HomeMy WebLinkAboutEva Creek Wind Turbines GVEA & AEA 08-2015-WFerry, Alaska
Eva Creek achieves 20 percent renewable energy
Quick Facts
Total Project Costs: $94 million
Funding: Renewable Energy Fund, State, & Local
Capital Costs
Design: $1,314,855
Construction: $92,685,145
Equipment Specifications
Make/Model: (12) Senvion MM92
Rated Capacity: 2.05 MW
Net Capacity Factor: 32.6%
Rotor Diameter: 92.5 meters
Hub Height: 685 meters
Total Rated Capacity: 24.6 MW
Diesel Equivalent Offset
Estimated Annual: 4,226,501 gallons
Actual Annual: 5,054,000 gallons
Oct. 2012-Dec. 2014: 11,020,000 gallons
Fuel Savings
Estimated Annual: $11,647,550
Actual Annual: $13,074,000
Oct. 2012-Dec. 2014: $28,349,000
Benefit/Cost Ratio: 2.68
Eva Creek Wind Turbines
Project Overview
In partnership with the Alaska Energy Authority
(AEA), Golden Valley Electric Association (GVEA)
completed the design and construction of a 24.6
Megawatt wind farm on Eva Creek near Ferry, Alaska.
Twelve Senvion turbines were installed and improve-
ments were made on a 17 mile road to the project. The
turbines have allowed GVEA to increase its renewable
energy production from 8 percent to 20 percent.
Objectives
The main objective of this project was to give GVEA
members a renewable, reliable, and cost effective
source of energy. GVEA is committed to providing 20
percent of their power with renewable sources. Be-
cause of this project, GVEA has reduced their carbon
footprint and displaced large quantities of expensive
diesel fuel.
Economic Feasibility
The project became operational in October of 2012.
Between October of 2012 and December of 2014,
the turbines generated 156,480 megawatt-hours of
electricity and displaced 11,020,000 gallons of diesel
fuel. This displacement saved GVEA communities
$28,349,000 in reduced fuel costs. Over its 20-year
projected lifespan, the project has a calculated benefit/
cost ratio of 2.68.
Project Specifications
Twelve Senvion MM92 turbines, each operating at
2.05 megawatts, were commissioned adjacent to the
Eva Creek Mine near Ferry, Alaska. They have a
maximum rated capacity of 24.6 megawatts, which is
enough energy to power some 9,100 homes in the In-
terior. Due to the harsh climate experienced by much
of Alaska, an anti-freeze solution is injected into the
conduit from the transformers to prevent cable dam-
Senvion MM92 wind turbines, photo courtesy of AEA.
age during freeze-up. Road improvements were also
made as part of the project to make turbine commis-
sioning easier in the somewhat difficult location.
Allocation of Funding
AEA’s Renewable Energy Fund (REF) granted
$3,463,200 for feasibility, design, and construction
of the project. A state legislative grant contributed
$10,000,000 toward design and construction. Local
matching funds contributed $82,536,800 that came
from 20-year bonds and loans.
Learning Experiences/Challenges
GVEA raised rates slightly in the beginning stages of
operation to help pay off the $23,731,051 loan in-
vestment. Since then, residential rates have hovered
around $0.18/kWh, which is a very reasonable rate.
An issue GVEA has faced is the variability of wind
power generation. Wind is not always available when
demand is highest, although winds are generally stron-
ger in winter when there is a greater need for heat and
electricity. In order to maintain a stable supply of pow-
er, GVEA runs a diesel-generated plant that responds
accurately and efficiently according to demand. This
keeps output at the desired level and fills in gaps if the
wind tapers off. An additional challenge has been the
maintenance of the 17-mile access road due to its high
elevation and terrain.
Community Benefits
GVEA is now able to sell wind-generated electricity
to its members for 8 to 9 cents per kilowatt-hour. This
price is equal to the cost of energy that Anchorage
consumers pay, or 50 percent less than the cost of
GVEA’s oil-fired energy.
The project has also seen the introduction of four local
full-time jobs. The GVEA position looks after the site
(roads, buildings, and equipment) while the Senvion
crew works on turbines. This project will continue to
develop a skilled workforce to operate and maintain
wind generation systems.
Eva Creek was the first major Arctic wind generation
project in America. With their infrastructure invest-
ment and lessons learned, GVEA has contributed to
understanding the challenges that come with constr-
Project Contact Information
Parties Involved:
Paul Morgan, GVEA wind generation mgr.
Email: pcmorgan@gvea.com
Phone: 907-458-5780
Case Study Author:
Zoe Tressel, AEA
Website: Akenergyauthority.org
Phone: 907-771-3000
Eva Creek Wind Turbines
Workers laying turbine foundation, photo courtesy of Akbizmag.com
Senvion MM92 turbine, photo courtesy of AEA.
Published August, 2015
ucting a large-scale
project in northern
climates. Any future
installation should
be easier as a result.
The Eva Creek site is
also able to accom-
modate expansion,
should the demand
for wind power
increase within the
Railbelt region.