HomeMy WebLinkAboutAEA_REF_Rd1_StatusReport_Feb2010
Renewable Energy Fund Round 1 projects
Alaska Energy Authority
LB&A Report
2/25/2010
LB&A Grant Report
Table of Contents
ii
LB&A Grant Report
Table of Contents
iii
Alaska Energy Authority
Renewable Energy Fund Round 1 projects
LB&A Report
February 25, 2010
Table of Contents
Introduction .................................................................................................................................................. 1
Project Development and Grant Progress .................................................................................................... 1
Grants Progress ......................................................................................................................................... 1
Progress on Projects ................................................................................................................................. 2
Cost Savings .............................................................................................................................................. 3
Appendix: Renewable Energy Fund Round 1, Project Status....................................................................... 6
Alaska Power & Telephone Co ...................................................................................................................... 7
North Prince of Wales Island Intertie Project ........................................................................................... 7
Alaska Environmental Power ........................................................................................................................ 8
Delta Area Wind Turbines-Construction ................................................................................................... 8
Alaska Gateway School District..................................................................................................................... 9
Tok Wood Heating Construction ............................................................................................................... 9
Alaska Green Energy, LLC ............................................................................................................................ 10
California Creek Hydroelectric Feasibility ............................................................................................... 10
Alaska Village Electric Coop ........................................................................................................................ 11
Ambler Solar PV Construction................................................................................................................. 11
Alaska Village Electric Coop ........................................................................................................................ 12
Cosmos Hills Hydroelectric Feasibility Study .......................................................................................... 12
Alaska Village Electric Coop ........................................................................................................................ 13
LB&A Grant Report
Table of Contents
iv
Mekoryuk Wind Farm Construction........................................................................................................ 13
Alaska Village Electric Coop ........................................................................................................................ 14
Old Harbor Hydroelectric Final Design.................................................................................................... 14
Alaska Village Electric Coop ........................................................................................................................ 15
Quinhagak Wind Farm Construction....................................................................................................... 15
Alaska Village Electric Coop ........................................................................................................................ 16
Toksook Wind Farm Construction........................................................................................................... 16
Alaska Wind Energy .................................................................................................................................... 17
Nikolaevsk Wind Farm Final Design ........................................................................................................ 17
Alaska Wind Power, LLC .............................................................................................................................. 18
Coal Mine Road Wind Farm Final Design ................................................................................................ 18
Aleutians East Borough ............................................................................................................................... 19
Aleutians East Borough Feasibility Study ................................................................................................ 19
Anchorage, Municipality of ......................................................................................................................... 20
Anchorage Landfill Gas Electricity Construction ..................................................................................... 20
Atka, City of ................................................................................................................................................. 21
Chuniisax Creek Hydroelectric Construction .......................................................................................... 21
Bethel, City of .............................................................................................................................................. 22
Bethel Wind Power Project Times Four .................................................................................................. 22
Burro Creek Holdings, LLC ........................................................................................................................... 23
Burro Creek Hydro Feasibility Study ....................................................................................................... 23
Cheesh'na Tribal Council ............................................................................................................................. 24
Chistochina Central Wood Heating Constr ............................................................................................. 24
Chena Power, LLC ........................................................................................................................................ 25
Biomass-fired Organic Rankine Cycle System ......................................................................................... 25
LB&A Grant Report
Table of Contents
v
Chignik Lagoon Power Utility ...................................................................................................................... 26
Chignik Lagoon Hydroelectric Final Design ............................................................................................. 26
Chignik, City of ............................................................................................................................................ 27
Indian Creek Hydro Feasibility Study ...................................................................................................... 27
Chilkoot Indian Association ......................................................................................................................... 28
Haines Central Wood Heating Construction ........................................................................................... 28
Copper River School District ........................................................................................................................ 29
Kenny Lake Wood Boiler Assessment ..................................................................................................... 29
Copper Valley Electric Association .............................................................................................................. 30
Allison Lake Hydro Feasibility Study ....................................................................................................... 30
Cordova Electric Cooperative ...................................................................................................................... 31
Cordova Heat Recovery Construction ..................................................................................................... 31
Cordova Electric Cooperative ...................................................................................................................... 32
Humpback Creek Hydroelectric Construction ........................................................................................ 32
Delta/Greely School District ........................................................................................................................ 33
Delta Junction Wood Chip Heating ......................................................................................................... 33
Fishhook Renewable Energy, LLC ................................................................................................................ 34
Fishhook Hydroelectric Construction...................................................................................................... 34
Golden Valley Electric Association .............................................................................................................. 35
Eva Creek Wind Farm Feasibility ............................................................................................................. 35
Golden Valley Electric Association .............................................................................................................. 36
McKinley Village Solar Thermal Construction ......................................................................................... 36
Golden Valley Electric Assoc ........................................................................................................................ 37
North Pole Heat Recovery Construction ................................................................................................. 37
Gulkana Village Council .............................................................................................................................. 38
LB&A Grant Report
Table of Contents
vi
Gulkana Central Wood Heating Construction ........................................................................................ 38
Gustavus Electric Company ......................................................................................................................... 39
Falls Creek Hydroelectric Construction ................................................................................................... 39
Gwitchyaa Zhee Utility Company ................................................................................................................ 40
Fort Yukon Central Wood Heating Design .............................................................................................. 40
Haida Power, Inc. ........................................................................................................................................ 41
Reynolds Creek Hydroelectric Construction ........................................................................................... 41
Haines Borough ........................................................................................................................................... 42
Haines Central Wood Heating Feasibility Study ..................................................................................... 42
Homer Electric Association .......................................................................................................................... 43
Falls Creek Low-Impact Hydro Assess PreConstr .................................................................................... 43
Homer Electric Association .......................................................................................................................... 44
Crescent Lk/Crk Low-Impact Hydro Assess Pre-Construction ................................................................ 44
Homer Electric Association .......................................................................................................................... 45
Grant Lk/Crk Low-Impact Hydro Assess Pre-Const ................................................................................. 45
Homer Electric Association .......................................................................................................................... 46
Ptarmigan Lk/Crk Low-Impact Hydro Assess Pre-Const .......................................................................... 46
Hooper Bay, City of ..................................................................................................................................... 47
Hooper Bay Wind Farm Feasibility .......................................................................................................... 47
Independence Power, LLC ........................................................................................................................... 48
Fourth of July Creek Hydroelectric Reconnaissance ............................................................................... 48
Interior Regional Housing Authority ........................................................................................................... 49
Galena Wood Heating Construction ....................................................................................................... 49
Juneau, City & Borough of ........................................................................................................................... 50
Juneau Ground Source Heat Pump Constr ............................................................................................. 50
LB&A Grant Report
Table of Contents
vii
Juneau, City and Borough of ....................................................................................................................... 51
Juneau Airport Ground Source Heat Pump ............................................................................................ 51
Kenai Winds, LLC ......................................................................................................................................... 52
Nikiski Wind Farm Construction ............................................................................................................. 52
Ketchikan Public Utilities ............................................................................................................................. 53
Whitman Lake Hydro Final Design .......................................................................................................... 53
Kodiak Electric Association .......................................................................................................................... 54
Pillar Mountain Wind Project - Construction .......................................................................................... 54
Kotzebue Electric Association ...................................................................................................................... 55
Kotzebue Wind Farm Expansion Construction ....................................................................................... 55
Kwaan Electric Transmission ....................................................................................................................... 56
Kake-Petersburg Intertie Final Design .................................................................................................... 56
Kwig Power Company ................................................................................................................................. 57
Kwigillingok High Penetration Wind-Diesel Smart Grid .......................................................................... 57
Lake and Peninsula Borough ....................................................................................................................... 58
Chignik Lake Area Wind-Hydro Final Design ........................................................................................... 58
Lake and Peninsula Borough ....................................................................................................................... 59
Lake Pen Borough Wind Feasibility Study ............................................................................................... 59
Lake and Peninsula Borough ....................................................................................................................... 60
Lake Peninsula Borough Wood Heating Final Design ............................................................................. 60
McGrath Light & Power Company .............................................................................................................. 61
McGrath Central Wood Heating Proj Dev Ph III ...................................................................................... 61
McGrath Light & Power Company .............................................................................................................. 62
McGrath Heat Recovery Construction .................................................................................................... 62
Metlakatla Indian Community .................................................................................................................... 63
LB&A Grant Report
Table of Contents
viii
Metlakatla-Ketchikan Intertie Design and Permittin .............................................................................. 63
Native Village of Eyak ................................................................................................................................. 64
Cordova Wood Processing Plant-Purchase and setup ............................................................................ 64
Nikolski IRA Council ..................................................................................................................................... 65
Nikolski Wind Integration Construction .................................................................................................. 65
Nome Joint Utility Systems .......................................................................................................................... 66
Nome Banner Peak Wind Farm Transmission Constructi ....................................................................... 66
Nome, City of ............................................................................................................................................... 67
Nome/Newton Peak Wind Farm Construction ....................................................................................... 67
Northwest Arctic Borough ........................................................................................................................... 68
Buckland, Deering, Noorvik Wind Farm Construction ............................................................................ 68
Northwest Inupiat Housing Authority ......................................................................................................... 69
Kobuk River Valley Woody Biomass Feasibility ...................................................................................... 69
Nushagak Electric and Telephone Cooperative ........................................................................................... 70
Lake Elva Hydropower Feasibility, Permitting & Final Design ................................................................ 70
Petersburg, City of ....................................................................................................................................... 71
Ruth Lake Hydro Reconnaissance ........................................................................................................... 71
Puvurnaq Power Company .......................................................................................................................... 72
Kongiganak High Penetration Wind-Diesel Smart Grid .......................................................................... 72
Sitka, City and Borough of ........................................................................................................................... 73
Takatz Lake Hydroelectric Feasibility ...................................................................................................... 73
South Fork Hydro, LLC ................................................................................................................................. 74
South Fork Hydroelectric Construction ................................................................................................... 74
St. George, City of ....................................................................................................................................... 75
St. George Wind Farm Construction ....................................................................................................... 75
LB&A Grant Report
Table of Contents
ix
TDX Power, Inc. ........................................................................................................................................... 76
Manley Hot Springs Geothermal Plant ................................................................................................... 76
Unalakleet Valley Electric Cooperative ....................................................................................................... 77
Unalakleet Wind Farm Construction....................................................................................................... 77
University of Alaska-Anchorage .................................................................................................................. 78
Statewide Hydrokinetic Feasibility Study................................................................................................ 78
University of Alaska-Fairbanks .................................................................................................................... 79
Nenana Hydrokinetic Construction ......................................................................................................... 79
Whittier, City of ........................................................................................................................................... 80
Whittier Creek Hydroelectric Reconnaissance ....................................................................................... 80
Wrangell, City and Borough of .................................................................................................................... 81
Wrangell Hydro Based Electric Boilers Construction .............................................................................. 81
Yakutat Power ............................................................................................................................................. 82
Yakutat Biomass Feasibility ..................................................................................................................... 82
Yukon River Inter-Tribal .............................................................................................................................. 83
Ruby Hydrokinetic ................................................................................................................................... 83
Kenai Hydro, LLC ......................................................................................................................................... 84
Grant Lake/Falls Creek ............................................................................................................................ 84
Cross Reference Table by Region ................................................................................................................ 85
P a g e | 1
Introduction
Project Development and Grant Progress
Grants Progress
To date AEA has issued grants for 60 Round 1 projects. Grants have not been issued for 13 projects.
Applicants have decided not to proceed on two projects: Nikolaevsk Wind Farm final design and Galena
Wood Heating construction. AEA is reallocating funds for these projects to the Takatz Lake Hydro
feasibility project as directed by the Legislative Budget and Audit Committee.
Maximum funding amounts of $4 million and $2 million were established in high and low energy cost
communities respectively in order to achieve a wider geographic distribution of projects. Although the
funding caps did enhance geographic spreading, they also resulted in delaying construction of five
projects totaling $15.7 million. They are as follows:
1. Kotzebue Electric Association Wind Farm Expansion ($4 million). KEA and AEA staff are working
to modify scope of work to address the decreased available funding. KEA has submitted an
application in Round 3 that is recommended for funding.
2. Nome Joint Utilities Newton Peak Wind Farm Construction ($4 million). NJUS and AEA staff
working to modify the scope to address the decreased funding and the need to integrate the
new Banner Ridge wind farm.
3. Haida Corporation and Alaska Power and Telephone Reynolds Creek Hydroelectric Construction
($2 million). Haida Corp and AP&T are requesting a Round 3 grant and financing from the Power
Project Loan Fund for the balance of the project.
