Overview
Cook Inlet PowerLink
Total cost: $413M
Funds raised to date: $270.7M
Funds still needed: $142.3M
Bradley Lake Expansion Project
Total cost: $400M
Funds raised to date: $20.7M(preconstruction costs)
Funds still needed: $400M
1
Bradley Lake Expansion Project
AEA is advancing the Bradley Lake Expansion Project—which includes the Dixon Diversion and Bradley Pool Raise sub-projects—and would divert water from Dixon Glacier to increase Bradley Lake’s annual hydropower output by approximately 50 percent
As of March 2026, Fiscal Year 2026 funding is secured, environmental studies are underway, a Draft Amendment Application has been submitted to FERC for review, and we continue to meet with a Board of Consultants for design and permitting
SOUTHCENTRAL ALASKA
Bradley Lake Hydroelectric Project
Total Project Cost – $400 Million
May Qualify for Up to $100 Million in Federal Tax Credits
ESTIMATED ANNUAL OUTPUT180,000 MWh
≈ 30,000 homes powered
NATURAL GAS OFFSET
1.5 Billion cu ft
7.5% of unmet demand (2030)
TARGET COMPLETION
2031
Shovel-ready status
ESTIMATED COST
$400 Million
Class IV Estimate
2
$3,600,000 $6,850,000
$13,084,000
$99,280,000
$86,391,000
$106,521,000
$9,352,000
2025 2026 2027 2028 2029 2030 2031
Funding Secured (Target):Q3 2026
Construction Begins:May 2027
Commissioning:December 2030
Bradley Lake Expansion ProjectConstruction Cost Timeline (Thousands)
3AEA BPMC Capital Project Finance Update | March 20, 2026
Cook Inlet PowerLink (CIPLink)
CIPLink is a high-voltage direct current transmission project connecting the Southern and Central Railbelt regions through a 38-mile subsea cable and overland routes, enabling up to 200 megawatts of bidirectional power flow
As of March 2026, preliminary engineering and environmental routing are complete, and the project is advancing into detailed design, permitting, and procurement in alignment with DOE Grid Resilience and Innovation Partnerships timelines
SOUTHCENTRAL ALASKA
Nikiski – Beluga Intertie
Total Project Cost – $413 Million
DOE Grant: $206.5 Million; Match of $64.2 Million Secured; $142.3 Million Needed
CAPACITY200 MW
Bidirectional Flow
CONNECTIVITY
Railbelt Link
Connects South & Central Regions
TARGET COMPLETION
2032
Shovel-ready status
ESTIMATED COST
$413 Million
Preliminary Engineering Done
4AEA BPMC Capital Project Finance Update | March 20, 2026
Funding Secured (Target):Q3 2026
Construction Begins:January 2029
Commissioning:April 2032
Cook Inlet PowerLinkConstruction Cost Timeline (Thousands)
$618,243 $881,757
$63,825,000 $63,825,000
$100,330,977 $99,565,091
$41,896,396 $42,057,536
$-
2024 2025 2026 2027 2028 2029 2030 2031 2032
5AEA BPMC Capital Project Finance Update | March 20, 2026
Expert Partners
Global Law – TechnologyEnergy & Infrastructure – Finance Public Finance Advisory& Capital PlanningGlobal Law – Energy & InfrastructureFinance – Tax
Engineering – Architecture – Environmental Consulting(Cook Inlet PowerLink)
Engineering – Planning – Surveying(Bradley Lake Hydroelectric Project)
6AEA BPMC Capital Project Finance Update | March 20, 2026
7AEA BPMC Capital Project Finance Update | March 20, 2026
Potential Financial Partners
U.S. Department of Energy (DOE) Energy Dominance Financing — Title 17Formerly known as the DOE Loan Programs OfficeTitle 17 Loans for large ($100M+) clean energy projects
U.S. Department of Agriculture (USDA)Rural Utilities Service (RUS) — System Borrow ProgramRUS Electric Infrastructure Loans for existing cooperative borrowers—lowest-cost federal financing
Tax-Exempt BondsSale of tax-advantaged municipal bonds in the public market at reduced interest rate
National Rural Utilities Cooperative Finance Corporation (NRUCFC) — Taxable BondsCurrent bondholder NRUCFC is interested in purchasing another series of Bradley bonds; flexible finance option
Taxable Bond MarketSale of bonds in the public market at current market rate
1
2
3
4
5
BRADLEY LAKE
BRADLEY LAKE & CIPLINK
BRADLEY LAKE & CIPLINK
BRADLEY LAKE & CIPLINK
8
BRADLEY LAKE
AEA BPMC Capital Project Finance Update | March 20, 2026
Investment Tax Credits – Bradley Lake
INVESTMENT TAX CREDITS – significant factor in the financial analysisBradley Lake Expansion Project only; CIPLink is not eligible $100M
POTENTIAL TAX CREDIT VALUE
Eligibility for Tax Credit
Tax credit eligibility analysis for full project scope
Maximizing the Tax Credit Dollar Amount
Strategies to maximize total credit dollar amount through project structuring and timing
The tax credit is reduced by 15 percent if tax-exempt bonds are used in the funding stack
9AEA BPMC Capital Project Finance Update | March 20, 2026
Other Funding Needs
SSQ Transmission and
Substation Upgrades Project
Soldotna–Sterling–Quartz Creek
Total Project Cost
$178.5 million including substation upgrades ($90 million raised to date)
Potential Financial Partners
DOE EDF, USDA RUS, NRUCFC,Public bond market
Next Steps
Pursue financing to complete the project
10AEA BPMC Capital Project Finance Update | March 20, 2026
Dispute Resolution Process -
Wheeling Services Agreement
813 W Northern Lights Blvd, Anchorage, AK 99503 Phone: (907) 771-3000 Fax: (907) 771-3044 Email: info@akenergyauthority.org
REDUCING THE COST OF ENERGY IN ALASKA AKENERGYAUTHORITY.ORG
MEMORANDUM
TO: BPMC
THROUGH: Curtis Thayer, Executive Director
FROM: Jim Mendenhall, P.E., Director of Owned Assets
DATE: March 16,2026
SUBJECT: Cook Inlet Power Link (CIPLINK) Update
Over the past month, AEA has focused on four primary areas of work:
1.Environmental Review and 2026 Marine Survey Planning
As previously reported, AEA issued a Task Order to HDR to advance environmental permitting and
planning for the summer 2026 marine survey season. Stantec, acting as Owner’s Engineer, is
coordinating with HDR to finalize the survey scope and support procurement of a marine survey
contractor.
The objective of the 2026 marine survey program is to collect the geophysical, bathymetric, and
environmental data necessary to refine the submarine cable route and landfall locations to reduce
technical uncertainty for cable suppliers. The survey data will support development of a cable design
that meets project environmental and engineering requirements and will inform future procurement
and installation planning.
AEA is pursuing a U.S. Army Corps of Engineers Nationwide Permit approach for survey activities.
Informal consultation under the Endangered Species Act is underway, including consideration of Cook
Inlet beluga whale protections through the use of low-impact survey methods. The anticipated agency
review period is approximately 8–12 weeks, with permits targeted for issuance by May 2026.
Geotechnical drilling is not currently planned for the 2026 marine survey season. However, limited
onshore boreholes may be completed later in the year at selected landfall locations to support design
and permitting activities.
2.Development of Major Equipment Procurement Documents
Stantec continues to support AEA in developing the procurement strategy and solicitation materials for
the project’s major long-lead equipment, particularly the HVDC converters and submarine cable. These
components are expected to have multiyear manufacturing lead times and represent a critical path for
the project schedule.
Current work includes development of procurement documentation and evaluation of contracting
approaches for these major components. Planned tasks include:
a.Determining contracting strategies for HVDC converters and submarine cable
b.Preparing and issuing requests for information
c.Obtaining preliminary technical information, budgetary pricing, and delivery schedules.
Alaska Energy Authority Page 2 of 2
Early market engagement indicates that the global HVDC cable market remains constrained but more
available than the converter market. Converter manufacturers typically require a preferred supplier or
negotiated agreement before committing significant engineering resources. Firm pricing for these
systems typically becomes available after approximately 30 percent design completion.
