HomeMy WebLinkAboutWind Turbine Provides Electricity-for-Arctic-Town CADDET Kotzebue Article 02-2001Wind Turbine Provides
Electricity for Arctic Town
Technical Brochure No. 143
WIND ENERGY
Summary
A small coastal town in Alaska is in
its third year of operating the first
successful utility wind power plant
in the state. The installation meets
the needs of about 200 homes in
Kotzebue and accounts for about
6% of total electricity consumed in
the town, which has 3,500 residents.
A new wind turbine, developed with
support from the US Department of
Energy (US DOE) and designed to
operate in cold climates, was
chosen. The project required
wintertime construction and special
procedures were followed to protect
the fragile arctic tundra.
First successful utility wind
power project in Alaska
Local co-operative
distributes electricity
through small grid
Wind turbine designed to
withstand arctic conditions
Potential for replication in
other communities
Highlights
The AOC 15/50 wind turbine, Alaska.Photograph: Kotzebue Electric Association
Project Background
Kotzebue, like most communities in
rural Alaska, uses electricity
produced by small, diesel-engine-
driven generators. Kotzebue
Electric Association (KEA) operates
six such generators with a combined
rated capacity of 11.2 MW. KEA
is a non-profit-making, electricity
co-operative that distributes power
to town residents through a small
distribution grid.
During the summer, when coastal
harbours are free of ice, barges carry
diesel to Kotzebue from southern
Alaska – a journey of more than
2,000 km. The fuel is stored in
large tanks for use during the long
winter. Many tanks in villages such
as Kotzebue are more than 20 years
old and nearing the end of their
useful life. Stricter environmental
regulations mean that costs for new
tanks are significantly higher than
they used to be. In addition, state
subsidies for diesel fuel have been
reduced and spread over a larger
base of population.
In response to these cost increases,
KEA turned to wind generation as a
way of reducing diesel consumption
and the cost of electricity for
residents. With long-term wind
speeds averaging 6 m/s, the idea of
harnessing wind energy has long
appealed to local people.
The Project
So far, KEA has installed 10
turbines with a combined rated
capacity of 660 kW. The Kotzebue
project is a joint undertaking
between the US DOE, the Electric
Power Research Institute (EPRI)
and the Alaska Energy Authority,
Alaska Industrial Development
Export Authority (AEA/AIDEA).
The AOC 15/50 turbines were
developed with support from the
US DOE’s Wind Turbine
Development Program and made
by the Atlantic Orient Corporation
(AOC) of Norwich, Vermont.
They were designed to operate
economically in cold climates
with moderately favourable
wind resources.
Several design features keep
maintenance of the AOC 15/50
to a minimum – a critical
requirement for machines operating
in remote locations such as
Kotzebue (see Figure 1). For
example, the rotor spins downwind
of the 24.4 m steel tower in a
passive yaw arrangement. Wind-
direction sensors and yaw-drive
motors, which must be checked
periodically, are thus not required to
keep the rotor spinning
perpendicular to the wind. In
addition, the gearbox is directly
connected to the drive train,
thereby eliminating the need for
maintenance-prone couplings inside
the nacelle.
The shape of the blades regulates
excessive power generation in
high winds. In high winds,
turbulent eddies of air form next
to the trailing surface of the blades.
These eddies cause the blades to
stall, thus reducing the aerodynamic
force on the rotor. Overspeed
control is provided by tip brakes
that deploy centrifugally at the end
of the blades. The tip brakes cause
a large aerodynamic drag on the
rotor and slow it down. Finally,
there are two types of brake – an
electrodynamic brake that uses the
generator, and a conventional disc
brake for stopping.
Construction took place during the
winter when the ground was
sufficiently frozen to support the
crane and other equipment without
damaging the tundra. KEA and
AOC trained local crews in
installation and maintenance
procedures. The first three turbines
were commissioned in September
1997 and the remaining seven in
June 1999.
Performance
KEA, US DOE and EPRI are
collecting data on the project, which
will be made available to other
utilities under the US DOE/EPRI
Turbine Verification Project (TVP).
The TVP evaluates wind turbines in
utility operating environments in the
USA with the purpose of sharing
experience and data with other
electric supply companies (see
CADDET Renewable Energy
Newsletter, 2/99).
Figure 1:
The AOC 15/50 wind turbine.
curve was required for both KEA
and AOC.
KEA’s wind installation reduces
annual diesel consumption by
340,000–380,000 litres. Based on
the average cost of diesel in 1998,
this translates into an annual saving
of about $86,000. Taking this into
account, the ‘levelised’ cost of
energy from the wind turbines is
estimated at $0.109/kWh.
