HomeMy WebLinkAbout2025-07-18 RTO Meeting AgendaRAILBELT TRANSMISSION ORGANIZATION (RTO) GOVERNANCE COMMITTEE AGENDA July 18, 2025 10:00 AM Alaska Energy Authority Conference Room To participate dial 1-888-585-9008 and use code 212-753-619# 1. CALL TO ORDER
2. ROLL CALL (for Committee members)
3. PUBLIC ROLL CALL (for all others present)
4. AGENDA APPROVAL
5. PUBLIC COMMENTS
6. APPROVAL OF THE MEETING MINUTES – June 20, 2025 and June 30, 2025
7. OLD BUSINESS - None
8. NEW BUSINESS
A. Open Access Transmission Tariff, RCA Matter # TA1-8001
B. Annual Meeting and Election of Officers
9. EXECUTIVE SESSION – (Bylaws Section 5.12.3) To discuss matters, the immediate knowledge of
which could have an adverse effect on the finances or legal position of the RTO, the Committee
or Authority, or that are confidential under state, federal, or local law.
10. MEMBERS COMMENTS
11. NEXT MEETING DATE – TBD
12. ADJOURNMENT
___________________________________________________________________________
RTO Minutes 6/20/25 Page 1 of 8
RAILBELT TRANSMISSION ORGANIZATION (RTO)
MEETING MINUTES
June 20, 2025
Alaska Energy Authority
Conference Room
1. CALL TO ORDER
Chair Izzo, MEA, called the Railbelt Transmission Organization Governance Committee meeting
to order at 12:01 p.m. A quorum was established.
2. ROLL CALL (for Committee members)
Tony Izzo (Matanuska Electric Association [MEA]); Travis Million (Golden Valley Electric
Association [GVEA]); Brad Janorschke (Homer Electric Association [HEA]); Brian Hickey (City of
Seward); Arthur Miller (Chugach Electric Association [CEA]); Curtis Thayer (Alaska Energy
Authority [AEA]); and Ed Jenkin (Railbelt Reliability Counsel [RRC]).
3. PUBLIC ROLL CALL (for all others present)
Karen Bell, Jennifer Bertolini, Mark Billingsley, Bill Price (AEA); Matt Clarkson, Nick Szymoniek
(CEA); Kody George (City of Seward); Daniel Heckman (GVEA); Larry Jorgensen, Sarah Lambe,
Jessica Spuhler (HEA); Andrew Jensen (Governor’s Office); Julie Estey, Matt Reisterer, Tony Zellers
(MEA); Carl Monroe (Munro Advisors, LLC); Tina Grovier (Stoel Rives, RTO); and Joel Groves
(RRC).
4. AGENDA APPROVAL
MOTION: A motion was made by Vice Chair Million to approve the agenda. Motion
seconded by Mr. Janorschke.
A roll call was taken, and the motion to approve the agenda passed unanimously.
5. PUBLIC COMMENTS
There were no public comments.
6. APPROVAL OF THE MEETING MINUTES – June 13, 2025
MOTION: A motion was made by Vice Chair Million to approve the Meeting Minutes of
June 13, 2025. Motion seconded by Mr. Hickey.
Tina Grovier, Stoel Rives, indicated there were two unidentified speakers listed on page five of
the minutes. She and staff will listen to the audio and insert the names of the speakers. There
was no objection to the impending identification of the unidentified speakers on page five.
___________________________________________________________________________
RTO Minutes 6/20/25 Page 2 of 8
A roll call was taken, and the motion to approve the Minutes of June 13, 2025, with the
impending identification of the unidentified speakers on page five, passed unanimously.
7. OLD BUSINESS
A. Working Group Update
Chair Izzo requested Daniel Heckman, GVEA, provide the RTO Working Group update. Mr.
Heckman noted that the Working Group has met a couple of times since the RTO Governance
Committee’s previous meeting. The Working Group focused on finalizing the public
presentations that will be discussed under Agenda Item 8. New Business, and Agenda Item 9.