Near term procurement packages are expected to include converters and cables, with overhead AC
transmission upgrades, substations, and termination facilities to follow.
3.DOE Negotiations and Community Benefits Plan Adjustment
With the elimination of the Community Benefit Plan (CBP) requirements under the DOE program, DOE
requested that AEA identify credits associated with work originally budgeted to support CBP work.
AEA has prepared a revised Budget Period 2 (BP2) budget reflecting these adjustments. DOE approved
retention of $262,969 of the total CBP related federal funds for eligible project activities. The remaining
$394,454 in federal funds originally allocated to CBP costs will be deobligated from the award.
AEA continues to coordinate with DOE to finalize the BP2 scope and budget.
4.Project Funding and Capital Stack Development
Per agenda item 8-A, AEA continues to evaluate options for completing the capital stack for CIPLink and
other major Railbelt infrastructure projects.
To date, AEA has secured $64.2 million in combined State appropriations and Bradley Lake bond
proceeds to support project development. An additional $142.3 million in funding is being pursued to
fully meet project cost share obligations.
Project expenditures through June 30, 2025 totaled $1,150,569, all of which have been reimbursed by
DOE. Total project expenditures through December 31, 2025 are $1,607,467 and will be invoiced
following execution of the BP2 agreement.
5.Staffing Update
Owned Assets recently hired a staff member to support project development and permitting activities
associated with the CIPLink, Bradley Lake Expansion, and other AEA infrastructure projects. This position
will support coordination of environmental reviews, agency consultation and permitting activities across
the projects.
MEMORANDUM
TO: Bradley Project Management Committee Through: Curtis Thayer, Executive Director FROM: Ryan McLaughlin, PE, Senior Infrastructure Engineer DATE: March 20, 2026 RE: Bradley Lake Expansion Project Update
AEA submitted a Draft Amendment Application (DAA) for the Bradley Lake Expansion Project to the Federal Energy Regulatory Commission (FERC) on February 13, 2026. The application and accompanying study reports are published and publicly available on AEA’s Bradley Expansion webpage. The DAA includes a Preliminary Draft Environmental Analysis as Exhibit E of the application. AEA expects to submit a Final Amendment Application (FAA) 120 days after submittal of the DAA (mid-June) and requests any comments from the public or utilities be submitted to AEA (Ryan McLaughlin) by the end of April so that changes can be incorporated into the FAA.
AEA hosted a Terrestrial Resources meeting on March 4th and Aquatics Resources Meeting on March 5th with resource agencies and members of the public. These meetings discussed results of our environmental studies, expected changes and impacts as a result of proposed project actions, and discussions on AEA’s proposed Protection, Mitigation, and Enhancement (PME) measures. AEA will continue coordination with resource agencies to develop a Minimum Instream Flow and further define PME measures before submittal of the FAA.
A new cost estimate has been developed for the project and the construction total is ~$400MM. Increases from the previous cost estimates are primarily attributable to inflation and market conditions, full concrete lining of the Dixon-Bradley Tunnel, and increased concrete volumes for spillway modifications. This cost estimate is also inclusive of expected FERC-required modifications to the Bradley dam and spillway to pass the update Probable Maximum Flood.
Planning efforts are underway for a long and busy subsurface investigation season. Crews will mobilize during the May high tide window (5/14-16), drill holes in front of the spillway while lake levels are low, an additional hole at the toe of the Bradley dam, geophysics and shallow drilling at the Dixon Diversion Dam site, PS logging through the dam crest, and two deep boreholes along the proposed tunnel alignment (35 days / 1000’ each). 2026 subsurface investigations are expected to be complete by late August / early September. A third Board of Consultants site visit and meeting is scheduled to overlap drilling activities June 23-25.
SQ Upgrade Update
Bradley Lake Operators Report Page 1
Bradley Lake Operator Report
BPMC
March 20, 2026
Unit Statistics:
Generation Unit 1 (MWhrs) Unit 2 (MWhrs) Total (MWhrs)
Jan. 2026
Feb. 2026
Mar. *2026
23,172
20,480
4,637
14,818
9,293
3,179
37,991
29,773
7,817
Hydraulics Avg. Lake Level
(ft.)
Bradley Fishwater
(ac ft.)
Battle Creek MIF
(ac ft.)
Jan. 2026
Feb. 2026
Mar. *2026
1,133
1,124
1,115
2,601
1,678
728
0
0
0
Battle Creek Inflows to Bradley
(ac ft.)
Jan. 2026
Feb. 2026
Mar. *2026
0
0
0
*Lake Level – 1,114.3’ As of Mar. 9, 2026
Activities
• Forced Outages – Unit #2 Failure to shut down. On 16 Feb. 2026 @ 0700hrs. CEA’s attempted to
shut down unit #2 failed. Bradley Operator were notified, secured unit #2 and began trouble
shooting. The issue was traced to a failed coil in the start /stop circuit. The coil was replaced and
tested. The unit was returned to service on 19 Feb. 2026 @0920hrs.
• Dam/Spillway – Completed the monthly Dam Safety inspections and the quarterly Penstock Drain
inspection.
• Battle Creek Diversion- Secured for winter.
• Safety – There have been no lost time or reportable accidents for the months of January,
February and as of to date in March. Conducted a safety meeting on Jan. 8, 2026 & Feb. 11, 2026.
Next safety meeting is March 18, 2026. We conducted Bridge Crane Safety Training on 25 Feb.
2026.
• Fire System- Yukon Fire personnel completed the Kidde fire system installation for the control
room and generators. They have a small punch list items to address. The parts have been
ordered. The system is fully functional.
• Arc Flash Study- Completed the five-year update of the Arc Flash study. Updated the equipment
with new Arc Flash stickers.
• Employee Housing- Complete the restoration work of the fire system water damage in Apt “D”
on Feb. 2, 2026.
Bradley Lake Operators Report Page 2
Contractors/ Visitors
• HEA – Larry Jorgensen & Brad Janorschke, Safety Meeting.
• Yucon Fire – Fire System replacement.
• Country Electric- Aspin Marlin, Ryan Tony, Phase two of the Kidde Fire System Electrical installation.
• Anderson Brothers Construction- Randall Anderson, Andrew Anderson and crew, Apt “D” repairs.
• HEA – JD Harris, Bridge Crane Training.
• Washington Crane- Mike Marquart, Bridge Crane Training Instructor.
