TO: Members of the Legislative Budget
and Audit Committee
FROM: Pat Davidsof`i
Legislative Auditor
DATE: February 17, 2009
RE: Limited Analysis of the Alaska Energy
Authority's Renewable Energy Grant
Recommendation Process
We were asked at the February 4, 2009 Legislative Budget and Audit Committee (LBA)
meeting to review the process used by the Alaska Energy Authority (AEA) to evaluate and
recommend alternative energy projects for funding under Ch 31 SLA 2008 (HB 152). We
were to report back to LBA by February 17, 2009.
Our analysis was focused on three areas:
1. Did the process used by AEA conform to HB 152?
2. Evaluate five projects to determine if AEA conducted its review and evaluation as it
presented to the LBA Committee.
3. Was AEA review and evaluation process sufficiently comprehensive and complete?
This is a very limited review and does not constitute an audit. During this limited review, we
reviewed grant applications, interviewed state employees at AEA, DNR, RCA and ISER as
well as their contractors. Additionally, we contacted other states and federal agencies
administering renewable energy grants.
AEA Compliance with HB 152 Requirements
The first area reviewed was a limited assessment as to whether AEA's process complied with the
requirements of HB 152. We observed the following:
Members of the Legislative Budget
and Audit Committee - 2 -
February 17, 2009
• AEA worked in consultation with a seven -member advisory committee, established
by HB 152, and the Department of Natural Resources.
• AEA developed a methodology for determining the order of projects to receive
funding, including separate requirements for grant eligibility'.
• The regulation adoption process for indentifying criteria to evaluate the benefit and
feasibility of projects applying for funding has not been completed.
• AEA's evaluation criterion with the largest number of possible points was the cost of
existing energy. This was intended to give the most weight to projects that service
any area in which the average cost of energy to each resident of an area exceeds the
average cost to each resident of other areas of the state.
• AEA with the support of the advisory committee used regional caps to ensure
"Significant weight" was given to a statewide balance of grant funds.
• AEA's evaluation criterion with the second largest number of possible points was the
amount of matching funds. This was intended to give "significant weight" to the
amount of matching funds an applicant is able to make available. AEA's formula for
evaluating the match gave significant weight to the percentage of match compared to
the total project costs as well as the nominal dollar value of the match.
Very little of the weight was given to the source of the match. Out of a total of 25
possible points there is only a two point difference between the match coming from
another state grant as opposed to local cash or in -kind contribution. Additionally
there is only a one point difference between the match coming from a federal or
private grant as opposed to local cash or in -kind contribution.
HB 152 also established project eligibility requirements for grants. To address these
eligibility issues:
• AEA's request -for -application process included a step requiring that the application
be for a new project not in operation on August 20, 20082 or an addition to an
existing project made after August 20, 2008.
I Grant eligibility includes eligible applicants as well as eligible projects. Eligible applicants include: (1) electric
utility holding a certificate of public convenience and necessity under AS 42.05, (2) independent power producer,
(3) local government, and (4) other governmental utility, including a tribal council and housing authority.
2 August 20, 2008 is the effective date of Section 3 of Ch 31, SLA 2008.
ALASKA STATE LEGISLATURE DIVISION OF LEGISLATIVE AUDIT
Members of the Legislative Budget
and Audit Committee - 3 - February 17, 2009
e All projects recommended must be at least one of the following: a hydroelectric
facility; a direct use of renewable energy resources; a facility that generates
electricity from fuel cells that use hydrogen from renewable energy resources or
natural gas; or a facility that generates energy from renewable energy resources.
® AEA's request -for -application process required that transmission projects must link a
renewable energy project or natural gas project to the transmission of distribution
infrastructure.
Detail Review of Projects
The next area was to review five projects. We selected these projects with intent to obtain a
distribution among regions, types of applicants and types of projects. The projects selected for
review were:
Applicant
Project
Recommended
Project Name
Applicant
Type
Type
Funding
Kongiganak Wind Farm
Puvumaq Power Co.
Utility
Wind
$1,700,000
Construction
Ambler Solar PV Construction
Alaska Village Electric
Utility
Solar
$550,000
Cooperative
Delta Junction Wood Chip Heating
Delta/Greely School
Gov't
Biomass
$2,704,684
Feasibility Study
District
Wrangell Hydro Based Electric
City and Borough of
Gov't
Other
$2,000,000
Boilers Construction
Wrangell
Ruby Hydrokinetic Construction
Yukon River Inter -Tribal
IPP
Hydro
$446,950
Watershed Council
Our review included inspecting submitted applications and supporting documentation,
AEA's project review scoring documentation including benefit/cost worksheets, and
interview of project manager, proposal evaluators, and AEA's contracted economist.