4. Delta Greely School District Wood Chip Boiler Heating System ($2 million). Delta Greeley SD has
requested funding from Round 3 for the balance of funding for the project. A grant is in place
for Round 1 funds.
5. Nushagak Cooperative’s Lake Elva Hydroelectric ($4,006,500) also has construction funds but
insufficient financing. A grant is in place, with $300,000 available for preconstruction activities
with the remainder reserved for construction. In Round 3 AEA has recommended reallocation
of $700,000 of these funds for preconstruction activities for Grant Lake Hydro, a related project.
P a g e | 2
Progress on Projects
This section provides a summary of the progress of the projects.
Figure 1 summarizes expected progress on completing Round 1 projects broken down by the of project
development phase (Reconnaissance/Feasibility, Final Design/Permitting, and Construction. By the end
of calendar year 2010, AEA expects that 46 projects will be completed. Most of the remaining projects
are expected to be completed by the end of calendar year 2011.
Figure 2 provides a cumulative projected drawdown of grant funds by quarter to the end of calendar
year 2013. By the end of 2010 AEA anticipates disbursing approximately $50 million to grantees for
Round 1 projects. AEA anticipates disbursing approximately $73 million by the end of 2011. 81% or the
total disbursements will be for construction projects.
5
26
36 37 37
1
9
10 10 10
2
11
21 22 23
0
10
20
30
40
50
60
70
80
2009 2010 2011 2012 2015Cumulative# Projects CompletedCalendar Year
Fig. 1. RE Fund Round 1
Scheduled Project Completion
Reconn/Feas
Final Design
Construction
P a g e | 3
Cost Savings
Cost savings can only be assessed after projects are in operation and have enough performance data to
provide a realistic picture of fuel savings and operation and maintenance costs. Fuel price will also have
a very great impact on savings.
Currently two Round 1 projects have been completed and in operation long enough to assess savings.
AEA provided the following information on cost savings for Kodiak Electric’s Pillar Mountain wind project
and Gustavus Electric Company’s Fall Creek Hydro Project in September 25, 2009. No new factors have
arisen that change the observed savings.
1. Pillar Mountain Wind Farm. KEA estimates savings of 5.8 cents per kWh of power generated by
wind, assuming the current displaced fuel price of $2.10 per gallon. They estimate savings of
12.7 cents per kWh of power generated by wind if the fuel price rises to $3.00 per gallon. The
estimated annual wind production is 12.2 million kWh, giving a community savings of
approximately $708,000 per year at $2.10 per gallon fuel and $1,549,000 per year at $3.00 per
gallon fuel. Savings are translated to a lower cost of power adjustment (fuel adjustment) on the
consumers’ bills.
2. Falls Creek Hydroelectric. GEC estimates savings of 29.3 cents per kWh of hydropower assuming
a displaced fuel price of $3.00 per gallon. The hydro plant is expected to generate almost all of
the community’s electric energy. Given sales of 1,572,316 kWh in fy08, this translates to total
savings of over $460,000 per year (before PCE). Savings will increase as fuel costs increase.
-
10
20
30
40
50
60
70
80
90
$ MillionFig. 2. RE Fund Round 1
Estimated Grant Drawdown (Cumulative)
Reconn/Feas
Final Design
Construction
P a g e | 4
In the meantime, the best data available for assessing savings of other Round 1 projects is based on
material submitted by applicants and evaluated by AEA, UAA Institute of Social and Economic Research,
and private economists during proposal review. Figure 3 provides an estimate of cumulative yearly
diesel and natural gas fuel savings over the next several years. The analysis assumes that savings will
accrue during the year following completion of construction. Units are given in million Btu or diesel
gallon equivalent for simplicity.
By the end of 2010 fuel savings are expected to be approximately one million gallon equivalent per year.
By the end of 2011 savings are anticipated to be 2.5 million gallons per year. By the end of 2012 savings
are estimated at 5.8 million gallons per year. Actual savings to the consumer will be assessed through
collection of detailed data through a monitoring program.
-
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
900,000
-
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
2010 2011 2012 2013 Million Btu per yearGallons per Year Diesel EquivalentYear
Fig. 3. RE Fund Round 1
Estimated Cumulative Annual Fuel Savings
P a g e | 5
P a g e | 6
Appendix: Renewable Energy Fund Round 1, Project Status
P a g e | 7
Alaska Power & Telephone Co
North Prince of Wales Island Intertie Project
PBO 318; Grant No: 2195360; Project No: 409018
RE Fund Grant: $3,752,181 Project Type: TRANSMISSION
Match: Applicant Type: Utility
Other Funding Sources: 2,402,838 Region: SOUTHEAST
Total Project Cost: $6,155,019
RE FUND EXPENDED $824,626 As of 2/15/2010
Project Description:
AP&T will construct a line extension to the communities of Coffman Cove and Naukati Bay, placing these
communities on the Prince of Wales Island (POW) electric grid which is supplied with hydroelectric
power from two projects. The total line is to be 48 miles (Coffman Cove = 37 miles; Naukati Bay = 11
miles) of overhead 3-phase 34.5 kV line. Milestones consist of 1) Reconnaissance, 2) Feasibility and
Conceptual Design, 3) Final Design and Permitting, and 4) Construction. The project is also being funded
by the Denali Commission under the Energy Cost Reduction Program.
Project Status:
AP&T has completed reconnaissance, feasibility, and design. AP&T has received power poles,
distributed them along the first 15.9 miles of the line, and begun installation.
The project will be delayed 3 months due to unexpected permitting delays from USFS. AP&T is in
discussion with the State Historic Preservation Office on whether an archaeological survey is necessary
for this project.
The project will be delayed 3 months due to unexpected permitting delays from USFS. AP&T is in
discussion with the State Historic Preservation Office on whether an archaeological survey is necessary
for this project. Permits are required for state Department of Transportation land. These permits have
been filed and posted. In this phase permits will be acquired, acquiring legal access to lands, and final
design for the construction phase including a final survey of the route. Project completion is anticipated
in 2012.
P a g e | 8
Alaska Environmental Power
Delta Area Wind Turbines-Construction
PBO 328; Grant No: 2195370; Project No: 410027
RE Fund Grant: $2,000,000 Project Type: WIND
Match: 801,500 Applicant Type: IPP
Other Funding Sources: Region: RAILBELT
Total Project Cost: $2,801,500
RE FUND EXPENDED $2,000,000 As of 2/15/2010
Project Description:
This project consists of construction of 1MW of wind power capacity near Delta Junction.
Project Status:
The wind project is nearly complete; both the 100kW and 900kW turbines have been erected. The
100kW turbine is producing power and the 900kW turbine has been commissioned but still needs to be
interconnected to the Golden valley Electric Association grid. Alaska Environmental Power will sell the
energy to GVEA at a cost-based rate. This rate is currently being determined with the assistance of an
independent consultant hired by AEA. The project should be fully operational by spring of this year.
P a g e | 9
Alaska Gateway School District
Tok Wood Heating Construction
PBO 377; Grant No: 2195417; Project No: 402038
RE Fund Grant: $3,245,349 Project Type: BIOMASS
Match: 15,000 Applicant Type: Government
Other Funding Sources: Region: YUKON-
KOYUKUK/UPPER
TANANA
Total Project Cost: $3,260,349
RE FUND EXPENDED $394,387 As of 2/15/2010
Project Description:
This project will provide the final design and construction of biomass boilers to heat the approximately
75,000 sq. ft. school with wood chips. The project will consist of a separate building to contain the wood
chip boiler and the wood chip storage/delivery system. The wood chip boiler will be connected to the
schools primary oil fired boilers that will be kept on stand-by at all times.
Project Status:
The project is 100% designed and is currently out to bid for construction. It is scheduled to be
completed late fall of 2010.
P a g e | 10
Alaska Green Energy, LLC
California Creek Hydroelectric Feasibility
PBO 381; Grant No: 2195422; Project No: 407052
RE Fund Grant: $47,625 Project Type: HYDRO
Match: 4,825 Applicant Type: IPP
Other Funding Sources: Region: RAILBELT
Total Project Cost: $52,450
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
These grant funds will be used to prepare a preliminary feasibility study of a micro-hydro system on
California Creek in the Girdwood Valley. The following tasks will be accomplished: (1) surveying and
mapping, (2) hydrology, hydraulics and geotechnical investigations, (3) electro-mechanical conceptual
design, (4) preliminary environmental review, and (5) final report.
Project Status:
Grant activities are planned to begin in January and be completed in September 2010.
P a g e | 11
Alaska Village Electric Coop
Ambler Solar PV Construction
PBO00371; Grant No: 2195412; Project No: 411002
RE Fund Grant: $550,000 Project Type: SOLAR
Match: 55,000 Applicant Type: Utility
Other Funding Sources: Region: NW ARCTIC
Total Project Cost: $605,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The project consists of the design and construction of a 15 kW photovoltaic array to be connected to the
community powerhouse. The scope includes site visits to the villages of Ambler, Shungnak and Noatak
to collect solar data and site specific foundation conditions. Preliminary designs will be evaluated and
final system design, equipment specifications and construction estimates will be developed. Equipment
will be procured and construction on one of the sites will lead to integration of the solar array into the
community power system.
Project Status:
Currently the grant document remains in draft. AVEC held meetings and site visits in the communities to
refine the locations proposed. Based on these meetings and a preliminary on-site engineering report,
AVEC is proposing to modify the size and location of the proposed project based on security and shading
concerns of the original locations. AVEC will submit the scope to AEA for finalization with a goal of
construction in summer 2010. The anticipated project completion date is September 2010.
P a g e | 12
Alaska Village Electric Coop
Cosmos Hills Hydroelectric Feasibility Study
PBO00372; Grant No: 2195413; Project No: 407040
RE Fund Grant: $1,025,000 Project Type: HYDRO
Match: 50,625 Applicant Type: Utility
Other Funding Sources: Region: NW ARCTIC
Total Project Cost: $1,075,625
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This purpose of this preconstruction grant is to prepare a feasibility study of the potential hydro
resources to serve the villages of Ambler, Kiana, Kobuk and Shungnak. In order to obtain the most
efficient use of these grant funds, hydro sites will only be considered which are appropriately sized to
meet village needs and lie within a 10 mile radius of the village to be served. The first step will be to
review prior studies, update cost estimates and re-run the economic analyses to arrive at a short list of
economic sites. The goal of this study will be to arrive at no more than a single site for each of the four
villages for further study. The findings will be documented in an interim report to AEA which details the
analyses and provides recommendations for further study. Community outreach to villages will follow,
and then proceeding into feasibility-level engineering activities. Environmental field studies and
permitting will be accomplished. Stream gauging, surveying and mapping, engineering and conceptual
design will be conducted. The final deliverable will be a feasibility final report which captures all data
collected, studies performed, and conclusions reached.
Project Status:
AVEC is planning for 2010 field work and collecting previous studies at this time. Interim report is
anticipated in late spring 2010. Final permitting and draft concept design report is scheduled to be
completed by November 2011.
P a g e | 13
Alaska Village Electric Coop
Mekoryuk Wind Farm Construction
PBO00344; Grant No: 2195384; Project No: 410038
RE Fund Grant: $3,155,765 Project Type: WIND
Match: 875,641 Applicant Type: Utility
Other Funding Sources: Region: LOWER
YUKON/KUSKOKWIM
Total Project Cost: $4,031,406
RE FUND EXPENDED $1,541,689 As of 2/15/2010
Project Description:
This project is the construction of a 200kW wind project that serves AVEC’s Mekoryuk power system.
Project Status:
The two turbines were both erected in September of 2009. In January 2010 the turbine erection
contractor installed 12 thermo-siphons to stabilize the foundation. The outstanding action items for the
wind turbine foundation are the installation of the thermister-strings and vibration sensors; both
sensors will be tied in to the remote display system.
The integration design has been finalized. Work to fabricate the control module is scheduled to begin
this month. The Control module is tentatively scheduled to be transported to Mekoryuk in July 2010 and
the turbines will be operational as soon as the module is installed soon after arrival.
P a g e | 14
Alaska Village Electric Coop
Old Harbor Hydroelectric Final Design
PBO00390; Grant No: 2195431; Project No: 407039
RE Fund Grant: $225,000 Project Type: HYDRO
Match: 25,000 Applicant Type: Utility
Other Funding Sources: Region: KODIAK
Total Project Cost: $250,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This grant provides funding to complete the FERC licensing of this 300 kW run-of-river hydroelectric
plant for the village of Old Harbor. Located on the East Fork of Mountain Creek this plant would displace
most of the diesel power generation for this Kodiak Island based village. The grant will take the project
through the following tasks: (1) initial site visit, (2) feasibility report, (3) Preliminary Application
Document, (4) scoping meeting and site visits, (5) study plan preparation, (6) 2010 summer field work,
(7) draft and final FERC license and other agency permits.