Bradley Lake, Feb. 28, 2026. Lake Elevation 1130.6
Bradley Lake Operators Report Page 3
Kidde Control Room and Unit #1 Fire Suppression Bottles
Kidde Fire Control Pannel
Bradley Lake Operators Report Page 4
Apartment “D” Up-Stairs
After Clean-Up After Mold Remediation
Finished Sheetrock, Paint & Flooring
Bradley Lake Operators Report Page 5
Apartment “D” Downstairs
After Clean-Up After Mold Remediation
Finished Paint, Sheetrock & New Windows
Bradley Lake Operators Report Page 6
Northern Lights Over Bradley 21 Feb 2026
Alaska Energy Authority
Bradley Lake
Budget to Actual Expenses
07/01/2025 to 12/31/2025
Page 1 of 12
FY24 FY24 FY25 FY25 FY26 FY26
BUDGET ACTUALS BUDGET ACTUALS BUDGET ACTUALS
Install New Bradley Microwave System 518,000 45,215 - - - -
Brush Hog for Front End Loader 150,000 - - 111,087 - -
JLG All Terrain Fork Lift- New Purchase 190,000 213,942 - - - -
Replace BL#5 2009 F150 Crew Cab Pickup 45,000 - - 48,995 - -
Warehouse Heaters x2 (Replace) 5,000 - - - - -
ISO Shipping Containers x2 (Replace) 40,000 30,700 - - - -
Polaris Side by Side (Replace) - - 65,000 62,645 - -
Crew Quarters Remodel - - 85,000 84,873 - -
New Circuit Breaker - Generator #2 - - - 60,988 - -
Contex HD Ultra X 3690 Color Scanner - - - 12,620 - -
Replace DC Station Service Batteries - - - - 130,000 -
Replace Needle Valve Position Arm Bushings - - - - 95,000 -
Replace ION Meters - - - - 120,000 -
AC unit in powerhouse server room - - - - 38,000 -
Powerhouse Control Rm and Office Flooring - - - - 28,000 -
Approach Path Indicator Lights (Replace) - - - - 40,000 -
Limitorque Actuators on fish water valve (Replace) - - - - 35,000 -
Domestic water tank, controls, and filtration system (Replace) - - - - 35,000 -
Total Non R&C Capital Purchases 948,000 289,857 150,000 381,209 521,000 -
BRADLEY LAKE
CAPITAL PURCHASES NOT FUNDED BY R&C FUND
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
SCHEDULE A
FOR THE PERIOD 07/01/2025 TO 12/31/2025
BRADLEY LAKE NON-R&C CAPITAL PURCHASES
Page 2 of 12
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
BRADLEY LAKE OPERATIONS & MAINTENANCE
BUDGET TO ACTUAL EXPENSES
SCHEDULE B
FOR THE PERIOD 07/01/2025 TO 12/31/2025
FY 26 FY 25
FY26 Approved
Budget
BUDGET %
07/01/2025 -
12/31/2025 HEA Actual CEA Actual AEA Actual Total Actual
(Over) Under
Budget to Date
FY25 Approved
Budget FY25 Actual
Summary by expense type
Staff Professional Services (Direct)360,000 180,000 - - 257,051 257,051 (77,051) 312,585 501,917
Labor & Benefits 1,497,414 748,707 513,787 12,684 119,952 646,423 102,284 2,054,317 1,435,363
Travel 40,300 20,150 410 - 2,978 3,388 16,762 51,500 57,509
Training 55,000 27,500 14,512 - 475 14,987 12,513 55,000 7,211
Contractual 1,392,497 696,249 492,166 - 137,937 630,103 66,146 1,243,010 1,118,636
Consulting-Administrative 155,000 77,500 - - 19,670 19,670 57,830 315,000 46,433
Supplies & Materials 342,000 171,000 63,870 677 - 64,547 106,453 378,500 296,310
Other Costs 77,518 38,759 22,004 14,483 - 36,487 2,272 112,718 95,087 Equipment, Furniture & Machinery 20,000 10,000 7,890 - 583 8,473 1,527 35,000 19,940
Administrative Costs 2,549,839 1,274,920 34,956 - 876,918 911,874 363,046 1,978,224 2,088,063
Indirect Costs 1,543,116 771,558 645,133 - - 645,133 126,425 1,480,105 1,340,986
O&M 4% Allocation to Battle Creek (321,307) (160,654) - - - - (160,654) (320,638) -
Total Bradley Lake Budget 7,711,376 3,855,688 1,794,729 27,844 1,415,565 3,238,138 617,550 7,695,321 7,007,455
FERC 535 - Operation Supervision & Engineering
Operations Sup/Eng
Bradley Lake Operating
Labor & Benefits 109,196 54,598 53,683 - - 53,683 915 105,451 99,743
Travel 5,000 2,500 - - - - 2,500 5,000 668
Training 5,000 2,500 - - - - 2,500 5,000 -
Contractual 3,000 1,500 - - - - 1,500 3,000 407
Supplies & Materials 25,000 12,500 1,153 - - 1,153 11,347 4,000 -
Indirect Costs 157,071 78,535 74,502 - - 74,502 4,033 155,698 139,723
Bradley Lake Operating Total 304,267 152,134 129,338 - - 129,338 22,795 278,149 240,542
FERC 535 - Operation Supervision & Engineering Total 304,267 152,134 129,338 - - 129,338 22,795 278,149 240,542
FERC 537 - Hydraulic Expenses
Hydraulic Expenses
Bradley Lake Operating
Labor & Benefits 81,895 40,947 40,449 - - 40,449 498 95,262 79,042
Contractual 15,000 7,500 - - - - 7,500 - -
Supplies & Materials 10,000 5,000 1,310 - - 1,310 3,690 4,000 1,729
Indirect Costs 113,127 56,564 52,543 - - 52,543 4,021 109,250 108,693
Bradley Lake Operating Total 220,022 110,011 94,302 - - 94,302 15,709 208,512 189,464
FERC 537 - Hydraulic Expenses Total 220,022 110,011 94,302 - - 94,302 15,709 208,512 189,464
FERC 538 - Electric ExpensesElectric Expenses
Bradley Lake Operating
Labor & Benefits 235,187 117,594 118,254 - - 118,254 (661) 218,044 227,478
Travel 7,000 3,500 303 - - 303 3,197 7,000 293
Training 30,000 15,000 14,512 - - 14,512 488 30,000 3,990
Contractual 18,000 9,000 12,133 - - 12,133 (3,133) 10,000 5,255
Supplies & Materials 23,500 11,750 1,294 - - 1,294 10,456 18,500 5,970
Indirect Costs 280,431 140,215 137,942 - - 137,942 2,274 262,004 268,318
Bradley Lake Operating Total 594,118 297,059 284,437 - - 284,437 12,622 545,548 511,305
FERC 538 - Electric Expenses Total 594,118 297,059 284,437 - - 284,437 12,622 545,548 511,305
FERC 539 - Misc. Hydraulic Power Generation Expenses
Misc Hydro Power Exp
Bradley Lake OperatingLabor & Benefits 130,567 65,283 34,354 - - 34,354 30,929 107,742 78,868
Training 20,000 10,000 - - - - 10,000 20,000 -
Contractual 606,317 303,159 298,728 - - 298,728 4,430 385,067 410,619
Supplies & Materials 30,000 15,000 9,905 - - 9,905 5,095 25,000 45,819
Equipment, Furniture & Machinery - - - - - - - - 2,563
Indirect Costs 122,323 61,162 47,748 - - 47,748 13,414 114,320 111,127 Bradley Lake Operating Total 909,207 454,604 390,736 - - 390,736 63,867 652,129 648,997
BRADLEY CIRCUITS/RADIO TO BERNICE LK
Other Costs 35,695 17,848 17,134 - - 17,134 713 35,695 34,268 BRADLEY CIRCUITS/RADIO TO BERNICE LK Total 35,695 17,848 17,134 - - 17,134 713 35,695 34,268
BRADLEY CIRCUITS BERNICE LK TO ANCH
Other Costs 29,773 14,887 - 14,483 - 14,483 404 29,773 28,985 BRADLEY CIRCUITS BERNICE LK TO ANCH Total 29,773 14,887 - 14,483 - 14,483 404 29,773 28,985
LOWER BRADLEY CIRCUITS/RADIO TO BARGE DOCK
Other Costs 10,000 5,000 4,870 - - 4,870 130 45,000 24,085 LOWER BRADLEY CIRCUITS/RADIO TO BARGE DOCK Total 10,000 5,000 4,870 - - 4,870 130 45,000 24,085