Executive Session. The Working Group continues its efforts to draft the tariff advice letter that is
the cover letter for the Open Action Transmission Tariff (OATT) filing. Additionally, the Working
Group finalized the draft of the OATT, which is included in member packets. Mr. Heckman
discussed that the Working Group has maintained its focus on the approaching Regulatory
Commission of Alaska (RCA) filing deadline. There were no comments or questions.
B. RTO Certificate Filing and OATT Filing
Chair Izzo requested that Ms. Grovier provide the update on the RTO Certificate Filing and the
OATT Filing. Ms. Grovier indicated that she has no information to add to Mr. Heckman’s report.
However, she does have matters related to the RCA Certificate, the upcoming tariff filing, and
those topics listed under New Business, to discuss in executive session, the immediate
knowledge of which could have an adverse effect on the legal position and financial position of
the RTO and/or the Committee members. There were no comments or questions.
8. NEW BUSINESS
A. Backbone Transmission System (BTS) Annual Transmission Revenue
Requirement (ATRR) Presentation
Chair Izzo requested Sarah Lambe, HEA, provide the presentation. Ms. Lambe discussed that the
presentation was a group effort developed by the Railbelt Chief Financial Officers (CFO) to
develop the backbone transmission system (BTS) Annual Transmission Revenue Requirement
(ATRR). The objective is to manage regulatory burden by adopting a consensus driven, Federal
Energy Regulatory Commission (FERC)-approved methodology for formulaic rate making that
could be applied uniformly across all Transmission Owners (TO). Ms. Lambe explained that the
BTS ATRR template is based on a Midcontinent Independent System Operator (MISO) template,
chosen in part because MISO has diverse members including cooperatives, municipalities, cities,
and for-profit entities that are all subject to FERC jurisdiction. The template includes workpapers
to provide transparency and reduce the need for discovery. The template is a consistent method
and supports non-discriminatory rate making.
Ms. Lambe discussed that the ATRR is based on the Uniform System of Accounts. It uses audited
financial statements for year ending December 31, for most utilities, and June 30 for both AEA
___________________________________________________________________________
RTO Minutes 6/20/25 Page 3 of 8
and Seward. The ATRR will be updated annually. The template’s processes include calculating
the asset basis of the BTS. This is informed by some of the decisions by the Governance
Committee. Each utility’s annual revenue requirement related to transmission will be calculated
uniformly. Additionally, allocators will be applied to the utility’s annual revenue requirement for
transmission. Once summed, these will produce a total cost of service from the template for the
BTS assets.
Ms. Lambe continued the presentation noting the process of identifying and excluding facilities
that are not considered part of the BTS, such as the generator interconnections and the
Generator Step Up Transformers (GSU’s). The exclusion value is based on the detailed utility
records in those cases. The non-backbone transmission assets include those assets excluded
from the RTO Governance Committee approved BTS line segments. The value of those excluded
assets is calculated using a weighted average cost per mile informed by the individual line’s
average capacity and length.
Ms. Lambe discussed that the template uses allocators to determine the portions of the utility’s
costs that should be attributed to the transmission function. The Transmission Plant (TP)
allocator is the utility’s total transmission plant, less the assets excluded from the RTO ATRR, and
then divided by the total transmission plant. This gives the percentage of the transmission plant
that is eligible to be included in the RTO rates. The example shown in the presentation (in round
numbers throughout) illustrates the TP allocator at 74%.
Ms. Lambe explained that the Gross Plant (GP) allocator in the example takes the total
transmission plant multiplied by the TP allocator and adds the general and intangible plant
multiplied by the wage and salaries (W/S) allocator, which equals a total gross plant figure. The
example shown in the presentation illustrates the GP allocator at 11.71%. Ms. Lambe noted that
the Net Plant (NP) allocator essentially follows the same exercise for determining gross plant
and applies it to the accumulated depreciation accounts. The example shown in the presentation
illustrates the NP allocator at 11.4%.
Ms. Lambe discussed that the wage and salaries (W/S) allocator is used for general and
intangible plant and for the administrative and general expenses. The allocation to transmission
function is based on the W/S allocator. The example shown in the presentation illustrates the
W/S allocator at 4.9%. Ms. Lambe reviewed that the Transmission Expense (TE) allocator is
applied to transmission expenses so that the portions of the expenses related to excluded assets
are not included. The example shown in the presentation illustrates the TE allocator at 60.8%.