Project Status:
The project is on schedule, having completed a study plan meeting with FERC and other agency staff in
late January 2010. Comments are being collected now on the draft study plan for field studies to be
completed in summer 2010 which will be subject to final approval by FERC. Estimated FERC license
issuance and grant completion is proposed for February 2012.
P a g e | 15
Alaska Village Electric Coop
Quinhagak Wind Farm Construction
PBO00342; Grant No: 2195383; Project No: 410037
RE Fund Grant: $3,882,243 Project Type: WIND
Match: 956,360 Applicant Type: Utility
Other Funding Sources: Region: LOWER
YUKON/KUSKOKWIM
Total Project Cost: $4,838,603
RE FUND EXPENDED $850,500 As of 2/15/2010
Project Description:
This project is the construction of a 300 kW wind power project that serves AVEC’s Quinhagak power
system.
Project Status:
The civil road and pad work was 85% completed in August 2009; the last 15% will be finish grade and
gravel top after the crane has completed its work. The thermo-piles and thermo-siphons were installed
in mid October. All three wind turbines have been erected; two of which are complete with rotor and
blades. The third unit is scheduled to be completed with rotor and blades by mid February. The
integration design has been finalized and materials have been ordered. The control module is tentatively
scheduled to be transported to Quinhagak in May of 2010. The turbines should be operational in the
summer of 2010 after installation of control equipment.
P a g e | 16
Alaska Village Electric Coop
Toksook Wind Farm Construction
PBO00343; Grant No: 2195385; Project No: 410039
RE Fund Grant: $1,037,750 Project Type: WIND
Match: 215,306 Applicant Type: Utility
Other Funding Sources: Region: LOWER
YUKON/KUSKOKWIM
Total Project Cost: $1,253,056
RE FUND EXPENDED $271,823 As of 2/15/2010
Project Description:
This project is a 100kW expansion of an existing 300kW wind farm that serves AVEC’s Toksook Bay
power system.
Project Status:
All necessary permitting has been completed. A pad for the wind turbine foundation is in place and the
turbine, rotors and tower have been delivered to the village. The tower base is currently in fabrication
and will be delivered in June of 2010. The turbine will be erected and commissioned in the summer of
2010.
P a g e | 17
Alaska Wind Energy
Nikolaevsk Wind Farm Final Design
PBO00385; Grant No: 2195426; Project No: 410043
RE Fund Grant: $180,600 Project Type: WIND
Match: Applicant Type: IPP
Other Funding Sources: Region: RAILBELT
Total Project Cost: $0
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The project consists of final design and permitting of a 6 MW wind farm near Nikolaevsk.
Project Status:
Alaska Wind Energy has decided not to proceed with the project. Project is being closed out.
P a g e | 18
Alaska Wind Power, LLC
Coal Mine Road Wind Farm Final Design
PBO00395; Grant No: 2195465; Project No: 410045
RE Fund Grant: $105,000 Project Type: WIND
Match: 26,250 Applicant Type: IPP
Other Funding Sources: Region: RAILBELT
Total Project Cost: $131,250
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This pre-construction wind project consists of wind resource assessment, permitting and design for a
potential wind farm in the Delta area. Funding from the Renewable Energy Fund is being combined with
other grant funding and managed as one grant.
Project Status:
The grant agreement is in final review and is expected to be finalized by March. Progress has been slow
in finalizing the grant due to the need for resolving potentially overlapping scopes of work funded by the
RE Fund versus other AEA funds. Despite not having a grant in place, the grantee has been moving
forward with wind resource assessment, avian studies, a preliminary layout, and an integration study.
The project is scheduled for completion in spring of 2011.
P a g e | 19
Aleutians East Borough
Aleutians East Borough Feasibility Study
PBO00367; Grant No: 2195408; Project No: 407051
RE Fund Grant: $25,000 Project Type: OTHER
Match: 15,000 Applicant Type: Government
Other Funding Sources: Region: ALEUTIANS
Total Project Cost: $40,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The funding is to conduct a reconnaissance report assessing possible renewable energy resources –
wind, hydro, current, tidal, and waste heat recovery – for the small isolated communities of Cold Bay,
False Pass, and Nelson Lagoon. The report will summarize the assessment and findings. The project
will be administered and managed by the AEB and will be conducted by a consultant chosen by the AEB.
Project scope includes compiling existing renewable energy resource studies, assessing existing energy
loads and fuel usage, identifying renewable energy system costs and savings, assessing needed permits
and land, and preparing an economic analysis of options in each community.
Project Status:
Aleutians East Borough has hired a contractor and submitted a first draft report in December 2009. The
Borough expected to complete final site visits by February 2010. The project is scheduled for
completion by June 2010.
P a g e | 20
Anchorage, Municipality of
Anchorage Landfill Gas Electricity Construction
PBO00389; Grant No: 2195430; Project No: 402032
RE Fund Grant: $2,000,000 Project Type: BIOFUEL
Match: 3,700,000 Applicant Type: Government
Other Funding Sources: Region: RAILBELT
Total Project Cost: $5,700,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The Municipality of Anchorage has proposed the design and installation of a 3-4 MW power plant
utilizing landfill gas, a by-product of anaerobic waste decomposition. The Municipality requested Round
1 funding of $3.7 million but funding was capped at $2 million.
Project Status:
Although the Municipality’s application proposed to use “landfill gas-to-power” technology, Anchorage
Assembly requested that other technology options be considered. Responding to this concern,
Anchorage Solid Waste Services Department is releasing an RFP in February 2010 to assess competitive
proposals for utilizing the gas, currently being flared. Now that the Municipality’s plans are clearer, AEA
is working with the Solid Waste Services to finalize the grant agreement. If the Municipality chooses a
project consistent with the original proposal AEA will make funds available for design and construction.
The Municipality anticipates a design contract by June 2010. Construction is planned for the summer of
2011 with system start-up by September 2011.
P a g e | 21
Atka, City of
Chuniisax Creek Hydroelectric Construction
PBO00335; Grant No: 2195376; Project No: 407033
RE Fund Grant: $996,000 Project Type: HYDRO
Match: 1,344,000 Applicant Type: Utility
Other Funding Sources: 574,891 Region: ALEUTIANS
Total Project Cost: $2,914,891
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This construction grant is to complete the final design, permitting and construction of an approximately
45% complete hydroelectric project on Chuniisax Creek. City of Atka has secured another grant from
Economic Development Administration (EDA) for this project. It will perform the work using force
account construction managed through a construction management (CM) firm and a professional
engineer, which are under contract. The remaining elements to be constructed include: dam with
intake, penstock, transmission line from existing hydro powerhouse to City, new controls and interface
between hydro and diesel powerhouses and final commissioning.
Project Status:
EDA funding required that the original wooden dam design be changed to concrete construction. The
final dam design has been reviewed by the State Dam Safety Officer. Further design modifications are
underway and will be completed in 1st quarter 2010. Pending EDA approval, construction is anticipated
to begin with materials orders in 1st quarter 2010, with project completion estimated by end of 2010.
P a g e | 22
Bethel, City of
Bethel Wind Power Project Times Four
PBO00391; Grant No: 2195432; Project No: 410034
RE Fund Grant: $2,598,320 Project Type: WIND
Match: 599,666 Applicant Type: Government
Other Funding Sources: Region: LOWER
YUKON/KUSKOKWIM
Total Project Cost: $3,197,986
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The project consists of the design, purchase and installation of four 100 kW wind turbines for integration
with the Bethel Utilities Corporation (BUC) power distribution system. The scope includes final design,
equipment procurement, installation of the wind towers and turbines and installation of control
equipment for connection to the power grid.
Project Status:
The grant has not been executed as the grantee has not submitted required documentation from the
various stakeholders in the community that will be involved in the project. The grant agreement has
been slow to develop for two main reasons. First, the City has not yet obtained an interconnection
agreement from BUC. The City has separate grant funding to complete the interconnection agreement.
Second, AEA is requiring a cost-based power sales rate, which is not consistent with the City’s proposed
business model that assumed the City would sell power to BUC at avoided cost. Given the cost-based
rate requirement, the City is considering other ways to structure the project. AEA anticipates project
completion in 2011.
P a g e | 23
Burro Creek Holdings, LLC
Burro Creek Hydro Feasibility Study
PBO00357; Grant No: 2195400; Project No: 407048
RE Fund Grant: $48,000 Project Type: HYDRO
Match: 12,000 Applicant Type: IPP
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $60,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This grant provides for a reconnaissance level study of the hydropower potential of Burro Creek, a creek
located south of Skagway on the west side of Lynn Canal. Grant tasks include: (1) survey of potential
site, (2) installation of stream gauge and collection of flow data, (3) engineering analysis and interim
report, (4) economic and market analysis of development options, and (5) final report.
Project Status:
The grant award is awaiting signature by grantee. The final report is expected in October 2011.
P a g e | 24
Cheesh'na Tribal Council
Chistochina Central Wood Heating Constr
PBO00340; Grant No: 2195380; Project No: 402028
RE Fund Grant: $500,000 Project Type: BIOMASS
Match: 12,000 Applicant Type: Government
Other Funding Sources: Region: COPPER
RIVER/CHUGACH
Total Project Cost: $512,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
Cheesh’na Tribal Council will complete the final design and construction of biomass boilers to heat a
small scale district heat loop for a community hall, new clinic, 2 office buildings, new washeteria, and
library. The project will consist of a new 24’x32’ building to contain the pellet furnaces. Insulated
underground heat lines will connect the furnace building to the several buildings that will be heated.
Project Status:
Project is currently under design and construction is anticipated by fall 2010.
P a g e | 25
Chena Power, LLC
Biomass-fired Organic Rankine Cycle System
PBO00316; Grant No: 2195358; Project No: 402025
RE Fund Grant: $2,000,000 Project Type: BIOFUEL
Match: 2,612,900 Applicant Type: Utility
Other Funding Sources: Region: RAILBELT
Total Project Cost: $4,612,900
RE FUND EXPENDED $600,000 As of 2/15/2010
Project Description:
This project consists of the design and construction of a 400 kW (net) power system that is fueled by
Fairbanks North Star Borough waste paper. The system includes two 250 kW UTC Pure Cycle ORC units;
a biomass boiler; fuel processing, storage and handling equipment; cooling pond; controls and grid tie-
in.
Project Status:
Chena Power has made initial payments and been reimbursed by AEA for a Wellons fluid bed boiler and
the UTC turbine-generators. Chena is also requesting initial payment on an SSI paper shredder. AEA
will require completion of design and a business plan before reimbursing final payments on the
equipment. Chena has taken partial delivery of the shredder and UTC equipment, and has renovated a
three-bay metal building that will serve as the power house. Currently a consultant hired by AEA is
assisting Chena with developing a cost-based power sales agreement with Golden Valley Electric
Association. Chena Power is scheduled to complete installation and commission the project in the third
quarter of 2010.
P a g e | 26
Chignik Lagoon Power Utility
Chignik Lagoon Hydroelectric Final Design
PBO00345; Grant No: 2195389; Project No: 407036
RE Fund Grant: $150,000 Project Type: HYDRO
Match: Applicant Type: Utility
Other Funding Sources: Region: BRISTOL
Total Project Cost: $150,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This pre-construction grant is to provide for developmental activities up through final design for this 190
kW hydro project on Packers Creek. Specific grant tasks include permitting, stream gauge, site survey
and final design.
Project Status:
The utility has retained an engineering firm to complete the grant tasks. Design work and permits under
this grant are anticipated to become available for review by summer 2010.
P a g e | 27
Chignik, City of
Indian Creek Hydro Feasibility Study
PBO00346; Grant No: 2195388; Project No: 407034
RE Fund Grant: $207,500 Project Type: HYDRO
Match: Applicant Type: Government
Other Funding Sources: Region: BRISTOL
Total Project Cost: $207,500
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project assesses the feasibility of expanding the existing 40 kW hydro plant currently licensed and
owned by Trident Seafoods to a City-owned hydro plant of 200kW capacity. Tasks to be completed
include: (1) establish MOU with Trident over future rights to an expanded hydro plant, (2) establish
MOU with US Fish and Wildlife Service and Alaska Dept. of Fish and Game over ways project impacts can
be mitigated, (3) fieldwork consisting of topographic surveys and hydrology data collection, and (4)
conceptual design report with cost estimate.
Project Status:
The city has hired a construction management firm to manage the grant. The firm has retained an
engineer to perform the grant tasks.
