HomeMy WebLinkAboutDRAFT Meeting Minutes June 8, 2010
Renewable Energy Fund Advisory Committee Meeting June 8, 2010
Page 1 of 5
Renewable Energy Fund Advisory Committee Meeting
June 8, 2010 – AEA Boardroom
1:00 pm to 4:00pm
1.) Call to Order
The Renewable Energy Fund Advisory Committee convened at 1:06 p.m. Chairman Vince Beltrami
presided over the meeting.
2.) Roll Call:
Committee Members AEA Staff Other Participants
Chair Vince Beltrami Steve Haagenson Gene Therriault (phone)
Chris Rose Mike Harper Pat Walker, Sen. Hoffman’s Ofc (phone)
Jim Posey Sara Fisher-Goad Kaci Hotch, Rep. Thomas’ Ofc (phone)
Brad Reeve Peter Crimp Wyn Menafee, Dept. of Law
Jodi Mitchell Doug Ott Mike Nave, Dept. of Law
Senator Lyman Hoffman Butch White Bob Pawlowski, Legislature
Representative Bill Thomas (phone) Chris Rutz Dennis Meiners, IES
Bruce Tiedeman Ona Brause, IES
Emily Binnian Faon O’Connor, YRITWC
Audrey Alstrom Jodi Fondy, Denali Commission
James Jensen
Bethany McDiffett
Shauna Howell
May Clark
3.) Public Comments
There were no public comments.
4.) Agenda Comments
Agenda Items 14 and 15 were removed from the agenda as being redundant. There were no objections.
5.) Approval of Meeting Minutes – January 13 & 14, 2010
Chair Beltrami thanked staff for timely distribution of the meeting minutes and attention to detail.
MOTION: Mr. Posey moved to approve the meeting minutes from the January 13 & 14, 2010
Renewable Energy Fund Advisory Committee meetings. The motion was seconded by
Mr. Reeve. The minutes were unanimously approved as presented.
6.) Debrief of Legislative Session
Renewable Energy Fund Advisory Committee Meeting June 8, 2010
Page 2 of 5
Mr. Haagenson stated SB220, out of Energy Bill HB306, is moving forward and the Emerging Technology
Fund was established by Legislature, which will be administered by AEA. $2M was refunded to AEA from
unexpended interest earned to manage the program, fund staff evaluations and economic analyses of the
RE Fund. The fund was cut from $52.25 million to $25 million, and some projects were not funded. Mr.
Therriault was asked by Senator Hoffman if he knew the justification as to why the Governor did not
follow HB152 intent and fund the $50 million in projects that were signed into law two years ago. Mr.
Therriault said the Governor viewed the extra $25 million as money beyond the $150 million for the third
year which meets the intent of the Legislation. The $2M mentioned above was not vetoed. Ms. Fisher-
Goad stated our original budget request had a $2 million appropriation to pay for AEA staff to administer
the program. Legislature adjusted that appropriation to give us a $2M operating appropriation to pay for
the program’s administrative costs freeing up additional capital monies for us to do other alternative
energy efficiency programs. Mr. Haagenson stated it is AEA’s opinion that we have provided sufficient
information to the LB&A and Governor’s office regarding allocations and the reason for the veto is
unclear. In response to a question by Chair Beltrami, Mr. Crimp stated project regional spreading was not
affected as a result of this cut.
Mr. Haagenson stated $10 million was put into the Power Project Fund and with the sale of the existing
bonds to AIDEA means another $21 million into the fund. The Legislature has approved $9 million for the
Reynolds Creek Hydro project in Southeast Alaska. HB306 also states the PPF will be the primary
funding source for renewable energy projects going forward. The Alaska Energy Pathway document is
out for public comment. With the Pathway, we will try to determine what the concept for loans and grants
will be (similar to the virtual G&T concept, where everyone pays the same rate across the state, an equal
energy footprint). Mr. Therriault emphasized that the Pathway shows individual communities that they
could step forward with alternative energy sources and not wait to be totally grant or loan funded.