FERC 539 - Misc. Hydraulic Power Generation Expenses Total 984,675 492,338 412,741 14,483 - 427,223 65,114 762,597 736,335
FERC 541 - Maintenance Supervision & Engineering
Maint Supervision/Eng
Bradley Lake Operating
Labor & Benefits 117,056 58,528 55,603 - - 55,603 2,925 110,451 104,197
Indirect Costs 157,071 78,535 74,502 - - 74,502 4,033 155,698 139,723 Bradley Lake Operating Total 274,127 137,064 130,105 - - 130,105 6,958 266,149 243,920
FERC 541 - Maintenance Supervision & Engineering Total 274,127 137,064 130,105 - - 130,105 6,958 266,149 243,920
FERC 542 - Maintenance of Structures
Maintenance of Structures
Bradley Lake Operating
Labor & Benefits 84,789 42,394 30,808 - - 30,808 11,587 89,710 67,928
Contractual 35,000 17,500 14,804 - - 14,804 2,696 126,000 103,435
Supplies & Materials 44,000 22,000 8,975 - - 8,975 13,025 70,000 40,551
Equipment, Furniture & Machinery 20,000 10,000 7,890 - - 7,890 2,110 20,000 14,623
Indirect Costs 115,838 57,919 42,717 - - 42,717 15,202 102,350 94,601
Bradley Lake Operating Total 299,627 149,814 105,194 - - 105,194 44,619 408,060 321,138
FERC 542 - Maintenance of Structures Total 299,627 149,814 105,194 - - 105,194 44,619 408,060 321,138
FERC 543 - Maintenance of Reservoirs, Dams & Waterways
Maint Res, Dams, WWays
Bradley Lake Operating
Labor & Benefits 17,992 8,996 1,110 - - 1,110 7,886 51,783 13,050
Page 3 of 12
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
BRADLEY LAKE OPERATIONS & MAINTENANCE
BUDGET TO ACTUAL EXPENSES
SCHEDULE B
FOR THE PERIOD 07/01/2025 TO 12/31/2025
FY 26 FY 25
FY26 Approved
Budget
BUDGET %
07/01/2025 -
12/31/2025 HEA Actual CEA Actual AEA Actual Total Actual
(Over) Under
Budget to Date
FY25 Approved
Budget FY25 Actual
Contractual 6,500 3,250 11,162 - - 11,162 (7,912) 39,500 41,306
Supplies & Materials 20,000 10,000 283 - - 283 9,717 85,000 63,338
Equipment, Furniture & Machinery - - - - - - - 15,000 -
Indirect Costs 22,556 11,278 1,720 - - 1,720 9,558 58,650 16,000
Bradley Lake Operating Total 67,048 33,524 14,275 - - 14,275 19,249 249,933 133,694
BRADLEY POWER TUNNEL MAINT (Dam)
Contractual 15,000 7,500 - - - - 7,500 15,000 -
BRADLEY POWER TUNNEL MAINT (Dam) Total 15,000 7,500 - - - - 7,500 15,000 -
FERC 543 - Maintenance of Reservoirs, Dams & Waterways Total 82,048 41,024 14,275 - - 14,275 26,749 264,933 133,694
FERC 544 - Maintenance of Electric Plant
Maintenance of Elec Plant
Bradley Lake Operating
Labor & Benefits 336,995 168,498 121,607 - - 121,607 46,890 309,110 261,477
Travel 4,500 2,250 108 - - 108 2,142 4,500 530
Contractual 24,000 12,000 37,284 - - 37,284 (25,284) 75,000 60,276
Supplies & Materials 40,000 20,000 7,809 - - 7,809 12,191 40,000 35,276
Indirect Costs 461,361 230,680 169,273 - - 169,273 61,407 423,178 367,649
Bradley Lake Operating Total 866,856 433,428 336,081 - - 336,081 97,347 851,788 725,208
FERC 544 - Maintenance of Electric Plant Total 866,856 433,428 336,081 - - 336,081 97,347 851,788 725,208
FERC 545 - Maintenance of Misc. Hydraulic Plant
Maint of Misc Hydr Plant
Bradley Lake Operating
Labor & Benefits 82,339 41,170 31,999 - - 31,999 9,171 69,297 68,096
Contractual 45,000 22,500 43,938 - - 43,938 (21,438) 45,000 38,420
Supplies & Materials 68,000 34,000 26,890 - - 26,890 7,110 68,000 56,391
Indirect Costs 113,337 56,669 44,186 - - 44,186 12,483 98,957 95,152
Bradley Lake Operating Total 308,677 154,338 147,013 - - 147,013 7,326 281,254 258,059
FERC 545 - Maintenance of Misc. Hydraulic Plant Total 308,677 154,338 147,013 - - 147,013 7,326 281,254 258,059
FERC 556 - System Control & Load Dispatching
System Cntl & Load Disp
Bradley Lake Operating
Labor & Benefits 20,174 10,087 21,159 - - 21,159 (11,072) 20,174 25,978
Contractual 143,500 71,750 20,757 - - 20,757 50,993 103,500 49,188
Supplies & Materials 12,000 6,000 - - - - 6,000 12,000 854
Bradley Lake Operating Total 175,674 87,837 41,916 - - 41,916 45,921 135,674 76,020
Snow Measurement
Bradley Lake Operating
Contractual 10,000 5,000 - - - - 5,000 10,000 9,600
Bradley Lake Operating Total 10,000 5,000 - - - - 5,000 10,000 9,600
Seismic Service
Bradley Lake Operating
Contractual 66,498 33,249 - - 28,649 28,649 4,600 64,868 62,273
Bradley Lake Operating Total 66,498 33,249 - - 28,649 28,649 4,600 64,868 62,273
Streamguaging Serv
Bradley Lake Operating
Contractual 221,682 110,841 - - 109,287 109,287 1,554 216,275 269,784 Bradley Lake Operating Total 221,682 110,841 - - 109,287 109,287 1,554 216,275 269,784
Permits
Bradley Lake Operating
Other Costs 350 175 - - - - 175 350 240 Bradley Lake Operating Total 350 175 - - - - 175 350 240
FERC 556 - System Control & Load Dispatching Total 474,204 237,102 41,916 - 137,937 179,852 57,250 427,167 417,917
FERC 562 - Station Expenses
Station Expenses
Bradley Lake Operating
Labor & Benefits 99,812 49,906 4,760 12,684 - 17,444 32,462 96,612 135,584
Travel 1,800 900 - - - - 900 2,500 773
Contractual 103,000 51,500 53,360 - - 53,360 (1,860) 79,800 32,843
Supplies & Materials 45,000 22,500 6,251 677 - 6,928 15,572 23,000 25,534
Other Costs 1,700 850 - - - - 850 1,900 1,536
Bradley Lake Operating Total 251,312 125,656 64,371 13,361 - 77,732 47,924 203,812 196,269
FERC 562 - Station Expenses Total 251,312 125,656 64,371 13,361 - 77,732 47,924 203,812 196,269
FERC 570 - Maintenance of Station Equipment
Maintenance of Station EquipBradley Lake Operating
Bradley Lake Operating Total - - - - - - - - -
FERC 570 - Maintenance of Station Equipment Total - - - - - - - - -
FERC 571 - Maintenance of Overhead Lines
Maint of OH Lines
Bradley Lake Operating
Labor & Benefits 32,574 16,287 - - - - 16,287 36,500 23,486
Contractual 80,000 40,000 - - - - 40,000 70,000 35,229
Supplies & Materials 20,000 10,000 - - - - 10,000 20,000 11,965
Bradley Lake Operating Total 132,574 66,287 - - - - 66,287 126,500 70,681
FERC 571 - Maintenance of Overhead Lines Total 132,574 66,287 - - - - 66,287 126,500 70,681
FERC 920 & 930 - Administrative Expense
AEA Bradley Fixed Admin Fees
Bradley Lake Operating
Staff Professional Services (Direct)360,000 180,000 - - 257,051 257,051 (77,051) 312,585 501,917
Travel - - - - 2,978 2,978 (2,978) - 53,177
Training - - - - 475 475 (475) - 3,221
Consulting-Administrative - - - - 1,037 1,037 (1,037) - 2,153
Supplies & Materials - - - - - - - - 8,882