The planned completion date of Tasks 1-4 was estimated to be May 2010, however the progress has
been slower than anticipated due to prior consultant time commitments. It is now anticipated the
earliest completion of Task 4 will be in 2011.
P a g e | 28
Chilkoot Indian Association
Haines Central Wood Heating Construction
PBO00333; Grant No: 2195373; Project No: 402034
RE Fund Grant: $288,222 Project Type: BIOMASS
Match: 28,467 Applicant Type: Government
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $316,689
RE FUND EXPENDED $5,677 As of 2/15/2010
Project Description:
This project will purchase and install cordwood-fired boilers to provide heat to a four-plex housing
facility that is currently under construction.
Project Status:
Permitting to proceed with the construction has been received, and the final design is in progress. The
project team is evaluating the location for the boiler building to minimize construction costs.
Construction is anticipated to be complete by September 2010.
P a g e | 29
Copper River School District
Kenny Lake Wood Boiler Assessment
PBO00259; Grant No: 2195302; Project No: 402019
RE Fund Grant: $120,000 Project Type: BIOMASS
Match: 10,000 Applicant Type: Government
Other Funding Sources: Region: COPPER
RIVER/CHUGACH
Total Project Cost: $170,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project will provide the final design and construction for a biomass boiler to heat the K-12 School.
The project will consist of a separate small wood furnace building with pellet storage and will tie into the
existing oil fired heating boilers that will be kept on stand-by at all times.
Project Status:
This project is currently under planning and design, with the design anticipated being complete by the
end of June, and construction to follow once funding has been secured. CRSD has applied for
construction funding under Round 3 of the REF Grants process.
P a g e | 30
Copper Valley Electric Association
Allison Lake Hydro Feasibility Study
PBO00350; Grant No: 2195390; Project No: 407038
RE Fund Grant: $2,288,000 Project Type: HYDRO
Match: 572,000 Applicant Type: Utility
Other Funding Sources: Region: COPPER
RIVER/CHUGACH
Total Project Cost: $2,860,000
RE FUND EXPENDED $342,637 As of 2/15/2010
Project Description:
The 4 MW Allison Lake Hydroelectric Project would supplement power to the CVEA system, whose
primary source is the 12 MW Solomon Lake Hydro electric project. The funding provided under this
grant is in addition to a FY 2009 Legislative grant. Tasks to be completed with these grants include: (1)
study plan preparation, (2) conduct environmental field studies for 2009 and 2010 seasons, (2) prepare
draft application for FERC license, (3) complete feasibility study, (4) submit license application to FERC
and (5) supporting engineering activities.
Project Status:
The 2009 field studies have been completed. Evaluation of the second season study plan is underway at
this time, as well as preparation of the feasibility report. The report is due in April 2010 where CVEA
Board of Directors will review and either recommend a go or no-go decision on further fund
commitments to the project. Project schedule indicates license application to FERC anticipated for
submission in December 2010 with consultation over the following year to respond to FERC and agency-
related related questions and concerns.
P a g e | 31
Cordova Electric Cooperative
Cordova Heat Recovery Construction
PBO00365; Grant No: 2195407; Project No: 403028
RE Fund Grant: $1,780,000 Project Type: HEAT RECOVERY
Match: 3,480,000 Applicant Type: Utility
Other Funding Sources: Region: COPPER
RIVER/CHUGACH
Total Project Cost: $5,260,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project will purchase and install a 250 kW Organic Rankine Cycle (ORC) heat recovery unit to
capture water jacket heat on a new high-efficiency, low emissions diesel generator, increasing the
electricity production by 4-6%.
Project Status:
The installation of the diesel generator is substantially complete with the exception of communication
wiring. For the Organic Rankine Cycle system, the conceptual design and necessary permits are
complete. An RFP is being developed for the ORC for circulation in 1st quarter 2010. Installation is
scheduled for September/October 2010.
P a g e | 32
Cordova Electric Cooperative
Humpback Creek Hydroelectric Construction
PBO00347; Grant No: 2195386; Project No: 407037
RE Fund Grant: $4,000,000 Project Type: HYDRO
Match: 430,238 Applicant Type: Utility
Other Funding Sources: 2,970,000 Region: COPPER
RIVER/CHUGACH
Total Project Cost: $7,400,238
RE FUND EXPENDED $1,054,305 As of 2/15/2010
Project Description:
This construction grant provides for improvements to the existing 1.25 MW run-of-river Humpback
Creek Hydroelectric project. The project rebuilds the intake structure which was damaged during a
flood in 2006, adds road access to the project site and improves the SCADA communications and
controls to more effectively utilize the hydropower potential of the creek. FEMA has also provided
some funding.
Project Status:
Road construction began in fall 2008 and was completed in February 2009. Bids for the tunnel, and
intake/diversion and conveyance structures were opened in July, 2009 and came in higher than
anticipated. The contract was awarded by the utility in September 2009 and the contractor mobilized in
October. Tunnel boring and concrete lining and excavation of the left and right abutments for the new
intake structure are underway at this time. The tunnel work is ahead of schedule. Critical path item is
delivery of the steel penstock and intake structure accessories. February activities include finish hard
rock excavation for diversion and intake structure. Overall project target completion date is late fall
2010.
P a g e | 33
Delta/Greely School District
Delta Junction Wood Chip Heating
PBO00331; Grant No: 2195395; Project No: 402033
RE Fund Grant: $2,000,000 Project Type: BIOMASS
Match: Applicant Type: Government
Other Funding Sources: Region: RAILBELT
Total Project Cost: $2,000,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project will provide the final design and construction for biomass boilers to heat the Delta School
with wood chips.
Project Status:
The project is currently under design with an anticipated conceptual/preliminary design completed 1st
quarter of 2010. The original budget submitted for REF Round 1 funding was about $2.9 million.
However, since Delta is connected to the Railbelt grid the project was capped at $2 million. The
recently-hired design consultant revisited the budget to see if the project could be designed and built
for $2 million, but it was determined that the original budget amount is needed. DGSD has applied for
the budget shortfall in Round 3. If successful the project will move forward quickly to design in 2010,
with construction beginning in 2010 and being completed in 2011.
P a g e | 34
Fishhook Renewable Energy, LLC
Fishhook Hydroelectric Construction
PBO00394; Grant No: 2195435; Project No: 407020
RE Fund Grant: $2,000,000 Project Type: HYDRO
Match: 2,412,961 Applicant Type: IPP
Other Funding Sources: Region: RAILBELT
Total Project Cost: $4,412,961
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This grant would partially fund the construction of a 2 MW run-of-river hydroelectric project located on
Fishhook Creek in the vicinity of Hatcher Pass. This grant was selected for funding based upon a
schedule of completion of milestones to be accomplished by spring 2009 under a separate pre-
construction grant. Pre-construction milestones include: (1) completion of all construction permits, (2)
provide final design documents, (3) enter into a power sales agreement with the local utility, 4) obtain a
Certificate of Public Need and Conveyance from the RCA, and 5) resolution of remaining technical
issues.
Project Status:
The grantee has been delayed in accomplishing pre-construction milestones. Project financing for the
remaining approximately $1.8M under the Power Project Loan Fund has not been approved by AEA
pending slow progress on the pre-construction grant and response to AEA questions raised by AEA
regarding the project. AEA project concerns include: 1) uncertainty in hydrological data, 2)
demonstration of owner equity in project, and 3) third party verification of project construction costs.
P a g e | 35
Golden Valley Electric Association
Eva Creek Wind Farm Feasibility
PBO00384; Grant No: 2195425; Project No: 410044
RE Fund Grant: $2,000,000 Project Type: WIND
Match: 300,000 Applicant Type: Utility
Other Funding Sources: Region: RAILBELT
Total Project Cost: $2,300,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
Golden Valley Electric Association originally proposed feasibility, design, and construction of a 24 MW
wind farm in the Healy area and requested $79 million in grant funding. AEA recommended $2.53
million for feasibility assessment, but the project was capped at $2 million.
Project Status:
AEA and GVEA are in the process of finalizing the grant scope of work and expect to complete the grant
agreement shortly. GVEA has continued to move forward collecting additional wind and geotechnical
data in the area for more than a year. The data are needed for specific turbine siting. Detailed final
design plans are being developed to address site access and equipment/material staging. Varied land
ownership at the site also requires extensive permitting. Feasibility and permitting activity are scheduled
to be complete by December 2010.
P a g e | 36
Golden Valley Electric Association
McKinley Village Solar Thermal Construction
PBO00354; Grant No: 2195394; Project No: 411003
RE Fund Grant: $190,000 Project Type: SOLAR
Match: 3,600 Applicant Type: Utility
Other Funding Sources: Region: RAILBELT
Total Project Cost: $193,600
RE FUND EXPENDED $190,000 As of 2/15/2010
Project Description:
This project consists of design and construction of a solar water heating system (SWHS) including a
ground mounted solar collector array with of 36 40-sf collectors, a small building housing a 3,000 gallon
hot water storage tank and heat exchange equipment, and 1,530 feet of a buried district heating pipe
loop that provides 18 buildings dispersed over about 4 acres with domestic hot water. The project also
includes conservation measures and training to minimize hot water usage.
Project Status:
The array was operational in July 2009 and construction was completed in August 2009. Final invoices
and reports have been submitted and project is ready for administrative close-out. Project savings
numbers will be assessed over the next operating season May – September 2010.
P a g e | 37
Golden Valley Electric Assoc
North Pole Heat Recovery Construction
PBO00351; Grant No: 2195391; Project No: 403029
RE Fund Grant: $840,000 Project Type: HEAT RECOVERY
Match: 210,000 Applicant Type: Utility
Other Funding Sources: Region: RAILBELT
Total Project Cost: $1,050,000
RE FUND EXPENDED $734,254 As of 2/15/2010
Project Description:
The project consists of installing a waste heat recovery system from the GVEA North Pole powerhouse
to several utility buildings. Fifteen glycol unit heaters will supply the heating load currently provided by
electric unit heaters. The scope includes procurement of materials and the installation of a glycol
heating distribution system, heating equipment and controls.
Project Status:
Currently the majority of the piping and unit heaters are installed and in operation. Variable speed
pump controls have been ordered and will be integrated into the heating controls when they arrive. The
grant was executed in August 2009. The anticipated project completion date is November 2010.
P a g e | 38
Gulkana Village Council
Gulkana Central Wood Heating Construction
PBO00341; Grant No: 2195381; Project No: 402030
RE Fund Grant: $500,000 Project Type: BIOMASS
Match: Applicant Type: Government
Other Funding Sources: Region: COPPER
RIVER/CHUGACH
Total Project Cost: $500,000
RE FUND EXPENDED $270,776 As of 2/15/2010
Project Description:
The project consists of final design and construction of biomass boilers to heat a small-scale district heat
loop for a community hall, clinic, two office buildings, and four duplexes. The project includes a new
24’x32’ building to contain the pellet and cord wood furnaces. The heat lines will also tie into the
community water loop distribution system to add heat to help deter freeze-ups in the winter.
Project Status:
This project is currently under construction with start-up scheduled during the 2nd quarter of 2010. The
wood furnaces are on site and the interior mechanical and electrical work is set to begin in February.
The underground heat lines to the various buildings were installed late last fall.
P a g e | 39
Gustavus Electric Company
Falls Creek Hydroelectric Construction
PBO00349; Grant No: 2195387; Project No: 407045
RE Fund Grant: $750,000 Project Type: HYDRO
Match: Applicant Type: Utility
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $750,000
RE FUND EXPENDED $750,000 As of 2/15/2010
Project Description:
The grant provided funding to assist in the final stages of construction of the Falls Creek 800 kW run-of-
river hydroelectric facility.
Project Status:
The project began reliable operation in late July 2009. The hydro has been able to displace practically all
of the diesel generation that now serves as a silent but available backup source for the Gustavus Electric
Service Area. The grant is complete
P a g e | 40
Gwitchyaa Zhee Utility Company
Fort Yukon Central Wood Heating Design
PBO00363; Grant No: 2195405; Project No: 402040
RE Fund Grant: $210,000 Project Type: BIOFUEL
Match: 140,656 Applicant Type: Utility
Other Funding Sources: Region: YUKON-
KOYUKUK/UPPER
TANANA
Total Project Cost: $350,656
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The project consists of the design of a central wood heating system using locally available biomass. The
scope includes a conceptual design of the heating system, and integration plan with the electric utility
heat recovery system and the community wood harvest plan.