7.) & 8.) Round 0-I-II-III Grant Updates
Mr. White stated Round 0 is included in the handout as the projects carried forward to Round I. We have
committed $79 million of the $100 million as grants and have dispersed $26 million in project funds for
Round I. For Round II, of $25 million, $10 million was awarded and $1 million dispersed. Due to the
veto, we are looking at 22 projects across the state in Round III and should have the grant agreements
out in early July. Mr. Haagenson said the Committee needs to define when a project is stalled, what we
can do about it, and whether the PPF could be utilized to get these projects moving. Mr. Posey agreed
with this approach, as opposed to cutting them off. In response to a question from Mr. Rose, in Rounds I
and II, Mr. Crimp stated both the South Fork Hydroelectric and Fishhook Hydroelectric construction
projects are not moving forward. South Fork was given the grant for signature in January and one issue
has been the maximum allowable cost of power in the Power Purchase Agreement (Mike Hubbard’s work
on the cost based rates). Fishhook has permitting and finance issues.
Regarding the Bethel Wind Power Project, Mr. Crimp stated AEA requested information from the City in
January with no response and requested guidance from the Committee on this matter. Mr. Haagenson
said we need to write to the City and find out what their intentions are. Bethel Utilities is not interested in
buying power from the City wind turbines as it will lower the rates. The Utilities may be up for sale, but
are not interested in selling to the City. Mr. Posey suggested a report to the RCA would prompt them and
the Legislature to investigate this matter. Senator Hoffman met with the City four months ago and if
nothing can be worked out with the Utility, they are interested in seeking Legislative direction. In
response to a question about what authority AEA had in moving monies around in the RE Fund, Ms.
Fisher-Goad stated Legislative authorization is needed to move funds from one round to another Round II
funds remain in Round II, etc. Senator Hoffman pointed out that we need to keep regional balancing in
check.
Renewable Energy Fund Advisory Committee Meeting June 8, 2010
Page 3 of 5
9.) Construction Project Schedule Review
Mr. Crimp distributed a timeline construction schedule which showed our best estimate as to when
projects will complete construction, except for those seven that are already completed. He said by the
end of 2010, 21 projects should be completed, with the remainder being completed by 2012, not including
projects that are stalled. Mr. Posey commented that having a completed project sheet is a good exhibit
and is important that the project duration timeline shows that renewable energy projects take time and are
not quick.
Mr. Rose commented that the NREL integration experts will be meeting in Anchorage at the end of June.
Mr. Crimp stated the Nome Newton Peak Wind Farm Project grant is almost in place and was short-
funded. We will proceed with the grant, final design and permitting and make a determination at that
time. This is a good example of a stalled project.
Mr. Posey inquired as to the status of the Anchorage landfill gas to electricity power project. Mr. Crimp
stated the LB&A approved a landfill gas to electricity power project to serve the Railbelt. The grant funds
will not be available for a compressed landfill gas and buss system or other. This project is moving
forward though not yet in place, but is not stalled.
Project mobilization, exploration and over cost estimates were discussed and need to be caught early
during the review status. We will continue to revise the construction project review schedule.
10.) Draft Questionnaire Review – RFA Period
Mr. Crimp stated we have committed to ask the customers their thoughts about the RE Fund process and
two months ago began work on a questionnaire requesting input into managing our projects; however, we
got bogged down very quickly, and are now proposing an RFP to contract out this task within the next
month, with survey results in two months. Mr. Haagenson said it’s good to ask how we are doing, i.e.
timing and backup vs. justification. Chair Beltrami asked about the timeframe for the questionnaire project
and Mr. Crimp said it would be out in about one month. Mr. Posey said that due to summer activities, it
might be prudent to collect the information later in the fall, as more people might participate. Mr.
Haagenson sated we are trying to get Round IV Request for Applications out by July 28 so having the
survey information in hand before then would be useful to tweak the next application process. Mr. Crimp
stated the RFA’s will go out on July 28 with September 8 as the due date for responses. He said we could
utilize the survey information received up until then and keep the survey response date open longer. Mr.