Ms. Lambe noted that when workpapers in the template result in the exclusion of all non-BTS
expense, those expenses are directly assigned to the transmission function.
Ms. Lambe indicated that the proposed margin calculation in the template is used by
cooperatives that are subject to FERC as well as municipalities and for-profit entities. The desire
was to provide consistency and eliminate discrimination in accordance with HB307. The CFOs
recommended the adoption of a uniform tier for all the participants based on analysis that
should occur prior to filing with the Commission for an effective rate. The revenues associated
___________________________________________________________________________
RTO Minutes 6/20/25 Page 4 of 8
with transmission expense or plant must be reflected as revenue credits against the BTS ATRR.
Ms. Lambe discussed the illustrative gross BTS ATRR calculation using the previously discussed
FERC function allocators. The result in the example is a total revenue requirement to be
collected through the Network Integration Transmission Service (NITS) rate of $5.4 million. Any
credits received by utilities for transmission function reduces the gross revenue requirement.
The example shown in the presentation illustrates a fully allocated ATRR of $5.4 million is
reduced by approximately $76,000 to arrive at the net revenue requirement for the BTS ATRR.
Mr. Miller requested clarification regarding the revenue on grandfathered agreements. He asked
if the revenue would be applied as a credit to the specific utility’s revenue requirement that
would then be collected in rates, and that the credits are focused at the utility level, rather than
the RTO collective system revenue requirement. Ms. Lambe clarified that it is done at the TO
level.
Mr. Hickey requested clarification regarding the wording in the presentation indicating that it
removes transmission assets associated with grandfathered agreements. Ms. Lambe explained
there are two cost treatments accounting for grandfathered agreements. One route is to directly
assign those assets, excluding them and removing them from the plant basis. The second route
could potentially be the application of the revenue credits, reducing the gross ATRR at a net
figure.
Mr. Hickey asked if either of those options are currently being utilized, and the effects of
removing the grandfathered agreements from the cost allocator. Ms. Lambe explained that the
template provides for the options. She understands that most of the utilities that are receiving
revenues are electing to reflect the credit. The utilities are keeping the full amount of the TP in
the ATRR, and they are reducing the revenue requirement by the revenue received from other
sources.
Mr. Thayer asked Ms. Lambe to confirm that AEA will have modifications to the format due to
the nature of how AEA reports. Ms. Lambe agreed.
Mr. Jenkin asked if the GSU transformers, interconnection facilities, and radial facilities are
excluded on Slide 9 because those facilities are not classified as transmission in a network
transmission system, and therefore not in the BTS. Ms. Lambe agreed. There were no other
questions or comments.
B. Open Access Transmission Tariff Presentation
Chair Izzo requested Carl Monroe, Munro Advisors, LLC, review the Open Access Transmission
Tariff Presentation. Mr. Monroe discussed that the previous presentation showed the initial
additions, the deletions, and the modifications of the tariff. Additional work has been completed
by the RTO Working Group on the draft tariff. As the ATRR and cost of service is determined,
changes will have to be made within the tariff. This includes the method to determine the ATRR
from each of the TOs and also the calculation of the cost of service. Additionally, changes to the
___________________________________________________________________________
RTO Minutes 6/20/25 Page 5 of 8
billing and invoicing have to be addressed. AEA has proposed changes to implementing and
integrating the billing and invoicing into the tariff.
Mr. Monroe discussed that HB307 addresses extended interruptions. Billing activities need to
occur because of the legislative requirement to develop billing to reflect a disruption that results
in isolation for more than 24 hours from the rest of the BTS. Mr. Monroe noted that the Working
Group has discussed proposing that the AEA administration fees be shared using the same
allocator for the BTS ATRR. It would be listed separately on each network customer’s bill.
Mr. Hickey asked if the network customer’s bill is the bill that goes from the RTO to each of the
governing members. Mr. Monroe agreed, clarifying that the bill goes to TOs that have load. He
gave the example that AEA has no load and will never receive a network customer bill.