Project Status:
The design will proceed to the pre-construction 95% engineered drawing stage, submission of necessary
MOU’s for wood supplies and heat sales agreements, right of way and permitting documents,
environmental analysis and an operational business plan. G-Z contractors will prepare a construction
budget and proposed construction schedule. Currently a 35% Design Report has been received and site
control and permitting issues are being investigated. The grant was executed in August 2009. The
anticipated project completion date is September 30, 2010.
P a g e | 41
Haida Power, Inc.
Reynolds Creek Hydroelectric Construction
PBO00399; Grant No: 2195440; Project No: 407032
RE Fund Grant: $2,000,000 Project Type: HYDRO
Match: 6,645,000 Applicant Type: Utility
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $8,645,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This construction grant is to fund the initial phase of construction of a 5 MW hydroelectric project on
Mellen Lake / Reynolds Creek to provide power to the existing intertied grid on southern Prince of Wales
Island in southeast Alaska. Other RE Fund grants have been made on behalf of this project including a
$100,000 preconstruction grant to Haida Corporation. A Round 3 RE Fund application for $2M has been
submitted by Alaska Power Company for a transmission line to connect Reynolds Creek to the grid. A
$9M Power project loan fund request has also been received by Haida Energy, Inc. to fund the balance
of the construction costs for this project. The Southeast Conference has also received a $2M legislative
grant for project construction.
Project Status:
Because of the large number of grantees and loan applicants involved with this project, AEA has
requested a Joint Venture (or Master Agreement) be completed amongst all participants to define
respective roles and responsibilities for this project, as well as the arrangements for construction and
operation and ownership of the project. This will guide the issuance of grants and loan to clarify the
respective roles and provide for coordination in their administration. AEA has also requested it be
provided a scope and budget, timeline and milestones for each of the grants and loan of record. AEA
has requested demonstration of site control, a construction cost estimate, a funding plan for the project
and demonstration of land rights to build and operate the intertie which would connect Reynolds Creek
to the existing Prince of Wales grid.
P a g e | 42
Haines Borough
Haines Central Wood Heating Feasibility Study
PBO00332; Grant No: 2195372; Project No: 402036
RE Fund Grant: $120,500 Project Type: BIOMASS
Match: 20,000 Applicant Type: Government
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $140,500
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The project consists of a study for using local wood biomass for supplying boilers in a central district
heating system for several existing public buildings. The scope includes a Site Reconnaissance Report,
Feasibility Report, and a Conceptual Design for providing heat for the Haines K-12 School, Voc-Ed
Building, Municipal Administration Building, and the Public Library.
Project Status:
Currently a draft wood resource report has been received and the draft conceptual design report is
being prepared. The grant was executed in May 2009. The anticipated project completion date is July
2010.
P a g e | 43
Homer Electric Association
Falls Creek Low-Impact Hydro Assess PreConstr
PBO00287; Grant No: 2195331; Project No: 407024
RE Fund Grant: $50,000 Project Type: HYDRO
Match: 25,000 Applicant Type: Utility
Other Funding Sources: Region: RAILBELT
Total Project Cost: $125,000
RE FUND EXPENDED $50,000 As of 2/15/2010
Project Description:
This pre-construction grant has provided funding to assess the feasibility of constructing a 5 MW run-of-
the-river hydroelectric plant on Falls Creek. Tasks included in this scope of work included: (1) an initial
site assessment, (2) a conceptual design, (3) a study plan, and (4) a reconnaissance report which
described the findings.
Project Status:
The Grantee is pursuing further project development under a new scheme in a Round 2 RE grant. The
report was issued on April 2, 2009. This grant is complete.
P a g e | 44
Homer Electric Association
Crescent Lk/Crk Low-Impact Hydro Assess Pre-Construction
PBO00290; Grant No: 2195334; Project No: 407023
RE Fund Grant: $50,000 Project Type: HYDRO
Match: 20,000 Applicant Type: Utility
Other Funding Sources: Region: RAILBELT
Total Project Cost: $100,000
RE FUND EXPENDED $23,273 As of 2/15/2010
Project Description:
This pre-construction grant has provided funding to assess the feasibility of constructing either a 2.3 or
5.8 MW run-of-the-river hydroelectric plant on Crescent Lake / Creek. Tasks included in this scope of
work included: (1) an initial site assessment, (2) a conceptual design, (3) a study plan, and (4) a
reconnaissance report which described the findings.
Project Status:
The report was issued on April 2, 2009. The Grantee has abandoned further interest in project
development due to high cost of project and energy production. Some grant funds remain unexpended
and available for re-programming. This grant is complete.
P a g e | 45
Homer Electric Association
Grant Lk/Crk Low-Impact Hydro Assess Pre-Const
PBO00289; Grant No: 2195333; Project No: 407025
RE Fund Grant: $50,000 Project Type: HYDRO
Match: 25,000 Applicant Type: Utility
Other Funding Sources: Region: RAILBELT
Total Project Cost: $125,000
RE FUND EXPENDED $50,000 As of 2/15/2010
Project Description:
This pre-construction grant has provided funding to assess the feasibility of constructing a 5 MW run-of-
the-river hydroelectric plant on Grant Lake / Creek. Tasks included in this scope of work included: (1) an
initial site assessment, (2) a conceptual design, (3) a study plan, and (4) a reconnaissance report which
described the findings.
Project Status:
The report was issued on April 2, 2009. The Grantee is pursuing further project development under a
new scheme in a Round 2 RE grant. This grant is complete.
P a g e | 46
Homer Electric Association
Ptarmigan Lk/Crk Low-Impact Hydro Assess Pre-Const
PBO00291; Grant No: 2195335; Project No: 407026
RE Fund Grant: $50,000 Project Type: HYDRO
Match: 25,000 Applicant Type: Utility
Other Funding Sources: Region: RAILBELT
Total Project Cost: $125,000
RE FUND EXPENDED $4,684 As of 2/15/2010
Project Description:
This pre-construction grant has provided funding to assess the feasibility of constructing a 3 MW run-of-
the-river hydroelectric plant on Ptarmigan Lake / Creek. Tasks included in this scope of work included:
(1) an initial site assessment, (2) a conceptual design, (3) a study plan, and (4) a reconnaissance report
which described the findings.
Project Status:
The report was issued on April 2, 2009. The Grantee has abandoned further interest in project
development due to high cost of project and energy production. . Some grant funds remain
unexpended and available for re-programming. This grant is complete.
P a g e | 47
Hooper Bay, City of
Hooper Bay Wind Farm Feasibility
PBO00398; Grant No: 2195439; Project No: 410040
RE Fund Grant: $80,000 Project Type: WIND
Match: Applicant Type: Government
Other Funding Sources: Region: LOWER
YUKON/KUSKOKWIM
Total Project Cost: $80,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The project consists of a feasibility study for the installation of two wind turbines near the water
treatment plant to supply a portion of the facility electrical load. The scope includes a site specific wind
resource analysis, feasibility study and conceptual design for integration of the wind system into the
water plant facility.
Project Status:
Currently the feasibility study is underway. The grant was executed in December 2009. The anticipated
project completion date is April 2010.
P a g e | 48
Independence Power, LLC
Fourth of July Creek Hydroelectric Reconnaissance
PBO00379; Grant No: 2195420; Project No: 407044
RE Fund Grant: $20,000 Project Type: HYDRO
Match: 20,000 Applicant Type: IPP
Other Funding Sources: Region: RAILBELT
Total Project Cost: $40,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This grant is for reconnaissance level assessment of a hydro resource located on Fourth of July Creek.
This creek is located east of Seward, Alaska near the Lemon Creek Penitentiary. The work scope
includes a hydrology study, stakeholder meeting and permitting analysis. All findings are to be
documented in a Reconnaissance Study and Initial Feasibility Assessment.
Project Status:
AEA received the Final Report in November 2009 and is reviewing it. The report predicts the hydro
nameplate capacity of the site is 5.4 MW and recommends advancement of the project into the
feasibility stage.
P a g e | 49
Interior Regional Housing Authority
Galena Wood Heating Construction
PBO00402; Grant No: 2195443; Project No: 402037
RE Fund Grant: $382,779 Project Type: BIOMASS
Match: 382,779 Applicant Type: Government
Other Funding Sources: Region: YUKON-
KOYUKUK/UPPER
TANANA
Total Project Cost: $765,558
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project consisted of design and construction of a wood-fired system to heat the assisted living
center in Galena.
Project Status:
IRHA has decided not to proceed with the project, and project funding is being reallocated.
P a g e | 50
Juneau, City & Borough of
Juneau Ground Source Heat Pump Constr
PBO00352; Grant No: 2195393; Project No: 406009
RE Fund Grant: $1,450,000 Project Type: GEOTHERM
Match: 500,000 Applicant Type: Government
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $1,950,000
RE FUND EXPENDED $139,911 As of 2/15/2010
Project Description:
The City and Borough of Juneau is designing and constructing a hybrid ground source heat pump (GSHP)
to serve 81% of the new Aquatic Center’s heating needs.
Project Status:
During the summer of 2009 a well field consisting of 164 350-foot wells was completed. The piping was
installed in the boreholes and most of the backfill was put in place, but was not finished prior to the
onset of winter. The remaining backfill will be finished in late spring, and the heat pumps will be
installed after the mechanical room is ready. As the Aquatic Center is still under construction, the GSHP
will not be fully functional until late 2010. Project completion is scheduled for winter 2010.
P a g e | 51
Juneau, City and Borough of
Juneau Airport Ground Source Heat Pump
PBO00317; Grant No: 2195359; Project No: 406008
RE Fund Grant: $513,000 Project Type: GEOTHERM
Match: 513,000 Applicant Type: Government
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $1,026,000
RE FUND EXPENDED $513,000 As of 2/15/2010
Project Description:
The Juneau Airport Ground Source Heat Pump (GSHP) project consists of the construction of the
geothermal loop field in conjunction with the overall airport renovation project.
Project Status:
The field consists of 108 360-foot deep borings that were drilled in a little more than one month’s time.
The borings were run with piping to carry the heat transfer fluid and connected with horizontal piping to
manifolds. With the completion of the borings and connections, the airport will continue the project by
connecting the field to the heat pumps in the airport buildings with non-RE Fund dollars. As the airport
is still undergoing renovations, the GSHP will not be functioning until the airport’s mechanical work and
building envelope are completed. Project completion is scheduled for Summer 2010.
P a g e | 52
Kenai Winds, LLC
Nikiski Wind Farm Construction
PBO00392; Grant No: 2195433; Project No: 410046
RE Fund Grant: $80,000 Project Type: WIND
Match: 18,920,000 Applicant Type: IPP
Other Funding Sources: Region: RAILBELT
Total Project Cost: $21,000,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project consists of final design and construction project of a 9 MW wind farm at a refinery in Nikiski.
Project Status:
Kenai Winds is currently applying for permits and developing a final design. Construction is scheduled
for summer/fall 2010. Kenai Winds has submitted Round 3 grant application to expand the capacity to a
total of 16 MW. Current focus is on completing the 95-percent design for AEA review and working with
AEA’s rate consultant to establish a cost-based rate. Grantee is hand delivering the signed grant
agreement on Feb. 23.
P a g e | 53
Ketchikan Public Utilities
Whitman Lake Hydro Final Design
PBO00400; Grant No: 2195441; Project No: 407046
RE Fund Grant: $1,300,000 Project Type: HYDRO
Match: 320,000 Applicant Type: Utility
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $1,620,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This pre-construction grant is to prepare final design documents for the Whitman Lake Hydroelectric
Project. The project was issued a license to construct by FERC on March 17, 2009. The intent of this
grant is to fund all remaining activities needed to be accomplished up to but not including construction
bidding for this project. These steps include preparation of final design drawings and specifications,
review and approval of same by FERC and preparation of final construction cost estimate and project
construction schedule.
Project Status:
The utility’s consultant is working through these milestones at present and is on schedule to complete
all tasks by April 2011.
P a g e | 54
Kodiak Electric Association
Pillar Mountain Wind Project - Construction
PBO00329; Grant No: 2195371; Project No: 410025
RE Fund Grant: $4,000,000 Project Type: WIND
Match: 1,000,000 Applicant Type: Utility
Other Funding Sources: Region: KODIAK
Total Project Cost: $5,000,000
RE FUND EXPENDED $4,000,000 As of 2/15/2010
Project Description:
This project consists of the installation and interconnection of three GE 1.5MW wind turbines on Pillar
Mountain near the City of Kodiak.
Project Status:
The project is complete and the turbines have been operational since July 3, 2009. The turbines have
been operating very well and have had an excellent 95% availability since commissioning. According to
Kodiak Electric Association the turbines have produced nearly 7.8 million kWhs of electricity and saved
nearly 550,000 gallons of diesel fuel.
