HomeMy WebLinkAboutDelta Area Wind Turbines Delta Junction Liquid Hydrocarbon 08-2015-WDelta Junction, Alaska
Delta Junction reduces liquid hydrocarbon use
Quick Facts
Total Project Costs: $3.97 million
Funding: Renewable Energy Fund: $2,000,000
Local Match: $1,970,000
Equipment Specifications
Make/Model: (1) NPS Northwind 100B
(1) EWT Direct Wind 54
Rated Capacity: 100 kW, 900 kW
Net Capacity Factor: 21%, 24%
Rotor Diameter: 21 meters, 54 meters
Hub Height: 37 meters, 75 meters
Total Rated Capacity: 1 MW
Diesel Fuel Offset
Estimated Annual: 166,090 gallons
Actual Annual: 145,000 gallons
Sept. 2010-Dec. 2014: 436,000 gallons
Fuel Savings
Estimated Annual: $415,225
Actual Annual: $392,000
Sept. 2010-Dec. 2014: $1,105,000
Benefit/Cost Ratio: 3.58
Delta Area Wind Turbines
Project Overview
In partnership with the Alaska Energy Authority
(AEA), Alaska Environmental Power (AEP) complet-
ed the design and construction of a 1 MW wind proj-
ect near Delta Junction, Alaska. The project installed
two wind turbines and was the first of its kind to
integrate into the Railbelt Grid using an experimen-
tal program by Golden Valley Electric Association
(GVEA). It employs a Northern Power Systems (NPS)
Northwind 100 kW turbine and an EWT DirectWind
900 kW turbine. These turbines are cold weather resis-
tant, operate down to -40 degrees F, and have proven
successful in Alaska. The project serves all the com-
munities on the Northern Railbelt Grid and produces
power without any emissions.
Objectives
The objective of this project was to provide residents
with an affordable and reliable energy source by dis-
placing costly diesel fuel with renewable wind energy.
Economic Feasibility
The turbines became operational in September of
2010. Between September of 2010 and December of
2014, they have produced 7,033 megawatt-hours of
electricity and displaced 436,000 gallons of diesel fuel.
This displacement saved $1,105,000 in just over four
years. With proper maintenance and operation, the
turbines are expected to last longer than their project-
ed lifespan of 20 years.
Project Specifications
The wind farm project was a joint effort between AEA
and AEP. Before the project began, GVEA was sourc-
ing about one third of their power from liquid hydro-
carbons, one third from coal, and the rest from South-
central Alaska utilities through the Northern Interie.
The Delta wind project reduced their use of liquid
“This project provides GVEA members with both
a fixed rate of electricity and a renewable energy
source with zero atmospheric emissions.”
Project construction, photo courtesy of AEA.
hydrocarbons, GVEA’s most expensive power source.
The project took approximately two years to construct.
The installed Northern Power turbine stands 37 meters
tall and the Direct Wind turbine stands 75 meters tall.
The original 138 kV transmission line was tied into a
new 1.5 mile 25 kV line and step-up transformers to
transmit power to the GVEA grid. Prior to the project’s
construction, detailed wind studies were conducted
to ensure the feasibility of such a project. The project’s
resource availability is a class 3 out of 7, but low road
system costs make the project economical. The class
is improves in winter when the demand is highest and
wind strongest.
Power Sales Agreement
A power sales agreement was made with GVEA prior
to release of grant funds that allowed GVEA to pur-
chase up to 2 MW of power capacity under the Ex-
perimental Renewable Resource Purchase Program.
GVEA’s power purchasing price was equal to the
actual avoided fuel cost, or $0.14/kWh. GVEA recently
changed the formula from an annual average avoided
cost to a monthly calculation, so their payments fluc-
tuate slightly throughout the year.
Learning Experiences/Challenges
Avian issues are often a concern at wind farm facili-
ties because of the potential for disturbance, habitat
impact, and mortalities or injuries from collisions. In
response to this, project managers had biological stud-
ies conducted on avian migration patterns, frequency,
population, species, etc. to determine and ensure their
safety.
The original project requested funding for the instal-
lation of 20 Northwind 100 kW turbines. After deter-
mining that the cost was too high, an amendment was
made to substitute 18 of the Northwind 100 turbines
for two of EWT’s 900 kW turbines, yielding a reduced
cost. AEA ended up funding one 900 kW turbine and
one Northwind 100 kW turbine. AEP later installed a
second 900 kW turbine with a loan from AEA’s Power
Project Fund, bringing total capacity to 1.9 MW.
Community Benefits
One of the benefits of this project is that wind energy
prices do not fluctuate with Alaska’s oil and gas pric-
es. This project provides GVEA members with both a
fixed rate of electricity and a renewable energy source
with zero atmospheric emissions.
Thanks to the project, electricity rates have gone down
from 22 cents per kWh (liquid hydrocarbon use) to 18
cents per kWh with wind energy.
Much of the power from this project is transmitted
to the Fairbanks area. Prior to this project, Fairbanks
experienced air quality issues as a result of the atmo-
spheric inversion layer at their location. Whatever
emissions (diesel, forest fire, etc.) are released are gen-
erally trapped underneath this layer and stay hovering
over the community. As a result of this wind project,
less diesel emissions have been trapped, improving air
quality for all residents.
Project Contact Information
Owner: Alaska Environmental Power
Phone: 907-388-9917
Grantee Contact: Mike Craft, managing partner
Email: mikecraft@akwind.net
Case Study Author: Zoe Tressel, AEA
Site: Akenergyauthority.org
Phone: 907-771-3000
Delta Area Wind Turbines
Published August, 2015Delta Junction turbines, photo courtesy of AEA.