Other Costs - - - - - - - - 5,972
Equipment, Furniture & Machinery - - - - 583 583 (583) - 2,754
Administrative Costs 240,000 120,000 - - 114,738 114,738 5,262 172,500 455,441
Page 4 of 12
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
BRADLEY LAKE OPERATIONS & MAINTENANCE
BUDGET TO ACTUAL EXPENSES
SCHEDULE B
FOR THE PERIOD 07/01/2025 TO 12/31/2025
FY 26 FY 25
FY26 Approved
Budget
BUDGET %
07/01/2025 -
12/31/2025 HEA Actual CEA Actual AEA Actual Total Actual
(Over) Under
Budget to Date
FY25 Approved
Budget FY25 Actual
Bradley Lake Operating Total 600,000 300,000 - - 376,862 376,862 (76,862) 485,085 1,033,515
Operating Committee Exp-Audit
Bradley Lake Operating
Administrative Costs 45,000 22,500 - - - - 22,500 41,000 38,534
Bradley Lake Operating Total 45,000 22,500 - - - - 22,500 41,000 38,534
Operating Committee Exp-Legal
Bradley Lake Operating
Administrative Costs 80,000 40,000 - - 60,885 60,885 (20,885) 80,000 125,918 Bradley Lake Operating Total 80,000 40,000 - - 60,885 60,885 (20,885) 80,000 125,918
Misc Admin
Bradley Lake Operating
Administrative Costs 13,000 6,500 - - 15,103 15,103 (8,603) 13,000 14,634
Bradley Lake Operating Total 13,000 6,500 - - 15,103 15,103 (8,603) 13,000 14,634
Professional Consultants
Bradley Lake Operating
Labor & Benefits 148,836 74,418 - - 119,952 119,952 (45,534) 744,181 250,437
Travel 22,000 11,000 - - - - 11,000 32,500 2,068
Supplies & Materials 4,500 2,250 - - - - 2,250 9,000 -
Bradley Lake Operating Total 175,336 87,668 - - 119,952 119,952 (32,284) 785,681 252,505
FERC 920 & 930 - Administrative Expense Total 913,336 456,668 - - 572,802 572,802 (116,134) 1,404,766 1,465,107
FERC 924 & 925 - Insurance Premiums
Insurance Premiums
Bradley Lake Operating
Administrative Costs 1,581,839 790,920 34,956 - 679,368 714,323 76,596 1,371,724 1,164,007
Bradley Lake Operating Total 1,581,839 790,920 34,956 - 679,368 714,323 76,596 1,371,724 1,164,007
FERC 924 & 925 - Insurance Premiums Total 1,581,839 790,920 34,956 - 679,368 714,323 76,596 1,371,724 1,164,007
FERC 923 - Outside Services Employed
Outside Services Employed
Bradley Lake Operating
Consulting-Administrative 155,000 77,500 - - 18,634 18,634 58,866 315,000 44,280
Bradley Lake Operating Total 155,000 77,500 - - 18,634 18,634 58,866 315,000 44,280
FERC 923 - Outside Services Employed Total 155,000 77,500 - - 18,634 18,634 58,866 315,000 44,280
FERC 928 - Regulatory Commission Expenses
FERC Admin Fees
Bradley Lake OperatingAdministrative Costs 170,000 85,000 - - - - 85,000 180,000 213,420
Bradley Lake Operating Total 170,000 85,000 - - - - 85,000 180,000 213,420
FERC Related Prof ServicesBRADLEY FERC PART 12 INSPECTION
Administrative Costs 300,000 150,000 - - - - 150,000 - -
BRADLEY FERC PART 12 INSPECTION Total 300,000 150,000 - - - - 150,000 - -
BRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUES
Administrative Costs 120,000 60,000 - - 6,825 6,825 53,175 120,000 76,109
BRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUES Total 120,000 60,000 - - 6,825 6,825 53,175 120,000 76,109
FERC 928 - Regulatory Commission Expenses Total 590,000 295,000 - - 6,825 6,825 288,175 300,000 289,529
O&M 4% Allocation to Battle Creek (321,307) (160,654) - - - - (160,654) (320,638) -
Total Bradley Lake Budget 7,711,376 3,855,688 1,794,729 27,844 1,415,565 3,238,138 617,550 7,695,321 7,007,455
- - - - - - - - -
Page 5 of 12
Actual Projected Actual Projected Actual Projected@ 6/30/24 TO REPAY Budget @ 6/30/25 TO REPAY Budget @ 6/30/26 TO REPAY Budget
Description Expense @6/30/24 FY24 Expense @6/30/25 FY25 Expense @6/30/26 FY26
R&C FUND PROJECTS
Governor - 4,052,070 - - 4,052,070 - - 4,052,070 -
Replace RFLS - 251,093 - - 251,093 - - 251,093 -
Replace Runners - 1,946,733 - - 1,946,733 - - 1,946,733 -
Replace cable from dam to power house - 2,321,923 - - 2,321,923 - - 2,321,923 -
Replace power system stabilizer - 619,205 - - 619,205 - - 619,205 -
Replace two RTUs - 86,905 - - 86,905 - - 86,905 -
Culvert Repairs - 675,967 - - 675,967 - - 675,967 -
Tower Repair for Jack Frost Heaves - 887,597 - - 887,597 - - 887,597 -
Replace Plant and SCADA Controls - 1,344,683 - - 1,344,683 - - 1,344,683 -
Vibration Monitoring System - 490 - - 490 - - 490 -
Fire Alarm System Replacement 33,942 171,339 1,338,000 - 171,339 1,307,299 205,000 376,339 1,471,407
Battle Creek Diversion - 1,170,000 - - 1,170,000 - - 1,170,000 -
Bradley Replace Electro-Mechanical Relays - 1,277,197 - - 1,277,197 - - 1,277,197 -
Fishwater Screen Debris Removal - 312,236 - - 312,236 - - 312,236 -
Turbine Nozzle Repair - 1,428,861 - - 1,428,861 - - 1,428,861 -
SVC replacement Daves Creek | Soldotna - 8,517,991 - - 8,517,991 - - 8,517,991 -
Equipment Storage Shed - 510,550 - - 510,550 - - 510,550 -
Emerson Operating System Upgrade - 622,665 - - 622,665 - - 622,665 -
Generator #2 Replacement - 953,213 - - 953,213 - - 953,213 -
Road Grader - 342,330 - - 342,330 - - 342,330 -
Battle Creek Construction - 3,739,591 - - 3,739,591 - - 3,739,591 -
Battle Creek Cash Call-Expended - 750,000 - - 750,000 - - 750,000 -
Battle Creek Cash Call-Paid by Utilities - (750,000) - - (750,000) - - (750,000) -
Needle Repairs - 1,482,791 - - 1,482,791 - - 1,482,791 -
Construct Additional Residence 805,515 1,000,284 910,000 75,156 1,075,440 - - 1,075,440 -
Bradley Lake Expansion Project**176,092 1,384,822 252,000 774,357 2,159,179 839,270 62,582 2,221,761 -
Needle Valve Rebuild 198,086 198,086 1,579,535 1,504,127 1,702,213 1,719,535 - 1,702,213 -
Barge Dock Rehabilitation - - - 401 401 600,000 - 401 600,000
Critical Spare (2) Nozzle Assemblies - - - - - - - - 400,000
Change out turbine nozzles units #1 and #2 - - - - - - - - 1,021,000
1,213,635 35,298,622 4,079,535 2,354,041 37,652,663 4,466,103 267,582 37,920,245 3,492,407
Current Year R&C Repayment (3,338,646) (2,580,808) (2,580,808)
Adjust balance to $5 million - - -
Interest in Fund Applied to Repayment (246,205) (157,748) (54,343)
Net Transfer from Revenue Fund (3,584,851) (2,738,556) (2,635,151)
Cumulative Prior Years R&C Repayments (31,677,137) (33,746,653) (35,082,970)
Due to (from) Utilities 1,515,335 1,402,238 2,635,151
Adjust Due to R&C Actual - - -
(30,161,802) (32,344,414) (32,447,820)
NET DUE TO R&C FUND 1,551,969 2,569,693 2,837,275
R&C FUND CASH FLOW PROJECTION
Beginning Investment Balance 4,370,333 6,177,000 6,186,586
