HomeMy WebLinkAboutcapped projects 110Round I / Renewable Energy Fund Projects not able to get underway because grant amount was capped
Grantee
Nome Joint Utility System
Unalakleet Valley Electric Coop
Cordova Electric Cooperative
Kodiak Electric Assn.
Kotzebue Electric Assn.
Municipality of Anchorage
GVEA
Chena Power Utility, LLC
Fishhook Renewable Energy, LLC
Ak Environmental Power, LLC
Delta/Greely School District
Haida Power, Inc
City & Borough of Wrangell
City & Borough of Sitka
Round II / Renewable Energy Fund Projects not able to get underway because grant amount was capped
Grantee
AVEC
Kenai Winds, LLC
Project
Newton Peak Wind Farm Construction
Unalakleet Wind Farm Construction
Humpback Creek Hydro
Pillar Mountain Wind Farm
Kotzebue Wind Farm Expansion
Anchorage Landfill Gas to Electric
Eva Creek Wind Farm
North Pole Biomass to Electricity
Fishhook Hydro Construction
Delta Junction Wind Farm Construction
Delta School Wood Chip Heating System
Reynolds Creek Hydro
Electric Boiler Conversions
Takatz Lake Hydro Feasibility
Project
Emmonak/Alakanuk Wind
Kenai Wind project at Nikiski
Project Cost per Application
15534309
8996832
11600000
23319539
14807535
7400000
93341555
4007900
4555922
8363886
2868000
17145000
3260000
2000000
Project Cost per Application
10733179
21000000
RE Fund Grant Request
13951326
8774080
5500000
9650000
12075535
3700000
79340322
2000000
2142961
6269750
2868000
10500000
3260000
2000000
RE Fund Grant Request
9670361
5850000
RE Fund Grant Amount
4000000
4000000
4000000
4000000
4000000
2000000
2000000
2000000
2000000
2000000
2000000
2000000
2000000
514684
RE Fund Grant Amount
8000000
2000000
Shortfall
9951326
4774080
1500000
5650000
8075535
1700000
77340322
0
142961
4269750
868000
8500000
1260000
1485316
1670361
3850000
Comments
On hold, PM discussing options with grantee
Substantially completed
Underway, requesting round 3 funds
Completed
Requesting additional round 3 funds to supplement round 1 and federal
AEA will enter into grant agreement for likely 2011 construction
Grant not in place but underway, feasibility/ concept design
Underway
Project on hold/including issues besides lack of funding
Substantially completed
Underway in final design phase, funding still issue. Requesting round 3 funds
On hold, Requesting round 3 funds
Underway, final design/construction
Underway
Grant not in place, PM working with AVEC
Underway, requesting additional round 3 funds for expansion