Mr. Monroe reviewed the ways in which the Working Group’s recommendations were modified
regarding the Transmission Service Administrator (TSA), who is only the administrator of the
tariff, the RTO. Mr. Monroe discussed that if the TO needs to complete studies for changes to
generation interconnection or changes to the network customer service, the cost will be paid
directly to the TO and not through any TSA accounting. Additionally, the TO will place change
requests in a queue in the order they are received. Handling of new upgrades will evolve with
the RRC’s IRP and transmission planning tariff work, but for now the default is that new
upgrades will be included in the ATRR of the TO. Mr. Monroe reported on discussions regarding
new facilities that might be built that were significantly different or significantly influential in the
operation and the connections to different parties within the transmission system. It is
understood that changes may be necessary if upgrades occur prior to the implementation of the
RRC’s tariff.
Mr. Monroe discussed that the Working Group continued to work on creditworthiness and the
procedure to follow in the cases of payment defaults. He highlighted that the RTO is meant to
be revenue neutral. Mr. Monroe reviewed that the Service Agreement is the legal agreement
between the Network Customer, the TOs, and the TSA. The Service Agreement must include
language that the TO, the BA, and the Network Customer will follow the tariff provisions. The
Service Agreement must also include that ancillary services are to be obtained, acceptance that
response to congestion relief will occur, when necessary, as well as binding those entities to any
other responsibility included in the tariff.
Mr. Monroe requested members to comment on any other issues where additional information
is needed or should be considered. He noted that members have the most recent draft
language and asked for feedback after their review. There were no comments or questions.
MOTION: A motion was made by Vice Chair Million to enter into Executive Session to
discuss confidential financial matters related to RTO finances and legal strategy. This is
consistent with our Bylaws, which allow the Board to consider confidential matters in
Executive Session. In this case, the RTO believes that these are subjects that would have an
adverse effect upon the finances of the RTO, are being discussed with an attorney, the
___________________________________________________________________________
RTO Minutes 6/20/25 Page 6 of 8
immediate knowledge of which could have an adverse effect on the legal position of the
Committee, or are protected by law due to rules protecting personal privacy and certain
business information. Motion seconded by Mr. Janorschke.
A roll call was taken, and the motion to enter into Executive Session passed unanimously.
9. EXECUTIVE SESSION – 12:38 pm. (Bylaws Section 5.12.3) To discuss matters, the
immediate knowledge of which could have an adverse effect on the finances or
legal position of the RTO, the Committee or Authority, or that are confidential
under state, federal, or local law.
The RTO Governance Committee reconvened its regular meeting at 4:09 p.m. Chair Izzo advised
that the RTO did not take any formal action on matters discussed while in Executive Session,
except as authorized in the Bylaws 5.12.2, to give directions to the attorney regarding the
handling of specific legal matters and pending negotiations.
A brief at-ease was taken.
The RTO Governance Committee reconvened its regular meeting.
MOTION: A motion was made by Mr. Thayer to adopt the ATRR template for calculating
the Annual Transmission Revenue Requirement for the backbone transmission system that
was presented earlier today, including its allocated methodologies, its use of unified tier,
and its accommodations for the treatment of the costs of grandfathered agreements, with
modifications that may be necessary for AEA, to include backbone transmission system
costs established by contract. Motion seconded by Mr. Miller.
Mr. Jenkin noted that costs of the grandfathered agreements and how they are being allocated
most likely does not eliminate wheeling. He looks forward to further discussions on that topic.
Mr. Million echoed Mr. Jenkin’s comments. He recognized that the intent of the RTO is to align
with the statute, as written. Ways to eliminate the wheeling as much as possible will be
reviewed.
A roll call was taken, and the motion to adopt the ATRR template passed unanimously.
Mr. Miller commented on the earlier discussion regarding the development of the backbone
transmission system transmission revenue requirement and the return component under the
FERC methodology. He discussed that in recognition of the cooperative utility structure on the
Railbelt, a consistent and equitable tier should be used for all participants in the Railbelt.
