HomeMy WebLinkAboutGVEA - EVA Creek Wind Turbine Purchase - 2013Eva Creek Wind Project Mike Wright VP Transmission & Distribution April 30, 2013 Project Timeline •2002-2009 Installed Meteorological Towers •2006-2009 Conducted Feasibility Assessment •2009 Received IRS Approval for CREB’s •2010 GVEA Board Gives Green Light •2011 Signed Contract with REpower and BOP Contractor, Michels Wind Energy •September 2011 Began Construction •October 2012 Completed Construction •December 2012 Commissioning Complete Costs – Eva Creek •Capital Costs –Capital Costs: $94 million (net of grants) –State Renewable Energy Fund: $3.6 million –State Grant: $10 million –CREB Financing at 1.05% •Operating Costs: $1,200,000/year •Cost of energy: 8.7 cents/kWh •Exclusive of: •Regulation costs •Potential Green Tag sales to the voluntary market REpower MM92 CCV WEC •Installed 12 REpower CCV MM92 Turbines 2.05MW rated output @ 12.5 m/s (28 mph) 80 m (262 ft) Hub Height 92.5 m (303 ft) Rotor Diameter 45.2 m (148 ft) Blade Length 3.0 m/s Cut-in Speed (6.7 mph) 24.0 m/s Cut-out Speed (53.7 mph) REpower MM92 Tower Base Nacelle & Hub Arrival in Anchorage Tower Arrival in Anchorage REpower MM92 Blade Delivery Balance of Plant Construction •Selected Michels Wind Energy for BOP –Brice, Inc. (Civil Construction) –PDC Engineers (Civil Design) –Golder Associates (Geo-Technical Design) –Stantec Engineering (Electrical Design) –Redi-Electric (Electrical Construction) –GHEMM Company (Buildings) –Fairbanks Sand & Gravel (Concrete) Components Delivered to Site Tower Erection Completed Blade Assembly Final Top Out Blade Repairs Total production for December was 8,645,650 kWh from 10 commissioned turbines. 54.43% CF 13.06 MW Regulation Issues - GVEA’s System •Cannot schedule non-firm energy around wind (must be day-ahead scheduling) •Wind will reduce the availability of non - firm energy •Once a firm resource (coal, combined cycle) is below a minimum output level, it must remain off-line for period of time •Start time and start-up costs Ability to Regulate •Historical GVEA generation commitment Spilled Wind (MWh) •2 minute data superimposed on hourly run •Doesn’t include spill due to ramp rate Regulation Costs Annual Savings and Regulating Costs Load following Eva Creek •NPEP –Suggested fixed low load limit 23 MW (for GT) –Lower loads possible based on the operator, ambient temperature, NOx bias, and turbine efficiency (wear) –Discuss duration of time steam turbine remains off after being shut down •Healy 1 – install AGC controls to allow dispatch to operate the plant in other than base-load condition North Pole LM6000 Low load near trip condition -Pink- Gas Turbine MW load -Green- Steam Turbine MW load -Blue- HP Boiler feed water flow -Light blue- HP steam pressure at the turbine control valve -Red- HP steam temperature at the control valve