Stage 1 — Application Review
Each project's application was reviewed for completeness and eligibility
Stage 2 — Project Feasibility
® Each project had an initial review by AEA staff with expertise in the applicable
energy technology and a consistency review by two AEA program managers.
Additionally, assistance was provided by the Department of Natural Resources
(DNR) for technical issues and economists for cost benefit calculations with the
exception of the Kongiganak.
ALASKA STATE LEGISLATURE DIVISION OF LEGISLATIVE AUDIT
Members of the Legislative Budget
and Audit Committee - 4 - February 17, 2009
According to AEA, Northern Economics is shown as having done the economic
review on the Kongiganak wind project. However, when we contacted Northern
Economics, they told us that they did not review this project. According to AEA the
project was not subjected to an external economic review due to oversight and timing.
The economic analysis was performed internally by AEA staff.
Except for the Kongiganak wind project, each project we reviewed followed AEA's
methodology, that methodology provides wide latitude for AEA staff to impose its
own professional judgment. The following items are where AEA's professional
judgment overrode the initial decisions or calculations.
o Wrangell Hydro Based Electric Boiler Construction The economist who
developed the benefit/cost (BCE) for this project notes it is assumed the City
and Borough of Wrangell will only realize fuel displacements for a period of
ten years because an electricity load forecast projects electricity demand to
exceed the existing hydro resource 3. Although the economist recognized that
the city will only realize fuel displacements for ten years, the BCE calculates
benefits for 30 years.
o Wrangell Hydro Based Electric Boiler Construction Calculation of the BCE
resulting from this project did not include the operating and maintenance costs
(O&M) reported in Attachment F - Application Cost Worksheet of the project
proposal. AEA staff chose not to use any O&M costs because they would be
borne by the city.
o Kongiganak Wind Farm Construction As previously noted, this project was
subjected to an external economic analysis. AEA's methodology calls for a
certain score to be given based on a range of BCE ratios. On this project,
AEA staff used their judgment to give the project a higher score than is
supported by the actual BCE ratio
o Delta Junction Wood Chip Heating Feasibility Study. Similar to the
Kongiganak wind farm project, AEA staff used their judgment to give this
project a higher score than is supported by the actual BCE ratio.
o Ambler Solar PV Construction This project received 16 of possible 20 points
for technical feasibility. However, AEA published a statewide energy plan in
January 2009 in which they concluded solar holds little promise to
economically reduce Alaska's dependence on fossil energy. Funding of the
'The economist cites a 2007 AK -BC Intertie Feasibility Study as the basis for this opinion.
ALASKA STATE LEGISLATURE DIVISION OF LEGISLATIVE AUDIT
Members of the Legislative Budget
and Audit Committee -5- February 17, 2009
Alaska Village Electric Cooperative (AVEC) solar PV-diesel hybrid
contradicts this conclusion.
o Ambler Solar PV Construction AEA did not request a business plan for the
applicant, AVEC. AEA justified this because of their prior working
experience with AVEC.
Stage 3 — Review Scores
For this stage, each project had an initial review by AEA staff with expertise in the
applicable energy technology and a consistency review by two AEA program managers.
® Each project's score for the cost of energy metric was calculated according to AEA's
methodology.
® Each project's score for the match metric was accurately calculated according to
AEA's methodology. Note: at this point AEA did not confirm the reported match.
® Each project's score for the project feasibility metric was developed as part of Stage
2.
® Each project's score for the readiness metric is based solely on the judgment of the
AEA reviewer.
® Each project's score for the benefit metric was calculated as the average from two
areas evaluated during Stage 2. These areas were the economic feasibility and the
other benefits.
® Each project's score for the sustainability metric was based solely on the judgment of
the AEA reviewer. According to AEA staff, they considered the key elements in this
metric to be the likelihood of a project functioning in 5 years and the complexity of
the technology.
® Each project's score for the local support metric was calculated according to AEA's
methodology.
Stage 4 — Funding Recommendation and Statewide Rank
We ascertained whether or not AEA's recommended project -funding directly corresponds to
the project's statewide rank.
4 AEA's spreadsheet titled Alaska Renewable Energy Fund, Ranking and Proposed Grant Allocation Round I dated
January 23, 2009 referred to this metric as Tech & Econ Feas. However, it actually includes all elements evaluated
during stage 2 which include 1) project management, development, and operation, 2) qualification and experience,
3) technical feasibility, 4) economic feasibility and 5) other benefits
ALASKA STATE LEGISLATURE DIVISION OF LEGISLATIVE AUDIT
Members of the Legislative Budget
and Audit Committee - 6 - February 17, 2009
We observed, again, that AEA used its judgment to make funding recommendations
regarding projects that are not directly supported by its evaluation process that ended with
statewide ranking.