MOTION: A motion was made by Mr. Miller that the RTO use, for illustrative purposes in
the RTO’s 2025 transmission submission to the Regulatory Commission of Alaska, a
unified tier of 1.35, with the understanding that when filing its initial cost of service, a full
cost of capital study will be completed that will identify the proposed final transmission
___________________________________________________________________________
RTO Minutes 6/20/25 Page 7 of 8
tier and the determination of the revenue requirement. Motion seconded by Vice Chair
Million.
A roll call was taken, and the motion passed unanimously.
Vice Chair Million commented that there was language in the statute regarding options on how
to allocate costs, including coincident peak, load ratio share, or a combination thereof.
MOTION: A motion was made by Vice Chair Million that the RTO allocate the cost of the
backbone transmission system through certified load serving entities on a coincidental
peak basis using a 12 CP method. Motion seconded by Mr. Miller.
Mr. Miller expressed his support for this allocation of transmission costs, recognizing that the
transmission system is used throughout the year, not only to meet peak requirements on a
monthly basis, but it is also used for transmitting energy as well. He believes that the 12 CP
recognizes the benefits to meet the system peak load during the winter months and also meet
the cost causation characteristics and use of the transmission system through other time periods
during the year on an equitable basis.
A roll call was taken, and the motion passed unanimously.
Mr. Hickey commented that the Working Group has expressed an interest in another cost
allocator related to regional and local benefits. He believes the Working Group has a strong
desire to study the components and determine the reasonable regional and local benefit
allocator.
MOTION: A motion was made by Mr. Hickey that the regional and local benefit allocator
to the backbone transmission system annual revenue requirement is studied, and that a
placeholder is included in the tariff with the ratio amount to be determined between
regional and local allocation, as well as two or three examples. Motion seconded by Mr.
Miller.
Vice Chair Million commented that entering this process, the regional and local benefit allocator
was never on his radar. He discussed that as the reports and presentations were conveyed by
the experienced consultants, he understands there could be benefits for the RTO to delineate by
regional and local benefits. Vice Chair Million agreed that there is not sufficient time to expound
on those details before the deadline. He supports the path of continued study and examples for
the filing process to determine the best allocation method for the Railbelt.
Mr. Janorschke asked if this issue has been discussed within the Working Group. Mr. Hickey
affirmed it has. Mr. Janorschke asked for the Working Group’s recommendation. Mr. Heckman
explained that the Working Group has discussed the regional and local benefit allocator. The
Working Group believes that additional evaluation is needed, and that it is worth including as
part of the overall filing. The Working Group has not recommended a percentage at this time
___________________________________________________________________________
RTO Minutes 6/20/25 Page 8 of 8
but could provide a range of examples to show the various benefits at different percentages.
There were no other comments or questions.
A roll call was taken, and the motion passed unanimously.
10. MEMBER’S COMMENTS
Mr. Hickey expressed appreciation to the Working Group and others for their diligent efforts
over the last few weeks. He thanked members for their leadership.
Mr. Janorschke echoed Mr. Hickey’s comments.
Mr. Miller echoed the recognition of the diligent efforts of the Working Group. He is happy with
the meaningful progress and the good collaboration among the utilities. Mr. Miller commented
that there is still a long road ahead after the filing is completed.
Mr. Thayer expressed appreciation for the good meeting, for resolving many issues today, and
for the progress since December.
Mr. Jenkin thanked the Working Group and thanked the CFOs for their efforts in refining the
cost allocation methodologies.
Vice Chair Million echoed the comments of appreciation to the Working Group for their
extensive time and effort, to the CFOs for their focus, and to the Technical Working Group for
their frontend efforts. He recognized the collaboration of all the groups, including the RTO
Governance Committee members.
Chair Izzo echoed the positive comments of others, especially to the Working Group, the
Technical Group, the Legal Group, and all of the parties who have spent countless hours during
this process.
11. NEXT MEETING DATE
Chair Izzo indicated that the next meeting date is June 30, 2025, at 10:30 a.m., via Teams.
12. ADJOURNMENT
There being no further business for the committee, the meeting adjourned at 4:31 p.m.