P a g e | 55
Kotzebue Electric Association
Kotzebue Wind Farm Expansion Construction
PBO00386; Grant No: 2195427; Project No: 410041
RE Fund Grant: $4,000,000 Project Type: WIND
Match: 427,495 Applicant Type: Utility
Other Funding Sources: Region: NW ARCTIC
Total Project Cost: $4,427,495
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
Kotzebue Electric originally proposed expanding its wind farm by 3.25 MW with $12.1 million in RE Fund
grant funds but was capped at $4 million. KEA has proposed a revised scope and requested an
additional $4,000,000 under Round 3. The revised project will consist of two new 900kW EWT900 wind
turbines and a 500kW/3.7MWh Zinc Bromide Flow Battery.
Project Status:
AEA and the Kotzebue Electric Association are currently developing the milestones and budget for the
revised project scope and expect to finalize the grant agreement in the next month. KEA has been
moving the project forward with geotechnical investigations and foundation design using their own
funding. The project is pursuing an aggressive schedule with a target completion date, pending
additional funding, of December 2010.
P a g e | 56
Kwaan Electric Transmission
Kake-Petersburg Intertie Final Design
PBO00374; Grant No: 2195414; Project No: 409019
RE Fund Grant: $2,990,000 Project Type: TRANSMISSION
Match: 2,500,000 Applicant Type: Utility
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $5,490,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The grant funds will be used towards environmental assessments and final design for the Kake –
Petersburg Hydroelectric Transmission Intertie. The applicant, along with the Alaska Department of
Transportation (ADOT), proposes to build a road and 69-kV transmission line to connect the community
of Kake with Petersburg. The road/intertie will allow the delivery of surplus hydropower available from
the Tyee project to Kake and eliminate its total reliance upon diesel generation. The principal tasks
involved in this project include: (1) preliminary feasibility report, (2) route selection, (3) environmental
permitting and (4) final design. It is anticipated this scope of work will take approximately three years to
complete.
Project Status:
ADOT has completed the preliminary feasibility report. The northern route has been selected as the
preferred option. The large cost of this project is under advisement at this time. Questions remain as to
potential funding sources for construction of this capital project and what, if any renewable energy
alternatives may be available located closer to Kake. Additionally, discussions are underway among the
Southeast Alaska Power Authority and KWETICO as to who will build, own and operate the intertie. As
these questions are answered the project will move forward.
P a g e | 57
Kwig Power Company
Kwigillingok High Penetration Wind-Diesel Smart Grid
PBO00369; Grant No: 2195410; Project No: 410036
RE Fund Grant: $1,600,000 Project Type: WIND
Match: 1,600,000 Applicant Type: Utility
Other Funding Sources: Region: LOWER
YUKON/KUSKOKWIM
Total Project Cost: $3,200,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project consists of the construction of a 450 kW high-penetration wind system in Kongiganak with
multiple secondary thermal loads in residences and the school. Project design is similar to systems
being installed in Kwigillingok and Tuntutuliak. Half of the funding is being provided by a legislative
grant.
Project Status:
Towers, turbines and foundation materials are staged and ready for construction in spring 2010 once
the final design is accepted following review by AEA and NREL. The grant agreement is currently being
reviewed internally by AEA.
P a g e | 58
Lake and Peninsula Borough
Chignik Lake Area Wind-Hydro Final Design
PBO00368; Grant No: 2195409; Project No: 410033
RE Fund Grant: $375,000 Project Type: WIND
Match: 96,000 Applicant Type: Government
Other Funding Sources: Region: BRISTOL
Total Project Cost: $471,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project is a feasibility study for both hydroelectric and wind energy in the vicinity of Chignik Lake. If
the feasibility studies show the potential for projects larger than Chignik Lake can use, the project will be
expanded to look at the feasibility of tying Chignik Lake with Chignik and Chignik Lagoon and could be
expanded to provide design funding for one of the feasible projects.
Project Status:
The grantee has hired a consultant, installed meteorological tower and completed a site visit for
selecting streams for the hydro assessment. The next steps include collection of resource data,
production of energy generation estimates, identification of permitting issues and the development of a
conceptual design. The project is scheduled for completion by the end of 2010.
P a g e | 59
Lake and Peninsula Borough
Lake Pen Borough Wind Feasibility Study
PBO00337; Grant No: 2195374; Project No: 410032
RE Fund Grant: $184,000 Project Type: WIND
Match: 40,000 Applicant Type: Government
Other Funding Sources: Region: BRISTOL
Total Project Cost: $224,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project is regional wind resource assessment and feasibility project for 6 different utilities in the
Lake and Peninsula Borough. The purpose of this grant is to determine which of the communities are
best suited for a wind project and then complete Engineering, Procure, and Construct (EPC) bid
documents for these communities.
Project Status:
The project is in the early stages and the Borough has just closed their RFP to select a contractor. The
contractor’s first activities will entail compiling existing data and determining where further data
collection is needed. This project is scheduled for completion in December 2010.
P a g e | 60
Lake and Peninsula Borough
Lake Peninsula Borough Wood Heating Final Design
PBO00364; Grant No: 2195406; Project No: 402026
RE Fund Grant: $77,000 Project Type: BIOMASS
Match: 18,000 Applicant Type: Government
Other Funding Sources: Region: BRISTOL
Total Project Cost: $95,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The project consists of final design and permitting to install high efficiency low emissions wood boilers in
five communities in the Land and Peninsula Borough to provide heat to the local schools and adjacent
teacher housing. The communities to be considered are Pedro Bay, Newhalen/Iliamna, Nondalton,
Kokhanok, and Port Alsworth. The scope includes a energy plan screening for the Borough, assessments
of high efficiency wood boilers, an estimate of wood operations and maintenance costs, a full
Reconnaissance Study and Preliminary Design, Site Control, Permitting and Right of Way assessment.
The final report will include a 95% Design Report Operational Business Plan, and an estimated
construction budget and construction schedule.
Project Status
Currently the wood resource evaluation is underway. The grant was executed in July 2009. The
anticipated project completion date is December 2010.
P a g e | 61
McGrath Light & Power Company
McGrath Central Wood Heating Proj Dev Ph III
PBO00361; Grant No: 2195403; Project No: 402039
RE Fund Grant: $322,000 Project Type: BIOMASS
Match: 183,000 Applicant Type: Utility
Other Funding Sources: Region: YUKON-
KOYUKUK/UPPER
TANANA
Total Project Cost: $505,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The project consists of the final design and permitting of a district heating system utilizing local woody
biomass to heat several public facilities including offices and school buildings in the City of McGrath.
The scope includes submission of a 65% Design Report and a System Integration Plan with the McGrath
Electric Utility Heat Recovery Construction Project (Round 1 Application #61). The final product includes
the 95% Design Drawings, Site Control Documentation, Environmental Analysis Report, Operational
Business Plan, and an estimated Construction Budget and Schedule.
Project Status:
Currently work is underway on the conceptual design of the heating system and integration plan with
the proposed new diesel powerhouse in Ft. Yukon. The grant was executed in July 2009. The
anticipated project completion date is May 2010.
P a g e | 62
McGrath Light & Power Company
McGrath Heat Recovery Construction
PBO00375; Grant No: 2195416; Project No: 403030
RE Fund Grant: $712,415 Project Type: HEAT RECOVERY
Match: 241,810 Applicant Type: Utility
Other Funding Sources: Region: YUKON-
KOYUKUK/UPPER
TANANA
Total Project Cost: $954,225
RE FUND EXPENDED $283,491 As of 2/15/2010
Project Description:
The McGrath Heat Recovery Project includes final design, permitting, and construction of power plant
efficiency improvements and a recovered heat system. Power plant improvements include fuel
efficiency upgrades, high efficiency fan and pump motors, and installation of marine jacketed exhaust
manifolds for increased heat recovery capture. The recovered heat system will provide available
recovered heat from the McGrath Light and Power (ML&P) power plant to four adjacent commercial
buildings, and the Iditarod Area School District (IASD) school complex. The project is designed for future
expansion to the new McGrath Clinic, as well as integration with the future McGrath Central Wood
Heating biomass project.
Project Status:
NEPA project level environmental permitting is complete. Installation of arctic piping to commercial and
IASD end-user facilities is complete. Power plant heat recovery room upgrades are 80% complete.
Installation of heat recovery equipment at end-user facilities is 55% complete. Power plant efficiency
improvements are 5% complete
P a g e | 63
Metlakatla Indian Community
Metlakatla-Ketchikan Intertie Design and Permittin
PBO00388; Grant No: 2195429; Project No: 409020
RE Fund Grant: $820,000 Project Type: TRANSMISSION
Match: 160,833 Applicant Type: Government
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $980,833
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This grant is to provide for the permitting and final design of a transmission line that would interconnect
the community power systems of Metlakatla to Ketchikan (and the associated Wrangell-Petersburg
grid). The proposed transmission line would follow the new road on Annette Island north to Walden
Point, and then require a submarine cable to connect to the Ketchikan Public Utility system. In addition,
grant funds will also be used to complete design upgrades to the various control systems of the MIC
electric system, including the governor and SCADA systems. Three tasks have been identified for this
grant including: (1) preliminary field design and right-of-way identification and (2) field staking and final
design and (3) construction drawings, staking sheets and bid documents.
Project Status:
MIC has hired a consultant to perform all grant related tasks. The tasks are underway at this time and
are expected to be completed by Spring 2010. No problems have been reported with the progress of
this grant.
P a g e | 64
Native Village of Eyak
Cordova Wood Processing Plant-Purchase and setup
PBO00358; Grant No: 2195399; Project No: 402027
RE Fund Grant: $147,720 Project Type: BIOMASS
Match: Applicant Type: Government
Other Funding Sources: Region: COPPER
RIVER/CHUGACH
Total Project Cost: $147,720
RE FUND EXPENDED $142,630 As of 2/15/2010
Project Description:
This project consists of the purchase and use of mobile firewood processor that will enable logs in
Cordova to be used for local space heating.
Project Status:
The Native Village of Eyak has purchased and transported the fuelwood processing plant and
transported it to Cordova. The equipment (a mobile Cord King Compact Model 69 with splitter and
60”saw blade on wheels) arrived in Cordova in January 2010. Currently the Village is setting up the unit
for initial training at a smaller log deck in Cordova. With recent heavy snow fall, the equipment was not
able to reach a larger log deck that will be eventually used. Once some of the snow melts, and the road
is plowed, then access to this site will allow the equipment to begin its work.
P a g e | 65
Nikolski IRA Council
Nikolski Wind Integration Construction
PBO00334; Grant No: 2195375; Project No: 410028
RE Fund Grant: $409,430 Project Type: WIND
Match: 41,500 Applicant Type: Government
Other Funding Sources: Region: ALEUTIANS
Total Project Cost: $450,930
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project will integrate an existing Vestas V15 65 kW wind turbine with an existing diesel
powerhouse. The integration consists of the installation of remote electrical boilers to utilize excess
wind energy for heating and adding to the existing switchgear. TDX Power has already installed the
thermal boilers in the school and local lodge.
Project Status:
The grant agreement has been prepared and is with the grantee for signature. Once the grant is signed
AEA will review the design and then the grantee will order the necessary equipment to complete the
job. Construction is scheduled for completion summer of 2010.
P a g e | 66
Nome Joint Utility Systems
Nome Banner Peak Wind Farm Transmission Constructi
PBO00403; Grant No: 2195444; Project No: 409017
RE Fund Grant: $801,000 Project Type: TRANSMISSION
Match: 89,000 Applicant Type: Utility
Other Funding Sources: Region: BERING
Total Project Cost: $890,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This is a grant to construct a two-mile intertie connecting a 1.17-megawatt wind farm constructed by
Banner Wind LLC with the Nome Joint Utility Systems electrical grid.
Project Status:
Construction has completed and the wind farm is producing power for the utility. NJUS will request
reimbursement for the full grant amount in March.
P a g e | 67
Nome, City of
Nome/Newton Peak Wind Farm Construction
PBO00397; Grant No: 2195438; Project No: 410030
RE Fund Grant: $4,000,000 Project Type: WIND
Match: 400,000 Applicant Type: Utility
Other Funding Sources: Region: BERING
Total Project Cost: $4,400,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
NJUS originally requested $13.95 million from Round 1 for feasibility, design and construction of a 3 MW
wind farm as a $13.5 million but project funding was capped at $4 million.
Project Status:
AEA and NJUS are working to revise the project scope, budget and milestones and expect to finalize the
grant within a month. Due to the change in scope, AEA will require feasibility analysis prior to
proceeding to final design or construction funding.