® Ambler Solar PV Construction AEA decided to fund only one solar project in
Northwest Arctic region even though 3 solar projects scored high enough in the
statewide ranking to be funded. Also, AEA said they were funding this as a
demonstration project
® Ruby Hydrokinetic Construction Under AEA's guidelines, partial funding is
recommended for viable projects that have construction scheduled for 2010 or later.
The Ruby Hydrokinetic project was fully funded by AEA even though it is not
expected to begin the construction phase until May 2010.
® Delta Junction Wood Chip Heating- Feasibility Study AEA's recommended funding
for this project was $2.7 million. This project is in the Railbelt region and per AEA
funding caps should not have been recommended for more than $2 million.
According to AEA, this was an oversight and the applicant will receive only $2
million.
Overall Observations Based on our Project Review
We understand AEA staff has strong historic and professional knowledge on which to base
its professional judgment. However, because some metrics did not have clearly articulated
criteria on which to base a conclusion, it is difficult to confirm all applicants were treated
consistently. Additionally, since AEA did not consistently provide sufficient support for
conclusions based on professional judgment, the historic, professional knowledge upon
which these conclusions were based are not passed on to future employees responsible for
grant operations.
AEA did not verify that matching funds reported by the applicants existed and were
available. According to AEA, this will be done in the grant award process after projects have
been approved.
Capital replacement costs were not incorporated into the economic analysis. AEA did not
consider it necessary as they are calculating benefits only over the projects initial useful life.
However, this assumes that additional funding will be available in the future to prevent the
community returning to non-renewable energy sources.
A considerable amount of effort was spent on the cost benefit analysis that ultimately had
little effect on the actual ranking of projects. The Stage 2 review, which included the
economic feasibility analysis, was not used to create a threshold for eligible projects, it
merely provided a score for the project feasibility and benefit metrics during Stage 3. Ten
ALASKA STATE LEGISLATURE DIVISION OF LEGISLATIVE AUDIT
Members of the Legislative Budget
and Audit Committee - 7 - February 17, 2009
projects with recommended construction funding of over $16.6 million have a benefit/cost
ratio of less than 1.0.
To provide assurance that the benefits of these capital investments actually flow to the
residents, AEA plans to require in the actual grant agreements for IPPs that they obtain an
RCA certificate of public convenience and necessity. It is currently unclear whether RCA
has the statutory and regulatory authority to conduct such reviews. This issue is addressed
further in section three below.
Analysis of AEA's Evaluation Process
The final area of review was to assess the comprehensiveness and completeness of AEA
evaluation process.
For this area we:
® Compared criteria used by AEA to criteria used by other government agencies
administering similar programs. This included Denali Commission, other State
governments5, and the federal government6. Information was obtained through
research and direct inquiry.
® Discussed the AEA process with Institute of Social and Economic Research (ISER)
and Northern Economics representatives. Topics of discussion included the cost
benefit analyses, the fuel cost assumptions built into the economic benefit analysis,
and the quality assurance work performed by ISER.
e Interviewed staff at the Department of Natural Resources.
® Discussed the IPP rate and certificating issues with RCA.
® Considered various generally available economic information and feasibility
information related to renewable energy technologies.
® Considered the potential effects of partial and multi -phase funding of projects.
Based on our inquiries there appear to be areas where AEA's evaluation process is not as
robust as other agencies. This increases the risk that a project will not be successful.
5 The State of Oregon has the Oregon Renewable Energy Feasibility Fund. The State of Minnesota has the Xcel
Energy Renewable Development Fund.
' The US Department of Agriculture (USDA) has the Rural Energy for America Program as well as the Rural
Development Renewable Energy Grants. The US Department of Energy has the Renewable Energy and Energy
Efficiency Deployment in Indian Country Grant.
ALASKA STATE LEGISLATURE DIVISION OF LEGISLATIVE AUDIT
Members of the Legislative Budget
and Audit Committee - 8 - February 17, 2009
Technical Feasibility
Requirements from other programs that were not effectively utilized by AEA in the grant
evaluation process include:
® A description of how the project's success will be measured, including a description
of how the applicant plans to measure its own progress during the project and a
description of the anticipated outcomes or impacts of the project.
e Plan for dismantling and disposal of project components.
® Having technical details reviewed by an independent qualified consultant, who must
provide an opinion and recommendation.
® Additional scoring metric based on the amount of energy replacement.
® Ensuring inter -operability with existing technologies.