____________________________________
Tony Izzo, Chair
_____________________________________
Curtis W. Thayer, Secretary
___________________________________________________________________________
RTO Minutes 6/30/25 Page 1 of 4
RAILBELT TRANSMISSION ORGANIZATION (RTO) GOVERNANCE COMMITTEE MEETING MINUTES June 30, 2025 Teams Meeting 1. CALL TO ORDER Chair Izzo, MEA, called the Railbelt Transmission Organization Governance Committee meeting to order at 10:30 a.m. A quorum was established. 2. ROLL CALL (for Committee members) Tony Izzo (Matanuska Electric Association [MEA]); Travis Million (Golden Valley Electric Association [GVEA]); Sarah Lambe (Homer Electric Association [HEA]); Brian Hickey (City of Seward); Arthur Miller (Chugach Electric Association [CEA]); Curtis Thayer (Alaska Energy Authority [AEA]); and Ed Jenkin (Railbelt Reliability Counsel [RRC]). 3. PUBLIC ROLL CALL (for all others present) Karen Bell, Jennifer Bertolini, Mark Billingsley, Bill Price (AEA); Matt Clarkson (CEA); Daniel Heckman (GVEA); Larry Jorgensen, Jessica Spuhler (HEA); Andrew Jensen (Governor’s Office); David Pease, Tony Zellers (MEA); Carl Monroe (Munro Advisors, LLC); Electra Kean (Public); Claire Latta-Knudsen (RCA); and Tina Grovier (Stoel Rives, RTO).
4. AGENDA APPROVAL MOTION: A motion was made by Mr. Thayer to approve the agenda. Motion seconded by Vice Chair Million. Ms. Lambe noted that the documents were not hyperlinked to the agenda, and were not attached to the calendar invite. Jennifer Bertolini, AEA, explained there are no public documents attached to the agenda. Ms. Lambe indicated that the agenda is not attached to her calendar invite, and requested an emailed copy. Mr. Hickey and Mr. Miller stated that they do not have the agenda either. Ms. Bertolini responded that she will distribute the agenda to all. Chair Izzo discussed that the current agenda does not include an item to approve the filing. He believes the approval of the filing is required by the Bylaws. Chair Izzo proposed inserting Item 9. New Business to approve the filing. Chair Izzo requested Tina Grovier, Stoel Rives, to comment on the proposed amendment. Ms. Grovier agreed that amendment makes sense.
___________________________________________________________________________
RTO Minutes 6/30/25 Page 2 of 4
Chair Izzo requested that members respond when they have received and reviewed the agenda. Mr. Thayer responded that he has a copy of the agenda and agrees with the friendly amendment. Vice Chair Million noted that if Chair Izzo’s recommendation was a motion to amend the agenda, Vice Chair Million will second the amendment. Chair Izzo indicated that it would be considered a friendly amendment. There was no objection. Mr. Hickey said he reviewed the agenda, and it looks fine. Mr. Miller agreed the agenda looks fine. Ms. Lambe agreed the agenda looks fine. Mr. Jenkin commented that he has no issues with the motion. A roll call was taken, and the motion to approve the agenda, as amended by inserting Item 9. New Business, Approval of Filing, passed unanimously. 5. PUBLIC COMMENTS
There were no public comments.
6. APPROVAL OF THE MEETING MINUTES – June 20, 2025
The minutes for the June 20, 2025, meeting were not available for review. 7. OLD BUSINESS
A. Working Group Update
Chair Izzo requested Daniel Heckman, GVEA, provide the RTO Working Group update. Mr. Heckman noted that the Working Group continues to focus its efforts on the Open Action Transmission Tariff (OATT) filing and the tariff advice letter that is the cover letter for the OATT filing with the Regulatory Commission of Alaska (RCA) that is due by the close of business tomorrow, July 1, 2025. The Working Group has conducted group reviews of the documents, as well as individual entity coordination reviews. The product for consideration today is in its substantive form and will be filed with the RCA on time. Mr. Heckman discussed that significant work has occurred since the prior Governance Committee meeting, including work over the weekend. He expressed continued appreciation for the diligent work and the resulting product. Mr. Heckman reiterated his thanks to the Working Group, the consultants, counsel, and the Governance Committee for their time, resources, and team effort during this process. He looks forward to submitting the filing to the RCA tomorrow. There were no comments or questions.