Disbursements-current year -Accrual - - -
Disbursements-prior year accrued (789,379) (1,213,635) (2,354,041)
Utilities' R&C Refund (988,805) (1,515,335) (1,402,238)
Net other cash inflow(outflow) - - -
Current year interest earnings 246,205 157,748 54,343
Participants Contributions to R&C Fund 3,338,646 2,580,808 2,580,808
Ending Investment Balance 6,177,000 6,186,586 5,065,458
Accrued Due to (from) Utilities (1,515,335) (1,402,238) (2,635,151)
R&C payable back to the revenue fund - - -
Accrued R&C vendor Payable at Year End (1,213,635) (2,354,041) (267,582)
PROJECTED NET DUE + ENDING INVESTMENT BALANCE 5,000,000 5,000,000 5,000,000
Bradley Lake Expansion Project
Budget Committed Encumbered Actuals Variance
Bradley Lake R&C Fund 2,300,000 22,280 57,384 2,220,336 -
REF Grant (CEA) 1,000,000 - 315,640 684,360 -
REF Grant Match 1,000,000 - - - 1,000,000
State Hydro Development 5,000,000 20,000 124,240 4,855,760 -
State Railbelt 1,379,700 - 626,644 753,056 -
Bond Series 11 Interest 6,000,000 - 1,402,612 236,512 4,360,875
Bradley Lake Dixon Diversion 4,000,000 - 2,470,865 1,529,135 -
Total Project Cost at 12/31/25 20,679,700 42,280 4,997,385 10,279,159 5,360,875
4th 1,321,709
3rd 247,054 4th 247,054
2nd 197,345 3rd 197,345 4th 197,345
1st 303,409 2nd 303,409 3rd 303,409
1st 588,510 2nd 588,510
1st 66,896
2,069,516 1,336,318 1,156,159
BRADLEY LAKE HYDROELECTRIC PROJECT
R&C FUND DISBURSEMENTS AND REPAYMENTS
SCHEDULE D
FOR THE PERIOD 07/01/2025 T0 12/31/2025
ALASKA ENERGY AUTHORITY
Page 6 of 12
FY24 FY24 FY25 FY25 FY26 FY26
BUDGET ACTUALS BUDGET ACTUALS BUDGET ACTUALS
Battle Creek Associated Costs 15,000 - - - - -
Survey and Monument DNR Lease 150,000 88,651 5,000 2,621 5,000 -
Total Non R&C Capital Purchases 165,000 88,651 5,000 2,621 5,000 -
BATTLE CREEK
CAPITAL PURCHASES NOT FUNDED BY R&C FUND
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
BATTLE CREEK NON-R&C CAPITAL PURCHASES
SCHEDULE E
FOR THE PERIOD 07/01/2025 TO 12/31/2025
Page 7 of 12
BATTLE CREEK OPERATIONS & MAINTENANCE
BUDGET TO ACTUAL EXPENSES
SCHEDULE F
FOR THE PERIOD 07/01/2025 TO 12/31/2025
FY 26 FY 25
FY26 Approved
Budget
BUDGET %
07/01/2025 -
12/31/2025 HEA Actual CEA Actual AEA Actual Total Actual
(Over) Under
Budget to Date
FY25 Approved
Budget FY25 Actual
Summary by expense type
Staff Professional Services (Direct)50,000 25,000 - - 22,750 22,750 2,250 50,000 46,192
Labor & Benefits 10,000 5,000 21,408 529 4,998 26,934 (21,934) 10,000 59,807
Travel - - 17 - 124 141 (141) - 3,322
Training - - 605 - 20 624 (624) - 300
Contractual 333,477 166,739 20,507 - 164,233 184,740 (18,002) 201,300 243,987
Consulting-Administrative - - - - 820 820 (820) - 1,935
Supplies & Materials 5,000 2,500 2,661 28 - 2,689 (189) 5,000 12,346
Other Costs - - 917 603 - 1,520 (1,520) - 3,962 Equipment, Furniture & Machinery - - 329 - 24 353 (353) - 831
Administrative Costs 14,000 7,000 1,456 - 36,538 37,995 (30,995) 14,000 93,093
Indirect Costs - - 26,881 - - 26,881 (26,881) - 55,874
O&M 4% Allocation to Battle Creek 321,307 160,654 - - - - 160,654 320,638 -
Total Battle Creek Budget 733,784 366,892 74,780 1,160 229,508 305,448 61,444 600,938 521,650
FERC 535 - Operation Supervision & Engineering
Operations Sup/Eng
Battle Creek Operating
Labor & Benefits 1,500 750 2,237 - - 2,237 (1,487) 1,500 4,156
Travel - - - - - - - - 28
Contractual - - - - - - - - 17
Supplies & Materials 1,000 500 48 - - 48 452 1,000 -
Indirect Costs - - 3,104 - - 3,104 (3,104) - 5,822
Battle Creek Operating Total 2,500 1,250 5,389 - - 5,389 (4,139) 2,500 10,023
FERC 535 - Operation Supervision & Engineering Total 2,500 1,250 5,389 - - 5,389 (4,139) 2,500 10,023
FERC 537 - Hydraulic Expenses
Hydraulic Expenses
Battle Creek Operating
Labor & Benefits 1,500 750 1,685 - - 1,685 (935) 1,500 3,293
Contractual 277,177 138,589 - - 143,736 143,736 (5,147) 145,000 141,077
Supplies & Materials 1,000 500 55 - - 55 445 1,000 72
Indirect Costs - - 2,189 - - 2,189 (2,189) - 4,529
Battle Creek Operating Total 279,677 139,839 3,929 - 143,736 147,665 (7,827) 147,500 148,972
FERC 537 - Hydraulic Expenses Total 279,677 139,839 3,929 - 143,736 147,665 (7,827) 147,500 148,972
FERC 538 - Electric Expenses
Electric ExpensesBattle Creek Operating
Labor & Benefits 1,500 750 4,927 - - 4,927 (4,177) 1,500 9,478
Travel - - 13 - - 13 (13) - 12
Training - - 605 - - 605 (605) - 166
Contractual - - 506 - - 506 (506) - 219
Supplies & Materials 1,000 500 54 - - 54 446 1,000 249
Indirect Costs - - 5,748 - - 5,748 (5,748) - 11,180
Battle Creek Operating Total 2,500 1,250 11,852 - - 11,852 (10,602) 2,500 21,304
FERC 538 - Electric Expenses Total 2,500 1,250 11,852 - - 11,852 (10,602) 2,500 21,304
FERC 539 - Misc. Hydraulic Power Generation Expenses
Misc Hydro Power Exp
Battle Creek Operating
Labor & Benefits 1,500 750 1,431 - - 1,431 (681) 1,500 3,286 Contractual - - 12,447 - - 12,447 (12,447) - 17,109
Supplies & Materials 1,000 500 413 - - 413 87 1,000 1,909
Other Costs - - 917 603 - 1,520 (1,520) - 3,639
Equipment, Furniture & Machinery - - - - - - - - 107
Indirect Costs - - 1,990 - - 1,990 (1,990) - 4,630 Battle Creek Operating Total 2,500 1,250 17,198 603 - 17,801 (16,551) 2,500 30,681
FERC 539 - Misc. Hydraulic Power Generation Expenses Total 2,500 1,250 17,198 603 - 17,801 (16,551) 2,500 30,681
FERC 541 - Maintenance Supervision & Engineering
Maint Supervision/Eng
Battle Creek Operating
Labor & Benefits 2,500 1,250 2,317 - - 2,317 (1,067) 2,500 4,342
Indirect Costs - - 3,104 - - 3,104 (3,104) - 5,822 Battle Creek Operating Total 2,500 1,250 5,421 - - 5,421 (4,171) 2,500 10,163
FERC 541 - Maintenance Supervision & Engineering Total 2,500 1,250 5,421 - - 5,421 (4,171) 2,500 10,163
FERC 542 - Maintenance of Structures
Maintenance of Structures
Battle Creek Operating
Labor & Benefits 1,500 750 1,284 - - 1,284 (534) 1,500 2,830
Contractual - - 617 - - 617 (617) - 4,310
Supplies & Materials 1,000 500 374 - - 374 126 1,000 1,690
Equipment, Furniture & Machinery - - 329 - - 329 (329) - 609
Indirect Costs - - 1,780 - - 1,780 (1,780) - 3,942
Battle Creek Operating Total 2,500 1,250 4,383 - - 4,383 (3,133) 2,500 13,381
FERC 542 - Maintenance of Structures Total 2,500 1,250 4,383 - - 4,383 (3,133) 2,500 13,381
FERC 543 - Maintenance of Reservoirs, Dams & Waterways
Maint Res, Dams, WWays
Battle Creek Operating
Labor & Benefits - - 46 - - 46 (46) - 544