Economic Feasibility
Requirements from other programs that were not effectively utilized by AEA in the grant
evaluation process include:
® Require applicant provide a preliminary economic assessment for the proposed
project and describe the plan to obtain necessary financing.
(While AEA does ask for the financing plan from the applicant, the imposition of
funding caps or decisions to partially fund a project makes AEA's assessment of the
total funding plan substantially less effective.)
® During the evaluation process, require applicant to identify sources of matching
funds, including any written communication between applicants and matching fund
source, and verify the existence of matching funds as identified.
Sustainability
Requirements from other programs that were not effectively utilized by AEA in the grant
evaluation process include:
• A plan for how the project will be financially sustained after funding ends.
® A replacement plan for when the capital equipment purchased with the grant has
reached the end of its useful life.
ALASKA STATE LEGISLATURE DIVISION OF LEGISLATIVE AUDIT
Members of the Legislative Budget
and Audit Committee - 9 - February 17, 2009
® Describe a preliminary training plan for the operation and maintenance of the
renewable energy system or the planning activities to be conducted as part of the
proposed project to define the training plan.
e Require applicant to describe the availability and sustainability of the renewable
energy resource. Consider setting minimum data availability requirements such as:
(1) One year's worth of anemometer data for wind projects, (2) Quantitative monthly
temperature and flow data traceable to a verifiable data source for geothermal
resources, solar system and hydroelectric system.
According to the Denali Commission, the sustainability? of a program is primarily
demonstrated through the business plan process. Applicants may be asked to revise the
business plan, along with related documents, originally submitted with their grant proposal as
their projects progress through the different phases of project development
(planning/conceptual design, final design/permitting, and construction).
AEA does not have a written infrastructure sustainability policy and criteria for the project
proposals, and it was difficult for AEA to articulate their evaluation of the sustainability of
the proposed projects. The process was very subjective.
Fuel Cost Assumptions
ISER used regression analysis to estimate the cost of fuel in the community relative to a
standard $110 per barrel of oil. However, projections that build in estimated year-to-year
fluctuations are readily available from sources such as the USDE.
Independent Power Producers
There is uncertainty in the ability of RCA to regulate IPP applicants awarded project grants.
AEA staff stated that one of the stipulations of grants to IPPs was that they petition the RCA
for a certificate of public convenience and necessity (CPCN) and to be economically
regulated by the Commission. These stipulations will be included in grant agreements. AEA
staff believes this requirement provides public protection for excessive rates charged for
power by the IPPs. In addition, RCA determines whether a utility is fit, willing, and able to
provide services to the public before issuing a CPCN. This would provide an additional
review of the IPPs ability operate and maintain the project.
The idea to require regulation of IPPs may be sound policy. However, there are uncertainties
as to whether and how RCA may regulate IPPs. A statutory change or new regulations may
In written policy, the Denali Commission defines sustainability as the ability of a recipient or applicant to
demonstrate the capacity, both administratively and financially, to provideforthe long-term operation and
maintenance of a facility. This demonstration may include such factors as maintenance costs, fuel/heating costs,
staffing/personnel costs, insurance as applicable, bonding, cost escalation factors, etc. Further, sustainability
includes all costs associated with management, operation and maintenance, renewal and replacement necessary to
maintain a given level of service.
ALASKA STATE LEGISLATURE DIVISION OF LEGISLATIVE AUDIT
Members of the Legislative Budget
and Audit Committee - 10 - February 17, 2009
be required. We note that RCA regulation proceedings can take up to two years to complete.
This type of delay could significantly hamper a project's completion.
The funding for RCA is provided by the regulated utilities. There does not appear to have
been any consideration of the impact that the costs associated with the RCA process would
have on the IPP or on the cost benefit of the project.
Funding Strategy
Both AEA's evaluation process and the processes of other State and federal entities gave
weight to projects that presented a complete financing plan. However, in an effort to meet
the intent of HB 152, AEA with support from the advisory committee imposed funding caps
on projects. While this does spread the funds to more projects it unbalances the applicant's
proposed funding plan.
Summary
This memorandum identifies a variety of areas in which AEA did not follow its established
methodology or was not as comprehensive or complete as other agencies are when
evaluating alternative energy projects. As result, we believe that there is a higher than
necessary risk that the projects will not be successful. During this analysis we define success
as the project being on time, on budget and able to produce the expected energy for the
projected costs.
However, we also believe that many of these risks can be mitigated with a very aggressive
grant management process. Currently, AEA plans to gather additional information and
impose additional requirements through the grant process. An aggressive grant management
process would include creating and enforcing kill points where the grant is terminated if
expected progress or outcomes are not attained.