___________________________________________________________________________
RTO Minutes 6/30/25 Page 3 of 4
B. RTO Certificate Filing and OATT Filing
Chair Izzo requested that Ms. Grovier provide the update on the RTO Certificate Filing and the OATT Filing. Ms. Grovier indicated that she has no information to add to Mr. Heckman’s report. She echoed the comments of appreciation for the hard work and indicated that she does have matters related to the upcoming tariff filing and related documents to discuss in executive session, the immediate knowledge of which could have an adverse effect on the legal position and financial position of the RTO and/or the Committee members. There were no comments or questions. MOTION: A motion was made by Mr. Hickey to enter into Executive Session to discuss matters, the immediate knowledge of which could have an adverse effect on the finances or legal position of the RTO, the Committee or Authority, or that are confidential under state, federal, or local law. Motion seconded by Mr. Miller. A roll call was taken, and the motion to enter into Executive Session passed unanimously. 8. EXECUTIVE SESSION – 10:46 am. (Bylaws Section 5.12.3) To discuss matters, the immediate knowledge of which could have an adverse effect on the finances or legal position of the RTO, the Committee or Authority, or that are confidential under state, federal, or local law. The RTO Governance Committee reconvened its regular meeting at 12:41 p.m. Chair Izzo advised that the RTO did not take action on any matters discussed while in Executive Session except as authorized in the Bylaws 5.12.2, to give directions to the attorney regarding the handling of specific legal matters and pending negotiations. There were no comments or questions. 9. NEW BUSINESS - APPROVAL OF THE FILING MOTION: A motion was made by Mr. Miller that the RTO do the following: 1.) approve the filing of the Nondiscriminatory Open Access Transmission Tariff and related documents with the Regulatory Commission of Alaska on July 1, 2025, consistent with the direction given to its attorney in executive session on this legal matter, and 2.) authorize RTO counsel to make any minor changes, modifications, and additions that she deems necessary, desirable, or appropriate to carry out the direction provided by the RTO Governance Committee or to otherwise comply with RCA regulations and practice. Motion seconded by Mr. Thayer. A roll call was taken, and the motion passed with Mr. Hickey absent. 10. MEMBER’S COMMENTS Mr. Thayer expressed appreciation to everyone during this process, particularly the Working
___________________________________________________________________________
RTO Minutes 6/30/25 Page 4 of 4
Group, the attorneys, Ms. Bertolini, Karen Bell, AEA, and the AEA team. He believes the work product has exceeded expectations during the 11 months of efforts since the Legislature and the Governor gave the assignment. Mr. Thayer is pleased that the filing will be completed tomorrow. Additional information within the next six months will determine next steps in the process. He reiterated his thanks to all involved. Chair Izzo noted that Claire Latta-Knudsen, RCA, posted a comment on the Teams meeting saying thank you. Vice Chair Million commented on the great work completed by all. He noted that the efforts to reach this goal were considerable, including working this weekend. He complimented the team and the Governance Committee for working through the issues to reach tomorrow’s filing date. Ms. Lambe reiterated the comments of appreciation for the efforts. She looks forward to beginning the next chapter of these endeavors. Mr. Miller echoed the recognition and appreciation of the previous comments, especially to the Working Group, Ms. Bertolini, Ms. Grovier, Carl Monroe, Munro Advisors, LLC, and to the Governance Committee members. He looks forward to tomorrow’s filing, and to the next segment of the filing process. Chair Izzo echoed the positive comments of others, especially to the Working Group and Mr. Heckman. He expressed congratulations to all involved in this process. There were no other comments or questions. 11. NEXT MEETING DATE Chair Izzo indicated that the next meeting date is tentatively scheduled for July 18, 2025, at 10:00 a.m. in the AEA conference room. There were no comments or questions. 12. ADJOURNMENT There being no further business for the committee, the meeting adjourned at 12:48 p.m. _____________________________________ Tony Izzo, Chair ______________________________________ Curtis W. Thayer, Secretary