Contractual - - 465 - - 465 (465) - 1,721
Supplies & Materials - - 12 - - 12 (12) - 2,639
Indirect Costs - - 72 - - 72 (72) - 667
Battle Creek Operating Total - - 595 - - 595 (595) - 5,571
FERC 543 - Maintenance of Reservoirs, Dams & Waterways Total - - 595 - - 595 (595) - 5,571
FERC 544 - Maintenance of Electric Plant
Maintenance of Elec Plant
Battle Creek Operating
Labor & Benefits - - 5,067 - - 5,067 (5,067) - 10,895
Travel - - 4 - - 4 (4) - 22
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
Page 8 of 12
BATTLE CREEK OPERATIONS & MAINTENANCE
BUDGET TO ACTUAL EXPENSES
SCHEDULE F
FOR THE PERIOD 07/01/2025 TO 12/31/2025
FY 26 FY 25
FY26 Approved
Budget
BUDGET %
07/01/2025 -
12/31/2025 HEA Actual CEA Actual AEA Actual Total Actual
(Over) Under
Budget to Date
FY25 Approved
Budget FY25 Actual
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
Contractual - - 1,554 - - 1,554 (1,554) - 2,511
Supplies & Materials - - 325 - - 325 (325) - 1,470
Indirect Costs - - 7,053 - - 7,053 (7,053) - 15,319
Battle Creek Operating Total - - 14,003 - - 14,003 (14,003) - 30,217
FERC 544 - Maintenance of Electric Plant Total - - 14,003 - - 14,003 (14,003) - 30,217
FERC 545 - Maintenance of Misc. Hydraulic Plant
Maint of Misc Hydr Plant
Battle Creek Operating
Labor & Benefits - - 1,333 - - 1,333 (1,333) - 2,837
Contractual - - 1,831 - - 1,831 (1,831) - 1,601
Supplies & Materials - - 1,120 - - 1,120 (1,120) - 2,350
Indirect Costs - - 1,841 - - 1,841 (1,841) - 3,965
Battle Creek Operating Total - - 6,126 - - 6,126 (6,126) - 10,752
FERC 545 - Maintenance of Misc. Hydraulic Plant Total - - 6,126 - - 6,126 (6,126) - 10,752
FERC 556 - System Control & Load Dispatching
System Cntl & Load Disp
Bradley Lake Operating
Bradley Lake Operating Total - - - - - - - - -
Battle Creek Operating
Labor & Benefits - - 882 - - 882 (882) - 1,082
Contractual - - 865 - - 865 (865) - 2,049
Supplies & Materials - - - - - - - - 36
Battle Creek Operating Total - - 1,746 - - 1,746 (1,746) - 3,167
Snow Measurement
Battle Creek Operating
Contractual - - - - - - - - 400
Battle Creek Operating Total - - - - - - - - 400
Seismic Service
Battle Creek Operating
Contractual - - - - 1,194 1,194 (1,194) - 2,595 Battle Creek Operating Total - - - - 1,194 1,194 (1,194) - 2,595
Streamguaging Serv
Battle Creek Operating
Contractual 56,300 28,150 - - 19,304 19,304 8,846 56,300 67,541 Battle Creek Operating Total 56,300 28,150 - - 19,304 19,304 8,846 56,300 67,541
Permits
Battle Creek Operating
Other Costs - - - - - - - - 10
Battle Creek Operating Total - - - - - - - - 10
FERC 556 - System Control & Load Dispatching Total 56,300 28,150 1,746 - 20,497 22,244 5,906 56,300 73,713
FERC 562 - Station Expenses
Station Expenses
Battle Creek Operating
Labor & Benefits - - 198 529 - 727 (727) - 5,649
Travel - - - - - - - - 32
Contractual - - 2,223 - - 2,223 (2,223) - 1,368
Supplies & Materials - - 260 28 - 289 (289) - 1,064
Other Costs - - - - - - - - 64
Battle Creek Operating Total - - 2,682 557 - 3,239 (3,239) - 8,178
FERC 562 - Station Expenses Total - - 2,682 557 - 3,239 (3,239) - 8,178
FERC 571 - Maintenance of Overhead LinesMaint of OH Lines
Battle Creek Operating
Labor & Benefits - - - - - - - - 979
Contractual - - - - - - - - 1,468
Supplies & Materials - - - - - - - - 499 Battle Creek Operating Total - - - - - - - - 2,945
FERC 571 - Maintenance of Overhead Lines Total - - - - - - - - 2,945
FERC 920 & 930 - Administrative Expense
AEA Bradley Fixed Admin Fees
Battle Creek Operating
Staff Professional Services (Direct)50,000 25,000 - - 22,750 22,750 2,250 50,000 46,192
Travel - - - - 124 124 (124) - 3,142
Training - - - - 20 20 (20) - 134 Consulting-Administrative - - - - 43 43 (43) - 90
Supplies & Materials - - - - - - - - 370
Other Costs - - - - - - - - 249
Equipment, Furniture & Machinery - - - - 24 24 (24) - 115
Administrative Costs - - - - 4,781 4,781 (4,781) - 18,977 Battle Creek Operating Total 50,000 25,000 - - 27,743 27,743 (2,743) 50,000 69,268
Operating Committee Exp-Audit
Battle Creek Operating
Administrative Costs - - - - - - - - 1,606 Battle Creek Operating Total - - - - - - - - 1,606
Operating Committee Exp-Legal
Battle Creek Operating
Administrative Costs 5,000 2,500 - - 2,537 2,537 (37) 5,000 5,247
Battle Creek Operating Total 5,000 2,500 - - 2,537 2,537 (37) 5,000 5,247
Operat Committee Exp-Arbitrage
Battle Creek Operating
Administrative Costs 2,500 1,250 - - - - 1,250 2,500 1,690
Battle Creek Operating Total 2,500 1,250 - - - - 1,250 2,500 1,690
Trust & Account Fees
Battle Creek Operating
Administrative Costs 5,500 2,750 - - - - 2,750 5,500 4,400
Battle Creek Operating Total 5,500 2,750 - - - - 2,750 5,500 4,400
Page 9 of 12
BATTLE CREEK OPERATIONS & MAINTENANCE
BUDGET TO ACTUAL EXPENSES
SCHEDULE F
FOR THE PERIOD 07/01/2025 TO 12/31/2025
FY 26 FY 25
FY26 Approved
Budget
BUDGET %
07/01/2025 -
12/31/2025 HEA Actual CEA Actual AEA Actual Total Actual
(Over) Under
Budget to Date
FY25 Approved
Budget FY25 Actual
ALASKA ENERGY AUTHORITY
BRADLEY LAKE HYDROELECTRIC PROJECT
Misc Admin
Battle Creek Operating
Administrative Costs 1,000 500 - - 629 629 (129) 1,000 610 Battle Creek Operating Total 1,000 500 - - 629 629 (129) 1,000 610
Professional Consultants
Battle Creek Operating
Labor & Benefits - - - - 4,998 4,998 (4,998) - 10,435
Travel - - - - - - - - 86
Battle Creek Operating Total - - - - 4,998 4,998 (4,998) - 10,521
FERC 920 & 930 - Administrative Expense Total 64,000 32,000 - - 35,907 35,907 (3,907) 64,000 93,341
FERC 924 & 925 - Insurance Premiums
Insurance Premiums
Battle Creek Operating
Administrative Costs - - 1,456 - 28,307 29,763 (29,763) - 48,500 Battle Creek Operating Total - - 1,456 - 28,307 29,763 (29,763) - 48,500
FERC 924 & 925 - Insurance Premiums Total - - 1,456 - 28,307 29,763 (29,763) - 48,500
FERC 923 - Outside Services Employed
Outside Services Employed
Battle Creek Operating
Consulting-Administrative - - - - 776 776 (776) - 1,845 Battle Creek Operating Total - - - - 776 776 (776) - 1,845
FERC 923 - Outside Services Employed Total - - - - 776 776 (776) - 1,845
FERC 928 - Regulatory Commission Expenses
FERC Admin Fees
Battle Creek Operating
Administrative Costs - - - - - - - - 8,893 Battle Creek Operating Total - - - - - - - - 8,893
FERC Related Prof Services
Battle Creek Operating