Environment
Construction of the wind plant took
place during the winter to avoid
damaging the fragile arctic tundra.
The tower foundations are specially
designed to keep the ground
continuously frozen and maintain
the integrity of the tundra.
Table 3 shows the diesel-generated
emissions avoided through the use
of wind turbines based on emissions
data reported to the US
Environmental Protection Agency
for KEA.
Although the project is still
evolving, the town of Kotzebue has
already learned a great deal about
wind systems. The town hopes to
use this experience to develop
regional expertise in wind systems
to help other communities generate
electricity from wind. KEA plans
to install other turbines, with up to
2 MW of capacity, at the Kotzebue
site. It also hopes to support
smaller installations in nearby
coastal villages.
All TVP projects, including the one
at Kotzebue, report performance and
other data according to utility
standards. For example, although
the generator is rated by its
manufacturer at 50 kW, the
maximum sustained output of the
wind turbine is 66 kW, so the TVP
rates the turbine at 66 kW. Turbine
availability is uniformly defined for
all TVP projects based on the time
the turbines are available to operate,
whether or not the wind is blowing.
Any downtime (for scheduled
maintenance, unscheduled outages,
interconnection or grid failures – or
even public tours) is subtracted from
the total. During the first two years
of operation, the TVP availability of
the Kotzebue wind installation was
96%, much higher than that of most
diesel-engine-driven generators.
Figure 2 shows the instantaneous
power output at standard conditions
over the range of wind speeds that
the turbine operates. Output is
higher during arctic winters because
of the greater density of cold air.
Economics
The first three turbines that were
erected cost $2,985/kW (where $ is
the US dollar) to install and
commission. KEA estimates that
the remaining seven turbines cost
$2,200/kW. For the 1997
installation, the costs incurred, in
addition to the turbine hardware,
amounted to 63% of the total.
For the 1999 installation, KEA
reduced these costs to about 50% of
the total.
Such costs are about twice the
industry standard for utility-scale,
wind-power plant. However, KEA
believes they are reasonable, given
that all construction projects in the
Arctic are expensive and a learning
Technical Brochure No. 143
Figure 2: Power output curve
of the AOC 15/50.
First year
kWh
546,882
Average wind speed
(m/s)
5.1
First year
capacity factor
0.14
Table 2: First-year electricity production from turbines 4–10,
1 July 1999 to 30 June 2000
1998
1999
CO2 (kg)
197,000
342,132
SO2 (kg)
825
1,433
NOx (kg)
5,048
8,981
Table 3: Emissions avoided by KEA wind installation
1998 1998 1998 1999 1999 1999
kWh average capacity kWh average capacity
wind speed factor wind speed factor
(m/s) (m/s)
270,874 4.9 0.16 208,582 5.4 0.12
Table 1: 1998 and 1999 electricity production from turbines 1–3
CADDET Centre for Renewable Energy
ETSU, 168 Harwell, Didcot
Oxfordshire OX11 0QJ
United Kingdom
Tel: +44 1235 432719
Fax: +44 1235 433595
E-mail: caddet.renew@aeat.co.uk
International Energy Agency
The International Energy Agency (IEA) is an
autonomous body which was established in 1974 within
the framework of the Organisation for Economic
Co-operation and Development (OECD) to implement
an international energy programme.
CADDET
CADDET was set up in 1988 as an IEA Centre for the
Analysis and Dissemination of Demonstrated Energy
Technologies. Today, there are two CADDET operations:
one is for energy-efficient technologies and the other for
renewable energy technologies. The Centres co-operate
with member countries in the exchange of high quality
information on energy technologies.
Disclaimer
Neither CADDET, nor any person acting on their
behalf:
(a) makes any warranty or representation, expressed or
implied, with respect to the information contained in
this brochure; or
(b) assumes any liabilities with respect to the use of this
information.
US 00 504
Printed on environmentally friendly paper.
Please write to the address below if you require more information.
Host Organisation
Kotzebue Electric Association
PO Box 44
Kotzebue, Alaska 99572, USA
Contact: Brad Reeve
Tel: +1 907 442 3491
Fax: +1 907 442 2482
E-mail: kea@ptialaska.net
Information Organisation
NREL
1617 Cole Boulevard
Golden, Colorado 80401–3393,
USA
Contact: David Warner
Tel: +1 303 275 3000
Fax: +1 303 275 4415
E-mail: david_warner@nrel.gov
See the whole range of CADDET Renewable Energy projects on www.caddet-re.org
First printed February 2001
Turbine installation.Photograph: Kotzebue Electric Association