P a g e | 68
Northwest Arctic Borough
Buckland, Deering, Noorvik Wind Farm Construction
PBO00336; Grant No: 2195377; Project No: 410042
RE Fund Grant: $10,758,928 Project Type: WIND
Match: 162,500 Applicant Type: Government
Other Funding Sources: Region: NW ARCTIC
Total Project Cost: $10,921,428
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project consists of feasibility through construction of wind energy projects in three separate
communities (Buckland, Deering, and Noorvik) in the Northwest Arctic Borough.
Project Status:
The grant agreement has been difficult to put together due to the complexity of awarding funds to the
Borough for potential construction projects in three separate communities with three separate utilities.
Memoranda of agreement between the three utilities and the borough have been drawn up and signed.
The grant agreement has completed AEA review and is with the Grantee for signature. Wind resource
assessment is ongoing in all three communities. The next step is to complete feasibility studies based
on the updated wind resource data. The results of these studies will determine which communities
proceed to the permitting and final design stage. Project(s) are scheduled for commissioning in late
2011.
P a g e | 69
Northwest Inupiat Housing Authority
Kobuk River Valley Woody Biomass Feasibility
PBO00330; Grant No: 2195397; Project No: 402031
RE Fund Grant: $249,500 Project Type: BIOMASS
Match: 248,980 Applicant Type: Government
Other Funding Sources: Region: NW ARCTIC
Total Project Cost: $498,480
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The project consists of a feasibility study to determine the sustainable level of biomass harvest in the
Upper Kobuk River Valley near the villages of Ambler, Shungnak, and Kobuk.
Project Status:
The scope includes a woody biomass resource assessment, harvest system alternatives, wood yard
conceptual design, feasibility of boiler types, preliminary business models and the production of a 35%
Conceptual Design Report with a final Environment Analysis, estimated construction budget and
schedule. Currently a reconnaissance of the wood resources is underway. The grant was executed in
September 2009. The anticipated project completion date is December 2011.
P a g e | 70
Nushagak Electric and Telephone Cooperative
Lake Elva Hydropower Feasibility, Permitting & Final Design
PBO00378; Grant No: 2195419; Project No: 407035
RE Fund Grant: $4,006,500 Project Type: HYDRO
Match: Applicant Type: Utility
Other Funding Sources: Region: BRISTOL
Total Project Cost: $4,006,500
RE FUND EXPENDED $108,095 As of 2/15/2010
Project Description:
This grant evaluates the 1.5 MW Lake Elva Hydropower project as a potential source of power for this
Dillingham-based utility. Located 36 miles northwest of Dillingham within the boundaries of the Wood-
Tikchik State Park, Lake Elva is a high mountain natural lake. Site access is either by snow machine in the
winter or by helicopter in the summer. The grant is divided into three phases. Phase 1 allows for a
feasibility study of the Lake Elva hydro and for stream gauging. Phase 2 will provide third party (AEA)
funding for preparation of a regional integrated resource plan to review all available regional energy
sources. Phase 3 would include permitting and final design subject to successful completion of Phases 1
and 2. Assuming work began on that phase in 2011, completion is projected to be in 2015.
Project Status:
Phase 1 feasibility study has been completed. Some minor work has been accomplished for Phase 2,
but further detailed study and additional funding are required before this task is considered complete.
It is anticipated this work will occur this summer with completion at the end of December 2010.
P a g e | 71
Petersburg, City of
Ruth Lake Hydro Reconnaissance
PBO00373; Grant No: 2195415; Project No: 407047
RE Fund Grant: $160,000 Project Type: HYDRO
Match: 44,556 Applicant Type: Utility
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $202,528
RE FUND EXPENDED $157,972 As of 2/15/2010
Project Description:
This grant provided funds to pre-feasibility reconnaissance of the Ruth Lake hydro site and assisted with
the City’s filing of the Preliminary Permit application to FERC. The site is a high mountain lake located in
Thomas Bay which could have a 20 MW nameplate capacity. The City filed the Preliminary Permit
application with FERC on February 3, 2009. In the fall of 2009, FERC ruled (by drawing) that of the three
competing municipal preference applications received for Ruth Lake, the City of Angoon was selected as
the recipient of the Preliminary Permit for Ruth Lake. This permit is good for 3 years from date of
issuance. Consequently, any further work on development of this site by the City of Petersburg has
been deferred pending future appeals or expiration of the Preliminary Permit.
Project Status:
The grant scope of work has been completed and the grant is closed.
P a g e | 72
Puvurnaq Power Company
Kongiganak High Penetration Wind-Diesel Smart Grid
PBO00370; Grant No: 2195411; Project No: 410035
RE Fund Grant: $1,700,000 Project Type: WIND
Match: 1,192,850 Applicant Type: Utility
Other Funding Sources: Region: LOWER
YUKON/KUSKOKWIM
Total Project Cost: $2,892,850
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This project consists of the construction of a 450 kW high-penetration wind system in Kwigillingok with
multiple secondary thermal loads in residences and the school. Project design is similar to a system
being installed in Kongiganak. Half of the funding is being provided by a legislative grant.
Project Status:
Towers and turbines are erected and ready for wiring, new controllers, and connection to the grid.
Turbines are expected to be generating power for the grid in late spring or early summer 2010. The
project management team is completing the final, integrated design for review by AEA and NREL.
P a g e | 73
Sitka, City and Borough of
Takatz Lake Hydroelectric Feasibility
PBO00376; Grant No: 2195418; Project No: 407049
RE Fund Grant: $514,684 Project Type: HYDRO
Match: Applicant Type: Government
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $514,684
RE FUND EXPENDED $60,422 As of 2/15/2010
Project Description:
The project assesses feasibility of connecting Sitka to a potential 25 MW hydroelectric power plant on
Takatz Lake, a high mountain lake located on the Chatham side of Baranof Island. The three main goals
of this grant are resource assessment, conceptual design and a feasibility study. Sitka obtained the
FERC-issued Preliminary Permit for Takatz Lake in September 2008 and has received FERC approval to
allow the Alternative Licensing Process to be used for Takatz Lake. Though approved for $2 million in
grant funding in Round 1, Sitka received approximately $515,000 because it was at the bottom of the
ranked grant funding list. Because of the limited funding, the project scope has been reduced to match
the funds available.
Project Status:
Sitka is in the process of selecting a consultant to provide for grant funded engineering services. Sitka
has installed a stream gauge and will be conducting environmental and geotechnical investigations and
obtaining aerial photography for the site and proposed transmission line route in 2010. The final
feasibility report will be produced in 2011 which will document the proposed conceptual design, cost
estimates and engineering and environmental issues associated with the project. The report will
recommend whether or not to pursue FERC licensing.
P a g e | 74
South Fork Hydro, LLC
South Fork Hydroelectric Construction
PBO00393; Grant No: 2195434; Project No: 407041
RE Fund Grant: $1,000,000 Project Type: HYDRO
Match: 2,087,000 Applicant Type: IPP
Other Funding Sources: Region: RAILBELT
Total Project Cost: $3,087,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This grant provides funds for the construction of a 1.2 MW run-of-river hydroelectric project located on
the South Fork of Eagle River. South Fork Hydro LLC proposes to construct an intake structure,
penstock, powerhouse and generation equipment, tailrace, transmission line and access road for this
project.
Project Status:
Currently, a utility rate specialist is working with South Fork Hydro LLC to calculate a cost-based power
sales rate from the project. The LLC will then need to enter into a Power Purchase Agreement with the
local utility and obtain a Certificate of Public Convenience and Necessity from the Regulatory
Commission of Alaska. After completing final design documents and obtaining all necessary permits, the
project will proceed into construction. Commissioning, final inspection, and punchlist completion will
follow. South Fork Hydro estimates the project construction will be completed within 13 months after
start of actual work on the project.
P a g e | 75
St. George, City of
St. George Wind Farm Construction
PBO00355; Grant No: 2195398; Project No: 410029
RE Fund Grant: $1,500,000 Project Type: WIND
Match: 500,000 Applicant Type: Government
Other Funding Sources: 1,000,000 Region: ALEUTIANS
Total Project Cost: $3,000,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
The proposed project is a high penetration wind-diesel project that will be owned by the City of St.
George. The project will consist of a 225 kW wind turbine and thermal dump loads.
Project Status:
AEA is waiting for the city to demonstrate that they have all necessary matching funds before the grant
is put in place. The city currently has a loan application into AEA's Power Project Loan Fund for
$500,000 match. However AEA awaits City responses to AEA information requests before additional
evaluation of the loan application. The City has been making some progress without grant funding in
place. The City has completed initial geotechnical assessments and all permits and land lease
agreements. Assuming the City secures match funding, the project will likely be completed in the 2011
construction season.
P a g e | 76
TDX Power, Inc.
Manley Hot Springs Geothermal Plant
PBO00380; Grant No: 2195421; Project No: 406006
RE Fund Grant: $215,000 Project Type: GEOTHERM
Match: 705,000 Applicant Type: Utility
Other Funding Sources: Region: YUKON-
KOYUKUK/UPPER
TANANA
Total Project Cost: $1,645,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
Resource assessment, feasibility, and design and construction
Project Status:
With the goal of installing a pre-packaged 200 kW geothermal-powered generator, TDX completed the
resource assessment phase of the project in the summer of 2009. The assessment included acquiring
aeromagnetic data and performing a RaMPS (Resistivity Monopole Profiling and Sounding) survey. The
data from these two surveys were compiled in a report, released in January 2010, that pinpointed two
potential drill sites. By April, based on the results of survey, estimated drilling costs, and available
funding TDX will determined the scope and schedule of the drilling program. Drilling may take place in
the summer of 2010. . Currently, the construction of the geothermal power plant is planned for 2011,
but is dependent on the drilling plan. The project is scheduled for completion in winter 2011.
P a g e | 77
Unalakleet Valley Electric Cooperative
Unalakleet Wind Farm Construction
PBO00359; Grant No: 2195401; Project No: 410031
RE Fund Grant: $4,000,000 Project Type: WIND
Match: 164,340 Applicant Type: Utility
Other Funding Sources: 1,350,000 Region: BERING
Total Project Cost: $4,164,340
RE FUND EXPENDED $3,788,533 As of 2/15/2010
Project Description:
This project consists of the construction of 600 kW of wind generating capacity to serve the Unalakleet
Valley Electric Coop system. Originally UVEC proposed a 1.2 MW system costing $9 million, but Round 1
capped project funding at $4 million. UVEC has proceeded with the smaller project with over $1 million
in additional funding from Norton Sound Economic Development Council and Unalakleet Native
Corporation.
Project Status:
The turbines were erected, commissioned, and operating by fall of 2009. The turbines currently need to
be operated manually since they have not yet been fully integrated into the power system with a dump
load boiler and automated controls. These final aspects of the project will be completed as AEA and
UVEC finish rebuilding the diesel powerhouse during the 2010 construction season through an
associated Rural Power System Upgrade project. The project is expected to be fully operational by the
end of 2010.
P a g e | 78
University of Alaska-Anchorage
Statewide Hydrokinetic Feasibility Study
PBO00401; Grant No: 2195442; Project No: 407054
RE Fund Grant: $565,439 Project Type: OCEAN/RV
Match: Applicant Type: Government
Other Funding Sources: Region: STATEWIDE
Total Project Cost: $565,439
RE FUND EXPENDED $171,119 As of 2/15/2010
Project Description:
This project is a resource assessment of hydrokinetic energy potential near 17+ communities in rural
Alaska.
Project Status:
UAA School of Engineering collected resource data in the field during summer 2009. Five communities
were surveyed on the Kuskokwim and twelve on the Yukon River. During the fall and winter, the data
has been analyzed to determine the velocity and volumetric flow at different water levels throughout
the year, so that yearlong models of potential power production can be made for each of the
communities. The communities to be assessed during the 2010 field season are in the process of being
chosen in conjunction with input from AEA, but will likely include a wider geographic distribution than
the 2009 field season. The project is scheduled for completion in spring 2011.
P a g e | 79
University of Alaska-Fairbanks
Nenana Hydrokinetic Construction
PBO00396; Grant No: 2195437; Project No: 407053
RE Fund Grant: $450,000 Project Type: OCEAN/RV
Match: Applicant Type: Government
Other Funding Sources: Region: RAILBELT
Total Project Cost: $450,000
RE FUND EXPENDED $163,380 As of 2/15/2010
Project Description:
In a two-phase project, the University of Alaska Fairbanks’ Alaska Center for Energy and Power (ACEP)
are researching the installation of hydrokinetic turbines in Alaska’s rivers.