Administrative Costs - - - - 284 284 (284) - 3,171 Battle Creek Operating Total - - - - 284 284 (284) - 3,171
FERC 928 - Regulatory Commission Expenses Total - - - - 284 284 (284) - 12,064
O&M Allocation to Battle Creek 321,307 160,654 - - - - 160,654 320,638 -
Total Battle Creek Budget 733,784 366,892 74,780 1,160 229,508 305,448 61,444 600,938 521,650
- - - - - - - - -
Page 10 of 12
FY 26 FY 25
FY26 Approved
Budget
BUDGET %
07/01/2025 -
12/31/2025 HEA Actual CEA Actual AEA Actual Total Actual
(Over) Under
Budget to Date
FY25 Approved
Budget FY25 Actual
Summary by expense type
Staff Professional Services (Direct)10,000 5,000 - - 2,079 2,079 2,921 40,000 7,086
Labor & Benefits 50,000 25,000 - - - - 25,000 50,000 47,722
Travel - - - - - - - - 63
Contractual 150,000 75,000 4,269 - - 4,269 70,731 150,000 58,795
Permitting 36,878 18,439 - - 3,032 3,032 15,408 36,878 72,223
Supplies & Materials 20,000 10,000 - - - - 10,000 20,000 52
Administrative Costs 7,000 3,500 - - 754 754 2,746 47,000 5,059
Total SSQ Line Budget 273,878 136,939 4,269 - 5,865 10,134 126,806 343,878 190,998
FERC 556 - System Control & Load Dispatching
Permits
SSQ Line Operating
Permitting 36,878 18,439 - - 3,032 3,032 15,408 36,878 72,223
SSQ Line Operating Total 36,878 18,439 - - 3,032 3,032 15,408 36,878 72,223
FERC 556 - System Control & Load Dispatching Total 36,878 18,439 - - 3,032 3,032 15,408 36,878 72,223
FERC 570 - Maintenance of Station Equipment
Maintenance of Station Equip
SSQ Line Operating
SSQ Line Operating Total - - - - - - - - -
FERC 570 - Maintenance of Station Equipment Total - - - - - - - - -
FERC 571 - Maintenance of Overhead Lines
Maint of OH Lines
SSQ Line Operating
Labor & Benefits 50,000 25,000 - - - - 25,000 50,000 47,722
Contractual 150,000 75,000 4,269 - - 4,269 70,731 150,000 58,795
Supplies & Materials 20,000 10,000 - - - - 10,000 20,000 -
SSQ Line Operating Total 220,000 110,000 4,269 - - 4,269 105,731 220,000 106,517
FERC 571 - Maintenance of Overhead Lines Total 220,000 110,000 4,269 - - 4,269 105,731 220,000 106,517
FERC 920 & 930 - Administrative Expense
AEA Bradley Fixed Admin Fees
SSQ Line Operating
Staff Professional Services (Direct)10,000 5,000 - - 2,079 2,079 2,921 40,000 7,086
Travel - - - - - - - - 63
Supplies & Materials - - - - - - - - 52
Administrative Costs - - - - 754 754 (754) 20,000 3,059
SSQ Line Operating Total 10,000 5,000 - - 2,833 2,833 2,167 60,000 10,259
Trust & Account Fees
SSQ Line Operating
Administrative Costs 2,000 1,000 - - - - 1,000 2,000 2,000
SSQ Line Operating Total 2,000 1,000 - - - - 1,000 2,000 2,000
FERC 920 & 930 - Administrative Expense Total 12,000 6,000 - - 2,833 2,833 3,167 62,000 12,259
FERC 928 - Regulatory Commission Expenses
FERC Related Prof Services
BRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUES
Administrative Costs 5,000 2,500 - - - - 2,500 25,000 -
BRADLEY CONTRACTUAL ENGINEER-FERC LICENSE ISSUES Total 5,000 2,500 - - - - 2,500 25,000 -
FERC 928 - Regulatory Commission Expenses Total 5,000 2,500 - - - - 2,500 25,000 -
Total SSQ Line Budget 273,878 136,939 4,269 - 5,865 10,134 126,806 343,878 190,998
- - - - - - - - -
ALASKA ENERGY AUTHORITY
SSQ LINE OPERATIONS & MAINTENANCE
SCHEDULE I
BUDGET TO ACTUAL EXPENSES
FOR THE PERIOD 07/01/2025 TO 12/31/2025
BRADLEY LAKE HYDROELECTRIC PROJECT
Page 11 of 12
Source
Construction
Funds at
11/30/22
Investment
Expenses
Calculated
Capital Reserve at
11/30/22
Released from
Capital Reserve
Earned Interest
Income
Total Available
Funding
Required Project Work Bond Series 11 Funding 166,013,134 (157,250) (12,454,346) 1,590,422 20,597,857 175,589,817
BESS Required Project Work Bond Series 11 Funded
Capital Projects Total Funding Project Budget Committed Encumbered
Total Actual
Costs
(Over) / Under
Project Budget
(Over) / Under
Total Funding
BRADLEY HEA BESS Preliminary Study 75,000 - 22,473 958 51,569
Oscillation Dampening Service - CEA 16,072,398 - - 1,299,040 14,773,358
Oscillation Dampening Service - MEA 3,870,839 - - 312,857 3,557,982
Oscillation Dampening Service - AEEC 3,365,947 - - 253,347 3,112,600
Total BESS Capital Projects 23,690,538 23,384,183 - 22,473 1,866,203 21,495,508 21,801,863
Transmission Required Project Work Bond Series 11
Funded Capital Projects Total Funding Project Budget Committed Encumbered
Total Actual
Costs
(Over) / Under
Project Budget
(Over) / Under
Total Funding
SSQ Line Sterling-Qtz Ck 230kV Construction 88,085,000 - 26,799 14,271,027 73,787,174
Soldotna-Sterling 230kV Construction 36,135,000 - - 998,015 35,136,985
Bradley Lake Expansion Project 6,000,000 - 1,402,612 236,512 4,360,875
BRADLEY Required Project Work Support - - - 173,411 (173,411)
Bradley RPW - Bond Series 11 - - - 58,032 (58,032)
Total Transmission Capital Projects 85,711,000 130,220,000 - 1,429,412 15,736,997 113,053,591 68,544,591
GRIP 3 Round 1 Required Project Work Bond Series 11
Funded Projects - HVDC Line Total Funding Project Budget Committed Encumbered
Total Actual
Costs
(Over) / Under
Project Budget
(Over) / Under
Total Funding
Allocate from BESS AEA Resolution 24-12 30,000,000 - - - 30,000,000
Allocate from Transmission AEA Resolution 24-02 20,000,000 - - - 20,000,000
Total Grip 3 Round 1 Capital Projects 50,000,000 50,000,000 - - - 50,000,000 50,000,000
Unassigned Earned Interest Income 16,188,279 - - - - - 16,188,279
Total Required Project Work 175,589,817 203,604,183 - 1,451,885 17,603,200 184,549,099 156,534,733
50,000,000 50,000,000
68,544,591 85,711,000
23,690,538 21,801,863
12/31/2025
APPENDIX ACAPITAL PROJECTS FUNDED BY SERIES 11 BOND PROCEEDS
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA ENERGY AUTHORITY
Page 12 of 12
Bradley Operation and Dispatch Committee Report
March 20th, 2026
Meeting Dates:
January 23rd, 2026, February 20th, 2026, and March 13th, 2026
Notable Discussions and Items:
□ O&D forwarded budget for inclusion in the full budget
Water Tracking & Lake Level:
□ As of March 1st, 2026, Bradley Lake contained approximately 78,533 MWh of energy.
Committee Assignments:
□ CEA continues work to address SCADA challenges to allow HEA wheeling capacity as
defined in the existing Bradley agreement.
□ BPMC approved - CEA & HEA investigating appropriate relay settings - $15k spend limit.
• HEA and CEA are working on the development of work scope for best practice analysis.
Next Meeting:
April 17th, 2025 @ 10am