Posey reiterated that we want to collect as much data as possible. Various dates for the survey and the
RFA application/review period were discussed. Senator Hoffman said that moving the dates around too
much confuses people. Mr. Posey pointed out that we are now going into Round IV and the proposers
are more comfortable and informed with the process. The RFA period will be July 21-September 15,
2010 and advertising will begin as soon as possible.
Ms. Fisher-Goad said that we can begin working on the Emerging Energy Technology Fund regulations,
but there’s a 90-day effective date from when the Governor signs it.
11.) Initial Reaction to Changes in Round IV
12.) Proposed Round IV Schedule (these two items were discussed simultaneously)
Renewable Energy Fund Advisory Committee Meeting June 8, 2010
Page 4 of 5
Ms. Fisher-Goad stated each RFA has been improved from the prior one. Caps were in place, and
although they were done, caps were applied after the fact for Rounds I and II, and it made it difficult for us
to get grants in place. This is not the case for Round III, since people submitted applications knowing
what the caps were. For Round IV, we should identify program changes and notify the applicants up
front. It needs to be decided to change the cap amount, and/or limit Round IV funding for projects that
received prior round funding. The RFA should specifically state that permitting and financing should be in
place for construction projects. Although we could consider implementing deadlines to get a grant in
place that could be extended for a good reason, Mr. Crimp pointed out that hydro projects especially are
time consuming.
13.) Performance Driven and/or Strategic Grant Making
A discussion was held on how to attract the good projects, and getting local and regional planners
involved. Senator Hoffman pointed out that most small communities don’t have the resources to go it
alone and most don’t have planners. Ms. Fisher-Goad pointed out that this is a grant recommendation
program and project list recommendations presented to the Legislature for funding are not adjusted. She
concurred that many communities rely on AEA for technical assistance. Mr. Rose stated that we will need
to define “emerging technology” and “strategic grant making” industry standards. Mr. Crimp stated
planning issues and AEA technical assistance are important aspects, reiterating regional spreading and
assisting smaller villages to find good projects. Buying and building locally was discussed. The Pathway
is a good first step. It puts together a plan for each community in Alaska – where community action is
key. AEA should push wind diesel forward and make a plan now.
The Committee proposed recommendations as follows:
1. INCORPORATE DEPLOYMENT TARGETS
Establish renewable deployment targets to increase the application of renewables in Alaskan
communities. Generic deployment strategies exist in Appendix 4 of the Alaska Energy Pathway.
These targets or standards could be used in the evaluation of RE Fund projects and could
advance integration of renewables through a competitive process. For instance, we should not
limit equipment to specific vendors, but instead establish a range of equipment that could be
selected in a community. All software should be non-proprietary. This concept should be
incorporated in Round 5 and may require program changes.
2. DEFINE CRITERIA FOR WHEN A PROJECT IS “STALLED”
The definition of a stalled project should incorporate the reasons for the stall, such as lack of:
permits, financial plan, power sales agreements, project readiness (specific phases, i.e.,
feasibility, final design, construction). Do not allow “war chests” to be built.
3. HEAT RECOVERY
Recognizing that thermal energy costs are the greatest burden to rural residents; staff will make
recommendations on means to develop thermal projects, such as diesel heat recovery following
the Pathway.
4. SUBMIT LETTER TO RCA REGARDING BETHEL ELECTRIC UTILITY AQUISITION
Mr. Haagenson will first discuss with Chairman Pickett the interconnection of renewable projects
in Bethel and opportunities to lower costs through the utility structure and ownership.
5. ADVERTISE RFA ASAP
The Round IV Request for Application period will be advertised as soon as possible.
Renewable Energy Fund Advisory Committee Meeting June 8, 2010
Page 5 of 5
Chair Beltrami requested that the list of recommendations be distributed to the Committee as soon as
possible.
16.) Next Meeting Date
The next meeting date will be Friday, August 13, 2010 in Fairbanks, AK.
17.) Adjournment
The meeting was adjourned at 3:58 p.m.