Project Status:
Staged on the Tanana River at Nenana, ACEP, working with partners and subcontractors, has
accomplished the first field season of resource assessment including: bathymetry, river current and
discharge, sediment transport, and side-scan sonar. During the late fall and winter, ACEP and Ocean
Renewable Power Co. (the holder of the FERC preliminary permit at the location) are studying the ice
and debris conditions. Due to regulatory and engineering hurdles, construction and installation of an
ORPC turbine will likely take place in 2011, instead of May 2009 as originally planned. The project is
scheduled for completion winter 2011
P a g e | 80
Whittier, City of
Whittier Creek Hydroelectric Reconnaissance
PBO00353; Grant No: 2195396; Project No: 407043
RE Fund Grant: $85,000 Project Type: HYDRO
Match: 15,000 Applicant Type: Government
Other Funding Sources: Region: RAILBELT
Total Project Cost: $200,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This grant provides for a reconnaissance level study of the hydropower potential of Whittier Creek .
Grant tasks include; (1) an Interim Report, (2) two years of stream gauging and hydrology analysis of
Whittier Creek, and(3) a preliminary design concept and analysis. The complete analysis and all field
data will be documented in a reconnaissance report which will be completed by May 2012. The U.S.
Army Corps of Engineers is matching the state grant funds and city funds with federal funds and will also
be managing the grant activities for the City of Whittier. The stream gauging installation and data
collection will be conducted by the USGS.
Project Status:
The grant award has been delayed due to the Whittier City Manager position becoming vacant in the fall
of 2009, but is anticipated to be awarded later this month.
P a g e | 81
Wrangell, City and Borough of
Wrangell Hydro Based Electric Boilers Construction
PBO00382; Grant No: 2195423; Project No: 407055
RE Fund Grant: $2,000,000 Project Type: OTHER
Match: 82,000 Applicant Type: Government
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $2,082,000
RE FUND EXPENDED $127,983 As of 2/15/2010
Project Description:
The project consists of the design, permitting, and construction of the conversion from diesel-fired
boilers to electric unit heaters, thereby utilizing excess hydro capacity. The scope includes final design
construction documents, procurement of the heating and control equipment, and the mechanical and
electrical installation of the system.
Project Status:
Currently installation of the electric unit heaters and electric supply and control equipment is underway
with several heaters in operation. The grant was executed in August 2009. The anticipated project
completion date is August 2010.
P a g e | 82
Yakutat Power
Yakutat Biomass Feasibility
PBO00383; Grant No: 2195424; Project No: 402035
RE Fund Grant: $249,600 Project Type: BIOMASS
Match: 17,652 Applicant Type: Utility
Other Funding Sources: Region: SOUTHEAST
Total Project Cost: $267,252
RE FUND EXPENDED $8,431 As of 2/15/2010
Project Description:
The project consists of an investigation of the local woody biomass resource, permitting issues and a
conceptual design of a biomass to electricity system. The electricity produced would be integrated into
the existing powerhouse to displace a portion of the diesel generator production. The scope includes a
local biomass resource evaluation and a conceptual design and integration plan with the existing diesel
powerhouse.
Project Status:
Currently a brief feasibility study of the technology is under AEA review and prospective engineering
firms are being evaluated. The grant was executed in August 2009. The anticipated project completion
date is September 2010.
P a g e | 83
Yukon River Inter-Tribal
Ruby Hydrokinetic
PBO00360; Grant No: 2195402; Project No: 407050
RE Fund Grant: $446,950 Project Type: OCEAN/RV
Match: 15,000 Applicant Type: IPP
Other Funding Sources: Region: YUKON-
KOYUKUK/UPPER
TANANA
Total Project Cost: $461,950
RE FUND EXPENDED $87,422 As of 2/15/2010
Project Description:
This project will expand the demonstration of a hydrokinetic energy conversion device near Ruby on the
Yukon River from 5 kW to 25 kW of installed capacity.
Project Status:
The Yukon River Intertribal Watershed Council (YRITWC) continued work on the 5-kW Encurrent turbine
pilot project in the summer of 2009. Functional testing and electricity production was cut short last
summer as abrasion of the transmission cable wore through the protective sheath and cut-off power
from the turbine. After analyzing the results and revising the construction plans this winter, YRITWC
plans on deploying the 25-kW Encurrent turbine next summer. Permanent permitting remains an on-
going effort. Completion is scheduled for June 2011.
P a g e | 84
Kenai Hydro, LLC
Grant Lake/Falls Creek
PBO00387; Grant No: 2195428; Project No: 407042
RE Fund Grant: $816,000 Project Type: HYDRO
Match: 204,000 Applicant Type: IPP
Other Funding Sources: Region: RAILBELT
Total Project Cost: $1,020,000
RE FUND EXPENDED $0 As of 2/15/2010
Project Description:
This pre-construction grant provides funding to develop field data and studies for support of a FERC
license for new 4.5 MW hydro scheme which draws water from Grant Lake and Falls Creek. Significant
milestone activities conducted in 2009 include: (1) environmental field studies, (2) engineering support
for FERC submissions of the Notice of Intent and the Pre-Application Document, (3) outreach meetings
for general public and agency personnel, and (4) preliminary engineering for support of FERC project
licensing.
Project Status:
Tasks 1-4 have been under way since May 2009 and are anticipated to continue in 2010. The project’s
LLC membership has recently changed with the announcement of the withdrawal by Kenai Winds, LLC a
J.V. between CIRI and EnXco. Homer Electric continues to pursue the project as the sole remaining LLC
member.
P a g e | 85
Cross Reference Table by Region
Page # ID Project Name Applicant
Aleutians
21 58 Chuniisax Creek Hydroelectric Construction City of Atka
65 89 Nikolski Wind Integration Construction Umnak Power / Nikolski IRA Council
75 90 St. George Wind Farm Construction City of St. George - St. George Municipal Electric
Utility
19 11 Aleutians East Borough Renewable Energy Reconnaissance Aleutians East Borough
Bering Straits
67 52 Nome/Newton Peak Wind Farm Construction City of Nome d/b/a Nome Joint Utility System
(NJUS)
77 50 Unalakleet Wind Farm Construction Unalakleet Valley Electric Cooperative, Inc. (UVEC)
66 47 Nome Banner Peak Wind Farm Transmission Construction City of Nome d/b/a Nome Joint Utilities System
Bristol Bay
59 64 Lake Pen Borough Wind Feasibility Study Lake and Peninsula Borough
58 62 Chignik Lake Area Wind-Hydro Final Design Lake and Peninsula Borough
60 63 Lake Pen Borough Wood Heating Final Design Lake and Peninsula Borough
27 40 Indian Creek Hydro Feasibility Study City Of Chignik
70 6 Lake Elva Hydropower Construction Nushagak Electric & Telephone Cooperative, Inc
26 14 Chignik Lagoon Hydroelectric Final Design Chignik Lagoon Power Utility (CLPU)
Copper River/ Chugach
32 21 Humpback Creek Hydroelectric Construction Cordova Electric Cooperative
31 22 Cordova Heat Recovery Construction Cordova Electric Cooperative
64 26 Cordova Wood Processing Plant Construction Native Village of Eyak
30 27 Allison Lake Hydro Feasibility Study Copper Valley Electric Association, Inc (CVEA)
24 15 Chistochina Central Wood Heating Construction Cheesh'na Tribal Council
29 46 Kenny Lake Wood Heating Construction Copper River School District
38 2 Gulkana Central Wood Heating Construction Gulkana Village Council
Kodiak
54 103 Pillar Mountain Wind Farm Construction Kodiak Electric Associaiton, Inc.
14 73 Old Harbor Hydroelectric Final Design Alaska Village Electric Cooperative
Lower Yukon/ Kuskokwim
22 122 Bethel Wind Power Project Times 4 City of Bethel
72 110 Kongiganak Wind Farm Construction Puvurnaq Power Company
57 107 Kwigillingok Wind Farm Construction Puvurnaq Power Company
15 70 Quinhagak Wind Farm Construction Alaska Village Electric Cooperative
P a g e | 86
Page # ID Project Name Applicant
13 72 Mekoryuk Wind Farm Construction Alaska Village Electric Cooperative
16 71 Toksook Bay Wind Farm Expansion Construction Alaska Village Electric Cooperative
47 35 Hooper Bay Wind Farm Construction City of Hooper Bay
Northwest Arctic
69 59 Kobuk River Valley Woody Biomass Feasibility Study Northwest Inupiat Housing Authority
11 75 Ambler Solar PV Construction Alaska Village Electric Cooperative
55 85 Kotzebue Wind Farm Expansion Construction Kotzebue Electric Association
68 56 Buckland/Deering/Noorvik Wind Farm Construction Northwest Arctic Borough
12 74 Upper Kobuk Region Hydroelectric Feasibility Alaska Village Electric Cooperative
Railbelt
20 68 Anchorage Landfill Gas Electricity Construction Municipality of Anchorage, Solid Waste Services
Dept
74 57 South Fork Hydroelectric Construction South Fork Hydro, LLC
17 94 Nikolaevsk Wind Farm Final Design Alaska Wind Energy, LLC, d/b/a Wind Energy
Alaska (WEA)
35 109 Eva Creek Wind Farm Construction Golden Valley Electric Association
25 53 North Pole Biomass Electricity/Heat Construction Chena Power Utility, LLC
34 87 Fishhook Hydroelectric Construction Fishhook Renewable Energy, LLC
52 34 Grant Lake/Falls Creek Hydro Feasibility Study Kenai Hydro, LLC
37 105 North Pole Heat Recovery Construction Golden Valley Electric Association
18 66 Coal Mine Road Wind Farm Final Design Alaska Wind Power, LLC
8 102 Delta Junction Wind Farm Construction Alaska Environmental Power LLC
52 98 Nikiski Wind Farm Construction Kenai Winds, LLC
10 78 Girdwood Gas CHP/Hydro/Wind Solar Construction Alaska Green Energy, LLC
80 48 Whittier Creek Hydroelectric Reconnaissance City of Whittier
48 86 Fourth of July Creek Hydroelectric Reconnaissance Independence Power, LLC
79 97 Nenana Hydrokinetic Construction University of Alaska Fairbanks, Office of
Sponsored Programs
33 112 Delta Junction Wood Chip Heating Feasibility Study Delta/Greely School District
36 108 McKinley Village Solar Thermal Construction Golden Valley Electric Association
84 -- Kenai Hydro Recon Assessment Homer Electric Association
Southeast
7 23 Coffman Cove-Naukati Intertie Construction Alaska Power & Telephone Company
56 29 Kake-Petersburg Intertie Final Design Kwaan Electric Transmission Intertie Cooperative,
Inc (KWETICO)
39 10 Falls Creek Hydroelectric Construction Gustavus Electric Company
P a g e | 87
Page # ID Project Name Applicant
41 104 Reynolds Creek Hydroelectric Construction Haida Power, Inc.
50 111 Juneau Ground Source Heat Pump Construction (Aquatic
Center) City & Borough of Juneau
53 37 Whitman Lake Hydro Construction Ketchikan Public Utilities- Electic Division
28 33 Haines Central Wood Heating System Construction (Low
Income Housing Project) Chilkoot Indian Association
82 60 Yakutat Biomass Gasification Construction Yakutat Power
71 38 Ruth Lake Hydro Reconnaissance City of Petersburg d/b/a Petersburg Municipal &
Light
23 42 Burro Creek Hydro Feasibility Study Burro Creek Holdings, LLC
63 20 Metlakatla-Ketchikan Intertie Construction Metlakatla Indian Community
42 41 Haines Central Wood Heating Feasibility Study (Community
Buildings) Haines Borough
81 9 Wrangell Hydro Based Electric Boilers Construction City and Borough of Wrangell
73 1 Takatz Lake Hydroelectric Feasibility City & Borough of Sitka
51 -- Juneau Ground Source Heat Pump Construction (Airport) City & Borough of Juneau
Yukon-Koyukuk/
Upper Tanana
62 61 McGrath Heat Recovery Construction McGrath Light & Power, Co.
49 54 Galena Wood Heating Construction Interior Regional Housing Authority (IRHA)
83 84 Ruby Hydrokinetic Construction Yukon River Inter-Tribal Watershed Council
9 49 Tok Wood Heating Construction Alaska Gateway School District
61 30 McGrath Central Wood Heating Construction McGrath Power and Light
40 31 Fort Yukon Central Wood Heating Construction Gwitchyaa Zhee Utility Company
76 -- Manley Hot Springs Geothermal Construction TDX Power
Statewide
78 88 Statewide Hydrokinetic Feasibility Study Thomas Ravens, Ph.D. and Myree McDonald,
Ph.D.