HomeMy WebLinkAboutBanner Peak Wind Farm Expansion Nome NJUS JohnHandeland 08-2015-WNome, Alaska
Wind farm expansion further reduces energy prices
Quick Facts
Total Project Costs: $9.6 million
Funding: Renewable Energy Fund & Local Match
Capital Costs
Design: $668,356
Construction: $8,929,454
Equipment
Make/Model: (2) EWT DirectWind 52s
Rated Capacity: 900 KW
Net Capacity Factor: 29%
Rotor Diameter: 52 meters
Hub Height: 50 meters
Total Rated Capacity (all turbines): 2.8 MW
Diesel Fuel Offset
Estimated Annual: Up to 200,000 gallons
Actual Annual: 78,000 gallons
Aug. 2013-Dec. 2014: 116,000 gallons
Fuel Savings
Estimated Annual: $744,000
Actual Annual: $266,000
Aug. 2013-Dec. 2014: $388,000
Benefit/Cost Ratio: 1.44
Banner Peak Wind Farm Expansion
Project Overview
In partnership with the Alaska Energy Authority
(AEA), Nome Joint Utility Systems (NJUS) expanded
the capacity of the Banner Peak Wind Farm by 1.8
MW. Two new 900 kW EWT DirectWind turbines
were added to the existing 16 Entegrity 65 kW tur-
bines for a total capacity of 2.8 MW.
Objectives
The objective of the project was to provide Nome and
the surrounding area with a reliable, renewable, and
cost-effective source of energy. Introducing wind en-
ergy allowed them to reduce their reliance on fluctuat-
ing and expensive diesel fuel.
Economic Feasibility
The turbines became operational in August of 2013.
Between August of 2013 and December of 2014, they
have produced 1,895 megawatt-hours of electricity
and displaced 116,000 gallons of diesel fuel. This dis-
placement saved the community $388,000 in the first
17 months. Over its 20 year projected lifespan, the
project has a calculated benefit/cost ratio of 1.44.
Project Specifications
Wind energy is ranked on a scale from 1 to 7, 1
being poor and 7 being superb. Much of the Bering
Straits region ranges from Class 4 to Class 7 winds,
so projects there tend to be more economical. The
EWT turbines were chosen after a detailed analysis of
their specific suitability for village installations. EWT
turbines have complex controls, variable pitch blades,
and state-of-the-art power electronics. They can be
integrated directly into existing utility grids and mon-
itored and controlled through internet connections.
The original Banner Peak wind project called for a
power sales agreement between NJUS and Banner
Wind LLC in which NJUS purchased power from 900 kW EWT DirectWind turbines, photo courtesy of AEA.
Banner Wind for $0.18/kWh. As of January 1, 2015,
this agreement was terminated when Banner Wind
turned the wind farm over to NJUS. NJUS no longer
has to purchase power.
Allocation of Funding
The Alaska Energy Authority’s Renewable Energy
Fund (REF) granted $8,069,000 for design and con-
struction of the project. Local matching funds contrib-
uted $884,088 for the same project phases. In a differ-
ent REF application, the state granted $801,000 and
local matches gave $89,000 for a transmission line that
would transfer power to NJUS communities.
Learning Experiences/Challenges
The expansion application originally sought to install
five 600 kW turbines on Newton Peak at a cost of $13.9
million. Due to a $4 million cap on all Renewable En-
ergy Fund (REF) projects, AEA recommended partial
funding of this project for $4,000,000. In response, the
wind farm was reduced to two EWT 900 wind turbines
with an additional grant request of $4 million in 2013.
The location was also changed from Newton Peak to
Anvil Mountain and then to Banner Peak due to icing
concerns and transmission costs.
The original Banner project began production in late
2008. Entegrity’s bankruptcy shortly thereafter im-
pacted the initial operation during 2009 due to a lack
of spare parts and support. Banner was able to source
parts from elsewhere, and by the time they applied for
the expansion project they found turbines from Emer-
gya Wind Technologies that met their needs.
Community Benefits
The Bering Straits Native Corporation Board of Direc-
tors passed a resolution requiring that 50% of all their
profits from the Entegrity turbines be reinvested in
renewable energy projects in the 17 villages that make
up the Bering Straits Region. This will enable more
cost effective, better maintained village projects in the
future while continually creating annual revenues to
support more development.
The majority of villages in the region have a subsis-
tence lifestyle, as they lack a true cash economy. High
energy costs for gas, fuel oil, and electricity put an even
higher burden of distress on these residents. Adding
wind generation allows residents to continue thriving
off of their environment and greatly reduces the need
for diesel fuel. This project has reduced residential
electricity costs by twelve cents per kilowatt hour.
Project Contact Information
Owner: Nome Joint Utility Systems (NJUS)
Phone: 907-443-6587
NJUS Contact: John Handeland
Email: johnh@njus.org
Electrical Engineer: Electrical Power Systems
Phone: 907-522-1953
Civil Engineer: BBFM Engineers, Inc.
Phone: 907-274-2236
Case Study Author: Zoe Tressel, AEA
Site: Akenergyauthority.org
Phone: 907-771-3000
Banner Peak Wind Farm Expansion
Meteorological tower, photo
courtesy of AEA.
Banner Peak turbines, photo courtesy of AEA.Published August, 2015
“EWT turbines have
complex controls,
variable pitch blades,
and state of the art
power electronics.”